Rev. DGS 1630 004 0 Page 1 of 21 ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS) DESIGN GENERAL SPECIFICATION INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS) 5 4 3 2 1 0 27/05/01 S. AZIZA R. SUNDAR ABDUL AZIZ AL AMERI ISSUED FOR IMPLEMENTATION A 10/11/99 A. ABDEL RAHMAN R. SUNDAR MOHAMMED A. SAHOO Issued for comments Rev Date DD/MM/YY WRITTEN BY CHECKED BY APPROVED BY STATUS DOCUMENT REVISIONS Sections changed in last revision are identified by a vertical line in the left margin

Upload: sujit-pande

Post on 09-Dec-2015

8 views

Category:

Documents


1 download

DESCRIPTION

d

TRANSCRIPT

Page 1: DGS-1630-00x

Rev.

DGS 1630 004 0

Page 1 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

DESIGN GENERAL SPECIFICATION

INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

5

4

3

2

1

0 27/05/01 S. AZIZA R. SUNDAR ABDUL AZIZ AL AMERI ISSUED FOR IMPLEMENTATION

A 10/11/99 A. ABDEL RAHMAN R. SUNDAR MOHAMMED A. SAHOO Issued for comments

Rev Date DD/MM/YY

WRITTEN BY

CHECKED BY

APPROVED BY

STATUS

DOCUMENT REVISIONS

Sections changed in last revision are identified by a vertical line in the left margin

Page 2: DGS-1630-00x

Rev.

DGS 1630 004 0

Page 2 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

CONTENTS

1. GENERAL ................................................................................................................................................................4

1.1 INTRODUCTION ......................................................................................................................................................4 1.2 PURPOSE..............................................................................................................................................................4 1.3 DEFINITIONS..........................................................................................................................................................4 1.4 TERMINOLOGY.......................................................................................................................................................4 1.5 ABBREVIATIONS.....................................................................................................................................................5 1.6 SCOPE OF SUPPLY.................................................................................................................................................5

2. CODES AND STANDARDS ....................................................................................................................................6

3. REFERENCE DOCUMENTS ...................................................................................................................................6

4. DOCUMENT PRECEDENCE...................................................................................................................................6

5. SPECIFICATION DEVIATION/CONCESSION CONTROL.....................................................................................7

6. QUALITY ASSURANCE/QUALITY CONTROL ......................................................................................................7

7. DOCUMENTATION..................................................................................................................................................8

8. SUBCONTRACTORS/SUBVENDORS ...................................................................................................................8

9. HANDLING...............................................................................................................................................................8

9.1 PACKAGING AND SHIPPING .....................................................................................................................................8 9.2 PRESERVATION AND STORAGE ...............................................................................................................................9

10. BASIC REQUIREMENTS ......................................................................................................................................9

10.1 BASIS OF DESIGN.................................................................................................................................................9 10.2 SERVICE CONDITIONS ..........................................................................................................................................9 10.3 MAIN POWER SUPPLY...........................................................................................................................................9 10.4 INFORMATION TO BE SUBMITTED WITH THE TENDER................................................................................................9

11. FUNCTIONAL REQUIREMENTS ........................................................................................................................10

11.1 GENERAL ..........................................................................................................................................................10 11.2 MOTOR PROTECTION .........................................................................................................................................10 11.3 MOTOR CONTROL ..............................................................................................................................................10 11.4 AUTOMATIC MOTOR RESTART .............................................................................................................................11 11.5 INDICATION AND ALARM......................................................................................................................................12 11.6 MEASUREMENTS AND RECORDINGS ....................................................................................................................12 11.7 SWITCHGEAR MONITORING AND CONTROL (DELETED) .............................................................................................. 11.8 EMERGENCY SHUTDOWN (SAFETY SYSTEM) INTERFACE .......................................................................................12 11.9 CONFIGURING AND COMMUNICATION...................................................................................................................12 11.10 TEST FACILITIES ..............................................................................................................................................14

12. PERFORMANCE REQUIREMENTS ...................................................................................................................14

Page 3: DGS-1630-00x

Rev.

DGS 1630 004 0

Page 3 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

12.1 RESPONSE TIME ................................................................................................................................................14 12.2 ELECTRICAL ENVIRONMENT IMMUNITY.................................................................................................................14 12.3 DISTURBANCE IMMUNITY ....................................................................................................................................14 12.4 ENVIRONMENTAL WITHSTAND .............................................................................................................................15 12.5 COMMUNICATION INTEGRITY...............................................................................................................................15

13. CONSTRUCTIONAL REQUIREMENTS..............................................................................................................15

13.1 UNIT ENCLOSURE ..............................................................................................................................................15 13.2 SYSTEM COMPONENTS.......................................................................................................................................15 13.3 WITHDRAWABLE TYPE MOTOR STARTERS ............................................................................................................15 13.4 RUNNING AND STANDBY DRIVES..........................................................................................................................16 13.5 POWER SUPPLY.................................................................................................................................................16 13.6 CURRENT AND VOLTAGE TRANSFORMERS ...........................................................................................................16 13.7 WIRING AND TERMINATIONS ...............................................................................................................................16 13.8 MARKING ..........................................................................................................................................................17 13.9 EARTHING ARRANGEMENT..................................................................................................................................17 13.10 ENGINEERING PC STATIONS..............................................................................................................................17 13.11 CAPACITY CENTRAL UNIT..................................................................................................................................17 13.12 NAMEPLATE ....................................................................................................................................................17

14. INSPECTION AND TESTS ..................................................................................................................................17

14.1 GENERAL ..........................................................................................................................................................17 14.2 PERFORMANCE TESTS .......................................................................................................................................18

APPENDIX 1 - SIMPLIFIED BLOCK DIAGRAM INTEGRATED PROTECTION & CONTROL SYSTEM ...........................................19 APPENDIX 2 - TYPICAL IPCS SCHEDULE ...............................................................................................................20,21

Page 4: DGS-1630-00x

Rev.

DGS 1630 004 0

Page 4 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

1. GENERAL

1.1 Introduction

This specification covers the minimum technical requirements for a micro-processor based Integrated Protection and Control System (IPCS) incorporated into a LV and HV switchgear for protection, control and monitoring of motors.

A simplified block diagrams of IPCS is given in Appendix 1.

1.2 Purpose

The basic purpose of the IPCS is the integration of Motor Controlgear Assemblies with Process Control Systems utilizing micro processor based protection and control devices installed in electrical equipment, connected to the DCS or SCADA system, via an Interface Control Unit utilizing serial communications.

Specific requirements will be given in the schedule for IPCS’s as part of the switchgear requisition. This schedule should be used in conjunction with the requisition data sheets for LV and HV controlgear.

1.3 Definitions

For the purposes of this specification, the following definitions shall hold:

COMPANY - ABU DHABI GAS INDUSTRIES LTD. (GASCO).

CONCESSION REQUEST - A deviation requested by the SUBCONTRACTOR or VENDOR, usually after receiving the contract package or purchase order. Often, it refers to an authorization to use, repair, recondition, reclaim, or release materials, components or equipment already in progress or completely manufactured but which does not meet or comply with COMPANY requirements. A CONCESSION REQUEST is subject to COMPANY approval.

CONTRACTOR - The party which carries out all or part of the design engineering, procurement, construction and commissioning or management of the project.

MANUFACTURER/VENDOR - The party which manufactures and/or supplies equipment, technical documents/drawings and services to perform the duties specified by COMPANY/CONTRACTOR.

PROJECT - (To be defined)

SHALL - Indicates a mandatory requirement.

SUBCONTRACTOR/SUBVENDOR - The party(s) which carry(s) out all or part of the design, procurement, installation and testing of the System(s) as specified by the CONTRACTOR/VENDOR.

1.4 Terminology

The following terms and interpretations shall apply for the purpose of this specification:

♦ Control Module - CM Control Module is a microprocessor based device with integrated control, monitoring and protection functions and communication facility serving a motor starter.

♦ Interface Control Unit - ICU An ICU is a microprocessor based interface device used to monitor and control a number of Control Modules via a serial bus and enabling communication with a higher level of control.

♦ Integrated Protection Control System - IPCS

Page 5: DGS-1630-00x

Rev.

DGS 1630 004 0

Page 5 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

A system comprising Control Modules, Interface Control Units, a serial bus connecting the Control Modules to the Central Unit and a serial communication facility enabling connection of Central Unit to a Distributed Control System (DCS).

♦ Expected Lifetime The expected lifetime of a Motor Control System is the time during which it remains suitable for the application for which it was made, provided it is used and maintained in accordance with the MANUFACTURER’S instructions.

♦ Operating Time Total time elapsed after initial commissioning and start-up of the IPCS at site but excluding the first three months of initial operation.

♦ Certificate of Conformity A certificate stating that the electrical apparatus complies with the relevant standards for apparatus for potentially explosive atmosphere.

♦ Mean Time Between Failure - MTBF MTBF represents the expected value of the duration at trouble-free operation (only applicable for repairable components) and is calculated as follows: Operating time (hours)

Number of faults resulting in outage

1.5 Abbreviations

CCR Central Control Room CRT Cathode Ray Tube DCS Distributed Control System ICU Interface Control Unit IPCS Integrated Protection and Control System PC Personal Computer MCS Motor Control Station RCU Remote Control Unit RTU Remote Terminal Unit (Transmission mode) SGS Safe Guarding System IES Instrument Equipment Shelter EWS Engineering Work Station

1.6 Scope of supply

The scope of supply of an IPCS shall include all design activities, supply of materials, factory acceptance tests and provision of documentations and instructions as stated in this specification.

The scope of material supply includes all IPCS components shown in Appendix 1 up to and including the Interface Control Unit. The interconnecting cables with DCS do not form part of the scope of supply.

Micro-processor based motor protection relays will be provided and installed within switchgear and MCCs by others.

The scope of supply also includes start-up assistance and, if specified, site installation. The MANUFACTURER shall indicate in his tender his capabilities for carrying out site installation work.

Equipment manufacturing record books, equipment record (data) books and operating and maintenance manuals are required. Immediately prior to contract award the MANUFACTURER shall give a technical presentation to COMPANY personnel

Page 6: DGS-1630-00x

Rev.

DGS 1630 004 0

Page 6 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

1.6.1 Responsibility

The Purchase Order for the IPCS shall be placed direct with a control system MANUFACTURER.

The MANUFACTURER of the IPCS shall be responsible for its performance as described in this specification and shall liaise with the switchgear/MCC and DCS MANUFACTURER’s for procedures, execution of interface and testing. Equipment MANUFACTURERS must be approved by the COMPANY.

2. CODES AND STANDARDS

The following codes and standards, to the extent specified herein, form a part of this specification. When an edition date is not indicated for a code or standard, the latest edition in force at the time of MANUFACTURER’S proposal submittal shall apply:

International Electrotechnical Commission (IEC): IEC 60060 High voltage test techniques IEC 60068 Environmental Testing IEC 60146 Semiconductor Convertors IEC 60158 Low Voltage Controlgear IEC 60255 Electrical Relays IEC 60391 Marking of insulated conductors IEC 60445 Identification of equipment terminals IEC 60446 Identification of conductors by colors or numbers IEC 60529 Degrees of protection provided by enclosures (IP code) IEC 60801 Electromagnetic compatibility for industrial process measurement and

control equipment IEC 60947 Low Voltage Switchgear and Controlgear EN 50019 European Standard for Increased Safety (EN)

3. REFERENCE DOCUMENTS

The following reference documents, to the extent specified herein, form a part of this specification. When an edition date is not indicated for a document, the latest edition in force at the time of MANUFACTURER’S proposal submittal shall apply:

DGS 1630 022 High Voltage Switchgear and Control Gear

DGS 1630 023 Low Voltage Switchgear and Control Gear

DGS 0000 004 Criticality Rating System

4. DOCUMENT PRECEDENCE

It shall be the MANUFACTURER’S responsibility to be, or to become, knowledgeable of the requirements of the referenced Codes and Standards.

The MANUFACTURER shall notify the CONTRACTOR of any apparent conflict between this specification, the related data sheets, the Codes and Standards and any other specifications noted herein. Resolution and/or interpretation precedence shall be obtained from the CONTRACTOR in writing before proceeding with the design/manufacture.

In case of conflict, the order of precedence shall be:

Page 7: DGS-1630-00x

Rev.

DGS 1630 004 0

Page 7 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

♦ System block diagrams ♦ Equipment Data Sheet(s) ♦ This Specification ♦ Design General Specifications and Standards ♦ Industry Codes and Standards

5. SPECIFICATION DEVIATION/CONCESSION CONTROL

Deviations from this specification are only acceptable where the MANUFACTURER has listed in his quotation the requirements he cannot, or does not wish to comply with, and the COMPANY/CONTRACTOR has accepted in writing the deviations before the order is placed.

In the absence of a list of deviations, it will be assumed that the MANUFACTURER complies fully with this specification.

Any technical deviations to the Purchase Order and its attachments including, but not limited to, the Data Sheets and Narrative Specifications shall be sought by the MANUFACTURER only through CONCESSION REQUEST format. CONCESSION REQUESTS require CONTRACTOR'S and COMPANY'S review/ approval, prior to the proposed technical changes being implemented. Technical changes implemented prior to COMPANY approval are subject to rejection.

6. QUALITY ASSURANCE/QUALITY CONTROL

The MANUFACTURER shall have in effect at all times, a QA/QC program which clearly establishes the authority and responsibility of those responsible for the quality system. Persons performing quality functions shall have sufficient and well defined authority to enforce quality requirements, initiate, identify, recommend and provide solutions to quality problems and verify the effectiveness of the corrective action.

A copy of the MANUFACTURER’S QA/QC program shall be submitted to the CONTRACTOR with its quotation for CONTRACTOR'S review and concurrence prior to award. If MANUFACTURER’S QA/QC program and facility, where the work is to be performed, is ISO 9000 certified, then only a copy of the MANUFACTURER’S ISO 9000 certificate is required. In addition, if MANUFACTURER’S facility is ISO certified, CONTRACTOR'S QA audit requirements will be waived in favor of ISO 9000 registrar audits, unless the CONTRACTOR'S trend analysis program indicates areas of concern.

The MANUFACTURER shall identify in purchase documents to its SUBVENDORS all applicable QA/QC requirements imposed by the CONTRACTOR, and shall ensure compliance thereto. On request, MANUFACTURER shall provide objective evidence of its QA/QC surveillance of its SUBVENDORS activities.

The MANUFACTURER shall submit certified reports of production tests as soon as the tests are completed satisfactorily.

The COMPANY/CONTRACTOR reserves the right to inspect materials and workmanship at all stages of manufacture and to witness any or all tests. The MANUFACTURER, 30 days after award but prior to the pre-inspection meeting, shall provide the CONTRACTOR with a copy of its Manufacturing and Inspection Plan for review and inclusion of any mandatory COMPANY/CONTRACTOR witness points.

The Criticality Rating (CR) System outlined in Design General Specification DGS 0000 004 shall be used to develop the design checking levels and minimum requirements for shop inspection, testing and materials certification.

Page 8: DGS-1630-00x

Rev.

DGS 1630 004 0

Page 8 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

7. DOCUMENTATION

The MANUFACTURER shall provide, in accordance with the purchase order requirements, the minimum following documents:

♦ General arrangement drawings

♦ Schematic diagrams

♦ Programming (logic) diagrams

♦ Equipment lists

♦ Recommended spare parts lists

♦ Test reports

♦ Operating manuals incorporating installation, commissioning, operating and maintenance instructions, and fault finding procedures.

♦ Self-documenting facilities of the IPCS shall be demonstrated by the MANUFACTURER.

♦ System software package.

8. SUBCONTRACTORS/SUBVENDORS

The MANUFACTURER shall assume unit responsibility and overall guarantee for the equipment package and associated equipment.

The MANUFACTURER shall transmit all relevant purchase order documents including specifications to his SUBVENDORS and SUBCONTRACTORS.

It is the MANUFACTURER'S responsibility to enforce all Purchase Order and Specification requirements on his SUBVENDORS and SUBCONTRACTORS.

The MANUFACTURER shall submit all relevant SUBVENDOR and SUBCONTRACTOR drawings and engineering data to the CONTRACTOR.

The MANUFACTURER shall obtain and transmit all SUBVENDOR and SUBCONTRACTOR'S warranties to the CONTRACTOR/COMPANY, in addition to the system warranty.

9. HANDLING

9.1 Packaging and shipping

Preparation for shipment shall be in accordance with the MANUFACTURER'S standards and as noted herein. MANUFACTURER shall be solely responsible for the adequacy of the preparation for shipment provisions with respect to materials and application, and to provide equipment at the destination in ex-works condition when handled by commercial carriers.

Adequate protection shall be provided to prevent mechanical damage and atmospheric corrosion in transit and at the job site.

Preparation for shipment and packing will be subject to inspection and rejection by COMPANY'S/CONTRACTOR'S inspectors. All costs occasioned by such rejection shall be to the account of the Vendor.

Separate, loose, and spare parts shall be completely boxed. Pieces of equipment and spare parts shall be identified by item number and service and marked with CONTRACTOR’S order number, tag number, and weight, both inside and outside of each individual package or container. A bill of material shall be enclosed in each package or container of parts.

Page 9: DGS-1630-00x

Rev.

DGS 1630 004 0

Page 9 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

One complete set of the installation, operation, and maintenance instructions shall be packed in the boxes or crates with equipment. This is in addition to the number called for in the Purchase Order.

9.2 Preservation and storage

Equipment and materials shall be protected to withstand ocean transit and extended period of storage at the jobsite for a minimum period of 18 months. Equipment shall be protected to safeguard against all adverse environments, such as: humidity, moisture, rain, dust, dirt, sand, mud, salt air, salt spray, and sea water.

10. BASIC REQUIREMENTS

10.1 Basis of design

The design of the IPCS shall be such as to minimize the risk of short circuits and shall ensure personnel and operational safety at all times.

The design and selection of equipment and components shall be based on achieving a minimum expected lifetime of 30 years. The IPCS including all individual components forming part of the system shall have a MTBF of not less than 60,000 hours - based on the conditions stated in (10.2) and (10.3).

All components shall be of a quality and reliability commensurate with the requirement to perform protection, control, monitoring and safeguarding functions on motor starters in continuously operating petrochemical process units, production facilities and utility installations.

The MANUFACTURER shall guarantee that the spare parts for the original equipment will remain available for the duration of the equipment expected lifetime.

10.2 Service conditions

Unless otherwise specified, the IPCS shall be installed in controlgear assemblies, located in a substation in which the following conditions apply:

♦ Maximum ambient air temperature: 40°C

♦ Relative humidity not exceeding: 60%

♦ Altitude not exceeding: 1000 m

10.3 Main power supply

For main power supplies and their variations during normal and transient conditions refer to respective switchgear specifications.

10.4 Information to be submitted with the tender

The MANUFACTURER shall submit a technical specification of the IPCS which shall include a description of the design, operation, construction, performance and maintenance aspects of the equipment.

The MANUFACTURER shall verify in the tender that the equipment fully complies with this specification. Any deviations from this specification shall be highlighted and the technical consequences shall be noted. The MANUFACTURER shall state in the tender the country of origin of the main components of the system. For maintenance and trouble shooting at site, the MANUFACTURER shall indicate the nearest service organization recommended for the location where the equipment will be installed.

10.5 Time Synchronization

Page 10: DGS-1630-00x

Rev.

DGS 1630 004 0

Page

10 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

CONTRACTOR shall design/engineer and supply a Global Positional System (GPS) at different Sub-stations to suit Project requirements. The IPCS shall be provided with a means of accepting external time synchronization input. The IPCS vendor shall design his system(s) to accommodate this arrangement.

10.6 The IPCS System shall be seamlessly integrated with the existing system in order to form one overall IPCS System.

11. FUNCTIONAL REQUIREMENTS

11.1 General

The primary purpose of the IPCS is to provide, by means of microprocessor based technology monitoring, control and protection functions for the Circuit breaker and Contactor controlled motor starters These functions shall provide data communication facilities with the DCS. An EWS shall be provided in the office of Electrical Section Head with data communication link to the IPCS.

The required I/Os will be listed on data sheets attached to the material requisitions.

The IPCS shall “communicate” with microprocessor based motor, protection relays to permit status to be monitored remotely.

11.2 Motor protection

Motor protection shall be provided by each individual motor starter Control Module. Its operation shall be completely independent of other Control Modules and/or ICU.

The protection functions as described in DGS 1630 022 and DGS 1630 023 for thermal overload, phase current unbalance, and earth fault protection shall be provided. The motor protection relay for LV motors shall be Motor Manager III (latest version) . Refer to section 11.5 for visual verification of alarm status and protection functions. .

The motor thermal overload protection shall simulate the motor cold and hot thermal capacity, the heating and cooling thermal time constants, and shall provide protection against overload, repeated starts and stalling.

This shall be achieved by creating a thermal replica of the motor requiring the input of data to represent the thermal characteristics of the specific motor. The protection shall incorporate a memory to take into account the thermal history of the motor before the overload occurs.

The thermal capacity utilized in accelerating the motor from standstill to rated speed shall be memorized. After an overload trip, the restart of the motor shall be inhibited during a cool down period which shall be only as long as required to recover sufficient thermal capacity as to ensure one successful start of the motor without tripping of the overload protection. Indication of the remaining time duration before a start becoming possible shall be indicated, i.e. "Restart Inhibit Time" message.

An adjustable overload pre-alarm shall be provided. This should be accompanied by an indication of the remaining duration before a trip will occur.

11.3 Motor control

Control Functions are required at the following locations:

Local Local control is meant to be from a position close to the motor. This is done via at least one Motor Control Station (MCS) by means of which the motors shall be able to be started and stopped

Page 11: DGS-1630-00x

Rev.

DGS 1630 004 0

Page

11 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

manually. The MCS may have hand/auto or local/remote position in which remote automatic control is allowed. For contactor controlled motor starters the "off" position of the MCS can be padlocked and should be regarded as a safety switch. In this position the MCS should be hardwired switched into the motor starter contactor circuit. Switching the motor "on" by means of the MCS shall be inhibited by the remote "off" controls.

Remote

Remote control is meant to be automatic process control from the process DCS, ESD or other Control System. This type of control, if required for plant operation, shall be applied in addition to the local control described above. Automatic process control may consist of:

a) “ON” and “OFF” controls for non-critical applications which shall be serially wired into the IPCS.

b) Safeguarding, sequence and interlock control signals which shall be hardwired into the motor starter circuit, overriding any other command issued from the CM or from the MCS.

Any other status input from IPCS for sequence, interlock, safeguarding shall be hardwired to DCS, ESD or other Control System through Remote I/O cabinet (RIC).

NOTE: No “ON” or “OFF” control shall be possible from the motor starter CM (s) nor from the ICU, during normal plant operating conditions.

11.4 Automatic motor restart

An automatic restart facility shall be provided to automatically restart the motor after voltage dips of limited durations. The restart facilities shall be provided on the individual motor starter Control Module.

The automatic restart facility shall be initiated under the following conditions:

♦ Voltage dip detection level 65% Un; voltage restoration detection level 90% Un; memory 4.5 s

♦ Immediate restart after voltage dips < 0.2 s

♦ Delayed restart after voltage dips of > 0.2 to < 4.5 s

♦ Running of the delayed restart timer only if voltage >90% Un.

♦ Delayed restart range 0.1 – 300 sec (typical)

Where process auto-restart is specified, the following functions shall be provided instead of the above:

♦ Voltage dip detection level 65% Un; voltage restoration detection level 90% Un

♦ Immediate restart after voltage dips < 0.2 s

♦ Delayed restart for voltage dips > 0.2 s, provide process ‘on’ command available

♦ Running of the delayed restart timer only if voltage > 90% Un.

♦ Delayed restart range 0.1 – 300 sec (typical0

Page 12: DGS-1630-00x

Rev.

DGS 1630 004 0

Page

12 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

11.5 Indication and alarm

Motor and breaker as shown on the single line diagram status indication and protection alarms shall be provided in accordance with the IPCS schedule. Those functions should be made available both at the motor starter and remotely i.e. to the ‘process’ DCS system via the ICU.

The status of the alarm and protection functions shall be visually verifiable, at the individual Control Modules and/or ICU, by appropriate indicators with first failure feature. Alarms associated with trip functions shall be hand-reset, except for the thermal overload trip which shall have an automatic reset function.

A watchdog alarm, as result of a component defect in a Control Module or in the ICU, or a communication failure alarm shall not, on their own, result in the trip of any motor starter.

11.6 Measurements and recordings

A number of motor circuit and operational data shall be monitored and indicated in accordance with the IPCS schedule.

The Control Module shall have either a 4-20 mA output to connect the RCU ammeter or a dedicated 1A secondary current transformer. Additionally, this data shall be transmitted to the ICU where the DCS can access the data for display.

Recording of events and trending of current shall be provided on a number of selected motors as per IPCS schedule. Current trending shall be triggered (adjustable) by an overload condition and comprise of pre- and post-event trending. Recording facilities shall be provided at the ICU.

The following trend facilities shall be provided:

♦ A trend for motor current with a span period of no less than 30 minutes, and sampling frequency of at least once per second with a minimum of 10 minutes pre-event trending;

♦ Provisions to configure other trends, e.g. busbar voltage for electrical system dynamic assessments.

11.7 Switchgear Monitoring and Control

A number of power circuit operational data shall be monitored and indicated in accordance with IPCS schedule. In general, system data such as Voltage (V), Current (A) and Power Factor (PF) shall be communicated to DCS and Engineering Work Station (EWS)-PC. Status of switchgear breakers and UPS units also will be accessible to DCS and EWS.

IPCS shall also provide CRT monitoring of HV and LV distribution accessible from EWS and DCS. The control circuits shall be capable of being configured to accept the modes of control detailed in the requisition. Unless specified otherwise it shall not be possible to close or trip any incoming bus section or feeder breaker from DCS or EWS. However, the above control and monitoring function is not required if the same is achieved by another system such as Load Management System (LMS).

11.8 Emergency shutdown (safety system) interface

Each CM shall include an inherent Emergency Shutdown (ESD) relay with a changeover contact connected in series with the CM output relay to provide interface facilities to the ESD system.

11.9 Configuring and communication

11.9.1 Configuring

The configuration of the IPCS and its interface with the DCS shall be made in accordance with the requirements stated on the IPCS schedules.

Page 13: DGS-1630-00x

Rev.

DGS 1630 004 0

Page

13 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

One ICU shall be provided in each substation unless otherwise specified in the requisition. The ICU shall be fully redundant including power supplies, processors, communication modules to the DCS.

The IPCS shall be configured via a system with access restrictions of keylock and password protection.

Configuring of the Control Module shall be possible from the Control Module or from the ICU. The configuration of the ICU and its facilities to enable communication with the DCS shall be possible from the ICU or via an engineering work station PC. The method shall be user friendly e.g. menu driven.

In case of replacement of a defective motor starter Control Module the spare Control Module shall be down loaded from the ICU with the relevant configuration after a simple initiation instruction. It shall be possible to replace faulty CM's without disrupting communication/control with other CM's connected to the ICU.

In the view mode, it shall be possible to monitor running data from the Control Module or ICU in the substation.

In the engineering mode (protected by keylock or password), it shall be possible to adjust configurations, control and protection system parameters, states and settings (in engineering units).

11.9.2 Communication Facilities

The following levels of communication are identified in the application of the IPCS (Appendix 1):

LEVEL 1, Motor starter Level

This comprises of the Control Module mounted on the motor starter.

At level 1 the collection of data from the motor circuit takes place as well as the protection and control of the motor. This level shall continue to operate during short voltage interruptions caused by transients during system faults as described in (10.3). Current detection systems should be able to cope with the thermal effects of short circuit current. Failure of a Control Module should initiate the internal watchdog alarm transmitted via the ICU to the CCR.

All level 1 data and messages shall be communicated to the ICU, by means of a redundant serial communication bus.

LEVEL 2, Substation Level

This comprises of an ICU which shall be redundant and its communication link to the protective devices as well as its serial communication facilities to a DCS, as shown in Appendix I.

The ICU shall be provided with a facility to connect a PC. This PC shall be used as an EWS-PC to allow the ‘engineer’ access to all available information from individual Control Modules, both ‘on’ and ‘off’ line. In addition a facility for connection of a printer shall be provided to print hard copy event logs and/or trends.

The communication between the motor starter Control Modules and the ICU may utilize MANUFACTURER’S standard serial links and protocol, however it shall at least be provided with a high level of security check (simple parity check is not acceptable).

In case of a communication failure between level 1 and 2, the motor starter Control Module shall continue operation as a stand-alone unit and not result in the trip of the motor starter.

Failure of the ICU or of the serial link to the motor starter Control Modules shall initiate operator alarms transmitted to the CCR via the DCS.

LEVEL 3, IES/CCR Level

Page 14: DGS-1630-00x

Rev.

DGS 1630 004 0

Page

14 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

The data and type of messages which shall be communicated to DCS are shown in the IPCS schedule attached to Requisition.

This comprises the communication interface between the ICU and the DCS.

The ICU shall be able to interface with the DCS via a fully redundant communication module. The preferred interface is direct node coupling of the ICU to the DCS data highway by means of chassis mounted communication modules capable of supporting ICU protocols and DCS highway protocol.

Each substation ICU shall be configured such that only signals for START, STOP and motor status are ‘read’ by the DCS

11.10 Test facilities

Facilities to allow function testing of the IPCS Control Modules, without having to run motors shall be provided.

This facility shall include provisions to test the motor starter Control Modules from the MCS and also to be able to test the automatic restart function.

Where a higher level of control (DCS) is installed, the complete loop test from the DCS to the motor starter Control Module should also be possible.

12. PERFORMANCE REQUIREMENTS

12.1 Response time

The response time for a control action to be executed in the motor starters from receipt of command from the DCS by the ICU should not exceed 0.5 second.

NOTE: Neither the motor automatic restart nor motor protection classify under this definition as the time response for these are governed by other, normally faster, criteria.

12.2 Electrical environment immunity

The IPCS shall be immune to voltage and frequency fluctuations within the limits given (10.3).

The IPCS shall be able to withstand the following tests in accordance with IEC 60255-5:

♦ High voltage test

♦ Impulse voltage withstand test

♦ Insulation resistance

Temporary loss of control power supply shall not result in the loss of application software data nor loss of dynamic data relevant to the operation of protection systems, e.g. available thermal capacity of motors (up to 30 seconds), and the operation of automatic motor restart. On restoration of power supply the system should be able to automatically resume normal operation. Battery back-up of individual Control Modules is not allowed.

12.3 Disturbance immunity

The IPCS shall be able to withstand the following electromagnetic compatibility test requirements:

♦ General performance requirements: In accordance with IEC 60255-6, Class 3.

♦ Surge withstand capability test: In accordance with IEC 60255-4

♦ Burst disturbance test: In accordance with IEC 60255-22-1

♦ Electrostatic discharge test: In accordance with IEC 60255-22-2

Page 15: DGS-1630-00x

Rev.

DGS 1630 004 0

Page

15 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

♦ Radiated electromagnetic field disturbance test: In accordance with IEC 60255-22-3

♦ Dielectric impulse test: In accordance with IEC 60060

♦ Immunity to external interference: In accordance with IEC 60801 Parts 1, 2, 3, 4, 5.

12.4 Environmental withstand

The IPCS shall be able to withstand:

The temperature ranges in service, during transport, and storage: in accordance with IEC 60068-2-1/2.

The damp heat cyclic test: in accordance with IEC 60068-2-30

Mechanical vibration stress test: in accordance with IEC 60255-21-1/2.

12.5 Communication integrity

The communication interface bus between ICU and Control Modules shall be able to withstand the fast transient disturbance test in accordance with IEC 60801-4 Class 3. It shall also be short circuit protected.

Reliability of the communication bus shall be monitored in terms of overruns, quality (i.e. framing, parity, and checksum errors), and response time-outs.

Failure of communication bus shall alarm to the CCR via the ICU but shall maintain the current state of devices.

13. CONSTRUCTIONAL REQUIREMENTS

13.1 Unit enclosure

The Control Module enclosure shall provide a degree of protection of not less than IP 41 in accordance with IEC 60529.

If the ICU enclosure is mounted on the switchgear / controlgear enclosure, or Motor starter, then IP 41 enclosure protection shall be applicable. The floor shall not be considered as forming part of the enclosure. If the ICU is mounted separately then IP 31 enclosure protection shall be applicable.

13.2 System components

Operating, status and diagnostic indications by means of Light Emitting Diodes (LED’s) or Liquid Crystal Displays (LCD’s) shall be used.

Programming by permanently installed key pads, a portable programmer or ‘engineering PC station’ is allowed.

Where required Printed Circuit Boards (PCB’s) shall be installed in standardized electronic equipment frames and be fitted with handgrips for easy removal. PCB’s shall include visual LED status indications and test connections on the front to facilitate fault diagnosis.

13.3 Withdrawable type motor starters

The serial bus in the motor starters between the starter Control Modules and the ICU shall be arranged such that it is possible to withdraw the motor starters with their Control Module without consequences for the remaining Control Modules connected to the serial bus.

Page 16: DGS-1630-00x

Rev.

DGS 1630 004 0

Page

16 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

13.4 Running and standby drives

To improve the availability of running and standby drives it is strongly preferred that these drives are connected to different serial links in the motor starters. These are normally distributed on the switchboard sections as indicated on the requisition. The aim being that failure of one link shall have no consequence for the availability of the standby drive.

13.5 Power supply

13.5.1 Control Modules

The power supply to the individual Control Modules shall be derived as follows :

HV and LV Switchgears and HV Motors : 110 Vdc (Switchgear Control Supply)

LV Motors : 240 Vac (Starter Control Supply)

The MANUFACTURER shall take into account that the supply to the Control Module will therefore be lost when the motor starter is isolated. A centralized power supply system with a distribution system for all Control Modules is not acceptable.

13.5.2 Interface Control Units

A power supply unit shall be provided for the ICU. The power supply shall comprise dual redundant power supply units with automatic change over facilities and remote alarm in case of failure of one. Power supply for the ICU shall be obtained from safe AC supplies or from substation 110 V DC from the DC UPS, as required.

13.6 Current and voltage transformers

Current and voltage transformers required for the functioning of the IPCS shall comply with the requirements of DGS 1630 022 and DGS 1630 023.

13.7 Wiring and terminations

13.7.1 Hardwiring and Terminals

Internal wiring, where applicable, shall be PVC or XLPE-insulated and have stranded copper conductors. The size and type of the wires to be selected shall be based on mechanical strength, voltage levels and, especially for current circuits, on the prospective current levels.

The minimum allowable cross-sectional area of the wires shall be 1.5 mm². Current transformer secondary circuits shall be 2.5 mm² minimum. Motor manager III protective relay secondary circuits shall be 1.0 mm2 minimum.

Color coding of secondary wiring shall be in accordance with IEC 60446. Earth wires shall be green/yellow striped. Wiring between two terminals shall be continuous and without joints.

Wiring ends of stranded conductors which have to be connected into bus-type contacts of terminals, shall be provided with compression-type pre-insulated wire pins with insulation support. In general, when lugs, wire pins, etc., are used, they shall be of the compression type.

13.7.2 Serial Wiring

Digital signals can be carried by screened twisted pair cables, coaxial cables or fibre optic cables. The choice is usually dictated by bandwidth and lay-out requirements. Terminating resistors, if required to prevent voltage signal reflections, shall be installed at each end. The method of linking the Control Modules with the ICU should be such as to avoid a common mode of failure.

Page 17: DGS-1630-00x

Rev.

DGS 1630 004 0

Page

17 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

13.8 Marking

All wires shall be identified at both ends by means of ferrules of insulating material, or by plastic code markers.

Marking shall be in accordance with the related MANUFACTURER’S drawings. For marking of conductors, reference is made to IEC 60391.

All external operating, measuring and indicating components shall be clearly identified with permanent descriptive labels that facilitate easy recognition by the operator. All components shall be identifiable by labels inscribed in accordance with the system of identification used on the MANUFACTURER’S drawings.

Rail mounted terminals shall be identifiable by numerical or alphabetical markings in accordance with the MANUFACTURER’S drawing and IEC 60445.

13.9 Earthing arrangement

The IPCS shall be connected to the plant earthing systems.

13.10 Engineering PC stations

The software required for the ‘engineering PC station’ shall run on a stand-alone IBM compatible PC using latest version of WINDOWS.

13.11 Capacity of central unit

In addition to the number of Control Modules specified in the requisition, spare capacity shall be provided in the ICU to cater for additional Control Modules. The spare capacity in the ICU shall comply with the spare requirements as laid down for motor starters/feeders in DGS 1630 022 and DGS 1630 023.

13.12 Nameplate

The nameplate shall be made of corrosion resistant metal and be fixed to a non-removable part of the ICU by means of durable self-threading screws or pop rivets. It shall be provided with indelible inscriptions in the language as specified on the requisition. The following information shall be given on the nameplate:

♦ MANUFACTURER’S name or trademark

♦ Type designation

♦ Purchase order number

♦ Year of manufacture

♦ Rated voltage of aux. Circuit (if applicable) ♦ Degree of protection

14. INSPECTION AND TESTS

14.1 General

Prior to dispatch, the MANUFACTURER shall verify by tests that the operation of the equipment complies with the requirements specified on the requisition, and shall submit to the CONTRACTOR a report incorporating the results of all tests performed.

Page 18: DGS-1630-00x

Rev.

DGS 1630 004 0

Page

18 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

If specified on the requisition, a representative of the COMPANY shall witness the functional factory acceptance tests (14.2) and shall carry out an inspection of the assembled equipment and related documents to verify compliance with the requirements of the purchase order.

14.2 Performance tests

14.2.1 Type Tests

The MANUFACTURER shall submit to the COMPANY for review and approval, the type test result of the electrical, disturbance and environmental immunity test requirements as per (12).

14.2.2 Functional Tests

The IPCS shall undergo a functional test to prove its compliance with the requirements of this specification (11.0).

Testing of the IPCS shall be performed integrally with testing of the switchgear/MCC. The CM's shall all be installed in their respective starters units and connected to the ICU. Using PC, or other devices to emulate the DCS, host commands shall be initiated and connection ascertained at each CM's associated cubicle. Status feedbacks from the CM's shall be read by the simulated host. System response time will be checked. Additionally, full verification of the DCS data table interface of the ICU shall be performed.

The MANUFACTURER shall provide the COMPANY, for his approval, a test procedure on how to carry out those verification tests.

Page 19: DGS-1630-00x

Rev.

DGS 1630 004 0

Page

19 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

LEGEND ER Engineering Room RIC Remote I/O Cabinet DCS Distributed Control System IES Instrument Equipment Shelter CCR Central Control Room IRP Interposing Relay Panel EWS Engineering Work Station CM Control Module PC Personal Computer ICU Interface Control Unit Serial Communication

Hard Wired

NOTES 1 Both Interface Control Units (ICU) & Serial

Communications Links Between ICU & Control Modules shall be redundant.

2. Control through substation interposing relay panel is only for critical motors (e.g. E.S.D or process sequence control)

3. Communication with DCS System shall utilize redundant link.

4. For remote control functions (serial versus narawirea) refer to section 11.3 of this specification

5. EWS-PC (at level 2) shall be suitable for connection with ICU No.1 or ICU No.2

6. For motor control station: - Emergency stop pushbutton shall be hardwired

into contactor circuit. - Start pushbutton shall be hardwired into the CM

-

Page 20: DGS-1630-00x

Rev.

DGS 1630 004 0

Page

20 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)

Page 21: DGS-1630-00x

Rev.

DGS 1630 004 0

Page

21 of 21

ABU DHABI GAS INDUSTRIES LTD. (GASCO) INTEGRATED PROTECTION AND CONTROL SYSTEM (IPCS)