designing a mine lay out

38
UNIVERSITY OF MORATUWA Faculty of Engineering DESIGN REPORT MODULE ER4122: DESIGN PROJECT DASSANAYAKE D.M.S.M. (100855B) PUSHPAKUMARA K.B.N. (100850F) SAMPATH R.P.S. (100836T) PRABHANGA U.B. (100830U) Department of Earth Resources Engineering Date of Submission 02-12-2014

Upload: sandun-dassanayake

Post on 03-Oct-2015

18 views

Category:

Documents


2 download

DESCRIPTION

the design is based on the contour map of the area

TRANSCRIPT

  • UNIVERSITY OF MORATUWA

    Faculty of Engineering

    DESIGN REPORT

    MODULE ER4122: DESIGN PROJECT

    DASSANAYAKE D.M.S.M. (100855B)

    PUSHPAKUMARA K.B.N. (100850F)

    SAMPATH R.P.S. (100836T)

    PRABHANGA U.B. (100830U)

    Department of Earth Resources Engineering

    Date of Submission 02-12-2014

  • Design Project 2015

    2

    PREFACE

    The major goal of designing a mine utilizing the optimum strategies is the gaining of economic

    stability when the hour of need arrives. No mine in the known world can be designed for 100%

    safety and overwhelming profits. Where there is a mine there is a threat for the people who are

    working in there, there is a threat of major economic draw backs and there is a threat for the

    natural habitat and the environment.

    The ultimate objective of a mining engineer or the group of design engineers is the minimization

    of threats and weaknesses and maximization of the strengths and opportunities, the desired mine

    will be facing in the future, past and most importantly in the present. This is the purpose of this

    whole design project. This particular design of the mine is the ultimate design we came up as a

    group for our final year design project.

    In the first chapter, an introduction is given regarding the location of the mine and the available

    details for the designing. In this context, the method which we used to determine the dip and strike

    of the ore body and the three dimensional visualization of the area geology are presented briefly.

    In the second chapter exploration program is discussed. Under that, the exploration done using

    the diamond drilling program and the selection of the locations for drilling are discussed. We

    strictly followed the continuity of the report, at the same time answering the desired questions

    which were attached with the initial design project materials.

    In the third chapter, the mining method and the operational and strategic utilization of the

    engineering knowledge in designing the mine are expressed. The design regarding the

    underground mineral transport system is also elaborated with general details.

    Final chapter is allocated for the costing and economical evaluation of the mine. With the

    available information we could build up a systematic approach to justify the accountability of the

    whole design project.

  • Design Project 2015

    3

    Table of Contents

    PREFACE .......................................................................................................................................................... 2

    1. CHAPTER I ................................................................................................................................................ 6

    1.1 Introduction ..................................................................................................................................... 6

    1.2 Calculating the strike and dip of the veins ...................................................................................... 7

    1.3 Surface distribution of the veins ............................................................................................................ 8

    1.3 Exploration ...................................................................................................................................... 9

    2.1.1 Diamond Drilling Programme ........................................................................................................ 9

    2.1.2 Developing access roads............................................................................................................... 14

    1.4 Mine opening ................................................................................................................................. 16

    2. CHAPTER III ............................................................................................................................................ 18

    3.1 Addit .................................................................................................................................................... 18

    3.1.2 Drilling pattern of the Addit ............................................................................................................. 18

    3.2 Blind Shaft ........................................................................................................................................... 20

    3.2.3 The auxiliary shaft of the mine ..................................................................................................... 21

    3.2.4 Blind shaft & auxiliary shaft sinking ............................................................................................. 22

    3.3 Shaft lining ........................................................................................................................................... 24

    3.5 Mining method .................................................................................................................................... 28

    3.5.1 Overhand cut and fill method ....................................................................................................... 28

    3.6 Mine Layout ........................................................................................................................................ 31

    3.7 Underground transportation system .................................................................................................... 32

    3.8 The conveyor belt system .................................................................................................................... 34

    3.8 Ventilation methods ............................................................................................................................ 36

    3.8.1 Stope ventilation methods ............................................................................................................ 36

    3.9 All the costing has attached to appendixes

    3. REFERENCES .......................................................................................................................................... 38

  • Design Project 2015

    4

    List of figures

    Figure 1.1 The contour map of the area .................................................................................................................. 6

    Figure 1.2 The projected strike lines of the veins ................................................................................................... 7

    Figure 1.3 The graphical representation of the dip and strike ................................................................................. 7

    Figure 1.4 The expected surface distribution of the veins ....................................................................................... 8

    Figure 1.5 The 3D visualization of the vein ............................................................................................................ 8

    Figure 2.1 The hypothetical pattern of the exposed point distribution .................................................................. 10

    Figure 2.2 The horizontal depth to 500 m depth of the ore ................................................................................... 10

    Figure 2.3 The 3D visualization of Drilling lines from the drilling point ............................................................. 11

    Figure 2.4 The drilling locations ........................................................................................................................... 12

    Figure 2.5 The map of the access roads ................................................................................................................ 14

    Figure 2.6 Adit opening......................................................................................................................................... 16

    Figure 3.1 The proposed addit with its dimensions ............................................................................................... 18

    Figure 3.2 Drilling pattern and the blasting sequence of the addit ........................................................................ 19

    Figure 3.3 The location of the blind shaft ............................................................................................................. 20

    Figure 3.4 Blind Shaft features and dimensions .................................................................................................... 21

    Figure 3.5 Auxiliary shaft Dimensions ................................................................................................................. 22

    Figure 3.6 Main shaft & Auxiliary shaft blasting pattern ..................................................................................... 23

    Figure 3.7 The winch and the steel structure ......................................................................................................... 24

    Figure 3.8 The cross cut with dimensions ............................................................................................................. 25

    Figure 3.9 The blasting pattern of the cross cut .................................................................................................... 27

    Figure 3.10 The ore blocks created to be mined ................................................................................................... 28

    Figure 3.11 The layout of the mine with cross cuts, winzes and shafts ................................................................ 29

    Figure 3.12 The extraction procedure ................................................................................................................... 30

    Figure 3.13 3D view of the mine lay out ............................................................................................................... 31

    Figure 3.14 The dimensions of the rail cross section ............................................................................................ 32

    Figure 3.15 The mine car with dimensions ........................................................................................................... 33

    Figure 3.16 The deflection of the pulley ............................................................................................................... 34

    Figure 3.17 Pulley width ....................................................................................... Error! Bookmark not defined.

  • Design Project 2015

    5

    List of tables

    Table 1-1 The Dip and Strike of the veins .............................................................................................................. 8

    Table 2-1 Distances to the drilling position .......................................................................................................... 11

    Table 2-2 The drilling length from the drilling locations ...................................................................................... 13

    Table 3-1 The location of the blind shaft .............................................................................................................. 20

    Table 3-2 Factor of safety for the rails .................................................................................................................. 33

    Table 3-3 Pulley width recommendations ............................................................................................................. 35

  • Design Project 2015

    6

    1. CHAPTER I

    1.1 Introduction

    This report is comprised of the mine design done by the group members of the final year design

    project group. The mine described here is a hypothetical mine. According to the given information

    the area geology suggests a steeply dipping graphite mineralization. The contour map including

    the mineralization of the area was given. The contour map is shown in figure 1.1

    Figure 1.1 The contour map of the area

  • Design Project 2015

    7

    1.2 Calculating the strike and dip of the veins

    The contour interval was given as 70m. Therefore we can generate the lines of strike of different

    levels as shown in figure 1.4.

    59o

    Figure 1.2 The projected strike lines of the veins

    Figure 1.3 The graphical representation of the dip and strike

  • Design Project 2015

    8

    1.3 Surface distribution of the veins

    Surface distribution pattern of the veins considering the vein thickness as 40cm and the marked

    points are in the center of the vein.

    Figure 1.4 The expected surface distribution of the veins

    Figure 1.5 The 3D visualization of the vein

    Vein Dip Strike

    C 59o

    9o 29 24

    D 63o

    181o 51

    Table 1-1 The Dip and Strike of the veins

  • Design Project 2015

    9

    CHAPTER II

    1.3 Exploration

    2.1.1 Diamond Drilling Programme

    The need of the diamond drilling arises when the sub surface distribution of the ore body has to be

    identified. It deviates from the earlier exploration methods as it allows the removal of solid

    cylinders of rock or often what referred to as core from deep within the earth. The materials

    present in the desired depth levels are visually inspected and later detailed investigations are run

    on them to identify what actually exists in the given depths.

    There are basically two ways in which the diamond drilling programme can be conducted.

    1. Inclined core drilling

    The main advantage in this method is that the drilling machine can be kept at one

    location. The drilling can be done at various directions. Since the angle of drilling

    increases the length between the drilling position and the desired ore body identified,

    the drilling length is usually high. It, the inclined core drilling method, has to be

    selected with great caution. When the estimated mobility cost of the drill machine is

    higher than the estimated drilling cost, application of this method is cheaper.

    2. Vertical core drilling

    The drilling can be done in various locations but the only condition is that the drilling

    should be done vertically penetrating the subsurface strata. The drilling length is always

    the vertical length and no any alteration regarding the length can be achieved other than

    changing the drilling location. When the estimated mobility cost of the drill machine is

    higher than the estimated drilling cost, application of this method is costlier.

    In this particular design-exploration programme, the depth at which the exploration ends is

    defined as 500m. Since the area geology is asked to be assumed closer to the one that in Bogala

    area (i.e. rock type; Metamorphic garnet biotite gneiss), with the dip of the mountain (higher cost

    for mobilization and stabilization of the drilling machine), the best way to do the diamond drilling

    is inclined core drilling.

    The requirement of the diamond drilling program in this context is to explore the underlying

    geology. Therefore out of the two methods of rotary drilling and wireline drilling, wireline

    drilling method is chosen. In wireline drilling method, it allows the inner tube of the core barrel

  • Design Project 2015

    10

    to be raised to the surface and empty the barrel to be pumped back into place without removing

    the drill string or diamond tools from the hole. Because of that there are long distances to be

    drilled this method is more suited.

    Figure 1.6 The hypothetical pattern of the exposed point distribution

    Let the distance between two parallel lines going parallel to the strike is X, the number of times

    which X has to be multiplied in order to find a location on the surface which meets the vein at

    500 m depth on the line going perpendicular to the strike is c. The dip angle is .

    c x X

    500m

    c x X tan = 500 m

    Figure 1.7 The horizontal depth to 500 m

    depth of the ore

  • Design Project 2015

    11

    The distances are calculated to the point where the ore body will be lying 500 m below.

    X c Horizontal Distance

    to the Location

    Vein C 36 m Vein C 59o

    Vein C 8 Vein C 288 m

    Vein D 41.99 m Vein D 63o

    Vein D 6 Vein D 249 m

    Table 1-2 Distances to the drilling position

    But based on the above calculations the drilling points will be located way beyond the perimeter

    of the given map. Assuming the map is the only reference we can have and there may be other

    constructions beyond the perimeter another method has to be developed.

    Lets find the point located at equal distances to the exposed vein-c points on the plane of the ore

    body.

    Inclined ore body

    Angled drill holes

    Figure 1.8 The 3D visualization of Drilling lines from the

    drilling point

  • Design Project 2015

    12

    Figure 1.9 The drilling locations

    The drilling locations are selected so that the distances from the drilling point to the respective

    exposed points are equal. An exception had to be made for the c-vein exposed points due to the

    presence of the river. There, drilling point and two exposed points are selected to measure the

    distance in each two cases avoiding the buffer zone of the river. That is the reason for the presence

    of two C-drill points named, C-drill point1 and C-drill point.

    AQ (Hole diameter: 48mm) (refer appendix i) drill bit is selected to be used for the drilling

    since, drilling lengths exceeding 1000 m can be achieved by it with minimum failures. Its core

    diameter is less and the torque needed to rotate the bit is less and fuel consumption is also less

    than other types. The drilling rig that fits the requirements is the hechang-HQY-500 drilling

    rig (refer appendix ii).

  • Design Project 2015

    13

    Surface drill point location Drilling details

    Bearing angle to the

    horizontal

    axis

    Drilling length

    D-drill point 1 Directly

    downwards

    90o 150 m

    048o 65

    o 200 m

    131o

    65o

    200 m

    C-drill point 1 Directly

    downwards

    90o 150 m

    284o 60

    0 200 m

    206o

    80o

    200 m

    C-drill point 2 Directly

    downwards

    90o 150 m

    325o

    65o

    150 m

    260o

    60o

    150 m

    Table 1-3 The drilling length from the drilling locations

    Apart from the initial exploration programme, continuous exploration programmes have to be

    conducted while the mine is under operation. The following figure shows the expected locations

    and drilling patterns when each level of the mine is under operation.

  • Design Project 2015

    14

    2.1.2 Developing access roads

    Based on the given area map, two access roads are developed as branches of the main roads

    specified in the map. R1 road will be the access road for the vein D addit entrance and R2 will be

    the access road for the vein C addit entrance.

    In the second stage when the mine is under operation, principle level roads are driven to the

    deposit. These roads are rail tracks for the ore transportation purposes. Since the lower levels are

    to be accessed, a blind shaft is sunk from the addit and the lower level rail tracks are connected to

    this blind shaft. This is the case for both the addits. Hence there are two blind shafts. These two

    will be eventually connected to all the cross cuts and auxiliary shaft.

    Figure 1.10 The map of the access roads

  • Design Project 2015

    15

    2.1.3 Ore grade calculation

    When the exploration drilling is over, the shape and the distribution of the ore body can be

    visualized. But that doesnt give a clear indication whether the initiation of the mining project is

    economically feasible. To find out whether mining is profitable more detailed survey has to be

    conducted. The drill core samples can be analysed to find the ore grade. Using statistical methods

    the total ore grade of the mine as well as the areas where higher grade deposits present can be

    mapped out. If the cut-off grade value is low the parts of the mine where the grade is low can be

    mined out quickly, if the cut-off grade is higher some parts of the mine will have to be abandoned.

  • Design Project 2015

    16

    1.4 Mine opening

    The two veins are located directly opposite to each other. With the river flowing on top of the vein

    c it would be difficult as well as costly to use addits to open the ore body. Therefore a better

    option would be sinking a shaft at the center of gravity of the two main veins in order to extract

    the maximum out of them.

    But the circumstance is such that the shaft has to be sunk on the top of the mountain. But that

    would require a huge investment. Since the extraction of the ore will not be possible until the

    drives are also developed, sinking a main shaft at the beginning would not be a good strategy.

    Therefore using one addit to enter into the ore body from the opposite side of the river while an

    auxiliary shaft is being sunk from the top of the mountain would be more economically viable

    since the revenues will be generated at the initial stage also with the production from the driven

    addit. The location of the addit is selected opposite to the river to avoid possible costly operations

    such as pumping water from the addit that is being excavated. The first move is merely for

    covering up as much as possible for the expenses incurred during the initial mine development

    operations.

    Figure 1.11 Adit opening

    It is expected that the auxiliary shaft will be finished up to the depth of the second level of the

    vein D, when the first few levels of the vein D are extracted. Then level by level the vein D can be

    extracted using cut and fill method.

    When adequate revenues are generated, the extraction can be started from the vein C using the

    second addit. The advancing of the addit will open up the first level of the vein C. with that being

    developed a cross cut is also developed to meet the auxiliary shaft. So the whole mine lay out

    comes in to operation with time.

  • Design Project 2015

    17

    When the mine becomes enlarged with the connection of the cross cut from the vein C to the

    auxiliary shaft, natural ventilation will not be adequate enough. Therefore an exhaust fan has to be

    implanted on the auxiliary shaft.

  • Design Project 2015

    18

    2. CHAPTER III

    3.1 Addit

    The mine is expected to be operated at the beginning using addits. The major reason behind that is

    the economic factor. The locations of the ore bodies are such that the safety also will be high if the

    initial opening was developed as an addit.

    Figure 2.1 The proposed addit with its dimensions

    3.1.2 Drilling pattern of the Addit

    In this particular blasting pattern, a burn cut at the centre is used to create the space for the burden

    of rocks to fall into. The specified blasting sequence helps the fragmented material to pile

    systematically without disturbing the flow of the blast. Closer spacing of the drill holes in the

    bottom emphasizes the fact that the load is predominant in the bottom part compared to the upper

    part of the perimeter.

    The following information are assumed in this design.

  • Design Project 2015

    19

    Addit area = 4.6 m2

    Bit size of the drilling machine =38 mm

    Advance of the shaft per round = 1m

    Number of holes per round = 53

    Powder factor for the blast = 2.7kg /m3

    Romanic Numbers half second delay

    Arabic numbers m second delay

    Figure 2.2 Drilling pattern and the blasting sequence of the addit

    Dimension in ft

    Cut Hole (64mm)

    Drill hole (38mm)

  • Design Project 2015

    20

    3.2 Blind Shaft

    The entry to the mine is achieved thorough an addit. Therefore to extract the underlying ore body

    in the subsurface of the mountain, a blind shaft has to be developed. This shaft is the main

    development shaft used to connect the cross cuts which are connected to the ore body from the

    other end. Since the shaft is not visible to the outside this is called a blind shaft. To hoist the

    materials being extracted from the underground there is a winch located at the top.

    Figure 2.3 The location of the blind shaft

    The location of the shaft is selected considering two reasons.

    1. The closeness of the shaft opening to the river (i.e. the buffer zone of the river)

    2. The distances at the subsurface level to the two ore bodies from the shaft (this should be as

    minimum as possible fulfilling the condition 1)

    Considering all these conditions the most favorable area boundary for the shaft sinking was

    identified and the location of the shaft can be given as follows.

    location (380, 630)

    Elevation (assumed from M.S.L.) 480 to 500 m

    Slope 27o

    Table 2-1 The location of the blind shaft

    Blind Shaft

    Addit

  • Design Project 2015

    21

    3.2.2 Blind shaft Dimensions & Features

    Although this is a blind shaft this may well be acting as a primary shaft in this design as the

    mining operations progress. This is the main transport passage into the underground from the

    main addit entrance. The 2x7 ft rectangle cross sectional area indicated in the below figure acts as

    the passageway for facilitating electricity, compressed air and other necessary supplies which are

    continuously needed when the mine is in operation. The skip is used to hoist material as well as

    men working underground. To hoist this cage the winch specified earlier is used with wire ropes.

    Figure 2.4 Blind Shaft features and dimensions

    3.2.3 The auxiliary shaft of the mine

    The need of an auxiliary shaft occurs mainly due to two factors.

    1. For the emergency exit purposes as a secondary entry path

    2. For effective ventilation across the mine.

    The dimensioning of the auxiliary shaft is given in the below figure. The shaft is sunk with the

    rectangular shape neglecting the resistance created by the shapefactor to the ventilating air flow

    considering the fact that the natural ventilation caused by it is high. Since the top most point of the

    shaft is located towards the top of the mountain, there exists a natural stream flow development

    through the main addit entry towards the upper opening of the auxiliary shaft due the differences

    in wind speeds in the respective hights. Thus the natural ventilation is pretty high and the

    Skip or Cage

    Ser

    vic

    es f

    acil

    itat

    ing a

    rea

    Blind shaft

    Guide vain

    Dimension in ft

  • Design Project 2015

    22

    ventillation by fans will be only needed after the first levels of the workings have advanced to a

    significant distance .

    Figure 2.5 Auxiliary shaft Dimensions

    3.2.4 Blind shaft & auxiliary shaft sinking

    The whole operation can be emphasized as the following sequence of points.

    Preparation for blasting (Cleaning and marking of the blast face)

    Drilling

    Charging and Blasting

    Washing & scaling

    Mucking

    Supporting

    This is a cyclic process. Once the sequence has reached to supporting stage again another blasting has to be

    undertaken. It is evident that the presence of the river will cause the water table to rise. When the water

    Dimension in ft

  • Design Project 2015

    23

    table is closer to the surface, dewatering process becomes a need. Not only that the blasting agents and the

    explosives also must be selected based on their ability to withstand wet conditions. Therefore water

    resistant explosives should be used.

    The following information are assumed in this design.

    Shaft area = 5.2m2

    Bit size of the drilling machine =38 mm

    Advance of the shaft per round = 1m

    Number of holes per round = 60

    Powder factor for the blast = 3.1 kg /m3

    Romanic Numbers half second delay

    Arabic numbers m second delay

    Figure 2.6 Main shaft & Auxiliary shaft blasting pattern

    Dimension in ft

  • Design Project 2015

    24

    Due to the presence of the river the water table might well be very close to the surface of the area.

    Therefore the mine shaft conditions are ought to be wet. It is important to use gelatineous water-

    resistant explosives. After drilling the holes must be blown out with compressed air. The premier

    cartridge must be inserted first into the hole, the detonator pointing to the main charge. The final

    trimmer holes should be drilled with a slightly smaller burden and loaded relatively lightly.

    3.3 Shaft lining Since the area geology is to be assumed that of a strong self-supporting type we can use concrete

    lining for the shaft. There is no seepage assumed because the shaft sinking location was selected

    avoiding the buffer zone of the river. The shaft collar is developed to the bed rock and at the shaft

    location it is assumed to be reaching the bed rock at a depth of 30 m. therefore the length of the

    drill collar is considered as 30 m and the thickness of the concrete wall of the collar is set in three

    different phases.

    For the first 15 m from the surface the thickness of the shaft collar is set as 1 m

    For the next 10 m it is set as 0.7 m.

    From 25 m to 30 m the thickness is set as 0.5 m.

    The winch is located at the same level where the top of the blind shaft lies, on top of the drill

    collar, using a steel structure as shown in the figure below. A very accurate survey has to be done

    to position the winch.

    Figure 2.7 The winch and the steel structure

  • Design Project 2015

    25

    3.4 Cross cut

    In this particular design the cross cuts are designed to be arched shape and are to be driven with a dip of

    0.005 towards the mouth. No extensive timbering is to be use. The cross cuts are designed to be of the

    shortest length from the main addits to the ore bodies, so that the cost would be minimum.

    The cross cuts are the developments used to reach the working areas of the mine. Therefore the

    ventilation and the electricity supplies have to be transported through these. As shown in the

    figure below the ventilation duct and the electricity lines are placed on to the left top corner of the

    cross cut cross section. There should be a spacing in between those and the mine cars as well as

    the men who are travelling in the cross cut. That is the reason why spacing is provided as shown

    in the figure.

    Figure 2.8 The cross cut with dimensions

    Dimension in ft

    Cross cut

    Ventilation

    Electrical Line Ore Transportation

  • Design Project 2015

    26

    The following figure exhibits the drilling pattern as well as the blasting sequence at the same time.

    To come to the conclusion regarding the number of drill holes and the advance of the shaft per

    one cycle of the process a small calculation has been done as follows.

  • Design Project 2015

    27

    Cross cut area = 4.1m2

    Bit size of the drilling machine =38 mm

    Advance of the shaft per round = 1m

    Number of holes per round = 37

    Powder factor for the blast = 2.5 kg /m3

    Figure 2.9 The blasting pattern of the cross cut

    Dimension in ft

    Cut Hole (64 mm)

    Drill Hole (32 mm)

    0

    0 0

    0

    ii

    ii

    ii

    ii

    Iv

    iv iv

    iv

    Iv

    vi

    vi

    iv

    3 3 3

    4

    4

    4

    4

    5

    5

    5

    vi

    6 6 6

    7 7

    8 9

    9

    9

  • Design Project 2015

    28

    3.5 Mining method

    3.5.1 Overhand cut and fill method

    Overhand cut and fill mining is a highly selective open-stope mining method considered ideal for

    steeply dipping high grade deposits found in weak host rock. Many variations of the general cut

    and fill technique exist. Overhand cut and fill evolved from square set stull stoping to provide

    stronger support. In this method, mining begins at the bottom of the ore body or block and

    progresses upward.

    During the mining sequence, the back of the excavation is to be temporarily supported using rock

    bolts before the stope is back filled to form the floor of the next level of development. Backfill is

    designed to provide mild excavation support as well as to provide a strong working floor for

    personnel and equipment. Backfill selection is dependent on the quality of the host rock and the

    size of equipment operating on top of the backfill.

    Figure 2.10 The ore blocks created to be mined

    In this particular design the height difference between the two levels is set to be about 40m. This

    undercut will form the transport drift from which ore will be removed by rail cars. The winzes

    were sunk from top level to bottom level in order to connect drives vertically. As we proceeds

    upwards, first one or two benches are to be kept vacant and the backfilling from the next bench is

    started. The reason for doing this is that we need that space to construct the haulage way and to

    install machinery, such as winches, pumps, etc.

  • Design Project 2015

    29

    Figure 2.11 The layout of the mine with cross cuts, winzes and shafts

    Advantages and Disadvantages of this Mining Method

    Advantages

    High selectivity and low dilution ma achieved

    Minimal development is required; low capital cost

    Versatile for mining method; can follow irregular ore bodies

    Flexible; mining method can be easily modified

    Low equipment investment relative to other methods

    Minimizes ground movement

    Disadvantages

    Cyclical ore production

    Labour and skill intensive

    Auxiliary shaft

    Ore body

    Drift

    Winzes

    Addit

    Cross Cut

  • Design Project 2015

    30

    Dangerous working conditions; work conducted on a top of freshly blasted rock

    High degree of ground control required

    Expensive and costly ventilation system

    Need for backfill infrastructure (piping and paste plant)

    Not suitable for low grade ore due to high mining cost

    The extraction operation is done in the traditional way, i.e. drilling and blasting. The drift is to be

    developed along the vein. The figure below illustrates the blasting sequence and the pattern.

    Figure 2.12 The extraction procedure

    The portion of the vein in a given cross sectional area is to be initially drilled, charged and

    blasted. After that mucking has to be taken place. When that is finished the remaining portion of

    the drifts cross section is drilled, charged and blasted to trim the edges in order to retain the shape

    of the drift. After the execution of the whole operation of drilling, charging and blasting a total of

    a 1 m advance is expected. At maximum of a two days duration the whole cycle is expected to be

    finished. Hence the rate of advancement of a drift is 1 m per two days.

  • Design Project 2015

    31

    3.6 Mine Layout

    The below figure shows the whole layout of the mine discussed so far. The two blind shafts

    connect to the auxiliary shaft through cross cuts. The auxiliary shaft is located at a position where

    the optimum use of the natural ventilation flow can be utilized and the distances to the ore bodies

    are minimized. Winzes and the drives are going along the ore body in different directions.

    Figure 2.13 3D view of the mine lay out

  • Design Project 2015

    32

    3.7 Underground transportation system

    In this particular mine, rail tracks and locomotives are used as the underground transportation

    system. The length of rails used in mines varies from 3 m to 7 m. The size chosen at a

    particular mine often depends on the limitations imposed by the shaft and

    transport arrangements. The aim should be to select the longest length of rail,

    which reduces the number of joints needed when it is installed. This will also result

    in a reduction in supply and maintenance costs. In this mine 7 m long rails are to be used.

    The minimum weight of rail recommended for any new installation

    underground in mines is 17.36 kg/m (35 lb/yd). Based on the expected production at the initial

    stages of the mine these minimum weighted rails are to be used.

    Figure 2.14 The dimensions of the rail cross section

    In this particular design of the mine, the use of locomotives is omitted since the cut and fill mining

    operation for such a narrow vein might not incur such a need.

    The next most important part of the rail track is the use of sleepers. Sleeper spacing is the distance

    between the centres of adjacent sleepers.

    The following sleeper spacings have proven acceptable in practice and should not be exceeded

    o locomotive track 840 mm;

    o man riding rope-haulage track 840 mm;

    o non-man riding rope-haulage track 1000 mmsince this design is for non-

    manriding rope-haulage track, the spacing should be taken as 1000 mm.

  • Design Project 2015

    33

    Mass of rail

    (kg/m)

    Maximum axle

    load (tonnes)

    Distance between

    sleepers (mm)

    Factor of

    Safety

    30.54 7.5 840 4.1

    24.8 7.5 840 3.1

    17.36 4 1000 2.5

    Table 2-2 Factor of safety for the rails

    The factor of safety for 17.36 kg/m rail is relatively low, and the maximum axle

    loading of 4 tonnes is considered to be an abnormal load, which is carried only infrequently,

    and not the regularly carried load. Fixed mine cars are used in this transport system. Their gauge

    width is approximately 2 feet.

    Considering the requirements MGC 1.7-6 mine cars can be recommended as more suitable for the

    mineral transport operation (appendix iii).

    Figure 2.15 The mine car with dimensions

    The broken ore is directly transported to the mineral processing plant located at the point

    specified. When the processing plant is to be located lot of factors have to be considered. The

    accessibility of the location is the major point in a project like this which is situated in a hilly

    terrain. Considering that and also the distance to be travelled from both the main addits, a location

    for the processing plant is identified.

  • Design Project 2015

    34

    3.8 The conveyor belt system

    The ore has to be transported from the mine to the processing plant. In this design, there is a

    conveyor belt system between the mine and the processing plant. This enables the continuous

    operation of the mine. The guidelines for the design of the conveyor system are as follows.

    Power system

    Standardized three-phase squirrel-cage motors with star-delta start are preferable. The starting is

    usually smooth. The belt speed is often controlled through an electronic frequency inverter.

    Driving pulley

    Here cylindrical conical shape driving pulleys are used since they will also produce a self-centring

    effect on the running behavior of the belt. Clean, oil- and grease-free steel pulleys with a smooth,

    almost polished surface (corresponding to a roughness Ra = 1.6 m) are in most cases sufficient to

    ensure slip-free power transmission.

    Pulley design

    Since, conical cylindrical pulleys are used in the design, the following condition for the

    admissible deflection y caused by the tension can be emphasized.

    Figure 2.16 The deflection of the pulley

    For Cylindrical-conical pulleys:

    y (0.001 d) + 0.07 *mm+

  • Design Project 2015

    35

    Pulley width

    Pulleys and rollers should be wide enough so that the belt would make full contact with them over

    its entire width, even when it is not positioned on the exact centre of the pulley.

    Figure 3.17 Pulley width

    Belt width bo Pulley width b

    bo 100 mm b = bo + 20 mm

    bo > 100 mm b = (1.08 bo) +

    12 mm

    Table 2-3 Pulley width recommendations

    Multiple rollers are expected to be fixed on the path of the conveyor belt.

  • Design Project 2015

    36

    3.8 Ventilation methods

    3.8.1 Stope ventilation methods

    The objective of any ventilation system is stage. First, the primary ventilation must course air

    through the main airways to the immediate working area out by the working faces, thus making

    fresh air available for face ventilation, and then return the contaminated air through return

    (exhaust) airways to the surface. Second, the face ventilation system must be designed to

    effectively utilize the available air in the immediate working area to sweep the working face, to

    capture and remove dust, and to dilute and carry away gas, if any, emitted during mining

    activities.

    Without a properly designed ventilation system, an efficient production cycle would not be

    possible. The system should provide the required air volumes and quality at reasonable pressure

    losses, perform with minimum interference and cost to production, and do so in the most cost-

    effective way possible. Furthermore, the primary ventilation system may be well designed, but if

    the available air brought to the working area is not properly utilized for ventilating the faces

    where most workers are located, the total system has failed.

    Stope Ventilation

    Separate ventilation shaft(in this design the auxiliary shaft) is used to the mine layout to throw the

    air out from mine. Air is sucked from the mine main shaft down to lower level and air circulate

    through all the working areas and used unclean air goes up through the winzes developed at the

    ore body into ventilation shaft. Two or three Centrifugal fans can be installed on the surface at the

    entrances of the two addits. Because of the fact that if one fan fails a specific amount of the total

    air volume can be provide from rest. It is possible for the fan to be located directly on the top of

    the auxiliary shaft. But usually air is turn through the right angle at the shaft collar and reach the

    fan through an inlet drift and set of self-closing door. For Specification for centrifugal fan refer

    appendix iii.

    All stopes are ventilated by the fresh air flowing up from the lower level of the stope. There are

    two raises constructed at each end of the stope. Air enters the raises at the bottom level and flows

    up the raise and then enters the stope and exits through the other raise, depending on the pressure

    difference. When stopes are mined out, the raises are closed, thus the movement of airflow was

    affected. Similarly, when new raises are constructed for stoping, airflow is also affected.

  • Design Project 2015

    37

    Therefore, there is a need to continuously monitor the movement of air especially in the stope

    where miners are working. This study is conducted to assess the movement of air in the stope.

    A mine ventilation booster fan is a primary fan that is in series with another primary fan. Without

    the booster fan operaton, the total mine airflow will fall significantly. Booster fans are typically

    installed as mine develops and primary fan no longer has the pressure or flow capability to service

    increased resistance of operation. In this sense, booster fan operates as an integral and symbiotic

    unit with original primary fan to provide sufficient total airflow for mine.

    Figure 2.16 Stop ventilation plan

    Mine booster fans are technically main fans which are installed underground to maintain required

    airflow by overcoming the mine resistance. Booster mine ventilation fans can reduce pressure of

    main fan and decrease system leakage and total required air power.

    A mines booster fan is an underground ventilation device installed in the main airstream (intake or

    return) to handle quantity of air circulated by one or more working districts. It is installed to

    operate in series with a main fan and boost air pressure of ventilation air passing through it.

    Specifications for the booster fans are given in appendix iv.

    Air input

    Air output

  • Design Project 2015

    38

    3. REFERENCES

    http://www.slideshare.net/hzharraz/lecture-1-9998430

    o Accessed on 24-11-2014

    Evaluation of Overhand Cut and Fill Mining Method used in Bogala Graphite Mines,

    SriLanka; P G R Dharmaratne, P V A Hemalal and M C Hettiwatte

    o Accessed on 22-11-2014