desilanation plant tender

45
SULTANATE OF OMAN RURAL AREAS ELECTRICITY COMPANY (SAOC) TENDER NO. /2009 TENDER DOCUMENT for CONSULTANCY SERVICES for DESIGN & SUPERVISION for CONSTRUCTION OF NEW REVERSE OSMOSIS (RO) DESALINATION PLANT AT TIBAT AREA in MUSANDAM GOVERNORATE NOVEMBER 2009

Upload: rajeshdebnath3647

Post on 18-Nov-2014

850 views

Category:

Documents


3 download

DESCRIPTION

Reverse osmosis sea water plant

TRANSCRIPT

Page 1: Desilanation Plant Tender

SULTANATE OF OMAN

RURAL AREAS ELECTRICITY COMPANY (SAOC)

TENDER NO. /2009

TENDER DOCUMENT

for

CONSULTANCY SERVICES

for

DESIGN & SUPERVISION for

CONSTRUCTION OF NEW REVERSE OSMOSIS (RO)

DESALINATION PLANT AT TIBAT AREA in

MUSANDAM GOVERNORATE

NOVEMBER 2009

Page 2: Desilanation Plant Tender

TABLE OF CONTENTS

PAGE

SECTION 1 INTRODUCTION

1.1 Invitation 1-1

1.2 Objective 1-1

1.3 Description of Work 1-1

1.4 Agreement 1-1

1.5 Non Compliance with Tender 1-1

SECTION 2 INSTRUCTION TO TENDERERS

2.1 General 2-1

2.2 Tender Submission 2-1

2.3 Addenda to Invitation for Tender 2-2

2.4 Site Visits 2-2

2.5 Project Office in Oman 2-2

2.6 Organization of Tender Documents 2-2

2.7 Preference 2-5

2.8 Prime offer and Alternative offer 2-5

2.9 Clarifications, Doubts or Obscurities 2-6

2.10 Tenderer’s Declaration 2-6

2.11 Tenderer’s Enclosures 2-6

2.12 Evaluation of Tenders 2-6

2.13 Right to Reject Tender 2-7

2.14 Professional Indemnity 2-7

SECTION 3 TERMS OF REFERENCE

3.1 Design and Tendering Services 3-1

3.2 Supervision Services 3-3

SECTION 4 REMUNERATION

4.1 General 4-1

4.2 Design Services 4-1

4.3 Supervision Services 4-2

4.4 Local Taxes, Duties, etc. 4-3

4.5 Visas and Permits 4-4

4.6 Validity of the Offer 4-4

4.7 Insurance Cover and Duration of Liability 4-4

SECTION 5 BRIEF DESCRIPTION AND SCOPE OF WORK

5.1 Background & Objectives 5-1

5.2 Design Criteria 5-1

5.3 Scope of Project 5-2

5.4 Preliminary Design Report 5-4

5.5 Final Design and Tender Documents 5-5

5.6 Data Collection, Survey Works, Site Investigations 5-6

5.7 Project Staffing 5-6

(i)

Page 3: Desilanation Plant Tender

PAGE

5.8 Submission of Reports, Drawings and Documents 5-8

5.9 Time Schedule 5-8

5.10 Consultants Understanding of the Scope 5-9

of Work and Services

5.11 Payments 5-9

5.12 Financial Offer 5-9

5.13 Qualifications and Experience of Supervisory Staff 5-10

SECTION 6 TENDER FORMS

- FORM OF TENDER 6-1

- FORM OF AGREEMENT 6-3

- APPENDIX-A TO THE FORM OF AGREEMENT 6-5

- APPENDIX-B TO THE FORM OF AGREEMENT 6-6

- APPENDIX-C TO THE FORM OF AGREEMENT 6-7

- APPENDIX-D TO THE FORM OF AGREEMENT 6-8

- APPENDIX-E TO THE FORM OF AGREEMENT 6-9

- EXHIBIT A– DETAILS OF DESIGN & SUPERVISORY STAFF 6-10

- EXHIBIT B– MANPOWER SCHEDULE 6-11

- EXHIBIT C– EXPERIENCE: RELEVANT PROJECT COMPLETED 6-12

SECTION 7 SCHEDULES OF PRICES

1. Design Services Fees 7-1

2. Supervision Services Fees 7-1

(ii)

Page 4: Desilanation Plant Tender

S E C T I O N 1

INTRODUCTION

1.1 Invitation

The Rural Area Electricity Co. hereinafter referred to as “the Client” invites

Consultancy proposals from Consultants who have previous experience in similar

works for:

“CONSULTANCY SERVICES FOR DESIGN & SUPERVISION FOR

CONSTRUCTION OF NEW REVERSE OSMOSIS (RO) DESALINATION

PLANT AT TIBAT AREA IN MUSANDAM GOVERNORATE”

1.2 Objective

The main objectives of the Project are summarized as follows:

Main objective of the Project is to construct a water production unit at TIBAT area

in Musandam Governorate to provide the inhabitants, commercial and industrial

customers between Tibat and Khasab areas with safe drinking water according to

the Omani Standards for drinking water. It is required to build desalination plant of

capacity 6000 m3/day including accessories with water distribution system through

tanker filling point in accordance with the PAEW standards and Guidelines and

other applicable International standards. The raw water sources is to be studied

during the Front End Engineering and Design (FEED) by the successful consultant

such that either direct sea water intake or water supply wells which shall be

executed and tested by the contractor during the construction stage of the project

and to be located in the vicinity of the plant site. The Desalination Plant is to be

located adjacent to the to-be-built gas based Power plant plot.

1.3 Description of Work

Detailed description of work is provided in Section 5.

1.4 Agreement

The Agreement shall, in general, be governed by the terms and conditions of

“Standard Form of Agreement and Conditions of Engagement for Consultancy

Services for Building and Civil Engineering Works”, Second Edition, March, 1987.

In particular for supervision services.

Tenderers are expected to be in possession of this document and to be fully aware

of its contents.

1.5 Non Compliance with Tender

The tenderer shall submit a separate list including all the items and areas of non-

compliance with the tender requirements. Failing to submit this list the tender will

be considered to be in full compliance with the tender requirements

1-1

Page 5: Desilanation Plant Tender

S E C T I O N 2

INSTRUCTIONS TO TENDERERS

2.1 General

2.1.1 These instructions to Tenderers are intended to aid Tenderers in the

preparation of their Tenders.

2.1.2 Tenderers are advised to read carefully these instructions prior to preparation

of their Tenders. Failure to provide the information required in the format

provided will be sufficient cause for rejection of the application at the

discretion of the Client.

2.1.3 Tenderers will not be reimbursed for any cost incurred by them in the

preparation and submission of their tenders or for any visits to project sites

for the purpose of Tendering.

2.2 Tender Submission

2.2.1 Two (2) Sets (1 original and 1 copy) of Tender Document containing the

Tender shall be submitted in a sealed envelope addressed to:

The Chairperson of Internal Tender Committee

Rural Areas Electricity Co. SAOC

P O Box 1166. Postal Code-133 Al Khuwair

Sultanate Of Oman.

2.2.2 Sets of Tender Document containing the Tender shall be delivered not later

than the date and time prescribed in the Invitation to Tender.

2.2.3 The Tenderers shall be held responsible for ensuring that their tenders are

received in accordance with the instructions stated herein. Late tenders shall

not be considered even though late as a result of circumstances beyond the

control of Tenderers

2.2.4 The Tender shall be signed only by the duly appointed Principal fully

authorized to represent and bind the Consultant. In the case of Joint

Ventures/Associations all parties to such Joint Ventures/Associations shall

sign the Tender.

2.2.5 The Consultant shall submit a Tender Bond, according to the format attached

herewith, for the value of one (1%) percent of the Tender Value along with

the Technical and Financial Proposals. The Tender Bond shall be valid for

ninety (90) days from the date fixed for the submission of Tenders.

2.2.6 The Client reserves the right to split and award the contract for any one of the

services mentioned in the proposed consultancy namely (a) Design (b)

Supervision to any one Consultant or delete the requirement of any of the

above services altogether.

2-1

Page 6: Desilanation Plant Tender

2.3 Addenda to Invitation for Tender

2.3.1 If for any reason prior to the tender submission it becomes necessary to

modify the Tender Documents, addendum/addenda will be issued and shall be

considered as part of the Tender documents.

2.3.2 Receipt of such addenda shall be acknowledged by the Tenderer, but non

acknowledgment of receipt shall not relieve the Tenderer from being bound

by such addenda if the addenda were communicated to the Tenderer by fax,

telex or registered mail provided that such addenda are issued 7 (seven) days

prior to the date fixed for submission of tenders.

2.4 Site Visit

2.4.1 In their own interest, the Tenderers are expected to visit the site and

familiarize with the terrain and nature of work involved.

2.5 Project Office in Oman

2.5.1 The successful Tenderer shall maintain an office in Oman during the entire

course of the Assignment and shall have discussions with the Client at least

biweekly.

2.6 Organization of Tender Documents

2.6.1 Procedure for Submission of Tender

The Tenderer shall submit his proposal to the Client in English in a plain,

sealed envelope containing one original and one copy. The envelope shall not

bear any name or mark identifying the Tenderer.

2.6.2 Proposal Contents

1. The proposal shall be organized into the following sections for the

purpose of evaluation:

a. Section 1. Background

b. Section 2. Objectives of the Project

c. Section 3. Scope of Work

d. Section 4. Approach and Methodology

e. Section 5. Work Plan

f. Section 6. Project Schedule

g. Section 7. Manpower Schedule

h. Section 8. Management Plan/Project Organization Chart

i. Section 9. Previous Experience

j. Section 10 Schedules with supporting documents

k. Section 11 Financial Proposal

2-2

Page 7: Desilanation Plant Tender

l. Section 12 Compliance Statement

m. Section 13 Copy of Tender Documents

2. The Tenderer shall describe in Section 1 of his proposal, the

background of the Tenderer and that of the project including brief

description of previous experience in similar assignments. This shall in

addition include a description of Tenderer’s listing of current staff, their

positions, experience and qualifications and support facilities available.

3. The Tenderer shall re-state in Section 2 of his proposal, the objectives

of the assignment as set out in this Tender Document and thereafter

comment on each of these objectives.

4. The Tenderer shall re-state in Section 3 of his proposal, the Scope of

Work, for the assignment as set out in this Tender Document and

explain his understanding of each activity in the scope of work (i.e.

those factors which will and will not be addressed and any working

assumptions which may significantly affect the project

implementation).

5. The Tenderer shall in Section 4 of his proposal, present his Approach

and Methodology for execution of the Project.

This section should be in sufficient detail to enable the Client to carry

out a proper evaluation of the Tenderer’s understanding of the duties,

responsibilities and obligations included in achieving the project

objectives within the time stated in Section 5 hereof. In addition,

technical details of the methodology and techniques to be used shall be

described in detail.

The Tenderer shall also specify any data required from the Client

including dates by when such data is required and list task specific

interim reports proposed to be submitted to the Client.

6. The Tenderer shall in Section 5 of his proposal, describe in detail his

overall work plan to accomplish the work objectives set out under each

activity in the Scope of Work by identifying specific tasks and dividing

the tasks into sub-tasks to the extent necessary to evolve the proposed

work plan

7. The Tenderer shall in Section 6 of his proposal, propose a Project

Schedule in the form of a Bar Chart Schedule on a task and sub-task

basis identifying project milestones, Client review periods and Client

decision points. Unless otherwise specified, the Client review periods

shall in general not exceed 14 days from the date of receipt of complete

documents.

2-3

Page 8: Desilanation Plant Tender

The Schedule shall include all items of work mentioned under Item(6)

above. This schedule shall be reviewed and agreed upon prior to

Contract award and shall thereafter be maintained and updated as a

measure of progress.

8. The Tenderer shall in Section 7 of his proposal, present a tabular

Manpower Schedule on a task basis specifying designation of the staff

required and the proposed period of time in weeks required for each

staff member in Oman and in the home office, if any, clearly

indicated. (Exhibit B)

9. The Tenderer shall in Section 8 of his proposal, set out his Project

Management Plan or Project Organization Chart for execution of the

works. The personnel to be assigned to each task shall be identified and

the Tenderer shall distinguish between key personnel and supporting

personnel. Reference number of CV shall also be indicated of each

staff member.

For each staff member, for each position, the Tenderer shall submit

with his Tender, a Curriculum Vitae (CV) which includes the bio-data

along with the work history for at least the periods of experience

required for the respective position. The work history shall include as a

minimum for each engagement: beginning and ending dates of

employment; employer name, address and phone or fax numbers;

location, description, and value of project, responsibilities, duties and

authority of the staff member. (Exhibit A)

If some of the personnel are not available at the time of tendering, the

Tenderers should specify the level of expertise (years of experience,

qualification and specialization) and the number of personnel to be

employed for executing the scope.

10. The Tenderer shall in Section 9 of his proposal present his previous

experience of work of a similar nature to the Assignment highlighting

the relevancy of these works. Tenderer shall provide brief descriptions,

contacts (name, organization, address, telephone and fax numbers) as

reference for their performance.

11. The Tenderer shall in Section 10 of his proposal submit the supporting

documents to his offer.

12. The Tenderer shall in Section 11 of his proposal, present his financial

proposal incorporating the requirements of Section 4. Qualifications, if

any, which may have a financial implication shall be clearly mentioned.

The lump sum fee for design services (Section 4.2) and the price ceiling

for supervision services (Section 4.3) shall be given separately and the

total carried to summary of prices.

2-4

Page 9: Desilanation Plant Tender

The breakdown of lump sum fee for design services and the price

ceiling for supervision services shall be separately tabulated indicating

the following:

Position No.

Required

Name of

Staff

Duration

In Weeks/

Months

Rate per Week /

Month

in R.O

Total

Amount in

R.O

Tenderers should note that all references to month, weeks, days etc.

shall be based on the following equation, where:

1 Month = 4.345 Weeks = 30.416 Days

And all remunerations, consultancy fees etc. including rates for

modified design services and Contract over-run periods shall be based

on the above equation. The Consultant Shall state the maximum

monthly over run rate.

Failure to comply fully with the above requirements shall be grounds

for rejection of the Tender.

13. The Tenderer shall in Section -12 of his proposal, submit the copy of

tender documents.

2.7 Preference

Preference shall be given to proposals including individuals who have requisite

experience in conditions similar to those prevailing in Oman and to those Tenderers

having an approved Quality Management System complying with ISO 9000 series

or approved equivalent. Preference shall also be given to consultant with prior

relevant experience in the mega scale Sea Water Desalination projects in Oman.

The Tenderer shall identify all seconded or temporary staff whom he proposes to

assign to the project and any specific works to be performed by any named sub-

consultant.

2.8 Prime offer and Alternative offer

The Tender may be submitted with a Prime Offer and an Alternative Offer. The

Tenderer is cautioned that the Prime Offer shall be submitted solely on the basis of

the Tender Documents and free of any qualification whatsoever.

In case of alternative offers, these may be submitted with deviations subject to

being accompanied by the Prime Offer as mentioned above.

2-5

Page 10: Desilanation Plant Tender

2.9 Clarifications, Doubts or Obscurities

Any clarifications required with regard to the Tender Documents or any other

matter concerning the contract shall be set forth in writing and delivered at the

Office of the Tender Committee not later than 15 (Fifteen) days before the date

fixed for the submission of Tenders. If considered appropriate, a reply in the form

of a circular letter/addendum will be distributed to all the Tenderers.

2.10 Tenderer’s Declaration

Tenderer shall sign a declaration stating that he will exclude from the project any

products manufactured by him or any of his affiliates (affiliation to be judged by

the direct or indirect ownership of fifteen percent or more of the equity shares of a

firm).

2.11 Tenderer’s Enclosures

The Tender shall be organized strictly as stipulated under Section 2.6.2 here-of and

be properly indexed and bound together with all supporting documents and all

sheets of this Tender Document. All sheets of each document submitted shall be

endorsed with the Tenderer’s official company stamp.

Where any Tenderer does not comply with this requirement or if supporting

documents and Schedules including Appendices A to E to the Form of Agreement

and the Exhibits (A,B & C) are not furnished, the Tender may be rejected without

any further requests or clarifications.

2.12 Evaluation of Tenders

The evaluation of Proposals will be based on the following factors as shown below:

Technical Evaluation – 70%

Criteria for evaluation of Technical Proposal shall be basically as follows:

1. General Experience of Tenderer’s Firm in designing and

supervising similar projects of RO Plant (≥ 6000 m3/day), water

retaining structures, etc. as furnished in Exhibit C 15 %

2. Minimum 7 years experience, in Oman or GCC, of Tenderer’s

Firm in designing and supervising similar projects of RO Plant

water retaining structures, etc.as furnished in Exhibit C 10 %

3. Proposed Approach and Methodology 10 %

4. Relevant Qualification & Experience of Key Personnel as

furnished in Exhibit A

20 %

5. Manpower Schedule as furnished in Exhibit B 10 %

6. Completeness and quality of overall tender submission 5 %

2-6

Page 11: Desilanation Plant Tender

Financial Evaluation – 30%

Criteria for evaluation of Financial Proposal shall be basically as follows:

1. Financial Proposal. 30 %

Price although important shall not be the only factor considered in deciding the

award.

2.13 Right to Reject Tender

The Client does not bind himself to accept the lowest or any Tender.

2.14 Professional Indemnity

The Tenderer shall fill the amount of insurance cover in the Standard from of

agreement, Clause (21.5) as 10% of the budget sum (for this project the budget sum

is estimated to be RO 10,000,000/-). Hence the professional indemnity to cover the

insurance of RO 1,000,000/-. The successful Tenderer shall be required to provide a

Professional Indemnity as stipulated in the Standard from of Agreement, Clause

(21.5).

2-7

Page 12: Desilanation Plant Tender

SECTION 3

TERMS OF REFERENCE

This Section shall be read in conjunction with Section-5 hereof.

3.1 Design and Tendering Services

3.1.1 General

The Consultant’s task is to design the Reverse Osmosis (RO) based Desalination

plant, prepare tender documents and drawings, evaluate the bids submitted by the

vendors, assist in the award of Contract and prepare confirmed contract documents.

Post award of contract to successful contractor the consultant shall be required to

provide construction supervision services in office and site.

The Consultant shall have a focal point along with its design and engineering

resources and facilities in Oman for communication with RAEC and for attending

meetings, clarifications, etc.

The CV's of the key personnel who will be involved in the consultancy contract will

be subject to review and approval by RAEC. It is the right of the Client to

withdraw at any time any approval of such staff if they are found to be unsuitable or

inefficient or insufficient professional performance or otherwise not desirable, in

which case such staff in question shall be replaced immediately by others approved

by the Client.

The Client also reserves the right to require the Consultant from time to time to

provide additional specialist staff if required for particular problems or call for the

presence of responsible partners or directors of the Consultant if deemed necessary

by the Client in the interest of the Project.

3.1.2 Engineering Services

The required Engineering Services during design and tendering stage shall include

but are not limited to the following:

A. Perform field investigations as necessary to determine design parameters

including a topographical survey, bathymetry survey or any other surveys

required for the proposed sites of RO Plant up to tanker filling station, Sea

Water Intake system (beach well or direct intake), brine reject system, and

collecting available data or information. The consultant with its data

collection and experience shall identify the type of Sea Water Intake system

to be used for the proposed project and substantiate by performing the

relevant studies or by drilling water supply test well (beach well). It is the

responsibility of the Consultant to obtain all pertinent data and other

information as shall be necessary and to carryout surveys required to perform

his obligations within the period of time specified for each task in his Project

Schedule.

3-1

Page 13: Desilanation Plant Tender

B Carryout all the investigations, i.e. investigation of subsoil conditions, floods,

tide or weather and arranging for boring tests, trial pits, test piling, models or

other investigations etc. as may be considered necessary to perform this

obligations. Carry out test beach well investigation (after performing drilling

of beach well), sea water intake and brine disposal investigation.

C. Verify suitability of proposed site location and perform topographical survey,

bathymetry survey or surveys of the proposed sites for RO desalination Plant

and obtain all approvals/ permits from all concerned authorities such as

Ministry of Environment (MOE), Public Authority for Electricity and Water

(PAEW), Ministry of Housing (MOH), Royal Oman Police (ROP), and

Ministry of Regional Municipality and Water Resources MRM&WR)

including land ownership documents.

E. Establish standard tendering and tender evaluation procedures and criteria.

F. Consultation with any other Consultants appointed by the Client or any other

Governmental Authorities regarding engineering matters related to the works.

G. Prepare Long Term and Short Term Water Demand Study for the inhabitants,

commercial and industrial customers between Tibat and Khasab areas in order

to verify design parameters.

H. Prepare minimum three options utilizing combination of different capacities

for development of proposed RO plant considering long and short term water

demands, and propose the most economical solution based on capital and

operating costs.

J. Preparation of preliminary design (also called as Front End Engineering and

Design - FEED), RO Plant projections, power requirement calculations,

chemical requirement calculations, structures architectural drawings, general

arrangement drawings, layout plans, proposed site facilities, engineering

documents, cost estimates and outline design report for the Clients approval.

M. Drafts of all reports, drawings, designs and design calculations shall be

submitted to the Client for discussion and approval. After such discussions

the Consultant shall amend and formally submit the reports, designs, design

calculations and others documents to the Client.

N. Upon approval of the preliminary design report, prepare of final designs and

draft tender documents for the following works

(a) EPC for New Reverse Osmosis based Desalination Plant at Tibat Area in

Musandam Governorate

Containing draft prime documents, scope of work, Technical Specifications,

tender drawings, Priced Bill of Quantities and Budget Estimate for tender

document for the Client’s approval.

3-2

Page 14: Desilanation Plant Tender

O. Upon approval of the Draft Tender Documents, prepare final tender

documents for the following work.

(a) EPC for New Reverse Osmosis based Desalination Plant at Tibat Area in

Musandam Governorate

Consisting of prime documents, tender Schedules, scope of work, Technical

Specifications, tender drawings to enable the Client to seek tenders.

P. Obtain permits and approval from concern authorities Ministry of

Environment, Ministry of Housing, Public Authority for Electricity and Water

(PAEW), Royal Oman Police, and Ministry of Regional Municipality and

Water Resources including land ownership documents.

Q. Accompany the Tenderers during site visits or any other visits required by the

Client.

R. Evaluate each tenders received and advise the Client of the most suitable

tender.

S. Assist the Client in contract negotiations with the chosen

contractor/contractors and preparation of the Contract documents. Seven (7)

sets of the each contract documents shall be prepared for signature by the

Client and the Contractor. The contract documents shall be submitted by the

Consulting Engineer within one (1) week from the date of receipt of Client’s

letter of intimation.

T. Assist the Client in all technical matters associated with the Project.

U Conduct Environmental Impact Assessment (EIA) and coastal studies, for the

proposed project and obtain Environmental permit from Ministry of

Environment. Conduct plume dispersion study or any other coastal study

deemed necessary to assess the location of the brine reject disposal back in

the sea as per the regulation of MRM&WR.

3.2 Additional / Supervision Services

3.2.1 General

After award of contract for the project to successful contractor, the client shall

perform supervision and management of the construction of all works under this

Consultancy Services during the construction and the maintenance period.

Requirements

The required supervision services shall include but are not limited to the

following:

A. Provide appropriately qualified Engineers and Construction Supervision Staff

experienced in similar projects.

3-3

Page 15: Desilanation Plant Tender

B. Prepare any further plans, designs and drawings necessary to carry out the

works. Where the Client does not consider such works to be substantial, the

site staff shall be fully qualified and experienced to carry out any such work.

No additional payment for design work carried out by the supervision staff

shall be allowed.

C. Establish quality control criteria and procedures to monitor standards,

implement a construction management system for the Works.

Implement a construction management system for the works.

Check that the Contractor has organized his work to achieve the approved

program.

Examine the methods proposed by the Contractor for the execution of the

works, the primary object being to see that they should ensure safe and

satisfactory construction.

Check that the Contractor and all others on site comply with health and safety

requirements.

Assist the Contractor to interpret drawings and understand the specifications

and questions, if any, to the main office for clarification.

D. Review and approve the manufacturer’s equipment drawings and detail

design drawings submitted by the consultant of EPC Contractor and/or sub-

contractors.

E. Make arrangements on behalf of the Client for inspection and testing during

manufacture of such materials and equipment as are usually inspected and

tested and issue inspection certificates to the Clients.

F. Issue instructions to the Contractor and supervise the execution of the Works.

G. Supervise acceptance tests on site including witnessing of tests at the

manufacturer’s Works along with the Client’s Engineer.

H. Issue all certificates to the Client for interim and final payment to the

Contractor(s) and other certificates and information as required by the Client.

For variations over contract provision, prior approval will be taken of the

Client before authorizing the Contractors to carry out any such work.

I. Prepare weekly and monthly progress reports and other technical and

financial reports associated with the Works.

J. Conduct contract/progress meetings as required to review progress and

identify problems, if any.

3-4

Page 16: Desilanation Plant Tender

K. Coordinate with other Consultants appointed by the Client regarding any

matter related to the Works.

L. Assist in commissioning and performance evaluation of completed facilities

and in setting up regular maintenance programs as required.

M. On Completion of the Works, the Consultant shall check and approve the As-

Built Drawings, Operation and Maintenance manuals produced by the

Contractor in accordance with the changes agreed to during the execution of

the Works.

N. Issue Provisional Acceptance Certificate (PAC) and Taking Over Certificate

(TOC) for the Project Works.

O. Assist in settling of disputes or differences that may arise between the Client

and the Contractor except litigation and arbitration.

P. Provide required assistance to the Client during the guarantee/maintenance

period of the project.

Q. Issue Job Completion Certificate and Final Acceptance Certificate (FAC) for

the Project Works.

3-5

Page 17: Desilanation Plant Tender

S E C T I O N 4

REMUNERATION

4.1 General

The remuneration of the Consultant shall be tabulated and quoted separately for the

design and supervision services.

4.2 Design Services

4.2.1 Design Fees

The Consultant shall provide all the staff and facilities necessary to undertake

and complete this assignment.

The Engineering Fees for the design stage services of the project shall be

lump sum amount in Omani Rials including: (a) Engineering Fees, (b) Sub-

Soil Investigation Fees.

4.2.2 Payment for Design Services

The payment for design and tendering services shall be a fixed lumpsum

amount in accordance with Clause 7.1(b) of the Standard Conditions of

Contract for Consultancy Services for Building and Civil Engineering Works.

The design fees will be paid in stages as shown below.

Percentage of

total design fees

Payment mode for design services

20 % Upon the client’s approval for the relevant Studies for the

design implementation of RO Desalination Plant and

submission of Preliminary design reports, Sub-Soil

Investigation Report well test report, and topographical and

bathymetry Surveys for the all the prime sites.

30 % Upon the submission of the final design reports, both draft

tender documents

30 % Upon the approval of both the final tender documents

15 % Either on the ratification of the contract for the works (for

the first stages) or 6 months from the approval of the tender

document whichever is earlier

5 % On the issue of the certificate of completion or, failing

ratification of the contract for the works, 12 months from

the approval of the tender document

4-1

Page 18: Desilanation Plant Tender

The above payment mode shall prevail over the payment mode stipulated in Clause

9.1 of the said Conditions of Contract for Consultancy Services.

4.2.3 Other Expenses

The above stated fees shall also include amongst others, the salaries, transport

expenses, overheads, profit and administration expenses including costs of all

supporting staff and additional specialist staff, partners or directors required

for solving problems in accordance with Section 3 here-of.

4.3 Supervision Services

4.3.1 Supervision Fees

Fees for the Supervision Stage Services whether prime or alternative offer

shall be quoted as a rate per month related to the supervision input of each

member of supervisory staff actually present and approved by RAECO and

all other terms shall be in accordance with Clause 7.2 (c) of the Standard

Form of Agreement and Conditions of Engagement for Consultancy Services

for Building and Civil Engineering Works and shall be paid in stages as

stipulated in Clause 9.2 of the same document. Fees shall include the

following:

A. Supervision Staff Salaries

B. Overhead and backup services of the Head Office and Main Office in

Muscat

C. All transportation costs

D. Services during the maintenance period.

The supervision fees shall be paid in two parts such that the team of engineers to

perform detail design review available at Muscat local office and team of engineers

to perform site supervision available at site.

The first part i.e. the team of engineers at Muscat for detail design review shall be

paid based on the lumsum price quoted in this tender divided, based on the

deliverables of the detail design to-be-submitted by the EPC consultant, over the

detail design review period (the weightage of detail design review period shall be

mutually agreed upon later during the course of contract agreement).

The second part of the supervision fees shall be paid based on the rates available in

this tender for the physical availability of the staff at site (as per actuals) based on

the work necessity (requirement) of the staff at site. If the work doesn’t warrants the

site supervisory staff at site the staff shall not be considered for payment.

4-2

Page 19: Desilanation Plant Tender

4.3.2 Rates for Supervision Staff

Full time site supervision is required only during the actual construction

period and the Consultant shall propose the types of supervisory staff to be

employed along with the applicable full time or part time monthly rates as

applicable, for each member of supervisory staff.

4.3.3 Breakdown Details of Staff Deployment

Breakdown details of staff deployment giving the number of weeks for each

category of the supervisory staff shall be submitted by the Tenderer. The

monthly/weekly rates inclusive of all expenses shall also be given for each

staff member. It is expected that staff proposed be identified by name and

their C.V. details included with the Tender. Any changes in staff proposed

shall be with the written approval of the Client.

4.3.4 Assignment Durations of Supervisory Staff

The members of supervisory staff to be assigned to construction supervision

and their assignment durations are to be agreed with the Client before the

commencement of construction and reviewed from time to time during

construction.

The Client also reserves the right to require the Consultant to increase, reduce

or delete the number or quality or change the formation of the staff in the

interest of the project.

4.3.5 Over-run Fees

For supervision services, the consultant may quote, in addition, a monthly

rate for the contract over-run period. For evaluation purposes, only 3 months

over-run will be considered. Payments, if any, shall however be in

accordance with Clause 4.3.2 here in above.

4.3.6 Site Office

The Contractor will supply and maintain for the Engineer’s supervision staff

furnished offices and accommodation, communications facilities and survey

equipment.

4.4 Local Taxes, Duties, etc.

The Consulting Engineer shall be responsible for the payment of all taxes including

income tax and customs or import duties and all other levies that are enforced

within the Sultanate of Oman for the time being and any effect of future legislation

on the above will be considered on presentation of supporting documents by the

Consulting Engineer and certification of the same by the Client.

4-3

Page 20: Desilanation Plant Tender

4.5 Visas and Permits

The Consulting Engineer shall be responsible for obtaining all visas and permits

required in the performance of his authorized duties. If necessary the Client shall

assist in obtaining such visas and permits.

4.6 Validity of the Offer

The offer shall remain valid for a period of 90 (ninety) days from the date of receipt

of the Tender.

4.7 Insurance Cover and Duration of Liability

The Consulting Engineer shall provide to the Client after award of the Contract, a

valid Certificate of Insurance relating to Professional Indemnity to cover his

liability (to the amount of RO 1,000,000/-) as defined in Clause 21.5 (Insurance

Cover) and 22.0 (Duration of Liability) of the Standard Form of Agreement and

Conditions of Engagement for Consultancy Services for Building and Civil

Engineering Works, Second Edition - March 1987.

4-4

Page 21: Desilanation Plant Tender

SECTION 5

BACKGROUND AND SCOPE OF WORK

5.1 Background & Objectives

Rural Areas Electricity Company (RAEC) SAOC is one of the subsidiary companies of

Electricity Holding Company which is fully owned by the Ministry of Finance. RAEC

generates, transmits and distributes electricity to the rural areas of Oman in the regions of

Al Wusta, Musandam and Dhofar (other than Salalah) and produces potable water (only)

for selective rural areas in Sultanate.

The Rural Areas Electricity Company (RAEC) is planning to participate in the

development of Musandam Area by construction of Reverse Osmosis (RO) based

Desalination plant at TIBAT area in Musandam Governorate, and wishes to appoint a

Consultancy Firm with relevant experience in similar projects especially in Oman, to

perform the following Services

“CONSULTANCY SERVICES FOR DESIGN & SUPERVISION FOR

CONSTRUCTION OF NEW REVERSE OSMOSIS (RO) DESALINATION PLANT

AT TIBAT AREA IN MUSANDAM GOVERNORATE”

RAEC invites such Consultancy Firms to submit their complete and comprehensive

Tender proposals for providing Consultancy Services for the proposed works.

Main objective of the Project is to construct a water production unit at TIBAT area in

Musandam Governorate to provide the inhabitants, commercial and industrial customers

between Tibat and Khasab areas with safe drinking water according to the Omani

Standards for drinking water. It is required to build desalination plant of capacity 6000

m3/day including accessories with water distribution system through tanker filling point

in accordance with the PAEW standards and Guidelines and other applicable

International standards. The raw water sources is to be studied during the Front End

Engineering and Design (FEED) by the successful consultant such that either direct sea

water intake or water supply wells which shall be executed and tested by the contractor

during the construction stage of the project and to be located in the vicinity of the plant

site. The Desalination Plant is to be located adjacent to the to-be-built gas based Power

plant plot.

5.2 Design Criteria

It is required to design and construct a new RO based desalination plant in Musandam

mainland, of necessary capacity to satisfy the water demand in the period up to 2030. The

design shall cover complete desalination plant and its auxiliaries required to include the

following

The design of the desalination plant should be based on the established design and

construction philosophy and techniques for such plants and use of currently available and proven technology, with an allowance for any design alternatives of the systems which may offer better techno-economic solutions;

5-1

Page 22: Desilanation Plant Tender

The design of the desalination plant should be done in accordance with recognized engineering techniques and methodologies, and shall comply with the design requirements of specific codes and standards;

The design life of the desalination plant including all mechanical equipment,

associated piping, electrical and instrumentation works should be 20 years, with regard to the aggressive dusty, hot, humid and salt-laden atmosphere of the Musandam coastal area;

The design should ensure maximum required availability and reliability of the plant

(in view of the importance of water requirements to the various consumers and the economy of the Governorate of Musandam) by selection and design of the new facilities to maintain production availability;

The design shall comply with economical, ergonomical and safety requirements. All

equipment shall be easily accessible for operation, maintenance, and removal;

The design of the desalination plant shall be in accordance to requirements of the concerned authorities such as Public Authority for Electricity and Water, Ministry of Regional Municipalities and Water Resources, Ministry of Environmental, Ministry of Defense, etc;

The Plant and materials shall comply with requirements of Omani standards and British Standards (BS) and codes of practice (BSCP) and other approved International Standards.

5.3 Scope of Project

The following brief description and scope of project is intended to give a broad outline on

the services to be provided by the Consultant and does not cover all aspects in detail. The

offer for consultancy services should be completed in all aspects and the Consultant shall

provide all services necessary whether or not these are explicitly mentioned in this

document.

The Project shall comprise of the following components but not limited to:

Raw Water Supply System

Identification of possible raw water sources either

by drilling of exploratory water supply wells and connection to the proposed

RO Plant.

or

by direct Sea Water Intake (SWI) system including SWI pipelines laid in the

sea, SWI pit and SWI pumping station.

All test and analysis required to estimate potential for organic, inorganic,

particulate, colloidal and bio-fouling in raw water

Water source connection

5-2

Page 23: Desilanation Plant Tender

Pre-Treatment Facilities

Pre-treatment facilities and equipment required for proper function of the

plant: like cartridge pumps and filters, dosing equipments, high pressure

pumps and all other necessary equipments.

Identification of the different pre-treatment systems and recommend the best

design option.

RO Plant of Capacity 6000 m3/day

Construction of Reverse Osmosis (RO) based Desalination Plant of 6000

m3/day output capacity in the 1st stage of construction, approximately to be

commissioned in the year 2011. The RO plant shall be design to

accommodate the future expansion based on the water demand forecast to be

concluded in 2nd

or 3rd

stage.

The Consultant shall verify output capacity by water demand forecast and

advice on the quantity and capacity of RO Plant to be installed.

Particular care should be taken in order to remove boron and strontium and

any other heavy and hazardous metal

Consultant shall prepare and include in the technical report all projections

require to design the plant safely and to calculate all chemicals required in the

pre and post- treatment stages.

Testing and monitoring facilities of quality and quantity control for feed,

product and brine water.

Treated water of the new RO units shall have total dissolved solids in the

limits of minimum 100 ppm and max 300 ppm during commissioning period

and max 500 ppm at the end of the life time of the membranes (5 years)

Product water quality must meet Omani Standards No 8/1998 for drinking

water

Post Treatment Facilities

Including Disinfection’s facilities as required

Product Water Export System

Elevated Water Storage Tank

The size of the product tank to be two day storage capacity for demand of

year 2030.

There will not be any distribution network in this scope of work. Consultant

shall eventually design up to construction of Tanker filling station.

Testing and monitoring facilities of quality and quantity control for feed, product

and brine water

Brine Reject System

5-3

Page 24: Desilanation Plant Tender

Power Supply to Desalination Plant

Supply & erection of Transformers

Supply & erection of LV Switchgear

Interconnection with the grid/to-be-executed Power Plant

Instrumentation and Control

Supply & installation PLC based control system

Supply & installation of Measuring and Control system

Supply & erection of Earthing System

Buildings and Structures

Pre-Treament Building

RO Plant Building

Post Treatment Buiding

Control room for complete remote operation of the Plant

Spare Parts Stores

Workshop

Chemical Store

Building Services

Infrastructure Facilities and Utility Systems

Construction of Fire Fighting & Alarm Systems for the proposed facilities as

per Civil Defence requirements

Supply & installation of lighting& emergency lighting system

Surface drainage, water supply and sewage system

First Aid Facility

Internal roads, paving, car parking areas and shades

Interconnecting pipelines between the components of the proposed plant and

with distribution tanker point

Air conditioning and ventilation system

Boundary wall, lighting, fencing, gates, security system etc.

5.4 Preliminary Design Report

A Preliminary design report shall be carried out as appropriate and a report shall

be submitted including various design options with detailed cost estimate.

Preliminary design report shall consider development of the area based on water

demand in the year 2030. The report shall include minimum but not limited to the

followings: -

a) Various options to realize the proposed project

5-4

Page 25: Desilanation Plant Tender

b) Cost estimate for the proposed options

c) Items referred in TOR Engineering Services Section 3.1.2 of this

document

d) Submission of all the study/survey reports such as topographical survey,

soil investigation, water supply well test report, bathymetry survey, EIA

report, including plume/dispersion study report, any other coastal study

report.

5.5 Final Design and Tender Documents

After RAEC approval of the Preliminary design the Consultant shall proceed with the

preparation of the Final Design and Tender Documents. The Draft Final Design period

allows for the amendment of the Preliminary Design to the satisfaction of RAEC.

The Final Design shall include but not be limited to the following :

1. Updating of the Preliminary design and all approved relevant data, design

calculations and drawings.

2. Further data collection and survey and investigation works

3. Obtain all necessary preliminary 'No Objection Certificates' and approvals from all

concerned authorities e.g. Ministry of Transportation and Communication,

M.R.M.& W.R, M.O.E, R.O.P., M.O.D., G.T.O., PA.E.W., etc.

4. Incorporation of all requirements of the concerned authorities in the Final Design.

5. Cost estimate for both proposed options based on the latest estimated rates and

realistic cost of materials prevailing in Oman.

6. Submission of Draft Tender Documents for the Client approval along with the

Draft Final Design Report.

7. Submission of Final Design report including an executive summary.

8. Submission of Final Tender documents complying with the Tender Board’s

comments.

9. The drawings and documents submitted for approval shall be stamped "Draft Final

Design" and "Draft Tender Documents".

10. It shall be the duty and responsibility of the Consultant to ensure that all Tender

Documents are complete in every respect and that there are no errors or omissions

which may entitle the Contractors to claim for Variation Orders.

11. Consultant shall ensure that all structures and pipeline profiles are based on correct

ground levels and shall assess the extent of rock likely to be encountered including

the conditions of soil and the type of special protection required for the structures

and pipelines.

5-5

Page 26: Desilanation Plant Tender

12. Consideration of existing and future developments based on the current

development plan of the RAEC including road works which may affect the project.

13. Consideration of existing and future services which may affect the project, in

particular, electricity, street lighting, telephone, drainage and irrigation which are

incorporated in the study prepared by others.

5.6 Data Collection, Survey Works, Site Investigations

5.6.1 Data Collection

The consultant shall be responsible to obtain the required data including maps from the

concerned authorities without additional cost to the contract, however RAEC will assist

the consultant to obtain the required data by issuing approach letters to the concerned

authorities at Musandam Governorate.

5.7 Project Staffing

5.7.1 General

The Consultant shall include in his Tender offer the list of personnel to be assigned to the

Project, their designations, curriculum vitae and the proposed duration of each in Oman

on the Project. All staff shall have recognized and experience commensurate with their

work in the project. The consultant shall not change or substitute the proposed staff

without prior written approval of RAEC.

5.7.2 Design Staff

The Consultant shall provide all expert technical advice and skills which are required for

all of the Consultancy Services during the whole period of planning, design and tendering

shall have adequate, qualified and experienced staff in Muscat.

The Senior Designs Engineer/Technical Manager shall be responsible for the design and

shall attend meetings as required to explain the design criteria and be able to answer any

relevant questions. He shall be available for consultation with the client as and when

required.

5.7.3 Supervision Staff (Local Office and Site)

The Consultant shall include in his Tender offer the list of personnel to be assigned for

this Project, their designations, curriculum vitae with the engineering experience in

Desalination Plant particularly involved in Reverse Osmosis based. Based on the above

mentioned scope of work the tenderer has to identify the discipline and duration of the

staff required to perform the design review placed at Muscat local office and the

following discipline and duration of staff required on the site for construction period of

Sixteen (16) months.

5-6

Page 27: Desilanation Plant Tender

1 - Project Manager (Part Time) : 16 Months

2 - Site Manager (Mechanical/Civil* Engineer) : 12 Months

3 - Electrical & Instrumentation Engineer : 6 Months

4 - Commissioning Engineer : 2 Months

5 - Civil/Mechanical* Engineer : 6 Months

6 - HSE Advisor : 10 Months

* If the Site Manager is Mechanical then the site discipline engineer should be

Civil or vice versa

The Consultant may give optional price for the supervision works if he feels that the

above staff requirement is not sufficient, identifying extra man months required and staff

rate.

The Client may revise the above site supervision staff during the construction period.

However the payment will be based on the rates proposed by the consultant for each

category and availability of staff at site.

The part time duration may discontinuous spread over the whole construction period as

required at site The rate of the project manager shall be included in the rate of other

supervision staff

The Consultant may propose and quote for an alternative arrangement for the supervision

staff along with the above recommended level which will be subject to the Client’s

approval.

Assistance as required during the mobilization, construction and maintenance periods

shall be made available from the main office in Muscat as per site requirement at no

additional cost to RAEC such as the input of the managerial level, engineers, quantity

surveyor, draftsman, accountant, typist, etc.. All staff shall have recognised qualifications

The Consultant shall not change or substitute staff proposed in his management

plan/organization chart without prior written approval of the Client.

The Consultant's staff where possible shall have experience of working on Projects of a

similar nature in the Sultanate of Oman.

It should be clearly understood that it is the right of the Client to withdraw at any time

any approval for such staff if they are found to be incompetent, unsuitable or otherwise

not desirable, in which case the person or persons in question shall be replaced by others

approved by the Client with immediate effect.

The Client reserves his right to award the Design Work only and cancel the supervision

phase if required.

Cancellation fees will not be paid for the supervision works if supervision cancelled

before awarding the construction works to the contractor

5-7

Page 28: Desilanation Plant Tender

5.8 Submission of Reports, Drawings and Documents

It shall be clearly understood by the Consultant that all reports, drawings and documents

submitted as indicated in the time schedule shall be checked and approved by a Senior

Partner or Director of the Consultancy Firm. In addition, each drawing shall signed by

the design engineer and those responsible for checking and approving the drawings on

behalf of the Consultancy Firm. All design calculations and drawings shall be recorded

on computer media and coded diskette shall be submitted to the Client. As built drawings

shall be submitted as per the requirements of the Client.

Number of copies of documents shall be as follows :-

1 Preliminary Design : 3 copies + 1 Soft Copy

2 Draft Final Design Report and Draft

Tender Documents

: 3 copies + 1 Soft Copy

3 Final Tender Documents : 3 sets initially and 10 sets after

incorporating Tender Board

comments.

4 Confirmed Contract Documents : 5 sets

5.9 Time Schedule

Preliminary Design from the date of Letter to Proceed 12 weeks

Draft Final Design and Draft Tender Documents from date of

approval of Preliminary Design.

6 weeks

Final Design and Final Tender Documents from date of

approval of Draft Final Design and Draft Tender Documents.

2 weeks

Tendering Period 8 weeks

Tender Evaluation Report from date of receipt of Tenders. 4 weeks

Preparation of Contract Documents and Award of Contract

from selection of Contractor.

2 weeks

Instruction to commence work and Mobilization Period. 1 month

Construction period 15 months

5-8

Page 29: Desilanation Plant Tender

5.10 Consultant's Understanding of the Scope of Work and Services

The Consultant shall clearly define in his proposal, his understanding of the scope of

work and consultancy services he proposes to undertake to ensure the successful

implementation of the project.

Consultant shall submit a clear bar chart of the proposed works under this Consultancy

and clarify the efficacy of the proposed methodology in successfully completing this

assignment within the prescribed time.

5.11 Payments

All payments to Consulting Engineer shall be as specified under Section 3 and Section 4

here-of and supplemented as detailed under this clause sections

The breakdown of the lump sum price for design stage and fees for supervision stage in

relation to the assignment, name, input, charge rate, etc. shall be provided in tabular form

showing the following:

Position Name of Staff Duration in

Months

Rate per

Month

Amount (RO)

All remuneration, Consultancy fees etc. including rates for modified design services or in

the event of extending the Scope of Work or Contract over-run shall be based on the

above rates.

The Client may revise the supervision staff during the construction period according to

the site requirement applying the monthly rates proposed by the consultant in his tender

The consultant may propose alternative mode of payment in his tender subject to the

approval of the Client

5.12 Financial Offer

The financial offer shall be detailed as follows :

1- Design Stage: (a) Design and Engineering Fees, (b) Sub-Soil Investigation Fees

(c) Topographical Survey (d) Bathymetry Survey (e) Raw Water Supply Test Well

Drilling (f) EIA Study including plume/dispersion study, etc. any other works listed in

TOR

2- Supervision service (office based) for Detail Design Review, Factory Inspection,

liaising between the contractor, client and other authorities and any other works listed

in TOR.

5-9

Page 30: Desilanation Plant Tender

3- Supervision service (site based) for site inspection as specified in Clause 5.7.3

4- Over run period: Maximum monthly fees during over run period assuming full Time

staff.

5.13 Qualifications and Experience of Supervisory Staff

The Consultant shall provide supervision staff of minimum qualifications and experience

commensurate with the task they have been provided to achieve the targets of the scope

of work listed in the TOR.

The minimum requirement of qualification, experience and the number of the supervisory

staff is listed hereunder.

For all supervisory staff it shall be mandatory to present them for individual interviews

and written approval prior to commencement of construction.

1. Project Manager

Qualifications : B.Sc. Mechanical Engineering

Experience : 15 years

The experience shall include at least 10 years in the construction and designs of RO based

Desalination plants.

Past experience shall include successfully completing a previous position as Project

Manager on a Project of similar nature and scope of work

2. Site Manager (Mechanical/Civil Engineer)

Qualifications : B.Sc. Mechanical/Civil Engineering

Experience : 15 years in increasingly responsible positions,

The experience shall include at least 10 years in the field of RO based Desalination plants

construction, design and supervision.

Past experience shall include successfully completing a previous position as Resident

Engineer on a Project of similar nature and scope of work.

3. Electrical & Instrumentation Engineer:

Qualifications : B.Sc. Electrical/Instrumentation Engineering

Experience : 10 years

The experience shall include at least 10 years in increasingly responsible positions in

construction electrical and instrumentation works required for RO plants. Past experience

shall include successfully completing a previous position as E&I or Process Engineer on

a Project of similar nature and scope of work

5-10

Page 31: Desilanation Plant Tender

4. Commissioning Engineer

Qualifications : B.Sc. Process/Instrumentation Engineering

Experience : 10 years,

The experience shall include at least 10 years in the Process and Instrumentation works

related to water supply projects particularly mega RO Plant projects.

Past experience shall include successfully completing a previous position as electrical

Engineer on a Project of similar nature and scope of work

5. Civil/Mechanical Engineer

Qualifications : B.Sc. Civil/Mechanical Engineering

Experience : 10 years

The experience shall include at least 10 years in the construction of above ground and

underground water retaining structures involved in mega desalination plants. RO Plant

Buildings

Past experience shall include successfully completing a previous position as civil

Engineer on a project of similar nature and scope of work.

It is intended that the above positions constitute the minimum recommended supervisory

staff for this Project. Tenderers may propose and submit for approval additional positions

which complement and supplement the above positions.

5-11

Page 32: Desilanation Plant Tender

SECTION – 6

TENDER FORMS

FORM OF TENDER

Short Description of Works : CONSULTANCY SERVICES FOR DESIGN &

SUPERVISION FOR CONSTRUCTION OF NEW

REVERSE OSMOSIS (RO) DESALINATION

PLANT AT TIBAT AREA IN MUSANDAM

GOVERNORATE

Note: The consultant is required to fill up the blank spaces in this Form of Tender.

To

The Chairperson of Internal Tender Committee

Rural Areas Electricity Company SAOC

P O Box 1166

Al Khuwair, P.C.133

Sultanate of Oman.

After compliments,

1. Having examined the Terms of Reference, Standard Conditions of Contract,

Scope of Works and visited the site to familiarize ourselves with facilities and

environment existing at site, we, the undersigned hereby offer to execute the

whole of the said works in conformity with the Scope of Works and Standard

Terms of Consultancy Agreement for the sum of:

Design & Engineering Services RO

Construction Supervision Services RO

Total R.O.

(Rials Omani ………………………………………………………………

……………………………………………………………… Only).

Or such other sum as may be ascertained in accordance with the said Tender

Conditions.

2. We agree to abide by our Tender for a period of ninety (90) days from the date

fixed for receiving the same it shall remain binding upon us and may be accepted

at any time before the expiration of the said period.

6-1

Page 33: Desilanation Plant Tender

3. We take no exception for the requirements of Standard Terms or the Scope of

Works except as specifically stated in the Terms of Reference.

4. In the event our Tender is accepted and until a formal Agreement is prepared and

executed, this Tender, together with your written acceptance thereof, shall

constitute a binding obligation upon us.

5. We understand that you are not bound to accept the lowest or any Tender you

may receive.

6. We acknowledge receipt of the following circular letters:-

Reference Number of Letter Date

______________________________ _______

______________________________ _______

______________________________ _______

______________________________ _______

______________________________ _______

Dated this___________________ day of ______________________ 2006.

Yours sincerely,

_________________

(Authorized Signatory)

Name of person signing :________________________________________________

Designation of person signing:____________________________________________

Name of the Consultant:________________________________________________

Company Stamp:_____________________________________________________

6-2

Page 34: Desilanation Plant Tender

FORM OF AGREEMENT

THIS AGREEMENT made on the ____________ day of ___________________ 2006

BETWEEN the RURAL AREA ELECTRICITY COMPANY S.A.O.C. (RAECO), P

O Box 1166, Postal Code 133 (hereinafter referred to as “the Client”) of the one part

AND

Messrs._________________________________________________________________

_________________________________________________whose registered office is at

_________________________________________________(hereinafter referred to as

“the Consulting Engineer”) of the other part.

WHEREAS the Client is desirous that Consultancy Services be rendered in accordance

with the Conditions of Engagement as contained herein

WHEREAS the Consulting Engineer is willing and capable to render the said Services

and has submitted an offer

AND WHEREAS the Client has accepted the same for the following:

PROJECT: CONSULTANCY SERVICES FOR DESIGN & SUPERVISION FOR

CONSTRUCTION OF NEW REVERSE OSMOSIS (RO)

DESALINATION PLANT AT TIBAT AREA IN MUSANDAM

GOVERNORATE

SERVICES: CONSULTANCY SERVICES

NOW THESE PRESENT WITNESS and it is hereby agreed and declared by and

between the parties hereto as follows:

1.0 In this Agreement the words and expressions shall have the same meanings as are

respectively assigned to them in the Standard Conditions of Contract hereinafter

referred to.

2.0 The following documents shall be deemed to form and be read and construed as

part of the Agreement viz:

a) The Invitation to Tender

b) The said Offer (The Consulting Engineer’s Technical and Financial Offer

No._______________________________)

c) The Standard Conditions of Contract (Consutancy Services for Building

and Civil Engineering Works – Second Edition – March 1987)

d) The Client’s Letter of Acceptance

6-3

Page 35: Desilanation Plant Tender

3.0 In consideration of the payments to be made by the Client to the Consulting

Engineer as hereinafter mentioned, the Consulting Engineer hereby covenants

with the Client to perform the Services in conformity in all respects with the

provisions of this Agreement.

4.0 The Client hereby covenants to pay the Consulting Engineer in consideration of

the above Services the remuneration at the times and in the manner prescribed by

this Agreement.

IN WITNESS whereof the parties hereto have hereunder set their respective hands and

seals on the day and year first above written.

________________________________ _________________

SIGNED BY A DULY AUTHORIZED WITNESS

SIGNATORY FOR AND ON BEHALF

OF RURAL AREAS ELECTRICITY

COMPANY S.A.O.C. (RAECO)

________________________________ _________________

SIGNED BY A DULY AUTHORIZED WITNESS

SIGNATORY FOR AND ON BEHALF

OF THE CONSULTING ENGINEER

Ratified in accordance with Sultani Decree No.48/76 as amended and in accordance with

Sutlani Decree Nos.69/95, 60/96 and 83/96.

6-4

Page 36: Desilanation Plant Tender

APPENDIX-A TO

FORM OF AGREEMENT

CONSTITUTION OF PRACTICE AND/OR COMPANY

The Consulting Engineer shall together with his Tender submit a bound volume

containing a copy of each of the following currently valid certificates and documents:

1. The Registration Certificate of the Practice/Company at the Commercial

Registration Department of the Ministry of Commerce and Industry.

2. The License approved and issued by the Department for Professional and Trade

Authorization of the Ministry of Commerce and Industry.

3. The Certificate of membership of the Practice/Company with the Omani Chamber

of Commerce and Industry.

4. The Certificate of Registration with the Tender Board.

5. The name of the responsible person authorized to sign the Form of Agreement, his

specimen signature and Letter of Authority from the Practice/Company.

6. The name of person or persons who will be responsible for the provision of the

services to be rendered together with their Curriculum Vitae.

7. A Professional Indemnity Policy drawn with an Insurance Company registered in

the Sultanate of Oman evidencing that there is sufficient cover for the possible

non-performance of the Consulting Engineer’s Services as contained in this

Agreement and as required by Clauses 21.5 and 22.0 of these Standard

Conditions. Professional Indemnity should be 10% of the Budget amount of the

project (for this project the budget sum is RO 10,000,000/-). Hence the

professional indemnity to cover the insurance of RO 1,000,000/-.

8. The name of the Person or Company if any who is the Agent if the Consulting

Engineer is in the Sultanate of Oman together with the certificates evidencing the

Agency.

9. List of current projects/similar studies with approximate construction values for

which the Consulting Engineer is at present providing services to Government

organizations and the private sector together with the commencement dates of

such services and the anticipated completion dates.

10. List of studies completed during the previous five years in the Sultanate of Oman

with the Contract Price and the name of the Client.

6-5

Page 37: Desilanation Plant Tender

APPENDIX-B

TO FORM OF AGREEMENT

Clause

1. PERIOD OF SUPERVISION 2.5 ___ MONTHS + 14 DAYS

SERVICES

2. LANGUAGES FOR 3.1 ARABIC AND/OR ENGLISH*

CORRESPONDENCE

3. SET OF DOCUMENTS:

- DRAFT RFP DOCUMENTS 4.1[c]iii AS PER SEC-5, CL.5.8 - FINAL RFP DOCUMENTS AS PER SEC-5, CL.5.8

- CONFIRMED CONTRACT DOCUMENT AS PER SEC-5, CL.5.8

4. DELAY BY THE CONSULTANT/CLIENT 11.1

5. AMOUNT OF INSURANCE 21.5 RO 1,000,000/-

10% OF THE PROPOSED

PROJECT BUDGET SUM#

_______________________________________________________________________

* DELETE WHERE INAPPLICABLE

# ASSUMING THE BUDGET SUM FOR THE PROJECT TO BE RO 10,000,000/- THE

PROFESSIONAL INDEMNITY/INSURANCE COVERAGE SHOULD COVER THE AMOUNT OF

RO 1,000,000/- FROM THE CONSULTANT

6-6

Page 38: Desilanation Plant Tender

APPENDIX-C TO

FORM OF AGREEMENT

COST OF ADDITIONAL DOCUMENTATION

A0 Copy negative _______________

AO Dyeline print _______________

A1 Copy negative _______________

A1 Dyeline print _______________

A2 Copy negative _______________

A2 Dyeline print _______________

A3 Photocopy _______________

A4 Photocopy _______________

PROFESSIONAL SERVICES

Manager/Partner _______________ ph/pd/pm*

Senior Engineer _______________ ph/pd/pm*

Specialist _______________ ph/pd/pm*

Assistant _______________ ph/pd/pm*

__________________________ _______________ ph/pd/pm*

__________________________ _______________ ph/pd/pm*

NOTE:

The above rates are to be fully inclusive of all costs, overheads and profit, and all things whatsoever

necessary for the provision of the Services required under Clauses 7.4(b) and 7.5 of the Agreement.

Where the Client requires sets of Documents in excess of the numbers stated in

Appendix-B herein before the costs of reproduction shall be charged at the above rates

* delete where inapplicable

6-7

Page 39: Desilanation Plant Tender

APPENDIX-D TO

FORM OF AGREEMENT

SCHEDULE OF FACILITIES REQUIRED DURING SUPERVISION PERIOD IN

ACCORDANCE WITH CLAUSE 12.0:-

a) WITHIN THE CAPITAL AREA, BURAIMI, NIZWA, SOHAR OR SALALAH

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

b) OUTSIDE THE CAPITAL AREA, BURAIMI, NIZWA, SOHAR OR SALALAH

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

6-8

Page 40: Desilanation Plant Tender

APPENDIX-E TO

FORM OF AGREEMENT

NAMES AND ADDRESS OF SUB-CONSULTANTS AND SERVICES TO BE

RENDERED in accordance with Clause 14.0:-

Name : _________________________________________________

Address : _________________________________________________

CR No. &

OCCI No. : _________________________________________________

SERVICE : _________________________________________________

Name : _________________________________________________

Address : _________________________________________________

CR No. &

OCCI No. : _________________________________________________

SERVICE : _________________________________________________

Name : _________________________________________________

Address : _________________________________________________

CR No. &

OCCI No. : _________________________________________________

SERVICE : _________________________________________________

Name : _________________________________________________

Address : _________________________________________________

CR No. &

OCCI No. : _________________________________________________

SERVICE : _________________________________________________

Name : _________________________________________________

Address : _________________________________________________

CR No. &

OCCI No. : _________________________________________________

SERVICE : _________________________________________________

Name : _________________________________________________

Address : _________________________________________________

CR No. &

OCCI No. : _________________________________________________

SERVICE : _________________________________________________

6-9

Page 41: Desilanation Plant Tender

EXHIBIT - A

DETAILS OF PROPOSED DESIGN AND SUPERVISORY STAFF

The following key personnel shall be assigned to the Design and Supervision Services of

the proposed project:-

Design Team

Key Personnel Name Qualification Major experience Years of

Experience

Project Manager

Desalination Engineer

Mechanical Engineer

E&I Engineer

Civil Engineer

Supervision Team

Key Personnel Name Qualification Major experience Years of

Experience

Site Manager

Commissioning

Engineer

E&I Engineer

Civil Engineer

HSE Advisor

6-10

Page 42: Desilanation Plant Tender

E

XH

IBIT

– B

MA

NP

OW

ER

SC

HE

DU

LE

To

tal

(M

an

Weeks)

Pers

on

nel (M

an

Week)

Sit

e

Ins

pec

tors

I,M

& E

E

ng

inee

rs

Res

ide

nt

En

gin

ee

r

Te

ch

nic

ia

ns

/ D

raft

sm

en

E,

M &

I

En

gin

ee

rs

6-1

1

Str

uc

tura

l

En

gin

ee

r

Pro

cess/

Desali

nati

on

E

ng

ineer

Pro

jec

t

Ma

nag

er

Om

an**

A

CT

IVIT

Y

Mo

bili

zatio

n o

f C

onsultant’s T

eam

Pre

limin

ary

Desig

n

Dra

ft F

inal D

esig

n a

nd D

raft

Te

nder

Docum

ents

Fin

al D

esig

n a

n F

inal T

ender

Docum

ent

Te

nder

Evalu

atio

n

Pre

para

tio

n o

f C

ontr

act

Docum

ent

Instr

uctio

n t

o c

om

mence w

ork

and

Mo

bili

zatio

n

Constr

uctio

n P

erio

d

To

tal

(Man

Weeks)

ID

1.

2.

3.

4.

5.

6.

7.

8.

9.

Page 43: Desilanation Plant Tender

C - EXHIBIT

/OngoingompletedExperience: Relevant Project C

Name of

Client –

including

Telephone &

Fax Number

Name of

Client

Responsible

Officer

handling

Project

Name

Location and

type of

Project

Contract Price

(R.O.)

Date of

Award

Original Date of

Completion

Actual Date of

Completion

Percentage of

Participation of

Firm in Project

Was Contract

Satisfactorily

Completed, including

Time Provision (if No,

explain on separate

sheet)

Any Liens or

Claims (Yes/No)

if Yes explain on

separate sheet

Design Supervi

sion Design

Supervisi

on Design

Supervisi

on

6-12

Page 44: Desilanation Plant Tender

SECTION-7

SCHEDULE-1

SCHEDULE OF PRICES

7.1 DESIGN SERVICES FEES

Item Description Total

Amount

(R.O.)

7.1.1. Design and Engineering Fees

7.1.2. Sub-Soil Investigation Fees

7.1.3. Topographical Survey Fees

7.1.4. Bathymetry Survey Fees including suspended particle test

7.1.5 Fees for Drilling & Testing of Water Supply Test Well

(Beach Well)

7.1.6 EIA studies including plume dispersion study or any other

relevant coastal studies mandatory for obtaining

Environmental permit

7.1

Total of Design & Engineering Fees (R.O.)

carried forward to Form of Tender

7.2 SUPERVISION SERVICES FEES

Item Description Amount

(R.O.)

7.2.1. Supervision Fees for the staff based in Local Office to

perform detail design review, detail design liaising services,

factory inspections, etc. (Lumsum Price)

7.2.2. Supervision Fees for the staff based in Site Office to perform

site inspection, site engineering, site liaising services etc.

(break up to be given as per below format)

7.2

Total of Supervision Fees (R.O.)

carried forward to Form of Tender

7.1 DESIGN SERVICES FEES

7.2 SUPERVISION SERVICES FEES

TOTAL CONSULTANCY FEES

Carried forward to Form of Tender R.O

(Rials Omani ___________________________________________________

_______________________________________________________________

______________________________ Only)

7-1

Page 45: Desilanation Plant Tender

Break-up Prices for Item No. 7.2.2

Position Number

required

Names Months RO/Month Total

Amount

R.O.

Project Manager

(Part Time) 1 16

Site Manager

(Mechanical/Civil

Engineer)

1 12

Electrical &

Instrumentation

Engineer

1 6

Commissioning

Engineer 1 2

Civil/Mechanical

Engineer 1 6

HSE Advisor 1 10

Sub-Total R.O.

(carried forward Item No 7.2.2)

___________

(Authorized Signatory)

Name of person signing :________________________________________________

Designation of person signing:____________________________________________

Name of the Consultant:________________________________________________

Company Stamp:_____________________________________________________

7-2