denver public schools invitation to bid 14-mc-2308...

79
THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2308 as follows: The Drawings, Specifications and Contract Documents on the project are modified, corrected, supplemented and/or superseded as hereinafter described. The following additions, deletions, changes and information shall become a part of and modify all work shown or described in the Drawings and Project Manual dated April 11, 2014. All bidders shall make necessary adjustments in their bid on account of this addendum. It will be construed that each bidder's proposal is submitted with full knowledge of all modifications and supplemental data specified herewith. Owner: Contractor will be able to use the school’s power for temporary power. Should there be any special circumstances in which the building power will not be in service due to construction the contractor will be responsible. Architecture Drawing Sheet A1.01: Add: The existing temporary wall between Auto Shop 113 and Gymnasium 115 shall be removed to accommodate new construction. Civil Drawing Sheet C4: Omit: Omit Drawing Sheet C4 in its entirety. Replace: Replace with Drawing Sheet C4 (attached). Mechanical/Electrical Changes and modifications as per attached BCER Enginering, Inc. Addendum No. 02 documents. See below for documents: BCER Mech drawings BCER Language BCER Communication Specs BCER elect drawing Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 14-MC-2308 ADDENDUM NUMBER TWO April 24, 2014

Upload: lykien

Post on 05-Jul-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

THIS ADDENDUM MUST BE ACKNOWLEDGED.

THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2308 as follows:

The Drawings, Specifications and Contract Documents on the project are modified, corrected, supplemented and/or superseded as hereinafter described.

The following additions, deletions, changes and information shall become a part of and

modify all work shown or described in the Drawings and Project Manual dated April 11,

2014.

All bidders shall make necessary adjustments in their bid on account of this addendum. It will be construed that each bidder's proposal is submitted with full knowledge of all modifications and supplemental data specified herewith.

Owner:

Contractor will be able to use the school’s power for temporary power. Should there be any special circumstances in which the building power will not be in service due to construction the contractor will be responsible. Architecture

Drawing Sheet A1.01: Add: The existing temporary wall between Auto Shop 113 and Gymnasium 115 shall be removed to accommodate new construction. Civil

Drawing Sheet C4: Omit: Omit Drawing Sheet C4 in its entirety.

Replace: Replace with Drawing Sheet C4 (attached). Mechanical/Electrical Changes and modifications as per attached BCER Enginering, Inc. Addendum No. 02 documents. See below for documents: BCER – Mech drawings BCER – Language BCER – Communication Specs BCER – elect drawing

Denver Public Schools Purchasing Department

1617 S. Acoma St. Denver, Colorado 80223

INVITATION TO BID 14-MC-2308

ADDENDUM NUMBER TWO April 24, 2014

Page 2: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

If your proposal has been submitted and you wish to amend it, please modify your proposal on company letterhead. The amended proposal must be received prior to or included at the time and date set for the proposal opening. Each modification submitted to the District's Purchasing Office located at 1617 S. Acoma St. Denver, CO 80223. It must have Vendor’s name and return address and the applicable RFP number and title of the RFP clearly marked on the face of the envelope. If more than one modification is submitted, the modification bearing the latest date of receipt by the District's Strategic Sourcing Office will be considered the valid modification. *****This addendum must be acknowledged, whether or not you amend your proposal.*****

This Addendum must be included in your submittal or proposal, providing you do not need to amend your proposal.

PRINT OR TYPE YOUR INFORMATION

Name of Company: ____________________________________________ Fax: _____________

Address: ________________________ City/State: ________________ Zip: ______________

Contact Person: ___________________ Title: _____________________ Phone: ___________

Authorized Representative’s Signature: ____________________________ Phone: ___________

Printed Name: ____________________ Title: _____________________ Date: _____________

Approved by: ______________ Date: _____________

Reviewed by: ______________ Date: _____________

14-MC-2308 Addendum # 2

Page 3: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

BID FORM

BASE BID TO: SCHOOL DISTRICT NO 1 IN THE

CITY AND COUNTY OF DENVER AND STATE OF COLORADO

PROJECT: PUSH Academy Phase 2

LOCATION: PUSH Academy – CAE Building 4501 Airport Way Denver, CO 80239

14-MC-2308

School Bid Amount

Push Academy Base Bid $______________________________

Alternate 1 – Add new exterior concrete walk pavement. Include the complete scope of new walk installation including the removal of existing turf landscape and relocation of existing site irrigation heads: RE: Drawing Sheet A1.00 $

Alternate 2 - Provide structured cabling at Classroom 105 as per Drawing Sheet E200 $

Name of Company: ____________________________________________ Contact Person: ___________________ Title: _____________________ Date:_____________

Authorized Representative’s Signature: ________________________________

Page 4: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME
Page 5: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

Addendum No. 2

April 23, 2014

Denver Public Schools Push Academy Phase 2

PP 2308

BCER Project No 39913015.01

This Addendum forms a part of the Contract Documents and modifies the original Bidding

Documents dated April 11, 2014, as noted below. Acknowledge receipt of this Addendum in the

space provided on the Bid Form. Failure to do so may subject Bidder to disqualification.

CHANGES TO DRAWINGS

1. Delete sheet M201 and replace in its entirety with the attached sheet M201.

2. Delete sheet E002 and replace in its entirety with the attached sheet E002.

3. Delete sheet E200 and replace in its entirety with the attached sheet E200.

CHANGES TO SPECIFICATIONS

1. ADD the following to specification section 230900 Controls:

a. Paragraph 1.3.B: Tridum/KMC as installed by Long and Associates is acceptable.

2. ADD the following specification sections:

a. 260526 – Grounding and Bonding

b. 260533 – Surface Raceways

c. 262816 – Enclosed Switches

d. 270100 – Operation and Maintenance of Communication Systems

e. 270500 - Common Work Results for Communications

f. 270513 – Communication Services

g. 270526 - Grounding and Bonding

h. 270528 - Pathways for Communication Systems

i. 270529 – Hangers and Supports for Communication Systems

j. 270553 – Conduits and Backboxes for Communication systems

k. 270539 – Surface Raceways for Communications Systems

l. 270553 – Identifications for Communications Systems

m. 270800 – Commissioning Communications

n. 271119 – Communications Patch Panel

o. 271500 – Communications Horizontal Cabling

p. 271619 – Communications Patch Cords, Stations Cords, and Cross Connect Wire

q. 283100 – Fire Detection and Alarm

ATTACHMENTS

M201, E002, E200

Specification sections 260526, 260533, 262816, 270100, 270500, 270513, 270526, 270528, 270529,

270533, 270539, 270553, 270800, 271119, 271500, 271619, 283100.

END OF ADDENDUM

Page 6: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

OPERATION AND MAINTENANCE OF COMMUNICATIONS SYSTEMS

DPS PUSH Academy Remodel – Phase 2

270100 - 1

SECTION 270100 - OPERATION AND MAINTENANCE OF COMMUNICATIONS SYSTEMS

PART 1 - GENERAL

1.1 MAINTENANCE OF PATCH FIELDS

A. Any persons with Contractor or Denver Public Schools adding or moving copper or fiber optic

patch (equipment) cords shall do so in a neat, workmanlike fashion in keeping with the original

system concept and according to all industry best practices as outlined in cabling standards and

applicable BICSI publications referenced previously in this document.

B. Persons performing such moves, adds or changes (MACs) shall further adhere to the following:

1. Contactor shall use existing cabling management pathways and take care to place cable

like with like, maintaining original segregation strategies for separating fiber and copper

cables as well as any separation necessary between different types of copper cables.

2. Cables shall be dressed neatly within patch management pathways with care taken to

maintain minimum bend radius of not less than 1 times the cord outer diameter for copper

and not less than a 1" bend radius for fiber jumpers as per ANSI/TIA 568-C.0.

3. All patch cords used shall be of same copper Category or fiber OM/OS designation or

higher than the media used in the permanent links.

4. Patching in all cases shall be done using factory terminated cords manufactured for that

purpose. Hand terminated patch cords will not be accepted.

5. All patch cords or jumpers must be completely contained within supplied cable

management paths. Cables draped across the front of cabinets or racks will not be

accepted.

6. Any persons moving fiber optic patch cords for any reason will clean the connector with

lint-free wipes and 99% or higher isopropyl alcohol before replacing the connector in a

port.

7. Any persons with Denver Public Schools or Installing Contractors performing moves,

adds or changes within patch field will label additions to the system according to the

labeling guidelines outlined in this document.

8. Any persons with Denver Public Schools or Installing Contractors performing moves,

adds or changes within patch field will record the move according to documentation

guidelines outlined in this document.

PART 2 - PRODUCTS – NOT USED

PART 3 - EXECUTION – NOT USED

END OF SECTION 271000

Page 7: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

OPERATION AND MAINTENANCE OF COMMUNICATIONS SYSTEMS

DPS PUSH Academy Remodel – Phase 2

270100 - 2

Page 8: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 270500 – COMMON WORK RESULTS FOR COMMUNICATIONS

PART 1 - GENERAL

1.1 The purpose of this document is to provide additional instructions for the planning, design and installation of an end-to-end Category 6 cabling system and associated fiber optic backbone cabling. This document will encompass the structured wiring, the system components, proper installation practices, support and management structures, cable testing, and most importantly the documentation. For specific installation, testing, grounding, bonding, and documentation guidelines please refer to the specific sections in this document.

1.2 A structured wiring solution is only as robust as its weakest component, therefore all wires and connections should be Category 6 rated on a component level as defined in the above referenced ANSI/TIA-568-C.2 standard or its more recent revision at the time of installation. The links shall further pass a permanent link performance test as described in this document. Multi-mode fiber links within buildings shall be of OM3 armored designation or higher as indicated by the project documents.

1.3 When planning and installing a structured cabling system for DPS the Contractor must pay particular attention to ensure all components used are of the same Category or optical OM level of performance. Splicing in copper horizontal links is expressly forbidden unless part of a planned zone cabling strategy.

1.4 The DPS network infrastructure design shall in all cases be a star topology unless indicated otherwise by specific project documentation. By pre-wiring all possible locations in a new or existing building in a star topology, all administrative moves, changes and additions will be made at patch field contained in the Telecommunications Rooms.

PART 2 - PRODUCTS

2.1 REGULATORY REFERENCES

A. These Denver Public Schools (DPS) Department of Technology Services (DoTS) cabling standards are based on the guidelines published by the Telecommunications Industries Association (TIA) as well as the more detailed requirements of the Building Industry Consultative Services International (BICSI).

B. Contractor is responsible for knowledge and application of current versions of all applicable Standards and Codes. In cases where listed Standards and Codes have been updated, Contractor shall adhere to the most recent revisions, including all relevant changes or addenda at the time of installation. A list of Regulatory References current as of the time of this writing is shown below:

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 1

Page 9: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

ANSI/TIA: ANSI/TIA-568-C.0 (September 2010) Generic Telecommunications Cabling for Customer Premises

TIA-568-C.0-1 (September 2010) Generic Telecommunications Cabling for Customer Premises-Addendum 1, Updated Reference for Balanced Twisted-Pair Cabling

ANSI/TIA-568-C.1 (February 2009) Commercial Building Telecommunications Cabling Standards

TIA-568-C.1-2 (November 2011) Commercial Building Telecommunications Cabling Standard, Addendum 2 General Updates

ANSI/TIA-568-C.2 (August 2009) Balance Twisted Pair Communications and Components Standards

ANSI/TIA-568-C.3 (June 2008) Optical Fiber Cabling Components Standard

ANSI/TIA-568-C.3-1 (December 2011) Optical Fiber Cabling Component Standard- Addendum 1, Addition of OM4 Cabled Optical Fiber and array connectors

ANSI/TIA-568-C.4 (July 2011) Broadband Coaxial Cabling Components Standard

ANSI/TIA-942-A (August 2012) Telecommunications Infrastructure Standard for Data Centers

TIA-569-B (October 2004) Commercial Building Standard for Telecommunications Pathways and Spaces

TIA-569-B-1 (May 2009) Temperature and Humidity Requirements for Telecommunications Spaces

ANSI/TIA-606-B (June 2012) Administration Standard for Telecommunications Infrastructure

TIA-607-B (September 2011) Generic Telecommunications Grounding (Earthing) and Bonding for Customer Premises

TIA-758-A (August 2004) Customer-Owned Outside Plant Telecommunication Infrastructure Standard

TIA-1152 (September 2009) Requirements for Field Test Instruments and Measurements for Balanced Twisted-Pair Cabling

ANSI/TIA-862-A (April 2011) Building Automation Systems Cabling Standard

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 2

Page 10: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

TIA-1005-1 (March 2010) Telecommunications Infrastructure Standard for Industrial Premises; Addendum 1 - Industrial Pathways and Spaces

ISO/IEC ISO 11801 - Generic Cabling for Customer Premises

National Electric Codes

National Electrical Safety Code (NESC) (IEEE C2-2012)

National Electrical Code (NEC) (NFPA 70)

OSHA Standards and Regulations – all applicable

Local Codes and Standards – all applicable

BICSI Telecommunications Distribution Methods Manual, 12th Edition

Information Transport Systems Installation Methods Manual (ITSIMM), 6th Edition

ANSI/BICSI 002-2011, Data Center Design and Implementation Best Practices

ANSI/NECA/BICSI 568-2006, Standard for Installing Commercial Building Telecommunications Cabling

NECA/BICSI 607-2011, Standard for Telecommunications Bonding and Grounding Planning and Installation Methods for Commercial Buildings

ANSI/BICSI 001-2009, Information Transport Systems Design Standard for K-12 Educational Institutions

AV Design Reference Manual, 1st Edition

Network Design Reference Manual, 7th Edition

Outside Plant Design Reference Manual, 5th Edition

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 3

Page 11: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

Wireless Design Reference Manual, 3rd Edition

C. Anywhere cabling standards conflict with electrical or safety codes, Contractor shall defer to NEC and any applicable local codes or ordinances, or default to the most stringent requirements listed by either.

D. Knowledge and execution of applicable codes is the sole responsibility of the Contractor. Any code violations committed at the time of installation shall be remedied at the Contractor’s expense.

PART 3 - EXECUTION

3.1 Structured Cabling Systems Definition

A. "Structured Wiring" is a philosophy of pre-installing necessary cabling to device locations to be available to be used as these devices come on line. Moves and changes are affected at structured patch fields with the permanently installed links being relatively unchanging. In most basic form, a structured wiring system consists of horizontal wiring and appropriate connecting hardware, with backbone cabling connecting the horizontal sub-system to the main and intermediate distribution areas.

B. The following terms for various sub-systems are defined within the ANSI/TIA 568-C series of standards and shall be referred to throughout this document. 1. The entrance facility (EF) is the point where the outside plant cables and associated

hardware is brought into the building. The entrance facility may be used for public network services, private network customer services or both. The demarcation points between carrier and customer and over-voltage protection devices are located here.

2. The telecommunications room (TR) (often referred to in the industry as MDF/IDF) is a centralized space for telecommunications equipment (e.g. PBX, computing equipment, video switch, etc.) that serves users in the building. This room is also, where the horizontal distribution cables are terminated. All recognized types of horizontal cabling are terminated on compatible connecting hardware. Similarly, recognized backbone cables are also terminated in the closet. Device activation is done with jumpers or patch cables to provide flexible connectivity for extending various services to users at the telecommunications outlets.

3. The backbone cabling provides interconnections between telecommunications closets, equipment rooms and entrance facilities. It consists of the backbone cables, main and intermediate cross-connects, mechanical terminations and patch cords or jumpers used for cross-connection. The backbone may connect Telecom Rooms within a building or between buildings.

4. The horizontal cabling consists of the physical media used to connect each outlet or device to a TR. Various types of cable can be used for horizontal distribution. Each type has its own performance limitations, size, and ease-of-use.

3.2 REGULATORY REFERENCES - CONCLUSION

A. Denver Public Schools is investing in the latest technology to increase the speed and capacity of our communications systems in order to create a network infrastructure that will support DPS

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 4

Page 12: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

into the future. New applications will allow people to share vast amounts of information in the form of voice, data and video at efficient speeds. However, investing in the latest electronics to support these applications will be an exercise in futility if the installed cable plant cannot support the technologies involved.

B. Structured cabling will allow us to build an infrastructure for our communication needs to last well into the future. However, the ability to run any application, to any work area, at any time comes only with the proper planning and installation of a high-performance structured cabling system. Proper planning includes examining all applications, network technologies and telecommunications outlet locations that are currently used or might be used in the future. Accounting for foreseeable scenarios allows the physical infrastructure to be installed once, yet serve our requirements not yet on the horizon. Moves, adds and changes no longer require pulling new cables – except when our physical space expands.

C. Choosing the proper media for a new cable installation depends on the applications and services that the network is expected to provide. However, regardless of the other UTP classifications, Category 6 will be used for all data and telephony applications. Electrically noisy areas such as HVAC equipment rooms or near motors may lend themselves more to shielded or optical fiber cable. Budgetary concerns should influence the decisions to this point. However, keep in mind that standards-based systems are designed to last a minimum of 25 years from the time of installation. Therefore, cutting corners on the foundation of the network will have ramifications for many years to come and will not be tolerated. A properly planned and installed system will allow Denver Public Schools to spend their time, attention, and limited capital resources in other areas.

3.3 GENERAL INSTALLATION GUIDELINES

A. This section emphasizes some important details and installation processes for the structured cabling system. For complete guidelines see "Regulatory References" above.

B. Each individual 4 pair cable will be used for one service unless the data link application is designed to do so (as in VoIP voice over Internet Protocol). Splitting of pairs from a 4 pair cable across more than one jack is forbidden.

C. When installing Unshielded Twisted Pair (UTP) it must be compliant with industry standards. When routing cables through walls and ceilings the Contractor must maintain all distance limitations from power cable and devices as outlined in TIA 569-B.

D. Pulling a cable with too much force or bending it too sharply can change the electrical characteristics of the cable and degrade its performance, so care must be taken during the installation process to prevent any undue stress on the cable. Contractor shall adhere to all manufacturer's guidelines on cable handling, as well as the recommendations in TIA 568-C.0

E. The cable should move freely at all times and be protected from sharp edges while it is being pulled. When pulling around tight or multiple corners, two or more people should be used to guide the cable and prevent damage to it.

F. Care should be taken when using any type of cable tie. Cables should be lightly tightened to avoid any visible stress, which can change the characteristics of the UTP cable.

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 5

Page 13: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

G. All Contractor installed raceways shall be installed in practical alignment with either the building or structures within the building and securely attached to the building by use of plastic anchors, toggle bolts, expansion anchors or other method appropriate for the application and approved by the DoTS Project Manager.

H. All Contractor installed raceways shall be installed within the building so as not to interfere with or block any existing fixture, painting, mural, or artwork presently existing in the building.

I. All Contractor installed raceways shall be level and plumb when run vertically or horizontally along walls or ceilings. On raceway runs under a height of 8 feet from the floor, Contractor shall glue all fittings to the raceway using PVC cement.

J. All service loops on cabling links shall be according to TIA guidelines with a minimum 12" copper UTP slack in the work area that should be partially pushed back into conduit and stored in the ceiling space leaving approximately 7" left in the wall box. Contractors shall under no circumstances use "accordion" folds or in any way violate cable bend radius to store service loops in the work area.

K. Service loops in the telecommunications rooms shall also meet TIA requirements of 3 feet for copper and a minimum 3 meters slack for fiber backbones. TR slack shall be appropriately and neatly stored in managers, on pathways or on walls as necessary for that environment using storage appliances built to that purpose.

L. All penetrations shall be fire stopped according to national and local codes.

M. All Category 6 cables will be terminated on Panduit angled standard density Patch Panels and performance verified according to test procedures located in the testing and acceptance section of this document. For actual part numbers of copper cable and termination appliances, see the parts list (Attachment 1) at the end of this document.

N. Coax cables shall be installed only in maintaining legacy systems. Additions to such systems shall be terminated on eight port splitters with a minimum of 6” between rows to connect all coax within a TR. The Contractor will use T&B snap and seal connectors. The Contractor shall place a 75-Ohm terminator cap on any unused splitter output ports.

O. The device end of legacy coax cables will be terminated in self-terminating inserts placed in an appropriate faceplate to match the installed systems. Any conduits supplied by the electrical sub-contractor for support of installed video locations are to be 1” in size.

P. The Contractor shall test any additions to legacy coax cables and provide documentation of these tests as outlined in this document.

Q. The wiring Contractor will make the head end connection to the cable TV Vendor’s entrance termination when making additions to any legacy broadband systems.

R. The Contractor placed drops for Wireless Data Access Points (WAP’s) shall be terminated at the serving TR end in the Panduit patch panels, using black jacks, with the other Category 6 terminations, and labeled in the same fashion as all other cables.

S. The device end of access point drops will be terminated with a Panduit RJ45 Category 6 ivory Mini-com jack in 2-port surface mount box. No service loops are needed on WAP locations.

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 6

Page 14: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

T. In all other applications (i.e. hard deck ceiling or wall penetration), the device end of the cable will be terminated with a Panduit RJ45 Category 6 ivory TG-style jack and installed in a two port flush mount or surface mount box.

U. The Contractor will be responsible for mounting the Wireless Access Points and covers in hard deck applications. For specific parts, see parts list (Attachment 1) at the end of this document.

V. All Wireless Access Points that are placed above drop ceiling will have a 1” wide label placed on the grid below the WAP location. This label will be 1” wide and have black text on an orange label.

W. Any conduits provided for the communication outlets are to be 1” in diameter with no daisy chaining allowed between work areas or speakers in audio systems.

X. In locations using Wiremold raceway, the Contractor may match the raceway previously installed. The legacy Wiremold is type 2400 or 4000. A 1” conduit will be supplied for each 10’ of Wiremold placed. All new installations shall use raceway types as described in the project documentation. For Panduit non-metallic raceway, see attachment 1 at the end of this document.

Y. The Panduit frame used in conjunction with Wiremold raceway is CFG2__ or CFG4__ which is a two port or four-port GFCI frame. The Contractor will select the color to match the raceway. For a complete list of materials, see "Attachment 1" at the end of this document.

Z. Non-metallic multi-channel raceway shall be Panduit T-45, T-70, TG-70 or Twin-70 as described in the raceway section of this document. Consult project documentation for specific raceway to be used on that project.

AA. Labor and material components will include TR build-out. The Wiring Contractor may be responsible for purchasing and installing additional 4x8x3/4” fire rated plywood backboards. These backboards shall be installed with firebrand facing outwards and painted with white fire-retardant paint according to TIA and BICSI guidelines. The standard number of plywood sheets for the Main TR is two and a minimum of one sheet of ¾” plywood installed for each TR.

BB. The Contractor shall be responsible for placing and mounting of all equipment racks, wire management, terminating hardware (copper and fiber), ladder racks (including waterfalls), grounding of the ladder racks and Panduit frames, and all labeling as described in this document.

CC. Other specific installation guidelines are included in sections referencing specific sub-systems within this document.

3.4 MANDATORY CONTRACTOR REQUIREMENTS

A. Any Contractor wishing to bid DPS projects must meet the following qualifications: 1. Contractor shall maintain an established, permanent local office in the Denver, Colorado

metropolitan area. 2. Contractor must provide insurance and performance bond certificate for the full amount

of the bid proposal. 3. Contractor must not have filed for bankruptcy within the past seven years.

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 7

Page 15: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

4. Contractor must not have defaulted on a material or performance bond within the past seven years.

5. Background checks and drug testing must be documented for all onsite Contractor employees and available for review by DPS.

6. All work performed will be completed by employees of the Contractor. No subcontracting will be permitted without prior written approval from DPS/DoTS.

7. Contactor shall be a Panduit Certified Installer. 8. At least 30 percent of the technicians on the job must have a current Panduit Certified

Copper Technicians certificate to install Panduit Copper Distribution Systems. 9. At least 30 percent of the technicians installing any Fiber Distribution Systems must have

a current Panduit Certified Fiber Technicians certificate to install Fiber Distribution Systems.

10. Contractor is responsible for workmanship and installation practices in accordance with the Panduit Certified Installers Program and all recommendations of TIA and BICSI references cited above.

11. A copy of contractor company and individual certification documents must be submitted with the quote in order for such quote to be valid.

12. All projects shall be covered by the Panduit Certification PLUS Warranty as described in this document.

13. Denver Public Schools requires that the Contractor have a BICSI Certified Registered Communications Distribution Designer (RCDD) on staff for the duration of the project.

14. Contractor shall supply detailed references of five or more recently installed sites similar in size, drop count and configuration (including backbone). Please submit the site name, contact, contact telephone number, date installed, and project size.

3.5 CONTRACTOR PERSONNEL/TECHNICIAN REQUIREMENTS:

A. Contractor shall provide an organizational chart of all personnel to be involved with this project. This chart shall include names and telephone contact numbers for all corporate officers, local management staff, Project Managers, RCDD’s and technical staff. This list shall be kept current and submitted bi-weekly to the Department of Technology Services (DoTS) Project Manager for the duration of the project. Resumes should be included for the assigned Project Manager, Lead Technicians for each proposed site, and the RCDD overseeing the bid design.

B. All of the installation personnel of the Installation Contractor shall be required to wear uniforms on-site. As a minimum, these uniforms shall consist of shirt with the company's name prominently displayed and all personnel shall comply with all Denver Public Schools appearance polices.

C. Technician photo ID badges are also required to be worn on the upper part of the body at all times.

D. Each Technician must have been employed directly by the Contractor for a minimum period of six (6) continuous months, have successfully passed a background check, and drug test.

E. All Contractor employees must successfully pass a background check and drug test. Proof of this requirement can be requested by DPS at any time.

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 8

Page 16: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

F. The Contractor may request in writing to DPS on a case-by-case basis to utilize personnel that has verifiable related work experience, but may not have been employed by the Contractor for at least six (6) months.

3.6 PROJECT MANAGER REQUIREMENTS

A. Contractor shall assign a dedicated Project Manager (PM) to serve as a primary liaison with DPS both during the project and for maintenance issues after project completion.

B. Minimum five years project management experience for voice, data, and multimedia cabling infrastructure systems.

C. RCDD preferred.

D. Have current, Panduit technician certificates in both copper and fiber installation.

E. Have thorough knowledge of all applicable standards, NEC, building and NFPA codes.

F. Have working knowledge of networking equipment and topologies.

G. Possess good personal interaction and communications skills.

H. Use computer-based project management software (preferably Microsoft Project, Microsoft Excel).

I. Have experience with formalized quality assurance practices.

3.7 TASKS REQUIRED OF THE CONTRACTOR PROJECT MANAGER:

A. Serve as single point of contact on project related issues.

B. Oversee the project and complete quality inspections

C. Have the authority to execute changes for the Contractor.

D. Project coordination (labor tasks and materials).

E. Attend all project related meetings, walk-through, etc.

F. Be on-site for critical junctures.

G. Ensure conformance with Contract Provisions.

H. Be responsible for conditions and commitments associated with the Panduit Certification PLUS Warranty.

I. The Contractor’s Project Manager will be required to attend all project meetings requested. These may be weekly scheduled meetings or as required.

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 9

Page 17: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

3.8 PROJECT PROGRESS REPORT

A. The Contractor’s Project Manager will be required to submit weekly progress reports to Denver Public Schools and/or its designees via electronic transmission each Monday, at the end of the business day. Each report shall contain the following: 1. Work completed for the week, work scheduled for completion the following week,

unforeseen construction obstacles, other comments. 2. Daily/Weekly Work Logs: Daily - The installation Contractor shall keep a daily log to be

left on the job site. At a minimum, this log is to contain the following; weekly status reports, installation-tracking forms, material-tracking forms, packing slips, injury report, etc. This log must be available for reviewing at all times.

3. DoTS will supply an electronic copy of this form upon request. 4. The Contractor Project Manager shall send the weekly log to the DoTS Project Manager

or his/her designee by either Email or fax. 5. The Contractor shall create all logs using an Excel spreadsheet. (This may require the

Installation Contractor to maintain a portable computer on the job site).

DATE: MDF-A

Operation Total Runs

Rough-In

Runs Comp.

% Comp.

Term. Closet

% Comp.

Term. Jacks

% Comp. Tested

% Comp.

Rough In Cat 6 Cable #DIV/0!

Place Cat 6 Cable 100% #DIV/0! #DIV/0! #DIV/0!

Place Speaker Cable 100% #DIV/0! #DIV/0! #DIV/0!

Wireless Access Point #DIV/0!

Totals 0 0 0 #DIV/0! 0 #DIV/0! 0 #DIV/0! 0 #DIV/0!

Place 25pr Tie Cables Size Rough-In Length

Date Placed

Date Term.

Date Tested

MDF to IDF B

MDF to IDF C

Place Cat 6 Tie Cables # of Rough-In Length

Date Placed

Date Term.

Date Tested

MDF to IDF B

MDF to IDF C

Place RG 11 Tie Cables # of Rough-In Length

Date Placed

Date Term.

Date Tested

MDF to IDF B

MDF to IDF C

Place Speaker Tie Cables # of Rough-In Length

Date Placed

Date Term.

Date Tested

MDF to IDF B

MDF to IDF C

Place Fiber Optics Cable Mode Rough-In Length

Date Placed

Date Term.

Date Tested

MDF to IDF B

MDF to IDF C

Room Build Date Placed

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 10

Page 18: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

MDF-A

IDF-B

IDF-C

On Site MDF A

Qwest Date Placed DoTS Responsibility

IT Feed

Trunks released

Data Switch Installation Stacks

Date Placed

Date Tested DoTS Responsibility

MDF-A

IDF-B

IDF-C

X-Connects & Patch cords

Total X-Con

X-Cons Comp.

% Comp. DoTS Responsibility

IT Feed #DIV/0!

MDF-A #DIV/0!

IDF-B #DIV/0!

IDF-C #DIV/0!

Totals #DIV/0!

Telephones Total Sets

Sets Comp.

% Comp.

Sets Tested

% Tested

DoTS Responsi-bility

Stations #DIV/0! #DIV/0!

Video Feeds Date Placed Date Tested DoTS Responsi-

bility

Comcast

Productivity Total Hours

Prod. Hours

% Prod.

Non-Prod Hours

% Non-Prod

Lead Technician #DIV/0! 5 #DIV/0!

Technicians #DIV/0! 0 #DIV/0!

Roadblock Resolution Resolution Date

B. The Project Manager shall in addition to formal weekly reports, participate in a walkthrough of the site as often as required by DPS/DoTS.

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 11

Page 19: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

3.9 CONTRACTOR ADDITIONAL RESPONSIBILITIES

A. The Contractor is responsible for the cost to repair or replace any items that are damaged because of the Contractor’s work. These items may include, but are not limited to, ceiling grids, ceiling tiles, patch/ paint walls to match existing color, electrical, HVAC lines, etc.

B. When working in and around the building, extreme care shall be exercised with regard to protection of the existing structure and mechanical systems. The Contractor will be required to notify DPS/DoTS for the repair or replacement of any damaged items. DPS will arrange for the repairs or replacement and bill the Contractor as appropriate.

C. The Contractor shall thoroughly examine the premises and observe all conditions under which the work will be performed. The Contractor shall document all existing conditions.

D. Unless documented otherwise, all finishes shall be assumed undamaged. Any damage noted by Denver Public Schools and/ or its designees in the area of work performed, and not previously noted, shall be the responsibility of the Contractor.

E. All repairs, restoration, patching, etc. shall match existing adjacent surfaces as to material, texture, and quality.

F. Site Clean Up: 1. The Contractor is responsible for removing all trash and debris to outside garbage

containers on a daily basis by the end of each day, or as needed during the course of the day. The Contractor shall provide their own trash containers or utilize DPS trash containers with prior written approval.

2. No trash or debris is to be left in any area where work has been performed. This includes removing trashcans or other forms of garbage collection devices at the end of each day.

3. At the completion of the installation, the Contractor shall clean all areas where work has been performed. This procedure shall include vacuuming and light mopping of floor surfaces, cleaning of racks, panels, boards, etc. The Contractor may be required to repeat this process during the acceptance period.

4. Workstation outlet location areas shall be cleaned on an on-going basis each time the Contractor completes work in the area.

G. The Project Manager and Project Lead Technician shall have cell phones and be accessible at all times.

H. The Contractor shall have an Internet addressable Email box for communications with Denver Public Schools or its designees for the purpose of gaining or distributing current information.

I. All Contractors and their employees are expected to conduct themselves in a professional manner at all times while implementing any DPS cabling project. All rules and guidelines of the project site shall be followed.

J. No alcohol use, drug use, smoking, or inappropriate language shall be permitted on the project site.

K. Appropriate dress and identifications is required at all facilities and Contractor’s must follow DPS rules and regulations.

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 12

Page 20: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

L. Under no circumstances shall any Contractor employee use any school or school employee’s equipment or material.

M. Denver Public Schools/or its designees shall have the right to immediately remove personnel without notice.

N. The Contractor shall provide, possess, and have proper knowledge of the appropriate tooling and equipment required to install the specified materials; 1. This includes, but is not limited to the following: safety equipment, correct power tools,

personnel lifts, termination tools, field test equipment, etc. 2. Any tools that require certification (such as a power-actuated fastener), shall be only

operated by individuals certified in their use.

3.10 MATERIALS STORAGE

A. The Contractor is responsible for providing storage on the grounds of the project. As a minimum, water tight, lockable container capable of storing a two week supply of materials plus all of the Contractor's equipment is acceptable.

B. Outside portable storage units will need DPS approval prior to placement. The Contractor must remove any graffiti on Contractor’s equipment immediately.

3.11 FIELD VERIFICATION

A. The Contractor shall field verify all dimensions prior to installation. Field verifications shall include, but not be limited to, installing measuring tape in backbone pathways and reporting lengths to Materials Contractor.

3.12 SCHEDULE

A. For individual projects, Denver Public Schools and/or its designees will have compiled a project schedule. This schedule will be provided at the biweekly Project Managers Meeting. Each Contractor shall be responsible for reviewing the schedule and determining the necessary personnel to ensure timely task completion.

3.13 CHANGES TO SCHEDULE

A. Denver Public Schools and/or its designees may find it necessary to reduce (shorten) the schedule or lengthen the schedule of the initial allotted time. DPS shall not incur any additional cost should the schedule change. Any changes to the schedule shall be handled individually, with the concurrence of all parties.

3.14 DPS PROJECT CONTACT

A. If there are any questions or if any additional information is required pertaining to the DPS Project Coordination, please contact: Mike Hall at 720-423-3898.

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 13

Page 21: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

3.15 SYSTEM COMPONENT WARRANTY

A. All installed communications products shall be covered by a manufacturer component warranty against any manufacturing defects for a period of 25 years. 1. The Contractor shall replace, free of charge for this period, any cable, connector, or other

component installed by the Installation Contractor that fails due to such defects. 2. The Materials Contractor shall provide a copy of this product warranty to the Installation

Contractor. The Materials Contractor shall replace free of charge for this period, any cable, connector, or other passive component installed by the Installation Contractor that malfunctions.

3.16 CERTIFICATION PLUS SYSTEM PERFORMANCE WARRANTY

A. Contractor shall provide a 25 year Panduit Certification PLUS warranty on all copper and fiber permanent cabling links. This warranty guarantees the installed system shall support all current and future data link protocols designed and specified by IEEE and TIA to operate over that Category (copper) or OM designation (fiber) of cable.

B. The Certification Plus Warranty may be applied only if the cabling links are comprised entirely of Panduit connectivity and cable.

C. To offer this warranty, Contractor agrees to adhere to the requirements listed below: 1. Installation firm must be a current Panduit Certified Installer (PCI) in good standing and

shall include a copy of the company PCI certification with the bid. 2. Contractor shall name a project manager to serve on site as a liaison responsible to

inspect and assure all terminations are compliant to factory methods taught in Panduit Technician Certification Training and according to all Standards cited in the Regulatory References section of this document. This liaison shall have a current, up-to-date Panduit Certified Technician (PCT) certificate in both copper and fiber. Copies of the copper and fiber certificates of the Panduit liaison shall be submitted with the bid.

3. Contractor agrees all components comprising active links shall be of the same copper Category or fiber OM designation as the system being installed. Contractor shall under no circumstances mix different Categories or OM classes of cable or termination devices (connectors) within the same link or system.

4. Contractor shall install all racking and support structures according to TIA Standards in such fashion as to maintain both Standard and Manufacturer recommendations for uniform support and protection, segregation of different cable types, maintenance of maximum pulling tensions, minimum bend radius, approved termination methods as well as adhering to industry accepted practices of good workmanship.

5. Contractor is responsible for understanding and submitting to Panduit all documents required prior to project start to apply for this warranty. These include but are not limited to the project information form and SCS warranty agreement.

6. Contractor is responsible for understanding and submitting to Panduit all documents required at project end. These include completed warranty forms, passing test reports and drawings of floor plans showing locations of links tested.

7. Test results shall be delivered in the tester native format (not Excel) and represent the full test report; summaries shall not be accepted. Contact Panduit for a current list of approved testers, test leads and latest operating systems.

8. Upon acceptance of Warranty, Panduit will mail a notification letter to the Installer and a notification letter and warranty certificate to DPS.

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 14

Page 22: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

3.17 RESTORATION/RESPONSE TIME

A. If the failure or malfunction of a component causes a single workstation outlet location to become inoperable, the Contractor shall correct and make serviceable the station within eight (8) business hours of being notified of the problem. The repairs may be made during normal business hours as defined herein. All repairs shall be given priority over new installation work.

B. If the failure or malfunction of a component causes more than a single workstation outlet location (such as a network segment or backbone cable) to become inoperable, the Contractor shall correct and make serviceable the stations within four (4) hours of being notified of the problem. The repairs shall be made regardless of time of day.

3.18 The Contractor shall maintain a method of contact for these repairs for both normal business hours and non-business hours (24x7, 365 days).

3.19 The Contractor shall stock a sufficient amount of replacement materials for the expressed purpose of restoring service. The Contractor shall follow the manufacturers’ procedures to replace any materials used from their stock for these repairs (e.g., from the Materials Contractor or from the manufacturer).

3.20 All costs for the entire warranty period (25 years) shall be included as part of the project price.

END OF SECTION 270500

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 15

Page 23: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

COMMON WORK RESULTS FOR COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270500 - 16

Page 24: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 270513 – COMMUNICATION SERVICES

PART 1 - GENERAL

1.1 The main TR supports the incoming feeds from various service providers into the building. It also contains the telephone system, the master data networking equipment, and video amplifiers, as well as being the serving terminal for all intermediate TRs.

A. The feed from Century Link is terminated in this room by Century Link.

B. The feed from Comcast is terminated in this room by Comcast.

C. The feed from Sprint TV (rooftop receiver) is terminated in this room by Sprint.

PART 2 - PRODUCTS – NOT USED

PART 3 - EXECUTION – NOT USED

END OF SECTION 270513

COMMUNICATION SERVICES DPS PUSH Academy Remodel – Phase 2

270513 - 1

Page 25: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

COMMUNICATION SERVICES DPS PUSH Academy Remodel – Phase 2

270513 - 2

Page 26: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 270526 – GROUNDING AND BONDING

PART 1 - GENERAL

1.1 GROUNDING AND BONDING

A. Contractor is responsible for bonding to ground all newly placed equipment and installed racks or cabinets per the TIA 607-B Standard using Panduit bonding systems. Details of bonding are as follows: 1. All newly installed racks and cabinets shall have installed a vertical busbar mounted

along one equipment rail to serve as a clean, low-resistance bonding place for any equipment not equipped with a designated grounding pad.

2. Smaller equipment without an integrated grounding pad shall be bonded to the vertical busbar through the use of a thread-forming grounding screw that is anodized green and includes serrations under the head to cut through oxidation or paint on the equipment flange.

3. Larger equipment (chassis switches) with a designated grounding terminal shall be bonded to the vertical busbar with an EBC (equipment bonding conductor) kit built to that purpose.

4. Contractor shall take care to clean (wire brush, scotchbrite pads) any metallic surface to be bonded down to bare metal and apply a film of anti-oxidation paste to the surfaces prior to effecting the bond.

5. All bonding lugs on racks and busbars shall be of two-hole irreversible compression type. Mechanical lugs and single-hole lugs will not be accepted and shall be removed and replaced at Contractor's expense.

6. Every rack or cabinet shall have an individual bonding conductor into the grounding network, serially connecting (daisy-chaining) of racks is expressly forbidden and will not be accepted.

7. Rack Bonding Conductors (RBC) may tap into an overhead or under floor aisle ground, or may run to the wall-mounted grounding busbar in smaller Telecommunications rooms containing five racks or less.

8. A minimum of every other rack or cabinet shall be outfitted with a properly installed and bonded ESD (electro-static discharge) port along with a wrist strap and lead to be used by any technicians servicing network equipment. On four post racks and cabinets, these ESD ports and straps shall be provided on front and back to be accessible and able to reach any active equipment needing servicing.

9. Armored cables shall be properly bonded to the earthing system with a kit built to that purpose.

1.2 For examples of rack and cabinet grounding refer to the illustrations below:

GROUNDING AND BONDING DPS PUSH Academy Remodel – Phase 2

270526 - 1

Page 27: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

Properly Bonded Cabinet

GROUNDING AND BONDING DPS PUSH Academy Remodel – Phase 2

270526 - 2

Page 28: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

1.3 PRODUCTS

A. For complete list of bonding materials see "Attachment 1 - Materials" at the end of this document.

GROUNDING AND BONDING DPS PUSH Academy Remodel – Phase 2

270526 - 3

Page 29: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

PART 2 - PRODUCTS – NOT USED

PART 3 - EXECUTION – NOT USED

END OF SECTION 270526

GROUNDING AND BONDING DPS PUSH Academy Remodel – Phase 2

270526 - 4

Page 30: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 270528 – PATHWAYS FOR COMMUNICATIONS SYSTEMS

PART 1 - GENERAL

1.1 The Contractor shall be responsible for installing all pathways for cables, including core holes through walls and floors.

1.2 Core holes shall be sized for not more than 40% fill per Manufacturer's calculations, and installed according to industry best practices and all guidelines in Standards and Codes named in the Regulatory References section of this document.

1.3 The structural integrity of the floors or wall must not be disturbed. Any change to the building’s structural integrity, and/or any damage done to adjacent workspaces or corridors shall be the sole responsibility of the Contractor.

1.4 In addition, it is the Contractors responsibility to ensure that the placement of any core holes do not damage any building facilities such as electrical, plumbing, air conditioning lines etc. This may require x-ray or similar type devices to locate these services.

1.5 Contractors are responsible for any damage and ramifications due to improper drilling or improper locations. All core holes must be properly sleeved and fire stopped. As with any other intrusive aspect of this project, drilling issues should be coordinated with the appropriate school staff.

PART 2 - PRODUCTS – NOT USED

PART 3 - EXECUTION – NOT USED

END OF SECTION 270528

PATHWAYS FOR COMMUNICATIONS SYSTEMS DPS PUSH Academy Remodel – Phase 2

270528 - 1

Page 31: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

PATHWAYS FOR COMMUNICATIONS SYSTEMS DPS PUSH Academy Remodel – Phase 2

270528 - 2

Page 32: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 270529 – HANGERS AND SUPPORTS FOR COMMUNICATIONS SYSTEMS

PART 1 - GENERAL

1.1 SUSPENSION DEVICES (J-HOOKS)

A. A J-Hook cable support system or DPS approved equivalent shall be utilized to suspend the twisted pair workstation cables in the interstitial ceiling space from the cable tray to the access point in the ceiling above the workstation location.

B. These J-hooks shall have built-in 1 inch bend radius control. The system shall accommodate cable ties to retain bundles and have available a full assortment of mounting options.

C. J-hooks shall be installed at no less than five foot (5 ft.) intervals and be attached to the building structure independent of ceiling systems and supports. J-hook shall be independently mounted using hardware built to that purpose.

D. No cable shall touch, or appear to touch, any other facility, system, apparatus, etc. in the interstitial ceiling space (e.g. ducts, conduits, pipes, etc.). Improperly installed cable and/or supports shall be remedied at Contractor's expense.

E. Only approved mounting fasteners shall be permitted. In no case shall the Contractor use a low velocity fastening tool into a surface not listed for such purpose (e.g. no shooting into the roof deck of the top floor).

F. The Contractor must adhere to the Category 6 manufacturer's fill recommendations for all j-hooks. DoTS requires any bundle over 180 cables be supported in wire basket.

G. J-Hook fill rates:

.75” J- Hook 8 Category 6 cables 1.31” J-Hook 25 Category 6 cables 2” J-Hook 46 Category 6 cables 4” J-Hook 180 Category 6 cables

H. DoTS requires any bundle over 180 cables be supported in ladder rack, wire basket or trough.

PART 2 - PRODUCTS

2.1 USE OF CABLE TIES

A. Blue Velcro type cable ties shall be installed in TRs. Plenum cable ties will be installed in all other location including the ceiling space.

B. Plenum cable ties must be red in color to be easily identifiable upon inspection. All cable wraps shall be loosely installed with no deformation to the cable jackets.

HANGERS AND SUPPORTS FOR COMMUNICATIONS SYSTEMS DPS PUSH Academy Remodel – Phase 2

270529 - 1

Page 33: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

C. See Attachment 1 - materials for cable tie part numbers.

PART 3 - EXECUTION – NOT USED

END OF SECTION 270529

HANGERS AND SUPPORTS FOR COMMUNICATIONS SYSTEMS DPS PUSH Academy Remodel – Phase 2

270529 - 2

Page 34: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 270533 – CONDUITS AND BACKBOXES FOR COMMUNICATION SERVICES

PART 1 - GENERAL

1.1 CONDUITS

A. Conduits shall be coupled with compression fittings listed for such purpose. All conduits shall be supported using the appropriate supporting hardware.

B. The inside radius of a bend in a conduit shall be at least 10 times the internal diameter of the conduit, regardless of size. All bends in conduits shall be done in a sweeping manner.

C. All metallic conduits shall be bonded to an approved connection point of the building grounding system. All conduits shall have an insulated bushing at each end.

D. Building codes require a bushing to be placed at each end of any conduit that is used for placing communications wiring. The purpose of these bushings is to protect the cabling as it is being placed. The Contractor will be required to ensure these bushings are in place prior to pulling wiring and not place them after the fact.

E. If upon inspection by the DoTS Project Manager, it is noted that the bushings are not in place or it appears that the bushings were placed after the cable was pulled (split bushing), the Contractor will be directed to remove the wiring that was placed, destroy that wiring, and re-pull the wiring with the appropriate bushings in place. This remedy will be at the Contractor's expense.

F. The electrical sub-contractor will place bushings for conduits they install. All installation of conduit shall be per previously referenced TIA and BICSI guidelines.

G. Double-gang wall boxes that will be used in conjunction with single-gang faceplates shall include a Panduit reducing plate to make the smaller plate fit. See Attachment 1 - Materials for part number.

PART 2 - PRODUCTS

2.1 CONDUIT SLEEVES

A. The Installation Contractor shall provide and install conduit sleeves wherever a cable passes through a boundary or partition (e.g. walls, ceiling tiles, floors, etc.). This requirement stands regardless of whether or not the boundary or partition is fire or smoke rated.

B. Conduit sleeves shall support multiple cable bundles, with no sleeve exceeding a maximum 60% fill factor upon installation per manufacturers fill guidelines, (provided sleeve is 24 inches in length or less; sleeves over 24 inches in length require a maximum fill percentage of 40%).

CONDUITS AND BACKBOXES FOR COMMUNICATIONS SYSTEMS DPS PUSH Academy Remodel – Phase 2

270533 - 1

Page 35: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

C. If identified fill factors are at capacity, additional sleeves will be required. Fire stop applications may dictate smaller fill ratios for a specific application. All conduit sleeves shall have a bushing at each end.

D. Conduit sleeves that route workstation cabling into a communications room (through walls, floors, or ceilings) shall be a minimum 4" in diameter and properly supported per standards cited in the Regulatory References section of this document.

PART 3 - EXECUTION

3.1 FIRE STOPPING

A. The Contractor shall properly fire stop all cable pathways designed for the installation of communications cables, regardless of who provided the opening and whether or not twisted pair workstation cable is routed through the openings. These include, but are not limited to conduit openings, cable tray penetrations, wall penetrations, core holes, sleeves, etc.

B. Both the inside and outside of the penetration must be fire stopped. Fire stop must fill the conduit or sleeve to a depth of 1” to meet the one-hour fire rating.

C. The Denver Building Department requires a fire seal in the ceiling end of conduits that stub up into the plenum ceiling area and as a result Contractor’s must include this activity as part of their bid.

D. If a General Contractor is involved, the General Contractor is required to fire seal the exterior perimeter of any conduits placed by the electrical subcontractor.

E. The Contractor will provide foam or another form of approved fire stopping method around the opening in the wall's top or conduit. All fire stop materials must be U.L. listed for the environment and purpose to which they are employed.

END OF SECTION 270533

CONDUITS AND BACKBOXES FOR COMMUNICATIONS SYSTEMS DPS PUSH Academy Remodel – Phase 2

270533 - 2

Page 36: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 2705239 – SURFACE RACEWAYS FOR COMMUNICATIONS SYSTEMS

PART 1 - GENERAL

1.1 CONTRACTOR PLACED RACEWAYS

A. The Contractor in accordance with the manufacturer’s instructions and installation guidelines contained in TIA 569-B, shall install cable trays/troughs. The Contractor will utilize a black 18” cable tray and 16" x 4” trough in all telecommunications rooms. The cable trays/troughs shall be utilized for routing and support of the communications cables within the TRs.

B. Cable trays/troughs shall be properly anchored to the racking structure in order to support the weight of the tray/trough and the cable within.

C. Cable tray/trough routing should avoid changes in elevation, direction, other building utilities and structural obstructions. Wherever possible, 12 inches of headroom shall be provided above the cable tray/trough.

D. The Contractor will attach to the top rear section of each Panduit frame an 18” black ladder rack. In addition, the Contractor will install a section of 18” black ladder rack spanning wall to wall at right angles to the Panduit frame. This ladder rack will be equipped with 16” cable tray. These cable trays will be installed by the Contractor to conceal wiring from the point of entry into the TR to the point the wiring drops down into the Panduit frame.

E. The Contractor shall permanently attach the cable tray to the ladder rack with the heads of the screws inside the tray and the threaded end of the screw not extending below the cable tray to prevent a hazard.

F. The Contractor will bundle together the workstation cable in the cable trough. These bundles shall be loosely held together with cable wraps and placed towards the center of the trough.

G. Placing the bundles towards the center of the cable trough will maintain an orderly installation in the cable trough during the initial implementation and will facilitate future installation of twisted pair workstation cables.

PART 2 - PRODUCTS – NOT USED

PART 3 - EXECUTION – NOT USED

END OF SECTION 270539

SURFACE RACEWAYS FOR COMMUNICATIONS SYSTEMS DPS PUSH Academy Remodel – Phase 2

270539 - 1

Page 37: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SURFACE RACEWAYS FOR COMMUNICATIONS SYSTEMS DPS PUSH Academy Remodel – Phase 2

270539 - 2

Page 38: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 270553 – IDENTIFICATIONS FOR COMMUNICATIONS SYSTEMS

PART 1 - GENERAL

1.1 LABELING

A. All permanently installed cable and network infrastructure labels shall be machine generated on labels manufactured for that purpose, and designed to outlast the elements to which they attach.

B. All permanently installed cable and network infrastructure labels shall be machine generated using Panduit Easy-Mark software, or generated on-site using a Panduit PanTher hand-held labeler. All materials are listed in "Attachment 1 - Materials" at the end of this document.

C. It is the responsibility of the Contractor to label all elements of the network cabling system with permanent, machine-generated labels according to: 1. Circuit naming conventions already established at Denver Public Schools. 2. Guidelines established in the TIA 606-B Standard. 3. Any project-specific instructions associated with particular jobs.

D. On specific projects, Contractor shall bring to the attention of DoTS anywhere these standards, guidelines and instructions may be in conflict for clarification and resolution.

E. The following are general points regarding how Denver Public Schools cabling shall be labeled: 1. Label each cable, work area outlet location, fiber enclosure, etc. with a computer

generated or machine printed label. Each label shall be easily visible and made of materials designed to outlast the elements to which they are attached.

2. Labels shall be machine generated using Panduit Easy-Mark labeling software and laser-printed onto Panduit sheet labels appropriate to the device to which they attach. See "Attachment 1" at the end of this document for complete materials list for labeling

3. Individual labels that must be printed on-site will be printed using the Panduit "PanTher" hand-held labeler (LS8EQ-KIT-ACS) onto labels made specifically for the elements to which they attach. See "Attachment 1" at the end of this document for complete materials list for labeling

4. Handwritten labels for anything besides temporary place-holders prior to placement of permanent

PART 2 - PRODUCTS

2.1 CABLE LABELS

A. The structured cabling system is based on a structured wiring design of three (3) - UTP Category 6 cables to each teacher/student outlet location. The cables shall be designated by TR room, rack, row, and position (i.e. A.2.14.24, B.2.5.15).

B. All additions to legacy coax cables will be labeled at both ends utilizing the alpha TR designation and a consecutive numeral designation beginning at one.

IDENTIFICATIONS FOR COMMUNICATIONS SYSTEMS DPS PUSH Academy Remodel – Phase 2

270553 - 1

Page 39: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

C. Hand-written cabling systems labels are not allowed and will not be accepted.

D. All cable labels shall be of the wrap around self-laminating type. It is Contractor's responsibility to confirm the label size is appropriate for the cable installed. See "Circuit Designation and Labeling Materials List" in Attachment 1 at the end of this document for complete list of DPS approved labeling supplies.

PART 3 - EXECUTION

3.1 EQUIPMENT LABELS – GENERAL

A. All telecommunications equipment and parts furnished and installed by the Contractor shall be equipped with a permanent numbering identification indicating its individual location within the school.

B. All such identification labels shall be machine generated. Hand written designators will not be accepted.

C. Label numbers shall be comprised of the TR room-rack-row-position. Equipment to be identified shall include, but not limited to, all wiring, faceplates, jacks and connecting blocks.

D. All vertical and horizontal faceplates and other miscellaneous locations (e.g. master clock, DDC/IBAS, security panel, etc.) will be identified using TR room-rack-row-position specific to the drop location.

E. Faceplates shall be provided a Panduit machine printed adhesive label placed directly on faceplate in the label area. The clear plastic label cover will then be installed over the permanent label.

3.2 JACK DESIGNATORS

A. All jacks at both the device and patch panel locations may be identified with a permanent fine tip Sharpie, handwritten using TR room-rack-row-position specific to the drop location on the side of the jack. This labeling shall not be visible from the exterior face of the jack.

3.3 PATCH PANEL LABELING

A. All patch panels located in the TRs will be identified by using rack-row-position specific to the drop location using permanent, pressure sensitive (sticky), machine generated labels designed to fit in the plates that snap into the front of the patch panels.

3.4 FIBER ENCLOSURE LABELING

A. The black enclosures shall be labeled with "From - To" information. All ports shall be labeled.

IDENTIFICATIONS FOR COMMUNICATIONS SYSTEMS DPS PUSH Academy Remodel – Phase 2

270553 - 2

Page 40: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

3.5 RACK LABELING

A. Racks will need to be numbered to conform to DPS/DoTS labeling requirements. For example, rack 0 should be installed closest to the wall and allowing for outward growth. The label shall be placed at the top and centered on the rack.

B. All racks will be labeled on the front and rear with 1" high continuous black on white vinyl tape.

END OF SECTION 270553

IDENTIFICATIONS FOR COMMUNICATIONS SYSTEMS DPS PUSH Academy Remodel – Phase 2

270553 - 3

Page 41: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

IDENTIFICATIONS FOR COMMUNICATIONS SYSTEMS DPS PUSH Academy Remodel – Phase 2

270553 - 4

Page 42: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 270800 – COMMISSIONING OF COMMUNICATIONS

PART 1 - GENERAL

1.1 SYSTEM PERFORMANCE TESTING

A. All cables shall be tested in accordance with this document, the ANSI/TIA standards, the PANDUIT® Certification Plus System Warranty guidelines and best industry practice.

B. If any of these are in conflict, the Contractor shall bring any discrepancies to the attention of the DPS project team for clarification and resolution.

C. Copper Testing: 1. All twisted-pair copper cable links shall be tested for Category 6 compliance per the

requirements in ANSI/TIA 1152 and ANSI/TIA 568-C.2 using a test unit meeting a minimum IEC IIIe level of accuracy.

2. All Category 6 cables shall have a minimum of +3db of headroom. 3. All testers used must have been factory calibrated by the manufacturer within one year of

use or according to factory calibration recommendations, whichever is the more stringent. 4. Contractor shall set references according to manufacturer’s recommendation prior to each

day’s testing and reset references anytime tester is left unused for more than two hours.

D. Fiber Testing 1. All installed fiber shall be tested for link-loss in accordance with ANSI/TIA-C.0 and shall

be within limits specified within ANSI/TIA-C.3. DPS may further define acceptable link loss thresholds for specific fiber links.

2. For horizontal cabling systems using multimode optical fiber, attenuation shall be measured in one direction at either 850 nanometer (nm) or 1300 nm using an LED light source and power meter.

3. Backbone multimode fiber cabling shall be tested at both 850 nm and 1300 nm (or 1310 and 1550 nm for single mode) in both directions.

4. Test set-up and performance shall be conducted in accordance with the ANSI/568-C.0 Standard, Method B. All test leads must be reference cords built specifically for fiber testing. Fiber testing performed using standard fiber jumpers will be considered invalid and must be repeated by the Contractor at no cost to DPS.

5. Where multiple links are combined to complete a circuit between devices, the Contractor shall test each individual terminated fiber link - so only basic link loss is required. The test method shall be the same used for the test described above. The values for calculating loss shall be those defined in the ANSI/TIA 568-C.3 Standard unless specified otherwise in by DPS.

6. Attenuation testing shall be performed with stable launch conditions, using as test leads true fiber reference cords built to that purpose. The light source shall be left in place after calibration and the power meter moved to the far end to take measurements. While an OTDR may be useful to determine exact locations of light loss, only a loss meter is required for simple link performance verification.

COMMISSIONING COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270800 - 1

Page 43: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

PART 2 - PRODUCTS

2.1 TEST RESULTS AND DOCUMENTATION

A. Upon completion of the installation and testing, the telecommunications contractor shall provide three (3) full documentation sets to the DPS/DoTS for approval within three weeks of completion of installation.

B. Test results must be in the tester native format, spreadsheets will not be accepted.

C. The media shall be clearly marked on the outside front cover with the words “Project Test Documentation”, the project name, and the date of completion (month and year).

D. The results shall include a complete record of test frequencies, cable type, conductor pair and cable (or outlet) I.D., measurement direction (where applicable), reference setup, and test crew member name(s).

E. The test equipment name, manufacturer, model number, serial number, software (OS) version, model number of test heads and leads (where applicable), and last calibration date will also be provided at the end of the document.

F. Unless the manufacturer specifies a more frequent calibration cycle, an annual calibration cycle is anticipated on all test equipment used for this installation.

G. The test document shall detail the test method used and the specific settings of the equipment.

H. When repairs and re-tests are performed, the problem found and corrective action taken shall be noted, and both the failed and passed test data shall be documented in the documentation.

I. DPS reserves the right to confirm contractor test results with random testing by a 3rd party including the right to require contractor to perform 100% retesting based upon the results of these random tests.

J. Mandated retests based on discovery of faulty methods/results shall be performed at Contractor's expense.

K. The As-Built drawings are to include cable routes and outlet locations. Their sequential number as defined elsewhere in this document shall identify outlet locations.

L. Numbering, icons, and drawing conventions used shall be consistent throughout all documentation provided.

M. DPS will provide floor plans in paper and electronic (DWG, AutoCAD - latest version) formats on which as-built construction information can be added. These documents will be modified accordingly by the telecommunications contractor to denote as-built information as defined above and returned to the DPS in hard copy and electronic form (AutoCAD).

COMMISSIONING COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270800 - 2

Page 44: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

PART 3 - EXECUTION

3.1 CUTOVER REQUIREMENTS

A. Contractor’s bid proposal shall include all labor and material necessary to cut over (migrate) the school/site communication system from the existing wiring infrastructure to the newly Contractor installed wiring infrastructure.

B. The system cutover timeframe for the voice, data, and video, etc. communications network will take place upon completion of the new wiring infrastructure but not in conjunction with the installation of the new system. The cutover schedule will be scheduled and coordinated by the DoTS Cut Coordinator.

C. The Contractor will be required to attend any walkthroughs with the DoTS Cut Coordinator, in order, to determine room/office outlet locations, phones that are defective and need to be replaced, new phone locations and any other documentation needed for a successful cut over.

D. DoTS Cutover Responsibilities: 1. The DoTS Cut Coordinator will be on site at the time of the cut over and work closely

with the Contractor to ensure a quick and successful cut over transparent to the end user. 2. The DoTS Cut Coordinator will provide the Contractor with cut sheets that will include

all information necessary for the Contractor to complete the work. 3. DoTS will provide any telephone instruments that are required. 4. The DoTS Cut Coordinator will remove all cross connects on the old terminal wall field

and determine for the Contractor what wiring and material the Contractor is to remove.

E. Contractor Cutover Responsibilities 1. The Contractor will assign a Cut Coordinator to the project who will work closely with

the DoTS Cut Coordinator. 2. Using the floor plans provided by the Contractor, the DoTS Cut Coordinator in

conjunction with the Contractor’s Cut Coordinator will conduct walkthroughs to determine room/office outlet locations, phones that are defective and need to be replaced, new phone locations and any other documentation needed for a successful cutover.

3. The Contractor will be responsible to identify and resolve any issues with the Contractor placed cables for opens, reversals, etc.

4. The Contractor will be responsible for removing and disposing of all old wiring and used material from the school as directed by the DoTS Cut Coordinator.

5. If the existing phone and data equipment is relocated to a new location, the Contractor, using the information provided by DoTS, will remove all phone and data related equipment (Phones, Ethernet switches, routers, NIU) from the existing location and reinstall that equipment in the new location and mount that equipment in either a rack or on the wall as directed by the DoTS Cut Coordinator.

6. Using the cut sheets, the Contractor will be responsible to place all voice and data patch cords, cross connects, line cords, and Remote Access Devices.

7. In conjunction with the equipment cutover, the Contractor will visit each phone and data location within the school and move the phone and computer from the old wiring to the new wiring location as designated on the cut sheets.

8. The Contractor will change all line and patch cords to lengths specified in the project documentation and per direction of the DoTS. See Attachment 1 at the end of this document for part numbers.

COMMISSIONING COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270800 - 3

Page 45: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

9. The Contractor will replace the existing computer patch cord with a new Contractor provided Category 6 patch cord. See Attachment 1 at the end of this document for part numbers.

10. All computers will be tested by DPS personnel during the cut over. 11. Where required, the Contractor will be responsible for changing the existing wall phone

to a desk set, and patch and repair all holes left in the walls. The replacement equipment for damaged telephone instruments or set bases will be provided by DPS.

12. In instances where the Contractor will be required to install or replace raceway, care shall be taken to match raceway with the legacy installation. See Attachment 1 at the end of this document for a listing of DPS acceptable raceway.

13. In the event certain portions of old raceway must be removed, the Contractor will be responsible to remove any raceway that has been damaged or detached from the original wall. However, painting to match the existing walls will not be required.

14. In cases where just a small amount of raceway is removed, end caps will also not be required.

15. If the existing faceplate and outlet are behind any piece of large furniture (e.g. cabinets, file cabinets, etc.) the Contractor will be responsible to move the furniture and replace the faceplate. If the Contractor feels this cannot be done in a safe manner, the Contractor should contact the DPS Cut Coordinator for instructions.

16. Situations might also arise where the existing holes cannot be patched or covered with a single or double gang outlet cover, this also should be noted and reported to the DPS Cut Coordinator for guidance.

17. Test each set for dial tone, line access and extension number. If during the cut over of the school/site there are any wiring outlets that were missed on the initial installation of the wiring or any problems found in the new infrastructure, the Contractor will correct these problems promptly at no additional cost to DPS.

18. The Contractor will be responsible for securely mounting all wireless access points provided by DPS. These access points will be mounted as directed by the DPS Cut Coordinator.

19. The Contractor will also be required to provide a patch cable to connect the wireless access point into the Category 6 cable and jack for each wireless access point installed.

20. After the cutover has been completed, the Contractor and the DoTS Cut Coordinator will conduct a final acceptance walkthrough to ensure that all problems have been resolved and the cut over has been successfully completed.

21. The Contractor should realize that each school will have different situations and circumstances that will be addressed on a case by case basis.

22. Contractor will also be responsible for resolving any structured cabling conversion related issues for 60 days after cutover.

23. If the Contractor and the DPS Cut Coordinator cannot resolve any problems that might arise then the decision of the DPS Cut Coordinator will be final and binding at no additional cost to DPS.

F. Inspection/Acceptance Period 1. Denver Public Schools and/or its designees shall periodically inspect the work of the

Contractor. When requested the Contractor shall, at no additional charge, supply an installation technician to accompany the individual(s) performing the inspection tasks. The Contractor shall be responsible for uncovering concealed areas in order for the work to be inspected.

2. Denver Public Schools requires a thirty (30) day acceptance period after the completion of any project, or a portion thereof if turned over to DPS prior to the completion of the

COMMISSIONING COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270800 - 4

Page 46: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

total project. Final project completion is the conclusion of all specified work, including all labeling, testing, documentation, site cleanup, and quality inspection.

3. DPS and/or its designees shall utilize this acceptance period to perform workmanship evaluations and random testing. A representative of the Contractor shall be available to work with DPS and/or its designees during this acceptance period.

4. The Contractor shall be required to make any repairs or modifications deemed necessary by Denver Public Schools and/or designees immediately, without exception or recourse.

5. The required warranties shall begin at the conclusion of the acceptance period.

END OF SECTION 270800

COMMISSIONING COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270800 - 5

Page 47: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

COMMISSIONING COMMUNICATIONS DPS PUSH Academy Remodel – Phase 2

270800 - 6

Page 48: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 271119 – COMMUNICATIONS PATCH PANELS

PART 1 - GENERAL

1.1 COPPER PATCH PANELS AND TERMINATION BLOCKS

A. Patch panels will be installed in all MDF, IDF and Entrance Facility locations.

B. All patch panels shall be standard density (48 ports per 2 RU), angled modular-jack style and designed to accommodate Panduit TG-style 8 position modular jacks.

C. No patch panel should be installed below row 26 except in rack zero without explicit instruction to do so from the DPS DoTS.

D. Smaller installations or ones with limited floor space may use wall mount distribution racks. In these instances the project documentation will so indicate and the DoTS PM will make this determination.

E. Multi-pair backbones shall be terminated on rack mounted 24 port angled modular panels or hardware selected to match legacy hardware for that location.

PART 2 - PRODUCTS – NOT USED

PART 3 - EXECUTION – NOT USED

END OF SECTION 271119

COMMUNICATIONS PATCH PANELS DPS PUSH Academy Remodel – Phase 2

271119 - 1

Page 49: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

COMMUNICATIONS PATCH PANELS DPS PUSH Academy Remodel – Phase 2

271119 - 2

Page 50: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 271500 – COMMUNICATIONS HORIZONTAL CABLING

PART 1 - GENERAL

1.1 ROUTING OF TWISTED PAIR WORKSTATION CABLE

A. All twisted pair workstation cables shall be within 295 feet from patch panel to faceplate.

B. Where installing cabling infrastructure in the interstitial ceiling space or routing cables to a workstation location, the cables shall be installed above all other apparatus in the ceiling, as close as possible to the deck above.

C. These cables shall be run in bundles and supported with an approved hanging system (e.g. Panduit J-mod, J-hook system). See 27 05 29 Hangers and Supports for Communications Systems section of this document for details.

D. The maximum span between supports shall be five feet (5 ft.). All cables shall be loosely bundled (never tightly) with plenum cable ties every five feet or less.

E. Without exception, in any instance where a cable passes through a wall or other barrier, the cable must be protected with a fire caulked metallic sleeve as described elsewhere in this document.

F. All cables routed from the termination point to the work area outlet shall be free of splices, deformations, jacket damage, or other factors that may degrade the performance of the cables.

G. See "Attachment 1 - Materials" at the end of this document for UTP cabling part numbers.

PART 2 - PRODUCTS

2.1 WORK AREAS – GENERAL REQUIREMENTS

A. All partition wall workstation outlet locations shall have the cables routed in the void space inside the wall whenever possible.

B. If conduit is provided at the location, the cables shall be routed therein to the outlet box.

C. If a conduit is not provided at the specified location, the Contractor shall make access to the void space above the ceiling level. The preferred method for this access is to utilize a stepper bit through the wall's top cap and insert a stud grommet.

D. The Contractor shall provide and install an outlet box at the standard electrical outlet height of 18” AFF. When practical the Contractor should match the orientation and height of the existing electrical outlets.

E. The Contractor shall provide foam or another form of approved fire stopping around the opening in the top of the wall.

COMMUNICATIONS HORIZONTAL CABLING DPS PUSH Academy Remodel – Phase 2

271500 - 1

Page 51: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

F. DPS standards are to install two teacher stations and one student station in each classroom.

G. The structured cabling system is based on a structured wiring design of three (3) - UTP Category 6 cables to each teacher/student outlet location.

H. The cables shall be designated TR room, rack, row, and position (i.e., A.2.14.24, B.2.5.15). All teacher/student cabling shall originate from Panduit jack panels in the TRs.

I. All twisted pair teacher/student cables shall be terminated on Panduit sloped horizontal or vertical type outlets.

J. Any other exceptions will be at the discretion of the DPS/DoTS project manager. All twisted pair workstation cables shall be terminated in consecutive order utilizing the station identification number.

K. All teacher/student cabling shall be configured to the 568B pinout.

L. Teacher outlet locations will consist of a four port sloped faceplate with three Category 6 cables. RG6 coax cable will be considered in additions to legacy systems only.

M. Student outlets will consist of a four port sloped horizontal or vertical faceplate with three Category 6 connections and the fourth port blanked out, or configured as called out in the documentation specific to that project.

N. The fixed video application is predominantly installed in new construction and remodeled schools; however, this application can be implemented in existing schools.

O. Contractor shall cable projector locations with low-skew, vga cable to the Teacher location. Low skew cable shall be termination on both ends with a 15 pin DB connector, Panduit part number CMD15HDEIY.

P. All horizontal wiring must not exceed (295 ft.). This is actual tested cable length, not the physical distance between the TR and the workstation outlet.

Q. If any horizontal cabling run is more than the 295 feet, it must be submitted to the DoTS Project Manager for written exemption to this document prior to being installed.

PART 3 - EXECUTION

3.1 INSTALLATION OF TWISTED STATION CABLES

A. The pulling tension of all twisted pair station cables shall not exceed 25 ft-lbs.

B. Jacketed twisted pair workstation cables shall have a minimum bend radius of four (4) times the diameter of the cable.

C. The jacket of the twisted pair cable for IDC type connections shall be removed as needed for termination, but jacket shall be as close as possible to insulation displacement clips as possible on installed devices as per TIA 568-C.0.

COMMUNICATIONS HORIZONTAL CABLING DPS PUSH Academy Remodel – Phase 2

271500 - 2

Page 52: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

D. The terminated workstation cables shall have equal tension on all conductors. In addition, conductors within a pair should not be bent around the other conductor to reach its termination point (commonly referred to as knuckling).

E. The pairs shall be visually inspected after the conductors are punched. If a connector needs to be re-terminated, all conductors in that cable shall also be re-terminated to keep consistent length, pair twists, and equal tension on all conductors.

F. On Panduit TG-style jack terminations, jacket of UTP cable shall pass entirely into device and be locked in place with retaining clip per Panduit Copper Technician certification class. Jacks showing exposed twisted pairs will not be accepted and must be corrected at Contractor's expense.

G. The conductors of the twisted pair cable shall be untwisted a maximum of (≈ 0.25 in.) from the point which the conductors are connected to the IDC (insulation displacement clips) of the termination device.

H. All terminations which require the use of an impact tool, shall have the insertion tool set to its lowest level. Only single conductor tools shall be permitted.

I. The installation technician shall visually inspect all seated conductors prior to using an insertion or impact tool to punch the conductors.

J. When pulling cable the cable shall not be bent around objects less than 4 inches in diameter, Contractor shall temporarily install a perpendicular, short length of 4 inch EMT or similar device to maintain cable integrity during installation.

3.2 MODULAR FURNITURE WORK AREAS

A. When modular furniture workstation outlets are required, all cables shall route through communications poles from the ceiling above the modular furniture.

B. Any holes drilled that expose any metal edges will be bushed to prevent damage to the wire.

C. In the event communication poles are filled to capacity, the Contractor will be required to install new poles (the old poles must be removed by the Contractor during the cutover).

3.3 SERVICE LOOPS AT WORK AREAS

A. DPS does not want “service loops” stored in wall boxes. When terminating the device end of the cabling, Contractor shall follow this procedure: 1. Pull 12” of wire out of the outlet box, trim and terminate the cabling. 2. After termination, push the cabling back up the conduit, leaving approximately 7” of wire

in the box. “Box stuffing” and kinking of cable will not be acceptable. 3. Allow the remainder to remain slack as it exits the upper end of the conduit and caulk the

conduit with fire caulking. 4. This applies to all horizontal terminal equipment locations including WAP locations in

dropped tile ceilings.

COMMUNICATIONS HORIZONTAL CABLING DPS PUSH Academy Remodel – Phase 2

271500 - 3

Page 53: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

3.4 USE OF CABLE TIES

A. Blue Velcro type cable ties shall be installed in TRs. Plenum tie-wraps will be installed in all other locations including the ceiling space.

B. Plenum cable ties must be red in color to be easily identifiable upon inspection. All cable wraps shall be loosely installed with no deformation to the cable jackets.

3.5 SEPARATION OF HORIZONTAL CABLE FROM EMI RFI SOURCES

A. All communications cabling shall be separated from sources of EMI/RFI according to by a minimum of six inches or according to guidelines in TIA 569-B, whichever is most stringent.

B. These EMI sources include, but are not limited to fluorescent lights/ballasts, air handling units, power risers, etc.

C. In any TR that is adjacent to an electrical room, mechanical room, elevator shaft, or other EMI/RFI source, the cables shall not be routed on the opposite sides of adjoining wall(s). Placement of cables in such situations shall follow guidelines in TIA 569-B and BICSI TDMM 13.

3.6 HORIZONTAL CABLE SEGREGATION

A. The Contractor shall segregate and bundle all workstation cables in the cable tray/trough as they enter the TR. All cables shall be bundled in groups of twenty-four (24) individual twisted pair workstation cables.

B. In horizontal TRs, the twisted pair workstation cables shall divide (right or left, top to bottom) depending upon the side of the patch panel to which the twisted pair workstation cables are terminated and from the direction the cables enter the racks.

C. The cables shall be grouped together for cable bundles destined for the same side of a wire management rack. This procedure shall produce an orderly installation with no crossovers for all visible cabling.

END OF SECTION 271500

COMMUNICATIONS HORIZONTAL CABLING DPS PUSH Academy Remodel – Phase 2

271500 - 4

Page 54: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 271619 – COMMUNICATIONS PATCH CORDS, STATION CORDS, AND CROSS CONNECT WIRE

PART 1 - GENERAL

1.1 COPPER AND FIBER PATCH CABLES

A. Patch cables are used to make the physical connection between the structured cabling and the network and telecommunications equipment.

B. At the TR, patch cables and fiber jumpers are used to facilitate fast and easy moves, changes or additions to the network.

C. At the desktop, station cables enable connectivity from the communications outlet to the end user’s network device.

D. All copper patch cables and fiber jumpers shall be factory assemblies. Hand termination of patch cables is not allowed.

E. All copper patch cables will be Panduit and will be color-coded blue and white to help differentiate between various systems running on the same cabling system.

F. The percentages of patch cables are as follows:

Per station jack (1) White & (1) Blue %

5' 48% 7' 34% 10' 15% 14' 2% 20’ 1%

G. In instances where the total patch cables exceeds 10 meters, the length of the permanent horizontal channel must be de-rated per the tables contained within TIA 568-C.0. Contractor is responsible to report all such instances to the DoTS for resolution.

PART 2 - PRODUCTS – NOT USED

PART 3 - EXECUTION – NOT USED

END OF SECTION 271619

COMMUNICATIONS PATCH CORDS, STATIONS CORDS, AND CROSS CONNECT WIRE DPS PUSH Academy Remodel – Phase 2

271619 - 1

Page 55: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

COMMUNICATIONS PATCH CORDS, STATIONS CORDS, AND CROSS CONNECT WIRE DPS PUSH Academy Remodel – Phase 2

271619 - 2

Page 56: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

7

20

T 2

21

71717

17

17E/G

17

17

20

2

21

20

20

20

T18

2

19

T

14

3

15

T

7 16 16 16 16

14

3

9

T

12

16

12

16

22

12 13

16

2222

89

66

5

6 666

333333

432

GFI

2

T

T4

P S G

P

S

G

P

Page 57: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME
Page 58: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 26 0526 - GROUNDING AND BONDING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Power System Grounding

B. Communication System Grounding

C. Electrical Equipment and Raceway Grounding and Bonding

1.3 REFERENCE STANDARDS

A. Comply with the requirements of the reference standards noted herein, except where more stringent requirements are listed herein or otherwise required by the Contract Documents.

B. NFPA Compliance: NFPA 70 "National Electrical Code (NEC).

C. UL Compliance: Applicable requirements of UL Standards Nos. 467 "Electrical Grounding and Bonding Equipment," and 869, "Electrical Service Equipment," pertaining to grounding and bonding of systems, circuits and equipment. In addition, require compliance with UL Std 486A, "Wire Connectors". Grounding and bonding products which are to be UL-listed and labeled for their intended usage.

D. IEEE Compliance: Applicable requirements and recommended installation practices of IEEE Standards 80, 81, 141 and 142 pertaining to grounding and bonding of systems, circuits and equipment.

1.4 SYSTEM DESCRIPTION

A. Ground the electrical service system neutral at service entrance equipment to metallic cold water service, building steel and to supplementary grounding electrodes, as indicated on drawings.

B. Ground each separately-derived system neutral to nearest metallic cold water pipe 2-inch diameter or larger, building steel and where present to the referenced ground bar as shown on drawings.

C. Provide communications system grounding conductor at point of service entrance and connect to nearest referenced ground bar as shown on drawings.

GROUNDING AND BONDING 26 0526 - 1 DPS PUSH Academy Remodel – Phase 2

Page 59: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

D. Bond together system neutrals, service equipment enclosures, exposed non-current carrying metal parts of electrical equipment, metal raceway systems, grounding conductor in raceways and cables, receptacle ground connectors, and plumbing systems.

1.5 SUBMITTALS

A. Submit shop drawings under provisions of Section 260500.

B. Indicate layout of ground ring, location of system grounding electrode connections, and routing of grounding electrode conductors.

C. Submit all field test reports.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Ground Rods: Copper or copper-clad steel, 3/4-inch diameter, minimum length 10 feet.

B. Mechanical Grounding Connectors: For all grounding connections above grade. 1. Manufacturer: Burndy Electrical 2. Material: Copper. 3. Compression Type: Irreversible. 4. UL listed under Standard UL467.

C. Wire: 1. Material: Copper. 2. Size: As indicated on the drawings. When size is not indicated, size per Article 250 of

NEC requirements.

D. Grounding Connection Accessories: 1. Electrical insulating tape, heat-shrinkable insulating tubing, welding materials, bonding

straps, as recommended by accessories manufacturers for type service required.

2.2 Field Welding: Exothermic welded connections are required where grounding conductors connect to underground grounding conductors and to underground grounding electrodes, and for bonding to steel. All underground connection shall be exothermic welded.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Provide a separate, insulated equipment grounding conductor in feeder and branch circuits. Terminate each ground conductor to the bushing and ground lug.

GROUNDING AND BONDING 26 0526 - 2 DPS PUSH Academy Remodel – Phase 2

Page 60: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

B. Connect grounding electrode conductors to metal water pipe using a suitable ground clamp. Make connections to flanged piping at street side of flange.

C. Supplementary Grounding Electrode: Use grounding mats, or driven ground rods, where indicated. Install ground rods in suitable recessed well; fill with gravel after connection is made.

D. Use minimum No. 6 AWG copper conductor for communications service grounding conductor. Leave 10-feet slack conductor at terminal board or cabinet.

E. Provide isolated grounds for all microprocessor and data processing equipment, where indicated on drawings.

F. Tighten grounding and bonding connectors and terminals, including screws and bolts, in accordance with manufacturer's published torque tightening values for connectors and bolts. Where manufacturer's torquing requirements are not indicated, connections are to be tightened to comply with tightening torque values specified in UL 486A to assure permanent and effective grounding.

G. Provide code-sized ground cable bonding jumpers, installed with ground clamps, across all conduit expansion couplings and fittings.

H. Route grounding connections, conductors to ground, and grounding conductors to protective devices in the shortest and straightest paths possible to minimize transient voltage rises.

I. Provide a corrosion-resistant finish to field connections, buried metallic bonding products, and where factory applied protective coatings have been destroyed, where subject to corrosive action.

J. All continuous runs of cable tray and all isolated sections of cable tray shall be grounded at intervals not to exceed 20 feet.

K. Provide an equipment grounding conductor in all non-metallic conduits.

L. Provide an equipment grounding conductor in all flexible metallic conduits.

M. Grounding conductor in feeders and branch circuits extend ground conductor to switches, receptacle, equipment enclosures, equipment, and panels etc. and ground as required.

3.2 FIELD QUALITY CONTROL

A. Upon completion of installation of electrical grounding and bonding systems, the ground resistance shall be tested with an earth ground resistance tester in accordance with IEEE 81, "Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Ground System". Where tests show resistance-to-ground is over values in Table 1 below, Contractor shall take appropriate action to reduce resistance to the values in Table 1, by driving additional ground rods; and then retest to demonstrate compliance. All results shall be recorded and submitted.

GROUNDING AND BONDING 26 0526 - 3 DPS PUSH Academy Remodel – Phase 2

Page 61: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

Table 1 Earth Ground Resistance to Equipment Equipment (Ohms) Pad Mount Transformer 5 Secondary Neutrals and Other Ground 10

END OF SECTION 260526

GROUNDING AND BONDING 26 0526 - 4 DPS PUSH Academy Remodel – Phase 2

Page 62: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 260533 - SURFACE RACEWAYS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

PART 2 - PRODUCTS

2.1 SURFACE METAL RACEWAY

A. Manufacturers: 1. Panduit Corp. 2. Square-D Company. 3. Hubbell, Inc. 4. Wiremold Company. 5. Substitutions: Under provisions of Section 260500.

2.2 SURFACE METAL RACEWAY

A. Description: Sheet metal channel with fitted cover, suitable for use as surface metal raceway.

B. Minimum Size: 1. Two Channels, one for power and one for data wiring: Wiremold 4000 or equivalent. 2. Single channel: Wiremold 700 or equivalent.

C. Finish: Factory applied paint finish or natural brushed or stainless steel. Coordinate finish with Architect.

D. Fittings, Boxes, and Extension Rings: Furnish manufacturer's standard accessories.

2.3 MULTIOUTLET ASSEMBLY

A. Manufacturers: 1. Wiremold Company 2. Hubbell, Inc. 3. Substitutions: Under provisions of Section 26 0500.

B. Multioutlet Assembly: Sheet metal channel with fitted cover, with pre-wired receptacles, suitable for use as multioutlet assembly.

C. Size: As indicated on Drawings.

D. Receptacles: Provide covers and accessories to accept receptacles specified in Section 262726.

SURFACE RACEWAYS 26 0533 - 1 DPS PUSH Academy Remodel – Phase 2

Page 63: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

E. Receptacle Spacing: As indicated on drawings.

F. Receptacle Color: As specified in Section 262726.

G. Channel Finish: Factory applied paint finish or natural brushed or stainless steel. Coordinate finish with Architect.

H. Fittings: Furnish manufacturer's standard couplings, elbows, and connectors.

2.4 WIREWAY

A. Manufacturers: 1. Cooper B-Line 2. Wiremold Company 3. Square-D 4. Hoffman 5. Substitutions: Under provisions of Section 26 0500.

B. General purpose type wireway.

C. Knockouts: Manufacturer's standard.

D. Size: As indicated on Drawings.

E. Description: Cover: Hinged cover.

F. Connector: Slip-in.

G. Fittings: Lay-in type with removable top, bottom, and side.

H. Finish: Factory applied paint finish or natural brushed or stainless steel. Coordinate finish with Architect.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Install products in accordance with manufacturer's instructions.

B. Use flat-head screws, clips, and straps to fasten raceway channel to surfaces. Mount plumb and level.

C. Use suitable insulating bushings and inserts at connections to outlets and corner fittings.

D. Wireway Supports: Provide steel channel as specified in Section 26 0529.

E. Close ends of wireway and unused conduit openings.

F. Ground and bond raceway and wireway under provisions of Section 26 0526.

SURFACE RACEWAYS 26 0533 - 2 DPS PUSH Academy Remodel – Phase 2

Page 64: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

G. Require electrical continuity of all raceway components throughout length of system. Metal raceway is not to be used as a grounding path.

END OF SECTION 260533

SURFACE RACEWAYS 26 0533 - 3 DPS PUSH Academy Remodel – Phase 2

Page 65: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SURFACE RACEWAYS 26 0533 - 4 DPS PUSH Academy Remodel – Phase 2

Page 66: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 26 2816 - ENCLOSED SWITCHES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SECTION INCLUDES

A. Fusible Switches

B. Nonfusible Switches

1.3 RELATED SECTIONS

A. Section 262813- Fuses.

1.4 REFERENCES

A. NECA - Standard of Installation (published by the National Electrical Contractors Association).

B. NEMA FU1 - Low Voltage Cartridge Fuses.

C. NEMA KS1 - Enclosed and Miscellaneous Distribution Equipment Switches (600 Volts Maximum).

D. NETA ATS - Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems (published by the International Electrical Testing Association).

E. NFPA 70 - National Electrical Code.

1.5 SUBMITTALS FOR REVIEW

A. Section 260500: Procedures for submittals.

B. Product Data: Provide switch ratings and enclosure dimensions.

1.6 SUBMITTALS FOR CLOSEOUT

A. Record actual locations of enclosed switches in project record documents.

ENCLOSED SWITCHES 26 2816 - 1 DPS PUSH Academy Remodel – Phase 2

Page 67: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

1.7 QUALIFICATIONS

A. Manufacturer: Company specializing in manufacturing the Products specified in this section with minimum three years documented experience.

1.8 REGULATORY REQUIREMENTS

A. Conform to requirements of NFPA 70.

B. Products: Listed and classified by Underwriters Laboratories, Inc. as suitable for the purpose specified and indicated.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Acceptable Manufacturers 1. Eaton Corporation 2. General Electric 3. Square-D 4. Siemens 5. Substitutions: Under provisions of Section 260500.

2.2 ENCLOSURES

A. Fabrication: NEMA KS 1. 1. Interior Dry Locations: Type 1. 2. Exterior Locations: Type 3R. 3. Elevator Locations: Type 4X.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Install in accordance with NECA "Standard of Installation".

B. Install fuses in fusible disconnect switches.

C. Apply adhesive tag on inside door of each fused switch indicating NEMA fuse class and size installed.

ENCLOSED SWITCHES 26 2816 - 2 DPS PUSH Academy Remodel – Phase 2

Page 68: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

3.2 FIELD QUALITY CONTROL

A. Inspect and test in accordance with NETA ATS, except Section 4.

B. Perform inspections and tests listed in NETA ATS, Section 7.5.

END OF SECTION 262816

ENCLOSED SWITCHES 26 2816 - 3 DPS PUSH Academy Remodel – Phase 2

Page 69: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

ENCLOSED SWITCHES 26 2816 - 4 DPS PUSH Academy Remodel – Phase 2

Page 70: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

SECTION 283100 - FIRE DETECTION AND ALARM

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes fire alarm systems.

B. Related Sections include the following: 1. Division 08 Section "Door Hardware" for door closers and holders with associated smoke

detectors, electric door locks, and release devices that interface with the fire alarm system.

1.3 DEFINITIONS

A. FACP: Fire alarm control panel.

B. LED: Light-emitting diode.

C. NICET: National Institute for Certification in Engineering Technologies.

D. Definitions in NFPA 72 apply to fire alarm terms used in this Section.

1.4 SYSTEM DESCRIPTION

A. Noncoded, addressable system; multiplexed signal transmission dedicated to fire alarm service only. 1. Interface with existing fire alarm system.

B. Noncoded, analog-addressable system; automatic sensitivity control of certain smoke detectors; and multiplexed signal transmission dedicated to fire alarm service only. 1. Interface with existing fire alarm system.

1.5 PERFORMANCE REQUIREMENTS

A. Comply with NFPA 72.

B. Premises protection includes E occupancy type with administration B occupancy.

C. Fire alarm signal initiation shall be by one or more of the following devices:

FIRE DETECTION AND ALARM 283100 - 1 DPS PUSH Academy Remodel – Phase 2

Page 71: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

1. Manual stations. 2. Heat detectors. 3. Smoke detectors. 4. Verified automatic alarm operation of smoke detectors. 5. Automatic sprinkler system water flow. 6. Fire extinguishing system operation.

D. Fire alarm signal shall initiate the following actions: 1. Alarm notification appliances shall operate continuously. 2. Identify alarm at the FACP and remote annunciators. 3. De-energize electromagnetic door holders. 4. Transmit an alarm signal to the remote alarm receiving station. 5. Unlock electric door locks in designated egress paths. 6. Release fire and smoke doors held open by magnetic door holders. 7. Switch heating, ventilating, and air-conditioning equipment controls to fire alarm mode. 8. Close smoke dampers in air ducts of system serving zone where alarm was initiated. 9. Record events in the system memory. 10. Shut down air transfer fans and close associated dampers.

E. Supervisory signal initiation shall be by one or more of the following devices or actions: 1. Operation of a fire-protection system valve tamper.

F. System trouble signal initiation shall be by one or more of the following devices or actions: 1. Open circuits, shorts and grounds of wiring for initiating device, signaling line, and

notification-appliance circuits. 2. Opening, tampering, or removal of alarm-initiating and supervisory signal-initiating

devices. 3. Loss of primary power at the FACP. 4. Ground or a single break in FACP internal circuits. 5. Abnormal ac voltage at the FACP. 6. A break in standby battery circuitry. 7. Failure of battery charging. 8. Abnormal position of any switch at the FACP or annunciator.

G. System Trouble and Supervisory Signal Actions: 1. Ring trouble bell and annunciate at the FACP and remote annunciators. 2. Record the event on system printer. 3. Transmit System trouble and supervising signal to the remote alarm receiving station.

1.6 SUBMITTALS

A. Product Data: For each type of product indicated.

B. Shop Drawings: 1. Shop Drawings shall be prepared by persons with the following qualifications:

a. Professional Engineer registered in the State of Colorado and familiar with this type of installation and with previous similar experience certifying that the Fire Alarm System has been designed in compliance with NFPA and governing codes.

2. System Operation Description: Detailed description for this Project, including method of operation and supervision of each type of circuit and sequence of operations for manually

FIRE DETECTION AND ALARM 283100 - 2 DPS PUSH Academy Remodel – Phase 2

Page 72: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

and automatically initiated system inputs and outputs. Manufacturer's standard descriptions for generic systems are not acceptable.

3. Device Address List: Coordinate with final system programming. 4. System riser diagram with device addresses, conduit sizes, and cable and wire types and

sizes. 5. Wiring Diagrams: Power, signal, and control wiring. Include diagrams for equipment

and for system with all terminals and interconnections identified. Show wiring color code.

6. Batteries: Size calculations. 7. Floor Plans: Indicate final outlet locations showing address of each addressable device.

Show size and route of cable and conduits. 8. All submittals, including but not limited to hydraulic calculations and drawings, created

by the Contractor and submitted to the Engineer shall have the signed stamp of a Professional Engineer registered in the State of Colorado and familiar with this type of installation and with previous similar experience certifying that the Fire Alarm System has been designed in compliance with NFPA and governing codes.

C. Qualification Data: For Installer.

D. Field quality-control test reports.

E. Operation and Maintenance Data: For fire alarm system to include in emergency, operation, and maintenance manuals. Comply with NFPA 72, Appendix A, recommendations for Owner's manual. Include abbreviated operating instructions for mounting at the FACP.

F. Submittals to Authorities Having Jurisdiction: In addition to distribution requirements for submittals specified in Division 01 Section "Submittals," make an identical submittal to authorities having jurisdiction. To facilitate review, include copies of annotated Contract Drawings as needed to depict component locations. Resubmit if required to make clarifications or revisions to obtain approval. On receipt of comments from authorities having jurisdiction, submit them to Architect for review.

G. Documentation: 1. Approval and Acceptance: Provide the "Record of Completion" form according to

NFPA 72 to Owner, Architect, and authorities having jurisdiction. 2. Record of Completion Documents: Provide the "Permanent Records" according to

NFPA 72 to Owner, Architect, and authorities having jurisdiction. Format of the written sequence of operation shall be the optional input/output matrix. a. Hard copies on paper to Owner, Architect, and authorities having jurisdiction. b. Electronic media may be provided to Architect and authorities having jurisdiction.

1.7 QUALITY ASSURANCE

A. The Contractor shall have at least 5 years experience in designing and installing fire alarm systems, with at least 3-systems greater than 200,000-square feet in the City and County of Denver within the last 2 years.

B. The installing company shall directly employ NIECET (minimum Level-II Fire Alarm Technology) technicians to guide the final checkout and to ensure system integrity. Anyone

FIRE DETECTION AND ALARM 283100 - 3 DPS PUSH Academy Remodel – Phase 2

Page 73: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

working on the fire alarm system must have a Denver Fire Alarm Systems License issue by the Denver fire Department for the current year with a maximum apprentice ratio of 2 to 1.

C. The Contractor shall employee a Journeyman Electrician for all electrical work. Electricians must have a Denver Fire Alarm Systems License.

1.8 PROJECT CONDITIONS

A. Interruption of Existing Fire Alarm Service: Do not interrupt fire alarm service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary guard service according to requirements indicated: 1. Notify Architect, Construction Manager and Owner no fewer than five working days in

advance of proposed interruption of fire alarm service. 2. Do not proceed with interruption of fire alarm service without Architect's, Construction

Manager's and Owner's written permission.

1.9 SEQUENCING AND SCHEDULING

A. Existing Fire Alarm Equipment: Maintain fully operational until new equipment has been tested and accepted. As new equipment is installed, label it "NOT IN SERVICE" until it is accepted. Remove labels from new equipment when put into service and label existing fire alarm equipment "NOT IN SERVICE" until removed from the building.

B. Equipment Removal: After acceptance of the new fire alarm system, remove existing disconnected fire alarm equipment.

1.10 EXTRA MATERIALS

A. Furnish extra materials described below that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Lamps for Remote Indicating Lamp Units: Quantity equal to 10 percent of amount

installed, but not less than 1 unit. 2. Lamps for Strobe Units: Quantity equal to 10 percent of amount installed, but not less

than 1 unit. 3. Smoke and Heat Detectors: Quantity equal to 10 percent of amount of each type

installed, but not less than 1 unit of each type. 4. Detector Bases: Quantity equal to 2 percent of amount of each type installed, but not less

than 1 unit of each type. 5. Keys and Tools: One extra set for access to locked and tamperproofed components. 6. Audible and Visual Notification Appliances: One of each type installed. 7. Fuses: Two of each type installed in the system.

FIRE DETECTION AND ALARM 283100 - 4 DPS PUSH Academy Remodel – Phase 2

Page 74: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Materials, appliances, equipment and devices shall be tested and listed by a nationally recognized approvals agency for use as part of a protective signaling system, meeting the National Fire Alarm Code.

2.2 EXISTING FIRE ALARM SYSTEM

A. Compatibility with Existing Equipment: Fire alarm system and components shall operate as an extension of an existing system.

2.3 SYSTEM SMOKE DETECTORS

A. General Description: 1. UL 268 listed, operating at 24-V dc, nominal. 2. Integral Addressable Module: Arranged to communicate detector status (normal, alarm,

or trouble) to the FACP. 3. Multipurpose type, containing the following:

a. Integral Addressable Module: Arranged to communicate detector status (normal, alarm, or trouble) to the FACP.

b. Piezoelectric sounder rated at 88 dBA at 10 feet (3 m) according to UL 464. c. Heat sensor temperature.

4. Plug-in Arrangement: Detector and associated electronic components shall be mounted in a plug-in module that connects to a fixed base. Provide terminals in the fixed base for connection of building wiring.

5. Self-Restoring: Detectors do not require resetting or readjustment after actuation to restore them to normal operation.

6. Integral Visual-Indicating Light: LED type. Indicating and power-on status. 7. Remote Control: Unless otherwise indicated, detectors shall be analog-addressable type,

individually monitored at the FACP for calibration, sensitivity, and alarm condition, and individually adjustable for sensitivity from the FACP. a. Fixed-temperature sensing shall be independent of rate-of-rise sensing and shall be

settable at the FACP to operate at 135 or 155 deg F (57 or 68 deg C). b. Provide multiple levels of detection sensitivity for each sensor.

B. Photoelectric Smoke Detectors: 1. Sensor: LED or infrared light source with matching silicon-cell receiver. 2. Detector Sensitivity: Between 2.5 and 3.5 percent/foot (0.008 and 0.011 percent/mm)

smoke obscuration when tested according to UL 268A.

2.4 NOTIFICATION APPLIANCES

A. Description: Equipped for mounting as indicated and with screw terminals for system connections.

FIRE DETECTION AND ALARM 283100 - 5 DPS PUSH Academy Remodel – Phase 2

Page 75: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

1. Combination Devices: Factory-integrated audible and visible devices in a single-mounting assembly.

B. Horns: Electric-vibrating-polarized type, 24-V dc; with provision for housing the operating mechanism behind a grille. Horns shall produce a sound-pressure level of 90 dBA, measured 10 feet (3 m) from the horn.

C. Visible Alarm Devices: Xenon strobe lights listed under UL 1971, with clear or nominal white polycarbonate lens mounted on an aluminum faceplate. The word "FIRE" is engraved in minimum 1-inch- (25-mm-) high letters on the lens. 1. Rated Light Output: As shown on drawings. 2. Strobe Leads: Factory connected to screw terminals.

D. Voice/Tone Speakers: 1. UL 1480 listed. 2. High-Range Units: Rated 2 to 15 W. 3. Low-Range Units: Rated 1 to 2 W. 4. Mounting: Flush, semirecessed, or surface mounted; bidirectional as indicated. 5. Matching Transformers: Tap range matched to the acoustical environment of the speaker

location.

2.5 ADDRESSABLE INTERFACE DEVICE

A. Description: Microelectronic monitor module listed for use in providing a system address for listed alarm-initiating devices for wired applications with normally open contacts.

B. Integral Relay: Capable of providing a direct signal to the elevator controller to initiate elevator recall.

2.6 GUARDS FOR PHYSICAL PROTECTION

A. Description: Welded wire mesh of size and shape for the manual station, smoke detector, gong, or other device requiring protection. 1. Factory fabricated and furnished by manufacturer of the device. 2. Finish: Paint of color to match the protected device.

B. Manual pull stations are to be provided with Stopper-II model STI-1100 devices.

2.7 WIRE AND CABLE

A. Wire and cable for fire alarm systems shall be UL listed and labeled as complying with NFPA 70, Article 760.

B. Connection between network control panels: Shall be a recognized network communication scheme and shall be wired in Class-A, Style-7 fashion.

C. Signaling Line Circuits: Twisted, shielded pair, not less than No. 16 AWG.

FIRE DETECTION AND ALARM 283100 - 6 DPS PUSH Academy Remodel – Phase 2

Page 76: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

1. Circuit Integrity Cable: Twisted shielded pair, NFPA 70 Article 760, Classification CI, for power-limited fire alarm signal service. UL listed as Type FPL, and complying with requirements in UL 1424 and in UL 2196 for a 2-hour rating.

2. Shall be wired in Class-B, Style-4 fashion.

D. Non-Power-Limited Circuits: Solid-copper conductors with 600-V rated, 75 deg C, color-coded insulation. 1. Low-Voltage Circuits: No. 16 AWG, minimum. 2. Line-Voltage Circuits: No. 12 AWG, minimum.

E. Notification Appliance Circuits: Shall be wired in Class-B, Style-Y fashion.

F. Initiating Device Circuits: Shall be wired in Class-B, Style-B fashion.

PART 3 - EXECUTION

3.1 EQUIPMENT INSTALLATION

A. Connecting to Existing Equipment: Verify that existing fire alarm system is operational before making changes or connections. 1. Connect new equipment to the existing control panel in the existing part of the building. 2. Connect new equipment to the existing monitoring equipment at the Supervising Station. 3. Expand, modify, and supplement the existing control equipment as necessary to extend

the existing control functions to the new points. New components shall be capable of merging with the existing configuration without degrading the performance of either system.

B. Smoke or Heat Detector Spacing: 1. Smooth ceiling spacing shall not exceed the rating of the detector. 2. Spacing of heat detectors for irregular areas, for irregular ceiling construction, and for

high ceiling areas, shall be determined according to Appendix A in NFPA 72. 3. Spacing of heat detectors shall be determined based on guidelines and recommendations

in NFPA 72.

C. HVAC: Locate detectors not closer than 3 feet (1 m) from air-supply diffuser or return-air opening.

D. Heat Detectors in Elevator Shafts: Coordinate temperature rating and location with sprinkler rating and location.

E. Remote Status and Alarm Indicators: Install near each smoke detector and each sprinkler water-flow switch and valve-tamper switch that is not readily visible from normal viewing position.

F. Audible Alarm-Indicating Devices: Install not less than 6 inches (150 mm) below the ceiling. Install bells and horns on flush-mounted back boxes with the device-operating mechanism concealed behind a grille.

G. Visible Alarm-Indicating Devices: Install adjacent to each alarm bell or alarm horn and at least 6 inches (150 mm) below the ceiling.

FIRE DETECTION AND ALARM 283100 - 7 DPS PUSH Academy Remodel – Phase 2

Page 77: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

H. Device Location-Indicating Lights: Locate in public space near the device they monitor.

I. FACP: Surface mount with tops of cabinets not more than 72 inches (1830 mm) above the finished floor.

J. Annunciator: Install with top of panel not more than 72 inches (1830 mm) above the finished floor.

K. Antenna for Radio Alarm Transmitter: Mount to building structure where indicated. Use mounting arrangement and substrate connection that will resist 100-mph (160-km/h) wind load with a 1.3 gust factor without damage.

3.2 WIRING INSTALLATION

A. Install wiring according to the following: 1. NECA 1. 2. TIA/EIA 568-A.

B. Wiring Method: Install wiring in metal raceway according to Division 26 Section "Raceway and Boxes for Electrical Systems." 1. Fire alarm circuits and equipment control wiring associated with the fire alarm system

shall be installed in a dedicated raceway system. This system shall not be used for any other wire or cable.

C. Wiring Method: 1. Cables and raceways used for fire alarm circuits, and equipment control wiring associated

with the fire alarm system, may not contain any other wire or cable. 2. Fire-Rated Cables: Use of 2-hour fire-rated fire alarm cables, NFPA 70 Types MI and

CI, is not permitted. 3. Signaling Line Circuits: Power-limited fire alarm cables shall not be installed in the

same cable or raceway as signaling line circuits.

D. Wiring within Enclosures: Separate power-limited and non-power-limited conductors as recommended by manufacturer. Install conductors parallel with or at right angles to sides and back of the enclosure. Bundle, lace, and train conductors to terminal points with no excess. Connect conductors that are terminated, spliced, or interrupted in any enclosure associated with the fire alarm system to terminal blocks. Mark each terminal according to the system's wiring diagrams. Make all connections with approved crimp-on terminal spade lugs, pressure-type terminal blocks, or plug connectors.

E. Cable Taps: Use numbered terminal strips in junction, pull, and outlet boxes, cabinets, or equipment enclosures where circuit connections are made.

F. Color-Coding: Color-code fire alarm conductors differently from the normal building power wiring. Use one color-code for alarm circuit wiring and a different color-code for supervisory circuits. Color-code audible alarm-indicating circuits differently from alarm-initiating circuits. Use different colors for visible alarm-indicating devices. Paint fire alarm system junction boxes and covers red.

FIRE DETECTION AND ALARM 283100 - 8 DPS PUSH Academy Remodel – Phase 2

Page 78: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

G. Risers: Install at least two vertical cable risers to serve the fire alarm system. Separate risers in close proximity to each other with a minimum 1-hour-rated wall, so the loss of one riser does not prevent the receipt or transmission of signals from other floors or zones.

H. Wiring to Remote Alarm Transmitting Device: 1-inch (25-mm) conduit between the FACP and the transmitter. Install number of conductors and electrical supervision for connecting wiring as needed to suit monitoring function.

3.3 IDENTIFICATION

A. Identify system components, wiring, cabling, and terminals according to Division 26 Section "Identification for Electrical Systems."

B. Install instructions frame in a location visible from the FACP.

C. Paint power-supply disconnect switch red and label "FIRE ALARM."

3.4 GROUNDING

A. Ground the FACP and associated circuits; comply with IEEE 1100. Install a ground wire from main service ground to the FACP.

3.5 FIELD QUALITY CONTROL

A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust field-assembled components and equipment installation, including connections, and to assist in field testing. Report results in writing.

B. Testing Agency: Owner will engage a qualified testing and inspecting agency to perform field tests and inspections and prepare test reports.

C. Testing Agency: Engage a qualified testing and inspecting agency to perform the following field tests and inspections and prepare test reports:

D. Perform the following field tests and inspections and prepare test reports: 1. Before requesting final approval of the installation, submit a written statement using the

form for Record of Completion shown in NFPA 72. 2. Perform each electrical test and visual and mechanical inspection listed in NFPA 72.

Certify compliance with test parameters. All tests shall be conducted under the direct supervision of a NICET technician certified under the Fire Alarm Systems program at Level III. a. Include the existing system in tests and inspections.

3. Visual Inspection: Conduct a visual inspection before any testing. Use as-built drawings and system documentation for the inspection. Identify improperly located, damaged, or nonfunctional equipment, and correct before beginning tests.

4. Testing: Follow procedure and record results complying with requirements in NFPA 72. a. Detectors that are outside their marked sensitivity range shall be replaced.

FIRE DETECTION AND ALARM 283100 - 9 DPS PUSH Academy Remodel – Phase 2

Page 79: Denver Public Schools INVITATION TO BID 14-MC-2308 ...purchasingts.dpsk12.org/bids/openbids/14-MC-2308 Addendum 2.pdf · THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME

5. Test and Inspection Records: Prepare according to NFPA 72, including demonstration of sequences of operation by using the matrix-style form in Appendix A in NFPA 70.

3.6 ADJUSTING

A. Occupancy Adjustments: When requested within 12 months of date of Substantial Completion, provide on-site assistance in adjusting system to suit actual occupied conditions. Provide up to two visits to Project outside normal occupancy hours for this purpose.

B. Follow-Up Tests and Inspections: After date of Substantial Completion, test the fire alarm system complying with testing and visual inspection requirements in NFPA 72. Perform tests and inspections listed for three monthly, and one quarterly, periods.

C. Semiannual Test and Inspection: Six months after date of Substantial Completion, test the fire alarm system complying with the testing and visual inspection requirements in NFPA 72. Perform tests and inspections listed for monthly, quarterly, and semiannual periods. Use forms developed for initial tests and inspections.

D. Annual Test and Inspection: One year after date of Substantial Completion, test the fire alarm system complying with the testing and visual inspection requirements in NFPA 72. Perform tests and inspections listed for monthly, quarterly, semiannual, and annual periods. Use forms developed for initial tests and inspections.

3.7 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain the fire alarm system, appliances, and devices. Refer to Division 01 Section "Demonstration and Training."

END OF SECTION 283100

FIRE DETECTION AND ALARM 283100 - 10 DPS PUSH Academy Remodel – Phase 2