Page 1: Design Kickoff Meeting Becky Houdek, MCWD 6-27-12

Minnehaha Creek (Reach 14) Streambank Improvement Project

Design Kickoff Meeting

Becky Houdek, MCWD6-27-12

Page 2: Design Kickoff Meeting Becky Houdek, MCWD 6-27-12

OutlineBackground

Design concepts

Expectations

Process/Schedule

What we need from you

Questions

Page 3: Design Kickoff Meeting Becky Houdek, MCWD 6-27-12

BackgroundProject identified in District

Plan

Project goals:

Improve riparian vegetation Stabilizes banks (deep roots) Filters runoff from land and

moderates flow Provides shading and shelter Deters geese Aesthetic value

Improve in-stream habitat and function

Education/demonstration

Page 4: Design Kickoff Meeting Becky Houdek, MCWD 6-27-12

Turf Grass vs. Native Plant Roots

Page 5: Design Kickoff Meeting Becky Houdek, MCWD 6-27-12

BackgroundFeasibility study completed

last summer

Gauged homeowner interestVoluntary projectNeighborhood meeting,

survey, site visits29 have expressed interest

Board ordered last fall Funding design, construction,

3 yrs maintenance

Page 6: Design Kickoff Meeting Becky Houdek, MCWD 6-27-12

Design ConceptsBalance homeowner interests/preferences with natural

resource benefitsAesthetics, plant height, existing structures, etc.

Vegetated streambank with 10-20 ft of native plantings that transitions to turf (minimum of 10 ft)Primarily grasses and flowers, shrubs optionalLittle to no rock needed

In-stream habitat improvements

Page 7: Design Kickoff Meeting Becky Houdek, MCWD 6-27-12

ExpectationsDistrict will fund design, construction, and first 3 yrs of

maintenance, then homeowners take over

Plantings will take a few years to be fully established - will incorporate some plant plugs so you see some growth and color right away

District rules require a declaration for any streambank projectsMuch of the land along creek is owned by City – will need 3-party

agreement

Not all properties may be suitable for this project

Page 8: Design Kickoff Meeting Becky Houdek, MCWD 6-27-12

Process/ScheduleDetermine who is on board - Letter of intent

Develop designs/planting plans:Individual site visits – mid-JulyPreliminary designs – Distributed late July Homeowner review and feedback (2-3 weeks) – mid-August Finalize designs – August-September

Execute declarations/maintenance agreements – September

Construction:In-stream/bank work – January - mid-FebruaryPlanting – Spring 2013

Page 9: Design Kickoff Meeting Becky Houdek, MCWD 6-27-12

What We Need From YouEmails and phone numbers

Flexibility and responsiveness

Coordinate on-site meetings Sign up for a time

For site visit: Complete plant worksheet Sign letter of intent

Declaration/maintenance agreement (once designs are developed)

Page 10: Design Kickoff Meeting Becky Houdek, MCWD 6-27-12

Questions?Contact information:

Becky [email protected]

Project webpage:http://www.minnehahacreek.org/projects (scroll down to

Reach 14)