diablo sps handbook opshandbook.pdf · related to the diablo canyon special protection scheme...
TRANSCRIPT
Diablo Canyon Special Protection Scheme
(DCSPS)
Operations Handbook
2009-07-14
About this Handbook
DCSPS Operations Handbook Page i Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
Table of Contents
1 ABOUT THIS HANDBOOK .......................................................................................................... 1-1
1.1 AUDIENCE ................................................................................................................................... 1-1
2 DOCUMENT REVISION HISTORY............................................................................................ 2-1
3 DESCRIPTION OF OPERATIONS .............................................................................................. 3-3
3.1 DIABLO CANYON SPS OVERVIEW AND CONCEPTS ..................................................................... 3-3
3.1.1 Background ........................................................................................................................ 3-3
3.1.2 Transmission System Overview.......................................................................................... 3-5
3.1.3 Diablo SPS (DCSPS) Purpose and Requirements ............................................................. 3-7
3.1.4 Diablo Canyon SPS System Description and Definitions .................................................. 3-7
3.1.5 Diablo Canyon SPS Event Categories ............................................................................. 3-11
3.2 STANDARD OPERATING DEVICES, DESCRIPTION AND PROCEDURES ......................................... 3-12
3.2.1 Diablo Canyon SPS Cut-Out Switch ................................................................................ 3-13
3.2.2 Diablo Canyon SPS Unit Selector Switch ........................................................................ 3-14
3.2.3 500kV Circuit Breaker Maintenance Switches ................................................................ 3-14
3.2.4 500kV Line/Unit Maintenance Switches .......................................................................... 3-16
3.3 SUMMARY OF SWITCHING PROCEDURES ................................................................................... 3-16
3.3.1 Open a 500kV circuit breaker (No physical work is performed on CB or Circuitry) ..... 3-16
3.3.2 Open and Clear 500kV Breaker ....................................................................................... 3-16
3.4 DIABLO CANYON SPS STATUS AND ALARM INDICATION ......................................................... 3-17
3.4.1 Alarm Categories & Conditions ...................................................................................... 3-17
3.4.2 Universal Relay N60 (UR N60) LED’s ............................................................................ 3-22
4 DETAILED SYSTEM DESIGN AND COMPONENTS ............................................................. 4-1
4.1 SCHEME ARCHITECTURE OVERVIEW .......................................................................................... 4-1
4.2 RELAY INSTALLATION (AC CIRCUITS)........................................................................................ 4-1
4.3 DIABLO CANYON SPS LOGIC OVERVIEW ................................................................................... 4-3
4.3.1 System Start Up .................................................................................................................. 4-3
4.3.2 One Line Trip State ............................................................................................................ 4-3
4.3.3 One Line Out Armed State ................................................................................................. 4-3
4.3.4 One Line Out/Normal State ............................................................................................... 4-4
4.3.5 Trip Logic State.................................................................................................................. 4-4
4.3.6 Execute Trip State .............................................................................................................. 4-5
4.3.7 System Locked Out State ................................................................................................... 4-5
4.3.8 System Inactive State.......................................................................................................... 4-5
4.3.9 Plant Over Power State ..................................................................................................... 4-5
4.4 COMMUNICATION INFRASTRUCTURE .......................................................................................... 4-7
4.4.1 High Speed Relay-to-Relay Communications .................................................................... 4-7
4.4.2 Ethernet Relay-to-Relay communication and Remote Access ........................................... 4-9
4.5 RELAY FUNCTIONS ................................................................................................................... 4-11
4.6 TRIP DETECTION AND BREAKER FAILURE RECOGNITION .......................................................... 4-11
4.7 BREAKER FAILURE FUNCTIONAL OVERVIEW ............................................................................ 4-13
5 TESTING REQUIREMENTS AND PROCEDURES .................................................................. 5-1
5.1 MAINTENANCE REQUIREMENTS AND PROCEDURES .................................................................... 5-1
About this Handbook
DCSPS Operations Handbook Page ii Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
5.2 DCSPS TESTING MATRIX ........................................................................................................... 5-1
6 DESIGN ADEQUACY (REF DCPP EDDG-006 ATTACHMENT 8.1) ..................................... 6-1
6.1 POWER SUPPLY (STATION BATTERY AND CHARGER) ................................................................. 6-1
6.1.1 Redundancy and Availability ............................................................................................. 6-1
6.1.2 Capacity and Capability .................................................................................................... 6-1
6.1.3 Worst Case Power Supply Conditions ............................................................................... 6-2
6.2 RACEWAY SYSTEM DESIGN ........................................................................................................ 6-2
6.2.1 Physical Separation ........................................................................................................... 6-2
6.3 SCHEME DESIGN ......................................................................................................................... 6-2
6.3.1 Redundancy ........................................................................................................................ 6-2
6.3.2 Single Point or Common Mode Failures (Failure Mode Analysis) ................................... 6-2
6.3.3 Security Enhancements ...................................................................................................... 6-4
6.4 SURGE PROTECTION .................................................................................................................... 6-7
6.4.1 UR Relay Surge Protection ................................................................................................ 6-7
6.4.2 EMI and RFI (Electro-Magnetic and Radio Interference) ................................................ 6-7
6.5 PROTECTION DEVICES ................................................................................................................. 6-8
6.5.1 Sensitivity ........................................................................................................................... 6-8
6.5.2 Relay Reliability ................................................................................................................. 6-8
6.5.3 Coordination ...................................................................................................................... 6-8
6.5.4 Relay Burden ...................................................................................................................... 6-8
6.5.5 Scheme Accuracy ............................................................................................................... 6-8
6.6 DESIGN CALCULATIONS (QUALITY ASSURANCE) ....................................................................... 6-9
6.6.1 Setting Reevaluation and Update ....................................................................................... 6-9
6.6.2 N60 Relay Setting Ownership .......................................................................................... 6-10
6.6.3 Setting Verification (Protection Department) .................................................................. 6-10
6.6.4 Relay Firmware ............................................................................................................... 6-10
7 GLOSSARY...................................................................................................................................... 7-1
8 ADDITIONAL REFERENCE DOCUMENTS ............................................................................. 8-1
9 APPENDIX A: DCSPS CRITICAL SET POINTS (COMMISSIONING SETTINGS) .......... 9-1
9.1 SET POINTS AND DEFINITIONS .................................................................................................... 9-1
10 APPENDIX B: DIABLO CANYON SPS ALARM POINTS ................................................ 10-1
10.1 DIABLO CANYON ANNUNCIATION & RTU ALARMS ................................................................. 10-1
11 APPENDIX C: DIABLO CANYON SPS DRAWINGS ........................................................ 11-1
11.1 DIABLO CANYON SPS DRAWING LIST ...................................................................................... 11-1
12 APPENDIX D: DCSPS EVENT CATEGORY DETAILED DESCRIPTION ................... 12-1
13 APPENDIX E: UNIT TRIPPING DETERMINATION AND KARNAUGH MAPS ........ 13-1
About this Handbook
DCSPS Operations Handbook Page 1-1 Rev Date/Time: 1/7/2019 4:31:00 PM
1 About this Handbook
This handbook was developed as a reference guide to the design, operating procedures, systems, and testing
related to the Diablo Canyon Special Protection Scheme (Diablo Canyon SPS).
This handbook is designed so that it may be used as a general reference guide, classroom-training manual or
tutorial for independent study. The organization allows different types of users to easily find the information
in the level of detail appropriate for their needs.
1.1 Audience
The target audience for the document includes:
▪ TOC (Transmission Operations Center) Operators
▪ Diablo Canyon Transmission Control Center Operators
▪ System Protection and Diablo Canyon Plant Engineers
▪ Diablo Canyon training personnel
▪ Strategic Planning and Technical Service (SATS) Department
▪ (OE) Operations Engineering Engineers
▪ Diablo Canyon Substation Maintenance
Document Revision History
DCSPS Operations Handbook Page 2-1 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
2 Document Revision History
Previous Document Version
Revision Date
Description of Changes Change Author/ Approver
New Version Number
N/A 10/10/05 ▪ Document Creation (Draft “Table of Contents Version” For Circulation)
Davis Erwin A
A 02/10/06 ▪ Adopted Anatoliy Meklin’s comments within the SPS Overview section (“Background” section authored by Anatoliy Meklin)
Davis Erwin / Anatoliy Meklin / Ed Taylor
2006-02-10
2006-02-10 03/14/06 Adopted comments from:
▪ Anatoliy Meklin (TES)
▪ John Grant (OPS Engineering)
▪ Ed Taylor (System Protection)
▪ Joe Goryance (Diablo Canyon Engineering)
▪ Davis Erwin (System Protection)
Davis Erwin 2006-03-14
2006-03-14 05/12/06 The following modifications are not a result of a change in the concept or functionality of the of the DCSPS scheme. The updates to the document are as follows:
▪ Updated Appendix A to include the DCSPS relay set-points that resulted from the April-May 2006 TES study. (These settings will be the In-Service commissioning set points)
▪ Updated Appendix B to include a better description of the SCADA Arming points (3-SYS A and 3-SYS B). This includes associated description in section 3.4.1.3
▪ Updated the DOO section 3.4.1.1.1 for operator response to a DCSPS trip. (Based on feedback from the on-site operator training held 04-27-2006)
▪ Added Testing Matrix to Section 5 (Matrix was completed for on-site commissioning during the first week of May 2006.)
▪ Added a description table for every DCSPS programmable LED. (section 3.4.2)
▪ Minor wording corrections to Section 6.3.3.3
Davis Erwin 2006-05-12
Document Revision History
DCSPS Operations Handbook Page 2-2 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
Previous Document Version
Revision Date
Description of Changes Change Author/ Approver
New Version Number
2006-05-12 07/14/09 The following modifications are not a result of a change in the concept or functionality of the of the DCSPS scheme. The updates to the document are as follows:
▪ Updated Figure 12 – Pictorial representation of the Communication Network connection of the DCSPS relays. The relays are to be moved from the PDN to the ODN to comply with NERC CIP requirements. (Sketch provided by Greg Howaniec – PG&E Sr. Network Specialist - ITI Network Operations)
▪ Updated wording in section 4.4.2 to describe the new ODN relay network connection.
▪ At three (3) places within the document, changed the wording “RAS Network” to “Communication Network”. Reason: “RAS Network “ Implies “PDN”
Davis Erwin 2009-07-14
Description of Operations
DCSPS Operations Handbook Page 3-3 Rev Date/Time 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
3 Description of Operations
This section contains core information on the operating procedures for the Diablo Canyon Special Protection
Scheme (DCSPS).
3.1 Diablo Canyon SPS Overview and Concepts
Special Protection Schemes (SPS) are designed to respond quickly to pre-defined events for which reliance on
human intervention is insufficient to protect equipment and minimize the adverse impacts of those events. Special
Protection Schemes can vary widely in purpose and scope.
The objective of this section is to provide an understanding of the purpose and function of the Diablo Canyon SPS.
It is also intended to provide information on system design, scope, how the scheme works and a comparison
between normal operating conditions and Diablo Canyon SPS event conditions. Specific guidelines and procedures
for the practical usage of the Diablo Canyon SPS system are covered in subsequent sections of this document.
3.1.1 Background
The various DCPP stability studies and the plant operating experience have not revealed any plant
stability problems related to its operation with all three 500 kV lines in service or following a loss of a
single 500 kV component (a line or a unit). The plant performance in such situations is in compliance
with the NERC/WECC Planning Standards
(http://www.wecc.biz/documents/library/procedures/CriteriaMaster.pdf, pages 9-13, 24 and 25) for the
A (all facilities in service) and B (loss of a single element) categories of events.
However, the various studies conducted by Strategic and Technical Services (SATS) and Operations
Engineering (OE) teams have shown that double line outages (DLO), single line outages (SLO) in 2-
line scheme and delayed SLO could lead to intensive synchronous swings or to a loss of synchronism
between the plant generators and the WECC system. This may trigger different plant protective
devices, such as out-of-step protection and Reactor Coolant Pump (RCP) undervoltage protection,
resulting in double unit outages (DUO). This may also violate the NERC/WECC Planning Standards
for more severe disturbances.
The potential of instability and DUO increases if one of the 500 kV lines is out of service. This
resulted in the DCPP practice to curtail the plant in 2-line schemes of operation.
More specifically, the main negative consequences of the intensive synchronous swings or a loss of
synchronism are:
a. DUO would impose definite strain on the remaining generating resources in the system
to supply demand, especially if other resources are off-line.
b. Out-of-step conditions would impose severe stress on both units’ equipment.
c. DUO could be accompanied by the undesirable loading of the on-site diesel generators
because capability of the off-site power source is not sufficient for DUO.
d. DUO can bring stability of the WECC system close to critical conditions causing a
severe test for the variety of control and protective devices in the entire system The
prevention of DUO would minimize the possibility of cascading, e.g. collapse and
separation of California-Oregon Intertie (COI). Cascading is not permitted by the
NERC/WECC Planning Standard even for relatively rare disturbances combined with a
failure or a partial operation of control and protective devices.
e. Transient voltage dips during the intensive synchronous swings or in out-of-step
conditions (before out-of-step protection trips the units) may exceed values allowed by
the NERC/WECC and PG&E Planning Standards.
The “d” and “e” items correspond to event categories C and D in the NERC/WECC Planning
Standard.
Description of Operations
DCSPS Operations Handbook Page 3-4 Rev Date/Time 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
The definitions of categories and the corresponding allowable impacts are given in Table I (NERC) of
the Standard. Category C corresponds to the above described DLO, SLO and delayed SLO with SLG
faults. Instability and cascading for category C are not allowed. Automatic removal of certain
generators is allowed to prevent instability or cascading.
The W-1 table (WECC) complements the category C definition by specifying event frequency, which
is 0.033-0.33 event/year. This frequency for DCPP is about 0.08 in accordance with the plant line
outage data.
Table W-1 and Figure W-1 specify allowable transit voltage dips - should not be greater than 30% for
category C. Even a short-time DCPP out-of-step violates this criterion because transient voltage dips
exceed 60% on the 500 kV bus and 40% on the 25 kV buses for about 1 second. The main goal of this
criterion is to prevent intensive swings or an out-of-step of large power plants or parts of the system.
Such DCPP swings produce a very significant impact to the entire system because a swing electrical
center is located in the 500 kV grid outside of the relatively small impedance of the plant and the
duration of the voltage decline is quite significant because of the high plant inertia (which is
additionally increased with the turbine replacement). Transient voltages should be even greater to
prevent operation of the RCP undervoltage protection. Everything possible should be done to avoid
intensive swings and even half of an out-of-step cycle of a 2,450 MW power plant. Out-of-step
protection is a last line of defense and should operate when measures, preventing an out-of-step, have
failed.
Category D corresponds to SLO with delayed 2 or 3-phase faults or to less severe disturbances with
failures or misoperations of control and protective devices (including devices outside DCPP). The
type of cascading, which can occur on a DCPP DUO, is not allowed.
The DCPP SPS installation will minimize the possibility of DUO and other negative consequences.
The 2001 SATS study “Mitigation Measures for Double Outages at Diablo Canyon Power Plant” and
the several farther developments defined the effective remedial actions and the main SPS design and
setup principles. Study conclusions include:
▪ The most effective remedial action to maintain DCPP stability is an immediate trip of one of the
generators. This action prevents intensive swings or out-of-step of the remaining generator for the
most credible severe line outages. The forced generator voltage pulsing and turbine fast valving
were found not effective enough.
▪ SPS should trip one generator on severe disturbances if plant generation exceeds certain levels.
These arming levels should be established in SPS for each type of outages (DLO, SLO in 2-line
scheme, delayed SLO) to provide compliance with the transient voltage dip criteria, non-operation
of the out-of-step protection and non-operation of the RCP protection.
▪ The arming levels could be automatically calculated in SPS as a function (e.g. polynomial) of the
most significant variables or set unchangeable based on the “worst” values of those variables. The
most significant variables - generator terminal bus voltages prior to a disturbance and short circuit
severity, which corresponds to the level and duration of a positive sequence voltage dip.
Maintaining initial terminal voltages as high as possible is essential. Voltage increase from 0.97
p.u. to 1 p.u. makes impossible post-disturbance oscillations, increases arming levels by more than
200 MW and makes SPS effective for a wider range of disturbances.
▪ The arming levels or arming functions, obtained from stability studies should be set with a margin,
sufficient to cover variations of the less significant variables and to count inaccuracy of the system
model and measurements.
Description of Operations
DCSPS Operations Handbook Page 3-5 Rev Date/Time 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
▪ Total SPS time from a 500 kV line short circuit inception to generator breaker trip coil energizing
should not be more than 0.07 sec. for normal line trips and 0.2 sec. for delayed line trips. This
means that the initiating relay protection circuits should not be supervised by contacts (signals) of
the line minimum current relays or the line breaker seals because of their insufficient speed.
▪ The immediate SPS actions are not necessary on outages, which are not aggravated by short
circuits. Therefore, all speed-critical outages are accompanied by relay protection operation on
both ends of the 500 kV lines. This makes unnecessary transferring line outage signals from Gates
and Midway to DCPP (see “Modification of the DCPP SPS Technical Requirements”, SATS,
2004).
▪ The SPS generator tripping action might be necessary to prevent purely damped oscillation which
may occur if only one 500 kV line remains after an outage. These post-disturbance oscillations
have been indicated in the simulations with the simplified representation of the DCPP auxiliaries.
The more detailed dynamic auxiliary models have resulted in better damping but did not eliminate
the possibility of oscillations if SPS does not trip a generator. The relay protection initiates
immediate SPS generator tripping for the fault related line outages. For the no-fault line outages,
a generator tripping action can be delayed by 2-3 seconds. This is sufficient to indicate no-fault
switching of either end of a 500 kV line and initiate SPS.
▪ Default SPS selection of a generator for tripping can be manually established by the operator.
This selection should be automatically overridden if the switchyard post-disturbance topology is
such that the default trip causes loss of both generators or 500 kV lines. The manual selection
should take into consideration that Unit 1 features more intensive swings because of the less
favorable generator characteristics. Therefore, a remedial trip of the Unit 1 generator is
more effective for the voltage transient dip reduction and for the plant stability.
▪ SPS actions provide satisfactory plant performance for the category C and some of the category D
disturbances. SPS actions are effective for double line outages, for single phase faults with
breaker failures (sometimes necessary) and some cases of multi-phase faults with single phase
breaker failures. SPS cannot prevent operation of the RCP undervoltage protection on multi-phase
faults with multi-phase breaker failures and on some multi-phase faults with single phase failures.
▪ Triggering of the RCP undervoltage protection cannot be excluded for some category D
disturbances when SPS is not armed or generator tripping is not effective. RCP shuts a reactor
down and closes turbine valves, but does not isolate a generator from the grid for 30 sec. The
isolation occurs earlier by the unit out-of-step protection if other generator tripping and valve
closing do not prevent a loss of stability.
The more detailed discussion of different SPS issues can be found in the above mentioned SATS
reports. The SPS arming level calculations is in progress and will be completed in May 2006.
3.1.2 Transmission System Overview
Figure 1 illustrates the electrical infrastructure of the transmission system at Diablo Canyon. To
varying degrees, all of the elements in the figure are essential to the schemes proper operation.
Included are the critical elements that interact with the DCSPS:
1. Diablo Canyon 500kV Bus 1 and Bus 2
2. Diablo Canyon 500kV Bays 2, 3, and 4.
3. Unit #1 and #2 500kV Breakers CB 532, 632, 542, 642.
4. Diablo Canyon 500kV Line Breakers CB 622, 722, 632, 732, 642, and 742
5. 500kV line “Remote End” terminals at Gates and Midway
Description of Operations
DCSPS Operations Handbook Page 3-6 Rev Date/Time 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
MIDWAY
BUS 2
GATES
BUS 1
DIABLO
CANYON
BUS 2
742642
DIABLO - MIDWAY #2 500kV LINE
DIABLO - MIDWAY #3 500kV LINE
GATES - DIABLO CANYON 500kV LINE
732
722622
812 912
802 902
652 552
542
DIABLO
CANYON
BUS 1
DIABLO
CANYON
UNIT 2
632532
DIABLO
CANYON
UNIT 1
ZZY Y
ZYX Y
ZYX YX YZ Y
Z YXY
DCPP_DCSPS 10-2005
Dpe4
Figure 1: Diablo Canyon One-Line Diagram including the Remote Line End Terminals
Description of Operations
DCSPS Operations Handbook Page 3-7 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
3.1.3 Diablo SPS (DCSPS) Purpose and Requirements
The Diablo Canyon SPS (DCSPS) was developed to mitigate the potential loss of two Diablo Canyon
Units after the occurrence of certain 500kV events. These events, left unmitigated, may result in the
loss of both Diablo Canyon units. DCSPS will prevent voltage dips that are in violation of the
NERC/WECC Standards. These events will be categorized and consist of combinations of Line Trips
and/or Line Outages and/or 500kV breaker failures.
For any system event that meets the criteria, the scheme will intentionally trip the 500kV breakers of
one unit, leaving the other unit connected to the 500kV system. A DCSPS trip will be issued for three
distinct scenarios. These scenarios are referred to in the remaining documentation as “DCSPS
Event(s)”:
DCSPS Event Description:
1. Two 500kV Line System, (one 500kV line has been “out” beyond a certain period of time),
followed by either of the following two events:
a. The sudden loss of one of the remaining two Diablo Canyon 500kV lines due to a
protective relay trip. (Tripping for this event is supervised by Diablo MW generation
arming level)
b. The loss of one of the remaining two Diablo Canyon 500kV lines by manual open (or
equivalent), at either Diablo or the remote station. (Tripping for this event is supervised
by a Diablo MW generation arming level)
2. Normal 500kV Line System, (all three lines are in-service and normal), followed by either of
the following two events:
a. The sudden loss of two Diablo Canyon 500kV lines due to a protective relay trip.
(Tripping for this event is supervised by a Diablo MW generation arming level)
b. The loss of two Diablo Canyon 500kV lines by a manual open (or equivalent), at either
Diablo or the remote stations. (Tripping for this event is supervised by a Diablo MW
generation arming level)
3. Diablo Canyon 500kV circuit breaker failure that occurs after failing to trip for a severe fault
condition. (Tripping for this event is supervised by Diablo MW generation arming level and
by the collapse of the 500kV positive sequence voltage level)
3.1.4 Diablo Canyon SPS System Description and Definitions
The Diablo Canyon SPS is a fully redundant scheme. The scheme consists of two systems, (System
“A” and System “B”), each of which are programmed identically, and each can operate independently
of the other. All of the components associated with the DCSPS are installed within the Diablo
Canyon 500kV control building. (No devices for this scheme exist at the remote stations or in the
Diablo Canyon plant)
The functionality of the Diablo Canyon SPS is dependent upon reliably performing the following:
1. Sensing a protective relay trip of any Diablo Canyon 500kV breaker.
2. Sensing a breaker failure condition of any Diablo Canyon 500kV breaker.
3. Sensing the position of each Diablo Canyon 500kV breaker (For the purposes of the
500kV Bus configuration. The bus configuration is used in the trip table.)
4. Sensing the current flow on each of the three 500kV lines and each of the two units (as
measured at 500kV)
5. Sensing a line outage of each of the three 500kV lines and a unit outage of each of the
two units.
6. Calculating the plant MW export flow.
7. Calculating the 500kV Positive sequence voltage.
Description of Operations
DCSPS Operations Handbook Page 3-8 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
8. Capability of tripping CB 532 and CB 632 (Unit #1 high side circuit breakers).
Capability of tripping CB 542 and CB 642 (Unit #2 high side circuit breakers)
9. Communication infrastructure that allows the transmission of data between all of the
devices in the scheme. (All devices for the scheme are located in the Diablo Canyon
500kV Control Room)
10. Sensing the operator designated interfaces with the scheme. (Pushbuttons, CB
Maintenance switches, and Unit selector switch, etc.)
3.1.4.1 DSCPS System Input and Output (I/O)
The Diablo Canyon SPS relays monitor the following AC quantities:
▪ Diablo – Gates 500kV Line three phase current
▪ Diablo – Midway #2 500kV Line three phase current
▪ Diablo – Midway #3 500kV Line three phase current
▪ Diablo Unit #1 500kV three phase current
▪ Diablo Unit #2 500kV three phase current
▪ Diablo Unit #1 500kV three phase potential
▪ Diablo Unit #2 500kV three phase potential
▪ Diablo – Gates 500kV Line three phase potential (System A only)
▪ Diablo – Midway #3 500kV Line three phase potential (System B only)
The DCSPS relays monitor the following digital events (DC status change):
▪ Eight CB status Inputs (Breaker position determined by 52b seals)
▪ Eight CB Breaker Failure Initiate Trip Circuit Inputs. (BFI indicate Protection Trips)
▪ Eight Breaker Failure Trips (Indicates when a breaker has failed to operate)
▪ Unit Selector Switch
▪ CB Maintenance Switch inputs for CB’s 532, 542, 632, and CB 642. (CB 622, 722, 732 and CB
742 monitor the CB Maintenance switch in parallel with the respective CB status input.)
The DCSPS relays output the following digital events via relay contact(s) closure:
▪ CB 532 Trip Output (Trip Coil 1)
▪ CB 532 Trip Output (Trip Coil 2)
▪ CB 632 Trip Output (Trip Coil 1)
▪ CB 632 Trip Output (Trip Coil 2)
▪ CB 542 Trip Output (Trip Coil 1)
▪ CB 542 Trip Output (Trip Coil 2)
▪ CB 642 Trip Output (Trip Coil 1)
▪ CB 642 Trip Output (Trip Coil 2)
▪ CB 532 Breaker Failure Initiate
▪ CB 632 Breaker Failure Initiate
▪ CB 542 Breaker Failure Initiate
▪ CB 642 Breaker Failure Initiate
Description of Operations
DCSPS Operations Handbook Page 3-9 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
▪ SCADA Alarms and Station Annunciation (See Appendix for Complete Listing)
▪ Relay status LED’s (See Later Sections for LED Assignments)
3.1.4.2 Diablo Canyon MW Export Calculations
Diablo Canyon MW export calculation is critical to the operation of the Diablo Canyon SPS and will
determine if any or all of the three distinct events categories are ARMED. For the Diablo SPS, the
Diablo Canyon Export is defined as the sum of power flow on the following two components:
▪ Unit #1
▪ Unit #2
The Diablo SPS relays require proper 500kV potential from Unit #1 and Unit #2 T-taps as well as
500kV currents from the Unit #1 and Unit #2 circuit breakers to accurately calculate the total Diablo
MW export.
3.1.4.3 500kV Bus Configuration
Diablo Canyon SPS determines 500kV bus configuration by continuously evaluating the breaker
position status and CB Maintenance switch inputs. Accurate determination of the 500kV Bus
configuration is essential for determining if a Unit will be tripped. If a Unit will be tripped, the 500kV
breaker configuration will determine which one (See Appendix).
3.1.4.4 Line and Unit Outage Status Determination
Diablo Canyon SPS determines 500kV Line/Unit outage status by continuously evaluating current
flow (to detect undercurrent conditions) and Line/Unit breaker seal status. The “Line Outage”
determination is done “Locally” by monitoring ONLY the necessary quantities at Diablo Canyon.
Line Outage Determination is necessary for two reasons:
1. If all prerequisite conditions are met, the Line Outage(s) will result in DCSPS tripping.
2. Distinguish the difference between DCSPS Event 1 and DCSPS Event 2 categories.
3.1.4.4.1 Local Line Outage
A Local line outage will be determined if both breakers for the line are opened (or in
Maintenance) AND the undercurrent element has been picked up. (See settings appendix for the
UC1 setpoint)
3.1.4.4.2 Remote Line Outage
A Remote line outage will be determined if the line is open ended at the remote substation by
sensing only the assertion of the undercurrent element for a predefined time (See settings
appendix for the UC1 setpoint).
Furthermore, to add security, the remote line outage determination will only be enabled when
the Plant Generation output is above the minimum MW arming setpoint. (Remote line outage
detection is disabled when the scheme is
3.1.4.5 Protection Relay Tripping – Sudden Line/Unit Trip Determination
The Diablo SPS detects the imminent, or sudden, outage of a Line/unit by continuously monitoring
the Breaker Failure Initiate circuits of each Diablo Canyon 500kV breakers. A Breaker Failure
Initiate (BFI) on a Circuit Breaker is an indication that the CB is being tripped by a protection device.
The DCSPS relay logic will determine what component(s), (Bank or Line), is tripped by sensing
which group of CB’s have had their Breaker Failure Device initiated.
A “Manual Open” of the Line/Unit is not defined as an Imminent or sudden outage of the Line/Unit.
Any normal clearance procedure is not defined as an Imminent or sudden outage. “Manual Open”
will NOT initiate breaker failure on the circuit breaker.
3.1.4.6 Breaker Failure Relay Tripping
If a breaker has failed to open for a trip issued by a protection relay, the breaker failure tripping will
open ALL breakers electrically adjacent to the failed CB.
Description of Operations
DCSPS Operations Handbook Page 3-10 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
The Diablo SPS detects breaker failure tripping by continuously monitoring the Breaker Failure TRIP
circuits of each Diablo Canyon 500kV breakers.
3.1.4.7 Fault Severity Determination
The fault severity sensing is used to supervise only in the Breaker Failure DCSPS events. Line
Outage and Line Tripping DCSPS events do not use positive sequence voltage supervision
Diablo Canyon SPS determines a “Medium” and “Severe” fault condition by measurement of the
500kV positive sequence voltage. Each System, (A and B), measure the 500kV voltage at the T-tap
CCVT’s for Unit #1 and Unit #2. Each CCVT secondary voltage is wired to separate relays.
A collapse of the positive sequence voltage beyond a certain set-point UVm will distinguish a
“Medium” fault condition. A collapse of the positive sequence voltage beyond a lower set-point UVs
will distinguish a “Severe” fault condition.
3.1.4.8 Diablo SPS Tripping
Diablo Canyon SPS will trip a Unit only if it result in a benefit to the system. Many of the events, by
there very nature and initial operational configuration of the 500kV bus, will result in the removal of
one or both units. If the initiating event removes one or both units, DCSPS will not issue a trip.
Description of Operations
DCSPS Operations Handbook Page 3-11 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
3.1.5 Diablo Canyon SPS Event Categories
The Diablo Canyon SPS (DCSPS) events are broken down into three major categories. (If
greater detail is desired, see the table in the appendix that describes each event and number
of permutations)
3.1.5.1 DCSPS Event 1: Loss of One Line in a Two Line System
One Line has been out of service for greater than TSIMULTANEOUS and Two lines are
in-service. This is the prerequisite condition for this event, followed by:
1. Protection trip of one of the two in-service lines
2. Outage of one of the two in-service lines
3.1.5.1.1 Description
A unit will be tripped for instance in this category provided ALL of the following
conditions are met:
• The Diablo Canyon plant Megawatt (MW) export level is above a predefined
arming level in the moments before the event. (The MW arming level for this
event will be referred to as L1 and the time prior to the event as TMW)
• The Diablo Canyon 500kV breaker configuration before and after the event
are positioned, (Open or Closed), such that a Diablo Canyon SPS operation is
logically reasonable. (If the initiating event removes one or both units, the
Diablo SPS will not trip) (See Trip Logic Appendix)
3.1.5.1.2 Indication
All appropriate Relay LED’s related to the particular event scenario will be
illuminated and latched. Any trip associated with the DCSPS and the event causing
the trip will be targeted on the 537DCSPS relay. (See RELAY LED section)
The appropriate Station Annunciators and RTU points asserted.
3.1.5.2 DCSPS Event 2: Loss of Two Lines in a Three Line System
Three lines in-service is the prerequisite condition for this event, followed by:
1. Protection trip of two lines within the TSIMULTANEOUS window of time
2. Protection Trip of one Line and the Outage (Non-Trip) of another line within the
TSIMULTANEOUS window of time.
3.1.5.2.1 Description
A unit will be tripped for instances in this category provided ALL of the following
conditions are met:
• The Diablo Canyon plant Megawatt (MW) export level is above a predefined
arming level in the moments before the event. (The MW arming level for this
event will be referred to as L2 and the time prior to the event as TMW)
• The Diablo Canyon 500kV breaker configuration before and after the event
are positioned, (Open or Closed), such that a Diablo Canyon SPS operation is
logically reasonable. (If the initiating event removes one or both units, the
Diablo SPS will not trip) (See Trip Logic Appendix)
Description of Operations
DCSPS Operations Handbook Page 3-12 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
3.1.5.2.2 Indication
All appropriate Relay LED’s related to the particular event scenario will be
illuminated and latched. Any trip associated with the DCSPS and the event causing
the trip will be targeted on the 537DCSPS relay. (See RELAY LED section)
The appropriate Station Annunciators and RTU points asserted.
3.1.5.3 DCSPS Event 3: 500kV Circuit Breaker Failure
3.1.5.3.1 Description
A unit will be tripped for instances in this category for two conditions:
1. Breaker Failure for a “Severe” fault
• The Diablo Canyon plant Megawatt (MW) export level is above a predefined
arming level in the moments before the event. (The MW arming level for this
event will be referred to as L3 and the time prior to the event as TMW)
• The positive sequence voltage has collapsed to a predefined level indicating a
“Severe” fault has occurred. (The positive sequence voltage level for this
event will be referred to as UVs )
• The Diablo Canyon 500kV breaker configuration before and after the event
are positioned such that a Diablo Canyon SPS operation is logically
reasonable. (If the initiating event removes one or both units, the Diablo SPS
will not trip)
2. Breaker Failure for fault with “Medium” severity
• The Diablo Canyon plant Megawatt (MW) export level is above a predefined
arming level in the moments before the event. (The MW arming level for this
event will be referred to as L4 and the time prior to the event as TMW)
• The positive sequence voltage has collapsed to a predefined level indicating a
“Medium” fault has occurred. (The positive sequence voltage level for this
event will be referred to as UVm)
• The Diablo Canyon 500kV breaker configuration before and after the event
are positioned such that a Diablo Canyon SPS operation is logically
reasonable. (If the initiating event removes one or both units, the Diablo SPS
will not trip)
3.1.5.3.2 Indication
All appropriate Relay LED’s related to the particular event scenario will be
illuminated and latched. Any trip associated with the DCSPS and the event causing
the trip will be targeted on the 537DCSPS relay. (See RELAY LED section)
The appropriate Station Annunciators and RTU points asserted.
3.2 Standard Operating Devices, Description and Procedures
Operators have several methods of interfacing with this scheme to facilitate implementing operation
directives as well as accommodating any system set-ups, (including procedures for equipment
maintenance and servicing activities), that the scheme could not normally detect without human
interface.
All of the equipment referred to in this section is located within the Diablo Canyon 500kV control
room.
Description of Operations
DCSPS Operations Handbook Page 3-13 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
The operator interface equipment include following:
1. System Cut-Out Switch
2. Unit Selector Switch
3. 500kV Circuit Breaker Maintenance Switch(s)
4. UR Relay Reset Pushbutton (To Reset the Scheme after Tripping)
5. Line and Unit Maintenance Switch(s)
Operator actions need to be included in individual switching tags for any clearances or real time
operating scenarios that affect the proper operation of the Diablo Canyon SPS. In general, the steps
involve positioning DCSPS related manual switches on control boards at the appropriate time within
the preferred sequence. This section will summarize the steps and sequence that need to be included
in typical clearances or operating set-ups. Clearances or set-ups not covered in the following sections
need to be assessed on a case-by-case basis. The responsible Operations Engineer and System
Protection Engineer should be consulted as needed to provide guidance on how to modify or
incorporate special steps, if any, in the switching tag.
3.2.1 Diablo Canyon SPS Cut-Out Switch
The Diablo Canyon SPS has two separate Cut-Out switches, one for System A and one for
System B. Each of these two switches has two positions: CUT-IN or CUT-OUT. Two
separate cutout switches allow greater flexibility to perform maintenance, software
upgrades, or testing one system at a time.
1. Diablo Canyon SPS System A Cutout Switch: DEVICE RCO/DCSPS-A
2. Diablo Canyon SPS System B Cutout Switch: DEVICE RCO/DCSPS-B
These cutout switches are located side-by-side on the Diablo Canyon SPS Control Panel
Rack #1.
Placing the System-A cutout switch in the CUTOUT position will result in the following:
a. The trip output circuits from System – A to CB 532, 542, 632, and 642 will
be physically interrupted by a contact of the Cut-Out switch. (No Trips
issued from System-A will result in a unit separation)
b. The breaker failure initiate output circuits from System – A to CB 532, 542,
632, and 642 will be physically interrupted by a contact of the Cut-Out
switch.
c. The unit-1 and unit-2 trip output circuits originating from System – A and
wired to the System – B inputs will be physically interrupted by a latching
contact of the System – A relay. (Enabling System-A to be cut-out for
testing while the other remains in-service)
d. The “System – A” cut-in status that is continuously communicated via
hardware connection from the System – A relay to System B will change
state. (System – B senses the Cut-Out status of System – A. This point is
used for the Sys-A&B trip comparison logic.)
e. System – A logic and settings function normally when System – A is cut-out.
(No logic supervision within System – A is utilized when System – A is cut-
out. This is important for testing scenarios)
Placing the System-B cutout switch in the CUTOUT position will result in the following:
a. The trip output circuits from System – B to CB 532, 542, 632, and 642 will
be physically interrupted by a contact of the Cut-Out switch. (No Trips
issued from System-B will result in a unit separation)
Description of Operations
DCSPS Operations Handbook Page 3-14 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
b. The breaker failure initiate output circuits from System – B to CB 532, 542,
632, and 642 will be physically interrupted by a contact of the Cut-Out
switch.
c. The unit-1 and unit-2 trip output circuits originating from System – B and
wired to the System – A inputs will be physically interrupted by a latching
contact of the System – B relay. (Enabling System-B to be cut-out for
testing while the other remains in-service)
d. The “System – B” cut-in status that is continuously communicated via
hardware connection from the System – B relay to System A will change
state. (System – A senses the Cut-Out status of System – B. This point is
used for the Sys-A&B trip comparison logic.)
e. System – B logic and settings will function normally when System – B is
cut-out. (No logic supervision within System – B is utilized when System –
B is cut-out. This is important for testing scenarios)
A figure in the testing section illustrates the Cut-Out functions that are described above.
To completely cutout the Diablo Canyon SPS, both switches will need to be placed in the
cutout position.
Each RCO is independently SCADA controllable.
3.2.2 Diablo Canyon SPS Unit Selector Switch
The Diablo Canyon SPS has one Unit Selector Switch. The selector switch provides an
input to both System A and System B. This is a two position switch: UNIT1 or UNIT2.
1. Diablo Canyon SPS Unit Selector Switch: DEVICE 543UTS
The Unit Selector Switch is located on the Diablo Canyon SPS Control Panel Rack #1.
Placing the Unit Selector Switch in the UNIT1 position informs the logic that the preferred
unit for tripping is Unit #1.
Placing the Unit Selector Switch in the UNIT2 position informs the logic that the preferred
unit for tripping is Unit #2.
It is important to note that the “DCSPS EVENT” as sensed by the scheme, and the 500kV
CB physical topology, determines which unit will be tripped. Only for those scenarios that
allow the unit selector switch to influence the logic, is it used for determination of unit
tripping. (See tripping logic in the Appendix). The scheme may trip the unit that is NOT
selected by the unit selector switch.
The Unit selector switch is not SCADA controllable.
3.2.3 500kV Circuit Breaker Maintenance Switches
The Diablo Canyon SPS makes use of the (8) 500kV circuit breaker maintenance switches.
Each maintenance switch provides an input to both System A and System B. These are
two position switches: NORMAL or MAINTENANCE.
These same switches are also used for the 500kV RAS. Recognize that the repositioning
of these switches affect both schemes independently.
• CB 622 Normal/Maintenance SW (DEVICE 543M-622)
o Affects the Diablo – Gates Line Outage Logic
o Affects the Diablo – Gates Line Trip Sensing Logic
o Affects the CB 622 Breaker Failure Tripping Sensing.
• CB 722 Normal/Maintenance SW (DEVICE 543M-722)
Description of Operations
DCSPS Operations Handbook Page 3-15 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
o Affects the Diablo – Gates Line Outage Logic
o Affects the Diablo – Gates Line Trip Sensing Logic
o Affects the CB 722 Breaker Failure Tripping Sensing.
• CB 532 Normal/Maintenance SW (DEVICE 543M-532)
o Affects the Unit #1 Outage Logic
o Affects the Unit #1 Trip Sensing Logic
o Affects the CB 532 Breaker Failure Tripping Sensing.
o Affects the UNIT #1 DCSPS TRIPPING
• CB 632 Normal/Maintenance SW (DEVICE 543M-632)
o Affects the Unit #1 Outage Logic
o Affects the Unit #1 Trip Sensing Logic
o Affects the Diablo – Midway #3 Line Outage Logic
o Affects the Diablo –Midway #3 Line Trip Sensing Logic
o Affects the CB 632 Breaker Failure Tripping Sensing.
o Affects the UNIT #1 DCSPS TRIPPING
• CB 732 Normal/Maintenance SW (DEVICE 543M-732)
o Affects the Diablo – Midway #3 Line Outage Logic
o Affects the Diablo –Midway #3 Line Trip Sensing Logic
o Affects the CB 732 Breaker Failure Tripping Sensing.
• CB 542 Normal/Maintenance SW (DEVICE 543M-542)
o Affects the Unit #2 Outage Logic
o Affects the Unit #2 Trip Sensing Logic
o Affects the CB 542 Breaker Failure Tripping Sensing.
o Affects the UNIT #2 DCSPS TRIPPING
• CB 642 Normal/Maintenance SW (DEVICE 543M-642)
o Affects the Unit #2 Outage Logic
o Affects the Unit #2 Trip Sensing Logic
o Affects the Diablo – Midway #2 Line Outage Logic
o Affects the Diablo – Midway #2 Line Trip Sensing Logic,
o Affects the UNIT #2 DCSPS TRIPPING
o Affects the CB 642 Breaker Failure Tripping Sensing.
• CB 742 Normal/Maintenance SW (DEVICE 543M-742)
o A portion of Diablo – Midway #2 Line Outage Logic
o A portion of Diablo –Midway #2 Line Trip Sensing Logic
o Part of CB 742 Breaker Failure Tripping Sensing.
Each of the Circuit breaker maintenance switches is located on the respective Circuit
Breaker Control Panel.
Description of Operations
DCSPS Operations Handbook Page 3-16 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
Placing a switch in the Maintenance position provides a breaker open status to the scheme
for that breaker. This affects the scheme logic in the following way:
1. 500kV Bus Configuration: The Maintenance position substitutes for the Breaker
Seal for determining position of the Breaker. The Breaker will be considered
OPEN. (The breaker position is critically important to determining the
operational configuration of the 500kV bus. The configuration will be used to
determine which, (If either), unit will be tripped for an initiating event)
2. OUTAGE Line or Unit: The Maintenance position substitutes for the Breaker
Seal for determining position of the Breaker. The Breaker will be considered
OPEN. (The remaining breaker for the Line or Unit that has its maintenance
switch in the “Normal” position will be the only breaker used for determining an
OUTAGE)
3. TRIP SENSING Line or Unit: The scheme logic will IGNORE any trips that are
sensed for a breaker with the CB Maintenance switch in the Maintenance
position. (The remaining breaker for the Line or Unit that has its maintenance
switch in the “Normal” position will be the only breaker used for determining
TRIP Sensing)
4. BREAKER FAILURE TRIP SENSING CB: The scheme logic will IGNORE
any trips from the Breaker Failure Relay Scheme.
5. DIABLO SPS TRIPPING: The scheme logic will NOT issue a trip to any
breaker with the CB Maintenance switch in the Maintenance position (Tripping
disabled by logic)
3.2.4 500kV Line/Unit Maintenance Switches
The Diablo Canyon SPS has been wired to the Line maintenance switches located on the
line control panels. Each maintenance switch provides an input to both System A and
System B. These are two position switches: NORMAL or MAINTENANCE.
The line Maintenance switches are not used within the DCSPS logic. The point is reserved
for future implementation if and when the switch becomes necessary.
3.3 Summary of Switching Procedures
3.3.1 Open a 500kV circuit breaker (No physical work is performed on CB or Circuitry)
There are no special steps that need to be added to the switching sequence if
maintenance personnel will not physically work on the circuit breaker (CB) or the
related circuitry.
The use of the N/M switch is not required when the breaker is simply opened. The
use of the switch should be limited to conditions when maintenance is to be
performed on the breaker.
3.3.2 Open and Clear 500kV Breaker
The Open and Clear procedure is used to remove a circuit breaker from the system
to perform maintenance or testing in a de-energized state. The Diablo Canyon SPS
is designed to accommodate this set-up.
Maintenance activities that directly affect the DCSPS
1. Opening and closing the breaker when the CB disconnects
are opened.
2. Relay Trip checks on any 500kV breaker
Description of Operations
DCSPS Operations Handbook Page 3-17 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
Every CB on a breaker and a half bus configuration is equipped with a
Normal/Maintenance (N/M) switch. The switch is used as an input to RAS/SPS
schemes and indicates breaker abnormal conditions.
Operator Switching Procedure:
1. Evaluate conditions that exist at the time and determine
appropriate action.
2. Open and Clear the CB in accordance with current
standard switching procedures.
3. Place the CB Normal/Maintenance (N/M) switch in the
Maintenance position immediately after the CB has been
opened and prior to opening the Circuit Breaker
Disconnects.
4. On the go-back, after the Circuit Breaker disconnect
switches have been closed and just prior to closing the CB
and releasing it back for normal operations; place the CB
Normal/Maintenance (N/M) switch in the Normal
position.
3.3.2.1 Scheme Logic Actions
▪ The N/M switch inputs to the DCSPS devices do not drive a non-volatile
latch within the relay.
▪ If both breaker Normal/Maintenance switches on a line (or Unit) are placed in
the Maintenance position, and the UNDERCURRENT element within the
relay is activated, (Indicating a low level current), the substation scheme logic
will generate a Line (or Unit) outage.
▪ In the event that both breakers on a line are switched to Maintenance position,
and a current is measured on the equipment (UNDERCURRENT element is
NOT picked-up), the undercurrent disagreement alarm and LED will be
activated.
3.4 Diablo Canyon SPS Status and Alarm Indication
The Diablo SPS System “A” and System “B” give various status and alarm point indications via the
station Annunciator, SCADA RTU, and relay LED faceplates.
Diablo Canyon SPS events (Outages and Tripping) and equipment malfunctions are detected by the
relays within the scheme. The relays continuously monitor the status of the electrical system and the
health of the schemes equipment. Any deviation between the actual status of the monitored points and
the pre-programmed logic expectations will result in the appropriate indication. When abnormalities
are recognized by the Diablo Canyon SPS components, annunciation of the conditions is made in the
form of Annunciator and SCADA RTU alarms. (See Appendix for all alarm points)
3.4.1 Alarm Categories & Conditions
The DCSPS alarms can be placed into three major categories:
1. DCSPS Tripping (Critical)
▪ Unit #1 or Unit #2
2. DCSPS Functional Alarms (Critical)
Description of Operations
DCSPS Operations Handbook Page 3-18 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
▪ System “A” Channel Fail
▪ System “B” Channel Fail
▪ System “A” relay critical failure
▪ System “B” relay critical failure
▪ System “A” maintenance alarm
▪ System “B” maintenance alarm
3. DCSPS System Operation Indications
▪ System Outage (Line and/or Unit)
▪ System Arming (Either System “A” or System “B”)
▪ Unit Selector Switch Position
▪ System “A” Cut-Out
▪ System “B” Cut-Out
3.4.1.1 DCSPS Tripping Alarm
A DCSPS trip will be indicated on the Station Annunciator and via the SCADA
RTU. Four Annunciator windows have been provided that will indicate the
following:
1. System “A” Unit 1 Trip
2. System “A” Unit 2 Trip
3. System “B” Unit 1 Trip
4. System “B” Unit 2 Trip
The particular system condition that resulted in the DCSPS trip will be latched on
the DCSPS “Lines” N60 relay located on Rack #1. (Device number 537DCSPS-A
or 537DCSPS-B). The relay LED section of this document gives a visual
presentation of the LED assignments.
3.4.1.1.1 Response
o Obtain permission from TOC to Cut-Out both DCSPS System – “A” and
DCSPS System “B”. Both schemes must be cut-out prior to closing a
DCSPS tripped 500kV Unit breaker. (DCSPS must be CUT-OUT prior
to closing either 500kV unit breaker after a DCSPS trip event. The
CB may “Trip-Free” otherwise – As an example, the same system
condition that caused the trip may still be present.)
o Record LED faceplate information.
o Wait for System Protection confirmation prior to Resetting the scheme via
the Device 537DCSPS pushbuttons. (This will ensure that all of the
appropriate event data has been collected for post event analysis) (It is
important to Reset BOTH System A and System B even if only one of
the systems has tripped. A DCSPS trip from one system will “Lock-
out” the alternate unit on both systems. Resetting will clear the
lockout condition)
o Close one or both breakers for the tripped unit.
o Cut-In DCSPS after confirmation from TOC and consultation with DCPP
Operations & Engineering. (Note: Do not Cut-In if Unit #1 Trip or Unit
#2 Trip LED’s are lit. i.e. “No Standing Trips”)
Description of Operations
DCSPS Operations Handbook Page 3-19 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
3.4.1.2 DCSPS Functional Alarms
DCSPS will indicate when the scheme has malfunctioned, or has detected an
illogical condition. Functional Alarms will be indicated on the Station Annunciator
and via the SCADA RTU. Alarms in this category require
1. System “A” Channel Failure
Either a relay communication card failure, or a failure in the fiber
optic interconnectivity, has compromised the System “A”
relay grouping communication channel.
2. System “B” Channel Failure
Either a relay communication card failure, or a failure in the fiber
optic interconnectivity, has compromised the System “B”
relay grouping communication channel.
3. System “A” Relay Critical Failure
Any one of the five relays associated with System “A” has failed.
4. System “B” Relay Critical Failure
Any one of the five relays associated with System “B” has failed.
5. System “A” Maintenance Alarm
The relay group has detected a failure or an illogical condition.
The exact condition can be determined by viewing the
N60 relay LED’s.
▪ Circuit Breaker Disagreement
System A and System B disagree on the position of a 500kV
breaker (Example – System “A” indicates CB 532 is
Open and System “B” indicates CB 532 is closed)
▪ Ethernet Failure
Any relay within a group cannot establish communication with the
communication network.
▪ UC and CB disagreement
The relay has detected that both breakers are open for a line or unit
and the Undercurrent element is not asserted. (Example:
The line circuit breakers are open and there is load current
on the line)
▪ VT fuse failure
Indicates that the N60 relays have detected a failure of the a CCVT
phase or related secondary wiring.
6. System “B” Maintenance Alarm
The relay group has detected a failure or an illogical condition.
The exact condition can be determined by viewing the
N60 relay LED’s.
▪ Circuit Breaker Disagreement
Description of Operations
DCSPS Operations Handbook Page 3-20 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
System A and System B disagree on the position of a 500kV
breaker (Example – System “A” indicates CB 532 is
Open and System “B” indicates CB 532 is closed)
▪ Ethernet Failure
Any relay within a group cannot establish communication with the
communication network.
▪ UC and CB disagreement
The relay has detected that both breakers are open for a line or unit
and the Undercurrent element is not asserted. (Example:
The line circuit breakers are open and there is load current
on the line)
▪ VT fuse failure
This target indicates that the N60 relays have detected a failure of
one or more CCVT phases or related secondary wiring.
3.4.1.2.1 Response
o Alarms in this category require immediate attention.
o By viewing relay LED’s and comparing the targets with actual system
conditions, determine which system is has the failure. Immediately Cut-
Out the failed system.
o Notify Maintenance department within a business day.
o Notify System Protection department within a business day.
o Notify DCPP Operations within a business day.
3.4.1.3 DCSPS System Operation Indication
DCSPS operational statuses are indicated via the SCADA RTU. These points are
designed to give a real time view of certain points within the schemes logic.
(Absence of the RTU point will indicate the logical inverse of the point. Example:
the absence of the System A MW arming Level 1 (L1) point will indicate that
System A is Level 1 (L1) is not armed)
1. Diablo – Gates 500kV Line Outage.
Either System “A” or System “B” detection of an “Outage” of this
line will be indicated by this RTU point.
2. Diablo – Midway #2 500kV Line Outage.
Either System “A” or System “B” detection of an “Outage” of this
line will be indicated by this RTU point.
3. Diablo – Midway #3 500kV Line Outage.
Either System “A” or System “B” detection of an “Outage” of this
line will be indicated by this RTU point.
4. Unit #1 Outage.
Either System “A” or System “B” detection of an “Outage” of this
line will be indicated by this RTU point.
5. Unit #2 Outage.
Either System “A” or System “B” detection of an “Outage” of this
line will be indicated by this RTU point.
6. Unit #1 Tripping Preference.
Description of Operations
DCSPS Operations Handbook Page 3-21 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
This point comes from the N60 relays and confirms serves as
confirmation that the System “A” and System “B” relays
sense the position of the units selector switch correctly.
7. Unit #2 Tripping Preference.
This point comes from the N60 relays and confirms serves as
confirmation that the System “A” and System “B” relays
sense the position of the units selector switch correctly.
8. System “A” (1-Line Out) & (U1+U2 MW Net > L1 Setpoint) Armed.
Both conditions must be present to bring in this point at it indicates
that the scheme is armed and will operate for a Line Trip
Condition. (See State Diagram and Setting Point
Appendix for description)
9. System “A” (1-Line Out) & (500kVVolts < Vdlos Setpoint) & (U1+U2 MW
Net > L1 Setpoint) Armed.
All three conditions must be present to bring in this point at it
indicates that the scheme is armed and will operate for a
Line Outage Condition. (See State Diagram and Setting
Point Appendix for description)
10. System “A” (2-Lines Out) & (U1+U2 MW Net > L5 Setpoint) Armed.
Both conditions must be present to bring in this point at it indicates
that the plant is generating over a MW setpoint limit for a
two line outage condition. (See State Diagram and Setting
Point Appendix for description)
11. System “A” SPARE.
Spare Scada point for future implementation.
12. System “A” SPARE.
Spare Scada point for future implementation.
13. System “B” (1-Line Out) & (U1+U2 MW Net > L1 Setpoint) Armed.
Both conditions must be present to bring in this point at it indicates
that the scheme is armed and will operate for a Line Trip
Condition. (See State Diagram and Setting Point
Appendix for description)
14. System “B” (1-Line Out) & (500kVVolts < Vdlos Setpoint) & (U1+U2 MW
Net > L1 Setpoint) Armed.
All three conditions must be present to bring in this point at it
indicates that the scheme is armed and will operate for a
Line Outage Condition. (See State Diagram and Setting
Point Appendix for description)
15. System “B” (2-Lines Out) & (U1+U2 MW Net > L5 Setpoint) Armed.
Both conditions must be present to bring in this point at it indicates
that the plant is generating over a MW setpoint limit for a
two line outage condition. (See State Diagram and Setting
Point Appendix for description)
16. System “B” SPARE.
Spare Scada point for future implementation.
17. System “B” SPARE.
Description of Operations
DCSPS Operations Handbook Page 3-22 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
Spare Scada point for future implementation.
18. System “A” Cut-Out.
This point indicates that the System “A” Cut-Out switch has been
placed in the “Cut-Out” position. System “A” is incapable
of tripping either unit.
19. System “B” Cut-Out.
This point indicates that the System “B” Cut-Out switch has been
placed in the “Cut-Out” position. System “A” is incapable
of tripping either unit.
3.4.1.3.1 Response
o As a general rule, these are DCSPS operational status points that give a
real-time indication of scheme performance. These status points can be
periodically compared to actual system conditions and verified to be
correct. (Example: DCSPS indicates that the Diablo – Gates Line is OUT.
This is condition can be verified to be correct.)
o Note: The Diablo SPS arms on Analog values. It is possible, when the
actual Diablo plant output is bordering a MW arming level, that System-A
and System-B will not arm at the same time. This condition should be
considered normal. (This phenomenon will be noticed when ramping up a
unit after an outage.)
o If the conditions differ from the actual system conditions, observe the
DCSPS LED targets to determine which DCSPS system (“A” or “B”) has
malfunctioned, and CUT-OUT the system. (Example: RTU point
erroneously indicates that the Diablo – Gates Line is Out, verify which
system is bringing in the alarm by viewing the N60 relay LED faceplates.)
o In the event of discrepancies, notify DCPP Operations, T/SM&C
Maintenance, and System Protection department within a business day.
3.4.2 Universal Relay N60 (UR N60) LED’s
As indicated in earlier sections, the N60 relay contains numerous programmable LED’s. These
LED’s enable the programmer to provide very detailed information to operations and maintenance
personnel. In normal operation, it is not necessary to view LED information.
3.4.2.1 Left LED and Pushbutton Panel
The Left LED panel is located on the N60 relay as indicated in Figure 2. This panel
is common to all N60 relays in the Diablo Canyon SPS.
The LED’s on this panel reflect the status of equipment connected to the device and
indicate if there are problems with any of the equipment.
Certain actions such as resetting an alarm or acknowledging an alarm may be
initiated by pressing the blue buttons on the right side of the panel.
Description of Operations
DCSPS Operations Handbook Page 3-23 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
LED PANEL
NOTE: TRIP and ALARM LEDs ARE USER PROGRAMMABLE
IN SERVICE
TRIP
CURRENTTROUBLE
TEST MODE
ALARM
PICKUP
VOLTAGE
FREQUENCY
NEUTRAL / GND
RESET
METER
LED TESTPHASE B
PHASE A
OTHER
STATUS EVENT CAUSE
PHASE C
LEFT LED PANEL EXAMPLE
Figure 2
LED Indicator Label Function
Trip The Trip LED is programmable and lights when the trip bus is energized for any given load block circuit breaker that is connected to the associated N-60
(This LED has NOT been programmed to Illuminate for any )
Alarm The Alarm LED is programmed to illuminate for Relay Problems.
Pushbutton Indicator Label
Function
Relay Reset Only resets the LED’s associated with this panel and clears the relay of any relay malfunction alarm.
(Example: Any relay malfunction or LCD latched target will be cleared by this button. This
Pushbutton does not perform the System Reset.
Meter If the relay does not have a Latched target on the LCD display - Pressing this button will rotate the LCD
through the programmed displays (Example: metering values)
LED Test Performs preprogrammed LED illumination tests
Description of Operations
DCSPS Operations Handbook Page 3-24 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
3.4.2.2 Right LED Panel Section
The Right LCD and pushbutton panel is located on the N60 relay as indicated in
Figure 3. This panel is common to all N60 relays in the Diablo Canyon SPS.
The LCD on this panel reflects the status of each individual relay and at anytime may
have a latched a non-programmable relay target. Information displayed within the
LED will assist in determining the source of any relay malfunction. When alarms
cannot be cleared using the Reset Pushbutton, maintenance personnel are to be
notified.
Once malfunctions have been detected and cleared, pressing the “Reset” pushbutton
will clear the target information.
If no relay target is displayed, the LCD will rotate through pre-programmed status
information. This preprogrammed information will include: Metering status (if
applicable), System and relay device number.
The Pushbuttons located behind the swing panel is used for maintenance personnel
to access the relay information and performed functions that cannot be performed via
computer – relay communications.
N60 RIGHT PANEL EXAMPLE
Figure 3
3.4.2.3 Lines Relay (537DCSPS) Middle LED Panel Sections
The “Lines” relay is the major operator interface for the scheme. Figure 4 illustrates
the programmable LED indications available on both the 537DCSPS-A and the
537DCSPS-B.
Pushbutton Indicator Label
Function
System Reset
(One PB on Sys-A and One PB on
Sys-B)
Operation of this pushbutton will clear the Lockout condition created by a DCSPS trip event. (This One
pushbutton will reset the lockout condition all five relays, as well as clear Latched LED’s on all five
relays.)
LED Number Description
1, 9, 17 Indicates a Line out condition at Diablo Canyon (Both line breakers Open (Or in Maint.) and an Undercurrent
2, 10, 18 Indicates a Line out condition at the remote end of the line (UC condition for a specified Time period)
Description of Operations
DCSPS Operations Handbook Page 3-25 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
LED Number Description
3, 4, 11, 12, 19, 20 Indicates when a breaker is Open or in Maintenance
5, 13, 21 Indicates when a line has been tripped by protection relays(s) or DTT. This LED will remain illuminated for a period of TSIMULTANEOUS. (Time period for transitioning from DCSPS EVE 2 to DCSPS EVE 1)
6, 7, 14, 15, 22, 23 Indicates a disagreement between the system A and system B sensing of the breaker position. (One system senses the breaker open, the other system senses it closed)
8, 16, 24 Indicates a disagreement with the line circuit breakers and the current on the line. (The system senses both breakers are open (or in Maint.), but does not sense an undercurrent condition).
25 The System Tripped due to a Line Trip event followed by another Line Trip that occurred within the TSIMULTANEOUS time period. (DCSPS EVE – 2)
26 Arming indication (One Line is out and the U1 + U2 Export is above the MW L1 Setting)
27 Indicates that the scheme tripped due to a Double Line Outage condition (Part of DCSPS EVE-1)
28 Indicates that the scheme tripped due to a Line Outage followed by a Line Trip condition (Part of DCSPS EVE-1)
29 Indicates that the scheme tripped due to a Line Trip followed by a Line Outage condition that occurred within TSIMULTANEOUS time period (Part
of DCSPS EVE-2)
30 Indicates that the scheme tripped due to a 500kV breaker failure condition (DCSPS EVE-3)
31 Indicates the scheme issued a trip for Unit #1 500kV breakers
32 Indicates the scheme issued a trip for Unit #2 500kV breakers
33, 34, 35, 36, 37, 38, 39, 40
Indicates that the DCSPS has detected that the breaker failure relay has operated. (This LED is latched, even if the scheme did not trip for the BF
condition – Requires a system reset to extinguish the LED)
41 Indicates that the relay cannot receive information via the direct connect fiber from other relays in the system (This is a critical failure and the scheme
should be cut-out)
42 Indicates that the relay cannot receive information over the Ethernet from the alternate system. (Results in the loss of Sys-A and Sys-B comparison
capability as well as remote access)
43 Indicates a Maintenance alarm condition (Many different errors result in a maintenance alarm – See other section within this document)
48 Indicates that the System is Unavailable either because it is cut-out or a relay logic status point has sensed unavailability – example: DD Com
Failure. (This LED will often be illuminated on all five chassis)
Description of Operations
DCSPS Operations Handbook Page 3-26 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
3.4.2.4 Unit1 Tripping Relay (578/586DCSPS-1) Middle LED Panel Sections
The Unit 1 System A and B “Tripping and Lockout” relay LED assignments can be
found in Figure 5.
LED Number Description
1 Indicates that the scheme detects that 2 500kV lines are out and the plant MW next export (U1 + U2) is above L5
7 The DCSPS System detects that the Unit Selector Switch is in the Unit 1 Position.
8 The DCSPS System detects that the Unit Selector Switch is in the Unit 2 Position.
25 Indicates that the System is physically incapable of tripping Unit #1. This lockout condition can be created by a Unit #2 trip from this system, or the alternate system. (This requires a System Reset to clear the lock-out condition)
41 Indicates that the relay cannot receive information via the direct connect fiber from other relays in the system (This is a critical failure and the scheme
should be cut-out)
42 Indicates that the relay cannot receive information over the Ethernet from the alternate system. (Results in the loss of Sys-A and Sys-B comparison
capability as well as remote access)
43 Indicates a Maintenance alarm condition (Many different errors result in a maintenance alarm – See other section within this document)
44 Indicates that the system has detected an error in sensing the position of the unit selector switch (Either senses both U1 and U2, or does not sense either
U1 or U2)
48 Indicates that the System is Unavailable either because it is cut-out or a relay logic status point has sensed unavailability – example: DD Com
Failure. (This LED will often be illuminated on all five chassis)
3.4.2.5 Unit1 Undercurrent and MW Relay (537/511DCSPS-1) Middle LED Panel Sections
The Unit 1 System A and B “Undercurrent and Multifunction (MF)” relay LED
assignments can be found in Figure 6.
LED Number Description
1 Indicates Unit 1 outage condition at Diablo Canyon 500kV (Both 500kV breakers Open (Or in Maint.) and an Undercurrent
2 Indicates a Unit 1 outage condition at the plant. (MW/UC condition for a specified Time period)
3, 4 Indicates when a breaker is Open or in Maintenance
5 Indicates when the voltage from the Unit T-Tap PT’s is below the Vdlos setting AND a 500kV line is out AND the power level is above L1 (All three conditions must be present simultaneously)
6, 7 Indicates a disagreement between the system A and system B sensing of the breaker position. (One system senses the breaker open, the other
Description of Operations
DCSPS Operations Handbook Page 3-27 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
LED Number Description
system senses it closed)
8 Indicates a disagreement with the line circuit breakers and the current on the line. (The system senses both breakers are open (or in Maint.), but does not sense an undercurrent condition).
25 Indicates that the U1+U2 Net MW export is above the L1 Setting
26 Indicates that the U1+U2 Net MW export is above the L2 Setting
27 Indicates that the U1+U2 Net MW export is above the L3 Setting
28 Indicates that the U1+U2 Net MW export is above the L4 Setting
29 Indicates that the U1+U2 Net MW export is above the L5 Setting
41 Indicates that the relay cannot receive information via the direct connect fiber from other relays in the system (This is a critical failure and the scheme
should be cut-out)
42 Indicates that the relay cannot receive information over the Ethernet from the alternate system. (Results in the loss of Sys-A and Sys-B comparison
capability as well as remote access)
43 Indicates a Maintenance alarm condition (Many different errors result in a maintenance alarm – See other section within this document)
48 Indicates that the System is Unavailable either because it is cut-out or a relay logic status point has sensed unavailability – example: DD Com
Failure. (This LED will often be illuminated on all five chassis)
3.4.2.6 Unit2 Tripping Relay (578/586DCSPS-2) Middle LED Panel Sections
The Unit 2 System A and B “Tripping and Lockout” relay LED assignments can be
found in Figure 7.
LED Number Description
25 Indicates that the System is physically incapable of tripping Unit #2. This lockout condition can be created by a Unit #1 trip from this system, or the alternate system. (This requires a System Reset to clear the lock-out condition)
41 Indicates that the relay cannot receive information via the direct connect fiber from other relays in the system (This is a critical failure and the scheme
should be cut-out)
42 Indicates that the relay cannot receive information over the Ethernet from the alternate system. (Results in the loss of Sys-A and Sys-B comparison
capability as well as remote access)
43 Indicates a Maintenance alarm condition (Many different errors result in a maintenance alarm – See other section within this document)
48 Indicates that the System is Unavailable either because it is cut-out or a relay logic status point has sensed unavailability – example: DD Com
Failure. (This LED will often be illuminated on all five chassis)
Description of Operations
DCSPS Operations Handbook Page 3-28 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
3.4.2.7 Unit2 Undercurrent and MW Relay (537/511DCSPS-2) Middle LED Panel Sections
The Unit 2 System A and B “Undercurrent and Multifunction (MF)” relay LED
assignments can be found in Figure 8.
LED Number Description
1 Indicates Unit 2 outage condition at Diablo Canyon 500kV (Both 500kV breakers Open (Or in Maint.) and an Undercurrent
2 Indicates a Unit 2 outage condition at the plant. (MW/UC condition for a specified Time period)
3, 4 Indicates when a breaker is Open or in Maintenance
5 Indicates when the voltage from the Unit T-Tap PT’s is below the Vdlos setting AND a 500kV line is out AND the power level is above L1 (All three conditions must be present simultaneously)
6, 7 Indicates a disagreement between the system A and system B sensing of the breaker position. (One system senses the breaker open, the other system senses it closed)
8 Indicates a disagreement with the line circuit breakers and the current on the line. (The system senses both breakers are open (or in Maint.), but does not sense an undercurrent condition).
41 Indicates that the relay cannot receive information via the direct connect fiber from other relays in the system (This is a critical failure and the scheme
should be cut-out)
42 Indicates that the relay cannot receive information over the Ethernet from the alternate system. (Results in the loss of Sys-A and Sys-B comparison
capability as well as remote access)
43 Indicates a Maintenance alarm condition (Many different errors result in a maintenance alarm – See other section within this document)
48 Indicates that the System is Unavailable either because it is cut-out or a relay logic status point has sensed unavailability – example: DD Com
Failure. (This LED will often be illuminated on all five chassis)
Description of Operations
DCSPS Operations Handbook Page 3-29 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
RESET
LINE OUT AT DC 2-LINES TRIP
LINE OUT / P > L1
2-LINES OUT
LINE OUT / LINE TRIP
System Unavailable
Sys DD Com Fail25
29
32
26
27
28
30
31
33
37
34
35
36
38
39
9
12
17
20
14
16
10
11
13
15
18
19
22
21
23
24
7
2
3
5
4
6
8 40
1
47
42
43
45
44
46
48
41
LINE OUT GATES
DC - GATES DC - MIDWAY #2 DC - MIDWAY #3
622 OPEN / MAINT.
722 OPEN / MAINT.
LINE TRIP ACTIVE
622 SYS A&B DISAG
722 SYS A&B DISAG
CB & UC DISAGREE
Operational Status Operational Status ALARMS
LINE TRIP / LINE OUT
BFT PLANT TRIP
UNIT #1 TRIP
UNIT #2 TRIP
LINE OUT AT DC
LINE OUT MIDWAY
642 OPEN / MAINT.
742 OPEN / MAINT.
LINE TRIP ACTIVE
642 SYS A&B DISAG
742 SYS A&B DISAG
CB & UC DISAGREE
LINE OUT AT DC
LINE OUT MIDWAY
632 OPEN / MAINT.
732 OPEN / MAINT.
LINE TRIP ACTIVE
632 SYS A&B DISAG
732 SYS A&B DISAG
CB & UC DISAGREE
622 BF
722 BF
532 BF
632 BF
732 BF
542 BF
642 BF
742 BF
ETHERNET Fail
MAINTENANCE ALARM
537DCSPS – (A or B) LED’s and Pushbuttons
Rack 1 Rack 2 Rack 3
Sys - A
Sys - B
537DCSPS-A
537DCSPS-B
Sys - A
Sys - B
Lines Rack Unit 1 Rack Unit 2 Rack
Figure 4: DCSPS Lines Relay LED & PB and Rack Location
Description of Operations
DCSPS Operations Handbook Page 3-30 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
25
29
32
26
27
28
30
31
33
37
34
35
36
38
39
9
12
17
20
14
16
10
11
13
15
18
19
22
21
23
24
7
2
3
5
4
6
8 40
1
47
42
43
45
44
46
48
41
U1 SELECT
U2 SELECT
UNIT SELECT ERROR
Operational Status
System Unavailable
Sys DD Com Fail
ETHERNET Fail
MAINTENANCE ALARM
U1 Trip Blocked
ALARMS
A-B DISAGREE
Operational Status
DLO & OVERPOWER
578/586DCSPS – 1(A or B) LED’s and Pushbuttons
Rack 1 Rack 2 Rack 3
Sys - A
Sys - B
Sys - A
Sys - B
578/586DCSPS-A1
578/586DCSPS-B1
Lines Rack Unit 1 Rack Unit 2 Rack
Figure 5: DCSPS Unit 1 Tripping-Lockout Relay LED Assignments and Rack Location
Description of Operations
DCSPS Operations Handbook Page 3-31 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
25
29
32
26
27
28
30
31
33
37
34
35
36
38
39
9
12
17
20
14
16
10
11
13
15
18
19
22
21
23
24
7
2
3
5
4
6
8 40
1
47
42
43
45
44
46
48
41GEN TIE OUT P > L1
GEN OFF LINE
DIABLO UNIT 1
532 OPEN / MAINT.
632 OPEN / MAINT.
532 SYS A&B DISAG
632 SYS A&B DISAG
CB & UC DISAGREE
U1 + U2 MW LEVEL
System Unavailable
Sys DD Com Fail
ETHERNET Fail
MAINTENANCE ALARM
ALARMS
P > L2
P > L3
P > L4
P > L5LO & V<Vdlos & P>L1
537/511DCSPS – 1(A or B) LED’s and Pushbuttons
Rack 1 Rack 2 Rack 3
Sys - A
Sys - B
Sys - A
Sys - B
537/511DCSPS-A1
537/511DCSPS-B1
Lines Rack Unit 1 Rack Unit 2 Rack
Figure 6: DCSPS Unit 1 Undercurrent and Multifunction Relay LED Assignments and Rack Location
Description of Operations
DCSPS Operations Handbook Page 3-32 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
25
29
32
26
27
28
30
31
33
37
34
35
36
38
39
9
12
17
20
14
16
10
11
13
15
18
19
22
21
23
24
7
2
3
5
4
6
8 40
1
47
42
43
45
44
46
48
41
Operational Status
System Unavailable
Sys DD Com Fail
ETHERNET Fail
MAINTENANCE ALARM
U2 Trip Blocked
ALARMS
578/586DCSPS – 2(A or B) LED’s and Pushbuttons
Rack 1 Rack 2 Rack 3
Sys - A
Sys - B
Sys - A
Sys - B
578/586DCSPS-A2
578/586DCSPS-B2
Lines Rack Unit 1 Rack Unit 2 Rack
Figure 7: DCSPS Unit 2 Tripping-Lockout Relay LED Assignments and Rack Location
Description of Operations
DCSPS Operations Handbook Page 3-33 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
25
29
32
26
27
28
30
31
33
37
34
35
36
38
39
9
12
17
20
14
16
10
11
13
15
18
19
22
21
23
24
7
2
3
5
4
6
8 40
1
47
42
43
45
44
46
48
41GEN TIE OUT
GEN OFF LINE
542 OPEN / MAINT.
642 OPEN / MAINT.
LO & V<Vdlos & P>L1
542 SYS A&B DISAG
642 SYS A&B DISAG
CB & UC DISAGREESystem Unavailable
Sys DD Com Fail
ETHERNET Fail
MAINTENANCE ALARM
ALARMSDIABLO UNIT 2
537/511DCSPS – 2(A or B) LED’s and Pushbuttons
Rack 1 Rack 2 Rack 3
Sys - A
Sys - B
Sys - A
Sys - B
537/511DCSPS-A2
537/511DCSPS-B2
Lines Rack Unit 1 Rack Unit 2 Rack
Figure 8: DCSPS Unit 1 Undercurrent and Multifunction Relay LED Assignments and Rack Location
Detailed System Design and Components
DCSPS Operations Handbook Page 4-1 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
4 Detailed System Design and Components
4.1 Scheme Architecture Overview
In order to meet the functional specifications of the Diablo Canyon SPS, five G.E. UR N60 relays are installed
for each system, (System “A” contains five relays and System “B” contains five relays). A total of ten UR
relays are necessary to complete the objectives necessary. This section will describe each relay, the
individual purpose, and the architecture of their connectivity.
Collect real time status and analog information. Examples:
1. Line and Unit Outages
2. Line and Megawatt Telemetry (Analog and Digital representations)
3. System Health Indicators (Discrete components, Load Group data, and
Communication Failures)
4. Circuit Breaker Maintenance Switch positions
5. Line and Unit Maintenance Switch positions (If used)
6. Relay front panel pushbutton status inputs
7. Circuit Breaker Trip wire monitor
8. Breaker Failure Condition monitoring
Perform logic processing. This is logic processing that is performed by all five relays in the system.
Examples:
1. Monitor system operational condition based on position of operator controlled
switches.
2. Determine Outage Status of power system components. (Lines and Transformers)
3. Calculate Individual Unit and Total Export quantities (MW)
Perform Output commands Examples:
1. Trip Unit 1 or Unit 2.
2. Alarm information output (System Tripping, Maintenance Alarm etc.)
4.2 Relay Installation (AC Circuits)
All of the relays associated with this scheme are located in the Diablo Canyon 500kVcontrol building. The
scheme monitors the protection trip and breaker failure trip circuits for the 500kV breakers, Unit 500kV
voltages and currents and 500kV line voltages and currents. It is important to note that only Diablo Canyon
500kV quantities are monitored.
Figure 9 depicts the ten Diablo SPS relays and shows how the relays are wired to Diablo Canyon 500kV
Current Transformer (CT) and Potential Transformer (PT) circuits. The System-A relays are wired in Set-A
protection scheme CT’s. The System-B relays are wired in the Set-B protection scheme CT’s. (Set-A and
Set-B protection scheme components are not explicitly shown in the figure.) The darkened hashed areas
indicate the cabinets in which the relays are physically mounted.
Detailed System Design and Components
DCSPS Operations Handbook Page 4-2 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
MIDWAY
BUS 2
GATES
BUS 1
DIABLO
CANYON
BUS 2
742642
DIABLO - MIDWAY #2 500kV LINE
537DCSPS-B
DIABLO - MIDWAY #3 500kV LINE
537DCSPS-A
GATES - DIABLO CANYON 500kV LINE
732
722622
812 912
802 902
652 552
542
DIABLO
CANYON
BUS 1
DIABLO
CANYON
UNIT 2
632532
DIABLO
CANYON
UNIT 1
SYS - A GE UR-N60: Place in LFDC CURRENT CIRCUIT
SYS - B GE UR-N60: Place in PLS CURRENT CIRCUIT
ZZY Y
ZYX Y
ZYX YX YZ Y
Z YXY
537/511DCSPSA-1537/511DCSPSA-2
537/511DCSPSB-2 537/511DCSPSB-1
578/586DCSPSA-1578/586DCSPSA-2
578/586DCSPSB-1578/586DCSPSB-2
SYS-A
F1: DIABLO-GATES
M1: DIABLO-MID #3
M5: DIABLO-MID #2
SYS-B
F1: DIABLO-MID #2
M1: DIABLO-MID #3
M5: DIABLO-GATES
RELAY CONFIG AS
VIEWED FROM
BEHIND PANEL
UNIT #2 DCSPS RACK 3
RELAY CONFIG AS
VIEWED FROM
BEHIND PANEL
UNIT #1 DCSPS RACK 2
RELAY CONFIG AS
VIEWED FROM
BEHIND PANEL
LINES DCSPS RACK 1
DCPP_DCSPS 12-2005
Dpe4
Figure 9: Basic Single Line Meter and Relay Sketch for DCSPS
Detailed System Design and Components
DCSPS Operations Handbook Page 4-3 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
4.3 Diablo Canyon SPS Logic Overview
Logic programmed into the Diablo Canyon SPS relays enables the detection of specific Diablo
Canyon SPS events and facilitates the execution of appropriate tripping. Due to the complexity of the
scheme, this logic is distributed over several relays in the system, (System-A or System-B as
applicable).
The logic is based on the fact that the system can exist in only one “State” at any point in time.
Changes in the system due to line outages or Unit power output result in a transition to another state.
The following paragraphs summarize the System State Diagrams shown in Figure 10.
4.3.1 System Start Up
▪ On start-up, the system transitions to the “3-Line In” state
▪ If at least one “Line Out” is detected and the plant output power is greater than Level 1
(L1), the system transitions to the “1-Line Out/Armed” state, and a “Line Out/Armed”
LED is lit.
▪ If at least one “Line Out” is detected AND the plant power level is less than Level 1
(L1), the system transitions to the “1-Line Out/Normal” state.
▪ If a “Line Trip” is detected, the system transitions to the “1-Line Trip” state and a
“Trip Active” LED is lit for 10 seconds for the tripped line
4.3.2 One Line Trip State
▪ A LED labeled “Trip Active” for the respective line is lit for 10 seconds
▪ If a second “Line Trip” occurs within 10 seconds of the first trip AND the plant output
power is greater than Level 2 (L2), the “Two Line Trip” event flag is set and the
system transitions to the “Trip Logic” state
▪ If a “Line Out” event occurs and Power is greater than Level 2 (L2), the “Line Trip /
Line Out” event flag is set and the system transitions to the “Trip Logic” state.
▪ If after 10 seconds, neither a Line Trip nor a Line Out occurs, the system transitions to
the “1 Line Out/Armed” state and the corresponding LED is lit
▪ If a Breaker Failure occurs during the Line Trip, AND the plant power level is greater
than Level 3 (L3) AND a “Severe” under voltage (V1 < UVs) has existed for at least
16 ms during the fault AND at the time of the Breaker Failure Trip, the positive
sequence voltage is still less than the Medium UV level (V1 < UVm), then the system
transitions to the “Trip Logic” state.
▪ If a Breaker Failure occurs during the “Line Trip” AND the plant power level is >
Level 4 (L4), AND a “Severe” under voltage (V1 < UVs) did not occur during the
fault AND the positive sequence voltage is still less than the Medium UV level (V1 <
UVm) at the time the BFT is issued, then the “BFT Plant Trip” event flag is set, the
“BFT Plant Trip” LED is lit and the system transitions to the “Trip Logic” state.
▪ If the line that was tripped is successfully reclosed then the system transitions back to
the “3-Lines In” state.
4.3.3 One Line Out Armed State
▪ In the “1-Line Out/Armed” state, a LED labeled “1 Line Out/Armed” is lit. This state
is characterized as having a “Line Out” event AND the power level of the plant is
greater than Level 1 (L1)
Detailed System Design and Components
DCSPS Operations Handbook Page 4-4 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
▪ If a “Line Trip” occurs AND the plant output power is greater than Level 1 (L1) (by
definition of being in this state), the “Line Out/Line Trip” event flag is set, the “Line
Out/Line Trip” LED is lit, and the system transitions to the “Trip Logic” state
▪ If a “Line Out” event occurs AND Power is greater than Level 1 (L1), the “Double
Line Out Trip” event flag is set, the “Double Line Out Trip” LED is lit, and the system
transitions to the “Trip Logic” state
▪ If a Breaker Failure occurs during the “Line Trip”, AND the plant power level is
greater than Level 3 (L3), AND a “Severe” under voltage (V1 < UVs) has existed for
at least 16 ms during the fault AND at the time of the Breaker Failure Trip, the
positive sequence voltage is still less than .60 pu (V1 < .60 pu), then the system
transitions to the “Trip Logic” state
▪ If a Breaker Failure occurs during the “Line Trip”, AND the plant power level is
greater than Level 4 (L4) AND a “Severe” under voltage (V1 < UVs) did not occur
during the fault AND the positive sequence voltage is still less than .60 pu (V1 <
UVm) at the time the BFT is issued , then the “BFT Plant Trip” event flag is set, the
“BFT Plant Trip” LED is lit and the system transitions to the “Trip Logic” state
▪ If the line that was out is successfully reclosed, then the system transitions back to the
“3-Lines In” state.
▪ If the plant power level drops below Level 1 (L1), the system transitions to the “1-Line
Out/Normal” state and the “1-Line Out/Armed” LED is extinguished.
4.3.4 One Line Out/Normal State
▪ The 1-Line Out/Normal state is characterized as having an outage on one line AND the
power level of the plant is less than Level 1 (L1).
▪ If the line that was out is successfully reclosed, then the system transitions to the “3-
Lines In” state.
▪ If the plant power level increases above Level 1 (L1), the system transitions to the “1-
Line Out/Armed” state and the “1-Line Out/Armed” LED is lit and the “1-Line
Out/Armed” event message is issued.
▪ If a second line outage occurs and the system power level is less than Level 1 (L1),
then the system transitions to the “System Inactive” state.
4.3.5 Trip Logic State
▪ The “Trip Logic” state is characterized by the fact that the DCSPS has determined that
a Unit Trip is needed and subsequently determines which unit to trip based on the
substation configuration. The Trip Determination is based on the logic diagrams
shown in the figures labeled “Category 1 and 2” and “Category 3”. These figures are
located in the “Unit Tripping Determination” appendix.
▪ If the Unit selected to be tripped by System A is the same as the Unit selected to be
tripped by System B, then the System transitions to the “Execute Trip” state.
▪ If the Unit selected to be tripped by System A is not the same as the Unit selected to be
tripped by System B, then the DCSPS locks out the trip path to both units and
transitions to the “System Locked Out” state.
▪ If one system (A or B) determines that a Unit X (X= 1 or 2) trip is required and the
other system issues no trip decision within 16ms, the active system transitions to the
“Execute Trip” state and trips the selected Unit.
Detailed System Design and Components
DCSPS Operations Handbook Page 4-5 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
▪ If one system (A or B) determines that a Unit X (X= 1 or 2) trip is required and the
other system has a “critical alarm” or the communication system has failed, the active
system immediately transitions to the “Execute Trip” state and trips the selected Unit.
4.3.6 Execute Trip State
▪ The Execute Trip state is characterized by the fact that a Unit X (X = 1 or 2) trip has
been issued. If a Unit 1 Trip determination is made then the Trip output to Unit 2 is
“Locked Out” through a non-volatile latch. An LED is lit indicating which unit trip
was issued (Unit 1 or Unit 2). Similar logic applies if a Unit 2 Trip determination is
made, and the trip to Unit 1 is locked out. Lockout-Trip coordination is established by
the proper use of logic and timers. (Lockout alternate unit prior to tripping desired
unit)
4.3.7 System Locked Out State
▪ The “System Locked Out” state is characterized by the fact that a Unit trip has been
issued and the trips to the other unit are “Locked Out”. The logic paths involved in the
trip decision are “sealed in” and no further action by the system is possible.
▪ If the “Reset Pushbutton” is pressed, the “latched” conditions are reset and the scheme
transitions to the appropriate state based on the configuration of the system. Note:
The Reset Pushbutton on both systems must be pressed on both System “A” and
System “B” before the tripped unit is brought back on-line.
▪ Following the Description of Operations section “DCSPS Tripping Alarm” response
procedures, in the order presented, will ensure no standing trip on the unit breakers.
4.3.8 System Inactive State
▪ The “System Inactive” state is characterized by the fact that a double-line outage exists
and a plant trip was not issued by the DCSPS system.
▪ If the plant output power is greater than Level 5 (L5), then the system transitions to the
Plant Over-Power State
▪ If a line is successfully reclosed, then the system transitions to the “1-Line Out” state
4.3.9 Plant Over Power State
▪ The “Plant Over-Power” state is characterized by the fact that two lines are out and
that the plant output power is greater than Level 5 (L5). An Alarm Contact is set and
an LED is lit
▪ If the Plant Output Power drops below Level 5 (L5), then the system transitions to the
“System Inactive” state and the output contact is opened and the LED is extinguished
▪ If a line successfully recloses, and the power is less than Level 1 (L1), the system
transitions to the “1-Line Out Normal” state and the Plant Over-Power alarm contact is
reset and the alarm LED is extinguished.
▪ If a line is successfully reclosed and the plant output power is greater than Level 1
(L1), then the system transitions to the “1-Line Out Armed” state.
Detailed System Design and Components
DCSPS Operations Handbook Page 4-6 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
System State Transition Diagram
Start
U1 Trip
U2 Trip
System
Locked Out
System
Inactive
• 2 lines out &
P>L5
3-Lines In
1-Line Trip1-Line Out-
Armed
• 1 line or element
TRIP & P>L2
• 1 line OUT & P>L1
• 1 line TRIP & P<L2
1-Line Out
Normal• 1 line OUT
& P<L1
• Time Out & 1 line
OUT
Trip
Logic
• 2nd Line TRIP &
P>L1
• 2nd Line TRIP
& P>L2
•BFT
& P>L3 & UVs or
•P>L4 & UVm
Execute
Trip
•Sys A = Sys B
Sys A-B
Mismatch
•Sys A Sys B
•Other Sys Error
•Other Sys = NO TRIP
•1 Line Reclose
•BFT & P< L3 or no UV
•2nd Line Trip/Out & P<L2
•2 Lines
OUT
•System Reset (PB)
•2 Lines
OUT
•1 Line out
& P>L1
•2nd Line Outage
•2nd line Trip
• Reclose
Legend:
P = Total Plant Output Power in MW
BFT = Breaker Failure Trip
L1 = Arming Level in MW for Line Out/Line Trip
L2 = Arming Level in MW for Line Trip/Line Trip or Out
L3 = Arming Level in MW for a BFT with a Severe UV
L4 = Arming Level in MW for a BFT with a Medium UV
L5 = Alarm level in MW for Plant Over Power alarm
UVs = Severe UV
UVm = Med. UV
PB = Pushbutton
LED N Lit
Vdlos = V1 sup. for
double line out
•Unit Tripped
•BFT
& P>L3 & UVs
or P>L4 &
UVm
•Line Out &
P>L2
2nd Line Out
& P>L1
& V<Vdlos
Plant
Over-Power
•P<L5
•Same state as above
31
32
30
2526
• Reclose 1
line &
P<L1
29
28
27
N
•Reclose 2
lines
Figure 10: DCSPS State Diagram
Detailed System Design and Components
DCSPS Operations Handbook Page 4-7 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
4.4 Communication Infrastructure
All equipment associated with this scheme is located in the Diablo Canyon 500kV control building.
The Diablo Canyon SPS telecommunication infrastructure can be broken down into two distinct
subgroups:
1. High Speed Relay-To-Relay communication, which enables the transmittal of analog
and digitally encoded data between the relays associated with the Diablo Canyon SPS.
2. Ethernet Communication allows passing status information between System A and
System B for alarm purposes and permits connection to the secure communication
network for remote access for downloading Oscillography and Event Status.
4.4.1 High Speed Relay-to-Relay Communications
DCSPS System-A is comprised of a group of five relays connected via a dual channel fiber loop
(Figure 11). This connection allows data and logic states to be passed directly between relays in the
group for high-speed processing. Relays configured in this manner effectively operate as ONE
functional device. If any of the relays fails, the functional integrity of the group is compromised, the
system will be taken out of service and an alarm will be issued.
DCSPS System-B is comprised of a similar group of five relays connected via a separate dual channel
fiber loop. System A and System B SPS relays operate independently and are NOT interconnected
via fiber for peer-to-peer data exchange.
Integrity of the fiber communications is critical to the functional dependability of the scheme.
Therefore, redundant fiber paths have been designed into the scheme.
The direct relay communications makes use of a 32 bit cyclic redundancy code, (CRC), for high
reliability.
4.4.1.1 Loss of Channel Logic
Loss of channel logic occurs when the high-speed relay communication interface
fails. For a signal to be recognized as reliable, it must transmit without interruption
for at least 250 milliseconds.
Detailed System Design and Components
DCSPS Operations Handbook Page 4-8 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
RX
TX
W7IC
1
TX
RX
C
2
RX
TX
W7IC
1
RX
TX
C
2
RX
TX
W7IC
1
RX
TX
C
2
RX
TX
W7IC
1
RX
TX
C
2
REDUNDANT
FIBER RING (TX &
RX 64 Bit)
RELAY TO RELAY
COM
REDUNDANT
FIBER RING (TX &
RX 64 Bit)
RELAY TO RELAY
COM
SYS - A
SYS - B
DCPP_DCSPS 12-2005
Dpe4
RX
TX
W7IC
1
TX
RX
C
2
RELAY CONFIG AS
VIEWED FROM
BEHIND PANEL
UNIT #2 DCSPS RACK 3RELAY CONFIG AS
VIEWED FROM
BEHIND PANEL
UNIT #1 DCSPS RACK 2
RELAY CONFIG AS
VIEWED FROM
BEHIND PANEL
LINES DCSPS RACK 1
RX
TX
W7IC
1
TX
RX
C
2
RX
TX
W7IC
1
RX
TX
C
2
RX
TX
W7IC
1
RX
TX
C
2
RX
TX
W7IC
1
RX
TX
C
2
RX
TX
W7IC
1
TX
RX
C
2
578/586DCSPSA-1
DD 3
578/586DCSPSA-2
DD 4
537/511DCSPSA-1
DD 1
537/511DCSPSA-2
DD 2
537DCSPS-A
DD 5
578/586DCSPSB-1
DD 3
578/586DCSPSB-2
DD 4
537/511DCSPSB-1
DD 1
537/511DCSPSB-2
DD 2
537DCSPS-B
DD 5
Figure 11: Fiber Optic Connections for Diablo SPS – System A and System B
Detailed System Design and Components
DCSPS Operations Handbook Page 4-9 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
4.4.2 Ethernet Relay-to-Relay communication and Remote Access
Ethernet communication is not critical to the Normal operation of the scheme; however it provides an
opportunity for continuously monitoring the health of System A and B. Without the Ethernet
communications, continuous comparison of System-A and System-B quantities will not take place.
(System-A and System-B quantities will be identical during normal operations.)
The Relays are connected to the Operational Data Network (ODN) and allow remote monitoring and
event file download by System Protection personnel (Identical to Path 15 RAS, Path 26 RAS, and
Metcalf SPS, SFRAS, etc.).
The relay Ethernet communications makes use of a 32 bit cyclic redundancy code, (CRC), for high
reliability.
A diagram of the scheme is shown in Figure 12.
Detailed System Design and Components
DCSPS Operations Handbook Page 4-10 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
ODN Network
578/586DCSPSA-1
578/586DCSPSA-2
537/511DCSPSA-1
537/511DCSPSA-2
537DCSPS-A
578/586DCSPSB-1
578/586DCSPSB-2
537/511DCSPSB-1
537/511DCSPSB-2
537DCSPS-B
1 2 3 4 5 6
7 8 9101112
AB
12x
6x
8x
2x
9x
3x
10x
4x
11x
5x
7x
1x
Eth
ern
et
A
12x
6x
8x
2x
9x
3x
10x
4x
11x
5x
7x
1x
C
Ethernet Switch
IRIG-B TIME
SOURCE
Compare
Sys-A and
Sys-B
SYS - A
SYS - B
Remote
Monitor and
Coms
Remote
Monitor and
Coms
IRIG
IRIG
IRIGIRIG
IRIG
IRIG
IRIGIRIG
IRIG
IRIG
Remote
Monitor and
Coms
Compare
Sys-A and
Sys-B
Compare
Sys-A and
Sys-B
Compare
Sys-A and
Sys-B
Compare
Sys-A and
Sys-B
Firewall
Computer
DCPP_DCSPS 10-2005
Dpe4
Firewall
1 2 3 4 5 6
7 8 9101112
AB
12x
6x
8x
2x
9x
3x
10x
4x
11x
5x
7x
1x
Eth
ern
et
A
12x
6x
8x
2x
9x
3x
10x
4x
11x
5x
7x
1x
C
Ethernet Switch
Note:Each relay will have
a separate LAN
connection into the switchFirewall
Figure 12: Diablo SPS Relay Ethernet Connections
Detailed System Design and Components
DCSPS Operations Handbook Page 4-11 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
4.5 Relay Functions
Although all five relays function together, and all are essential for proper scheme operation; each relay
within the relay group performs a specific function. The table below provides a brief description:
UR N60 Chassis Functions (System A or B)
578/586DCSPS-1 Trip Outputs and Non-Volatile Latching supervision contacts (Lockout) for Unit #1 500kV CB 532 and CB 632. Houses the majority of the
tripping and voting-comparison logic.
578/586DCSPS-2 Trip Outputs and Non-Volatile Latching supervision contacts (Lockout) for Unit #2 500kV CB 542 and CB 642
537/511DCSPS-1 CT and PT inputs for Unit #1 and CB breaker status monitoring for CB 532 and CB 632
537/511DCSPS-2 CT and PT inputs for Unit #2 and CB breaker status monitoring for CB 542 and CB 642
537DCSPS CT and PT inputs for the Diablo – Gates 500kV line, Diablo – Midway #3 500kV Line, and Diablo – Midway #2 500kV Line. Calculates the MW unit output for monitor display purposes. Monitors the status of 500kV
CB 622, CB 722, CB 732, and CB 742
4.6 Trip Detection and Breaker Failure Recognition
Protection tripping for circuit breakers is taken from the Breaker Failure Initiate (BFI) circuit for each
circuit breaker (see Figure 13).
A line is determined to be tripped by protection if either of the following occurs:
1. One line breaker is open or on maintenance AND the other breaker is tripped
three-pole by protective relays
2. Both breakers are tripped three-pole by protective relays
The figure also illustrates how the DCSPS is wired within each breaker failure circuit to detect when a
breaker has failed. (The figure depicts one of the eight breakers)
Detailed System Design and Components
DCSPS Operations Handbook Page 4-12 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
BF
(A)
BF
(B)
BF
(C)
DSPS
SYS A
DSPS
SYS B
BF DC (-)
BF DC (+)
Protection Relay
Breaker Fail init
DCSPS BFI
UNIT CB’s
CB
BREAKER
FAIL RELAY
TIMER
TD-5
BREAKER
FAIL RELAY
TIMER
AR TRIPPING
RELAYS
DSPS
SYS A
DSPS
SYS B
TCO
RCO
DCPP_DCSPS 10-2005
Dpe4
Figure 13: SPS Protection Trip Detection
Detailed System Design and Components
DCSPS Operations Handbook Page 4-13 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
4.7 Breaker Failure Functional Overview
As discussed in previous sections, the breaker failure logic is separated into two distinct categories and
is a function of the following:
1. Plant MW Export Level
2. 500kV Positive sequence voltage during the fault (Indicates fault severity)
3. 500kV Positive sequence voltage at the breaker failure time.
Figure 14 illustrates the voltage level and timing of the two categories
• Voltage Restrained Breaker Failure Trip
– V1 < UVs pu & V1< UVm & P>L4 (SEVERE FAULT)
– V1 > UVs & V1< UVm & P>L3 (MEDIUM SEVERITY FAULT)
V1< UVm
V1< UVs
“Severe” Under-Voltage profile “Medium” Under-Voltage profile
t=0 t~8c t=0 t~8c
Figure 14: Breaker Failure Timing
DCSPS Operations Handbook Page 5-1 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
5 Testing Requirements and Procedures
Diablo Canyon Special Protection Scheme testing is necessary to ensure the following:
▪ Verify that the SPS relays and logic correctly translate in Status Inputs to the Scheme. (Breaker
position, Protection Relay Trips, Breaker Failure Relay Trips, Operator Inputs)
▪ Verify that the SPS logic correctly operates (Outputs information) based on translations of various status
input combinations.
▪ Verify that the SPS relays accurately read AC quantities, (Current and Voltage), and calculate analog
quantities correctly (MW and Positive Sequence Voltage).
▪ Verify that the scheme operates within the Speed requirements.
Specific testing procedures for the Diablo Canyon SPS are provided within a separate document;
“DIABLO CANYON SPS TESTING - Version XX”. The testing document is located on the System
Protection Share drive: "ETM on 'Oakland03'" under the "RAS - SPS Info/DCSPS" folder. Contact
System Protection to obtain the latest version of the document.
System tests will be conducted at a minimum of once every four years. Alterations to the scheme,
(Logic or Hardwire), will require testing to verify that the changes meet expectations. The SPS
alteration will be evaluated to determine if a “Full” test or a “Subset” test is necessary for
verification.
The normal test cycle will be scheduled during the unit outage cycle when it is not necessary for the
scheme to be in service.
5.1 Maintenance Requirements and Procedures
Major construction changes (Addition of a CB to the scheme) will require performing portions of the
Diablo Canyon SPS testing document.
CT ratio changes on the breakers associated with the Diablo Canyon SPS scheme require setting
changes within the appropriate N60 for accurate MW calculations and Outage undercurrent elements.
Load checks should be performed to validate settings.
5.2 DCSPS Testing Matrix
The testing matrix in this section should be used as a template for testing the DCSPS logic. The matrix
provides the expected results, along with a “Test” column for the actual scheme response. (Example:
“SYS AB OK”)
The voltage and current connections necessary to set-up the scheme for arming should only be
connected to the DCSPS Unit relay (537) on the unit that is out during the main bank outage. Provided
that the other unit is on-line, it will provide the necessary base-line MW for arming.
Testing Requirements and Procedures
DCSPS Operations Handbook Page 5-1 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
EVE Scenario ARM LEVELS G→MW2 Test MW2→G Test G→MW3 Test MW3→G Test MW2→MW3 Test MW3→MW2 Test
UNIT SEL SW
1
LLO → TRIP
L3<MW<L1 No Trip No Trip No Trip No Trip No Trip No Trip
L1<MW U2 TRIP U2 TRIP U1 TRIP U1 TRIP
U1 TRIP U1 TRIP Unit 1 Selected
U2 TRIP U2 TRIP Unit 2 Selected
ROD → TRIP
L3<MW<L1 No Trip No Trip No Trip No Trip No Trip No Trip
L1<MW U2 TRIP U2 TRIP U1 TRIP U1 TRIP
U1 TRIP U1 TRIP Unit 1 Selected
U2 TRIP U2 TRIP Unit 2 Selected
LLO → LLO
MW<L1 & V1<Vdlos No Trip No Trip No Trip No Trip No Trip No Trip
MW>L1 & V1>Vdlos No Trip No Trip No Trip No Trip No Trip No Trip
L1<MW & V1<Vdlos U2 TRIP U2 TRIP U1 TRIP U1 TRIP
U1 TRIP U1 TRIP Unit 1 Selected
U2 TRIP U2 TRIP Unit 2 Selected
LLO → ROD
MW<L1 & V1<Vdlos No Trip No Trip No Trip No Trip No Trip No Trip
MW>L1 & V1>Vdlos No Trip No Trip No Trip No Trip No Trip No Trip
L1<MW & V1<Vdlos U2 TRIP U2 TRIP U1 TRIP U1 TRIP
U1 TRIP U1 TRIP Unit 1 Selected
U2 TRIP U2 TRIP Unit 2 Selected
ROD → LLO
MW<L1 & V1<Vdlos No Trip No Trip No Trip No Trip No Trip No Trip
MW>L1 & V1>Vdlos No Trip No Trip No Trip No Trip No Trip No Trip
L1<MW & V1<Vdlos U2 TRIP U2 TRIP U1 TRIP U1 TRIP
U1 TRIP U1 TRIP Unit 1 Selected
U2 TRIP U2 TRIP Unit 2 Selected
ROD → ROD
MW<L1 & V1<Vdlos No Trip No Trip No Trip No Trip No Trip No Trip
MW>L1 & V1>Vdlos No Trip No Trip No Trip No Trip No Trip No Trip
L1<MW & V1<Vdlos U2 TRIP U2 TRIP U1 TRIP U1 TRIP
U1 TRIP U1 TRIP Unit 1 Selected
U2 TRIP U2 TRIP Unit 2 Selected
2 TRIP → TRIP Within 10 sec
MW<L3 No Trip No Trip No Trip No Trip No Trip No Trip
L3<MW<L2 No Trip No Trip No Trip No Trip No Trip No Trip
L2<MW U2 TRIP U2 TRIP U1 TRIP U1 TRIP U1 TRIP U1 TRIP Unit 1 Selected
Testing Requirements and Procedures
DCSPS Operations Handbook Page 5-2 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
EVE Scenario ARM LEVELS G→MW2 Test MW2→G Test G→MW3 Test MW3→G Test MW2→MW3 Test MW3→MW2 Test
UNIT SEL SW
U2 TRIP U2 TRIP Unit 2 Selected
TRIP → LLO Within 10 sec
L3<MW<L2 No Trip No Trip No Trip No Trip No Trip No Trip
L2<MW U2 TRIP U2 TRIP U1 TRIP U1 TRIP
U1 TRIP U1 TRIP Unit 1 Selected
U2 TRIP U2 TRIP Unit 2 Selected
TRIP → ROD Within 10 Sec
L3<MW<L2 No Trip No Trip No Trip No Trip No Trip No Trip
L2<MW U2 TRIP U2 TRIP U1 TRIP U1 TRIP
U1 TRIP U1 TRIP Unit 1 Selected
U2 TRIP U2 TRIP Unit 2 Selected
742 BF Test 732 BF Test 622 BF Test 722 BF Test
3 L3<MW V1<Uvs
U2 TRIP N/A N/A U1 TRIP U1 TRIP Unit 1 Selected
N/A N/A U1 TRIP U2 TRIP U2 TRIP Unit 2 Selected
N/A N/A N/A N/A N/A N/A U1 TRIP Unit 1 Selected 632 OPEN
N/A N/A N/A N/A N/A N/A U2 TRIP Unit 2 Selected 642 OPEN
Ensured for Each BF test that without the Voltage collapse and Power greater than L3, NO TRIP
Ensured for Each BF test that with the Voltage collapse and Power less than L3, NO TRIP
Design Adequacy (Ref DCPP EDDG-006 Attachment 8.1)
DCSPS Operations Handbook Page 6-1 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
6 Design Adequacy (Ref DCPP EDDG-006 Attachment 8.1)
This section will address those particular design details expressly requested by the Diablo Canyon PP.
The “Electrical Design Desk Guide” EDDG-006 Attachment 8.1 will be used as a reference document.
The following sections will refer to the concept of reliability. Reliability is a measure of a schemes
performance. Reliability is comprised of both Dependability and Security.
1. Security is the measure of a schemes ability not to operate, (Trip), for unexpected conditions.
2. Dependability is the measure of a schemes ability to operate, (Trip), for expected conditions.
6.1 Power Supply (Station Battery and Charger)
6.1.1 Redundancy and Availability
The UR relays for this scheme are powered by the 125VDC station battery. This battery is the source
for all 500kV microprocessor based relays and accessories located in the Diablo Canyon 500kV
control building. There is only one battery system and associated charger.
Diablo Canyon SPS is composed of two separate distinct Systems – System A and System B. The
systems are identical and can be thought of as operating in parallel. Any failure of one system, (or
component therein), will not adversely affect the reliability of the other.
Each system’s relays are sourced from an independent DC Circuit breaker. If an abnormal DC circuit
condition should cause the DC breaker to trip, the alternate system will continue to be operational.
• System A relays (Qty: 5) receive 125VDC from CB 39
• System B relays (Qty: 5) receive 125VDC from CB 40
The 125VDC Station Battery at the 500kV Switchyard of Diablo Canyon Power Plant is rated at 1010
Ampere Hours. The station has redundant battery chargers each rated at 200 Amps DC. The output
of the battery chargers are connected in parallel, but only one is charging at a given time.
The chargers are fed on separate branch circuit breakers on 480 VAC Distribution Panel No.2. This
panel is supplied by two 4.16kV/480 Transformers which are designated as normal and alternate
sources for Panel No. 2. Please refer to Single Line Diagram of DC Panels (Dwg. 440004, Rev. 17)
and Single Line Diagram of AC Station Service (Dwg. 440003, Rev. 11).
6.1.2 Capacity and Capability
The addition of the relays associated with DCSPS adds burden to the existing battery source. Ten
(10) UR N60 Relays are installed for the DCSPS.
The manufacturer product description specifies the following:
• Power Consumption (per relay): Typical = 35 VA; Max. = 75 VA
• Calculation Total for (10 relays): Typical = 350 VA; Max. = 750 VA
Test Observation: Prior to connection of the DCSPS relays, the continuous 125V
DC load was measured at 13 Amps. The addition of the ten (10) DCSPS relays
increased the continuous load to 15 Amps.
During a quiescent state, the relays LED’s and output contacts are in the normal de-
energized state. The current measured by the aggregate group of ten relays during
the quiescent state was 2 Amps.
Design Adequacy (Ref DCPP EDDG-006 Attachment 8.1)
DCSPS Operations Handbook Page 6-2 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
6.1.3 Worst Case Power Supply Conditions
The battery is expected to continue sourcing all protection related equipment, including circuit
breakers, for a period of Eight hours in the event of a loss of AC power.
Substation Engineering performed a battery size calculation that considered the newly connected
continuous load. The calculations show that the station requires 495 Ampere Hours capacity battery.
This is less than half the ampere hour rating of the existing station battery.
6.2 Raceway System Design
6.2.1 Physical Separation
The UR relays instrumentation (AC Current Source, AC Voltage Source, and Status) are routed in the
existing 500kV Basement tray system. The tray system is used by all existing 500kV protection
schemes. No special accommodations were made to design a separate tray or routing system for the
DCSPS.
PG&E substation design requirements prohibit routing the instrumentation wires with power cables
(480 Volts). All standard PG&E substation design standard practices were followed for the design
and construction of the Diablo Canyon SPS.
6.3 Scheme Design
6.3.1 Redundancy
Various conditions will directly affect the reliability of the DCSPS:
• Failures in any DCSPS component(s).
• Failure of DCSPS wiring (AC and DC).
Diablo Canyon SPS is composed of two separate distinct Systems – System A and System B. The
systems are identical and can be thought of as operating in parallel. A failure of one system, (or
component therein), will not adversely affect the reliability of the other.
The exceptions to the statement above are the following:
6.3.2 Single Point or Common Mode Failures (Failure Mode Analysis)
Single point failures, for the purposes of this document, are defined as the “Failure of any single
module or subsystem that affects the DCSPS reliability”
• Circuit Breaker Maintenance Switch
Only one circuit breaker Maintenance switch is provided for each breaker.
(Currently all Diablo Canyon 500kV breaker Maintenance switches – with the
exception of CB 532 and CB 542, are used in the 500kV RAS).
The correct position of this switch is critical for the correct operation of the DCSPS
scheme, as well as the 500kV RAS.
There are two contacts from the switch provided for the DCSPS. One contact from
the switch is connected to System-A, the other to System-B.
There are no provisions, other than operator vigilance, for detecting or verifying the
correct position of a CB Maintenance switch. Currently the Maintenance switch
status is not monitored by SCADA. If and when the station becomes unattended,
consideration will be given to providing Maintenance switch status to SCADA.
Design Adequacy (Ref DCPP EDDG-006 Attachment 8.1)
DCSPS Operations Handbook Page 6-3 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
6.3.2.1 Circuit Breaker Maintenance Switch erroneously in the Maintenance Position
If the circuit breaker is Normal, (Closed and carrying load), A CB Maintenance
switch left in the Maintenance position will adversely affect the Schemes
Dependability or Security depending on the DCSPS Event.
The scheme will recognize the following:
▪ Determine that the Breaker is Open
▪ Ignore any Protection relay trips for the Breaker
▪ Ignore any Breaker Failure Conditions
▪ The scheme will not Trip a breaker in Maintenance. (Logic prohibits trip)
Impact on Dependability:
▪ The schemes ability to monitor the breaker positions is paramount. The maintenance
switch left in the Maintenance position will be interpreted as an OPEN CB by the
scheme.
DCSPS Event-1 and DCSPS Event-2 will not be Dependable.
▪ Any protective relay trip or Breaker failure trip sensed by the DCSPS will be ignored
for a breaker in the Maintenance, (or sensed in the Open) position. If a line trips, and
one of the CB’s for the line is in the maintenance position, the DCSPS will ignore any
Breaker Failure condition that may occur.
DCSPS Event-3 will not be Dependable.
▪ The schemes ability to trip a Unit breaker is critical to ALL Event Categories.
DCSPS Event-1, 2, and 3 will not be Dependable and may cause additional problems
if only one Unit Breaker is tripped.
Impact on Security:
▪ Initial reviews do not reveal any impact on the schemes security.
6.3.2.2 Circuit Breaker Maintenance Switch erroneously in the Normal Position
If the circuit breaker is abnormal, (Open and Cleared), A CB Maintenance switch
left in the Normal position will adversely affect the Schemes Dependability or
Security depending on the DCSPS Event.
The scheme will recognize the following:
▪ The maintenance switch left in the Normal position will be interpreted as OPEN or
CLOSED depending on the actual position of the breaker. (When a CB is Open and
Cleared, the scheme may erroneously recognize a CLOSED normal breaker).
▪ Recognize all Protection relay trips for the Breaker
▪ Recognize Breaker Failure Conditions
▪ The scheme will attempt to Trip the breaker.
Impact on Dependability:
▪ The schemes ability to monitor the breaker positions for 500kV bus configuration is
paramount.
Design Adequacy (Ref DCPP EDDG-006 Attachment 8.1)
DCSPS Operations Handbook Page 6-4 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
DCSPS Event-1, 2, and 3 will not be Dependable. (Inability to accurately recognize a
Line Outage and the actual operating configuration of the Diablo 500kV Bus)
▪ The schemes ability to trip a Unit breaker is critical to ALL Event Categories.
The Diablo SPS May attempt to trip a breaker that is Open and Cleared. This may be
a safety issue if the Test switches from the scheme have not been isolated.
▪ Impacts the schemes ability recognize a trip of the breaker from a protection relay.
The test switches from the breaker may have been isolated by the Maintenance group.
The closed breaker will not be tripped, and the Diablo SPS will not recognize a
Sudden Line Trip. DCSPS Event-1, 2, and 3 will not be Dependable.
Impact on Security:
▪ The schemes ability to monitor the breaker positions for 500kV bus configuration is
paramount. The maintenance switch left in the Normal position will be interpreted as
OPEN or CLOSED depending on the actual position of the breaker. (When a CB is
Open and Cleared, the scheme may erroneously recognize a CLOSED normal
breaker).
Any trip Tests from protection relays completed on a CB in Maintenance will be
interpreted as a CB trip condition. This may cause a DCSPS initiated trip.
6.3.2.3 Circuit Breaker Breaker Failure Relay
As a standard design, the CB’s only have one breaker failure relay. If the breaker
failure relay is OUT for maintenance or defective, the scheme will be impacted.
To overcome this issue, the Circuit breaker with a defective breaker failure relay
must be open and cleared, and the CB Maintenance switch MUST be placed in the
Maintenance position
The scheme is impacted in the following way:
▪ Scheme may not be able to recognize Protection Trips for the CB.
▪ Scheme may not be able to recognize CB Breaker Failure Conditions.
Impact on Dependability:
▪ DCSPS Event-1, 2, and 3 will not be Dependable
Impact on Security:
▪ Initial reviews do not reveal any impact on the schemes security.
6.3.3 Security Enhancements
The following is a listing of those design and logic decisions that result in security enhancements:
6.3.3.1 DCSPS Limited Scenario Tripping
• DC SPS will trip for the events programmed, (DCSPS Event Category 1, 2,
and 3), only if the initiating event did not result in a Unit separation. For
many events, a unit separation will occur as a result of the initiating event and
the initial 500kV breaker positions. Although there are many, two examples
Design Adequacy (Ref DCPP EDDG-006 Attachment 8.1)
DCSPS Operations Handbook Page 6-5 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
will be given where it would initially appear that the DCSPS should operate,
but will be restrained from tripping:
1. A CB 632 breaker failure will result in the separation of
Unit 1. The unit separation is a function of the event.
2. Initial condition: 542 Open. The loss of the Diablo –
Midway #2 and Diablo – Gates line will result in the
separation of Unit #2. The unit separation is a function of
the initial condition of the 500kV breakers and the
initiating event.
6.3.3.2 Physical Lockout
The physical lockout feature, (physical as opposed to a software lockout), provides
a level of comfort in limiting the ability of the DCSPS trip of both units.
• If DCSPS issues a unit trip, the alternate unit tripping circuit will be
physically interrupted by latching contacts.
• The System A latching contacts for the non-tripping unit will open either by a
System A trip OR a System B trip.
• The System B latching contacts for the non-tripping unit will open either by a
System B trip OR a System A trip.
• The latching contacts will remain open until the RESET pushbutton is
depressed. (System A latching contacts will close only when the System A
reset pushbutton is pressed. System B latching contacts will close only when
the System B reset pushbutton is pressed).
Figure 15 provides a visual representation of the latching “Lockout” concept. The
figure only explicitly shows the tripping and lockout for unit 1. (Unit 2 trip circuit
will look identical)
6.3.3.3 Two Tripping Contacts in Series
As seen in Figure 15, two trip contacts are wired in series for each circuit breaker
trip coil and breaker failure initiate circuit. Each contact must close prior to
initiating the function. Each of the two contacts resides on different relay modules.
This physical design feature provides a level of comfort in limiting the tripping of a
unit by the inadvertent closure of one relay contact. Inadvertent contact closure
could theoretically be caused by module failure or unintentional contact shorting.
6.3.3.4 DCSPS “Voting” Scheme (or Cross Blocking Scheme)
System “A” and System “B” exchange Trip information for comparison purposes.
If System “A” or System “B” makes the decision to trip a Unit, the tripping System
(“A” or “B”) waits for a response from the alternate system. If there is no decision
issued by the alternate system, then the unit will be tripped. If the alternate system
also has made a trip decision, and the unit selection matches; the unit is tripped. If
the alternate system makes a decision to trip a unit, and the unit selected is in
disagreement, then NO unit will be tripped.
This portion of the scheme logic may be more easily described as a “Cross Blocking
Feature”. Each system can be blocked from tripping by the alternate system.
Design Adequacy (Ref DCPP EDDG-006 Attachment 8.1)
DCSPS Operations Handbook Page 6-6 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
Trip Coil 1 DC (-)
Trip Coil 1 DC (+)
DCSPS Unit-1 Tripping Relays
U1
CB
TC 1
DCPP_DCSPS 01-2006
Dpe4
Cut-Out Switch
RCO/DCSPS-A
Cut-Out Switch
RCO/DCSPS-B
Trip Coil 2 DC (-)
Trip Coil 2 DC (+)
U1
CB
TC 2
Cut-Out Switch
RCO/DCSPS-A
Cut-Out Switch
RCO/DCSPS-B
OPEN
CLOSE
LATCH
SYS-A
BF DC (-)
BF DC (+)
Cut-Out Switch
RCO/DCSPS-B
Cut-Out Switch
RCO/DCSPS-A
PRI
TC-1
SYS-A
Mod-F
PRI
TC-1
SYS-B
Mod-F
OPEN
CLOSE
LATCH
SYS-B
OPEN
CLOSE
LATCH
SYS-BOPEN
CLOSE
LATCH
SYS-B
OPEN
CLOSE
LATCH
SYS-AOPEN
CLOSE
LATCH
SYS-A
BF INIT
SYS-A
SYS-B
CB
CLOSE
579H
Auto Reclose
DCSPS
TRIP COIL #1
TRIP
DCSPS
Reclose
Block
DCSPS
TRIP COIL #2
TRIP
DCSPS
Breaker Failure
Initiate
Unit #1 Sys - A Trip
Unit #1 Sys - B Trip
ORUnit #2 DCSPS
Lockout
Close
Close Close
Close
Ope
n
Unit #1 DCSPSLockout
(From U2 Trip bySys-A OR Sys-B)
SYS A RESET PB
Open Close
Clo
seSEC
TC-1
SYS-A
Mod-M
SEC
TC-1
SYS-B
Mod-M
PRI
TC-2
SYS-A
Mod-F
PRI
TC-2
SYS-B
Mod-F
SEC
TC-2
SYS-A
Mod-M
SEC
TC-2
SYS-B
Mod-M
PRI
BFI
SYS-A
Mod-F
PRI
BFI
SYS-B
Mod-F
SEC
BFI
SYS-A
Mod-M
SEC
BFI
SYS-B
Mod-M
Close
Close Close
Close
U1 Trip Lockout U1 Trip Lockout
Sys-B Reset
Close
Close
Close
Clo
se
SYS-BSYS-A SYS-BSYS-A SYS-BSYS-A
SYS B RESET PB
Sys-A Reset
Sys-B Reset
Sys-A Reset
Figure 15: Alternate Unit DCSPS Tripping Lockout
Design Adequacy (Ref DCPP EDDG-006 Attachment 8.1)
DCSPS Operations Handbook Page 6-7 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
6.4 Surge Protection
All Protection and Auxiliary relays used for this scheme are approved by Substation engineering for use
in Substation environments.
6.4.1 UR Relay Surge Protection
Refer to the UR Relay Instruction manual for specific industry standard tests. The following
information was obtained from the UR N60 Relay Instruction manual:
Surge Impunity Test
▪ EN 61000-4-5
6.4.2 EMI and RFI (Electro-Magnetic and Radio Interference)
All Protection and Auxiliary relays used for this scheme are approved by Substation engineering for
use in Substation environments.
6.4.2.1 UR Relay EMI/RFI tests
Refer to the UR Relay Instruction manual for specific industry standard tests. The
following information was obtained from the UR N60 Relay Instruction manual:
Electrical Fast Transient:
▪ ANSI/IEEE C37.90.1
▪ IEC 61000-4-4
▪ IEC 60255-22-4
RFI Susceptibility:
▪ ANSI/IEEE C37.90.2
▪ IEC 61000-4-3
▪ IEC 60255-22-3
▪ Ontario Hydro C-5047-77
Conducted RFI:
▪ IEC 61000-4-6
Power frequency Magnetic field immunity:
▪ IEC 61000-4-8
6.4.2.2 DC Transients
All new substation projects install shielded cables to reduce the electrical transients
on the attached equipment.
Some of the possible causes of transient events include:
▪ Switching surges
▪ Floating DC circuits or when DC sources are being tested for other future projects
▪ Battery charger startup
Design Adequacy (Ref DCPP EDDG-006 Attachment 8.1)
DCSPS Operations Handbook Page 6-8 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
In order to secure the functionality of the scheme under transient conditions, all of
the following DC inputs will be set with a 16 millisecond time delay. (Input must
be asserted continuously for the pickup time before the relay logic will act on the
input).
▪ BF Initiate Inputs
▪ Breaker Status Change
▪ Breaker Maintenance Switches
▪ Breaker Failure Tripping
6.5 Protection Devices
6.5.1 Sensitivity
All Protection and Auxiliary relays used for this scheme are approved by Substation engineering for
use in Substation environments.
6.5.2 Relay Reliability
Approval from GE was obtained prior to quoting the following statistics:
• MTBF (Mean Time Between Failure): 104 years
• Availability: 99.99963%
For details regarding the actual equations for the statistics shown above, contact the GE factory.
6.5.3 Coordination
It is essential that this scheme coordinates with the Line and Unit relays
• The DCSPS must react faster than the Unit Out-of-Step relaying. The
DCSPS must issue a trip within 70 milliseconds of line short circuit inception
and 200 milliseconds for breaker failure scenarios. (See “Additional
Reference Documents”, Item #4)
• The 500kV line relay Out-of-Step blocking functions must be enabled to
prevent line tripping for Out-of-Step conditions.
6.5.4 Relay Burden
Microprocessor relays add minimal burden to the AC circuitry. The wiring added to include the new
relays was minimal and routed within the control room.
The following information was obtained from the UR N60 Relay Instruction manual:
▪ Relay AC Current Burden: < 0.2 VA at rated secondary
▪ Relay AC Voltage Burden: < 0.2 VA at rated secondary
6.5.5 Scheme Accuracy
The Relay Accuracy will directly impact the setpoint accuracy.
CT Error (CT accuracy) 1.0%
PT Error (PT accuracy) 1.0%
N60 Power Computation Accuracy 1.0%
N60 Digitizer Computation Accuracy 0.5%
Margin factor 1.5%
Design Adequacy (Ref DCPP EDDG-006 Attachment 8.1)
DCSPS Operations Handbook Page 6-9 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
Total Error (Worst Case: 120 MW at
full scale)
5.0%
6.6 Design Calculations (Quality Assurance)
Those items not specifically referred to in this sub-section can be found within this document as a
whole. (Example: Design details, drawing list, description of Operations, Testing Criteria etc.)
6.6.1 Setting Reevaluation and Update
The set points for the scheme, (See appendix), will be reevaluated by PG&E Operation Engineering
department on a periodic basis. Setpoint setting changes may be the result of updated studies.
System Protection will coordinate any setting changes with DCPP Engineering for review and
concurrence prior to implementation.
6.6.1.1 Setpoint changes
Any setpoint change requests will be routed through PG&E System Protection Department
for implementation. The setpoint setting change request must be communicated to Diablo
Canyon Engineering.
Setpoint changes may include but are not limited to:
▪ New Set points for Positive Sequence Voltage level Setting
▪ Adjustment of Megawatt arming levels
The recommended procedure is as follows:
1. Obtain permission from the TOC for cutting out System A. (or System B)
2. Cut-Out System A. (or System B)
3. Maintenance or Construction tech makes necessary setting change(s) by either
loading file, or changing each setting individually.
4. Send As-Left settings to protection engineer for verification. Perform any other
necessary checks per Protection Engineer request. (Additional checks may be
verification of LED status, etc.)
5. Protection Engineer releases scheme to Operations
6. Operations to verify that the scheme does not have a sealed trip.
7. Cut-In scheme.
8. Repeat steps for alternate system. (System B)
6.6.1.2 Logic Changes
Logic changes may be necessary to improve the scheme performance.
Logic changes may include but are not limited to:
▪ Adjustment of timer pickup and/or dropout times
▪ Removal of Logic that is no longer required
Design Adequacy (Ref DCPP EDDG-006 Attachment 8.1)
DCSPS Operations Handbook Page 6-10 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
6.6.2 N60 Relay Setting Ownership
The PG&E System Protection Department is responsible for providing any future setting changes
necessary for proper scheme operation. Setting changes will be issued in the form of a setting file to
the responsible PG&E Construction or Maintenance personnel.
The PG&E Maintenance headquarters associated with Diablo Canyon 500kV switchyard will
maintain setting files for the scheme. These setting files will accurately reflect the existing settings on
all relays associated with Diablo SPS.
The PG&E System Protection Department will maintain up-to-date Diablo Canyon SPS setting files
within the Protection Relay Setting Database. These files will accurately reflect the existing settings
on all relays associated with Diablo SPS.
6.6.3 Setting Verification (Protection Department)
6.6.3.1 Periodic
The Scheme settings will be verified on a periodic basis to ensure that the set points and
logic are as expected. Settings should be verified during the regularly scheduled Diablo
SPS test cycle.
6.6.3.2 Setting Change(s)
Upon downloading a new setting file into the appropriate relay(s), the responsible PG&E
Construction or Maintenance personnel will return a copy of the “As-Left” relay(s)
settings to PG&E System Protection for comparison with the expected settings.
6.6.4 Relay Firmware
6.6.4.1 Existing Firmware
The relay firmware upon commissioning of the scheme is version 5.0
6.6.4.2 Changes to Firmware
Any changes to the Relay firmware will require a review of the settings to ensure any
setting elements used in the scheme have not been removed by the new firmware. Any
new settings made available by the firmware upgrade should be reviewed to determine if
they provide any additional benefits for use in the scheme. (Examples may include
additional I/0, enhanced voltage measurements, etc.)
As a general rule, a relay firmware upgrade will require a system test of the affected
relays.
Glossary
DCSPS Operations Handbook Page 7-1 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
7 Glossary
Fault Severity For the Purposes of the Diablo SPS, fault severity is defined by the collapse of the 500kV Positive Sequence Voltage. The Breaker
Failure DCSPS events utilize the Positive sequence voltage collapse to determine severity of the fault.
NERC North American Electric Reliability Council
Relays Relays are devices that monitor and sense abnormalities within an electric system. Relays are programmed to close contacts within an
electric circuit when certain imbalance thresholds have been met.
CAISO California Independent System Operator
Contingency The loss of an element in the power system. “First Contingency” refers to the loss of one unique element (e.g., the loss of a critical
transmission line or generator). “Second Contingency” refers to the loss of a subsequent unique element while the first element is still out
of service.
Inrush Current Inrush current is the short duration, large magnitude current required creating the fields that start motors, AND magnetize transformer
cores.
MW Megawatt
SPS Special Protection System. As implied by the name, an SPS is a protection scheme that goes beyond the scope of a standard
protection scheme. Special Protection Schemes (SPS) are designed to respond quickly to pre-defined events for which reliance on human
intervention is insufficient to protect equipment and minimize the adverse impacts of those events.
SATS Strategic and Technical Services PG&E engineering department
Overcurrent A condition in which the flow on a system element is above an established threshold. Overcurrent conditions are used in
conjunction with breaker seal status in some SPS to improve the reliability of outage status determination.
Undercurrent A condition in which the current flow on a system element is below an established threshold. Undercurrent conditions are used in
conjunction with breaker seal status in some SPS to improve the reliability of outage status determination.
Remote End Remote End 500kV Line Terminal
SCADA Supervisory Control and Data Acquisition. SCADA is a system of RTUs, communication links and master control stations devices that enable Electric Transmission Control Center operators to remotely
monitor system conditions such as MWs, amps, volts and the open/close status of circuit breakers and switches. It also makes the control of circuit breakers, switches, and other apparatus possible.
TOC Transmission Operations Center, located in the San Francisco General Office. System Dispatchers are a part of the TOC.
Additional Reference Documents
DCSPS Operations Handbook Page 8-1 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
8 Additional Reference Documents
Document Owner Document Location
1 “Electrical Design Desk Guide” EDDG-006 Attachment 8.1
Diablo Canyon PP Reference version will be included on the System
Protection Share drive: "ETM on 'Oakland03'" under the
"RAS - SPS Info/DCSPS" folder from DCPP
2 Diablo Canyon SPS UR Relay Commissioning Testing
System Protection Engineering
All documentation associated with Diablo Canyon SPS design
will be stored on the System Protection Share drive: "ETM
on 'Oakland03'" under the "RAS - SPS Info/DCSPS" folder. If documents are required, please contact System Protection for
assistance.
3 Mitigation Measures for Double Outages at Diablo Canyon Power Plant
Electric Transmission and Distribution Engineering
Electric Transmission and Distribution Engineering for
Details
4 DCPP SPS Technical Requirements (Modification of Section 6 in the SATS
report)
Electric Transmission and Distribution Engineering
Electric Transmission and Distribution Engineering for
Details
5 O23 Operations Engineering
Appendix A: DCSPS Critical Set Points (Commissioning Settings)
DCSPS Operations Handbook Page 9-1 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
9 Appendix A: DCSPS Critical Set Points (Commissioning Settings)
9.1 Set Points and Definitions
SETPOINT DESCRIPTION
Relay Setting
(May 06)
Set Point Accuracy
1
TMW
The Definite Time setting necessary for MW Arming and
Disarming. (The setting prohibits a DCSPS arming status
change during an event or post-event transients. MW arming
will occur when the U1+U2 NET MW Export is above the
MW arming setting, (L1 through L5), for the TMW period.
MW disarming will occur if the U1+U2 NET MW Export is
below the MW arming setting, (L1 through L5), for the TMW
period.)
10 Sec +/- 1 msec
2 TSIMULTANEOUS
The period of time, within which two events occur, will be
considered simultaneous 10 Sec
+/- 1 msec
3
L1
(Level 1)
Plant U1+U2 NET MW export arming level for DCSPS Event
– 1
(Setting is a function of plant minimum operating voltage –
0.975 pu of 25kV)
1808 MW < 5.0%
4
L2
(Level 2)
Plant U1+U2 NET MW export arming level for DCSPS Event
– 2
(Setting is a function of plant minimum operating voltage –
0.975 pu of 25kV)
1790 MW < 5.0%
5
L3
(Level 3)
Plant U1+U2 NET MW export arming level for DCSPS Event
– 3
(Breaker Failure with a Severe Fault)
(Setting is a function of plant minimum operating voltage –
0.975 pu of 25kV)
1723 MW < 5.0%
6
L4
(Level 4)
Plant U1+U2 NET MW export arming level for DCSPS Event
– 3
(Breaker Failure with a Medium severity level fault)
3000 MW (DISABLED
) < 5.0%
7
L5
(Level 5)
Plant U1+U2 NET MW export arming level for Double Line
Outage.
(Supports O23 operating procedure.)
1600 MW < 5.0%
8
UVm
500kV positive sequence setting value. Per Unit of nominal
voltage. (The measured 500kV positive sequence voltage
MUST fall below this setting level for the fault to be
categorized as “Medium” severity)
400 kVLL
(0.77 pu of 519.6 kVLL)
+/- 0.5%
9
UVs
500kV positive sequence setting value. Per Unit of nominal
voltage. (The measured 500kV positive sequence voltage
MUST fall below this setting level for the fault to be
categorized as “Severe”)
285 kVLL
(0.548 pu of 519.6 kVLL)
+/- 0.5%
Appendix A: DCSPS Critical Set Points (Commissioning Settings)
DCSPS Operations Handbook Page 9-2 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
SETPOINT DESCRIPTION
Relay Setting
(May 06)
Set Point Accuracy
10
TV1
The 500kV positive sequence voltage dip window. (The
positive sequence voltage dip must be sensed in the window
of time beginning with an event initiation and ending with this
timer setting)
12 Cycles +/- 1
mesec
11
UC1
Undercurrent Pickup setting. (Used for Local Line outage and
Remote Line Outage)
220 Amps
(0.11 pu 1% Hyst.)
+/- 1 %
12
Vdlos
The positive sequence voltage level that supervises a double
line outage scenario (Outage → Outage). The voltage must
be below the setting
540 kV
(1.039 pu of 519.6 kVLL Hyst. 0.2%)
+/- 0.5%
13
Digitizer
The MW Quantities calculated by the relay are Digitized and
sent via relay-to-relay communication for Summation and
compared against MW setpoints
11 MW/BIT
(Summed Values are 22 MW/BIT)
0.5%
Appendix B: Diablo Canyon SPS Alarm Points
DCSPS Operations Handbook Page 10-1 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10 Appendix B: Diablo Canyon SPS Alarm Points
10.1 Diablo Canyon Annunciation & RTU Alarms
DESCRIPTION
ORIGINATION
Station
ANNUNCIATOR RTU
1
DIABLO - GATES 500kV LINE OUTAGE
Indicates that the DCSPS logic has Determined a
Diablo – Gates Line Outage
537DCSPS-A and 537DCSPS-B in PARALLEL
(One Or Both Systems will bring in this Point)
NO 500 D20ME RTU
2
DIABLO - MIDWAY #2 500kV LINE OUTAGE
Indicates that the DCSPS logic has Determined a
Diablo-Midway #2 Line Outage
537DCSPS-A and 537DCSPS-B in PARALLEL
(One Or Both Systems will bring in this Point)
NO 500 D20ME RTU
3
DIABLO - MIDWAY #3 500kV LINE OUTAGE
Indicates that the DCSPS logic has Determined a
Diablo – Midway #3 Line Outage
537DCSPS-A and 537DCSPS-B in PARALLEL
(One Or Both Systems will bring in this Point)
NO 500 D20ME RTU
4
UNIT #1 OUTAGE
Indicates that the DCSPS logic has Determined a
Unit #1 Outage
537DCSPS-A and 537DCSPS-B in PARALLEL
(One Or Both Systems will bring in this Point)
NO 500 D20ME RTU
5
UNIT #2 OUTAGE
Indicates that the DCSPS logic has Determined a
Unit #2 Outage
537DCSPS-A and 537DCSPS-B in PARALLEL
(One Or Both Systems will bring in this Point)
NO 500 D20ME RTU
6 UNIT #2 TRIPPING PREFERENCE
Indicates the Position of the Unit Selector Switch
537DCSPS-A and 537DCSPS-B in PARALLEL
(One Or Both Systems will bring in this Point)
NO 500 D20ME RTU
7 UNIT #1 TRIPPING PREFERENCE
Indicates the Position of the Unit Selector Switch
537DCSPS-A and 537DCSPS-B in PARALLEL
(One Or Both Systems will bring in this Point)
NO 500 D20ME RTU
8 SYSTEM A: (LINE-OUT) and (U1+U2 MW NET > L1) 578/586DCSPSA-1 (System A will bring in this Point) NO 500 D20ME RTU
Appendix B: Diablo Canyon SPS Alarm Points
DCSPS Operations Handbook Page 10-2 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
DESCRIPTION
ORIGINATION
Station
ANNUNCIATOR RTU
ARMING INDICATION
9
SYSTEM A: (LINE-OUT) and
(500kV-VOLTS< Vdlos) and (U1+U2 MW NET > L1)
ARMING INDICATION
578/586DCSPSA-1 (System A will bring in this Point) NO 500 D20ME RTU
10
SYSTEM A: (TWO LINES-OUT) and
(U1+U2 MW NET > L5)
ARMING INDICATION
578/586DCSPSA-1 (System A will bring in this Point) NO 500 D20ME RTU
11 SYSTEM A: SPARE 578/586DCSPSA-2 (System A will bring in this Point) NO 500 D20ME RTU
12 SYSTEM A: SPARE 578/586DCSPSA-2 (System A will bring in this Point) NO 500 D20ME RTU
13 SYSTEM B: (LINE-OUT) and (U1+U2 MW NET > L1)
ARMING INDICATION
578/586DCSPSB-1 (System B will bring in this Point) NO 500 D20ME RTU
14
SYSTEM B: (LINE-OUT) and
(500kV-VOLTS< Vdlos) and (U1+U2 MW NET > L1)
ARMING INDICATION
578/586DCSPSB-1 (System B will bring in this Point) NO 500 D20ME RTU
15
SYSTEM B: (TWO LINES-OUT) and
(U1+U2 MW NET > L5)
ARMING INDICATION
578/586DCSPSB-1 (System B will bring in this Point) NO 500 D20ME RTU
16 SYSTEM B: SPARE 578/586DCSPSB-2 (System B will bring in this Point) NO 500 D20ME RTU
17 SYSTEM B: SPARE 578/586DCSPSB-2 (System B will bring in this Point) NO 500 D20ME RTU
18
SYSTEM A UNIT 1 TRIP
Indicates that System A has tripped
Unit #1
578/586DCSPSA-1 YES 500 D20ME RTU
19 SYSTEM A UNIT 2 TRIP 578/586DCSPSA-2 YES 500 D20ME RTU
Appendix B: Diablo Canyon SPS Alarm Points
DCSPS Operations Handbook Page 10-3 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
DESCRIPTION
ORIGINATION
Station
ANNUNCIATOR RTU
Indicates that System A has tripped
Unit #2
20
SYSTEM B UNIT 1 TRIP
Indicates that System B has tripped
Unit #1
578/586DCSPSB-1 YES 500 D20ME RTU
21
SYSTEM B UNIT 2 TRIP
Indicates that System B has tripped
Unit #1
578/586DCSPSB-2 YES 500 D20ME RTU
22
SYSTEM A CHANNEL FAIL
Indicates that Both Communication channels
For System-A have failed. (No Relay-Relay
Communication Capability)
ALL SYSTEM “A” RELAYS IN PARALLEL YES 500 D20ME RTU
23
SYSTEM B CHANNEL FAIL
Indicates that Both Communication channels
For System-A have failed. (No Relay-Relay
Communication Capability)
ALL SYSTEM “B” RELAYS IN PARALLEL YES 500 D20ME RTU
24
SYSTEM A CUT-OUT
SYSTEM A C/O SWITCH NO 500 D20ME RTU
25
SYSTEM B CUT-OUT
SYSTEM B C/O SWITCH NO 500 D20ME RTU
26
SYS A RELAY CRITICAL FAILURE
ALL SYS A RELAYS IN PARALLEL
(Any failure of ONE relay will bring in this point)
YES 500 D20ME RTU
27 SYS B RELAY CRITICAL FAILURE ALL SYS B RELAYS IN PARALLEL YES 500 D20ME RTU
Appendix B: Diablo Canyon SPS Alarm Points
DCSPS Operations Handbook Page 10-4 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
DESCRIPTION
ORIGINATION
Station
ANNUNCIATOR RTU
(Any failure of ONE relay will bring in this point)
28
SYS A MAINTENANCE ALARM
537/511DCSPSA-1 and 537/511DCSPSA-2 in PARALLEL
(Any System A Maintenance Alarm will bring in this point)
YES 500 D20ME RTU
29
SYS B MAINTENANCE ALARM
537/511DCSPSB-1 and 537/511DCSPSB-2 in PARALLEL
(Any System A Maintenance Alarm will bring in this point)
YES 500 D20ME RTU
NOTE:
RTU: All points indicated for the RTU will be available
AFTER the RTU replacement
(Note: 10/05/2005)
▪ It is projected that the 500kV RTU will be replaced by June 2006
Appendix C: Diablo Canyon SPS Drawings
DCSPS Operations Handbook Page 11-1 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel
Only
11 Appendix C: Diablo Canyon SPS Drawings
11.1 Diablo Canyon SPS Drawing List
DESCRIPTION Design Drawing
Number
1 Single Line Meter and Relay 56654
2 Unit 1 500/25kV- (CB 532 & 632) (AC) 435804
3 CB 532 Control (DC) 435807
4 Unit 2 500/25kV- (CB 542 & 642) (AC) 435538
5 CB 542 Control (DC) 443541
6 500kV RAS (Maintenance Switch) 4004438
7 Diablo – Midway #3 (CB 632 & 732) (AC) 4012506
8 Bay 3 BF Timing (CB 532, 632, & 732) (DC) 4012509
9 CB 632 Control (DC) 4012514
10 CB 732 Control (DC) 4012515
11 Diablo – Midway #2 (CB 642 & 742) (AC) 4012518
12 Bay 4 BF Timing (CB 542, 642, & 742) (DC) 4012520
13 CB 642 Control (DC) 4012525
14 CB 742 Control (DC) 4012526
17 Diablo – Gates (CB 622 & 722) (AC) 4013352
18 Bay 2 BF Timing (CB 622 & 722) (DC) 4013354
19 CB 622 Control (DC) 4013359
20 CB 722 Control (DC) 4013360
21 DCSPS Panel Arrangement 4038189
22 DCSPS Alarms and SCADA points 4038190
23 DCSPS Alarms and SCADA points 4038191
24 DCSPS System A Unit 1 Device 578/586DCSPSA-1 (DC) 4038194
25 DCSPS System B Unit 1 Device 578/586DCSPSB-1 (DC) 4038195
26 DCSPS System A Unit 2 Device 578/586DCSPSA-2 (DC) 4038196
27 DCSPS System B Unit 2 Device 578/586DCSPSB-2 (DC) 4038197
28 DCSPS System A Line Device 537DCSPS-A (AC) 4038198
29 DCSPS System B Line Device 537DCSPS-B (AC) 4038199
30 DCSPS System A Line Device 537DCSPS-A (DC) 4038200
31 DCSPS System B Line Device 537DCSPS-B (DC) 4038201
Appendix C: Diablo Canyon SPS Drawings
DCSPS Operations Handbook Page 11-2 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel
Only
DESCRIPTION Design Drawing
Number
32 DCSPS System A Unit 1 Device 537/511DCSPSA-1 (AC) 4038202
33 DCSPS System B Unit 1 Device 537/511DCSPSB-1 (AC) 4038203
34 DCSPS System A Unit 1 Device 537/511DCSPSA-1 (DC) 4038204
35 DCSPS System B Unit 1 Device 537/511DCSPSB-1 (DC) 4038205
36 DCSPS System A Unit 2 Device 537/511DCSPSA-2 (AC) 4038206
37 DCSPS System B Unit 2 Device 537/511DCSPSB-2 (AC) 4038207
38 DCSPS System A Unit 2 Device 537/511DCSPSA-2 (DC) 4038208
39 DCSPS System B Unit 2 Device 537/511DCSPSB-2 (DC) 4038209
40 Diablo Canyon DC Panels 440004
Appendix D: DCSPS Event Category Detailed Description
DCSPS Operations Handbook Page 12-1 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
12 Appendix D: DCSPS Event Category Detailed Description
The following table defines the three Event Categories part of the Diablo Canyon SPS.
DCSPS Event Definition
1
One Line Trip or One Line Outage in a Double line configuration (Two Lines Initially In-Service):
Twelve (12) Permutations:
OUTAGE (1st Line) → TRIP (2nd Line)
OUTAGE (1st Line) → OUTAGE (2nd Line)
Diablo – Gates 500kV Line Outage
A. Protection Trip (or Outage) of the Diablo Canyon – Midway #3 500kV
line. (Two Permutations)
Protection Trip (or Outage) of the Diablo Canyon – Midway #2 500kV line.
(Two Permutations)
Diablo – Midway #3 500kV Line Outage
Protection Trip (or Outage) of the Diablo Canyon – Midway #2 500kV line.
(Two Permutations)
Protection Trip (or Outage) of the Diablo Canyon – Gates 500kV line. (Two
Permutations)
Diablo – Midway #2 500kV Line Outage
Protection Trip (or Outage) of the Diablo Canyon – Gates 500kV line. (Two
Permutations)
Protection Trip (or Outage) of the Diablo Canyon – Midway #3 500kV line.
(Two Permutations)
Appendix D: DCSPS Event Category Detailed Description
DCSPS Operations Handbook Page 12-2 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
DCSPS Event Definition
2
Double Line Trips or Double Line Outages in a Triple line configuration (Three Lines initially In-Service)
Twelve (12) Permutations:
TRIP (1st Line) → TRIP (2nd Line)
TRIP (1st Line) → OUTAGE (2nd Line)
A. Protection Trip (or Outage) of the Diablo Canyon – Gates 500kV line
AND a Protection Trip (or Outage) of the Diablo Canyon – Midway #3
500kV line within the TSIMULTANEOUS time window. (Four
Permutations)
B. Protection Trip (or Outage) of the Diablo Canyon – Midway #3 500kV
line AND a Protection Trip (or Outage) of the Diablo Canyon – Midway
#2 500kVline within the TSIMULTANEOUS time window. (Four
Permutations)
C. Protection Trip (or Outage) of the Diablo Canyon – Midway #2 500kV
line AND a Protection trip (or Outage) of the Diablo Canyon – Gates
500kV line within the TSIMULTANEOUS time window. (Four
Permutations)
3
500kV Circuit Breaker Failure
Four (4) Distinct Possibilities:
A. CB 622 Failure
CB 722 Failure
CB 532 Failure (Not Required)
CB 632 Failure (Not Required)
CB 732 Failure
CB 542 Failure (Not Required)
CB 642 Failure (Not Required)
CB 742 Failure
Appendix E: Unit Tripping Determination and Karnaugh Maps
DCSPS Operational Handbook Page 13-1 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
13 Appendix E: Unit Tripping Determination and Karnaugh Maps
The Karnaugh Maps in this appendix are included to illustrate the process involved with Unit trip
selection as a function of the Diablo Canyon 500kV Bus configuration at the time of the event.
The Unit Selection trip logic was derived with the use of the Karnaugh Maps and is included in this
section as well.
Appendix E: Unit Tripping Determination and Karnaugh Maps
DCSPS Operational Handbook Page 13-1 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
BUS 2
742642
732
722622
542
BUS 1
632532
DIABLO - MIDWAY #2
500kV LINE
DIABLO - MIDWAY #3
500kV LINE
GATES - DIABLO
500kV LINE
DIABLO
UNIT 2
DIABLO
UNIT 1
BUS 2
742642
732
722622
542
BUS 1
632532
DIABLO - MIDWAY #2
500kV LINE
DIABLO - MIDWAY #3
500kV LINE
GATES - DIABLO
500kV LINE
DIABLO
UNIT 2
DIABLO
UNIT 1
BUS 2
742642
732
722622
542
BUS 1
632532
DIABLO - MIDWAY #2
500kV LINE
DIABLO - MIDWAY #3
500kV LINE
GATES - DIABLO
500kV LINE
DIABLO
UNIT 2
DIABLO
UNIT 1
DCSPS EVE-1A
DCSPS EVE-1D
DCSPS EVE-1C
DCSPS EVE-1F
DCSPS EVE-1B
DCSPS EVE-1E
DIABLO - MIDWAY #3 LINE OUTAGEDIABLO - MIDWAY #2 LINE TRIP
DIABLO - GATES LINE OUTAGEDIABLO - MIDWAY #2 LINE TRIP
DIABLO - GATES LINE OUTAGEDIABLO - MIDWAY #3 LINE TRIP
DIABLO - GATES LINE TRIPDIABLO - MIDWAY #3 LINE OUTAGE
DIABLO - MIDWAY #3 LINE TRIPDIABLO - MIDWAY #2 LINE OUTAGE
DIABLO - GATES LINE TRIPDIABLO - MIDWAY #2 LINE OUTAGE
DIABLO - MIDWAY #3 LINE TRIP or OUTAGEDIABLO - MIDWAY #2 LINE TRIP or OUTAGE
DIABLO - MIDWAY #2 LINE TRIP or OUTAGEDIABLO - GATES LINE TRIP or OUTAGE
DIABLO - GATES LINE TRIP or OUTAGEDIABLO - MIDWAY #3 LINE TRIP or OUTAGE
DCSPS EVE-2B DCSPS EVE-2CDCSPS EVE-2A
DCPP_DCSPS 10-2005
Dpe4
For DCSPS Event 2x, the breakers at Diablo on the linethat is OUT may not be open (Remote Open Detection).The Remote End breakers, instead, may be open. Thefigure above is equivalent to the remote end breakersOpen.
Diablo - Midway #2 Line is the only export Path
By inspection, Unit 2 will never be tripped in thiscondition.
DCSPS Trips UNIT #1, (if MW and VOLTAGEsupervision is satisfied), AND only if CB’s 532, 542,and 642 are closed. (742 position status is not relevant)(DCSPS will be restricted from tripping unless theconfiguration of the four breakers that are unaffected bythe event are in a configuration such that DCSPS willresult in a beneficial action. )
DCSPS Event - 1x and 2x: Unit Trip Selection as a function of BUS CONFIGURATION
NO
TE
S
For DCSPS Event 2x, the breakers at Diablo on the linethat is OUT may not be open (Remote Open Detection).The Remote End breakers, instead, may be open. Thefigure above is equivalent to the remote end breakersOpen.
Diablo - Gates Line is the only export Path
By inspection, Either Unit #1 or Unit #2 can be tripped.
DCSPS Trips by the Unit Selector Switch Preference, (ifMW and VOLTAGE supervision is satisfied), AND onlyif CB’s 532, 542, and 622 are closed. (722 position statusis not relevant)(DCSPS will be restricted from tripping unless theconfiguration of the four breakers that are unaffected bythe event are in a configuration such that DCSPS willresult in a beneficial action. )
For DCSPS Event 2x, the breakers at Diablo on the linethat is OUT may not be open (Remote Open Detection).The Remote End breakers, instead, may be open. Thefigure above is equivalent to the remote end breakersOpen.
Diablo - Midway #3 Line is the only export Path
By inspection, Unit 1 will never be tripped in thiscondition.
DCSPS Trips UNIT #2, (if MW and VOLTAGEsupervision is satisfied), AND only if CB’s 532, 542,and 632 are closed. (732 position status is not relevant)(DCSPS will be restricted from tripping unless theconfiguration of the four breakers that are unaffected bythe event are in a configuration such that DCSPS willresult in a beneficial action. )
UN
IT T
RIP
DE
CIS
ION
AS
A
FU
NC
TIO
N O
F R
EM
AIN
ING
50
0k
V B
RE
AK
ER
CO
NF
IGU
RA
TIO
N
BU
S C
ON
FIG
UR
AT
ION
AS
A
FU
NC
TIO
N O
F T
HE
EV
EN
T
N
N
N
N
N
N
N
N
U1
N
N
N
N
N
N
00 01 11 10
00
01
11
10
N
N
N
N
N
N
N
N
U2
N
N
N
N
N
N
N N N N
N N N N
N N E N
N N E N
00 01 11 10
00
01
11
10
00 01 11 10
00
01
11
10
622 532
722 542632 532
732 542642 532
742 542
U1 U2
1: CB is Closed at the time of Initiating Event (t0) 0: CB is Opened at the time of Initiating Event (t
0)
Diablo SPS will only trip if it results in a benefit. (Removal of one of two units that remain tied to the system after the initiating event.
U1: Unit #1 Tripped U2: Unit #2 Tripped E: Either - Unit Tripped based on Unit Selector Sw
Appendix E: Unit Tripping Determination and Karnaugh Maps
DCSPS Operational Handbook Page 13-2 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
AND
CB 532 CLOSED
CB 542 CLOSED
CB 642 CLOSED
OR
AND
AND
AND
DG OUTAGE
DM#3 TRIP
DM#3 OUTAGE
DG TRIP
DM#3 (OUTAGE or TRIP)
DG (OUTAGE or TRIP)AND
UNIT #1 TRIP
AND
CB 532 CLOSED
CB 542 CLOSED
CB 622 CLOSED
OR
AND
AND
AND
DM#2 OUTAGE
DM#3 TRIP
DM#3 OUTAGE
DM#2 TRIP
DM#3 (OUTAGE or TRIP)
DM#2 (OUTAGE or TRIP)AND
UNIT TRIP BY UNITSELECTOR
AND
CB 532 CLOSED
CB 542 CLOSED
CB 632 CLOSED
OR
AND
AND
AND
DG OUTAGE
DM#2 TRIP
DM#2 OUTAGE
DG TRIP
DM#2 (OUTAGE or TRIP)
DG (OUTAGE or TRIP)AND
UNIT #2 TRIP
DCSPS EVE-1A
DCSPS EVE-1D
DCSPS EVE-1C
DCSPS EVE-1F
DCSPS EVE-1B
DCSPS EVE-1E
DCSPS EVE-2B
DCSPS EVE-2C
DCSPS EVE-2A
TRIP LOGIC DCSPS Event - 1x and 2x (SEE STATE TRANSITION DIAGRAMS)
Physical Topology ofthe 500kV Bus
(From Karnaugh Map)
Physical Topology ofthe 500kV Bus
(From Karnaugh Map)
Physical Topology ofthe 500kV Bus
(From Karnaugh Map)
DCPP_DCSPS 12-2005
Dpe4
Appendix E: Unit Tripping Determination and Karnaugh Maps
DCSPS Operational Handbook Page 13-3 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
632
742
BUS 2
742642
732
722622
542
BUS 1
632532
DIABLO - MIDWAY #2
500kV LINE
DIABLO - MIDWAY #3
500kV LINE
GATES - DIABLO
500kV LINE
DIABLO
UNIT 2
DIABLO
UNIT 1
FAILBUS 2
642
BUS 1
632
DIABLO - MIDWAY #2
500kV LINE
DIABLO - MIDWAY #3
500kV LINE
GATES - DIABLO
500kV LINE
DIABLO
UNIT 2
DIABLO
UNIT 1
722
FAIL
622
732532
542 742
BUS 2
642
DIABLO - MIDWAY #2
500kV LINE
DIABLO - MIDWAY #3
500kV LINE
GATES - DIABLO
500kV LINE
DIABLO
UNIT 1
FAIL
532
542
BUS 1
722
732
622
DIABLO
UNIT 2
BUS 2
DIABLO - MIDWAY #2
500kV LINE
DIABLO - MIDWAY #3
500kV LINE
GATES - DIABLO
500kV LINE
DIABLO
UNIT 1
532
542
722622
DIABLO
UNIT 2
732632
642
FAIL
742
DCSPS Event - 3x: Unit Trip Selection as a function of BUS CONFIGURATION
DCSPS EVE-3ACB 622 Failure
DCSPS EVE-3BCB 722 Failure
BUS 1
DCSPS EVE-3ECB 732 Failure
DCSPS EVE-3HCB 742 Failure
BU
S C
ON
FIG
UR
AT
ION
AS
A
FU
NC
TIO
N O
F T
HE
EV
EN
T
N
N
N
N
N
N
N
N
E
N
N
N
N
00 01 11 10
00
01
11
10
732 632
742 642
E
E
E
UN
IT T
RIP
DE
CIS
ION
AS
A
FU
NC
TIO
N O
F R
EM
AIN
ING
50
0k
V B
RE
AK
ER
CO
NF
IGU
RA
TIO
N
Diablo - Midway #2 or #3 Lines can be anexport Path (Depending on Initial Busconfiguration)
Given the proper initial bus configuration,Either Unit Can be tripped.
DCSPS Trips by the Unit Selector Switch, (ifMW and VOLTAGE supervision is satisfied),AND only if CB’s 632, 642, are closed. (732and 742 Position is not relevant)
N
N
N
N
N
N
N
E
N
N
N
00 01 11 10
00
01
11
10
632 532
642 542
EE E
U1
U2
N
N
N
N
N
N
N
N
N
N
00 01 11 10
00
01
11
10
622 532
642 542
U1
U1
N N U1 U1
N
N
N
N
N
N
N
N
N
N
00 01 11 10
00
01
11
10
622 532
632 542
U2
U2
N NU2 U2
Diablo - Midway #2 or #3 Lines can be anexport Path (Depending on Initial Busconfiguration)
Given the proper initial bus configuration,Either Unit can be tripped (Provided the MWand VOLTAGE supervision are satisfied):
DCSPS Trips by the Unit Selector Switch, IfCB 632 and CB 642 are closed. (CB 532 and542 position status is not relevant)
DCSPS Trips UNIT #1, If CB’s 532, 542, and642 are closed AND 632 is opened.
DCSPS Trips UNIT #2, If CB’s 532, 542, and632 are closed AND 642 is opened.
NO
TE
S
Diablo - Midway #2 or Diablo - Gates Linescan be an export Path (Depending on InitialBus configuration)
Given the proper initial bus configuration,Only Unit 1 will be tripped.
DCSPS Trips UNIT #1 For (3) Conditions(Provided the MW and VOLTAGEsupervision are satisfied):
If CB’s 532, 542, and 642 are closed (CB 622position status is not relevant).
If CB’s 622, 642, and 532 are closed (CB 542position status is not relevant).
If CB’s 532, 542, and 622 are closed (CB 642position status is not relevant).
DCPP_DCSPS 10-2005
Dpe4
1: CB is Closed at the time of Initiating Event (t0) 0: CB is Opened at the time of Initiating Event (t
0)
Diablo SPS will only trip if it results in a benefit. (Removal of one of two units that remain tied to the system after the initiating event.
U1: Unit #1 Tripped U2: Unit #2 Tripped E: Either - Unit Tripped based on Unit Selector Sw
Diablo - Midway #3 or Diablo - Gates Linescan be an export Path (Depending on InitialBus configuration)
Given the proper initial bus configuration,Only Unit 2 will be tripped.
DCSPS Trips UNIT #2 For (3) Conditions(Provided the MW and VOLTAGEsupervision are satisfied):
If CB’s 532, 542, and 632 are closed (CB 622position status is not relevant).
If CB’s 622, 632, and 542 are closed (CB 532position status is not relevant).
If CB’s 532, 542, and 622 are closed (CB 632position status is not relevant).
Appendix E: Unit Tripping Determination and Karnaugh Maps
DCSPS Operational Handbook Page 13-4 Rev Date/Time: 1/7/2019 4:31:00 PM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
AND
CB 632 CLOSED
CB 642 CLOSED
ANDCB 622 Fail
UNIT TRIP BY UNITSELECTOR
AND
CB 542 CLOSED
AND
CB 632 CLOSED
CB 642 CLOSED
TRIP LOGIC DCSPS Event - 3x (SEE STATE TRANSITION DIAGRAMS)
Physical Topology ofthe 500kV Bus
(From Karnaugh Map)
PhysicalTopology of
the 500kV Bus (From
KarnaughMap)
DCSPS EVE-3A
CB 642 CLOSED
AND
CB 542 CLOSED
CB 632 CLOSED
AND
CB 632 OPENED
CB 642 OPENED
CB 532 CLOSED
CB 532 CLOSEDAND
UNIT TRIP BY UNITSELECTOR
UNIT #1 TRIP
ANDUNIT #2 TRIP
CB 722 FailDCSPS EVE-3B
OR
AND
CB 532 CLOSED
CB 542 CLOSED
CB 642 CLOSED
AND
CB 532 CLOSED
CB 542 CLOSED
CB 622 CLOSED
AND
CB 532 CLOSED
CB 622 CLOSED
CB 642 CLOSED
ANDCB 732 Fail
UNIT #1 TRIP
DCSPS EVE-3E
PhysicalTopology of
the 500kV Bus (From
KarnaughMap)
OR
AND
CB 532 CLOSED
CB 542 CLOSED
CB 632 CLOSED
AND
CB 532 CLOSED
CB 542 CLOSED
CB 622 CLOSED
AND
CB 542 CLOSED
CB 622 CLOSED
CB 632 CLOSED
ANDCB 742 Fail
UNIT #2 TRIP
DCSPS EVE-3H
PhysicalTopology of
the 500kV Bus (From
KarnaughMap)
DCPP_DCSPS 12-2005
Dpe4