demand for and sale of power

34
1 A Presentation on ARR & Tariff Proposal of GRIDCO for FY 2008-09 Analysis/Objections/Suggestions February 7, 2008 By Dr. Shibalal Meher (Consumer Counsel) Nabakrushna Choudhury Centre for Development Studies, Bhubaneswar

Upload: felicia-munoz

Post on 30-Dec-2015

25 views

Category:

Documents


2 download

DESCRIPTION

A Presentation on ARR & Tariff Proposal of GRIDCO for FY 2008-09 Analysis/Objections/Suggestions February 7, 2008 By Dr. Shibalal Meher (Consumer Counsel) Nabakrushna Choudhury Centre for Development Studies, Bhubaneswar. Demand for and Sale of Power. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Demand for and Sale of Power

1

APresentation

onARR & Tariff Proposal of GRIDCO for

FY 2008-09Analysis/Objections/Suggestions

February 7, 2008By

Dr. Shibalal Meher(Consumer Counsel)

Nabakrushna Choudhury Centre for Development Studies, Bhubaneswar

Page 2: Demand for and Sale of Power

2

Demand for and Sale of Power• GRIDCO has filed ARR & Price application for 2007-08 for its

bulk supply activity.

• GRIDCO and DISTCOs have furnished the following projections regarding demand and sale of power:

OERC Approval 2007-08

GRIDCO projection 2008-09

SMD (MVA) 2634.53 2721.67

Sale to DISTCOs 16653.00 18144.00

Sale to CGPs 10.00 10.00

Total Sale (DISTCOs + CGPs) MU

16663.00 18154.00

Page 3: Demand for and Sale of Power

3

Distco-wise Demand for and Sale of Power

• Distco-wise breakup of demand for and sale of power as projected by Distcos and Gridco are furnished in the table below:

SMD (MVA) Sales to DISTCOs (MU)Distcos Projection

Gridco’s Projection

Distcos

Projection

Gridco’s Projection

CESU - 834.69 - 5760NESCO 724 724 - 4730WESCO 900 837.98 - 5627SOUTHCO 325 325 - 2027All Distcos 1949 2721.67 - 18144

Page 4: Demand for and Sale of Power

4

Transmission Loss and Power Procurement

• GRIDCO projects transmission loss of 5.00% for 2008-09. • A total energy procurement of 19110 MU for the ensuing

year has been considered.• Total power purchase and the costs thereof have been

projected as follows:

Year OERC Approval (2007-08)

GRIDCO’s Proposal

(2008-09)

Power Purchase (MU) 17539.47 19110

Power Purchase Costs (Rs. Crore)

2103.11 2577.68

Page 5: Demand for and Sale of Power

5

Analysis of the Proposal

Page 6: Demand for and Sale of Power

6

Revenue Gap of GRIDCO during 2008-09 (Rs in Crore)

2008-09

Proposal

Revenue requirement including return on equity during 2008-09

2816.04

Pass through Expenses 532.80

Total Revenue Requirement 3348.84

Revenue receipts from sale of power to DISTCOs 2439.18

Misc. Receipts 3.30

Total Revenue Receipts 2442.48

Revenue Gap 906.36

Page 7: Demand for and Sale of Power

7

Annual Revenue Requirement for FY 2008-09 (Rs Crore)

OERC approval 2007-08

GRIDCO proposal 2008-09

Power procurement cost 2103.11 2577.68

Interest Cost 158.12 169.79

Other costs (Employee, A&G expenses, R&M expenses, ERLDC & NLDC charges)

5.09 7.95

Return on equity 0.00 60.62

Pass through of past losses 644.38 532.80

Gross Revenue Requirement 2910.70 3348.84

Page 8: Demand for and Sale of Power

8

Proposed power procurement cost during FY 2008-09

Generators Energy (MU)

Rate (P/U) Total Cost (Rs crore)

State Hydro 5955.75 51.29 305.45

State Thermal 7026.94 154.90 1088.44

Total State 12982.69 107.37 1393.89

Central Sector 6127.36 193.20 1183.79

Total procurement

19110.05 134.89 2577.68

Page 9: Demand for and Sale of Power

9

Tariff Proposal for 2008-09

Energy charge (P/U)

Energy charge during 2007-08

135.66

Energy charge proposed for 2008-09

184.39

% rise over current energy charge

36.00

Page 10: Demand for and Sale of Power

10

GRIDCO’s Proposal to meet TRR of Rs 3085.95 Crore.

• Hike in average energy charge from 135.66 P/U to 184.39 P/U

Page 11: Demand for and Sale of Power

11

Deficit Reduction

• GRIDCO has included past losses of Rs 532.80 Crore for calculation of average energy charge. This may not be considered.

• While calculating power procurement cost GRIDCO has considered the hike in tariff proposed by OHPC, which the Commission has not approved so far.

Page 12: Demand for and Sale of Power

Difference in Power Procurement Cost between existing rate and proposed rate

Energy (MU)

Existing rate (P/U) Proposed rate (P/U) Difference in cost (Rs Cr)

Rate P/U

Cost (Rs Cr)

Rate P/U

Cost (Rs Cr)

HPS 1037.75 54.79 56.86 58.07 60.26 3.37BHEP 1168.20 53.52 62.52 57.01 66.60 4.08RHEP 693 35.17 24.37 62.06 43.01 18.64UKHEP 829.62 21.24 17.62 40.39 33.51 15.89UIHEP 1962.18 67.16 131.78 67.81 133.06 1.28Total 5690.75 293.15 336.44 43.29

Page 13: Demand for and Sale of Power

13

Deficit Reduction (Contd…)

• While calculating the sale of energy GRIDCO has made its own projection of demand from DISTCOs, while DISTCOs have shown different projections.

Page 14: Demand for and Sale of Power

Gap in Projection of demand by DISTCOs and GRIDCO

Projection submitted by DISTCOs to OERC (MU)

Projection of demand from DISTCOs by GRIDCO (MU)

Gap in demand submitted by DISTCOs to OERC and projected by GRIDCO (MU)

CESU 5742.69 5760 17.31

WESCO 5756.00 5627 -129.00

NESCO 4659.50 4730 70.50

SOUTHCO 1980.00 2027 47.00

Total 18138.19 18144 5.81

Page 15: Demand for and Sale of Power

15

Deficit Reduction (Contd…)

• GRIDCO has predicted existing transmission loss of 5%, though the Kanungo Committee had recommended step wise reduction of transmission loss.

Page 16: Demand for and Sale of Power

16

Deficit Reduction (Contd…)

• Reduction in fixed cost

– Employee cost

– A & G Cost

• Non allowing of Reasonable Return

Page 17: Demand for and Sale of Power

17

BROAD TARIFF RELATED BROAD TARIFF RELATED ISSUES RAISED BY ISSUES RAISED BY

OBJECTORS OBJECTORS (To be addressed by GRIDCO)(To be addressed by GRIDCO)

Page 18: Demand for and Sale of Power

18

• Legal IssuesThe ARR application filed by GRIDCO is not tenable under law due to the following defects:– The application so filed by the GRIDCO, who is neither a licensee

nor a trader and is not bonafide and tenable under law as such the same is liable to be rejected.

– The ARR application filed by GRIDCO for determination of price is not tenable as the Commission has no authority under law and more particularly u/s 62 of E. Act, 03, to determine tariff on the application of a non-licensee, i.e. GRIDCO.

– Functioning of GRIDCO as company is unnecessary to act as middle man between the generating licensee and distribution licensees that too in the absence of competition.

– The GRIDCO account has not been audited for the financial year 2005-06 & 2006-07.

Issues emerge from the objections/ suggestions submitted by the Objectors

Page 19: Demand for and Sale of Power

19

Issues emerge from the objections (Contd..)

– GRIDCO has filed the application to confuse the consumer public without disclosing the purpose for such filing.

– Notice so published inviting objections does not confirm to the requirements.

– The procedure/method adopted by the Commission should be simple and inexpensive to enable the public to participate.

– The Commission may kindly examine whether GRIDCO has compiled with the directions, conditions of licensee etc. issued by the Commission.

Page 20: Demand for and Sale of Power

20

• SD & Energy Drawl– GRIDCO should submit the data relating to the

maximum and minimum draw down levels of the hydro reservoirs from 1.11.2006 to 1.11.2007 along with the month wise generation.

– It is not clear how and what distribution losses are considered by GRIDCO while projecting the power demand of the distribution companies for consumers and procurement from generating stations.

– The simultaneous power demand projected by GRIDCO for FY 2008-09 may be accepted. But this demand is because of higher distribution loss in various DISTCOs.

Issues emerge from the objections (Contd..)

Page 21: Demand for and Sale of Power

21

• Energy Availability and Procurement– GRIDCO has not independently assessed the

availability of hydropower during 2007-08 but has merely accepted the data submitted by the OHPC based on design energy.

– The availability of power from hydel stations should be considered on the basis of the reservoir levels of the hydel stations in the current year, generation in the first seventh months of FY08 and past trends.

– For thermal stations, the PLF achieved in the first seven months and previous year should be taken into account for estimation of availability of power.

– It is estimated by some objectors that the total availability of power would be 21100 MU during FY 2008-09 instead of 19110 MU projected by GRIDCO.

Issues emerge from the objections (Contd..)

Page 22: Demand for and Sale of Power

22

– Another objector has projected total availability as 21790 MU, with Hydro availability7360 MU, total state availability 14690 MU and central power availability 6100 MU.

– Power availability may be considered on design energy or based on actual performance for a number of years with additional capacities built up during 2007-08.

– The projections given by state generating stations, both OHPC and OPGC, on the generation capacities and tariffs are not matching with the projections given by GRIDCO.

– Hydro availability for FY 2008-09 can be taken as 7360 MU due to better hydrological condition.

– GRIDCO should schedule for higher energy availability from OHPC through suitable incentives in PPAs. Higher availability from central thermal stations at about 90% PLF during off peak hours be purchased to create a surplus by closure of hydro generation.

Issues emerge from the objections (Contd..)

Page 23: Demand for and Sale of Power

23

• Transmission loss– A transmission loss of only 4% on the OPTCL transmission line

should be allowed.– All the central generation is availed through central transmission

system at the load center after accounting 3.62% as central transmission loss. This itself is very high subject to prudent check by GRIDCO. This central transmission loss when accounted for power drawl should reduce OPTCL transmission loss.

• Power Procurement cost– According to the PPA, GRIDCO can verify the data submitted by

the Generators. It should confirm whether the fuel cost and the FPA have been verified in relation to at least TTPS & TSTPS.

– The higher cost of power from OHPC stations is considered based on the higher ARR. The ARR of different stations would be lower than as projected.

Issues emerge from the objections (Contd..)

Page 24: Demand for and Sale of Power

24

– The fixed cost of OPGC was allowed in the GRIDCO ARR based on the previous year tariff of OPGC. As per practice, the fixed cost element ought to reduce in subsequent year due to repayment of principal loan, which offset any increase in O&M in each year. The fixed cost of OPGC may therefore be estimated for FY 2008-09 separately without considering the figure of FY 2006-07, as there would be a substantial reduction of fixed cost on account of depreciation and interest on loan notwithstanding the nominal increase in O&M expenses.

– GRIDCO may be directed to submit the details of the reduction in fixed costs for CGSs for the years 2001-02 to 2006-07, which may be taken into account for fixation of tariff for FY 2008-09.

– GRIDCO has computed the variable charges for OPGC, TTPS, TSTPS, FSPTS, KHSTPS in the absence of latest CERC approvals. However, the FPA allowed earlier is in excess of the actual and the same should be trued up.

Issues emerge from the objections (Contd..)

Page 25: Demand for and Sale of Power

25

– GRIDCO may be directed to furnish evidential documents for the PGCIL Transmission charges along with the corresponding CERC norms pertaining to tariff approved for the various transmission links. The incentive should be allowed to the extent of payments made.

– Hon’ble Commission may strictly scrutinize the Power Cost projected by the state generating stations and allow the procurement from central power stations on merit order to meet the power requirement of the state for GRIDCO, which becomes a major part of the Bulk Supply Price.

Issues emerge from the objections (Contd..)

Page 26: Demand for and Sale of Power

26

• Employee cost– The employee cost projected for FY 2008-09 is on the

higher side and needs a detailed scrutiny by the Hon’ble Commission. With 6% escalation it will be Rs 2.15 crore.

• A & G Cost– With 5.2% escalation per year under this head as

permitted by the Hon’ble Commission, the A&G cost should be Rs 1.83 crore for FY 2008-09.

• R&M Cost– No amount should be allowed under this head, as the

Hon’ble Commission had not permitted any amount during last two years.

Issues emerge from the objections (Contd..)

Page 27: Demand for and Sale of Power

27

• Interest on long-term liabilities– The interest cost may not be recovered through the Bulk Supply

Price.– While carrying the truing up exercise of the interest cost of

GRIDCO, the incentive received in cash or adjusted with GRIDCO dues under one time settlement scheme from 1.10.2001 to 30.9.2007 may be allowed in the best interests of passed on to the consumers of Orissa.

– The interest recoverable from DISTCOs, as claimed by GRIDCO need to be considered as income in the ARR of GRIDCO.

– The interest waiver amounting Rs 91.50 crore is required to be considered as income in the ARR of GRIDCO.

– While all the interest cost of GRIDCO on the securitised amount is pass through in the BSP, the DPS amount reveivable from DISTCOs as per the OERC order should be treated as income in the ARR of GRIDCO.

– Re-phasing of the loans by GRIDCO for a longer time, the interest on the same may be allowed in the ARR of GRIDCO.

Issues emerge from the objections (Contd..)

Page 28: Demand for and Sale of Power

28

• ERLDC/NLDC Fees– The Commission may allow the same amount of Rs

1.32 crore for 2008-09.• Return on Equity

– No amount should be allowed under this head, as the Hon’ble Commission had not permitted any return on equity as per Govt. of Orissa notification dated 29.1.2003.

• Pass through of Previous Loss– GRIDCO proposes to pass through of a substantial

amount of past losses, which are mostly on account of its inefficient operation and are therefore not payable.

– The proposal of pass through needs to be justified on consideration of prudence after going through the process of public hearing.

Issues emerge from the objections (Contd..)

Page 29: Demand for and Sale of Power

29

• Sales Projection– Projection of energy requirement made by DISTCOs is based on

the ground realities and more than that projected by GRIDCO.

• Misc. Receipts– GRIDCO may recover the receivables from the DISTCOs and

other beneficiaries through escrow mechanism and pass on such collection to the state govt. The actual collection may be furnished by GRIDCO.

– GRIDCO should indicate the action being taken to recover the arrear dues from DISTCOs.

– GRIDCO may be asked to indicate the amount collected during 2006-07, estimated to collect during 2007-08 and proposal for 2008-09.

• Non-accounting of Revenue Receipts– The earnings from trading of surplus energy needs to be

considered in the ARR of GRIDCO.

Issues emerge from the objections (Contd..)

Page 30: Demand for and Sale of Power

30

• Over drawl Charges– Only the incremental cost for additional generation may be

approved for billing in case there is a over drawl by any DISTCOs over and above the quantum fixed by OERC as the entire fixed cost is taken while computation of power purchase cost of GRIDCO which is to be recovered from DISTCOs.

• Rebate– Approval for the rebate of 2% to NESCO for prompt payment of

BST bills within three working days excluding Sunday and holidays as per Negotiable Instrument Act from the date of payment of the BST bill.

• BST– GRIDCO has proposed steep increase in BST, in spite of the large

increase in BSP for the FY 2007-08.– Hon’ble Commission may reduce the Bulk Supply Price and pass

on the benefit of the reforms to the consumers by reduction of RST.

Issues emerge from the objections (Contd..)

Page 31: Demand for and Sale of Power

31

• Export of Power– Even though the OERC order dated 23.3.06 shows that

there is nil export to outside state, there was heavy export. GRIDCO may submit the actual earnings from export of power and U.I. charges separately for FY 2005-06, 2006-07, and April 2007 to Sept 2007.

• Two-Part Tariff– GRIDCO should submit a proposal for bulk supply

price consisting of Demand Charges and Energy Charges.

• Metering– There are number of meters recording input to the

system from generators including central generators and output for sale to the DISTCOs and export to other states. OERC may like to test check few of the meters by independent inspectors.

Issues emerge from the objections (Contd..)

Page 32: Demand for and Sale of Power

32

• General– GRIDCO has not taken adequate steps for early disposal of the

OPGC case in the Supreme Court. It may submit copy of the petition filed before the Supreme Court.

– GRIDCO should make early clearance of feasibility reports/detailed report/power purchase agreements for the small hydro power projects.

– Neither the past liabilities can be transferred to GRIDCO nor the past losses can be recovered by GRIDCO. It is only entitled to recover the cost of procurement of power and trading margin less misc. revenue on account of earnings from export and U.I. charges.

– As per OERC order GRIDCO had to reach a target of generation from Renewable source for 200 MU for 2006-07 and 5% of total generation in 2007-08. GRIDCO has not spelled out whether the targets for both these years have been achieved.

Issues emerge from the objections (Contd..)

Page 33: Demand for and Sale of Power

33

– Any of the existing substations have reached their loading capacities and the developers are unable to plan the connectivity without a firm programme of GRIDCO for the point of interconnection.

– Quite often GRIDCO is advising the consumers to install their own captive stations, even though it has surplus power situation. GRIDCO will be loosing if steps are not taken for coordinating with appropriate agency for augmentation of generation capacity.

– The licensee has acted without any authority of law and in violation of the earlier orders of Commission, by manipulating the accounts, making unjust and undue again, and draining out/diverting the funds showing it has bad debts, licensee is going to burdening the consumers as such the application should be rejected.

Issues emerge from the objections (Contd..)

Page 34: Demand for and Sale of Power

34