del him undr a pipeline project

41
Detailed Report on Delhi-Mundra Pipeline Project Document is made available by http://www.infraline.com 1 Detailed Report on Delhi-Mundra Pipeline Project 1.0 Project Description M/s Hindustan Petroleum Corporation Limited (HPCL) proposes to lay a cross country multi- product pipeline from their proposed storage terminal in Mundra in Gujarat state to Bahadurgarh in Haryana (near New Delhi) for transporting POL products namely Motor Spirit (MS), Ultra Low Sulphur MS (ULMS), High Speed Diesel (HSD), Ultra Low Sulphur HSD (ULHSD) and Superior Kerosene Oil (SKO). The design capacity of the pipeline shall be 5.0 MMTPA in Phase-I & 5.8 MMTPA in Phase-II. The tap-off points for marketing installation are proposed at Palanpur, Ajmer, Jaipur, Rewari and Bahadurgarh. New marketing installations are proposed to be constructed separately by HPCL at 4 locations viz. Palanpur, Ajmer, Jaipur with road loading facilities and Bahadurgarh with Rail/Road loading facilities. At Rewari, the existing installation is proposed to be used. The above project requirements are proposed to be met by laying: 1. Mainline: A cross country main pipeline of 1036.4 km long (approx) from HPCL's proposed storage terminal at Mundra to Bahadurgarh with Tap-off points for Marketing Terminals at Palanpur, Ajmer, Jaipur, Rewari & Bahadurgarh. 2. Optional feeder line: Optional feeder line from Petronet VKPL's landfall point at Luni joining Mundra Palanpur pipeline section at Chhasra of approximately 8.5 kms length in the state of Gujarat. 3. Spur Lines: Three spur lines from Bahadurgarh to Tikrikalan in Delhi (Industry's resitement location from Shakurbasti in Delhi) of approximately 12.0 kms for ULMS, ULHSD & SKO each designed to meet the projected throughput of 0,75 MMTPA in Phase-II (of year 2016-2017). 1.1 Project Highlights The salient features of the proposed Mundra-Delhi petroleum product pipeline has been summarized in Table-1.1.1 below. Table -1.1.1 Salient Features of the Pipelines Name Mudra-Delhi Pipeline Transport material MS, ULMS, HSD, ULHSD & SKO Pipeline length Mainline:1036.4 km, Feeder Line:8.5km, Spur Lines:12Kms Take-off point Main Line: Proposed Mundra Originating Terminal in Gujarat (km 0.0, 4.8m AMSL) Feeder Line : Optionally Luni (Petronet VKPL's intermediate landfall point) (km 0.0) Spur Lines: Proposed Bahadurgarh Terminal (km 0.0, 220m AMSL) Terminal point Bahadurgarh Terminal in Haryana (km 1036.4) for main line. Chhasra for feeder line (8.5kms) &Tikrikalan for Spur lines (12 kms)

Upload: anujorss

Post on 27-Nov-2014

131 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 1

DDeettaaiilleedd RReeppoorrtt oonn DDeellhhii--MMuunnddrraa PPiippeelliinnee PPrroojjeecctt

1.0 Project Description

M/s Hindustan Petroleum Corporation Limited (HPCL) proposes to lay a cross country multi-product pipeline from their proposed storage terminal in Mundra in Gujarat state to Bahadurgarh in Haryana (near New Delhi) for transporting POL products namely Motor Spirit (MS), Ultra Low Sulphur MS (ULMS), High Speed Diesel (HSD), Ultra Low Sulphur HSD (ULHSD) and Superior Kerosene Oil (SKO). The design capacity of the pipeline shall be 5.0 MMTPA in Phase-I & 5.8 MMTPA in Phase-II.

The tap-off points for marketing installation are proposed at Palanpur, Ajmer, Jaipur, Rewari and Bahadurgarh. New marketing installations are proposed to be constructed separately by HPCL at 4 locations viz. Palanpur, Ajmer, Jaipur with road loading facilities and Bahadurgarh with Rail/Road loading facilities. At Rewari, the existing installation is proposed to be used.

The above project requirements are proposed to be met by laying:

1. Mainline: A cross country main pipeline of 1036.4 km long (approx) from HPCL's proposed storage terminal at Mundra to Bahadurgarh with Tap-off points for Marketing Terminals at Palanpur, Ajmer, Jaipur, Rewari & Bahadurgarh.

2. Optional feeder line: Optional feeder line from Petronet VKPL's landfall point at Luni joining Mundra Palanpur pipeline section at Chhasra of approximately 8.5 kms length in the state of Gujarat.

3. Spur Lines: Three spur lines from Bahadurgarh to Tikrikalan in Delhi (Industry's resitement location from Shakurbasti in Delhi) of approximately 12.0 kms for ULMS, ULHSD & SKO each designed to meet the projected throughput of 0,75 MMTPA in Phase-II (of year 2016-2017).

1.1 Project Highlights

The salient features of the proposed Mundra-Delhi petroleum product pipeline has been summarized in Table-1.1.1 below.

Table -1.1.1 Salient Features of the Pipelines

Name Mudra-Delhi Pipeline Transport material MS, ULMS, HSD, ULHSD & SKO Pipeline length Mainline:1036.4 km, Feeder Line:8.5km, Spur Lines:12Kms Take-off point Main Line: Proposed Mundra Originating Terminal in Gujarat (km 0.0,

4.8m AMSL) Feeder Line : Optionally Luni (Petronet VKPL's intermediate landfallpoint) (km 0.0) Spur Lines: Proposed Bahadurgarh Terminal (km 0.0, 220m AMSL)

Terminal point Bahadurgarh Terminal in Haryana (km 1036.4) for main line. Chhasrafor feeder line (8.5kms) &Tikrikalan for Spur lines (12 kms)

Page 2: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 2

ROW 18m Intermediate Pumping Station

Santalpur, Palanpur, Awa, Ajmer & Jaipur (In Phase I) Bhachau,Pindwara & Rewari (In Phase II)

Marketing Terminals Mundra, Palanpur, Ajmer, Jaipur, Rewari (existing) & Bahadurgarh State en-route Gujarat, Rajasthan, Haryana & Delhi Districts en-route 12 districts en-route: Kutch, Banaskantha & Patan districs in Gujarat,

Sirohi, Pali, Ajmer, Jaipur & Alwar in Rajasthan, and Rewari, Gurgaon& Jhajjar in Haryana & New Delhi

River Crossing 12 river crossings having more than 100m width (Important are Banas,Mithri, Sukri, and, Modiya & Raipur Luni)

Road/rail crossing 17 NH crossings, 26 SH crossings & 16 railway crossings.

Summary Details of various Pipeline/Terminal facilities proposed to be created at important main locations are detailed in Table 1.1.2.

Table - 1.1.2 Station Details

Location Station Type Facilities proposed Ch. (km)

Mudra Mundra Despatch Station+ Storage Terminal

Receipt facilities from Jetty to Terminal, Mainpump station, Storage Tank facility and PIGlauncher will be provided. Pump station andstorage tanks will be within HPCL;s Mundra-Bhatinda Pipeline Crude Oil Terminalpremises.

0.0

Chhasra/(Luni) Meeting point of PetronetVKPL's land fall point atLuni on Mainline fromMudra

PIG (scrapper) receiving facilities, meteringfacilities, Isolation valves.

At Luni, exchange point of PVKPL (Ch. 0.0 ofoptional feeder line), Isolation valves, PigLaunching facility

20.5

Bhachau Intermediate PumpingStation (Phase - II)

Pumping facilities in Phase - II 90.0

Santalpur Intermediate PumpingStation

Pump station and Pigging facility 198.0

Palanpur Intermediate Tap off cumBooster Pumping Station +Marketing Terminal

Pump station, Storage tanks for tap off, TankTruck loading facility & Pigging facility,Metering, Sump tank, Slop tank.

329.5

Pindwara Intermediate PumpingStation (Phase - II)

Pumping facilities in Phase - II 430.0

Awa Intermediate BoosterPumping Station.

Pump station and Pigging facility 539.9

Ajmer Intermediate Tap Off cumBooster Pumping Station +Marketing Terminal

Pump station, storage tanks for tap off, TankTruck loading facility & Pigging facility,Metering, Sump tank, Slop tank.

667.5

Jaipur Intermediate Tap Off cum Pump station, Storage tanks for tap off, Tank 778.9

Page 3: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 3

Booster Pumping Station +Marketing Terminal

Truck loading facility & Pigging facility,Meeting, Sump tank, Slop tank.

Rewari Intermediate Tap OffStation + ExistingTerminal

Storage tanks for tap off, Tank Truck loadingfacility & Pigging facility, Metering, Sumptank, Slop tank, etc. Existing storage tankfacility and T/T gantry at HPC Rewari will beutilized. Intermediate Pumping facilities inPhase - II

965.1

Bahadurgarh Terminal Delivery + Marketing Terminal

Storage tanks, Tank Truck and Tank Wagonloading facility & Pigging facility, Metering,Sump tank, Slop tank.

1036.4

Bahadurgarh Originating PumpingStation

Pump station, Storage Tank facility and PIGlauncher will be provided.

0.0

* Existing Terminal

Project Costs: The estimated total capital cost for the project based on Phase - I (Year 2011-12) is estimated at Rs.1197.08 crores for Mundra-Bahadurgarh pipeline, Rs.33.42 crors for the three Bahadurgarh-Tikrikalan spur pipelines, Rs.19.74 Crores for optional feeder line from Petronet VKPL landfall point at Luni to Chasra and Rs.304.34 Crores for the Storage/Marketing Terminals. District wise distribution of the estimated project cost for Main Pipeline, Spur Pipelines & Terminals is detailed in Table - 1.1.3.

Table 1.1.3 District wise Project Cost

State District Project Cost (Rs. Crores)

Kutch 315 Patan 124

Gujarat

Banaskantha 164 Sirohi 60 Pali 226 Ajmer 136 Jaipur 237

Rajasthan

Alwar 32 Rewari 42 Gurgaon 18 Jhajjar 174

Haryana

Delhi 8 Total 1,535

Project Schedule: The proposed project facilities for Phase-I are expected to be completed in 36 months (mechanical completion) from the formal announcement by MOP&NG (11-05-04) i.e May'07.

Page 4: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 4

1.2 Details of Pipeline Route & Terminal Locations

1.2.1 Pipeline Route Description

The pipeline takes off from proposed HPCL Mundra terminal located 4 km South-West of Mundra town (km 0.0, 4.8m AMSL) in Gujarat and terminates at proposed HPCL terminal at Bahadurgarh in Haryana (Near Delhi), near existing HPCL LPG plant, which is located near Asaudah Sewan railway station (km 1036.4, 220m AMSL). at Bahadurgarh. Between take off KP 0.000 near Mundra and KP 243.300 near Radhanpur the proposed Mundra-Delhi pipeline will be laid in common ROU with in the ROU of proposed GGSRL Mundra-Bhatinda crude oil pipeline route.

En-route it passes through Santalpur (Booster Station), Palanpur (Tap-off cum Booster Station), Awa (Booster Station), Ajmer (Tap-off cum Booster Station), Jaipur (Tap-off cum Booster Station) and Rewari (Tap-6ff in Phase-I & Tap-off cum Booster Station in Phase-II). An optional feeder line is proposed from Petronet VKPL's landfall point at Luni, which will join Mundra-Palanpur pipeline section at Chhasra in the state of Gujarat. Three spur lines are proposed from Bahadurgarh to HPCL's proposed Marketing installation at Tikrikalan (in Delhi).

1.2.2 Geographical Location

Geographical locations of Take-off, Intermediate Pumping Stations, Intermediate Terminals and End Terminal are given in Table-1.2.2.

Table-1.2.2 Geographical Locations of Various Stations of the Pipeline

Stations Ch. (KP) RL (m) Lat (N) Long (E) Village District State

Mundra Take Off Terminal 0/0 4.8 22o 48' 69o 41' Dhrab Kutch Gujarat

Santalpur IPS 198/0 18 23o 46' 71o 11' Santalpur Patan Gujarat Palanpur Terminal + IPS 329/5 190 24o 12' 71o 21' Chadotar Banaskantha Gujarat

Awa IPS 539/9 300 25o 38' 73o 41' Makam Sing Ka Gurha Pali Rajasthan

Ajmer Terminal + IPS 667/5 460 26o 20' 74o 34' Saradhana Ajmer Rajasthan

Jaipur Terminal + IPS 778/9 350 26o 50' 75o 35'

Dhami Khurd/Dhami Kalan

Jaipur Rajasthan

Rewari Terminal* 965/1 254 28o 08' 76o 36' Karnawas Rewari Haryana Bahadurgarh Terminal 1036/4 220 28o 43' 76o 51' Asaudah Jhajjar Haryana

* Existing Terminal

1.2.3 Administrative Jurisdiction

Page 5: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 5

HPCL Mundra-Delhi main pipeline route between KP 0.0 and KP 1036/4 passes through the districts of Kutch, Patan & Banaskantha in Gujarat state, covering a length of 374.2 km, then through the districts of Sirohi, Pari, Ajmer, Jaipur & Alwar in Rajasthan state, covering a length of 576.0 kms, and then 86.2 kms through the districts of Rewari, Gurgaon and Jhajjar in Haryana state. The details of administrative jurisdiction for Mainline, optional feeder line and Spur lines are tabulated in Table-1.2.3 & 1.2.4.

Table - 1.2.3 Administrative Jurisdiction of the Pipeline Route in Details

Chain age (KP) Length Pipeline Sl. No.From TO Length (km)

District State

1 0/0 172/5 172.5 Kutch 2 172/5 254/05 81.55 Patan Gujarat 3 254/05 279/8 25.75 Banas Kantha Gujarat 4 279/8 282/3 2.5 Patan Gujarat 5 282/3 298/0 15.7 Banas Kantha Gujarat 6 298/0 310/8 12.8 Patan Gujarat 7 310/8 374/2 63.4 Banas Kantha Gujarat 8 374/2 438/55 64.35 Sirohi Rajasthan 9 438/55 644/95 206.4 Pali Rajasthan

10 644/95 726/45 81.5 Ajmer Rajasthan 11 726/45 914/15 187.7 Jaipur Rajasthan 12 914/15 914/96 0.45 Alwar Rajasthan 13 914/6 915/95 1.35 Jaipur Rajasthan 14 915/95 949/3 33.35 Alwar Rajasthan 15 949/3 951/0 1.7 Rewari Rajasthan 16 951/0 951/9 0.9 Alwar Rajasthan 17 951/9 982/15 30.25 Rewari Haryana 18 982/15 993/15 11.0 Gurgaon Haryana 19 993/15 996/95 3.8 Jajjar Haryana 20 996/95 1005/25 8.3 Gurgaon Haryana

Main Line (Mundra-Bahadurgarh)

21 1005/25 1036/4 31.15 Jajjar Haryana Optional Feeder Line (Luni-Chhasra)

1. 0/0 8/5 8.5 Kutch Haryana

1. 0/0 9/0 9.0 Jhajjar Haryana Three Spur Lines (Bahadurgarh-Tikrikalan)

2. 9/0 12/0 3.0 Delhi Delhi

Table 1.2.4 State Wise Administrative Jurisdiction of the Pipeline Route

Chain age (KP) Line From TO

Length State

0/0 374/2 374.2 Gujarat 374/2 951/9 576.0 Rajasthan

Main Line (Mundra to Bahadurgarh)

951/9 1036/4 86.2 Haryana

Page 6: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 6

Optional Feeder Line (Luni - Chhasra) 0/0 8/5 8.5 Gujarat 0/0 9/0 9.0 Haryana Three Spur Lines (Bahadurgarh to

Tikrikalan) 9/0 12/0 3.0 Delhi

1.3 Details of Pipeline and Station Facilities

1.3.1 Station Details

Engineers India Limited (EIL) has prepared the Detailed Feasibility Report (DFR) for this project. The main pumping station at Mundra Dispatch station will have booster and mainline pumps followed by intermediate Booster pumping stations at Bhachau (Phase- II), Santalpur (Phase-I), Palanpur (Phase-I), Pindwara (Phase-II), Awa (Phase-I), Ajmer (Phase-I), Jaipur (Phase-I) & Rewari (Phase-II). All pump stations will have 2 Nos. working pumps + 1 No. standby pumping configuration for both phases.

A separate dispatch pumping stations at Bahadurgarh has been envisaged for pumping of products from the proposed Bahadurgarh Storage Terminal to Tikrikalan through three spur pipelines. For the optional feeder line, the existing pump station of PVKPL at Sikka will pump the products upto the next pump station at Santalpur in Mundra Bahadurgarh main pipeline with due augmentation of their pumping facilities.

Mundra Dispatch Station: Dispatch station at Mundra is considered for the proposed pipeline. Pipeline facilities at dispatch station shall have piping manifold, booster pumps, mainline pumps, filtering, metering, pressure reduction, corrosion inhibitor tank & pump, sump tanks and pumps and scraper launcher.

Chhasra Intermediate Station: Provision for pigging facilities at an intermediate station for Petronet VKPL is considered at Chhasra. The proposed pipeline facilities at Chhasra shall consist of scraper receiver for Sikka -Chhasra section, sump tank, metering and pump.

Santalpur/Awa Intermediate Pumping Station: Pipeline is proposed to have Intermediate Pumping cum Pigging Station at Santalpur and at Awa. Proposed pipeline facilities at Santalpur and Awa stations shall consist of scraper receiver, scraper launcher, filtering, metering, mainline pumps, pressure reduction, sump tanks and pumps.

Palanpur/Ajmer/Jaipur Intermediate Receipt cum Pumping Station: Pipeline is proposed to have Intermediate receipt cum Pumping Station at Palanpur, Ajmer and Jaipur. Proposed pipeline facilities at the above mentioned stations shall consist of scraper receiver, scraper launcher, filtering, metering, piping manifold, mainline pumps, pressure reduction, sump tanks & pumps, meter prover (only at Ajmer), corrosion inhibitor tank & pump (only at Palanpur and Jaipur).

Bahadurgarh Receipt cum Dispatch Station: Receipt station for the proposed main pipeline shall be at Bahadurgarh. Pipeline facilities at Bahadurgarh shall consist of scrapper receiver, filtering, filter separator, pressure reduction, metering, piping manifold and sump tanks and pumps. Bahadurgarh is also envisaged as -dispatch station for Bahadurgarh- Tikrikalan spur

Page 7: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 7

lines. Proposed pipeline facilities at each dispatch station shall consist of piping manifold, booster pumps, filtering, metering, mainline pumps, pressure reduction, corrosion inhibitor tank & pump, sump tanks and pumps and scraper launcher.

Tikrikalan Receipt Station (For Bahadurgarh- Tikrikalan spur line): Receipt Station for the proposed spur lines shall be Tikrikalan. Pipeline facilities at Tikrikalan shall consist of scraper receiver, filtering, pressure reduction, metering, piping manifold and sump tanks & pumps.

The proposed pipeline facilities SV/CP station for the entire route are depicted in the 'Schematic Arrangement for Pipeline Facilities' in Figure-1.1.

Pipeline Size & Thickness

Pipe size details like length, diameter, wall thickness & grade of the pipeline at various sections including ROW & burial depth are given in Table-1.3.2.

Table - 1.3.2 Details Pipeline Size & Thickness

Section Length (km)

Line Size

(inch)

Length (km)

Thickness (mm)

Pipe Grade Design Pressure

(kg/cm2g)

ROW (m)

90 18 13 7.1 API 5L X-65 87.7 18 Mundra-Bhachau 77 6.4 API 5L X-65 84 18

Bhachau-Santalpur 108.0 18 108 6.4 API 5L X-65 84 18 131.5 18 42 7.1 API 5L X-65 92.5 18 Santalpur-Planpur

89.5 6.4 API 5L X-65 84 18 100.5 18 28.7 7.9 API 5L X-65 99.6 18

23.5 7.1 API 5L X-65 94 18 Palanpur-Pindwara

48.3 6.4 API 5L X-65 84 18 Pindwara-Awa 109.9 18 109.9 6.4 API 5L X-65 84 18

127.6 18 18.6 7.1 API 5L X-65 89.4 18 Awa-Ajmer 109 6.4 API 5L X-65 84 18

Ajmer-Jaipur 111.5 18 111.5 6.4 API 5L X-65 82.6 18 186.1 18 8.2 7.9 API 5L X-65 99.6 18

19.1 7.1 API 5L X-65 94 18 Jaipur-Rewari

158.8 6.4 API 5L X-65 84 18 Rewar-Bahadurgarh 71.3 16 71.3 6.4 API 5L X-65 84 18 Total Main Line 1036.4 -- -- -- API 5L X-65 -- -- Luni-Chhasra 8.5 18 8.5 6.4 API 5L X-65 84 18 Bahadurgarh-Tikrikalan

12.0 8 12.0 6.4 API 5L Grade B

26.7 18

Corrosion allowance: 0.5 mm Minimum burial depth: 1 m Design temperature: Above ground: 65oC, Buried:45oC

Page 8: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 8

Product Handled: MS, ULMS, HSD, ULHSD, & SKO 1.3.3 Flow & Pressure Details Flow & pressure details of various of the pipeline including elevation are given in Table- 1.3.3.

Operating Line Pressure (kg/cm2 g) Service Flow (m3/hr) Outgoing Incoming Outgoing

Station Elevation above MSL

(m) Incoming

Ph - I Ph - II Ph - IPh - IIPh - IPh - IIMundra 4.8 Atm 79.7 52.7 -- 784 909 Bhachau (Phase-II) 4 -- 56.2 784 -- 784 909 Santalpur 18 6 68.7 84.1 784 909 784 909 Palanpur 190 4 90.5 69.5 784 909 784 909 Pindwara (Phase-II) 4 -- 50.4 784 909 784 909 Awa 300 6 66.5 81.3 784 909 784 909 Ajmer 460 6 56.3 75.1 784 909 713 825 Jaipur 350 6 91.3 72.0 713 825 713 825 Rewari (Phase - II) 254 6 -- 53.7 713 825 713 825 Bahadurgarh 220 6 -- -- 713 825 713 825 Bahadurgarh (Spur) 220 Atm 19.0 24.3 -- -- 150 185 Tikrikalan 213 6 0 0 150 185 -- -- 1.3.4 Pump Details Details of pumps at various stations along the pipeline and their number, capacities & motor rating are given in Table - 1.3.4. Table - 1.3.4 Pump Details

Pump Capacity (m3/h)Station No. of Pumps Phase - I Phase - II

Motor Rating (KW)

Booster: 2+1 single stage 784x1.1 909x1.1 132 Mundra Mainline:2+1 seven stages 1650

Bhachau (Phase - II) Mainline:2+1 six stages No pumping 909x1.1 1350 Santalpur Mainline:2+1 eight stages 784x1.1 909x1.1 2050 Palanpur Mainline:2+1 eight stages 784x1.1 909x1.1 2000 Pindwara (Phase - II) Mainline:2+1 five stages No pumping 909x1.1 1250 Awa Mainline:2+1 seven stages 784x1.1 909x1.1 2000 Ajmer Mainline:2+1 seven stages 713x1.1 825x1.1 1700 Jaipur Mainline:2+1 eight stages 713x1.1 825x1.1 1850 Rewari (Phase - II) Mainline:2+1 five stages No pumping 825x1.1 1250

Booster: 3+1 single stage 150x1.1 185x1.1 45 Bahadurgarh Mainline: 3+1 two stages 170

Page 9: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 9

1.3.5 CP & SV Details

Along the main pipeline sectionalizing valves are provided. When required, the sectionalizing valve and mainline station valve can be closed from SMCS after ensuring the shutdown of entire pipeline operation. Permanent Cathodic protection of the pipeline shall be by impressed current method. Number of cathodic protection (CP) stations & sectionalizing valves (SV) stations along the pipeline is given in Table-1.3.5.

Table - 1.3.5 Number of CP Stations & SV Stations

Pipeline Segment No. of SV Stations No. of CP Stations

Main line (Mundra-Bahadurgarh) 34 32

Feeder line (Luni-Chhasra) 0 1

Spur lines (Bahadurgarh-Tikrikalan) -- 2

Total 34 35

Sectionalizing Valves/Station Block Valves: Sectionalizing valves (SV) and station block valves shall be motor operated full bore valves (MOV). All sectionalizing valves shall have provision for remote operation (ROV). Sectionalizing valves shall be buried and provided with stem extension except at Bhachau & Pindwara stations where SV shall be installed above ground. Mainline valves shall be full bore type ball valves to allow smooth passage of scrapers or pigs through them. These valves shall conform to API-6D.

Scraper Traps: Scraper Traps (Launcher/Receiver) shall be provided at the dispatch terminals, intermediate pumping stations, intermediate receipt cum pumping stations and receipt terminals for facilitating intelligent pigging and cleaning pigging. However, at Bhachau and Pindwara SV stations, pumping station without the provision of scraper traps are envisaged in phase-II. Scraper Traps shall be designed as per ASME B 31.4. The material of scraper traps shall be compatible with line pipe material. Design factor and corrosion allowance for designing scraper shall be considered as 0.5 and 3 mm respectively.

1.3.6 Materials & Throughput

The project requirement is to transport 5.0 Million Metric Tonnes Per Annum (MMTPA) of white POL products namely MS, ULMS, HSD, ULHSD & SKO in Phase-I and 5.8MMTPA in Phase-II from Mundra portiPetronet VKPL (optional) to Bahadurgarh/Trikrikalan (Delhi) with tap-off points for Marketing installation at Palanpur, Ajmer. Jaipur and Rewari. Pipeline throughput projections considering HPCL own volumes & additional 25% capacity to be provided for others for phase-I & phase-II are given in Table-1.3.6.

Page 10: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 10

Table-1.3.6 Mundra-Delhi Pipeline Throughput Projections (in MTPA) With HPC Volumes + 25% Excess to be taken as Basis for Pipeline & Pump Design)

Volumes in MT in Phase - I (Year 2011-12) TOP MS UL MS HSD UL HSD SKO Total

Palanpur 60531 66064 232564 33153 50053 442365 Ajmer 59305 0 369104 0 20997 449406 Jaipur 127695 0 302127 0 36722 466544 Rewari 51259 0 285398 0 42762 379419 Delhi 278702 494798 1519924 663704 302593 3259721 Total 577492 560861 2709117 696856 453128 4997455

Volumes in MT in Phase - II (Year 2016-17 MS UL MS HSD UL HSD SKO Total

Planpur 86095 93964 250538 35715 50053 516364 Ajmer 84350 0 397630 0 20997 502977 Jaipur 181624 0 325476 0 36722 543822 Rewari 72907 0 307455 0 42762 423124 Delhi 396405 703763 1644727 714997 30293 3762485 Total 821381 7947726 2925826 750712 453128 5748772

Note: MS & HSD are likely to become ULMS & ULHSD in near future.

Throughput for Bahadurgarh- Tikrikalan pipeline system:

Phase-I: 0.6 MMTPA (Year 2011-12) Phase-II: 0.8 MMTPA (Year 2016-17)

1.3.7 Sump Tank Details

Details of sump tanks at various stations along the pipeline are presented in Table- 1.3.7.

Table -1.3.7 Sump Tanks in Pipeline Stations

Buried Sump Tank Station Capacity (KL) Dia x Length (m) Mundra 2x20 2.2x6.4 (Approx) Chassra 1x20 2.2x6.4 (Approx) Bhachau (Ph-II) 2x20 2.2x6.4 (Approx) Santalpur 2x20 2.2x6.4 (Approx) Palanpur 2x20 2.2x6.4 (Approx) Pindwara (Ph-II) 2x20 2.2x6.4 (Approx)

Page 11: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 11

Awa 2x20 2.2x6.4 (Approx) Ajmer 2x20 2.2x6.4 (Approx) Jaipur 2x20 2.2x6.4 (Approx) Rewari (Ph-II) 2x20 2.2x6.4 (Approx) Bahadurgarh 2x20 2.2x6.4 (Approx) Tikrikalan 2x20 2.2x6.4 (Approx)

* Sump tank is designed to receive surge flow, blow down wherever envisaged

1.3.8 Corrosion Control

The pipeline shall be protected against external corrosion by 3 Layer Polyethylene (PE) coating and additionally by impressed current cathodic protection system.

Corrosion Coating: It is proposed to provide corrosion protection of the buried pipeline using 3 layer side extruded Poly Ethylene (PE) coating for the entire pipeline from Mundra to Bahadurgarh including Luni-Chhasra feeder line and Bahadurgarh- Tikrikalan spur lines.

The total thickness of the coating shall be minimum 2.2 mm 'n' type for 18" NB and 16" NB pipeline and 2mm 'n' type for 8" NB pipeline.

Field weld joints shall be coated with heat shrinkable sleeves or cold applied tapes.

In addition to the corrosion coating, the entire buried portion of the pipeline system shall be provided with cathodic protection system.

Continuous Concrete Weight Coating: Continuous Concrete Weight Coating is proposed to be provided on the line pipe crossing waterway crossings.

Painting: Above ground section of the pipeline shall be provided with suitable anti- corrosive paint suitable for normal corrosive/corrosive industrial environment.

Corrosion Inhibitor Dosing System: Corrosion inhibitor chemical tank and pump is provided for dosing the corrosion inhibitor chemical upstream of mainline pumps for internal corrosion protection. Suitable automation will be provided to monitor the dosage rate based on CI ppm and product flow rate.

1.3.9 Pipeline Materials

Pipeline and its appurtenances shall be provided with carbon steel materials suitable for the intended service, as indicated below:

Line Pipe: Line pipe shall conform to API specification 5L. The process of manufacture of line pipe shall be electric welded construction for 16" NB & 8" NB line pipe and HSAW/LSAW construction for 18"NB line pipe. The grades and size of the pipeline are given in the table no. 1.3.2. Pipe wall thickness shall conform to ASME B31.4 and shall also meet the requirements of OISO 141. At river/major crossings higher wall thickness shall be used.

Page 12: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 12

Pipeline Fittings and Flanges: All pipeline materials downstream of the mainline pumps such as valves, flanges and fittings etc. shall be class 600# rating.

Flow Tees: All branch connections on the mainline, which are greater than 40% of the mainline diameter, shall be provided with flow tees to allow smooth passage of pigs.

Insulating Joints: Insulating joints shall be provided at transition point of above ground and under ground section of pipeline for electrical isolation. Insulating joints shall be of mono block type.

1.3.10 Pipeline Construction Method

Pipeline and associated facilities shall be constructed in accordance with ASME B 31.4and other applicable API standards.

Cover: The pipeline shall be laid underground with minimum 1 meter cover. Additional cover, wherever required, shall be provided in accordance with OISD 141.

Welding: Welding shall be carried out as per API 1104. All welds shall be 100% radiographed.

Testing: After the installation is completed, the entire pipeline shall be hydrostatically tested.

Trenching & Back-filling: Surface soil on the majority of pipeline route is silty clay/sandy clay and silty clay/silty sand with weathered rock at some places. Generally. weathered rock can be excavated with the help of dozer / ripper and back- hoes. In case of sub surface encountered being weathered rock, a minimum of 150 mm thick layer of soft back-fill material shall be provided all around the pipeline prior to back- filling the trench with excavated material. The type of corrosion coating selected (PE) for the pipeline has adequate mechanical properties to withstand the hard surface features.

Railway Crossings: All railway lines shall be crossed by boring method. Approval of designs and construction methodology shall be obtained from concerned railway authorities. Pipeline at railway crossings shall be provided with casing pipe. The carrier pipe shall be installed inside casing pipe. The casing pipe shall be three nominal pipe sizes larger than carrier pipe. The minimum clear cover at the crossing above top of pipeline shall be- 1.7m. The crossing angle shall be as close to 90o as possible. The railway crossings shall comply with the requirements of API 1102 and Indian Railway Authorities. Casing insulators and end seals shall be provided to isolate carrier and casing pipes.

Road Crossings: Road crossings shall comply with the requirements of API 1102 and the requirements of the concerned road authorities. Pipeline at National Highways and State Highways crossings shall be provided with the casing pipe. Metal roads other than the national highways and state highways shall be crossed by open cut method. However, at locations where it is not feasible to cross the road by open cut method, boring/jacking method shall be used. All the cart tracks crossings shall be carried out by open cut method. The road crossings shall be provided with a minimum clear cover of 1.2 m measured from top of the carrier pipe.

Page 13: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 13

Canal Crossings: Irrigation lined canals shall be crossed by boring method wherever required by the statutory authorities. All other minor canals and nallas crossings shall be carried out with conventional open cut method unless directed otherwise by the concerned authorities. The canal crossings and other water crossings shall be provided with a minimum clear cover of 1.5 m.

River Crossing: Rivers crossings are proposed to be crossed by conventional open cut method. Pipeline shall be installed approx. 1.5 m below the lowest bed level. Lowest bed level shall be calculated after giving due consideration to scour depth of such water crossings. The line pipe shall be concrete coated, if required, to provide sufficient negative buoyancy.

1.3.11 Summary of Pipeline Parameters

Summary of the various pipeline parameters is given in Table-1.3.8.

Table-1.3.8 Summary of Pipeline Parameters

Item Details Length (km) Main line:1036.4 km, Optional Feeder line: 8.5 km, Spur lines: 12.0

kms each Line size & thickness Main/Feeder Liner sizes: 16-18", Spur lines: 8", Pipe thickness: 6.4-7.9

mm Pipe Grade API 5L X-65, X-60, Grade B ROW (m) 18m Throughput 5 MMTPA in Phase - I (2011-12), 5.8 MMTPA in Phase- II (2016-17)

Pumps Mainline: 2+1, Booster: 2+1 Capacity: 713-78 m3/hr in Phase - I & 825-909 m3/hr in Phase - II

Pipeline laying Buried Burial depth (m) Minimum 1 meter clear cover from pipe top. At crossings higher

cover as p er OISD 141 Methods for rail/road/river/ canal crossings

Rail, NH, SH, major road and lined canal/perennial river crossing: byhorizontal boring. Other road, canal, and non-perennial rivercrossing: - by op en cut. Sp ecification for above will be as p er API1102.

Pipeline design basis ASME B 31.4 and OISD-141 Operating hours 8000 hrs/ year Pipeline operating life 35 years Hydraulic calculation basis All hydraulic calculation will be based on HSD at 25"C Pipeline material Carbon Steel Pipeline roughness 45 microns Corrosion allowance 0.5 mm Pigging facilities Permanent pigging facilities suitable for " Intelligent Pigs" shall be

provided at suitable distances

Page 14: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 14

Subsoil temperature 25.C (1m below ground) throughout the entire length of the pipeline Surge control Suitable surge control/surge relief system will be provided as per

requirement. The surge analysis will be done during the progress ofdetailed engineering.

Pipeline corrosion

Protection measures

Internal: By injection of corrosion inhibitor along with product.

External: By external 3 layer PE Coating and impressed currentcathodic protection system (ICCP)

Cathodic Protection (CP) details

Temporary CP during construction. After construction PermanentICCP with CP stations at approx. 30 km interval.

Sectionalizing valves (SV) details

Requisite no. of sectionalizing valves along the pipeline will beprovided as per ASME B 31.4 & relevant provisions of PetroleumRules 2002. OISD etc.

Power supply AC power from the grid power supply along with battery back up toSVs, CPs, repeater staions & intermediate pigging (IPG) stations.

Communication system OFC based telecom system (including data and voice mail) Leak detection & protection system

SCADA and Real Time Transient Model Enveloping Modelcompensated Volume Balanced based Leak Detection system.

Inspection & patrolling system

Periodical inspection of ROU by officers, periodical inspection ofpipeline & coating health. Daily patrolling of ROU by Line Walkers.

1.4 Utilities

1.4.1 Power Supply Arrangement

Power requirement will be fulfilled from the local grid. Provision for DG set will be kept as backup arrangement for emergency power only. The estimated power requirement is given in Table 1.4.1.

Table 1.4.1 Power Supply Arrangement

Station Requirement (KVA)

Source Back up DG Set for Emergency Power

(KVA) Mundra 3710 66 KV (Grid) 200 Bhachau (Ph-II) Santanpur 3078 33 KV (Grid) 200 Planpur 3030 66 KV (Grid) 200 Pindwara (Ph - II) Awa 3005 33 KV (Grid) 200 Ajmer 2426 132 KV (Grid)/33 KV (Grid) 200 Jaipur 1698 33 KV (Grid) 200 Rewari (Ph-II) 1316 33 KV (Grid) 80 Bahadurgarh 680 11 KV (Grid) 200 Tikrikalan 80 80

Page 15: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 15

1.4.2 Service Water

Source: From existing terminal/ground water.

1.5 Instrumentation, Control & Communication System

1.5.1 Instrumentation & Control System

Instrumentation & control shall be provided for safe and efficient operation of the .pipeline, dispatch station, intermediate pumping stations and intermediate pigging stations, SV stations, tap-off points and receipt terminals. Control rooms shall be provided in pipeline dispatch terminals, intermediate pumping stations and at each pipeline receipt terminals with facility to monitor and control the station from the station PLC based control system. Additionally necessary interface is envisaged in each station including SV stations and IP stations to connect pipe line/terminal parameters to the SCADA system for remote control and telemetering.

The details of Instrumentation and Control System to be provided for safe & efficient control of the pipeline project are:

• PLC based control system is envisaged at Dispatch Stations, Intermediate Stations, and Receipt Stations for the process interlocks/ shutdown logic/ MOVs operation and station monitoring. Control panels are provided for mounting the flow computers, density converter etc.

• All controls, recording and link to remote indicating devices shall be through PLC located in the control rooms at Mundra & Bahadurgarh dispatch stations, all receipt stations and all intermediate stations.

• All essential control parameters of receipt terminals / other pipelines shall be integrated suitably in SCADA system & PLC control.

• Metering facilities shall be provided at Mundra, Chhasra, Santalpur, Palanpur. Awa, Ajmer, Jaipur, Rewari, Bahadurgarh receipt & dispatch stations and Tikrikalan at Delhi.

• Flow meters shall be turbine meters with flow computers to compute corrected volumetric flow rate, mass flow and total mass flow. At Ajmer, Meter Prover and arrangement for meter proving of other station turbine meters have also been provided.

• Density meters with density converters will be used at Mundra, Chhasra, Santalpur, Palanpur, Awa, Ajmer, Jaipur, Rewari, Bahadurgarh and Tikrikalan for density measurement and interface detection.

• Pump machine interlocks / start / stop and trip functions will be implemented duly interfacing with the PLC system.

• The main pumping units will be shut down automatically in the event of low suction pressure or high discharge pressure, mechanical seal failure, high vibration, casing temperature etc. Very high station discharge pressure will also shutdown the pumps. One control valve has been provided on the down stream of each pump station for control1ing the pressure in the pipeline.

• The sump pump and/or slop transfer pump will be tripped in case of low liquid level in the sump tank.

• Suitable surge relief system and thermal relief/ safety valves are considered as per the requirement.

Page 16: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 16

• Along the main pipeline sectionalizing valves are provided. When required, the sectionalizing valve and mainline station valve can be closed from SMCS after ensuring the shutdown of entire pipeline operation.

• Corrosion Inhibitor chemical tank and pump is provided at Mundra dispatch station, Jaipur tap-off / receipt station and at Bahadurgarh dispatch station for dosing the corrosion inhibitor chemical upstream of main line pumps for corrosion protection. Suitable automation will be provided to monitor the dosage rate based on CI ppm and product flow rate.

1.5.2 Telecommunication System

Since the pipeline shall pass through the cross country area not adequately covered by the public telecommunication system, a dedicated telecommunication system is proposed to be implemented to meet the operation and maintenance requirements of this pipeline.

Suitable back-up arrangements with other service providers will also be reviewed. The proposed telecommunication system shall be required to provide the following services and facilities:

• Direct dialing facility between the various attended stations and between each unattended station to the nearest attended station of this network.

• Conference facility: This facility shall enable selective connection amongst the attended stations.

• Voice communication for use by pipeline maintenance/security personnel between a section of unattended station and the nearest attended station on either side.

• Engineering order wire circuits shall be provided to facilitate maintenance of the system. • Facsimile communication to facilitate transmission of written message, charts graphs,

etc. amongst the attended stations. • A network management system to facilitate remote monitoring and control of

equipment status etc. at various stations. • Low speed and High speed data communication circuits for telesup ervisory and control

system connecting the various stations of this pipeline for

a) SCADA RWS, HPCL LAN & Video conferencing b) CCTV's for unattended stations

1.5.3 SCADA & APPS System

To ensure effective and reliable control, management and supervision of the pipeline, the entire pipeline network is envisaged to be monitored and controlled from Supervisory Control and Data Acquisition (SCADA) system consisting of SCADA Master Control Station (SMCS).

At the following locations, one Remote Work Station (RWS) each shall be provided for exercising monitoring for the complete pipeline:

• Chhasra • Santalpur

Page 17: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 17

• Palanpur • Awa • Ajmer • Jaipur • Rewari & Bahadurgarh

Remote Telemetry Units (RTU) at all the terminals and at SV, SV/CP station shall be considered for telemetry purposes at various locations (as per pipeline schematic arrangement of pipeline facilities).

The SCADA system will monitor & control the pipeline facilities in a timely manner and provide centralized alarm & event management and operation & management reports for all distributed pipeline facilities. The SCADA system also ensures proper pipeline operations for all combinations of station shutdown/draw off operations & enables shutdown by closing various pipeline facilities in orderly manner in the emergency situation.

In addition, the system will facilitate running of Application Software (APPS) package for reliable operation of the pipeline viz.:

• Leak detection and location in all conditions • Batch Scheduling and Batch Tracking • Stock accounting to assess customer wise, batch wise & product wise stock reconciliation

(stock loss/gain and variation) statement and transportation invoice generation right from order to execution stage

• PIG launch/Receipt and Tracking of PIG.

1.5.4 Pump Station Operation

Pump unit sequence for the booster pumps & mainline pumps performs the following functions:

• Check the position of MOV on the discharge of pump and bring it to close position, if required.

• Check the position of MOV on the suction of main pump and bring it to open position. • Pump motor is started and MOV of discharge is opened after a time delay.

Any of the main pumping units can also be shut down manually by pressing the stop button, As the motor stops, the suction and discharge valve closes automatically after a time delay. The station sequence sends a ready signal through RTU to the immediate pumping station for start-up. In case any pump station trips other station shall be informed through RTU or control panel, if required.

The main pumping units will be shut down automatically in the event of low suction pressure or high discharge pressure. Very high station discharge pressure will also shut down the pumps. One control valve will be provided on the down stream of each pump station for controlling the pressure in the pipeline. A pressure controller is provided on the suction side of the pumps to keep the suction pressure within the limits.

Page 18: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 18

1.6 Fire Protection System

The multi-product pipeline facilities starting from Dispatch Terminal at Mundra and terminating at Receipt Terminal at Bahadurgarh consist of a number of Sectionalizing Valve Stations, Intermediate Pumping Stations and Dispatch and Receipt Terminals. As per the requirement of OISD-117, fire protection facilities are required to be provided at oil terminals/ pipeline installations (with or without storage). Accordingly, fire protection facilities are proposed to be provided at all dispatch and receipt terminals along with at intermediate pumping stations (these are being considered as pipeline installation without storage).

A) At Mundra, Palanpur, Ajmer, Jaipur & Bahadurgarh, fire water storage & pump station facilities shall be common for both pumping station and storage terminals. The following fire protection facilities are required at these locations as per the requirements of OISD-117:

a. Fire Water System -Pressurized b. Foam system c. First Aid Fire Fighting Equipment and safety accessories d. Mobile Fire Fighting Equipment

Fire Protection Facilities

The facilities provided consist of the following units

1) Fire Water Storage Tanks 2) Fire water Pumps and Jockey Pumps 3) Fire water Piping 4) Fire Hydrants 5) Fixed Foam System 6) Water/foam Monitors 7) Fixed water Spray Systems 8) Mobile Fire Fighting Equipment 9) Portable extinguishers

B) At intermediate pumping stations at Santalpur & Awa, following fire protection facilities proposed to be provided:

i. Fire water system ii. Clean agent/CO2 system for manned/unmanned control rooms/repeater rooms.

iii. First aid fire fighting equipment

Design of the fire water system shall be based on one single largest risk. Since no storages are proposed at these locations, fire water demand is based on the requirements of equipments areas handling oil products or supplementary hose stream requirements, whichever is greater. The following fire protection system shall be installed in the complex to control and fight fire.

• Fire water tanks: 2 nos. of fire water tanks of capacity 820 m3 each are proposed to be provided to meet the fire water storage for 4 hours of pumping.

Page 19: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 19

• Fire water pumps: Two standard TAC approved electric driven pumps (1 working + 1 standby) of 410 m3/hr capacity & 8.8 kg/cm2g head are proposed to be provided alongwith 2 nos. of electric driven jockey pumps (1 working + 1 standby) to keep the network pressurized.

• Hydrants: On the fire water network hydrants/monitors shall be provided at a spacing of 30 m C/C around oil handling facilities as per requirements and hydrants at a spacing of 45 m C/C shall be provided in non-hazardous areas.

C) At all SV stations only CO2 system for unmanned repeater rooms and portable fire extinguishers shall be provided.

1.7 Crossings

The pipeline runs cross-country crossing network of National highways, State Highways, Major District Roads, Village Roads, Canals, Railway Lines, Rivers and Nallas. The number of crossings along the pipeline route identified during the reconnaissance survey is furnished in Table-1.8.1.

Table-1.7.1 Number of Crossings along the Pipeline

S. No.

Type of Crossing Main Route

Feeder Line (Luni

Chhasra)

Spur Line (Bahadurgarh

Tikrikalan)

Total

1. National Highway 17 -- -- 17

2. State Highway 26 -- -- 26

3. Asphalted & Other Road 308 3 5 36

4. Railway Line 13 1 2 16

5. Canal 19 -- -- 19

6. Rivers & Streams 51 -- -- 51

7. Pipeline 20 1 -- 22

8. Forest 7 -- -- 7

1.7.1 Forest Crossings

Pipeline has been routed carefully to avoid forestland to the maximum extent possible. At some of the locations it is difficult to avoid the forest land due to terrain conditions and developments along the route. Pipeline passes through reserved forest area in Kutch, Patan & Banaskantha districts area in Gujarat. Route cuts across a few small stretches of forest lands identified till date are given in Table-1. 7 .2. The pipeline will also cross social forestry at major road crossings.

Page 20: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 20

Table-1.7.2 List of Reserved Forest Crossing

S.No. Chainage (KP) Length (km) Village District State

1. 1.496 0.40 Gundala Kutch Gujarat

2. 5.743 0.30 Gundala Kutch Gujarat

3. 26.241 0.80 Kheldoi Moti Kutch Gujarat

4. 28.362 2.00 Kheldoi Moti Kutch Gujarat

5. 194.107 0.72 Chhansara Patan Gujarat

6. 209 0.615 Unrot Patan Gujarat

7. 346.1 0.020 Bantawada Banaskantha Gujarat

- 4.855 -- -- -

1.7.2 Road & Railway Crossings

There are about 18 NH crossings, 27 SH crossings and 16 railway crossings. The list of National Highway (NH) crossings is given in Table-1.7.3. The list of State Highway (SH) crossings is presented in Table-1.7.4. The list of Railway crossings is given in Table- 1.7.5.

Table - 1.7.3 List of National Highway Crossing

S.No. Details of Crossing CH. (KP) RL (m) State

Main Line (Mundra-Bahadurgarh)

1. NH-15 (Varahi to Adesar) 164/15 40

2. NH-15 (Varahi to Adesar) 165/0 40

3. NH-15 (Varahi to Adesar) 214/2 25

4. NH-15 (Radhanpur to Bhabhar) 246/9 38

5. NH-14 (Radhanpur to Deesa) 265/5 53

6. NH-14 (Palanpur to Deesa) 329/5 190

Gujarat

7. NH-14 (Swarupganj to Sirohi) 411/10 325

8. NH-76 (Pindwara to Kyari) 429/5 374

9. NH-14 (Pali to Ajmer) 607/6 350

10. NH-8 (Ajmer to Beawar) 667/9 460

11. NH-79 (Ajmer to Nasirabad) 684/5 445

12. NH-7A (Nasirabad to Kishangarh) 688/6 440

13. NH-8 (Jaipur to Ajmer) 779/0 350

Rajasthan

Page 21: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 21

14. NH-11 (Jaipur to Bikaner) 816/0 470

15. NH-8 (Jaipur to Delhi) 847/2 440

16. NH-8 (Jaipur to Delhi) 943/3 290

17. NH-10 (Rohtak to Bahadurgarh) 1036/3 220 Haryana

Table-1.7.4 List of State Highway Crossing

Details of Crossing CH. (KP) RL (m) State S.No. Main Line (Mundra-Bahadurgarh)

1. SH-6 (Kundrodi to Bhadreswar) 20/55 37

2. SH-50 (Chhasra to Anjar) 42/15 80

3. SH-45 (Rodal to Anjar) 51/05 73

4. SH-45 (Dudhai to Anjar) 54/0 71

5. SH-42 (Dudhai to Bhachau) 92/4 37

6. SH-51 (Chtrod to Rapar) 128/45 114

7. SH-130 (Umbri to Wayad) 290/4 85

8. SH-7 (Deesa to Virangam) 305/3 114

9. SH (Moti Bhatamal to Malana) 338/8 192

Gujarat

10. SH-11 (Revdar to Abu Road) 379/4 243

11. SH-14 (Abu Road to Mount Abu) 387/5 278

12. SH-14 (Mount Abu to NH-14) 390/9 281

13. SH-16 (Bali to Mundara) 485/0 330

14. SH-117 (Sojat road to Bhopari) 558/9 305

15. SH-5 (Bar to Jodhpur) 609/9 355

16. SH-39 (Babra to Beawar) 633/7 390

17. SH-7 (Kishangarh to Arain) 714/8 400

18. SH-4 (Dudu to Sewa) 748/6 350

19. SH-2 (Dudu to Mozammabad) 750/2 340

20. SH-2A (Champapura to Hathod) 802/1 420

21. SH-13 (Alwar to NH 8) 867/3 430

2.. SH-14 (Bahror to Baraud) 927/9 310

Rajasthan

23. SH-5 (Shahjahanpur to Rewari SH 5) 952/2 270 Haryana

Page 22: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 22

24. SH-28 (Rewari to Hansaka) 975/1 240

25. SH (Rewari to Pataudi) 986/7 230

26. SH-22 (Jhajjar to Bahadurgarh) 1029/3 215

Table-1.7.5 List of Railway Line Crossing

Details of Crossing CH. (KP) RL (m) State S.No. Main Line (Mundra-Bahadurgarh)

1. M.G Western Railway Line (Gandham to Bhuj) 52/7 71

2. Western Railway Line (Palanpur to Kandla) 243/05 32

3. M.G. Western Railway Line (Palanpur to Deesa) 328/3 190

Gujarat

4. B.G. Western Railway Main Line 413/0 335

5. Railway Line (Railway siding for Laxmi Cement) 417/8 353

6. Western Railway Line (Marwar Junction to Mavli Junc) 550/1 300

7. B.G Railway Line (Marwar Junction to Ajmer) 600/4 340

8. B.G. Railway Line (Ajmer to Beawar) 665/2 450

9. Western Railway Line (Khandwa Ratlam to Ajmer) 677/1 460

Rajasthan

10. Western Railway Line (Double Line) 794/5 415

11. Railway Line (Sawai Madhopur to Loharu section) 812/0 460

12. B.G. Western Railway Line (Mainline Rewari to Jaipur) 963/6 255

13. M.G. Northern Railway Line (N.R mainline) 984/8 230

Haryana

Feeder Line (Luni to Chhasra)

1. Adani Port Railwayline 0/2 3.5 Gujarat

Spur Line (Bahadurgarh to Tikri Kalan)

1. Railway Line (Rohtak to Delhi) (2 lines) 1/0 217 Haryana

1.7.3 River & Canal Crossings

There are only 12 river crossings having width of more than 100 m (Table-1.7 .6). The important rivers are Banas in Gujarat, and Mithri, Sukri, Bandi, Modiya, & Raipur Luni in Rajasthan. Including the small streams, in total, there are about 51 river crossings which are listed in Table-1. 7.7. There are about 19 canal crossings. Important canals are Sangwara Minor, Jahangirpur Minor & Bahadurgarh Minor. The list of canal crossings is presented in Table-1. 7.8.

Page 23: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 23

Table-1.7.6 River Crossing having Width more than 100 m

S.No. Name of River Chainage (km)

Width (bank to bank) (m)

Type of River Major / Minor

State

1. Banas River 271/9 750 Non perennial Minor Gujarat

2. Balaram River 346/9 150 Non perennial Minor Gujarat

3. Banas River 365/9 350 Non perennial Minor Gujarat

4. Banas River 404/5 300 Non perennial Minor Rajasthan

5. Jawal River 444/9 150 Non perennial Minor Rajasthan

6. Tarawari River 463/5 150 Non perennial Minor Rajasthan

7. Mithri River 474/9 250 Non perennial Minor Rajasthan

8. Sukri River 501/15 250 Non perennial Minor Rajasthan

9. Bandi River 533/1 200 Non perennial Minor Rajasthan

10. Kantaliya River 565/5 150 Non perennial Minor Rajasthan

11. Modiya River 571/95 200 Non perennial Minor Rajasthan

12. Raipur-Luni River 601/4 300 Non perennial Minor Rajasthan

Table-1.7.7 List of River Crossing

Details of Crossing CH. (KP) RL (m) State S.No. Main Line (Mundra to Bahadurgarh)

1. Phot Nadi 0/8 15

2. Luni River 15/2 25

3. Mitti Nadi 21/4 38

4. Ruparel Nadi 28/6 60

5. Lerak Nadi 36/1 60

6. Song Nadi 46/3 80

7. Song Nadi 48/2 75

8. Churwa Nadi 58/35 45

9. Sakra Nadi 75/6 23

10. Khari Nadi 119/6 92

11. Banas River 271/9 60

12. Ladbi Nadi 308/6 115

Gujarat

Page 24: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 24

13. Balaram River 347/0 187

14. Banas River 366/0 216

15. Kaleri Nadi 372/1 227

16. Banas River 404/5 309

17. Banas River 420/6 352

18. Darvot Nadi 424/6 358

19. Darvot Nadi 426/2 360

20. Bilar Nadi 436/5 388

21. Jawai River 444/9 364

22. Sela Nadi 451/3 338

23. Tarawari Nadi 463/5 320

24. Mithri River 477/0 316

25. Magai Nadi 490/9 330

26. Sukri River 501/2 335

27. Cheli Nadi 512/2 320

28. Somesar Nadi 518/7 320

29. Kot Ki Nadi 524/8 312

30. Bandi River 533/1 296

31. Lilki Nadi Branch 540/8 295

32. Lilki Nadi 541/9 295

33. Sukri Nadi 547/0 300

34. Kantaliya Nadi 565/6 305

35. Modiya Nadi 572/0 320

36. Sukri River Branch 573/1 320

37. Lilri River 582/7 335

38. Guriya Nadi 588/3 350

39. Guriya Nadi 591/8 350

40. Raipur Luni River 601/4 340

41. Sukri Nadi 614/7 350

42. Sukri Nadi 622/1 360

43. Lilri River 634/0 390

Rajasthan

Page 25: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 25

44. Mashi Nadi 722/0 370

45. Dantura Nadi 744/3 340

46. Sndriya Nadi 777/1 335

47. Dhudhala Nadi 847/9 430

48. Madhobini Nadi 849/1 440

49. River 876/3 400

50. Sabi Nadi 890/8 365

51. Sota Nadi 920/9 320

Table-1.7.8 List of Canal Crossing

Details of Crossing CH. (KP) RL (m) State S.No.

Main Line (Mundra to Bahadurgarh)

1. Canal 23/15 45

2. Canal 295/0 93

3. Canal 303/6 112

4. Ghad Canal 316/2 138

Gujarat

5. Righ Canal 386/3 268

6. Canal (Sangwara Minor) 400/3 303

7. Canal 411/9 328

8. Canal 430/6 379

9. Canal 604/0 340

10. Canal 621/1 355

11. Canal 765/3 350

Rajasthan

12. J J L Canal 969/9 245

13. Disused Canal 972/3 245

14. Disused Canal 1011/7 215

15. Jahangirpur Minor 1017/1 215

16. Dulehra Distributory 1021/2 215

17. Canal 1029/2 215

18. Dabauda Sub Minor 1033/4 220

19. Bahadurgarh Minor 1036/2 220

Haryana

Page 26: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 26

1.7.4 Pipeline Crossings

The list of pipeline crossings is given in Table-1.7.9. There are about 23 oil or gas pipeline crossings, pipelines belonging to IOCL & GAIL.

Table-1.7.9 List of Pipeline Crossing

Details of Crossing CH. (KP) RL (m) State S.No.

Main Line (Mundra to Bahadurgarh)

1. GAIL JLPL 138/3 45

2. IOCL KBPL 138/3 45

3. GAIL JLPL 142/0 58

4. IOCL KBPL 142/0 58

5. GAIL JLPL 153/2 40

6. IOCL KBPL 153/2 40

7. GAIL JLPL 173/0 8

8. IOCL KBPL 173/0 8

Gujarat

9. IOCL KBPL 416/6 346 Rajasthan

10. IOCL SMPL 416/6 346

11. IOCL VCPL 416/6 346

12. GAIL JLPL 416/6 346

13. IOCL KBPL 599/3 340

14. IOCL SMPL 599/3 340

15. IOCL VCPL 599/3 340

16. GAIL JLPL 599/3 340

17. GAIL Spurline to IOCL Ajmer LPG Plant 604/0 480

18. GAIL Spurline to BPCL Ajmer LPG Plant 621/1 470

19. GAIL JLPL 840/1 450

20. IOCL KBPL 849/6 450

Feeder Line (Luni to Chhasra

1. IOCL Mundra - Kandla Pipeline 0/1 5 Gujarat

Spur Pipelines (Bahadurgarh to Tikrikalan)

1. GAIL pipeline

Page 27: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 27

1.8 Land Requirement & Compensation

1.8.1 Land Requirement & Land Cost for Stations

Land acquisition for the proposed new IPS is in progress. The land requirement for various proposed IPS is given in Table-1.8.1.

Table-1.8.1 Land Requirement and Land Cost for Stations.

Station Requirement (acres)

Present Ownership

Present LandUse

Acquisition Status

Land Cost (Rs. Lakhs per acre)

Total land Cost (Rs. Lakhs)

Mundra Take Off Terminal

80 GGSRL Industrial Acquired

Chhasra (Feeder Line Hookup)

1 Private Agricultural Ongoing 2.0 2

Santalpur IPS 17 Private Agricultural Ongoing 2.0 34

Palanpur Terminal & IPS

66 Private Agricultural Ongoing 2.5 165

Awa IPS 17 Private Agricultural Ongoing 2.0 34

Ajmer Terminal & IPS

46 Private Agricultural Ongoing 3.5 161

Jaipur Terminal & IPS

40 Private Agricultural Ongoing 10 400

Rewari Terminal* Existing HPCL Industrial Acquired -- --

Bahadurgarh Terminal

90 HPCL Industrial Acquired -- --

Total 187 796

* Existing terminals

1.8.2 Estimated Cost of ROU Acquisition

Cost of ROU acquisition & Crop compensation is estimated to be Rs. 15.85 Crores.

2.0 Project highlights: Terminals

2.1 The following new terminals are proposed for receipt and marketing of the POL products:

1. Mundra - Despatch Terminal 2. Palanpur - Marketing Terminal (Tap off Point) 3. Ajmer - Marketing Terminal (Tap off Point)

Page 28: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 28

4. Jaipur - Marketing Terminal (Tap off Point) 5. Bahadurgarh - Marketing Terminal (Tap off Point)

2.2 The following existing terminals will be hooked up for receipt and marketing of the POL products:

1. Rewari - Marketing Terminal (Tap off Point, Expansion of Existing Terminal)

The salient features of the terminals has been summarized in Table-2.2.1 below.

Table-2. 2.1 Salient Features of the Terminals

No. of Proposed Storage Tanks Terminal Type of Terminal

State MS ULM HSD ULH

SD SKO Total

Receipt Facilities

Loading Facilities

Mundra Proposed Despatch Terminal

Gujarat 2 2 4 3 2 13 Oil Tankers at Mundra Port

--

Palanpur Proposed Marketing Terminal

Gujarat 3 2 3 2 2 12 Mundra Delhi Pipeline

TT loading

Ajmer Proposed Marketing Terminal

Rajasthan3 -- 3 -- 2 8 Mundra Delhi Pipeline

TT loading

Jaipur Proposed Marketing Terminal

Rajasthan- 3 - 3 2 8 Mundra Delhi Pipeline

TT loading

Rewari Existing Marketing Terminal

Haryana 1 -- -- -- -- 1 Mundra Delhi Pipeline

TT loading

BahadurgarhProposed Marketing Terminal

Haryana 4 3 3 3 3 16 Mundra Delhi Pipeline

TT & TW loading

TT - Tank Trucks (Road Loadings) TW - Tank Wagons (Rail Loadings)

All Road and Rail loading terminals will also have small storage and injection facilities for dosage of Ethanol and various other additives like Furfural, Blue Dye, Power, Turbojet, Marker etc.

All terminals will also store and market packed lubricants, greases & Finit etc along with petroleum products.

Page 29: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 29

2.3 Facilities provided at terminals

Despatch Terminal at Mundra: Petroleum products i.e Motor Spirit (MS)/Ultra Low Sulphur Motor Spirit (ULMS), High Speed Diesel (HSD), Ultra Low Sulphur Diesel (ULHSD) & Superior Kerosene Oil (SKO) will be received through oil tankers at the existing Mundra port jetties, 3 nos. of marine unloading arms are envisaged at the jetty for receiving the POL products. 3 nos. of pipelines will be laid from the jetty to the oil storage terminal. Products will be pumped to the storage tanks with the ocean tanker pumps thru the above 3 receipt pipelines. These pipelines are proposed to be routed through the existing pipe bridges/supports available at the port area for a distance of around 4 km from the jetty. Subsequently the new pipelines will be supported above ground over concrete pedestals for a distance of about 4 km up to the terminals. Pumping rate of 2000 KL/hr. has been considered for each of these lines. Petroleum products will be stored in the storage tanks proposed to be constructed in Mundra COT area. Products from the storage tanks will be taken receipt thru dedicated pipelines to the Mundra Pump station and will be pumped further Bahadurgarh and various intermediate Marketing Terminals thru Mundra Delhi Cross Country Pipeline.

Marketing Terminals: In marketing terminals at Palanpur, Ajmer, Jaipur, Rewari (existing) & Bahadurgarh, respective products will be received at the storage tanks in the terminal through pipelines from the Mundra Delhi cross-country pipeline tap off and receiving stations located adjacent to the terminal.. All these terminals will have road loading facilities. Rail loading facilities will be provided only in Bahadurgarh terminal.

All Marketing Terminals will also have small storage and injection facilities for dosage of Ethanol and various other additives like Furfural, Blue Dye, Power, Turbojet, Marker etc. All these terminals will also store and market packed lubricants, greases & Finit etc along with petroleum products.

The details of the different facilities like pumping & loading facilities, storage facilities etc. included in the terminals are discussed below:

2.3.1 Product Pumps

The pumping facilities planned for road & rail loading, slop transfer & tank to tank transfer in various Terminals is given in Table-2.3.1.

Table-2.3.1 Pumping & Loading Facilities Proposed in Terminals

Product Mundra (No. x lpm)

Palanpur (No. x lpm)

Ajmer (No. x lpm)

Jaipur (No. x lpm)

Rewari* (No. x lpm)

BahadurgarhRoad

Loading (No. x lpm)

BahadurgarhRail Loading(No. x lpm)

HSD 3 x 4800 4 x 4800 -- -- 3 x 4800 4 x 4800 ULHSD 2 x 2400 -- 3 x 3600 -- 3 x 3600 2 x 4800 MS 3 x 2400 3 x 2400 -- -- 3 x 2400 2 x 2400 ULMS 2 x 2400 -- 3 x 2400 -- 3 x 2400 2 x 2400 SKO 2 x 2400 2 x 2400 2 x 1200 -- 2 x 2400 3 x 2400

Page 30: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 30

Slop 2 x 4800 2 x 1200 2 x 1200 2 x 1200 2 x 1200 2 x 1200 2 x 300 U/G & HOR

2 x 300 7 x 300 5 x 300 5 x 300 -- 10 x 300 --

No. of pumps: Operation + Standby * Existing terminal

U/G & Hor - Under ground (U/G) and Horizontal (Hor) tanks are small tanks of approximately 70 KI capacity. Underground tanks to be used for receiving product from trucks or sick tank wagons and will be pumped into respective storage tanks. Small Horizontal tanks will be used for storing Ethanol and dosing in Motor spirit.

2.3.2 Tank Truck Loading Facilities

The Tank Truck loading Gantry will consist of loading bays & loading arms. Product wise distribution of loading arms envisaged in the Gantry of various Terminals is given in Table-2.3.2.

Table-2.3.2 TT Loading Facilities Proposed in Terminals

No. of Loading Arms for Terminal No. of Loading

Bays HSD ULHSD MS ULMS SKO

Mundra -- -- -- -- -- --

Palanpur 12 8 2 4 3 3

Ajmer 12 13 -- 4 -- 2

Jaipur 8 -- 6 -- 4 2

Rewari* -- -- -- -- -- --

Bahadurgarh 24 10 6 4 4 4

2.3.3 Tank Wagon Loading Facilities

The Wagon loading Gantry will consist of 80 nos. of loading points for each of the 2 spurs for loading different products various Depots and Marketing installations. Simultaneous loading into wagons placed at two spurs is considered for loading operation. Product wise distribution of loading arms envisaged in the Gantry are is given in Table-2.3.3.

Same spurs will also be used for wagon unloading in case of exigencies. Common headers will be used for loading and unloading of each product. Unloading points consisting of isolation valves, unloading hoses etc. will be provided for each product.

Page 31: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 31

Table-2.3. Tank Wagon Loading Facilities Posed in Bahadurgarh Terminal

Product HSD/ULHSD MS/ULMS SKO No. of loading arms provided 80 x 2 = 160 80 x 2 = 160 80 x 2 = 160

2.3.4 Storage Tank Facilities

The type of storage tanks considered for different products are as follows:

HSD, MS & SKO: Floating roof vertical tank (FRVT) Slop: Floating roof vertical tank (FRVT) Sump: Underground (U/G) Horizontal tank (HOR)

Details of slop/sump tanks at various terminals along the pipeline are presented in Table-2.3.4. Details of storage tanks at various terminals along the pipeline are presented in Table-2.3.5.

Table-2.3.4 Proposed Product Storage Tanks in Terminals

Terminal Product Nominal Capacity (KL)

Dia (m)

Ht (m)

Storage Temp. &Pressure

Type ofTank

Dyke Sizes (m x m)

HSD 4 x 35000 61 13 Ambient FRVT ULHSD 3 x 10000 34 13 Ambient FRVT MS 2 x 30000 56 13 Ambient FRVT ULMS 2 x 20000 46 13 Ambient FRVT

Mundra

SKO 2 x 10000 34 13 Ambient FRVT

172 x 182 142 x 200 145 x 182

HSD 3 x 3100 18 13.5 Ambient FRVT ULHSD 2 x 1000 12 10 Ambient FRVT MS 3 x 2600 16 14 Ambient FRVT ULMS 2 x 3300 18 14 Ambient FRVT SKO 2 x 1000 12 10 Ambient FRVT

Palnpur

Ethanol 2 x 70 3 11 Ambient FRVT

107 x 56 107 x 59

HSD 3 x 5000 22 14 Ambient FRVT MS 3 x 2000 16 12 Ambient FRVT SKO 2 x 1000 12 10 Ambient FRVT

Ajmer

Ethanol 2 x 70 3 11 Ambient HOR.

72 x 77 43 x 74

Jaipur ULHSD 3 x 2100 16 12 Ambient FRVT ULMS 3 x 2300 16 12 Ambient FRVT SKO 2 x 1000 12 10 Ambient FRVT Ethanol 2 x 70 3 11 Ambient HOR.

70 x 51 65 x 51

Rewari* MS 1 x 2200 16 12 Ambient FRVT

HSD 3 x 26000 48 14.5 Ambient FRVT ULHSD 3 x 9000 30 14 Ambient FRVT MS 4 x 16000 38 14.5 Ambient FRVT

Bahadurgarh

ULMS 3 x 13000 34 14 Ambient FRVT

118 x 230 158 x 113

Page 32: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 32

SKO 3 x 5000 22 14 Ambient FRVT 1 x 1000 12 10 Ambient FRVT

Ethanol

3 x 70 3 11 Ambient HOR.

99 X 104 78 X 120

FRVT: Floating Roof Vertical Tank * Existing Terminal

Table-2.3.5 Proposed Stop & Sump Tanks in Terminals

Above Ground Stop Tank* Buried Sump Tank Terminal

No. x KL Dia x Ht (m) Type No. x KL Dia x Ht (m)Type

Mundra 2 x 1000 12 x 10 FRVT 2 x 16 2 x 6 Burried

Palanpur 2 x 500 10 x 8 FRVT 5 x 70 3 x 11 Burried Horiz

Ajmer 2 x 500 9 x 9 FRVT 3 x 70 3 x 11 Burried Horiz

Jaipur 2 x 500 9 x 9 FRVT 3 x 70 3 x 11 Burried Horiz

Rewari 2 x 500 10 x 8 FRVT -- -- --

Bahadurgarh 2 x 1000 12 x 10 FRVT 7 x 70 3 x 11 Burried Horiz * Slop tank is designed to receive product interfaces & surge flow. Buried under ground Sump tanks are envisaged to receive thermal expansion blow downs etc. wherever envisaged.

Design Temperature: 550 C Operating Temperature: Ambient

For handling dosage of various additives, packed lubricants, greases & finit etc., following storage spaces are also envisaged at each of the marketing terminals.

Table-2.3.6 Storage Space in Terminals

Additives Storage Lubricants / Greases Finite (Area in m2 )

Terminal

Blue Dye (Litres)

Furfural (Litres)

Marker (Kgs)

Power (Litres)

Turbojet (Litres)

Warehouse Drum yard

Mundra 0 0 0 0 0 0 0 Palanpur 150 100 100 700 300 30 x 15 30 x 15 Ajmer 100 100 100 350 450 30 x 15 30 x 15 Jaipur 100 100 100 700 400 15 x 15 20 x 15 Rewari 100 100 100 300 350 18 x 12 15 x 5

45 x 15 Bahadurgarh 800 650 800 4400 2600 15 x 20 15 x 50

Page 33: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 33

2.4 Design basis for products facilities

2.4.1 Product Characteristics

Main POL Products to be handled/stored are: MS, ULMS, HSD, ULHSD & SKO Physical characteristics of the products are given in Table-2.4.1

Table-2.4.1 Physical Characteristics of the Products

Product Sp. Gr. at 150 C (CST)Viscosity at 380 C (CST)Vapour Pr. (kg/cm2)

MS 0.73 0.51 0.7

ULMS 0.73 0.51 0.7

HSD 0.83 5 0.1

ULHSD 0.83 5 0.1

SKO 0.81 1.18 0.1

2.4.2 Product Receipt & Off-takes

At Mundra Despatch Terminal:

POL products will be received at Mundra Despatch Terminal from oil Tankers berthed at Mundra port located at 8 km from the Terminal. 3 nos. of pipelines for transporting the products will be laid from the jetty to the terminal i.e. 1 no. each for MS & ULMS, HSD & ULHSD & SKO. 3 nos. of marine unloading arms are envisaged at Mundra Port to supply oil to each of the above set of products. Maximum pumping rate for the products will be around 2000 KUHr to suit the capacities of pumps available in the ships

At Palanpur, Ajmer, Jaipur, Rewari & Bahadurgarh:

POL products will be received at all the above locations through pipeline from cross-country pipeline station. Individual pipeline is considered for each of the POL product and SLOP. Receipt lines at various stations will be provided to suit the following flow parameters:

(Flow rate in Kl/Kr)

Average Max. Flor Rate

Palanpur 84 667

Ajmer 111 607

Jaipur 129 525

Rewari 105 467

Bahadurgarh 825 825

Page 34: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 34

Annual volume deliveries projected for the year 2011-12 at different terminals is given in Table-2.4.2. Corresponding Batch deliveries & Average daily product off-takes is given in Table-2.4.3 & Table-2.4.4 respectively.

Table-2.4.2 Annual Volume Deliveries at Different Terminals

Annual Volume in KL TOP

MS ULMS HSD ULHSD SKO Total

Palanpur 86840 74731 279005 31773 66486 538836

Ajmer 89148 0 442521 0 24906 556575

Jaipur 0 101077 0 184877 16879 302833

Rewari 47985 0 136182 0 24616 208782

Bahadurgarh 687368 559715 2082283 636094 393238 4358698

Total 911341 735523 2939991 852744 526125 5965724

Table-2.4.3 Batch Deliveries at Different Terminals

Batch Deliveries in KL TOP

MS ULMS HSD ULHSD SKO

Palanpur 3230 2780 2595 295 495

Ajmer 3316 0 4115 0 185

Jaipur -- 3760 0 1719 126

Rewari 1785 0 1266 0 183

Bahadurgarh 25588 20820 19364 5915 2925

Total 33899 27359 27340 7930 3914

Table-2.4.4 Daily Off-takes at Different Terminals

Average Daily Off-takes in KL TOP

MS ULMS HSD ULHSD SKO Total

Palanpur 289 249 930 106 222 1796

Ajmer 297 0 1475 0 83 1855

Jaipur 0 337 0 616 56 1009

Rewari 160 0 454 0 82 696

Bahadurgarh 2291 1866 6941 2120 1311 14529

Page 35: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 35

Total 3038 2452 9800 2842 1754 19885

2.43. Storage Facilities

The storage facilities are planned to suit the minimum requirement of 1 Batch plus 5 days offtake at various locations.

2.4.6 Rail/ Road Loading /Receipt Facilities

Product loading in Road tankers and Rail Tank wagon will be thru loading arms. Contingency provision will also be made for unloading of product from rail/road tankers and pumping into respective storage tanks.

2.4.7 Applicable Codes & Standards

Table 2.4.5 Applicable Codes & Standards

S.No. Code/Standard Applicable for

1. API 650 / IS 803 For above ground storage tanks

2. IS 10987 For underground storage tanks

3. API 5L For product pipes

4. API 1104 For welding of pipelines and related facilities

5. API 1110 Pressure testing of pipelines

6. OISD 117 For fire fighting facilities

7. OISD 118 Layout of Terminal Depots

8. API 600 Gate Valves

9. API 6D Pressure Balanced Plug Valves

10. BS 5351 Ball Valves

11. ASME B 16.9 Pipe Fittings

12. ASME B 16.5 Pipe Flanges

13. API 610 Product Pumps

2.5 Instrumentation, Control & Communication System

2.5.1 Instrumentation & Automation

The major activities performed by terminals/depots are the following:

a. Storage facilities for MS, ULMS, SKO. HSD, ULHSD

Page 36: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 36

b. Receipt of product through pipeline c. Road loading system d. Rail loading/unloading system e. Sump & Slop system f. Fire water pump system and make up water system

Full fledged Terminal Automation System (TAS) is envisaged for these units. These includes:

a. Tank Farm Management System (TFM) b. Terminal data management system c. Bay Queuing d. Tank Truck loading e. Station control system f. Terminal security system (TSS) g. Fire water system h. Borewell/Makeup water pump operation

Automation facilities have been envisaged with a view to ensure safety and ease the operation of most critical areas of the terminals/depots like product receipt, storage and loading. Services requirements such as scheduling invoicing, accounting, sales, stock control, terminal security (restricting entry of unauthorized personnel into licensed area), maintenance etc to be carried out at the terminal shall be taken care of.

TFM Automation

Tank Farm Management System (TFMS) is a part of Terminal Automation System. Each tank shall be provided with Radar type level transmitter, Multi Element averaging temperature sensor, Water/Product interface measurement and pressure transmitters for density measurement. The indication shall be available locally in the tank side display unit and in the TAS in the control room. Underground tanks shall be provided with Radar type level transmitter. Data of the underground tank shall be available on the TAS. Volumetric data of each product shall also be available as a part of tank farm management system.

TLF Pump Automation

Product loading pumps for TLF bay shall be started automatically. No. of pumps in operation is decided by the demand of the product/no. of loading 'bays in operation/flow rate. In case primary pump fails stand by pump shall take over. Pumps can be operated in local mode and remote mode. Pump control is achieved through the PLC. Operations of pump are interlocked with the level of product in the tank.

Page 37: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 37

Fire Water Pump Automation

Fire water pumps shall be diesel engine driven. Pumps shall be activated by pressure switches installed on the fire water header. As the pressure falls below 7 kg/cm2 second pump shall start automatically. Three nos. of firewater pumps are provided for each terminal. At any point of time a maximum of two pumps will be operating. One pump shall be standby. Fire water pump automation is achieved through PLC. It shall be possible to operate the pumps manually too locally and from control room.

Make Up Water Pump Automation

Make up water system may be either by means of bore well pumps / make up water pumps. The pumps shall start automatically whenever the level in any of the two water tanks falls below 15 cm from the max level of the tank. Pumps will stop automatically when the level reaches max level. This operation is achieved through PLC. Necessary alarm logic shall be available in the control room. It shall be possible to operate the pumps manually either locally or from control room.

2.5.2 Shut Down Features

Emergency shut down shall be provided in the marketing terminal/depot control room to stop all dispatch operation. ESD shall be implemented in the PLC logic as part of terminal automation.

Emergency push buttons to stop all road loading operations shall be provided one on either side of the gantry and one in the middle of gantry.

Emergency push buttons to stop all rail loading operations shall be provided one on either side of the rail gantry and one in the middle of gantry.

Emergency push buttons to stop all loading operations in the terminal/depot shall be provided in the control room.

2.5.3 Communication System

Telecommunication system (interfaced with the public address system) along with Plant Communication System (PCS) is envisaged for the terminals. The Communication system shall broadly comprise of the following:

1. Telephone exchange equipment and peripherals (EPABX) 2. Main Distribution Frame 3. Explosion proof and industrial type telephone instruments 4. Centralized Amplifier 5. Loudspeakers 6. Microphones

Page 38: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 38

7. Interconnecting cables and accessories.

An Electronic Private Automatic Branch Exchange (EPABX) equipped for 32 extension with 8 trunk lines and expandable to 64 extension with 16 trunk lines shall be provided. The system shall be interfaced with the public address paging system consisting of Central Exchange equipment and peripherals. The exchange shall be suitable for 48 V DC derived from 230 V, 1 ph 50 Hz, AC and backup power supply obtained from float chargers backed up by a bank of batteries to provide uninterrupted communication during mains power failure for 4 hours. A 100 pair Main Distribution Frame shall be provided in order to serve as a common termination point of the telephone cables network.

The telephones used for the plant shall be of the following types depending in the type of applications:

a. IP -55 enclosures for indoor applications b. IP -65 enclosures for outdoor applications c. Explosion proof type with handset consisting of noise canceling type microphone,

suitable coiled cord, press to operate switch in-built speakers for annunciation for hazardous areas.

Plant Communication System (PCS)

(PCS) shall be PCM/TDM digital exchange with 100% non-blocking type. A centralized power amplifier of adequate capacity with redundancy shall be provided along with exchange. The power amplifier shall be located in the exchange room. The loud speakers shall be Re-entrant horn type of rating 25 Watts for outdoor locations and Cone type of rating 5 Watts for indoor use.

Paging

The system shall employ two modes of operations i.e. Page mode & Party mode. The paging function shall be accomplished by means of a central redundant amplifier and an array of speakers connected to this amplifier. Box type loudspeakers shall be provided for indoor applications. For outdoor applications industrial horn type along with driver unit (flame proof / non-flame proof) shall be provided. Party mode shall be a close talk communication used for prolonged conversation between two or more selective stations as desired without broadcasting the same over the loudspeakers.

2.6 Fire protection system for all terminals

2.6.1 System Description

The following fire protection facilities are envisaged at all terminals as per the requirements of OISD-117:

a. Fire Water System - Pressurized b. Foam system

Page 39: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 39

c. First Aid Fire Fighting Equipment and safety accessories d. Mobile Fire Fighting Equipment

2.6.2 Fire Protection Facilities

The facilities provided consist of the following units

1. Fire Water Storage Tanks 2. Fire water Pumps and Jockey Pumps 3. Fire water Piping 4. Fire Hydrants 5. Fixed Foam System 6. Water/foam Monitors 7. Fixed water Spray Systems 8. Mobile Fire Fighting Equipment 9. Portable extinguishers

The design of the fire water system shall be based on one single largest risk. Table-2.6.1 presents the requirements of firewater tanks and pumps at different locations.

Table-2.6.1 Proposed Fire Water Tanks & Fire Fighting Pumps at Terminals

Fire Water Tank Fire Water Pumps Terminal

Capacity Dia x Ht (m) No. Capacity

Mudra Terminal 2 x 3500 KL 20 x 13 3W + 2S 410 m3 /hr

Palanpur Terminal 2 X 2000 KL 14 x 14 2W + 1S 410 m3 /hr

Ajmer Terminal 2 X 2000 KL 14 x 14 2W + 1S 410 m3 /hr

Jaipur Terminal 2 X 2000 KL 14 x 14 2W + 1S 410 m3 /hr

Rewari Terminal Existing Existing

Bahadurgarh Terminal 2 x 3500 KL 18 x 16.5 3W + 2S 670 m3 /hr * DCP/C02 extinguishers, water/foam monitors, personnel provided as per the prevailing also norms.

2.6.3 Fire Detection & Alarm System

The system shall comprise of a 2 loop intelligent fire alarm control panel, detectors (smoke & heat), manual call points with necessary enclosures (IP-55 for indoor applications, IP-65 for outdoor applications and explosion proof enclosures for Hazardous areas), hooters, cables and accessories.

Fire Alarm Control Panel: A 2-loop panel with an in-built battery charger shall be provided. The Fire alarm Panel shall be located in the control room. The panel shall operate on 24V DC off 230V, 1 Ph AC power supply and backed up by 4 hours battery bank. These batteries shall be of SMF lead acid type.

Page 40: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 40

Detectors: Photoelectric smoke and fixed cum rate of rise heat detectors shall be provided. The detectors shall operate on 24 VDC supply derived from the panel. The control room shall be provided with photoelectric type smoke detectors. In places like Electrical/ MCC room a combination of fixed cum rate of rise heat and photo electric smoke detectors shall be provided. Detectors above false ceiling shall be provided with response indicators.

Manual Call Points: Addressable break glass type manual call points with monitor modules shall be provided at the exits, walkways and staircase landings of each buildings.

Repeater Panel: The repeater panel shall be located at an appropriate location so as to mimic all the displays on the main fire alarm panel. Zone wise indication shall be considered in the mimic panel.

Remote Response Indicators: These shall be provided so as to monitor the detector status in closed premises. The Remote Response Indicators shall comprise of red LED lamp enclosed in a plastic cover and fitted inside a MS box and engraved "FIRE" on the plastic cover.

Cables/Conduits: All cables shall be multicore, stranded, annealed copper conductor, PVC insulted PVC inner sheath and with PVC outer sheath and GI round wire as armour. 25 mm dia, 2 mm thick M.S. conduits shall be considered wherever necessary for cables crossing through walls. Cables inside conduits shall be armoured.

2.7 Utilities

2.7.1 Power Supply Arrangement

Power requirement will be fulfilled from the local grid. Provision for DG set will be kept as backup arrangement for emergency power only. The estimated power requirement is given in Table-2.7.1.

Table-2.7.1 Power Supply Arrangement

Station Requirement (KVA) Source Back up DG Set for

Emergency Power (KVA) Mundra 250 66 KV (Gnd) 320 Palanpur 420 66 KV (Grid) 525

Ajmer 400 132 KV (Grid) / 33 KV (Grid) 525

Jaipur 280 33 KV (Grid) 445 Rewari* 30 33 KV (Grid) Existing Bahadurgarh 690 11 KV (Grid) 960

* Additional power requirement in existing Rewari Terminal

Page 41: Del Him Undr a Pipeline Project

Detailed Report on Delhi-Mundra Pipeline Project

Document is made available by http://www.infraline.com 41

2.7.2 Make Up Water System

The source of water for the make up water system is borewells. Water from the borewell will be collected in a sump. From the sump water will be pumped by self priming pumps installed on top of the sump and disturbed through a network of buried GI pipes to individual HOPE overhead tanks of Amenities buildings, Admin. building, drivers rest room etc. and to the fire water storage tanks.

2.7.3 Effluent Treatment Plant (ETP)

The Effluent Treatment Plant receives oily water through a separate drain line connecting tank farms, TT Gantry area, Pump house manifold area etc. The plant includes a Primary separation unit consisting of a bar screen, Titled Plate Interceptor and Belt type oil Skimmer. Subsequently Effluent will be pumped to Filtration unit using a multimedia filter and coalescing filter. The slop oil collected will be pumped to the slop tank. The capacity of the ETP will be 100 KL/hr.