Design, validation and commissioning processes for metal structures belonging to the railway signaling infrastructure Faculty of Civil and Industrial Engineering Master Degree in Transport Systems Engineering Course of Railway Engineering Candidate Fatima Chemsi Supervisor External Supervisor Prof. Eng. Stefano Ricci Eng. Claudio Cantatore

Upload: others

Post on 18-Oct-2021

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Design, validation and commissioning processes for metal

Design, validation and commissioning

processes for metal structures belonging to the

railway signaling infrastructure

Faculty of Civil and Industrial Engineering

Master Degree in Transport Systems Engineering

Course of Railway Engineering

Candidate

Fatima Chemsi

Supervisor External Supervisor

Prof. Eng. Stefano Ricci Eng. Claudio Cantatore

Page 2: Design, validation and commissioning processes for metal

The present thesis was written within an internship in

Bombardier Transportation

Page 3: Design, validation and commissioning processes for metal

"If I have seen further it is by standing on the shoulders of Giants."

(Isaac Newton)

My first acknowledgements go out to the professors that I have had the honor

of learning from all along this degreeโ€™s program, who with their passion and

sincere dedication have transmitted to me valuable knowledge and above all

the continuous desire to learn.

I thank in particular Professor Stefano Ricci, the supervisor of this thesis, for

his time, dedication and support by every means possible at every step of the

writing process.

I would also like to thank the people of Bombardier Transportation;

Eng. Diego Marino for offering me the unequaled opportunity to conduct my

thesisโ€™ internship within one of the leading companies in the world in the

railway sector.

Eng. Claudio Cantatore, my supervisor in the company, for providing me

with the help and the necessary support to complete my work.

And Eng. Alessio Spaziani, for his kindness and for always being available

to help me during this process.

I also thank Eng. Salvatore Musella and Eng. Nicolรฒ Di Domenico of Rete

Ferroviaria Italiana for the kindness with which they helped me and for

having provided me with the material I needed to write this thesis.

I write it on this page and I will not fail to tell you out loud, THANK YOU!

Thanks to my family for encouraging me through all these years, especially

my parents for their everlasting support both financially and morally. Thank

you for accompanying me with every means possible to the top of the

springboard. Thank you for making this day possible.

I thank Marta for always being there.

I thank my friends for making the difficult days a little less difficult and for

helping me overcome the obstacles more lightly and with a smile.

A heartfelt thank you to all!

Fatima Chemsi

Rome, January 21th 2019

Page 4: Design, validation and commissioning processes for metal

Table of contents

Table of contents 4

List of figures: 6

List of tables: 8

CHAPTER 1: OBJECTIVES OF THE THESIS 1

CHAPTER 2: INTRODUCTION TO RAILWAY SAFETY AND SIGNALING SYSTEMS 4 2.1 Evolution of safety and line signaling systems: 10 2.2 Description of the structures supporting the signaling infrastructure: 31

2.2.1 Fiberglass poles 31 2.2.2 Signal Cantilever bridge 34 2.2.3 Signal Bridges 36

CHAPTER 3: INPUT NECESSARY FOR THE PRELIMINARY DESIGN OF THE STRUCTURES 37 3.1 Railway track Planimetry 38

3.1.1 Transition curves 39 3.1.2 Switches 43

3.2 Railway track cross sections 46 3.3 Schematic signaling plan 48

CHAPTER 4: GEOMETRIC DEFINITION OF THE STRUCTURES 52 4.1 Analysis of the schematic signaling plan 52 4.2 Analysis of the track planimetry 53 4.3 Analysis of the cross section drawings 54 4.4 Staking operations 56 4.5 Design of the structures 58

4.5.1 Choice of the type of structure to be designed 58 4.5.2 Definition of the geometric measurements of the structure: 66

4.6 Selection of structure types to be designed by the structural engineer 68

CHAPTER 5: STRUCTURAL DESIGN 71 5.1 Documentation to be supplied to the structural engineer 72

5.1.1 Geological and seismic report 72 5.1.2 Geometric characteristics of the structures 90 5.1.3 Loads to be assigned to the structures 90

5.2 Documentation supplied by the structural engineer 90 5.2.1 Technical report 90 5.2.2 Construction (or detailed) design of the structure 131 5.2.3 Maintenance plan 133

CHAPTER 6: PRODUCTION AND FACTORY ACCEPTANCE OF STEEL STRUCTURAL ELEMENTS 145

6.1 Processes for production of structural steel 145 6.1.1 Cast iron transformation process: 145 6.1.2 Steel rolling 150 6.1.3 Rolling defects: 151

6.2 Regulatory framework for the production of hot laminates for structural steel 152 6.2.1 Controls on steels (for concrete reinforcement or for metal structures): 154 6.2.2 Processing centers (or transformation centers): 156 6.2.3 Laboratory tests to be performed on structural steel rolled products: 157 6.2.4 Checks of bolted joints 164

Page 5: Design, validation and commissioning processes for metal

6.3 Welding process: 165 6.3.1 Types of welding: 167 6.3.2 Welding techniques: 168 6.3.3 Regulatory framework for welding processes of structural steel elements: 169

6.4 Factory acceptance of the structure 170

CHAPTER 7: ACCEPTANCE OF THE STRUCTURE AND CONSTRUCTION OF THE PLINTH AT THE BUILDING SITE 174

7.1 Acceptance of the structure materials on-site before starting the construction 174 7.1.1 Steel 175 7.1.2 Concrete 179

7.2 Construction of the plinth on site 183 7.3 Assembling of the structure on-site: 188

7.3.1 Analysis and assessment of possible risks 189 7.3.2 Instructions for workers 190 7.3.3 Emergency procedures 192 7.3.4 Mounting of structures 192

CHAPTER 8: COMMISSIONING OF THE STRUCTURE AT THE BUILDING SITE 197 8.1 Load tests 199

CHAPTER 9: CONCLUSIONS 201

APPENDIX A: Examples of cross sections located in the Casablanca triangle 202

References 207

Page 6: Design, validation and commissioning processes for metal

List of figures: Figure 1: Signal Cantilever bridge ......................................................................................................... 1 Figure 2: Signal bridge .......................................................................................................................... 1 Figure 3: Manual signal ...................................................................................................................... 10 Figure 4: Disc signal ............................................................................................................................ 14 Figure 5: Wing signal (main signal) .................................................................................................... 14 Figure 6: Wing signal (advance signal)............................................................................................... 15 Figure 7: Candlestick signal ................................................................................................................ 15 Figure 8: Fixed light signal .................................................................................................................. 17 Figure 9: Minimum visibility distance as a function of the maximum permitted speed ..................... 20 Figure 10: Line buoy ........................................................................................................................... 23 Figure 11: Monitor SCMT+RSC ........................................................................................................... 24 Figure 12: Indication authorizing maximum speeds of 300 km/h ...................................................... 24 Figure 13: Indication authorizing maximum speeds of 270 km/h ...................................................... 24 Figure 14: : Indication authorizing maximum speeds of 160 km/h .................................................... 24 Figure 15: : Indication that invites the train to stop before the first signal detected ......................... 24 Figure 16: Indication that orders the driver to travel on sight stopping before the first signal detected ............................................................................................................................................. 25 Figure 17: Control signal - lanterns .................................................................................................... 27 Figure 18: Operating light signal ........................................................................................................ 27 Figure 19: Control signals on the right side of the track .................................................................... 28 Figure 20: : Identification table for LC according to FS ....................................................................... 29 Figure 21: Diagram of automatic LC signals arrangement according to FS ....................................... 29 Figure 22: Fiberglass pole ................................................................................................................... 32 Figure 23: Standard dimensions of a 2 lights main signal in FS ......................................................... 33 Figure 24: Signal cantilever bridge installed along the Casablanca-Tangier line ............................... 34 Figure 25: Signal Cantilever bridge schematic representation .......................................................... 36 Figure 26: Signal Bridge installed along the Casablanca-Tangier line ............................................... 37 Figure 27: Example of a railway track planimetry .............................................................................. 39 Figure 28: Equilibrium of a vehicle running a curve ........................................................................... 40 Figure 29: Equilibrium of a vehicle running a curve with a cant ........................................................ 40 Figure 30: Example of the transition curves tables contained in a railway track planimetry ............ 42 Figure 31: : Representation of tangency points between planimetric elements in a railway track planimetry .......................................................................................................................................... 43 Figure 32: Switch example ................................................................................................................. 43 Figure 33: Switch schematization ....................................................................................................... 44 Figure 34: Train wheelset running on a track ..................................................................................... 45 Figure 35: Example of switch tables contained in a railway track planimetry ................................... 46 Figure 36: Schematization of the railway superstructure and characteristics measurements........... 47 Figure 37: Example of a schematic signaling plan ............................................................................. 49 Figure 38: Elements of the schematic signaling plan - schematization of the joint ........................... 49 Figure 39: Elements of the schematic signaling plan - schematization of double comunication ....... 49 Figure 40: : Elements of the schematic signaling plan - schematization of signal portals ................. 50 Figure 41: : Elements of the schematic signaling plan - schematization of signal cantilever bridges 50 Figure 42: Elements of the schematic signaling plan - schematization for reflecting signs ............... 50 Figure 43: Elements of the schematic signaling plan - schematization of signal for ending zone at limited speed ...................................................................................................................................... 50 Figure 44: : Elements of the schematic signaling plan - schematization of banalized line ................ 50 Figure 45: : Elements of the schematic signaling plan - definition of the action zone boundaries of a control post ........................................................................................................................................ 51 Figure 46: Two-dimensional schematic representation of the overhead line system indicating key elements. Dimensions indicate typical values .................................................................................... 55 Figure 47: Electric traction infrastructure .......................................................................................... 56 Figure 48: Signal portal referring to 2 tracks ..................................................................................... 60 Figure 49: Interaxis representation .................................................................................................... 60

Page 7: Design, validation and commissioning processes for metal

Figure 50: vehicle's overall dimensions when cornering .................................................................... 61 Figure 51: Gabarit categories according to SNCF ............................................................................... 62 Figure 52: International gauge G1 and national gauges ................................................................... 63 Figure 53: Example of correct spacings between plinth and rail ........................................................ 64 Figure 54: Example of the installation of a signal cantilever bridge in presence of an obstacle ........ 65 Figure 55: Example of installation of 2 signal cantilever bridges instead of a simple portal due to the altitude difference between the tracks .............................................................................................. 66 Figure 56: Example of incorrect mounting of the signal cage ............................................................ 68 Figure 57: Example of correct installation of the signal cage ............................................................ 68 Figure 58: signal bridge with 2 cantilever beams ............................................................................... 69 Figure 59: ZS9 seismogenic zonation.................................................................................................. 75 Figure 60: Seismic hazard values according to OPCM 3519/2006 ..................................................... 76 Figure 57: Seismic zonation in terms of Amax for RPS2011 ............................................................... 77 Figure 58: Seismic zonation in terms of Vmax for RPS2011 ............................................................... 77 Figure 63: Coring procedure with direct circulation of fluids ............................................................. 80 Figure 64: Example of extruding the soil from the core drill .............................................................. 81 Figure 65: Example of core sample storage ....................................................................................... 81 Figure 66: Standard penetration test ................................................................................................. 82 Figure 67: Stress and deformation diagram for steel ......................................................................... 93 Figure 68: Stress and deformation diagram for concrete .................................................................. 96 Figure 69: Concrete reinforcement steel ............................................................................................ 97 Figure 70: Stress and deformation diagram for reinforcement steel ................................................. 98 Figure 71: Characteristic values of qsk actions for vertical surfaces parallel to the track ................. 107 Figure 72: Characteristic values of qsk actions for horizontal surfaces parallel to the track ............ 108 Figure 73: Characteristic values of qsk actions for vertical surfaces parallel to the track................ 108 Figure 74:Illustrations of the exposure factor ce(z) for c0=1,0, k=1,0 ............................................... 114 Figure 75: Principal system............................................................................................................... 117 Figure 76: Deformations of the principal structure with the deformation method.......................... 117 Figure 77: Form functions with higher than 1 Figure 78: Linear form functions ................... 121 Figure 79: Local reference system for the rods................................................................................. 124 Figure 80:Local reference system for the shell element ................................................................... 124 Figure 81: Design response spectrum............................................................................................... 127 Figure 82: Representation of the Winkler model for the foundation ground ................................... 129 Figure 83: Joint detail nยฐ1 of executive project drawing .................................................................. 132 Figure 84: Example of Plinth details of an executive project drawing.............................................. 132 Figure 85: Joint detail nยฐ2 of executive project drawing .................................................................. 133 Figure 86: Schematic representation for plinth subsidence ............................................................. 138 Figure 87: Example of moisture penetration .................................................................................... 139 Figure 88: Example of cracking, detachment of concrete and rust formation on reinforcement steel.......................................................................................................................................................... 140 Figure 89: Bessemer converter ......................................................................................................... 148 Figure 90: L.D converter ................................................................................................................... 149 Figure 91: Electric furnace ................................................................................................................ 149 Figure 92: Steel rolling ...................................................................................................................... 150 Figure 93: General scheme of rolling processes ............................................................................... 151 Figure 94: Rolling defects ................................................................................................................. 152 Figure 95: Sampling indications for testings according to UNI EN 10025-1 standard ..................... 159 Figure 96: Sampling indications for testings according to UNI EN 10025-1 standard ..................... 160 Figure 97: Resilience test on steel .................................................................................................... 162 Figure 98: Test specimens for resilience test (dimensions are indicated in mm) ............................. 162 Figure 99: Brinell hardness test ........................................................................................................ 163 Figure 100: Elements constituting a bolt .......................................................................................... 165 Figure 101: Excavation scheme forformworks ................................................................................. 186 Figure 102: Plinth-column coupling detail ........................................................................................ 187 Figure 103: Executive project drawing for plinth-column coupling .................................................. 187 Figure 104: Example of the introduction of anti-shrinkage expansive mortar ................................. 188 Figure 105: Example of steel dowel pins .......................................................................................... 194

Page 8: Design, validation and commissioning processes for metal

Figure 106: Example of torque wrench ............................................................................................ 195

List of tables:

Table 1: Parameters for the definition of clothoids _______________________________________42 Table 2: Comparison between requested investigation and executable investigations for the structures _______________________________________________________________________78 Table 3: Soil categories accordin to the DM 17-01-2018 __________________________________87 Table 4: Topographic categories according to the DM 17-01-2018 __________________________89 Table 5: Maximum values of the topographic amplification coefficient ST ____________________89 Table 6: Exposure classes for concrete according to UNI EN 206-1 ________________________ 101

Page 9: Design, validation and commissioning processes for metal

1

CHAPTER 1: OBJECTIVES OF THE THESIS

The present thesis aims to define a process covering the preliminary and

construction design phases, up to the manufacturing, construction and

commissioning of the steel structures belonging to the railway signaling

infrastructure. These structures are:

Signal cantilever bridges

Figure 1: Signal Cantilever bridge

Signal bridges (or portals)

Figure 2: Signal bridge

Page 10: Design, validation and commissioning processes for metal

2

The definition of these processes aims to create a reference guideline for all

the stakeholders that will be involved in the project, defining design criteria

and parameters to be considered and evaluated during the design,

manufacturing and construction phases in order to avoid errors, delays and

therefore increases in costs.

The need to define a reference for the design and construction of these

structures derives from the lack of relevant international standards or

Country-specific railway administration regulations covering the whole

process from the preliminary design to the commissioning.

Unlike other structures for which standardized technical and dimensional

specifications exist and may vary according to local regulations, for these

structures are not present. The motivation for this lies in the variability of

working hypotheses and site conditions that have to be considered.

The project underlying the thesis, which showed the need to implement these

guidelines, is located in the Kingdom of Morocco and in particular in what is

called the Casablanca triangle, consisting of the following stations:

โ€ข Casa Port;

โ€ข Ain Sebaa;

โ€ข Casablanca Voyageurs.

After a brief description of these structures, the input documents that are

provided for the design and construction of these structures will be analyzed

in order to establish which input documents must be requested at a

preliminary stage.

The description of the pre-sizing process of the structures will continue, with

the identification of the location within the railway track and the study of the

visibility of the signal.

Page 11: Design, validation and commissioning processes for metal

3

The structural design of the works will require a structural engineer who will

have to realize the project of the steel works (the portals themselves) and their

foundations.

The projects defined in this way must be delivered to the factory which will

take care of the supply of certified and CE-marked steels according to the

European standards of the rolling processes and construction of the

structure. In these guidelines, in addition to the specifications on materials,

the criteria for acceptance of the structure at the factory will also be defined.

While the structure is made in the factory and then assembled on site, the

foundation is excavated and cast-in-place. Also for this, however,

requirements for acceptance of materials (concrete and steel for

reinforcement) and criteria for their realization will be defined.

Finally, the commissioning processes for the structures, with the description

of on-site verifications to be performed will be specified.

Briefly, the end goal of this thesis is to create a procedural standard to be used

in every contract that requires the design and construction of metallic

structures necessary for railway signaling, in order to allow a precise and

organized management of the process starting from the first preliminary

stages to the completion of the work.

Page 12: Design, validation and commissioning processes for metal

4

CHAPTER 2: INTRODUCTION TO RAILWAY

SAFETY AND SIGNALING SYSTEMS

The railway signaling systems constitute that set of devices which are in

charge of the exchange of information between the fixed installations and the

moving vehicle with the purpose of ensuring that the train's journey takes

place under conditions of safety while ensuring high availability of the

infrastructure.

The objectives of the signaling system are many, but can be summarized in

five main points:

Allow a spacing of traffic;

Ensuring the protection of traffic at the turnouts at the station;

Manage traffic on railway tracks;

Avoid derailments due to excessive speed;

Protect level crossings.

To obtain the spacing, the line is subdivided into elementary sections, called

Block Sections, of variable length (e.g. in Italy at RFI it is generally 1350 m).

On each block section only one train can circulate at a time.

As can be seen from the definitions, security is at the basis of signaling. In

each transport system, it is possible to recognize two distinct groups of

security conditions:

โ€ข The safety in the motion of a single train: function of the road safety

and of the vehicles constituting the train;

โ€ข The safety in the motion of each train placed in relation to the

simultaneous circulation at the same site of other vehicles of the same

Page 13: Design, validation and commissioning processes for metal

5

type or even of different types (such as road traffic at level crossings):

in this case there are a set of rules and precautions to guarantee that a

train will occupy a certain stretch of track. In fact, the track is viable

only when the route is free from other trains circulating in the same

block section and also from maneuvers. To make this possible, while

the train considered runs through the block section, the track canโ€™t be

occupied by the contemporary motion of other trains and even

maneuvers are forbidden.

Unlike the road case, the freedom of the block section canโ€™t be ascertained by

the train driver. In fact, this is not possible taking into account the train speed

and its corresponding long braking distances and the fact that the driver canโ€™t

have the certainty of the freedom of the route on long distances. Therefore,

at least in the traditional systems, it is the ground personnel that manages the

traffic, to ascertain the state of freedom of the route and to inform the train

driver about it. Information is provided by means of signals whose meaning

is preventively and unequivocally established. Optical signals can also be

used together with on-board systems supporting the driver directly in

his/her cab or even replaced by other means, thanks to the new developed

technologies.

Generally, to ensure the safety conditions on the line, when a train leaving a

station must reach the next station it is necessary to follow these steps:

โ€ข Ascertaining the freedom of the section between the two stations:

this assessment is responsibility of the train Movement Director of

the departure station;

โ€ข Permissive disposal of a starting signal at the departure station;

Page 14: Design, validation and commissioning processes for metal

6

โ€ข Occupation of the above signal followed by the immediate return

to the stop aspect as the train passes it, in order to prevent a second

train to consider the indication of green light valid;

โ€ข Blocking the route section;

โ€ข Clearance the route section and making it usable for the next train.

In stations, these phases are implemented with further phases mainly due to

the presence of turnouts:

โ€ข Route setting, arrangement of the switches according to the route

that the train must travel;

โ€ข Switch locking, guaranteeing that the position of the switches

remains secured in the required position;

โ€ข Check of route compatibility and assumption of certainty that

incompatible routes will not be defined at the same time;

โ€ข Verification of freedom of the route section;

โ€ข Permissive aspect of the signal for allowing train departure over

that route, blocking the route and the position of its switches, until

the route has been completely traveled by the train;

โ€ข Signal occupation;

โ€ข Route release, once it has been completely traveled.

These phases must be observed both in the case where safety is entrusted

exclusively to manual controls and operations as well as if it is entrusted to

fully automatic systems (e.g. interlocking systems).

There are fundamental concepts underlying railway signaling and safety:

Fail-Safe;

Page 15: Design, validation and commissioning processes for metal

7

Redundancy;

Wired logic systems. Relays;

Programmed logic systems.

Fail-Safe refers to those systems for which any failure causes a situation of

lesser usability but equal safety, i.e. a more restrictive situation for

circulation until the trains running on the fault-affected section have come

to a complete standstill, at the limit. An example of a suitable Fail-Safe

system is the so-called cycle control. The operations of trains on a line

section are repetitive actions that follow one another according to certain

cycles. Fail-safe safety can be achieved by allowing each phase to start only

if the previous phase has had a complete and regular course: in this way

any anomaly prevents the succession of the cycle phases, thus blocking the

circulation.

On the other hand, the redundancy method, requires that, for a complex

plant, redundancy is achieved at least by doubling the conditions that must

be met in order to achieve a given operation. An example of a redundancy

method may be spatial duplication, obtained by using two or more

independent devices that must simultaneously provide matching output

signals.

In general, between fail-safe and redundancy criteria, it is preferable to

focus more on fail-safe criteria, as they allow high levels of security to be

guaranteed at a competitive cost.

The translation of these two principles has led to the introduction in the

railways of logic systems wired via relays, using this as an elementary

component through which it is possible to design and compose more and

more articulated circuits.

Page 16: Design, validation and commissioning processes for metal

8

The relay is still the main component of the safety and signaling systems,

and it is precisely that elementary logic device through which increasingly

complex modules and schemes can be created.

Regarding safety and signaling systems, we refer to electric relays, which

can be used:

โ€ข To replace a weak incoming power supply with a more

robust one;

โ€ข To replace an incoming power supply with an output

power supply of different characteristics;

โ€ข To multiple from a single incoming power supply to

several outgoing circuits.

Programmed logic systems are made by using electronic components and

software program processing. The use of this more flexible and easily

applicable technology, in relation to the reduction of space requirements

(e.g. for relay cabinets) and lower costs in large-scale use, has allowed the

introduction of a new way of designing and implementing safety and

signaling systems. In this case, safety-critical applications are defined, in

which fail-safe conditions are guaranteed by means of safeware

technologies, i.e. safety is entrusted to the result of processing logic

(software) and to electronic components (hardware) with safety features.

At European level, this new technology has led to the introduction of the

following standards for both electromechanical and electronic systems:

โ€ข EN 50124, coordination of the isolation: This European

standard concerns the coordination of insulation in the

railway sector. It applies to signaling, rolling stock and

Page 17: Design, validation and commissioning processes for metal

9

fixed installation equipment. These standards therefore

cover the isolation of electrical and electronic devices. One

objective of insulation coordination is to avoid oversizing

of the insulation itself.

โ€ข EN 50126, The specification and demonstration of

reliability, availability, maintainability and safety (RAMS):

this standard defines the characteristics of availability,

reliability, maintainability and safety of the systems, as

well as the set of technical and functional requirements for

the proper implementation of a system.

โ€ข EN 50128, Telecommunication, Signalling and Processing

Systems - Software for Railway Control and Protection

Systems: This standard focuses on the methods that need

to be used to provide software that meets basic safety

integrity requirements.

โ€ข EN 50129, Railway applications - safe electronic systems

for signaling: this standard covers the requirements for

computerized rail signaling systems, considering safety

aspects.

โ€ข EN 50159, Fixed installations - contact wire belonging to

railway electric traction systems: this standard applies to

the design and construction of contact wires for the

railway electric traction infrastructure, tram and metro, for

complete renewals in electrified sections or new

electrifications. The standard contains the design

requirements, the elements for testing the lines and some

components and the methods for dimensioning the

structures.

Page 18: Design, validation and commissioning processes for metal

10

2.1 Evolution of safety and line signaling systems:

On the first railway lines there were no safety systems and the signals were

made by colored flags or, at night, by colored lanterns.

Figure 3: Manual signal

Generally, trains stopped at all stations and the information was

communicated directly to the drivers by the train movement director

(TMD).

The first system used by the TMDs to define when trains could leave the

station was the time-distance system: a train could only be forwarded after

a certain time had elapsed since the departure of the previous train. The

protection in the event of an anomaly with a train stopped on the line was

provided by the train staff through the exposure, at a reasonable distance,

of hand signals.

This type of system did not guarantee absolute safety and would not have

been suitable for higher speeds and greater circulation.

Subsequently, space-based distance systems were developed based on the

criterion that ensures the presence of only one train at a time between two

Page 19: Design, validation and commissioning processes for metal

11

successive distance points (block sections). In single-track lines, therefore,

were defined spacer posts, i.e where trains had to wait for the TMDโ€™s consent

to leave the stations. In the classic double track lines, on the other hand, there

could also be spacers at intermediate points of the section, where the trains

had to stop and respect the signals made with flags or lanterns.

Train spacing could be implemented by telephone communications and

according to two traffic regimes:

o โ€œArrivedโ€ regime: in this regime, a train that was sent from

station A, arrived at station B, which once received the train

and verified its completeness, had to send to station A a

dispatch of โ€œarrivedโ€ indicating the distinctive number of the

train. At this point from station A it was possible to send the

next train. In a system like this, it is obvious how important it

is to record at both stations the dispatch and compliance with

certain rules and controls to ensure its regularity. The system

of joint arrangements was then abandoned by FS.

o Phone block: in this type of regime, if station A must send a

train to station B, the station A must ask for a real consent also

remembering the last train already sent. Station B will give its

approval only if the previous train has arrived in it

completely. Today this system is still used in secondary lines

as a replacement for other systems.

The need to introduce fixed signals began to be felt mainly for the purpose

of being able to create a kind of access door for trains that must enter the

station. The station's protection signals were then introduced and which

could take two positions:

Page 20: Design, validation and commissioning processes for metal

12

โ€ข Closed, to indicate the prevented way to the internal exchanges at

the station;

โ€ข Open, to allow trains to enter the station.

A set of circuits of the station apparatus also made it possible to guarantee,

by means of appropriate electrical connections, the real condition of the free

section, from the departure signal of the forwarding station, to the

protection signal of the arrival station.

As speeds increased, it became clear that it was impossible for a driver,

especially in adverse weather conditions, to obtain the distance of free

visibility in relation to the longer braking distances.

At the beginning, it was remedied admitting some overcoming of the

signal, disposed consequently to opportune distance from the protected

point. A subsequent measure was to precede the protection signal (main

signal) by another fixed, not maneuverable signal, called โ€œadvance signalโ€.

The purpose of this signal was to draw the driver's attention to the point

where he had to start reducing his speed.

The attention signal then became a real โ€œadvance signalโ€, maneuverable,

able to notify in advance the indications of principal signal. The latter took

the name of โ€œmain signalโ€ and became, then, a signal which must not be

exceeded in the event of stop signal.

Between the advance signal and the main signal, the distance must be

calculated, and has to be at least equal to the braking distance

corresponding to the maximum speed allowed on the route for the specific

train in transit, then increased by a certain safety margin. This distance will

therefore be a function of the speed but also of the slope of the line.

Page 21: Design, validation and commissioning processes for metal

13

In Italy, for speed conditions up to 140 km/h, the distance generally used

between warning signal and main signal is 1200 m. In some cases,

especially when it is necessary to bring the signal in a position of safe

visibility (out of curves, tunnels, etc. ...) the distance of 1200 m may be

exceeded, but within certain limits, not to require the driver to remember

for too long the previous indication.

Usually, in Italy, the protection signal is combined with the advance signal

of departure and getting thus a coupled signal that can have three different

aspects:

Impeded way (stop signal): red;

Permissive signal with warning of the next impeded way:

yellow;

Permissive signal with subsequent clearance warning: green.

The first fixed signal used essentially as a protection signal was the disc-

shaped signal. The disc signal consisted of a large table, usually circular and

red painted, able to rotate around a vertical axis, to present itself in the face

of the trains to be stopped and at the edge to the trains to which the

approval was to be granted.

Page 22: Design, validation and commissioning processes for metal

14

Figure 4: Disc signal

The disc signal was in fact disrupted in 1920 and later, this signal was

replaced by the traffic light or wing signal. This signal consists of a

rectangular sail, always visible to the trains, and which can assume two

different positions: horizontal for the blocked way and inclined downwards

for signaling the free way.

Figure 5: Wing signal (main signal)

In the Italian railways type, the wing has two glasses, one red and one

green, and depending on how the wing is arranged, one in front of the

Page 23: Design, validation and commissioning processes for metal

15

other, it give โ€œimpeded wayโ€ with the red color and โ€œproceedโ€ with the

green color.

The wing signal has been used also as an advance category signal, in this

case it is yellow and with fish tail shaped extremities. The movement of the

wing is the same as the one for the main signal. [9]

Figure 6: Wing signal (advance signal)

At a point where the line branches, it is advisable to include with the

indication of permissive and impeded way, also information enabling to

identify the road into which it is being forwarded.

Signals with overlapping wings or candlesticks were then inserted. The

wings, in this case, could be at the same height (in the case of two or more

lines with switches to be covered at 30 km/h) or different: in this case, the

upper one indicated the correct route and the lower one(s) the deviated

branch.

Figure 7: Candlestick signal

Page 24: Design, validation and commissioning processes for metal

16

The wing signal, however, had two major drawbacks although less than

those related to the disc signal: to have a moving part exposed to the

weather and provide a daytime indication different from the night one.

To overcome these problems, they switched to permanently luminous

signals, which, at first, the so called color fires.

A color fire signal is a signal with several overlapping eyes in which each

eye has a light bulb and each eye has a differently colored lens.

With this system, it was possible to create multiple signals with

overlapping lights, but the presented 2 major problems:

o When a signal was taken in full by the sun's rays, it gave the

impression that all the lights were on;

o Requiring two or three eyes overlapped for each indication,

they were considerably cumbersome.

It was then completely abandoned and replaced by the moving screen light

signal.

A moving screen light signal consists of a single optical complex, with a

single filament bulb, placed in the fire of a spherical mirror. A three-aspect

signal (red, yellow and green), as it goes from yellow to green, it goes

through red for a moment. If a driver was passing through, in the last

stretch in which he saw the signal, at the very moment of this red flash, he

was obliged to carry out an emergency brake if he doubted that it was not a

switchover of a stop aspect of the signal. This situation could often arise on

lines with heavy traffic. For this reason, a moving screen signal was studied

and realized in which the central slide of the fan is yellow while green and

red are lateral.

Page 25: Design, validation and commissioning processes for metal

17

The eye of the signal is mounted in the center of a large pan that, acting as a

background, improving its visibility, a purpose which is concurrently a

sunscreen (visor) that protrudes forward, covering the top of the beginning

of the light stream.

Figure 8: Fixed light signal

On FS network and others such as SNCF1, the fixed signals are located to

the left of the trains. This is due to the traditional movement of trains

running on the double track to the left.

In a double track line the signals referring to the left track are placed to the

left of the track itself and their screen is circular. Those referring to the right

track are placed to the right of it and their screen is square.

Signals shall, as a rule, be placed as close as possible to the track to which

they relate and those placed in tunnels shall not be equipped with a sail

(neither round nor square).

Specific rules must be regarded to place signals along the tracks.

Regarding departure main signal:

1 SNCF stands for โ€œService National des Chemins de Ferโ€, which is the national French railway company.

Page 26: Design, validation and commissioning processes for metal

18

Departure signals shall be placed after the โ€œnormal stop

pointโ€ (at stations or stops), which is defined as the point

where trains normally stop to carry out passenger or freight

related operations;

If the departure signal refers to several tracks from which

trains always depart from stops (trains may not pass without

stopping on these tracks), the signal must be placed at a

suitable point and is always round sailing;

If the departure signal refers to more than one track and trains

can pass through one of these without stopping, the signal

must be placed to the left or right of that track and, in any

case, close to it;

At stations, it is allowed that the signal that controls the

departure from a single track (not a running track) is placed to

the right of the same (square sail) and as close as possible to it;

Departure signals referring to one or more tracks from which

trains can be routed on a truncated track shall be placed

before the tip of the switch that leads to the truncated track

and at least 50 m from the bumper or the end of that track.

Specific rules for protection main signals require they shall be placed at

least 100 meters from the point that is intended to protect:

The protection main signal for stations, turning points,

crossings, etc. shall be placed at least 100 meters from the

point that is intended to protect:

The tip of the first switch encountered by the train;

Page 27: Design, validation and commissioning processes for metal

19

The limit cross of the intersection or of the first switch

encountered by the train (if taken by the trailing side);

The limit picket of the shunting;

The point where the tail of the train of maximum permitted

composition can be found stopped at the station or at a

subsequent main signal.

The main signals protecting level crossings must be at least 50

meters from the crossing itself.

On electrified lines, protection main signal shall in any case be

placed before the electric traction bridges of the station contact

wire sectioning.

Under normal weather conditions, main signals and advance signals

advance signals shall be visible at 200 meters if the maximum train speed in

the section of line preceding the signal is greater than or equal to 90 km/h

and 150 meters if lower.

In cases due to the orographic layout of the line (curves, ridges etc.) which

prevent the respect of these minimum standard values, the central offices of

RFI (in particular the office called Technical Direction) may authorize

shorter distances of visibility after reducing the maximum speed of the line,

if necessary, in the section concerned (that preceding the signal). These

maximum line speed values are calculated approximately based on the

following graph in relation to the physiological reaction times of the

drivers.

This reduced visibility distance is given in a special box in a special booklet

describing the characteristics of each line called Line Booklet (FL) / Time

Booklet (FO).

Page 28: Design, validation and commissioning processes for metal

20

Figure 9: Minimum visibility distance as a function of the maximum permitted speed

Advance signals shall be placed on the same side of the main signals to

which they relate.

After describing the methods used to indicate the various inputs to be given

to the driver, the track circuits are now going to be described.

This allows to define automatically the state of freedom of the route, i.e.

whether it is possible to allow a train to run on a given section of track.

In its simplest form, a track circuit is a direct current electrical circuit which,

fed from one end by means of a battery or accumulator, supplies a track

relay at the other end. Part of the circuit consists of the two rails of the

section that must be to be controlled, so that each of the two rails carries a

polarity. The track section that will be controlled is the one between two

insulated joints, which, while guaranteeing mechanical tightness, interrupt

the electrical continuity between the two adjacent rails. If a line is

electrified, the electrical continuity required as a return circuit must always

be guaranteed at least on one rail. In general, however, even for non-

electrified lines, the insulation of both rails is avoided.

0102030405060708090100110120130140150

406080100120140160180200

Max

imu

m a

llow

ed s

pee

d [

km/h

]

Minimum distance [m]

Minimum visibility distance

Page 29: Design, validation and commissioning processes for metal

21

On direct current electrified lines, track circuits supplied with 50 Hz

alternating current are used.

Modern track circuits are audio-frequency (2-4 KHz) electronic circuits and

are of the digital type with frequency modulated signals. The digital

electronic track circuits are easily interfaced with computerized systems,

such as the Static Central Devices and, in Italy, are being applied on the

high speed lines.

However, in order to define the passage of the train at a certain point and to

ascertain the release of the section, it is necessary to introduce the

equipment called pedals.

This equipment is placed on a rail of the track and is operated by the wheel

of the train that passes through it.

A simple type of pedal is that one equipped with a moving part which,

when activated by the wheel flange, closes the electrical contacts.

Another type of pedal is the SILEC one, which is very popular on French

railways. This pedal has a mobile arm that can always be operated by the

wheel flange and is used only for the automatic control of the half-barriers

of level crossings and never for liberation tasks.

Another type of pedal is the one with magnetic action, which can feel the

variations that occur in a special magnetic circuit when the metal masses of

the wheels in transit pass through it.

The most used type of pedal for the purpose of evaluating the clearance of

the way is the electromechanical one. This type of pedal controls the

inflection of the rail that occurs between two crossbars when a train pass.

In order to ensure that a train does not enter a given section of track if no

previous train has left it, interlocking systems are set up.

Interlocking systems are automatic, creating track circuits that cover the

entire section or by installing axle counting pedals, located on the track in

Page 30: Design, validation and commissioning processes for metal

22

and out of the block section to count the number of axles in and out of a

section.

The automatic interlocking system can be reversed and used even in the case

of a double track line to banalize the line. It may be necessary, in fact, banalize

a track to create priorities and allow fast trains to overtake slow trains, or run

in two directions on one of the two tracks while the other is out of service.

In fact, an automatic interlocking system causes the occupation of a section

when a train penetrates from the two ends.

Until now, attention has been focused on the care that a designer of a safety

system must put in building circuits and equipment such that any failure,

even if unlikely, blocks the circulation by taking the signals to impeded

way.

This precaution, however, can be in vain if the distraction of the driver or

situations of poor visibility, imply that the train passes the signal of an

impeded way and maybe even at high speeds.

Over the years, therefore, it have begun the study of systems capable of

repeating on board locomotives the indication of fixed line signals.

There are two types of on-board systems:

Point or discontinuous system (Discontinuous Digital Signal

Repetition)

Continuous systems (Continuous Signal Repetition)

In the first case, there are buoys mounted along the line at each signal,

which is capable of informing the installed equipment on board, giving it

an indication corresponding to the appearance of the signal at that time.

Page 31: Design, validation and commissioning processes for metal

23

Figure 10: Line buoy

In continuous systems, on the other hand, there is always a continuous

connection between track and train via a track circuit and thus a change in

the appearance of the signal that can be made known to the driver.

Recently, among the interlocking systems that allow to protect the driver's

driving and thus prevent the train from exceeding certain limits, the Train

Running Control System is taking off. In this system, the track-side

subsystem transmits the data to the on-board subsystem in such a way as to

control the speed of the train at that point on the line. This system is of a

discontinuous type and the transmission of signals always takes place by

means of buoys placed on the track, attached to the crossbars and therefore

the reception of the signal takes place only at these points.

Page 32: Design, validation and commissioning processes for metal

24

Figure 11: Monitor SCMT+RSC

According to SNCF, here is the type of information on the monitor:

Figure 12: Indication authorizing maximum speeds of 300 km/h

Figure 13: Indication authorizing maximum speeds of 270 km/h

Figure 14: : Indication authorizing maximum speeds of 160 km/h

Figure 15: : Indication that invites the train to stop before the first signal detected

Page 33: Design, validation and commissioning processes for metal

25

Figure 16: Indication that orders the driver to travel on sight stopping before the first signal detected

Considering the signaling in stations, in addition to the assessment of

permissive or impeded way, there are all those commands that are added to

determine the desired route. Even in this case, the historical evolution has

passed from the mechanical remote control of the signals to the centralized

control of all the bodies in a single central apparatus that also allows all the

necessary controls.

The first traffic light signals were controlled by means of flexible

transmissions, made of steel ropes, sliding on pulleys supported by small

posts arranged along the tracks. The manoeuvre was then carried out by

means of large levers equipped with counterweights or with balanced

cranks that turned a winch on which the flexible rope could be wound and

turned.

When it was then decided to subordinate the manoeuvring of the signals

according to certain conditions, keys were used that once introduced into

the manoeuvring device allowed it to move.

Subsequently, hydrodynamic equipment was used, which allowed the

various yard bodies to manoeuvre by means of water under pressure. This

completely Italian innovation has been totally abandoned to date.

Currently, the equipment are all electrical and the maneuvers are

effectuated by means of relays and motors applied to the signals, exchanges

and bodies of the yard.

Page 34: Design, validation and commissioning processes for metal

26

The evolution of modern central equipment, i.e. those cabins in which all

the command and control devices of the various bodies are centralized, has

been:

o Electric Central Apparatus with individual levers;

o Electric Central Apparatus with Itinerary Pushbuttons;

o Static Central Apparatus.

According to the "Regulations for the Circulation of Trains": manoeuvre is

defined as any movement of traction vehicles or vehicles, which normally

takes place within a place of service, except for the start of a train that has

received the order of departure and for the entry of an incoming train, up to

the point of normal stop.

In non-centralized yards, the manoeuvres were commanded by means of

station operators with hand signals, via direct agreements with the

diverters in charge of the exchange manoeuvres, under the supervision of

the TMD.

In centralized yards, instead, it is necessary to adopt special signals for the

manoeuvres that are traditionally defined as low signals.

Initially the low signals consisted of a parallelepiped box called lantern that

could be rotated by 90ยฐ around its vertical axis.

Page 35: Design, validation and commissioning processes for metal

27

Figure 17: Control signal - lanterns

In more recent installations, the low signal described, which in Italian

jargon called a โ€œmarmotโ€, has been replaced by a more reliable light signal,

without any movement.

Figure 18: Operating light signal

Low signals are usually inserted to the left of the track. If they were placed

to the right of the track, they would be presented with an arrow pointing to

the track they are referring to.

Page 36: Design, validation and commissioning processes for metal

28

Figure 19: Control signals on the right side of the track

Regarding level crossing signaling we have the following classification:

Level crossings with barriers operated on site;

Level crossings with remotely controlled barriers;

Level crossings with automatically operated barriers.

For level crossings operated at a distance, historically were initially used

barriers operated with a simple wire transmission that could be controlled

using manoeuvring levers; the system was then replaced by a double wire

system in which the flexible wire transmission has an entry and an exit

branch.

Like all remote systems, this system is equipped with a ringer that is

mechanically operated at least five seconds before the barriers begin to

move.

This was followed by the use of electrically operated barriers. In the event

of a power failure, even accidental, the barriers are lowered.

The level crossings are therefore equipped with electrical control boxes for

direct current barriers, which are operated with a motor like that used for

the switches.

Page 37: Design, validation and commissioning processes for metal

29

Remote controlled level crossings are equipped with the following devices:

o Closing control;

o Checking the integrity of the barriers;

o Control on the freedom of the level crossing.

Level crossings regulated by FS have the following signs:

Figure 20: : Identification table for LC according to FS

Figure 21: Diagram of automatic LC signals arrangement according to FS

From the above, it can be seen that technological evolution and the growing

drive towards automation in recent decades have favored the replacement

of activities traditionally carried out by human operators with automatic

Page 38: Design, validation and commissioning processes for metal

30

systems. Those systems involve the command and the control of traffic and

the unification of the same activities through central systems, generally far

from the line, which are fewer and fewer in number and under the

responsibility of a small number of operators, with responsibility for the

management of increasingly extensive areas of the railway network.

Here 3 important command and control systems are therefore introduced:

CTC systems: Centralized traffic control and command;

CCL systems: Control of Line Circulation;

SCC Systems: Command and Control Systems.

The technique of centralized traffic control originated in the United States

where a telephone operator called dispatcher could communicate the entire

route to be travelled to the drivers of the various trains and give

instructions regarding the shunting to be carried out. The system then

evolved with remote-controlled systems capable of allowing the central

operator to manoeuvre the exchanges and signals directly.

Obviously, the availability of such a system, Centralized Train Control

(CTC), reducing the work of the central operator at the same traffic

intensity, made possible to create longer line sections than those entrusted

to the dispatcher.

The introduction, then, of electronic equipment, has allowed continuous

operation and the so-called cyclical exploration of the state of controls, so

that the overall situation of all the peripheral stations is continuously

examined and renewed at the center by interventions of only a few seconds

(polling). The commands to specific remote places are made by interrupting

the polling and sending the commands themselves, after selecting the place

to be remotely controlled.

Page 39: Design, validation and commissioning processes for metal

31

While a CTC system does not extend beyond 150 km, an SCC system can

control an area that extends beyond 1000 km. With this system it is possible

having, for a country, the presence of the infrastructure manager in a few

strategic centers of command and control.

Finally, in the description of the evolution of signaling systems, the

innovative European systems called ERTMS/ETCS systems should be

introduced.

The ERTMS/ETCS (European Rail Traffic Management System/European

Train Control System) standard is one of the most significant innovations

introduced into the European railway landscape and allows trains of

different nationalities to run on the basis of common information

transferred using a common language, managed with interoperable

trackside and on-board subsystems. The standard defines the way in which

signaling information is exchanged between trackside installations and

trains, identifying the transmission techniques to be used, the format and

the content of the messages. The ERTMS/ETCS system thus provides the

driver, in a standard manner, with all the information necessary for

optimum driving, continuously monitoring the effects of his actions on the

safety of the train's running and activating emergency braking in the case of

train speeds above the maximum permitted speed for safety. There are

currently different levels of implementation of the ERTMS system, level 1 is

the basic level and the next 2 provide more and more automated

technologies.

2.2 Description of the structures supporting the signaling

infrastructure:

2.2.1 Fiberglass poles

Page 40: Design, validation and commissioning processes for metal

32

The fiberglass poles are used in the railway sector to support light signals

and are an excellent alternative to metal structures.

In general, this type of support consists of an armoured fibreglass pole and

one or more high pressure moulded fibreglass shelves.

The pultrusion process (pull+extrusion) is a continuous process used to

produce reinforced polymer profiles.

Figure 22: Fiberglass pole

The dimensions of main signal according to FS standards are shown in the

figure below:

Page 41: Design, validation and commissioning processes for metal

33

Figure 23: Standard dimensions of a 2 lights main signal in FS

Generally, a pole of this type is equipped with the following accessories:

โ€ข Ladder;

โ€ข Channel parapet made of fiberglass armchairs;

โ€ข High pressure molded fiberglass platform;

โ€ข Kit of the relative fixing elements in stainless steel;

โ€ข Additional parapet;

โ€ข Tilting platform in case of three-light signal;

โ€ข Anchorage plate of the ladder in hot-dip galvanized iron.

This structure must be positioned on a foundation plinth made of

reinforced concrete and must be anchored to this structure by means of an

anchoring plate.

Page 42: Design, validation and commissioning processes for metal

34

The material used for the construction of these poles gives it excellent

performance and mechanical characteristics such as: lightness and high

mechanical characteristics and therefore resistance.

The lightness allows easy transport and installation. Furthermore, high

electrical insulation characteristics are guaranteed, in the absence of

earthing, chemical and atmospheric resistance without the need for

maintenance.

2.2.2 Signal Cantilever bridge

The station signals, both single and multiple, can be installed on cantilevered

beams or on portals depending on the spaces available in the station itself

and according to the criteria that will be defined in the following chapters.

These structures can take 2 configurations, the normal one as shown in the

figure below and with the addition of a further beam in order to cover an

additional track.

Figure 24: Signal cantilever bridge installed along the Casablanca-Tangier line

These steel structures are lattice structures made of galvanized steel and

installed on a reinforced concrete foundation.

Page 43: Design, validation and commissioning processes for metal

35

These structures consist of a support that is directly anchored by means of a

plate and anchoring kit to the concrete foundation, and a beam (or 2 beams)

at the top connected to it by means of special metal carpentry.

The geometrical dimensions of the beams are very variable and the

parameters that influence their length will be described in chapter 4, as well

as the sizing criteria. The height of the pillars is defined based on the

arrangement of the elements of the electric traction infrastructure.

The dimensioning of the beam and the definition of the different profiles to

be adopted are defined by the structural designer. For example, with regard

to the metal structures installed in Morocco, metal profiles of the UPN type

have been installed and reinforcements with diagonal elements with an L-

section or other minor UPN sections have been adopted; the pitch of the

different metal modules has been fixed at 0.75m.

The constituent elements of these structures can be divided in primary (with

structural purpose) and secondary (with non-structural purpose) ones:

PRIMARY

โ€ข Supporting column

โ€ข Load-bearing beam

โ€ข Plinth

SECONDARY

โ€ข Signal cages

โ€ข Ladders

โ€ข Hand rail

Page 44: Design, validation and commissioning processes for metal

36

Figure 25: Signal Cantilever bridge schematic representation

2.2.3 Signal Bridges

As mentioned above, station signals can be installed on cantilevered beams

or portals. The main difference between these 2 structures is obviously the

presence of an additional column that allows a longer dimension of the beam

for the laying of more signals in reference to more tracks.

The support portals for railway signaling, like the cantilevered beams, can

also take on more configuration depending on whether 1 or 2 overhangs are

added to the basic structure so as to cover additional tracks.

The installation criteria for these structures are more binding than for

cantilevered beams as the minimum safety distances from the tracks for both

plinths will have to be taken into account, but this will be discussed in

chapter 4.

Page 45: Design, validation and commissioning processes for metal

37

The constituent parts of these structures are similar to those of cantilevered

beams with the addition of one (or more) steel column(s).

Figure 26: Signal Bridge installed along the Casablanca-Tangier line

Page 46: Design, validation and commissioning processes for metal

38

CHAPTER 3: INPUT NECESSARY FOR THE

PRELIMINARY DESIGN OF THE STRUCTURES

This chapter defines the input documents necessary to the preliminary

design of the structures, an operation prior to the actual structural design

that is entrusted to a free-lance structural engineer certified by the state or to

a civil engineering firm.

By preliminary design, it is meant the definition of the geometric sizes of the

several structures based on their position along the railway track,

considering different aspects that will be better clarified in the next chapter.

The input documents to be provided to the contracting company in order to

proceed with the design, supply and installation of the metal support

structures for signaling are:

โ€ข Railway track planimetry;

โ€ข Railway track cross sections (showing electrical traction elements);

โ€ข Signaling scheme plan.

3.1 Railway track Planimetry

The railway track planimetry represents the planimetric course of the railway

in reference to a particular height generally referring to the top of the rail (or

running plane). In this elaborate, there is information regarding the

geometric development of the whole route and of the switches.

The geometric elements of a railway route are:

โ€ข Straight sections;

โ€ข Circular curves;

Page 47: Design, validation and commissioning processes for metal

39

โ€ข Transition curves.

The value of the radius of the circular curves affects both the maximum

admissible speed on a line (running costs, profitability, external costs, etc.)

and the easiness (or not) of insertion of the railway in the territory

(construction and maintenance costs).

On the existing lines, speed increases can be introduced with respect to the

limits envisaged in the project, introducing geometric variations on the track

and / or accepting greater stresses on the wheel-rail contact.

The figure below represents an example of a railway track planimetry.

Figure 27: Example of a railway track planimetry

3.1.1 Transition curves

The vehicle, when running on a curve, is subjected to the centrifugal force

which causes the vehicle to roll-over, stressing the external rail of the track

and reducing the comfort for the passengers.

Page 48: Design, validation and commissioning processes for metal

40

The forces acting on a vehicle running on a curve are:

โ€ข Weight force (P);

โ€ข Centrifugal force (FC) expressed as a function of the vehicle weight (P),

gravitational acceleration (g), square of speed (v2) and radius of the

curve (R).

๐น๐‘ =[(

๐‘ƒ๐‘”) ๐‘ฃ2]

๐‘…

Figure 28: Equilibrium of a vehicle running a curve

Figure 29: Equilibrium of a vehicle running a curve with a cant

To increase the speed, and keep the same transversal acceleration, is

generally used to create an inclination of the platform with respect to the

horizontal plane, raising the external rail with respect to the interior one, thus

improving the comfort conditions for passengers. The cant values, however,

must be limited for coexistence on the lines of trains circulating at different

speeds, in fact slow trains encountering an excess of cant, would suffer the

Page 49: Design, validation and commissioning processes for metal

41

effect of the centripetal force. The maximum allowed elevation in Italy is 160

mm.

The passage between a straight section to a circular curve or between two

circular curves with different radius must always occur through a transition

curve, in order to limit the abrupt variation of the transversal acceleration

that is generated for the transition from an element to the other. The

transition curve is sized trying to keep the jerk2 as smooth as possible and

making sure that the speed of rotation of the vehicle around its axis of gravity

increases uniformly. Transition curves also have the function of making a

progressive variation of the external rail elevation during the passage from a

straight section (zero elevation) to the circular curve (maximum calculated

elevation).

There are 3 transitions curves that are adopted on railway tracks:

โ€ข Cubical Parabola;

โ€ข Sinusoidal transition curve;

โ€ข Clothoid, which has the particularity of allowing the

continuous variation of the radius from an infinitely large value

(corresponding to the straight section), up to whatever radius

value. The general equation of the clothoid is:

๐‘Ÿ โˆ™ ๐‘  = ๐ด2

In the railway track planimetry there are tables with inside the calculation

parameters of each transition curve inserted in the track layout. An example

is shown in the figure below, with reference to the Moroccan line.

2 variation of the uncompensated acceleration in the time unit.

Page 50: Design, validation and commissioning processes for metal

42

Figure 30: Example of the transition curves tables contained in a railway track planimetry

In this track layout, the geometrical element chosen as transition curve

between a straight line and a circular curve is the clothoid and the tables

inserted therein have the following form:

Xs Abscissa of the curve vertex

Ys Ordinate of the curve vertex

R Curve radius

A Scaling factor of the clothoid

L Length of the clothoid

T Tangent to the circular curve

dec Arc offset from the straight line

Dv Length of the curve + clothoid

Dc Length of the curve

Table 1: Parameters for the definition of clothoids

For each curve are also reported the coordinates of the tangency point

between transition curves and straight lines, the tangency point between a

transition curve and a circular curve, the midpoint of the circular arc and the

center of the curve.

Page 51: Design, validation and commissioning processes for metal

43

Figure 31: : Representation of tangency points between planimetric elements in a railway track planimetry

ORP1 Tangency point straight line โ€“ entrance transition curve

FRP1 Tangency point transition curve โ€“ circular curve

BX Midpoint of the circular arc

FRP2 Tangency point circular curve โ€“ exit transition curve

ORP2 Tangency point exit transition curve โ€“ straight line

centre Center of the curve

3.1.2 Switches

Figure 32: Switch example

For the switches, in the railway track planimetry, there is a table showing the

coordinates of the 4 necessary points for its univocal definition:

PA Switch point

CA Geometric center

Page 52: Design, validation and commissioning processes for metal

44

TA 1 โ€“ TA 2 Heels of the switch

Figure 33: Switch schematization

A switch is a device that makes possible the passage of a vehicle from the

track in which it is running to another track that branches off from it.

Switches must therefore be able to assume two distinct positions: one in

which the vehicle must be able to continue on the track in which it is located,

and another in which the train can move and start running on the deviated

track.

In a switch, there are two fundamental characteristic parts:

โ€ข A movable part, commonly called the needle frame, capable of

assuming two different positions to guarantee the continuity of

the entry track and the exit track deviated from it.

โ€ข A fixed part, in which the march of vehicles is made possible,

on one or the other exit.

The two main parts are connected to each other by four short rails called

intermediate rails.

In order to allow the flange of a wheel to move on a route other than that

corresponding to the rail on which it is rolling (i.e. to bring the wheel onto a

different rail) it is necessary that the new rail be brought closer to the first in

order to move the wheel flange on it and thus bring the whole wheel to the

new direction.

Page 53: Design, validation and commissioning processes for metal

45

Figure 34: Train wheelset running on a track

It is evident that the passage of the wheel on the new rail, approached to the

first, must be smooth and that, once the two rails are approached, the

exchange must be safe and complete. To guarantee all this, the end of the

mobile rail in order to ensure a perfect adaptation of its side to the side of the

fixed rail has a particular shape. In fact this is the reason for the characteristic

thinning of the tip of the moving intermediate rail, the so called needle.

The fixed rail part against which the needle is supported is instead called a

stock rail3.

The fixed part, that is the heart of the switch, has a width that is the function

of the deflection angle formed by the axis of the two exiting routes from the

switch.

On the railway track planimetry are reported the types of switches and their

dimensions.

3 In Italian, it is called a โ€œcontragoโ€

Page 54: Design, validation and commissioning processes for metal

46

Figure 35: Example of switch tables contained in a railway track planimetry

Taking as an example the railway track planimetry of the Moroccan line in

particular referring to the station of Casa Voyageurs, in the table are shown

the coordinates of the points forming each switch.

3.2 Railway track cross sections

The railway land consists of a railway superstructure supported by a road

body.

The railway superstructure is normally composed of:

โ€ข The rails which together with the sleepers on which they are fixed

by means of suitable attachment devices, and to the switches

constitute the track (or the armament);

โ€ข A layer of crushed stone, called ballast, which supports the

armament.

Page 55: Design, validation and commissioning processes for metal

47

Figure 36: Schematization of the railway superstructure and characteristics measurements

The railway body, on the other hand, is formed:

โ€ข From the actual roadway built on surveys or other works of art,

whose upper part is called the road platform and also includes

complementary work such as quays, roads and access roads for the

tracks;

โ€ข From works of art, such as surveys, viaducts, bridges, tunnels,

trench walls, which create the plano-altimetric layout of the railway

line, ensuring the necessary functionality and integration with the

territory;

โ€ข Minor and protective works of art such as bridges, platform gutters

and guard ditches.

In the Moroccan project, the sections shown in the elaborates contain no

information about the type and height of the catenary, nor the presence of

any poles that support it. Because of the modifications carried on the tracks,

the electric traction infrastructure must necessarily have undergone some

changes in its configuration which are not deducible from the documents

provided.

Page 56: Design, validation and commissioning processes for metal

48

From these cross sections documents, it is only possible to obtain information

on the geometry of the track and the position of the structures near the tracks

that could interfere with the installation of any structures necessary for the

signaling implant.

A useful information obtainable from the cross sections is the cant value of

the rails in a curve, allowing to determine the rolling plane with respect to

which the heights are defined.

Very important information for the design of the positioning of the structures

necessary for the electric traction and signaling infrastructures, in addition to

the knowledge of the position of structures outside the tracks, is the interaxis

between the tracks, which allows to know if it is possible to install these

structures between a track and another, respecting the minimum distances

of the structures from the inner edge of the rail closest to the obstacle.

The sections, therefore, are a useful tool to know the existing and project

armament that is necessary for the study and design of the signaling systems

but they are not sufficient for the drafting of the entire project. Some

examples of cross section drawing are reported in Appendix A.

3.3 Schematic signaling plan

The schematic signaling plan shows schematically, and therefore without

respect for the proportions, the topography of station tracks, turnouts and

line tracks, passenger buildings, platforms, road crossings, tunnels and the

position and the type of signals that must be present in the specific points of

the line (and that are not built or installed yet) without indications (or only

with preliminary assumptions) about the structures to be designed to

support them.

Page 57: Design, validation and commissioning processes for metal

49

The positioning of the signals is strictly linked to the regulations referred to

in the drafting of the schematic plan.

In the Moroccan project, basically the French regulation was applied and

therefore according to the indications of the SNCF.

Here is an example of schematic signaling plan:

Figure 37: Example of a schematic signaling plan

The figures below show some elements in the schematic signaling plane of

the Casablanca Triangle:

Figure 38: Elements of the schematic signaling plan - schematization of the joint

Figure 39: Elements of the schematic signaling plan - schematization of double comunication

Page 58: Design, validation and commissioning processes for metal

50

Figure 40: : Elements of the schematic signaling plan - schematization of signal portals

Figure 41: : Elements of the schematic signaling plan - schematization of signal cantilever bridges

Figure 42: Elements of the schematic signaling plan - schematization for reflecting signs

Figure 43: Elements of the schematic signaling plan - schematization of signal for ending zone at limited speed

Figure 44: : Elements of the schematic signaling plan - schematization of banalized line

Page 59: Design, validation and commissioning processes for metal

51

Figure 45: : Elements of the schematic signaling plan - definition of the action zone boundaries of a control post

Page 60: Design, validation and commissioning processes for metal

52

CHAPTER 4: GEOMETRIC DEFINITION OF THE

STRUCTURES

The definition of the geometry of the structures is a complex and important

process where the slightest mistake would lead to delays and therefore be

financially costly.

This process consists of several phases:

Analysis of the schematic signaling plan and the staking reports

giving the first information about location of signals along the tracks

Analysis of the track planimetry providing distances between tracks

at those locations

Analysis of the cross section drawings showing:

o Tracks

o Elements belonging to the electric traction infrastructure

o Any other obstacle affecting the design and the structure

location (boundary walls, bridges, tunnels etc.)

Staking operations to verify the actual feasibility on site (not all the

obstacles are shown in the above-mentioned documents)

Design of the structures

o Choice of the type of structure to be designed

o Definition of the geometric dimensions of the structure

4.1 Analysis of the schematic signaling plan

The schematic signaling plan is drawn up by experienced railway signaling

professionals based on a reference standard. For instance, in Italy, the

Page 61: Design, validation and commissioning processes for metal

53

schematic plan is elaborated on the basis of the FS standards for the location

and appearance of signals (Norme per lโ€™ubicazione e lโ€™aspetto dei segnali)

and the related circulars of 19-05-1981 and 09-01-1984. In other railway

administrations different rules are regarded.

From the signaling scheme plan are extrapolated information about the

location of the signals along the line or in the station and the type of signals

to be installed on the structures. There are only preliminary assumptions on

the type of structures (Portals, Cantilever bridges or poles) to be installed;

neither it is possible to see planimetric data of the locations where the

structures will be installed (straight section, circular curve or transition

curve), nor there is information about the distance between the tracks nor the

presence of elements of the electric traction infrastructure.

That is why staking operations are needed to get the information necessary

to the geometrical definition of the structures.

4.2 Analysis of the track planimetry

The track planimetry is a scaled top view of the tracks providing all the

planimetric data necessary to the design of metallic structures.

For the realization of the structures, the track plan represents a fundamental

input document because once the type of signals to be installed has been

deduced from the schematic plan, it is possible to deduce the planimetric

element (straight section, circular curve or transition curve) in which the

structure will be installed, leading also to initial considerations regarding the

visibility of the signals. This document also shows the distances between the

tracks allowing to make preliminary assumptions about the possibility or not

to install the plinths of the structures, as well as the presence of obstacles such

as boundary walls that represent design constraints to the construction of the

structures.

Page 62: Design, validation and commissioning processes for metal

54

After the analysis of the track plan, staking operations are carried out in order

to verify the site conditions and detect other possible design constraints not

present or deductible from this document.

4.3 Analysis of the cross section drawings

A first evaluation of the positioning and the type of structure to be installed

is carried out on the basis of the cross-sections drawings provided as input

documents.

From the cross-sections are deduced information about the distance between

the tracks, the presence of obstacles, if any, that prevent the installation of the

structure at a certain location of the line and of elements belonging to the

electric traction infrastructure.

On the basis of these information, taking into account the minimum safety

distances imposed by the harmonized European standards, a first design

hypothesis can be made and which will then be confirmed or not after the

staking procedures are carried out.

It is necessary for design purposes to have the cross-sections of the railway

platform elaborated in the point where the structures will be installed in

order to have information on the differences in height between the tracks as

well as the presence and actual location of the elements belonging to the

infrastructure of electric traction.

Verifying the presence of electric traction infrastructures is essential for

compliance with the safety standards described in the EN 501101, which

requires a minimum distance of 1.12 m between the metal structures and the

tension elements.

The elements to consider in this case are 3:

Page 63: Design, validation and commissioning processes for metal

55

Catenary

Contact wire

Feeder

Figure 46: Two-dimensional schematic representation of the overhead line system indicating key elements. Dimensions indicate typical values

The contact wire to which the trains are electrically connected with a sliding

system (pantograph) is powered by electrical substations. For direct current

traction, safety regulations impose a minimum distance between the contact

wire and the top of rail of 4.40 m (typical values are around 4.7 โ€“ 4.8 m). The

contact wire should have the following characteristics:

Maintain a constant distance from the track

Present an equal yield to the passage of the pantograph

Keep the conductors along the axis of the path

For railway speeds, the inertia of the pantograph mass would not allow

immediate reaction to the inevitable changes in height of the line. Therefore,

load-bearing ropes are used and which are arranged between the supports

according to a curve, said catenary, while the contact wire (rectilinear) is

connected to said rope by means of the droppers.

Page 64: Design, validation and commissioning processes for metal

56

The supporting ropes are propped up by a Teflon insulator fixed on the shelf

while shelves are fixed to the poles by tie rods. In straight sections, the poles

are spaced about 60 m from each other but the distance is smaller if the curves

are circular.

The line is arranged according to a catenary and the distance between the

rope and the contact wires at the suspension point is 1.20 m. The length of

the droppers is made so that the wires of the contact wire are horizontal. The

feeder runs along the railway line and is mounted on the catenary support

poles.

Figure 47: Electric traction infrastructure

4.4 Staking operations

Once the track planimetry has been analyzed, deducting the first information

about the presence of obstacles and the distance between the tracks, and once

the input cross sections have been analyzed, the next step are the staking

procedures.

Staking means the operation for which the conditions deduced from the

previous documents are verified on site and obtaining other information that

could not be obtained from the previous documents.

Page 65: Design, validation and commissioning processes for metal

57

The cross sections are processed with a distance ranging from 25m to 30m so

the information about the elements of electric traction infrastructure are not

constant and need to be verified on site.

The purpose of staking is therefore to verify the possibility or not of installing

the structures, by checking:

The presence of electric traction elements:

o Foundation plinths of poles and portals

o Consider the minimum distance between the metal parts and the

elements under tension according to the UNI 501101 standard;

Presence of obstacles not deductible from the documents previously

analyzed;

Presence of other constraints that would not allow the installation of

structures and where excavations are not allowed, such as overpasses

or bridges.

Therefore, starting from the track plan, with the exact information on the

location of the points to be staked (kilometers and hectometres) it is possible

to perform the staking operations on site with the help of tools such as:

Total station

Satellite receivers (GPS)

Odometer

Page 66: Design, validation and commissioning processes for metal

58

4.5 Design of the structures

4.5.1 Choice of the type of structure to be designed

Before proceeding with the geometric definition of the structures it is

necessary to have a cross-section of the railway platform on the points where

the structure will have to be installed.

Stakes are placed following the distance rules described in the previous

paragraph on the basis of the geometric element of the alignment in which

the stakes are placed in and in correspondence with each of these points the

cross section of the infrastructure is elaborated.

The exact positioning of the metal structures deduced from the schematic

signaling plane must also be checked and staked in order to have a cross-

section of the rail platform in the point in question, as it is highly unlikely

that between the points staked previously is also the one relative to the

position of the signal.

The project alternatives are mainly 5:

Cantilever bridge

Cantilever bridge in โ€œTโ€ shape

Simple Portal (two columns)

Portal (two columns) with one or two additional arms

Portal with more than 2 columns

The choice of the type of structure to be designed depends on:

Number of tracks and their relative distance

Presence on-site of obstacles detected during staking procedures

Page 67: Design, validation and commissioning processes for metal

59

Altitude difference between the tracks

The choice of the type of structure is not a standard process, but it must

consider a series of factors that must be evaluated on a case-by-case basis.

As an indication, it can be said that it starts from the evaluation of the number

of tracks to which the signals refer:

2 tracks Cantilever bridge

3 tracks Cantilever bridge in โ€œTโ€ shape

3 tracks Simple or with 1-2 arm(s) Portal

3 tracks Normal or with 1-2 arm (s) Portal

Actually, it often happens that for several reasons the choice falls into a

combination of those structures in order to guarantee all the safety standards.

In the following paragraphs are reported a series of factors to consider for

choosing the most suitable type of structure.

Distance between the tracks:

The distance between the tracks is a fundamental parameter to consider

when choosing the type of structure to be designed in order to establish

whether there is sufficient space for the insertion of the plinth in reinforced

concrete.

Page 68: Design, validation and commissioning processes for metal

60

Figure 48: Signal portal referring to 2 tracks

In the image above, the spacing between the 2 tracks was sufficient for the

portal installation.

The distance between two neighbor tracks can be considered sufficient when:

โ€ข It is possible to install the column so that the safety

distance between the fixed obstacle and the

kinematic Gabarit is respected, this distance is

defined as "free margin" and is set by FS in 150 mm.

โ€ข The excavation for the plinth can be done without

damaging the track

Figure 49: Interaxis representation

Page 69: Design, validation and commissioning processes for metal

61

The structure gauge (or Gabarit) of the vehicles have been fixed for a vehicle

that is, in static conditions, centered on a straight section. When the vehicle

goes along a curve, in relation to the wheelbase, the length and the

mechanical characteristics of the vehicle, the shape of the vehicle protrudes

towards the inside of the curve in the central part i (between the axles of the

bogie) and towards the outside of the curve in the parts between the axle of

the bogie and the nearest end of the vehicle e (as shown in the figure below).

The i and e values depend on the wheelbase (p), the length (lc) and the

semi-width of the bogie (b/2) as well as the radius of curvature (R).

Figure 50: vehicle's overall dimensions when cornering

To pass from the structure gauge to the minimum obstacle profile (PMO)

determining the minimum distances at which to place the obstacles present

along the line, it must be considered a margin that also takes into account the

characteristics of suspension and rolling of vehicles, speed and radius of the

curves.

Each country has its own Gabarit standards. For example SNCF defines 2

categories of Gabarit:

โ€ข The nominal Gabarit: independent of the rolling plan in its

measurement mode which are done in a horizontal and vertical

orthonormal coordinate system.

Page 70: Design, validation and commissioning processes for metal

62

โ€ข The limit Gabarit: which measurements are done in reference to an

orthonormal coordinate system according to the rolling plane.

Figure 51: Gabarit categories according to SNCF

The UIC (Union Internationale des Chemins de Fer) has defined common

international gauges in order to allow the circulation of vehicles on different

networks . The G1 is the international limit gauge (allowed to circulate on all

lines open to international traffic for which there are no special conditions)

to which are added the B and C for high-speed lines.

The figure shows the international limit gauge G1 and other gauges adopted

in other countries.

Page 71: Design, validation and commissioning processes for metal

63

Figure 52: International gauge G1 and national gauges

While the legislation refers to the distance between the fixed obstacle (in this

case the steel column of the structure supporting the railway signals) and the

structure gauge, it does not take into account the space necessary for placing

the plinth installed in the subsoil.

The plinth cannot be built too close to the railway platform in order to avoid

damage to the railway infrastructure during the excavation for the plinth

installation. In fact, if the plinth is too close a preliminary reinforcement must

be considered to support the railway site. The distance of the plinth from the

railway platform is established by the structural engineer on the basis of the

considerations he made when designing the structure. The minimum

distance from the edge of the plinth toward the railway platform and the

Page 72: Design, validation and commissioning processes for metal

64

external part of the first railhead towards the structure varies in a range of

1.5 -2.0 m.

Figure 53: Example of correct spacings between plinth and rail

The plinth develops in length, parallel to the course of the tracks, therefore

its width should be considered. The type of structure and the "order of

magnitude" of the loads applied to it, whose width varies between 2.2 and

2.9 m, should be noted as well.

The portals are more difficult to install as they demand a series of

requirements, including the presence of the free margin necessary for the

installation not of one, but of 2 plinths, always respecting the safety distances

and ensuring that there are no obstacles between the structure and the

railway platform.

Presence of on-site obstacles

For the choice of the typology of structure it is necessary to verify, with a

survey in the field, that there are no fixed obstacles (for example walls or

pickets). The staking operations are fundamental also in this case because

often there are obstacles not deductible from the documents provided

leading to the choice of a typology of structure over others that perhaps from

the documents alone was not the one that was expected to be realized. The

Page 73: Design, validation and commissioning processes for metal

65

presence of obstacles influences the choice as it may happen situations where

their presence makes it necessary to adopt configurations of structures

specific to the situation.

Figure 54: Example of the installation of a signal cantilever bridge in presence of an obstacle

Altitude differences between the tracks

The difference in altitude between the different tracks is one of the most

binding parameters for the choice of the structure. Given a certain number of

tracks, in the case of a large difference in height between the different

platforms, we could resort to completely different structures.

In the example below (case with 4 total tracks), the choice fell on 2 simple

cantilever bridges rather than a portal due to the altitude difference,

resulting in higher costs for the design and the construction of the

structures.

Page 74: Design, validation and commissioning processes for metal

66

Figure 55: Example of installation of 2 signal cantilever bridges instead of a simple portal due to the altitude difference between the tracks

4.5.2 Definition of the geometric measurements of the structure:

Once the typology of the structure has been chosen, the next step is to define

the geometrical measurements that will characterize it.

The dimensions to be evaluated for each structure are:

Height of the column/s

Cantilever length (for cantilever bridge or arm/arms of the portal)

Length of the beam (for portal)

The height of the column is obtained once the exact height of the overhead

catenary for the electric traction is known, keeping in mind the minimum

distance of 1.12 m imposed by the EN501101 standard between each metal

part and the active elements up to 25kV.

Page 75: Design, validation and commissioning processes for metal

67

All the structures designed along the Casablanca-Tangier line have 10 m high

columns (input received by ONCF electric traction department). The total

height of the structure will be known once the beam is also definitively sized.

The length of the cantilever beams and portals depends on:

The number of tracks and their relative distance based on the point of

the line in which they will be installed.

The laying side of the structure with respect to the tracks, in fact the

length of the cantilever varies according to the presence of obstacles

or to the short distances that do not allow the installation of reinforced

concrete plinths.

The position of the signal on the cantilever beam, in fact signals must

be installed to the left with respect to the direction of travel of the train,

so if the cantilever beam is also installed from the left side, there will

be a shorter length, while if the structure is installed on the right side,

it will be longer for positioning the signal on the left side with respect

to the direction of travel, at a suitable distance from the axis of the

track. The distance between the signal axis and the track axis to which

the signal refers varies according to local regulations. With regard to

the Moroccan project (and therefore according to the ONCF4) the

distance is maintained in a range of 1.25 - 1.35 m. As it can be seen

from the previous figure in which there are 2 cantilevers bridges that

cover the same number of rails, but one positioned on the left and one

right with respect to the direction of travel, the length of the cantilever

beams are in fact respectively 8.4 m and 9.7 m.

4 ONCF stands for โ€œOffice National des Chemins de Ferโ€, which is the Moroccan national railway

company.

Page 76: Design, validation and commissioning processes for metal

68

Position of the signal cage with respect to the steel beam modules.

Two factors have to be considered: The bolts for mounting the signal

cage on the beam must not conflict with the elements of the steel beam

and its position must also be such as to allow maintenance workers to

intervene. The example in the first figure is not realistic, in addition to

the image not properly scaled, there is an interference between the

bolts for mounting the cage and the vertical modules of the beam. The

second figure instead shows a realistic example of correct installation

and highlights how to comply with the above criteria it was necessary

to add another module to the steel beam, thus increasing its total

length.

Figure 56: Example of incorrect mounting of the signal cage

Figure 57: Example of correct installation of the signal cage

4.6 Selection of structure types to be designed by the structural

engineer

Once the site conditions have been studied through staking operations and

after considering the parameters listed above, it is necessary to try to group

Page 77: Design, validation and commissioning processes for metal

69

all the structures designed into a small number of structure types. This will

reduce structural design costs.

In the case of the design of new implants over large areas it is not conceivable

to design a different structure for each location, in fact it is reasonable to

define "standard structure types" able to comply with the installation

requirements in several situations.

In other cases, the same metallic structure type can be associated with several

types of plinth, thus allowing its installation in several locations without

changing the design of the metallic parts. A typical case is, for the same is

the possibility to choose between two or more plinth types according to the

distances plinth-track, without starting a new structural design from scratch.

In the figures below are some examples of structures designed along the line:

Figure 58: signal bridge with 2 cantilever beams

Page 78: Design, validation and commissioning processes for metal

70

Figure 59: Signal bridge with 1 cantilever beam

Figure 60: Signal cantilever bridge in T shape with an extra cantilever

Page 79: Design, validation and commissioning processes for metal

71

CHAPTER 5: STRUCTURAL DESIGN

The structural design of the structures is carried out by a civil structural

engineer registered at the professional board of engineers.

For the design of the structures it is necessary to provide the following

inputs:

A geological and seismic report of the area in which the structures will

be installed

The geometric data of each structure type to be designed

o The geometric dimensions defined according to the criterions

listed in the previous chapter

o Information about the maximum length of the beams, in view

of the transport of the parts of the structure to the building site

and the galvanization plant where the structural elements will

be. For the structures manufactured and installed in Morocco,

the maximum length was set at 14m. It will then be up to the

designer to define the points where the cuts will be made based

on the points more or less stressed during the operational life

of the structure and to dimension corresponding joints.

o Information about any cuts along the handrail to allow

maintenance operations on the light panels placed behind. The

cuts must be provided because any cuts on site would

compromise the finishing of the galvanization.

The loads to be assigned to the structures (Weight of the signals, of the

luminous panels and metallic plates)

Page 80: Design, validation and commissioning processes for metal

72

Any contract specific requirement about material and its finishing

(e.g. galvanization thickness and type)

Mechanical details of the objects to be installed to allow a proper

predisposition of their supports

The designer of the structure is responsible to dimension the structure by

providing all the necessary documentation for its construction:

Technical report:

o Specification of the reference standards adopted and brief

description of the project to be designed

o Specifications on the materials used

o Evaluation of the loads considered to be applied on the structure

o Calculation report

o Results and verifications

o Verification of bolted joints

o Verification of the plinth

Executive design of the structure with all the construction details

Maintenance plan

5.1 Documentation to be supplied to the structural engineer

5.1.1 Geological and seismic report

The geological and seismic report is a necessary document for the designer

engineer both for the evaluation of the type of foundation to be designed

based on the type of subsoil and the definition of the seismic response that

the structure must present.

Page 81: Design, validation and commissioning processes for metal

73

This report is subdivided into:

Description of the planned structure

Seismic hazard evaluation

General geological framework

Description of the survey methodologies followed

Geological model

Seismic considerations

o Identification of the soil category of the foundation

o Topographic amplification effects

o Definition of the elastic response spectra in acceleration

5.1.1.1 Description of the planned structure

The structures in question are cantilever signal bridges and regular signal

bridges which belong to usage class IV and are classified as type 2

constructions in accordance to the Ministerial Decree DM 17-01-2018 of the

Italian legislature. They are therefore described as ordinary structures of a

limited size and average importance with a 50-year nominal life (years in

which the structure, subject to regular maintenance, maintains specific

performance levels).

According to the DM 17-01-2018, the reference period for seismic action is

evaluated based on a reference period VR that depends on the type of

construction (type 2, in our case) that equals the product of the nominal life

of the structure (VN) and the use coefficient CU.

๐‘‰๐‘… = ๐‘‰๐‘. ๐ถ๐‘ˆ

Page 82: Design, validation and commissioning processes for metal

74

The use coefficient value is, for buildings belonging to class IV, equal to 2.

The reference life for these structures is therefore of a 100 years.

5.1.1.2 Seismic hazard evaluation:

The seismic hazard evaluation depends on the seismological characteristics

of the area such as typology, size and depth of the seismic sources as well as

the energy and frequency of the earthquakes. This evaluation estimates the

values of the parameters suitable to predict the probability of exceedance

using probabilistic methodologies for a region at a given period of time.

Those parameters include speed, acceleration, intensity as well as the spectral

ordinates describing the shaking produced by the earthquake in conditions

of rigid soil and without morphological irregularities.

The seismogenic zonation reference in Italy is the ZS9, a variation of the

previous ZS4 zonation owing to the introduction of updated data on the

geometry of the seismogenic sources.

The SZ9 zonation consists of a subdivision of the Italian territory into 36

demarcated areas on the basis of geological-structural information, tectonic

and of other characteristics of seismicity such as the spatial distribution,

frequency of earthquakes or even the maximum magnitude released.

Page 83: Design, validation and commissioning processes for metal

75

Figure 59: ZS9 seismogenic zonation

Zones are identified by appointed numbers and have each different

seismogenic characteristics. The areas indicated with letters have not been

used for the evaluation of the seismic hazard.

The OPCM5 of April 28th 2006 nยฐ 3519 stating the โ€œgeneral criteria for the

identification of seismic zones and for the formation and updating of the lists

of the same areasโ€ identifies and approves the general criteria and the seismic

hazard map of reference in Italy by defining 4 zones, each of which is

identified by a maximum acceleration ag and with an exceedance probability

of 10% in 50 years (referring to rigid soils).

The evaluation of the acceleration ag is carried out on the basis of studies of

seismic hazard conducted on updated data and validated methodologies and

measured on a sufficient number of points and with the estimates of

associated uncertainties.

5 OPCM = โ€œOrdinanza del presidente del consiglio dei ministriโ€

Page 84: Design, validation and commissioning processes for metal

76

Figure 60: Seismic hazard values according to OPCM 3519/2006

For the assessment of seismic risk, Morocco relies on the โ€œEarthquake-

resistant building regulations RPS2011โ€ decreed by the Department of

Quality and Technical Affairs of the Ministry of Housing and City Policy.

Similarly, to the Italian approach, the RPS2011 requires a subdivision of the

national territory into homogeneous seismic areas presenting approximately

the same level of seismic risk with a certain probability of occurrence.

In each zone, the values defining the seismic hazard are considered to be

constant and refer to the maximum horizontal acceleration (Amax) or velocity

(Vmax) to the ground for a probability of exceedance of 10% in 50 years. This

equals to a return period of 475, corresponding to moderate earthquakes

likely to occur several times during the nominal life of the structures.

Page 85: Design, validation and commissioning processes for metal

77

The

Moroccan railway line from Casablanca to Tangier, as seen on the previous

figures, crosses zones with different seismic risks thus requiring different

assessments when designing the structures based on their location on the

Moroccan territory.

5.1.1.3 General geological framework:

This part of the technical report provides a geological description of the

territory in which the structures will be installed giving information about

the stratigraphy of the soil since each type of soil differs in its reaction and

the order in which they occur starting from the ground-level.

In addition to the stratigraphy, descriptions of the hydrogeological aspects

of the territory if near the installation sites of the structures are also included.

Figure 62: Seismic zonation in terms of Vmax for RPS2011 Figure 61: Seismic zonation in terms of Amax for RPS2011

Page 86: Design, validation and commissioning processes for metal

78

5.1.1.4 Description of the adopted survey methodologies:

In Italy, the surveys required for the different types of structures depend on

regional regulations. The table x shows the investigation conducted by the

Regional Regulation 7-02-2012 for the Lazio region and the testing that can

be performed according to the type of structure.

Generic requested investigation

Investigations needed for the structures in

question

Nยฐ 1 geognostic survey Nยฐ 1 geognostic survey

Nยฐ2 penetration tests Nยฐ1 penetration tests

Nยฐ2 MASW analyses for Vs30

calculation Nยฐ2 MASW analyses for Vs30 calculation

Measure of foundamental

frequency of the terrain Unneeded test for this typology of structure

Direct seismic test Unneeded test for this typology of structure

Stability Checks

Unneeded test since the applied loads are

modest and don't alter the stability conditions

of the area

Table 2: Comparison between requested investigation and executable investigations for the structures

For the characterization of the stratigraphy, the physical-mechanical and the

seismic response of the terrain on-site tests are used such as:

Continuous coring surveys with a depth value varying from 20 to 25

meters from the ground-level with at least one equipped with a

piezometer test to measure the groundwater.

Dynamic penetration test performed to evaluate the stratigraphy and

geotechnical parameters of the soil.

Page 87: Design, validation and commissioning processes for metal

79

MASW Seismic surveys for the evaluation of the equivalent mean

speed Vs30 indicating the speed of the shear waves in the first 30 m in

depth from the ground-level.

On-site geotechnical investigations are directed and checked by a geologist

certified by the State and carried out in compliance with the UNI EN/1997

regulation.

Continuous coring surveys

A geognostic survey is a survey methodology that allows the direct

inspection of the soil by perforating the ground using a drill. It is used for:

Reconstruction of the stratigraphic profile of the soil crossed.

Collection of representative samples to be submitted to subsequent

laboratory investigations

Reaching a certain depth

Coring surveys are performed by rotation and the drilling tool is composed

of a core drill (simple, double or triple) equipped at its end with a toothed

crown. The procedure starts by applying to the tool, through a battery of rods

that connects it to the surface, a simultaneous action of pushing and rotating.

The diameters used normally vary between 75 millimeters and 150

millimeters.

The drilling procedure can either be performed dry or with the introduction

of fluids.

The injection of the drilling fluid can be done on direct circulation if the fluid

falls in the internal rods or by inverse circulation (less frequent) if the fluid

Page 88: Design, validation and commissioning processes for metal

80

goes down along the walls of the hole. The use of fluids significantly

increases the speed of advancement but makes the coring of soft or coarse-

grained materials more complicated.

The direct circulation scheme is represented in the following diagram (figure

61) the pump lifts the fluid out of the tank and feeds it into the central tube.

From the bottom of the hole, the fluid rises to the surface, taking away the

crushed soil that settles in the collecting tank.

Figure 63: Coring procedure with direct circulation of fluids

The main goal for continuous coring surveys is the determination of the

stratigraphy of the terrain and the extraction of soil samples for laboratory

investigations. The perforation is performed by rotation through simple,

double or triple core drill according to the nature of the soil. These

instruments minimize the disturbance of the materials and allow the

collection of representative samples (core samples).

Page 89: Design, validation and commissioning processes for metal

81

Figure 64: Example of extruding the soil from the core drill

The core samples extracted from the core drill are then placed in appropriate

boxes, suitable for their conservation and on which the survey identification

number and the reference depth are indelibly marked.

Figure 65: Example of core sample storage

Penetration tests

Those surveys have been developed all over the world starting from the

studies of Mohr in the United States in 1927. Their widespread diffusion is

mainly linked to the possibility of operating directly on site providing

continuous geotechnical indications.

Page 90: Design, validation and commissioning processes for metal

82

The Standard Penetration Test (SPT) consists in allowing a standardized

sampler (Raymond sampler with thick walls) to penetrate the ground under

the blows of a hammer weighting 63.5 Kg.

The hammer is dropped from a constant height of 0.75 m and the

measurements are made for three consecutive advances of 15 cm each,

counting the number of blows needed (NSPT) for each advance. The resistance

to penetration of the soil is characterized by the sum of the number of blows

for the second and the third advances (N = N2 + N3). The test is performed at

the bottom of a probing hole (possibly altering the soil as little as possible)

previously excavated by means of a coring machine for example, at the

desired depth.

Figure 66: Standard penetration test

An object of conic shape embedded in the ground by successive blows

encounters during the penetration process, a resistance directly proportional

to one of the materials. If the material is the soil, this resistance gives the

physical-mechanical characteristics of the terrain in its natural state and

therefore, for coarse-grained soils this resistance depends mainly on the

Page 91: Design, validation and commissioning processes for metal

83

thickness of the granules, while on fine-grained soils it depends on its natural

water content.

Unlike the SPT test which is performed during the perforation process, the

DP (Dynamic Probing test) consists in measuring the resistance to

penetration of a metallic conical tip, connected to an extensible steel rod with

the addition of successive rods of standardized dimensions, fixed

perpendicularly to the ground by dropping the hammer of a given weight

from a constant height. The information provided by the test is continuous,

as penetration resistance measurements are performed through infixing.

The characteristics of the equipment and the execution methods have been

standardized in the International Reference Procedures elaborated by the

ISSMFE (International Society for Soil Mechanics and Foundation

Engineering) which includes four types of penetrometer on the basis of the

weight of the hammer:

DPL (light) M โ‰ค 10 kg

DPM (medium) 10 kg < M < 40 kg

DPH (heavy) 40 kg < M < 60 kg

DPSH (super heavy) M โ‰ฅ 60 kg

The count of the blows necessary for the advancement of a length of rod of

established length (NSPT) allows the use of empirical relationships that

provide the resistance of the soil to the infixing (Rd). This allows the

correlation of NDPSH to NSPT and the comparison of NDPSH (nยฐ of shots counted

to the advancement of the rod obtained with a super heavy hammer) with

the Qc obtained from the static test.

The dynamic resistance at the tip correlated to the number of blows N is

evaluated with the Dutch formula:

Page 92: Design, validation and commissioning processes for metal

84

๐‘…๐ท๐‘ƒ =๐‘€2. ๐ป

๐ด. ๐‘’. (๐‘€ + ๐‘ƒ)=

๐‘€2. ๐ป. ๐‘

๐ด. . (๐‘€ + ๐‘ƒ)

in which:

RDP = Dynamic resistance at the tip (Area A)

e = /N = piling per blow

M = blowing mass (dropping height H)

P = total mass (rods and whole system)

MASW analysis

The MASW6 method is a non-invasive investigation technique (it is in fact

not necessary to perform a drilling or excavation, limiting therefore the costs)

which identifies the speed profile of vertical shear waves (Vs) based on

surface waves measurements made through a certain number of sensors

(accelerometers or geophones) placed on the surface of the ground.

Those surveys are necessary to the:

Evaluation of the projectโ€™s seismic action at the level of the foundation.

Evaluation of the potential risk for liquefaction of the soil occurring

on saturated soils in which the strength and stiffness of it is reduced

by earthquake shaking or other rapid loading.

Evaluation of the seismic acceleration for the calculation of slope

stability and/or retaining structures against seismic action.

6 acronym for Multi-channel Analysis of Surface Waves

Page 93: Design, validation and commissioning processes for metal

85

Evaluation under seismic conditions of the load-bearing capacity

(capacity of soil to support the loads applied to the ground) and the

subsidence of road embankments, retaining structures and

foundations of buildings.

The predominant contribution to surface waves is given by Rayleigh waves

which travel at a speed depending on the stiffness of the portion of soil

involved in the propagation process of waves. In a stratified medium, the

Rayleigh waves are dispersive, i.e. waves with different wavelengths

propagate with different phase velocity and group velocity. In other words,

the apparent phase (or group) velocity of the Rayleigh waves depends on the

propagation frequency. The dispersive nature of surface waves is correlated

to the fact that high frequency waves with short wavelengths propagate in

the most superficial layers and therefore give information on the most

superficial part of the soil. In contrast, low frequency waves propagate in the

deeper layers and therefore affect the deeper layers of the soil.

The MASW method is divided into three phases:

Calculation of the phase velocity (experimental)

Calculation of the numerical phase velocity

Identification of the vertical shear waves velocity profile Vs suitably

modifying the thickness h of the soil layer, the shear speeds Vs and

compression speed Vp, the mass density ฯ of the layers covering the

soil model, the dispersion curve and the phase velocity (or dispersion

curve) corresponding to the assigned soil model.

The soil model and therefore the velocity profile of shear waves can be

identified by a manual or an automatic procedure or by a combination of the

Page 94: Design, validation and commissioning processes for metal

86

two. The number of layers of the soil model, the Poisson coefficient U, and

the mass density ฯ are generally assigned and the thickness h and Vs are

variable parameters.

In the manual procedure, the user assigns different values of the velocities Vs

and thickness h attempting to bring the numerical dispersion curve closer to

the experimental dispersion curve. In the automatic procedure, the search for

the optimal speed profile is entrusted to a global or local search algorithm

that tries to minimize the error between the experimental curve and the

numerical curve (Rome 2002, Joh 1998).

Generally, when the relative error between the experimental curve and the

numerical curve is between 5% and 10%, there is a satisfactory correlation

between the two curves, the velocity profile of the shear waves Vs and

therefore the type of consequent seismic soil represents a valid solution from

an engineering point of view.

After determining the velocity profile of vertical shear waves Vs, it is possible

to calculate the equivalent velocity in the first 30m of depth Vs30 and then to

identify the seismic category of the terrain.

๐‘‰๐‘ 30 =30

โˆ‘โ„Ž๐‘–

๐‘‰๐‘ ๐‘–

๐‘›1

The process of classification of the subsoil through the values of Vs, in the

DM 17-01-2018 is referred to as โ€œsimplified approachโ€ and is applicable only

if the soil is inscribed in one of the categories described in the table below,

otherwise, the effect of the local seismic response must be evaluated through

specific studies described in the DM.

Page 95: Design, validation and commissioning processes for metal

87

Category Foundation Soil Vs

A

Rocky outcrops or very rigid soils, possibly including

surface soils with poorer mechanical properties with a

maximum thickness of the layer of 3m > 800 m/s

B

Tender rocks of very thick coarse-grained soils or very fine-

grained soils characterized by a gradual improvement of

mechanical properties with depth

360 m/s < Vs <

800 m/s

C

Deposits of medium-thick coarse-grained soils or medium-

thick fine-grained soils with substrate depths >30m

characterized by improved mechanical properties with

depth

180 m/s < Vs <

360 m/s

D

Deposits of low density coarse-grained soils or scarcely

thickened fine-grained soils with substrate depths >30m

characterized by improved mechanical properties with

depth

100 m/s < Vs <

180 m/s

E

Soils with characteristics attributable to those defined for

categories C or D and substrate depth not exceeding 30m.

100 m/s <Vs <

360 m/s

Table 3: Soil categories accordin to the DM 17-01-2018

5.1.1.5 Geological Model:

The geological model consists in the definition of the stratigraphy and of the

nominal average geotechnical parameters obtained on the basis of the

investigations carried out and explained in the previous paragraph.

The most superficial layer in the stratigraphy shows for the type of structures

in question, the railway ballast for an average depth of 0.6 meters from the

ground-level and then the other layers for a depth of about 15m.

Page 96: Design, validation and commissioning processes for metal

88

For each of the layers, from the investigations carried out, the following

parameters must be deducted:

Weight per unit of volume

Weight per unit of saturated volume โ€™

Angle of internal friction

Effective cohesion cโ€™

Undrained cohesion Cu

Oedometric Modulus Ed

5.1.1.6 Seismic considerations:

The classification is carried out on the basis of the Vs30 equivalent velocity

values of share wavesโ€™ propagation within the first 30 m of depth. For

superficial foundations, this depth refers to the laying surface of it. To define

the seismic action for the project, the DM 17-01-2018 defines the stratigraphic

profile categories of foundations.

The amplification of the seismic motion due to irregularities of the

topographic profile was considered one of the main causes of damage

concentration during several earthquakes. Topographic amplification can

occur when local conditions are represented by the irregular morphology of

the surfaces and by topographic irregularities in general. These conditions

contribute to the concentration of the seismic waves near the relief ridge

following the reflection phenomena on the land and of the interaction

between the incident wave field and the diffract wave field. If the

topographic irregularity is represented by a bedrock, a pure topographic

amplification effect occurs while in the case of reliefs replaced by non-rocky

Page 97: Design, validation and commissioning processes for metal

89

materials the amplifying effect is the result of the interaction (hardly

separable) between the topographic and lithological effect.

For complex topographic conditions, it is necessary to conduct specific

analyzes of the local seismic response. For simple configurations, the

classification provided by the technical regulations of the DM 17-01-2018 can

be adopted and provides the value of the topographic amplification

coefficient ST, necessary for the studies of the elastic response spectra of

acceleration and function as well as of the location of the opera or

intervention.

Category Characteristics of the topographic surface

T1

Flat surface, slopes and reliefs with an average inclination i โ‰ค

15ยฐ

T2 Slopes with an average inclination i > 15ยฐ

T3

Reliefs with ridge width much less than at the base and

average inclination 15ยฐ โ‰ค i โ‰ค 30ยฐ

T4

Reliefs withridge width much less than at the base and

medium inclination i > 30ยฐ

Table 4: Topographic categories according to the DM 17-01-2018

Category Location of the structure or intervention ST

T1 - 1

T2 At the top of the slope 1.2

T3

At the ridge of a relief with an average inclination

> 30ยฐ 1.2

T4

At the ridge of a relief with an average inclination

โ‰ค 30ยฐ 1.4

Table 5: Maximum values of the topographic amplification coefficient ST

Page 98: Design, validation and commissioning processes for metal

90

5.1.2 Geometric characteristics of the structures

The task of the structural engineer is to size the structure based on the

information received and to produce all the documentation necessary for its

realization.

The geometrical dimensions of the structure and the parameters to be

considered for their definition were discussed in the previous chapter.

5.1.3 Loads to be assigned to the structures

The loads that are communicated to the structural engineer concern the

weight in Kg of the signals that the structures will have to support.

The type of signal to be mounted on each individual structure is deduced

from the schematic signaling plan and the technical specifications of the

signals are instead supplied by the company manufacturing these signals.

In the design phase, the signal and/or specific sign for each individual

structure is not considered, but rather a combination of them is. In particular,

it is the heaviest combination in terms of weight of the signals that is

considered to size the structure.

The positioning of the signal on the structure is defined in the preliminary

phase and derives from all the considerations made in the previous chapter.

5.2 Documentation supplied by the structural engineer

5.2.1 Technical report

The technical report is a document including the preparation of the

calculations for the metallic structures and the reinforced concrete plinths,

Page 99: Design, validation and commissioning processes for metal

91

considering all the preparatory aspects for the design of each construction

detail and providing all the verification systems.

5.2.1.1 Specification of the reference standards adopted

In Italy, the reference regulation for construction is the Ministerial Decree 17-

01-2018.

More generally, Europe relies on the Eurocodes covering every phase of the

structural project, particularly for the design of these structures we refer to:

Eurocode 0: Basis of structural design

EN 1990:2003 Basis of structural design

Eurocode 1: Actions on structures

EN 1991-1-1:2009 General actions - Densities, self-weight, imposed

loads for buildings.

EN 1991-1-3:2003 General actions - Snow loads

EN 1991-1-4:2005 General actions - Wind actions

EN 1991-1-5:2004 General actions - Thermal actions

EN 1991-1-6:2005 General actions - Actions during execution

EN 1991-1-7:2007 General actions - Accidental actions

Eurocode 2: Design of concrete structures

EN 1992-1-1:2004 General rules and rules for buildings

EN 1992-2:2005 Concrete bridges - Design and detailing rules

Page 100: Design, validation and commissioning processes for metal

92

Eurocode 3: Design of steel structures

EN 1993-1-1:2005 General rules and rules for buildings

EN 1993-1-5:2006 General rules - Plated structural elements

EN 1993-1-10:2005 Material toughness and through-thickness

properties

EN 1993-1-11:2006 Design of structures with tension components

5.2.1.2 Specifications on the materials used

In this part of the technical report are provided the characteristics of the

materials with which the structure was conceived in order to guarantee all

safety standards and design performances.

Steel

Steel is a metal alloy composed of 98% of iron and 2% of carbon which gives

it its typical strength. The graph below shows the behavior of a steel sample

subjected to a mono-axial traction test which is the most important laboratory

test for the characterization of the type of steel and from which the

characteristic parameters for the purposes of design are deduced.

Page 101: Design, validation and commissioning processes for metal

93

Figure 67: Stress and deformation diagram for steel

The graph reports on the ordinate the axial stress to which the material is

subjected while on the abscissa we find the elongation. The behavior of a

tensile steel can be divided into 4 phases:

Elastic phase: the application of a certain load determines a

proportional elongation of the sample, the diagram is rectilinear and

the deformations are elastic: after the elimination of the load, the steel

sample reacquires the initial size. This phase is governed by the law

of Hook:

๐œŽ = ๐ธ. ๐œ€

Where "ฯƒ" represents the applied load, "E" indicates the Young's

modulus (considered constant and equal to 210000 N/mm2), while "ฮต"

is the elongation (ฮต=ฮ”L/L).

Elasto-plastic phase: By increasing the load, the deformations are no

longer directly proportional to the applied stress in fact the diagram

slightly curves to the right. The steel sample stretches and the

elongations increase more rapidly than the increase of the load.

Permanent elongations are added to the elastic deformations and are

Page 102: Design, validation and commissioning processes for metal

94

as large as the load increase. The highest point of the curve section of

the graph is called yield strength (fyk).

Strain hardening and necking: In this phase, as the load increases,

elongations also increases until reaching its maximum value and

causing an increase in resistance. The deformations in this case are

plastic and even after the removal of the applied load, it will not be

possible to return to the initial size of the sample. Once the breaking

load (ftk) has been exceeded, there is the so called necking

phenomenon which corresponds to an area reduction of the section

and that point is also stochastically coinciding with the breaking point.

After the necking phenomenon, by continuing to increase the load, the

sample breaks.

The European standard UNI EN 10025-2 describes the quality of the types of

steel commonly adopted in buildings and provides the technical

characteristics of the materials in question.

Yield strength (fyk) [N/mm2]

Breaking load (ftk) [N/mm2]

Poisson coefficient (ฮฝ)

Young's modulus or elasticity (E) [N/mm2]

Thermal expansion coefficient (ฮฑ) [m/m /ยฐC]

Bolts:

Regarding bolts, the European reference standards are the UNI EN ISO 4016:

2002, the UNI 5592: 1968.

Page 103: Design, validation and commissioning processes for metal

95

Bolts are classified into resistance classes, for the Eurocode 3 the following

classes are considered: 4.6, 4.8, 5.6, 6.8, 8.8 and 10.9.

The nominal values of the breaking load and of the yield strength of the bolts

can be deduced directly and very simply from the code that characterizes the

class: each abbreviation is composed of two numbers where the first,

multiplied by 100, indicates the value of the breaking load (ftk) in N/mm2 and

the second, preceded by the point, indicates the coefficient that multiplied by

the value of the breaking load gives the yield strength (fyk) in N/mm2.

The characteristic resistance of a tensile bolt fk, N is obtained as the yield with

the variant that the multiplicative coefficient must not exceed the value of .7,

i.e for the bolts of classes 8.8 and 10.9 the characteristic tensile strength is

obtained by replacing โ€œ.8โ€ and โ€œ.9โ€ the value โ€œ.7โ€.

In the technical report the resistances of the adopted bolt classes must be

specified.

PLINTH IN REINFORCED CONCRETE

Concrete

Concrete is a material obtained by mixing a hydraulic binder, an inert

material and water. Portland cement is normally used as the binder, while

inert material is crushed stone from the shattering of sedimentary or

metamorphic eruptive rocks. The concrete responds well to compression,

which is why the laboratory test that is carried out to characterize it is the

compression test, while in the design phase its tensile strength is not even

considered. The diagram below shows the reaction of a concrete sample to a

monoaxial compression test.

Page 104: Design, validation and commissioning processes for metal

96

Figure 68: Stress and deformation diagram for concrete

On the axis of the ordinates there is the compressive stress while on the

abscissae we can read the deformations. The diagram has a parabolic trend

up to a 0.2% deformation and then presents a perfectly plastic course up to

the tensile deformation conventionally fixed at 0.35%. A non-linear behavior

is also noted for the concrete, even for low levels of applied load. The

maximum stress level below which the behavior of the compressed concrete

can be considered linear-elastic is about 30% of the peak resistance. The peak

load corresponds to a deformation of 0.2% which is somehow independent

from the resistance of the concrete. Concrete has a softening behavior,

meaning that once the peak load is reached, the material is not able to absorb

deformations greater than the one corresponding to the peak load, except

through a reduction of the load itself.

The compression tests are performed on cylindrical specimens (fck,

determining the characteristic cylindrical resistance of the concrete) or on

cubic specimens (Rck, which indicates the characteristic cubic resistance). The

technical standards consider the following relationship between the two

characteristic resistances:

๐‘“๐‘๐‘˜ = 0,83. ๐‘…๐‘๐‘˜

Page 105: Design, validation and commissioning processes for metal

97

In the technical report, the class of concrete to be used must be specified, for

example the C20/25, where "C" stands for "Concrete", "20" indicates the value

of the characteristic cylindrical resistance at 28 days (concrete setting time),

while "25" indicates the characteristic cubic resistance. In addition to the

concrete class, the following parameters must be specified:

Weight per unit of volume [kN/m3]

Poisson coefficient

Thermal expansion coefficient [m/m /ยฐC]

Reinforcement steel

Steel for reinforced concrete must be weldable and with improved adhesion,

i.e it must be designed with transversal ribs or indentations, uniformly

distributed over the entire length, suitable for increasing adherence to

concrete.

Figure 69: Concrete reinforcement steel

Page 106: Design, validation and commissioning processes for metal

98

In the figure below is represented the behavior of the weldable reinforcing

steel subject to a monoaxial traction test:

Figure 70: Stress and deformation diagram for reinforcement steel

Mainly 4 phases are distinguishable:

Elastic linear phase: any deformation due to the application of a load

lower than the value of yield fy, once removed, does not leave residual

deformations. The material returns to its initial configuration.

Deformation at a constant load: considerable deformations can be

noticed by keeping the yield load fy constant.

Hardening: After the deformation ฮตh is reached, there is a partial

recovery (hardening) and the tension can grow up to the maximum

value fu.

Necking: Further deformations are noted with a decreasing of the load,

accompanied by a reduction of the section until the specimen breaks.

Page 107: Design, validation and commissioning processes for metal

99

In the technical report, the characteristic qualities of the selected steel type

must be indicated according to EN 1992-1-1 regulation:

Yield strength (fyk) [N/mm2]

Breaking load (ftk) [N/mm2]

Poisson coefficient (ฮฝ)

Young's modulus or elasticity (E) [N/mm2]

Thermal expansion coefficient (ฮฑ) [m/m/ยฐC]

Exposure class and durability

The specifications on the selected materials conclude with indications

relating to the exposure class, the durability of the materials (for the concrete,

reference is made to the UNI EN 206-1 standard) and to any treatments to be

submitted to the materials such as galvanization for steels (including the

bolts).

Galvanization is an industrial process consisting in covering a metal product

with a thin and strongly adherent layer of another metal in order to protect

it from corrosion. The most frequent galvanizing process consists in coating

steel and iron products with zinc. The most common type of a galvanizing

process is the hot-dip, which is carried out by immersing the product in a

tank containing molten zinc (with small amounts of other metals), at a

temperature of approximately 450 ยฐC. After the procedure, on the surface of

the steel there is the formation of several layers consisting of almost pure zinc

(outer layer), alloys and intermetallic iron-zinc compounds of various

composition. The overall thickness depends on the type of manufactured

article, but generally it is of the order of at least 50รท100 ฮผm. The protective

mechanism of the layer that is thus formed is twofold. In addition to

Page 108: Design, validation and commissioning processes for metal

100

constituting a physical barrier that slows down the corrosion and

deterioration of the steel surface, zinc acts with an electrochemical

mechanism (hence the name of galvanization given to the process): if the

coating is damaged, leaving portions of the underlying material uncovered,

the surrounding zinc acts as a sacrificial anode (cathodic protection) avoiding

oxidation (rust formation) of the iron. Before embedding, the surface of the

manufacture to be galvanized must be subjected to degreasing and pickling.

The galvanized products can withstand for years exposed to oxidizing or

aggressive environments (atmosphere, rains, soils, sea water, etc.) especially

if the protection is reinforced by the subsequent application of suitable

paints.

The durability of the concrete is its ability to last over time, resisting the

aggressive actions of the environment, chemical attacks, abrasion or any

other degradation process that involves not only the cement paste but also

reinforcement steel.

The following table shows the exposure classes for the structural concrete

basing on environmental conditions of the site according to the UNI EN 206-

1 standard.

Page 109: Design, validation and commissioning processes for metal

101

Table 6: Exposure classes for concrete according to UNI EN 206-1

5.2.1.3 Evaluation of loads

There are many loads acting on the structures to be evaluated during the

design phase.

Page 110: Design, validation and commissioning processes for metal

102

Thermal action:

The thermal variations that act on the structures can be classified in:

Variations that only produce displacements and deformations

Variations that produce even or only coercion states (internal

solicitations)

Considering a free body in space and subjecting it to a temperature variation

ฮ”T. Due to the effect of thermal variation, the body undergoes at every point

a deformation ฮตT, whose magnitude is directly proportional to the

temperature variation.

The proportionality constant, i.e the coefficient of thermal expansion is

characteristic for each material and is indicated with ฮฑ:

๐œ€๐‘ก = ๐›ผ. โˆ†๐‘‡

Since the body is free to deform in any direction of space, because it is free of

constraints, the thermal variation produces only displacements and

deformations without causing any state of stress to arise within the body.

When we consider the effects of a thermal variation on a beam or on a beam

system subject to an assigned number of constraints, the effects that are

recorded vary according to the number and disposition of the constraints. In

particular, it is possible to notice:

Only deformations and displacements (as in the case of the free body)

Deformations, displacements and internal stresses

Page 111: Design, validation and commissioning processes for metal

103

Internal solicitations only

The cantilever bridges and the portals are statically simple and overall

isostatic structures therefore stresses due to thermal variations can be

considered negligible in terms of influence on the stress state of the structure.

However, it is up to designer to evaluate case by case.

Structural own weight (permanent)

The loads acting on the structures are divided into permanent and variable.

The load due to the weight of the structure is a permanent load and is

evaluated on the basis of the weight per unit of volume of the materials used

(concrete and steel) as indicated in paragraph 2.1 of the Eurocode 1 or the

Ministerial Decree 17-01-2018 in Italy.

The evaluation of the weight of the metal structure and of the reinforced

concrete plinth is left to the structural modeling and design software to which

the values of the specific weights of the materials are supplied as input data.

Non-structural weight (permanent)

The permanent non-structural weight refers to all metal elements not

belonging to the supporting structure (column (s) and beam (s)), that are

mounted and which are present during the normal operation of the structure.

Those permanent gravitational actions are derived from the geometric

dimensions and the weights per unit of volume of the materials constituting

the structure.

Page 112: Design, validation and commissioning processes for metal

104

For these structures, the non-structural permanent loads are spelled out in

terms of concentrated loads acting on the assembly points on the supporting

structure and their position on the structure. Here the loads to consider:

Weight on the catwalk

Weight of the climbing cage

Weight of the signal cage

Weight of the signals (signals, reflecting signs, LED illuminated

signs)

Mobile overloads

Overloads include loads related to the intended use of the structures. In this

case we consider the weight of workers equipped with tools for maintenance

in the external climbing cage and on the catwalks. The value of those loads

are assigned by the Eurocodes.

Snow actions

The load due to the snow is computable by following the calculations

reported on the Eurocodes. Here the process to follow according to the Italian

Ministerial Decree 17-01-2018:

๐‘ž๐‘  = ๐‘ž๐‘ ๐‘˜. ๐œ‡๐‘– . ๐ถ๐ธ . ๐ถ๐‘ก

where:

qsk is the reference value of the snow load on the ground and

depends on the local climate and exposure conditions, considering

Page 113: Design, validation and commissioning processes for metal

105

the variability of snowfall from area to area. Adequate statistical

surveys and specific local studies take into account both the height

of the snowpack and its density. The reference value of the snow

load on the ground, for locations at less than 1500 m above sea

level, it is assumed to be not lower than that calculated on the basis

of the expressions provided by Ministerial Decree 17-01-2018 in

paragraph 3.4.2 corresponding to a return period of 50 years for

the different areas of Italy.

For altitudes higher than 1550 m above sea level, local conditions

of climate and exposure must be taken into consideration, using

snow load values no lower than those foreseen for 1500 m.

ฮผi is a coefficient depending on the shape of the roof, on its

inclination with respect to the horizontal plane and on the local

climatic conditions of the construction site. For the structures

subject of this thesis, it is permissible to consider a form coefficient

of 0.8 relative to horizontal roofs and pitches less than or equal to

30 ยฐ.

CE is the exposure coefficient, taking into account the specific

characteristics of the area in which the structure will be built, in

case of scarce information about it we assume CE = 1.

Ct is the thermal coefficient, considering the reduction of the snow

load due to its dissolution, caused by the heat loss of the

construction. This coefficient depends on the thermal insulation

properties of the material used in the roof, in the absence of specific

studies or documents it is assumed as a precautionary measure

Ct=1.

Page 114: Design, validation and commissioning processes for metal

106

Aerodynamic effects caused by the transit of trains

Among the loads to be considered in the sizing phase of this type of structure

is the aerodynamic effect due to the passage of trains on the surfaces near the

tracks. This topic is reported in the FS document "Overloads for the

calculation of railway bridges - Planning instructions, 'performance and

testing' and in the EN 1991-2: 2003. The extent of the actions depends on the

following factors:

โ€ข The square of the train speed

โ€ข The aerodynamic shape of the train

โ€ข The shape of the structure

โ€ข The position of the structure and its distance from the track

Actions can be summarized by equivalent loads acting in areas close to the

head and tail of the train; these equivalent loads are considered characteristic

values of the actions.

The values of the aerodynamic actions are combined with the wind action

according to the rules reported in the above mentioned FS standard, relative

to the combinations of the actions for the ULS7. There are 3 case studies:

โ€ข Vertical surfaces parallel to the track

โ€ข Horizontal surfaces above the track

7 ULS is the Ultimate Limit State. The ultimate limit state is the design for the safety of a structure

and its users by limiting the stress that materials experience. In order to comply with engineering

demands for strength and stability under design loads, ULS must be fulfilled as an established

condition.

Page 115: Design, validation and commissioning processes for metal

107

โ€ข Horizontal surfaces adjacent to the track

โ€ข Structures with multiple surfaces alongside the vertical, horizontal

or inclined track.

The last case is related to the type of structures object of this thesis which

corresponds to a combination of the first case and the third one, therefore

concerning vertical surfaces parallel to the track (figure 69) and horizontal

surfaces adjacent to the track (figure 70). From the diagrams below it is

possible to obtain the characteristic values of the actions to be included in the

load combinations to the ULSs.

Figure 71: Characteristic values of qsk actions for vertical surfaces parallel to the track

Page 116: Design, validation and commissioning processes for metal

108

Figure 72: Characteristic values of qsk actions for horizontal surfaces parallel to the track

Figure 73: Characteristic values of qsk actions for vertical surfaces parallel to the track

Wind loads

The direction of the wind is generally considered horizontal, and it applies

actions on the constructions that vary in time and space, causing dynamic

effects. Below are reported the indications of the Italian legislation

concerning wind actions:

Page 117: Design, validation and commissioning processes for metal

109

Basic wind velocity

The basic wind velocity (vb) is the average value over 10 minutes, at 10 m

height above the ground on a homogeneous flat terrain of exposure category

II and referred to a return period TR = 50 years.

In the absence of specific and adequate statistical surveys, vb is given by the

expression:

๐‘ฃ๐‘ = ๐‘ฃ๐‘,0. ๐‘๐‘Ž

where:

vb,0 is the fundamental value of the basic wind velocity at sea level

and depends on the area where the construction is located.

ca is the altitude coefficient provided by the relation:

๐‘๐‘Ž = 1 for ๐‘Ž๐‘  โ‰ค ๐‘Ž0

๐‘๐‘Ž = 1 + ๐‘˜๐‘  (๐‘Ž๐‘ 

๐‘Ž0) for ๐‘Ž0 < ๐‘Ž๐‘  โ‰ค 1550 ๐‘š

where:

๐‘Ž0, ๐‘˜๐‘  are parameters depending on the building aite

๐‘Ž๐‘  is the altitude above sea level of the site where the building is

located.

For altitudes higher than 1500 m above sea level, basic wind velocity values

can be derived from appropriate documentation or adequately proven

statistical surveys referring to local climate and exposure conditions. The

values used shall not be less than those forecast for 1500 m altitude.

Page 118: Design, validation and commissioning processes for metal

110

Reference wind velocity

The reference wind velocity vr is the average value over 10 minutes, at 10 m

height above the ground on a homogeneous flat terrain of exposure category

II and referred to a return period TR = 50 years defined by the mathematical

relationship:

๐‘ฃ๐‘Ÿ = ๐‘ฃ๐‘ . ๐‘๐‘Ÿ

where:

vb is the basic wind velocity

cr is the return coefficient, function of the project return period TR

(expressed in years).

In the absence of specific and adequate statistical surveys, the return

coefficient is provided by the following mathematical formula:

๐‘๐‘Ÿ = 0.75โˆš1 โˆ’ 0,2. ๐‘™๐‘› [โˆ’๐‘™๐‘› (1 โˆ’1

๐‘‡๐‘…)]

Unless otherwise specified, it is assumed TR = 50 years, corresponding to cr =

1. For a new construction or for the transitional phases related to

interventions on existing buildings, the return period of the action can be

reduced as specified below:

Page 119: Design, validation and commissioning processes for metal

111

โ€ข For construction phases or transitional phases with a project

duration of no more than three months, it is assumed TR 5 years;

โ€ข For construction phases or transitional phases with a project

duration between three months and one year, it is assumed TR 10

years.

Equivalent static actions

Wind actions are constituted by pressures and depressions acting on the

normal direction with respect to the surfaces of the structures.

The action of the wind must be determined considering the most severe

combination of the pressures acting on the two faces of each element

(internally and externally).

The overall action exerted by the wind on a building is given by the result of

the actions on the individual elements. The wind direction is the one

corresponding to one of the main axes of the building plan.

Wind pressure

Wind pressure is given by the expression:

๐‘ = ๐‘ž๐‘Ÿ . ๐‘๐‘’ . ๐‘๐‘. ๐‘๐‘‘

where:

โ€ข qr is the reference kinetic pressure

โ€ข ce is the exposure coefficient

โ€ข cp is the pressure coefficient

โ€ข cd is the dynamic coefficient

Page 120: Design, validation and commissioning processes for metal

112

Tangent action of the wind

The tangent action per unit of surface parallel to the wind direction is given

by the expression:

๐‘๐‘“ = ๐‘ž๐‘Ÿ . ๐‘๐‘’ . ๐‘๐‘“

where:

qr is the reference kinetic pressure

ce is the exposure coefficient

cf is the friction coefficient

Reference kinetic pressure

The reference kinetic pressure is given by the expression:

๐‘ž๐‘Ÿ =1

2๐œŒ๐‘ฃ๐‘Ÿ

2

where:

๐‘ฃ๐‘Ÿ is the reference wind velocity

๐œŒ is the air density assumed conventionally constant and equal to

1.25 kg/m3

Expressing ๐œŒ in kg/m3 and ๐‘ฃ๐‘Ÿ in m/s, qr is expressed in N/m2

Page 121: Design, validation and commissioning processes for metal

113

Exposure coefficient

The exposure coefficient ce depends on the height โ€œzโ€ above the ground of

the considered point, on the topography of the terrain and on the exposure

category of the site where the construction is located. In the absence of

specific analyzes considering the origin direction of the wind and the actual

roughness and topography of the land surrounding the building, for heights

above the ground not greater than z = 200 m, it is given by the formula:

๐‘๐‘’(๐‘ง) = ๐‘˜๐‘Ÿ2๐‘๐‘ก ln (

๐‘ง

๐‘ง0) . [7 + ๐‘๐‘ก๐‘™๐‘› (

๐‘ง

๐‘ง0)] for ๐‘ง โ‰ฅ ๐‘ง๐‘š๐‘–๐‘›

๐‘๐‘’(๐‘ง) = ๐‘๐‘’(๐‘ง๐‘š๐‘–๐‘›) for ๐‘ง < ๐‘ง๐‘š๐‘–๐‘›

where:

kr, z0, zmin are tabulated according to the exposure category of the

construction site

ct is the topography coefficient

The exposure category is assigned according to the geographic position and

the roughness of the land. In the bands within 40 km from the coast, the

exposure category is independent of the altitude of the site.

Page 122: Design, validation and commissioning processes for metal

114

The topography coefficient ct is generally set equal to 1, both for the flat areas

and for the undulating, hilly and mountain areas

In the case of buildings located at the top of hills or isolated slopes, the

topography coefficient ct can be obtained from data supported by

appropriate documentation.

Figure 74:Illustrations of the exposure factor ce(z) for c0=1,0, k=1,0

Aerodynamic coefficients

The pressure coefficient cp depends on the type and geometry of the

construction other than its orientation with respect to the wind direction.

Page 123: Design, validation and commissioning processes for metal

115

The coefficient of friction cf depends on the roughness of the surface on which

the wind exerts the tangent action.

Both of these coefficients, defined aerodynamic coefficients, can be derived

from data supported by appropriate documentation or experimental wind

tunnel tests.

Dynamic coefficient

The dynamic coefficient takes into account the reductive effects associated

with the non-simultaneity of the maximum local pressures and of the

amplification effects due to the dynamic response of the structure.

It can be cautiously assumed to be equal to 1 in recurring constructions, such

as buildings with a regular shape not exceeding 80 m in height and industrial

buildings, or it can be determined by specific analyzes or by referring to data

of proven reliability.

For this type of structures wind is considered based on different directions

with respect to the structure, below the cases to be considered in the design

phase:

Wind parallel to the tracks:

o Wind on the catwalk

o Wind on the pylon

o Wind on the external cages

o Wind on the climbing cage

Wind perpendicular to the tracks:

o Wind on the catwalk

o Wind parallel to the cantilever (or to the beam for the portals)

o Wind on the pylon

Page 124: Design, validation and commissioning processes for metal

116

o Wind on the external cages

o Wind on the climbing cage

5.2.1.4 Calculation report

Calculation methods

The calculation report shows the results of the calculations concerning the

verification of the working tensions of the materials and of the ground in

compliance with current regulations. There are also reported the calculation

methodologies adopted, in general:

โ€ข For static loads: The deformation method

โ€ข For seismic loads: The method of modal analysis or equivalent static

seismic analysis.

The method of deformations (or displacements) is a resolutive method for

hyperstatic structures and is generally the one used in automatic calculation

software.

The principal system is geometrically determined and obtained by adding

constraints until the structure has its beams perfectly constrained. The

principal system is soluble (since is formed by constrained beams) and

respects the congruence (all the real constraints have been maintained).

However, the equilibrium is not respected since to keep the knots locked, it

is necessary to apply forces and/or couples that are different from the real

ones.

Page 125: Design, validation and commissioning processes for metal

117

Figure 75: Principal system

The actual system is found by applying to the principal system the actual

displacements and/or rotations (๐œ‰i ) of the nodes that have been locked.

Figure 76: Deformations of the principal structure with the deformation method

Page 126: Design, validation and commissioning processes for metal

118

The real displacements and/or rotations (๐œ‰i) are obtained by imposing that in

order to obtain them are applied in the nodes of the principal system forces

and/or rotations that, added to those caused by the load, restore the external

forces and/or rotations actually acting on the nodes themselves (which are

known). All these forces and/or couples are calculated on a system that is

solvable (the principal system formed by a set of embedded beams).

Therefore, the determining equations of ๐œ‰i are equations of equilibrium. Once

calculated the ๐œ‰i, the displacements and the rotations at the extremes of all

the beams are known and therefore with the formulas of the beam embedded

with the subsidence and rotations of the known constraints we can determine

the Normal stress, bending moment and shear stress.

The method of modal analysis concerns the study of the dynamic behavior

of structures that are subjected to vibrations (such as seismic vibrations). In

structural analysis, it allows the determination of the properties and the

response of a structure, constrained or free, in autonomous dynamics or

excited by dynamic forcing stress imposed from the outside. In the case of

simple bodies, modal analysis is able to study the dynamic behavior in detail

through the evaluation of its natural frequency and its associated vibrating

modes. In the case of complex structures, they are previously schematized

through the finite elements method in order to obtain the same results

referred to the whole.

The problem of free oscillations in a system without damping can be

explained by the following relation:

๐‘€๏ฟฝฬˆ๏ฟฝ + ๐พ๐‘ฅ = 0

admitting solutions like:

Page 127: Design, validation and commissioning processes for metal

119

๐‘ฅ(๐‘ก) = ๐‘(๐‘ก)

and having in general:

๐‘(๐‘ก) = ๐ด. sin(๐œ”๐‘ก + ๐‘ž)

Vectors and pulsations are found in correspondence with the eigenvalue

problem:

(๐พ โˆ’ ๐œ”2๐‘€)๐œ“ = 0

If the mass and stiffness matrices are nonsingular8 there will be โ€œnโ€ solutions,

otherwise if the matrix M has rank โ€œrโ€ the solutions will be just โ€œrโ€. The

stiffness matrix is generally nonsingular, meaning that there are no rigid

motions, while the mass matrix can often be singular since the rotational

moments of inertia are currently neglected. From the above formulas, it is

important to deduce how the dependence on time and position are

decoupled, in the course of a main oscillation the shape of the oscillation does

not change: only the amplitude of the oscillation changes with time.

The dynamic behavior of a structure is seen as the sum of a certain number

of elementary oscillations, each of which occurs according to its own period.

Moreover, in general, the various oscillations are not in phase with each other

therefore the maximums are reached at different times. Therefore, the overall

behavior is given by the sum of all the elementary modes:

8 The concept of nonsingular matrix is for square matrix, it means that the determinant is nonzero,

and this is equivalent that the matrix has full-rank.

Page 128: Design, validation and commissioning processes for metal

120

๐‘ฅ(๐‘ก) = โˆ‘ ๐‘๐‘–(๐‘ก)

(i = 1, n)

The modal analysis serves to find a certain number โ€œmโ€ (m << n) of these

pendulums while not having information about the shape of the oscillation.

The free oscillation of the model (not of the structure) is obtained by

imposing all the initial conditions in order to obtain the amplitudes and

phases of each of the oscillations. As for seismic analyzes, a sort of weighted

average of all these oscillations is made, arriving at a result in terms of

displacements and deformations (Analysis with the response spectrum).

For the calculation of this type of structure, it is hypothesized that in

correspondence with the seismic planes, the floors are infinitely rigid in their

plan and that the masses, for the purposes of calculating the plan forces, are

concentrated at their altitudes

Calculation of displacements and characteristics

The calculation of displacements and characteristics is generally done

according to the finite element method. This method allows to solve the

problem of determining the state of stress and deformation in elements under

load conditions for which the analytical solution canโ€™t be found or obtained.

The continuous, which has infinite degrees of freedom, is discretized, with a

set of elements of finite dimensions and interconnected in predefined points

(nodes).

The form functions bind the displacements at the generic point of the finished

element to the nodal displacements. For linear form function we have:

Page 129: Design, validation and commissioning processes for metal

121

๐‘ข = ๐‘Ž1 + ๐‘Ž2๐‘ฅ + ๐‘Ž3๐‘ฆ

๐‘ฃ = ๐‘Ž4 + ๐‘Ž5๐‘ฅ + ๐‘Ž6๐‘ฆ

in which the coefficients โ€œaโ€ are constant, u is the displacement and v is the

speed.

The choice of the form function influences the phase of subdivision into finite

elements. Using finite elements with linear form functions allows to model

the movements within the single finite elements through linear functions.

This process requires a very thick subdivision in correspondence of the areas

of the element in which there is expected to be a high degree of stress.

The introduction of finite elements allowing the use of form functions having

a higher degree, consent to adapt the degree of the form function to the

particular application (passing from simple interpolating polynomials to

more complex polynomials). It is the calculation program that, once having

fixed the type of subdivision into finite elements, uses functions of a suitable

degree form (in a hierarchical way, starting from polynomials of a lower

degree).

Figure 77: Form functions with higher than 1 Figure 78: Linear form functions

Page 130: Design, validation and commissioning processes for metal

122

For the metallic structures studied in this thesis work there are 2 types of

elements that can be defined and used:

One-dimensional rod element (beam) joining two nodes each with 6

degrees of freedom. For precision purposes, the shear and axial

deformability of these elements are also taken into account. Moreover,

these rods are not considered flexible from node to node but have on

the initial and final part 2 infinitely rigid sections formed by the beam

part incorporated in the thickness of the column; these rigid traits

provide the knot with a real dimension.

The two-dimensional shell (quad) element that unites 4 nodes in space. Its

behavior is twofold, it works as a plate for the loads acting on the

plane and as a plate for the orthogonal loads.

After assembling the stiffness matrices of the single elements in that of the

spatial structure, the resolution is pursued by various methods, such as the

Cholesky method.

For the purpose of resolution of the structure, the X and Y displacements and

the rotations around the vertical axis Z of all the nodes lying on a rigid

declared deck are mutually constrained.

Seismic and dynamic analysis with concentrated masses

Dynamic seismic analysis is carried out through modal analysis, the search

for modes and relative frequencies is pursued by the method of iterations in

the subspace. The number of vibration modes considered must be sufficient

to ensure the excitation of more than 85% of the total mass of the structure.

Modal forces are evaluated for each direction of the earthquake and are

Page 131: Design, validation and commissioning processes for metal

123

applied to each spatial node (3 forces, in the X, Y and Z directions, and 3

moments).

For the verification of the structure, it is usual to refer to the modal analysis,

therefore first the solicitations and the modal displacements are calculated

and then their effective value is computed. The equilibrium at the nodes loses

its meaning and the values of the seismic stresses are combined linearly (in

sum and in difference) with those for static loads in order to obtain the

seismic stresses in the two directions of calculation. It is necessary to define

with respect to which axis the angles of the seismic input directions are

evaluated in relation to the global reference system.

Reference systems, units of measurement and sign convention

It is important to define the reference system adopted for each individual

element:

Global reference system of the spatial structure: the reference system

consists of three Cartesian orthogonal axes (O-XYZ) where for

example the Z axis, which represents the vertical axis, can be

considered pointing upwards. The rotations are considered positive if

they agree with the vector axes.

Local reference system of the rods: the reference system, whether inclined

or not, consists of three Cartesian orthogonal axes. Generally, the Z

axis coincides with the longitudinal axis of the rod and is oriented

from the initial to the final node. The X and Y axes will be oriented

accordingly.

Page 132: Design, validation and commissioning processes for metal

124

Figure 79: Local reference system for the rods

Local reference system of the shell element: the reference system of the

shell element is also constituted by three Cartesian orthogonal axes.

Generally, the X axis coincides with the direction between the first and

the second input node, the X axis lying in the shell plane and the Z

axis in the thickness direction.

Figure 80:Local reference system for the shell element

It is important to specify the units of measurement adopted for:

o Lengths

o Strength

o Time

Page 133: Design, validation and commissioning processes for metal

125

o Temperature

It is also essential to define the conventions on the signs adopted. The loads

acting on the structures are of 2 types:

Loads and moments distributed along the coordinated axes

Loads and nodal couples concentrated on the nodes

Conventionally the distributed forces are considered positive if they agree

with the local reference system of the rod, the concentrated loads are positive

if their direction agrees with the global reference system.

In the calculation report must be inserted a section dedicated to the

explanation of the acronyms used in the tables of the thermal and distributed

loads on the rods, the concentrated loads, the shell thermal loads and the

loads on the shell elements. Beyond the tables that must be inserted are

related to:

Section archive:

o Angular with unequal sides

o Static characteristics of the profiles (moment of inertia, plastic

resistance module ...)

o Data for verification of the Eurocode

o Characteristics of the material

General structure data:

o Geometric dimensions

o Seismic parameters (nominal life, usage classes ...)

o Parameters of the seismic elastic spectrum to the Operability

Limit state (OLS)

Page 134: Design, validation and commissioning processes for metal

126

o Parameters of the seismic elastic spectrum to the Damage

Control Limit State (DCLS)

o Parameters of the seismic elastic spectrum to the Life-Saving

Limit State (LLS)

o Parameters of the seismic elastic spectrum to the Collapse

Prevention Limit State (CPLS)

o Parameters of the steel construction system

o Safety coefficients adopted for the materials

Coordinates of the nodes

Spatial rod data

Spatial shell data

Constraints and nodal settlements

Loads distributed on the rods

Loads concentrated on the nodes (thermal, distributed and

concentrated)

Loads on the shells

Load combinations

5.2.1.5 Results and verifications

In this section of the technical report are shown all the results of the analyzes

made using the calculation software. In particular, there are:

Graph of the spectral accelerations as in the figure below, but in

which the relative trends must be reported for each single load

combination both in horizontal and vertical direction.

Page 135: Design, validation and commissioning processes for metal

127

Figure 81: Design response spectrum

Table with excited frequencies and masses

Graphical representation of the vibrating modes of the

structure

โ€ข Graphic representation of the deformed structure considering the

wind parallel to the tracks

โ€ข Graphic representation of the deformed structure considering the

wind orthogonal to the tracks

โ€ข Graphical representation of the deformed structure for vertical

earthquake

Graphical representation of the maximum stress state in the

absence of earthquake

Graphical representation of the stress state with vertical

earthquake

Graphical representation of the stress state with earthquake

parallel to the tracks

Graphical representation of the stress state occurring in presence

of an earthquake having direction orthogonal to the tracks

Page 136: Design, validation and commissioning processes for metal

128

5.2.1.6 Verification of the plinth

This section shows the calculation results concerning the reinforcement

project, the resistance checks of the elements and the verifications related to

a foundation built on plinths.

For these structures, direct rectangular plinths are used and are generally

assumed to stay perfectly rigid as regards the calculation of the contact

pressures with the ground, which therefore have a linearly variable trend.

The soil is simulated as a reactive elastic compression surface (Winkler

model) and non-reactive tensile surface. The distribution and the extent of

the stresses on the ground is therefore a function of the resulting eccentricity

of all the efforts that discharge into the foundation, including the weight of

the plinth.

Winkler model: It is the most used model for calculating stresses in

foundation elements. The foundation soil is schematized as a bed of springs

having stiffness โ€œkโ€ (Winklerโ€™s โ€œkโ€), independent of each other;

consequently, the lowering of a spring does not involve also the lowering of

the adjacent spring. The value to be attributed to Winkler's โ€œkโ€ is an

expression of the geotechnical model of the subsoil. This value is generally

defined as the ratio between the applied load and the subsidence โ€œwโ€

obtained using an appropriate calculation method and the information

obtained from geotechnical investigations.

Page 137: Design, validation and commissioning processes for metal

129

Figure 82: Representation of the Winkler model for the foundation ground

The calculation of the plinth reinforcement can be performed using

simplified procedures. This is possible since the foundation plinths are

sufficiently thick to consider the plate behavior as that of four independent

brackets fixed to the base of the column.

The reinforcement of the basic grating can be obtained from the simple

bending calculation of the single brackets. Those corbels are considered

loaded by the pressure of the soil resulting from the combination of the

heaviest load.

The shear verification is therefore always carried out on the same brackets,

on a reference section distant from the column thread of a section equal to

half of the maximum height of the plinth. The satisfaction of such verification

automatically implies satisfaction of the punching9 verification.

If the length of the inspection bracket is less than 1.5 the maximum height of

the plinth, it is assumed to be sufficiently thick so as not to require any shear

verification. The verification of the base reinforcement is carried out with the

brace strut and tie scheme.

In the plinth verification section of the technical report, must be present

tables regarding:

9 Punching results from the application of a concentrated load or a reaction acting on a relatively small area of a plate or a foundation, called โ€œloaded areaโ€.

Page 138: Design, validation and commissioning processes for metal

130

โ€ข General calculation data

o Criteria for calculating the plinths

Minimum cover

Minimum percentage of reinforcement in a tensile

area

o Calculation criteria for poles

Load bearing capacity of the poles

Minimum percentage of total reinforcement

Tie factor at the top of the pole

Minimum net cover of the reinforcement concrete

brackets

o Verifications carried out using the Eurocodes method

Partial geotechnical coefficients

o Characteristics of the materials

Characteristics of the reinforced concrete

Stratigraphic characteristics

Load combinations:

o Ultimate Limit States (ULS) load combinations

o Life-saving Limit State (LLS) load combinations

o Rare load combinations to the serviceability Limit State (SLS).

o Frequent Load combinations to the serviceability Limit State

(SLS).

o Permanent load combinations to the serviceability Limit State

(SLS).

Loads on the plinths and hence on the foundation

Direct plinth verifications

o Slip check

o Serviceability limit state of the plinths

Page 139: Design, validation and commissioning processes for metal

131

5.2.2 Construction (or detailed) design of the structure

Among the most important output documents provided by the structural

engineer are the construction drawings.

In Italy, according to Presidential Decree 554/99 art. 38, the drawings are

drawn up on a scale of at least twice that of the final project, or in any case

in such a way as to allow the performer a reliable interpretation and

execution of the works in all their elements.

The graphic elaborations of an executive project include:

the drawings including all the graphic drawings of the final project;

the drawings which are necessary for the execution of the works on

the basis of the results, studies and investigations carried out during

the executive design phase;

drawing of all the construction details;

drawings illustrating the detailed methods of execution;

drawings needed to define the dimensional, performance and

assembly characteristics of the prefabricated components.

The construction design of the structures, according to Presidential Decree

554/99 art. 39 must include:

the graphic drawings of the whole structure (Carpentry, profiles and

sections) on a scale of not less than 1:50;

detailed graphic works on a scale of at least 1:10.

Page 140: Design, validation and commissioning processes for metal

132

Below are some details of the graphic drawings of the executive project of

the structures installed on the Moroccan line. Respectively there are 2

details on the joints and some details about the reinforced concrete plinth,

in particular about the positioning of the metal plates on the plinth for the

subsequent positioning of the columns, the details about the plates

themselves and other details.

Figure 83: Joint detail nยฐ1 of executive project drawing

Figure 84: Example of Plinth details of an executive project drawing

Page 141: Design, validation and commissioning processes for metal

133

Figure 85: Joint detail nยฐ2 of executive project drawing

5.2.3 Maintenance plan

The maintenance plan of the structures is the document that serves to

forecast, plan and program the maintenance activity. The aim of the

maintenance plan is to assure the functionality and quality features of the

structures over their nominal life (as defined by the design) as well as the

efficiency and economic value of it.

The user and maintenance manuals represent the tools with which the user

relates to the property, avoiding abnormal behavior that may damage or

compromise its durability and characteristics. Those manuals are also

consulted by maintainers who will use methods that are more suitable for a

management that combines economic efficiency and durability of structure.

Manuals define the procedures for collecting and recording information as

well as the actions necessary to set up the maintenance plan and to organize

the maintenance service efficiently, both technically and economically.

The user manual sets up a method of inspection of the artifacts that identifies

on the basis of the requirements set by the designer during the drafting of the

Page 142: Design, validation and commissioning processes for metal

134

project. In this manual are presented a series of faults that can affect the

durability of the structure and for which a maintenance intervention could

represent lengthening of the useful life and maintenance of the asset value.

The maintenance manual, on the other hand, represents the tool for the

subjects having the task of managing the asset to be able on planning the

activities. In fact, in this elaborate there are information based on the forecast

of the maintenance interventions whose frequency is presumed, the

indicative cost indexes and the medium and long-term implementation

strategies.

The maintenance plan is organized in relation to the art. 40 of the LLPP

regulation, in:

User manual;

Maintenance manual;

Maintenance program, organized in:

o The performance sub-program, which considers the services

provided by the structure and its parts during its life cycle.

o The control sub-program, which defines the program of checks

and controls in order to detect the performance level

(qualitative and quantitative) in the subsequent moments of the

asset's life.

o The maintenance sub-program, which reports the different

maintenance interventions in order to provide the information

for a correct conservation of the asset.

These instruments, in accordance with the UNI 10874 standard, are needed

to achieve the following objectives:

Page 143: Design, validation and commissioning processes for metal

135

Technical-functional objectives:

o Establish a system for collecting "basic information" and

updating it with "return information" following the

interventions allowing through the implementation and

constant updating of the "information system", to know and

maintain correctly the building and its parts;

o Allow the identification of the most appropriate maintenance

strategies in relation to the characteristics of the structure and

to the more general property management policy;

o Instruct technical operators on inspection and maintenance

operations to be carried out, favoring the correct and efficient

execution of the interventions;

o Instruct users on the correct use of the building and its parts on

any minor maintenance operations they can perform directly;

on the correct interpretation of the indicators of a fault or

malfunction state and on the procedures for its reporting to the

competent maintenance structures;

o Define the instructions and procedures to check the quality of

the maintenance service.

Economic objectives:

o Optimizing the use of the structure and extending its life

cycle by carrying out targeted maintenance operations;

5.2.3.1 User manual

The structural components of the structure object of the project are listed with

a description, their function and their correct use.

Page 144: Design, validation and commissioning processes for metal

136

The structures that are the object of this thesis are the signal cantilever

bridges and portals for railway signaling, therefore the structural units will

be:

For simple signal cantilever bridges, we have:

โ€ข Reinforced concrete plinth

o Description: Structural element in reinforced cement

conglomerate with horizontal or sub-horizontal surface

development with surfaces in contact with the ground or

concrete slab.

o Function: Distribution of the loads of the structure on the

ground.

o Proper use: the plinth is designed to withstand the design loads

of the elevated structure. It is advisable that the laying plan in

a foundation is all at the same level.

โ€ข Steel column

o Description: Structural element in steel with vertical or sub-

vertical linear development.

o Function: Support beams.

o Proper use: The column is designed to withstand the project

loads transmitted by the beams. The integrity and functionality

must not be compromised and a periodic check of the degree of

wear is necessary with the simultaneous recognition of any

anomalies.

โ€ข Steel beam

o Description: Structural elements in steel with horizontal or sub-

horizontal linear development.

Page 145: Design, validation and commissioning processes for metal

137

o Function: Support for railway signal cages.

o Proper use: The steel beams are designed to withstand the

project loads acting on them or transmitted by the elements

connected to them and their integrity and functionality must

not be compromised. It is necessary to periodically check the

degree of wear with the simultaneous recognition of any

anomalies.

In the case of T-shaped cantilevers bridges, there will be 2 cantilevers and

therefore 2 beams whose description, functionality and mode of use coincide.

For simple portals or with 1 or 2 cantilevers, the situation is similar since the

components are the same and therefore the mode of use and functionality are

equal to the ones referred to the cantilever bridges.

5.2.3.2 Maintenance Manual

Reinforced concrete plinth

The minimum level of performance for the reinforced concrete plinth is the

guarantee that the performance specifications indicated in the structural

design are respected.

Abnormalities found in the foundation plinths:

Subsidence: due to different causes and sometimes with

manifestations of the lowering of the foundation's laying plan.

Page 146: Design, validation and commissioning processes for metal

138

Figure 86: Schematic representation for plinth subsidence

Deformations and displacements: due to external causes that alter

the normal configuration of the element.

Detachment: disaggregation and detachment of significant parts of

the material that can also occur through the expulsion of

prefabricated elements.

โ€ข Exposure of reinforcing steel: detachment of parts of concrete

(concrete cover) and relative exposure of the steel rods to corrosion

phenomena due to the action of atmospheric agents.

โ€ข Cracks: degradation noticeable by the formation of continuity

solutions of the material and which may involve the reciprocal

displacement of the parts.

โ€ข Not perpendicularity of the manufacture: due to failures or events

of a different nature.

โ€ข Moisture penetration: appearance of moisture spots due to the

absorption of water.

Page 147: Design, validation and commissioning processes for metal

139

Figure 87: Example of moisture penetration

The image above shows the typical white efflorescence, consisting of sodium,

potassium, calcium and magnesium sulfates that appear on the concrete due

to moisture. The intervention methods are varied and regulated by the UNI

EN 1504 standard, include:

o Hydrophobic impregnation: treatment of concrete to obtain a

water-repellent surface

o Fluoro-carbonic impregnation: performs the same function as

hydrophobic impregnation while maintaining the breathability of

concrete.

o Impregnation: treatment of concrete aimed at reducing the

porosity of the surface and reinforcing it. Pores and capillarity are

partially or totally filled, this treatment generally produces a thin,

discontinuous film on the surface of the concrete.

o Coating: treatment aimed at obtaining a continuous protective

layer on the surface, with thickness ranging from 0.1 mm to 5.00

mm. The used binders are, for example, organic polymers, organic

polymers with cement as filler or hydraulic cement modified with

polymeric latex.

Page 148: Design, validation and commissioning processes for metal

140

โ€ข Swelling: variation of the shape of the concrete surface affecting the entire

thickness of the material. It is recognizable being given by the typical

"bubble" trend combined with the action of gravity.

Figure 88: Example of cracking, detachment of concrete and rust formation on reinforcement steel

In the image above we can see the cracking and the detachment of pieces of

concrete, in particular the total fall of the concrete cover with a consequent

exposure of the reinforcement rods which due to the action of atmospheric

agents led to the formation of rust.

Controls:

For this type of structures, the controls are set with an annual frequency

performed by specialized operators. The control procedure is visual and it is

supplemented by any non-destructive tests.

Page 149: Design, validation and commissioning processes for metal

141

Steel beams and columns:

As for the reinforced concrete plinth, the beams and columns must ensure

that the performance specifications indicated in the structural design are

respected.

Abnormalities found in beams and columns in steel:

โ€ข Bubbles or cracks: they may occur in the surface protective layer

with danger of corrosion and rust formation.

o Causes: action of atmospheric agents and environmental

factors, impacts or minimal external mechanical stresses; loss

of adhesion of the protective layer;

o Effect: exposure of the metallic element to the corrosive agents

and to the formation of rust;

o Evaluation: moderate;

o Required resources: anti-rust and / or passivating products,

paints, manual equipment, specific treatments;

o Performer: specialized company;

Corrosion or presence of rust: presence of areas corroded by rust,

extensive or localized even at joints and junction elements.

o Causes: loss of protective and/or passive layers, exposure to

atmospheric agents and environmental factors, presence of

chemical agents;

o Effect: reduction of the thicknesses of the various parts of the

element, loss of stability and resistance of the structural

element;

o Evaluation: serious

Page 150: Design, validation and commissioning processes for metal

142

o Required resources: anti-rust products, passivating agents,

paints, products and/or specific treatments for rust removal,

manual equipment;

o Performer: specialized company.

โ€ข Deformations and distortions: presence of evident and excessive

geometrical and shape variations of the structural element.

o Causes: excessive deformations and distortions occur when the

stress to which the structural element is subjected exceeds the

corresponding resistance of the material;

o Effect: loss of stability and resistance of the structural element

o Evaluation: serious;

o Required resources: new components, reinforcing elements,

provisional works;

o Performer: specialized company.

โ€ข Local buckling: local instability phenomenon that can occur in the

metal sheets constituting a structural steel element.

o Causes: concentrated loads, changing of the load conditions;

o Effect: loss of stability and load bearing capacity of the

structural element;

o Evaluation: serious;

o Required resources: reinforcing elements, stiffeners, new

components, welding equipment in place

o Performer: specialized company

โ€ข Tightening of jointed elements: loss of clamping force in the bolts

joining the steel elements.

o Causes: incorrect installation of jointed elements, change of

loading conditions, external causes;

Page 151: Design, validation and commissioning processes for metal

143

o Effect: loss of strength of the joint and therefore loss of stability

of the structural element;

o Evaluation: serious;

o Required resources: manual equipment, special equipment,

torque wrench

o Performer: specialized company

โ€ข Fireproof treatments: loss of protection and/or fire-retardant

coatings

o Causes: atmospheric agents and external environmental

factors, deterioration of coatings, minimal external mechanical

stresses

o Effect: loss of protection against high temperatures leading to

considerable deformations and therefore the possible collapse

of structural elements

o Evaluation: serious

o Required resources: fireproof products, manual equipment,

specific treatments

o Performer: specialized company

Controls:

For this type of structures, the controls are set with an annual frequency

performed by specialized operators. The control procedure is visual and

supplemented by any non-destructive tests.

Page 152: Design, validation and commissioning processes for metal

144

5.2.3.3 Maintenance schedule

The outcome of each inspection is the subject of a specific report to be kept

together with the related technical documentation. At the end of each

inspection, the technician in charge, if necessary, indicates any maintenance

operations to be carried out and express a summary judgment on the state of

the structure.

Page 153: Design, validation and commissioning processes for metal

145

CHAPTER 6: PRODUCTION AND FACTORY

ACCEPTANCE OF STEEL STRUCTURAL ELEMENTS

6.1 Processes for production of structural steel

6.1.1 Cast iron transformation process:

Steel is a metal alloy, meaning that there are dispersions of a solid into

another solid. There are:

โ€ข Solvent: base metal (metal material present in greater quantity)

โ€ข Solute: alloying metal (metal or non-metal material present in smaller

quantities and added to modify or improve the properties of the base

metal.)

Metals are polycrystalline solids, i.e. they are aggregates of many crystals

called grains and whose dimensions depend mainly on the cooling rate and

heat treatments. During the solidification of a liquid metal, the "crystalline

grains" are gradually formed throughout the mass.

Steel is a metal alloy, in particular it is a Fe-C alloy, in which carbon can be

present in the combined state in the form of iron carbide Fe3C (cementite), or

in pure form as graphite.

Depending on the percentage present in the alloy, ferrous materials are

classified as follows:

โ€ข Iron, with C <0.008%

โ€ข Steel, with C = 0.008 - 2.06%

Page 154: Design, validation and commissioning processes for metal

146

โ€ข Cast iron, with C = 2.06 - 6.67%

The physical, mechanical and technological properties of these alloys depend

essentially on the carbon content (and the undergone heat treatment). The

increase in the percentage of carbon in the alloy causes:

โ€ข Increased tensile strength (capacity of the material withstands normal

axial traction stresses)

โ€ข Increase in hardness (resistance to plastic deformation)

โ€ข Increase in fusibility (property of a material to melt at certain

temperatures)

โ€ข Decrease in resilience (ability of a material to absorb elastic

deformation energy)

โ€ข Decreased lengthening

โ€ข Reduction of weldability

โ€ข Reduction of forgeability (ability of a metallic material to be plastically

deformed when hot).

Cast iron can be of 2 types:

โ€ข Pig iron: obtained from the blast furnace and contains high

percentages of carbon (4-6%)

โ€ข Second cast iron: obtained by re-casting, in a special oven, the cast iron,

with the addition of scrap iron and other elements. Here the types of

second cast irons:

o White cast iron: carbon is in the form of Cementite Fe3C

o Lamellar cast iron: carbon is in the form of lamellar graphite

Page 155: Design, validation and commissioning processes for metal

147

o Spheroidal cast iron: carbon is in the form of spheroidal

graphite

The transformation process from cast iron to steel is called cast iron

conversion, in which the carbon content of the cast iron is reduced to obtain

the desired carbon content: decarburization of the cast iron.

In order to obtain the steel with the desired characteristics, in addition to the

reduction of the carbon content, the impurities are reduced and the

percentages of the alloying (silicon, phosphorus, sulfur, oxygen and other

gases) are modified with correction or refining operations. The

decarburization of the cast iron takes place in special ovens called

"converters", by means of a stream of compressed air that passes through the

liquid mass.

The first used converters include the Bessemer and the Thomas. Due to the

speed of the process and the presence of nitrogen (added in by the air blown)

those converters provide steel of poor quality. On the other hand, the steel

produced with the L.D converter (Linzer Dusenverfahren) or electric

furnaces is of higher quality.

Bessemer and Thomas converter

It consists of a pear-shaped receptacle, internally lined with refractory

materials and revolving around a central pivot, the difference between the

Bessemer converter and Thomas is in the type of coating: acid type in the first

(silica bricks) and basic type in the second (magnesia bricks).

The converter is loaded with liquid cast iron in a horizontal position and then

brought back to a vertical position, during this operation air under pressure

Page 156: Design, validation and commissioning processes for metal

148

is introduced through holes in the bottom. The oxygen contained in the air

burns the carbon in the cast iron which gradually turns into steel.

Figure 89: Bessemer converter

L.D. Converter

The acronym L.D indicating Linzer Dusenverfahren, stands for "process with

Linz spear". A long "spear" feeds pure oxygen into the converter containing:

โ€ข Liquid cast iron (70%)

โ€ข Iron scrap (for 30%)

โ€ข Lime

The exothermic reaction would bring the oven temperature to 2000 ยฐ C: this

is why ferrous scrap is introduced in fact it absorbs heat and lowers the oven

temperature to 1650 ยฐC. This converter produces high quality steels without

sulfur and little percentages of phosphorus and oxygen; they have excellent

mechanical and technological characteristics, more than 75% of the steel is in

fact manufactured with this method.

Page 157: Design, validation and commissioning processes for metal

149

Figure 90: L.D converter

Electric furnace:

Commonly called โ€œelectric arc furnaceโ€ since graphite electrodes are used

and after the current flows through them, they create an electric arc. The

electric arc can snap between the 2 electrodes or between the electrode and

the metallic bath creating an environment suitable for consuming excess

carbon. The high temperatures reached and the lack of chemical interference

due to combustion makes possible to produce steel with a low sulfur and

phosphorus content, as well as to treat cast iron, and is therefore suitable for

the manufacture of special steels starting from an already refined steel.

Figure 91: Electric furnace

Page 158: Design, validation and commissioning processes for metal

150

6.1.2 Steel rolling

The steel produced is marketed in the form of semi-finished products

obtained through the rolling process. Rolling is carried out directly at the end

of the continuous casting of the steel coming from the furnace or on the

ingots.

Laminates are subdivided in:

โ€ข Plates (thickness โ‰ฅ 6 mm)

โ€ข Sheets (thickness <6 mm)

The first rolling is carried out hot in order to change the melt microstructure

into a finer and more regular grain for subsequent rolling. The purpose of the

first rolling is also to dimensionally uniform the element and to reduce its

porosity thus increasing its ductility. Small diameter rollers tend to deform

the surface more and put it in compression, while with large diameter rollers,

friction limits the deformation of the surface and the interior deforms more

and results in a compression state.

Figure 92: Steel rolling

Page 159: Design, validation and commissioning processes for metal

151

After the first rolling, are produced:

โ€ข Blooms: with a square section from which the beams of various

sections or rails will be produced.

โ€ข Slabs: with a rectangular section and that will proceed to further

rolling procedures to produce laminates such as plates.

โ€ข Billets: smaller, square or round to be used for subsequent drawing.

The following diagram shows the general scheme of the rolling processes:

Figure 93: General scheme of rolling processes

6.1.3 Rolling defects:

Surface and structural defects may occur during the rolling process.

Page 160: Design, validation and commissioning processes for metal

152

Surface defects may derive from inclusions in the material of oxide, dirt

and/or other scales. Defects on the surface of the laminate can also occur as

result of the pre-rolling processes. In hot rolling, the oxides are removed in

advance with a torch treatment.

Structural defects, on the other hand, distort or compromise the integrity of

the laminate. Here are listed the main structural defects resulting from rolling

processes:

a) Undulations on the edge

b) Zippered cracks in the center

c) Cracks at the edge

d) Alligatoring

Figure 94: Rolling defects

6.2 Regulatory framework for the production of hot laminates for

structural steel

The standard that defines steel products by classifying them according to

shape, size, appearance and surface condition is UNI EN 10079. In addition

Page 161: Design, validation and commissioning processes for metal

153

to the finished products, this standard also includes a series of "semi-

finished" products from rolling mills.

The standard that defines the technical conditions for the supply of hot-rolled

(long and flat) products for structural use is UNI EN 10025. Hot-rolled long

steel products are commonly divided on the market into 2 macro-categories:

โ€ข Beams: profiles whose straight section resembles that of the letters H,

I, and U and whose core has a height equal to or greater than 80 mm.

โ€ข Merchant Laminates: this category ranges between bars (flat, convex,

round, polygonal, etc. and not intended for cement reinforcement),

angles and profiles that include profiles with L, T, I, U, H section

(completely identical to the beams except for the height of the core

which is less than 80 mm).

The materials and products for structural use must be:

โ€ข Univocally identified by the manufacturer

โ€ข Qualified under the responsibility of the manufacturer

โ€ข Accepted by the construction manager

For the typology of structures covered by this thesis, are used materials and

products for which European standards are available and their use on

structures is permitted only if accompanied by the:

โ€ข Declaration of performance: describes the performance of construction

products in relation to the essential characteristics of these products, in

accordance with the harmonized technical specifications. It contains

information such as the reference of the product-type for which the

Page 162: Design, validation and commissioning processes for metal

154

declaration of performance is drawn up, the system or systems of assessment

and verification of constancy of performance, the intended uses of the

construction product and the list of essential characteristics as set out in the

harmonized technical specification for the declared intended use or uses.

This declaration is drawn up according to a model in Annex III of EU

Regulation 305/2011.

โ€ข CE marking: It is affixed only to construction products for which the

manufacturer has drawn up the declaration of performance in accordance

with EU regulation 305/2011 and is the only marking attesting the conformity

of the construction product to the performance declared in relation to the

essential characteristics in accordance with the harmonized technical

specifications in the UNI EN 1090-1: 2012 standard.

In drawing up the declaration of performance and the qualification

documentation, the manufacturer assumes responsibility for the conformity

of the construction product with the declared performances.

6.2.1 Controls on steels (for concrete reinforcement or for metal structures):

The controls that are mandatory for each structural element are:

โ€ข Control in the production plant, to be carried out on the production

lots10

โ€ข In processing centers

โ€ข Acceptance on site

10 It refers to continuous production, ordered chronologically by affixing marks to the finished product. A

production batch must have homogeneous nominal values (dimensional, mechanical formation) and can be between 30 and 120 tons.

Page 163: Design, validation and commissioning processes for metal

155

Each type of steel destined for structural use, therefore both beams and

reinforcing steel for concrete, must be produced by means of a permanent

control system inside the plant, having to guarantee the same level of

reliability in the conformity of the finished product, regardless of the

production process.

The quality management system during the manufacturing process must

follow the provisions of the UNI EN ISO 9001 standard and certified by a

third party body that operates according to the UNI CEI EN ISO / IEC 17021-

1 standards.

The UNI EN ISO 9001 defines the minimum requirements that the quality

management system of an organization must demonstrate to satisfy in order

to guarantee the level of quality of the product. Today this standard

represents the best known international standard applicable to any

organization, regardless of the type and the economic sector to which it

belongs. This standard promotes the adoption of a process approach in the

development, implementation and improvement of the effectiveness of a

quality management system.

The UNI CEI EN ISO / IEC 17021 standard is the international standard that

defines the requirements for organizations that provide audits and

certification of management systems in general for the quality, environment

and health and safety of workers. The purpose of this standard is to ensure

that all the interested parties that the certified management systems meet the

requirements of the reference standard, substantially serves to guarantee the

credibility of the certifications.

The regulations require that each qualified product must constantly be

recognizable as regards the qualitative characteristics and traceable to the

production plant through indelible marking from which the reference of the

Page 164: Design, validation and commissioning processes for metal

156

manufacturing plant11, the plant, the type of steel and its steel is

unequivocally deductible possible weldability. These marks may be made by

different systems based on their use. Markings can be carried out with the

impression on the rolling products with hot and cold procedures. The

branding is mandatory and its application methods are regulated.

6.2.2 Processing centers (or transformation centers):

The transformation centers are defined as the external plants to the

production factories or the fixed or mobile construction site, which receives

the basic elements from the steel producer and packages the structural

elements directly usable on site, ready to be installed. These centers can

receive and work only products originally qualified accompanied by the

required documentation (CE marking and declaration of performance).

These plants must be equipped with a control system (in compliance with the

UNI EN ISO 9001 standard) of the processing in order to ensure that the

processes performed there ensure compliance with the mechanical and

geometric characteristics of the products.

The products supplied on site after the intervention of a processing center

must be accompanied by documents attesting to the origin and production

processes of the element itself.

During the production process within manufacturing centers special

attention must be paid to the roll face milling, cutting, drilling and bending

processes, as well as to the welding procedures. The technical director of the

workshop must ensure that the processes adopted do not alter the original

mechanical characteristics of the material.

11 The plant refers to a production unit, with its own plants and warehouses for the finished product.

Page 165: Design, validation and commissioning processes for metal

157

The checks must concern at least 1 test every 30 t of steel of the same category

coming from the same factory, even if acquired at different times, having the

foresight to take samples from different types of products or thicknesses from

time to time.

The data obtained from the experimental tests must meet the requirements

of the harmonized European standards UNI EN 10025 for the tensile and

resilience tests, as well as the UNI EN 10210-1 and UNI EN 10219-1 standards

for the chemical-physical characteristics.

6.2.3 Laboratory tests to be performed on structural steel rolled products:

For the realization of metal structures and composite structures steel must be

used in compliance with the standards UNI EN 10025-1, UNI EN 10210-1 and

UNI EN 10219-1 and must possess the CE mark.

For the declaration of services and labeling, the methods provided for by the

European standards have to be applied and in particular it will be necessary

to provide:

โ€ข Declaration of the geometric characteristics and properties of the

material.

โ€ข Declaration of component performance on the basis of Eurocodes.

โ€ข Declaration based on a specific project specification.

In the processing centers, laboratory tests must be performed on the beams

produced to verify their mechanical characteristics. The values of the yield

and breaking stress must, of course, always be lower than the table limits

present in the standards and must be checked that the manufacturing

tolerances respect the limits indicated in the applicable European standards.

Page 166: Design, validation and commissioning processes for metal

158

The tests are carried out by taking samples in well-defined points of the

laminated product. The tests that must be carried out on the production lots

are:

โ€ข Chemical analysis

โ€ข Tensile test

โ€ข Proof of resilience

โ€ข Hardness test

โ€ข Microscopy

โ€ข Surface roughness

In the tables below the indications relating to the sampling and the type of

test according to the UNI EN 10025-1 standard.

Page 167: Design, validation and commissioning processes for metal

159

Figure 95: Sampling indications for testings according to UNI EN 10025-1 standard

Page 168: Design, validation and commissioning processes for metal

160

Figure 96: Sampling indications for testings according to UNI EN 10025-1 standard

6.2.3.1 Chemical analysis:

The chemical analysis is performed with an emission spectrometer which

analyzes the metal by means of an electric discharge between the sample,

previously prepared by grinding, and a tungsten or silver electrode in an

inert atmosphere chamber (argon). The excitation of the specimen generates

a beam of light that purposely dispersed by a prism hits the phototubes

Page 169: Design, validation and commissioning processes for metal

161

sensitive to the various bands with different wavelengths that are generated

and at each determined wavelength corresponds an element to be analyzed.

6.2.3.2 Traction test:

The tensile test consists of subjecting a steel sample having a constant section,

with a tensile load applied along its axis. The applied load must increase

gradually until the sample is broken. From this test we obtain the stress-

deformation graph characteristic of the various types of steel (see figure 65).

From the test we get:

โ€ข Unitary breaking load (R)

โ€ข Unitary load of deviation from proportionality (given by the ratio

between total load to yield limit and the original section of the tube

expressed in mm2)

โ€ข Elongation (A%)

6.2.3.3 Proof of resilience

It consists in hitting with a club of known weight, one meter from its fulcrum,

a steel sample in which a notch has been made to facilitate the breaking. With

the resilience, the toughness of the steel and the bending resistance by impact

are measured. The notch on the specimen can be in a shape of a "V" or "U".

Page 170: Design, validation and commissioning processes for metal

162

Figure 97: Resilience test on steel

Figure 98: Test specimens for resilience test (dimensions are indicated in mm)

The test can be performed at room temperature at 0 ยฐ C or at a temperature

below zero ยฐ C.

The results are expressed in Joule per cm2.

6.2.3.4 Hardness test

The hardness of a material is defined as its resistance to deformation, as its

resistance to being damaged by another harder material. The hardness values

Page 171: Design, validation and commissioning processes for metal

163

obtained depend on the type of test to which the specimens have been placed,

there are 3 methods:

โ€ข Brinell hardness (Rockwell): An indenter (hard metal ball with diameter

D) is forced into the surface of a test tube and the diameter of the

impression d left on the surface after releasing the load F is measured.

Brinell hardness represents the quotient between the applied load and

the area of the spherical surface of the impression.

Figure 99: Brinell hardness test

โ€ข Vickers hardness: A diamond penetrator having the shape of a straight

pyramid with a square base with a vertex angle between opposite

specified faces, is made to penetrate within the surface of a tube; then

the length of the diagonal of the impression left on the surface is

measured after removal of the test load, F.

6.2.3.5 Optical microscopy

Optical microscopy is a fundamental method for the structural analysis of

materials. The possibility of enlarging a section of the suitably treated

material allows to investigate the thermal history of the preparation from the

moment of its solidification in the foundry. This test gives precious and

almost always complete information about the use of the material, as it

determines the mechanical resistance, the corrosion resistance and the wear

Page 172: Design, validation and commissioning processes for metal

164

of the material itself. The technique is particularly effective for the study of

heat treatment anomalies, for the evaluation of inclusions, for the

interpretation of breakages and for the evaluation of the welding and

coatings. The results of these tests must be interpreted in order to be able to

issue a diagnosis on the analyzed material. From the images are extracted

information such as the percentage of presence of the various phases

constituting the material, the distribution, the circularity and the dimensional

degree of the graphite spheroids.

6.2.3.6 Roughness

The roughness is measured using tools called roughness meters. Roughness

is a property of the surface of a body, consisting of geometric micro-

imperfections normally present on the surface or even resulting from

mechanical processing. The roughness measurement procedure consists in

recording the profile of the surface obtained along a determined

measurement line (or scan).

6.2.4 Checks of bolted joints

The connecting elements must comply with the provisions contained in the

following standards:

โ€ข UNI EN ISO 3506-1: 2010 for screws (item "a" in the figure below)

โ€ข UNI EN ISO 3506-2-2010 for nuts (element "b" of the figure below)

โ€ข UNI EN ISO 3506-3: 2010 for headless screws and similar parts not subject

to tension (element "c" of the figure below)

Page 173: Design, validation and commissioning processes for metal

165

Figure 100: Elements constituting a bolt

The main tests carried out in the laboratory to know the quality of the

connecting elements are:

โ€ข Traction test on test tubes

โ€ข Tensile test on full screw

โ€ข Hardness test

โ€ข Resilience on a test tube

โ€ข Toughness of the head of screws

โ€ข Shear test

โ€ข Determination of the percentage elongation after rupture

โ€ข Determination of the breaking load

โ€ข Determination of yield strength

โ€ข Tearing resistance

โ€ข Check the tightening torque of the bolt

6.3 Welding process:

The welding technique allows two metal parts to be joined through the use

of heat. The localized fusion of the edges of the pieces to be joined is obtained

by the addition or not of a filler material.

The brazing procedure refers to when the base material is not melted but only

heated and the process of joining the materials is made by melting only the

filler material, having a melting temperature lower than that of the base

material.

Page 174: Design, validation and commissioning processes for metal

166

A material is considered weldable when it lends itself to the realization of a

structure in which continuity is assured and that presents characteristics that

meet the required quality standards.

The welding process involves one or more types of materials, which mainly

fulfill two roles:

โ€ข Base material: it is the material that makes up the pieces to be welded;

it can be the same for both pieces (homogeneous welding), or different

(heterogeneous). The most commonly combined metallic materials are

steel, aluminum alloys, nickel alloys and titanium alloys. The only

polymeric materials that can be welded are the thermoplastic ones.

โ€ข Filler material: it is the material that is introduced in the form of rods,

wires or strips and deposited in the molten state between the flaps to

be joined. The filler materials are always particularly pure, so the

impurities within the molten area of a joint generally come from the

base material.

The management of the various welding and brazing procedures is based on

the choice of specific parameters for each type of process. On a general level,

in most processes it is possible to identify mainly two characteristic

parameters:

โ€ข The specific power: represents the thermal power delivered per unit of

surface of base material, measured in W/cm2;

โ€ข The welding speed: represents the speed of the thermal source,

measured in cm/min.

Page 175: Design, validation and commissioning processes for metal

167

6.3.1 Types of welding:

At the macroscopic level, the processes that have been most developed in the

industrial field belong to the fusion welding group.

These processes use heat, generated in various ways, to merge the base

material. The most commonly used processes can be classified in the

following sub-groups:

โ€ข Electric arc: Arc welding refers to a group of processes that exploits

the electric arc generated between two electrodes. The โ€œarcโ€ can be

obtained using:

o A fusible electrode;

o A refractory electrode, that is not fusible;

In the first case, the melting electrode, supplies the filler metal. On the other

hand, when non-fusible electrodes are used at the arc temperature, the filler

material (if necessary) is supplied separately, using rods or wires. The

fundamental element to obtain an electric arc is the current. It is possible to

supply the arc both with direct current (DC) and with alternating current

(AC). The choice between DC and AC depends on the type of process used

and on the material to be welded.

The main types of electric arc welding are:

Manual Metal Arc welding (MMA)

Submerged arc welding (SAW)

Page 176: Design, validation and commissioning processes for metal

168

Continuous wire under gaseous protection (MIG /

MAG)

Under gaseous protection and with an non fusible

electrode, the so called Tungsten Inert gas (TIG)

โ€ข Resistance welding: It is a joining process without filler metal, in which the

heat required to melt the edges to be welded is provided by the resistance

opposed to the passage of an electric current through the area to be joined.

โ€ข Oxyacetylene: Oxyacetylene welding is a process that uses, as a heat source,

the flame resulting from the combustion of acetylene (C2H2) with oxygen

(O2).

โ€ข Concentrated energy: This group includes the processes that use energy

bundles that can concentrate very high powers on the piece, ranging from

several thousand to several million watts per square millimeter of surface.

6.3.2 Welding techniques:

The welding process can be manual, semi-automatic, automatic or robotic,

depending on the equipment and mode of execution.

โ€ข Manual: In the manual process, the welder manually adjusts the

equipment and moves the electrode or heat source (electrode coated

and oxyacetylene welding);

โ€ข Automatic: a device feeds the electrode or the beam generating

source, to keep it at a suitable distance from the piece and move it

Page 177: Design, validation and commissioning processes for metal

169

along the welding line (submerged arc welding, with electric arc

under MIG / MAG gas protection and TIG, with concentrated energy).

โ€ข Semi-automatic: The semi-automatic process is a middle way between

the two previous ones: a device feeds the electrode wire or delivers

the current while keeping the other parameters constant, while the

operator has the task of moving the electrode along the line welding

(electric arc processes under MIG / MAG and TIG gaseous protection).

โ€ข Robotic: If the operation is carried out using an industrial robot or a

programmable manipulator, it is defined a robotic welding procedure.

It is mainly used for electric arc welding under MIG / MAG and TIG

gas protection and for laser welding, but also in the final assembly of

cars for the resistance union of the bodywork.

6.3.3 Regulatory framework for welding processes of structural steel elements:

For the welding of structural steel elements, reference is made to the UNI EN

ISO 4063: 2011 standard for electric arc welding, while for other types of

welding, theoretical and experimental supporting documentation must be

provided.

For each welding technique, operators must possess qualifications:

โ€ข The welders in semi-automatic and manual processes must be

qualified according to the UNI EN ISO 9606-1-2017 standard by a third

party that can choose the manufacturer according to criteria of

competence and independence. The Italian legislation also requires in

Page 178: Design, validation and commissioning processes for metal

170

addition to what is required by European legislation that welders who

perform T-joints with corner cords must be specifically qualified and

can not be qualified only by the execution of head-head joints.

โ€ข The operators of automatic or robotic procedures must instead be

certified according to the UNI EN ISO 14732: 2013 standard.

All welding processes must instead be qualified by WPQR (qualification of

welding procedures) according to the UNI EN ISO 15614-1: 2017 standard.

The welding processes carried out must be accompanied by documentation

that certifies them in the molten area and in the thermal zone and providing

the following characteristics:

โ€ข Ductility

โ€ข Yield

โ€ข Toughness12

6.4 Factory acceptance of the structure

The factory acceptance of a structure consists of a series of processes and

checks on the structures in order to ensure that what is produced by the

factory itself complies with the functional specifications of the project.

As seen in the previous paragraphs, all steel elements must pass a series of

checks before they can be put into use.

Factories that produce metal carpentry and subsequently manufacture the

structures can only process steels from production plants that meet all quality

12 The ability of a material to absorb energy and to deform plastically before rupture is defined as the area below the stress/deformation curve of a tensile test.

Page 179: Design, validation and commissioning processes for metal

171

criteria according to UNI EN 9001 and that possess a CE marking and a

Declaration of Performance.

Subsequently in the factories, once the structural elements have been rolled,

further tests are carried out in order to verify that these manufacturing

processes have not altered the properties of these materials.

The factory acceptance checks for the type of structures covered by the thesis

consist of:

Geometric checks:

Completeness of the structure: Check the presence of each single

element constituting the structure according to the executive design

and therefore the bearing structure, bolts, ladders, signal cages and

hand rails;

Verify that the individual elements of the load-bearing structure

respect the dimensions and configurations indicated in the executive

project. These elements are:

o Steel columns (also check the plate for anchoring the column to

the plinth)

o Beams:

Check the conformity of the type of profile produced with

that present in the structural design (UPN);

Check that the cuts have been made at the points indicated

in the executive project;

Check that the welds have been carried out in conformity

with the design instructions in accordance with EN ISO

23277.

Page 180: Design, validation and commissioning processes for metal

172

Check the arrangement of the modules according to the

design drawing

Check that the dimensions of the non-load-bearing structural

elements are in accordance with the design drawings, these elements

are:

o Ladder

o Hand rail

o Signal cage

The last geometric check consists in verifying the compatibility of the holes

for the realization of the bolted unions.

Checks on the treatments carried out on the steels:

For this type of structure, the treatment that is performed is the

galvanization. It is necessary:

Check that the hot-dip galvanizing procedure has been carried out in

accordance with EN 1090-2;

Visual inspection to check that there are no oxidation phenomena;

Check that the thickness of the layer complies with the design

specifications.

Documentation to be requested at the time of acceptance of the structure at

the factory:

Request the CE marking certificate and the Declaration of

Performance issued by the steel production plant (and check that the

Page 181: Design, validation and commissioning processes for metal

173

type of steel used for the construction of the structure coincides with

the one present in the material specifications of the executive project);

Certification of execution of welding processes according to UNI EN

ISO 4063: 2011 and verify that the welders are trained according to the

indications given in UNI EN ISO 9606-1-2017;

Manual for assembly of the structure on site.

Page 182: Design, validation and commissioning processes for metal

174

CHAPTER 7: ACCEPTANCE OF THE STRUCTURE

AND CONSTRUCTION OF THE PLINTH AT THE

BUILDING SITE

This chapter describes the procedures for accepting the metal structure on

site according to Italian regulations. European standards cover the processes

of production and supply of materials, in order to ensure a common standard

for what concerns the products marketed in Europe. However, with regard

to the procedures for acceptance, sampling and subsequent performance of

laboratory tests, the national standards are referred to. In Italy, reference is

made to the technical standards for construction NTC 17-01-2018.

In the chapter will also briefly describe the procedure for the construction of

the plinth on site and the subsequent phase of assembly of the structure

arrived on site from the processing center (factory).

7.1 Acceptance of the structure materials on-site before starting the

construction

Acceptance on site of the structure materials means the acceptance of its

individual components by the site manager. The on-site acceptance checks

for these structures will therefore cover:

Steel for metal structures

Bolts

Concrete

Steel for concrete reinforcement

Page 183: Design, validation and commissioning processes for metal

175

7.1.1 Steel

The acceptance procedure for the structures on building site of shipping lots

of a maximum of 30 tons must be equipped by:

o Identification mark (unalterable over time and without the

possibility of tampering)

o Different identifiers for products having different

characteristics even if manufactured in the same factory.

If these 2 elements are not present, the product is absolutely not usable on

site.

In Italy, on-site supplies of pre-welded, pre-shaped or pre-assembled

elements made by a processing center must be accompanied by a declaration

on the Transport Document of the details of the declaration of activity issued

by the Central Technical Service of the Higher Council of LL.PP with the logo

of the center itself and the attestation of the internal control tests carried out

by the technical director of the processing center.

The Site Manager must carry out checks on each type of supply at the

laboratories in accordance with art. 59 of Presidential Decree no. 380/2001.

The qualitative and quantitative validity of the on-site checks must then be

checked by the Inspector who, if not, is required to have the tests provided

for by the standard carried out and/or completed.

7.1.1.1 Steel for metal structures:

Only qualified steels with an identification mark are allowed on site, with

mandatory controls both in the processing centers and on site.

Page 184: Design, validation and commissioning processes for metal

176

On-site inspections are managed by the Site Manager and consist in taking

from each supply a maximum of 30 tons of at least 3 samples, of which, one

is on the maximum thickness and the other one is on the minimum thickness

as shown in the figure (X - chapter 6). From these tests will be obtained the

test tubes for the tests of:

o Traction

o Resilience

o Chemical composition

If the outcome of the testing is negative, the standards require tests to be

carried out on a further 10 tests to verify the acceptance of the tests before

refusing the supply.

All samples must be taken in the presence of the site manager or a trusted

technician.

Samples must be labelled and accompanied by explicit documents, the

request for testing signed by the site manager must be delivered to the

laboratory by the site manager himself.

For supplies coming from a processing center (as is generally the case for the

type of metal structure in question), the site manager must make sure that

the center meets all the requirements (chapter 6) and if adequate samples to

be tested are not delivered to the worksite, he may himself go to the

processing center to carry out the relevant checks and arrange for samples to

be taken. In this case, the sampling is carried out by the technical director of

the processing center.

The site manager must ensure, by means of indelible markings and labels,

that the samples to be tested in the laboratories are actually those taken by

Page 185: Design, validation and commissioning processes for metal

177

him and must sign the related request for tests and deliver the samples

personally or by a technician of his choice.

7.1.1.2 Steel for concrete reinforcement:

Acceptance checks on site for concrete reinforcing steel are mandatory and

must be carried out by the site manager within 30 days of delivery of the

material and in any case before it is put into use.

Acceptance checks are carried out on each shipment lot of a maximum of 30

tons from the same factory and consist of 3 pieces of the same diameter and

of 3 with different diameters. The following tests shall be carried out on these

samples:

o Traction

o Elongation and bending

o Adherence

o Chemical composition

If the identification mark and accompanying documentation do not show

that the material comes from the same establishment, checks are extended to

all batches from other plants.

The strength, elongation and bending values of each sample of the same

diameter must be comprised in the values listed in the standards. If the value

of the results of the tests carried out on one of the samples obtained from the

three lengths is lower than the prescribed value, an additional sample shall

be taken.

If the average of the previous two and the new one does not meet the

acceptance criteria, 10 additional samples must be taken from different

Page 186: Design, validation and commissioning processes for metal

178

products in the presence of the manufacturer, who may also be present

during the performing of the tests at the laboratory.

If the average of the 10 results is not greater than the characteristic value and

the individual values are not included between the minimum and maximum

value of the values indicated in the standard, the shipment lot must be

rejected, with notification to the Central Technical Service by the site

manager.

Sampling must be carried out by the site manager (or by a technician of his

choice) who will label the samples and draw up and sign a specific sampling

report.

For supplies (shaped or assembled elements) coming from the processing

centers, the site manager checks the requirements and, if adequate samples

to be subjected to laboratory tests are not supplied to the site, he can go to the

same plant, carry out the relative checks and order the collection of samples

(carried out by the technical manager of the processing center) to be sent to

the laboratory. In both cases:

The request for tests to the Laboratory, as per art. 59 of Presidential Decree

no. 380/2001, must be signed by the Works Manager and must contain all

useful information on the structures involved in the sampling.

The samples must be delivered to the testing laboratory by the site manager

or by a technician of his choice.

The test certificates must show the identification mark recorded by the

laboratory on the samples tested.

7.1.1.3 Bolts

The acceptance of the bolts on site must also be carried out by the site

manager. 3 samples are taken for every 1500 pieces. The number of samples,

Page 187: Design, validation and commissioning processes for metal

179

taken and tested within the same work, may not be less than three. For works

for which the use of a quantity of pieces not exceeding 100 is envisaged, the

number of samples to be taken is identified by the site manager. The tests are

the same as those carried out in chapter 6, regarding the operations of

acceptance of the bolts in the factory.

7.1.2 Concrete

The acceptance check of the concrete is made by taking a quantity of concrete

from the mix when it is poured in place.

A quantity is taken to allow the packaging of 2 samples that will be subjected

to compression resistance tests, providing with their average the

"Withdrawal Resistance" used for the associated type A and type B checks.

These samples must be collected in the presence of the site manager, who

will identify the samples by means of indelible initials and labels and will

draw up and sign the appropriate sampling report.

The request for tests to the laboratory must be signed by the site manager

and must contain precise information on the position in the facilities affected

by each sampling and must report the details of the "Record of Withdrawal",

the certification issued by the laboratory must refer to this Record.

In this case too, the samples must be delivered to the laboratory by the site

manager or by a technician of his choice.

The Site manager is obligated to carry out systematic checks during

construction to verify the conformity of the characteristics of the concrete

used with respect to that established by the project and experimentally

verified during the preliminary assessment: he must in any case prescribe

further samples compared to the minimum prescribed whenever changes in

the quality of the concrete should occur.

Page 188: Design, validation and commissioning processes for metal

180

These acceptance checks, performed on homogeneous mixtures at the

Laboratories referred to in art. 59 of Presidential Decree 380/2001, are

conducted on the basis of the quantity of homogeneous concrete concerned.

Type A control:

This control refers to a quantity of homogeneous concrete mixture of less

than 300 m3 used in structural works. Each control is represented by a

maximum sampling every 100 m3 and for each day of casting.

For constructions with less than 100 m3 of homogeneous mixture jet (as in the

case of the structures subject to the thesis), for which it is allowed to derogate

from the obligation of daily sampling, the number of samples can be reduced

to a minimum of 3.

The check is successful if the following inequalities are verified:

๐‘…1 โ‰ฅ ๐‘…๐‘๐‘˜ โˆ’ 3,5 (๐‘/๐‘š๐‘š2)

๐‘…๐‘š โ‰ฅ ๐‘…๐‘๐‘˜ + 3,5 (๐‘/๐‘š๐‘š2)

where:

R1 the minimum value of the withdrawals

Rm Average resistance of samples

Rck Design characteristic strength (or concrete strength class)

For this type of control, the circular explaining the standard specifies that, if

the number of concrete samples delivered to the laboratory is less than six

Page 189: Design, validation and commissioning processes for metal

181

per homogeneous mixture, the laboratory, having conducted the tests, issues

the required certification but must inform the workโ€™s director that the

number of samples taken is not sufficient to perform the type A control

provided for in the Ministerial Decree 17-01-2018.

Type B control:

This type of statistical acceptance check is mandatory for quantities of

homogeneous mixture greater than 1500 m3 used in structural works and is

followed with a frequency of one check every 1550 m3. For the structures

under investigation, this check is therefore not necessary.

The standard specifies that the work or part of the work that does not comply

with the acceptance checks cannot be accepted until the conformity has been

definitively removed by the manufacturer, who must check the

characteristics of the concrete put in place by using other means of

investigation as prescribed by the site manager and in accordance with what

is indicated in the control of the strengths of the concrete in place.

If the additional checks confirm the results obtained, a theoretical and/or

experimental safety check of the structure affected by the quantity of non-

conforming concrete must be performed on the basis of the reduced strength

of the concrete.

If this is not possible, or if the results of this investigation are not satisfactory,

the work can be de-qualified, a consolidation work can be executed or the

work can be demolished.

Acceptance checks are mandatory and the inspector is required to check their

validity, quality and quantity; if this is not the case, the inspector is required

to have tests performed that certify the characteristics of the concrete,

Page 190: Design, validation and commissioning processes for metal

182

following the same procedure that is applied when the limits set by the

"acceptance checks" are not respected.

In-situ resistance checks:

When the "acceptance tests" are not satisfactory or when the inspector deems

it appropriate, or when it is necessary to evaluate "a posteriori" the properties

of a concrete already in place and hardened, it is possible to carry out

resistance tests on the concrete through a series of both destructive and non-

destructive tests: these tests, however, cannot replace the acceptance tests.

First of all, by means of non-destructive tests such as SONREB (combined

sclerometer-ultrasound method), zones of structures with homogeneous

resistance are identified, delimited and then, by means of "core drilling",

cylindrical samples are taken in order to obtain a reliable estimate of the

resistance of a test area with at least 3 samples (core samples) with a diameter

between 75 and 150 mm (preferably 100 mm) from which cylindrical samples

with twice the diameter height are obtained.

Properly prepared (test surfaces ground with diamond discs and parallel to

each other and orthogonal to the directions), the specimens are subjected to

a compressive rupture test to determine the average value of the structural

cylindrical resistance in place, which must be at least 85% of the design

(average acceptable value, compared to the design strength and potential

resistance of samples taken in the casting phase and matured in the

laboratory under normalized conditions of temperature and humidity).

For concrete class Rck = 30 N/mm2 (C25/30)

Circular no. 617/2009 states:

Page 191: Design, validation and commissioning processes for metal

183

o Obtained the average value of the cylindrical resistance of the

core samples fcm

o Considering that:

๐‘“๐‘๐‘š = ๐‘“๐‘๐‘˜ + 8 (๐‘/๐‘š๐‘š2)

where:

๐‘“๐‘๐‘˜ = 0,83. ๐‘…๐‘๐‘˜ per core sample having h = 2D

Must result an average value of the cylindrical resistance in place

๐‘“๐‘œ๐‘๐‘’๐‘Ÿ๐‘Ž.๐‘š โ‰ฅ 0,85. ๐‘“๐‘๐‘š (๐‘/๐‘š๐‘š2)

๐‘“๐‘œ๐‘๐‘’๐‘Ÿ๐‘Ž.๐‘š โ‰ฅ 0,85. (0,83๐‘…๐‘๐‘˜ + 8) (๐‘/๐‘š๐‘š2)

๐‘“๐‘œ๐‘๐‘’๐‘Ÿ๐‘Ž.๐‘š โ‰ฅ 27,96 (๐‘/๐‘š๐‘š2)

In the case of cylindrical core samples with a height equal to the

diameter fck = Rck

7.2 Construction of the plinth on site

Once the materials have been accepted on site, the structure is put into

operation. The plinth is made and then the steel structure is mounted on it.

The plinth is a continuous surface foundation and is used when the

structures in elevation are of the frame type. They are placed with the center

of gravity on the vertical resultant of the forces transmitted to allow the

uniform distribution of the loads of the structure to the laying surface. The

Page 192: Design, validation and commissioning processes for metal

184

function of the plinth is to distribute the load over a larger footprint to

prevent the columns from sinking into the ground.

From a geometric point of view, the plinths can be divided into:

High

Short

Deformable

Rigid

From a mechanical point of view, depending on the choice, the behavior of

the plinth changes, both its interaction with the ground below and therefore

the distribution of tensions.

In general, the various categories of plinths are divided into:

๐‘ โ‰ฅ 4โ„Ž great thinness

โ„Ž

2โ‰ค ๐‘ โ‰ค 4โ„Ž medium thinness

๐‘ โ‰คโ„Ž

2 small thinness

Plinths, but more generally foundations, must not lay directly on the ground

because the reinforcements could oxidize. A layer of concrete with a low

cement content, called "lean concrete", is realized, with a thickness varying

from 5 to 10 cm, whose task is to provide the leveled base of support to the

foundation structures and to avoid the direct contact of the reinforcement

steel with the ground, as well as the permeation of rising water.

The process for the realization of the plinth begins with the excavation in the

grounding the positioning of the formwork, where the reinforcing irons

Page 193: Design, validation and commissioning processes for metal

185

(including coach screws) will be positioned first and then followed by the

casting of concrete.

Before casting, the formwork must be cleaned inside and preferably covered

with a layer of release agent to allow it to detach from the concrete once it

has hardened, and the formwork walls must be perfectly sealed.

It is also important to ensure that the walls of the formwork do not open

under the pressure of the concrete, which must maintain its position and

shape unchanged.

The design of the reinforcement cage and the positioning of the

reinforcements must be deduced from the design documents supplied by the

designer and it is important that during the assembly phase of the

reinforcements and formwork's the spacers are prepared. Spacers are special

elements that separate the reinforcements from the walls of the formworks,

keeping them in position during the casting and ensuring the correct

execution of the iron cover. It is also advisable to make sure that the steel rods

are closely linked to each other to prevent movement during the casting.

Concrete can be transferred into the formwork directly by means of slides or

pipes, or with the aid of a motor pump that allows obstacles or differences in

level to be overcome. To make a good casting, the formwork must be filled

slowly, thus avoiding the formation of air bubbles in the material.

During the casting process, the concrete introduced into the formwork

always contains a quantity of embedded air, which must be absolutely

eliminated in order to obtain a durable and high-quality mix. This is achieved

by compacting or constipation, which is normally carried out by mechanical

means.

Page 194: Design, validation and commissioning processes for metal

186

This can be done by means of a vibrator, i.e. by immersing a tapered element

called a needle in the concrete, which produces a vibration of the material,

making it easier for air bubbles to escape, or by means of a vibration

transmitted to the concrete by the formworks.

Figure 101: Excavation scheme forformworks

Formworks can be of different types and consist of different materials, such

as steel, plastic, wood and resins and new materials.

The profiles of the columns, in the lower part of support to the plinth, are

welded to a horizontal perforated plate that acts as a load distribution plate

that can be stiffened by lateral fins as shown in the image below.

Page 195: Design, validation and commissioning processes for metal

187

Figure 102: Plinth-column coupling detail

The column is fixed with a series of coach screws that are drowned in the

concrete. The coach screws are made up of bars bent into hooks in the lower

part and threaded in the upper part emerging from the foundation and are

positioned with extreme precision before the casting by means of a

positioning bar.

Figure 103: Executive project drawing for plinth-column coupling

Page 196: Design, validation and commissioning processes for metal

188

At the end, the column is positioned by bolts and washers that allow it to be

plumbed leaving the column raised by a height of about 6-8 cm from the

plinth. The structural continuity is ensured through the realization of an

integrative jet with anti-shrinkage expansive mortar.

Figure 104: Example of the introduction of anti-shrinkage expansive mortar

7.3 Assembling of the structure on-site:

Once the construction project has been submitted to the plant in charge of the

production of the structures, it will then be the task of that plant or processing

center to provide instructions for the assembly of the structures on site.

The document in which the indications are given about the steps to be

followed for the assembly of the structure, as well as the order in which they

have to be performed, is called Assembly Plan. In conjunction with the

assembly plan, a safety plan must also be drawn up with measures to prevent

accidents during assembly.

Page 197: Design, validation and commissioning processes for metal

189

The assembly is carried out by the factory itself or can be hired companies

specializing in the assembly of metal structural works.

7.3.1 Analysis and assessment of possible risks

During the assembly phase of the structure, it is necessary to take preventive

measures against the risks arising from the assembly operation itself.

The assembly of metal structures for railway signaling is often conducted at

night at time intervals that vary according to line and traffic regulations, as

the power supply of the line section concerned must be cut off. Possible risks

include:

Falls from height

Blows, impacts, compressions

Slips, level falls

Heat, flames (in case of on-site welding processes)

Electricity

Noise

Shearing, crushing

Manual handling of loads

The personal protective equipment that is made available is generally:

Helmet

Safety footwear with anti-crushing toecap

Gloves

Noise protection care (earplugs or ear muffs)

Fall protection equipment

Page 198: Design, validation and commissioning processes for metal

190

Eyewear

Respiratory protection masks

Protective clothing

In consideration of these risks, it is necessary to draw up a safety and accident

prevention plan.

7.3.2 Instructions for workers

The assembly work must be carried out by physically trained workers under

the guidance of an experienced technician (assembly assistant).

During the assembly work, the personnel in charge must be divided into

clearly defined tasks for which they must have received information and

training appropriate to the functions performed.

As a general rule, the assembly work involves the following activities, which

must be conducted by a sufficient number of assigned workers:

For the structures under examination, it is preferable, where

possible, to reach the point of installation by specialized

trucks in terms of costs and logistical operations, otherwise

railway wagons are used which are additionally equipped

on board with equipment for handling loads.

Pre-assembly at the foot of the work of the elements and

security systems;

Lifting of single or pre-assembled elements by means of

lifting equipment;

Page 199: Design, validation and commissioning processes for metal

191

Preparation of the accident prevention arrangements on the

ground and harnessing of the pieces;

Reception, positioning and stabilization of the elements on

site;

Installation of safety guards (parapets, nets, etc.).

The following rules must be observed during assembly:

o The installation operations must be directed by a designated

person (team leader);

o For lifting, special equipment must be used with tie rods, sling

bars and tools suitable for the weight of the elements;

o Before each operation, it must be checked that the lifting

equipment is supplied with the appropriate equipment for the

type of element to be lifted;

o During all manoeuvres, the crane operator must act with the

utmost care, avoiding sudden movements or accelerations.

Each manoeuvre must be preceded by an acoustic signal;

o Elements that show anomalies in the systems for attaching to

the lifting equipment or for removing the guards on site must

be discarded;

o The anchoring devices must be installed on the individual

elements during construction or pre-assembly on the ground of

the carpentry;

o The safety devices and their accessories must be stored,

transported and handled with care to avoid their deterioration;

o Methods that reduce the risk of falling to a minimum must be

used during installation;

Page 200: Design, validation and commissioning processes for metal

192

o Anchorage systems and personal fall protection equipment for

the personnel in charge of their installation must be provided

and set up during construction or pre-assembly on the ground

of the carpentry;

7.3.3 Emergency procedures

The documentation to be made available includes instructions on emergency

procedures indicating the weather conditions under which, in relation to the

activities carried out, the work must be stopped.

The maximum wind speed allowed in order not to interrupt the assembly

work must be determined on site taking into account the surface area and

weight of the elements as well as the particular type of lifting equipment

used.

As a rule, lifting equipment must not be used if the wind speed exceeds 60

km/h.

When atmospheric discharges due to storms in progress that may affect the

work area are foreseen, operations must be suspended immediately.

Any instability during the assembly phases must be promptly assessed by

the person in charge, who must arrange for reinforcement of the temporary

support instruments or, if necessary, the immediate evacuation of the danger

zone.

7.3.4 Mounting of structures

The structures are assembled with the help of equipment suitable for lifting

the structural elements. The company in charge of assembly must provide a

Page 201: Design, validation and commissioning processes for metal

193

detailed list of the main equipment, such as fixed cranes, mobile cranes or

other machinery providing the routes and areas required for these machines.

It is the responsibility of the site manager or the person responsible to

provide information about the situation of the terrain on site and any other

risks of which the company in charge of assembly must be informed in order

to take the right precautions and make the appropriate logistical decisions.

Before starting the lifting operations, the operators must carry out the

following checks:

Check the lifting axes of the foundation plinth on which the

structure is to be mounted;

Check that the foundation bolts have been correctly

assembled, with regard to positioning, number, bolt circle,

bolt diameter and protrusion from the foundation, length of

threads and good flow of the washers and locking nuts;

Provide for good lubrication of the threads of the bolts and

nuts;

Check that the elevation measured on the anchor plate is

correct;

Check that the parts of the lifting equipment are working

properly.

When installing the various pieces and/or elements of the metal structures, it

is necessary to pay attention to the verticality of the column(s), to the

elevation of the laying surface and to the position in the plan so as to avoid

any demolition in the event of unacceptable installation errors.

For these structures, it is not possible to define any a priori procedure

regarding the assembly methods, as the sizes of the elements are very

Page 202: Design, validation and commissioning processes for metal

194

variable and therefore also the different solutions for their transport to the

building site.

Implementing rules for bolted unions

It is advisable that the parts to be bolted on site are marked in such a way as

to be able to reproduce in the final assembly the same positions that they had

in the factory when the holes were reamed.

During the assembly phase, it is important to be careful not to create greater

eccentricities than the bolt-hole play. Usually the use of steel dowel pins is

used to put the parts in the right position. The steel pins are used to create

very precise unions and couplings, they are cylindrical or conical elements

that, placed in the appropriate holes, make torsionally and axially joined two

different pieces.

Figure 105: Example of steel dowel pins

Bolts can be tightened with key bolts until the plates between the head and

the nut are in contact. The nut is then rotated between 90ยฐ and 120ยฐ with

tolerances of 60ยฐ more.

For a correct operation, it is important that the contact surfaces on assembly

are clean, i.e. free of oil, paint, rolling scales or grease stains. As a rule,

Page 203: Design, validation and commissioning processes for metal

195

cleaning is carried out by sandblasting; simple brushing of the contact

surfaces is permitted for joints mounted on site.

For the tightening of the bolts, torque wrenches are used by hand, with or

without a torque limiting mechanism, or pneumatic wrenches with a torque

limiting mechanism; however, all of them must be such as to guarantee an

accuracy of no less than ยฑ 5%.

Figure 106: Example of torque wrench

When tightening the bolts, it is recommended to proceed as follows:

Tighten the bolts, with a torque equal to about 60% of the

prescribed torque, starting from the innermost bolts of the

joint and proceeding to the outermost ones;

Repeat the operation, as described above, tightening the

bolts completely according to the specifications on the

constructive project.

To check the efficiency of the tightened joints, the torque applied can be

checked in one of the following ways:

Page 204: Design, validation and commissioning processes for metal

196

The torque required to turn the nut further by 10ยฐ is measured

with a torque wrench;

After marking the nut and bolt to identify their relative

position, the nut must first be loosened with a rotation of at

least 60ยฐ and then tightened again, checking whether the

application of the prescribed torque returns the nut to its

original position.

If even one bolt in a joint does not meet the tightening requirements, all other

bolts must also be checked.

Page 205: Design, validation and commissioning processes for metal

197

CHAPTER 8: COMMISSIONING OF THE

STRUCTURE AT THE BUILDING SITE

As with the procedures for the acceptance of structures on site, there are no

European standards for commissioning. Therefore, for the testing of the

structures it will be necessary to refer to the national standards in which the

structure will be built. Below is reported the Italian procedure regarding the

commissioning procedure.

The technical standards for Italian constructions define testing as the

procedure aimed at assessing and evaluating the performance of structural

works and components. In the event of a positive outcome, the test procedure

ends with the issue of the Test Certificate.

The static test must be carried out during the work in progress and these

structures may not be put into operation before that. The static tests of all

civil engineering works include the following requirements:

Checking of the prescribed provisions for works carried out with

materials regulated by Presidential Decree no. 380 of 6 June 2001, laws

no. 1086/71 and no. 64/74 with different materials;

Inspection of the work during the construction phases of the structural

elements and of the work as a whole, in particular for these structures

is important to verify:

o The completeness of the structure (if all the constructive

elements figuring on the executive project have been assembled

and correctly installed on the load-bearing structure)

o Verticality of the columns (for example through the plumb-bob

technique);

Page 206: Design, validation and commissioning processes for metal

198

o State of the welded joints (visual inspection)

o Checks by means of a wrench torque that the tightening torque

of the bolts corresponds to that indicated in the construction

plan.

o Verification of compliance with the safety distances of the

assembled structure from the elements under voltage

according to EN 501101.

It is the task of the tester to check that the design requirements have

been implemented and that the experimental checks have been carried

out.

Examination of material testing certificates, divided into:

o Verification of the number of samples taken and their

conformity with the prescriptions in chapter 11 of DM 17-

01-2018 (described in chapter 6 of this thesis regarding

factory acceptance and in chapter 7 regarding on-site

acceptance);

o Check that the results of these tests have been successful in

accordance with the standards.

Examination of the certificates of inspections in the production plants

and during the production cycle;

Checking the reports and results of any load tests carried out by the

site manager.

The tester also has the task of:

Examining the design of the structure, the general layout, the

structural and geotechnical design, the calculation schemes adopted

and the actions considered;

Page 207: Design, validation and commissioning processes for metal

199

Examining the investigations carried out in the design and

construction phases.

The tester may also require:

Studies, investigations, experiments and research useful to convince

himself of the safety, durability and testability of the work as:

o Load tests

o Testing of materials also by non-destructive methods

o Programmed monitoring of significant quantities

describing the behavior of the work, possibly even after

it has been tested.

In general, the structural elements, once installed, are no longer able for

testing neither controllable and therefore the static test is a test being

performed during the construction.

8.1 Load tests

As mentioned above, load tests are not compulsory, but can be requested by

the tester and it is always the latter who must define the program of such

tests, indicating the loading procedures and expected performance which

must in any case also be submitted to the attention of the manufacturer and

the designer as well as to the site manager who is also responsible for their

material implementation.

Load tests are tests designed to verify the behavior of structures under

operational actions in order to induce maximum operational stresses for rare

Page 208: Design, validation and commissioning processes for metal

200

characteristic combinations. The test results are judged by the tester and must

be assessed on the basis of the following factors:

The increase in deformation is approximately proportional to the

loads;

During the test, no fractures, cracks, deformations or disruptions

occur that compromise the safety or the preservation of the work;

The residual deformation after the first application of the maximum

load does not exceed a portion of the total deformation commensurate

with the foreseeable initial inelastic settlements of the structure. If, on

the other hand, these limits are exceeded, the subsequent load tests

must indicate that the structure tends towards elastic behavior;

The elastic deflection shall not be greater than the calculated

deflection.

If the tester requires it, dynamic tests and breaking tests on structural

elements may be added.

As can be seen from the standards, there is no distinction between the

different materials that perform a certain load bearing function and therefore

the test is extended to all the load bearing structures (columns and beams)

whatever the material used for this purpose.

Page 209: Design, validation and commissioning processes for metal

201

CHAPTER 9: CONCLUSIONS

With this thesis a process has been defined for the realization of these

structures, starting from the input documents up to the turnkey delivery of

the structure with a multidisciplinary approach ranging in different fields of

civil engineering such as geotechnics and structural design. Every single

phase of the process has been faced, providing on each occasion the

motivations behind each choice and consideration.

The structures that are the subject of the thesis, in addition to having to meet

the criteria of technical design and construction, must also comply with the

indications and restrictions imposed by the regulations of the railway

system. It was therefore also a work of integration at the regulatory level.

Particular attention has been paid to the different inputs to be provided to

the different stakeholders involved in the construction of these structures,

which may not be as familiar with the railway sector or with the types of

structures described in this thesis.

For example, this was the case in Morocco with regard to the factories in

charge of the production of these structures, which faced this type of

production for the first time. It was therefore essential to pay particular

attention to the inputs and indications provided so as not to be faced with

delays and cost increases.

Page 210: Design, validation and commissioning processes for metal

202

APPENDIX A: Examples of cross sections located in

the Casablanca triangle

This appendix contains a brief analysis of the cross-sections of a section of

the Moroccan line, with some considerations regarding the installation of the

structures.

In this specific case, there was no information about the electric traction

elements in the drawings therefore no information about the contact wire

height. Consequently, at the design stage, the height of the columns was set

at 10m as a precautionary measure.

The image below shows part of the plan view of the line section in question,

while the other figure is a close up.

Page 211: Design, validation and commissioning processes for metal

203

From section number 9 to section number 36 it can be noticed that there are

3 tracks alongside each other with non-constant interaxis, and with the

presence of a side wall.

The side wall is located at a minimum distance from the nearest rail of 1.46

m (section nยฐ35) and at a maximum distance of 4.83 m (section nยฐ20).

Cross section nยฐ20

Page 212: Design, validation and commissioning processes for metal

204

Cross section nยฐ 35

In section 35, the side wall would not allow the installation of any structure

between the track and the wall itself, as it is positioned too close to the inner

edge of the nearest rail.

The height of the wall in relation to the rolling plane, however, being 1.96 m,

would allow the position of structures in elevation positioned beyond that

wall. Obviously, inspections and surveys on site would be necessary to

understand the real feasibility of such a hypothesis, as it is not possible to

define it just from the cross sections.

In section 20, however, depending on the type of structure that needs to be

installed, there may be space for structures.

As for the interaxis, still considering the same line section, the distance

between the two left tracks varies between 3.50 m and 3.70 m from section 9

to section 22, while it remains constant by 3.69 m from section 23 to section

36.

Section number 36 has the maximum distance between sections 9-36 between

the rightmost tracks. This distance is 5.72m, which subtracts one track gauge

(half of one track and half of the other) and places the inner rails at a distance

of 4.29m.

Page 213: Design, validation and commissioning processes for metal

205

At this distance, it would be possible to verify the feasibility of installing the

structures, considering that the minimum distance must be respected for

both tracks.

As can be seen in cross section 36, in this specific case a possible solution

should also be studied to divert or incorporate the project well to any

foundations of the structures.

Cross section nยฐ 36

From cross section number 37 to section number 43, in addition to the wall,

already present in the previous sections, the project also provides for a

retaining wall with an L-section of 3.70 m high and 3.00 m wide, which

should not create problems at the design stage, as a possible solution would

still be to place the foundation plinth beyond the retaining wall, always

respecting the minimum safety distances. Again, no assumptions can be

made about the type of structures.

It can therefore be said that cross sections are an important tool during the

preliminary stages of the project, but they are not sufficient to allow valid

design assumptions to be made without integration with the staking

procedures.

Page 214: Design, validation and commissioning processes for metal

206

Crosse section nยฐ 43

Page 215: Design, validation and commissioning processes for metal

207

References

Cherkaoui, T.-E., and Asebriy, L. (2003). Le risque sismique dans le Nord du Maroc. Traveaux Inst. Sci. Traveaux de lโ€™Institut Scientifique, sรฉrie gรฉogr. , 225โ€“232. Babak, P. and al. (2017). Seismic wave amplification by topographic features: A parametric study. Soil Dynamics and Earthquake Engineering., 503-527 Meletti, C. and Valensise, G. (2004). Zonazione sismologica ZS9 โ€“ App.2 al Rapporto Conclusivo. Istituto Nazionale Di Geofisica E Vulcanologia.( ordinanza PCM 20-03.03 n 3274) Criteri generali per l'individuazione delle zone sismiche e per la formazione e l'aggiornamento degli elenchi delle medesime zone. Gazzetta Ufficiale n. 108 del11 maggio 2006 (O.P.C.M. 28 aprile 2006 n. 3519) CENELEC, en 50124 (2017). Railway applications โ€“ Insulation coordination CENELEC, en 50126 (2017) Railway applications โ€“ The Specification and Demonstration of Reliability, Availability, Maintainability and Safety (RAMS) CNR - AEI - CEI EN 50128 (2002). Railway applications Communications, signaling and processing systems - Software for railway control and protection systems CENELEC en 50126 (2003). Railway applications โ€“ Communication, signaling and processing systems โ€“ Safety related electronic systems for signaling CEI en 50119 (2010) Railway applications - Fixed installations - Electric traction overhead contact lines. Martino, A (2017). Storia della Normativa e della tecnica ferroviaria e Segnali ferroviari italiani, www.rsifn.it. Valfrรจ, V (2011). Il segnalamento di manovra nella impiantistica FS Volume I โ€“ CIFI Guida P.L. and Milizia E., (2016) Impianti Ferroviari Volume I, Lucio MAYER โ€“ CIFI, Ristampa SNCF (2013). Sรฉcuritรฉ De Lโ€™exploiatation Sur Le Chemin Ferrรฉ National Franรงais. Report annuel Baker, C. and al, (2019). Transient aerodynamic pressures and forces on trackside and overhead structures due to passing trains. Part 2 Standards applications. Birmingham Centre for Railway Research and Education, University of Birmingham Reglement De Construction Parasismique (R.P.S (2002). Ministรจre de lโ€™Amรฉnagement du Territoire, de lโ€™Urbanisme, de lโ€™Habitat et de lโ€™Environnement. Riggio, A,. and Carlucci R,. Topografia Di Base Fondamentali della geomatica per la misura e rappresentazione del territorio