Delivering Safe Projects IRSE Technical Conference Andy Webb MIRSE | Head of Strategic Projects 20 March 2015

Upload: others

Post on 17-Jun-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Delivering Safe Projects IRSE Technical Conference Andy Webb MIRSE | Head of Strategic Projects

20 March 2015

Page 2: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

2

Contents

> Introduction to the Office of

the National Rail Safety

Regulator

− coverage

− organisation

− function

> Introduction to ONRSR’s

Major Project Guideline

− published at www.onrsr.com.au

Page 3: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

3

ONRSR: key facts

> commenced on 20 Jan 2013

> an independent authority

> funded by industry and

government

> WA anticipated June 2015

> Head Office: Adelaide

> Central Branch: SA, TAS, NT, ACT

> NSW Branch

> Victorian Branch

ONRSR Office

ONRSR regulatory oversight of railway operations

Map Source: PowerPoint Toolkit, http://ppt-

toolkit.com

Page 4: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

4

ONRSR: organisation overview

Sue McCarrey

Chief Executive

Executive Director,

National Operations

Executive Director,

Policy, Comms &

Planning

Executive Director,

Technical

• Engineering

• Strategic Projects

• National

Investigations

• Learning &

Development

• Central Branch

• NSW Branch

• Vic Branch

• Safety & Risk

• National Operations

• Policy & Strategy

• National

Communications

• Planning &

Reporting

Page 5: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

5

ONRSR: key functions

• administer, audit and review the accreditation

regime under the Rail Safety National Law

(RSNL) and Regulations

• work with rail transport operators, rail safety

workers and others involved in railway

operations to improve rail safety nationally

• conduct research, collect and publish

information relating to rail safety

Page 6: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

6

ONRSR: key functions

• provide, or facilitate the provision of, advice,

education and training in relation to rail safety

• monitor, investigate and enforce compliance

with the RSNL

• engage in, promote and coordinate the

sharing of information to achieve the objects of

the RSNL

Page 7: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

7

Major Project Guideline

Background Structure &

Content Next Steps

Page 8: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

8

Background: context

> Major projects are complex, typically:

− multi-disciplinary activity

− use of novel technology

− significant change

> No standard delivery structure

− many models can be used

> Growing need to document ONRSR’s minimum

expectations

Page 9: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

9

Background: delivering safe projects

Major projects develop with

insufficient safety management

leading to delay in gaining safety

accreditation

Multiple entities developing major

projects results in unclear safety

responsibilities leading to delay in

gaining safety accreditation

Major projects do not consider

ops & mtce safety risks resulting

in inappropriate solutions leading

to delay in gaining safety

accreditation

Delivery risks

Document safety roles and

responsibilities

Early engagement: ONRSR /

government / industry

Document accreditation

strategy

Early identification of railway

transport operator that

manages O&M risks

Plan for safety assurance;

manage safety risks from the

start

Industry controls

Page 10: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

10

Background: challenges

> ensuring the concept design minimises macro risk

> identification of the accredited party(s)

> demonstration of effective management & control:

− to ensure safety risk is managed

> assuring safe outcomes:

− confidence that safety risk managed appropriately for the

complexity of the project

− the project has the competence and capacity to manage safety

risk.

Page 11: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

11

Background: key risks

> Lack of effective safety management due to:

− poor safety leadership

− multiple entities having control throughout the project lifecycle

− commercial pressures taking precedence.

> Assuring safe outcomes

− safety requirements inadequate

− project scope inadequately addresses safety improvement

− developed design inadequate for safe outcomes

− constructed assets inadequate for safe outcomes

− lack of industry understanding on ONRSR expectations.

Page 12: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

12

Major Project Guideline

Background Structure &

Content Next Steps

Page 13: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

13

Guideline: structure

Major Project Guideline

Effective Management &

Control

Safety roles & responsibilities

Accreditation Planning

Common Safety Approach

O & M Requirements

Safety Assurance

minimum requirements for major projects

by agreement

Page 14: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

14

Guideline: structure

Major Project Guideline

Effective Management &

Control

Safety Assurance

Planning safety assurance

ISA

System safety

Quantitative techniques

HF integration

Standards

Level crossings

minimum requirements for major projects

by agreement

Page 15: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

15

Major Project Guideline

Background Structure &

Content Next Steps

Page 16: Delivering Safe Projects - Office of the National Rail ... · 3/20/2015  · Office of the National Rail Safety Regulator 10 Background: challenges > ensuring the concept design minimises

Office of the National Rail Safety Regulator

16

Next Steps

Published (Dec 2014)

Communication with industry (2015)

Application with industry (2015)