decision authorizing long-term procurement for …
TRANSCRIPT
89008104 - 1 -
ALJ/DMG/avs Date of Issuance 3/14/2014
Decision 14-03-004 March 13, 2014
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Order Instituting Rulemaking to Integrate and Refine Procurement Policies and Consider Long-Term Procurement Plans.
Rulemaking 12-03-014 (Filed March 22, 2012)
DECISION AUTHORIZING LONG-TERM PROCUREMENT FOR LOCAL CAPACITY REQUIREMENTS DUE TO PERMANENT RETIREMENT OF THE
SAN ONOFRE NUCLEAR GENERATIONS STATIONS
R.12-03-014 ALJ/DMG/avs
- i -
TABLE OF CONTENTS Title Page DECISION AUTHORIZING LONG-TERM PROCUREMENT FOR LOCAL CAPACITY REQUIREMENTS DUE TO PERMANENT RETIREMENT OF THE SAN ONOFRE NUCLEAR GENERATION STATIONS ............................................ 2
1. Summary ................................................................................................................... 2 2. Background ............................................................................................................... 5
2.1. Procedural Background ................................................................................. 5 2.2. Statutory Requirements, Energy Action Plan
and the Loading Order ................................................................................ 12 2.3. Motions to Strike Briefs and Reply Briefs ................................................. 16
3. Long-Term Local Capacity Requirements in the SONGS Study Area .......... 22 3.1. Joint Comparison Exhibit ............................................................................ 22 3.2. Discussion Overview .................................................................................... 22 3.3. Potential Forecast Adjustments .................................................................. 28
3.3.1. Track 1 SCE Procurement Authorization ....................................... 28
3.3.2. SDG&E Procurement Authorization .............................................. 30
3.3.3. Reactive Power and VAR Support .................................................. 31
3.3.4. Demand Forecast ............................................................................... 34
3.3.5. Load Shedding ................................................................................... 36
3.3.6. Category C vs. Category D ............................................................... 47
3.3.7. Transmission Solutions ..................................................................... 49
3.3.8. Demand Response ............................................................................. 53
3.3.9.nergy Storate ........................................................................................ 58
3.3.10. Energy Efficiency ............................................................................. 62
3.3.11. Solar Photovoltaic (PV) ................................................................... 63
3.3.12. Living Pilot ....................................................................................... 65
4. Need Determination .............................................................................................. 66 5. Filling the Identified Need ................................................................................... 87
5.1. Requirement for Procurement of Preferred Resources ........................... 87 5.2. Energy Storage .............................................................................................. 99 5.3. Large Scale Pumped Storage (Bulk Storage) Procurement .................. 100 5.4. Contingency (Options) Contracts ............................................................. 102
6. Conditions for Procurement .............................................................................. 107 6.1. Procurement Process .................................................................................. 107 6.2. Solicitation Requirements .......................................................................... 113
7. 2013/2014 TPP Update ....................................................................................... 115
R.12-03-014 ALJ/DMG/avs
- ii -
TABLE OF CONTENTS (Con't.)
Title Page
8. Cost Allocation Mechanism ............................................................................... 117 9. Comments on Proposed Decision ..................................................................... 122 10. Assignment of Proceeding ............................................................................... 123
Findings of Fact ............................................................................................................. 123 Conclusions of Law ...................................................................................................... 135 ORDER ........................................................................................................................... 141 ATTACHMENT A – Joint Exhibit ATTACHMENT B -- SDG&E Procurement Plan Requirements
R.12-03-014 ALJ/DMG/avs
- 2 -
DECISION AUTHORIZING LONG-TERM PROCUREMENT FOR LOCAL CAPACITY REQUIREMENTS DUE TO PERMANENT RETIREMENT OF THE
SAN ONOFRE NUCLEAR GENERATION STATIONS 1. Summary
This is the Track 4 decision in the 2012 long-term procurement proceeding.
In this decision, we authorize Southern California Edison Company (SCE) to
procure between 500 and 700 Megawatts (MW), and San Diego Gas & Electric
Company (SDG&E) to procure between 500 and 800 MW by 2022 to meet local
capacity needs stemming from the retired San Onofre Nuclear Generation
Stations (SONGS). SCE is required to procure at least 400 MW, and may procure
up to the full 700 MW of authorized additional capacity, from preferred
resources or energy storage. SDG&E is required to procure at least 200 MW, and
may procure up to the full 800 MW of authorized additional capacity, from
preferred resources or energy storage.
Consistent with Decision (D.) 13-02-015, the 2013 Track 1 decision in this
proceeding authorizing procurement by SCE in the LA Basin, this decision
provides “buckets” of procurement for preferred resources (such as renewable
power, demand response resources and energy efficiency), energy storage and
gas-fired resources. Combining Track 1 and Track 4 procurement authority, SCE
is authorized to procure between 1,900 and 2,500 MW in the LA Basin. SCE is
required to procure up to 60% of new local capacity in the LA Basin from
preferred resources. SDG&E is required to procure at least 25% -- and up to
100% -- of new local capacity from preferred resources. SCE and SDG&E are
required to procure at least 50 MW and 25 MW, respectively, from energy
storage. The following charts show the procurement levels for each utility. The
procurement authorized by this decision as well as the Track 1 and Pio Pico
R.12-03-014 ALJ/DMG/avs
- 3 -
(D.14-02-016) decisions will offset the retirement of the 2,200 MW SONGS facility
and nearly 5,900 MW of once-through cooling plants.
SCE Procurement Authorization And Requirements (Track 1 + Track 4)
Resource Type
Track 1 LCR
Resources
(D.13-02-015)
Additional Track 4
Authorization
Total
Authorization
Preferred Resources
Minimum
Requirement
150 MW 400 MW 550 MW
Energy Storage
Minimum
Requirement
50 MW -- 50 MW
Gas-fired Generation
Minimum
Requirement
1000 MW -- 1000 MW
Optional Additional
From Preferred
Resources/Energy
Storage Only
Up to 400MW Up to 400 MW
Additional from any
Resource
200 MW 100 to 300 MW 300 to 500 MW
Total Procurement
Authorization
1400 to 1800
MW 500 to 700 MW 1900 to 2500 MW
R.12-03-014 ALJ/DMG/avs
- 4 -
SDG&E Procurement Authorization and Requirements
Resource Type D.13-03-029/
D.14-02-016
Additional Track 4
Authorization
Total
Authorization
Preferred
Resources
(including energy
storage)
Minimum
Requirement
--- 175 MW 175 MW
Energy Storage
Minimum
Requirement
--- 25 MW 25 MW
Additional from
any resource
300 (Pio Pico) 300 to 600 MW 600 to 900 MW
Total Procurement
Authorization
300 MW 500 to 800 MW 800 to 1100 MW
SCE is authorized to use the procurement process approved in Track 1 of
this Rulemaking to procure capacity for the purposes of both Track 1 and
Track 4. SCE is expected to file an application for approval of up to 2,500 MW of
local capacity resources later in 2014. SDG&E is authorized to solicit
procurement offers through an all-source RFO and bilateral negotiations, subject
to Energy Division approval of its procurement process. SCE and SDG&E may
propose options or contingency contracts in their procurement applications, or
separate applications, subject to responses to specific inquiries. SDG&E is
strongly encouraged to develop a Living Pilot for preferred resources similar to
the one proposed by SCE.
Both SCE and SDG&E are authorized to include the costs of the
procurement authorized today through the Cost Allocation Mechanism,
R.12-03-014 ALJ/DMG/avs
- 5 -
consistent with its established rules, and/or other applicable procurement cost
allocation processes.
2. Background
2.1. Procedural Background
This proceeding is the successor proceeding to rulemakings dating back to
2001 intended to ensure that California’s major investor-owned utilities (IOUs)
can maintain electric supply procurement responsibilities on behalf of their
customers. The most recent predecessor to this proceeding was Rulemaking
(R.) 10-05-006. As stated in the order originating this rulemaking in Ordering
Paragraph 3, the record developed in R.10-05-006 is “fully available for
consideration in this proceeding” and is therefore incorporated into the record of
this proceeding.
In the Scoping Memo for this proceeding, issued on May 17, 2012, the
general issues for the 2012 procurement planning cycle were divided into three
topics1:
1. Identify Commission-jurisdictional needs for new resources to meet local or system resource adequacy (RA), renewable integration, or other requirements and to consider authorization of investor-owned utility (IOU) procurement to meet that need. This includes issues related to long-term renewable planning and need for replacement generation infrastructure to eliminate reliance on power plants using once-through cooling technology (OTC);
1 Scoping Ruling at 5.
R.12-03-014 ALJ/DMG/avs
- 6 -
2. Update, and review individual IOU bundled procurement plans consistent with Public Utilities Code Section 454.5;2 and
3. Develop or refine procurement rules that were not resolved in R.10-06-005, and consider other emerging procurement policy topics.
The Scoping Memo divided the proceeding into three Tracks. Track 1
considered issues related to the overall long-term need for new local reliability
resources to meet long-term local capacity requirements (LCRs) through 2022.
Such long-term LCRs are expected to result from the retirement of approximately
5,900 Megawatts (MW) from current once-through cooling generators in the Los
Angeles (LA) Basin, and approximately 900 MW in the San Diego local area, to
comply with State Water Quality Control Board regulations. Other changes in
supply and demand over time will also impact long-term LCRs.
The Track 1 decision, Decision (D.) 13-02-015, authorized Southern
California Edison Company (SCE) to procure between 1,400 and 1,800 MW of
electrical capacity in the West Los Angeles sub-area of the LA Basin local
reliability area to meet long-term local capacity requirements (LCRs) by 2021.
For the defined portion of the LA Basin local area, at least 1,000 MW, but no
more than 1,200 MW, of this capacity was to be procured from conventional gas-
fired resources. At least 50 MW was to be procured from energy storage
resources. At least 150 MW of capacity was to be procured through preferred
resources3 consistent with the Loading Order in the Energy Action Plans. SCE
2 All statutory references are to the Public Utilities Code, unless otherwise noted.
3 Preferred Resources are defined in the State’s Energy Action Plan II, at 2, as follows: “The loading order identifies energy efficiency and demand response as the State's preferred means of meeting growing energy needs. After cost-effective efficiency and
Footnote continued on next page
R.12-03-014 ALJ/DMG/avs
- 7 -
was also authorized to procure up to an additional 600 MW of capacity from
preferred resources and/or energy storage resources. In addition, SCE was
required to continue to obtain resources that can be used in these local reliability
areas through processes defined in energy efficiency, demand response,
renewables portfolio standard, energy storage and other relevant dockets. SCE
was also authorized to procure between 215 and 290 MW in the Moorpark sub-
area of the Big Creek/Ventura local reliability area.
D.13-02-015, Ordering Paragraph (OP) 11 required that SCE file one
Application for approval of any and all contracts entered into as a result of the
procurement process authorized by this decision for the Los Angeles basin local
reliability area, and one Application for these purposes for the Big
Creek/Ventura local reliability area. An exception was made if SCE’s
procurement plan, as approved by Energy Division, provided for one separate
and earlier Application to procure gas-fired generation for both local reliability
areas. The Applications were to specify how the totality of the contracts met
criteria specified in OP 11. SCE’s procurement plan was approved by
demand response, we rely on renewable sources of power and distributed generation, such as combined heat and power applications. To the extent efficiency, demand response, renewable resources, and distributed generation are unable to satisfy increasing energy and capacity needs, we support clean and efficient fossil-fired generation. Concurrently, the bulk electricity transmission grid and distribution facility infrastructure must be improved to support growing demand centers and the interconnection of new generation, both on the utility and customer side of the meter.” Energy Storage is a potential enabling technology, but is not a Preferred Resource because it stores power regardless of how that power is produced. However, in this decision, we also include Energy Storage in the category of Preferred Resources for ease of use unless otherwise noted.
R.12-03-014 ALJ/DMG/avs
- 8 -
Energy Division in August 2013. SCE currently expects to file applications
resulting from Track 1 solicitations later in 2014.
Track 2 of R.12-03-014 considered procurement of system reliability
resources for the three major electric IOUs. D.12-12-010 adopted final
Standardized Planning Assumptions and Scenarios for Track 2. Modeling results
pertaining to flexible resources have not been formally considered by the
Commission because the ISO stated at a September Prehearing Conference
(PHC) that it was not prepared to submit testimony on the topic. Therefore, a
Ruling issued on September 16, 2013 deferred Track 2 to a new 2014 Long-Term
Procurement Plans (LTPP) Rulemaking, stating “[b]efore Track 4 was initiated, it
was anticipated that Track 2 would be informed by the Track 1 local capacity
requirements decision. With the addition of Track 4, it makes sense to also
consider local capacity procurement authorized in Track 4 in determining system
flexibility needs.” The Ruling anticipated system reliability issues related to
flexibility would be considered in the 2014 LTPP Rulemaking.
Track 3 of R.12-03-014 considered a number of rule and policy issues
related to IOUs’ procurement practices. D. 14-02-040 was approved by the
Commission on February 27, 2014.
A revised Scoping Memo dated March 21, 2013 in R.12-03-014 initiated
Track 4 in this proceeding to consider additional resource needs relate to the
long-term outage (and subsequent permanent closure in June 2013) of the
San Onofre Nuclear Generation Station, Units 2 and 3 (SONGS). This is the
decision for Track 4 of this proceeding.
This decision is a follow-up to the Track 1 decision in this proceeding, but
is more narrowly focused on local capacity requirements in what is known as the
R.12-03-014 ALJ/DMG/avs
- 9 -
SONGS study area. This area consists of all of the territory of San Diego Gas and
Electric Company (SDG&E), and the LA Basin portion of SCE’s territory.
Generally, we consider new developments related to supply and demand
as a matter of course in our bi-yearly LTPP proceedings. The June 2013
permanent retirement of SONGS (following its initial shutdown in 2012)
presented a unique and highly significant event. Until 2012, SONGS had
supplied 2,246 MW of greenhouse gas (GHG)-free base load power to the
LA Basin and San Diego and played an important role in system stability in the
San Diego Local Area. The issues of ensuring local reliability and system
stability in San Diego and the LA Basin while continuing to meet the State’s GHG
goals justified expedited reconsideration of capacity needs in the SONGS study
area. Track 4 of the 2012 LTPP was opened to grapple with these issues.
At the September 4, 2013 PHC, Administrative Law Judge (ALJ) Gamson
noted that the California Independent System Operator (ISO or CAISO) in its
August 5, 2013 Track 4 testimony called for deferring Track 4 until after results of
the ISO’s 2013/2014 Transmission Planning Process (TPP) would be available.
The ISO stated that it would be able to provide testimony as to the transmission
alternative study results (including reactive power needs) as soon as
January 2014.4 However, the final TPP was not expected to be available until
March 2014. Per the ISO’s initial recommendation, a decision on Track 4 would
not occur until the 2nd or 3rd quarter of 2014.5
4 A draft 2013/2014 TPP was issued in early February 2014.
5 The ISO now recommends authorization of procurement amounts at this time, as discussed herein.
R.12-03-014 ALJ/DMG/avs
- 10 -
The September 16, 2013 Assigned Commissioner/ALJ Ruling noted that
the 2013/2014 TPP is expected to provide useful information to inform the
Commission regarding a decision on both the level and type of resources to
replace SONGS capacity in the long run. The Ruling agreed with the comments
of most parties that the determination of the level and type of need to replace
SONGS capacity over the long-term should take the TPP into account in making
this decision. At the same time, due to long lead times for new resources, the
Ruling determined that there it was urgent to start identify and fill any identified
need as soon as possible. Therefore, the Ruling established a streamlined
schedule to provide guidance and direction to SCE and SDG&E to allow these
utilities to move forward on a complex and multi-year procurement process.
Under this process, this Track 4 decision will not include the TPP results
expected in the first quarter of 2014.
Some parties continue to argue that the Commission should not make a
decision on additional procurement related to the SONGS retirement at this time.
For example, CEERT states: “The bottom line is, particularly without the benefit
of updated assumptions to mirror critical near-term information (i.e., the
2013-2014 TPP results) that can impact mitigation options that could reduce or
meet LCR need other than procuring more conventional gas-fired generation, the
Commission simply does not now have a reliable record for making any Track 4
GFG procurement authorization for either SCE or SDG&E in January 2014,
whether “interim” or not.”6
6 CEERT Opening Brief, at 20.
R.12-03-014 ALJ/DMG/avs
- 11 -
As discussed herein, we determine that it is necessary to authorize
additional procurement at this time. The 2013/2014 TPP results are expected to
be complete by March 2014. However, further procedural activities in this
docket would necessitate at least several months to fully develop a record to
incorporate the new TPP results. With long lead-time resources requiring several
years of effort, and potential reliability issues surfacing starting in 2018, we
cannot wait for further information at this point. Further, additional information
inevitably becomes available as time passes. It is simply not possible to both
incorporate all information and make timely decisions. However, knowing the
TPP results are soon to be available and that additional transmission solutions
may impact future LCR needs (by lowering local procurement requirements), we
will take a cautious approach to avoid over procurement.
The ISO served its testimony on August 5, 2013. SCE, SDG&E, Office of
Ratepayer Advocates (ORA) and the City of Redondo Beach served testimony
including modeling studies on August 26, 2013. Comments on questions from
the ALJ at the September 4, 2013 PHC were filed on September 30, 2013, with
reply comments on October 14, 2013. Opening testimony and testimony in
response to modeling parties’ testimony was served on September 30, 2013.
Rebuttal testimony was served on October 14, 2013.7 Evidentiary hearings were
held October 28 through November 1, 2013. Briefs were filed on
November 25, 2013 and Reply Briefs were filed on December 16, 2013. This track
of the proceeding was submitted on December 16, 2013.
7 Certain parties served supplemental and other versions of testimony on other dates with permission of the ALJ.
R.12-03-014 ALJ/DMG/avs
- 12 -
The parties which served testimony in Track 4 of this proceeding are8:
AES Southland LLC (AES Southland), Alton Energy Inc. (Alton Energy),
California Energy Storage Association (CESA), California Environmental Justice
Alliance (CEJA), California Large Energy Consumers Association (CLECA),
Calpeak Power, LLC (Calpeak), Center for Energy Efficiency and Renewable
Technologies (CEERT), City of Redondo Beach (Redondo Beach), Clean
Coalition, Direct Access Customer Coalition/Alliance for Retail Energy Markets
(DACC/AReM or AReM/DACC), Eagle Crest Energy Company (Eagle Crest),
EnerNOC, Independent Energy Producers Association (IEP), the ISO,
Environmental Defense Fund (EDF), Marin Clean Energy (also known as Marin
Energy Association or MEA); Natural Resources Defense Council (NRDC), NRG
Energy (NRG), ORA,9 Pacific Gas & Electric (PG&E), Protect Our Communities
Foundation (POC), SCE, SDG&E, Sierra Club California (Sierra Club), The Utility
Reform Network (TURN), Western Power Trading Forum (WPTF), The Vote
Solar Initiative (Vote Solar) and Wellhead Electric Company, Inc. (Wellhead).
Testimony from each of these parties was received into evidence at the
evidentiary hearing.
2.2. Statutory Requirements, Energy Action Plan and the Loading Order
In considering long-term procurement, the Commission must address a
variety of policy and legal concerns. While a primary responsibility of the
Commission is to ensure safety and reliability in the electrical system, that
8 Parties serving testimony that was subsequently stricken from the record are not included in this list.
9 Formerly known as Division of Ratepayer Advocates.
R.12-03-014 ALJ/DMG/avs
- 13 -
responsibility must be balanced with other statutory and policy considerations.10
Specifically, the Commission has a statutory duty to ensure that customers
receive reasonable services at just and reasonable rates,11 and to protect the
environment from deleterious impacts from utility facilities under our
jurisdiction.
California law repeatedly emphasizes the importance of maintaining the
reliability of the electric grid. For example:
“Reliable electric service is of utmost importance to the safety, health, and welfare of the state’s citizenry and economy.” (§ 330(g).)
“It is important that sufficient supplies of electric generation will be available to maintain the reliable service to the citizens and businesses of the state.” (§ 330(h).)
“Reliable electric service is of paramount importance to the safety, health, and comfort of the people of California.” (§ 334.)
The CAISO “shall ensure efficient use and reliable operation of the transmission grid” (§ 345) and shall “ensure the reliability of electric service and the health and safety of the public.” (§ 345.5(b).)
The Commission “shall ensure that facilities needed to maintain the reliability of the electric supply remain available and operational.” (§ 362(a).)
The Commission also has a statutory mandate to implement procurement-
related policies to protect the environment. Section 454.5(b)(9)(C) states that
utilities must first meet their “unmet resource needs through all available energy
efficiency and demand reduction resources that are cost-effective, reliable and
10 D.13-02-015 at 35.
11 Pub. Util. Code § 454.5. All statutory references are to the Public Utilities Code unless otherwise noted.
R.12-03-014 ALJ/DMG/avs
- 14 -
feasible.” Consistent with this code section, the Commission has held that all
utility procurement must be consistent with the Commission’s established
Loading Order, or prioritization. The Loading Order, first set forth in the
Commission’s 2003 Energy Action Plan, was presented in the Energy Action
Plan II adopted by this Commission and the California Energy Commission
(CEC) in October 2005. The Loading Order, which has been reiterated in
multiple forums (including D.12-01-033 in the predecessor to this docket, and
D.13-02-015 in this docket), requires the utilities to procure resources in a specific
order:
“The ‘Loading Order’ established that the state, in meeting its energy needs, would invest first in energy efficiency and demand-side resources, followed by renewable resources, and only then in clean conventional electricity supply.” (Energy Action Plan 2008 Update at 1.)
In the 2008 Energy Action Plan Update at 20, the Commission further
interpreted this directive to mean that the IOUs are obligated to follow the
Loading Order on an ongoing basis. Once procurement targets are achieved for
preferred resources, the IOUs are not relieved of their duty to follow the Loading
Order. In D.07-12-052 at 12, the Commission stated that once demand response
and energy efficiency targets are reached, “the utility is to procure renewable
generation to the fullest extent possible.” The obligation to procure resources
according to the Loading Order is ongoing.12 In D.12-01-033 at 21, the
Commission recognized that procuring additional preferred resources is more
difficult than “just signing up for more conventional fossil fuel generation,” but
12 D.12-01-033 at 19.
R.12-03-014 ALJ/DMG/avs
- 15 -
consistency with the Loading Order and advancing California’s policy of fossil
fuel reduction demand strict compliance with the loading order.
This clarified Loading Order is a departure from the Commission’s
previous position of procuring energy efficiency and demand response, then
renewable energy, and then allowing “additional clean, fossil-fuel, central-station
generation,” because “preferred resources require both sufficient investment and
adequate time to ‘get to scale.’”13 Instead of procuring a fixed amount of
preferred resources and then procuring fossil-fuel resources, the IOUs are
required to continue to procure the preferred resources “to the extent that they
are feasibly available and cost effective.”14 While procuring a fixed amount of
preferred resources provides flexibility and a clearer idea of how to approach the
procurement process, the Loading Order approach is more consistent with
Commission policy.
In D.13-02-015, Ordering Paragraph 4 required that any Requests for
Offers (RFO) issued by SCE pursuant to that decision must include 12 elements,
including “provisions designed to be consistent with the Loading Order
approved by the Commission in the Energy Action Plan and to pursue all
cost-effective preferred resources in meeting local capacity needs.” Ordering
Paragraph 11 (which required SCE to file one or more applications for resource
procurement authorized by that decision) required that SCE follow five criteria
including: “Consistency with the Loading Order, including a demonstration that
it has identified each preferred resource and assessed the availability, economics,
13 D.04-06-011, footnote 22, at 31.
14 D.12-01-033 at 21.
R.12-03-014 ALJ/DMG/avs
- 16 -
viability and effectiveness of that supply in meeting the LCR need.” We
maintain our commitment to the Loading Order in this decision.
2.3. Motions to Strike Briefs and Reply Briefs
As discussed in detail in this section, several Motions were filed to strike
all or part of Opening or Reply Briefs. SCE filed Motions to Strike the Opening
Briefs of Nevada Hydro and MEA, and a Motion to Strike Portions of the
Opening Brief of Redondo Beach. SCE and SDG&E jointly filed a Motion to
Strike the Opening Brief of POC. PG&E and SDG&E both filed Motions to Strike
Portions of the Opening Brief of MEA. In addition, SCE and SDG&E jointly filed
a Motion to Strike the Reply Brief of POC.
The revised Scoping Memo stated at page 4:
“Track 4 will consider the local reliability impacts of a potential long-term outage at the San Onofre Nuclear Power Station (SONGS) generators, which are currently not operational. The CAISO is developing a study to assess both the interim (2018) and long-term (2022) local reliability needs in the Los Angeles Basin local area and San Diego sub-area resulting from an extended SONGS outage.”
Generally, all relevant evidence is admissible unless otherwise provided
by law. (Cal. Evid. Code, Sec. 350.) Per Rule 7.3 of the Rules of Practice and
Procedure, the explanation of the issues to be considered in a particular
Commission proceeding is ordinarily provided in a scoping memo. Here, the
assigned Commissioner issued an initial scoping memo on May 17, 2012 and a
revised scoping memo on May 21, 2013. The revised scoping memo specifically
at 4-5 noted that Track 4 would not address general system operational needs
and procurement processes.
Rule 13.6(a) provides that although not all technical rules of evidence need
be applied in Commission proceedings, “substantial rights of the parties shall be
R.12-03-014 ALJ/DMG/avs
- 17 -
preserved.” Rules 13.7 and 13.8 provide details regarding the submission of
exhibits and prepared testimony as evidence in Commission proceedings.
Rule 13.8(b) provides that substantially modified testimony beyond that
provided in prepared testimony shall not be admitted into evidence absent
explanation of why the additional testimony could not have been included with
the original testimony or other reason why the additional testimony should be
admitted. Rule 13.8(d) requires that prepared testimony must be served on
parties.
On December 2, 2013, SCE filed a motion to strike portions of Opening
Brief of Redondo Beach regarding Track 4 (SCE/Redondo Motion) on the basis
that various sections of the Brief relied upon evidence not supported by the
record of the proceeding. Such allegedly unsupported analysis included specific
details regarding Redondo Beach’s power flow analysis. (See SCE/Redondo
Motion at 2.)
On December 12, 2013, Redondo Beach filed an opposition to the
SCE/Redondo Motion (Redondo Response), urging that the motion should be
denied because the evidence that is the subject of SCE’s motion was submitted
as, or attached to the testimony of, Redondo Beach’s expert witness Firooz
and/or was submitted as part of Redondo Beach’s production of analysis in
response to SCE data request. (See Amended Opening Testimony of Jaleh Firooz
on behalf of the City of Redondo Beach, dated October 25, 2013 and Attachment;
and see Redondo Response at 5.) Redondo Beach further argues that because SCE
included argument in its Track 4 Rebuttal Testimony criticizing the substance of
Redondo Beach’s power flow analysis, it would violate due process of law to
both strike Redondo Beach’s analysis as well as attempt to bolster its own case by
attacking the same testimony.
R.12-03-014 ALJ/DMG/avs
- 18 -
Here, the evidence that is the subject of the SCE/Redondo Motion is
directly related to studies of the local reliability of the SCE and SDG&E local
areas by various parties. Such information appears in Redondo Beach’s
Amended Opening Testimony, allowing SCE the opportunity to attack the
validity of such analysis. SCE did in fact attack the validity of Redondo Beach’s
testimony, and thus was not deprived of the ability to review and criticize such
evidence. Thus, the SCE/Redondo Motion is denied in its entirety.
SCE and SDG&E each filed Motions onto strike large portions of the
opening brief of MEA on December 4 and December 5, 2013, respectively.
SDG&E’s filing expressed that it supported SCE’s Motion to strike in its entirety
(we therefore refer to the two motions as the SCE/MEA Motion). PG&E also
filed a Motion supporting SCE’s Motion to Strike, and also identifying additional
segments of the MEA brief that it urged should be stricken due to lack of factual
basis in the record. The Motions claim that specified portions of MEA’s brief are
not supported by the evidentiary record and that MEA improperly introduces
for the first time in Section VIII.C. of its opening brief a new proposal regarding
the general application of the CAM to Community Choice Aggregators (CCAs).
The SCE/MEA Motion observes that MEA presented no testimony in Track 4 of
this proceeding.
MEA filed a response (MEA Response) to all of the IOU’s Motions to strike
on December 12, 2013, including responses to each IOU’s individual criticisms.
MEA also included a chart containing its explanations for the admissibility of
each portion of its opening brief that SCE requested to be stricken, attached to its
Motion as Appendix A.
As reflected in Appendix A of MEA’s response to the SCE/MEA Motion,
all of MEA’s discussion that the utilities requested to be stricken are discussions
R.12-03-014 ALJ/DMG/avs
- 19 -
of the effects of CAM on CCA’s in general rather than discussion of the subject of
Track 4: local reliability issues raised by the closure of the SONGS facility. For
example, MEA argues, “CAM exists as a separate procurement mechanism that
must be integrated into the larger whole of the Commission’s RA procurement
processes in order to ensure fair implementation of all procurement tools.”
(MEA Response, Appendix A at 18.) MEA itself acknowledges that “the
Commission will examine CAM methodology in Track 3 of this proceeding.”
(MEA Response, Appendix A at 14.) Similarly, regarding MEA’s allegedly new
proposal regarding how the CAM should be applied to CCA customers, MEA
concedes that its opening brief in Track 4 addresses “the greater issue of whether
and how the CAM should be applied to CCA customers.” (MEA Motion at 2.)
Further, many of the alleged bases for the admissibility of MEA’s
assertions of fact are legally problematic. California rules of evidence provide
that only “[f]acts and propositions of generalized knowledge that are so
universally known that they cannot reasonably be the subject of dispute” may be
admitted into evidence through judicial notice. (Cal. Evid. Code, Sec. 451, subd.
(f); see generally Cal. Evid. Code, Secs. 450 and 451.) The fact that MEA cites to
various online news articles and websites to support many of its factual
assertions tends to indicate that such matters are not in fact universally known.
The IOU Motions to strike filed against MEA are granted because the
stricken language is not relevant to the scope of Track 4. The briefing of issues
that are not relevant to the express subject of a particular stage of briefing wastes
the time and resources of both parties and Commission staff.
POC filed a Motion for Official Notice of three documents on
November 4, 2013. Specifically, those documents were “Reliability Performance
Evaluation Working Group – Phase I Probabilistic Based Reliability Criteria
R.12-03-014 ALJ/DMG/avs
- 20 -
Implementation Procedure,” dated June 14, 2001 (Previously marked for the
record as POC-4); “Seven Step Process for Performance Category Upgrade
Request,” Dated October 2004 (Previously marked for the record as POC-5); and
“WECC Board of Directors Request Regarding Performance Category Upgrade
Request,” Dated February 20, 2013 (Previously marked for the record as POC-6).
The Joint Utilities filed on November 6, 2013 a Joint Response to the Motion of
POC on the basis that the documents did not qualify for Judicial Notice pursuant
to Commission Rules of Practice and Procedure, Rule 13.9 and California
Evidence Code, Sections 450 et seq.; and further, were not relevant because they
predated current NERC standard or were otherwise not applicable to the facts at
hand. ALJ Gamson issued an e-mail Ruling on November 14, 2013, denying
POC’s request for Official Notice of those exhibits. This Ruling is affirmed.
On December 4, 2013, SCE and SDG&E filed a joint motion (Joint Motion)
to strike portions of the POC Opening Brief because the specified portions relied
upon evidence which the ALJ had deemed inadmissible by the November 14
Ruling. POC filed a response to the Joint Motion arguing that the Joint Motion
was overly broad and that some of the materials that were requested to be
stricken properly relied upon evidence in the record.
POC’s Response belies the content of its Opening Brief. In fact, the
sections referenced in the Joint Motion discuss the stricken exhibits POC-4,
POC-5, as well as an unnamed source (POC Opening Brief, at 16, fn. 27 provides
the source of a quote as “xxxxx at 8.”). The Joint Motion is thus granted, and the
referenced portions of the POC Opening Brief are stricken.
SCE filed a Motion to Strike Portions of the Opening Brief of Nevada
Hydro (SCE/NHC Motion) on December 4, 2013, on the basis that specified
segments of the brief attempted to support Commission approval of two
R.12-03-014 ALJ/DMG/avs
- 21 -
proposed grid additions (known as LEAPS and TE/VS Interconnect) that NHC
urged would help fulfill resource needs created by the shutdown of SONGS.
SCE argued that parties “have not been provided the opportunity to examine
LEAPS or the TE/VS Interconnect projects through discovery, testimony or
evidentiary hearings.” (NHC Motion at 2.)
NHC filed its Motion Opposing the SCE/NHC Motion (NHC Opposition)
on December 10, 2013, in which it argued that the specified discussion of the
LEAPS and TE/VS projects should not be stricken because the Commission
should allow projects proposed by non-IOU entities to be considered to fulfill
local reliability needs rather than letting SCE build replacement generation
facilities in order to remedy a reliability problem that SCE itself caused. (NHC
Opposition at 3-4.)
NHC concedes that, “the Commission did not intend this proceeding to be
used to advocate for the merits of any particular solution to the loss of the
San Onofre Nuclear Generating Station (SONGS) to SCE’s ratebase and to the
local generating capacity of the basin[]” and that “this proceeding was not the
venue to debate facts supporting the worth of Nevada Hydro’s LEAPS and the
closely related TE/VS Interconnect.” Rather, Nevada Hydro noted that it will
make factual assertions in connection with the value of these projects to
ratepayers in Certificate of Public Convenience and Necessity applications it will
make for each project, through which the merits of each project can be fully
vetted.” (NHC Opposition at 2-3.) Thus, NHC essentially admits that the
characteristics of two particular projects are not matters of factual dispute within
the scope of Track 4, which was designed to determine the local reliability
resource needs required by the shutdown per the revised Scoping Memo at 4,
rather than to identify specific projects that should be developed to fulfill such
R.12-03-014 ALJ/DMG/avs
- 22 -
local reliability needs. Therefore, the SCE/NHC Motion is granted; discussion of
the capabilities of the designated sections of NHC’s Opening Brief are stricken
because they are not relevant to the evaluation of reliability needs.
3. Long-Term Local Capacity Requirements in the SONGS Study Area
3.1. Joint Comparison Exhibit
Per the instructions of the ALJ, parties prepared a Joint Comparison
Exhibit, admitted as Exhibit 1. Exhibit 1 shows each party’s recommendations
for Track 4 needs by utilities, and the basis for the need recommendations.
Exhibit 1 is attached as Appendix 1 to this decision.15
3.2. Discussion Overview
The early retirement of SONGS removed over 2,200 MW of capacity from
southern California. Replacing the capacity from SONGS is not a simple matter.
SONGS was located in a critical spot on the coast straddling the SCE and SDG&E
territories, providing energy, capacity and ancillary services such as Voltage
Ampere Reactive (VAR) support to both territories.
Each year, the RA proceeding (currently R.11-10-023) considers utility
capacity needs across California for the upcoming year. In June 2013,
D.13-06-024 (among other things) considered capacity needs for 2014. That
decision adopted higher capacity requirements for southern California for 2014
than otherwise needed if SONGS was still active. Specifically for the SDG&E
local area, D.13-06-024 adopted a local capacity requirement of about 450 MW
more than if both SONGS plants were operational.
15 The contents of Exhibit 1 were based upon parties Opening Testimony for Track 4, unless otherwise cited from a different source.
R.12-03-014 ALJ/DMG/avs
- 23 -
Over the medium-term – a period of greater than the one year considered
in RA proceedings, but shorter than the 10-year view in LTPP proceedings – both
SCE and SDG&E have sufficient supplies to meet projected demands in the
SONGS service area through at least 2018, even with the unexpected early
retirement of SONGS. Significant supplies have come online in recent years,
while overall demand is lower than anticipated several years ago (due to both
weakness in the economy and the success of demand side management and
energy efficiency programs). In addition, SCE has procured additional capacity
to fill the gap left by SONGS over the medium-term. For example, on
May 9, 2013 the Commission approved a bilaterally negotiated capacity sale and
tolling agreement between SCE and BE CA LLC (BECA) for 3,690 megawatts
(MW of contracted capacity in the LA Basin for the period October 2013 to
May 2018. (See Resolution E-4584.)
Starting in 2015, around 4,900 MW of OTC plants in the local
transmission-constrained areas of the LA Basin local area may retire over the
next several years, as well as other OTC plants in the San Diego local areas,
because of State Water Resources Control Board (SWRCB) regulations.16
(See D.13-02-015 at 6-7 and Section 4.2.2 for a discussion of potential OTC plant
closures.) These potential retirements formed much of the basis of the ISO’s
analysis of 2,400 MW of need in the LA Basin in Track 1.
In this Track 4 proceeding, the ISO modeled retirement of OTC plants in
the SONGS study area, along with the retirement of SONGS, to produce an
analysis of need for the area. The ISO essentially used the same models as in
16 See State Water Resources Control Board Resolution No. 2010-0020, adopted on May 4, 2010, effective 9/28/2010; Attachment 1, Milestone No. 26 at 14.
R.12-03-014 ALJ/DMG/avs
- 24 -
Track 1 to determine LCR needs for 2022 (including the expected retirement of
OTC plants), but modified its modeling to reflect the loss of SONGS. Thus, the
ISO did not narrowly attempt to identify how much local capacity will be needed
to replace SONGS, but modeled overall LCR needs in the SONGS service
territory through 2022.
Developing a forecast of needs several years into the future requires
incorporation of a number of assumptions. In this proceeding, the ISO based its
long-term LCR study on a 1-in-10 year annual peak load and a Category C
Contingency.17 In D.12-12-010 in this proceeding, the Decision Adopting Long-
Term Procurement Plans Track 2 Assumptions and Scenarios, the Commission
approved the use of a 1-in-10 year peak weather forecast for transmission
planning and local area planning.18 In Track 1 of this proceeding the
Commission determined that the ISO’s use of a scenario in which two import
pathways to SCE’s territory would be unavailable on the hottest day in 10 years
was an acceptable methodology for determination of LCR needs.19 Similarly, in
D.13-03-029 (the SDG&E Power Purchase Tolling Agreement) the Commission
based its LCR determination, in part, on an ISO study that included a power flow
model of an outage of the Imperial Valley-Suncrest portion of the Sunrise
transmission line followed by the non-simultaneous loss of the ECO-Miguel
portion of the Southwest Powerlink transmission line.
On May 21, 2013, the revised Scoping Memo (in its Attachment A) for this
proceeding set forth a series of assumptions for the ISO to use in modeling
17 A Category C contingency.
18 D.12-12-010, Attachment A at 23.
19 D.13-02-015 at 40.
R.12-03-014 ALJ/DMG/avs
- 25 -
long-term capacity needs in the absence of SONGS. The assumptions are
established consistent those in D.12-12-010, D.13-02-015, and D.13-03-029. The
revised Scoping Ruling determined that certain revised study assumptions were
appropriate, including using a 1-in-10 year versus 1-in-2 year peak weather
forecast for transmission and local area planning, and allocation methodologies
for assigning energy efficiency and demand response to busbars.
The ISO study is based upon the assumptions in the revised Scoping
Memo and forecasts a need of between 4,507 MW and 4,642 MW, respectively
depending upon whether the capacity is split 80/20 or 67/33 between SCE and
SDG&E.20 The ISO analysis takes into account the recent Commission
authorizations in Track 1 and in D.13-03-029 to calculate an LCR need for the
SONGS study area for 2022. Table 1 below (which is also Table 13 in the
testimony of ISO witness Sparks) identifies the ISO’s calculation of the residual
resource needs in 2022 without SONGS:21 As can be seen in the table, the ISO
calculates that between 2,399 MW and 2,534 MW (depending on the allocation
between SCE and SDG&E) will be needed in the SONGS study area by 2022. The
ISO does not recommend authorization of these levels of procurement at this
time.
Certain parties disagree with the ISO’s modeling efforts, as discussed in
sections below. After detailed review, we agree with the ISO’s contention22 that
it correctly modeled the input assumptions described in the revised Scoping
Ruling. At the same time, because any complex forecast several years into the
20 The ISO also adds a 2.5% reserve margin to its need calculation.
21 Exhibit ISO-1 (Sparks), at 26.
22 ISO Opening Brief, at 12-15.
R.12-03-014 ALJ/DMG/avs
- 26 -
future is by definition imperfect, the ISO’s study results cannot be considered an
exact need amount.
Table 1
ISO Table 13 – Residual Resource Needs in 2022 Without SONGS
Scenario Track 1 Decisions
(MW)
Track 4 Studies (2022)
(SONGS Study Area = LA Basin + San Diego)
(MW)
Residual
Resource
Needs
(Total
Track 4 –
Maximum
Track 1) for
SONGS Study Area
(MW)
LA
Basin
San
Diego
DR
Assumptions
Modeled for
Studies***
Inc. EE
Assumptions
Modeled for
the Studies
System-
Connected
DGs
(Commercial Interest)
Identified
Resource
Needs
Without SONGS
80%/20%
(LA/SD) Total
Resource
Development Scenario
1,800* 308** 198 983 1,016
(Installed)
457 (NQC)
4,642 4,642 –
1,800 - 308 = 2,534
Breakdown:
LA Basin
(1,922)
San Diego
(612)
Two-
thirds/One-
Thirds(LA/SD)
Total Resource
Development
Scenario
1,800* 308** 198 983 1,016
(Installed)
457 (NQC)
4,507 4,507 –
1,800 – 308 = 2,399
Breakdown:
LA Basin (1,222)
San Diego (1,177)
The ISO encourages the Commission to move forward with authorizing an
interim amount of additional “no-regrets” resource procurement at this time.23
Specifically, the ISO supports the SCE and SDG&E additional procurement
requests.24 As shown in the Joint Comparison Exhibit, at this time SCE
recommends a procurement authorization of 500 MW in the LA Basin and
23 ISO Opening Brief, at 3.
24 ISO Opening Brief, at 29-33.
R.12-03-014 ALJ/DMG/avs
- 27 -
SDG&E recommends a procurement authorization of 500-550 MW in the SDG&E
service territory.
The first task at hand in Track 4 is to determine a reasonable and prudent
LCR need amount for the SONGS service area by 2022. Several parties argue that
the ISO’s modeling and reliability assumptions (as well as SCE and SDG&E’s
assumptions) were at minimum “very conservative.”25 To the extent that the
revised Scoping Memo took a conservative approach in its models, so did the
ISO.
As the ISO states: “The SCE and SDG&E study results are consistent with
the ISO’s findings.”26 All of these studies show projected residual long-term
local capacity needs ranging from 2,302 – 2,534 MW based on slightly different
assumptions and methodologies; certain of these differences we discuss herein.
The ISO assumed a significant level of new preferred resources, consistent with
the revised Scoping Memo. SDG&E’s base case analysis assumes the existence of
an incremental 408 MW of not-yet-procured preferred resources.27 Similarly, the
planning assumptions adopted for this track of the proceeding that SCE uses for
its studies also assume substantial incremental MW of not yet procured preferred
resources for SCE.28
25 Exhibit ORA-1 (Ciupagea), at 8-9; see also, Exhibit CEJA-1 (May), at 2, 4-6, 9, 14, 21, 28; Exhibit CC-1, (Wang/White), at 1; Exhibit EDF-1 (Fine/Moss), at 2; Exhibit EnerNOC-1, (Tierney-Lloyd), at II-5; Exhibit SC-1 (Powers), at 1; Exhibit NRDC-1 (Martinez), at 4-5.
26 ISO Opening Brief, at 29.
27 SDG&E Opening Brief, at 12.
28 SCE Opening Brief, at 21-22.
R.12-03-014 ALJ/DMG/avs
- 28 -
We will use the ISO models in this decision as the basis for determining
authorized procurement. In this decision, we evaluate potential modifications to
the ISO’s study results. The ISO agrees that its study results do not include a
number of supply and demand considerations that would reduce the total LCR
need. Other parties point to other considerations for the Commission to consider
in authorizing procurement levels at this time. In nearly all cases, parties (PG&E
being the exception) recommend that the Commission authorize procurement
levels far below the approximately 2,400 – 2,500 MW output from the ISO study,
with a number of parties recommending no additional procurement at this time.
We discuss various recommended modifications to the ISO study results in detail
below in order to determine analytically if the recommendations of parties are
reasonable.
3.3. Potential Forecast Adjustments
In the sections below, we consider a variety of factors which impact the
needs shown in the ISO study. It is important to note that all potential changes
considered in the record are in one direction – a lower level of LCR need. The
main question is whether any potential reductions are certain (or at least very
likely), reasonably possible or merely speculative. A prudent authorization
should take into account reductions to the ISO forecasts which are certain or very
likely, should not take into account reductions which are merely speculative, and
should consider reductions which are reasonably possible as providing the basis
for the range of prudency.
3.3.1. Track 1 SCE Procurement Authorization
In D.13-02-015, the Track 1 decision of this proceeding, SCE was
authorized to procure between 1,400 and 1,800 MW in the West LA sub-area of
the LA Basin. Other than PG&E, no party challenges an assumption that the full
R.12-03-014 ALJ/DMG/avs
- 29 -
1,800 MW of this authorization will ultimately be procured by SCE. Since the full
procurement authorization would necessarily be undertaken in the West LA
sub-area – which is within the SONGS study area -- this figure directly reduces
the ISO forecasted need by 1,800 MW. The ISO agrees and includes this
adjustment in its forecast.
SCE’s procurement plan was approved by Energy Division in August
2013, and SCE has conducted an RFO for this purpose. As directed by D.13-02-
015, SCE will file an application with the Commission for approval of
procurement contracts. This application is currently expected later in 2014. SCE
may or may not seek approval for the full 1,800 MW (or even 1,400 MW) in its
application, depending on the viability of the bids it receives. In addition, the
application may or may not be approved in whole or in part. SCE witness
Cushnie testified that it is SCE’s preference to acquire the full 1800 MW of new
LCR resources authorized in D.13-02-015, including the 400 MW of additional
Preferred Resources. Cushnie also testified that if SCE does not receive cost
competitive and/or cost-effective bids for the full 1,800 MW in its first
solicitation, it may seek the needed resources through later solicitations or
expansion of existing utility Preferred Resource programs.29
The authorization we approved in D.13-02-015 was based on SONGS
continuing in service; the Track 1 decision can now be seen as a first step in a two
or more step authorization process. We determine in this decision that it would
be prudent to authorize further procurement due to the retirement of SONGS –
adding up to more than 1,800 MW in total. SCE has stated that it plans over time
29 RT 2000 – 2001.
R.12-03-014 ALJ/DMG/avs
- 30 -
to fill the full 1,800 MW from Track 1; no party disagrees that this will occur.
Therefore, we find that it is very likely or near certain that 1,800 MW from the
Track 1 decision will be procured by SCE and agree with this ISO adjustment in
its forecasted LCR need for the SONGS study area.
3.3.2. SDG&E Procurement Authorization
D.13-03-029 determined a local capacity requirement need and directed
SDG&E to procure up to 298 megawatts of local generation capacity beginning in
2018.30 The decision also granted SDG&E authority to enter into a purchase
power tolling agreement with Escondido Energy Center. This decision denies
authority to enter into purchase power tolling agreements with Pio Pico Energy
Center and Quail Brush Power, without prejudice to a renewed application for
their approval, if amended to match the timing of the identified need, or upon a
different showing of need.
In A.13-06-015, SDG&E sought authority to enter into an amended power
purchase tolling agreement with the Pio Pico Energy Center, based upon the
authority granted in D.13-03-029. D.14-02-016 in this docket approving the
agreement was approved on February 5, 2014. The ISO had already included
this adjustment in its study in this record.
We determine in this decision that it would be prudent to authorize
further procurement due to the retirement of SONGS. SDG&E has already
received approval for procurement based on the authority in D.13-03-029.
Therefore, it is clear that SDG&E will procure the amounts authorized in
30 Other aspects of that decision push the level to 308 MW. In this decision, we round the D.13-03-029 authorization to 300 MW.
R.12-03-014 ALJ/DMG/avs
- 31 -
D.14-02-016. We therefore agree with this ISO adjustment in its study for the
SONGS study area.
3.3.3. Reactive Power and VAR Support
On June 28, 2013, ORA, CEJA and Sierra Club filed a motion requesting
that the Commission ask the ISO to include the full range of reactive power
resources identified in ISO’s 2012-2013 Transmission Plan in the ISO’s local
capacity studies without SONGS. These parties argue that power flow modeling
results that exclude the full available range of reactive power options make it
difficult to identify the true impact that reactive power can have in reducing new
procurement need. In response, TURN agreed that the impact of “reactive
power alternatives should be considered by this Commission in assessing how to
respond to the SONGS retirement.” The ISO opposed the motion to include
modeling of additional reactive power resources in its Track 4 modeling.
Reactive power must be present in the transmission and distribution
system to keep electrical current and voltage in phase and to operate electrical
equipment with inductive load, such as motors, magnetic equipment, and
transformers. Reactive power capacity is measured in units of volt-ampere
reactive (VAR). SONGS was in a strategic location to provide voltage support in
southern California. ISO witness Millar testified that SONGS was “critical in
supporting voltages and transfers into San Diego.”31
31 RT 1678.
R.12-03-014 ALJ/DMG/avs
- 32 -
The ISO modeled 720 MVAR of dynamic reactive support in its Track 4
studies, while SCE/SDG&E (jointly) modeled 1,220 MVAR of dynamic reactive
support.32 The ISO model included some, but not all, resources with potential to
mitigate the loss of reactive support provided by SONGS in its Track 4 analysis.
The Johanna, Santiago, and Viejo shunt capacitors are completed and included in
the ISO’s modeling.33 The Huntington Beach synchronous condensers are also
completed.34 However, while the Huntington Beach condensers are assumed by
the ISO to be available in the 2018 SONGS-out assessment, they are not included
in the revised Scoping Memo’s Track 4 2022 assumptions.35
ORA points to a number of potential resources which may provide
additional VAR support but were not modeled by the ISO,36 including some data
from the ISO’s 2012/13 TPP.37 ORA proposes a 350 MW reduction in need to
approximate the impact of additional reactive power resources expected to
32 Exhibit ISO-1 (Sparks), at 15.
33 Exhibit CEJA-2 (May Supporting Documents) at 48-50 (California Independent
System Operator, Response of the California Independent System Operator Corporation to the First Set of Data Requests Related to Track 4 of the Division of Ratepayer Advocates; California Environmental Justice Alliance; Sierra Club, CA; and Clean Coalition, Request No. 2 (July 12, 2013)).
34 Exhibit CEJA-1 (May) at 8.
35 Exhibit ISO-1 (Sparks) at 9; Exhibit CEJA-2 (May Supporting Documents) at 48-50
(California Independent System Operator, Response of the California Independent System Operator Corporation to the First Set of Data Requests Related to Track 4 of the Division of Ratepayer Advocates; California Environmental Justice Alliance; Sierra Club, CA; and Clean Coalition, Request No. 1 (July 12, 2013)).
36 Exhibit ISO-1 (Sparks), at 15.
37 2012/13 TPP, p. 185-186, Table 3.5-10, note identifier “#” (at 186) (Appended as Attachment C to June 28, 2013 Motion).
R.12-03-014 ALJ/DMG/avs
- 33 -
decrease the need for real power, but ORA recommends that this estimate be
confirmed by comprehensive power flow studies in the ISO’s 2013-2014 TPP.
CEJA shows that SDG&E has proposed two 230 kilovolt (kV) synchronous
condenser projects that provide 480 MVARs of dynamic reactive support within
the SONGS study area.38 CEJA contends that a rough estimate of the total need
reduction in the San Diego area resulting from these projects is at least 200 MW.39
SCE has proposed adding another 550 MVAR [Static VAR Compensators] at
San Onofre. CEJA shows that the ISO estimates that this addition will reduce
need in the LA Basin by 300 MW.40 This reactive support was not included in the
2022 results of the ISO’s Track 4 Opening Testimony.
The June 28, 2013 Motion was not ruled upon during the proceeding. We
will now deny this Motion as moot. The revised Scoping Memo did not include
any specific amount of reactive power as an assumption for the ISO to model.
The record in the proceeding shows that there are sufficient resources to provide
VAR support in the SONGS study area without further action at this time.41 We
do not have sufficient information available from the record at this time to
determine if additional reactive power resources not modeled by the ISO could
be available to reduce LCR needs. Therefore, we find that any estimate of
whether or how much additional reactive power support would change LCR
38
Exhibit SCE-1, at 28, Table III-3. These projects included a Suncrest 240 MVAR synchronous condenser and a Cannon/Encina 240 MVAR synchronous condenser. (See also at 31, Table III-4 notes.)
39 Exhibit CEJA-1, (May) at 9.
40 Exhibit CEJA-1 (May Opening Testimony) at 7.
41 Exhibit ISO-1 (Sparks); at 16-17. Also see RT 2046-2050.
R.12-03-014 ALJ/DMG/avs
- 34 -
needs to be speculative, and will not make any adjustment to the ISO’s study for
this purpose.
3.3.4. Demand Forecast
The demand input assumptions in the revised Scoping Memo are based on
forecasts in the CEC 2012 Integrated Energy Policy Report (IEPR), August 2012
revision.42 The 2012 IEPR is based on the May 2012 CPUC Energy Efficiency
Potential Study and the CEC’s California Energy Demand 2012-2022 Final
Forecast.43 The ISO, SCE, and SDG&E studies are all based on demand input
assumptions from that same data set.44
NRDC argues that the data in these studies provides an incomplete basis
upon which to estimate energy savings through 2022 because the data lacks
important information such as the effects of the CEC’s building efficiency
standards set to take effect in 2017 and 2020 and other energy efficiency codes
and standards that will produce savings from 2015 and beyond.45 CEJA also
contends that data in the August 2012 IEPR therefore provide an incomplete
basis upon which to estimate energy savings through 2022.46 Sierra Club
contends the September 2013 draft update to the CEC demand forecast projects
42
Revised Scoping Memo, Attachment A, at 3.
43 Exhibit NRDC-1 (Martinez); at 7, Diagram 1.
44 Exhibit ISO-1 (Sparks), at 4; Exhibit SCE-1 (SCE), at 31; Exhibit SDG&E-1 (Anderson),
at 6.
45 Exhibit NRDC-1 (Martinez), at 6-7.
46 CEJA Opening Brief, at 19-20.
R.12-03-014 ALJ/DMG/avs
- 35 -
321 MW less load growth than the 2012 demand forecast that serves as the basis
for the Commission-approved load assumptions.47
NRDC contends the energy efficiency estimates that the ISO and SCE
relied on: (i) were based on an incomplete assessment of energy efficiency
potential; (ii) omitted incremental “naturally-occurring” savings that are by
definition reasonably expected to occur; and (iii) incorrectly used a low estimate
of efficiency in SDG&E’s local area instead of the mid estimate.48 NRDC claims
that including these additional energy efficiency savings increases the energy
efficiency assumptions used in the ISO’s and SCE’s modeling by 885 MW in the
SONGS study area, with 543 MW in the LA Basin and 342 MW in the San Diego
local area.49
We will not at this time consider changes or updates related to the CEC’s
demand forecast. It is not reasonable, at this point in this proceeding, to delay
the Track 4 decision until all of the assumptions prescribed in the revised
Scoping Memo can be restudied; nor is it reasonable to selectively update
assumptions. Both the NRDC proposal and the Sierra Club calculation are based
on a CEC staff draft forecast of uncommitted energy efficiency that came out in
September 2013. Both the ISO and SCE expressed concern about uncertainty in
the updated demand forecast, citing the fact that the revised forecast is not yet
47 Sierra Club Opening Brief, at 5. This number is derived from Sierra Club Opening Comments, at 7 & n. 14 (citing California Energy Commission, Mid Case LSE and Balancing Authority – Baseline, Form 1.5d, lines 40 and 49. (Sept. 20, 2013) Retrieved from http://www.energy.ca.gov/2013_energypolicy/documents/2013-10-01_workshop/spreadsheets/).
48 NRDC’s item iii is addressed in Section 3.3.10 (Energy Efficiency) in this decision.
49 Exhibit NRDC-1 (Martinez), at 4-5 (Table 1).
R.12-03-014 ALJ/DMG/avs
- 36 -
final.50 Further, any updates after August 2012 were not modeled by the
modeling parties, consistent with the revised Scoping Memo. Thus, even if there
are changes to the CEC demand forecast, there is nothing in the record to show
how or whether any such updates might impact LCR needs.
However, all of the potential demand adjustments in the record point in
one direction: lower demand. We find based on the record that updates to the
demand forecast are reasonably likely to lower LCR needs. Without quantifying
the LCR effect of such potential demand response resources, we conclude that it
is reasonable to consider this potential as a directional indicator. In other words,
these factors give us more confidence that it is not necessary at this time to
authorize the utilities to procure all of the resources indicated to be necessary in
the ISO’s study.
3.3.5. SPS and Load Shedding51
Consistent with guidelines from the Western Electricity Coordinating
Council (WECC) and the North American Reliability Corporation (NERC), the
ISO has approved Special Protection Systems (SPS), also known as a Special
Protection Schemes, on several occasions in California.52 An SPS allows the use
of load shedding as an interim measure when there are insufficient resources to
meet more stringent guidelines. The ISO (again consistent with WECC and
50 Exhibit SCE-2 (Various Witnesses) at 7; RT 1495.
51 “Load shedding” in the context of this proceeding means controlled, but immediate, blackouts of one or more 500 MW blocks (affecting approximately 375,000 households) in a defined area, in response to specific critical failures of generation and/or transmission resources.
52 NERC reliability standard TPL-003 permits load shedding in response to Category C contingencies (ISO Opening Brief, at 17).
R.12-03-014 ALJ/DMG/avs
- 37 -
NERC guidelines) considers the appropriate reliability level to be an
“overlapping” or sequential outage in which one element or “contingency” is
lost, there is time for the system to be readjusted (within 30 minutes), and then a
second contingency is lost.53 The two major contingencies usually will be a
failure of the largest transmission lines and/or generation resources in the local
area. This is known as an N-1-1 contingency. The ISO considers an SPS to be a
temporary measure to be in place while long lead-time resources, such as new
transmission lines, are being constructed. 54 For example, there is an SPS, with
the potential to shed over 100 MW of load, in place for the San Francisco
peninsula while PG&E completes several related transmission rebuilding
projects.55 When the new resources are in place, the SPS is ended.56
The ISO, SCE and SDG&E calculate the local capacity need for the SONGS
study area using different approaches to acceptable mitigation strategies for the
limiting N-1-1 contingency consisting of the sequential loss of the ECO-Miguel
section of the Southwest Powerlink 500 kV line and the Ocotillo Express-Suncrest
section of the Sunrise Powerlink. The ISO did not model the effect of the
potential use of an SPS and instead assumes that new resources are needed to
resolve the contingency.57 SDG&E acknowledges the presence of a
53 Exhibit ISO-2 (Sparks) at 10.
54 For large urban areas, the ISO’s historic practice has been, as a last resort, to rely on load shedding as an interim measure only until the permanent solution can be put in place (ISO Opening Brief, at 18).
55 RT 1472.
56 Two such examples are provided in Exhibit ISO-2 (Sparks), at 5.
57 Exhibit ORA-3 (Fagan), Attachment B (ISO Data Request Response 2).
R.12-03-014 ALJ/DMG/avs
- 38 -
WECC-approved SPS in its territory but does not directly model the effect of the
SPS when considering the range of need for the N-1-1 contingency.58 SDG&E
and the ISO assume new generation resources (and/or transmission solutions)
are needed to resolve the contingency. SCE models and calculates local capacity
need assuming the SPS is available to mitigate the limiting contingency, but then
requests additional procurement authority because the ISO does not allow
reliance on this SPS for long-term planning.59
The use of an SPS to mitigate the N-1-1 contingency makes a significant
difference in the determination of need. SCE’s model shows that reliance on the
existing SPS for relevant N-1-1 conditions60 would decrease SCE’s need for new
generation by 438 MW in the all generation scenario.61 Further, the effectiveness
of SCE’s proposed Mesa Loop-In project reduces the need for new generation
from 1,200 MW to 734 MW without load shedding.62 SDG&E witness Jontry
testified that “Planning analyses performed by the CAISO supporting the Final
2013 LCR Technical Study indicate that adherence to the N-1-1 criteria without
the possibility of load shedding increases the LCR requirements for the
San Diego LCR area by over 1,000 MW, the equivalent of two combined cycle
58 Exhibit SDG&E-3 (Jontry), at 7.
59 Exhibit SCE-1 (Chinn) at 6-7.
60 As noted by ORA witness Fagan (RT 1835-1836) using the SPS to shed load would only be necessary if the relevant conditions occurred simultaneously – very high peak load, and loss of both 500 kV lines. Its consideration in the planning stages does not imply deployment in operation.
61 Exhibit SCE-1 (Chinn), at 32, Table III-5.
62 Exhibit SCE-1 (Chinn), at 37.
R.12-03-014 ALJ/DMG/avs
- 39 -
units.”63 Jontry also testified that reliance on the SPS in the SDG&E territory
would decrease the need for new generation by approximately 150 MW to
250 MW.64 Considering all possibilities in the record, the amount of new
generation that reliance on the SPS could displace ranges from about 588 MW
(assuming 438 MW for SCE’s and 150 MW for SDG&E) to 1,000 MW or more.65
ORA, TURN, CEJA, CLECA, Redondo Beach and Sierra Club all question
the decision of the ISO, SDG&E and SCE not to consider the use of an SPS to
mitigate the SONGS contingency in the absence of more complete information
about the costs, benefits risks and affordability of relying on the SPS.66 ORA
witness Fagan testified that that an SPS could serve as a “’bridge’ measure,
depending on future transmission and/or preferred resource development
circumstances. Fagan testified that:
(if a new 500 kV) transmission connection between SCE and San Diego…was under consideration, there might be a period of time after OTC unit retirement and prior to completion of such a project that the SPS could serve as a bridge to ensure reliability. Or, if preferred resource development is advancing rapidly but has not yet reached a required threshold level by…2020, but would reach such a level a few years later, the SPS could serve as a bridge during that period.”67
63 Exhibit SDG&E-3 (Jontry), at 7-8.
64 RT 1714–1715; Exhibit SDG&E-4 (Jontry), at 2-3.
65 Exhibit TURN-1 (Woodruff), Table 4, at 17.
66 Exhibit ORA-3 (Fagan), at 3-10; Exhibit TURN-1 (Woodruff), at 12-27; Exhibit CEJA-1(May), at 34-38; Comments of the CLECA, September 30, 2013, at 10-1; Exhibit SC-1 (Powers), at 1-11.
67 Exhibit ORA-3 (Fagan), at 11.
R.12-03-014 ALJ/DMG/avs
- 40 -
CLECA posed the question: “Is it a good use of ratepayer money to add
yet another roughly 500-1,500 MW in resources that will rarely if ever be used
instead of using controlled load shedding by SDG&E in the case of an N-1-1
contingency under a 1-in-10 peak load condition? This is not a matter of failing
to meet NERC and WECC requirements. This is a matter of having ratepayers
foot the bill for going beyond those requirements.”68 TURN witness Woodruff
emphasized that consideration of whether to allow load shedding to mitigate the
key N-1-1 contingency should not be confused with a lack of concern about
reliability.69
Parties dispute whether it would be cost-effective to have an SPS in place
in San Diego. ORA witness Fagan testified that the alternative to an SPS would
be the cost of new gas-fired generation, estimated to range from $595 million
(436 MW) to $1.36 billion (1,000 MW) using $1,363/kW as the installed capital
cost for a combustion turbine.70 Similarly, TURN witness Woodruff estimated
that the cost of SCE’s Preferred Resource scenario appears to be $595.5 million
higher in the absence of using a load shedding SPS as part of a contingency
mitigation plan.71
68 CLECA Comments, at 10-11.
69 Exhibit TURN-1 (Woodruff), at 26-27.
70 Exhibit ORA-3 (Fagan) at 7.
71 Exhibit TURN-1 (Woodruff), Table 4, at 17.
R.12-03-014 ALJ/DMG/avs
- 41 -
Other parties argue that an SPS is not appropriate and/or is not
cost-effective. ISO witness Sparks testified that it is the ISO’s position that load
shedding in the highly urbanized San Diego area should not be used as a
transmission planning tool, due to the significant amount of load that would be
subject to load shedding, the sensitivity of urban loads to large blocks of load
shedding, the complexity of operating arrangements in the area, and the
proximity of particular transmission lines.72 SDG&E witness Jontry cautioned
against the “potentially severe economic and civil consequences”73 that might
result from controlled load shedding. Neither the ISO74 nor SDG&E75 conducted
studies to compare the cost or risk of relying on its SPS versus the costs of other
resources to mitigate the critical contingency.
IEP witness Monson testified that loss of service would result in costs
including “spoilage, lost production time, and lost sales” as well as well possible
traffic accidents and medical problems.76 Monson testified that the costs of
curtailment of firm load “depend on the frequency and duration of curtailments,
the amount of capacity curtailed, and the value of service for customers,” but
were not calculated.77 IEP calculates that, using an average financial cost of an
72
ISO-3, at 7.
73 Exhibit SDG&E-4 (Jontry), at 2.
74 RT 1843.
75 Exhibit ORA-3 (Fagan), Attachment D: SDG&E response to DRA-Sierra Club-CEJA data request second set, question 2. (“SDG&E has not conducted any studies quantifying the cost effectiveness of load shedding versus new in-basin generation resources.”)
76 Exhibit IEP-2 (Monsen), at 15.
77 Exhibit IEP-2 (Monsen), at 15-16.
R.12-03-014 ALJ/DMG/avs
- 42 -
outage of the electric system of $40,000/MWh for a 12-hour outage, like the one
San Diego experienced in September 2011, the cost of a similar outage would
approach a quarter of a billion dollars.78 However, TURN performed an analysis
(which it terms “preliminary”) showing under various assumptions that
investments to avoid load shedding in case of an N-1-1 contingency are not cost-
effective for ratepayers.79
Redondo Beach contends that the Commission could find that the costs
and possible consequences of any controlled load drop are unacceptable, but the
Commission should make such findings based on concrete analytic evidence.
Redondo Beach claims such evidence is not present.80 We agree that the evidence
in this proceeding is not conclusive on this point.
In trying to estimate the potential consequences of an SPS, relevant factors
include how often the identified N-1-1 contingency in San Diego is likely to
occur, the likelihood that the contingency would occur when there were not
adequate resources to serve load in the event one of the lines went down, and a
range of costs of not serving load. One factor to consider is that the SPS might
never be used.81 ISO witness Sparks testified that there is a significant risk (and
historical record) of fire in the area of the two transmission lines (which are as
close as four miles apart) which form the N-1-1 contingencies, and that the
78 IEP Opening Brief, at 16. IEP adds: “The social costs of blacking out 500 MW of customer load, including the disruptions to transportation, traffic control systems, and waste management systems, would be substantial, if difficult to quantify.”
79 TURN Opening Brief, at 13-14.
80 Redondo Beach Opening Brief, at 17.
81 RT 1837.
R.12-03-014 ALJ/DMG/avs
- 43 -
probability of a simultaneous outage of the two lines “trends” towards one in
21 years.82 Other credible data in the record shows likely intervals between
potential failures may be up to 928 years.83
As ORA witness Fagan points out, ISO data shows the highest load on the
combined Orange County SCE/SDG&E region occurs for no more than 89 hours
over the course of the 3672-hour period between May 1 and September 30th, or
less than 2.5% of summer hours.84 Redondo Beach attempted to estimate the
probability that two sets of low probability events – i.e., very high peak load and
loss of both 500 kV lines in sequence – would occur at the same time on the same
day, contending that “the probability of an N-1-1 contingency occurring at the
peak hour of a 1-in-10 load forecast is…about 1 in a billion for the peak hour” or
about 1 in 5 million if surrounding hours are included. 85 ISO witness Millar
testified that “we don’t believe this circumstance is one where a straightforward
cost benefit analysis is an effective consideration.”86
82
Exhibit ISO-2, at 5-6.
83 Exhibit ISO-2 (Sparks), at 5– 6; See Exhibit TURN x ISO 7, at 56; cf. Ex. TURN x ISO 2, at 3.
84 Exhibit ORA-3 (Fagan) at 9.
85 Redondo Beach Report, p. 13; Redondo Beach Opening Brief, p. 14.
86 RT 1613; see also RT 1622: appropriate use of cost benefit information refers to “circumstances lending themselves to producing a meaningful result that can be effectively taken into account by a decision maker in weighing the costs against the calculation benefits of mitigating against the large outage.
R.12-03-014 ALJ/DMG/avs
- 44 -
Per § 345, the ISO is responsible for operating the transmission grid used
by SCE, PG&E, and SDG&E “consistent with achievement of planning and
reserve criteria no less stringent than those established by the Western Electricity
Coordinating Council and the North American Reliability [Corporation].” The
Commission is responsible for service reliability and maintaining reasonable
rates. In previous decisions, we rejected the notion of “reliability at any cost,”
indicating instead that “measures that are proposed to promote greater grid
reliability should be evaluated by weighing their expected costs against the value
of their expected contribution to reliability…”87
We do not find that long-term reliance on an SPS to resolve LCR need
related to the retirement of SONGS is appropriate. We agree with SCE witness
Chinn that “load shedding should only be used judiciously as mitigation for
contingencies.”88 We also agree with IEP that we should not make a “change to
long-term resource planning policy to incorporate blackouts as a standard,
planned response to N-1-1 contingencies, a response on par with supply or
demand-side additions, to avoid procuring the resources needed to reduce the
risk of blackouts.”89
The crux of the issue before us regarding load shedding is whether we
should at this time authorize additional procurement to achieve the level of
reliability the ISO recommends: Sufficient resources to mitigate a specific, but
unlikely, N-1-1 contingency in the SDG&E territory. We note that an SPS that
would allow load shedding is an option permitted by NERC and WECC
87 D.05-10-042 at 7.
88 Exhibit SCE-2 (Chinn) (Revised 10/24/13), at 15.
89 IEP Opening Brief, at 18.
R.12-03-014 ALJ/DMG/avs
- 45 -
standards.90 We find based on the record the following: 1) The ISO has the
authority within WECC/NERC guidelines to implement or continue a SPS in the
SDG&E territory; 2) Such an SPS in the particular area identified by the ISO has a
likelihood of an N-1-1 failure between every 21 and 928 years; 3) Even if such a
failure occurs, it will not lead to load shedding except for less than 2.5% of
summer hours;91 4) There would need to be a minimum of 588 MW fewer
resources if there is a temporary SPS in place, as compared to the resources
needed to support the N-1-1 contingency identified by the ISO; 5) The cost to
ratepayers of these additional resources would be at least $595 million (this
amount is the benefit of an SPS approach) and there is evidence that such
investment may not be cost-effective; 6) The cost to affected customers of a load
shedding event under an SPS approach is estimated at under $250 million per
event, and must be weighted by the low probability of the occurrence of load
shedding.
We conclude that it is not reasonable at this time to authorize utilities to
procure – and ratepayers to pay the cost of -- the additional resources required to
fully mitigate the identified N-1-1 contingency without an SPS. This
determination does not mean that we favor a lower level of reliability than does
the ISO. We agree with SDG&E and IEP that that it is not prudent to take a
long-term system planning approach that assumes reliance on load shedding in a
90 Exhibit ORA-3 (Fagan), at 7: 15 and Attachment B, at 1.
91 We recognize that an outage resulting from an N-1-1 contingency may occur outside of summer hours; however, the summer is generally considered the most likely season for this to occur due to higher temperatures, higher load and greater fire risk near the subject transmission lines.
R.12-03-014 ALJ/DMG/avs
- 46 -
densely-populated urban area as mitigation for contingency events.92 Instead,
we determine that it is prudent to wait to see what resources develop in the
SONGS service area to determine whether an SPS or other load-shedding
protocol need serve as a bridge until such resources are in place. In particular,
we see the likelihood that the procurement of preferred resources as authorized
herein (and as acquired through other means) will develop sufficiently over time
to mitigate the need for further resources, so that the SPS in the SDG&E territory
can be lifted and reliability at an N-1-1 contingency level can be maintained. In
addition and/or alternatively, transmission solutions such as the Mesa Loop-In
may mitigate the need for further resources.
We note that ISO witness Millar testified that the ISO intends to address its
transmission planning policy regarding load shedding in large urban areas as
part of an open stakeholder process in the first half of 2014.93 While it is
unknown what the outcome of this process will be, it is possible that the ISO will
adopt a different position that it currently holds regarding when an SPS should
be approved and how load shedding should be considered. By not authorizing
procurement at this time to the ISO’s current policy standard, we retain the
option of reconsidering the appropriate level of procurement in the future in the
light of future ISO planning policy.
Therefore, we conclude that it is reasonable to subtract a conservative
estimate of 588 MW from the ISO’s forecasted LCR need because our policy
decision entails a certainty that resources will not be procured at this time to
92 SDG&E Opening Brief, at 30. 93
Exhibit ISO-7, at10.
R.12-03-014 ALJ/DMG/avs
- 47 -
fully avoid the remote possibility of load-shedding in San Diego as a result of the
identified N-1-1 contingency.
3.3.6. Category C vs. Category D
Several parties argue that the Category C contingency in San Diego
modeled by the ISO is functionally a Category D contingency under WECC
reliability standards, using a probabilistic analysis. Sierra Club witness Powers,94
CEJA witness May and POC witness Peffer presented extensive technical
testimony on this point; all claim that the SWPL/Sunrise overlapping N-1-1
contingency is a Category D extreme event for which transmission upgrades are
not required under NERC standards.95 ISO witness Sparks responded that these
witnesses seemed to be confusing the overlapping outages of the two lines (loss
of one element, system re-adjusted, followed by loss of a second element), with
the simultaneous loss of two transmission lines (a Category D contingency).96
On cross examination, witness Powers claims the overlapping outage of
SWPL and Sunrise is a “functional” Category D because SDG&E could “convert
it from a Category C to a Category D” using the WECC process followed by
SDG&E in evaluating the performance criteria of the Sunrise route alternatives.97
However, SDG&E witness Jontry testified that the WECC re-classification
process is not available for an N-1-1 contingency.98 ISO witness Sparks also
94 Exhibit SC-1 (Powers), at 3; RT at 1931, 1932, 1935. 95
Exhibit SC-1 (Powers), at 2; Exhibit POC-1 (Peffer), at 11; Exhibit CEJA-1 (May), at 30.
96 Exhibit ISO-2 (Sparks), at 11-13.
97 RT 1932. (See also Exhibit POC-X-CAISO-3.)
98 RT 1775.
R.12-03-014 ALJ/DMG/avs
- 48 -
noted that he had never seen the process applied to a Category C3 contingency,
and that WECC is moving to eliminating the process altogether.99
In relevant past decisions, the Commission has disputed some of the ISO's
input assumptions to its modeling (such as megawatts of demand response and
incremental uncommitted energy efficiency, and load forecasts). We modify
various ISO input assumptions in this decision as well. Yet, the Commission has
consistently relied on ISO transmission planning studies which use the ISO’s
methodology and interpretation of Category C and D contingencies. This is seen
in decisions including the 2013 RA decision (D.13-06-024), the Track 1 LTPP
decision in this docket (D.13-02-015), and our recent SDG&E procurement-
related decision (D.13-03-029). In these decisions we defer to the ISO regarding
power flow modeling. For example, D.13-02-015 Findings of Fact 2 states: "It is
reasonable to use local capacity studies and power flow modeling from the ISO
for LCR forecasting. . . .” Similarly, in D.13-03-029, Conclusion of Law 5 states:
“The CAISO’s modeling assumptions, other than with respect to uncommitted
energy efficiency and demand response and incremental CHP, are reasonable.”
Further, the 2013 RA Decision relies on the ISO's 2014 Local Capacity
Requirements Study,100 which employ the same Category C distinctions that the
ISO uses here in Track 4.
99
RT 1562.
100 D.13-06-024, Conclusion of Law 1 states: “The ISO’s 2014 Local Capacity Technical Analysis Final Report and Study Results should be approved as the basis for establishing local procurement obligations for 2014 applicable to Commission-jurisdictional LSEs, using the “no SONGS” scenario."
R.12-03-014 ALJ/DMG/avs
- 49 -
We will use the ISO power flow models as the basis for this decision as
well. The ISO power flow modelling was performed consistent with the revised
Scoping Memo. The exogenous modifications we make (including assumptions
regarding load-shedding) do not affect the modelling directly, but inform our
judgment regarding appropriate procurement levels. Changing a Category C
contingency to a Category D contingency would directly change the ISO model
output. We find that issues regarding whether an ISO-determined Category C
contingency should instead be functionally a Category D contingency under
WECC reliability standards are more within the expertise of the ISO than the
Commission. In any event, we find no credible basis upon which to find that the
ISO’s analysis is flawed and that the limiting contingency for the SONGS study
area is anything but the N-1-1 Category C3 SWPL/Sunrise overlapping outage
assumed and modeled by the ISO.
3.3.7. Transmission Solutions
SCE proposes a potential transmission solution to part of the LCR need in
the SONGS study area. The Mesa Loop-In project involves rebuilding and
upgrading the existing Mesa 230 kV substation in the LA Basin to 500 KV and
looping the Vincent – Mira Loma 500 kV line and two 230 kV lines into the
substation. SCE describes several positive benefits of the Mesa Loop-In: 1) it
relieves the loading on the Serrano corridor by delivering power into the LA
Basin from the northwest;101 2) because of the addition of the new 500 kV
substation, the capacity of the transmission grid to import power to the LA Basin
would be increased,102 allowing any new resources to come from outside of the
101 Exhibit SCE-1 (Silsbee), at 36; RT 2160.
102 Exhibit SCE-1, at17; at 36.
R.12-03-014 ALJ/DMG/avs
- 50 -
LA Basin, where there are fewer impediments to generation development,
fostering more competition and reducing procurement costs;103 3) the Mesa
Loop-In would reduce the amount of gas-fired generation that would need to be
sited in the LA Basin by approximately 1,200 MW104 (734 MW if no load
shedding or additional gas-fired generation in the SDG&E territory).
Due to the Mesa Loop-In’s characteristics, including the fact that most of
the infrastructure changes will take place within the boundaries of the current
substations, SCE contends it is reasonably possible the Mesa Loop-In can be
constructed by 2020 when significant amounts of OTC generation is expected to
retire. We agree with SCE. SCE cautions that this completion schedule will
require aggressive scheduling of regulatory agency reviews and minimal public
opposition.105
The Mesa Loop-In project was submitted to the ISO as part of its 2013-2014
Transmission Planning Process. However, there is no record to determine if the
Mesa Loop-In will be approved by the ISO in its TPP. Even if this occurs, it is not
possible to know at this time if this project would receive all necessary permits
and approvals and be constructed in the timeframe SCE suggests; SCE admits
that many significant hurdles would need to be overcome for this to occur.
Nevertheless, the Mesa Loop-In proposal is a promising and reasonably likely
alternative to other new resources in the LA Basin. While significant
uncertainties require that we not adjust the ISO’s forecast at this time to assume
LCR benefits from the Mesa Loop-In project, it is important to keep in mind that
103 Exhibit SCE-1, at 36; Exhibit SCE-2, at 4.
104 Exhibit SCE-1, at 36.
105 SCE Opening Brief, at 28.
R.12-03-014 ALJ/DMG/avs
- 51 -
it may not be necessary to authorize (or if authorized, ultimately approve)
funding for various procurement projects if the Mesa Loop-In becomes viable in
a timely manner.
AES Southland points out that any reduction of the need for LA Basin
generation by the Mesa Loop-In does not reduce overall generation needed to
maintain system reliability; rather it just allows the need to be met by resources
located over a larger geographic area.106 For the LA Basin Transmission Scenario,
SCE modeled 600 MW of generation outside the LA Basin.107 Thus, the Mesa
Loop-In project may lead to an overall reduced need for 134 to 600 MW,
accounting for the 734 to 1,200 MW reduction in LCR in the SONGS service
territory, but 600 MW of new generation outside of the SONGS service area. The
GHG impacts of the overall impact of the proposed Mesa Loop-In project would
be considered in a separate application.
SDG&E examined the addition of two regional transmission projects that
could reduce LCR need. The first project SDG&E included is a 500 kV Direct
Current (DC) transmission project from Imperial Valley to SONGS.108 SDG&E’s
study shows the addition of a DC line would reduce the San Diego generation
requirement by 850 MW and would reduce the generation requirement for the
LA Basin by 551 MW.109 The second project is a 500 kV regional transmission
project from Devers Substation to a new 230 kV substation in north San Diego
106 AES Southland Opening Brief, at 7.
107 Exhibit SCE-1 (Silsbee), at 40.
108 Exhibit SDG&E-3 (Jontry), at 8-9.
109 Exhibit SDG&E-3 (Jontry), at 13.
R.12-03-014 ALJ/DMG/avs
- 52 -
County.110 SDG&E shows this project would reduce the LCR need for San Diego
by 550 MW and reduce the LCR need for the LA Basin by 400 MW.111 SDG&E
witness Jontry noted that both of these projects “may differ slightly [from those
submitted to the 2013/2014 Transmission Planning Process], but will be
electrically equivalent.”112 SDG&E testified that it submitted two 500 kV options
with different routing options from Imperial Valley to North County to the ISO’s
2013-2014 Transmission Planning Process.113 SDG&E witness Anderson testified
that “adding major transmission capability in to the load pocket can reduce the
need for local generation by approximately 1000 to 1400 MW,” but that there was
substantial uncertainty as to how quickly those projects could be licensed and
built.114
There is not enough information available at this time to make a specific
finding that any transmission project will be able to reduce the LCR need in the
SONGS service territory by 2022. Partially, this is because the ISO’s 2013/2014
TPP is not yet final. Beyond this, there are various approval and permit
processes – as well as public input – before construction can begin. The
construction process can take several years, and is subject to significant delay.
We find that there is a reasonable possibility that at least one of the transmission
solutions examined by SCE and SDG&E will be operational by 2022. The least
110
Exhibit SDG&E-3 (Jontry), at 9.
111 Exhibit SDG&E-3 (Jontry), at 13.
112 Exhibit SDG&E-3 (Jontry), at 9.
113 RT 1749.
114 Exhibit SDG&E-1 (Anderson), at 2.
R.12-03-014 ALJ/DMG/avs
- 53 -
complex of these projects is the Mesa-Loop-In project, which is therefore the
most likely to meet this timeframe.
We find based on the record the proposed transmission solutions in the
record would most likely lower LCR needs, if completed in the appropriate
timeframe. While the LCR effect of such potential transmission solutions has
been quantified, we conclude that it is reasonable to consider this potential as a
directional indicator rather than a reduction to the LCR needs identified by the
ISO. Therefore, potential transmission solutions give us more confidence that it
is not necessary at this time to authorize the utilities to procure all of the
resources indicated to be necessary in the ISO’s study.
TURN points out that it is conceivable that future transmission planning
efforts by the two utilities and the ISO will identify additional transmission
projects or other measures that can meet local need more cost effectively.115 We
agree; however, this potential is speculative based on the record in this
proceeding.
3.3.8. Demand Response
The revised Scoping Memo sets out assumptions for demand response
resources for 2018 and 2022. The demand response assumptions are the same for
both years, 189 MW of “fast” demand response (potential to be activated in
30 minutes or less after the first contingency) to be modeled as a “First
Contingency” resource and 997 MW of demand response which is to be
115 TURN Opening Brief, at 5.
R.12-03-014 ALJ/DMG/avs
- 54 -
accounted for as a “Second Contingency Resource.” 116 According to the revised
Scoping Memo, the studies “shall model ‘First Contingency’ resources as
addressing the first contingency to prepare for the second contingency.” Second
Contingency resources “are not modeled but would be accounted for as potential
resources to address any residual need identified by a second contingency
condition in the studies.” The revised Scoping Memo states an expectation that
these demand response programs could become more capable of meeting needs
by 2022 while also noting that further action would be needed to make that a
reality, and that the study results “shall provide a broad assessment of local area
needs that inform the programs of ‘second contingency’ resources such that they
can adapt to meet the residual need.”117
CEJA argues that the ISO’s treatment of ’second contingency’ demand
response is problematic for two reasons: first, the ISO appears to assume that the
character of the demand response programs that exist today are the same as will
exist in 2022; second, the Commission recently instituted R.13-09-011 to enhance
the role of demand response programs. CEJA notes that R.13-09-011 makes it
clear that the Commission does not intend for demand response programs to
remain in stasis for the next 9 years.118 Sierra Club makes similar points.119
NRDC argues that all of the model results presented by the ISO and the
utilities should be adjusted downward in order to account for the amount of
116 Per the revised Scoping Memo, price responsive and day-ahead demand response programs or demand response programs outside the geographic areas of most concern (the west LA Basin and the SDG&E territory) fit the “Second Contingency” category.
117 Revised Scoping Memo, Attachment A, at 2.
118 CEJA Opening Brief, at 11.
119 Sierra Club Opening Brief, at 8-l l.
R.12-03-014 ALJ/DMG/avs
- 55 -
demand response that is reasonably expected to occur. NRDC contends that the
ISO only used the ‘first contingency’ resources in its studies, which NRDC
contends are only a portion of the demand response input assumptions that the
revised Scoping Memo directed it to use in its studies. NRDC maintains that
“second contingency” resources identified in the revised Scoping Memo should
be counted toward meeting LCR needs.
We disagree with these parties. The revised Scoping Memo specifically
indicated that: “‘Second Contingency’ consists of assumptions representing
residual resources that could be used to meet subsequent post-contingency
needs. ‘Second Contingency’ resources are not modeled but, would be
accounted for as potential resources to address any residual need identified by a
second contingency condition in the studies (emphasis added).”120 Consistent
with the instructions of the revised Scoping Memo, the 997 MW of ‘second
contingency’ demand response in the ISO modeling was not available to avoid
the second contingency, but would be available to respond to the second
contingency.
As ISO witness Sparks stated:
“…our understanding, is the existing (demand response) that doesn't have characteristics that -- at least currently doesn't have characteristics that meet the needs. Not to say that we couldn't find some other (demand response) or modify that (demand response), but at this point in time we didn't want to cause confusion that that (demand response), as it exists today, could meet the need. And so that was not included in the residual calculation.”121
120 Revised Scoping Memo at 2.
121 RT 1456.
R.12-03-014 ALJ/DMG/avs
- 56 -
The ISO's modeling followed the revised Scoping Memo's instructions,
which reflected the operating and performance characteristics of ‘second
contingency’ demand response resources. In the ISO’s reliability rubric, these
resources should not be counted because they cannot be relied upon to activate
within 30 minutes after the first contingency. We find that, consistent with the
revised Scoping Memo, the ISO properly did not model ‘second contingency’
demand response resources for determining LCR needs. We will not revisit
these demand response assumptions here for the purpose of changes to the ISO
study itself, but instead consider whether potential additional demand response
should affect authorized procurement amounts.
SCE had already started its analysis prior to the issuance of the revised
Scoping Memo. SCE found that, “[o]verall there is about a thousand megawatts
of [demand response] assumed in the overall Los Angeles Basin.” In the smaller
West LA Basin (where the revised Scoping Memo is focused for demand
response resources), SCE assumed 620 MW of demand response available as a
reasonable estimate and discounted that amount by 50%, because those
programs were initially developed to meet system, not local, needs. In addition,
SCE augmented this amount by 283 MW of additional demand response in the
Johanna/Santiago Substations (also in the west LA Basin), again discounted by
50%. In total, SCE assumed 451 MW of demand response in the Track 4
modeling.122
122 RT 2121 – 2122.
R.12-03-014 ALJ/DMG/avs
- 57 -
We will not modify the ISO’s LCR analysis based on ‘second contingency’
demand resources. However, the expectation of over hundreds of MWs of
‘second contingency’ demand response resources identified by the revised
Scoping Memo cannot be disregarded. SCE’s model assumed that some of this
demand response would be available to meet LCR needs. EnerNOC points out
that the ISO in some cases does count demand response resources that do not
activate in under 30 minutes as counting toward reducing the LCR need.123
While the ISO contends (consistent with the revised Scoping Memo) such
resources would not mitigate the N-1-1 contingency under its rubric, the revised
Scoping Memo took a conservative view of the potential of demand response
resources in this regard.
There may be a transient design issue with demand response resources at
this time. CEJA is correct that we expect demand response programs to evolve
and improve. In the future, it is reasonable to expect that some amount of what
is now considered ‘second contingency’ demand response resources can be
available to mitigate the first contingency, and therefore meet LCR needs. ISO
witness Millar agrees that it is possible that additional demand response
resources with more notice would also be able to respond within the time frame
expected to meet the N-1-1 contingency within 30 minutes.124 For example,
demand response customers may have provisions which, when they are alerted
in advance of a potential need for these resources to activate (such as a very hot
weather forecast), require such resources to be activated within 30 minute when
called. Further, ISO witness Sparks testified that, in “the current ISO planning
123 EnerNOC Opening Brief, at 15.
124 RT 1692.
R.12-03-014 ALJ/DMG/avs
- 58 -
process,” the ISO is “also working on identifying the necessary characteristics of
preferred resources such as demand response such that it can meet local
needs.”125
We do not at this time assume additional demand response resources,
beyond those modeled by the ISO, will be available to meet LCR needs. We do
find that there is a reasonable likelihood that more demand response resources
will be available for such purposes in the future. While we cannot quantify the
LCR effect of such potential demand response resources, we conclude that it is
reasonable to consider this potential as a directional indicator. In other words,
this gives us more confidence that it is not necessary at this time to authorize the
utilities to procure all of the resources indicated to be necessary in the ISO’s
study.
3.3.9. Energy Storage
On October 17, 2013, the Commission issued D.13-10-040, the “Decision
Adopting Storage Procurement Framework and Design Program”. That
decision, in Appendix A, at 1., states that a “guiding principle” for energy
storage is: “The optimization of the grid, including peak reduction, contribution
to reliability needs, or deferment of transmission and distribution upgrade
investments.” D.13-10-040, Appendix A, at 2, sets energy storage targets of
580 MW for SCE and 165 MW for SDG&E. These targets are to be procured
gradually through biennial solicitations from 2014 through 2020.126 Though the
utilities may defer up to 80% of their MWs to later procurement periods,127 they
125 RT 1553.
126 D.13-10-040 at Appendix A, at 5, Section 3(a).
127 D.13-10-040 at Appendix A, at 3, Section 2(c).
R.12-03-014 ALJ/DMG/avs
- 59 -
must ultimately have 100% of their respective storage targets online no later than
December 31, 2024.128
The ISO presumes “the Commission will consider energy storage targets
identified in” the energy storage decision, but is concerned about “the ultimate
amount, location and timing of energy storage actually developed.”129 SCE
similarly suggests that some portion of the targeted storage resources will end
up in the LA Basin and be available to meet LCR needs, but as SCE witness
Nelson testified, the “timing is unknown. It’s not clear to me…what the
accounting will be for LCR purposes of storage.”130
SDG&E contends there are many issues related to energy storage
procurement that require resolution, including the operational characteristics
that energy storage must satisfy in order to be relied upon to meet LCR need.
SDG&E witness Anderson noted that “some amount of energy storage – the right
kind of energy storage at the right locations – may play a role in meeting some of
SDG&E’s identified LCR need.”131 He noted that energy storage procurement
undertaken in order to meet to targets adopted in the dedicated energy storage
proceeding may or may not be procurement capable of meeting LCR need.132
128
D.13-10-040 at Appendix A, at 1, Section 2(a) (“Southern California Edison Company, Pacific Gas and Electric Company, and San Diego Gas & Electric Company shall procure (i.e., pending contract, under contract, or installed) 1,325 MW of energy storage by 2020 with the requirement that the overall procurement goal of 1,325 MWs will be installed and delivering to the grid by no later than the end of 2024….”).
129 ISO Comments, at 3.
130 RT 1903.
131 Exhibit SDG&E-2 (Anderson), at 1.
132 Exhibit SDG&E-2 (Anderson), at 2.
R.12-03-014 ALJ/DMG/avs
- 60 -
CEJA contends that with storage procurement anticipated by D.13-10-040
complete by 2020 and energy storage deploying relatively quickly,133 most if not
all of the decision’s storage targets should be available by 2022. Therefore, CEJA
recommends that the Commission include SCE’s and SDG&E’s energy storage
targets to lower LCR needs within the SONGS study area by 612 MW.
Sierra Club similarly would reduce Track 4 procurement by 745 MW to account
for energy storage in SDG&E's and SCE's territories by 2020.134
In D.13-02-015, we required procurement of 50 MW of energy storage as
part of SCE’s 1,400-1,800 MW procurement requirement. This procurement level
is already included in the ISO, SCE and SDG&E calculations of LCR needs. In
D.13-02-015 we indicated that energy storage procurement was an experiment;
Finding of Fact 44 in D.13-02-015 stated: “A requirement to procure a modest
level of energy storage resources, such as 50 MW provides an opportunity to
assess the cost and performance of energy storage resources.” The decision also
provided ratepayer safeguards: Ordering Paragraph 12 provides, in part, that
SCE: “shall present contracts for at least 50 MW of energy storage resources … to
the Commission for approval, or have the burden to show that it should procure
less than 50 MW because the bids it received were unreasonable.”
We agree with SDG&E, SCE and the ISO that the energy storage targets
adopted in D.13-10-040 cannot be assumed to count toward LCR need on a
megawatt-for-megawatt basis. We confirm the intent of D.13-10-040 to jumpstart
the use of energy storage resources in California. We strongly believe energy
storage will be useful to meet LCR resources in the future; in general, we expect 133 Exhibit CEJA-1 (May); at 54.
134 Sierra Club Opening Brief, at 11-14.
R.12-03-014 ALJ/DMG/avs
- 61 -
development of these resources to have an environmentally beneficial impact on
energy supply and reliability in California.
D.13-10-040, Ordering Paragraph 3, orders SCE and SDG&E (as well as
PG&E) to file applications containing a proposal for procuring energy storage
resources by March 1, 2014, with the solicitation to occur no later than
December 1, 2014. Ordering Paragraph 4 of that decision requires these utilities
to file applications for future biennial energy storage procurement periods in
2016, 2018 and 2020, with any proposed modifications based on data and
experiences from previous procurement periods. Much more will be known
about procurement of energy storage resources and their impact on reliability as
these processes develop.
The incipient nature of energy storage resources, uncertainty about
location and effectiveness, and unknowns concerning timing provide insufficient
information at this time to assess how and to what extent energy storage
resources can reduce LCR needs in the future. At the same time, the targets and
requirements of D.13-10-040 lead to a conclusion that energy storage resources
will reduce LCR needs in the SONGS service area in the future. While we cannot
quantify the LCR effect of potential energy storage resources, we conclude that it
is reasonable to consider this potential as a directional indicator. In other words,
this gives us more confidence that it is not necessary at this time to authorize the
utilities to procure all of the resources indicated to be necessary in the ISO’s
study.
R.12-03-014 ALJ/DMG/avs
- 62 -
3.3.10. Energy Efficiency
SDG&E assumed 338 MW of energy efficiency peak reductions on a hot
summer peak load basis.135 Specifically, SDG&E reduced the load in its model by
the mid-case forecast for uncommitted energy efficiency amounts adopted in the
2012 LTPP planning assumptions. This reduction is different than the one used
by the ISO in its study. The ISO used the low-case uncommitted energy
efficiency amount in the 2012 LTPP planning assumptions, per the revised
Scoping Memo, which called for 187 MW of energy efficiency peak reductions.136
NRDC agrees with SDG&E’s methodology, arguing that the Commission
should reduce ISO’s need estimates by 152 MW (338 minus 187, with rounding)
in the San Diego local area because the evidence in this proceeding demonstrates
that the revised Scoping Memo mistakenly assumed that SDG&E’s local area was
different from its service territory area. The revised Scoping Memo directed the
ISO to use the “low level of [energy efficiency] savings for use in this set of
studies” in SDG&E’s local capacity area.137 Normally, the low estimate would be
used to account for the uncertainty of locational impacts of energy efficiency
within a utility’s service area.138 As NRDC’s witness Martinez testified, “The
amount included in the local area should simply be the amount reasonably
135 Exhibit SDG&E-1 (Anderson), at.10.
136 May 21, 2013 revised Scoping Memo in R.12-03-014, Attachment A, at 4.
137 Scoping Memo, Attachment A at 4.
138 Scoping Memo, Attachment A at 4. “When the service territory of a large utility that
has areas both inside and outside a local capacity area is unlikely to have savings spread completely evenly throughout the territory, the CPUC will make a low savings estimate of energy efficiency to account for the possibility that the local capacity area might not get a proportional share of territory-wide savings; a “mid” estimate would reflect the CEC’s best estimate across the entire territory. “
R.12-03-014 ALJ/DMG/avs
- 63 -
expected to occur in SDG&E’s service territory, since they are the same
geographical area.”139
We agree with SDG&E and NRDC that the revised Scoping Memo should
have used a different methodology with the mid-level energy efficiency estimate.
The revised Scoping Memo stated: “across the SCE and SDG&E areas we expect
the mid-level of savings to occur.”140 The revised Scoping Memo erroneously
decreased energy efficiency estimates by assuming that the SDG&E service
territory was not the same as the SDG&E portion of the SONGS service area.
This is incorrect: they are one and the same. SDG&E properly applied the mid
case estimate of 318 MW in its study.141 Because we have data from SDG&E
showing the LCR difference for the more appropriate mid-level energy efficiency
estimate, it is reasonable to adjust the ISO study results by 152 MW.142
3.3.11. Solar Photovoltaic (PV)
The revised Scoping Memo designates incremental customer-side solar PV
as a ‘second contingency’ resource because it is difficult to predict the location
where customer-side PV will get built. The revised Scoping Memo directs the
ISO to determine the most effective busbars where customer-side PV should be
located in order to address those contingencies: “[o]nce those locations are
139 Exhibit NRDC-1 (Martinez), at 11-12.
140 Revised Scoping Memo, Attachment A, at 4.
141 Exhibit SDG&E-1 (Anderson), at 5.
142 We note that this is the one exception we will make to the assumptions in the revised Scoping Memo, as this adjustment is due to an error and the LCR adjustment is clearly available in the record.
R.12-03-014 ALJ/DMG/avs
- 64 -
identified, the Commission can then direct customer-side generation programs,
like the California Solar Initiative or other efforts, to target those locations.”143
ISO witness Sparks testified: “The incremental small PV is actually a load
modifier, it's typically behind the meter; and again, because it's not really known
where the locations are, it was not included either. Not to say that it couldn't be
used to meet the need if the characteristics are appropriate and it becomes more
certain.”144
CEJA contends that by 2022, with the likely implementation of smart
inverters and a smarter grid in general, distributed generation such as customer
side PV will provide manageable power located in the affected area that can
reduce peak loads, reduce transmission line loss, and provide ancillary services
such as reactive power and voltage support.145
CEJA may be correct about what will occur in the future; we are confident
that our programs and the marketplace will increase the amount of solar PV in
the future. However, we have no specific data or analysis in the record to
determine where solar PV will locate, or the impacts of solar PV on LCR needs.
We are hopeful that solar PV can be useful in reducing LCR needs in the future,
but it is too speculative to make any changes to the ISO study results on this
basis at this time.
143 Revised Scoping Memo, at 10.
144 RT 1456.
145 CEJA Opening Brief, at 43.
R.12-03-014 ALJ/DMG/avs
- 65 -
3.3.12. Living Pilot
SCE describes its plan for an aggressive pursuit of preferred resources
through the “Preferred Resource Living Pilot Program” (Living Pilot) in the
vicinity of the Johanna and Santiago substations in the LA Basin (these
substations are in Orange County, in the west LA portion of the LA Basin). The
purpose of the Living Pilot is to aggressively pursue energy efficiency, demand
response and distributed generation resources in this high impact area. SCE
intends to use the Pilot to demonstrate the value that preferred resources can
contribute to meeting LCR needs.146 SCE anticipates that development of the
Pilot will be a collaborative process undertaken with substantial input from the
ISO and other stakeholders.147 SCE is not seeking approval of the Living Pilot in
this proceeding; SCE intends to file a future application on this topic.
As the Living Pilot is not before us at this time, we cannot make any
determination about its viability or ability to meet LCR needs in the LA Basin.148
To the extent that new resources are eventually procured through this effort, we
will need to look closely to determine how they interact with other
146 Exhibit SCE-1, at 52.
147 Exhibit SCE-1, at 51.
148 In order to support the implementation of the Living Pilot while still maintaining local reliability should the Living Pilot not achieve its goals, SCE states that it plans to develop gas-fired generation sites near the Johanna and Santiago substations. SCE states that it will work to obtain the necessary sites and associated permits; these sites would only be utilized only if the Pilot is unsuccessful and an LCR need continues to exist. If a contingency arose, SCE would put the sites out to bid to Independent Power Producers (IPP). The successful IPP would be awarded a power purchase agreement to finish the development of the project. SCE is not requesting approval of this plan at this time. SCE plans to file an Application with the Commission which will provide additional information regarding contingency siting. We do not opine about these potential contingent site development plans at this time.
R.12-03-014 ALJ/DMG/avs
- 66 -
authorizations (e.g., do Living Pilot procurements count toward SCE’s LTPP
preferred resources requirements?). At the same time, in concept the Living Pilot
is promising both as a way to meet LCR needs and as a laboratory for innovation
regarding preferred resources. We intend to take a close look at the Living Pilot
when SCE files its application. For now, we simply note that projects which may
become part of the Living Pilot may have the potential to reduce the need for
other resources to meet LCR needs in the LA Basin. 149
In addition, we strongly encourage SDG&E to pursue its own Living Pilot,
or a tailored version of it. When asked by Commissioner Florio whether, if the
Commission requested SDG&E could do something similar to SCE’s preferred
resources RFO or Living Pilot, SDG&E witness Anderson testified: “I’m sure if
the Commission asked, we will find a way to do it.”150 SDG&E should consider
this decision as the Commission’s request.
4. Need Determination
The only party to recommend a local capacity requirement (LCR) need
level at or above the amount in the ISO study, without any downward
adjustment at this time, is PG&E. PG&E recommends adopting an identified,
incremental LCR need of 5,070 MW in southern California. PG&E recommends
this adopted incremental LCR need “should not be artificially reduced by
assuming that other not-yet-approved generation and transmission projects will
come to fruition.” PG&E recommends adopting an incremental LCR need for
SCE of 3,300 MW of resources, and an incremental LCR need for SDG&E of
149 The Commission held a Symposium on the SCE Living Pilot concept on November 6, 2013.
150 RT 1815-16.
R.12-03-014 ALJ/DMG/avs
- 67 -
1,770 MW of resources. PG&E would count toward these procurement amounts
Commission authorizations for “all incrementally procured resources that have
been demonstrated to be effective in meeting the identified incremental LCR
need including.” These would include (at some point), resources procured by
SCE in response to the Track 1 authorization (D.13-02-015) and by SDG&E in
response to the D.13-03-029 authorization now approved in D.14-02-016, as well
as transmission solutions verified to reduce local reliability needs without
building new generation and on track to be completed in the necessary
timeframe.151
In D.13-02-015, Finding of Fact 7, we addressed concerns about
over-procurement and under-procurement: “Both under-procurement and
over-procurement entail significant risks. Under-procurement entails risks of
reliability problems and the impacts of mitigating such problems in a short
timeframe. Over-procurement entails risks of excessive costs and unnecessary
environmental degradation. It is not possible to quantify whether the risks of
over- or under-procurement are greater.” In Finding of Fact 32 in that decision,
we stated: “A maximum LCR procurement level will protect ratepayers from
excessive costs resulting from potential over-procurement.” We continue to be
concerned about the potential excess ratepayer costs resulting from
over-procurement.
PG&E’s recommendations carry a significant risk of over-procurement.
PG&E does not adequately take into account the likelihood of various supply or
demand considerations which are either very likely or reasonably likely to occur;
151 PG&E Opening Brief, at 2-3.
R.12-03-014 ALJ/DMG/avs
- 68 -
these factor will lower the overall need from the levels modeled by the ISO.
PG&E’s recommendations also would empower SCE and SDG&E to determine
on their own whether further procurement is needed through 2022 in the SONGS
service area, beyond amounts authorized in a limited number of Commission
decisions. We are not convinced that it is either reasonable or prudent to grant
such latitude to the utilities; we note that neither SCE nor SDG&E seek such
broad authority. While the procurement objectives of utilities are often aligned
with the public interest (e.g., ensuring reliability, consistency with environmental
statutes), utilities may also have objectives (e.g., additions to rate base,
competitive concerns) that differ from the public interest. Such divergent
interests may result in higher ratepayer costs than with more close regulation.
Based upon the foregoing analysis, there is a wide range of possible
reasonable and prudent outcomes. We find that the highest reasonable need
level must take into account those resources which are very likely to be procured
in the time frame between now and 2022. These include the full Track 1
authorizations for SCE (1,800 MW), and the D.13-03-029 and D.14-02-016
authorizations for SDG&E (300 MW). Further, we find that it is reasonable at this
time to authorize procurement of at least 588 MW fewer resources than would be
necessary to achieve the ISO’s current reliability objective, with the
understanding that actual load shedding would be a very remote possibility and
that the ISO has the authority to continue the current SPS in the San Diego area.
We leave open the possibility that additional resources may need to be procured
to maintain consistency with ISO transmission policy over the long run, while
noting that ISO transmission planning policy may evolve over time. We also
find it reasonable to reduce the required LCR procurement level by 152 MW to
R.12-03-014 ALJ/DMG/avs
- 69 -
properly take into account the mid-level energy efficiency forecast in the SDG&E
local area.
Taking these very likely or certain modifications into account, the highest
prudent level of procurement authorization for the SONGS study area would be
1,802 MW (rounded to 1,800 MW). This calculation is based on the ISO’s high
starting point of 4,642 MW (based on 80% of resources in the SCE territory),
subtracting out SCE Track 1 authorization (1,800 MW), SDG&E’s D.13-03-
029/D.14-02-016 authorization (300 MW), a potential continued SPS in San Diego
(588 MW) and the adjustment for mid-level uncommitted energy efficiency (152
MW). (See Chart 1.)152 Any level above this amount entails too high of a
possibility of over procurement. However, it would also be prudent to authorize
a lower level of procurement to the extent that other resources that are
reasonably likely to be procured are considered, even if their LCR impacts cannot
be precisely measured.
152 Starting from the ISO’s lower starting point of 4,500 MW (based on 67% of resources in the SCE territory), the maximum level would be approximately 1,650 MW.
R.12-03-014 ALJ/DMG/avs
- 70 -
Chart 1 Maximum Procurement Calculation
We have identified a number of resources, at least some of which are
reasonably likely to be procured in the SONGS study area by 2022 outside of this
procurement proceeding. These include additional transmission (in particular,
the Mesa Loop-In), demand response, energy efficiency, solar PV and energy
storage resources. In addition, while it is speculative to consider the impacts of
resources such as reactive power support, if such resources are available and
effective at the right place and in a timely manner, they would have the impact of
lowering LCR needs. Further, the future Living Pilot may add additional
resources. We find that it is unreasonable to assume that none of these resources
will be procured and able to meet local reliability needs in the SONGS service
area by 2022. While the exact levels of procurement of these resources via other
Commission proceedings, other agency requirements, and various market
processes cannot be known with any certainty at this time, assuming that none of
these potential resources will be available would not be prudent because it
R.12-03-014 ALJ/DMG/avs
- 71 -
would most likely lead to over-procurement. In our judgment, it is reasonable to
assume that at least between 10% and 20% of these resources will be available, in
some combination.
Therefore, we find that there is a range of reasonable need levels that we
can consider to be prudent.153 This high end of the range is approximately
1,800 MW; authorization of this level of resources at this time would be the most
conservative (but still prudent) action we could reasonably take in terms of
reliability – but also the most costly in terms of procurement and most likely the
least environmentally sensitive.
It is important to note that the methodology to determine the outer edges
of a reasonable procurement range in this decision may not be the only
reasonable methodology. In order to test the robustness of our determination
that 1,800 MW is the maximum prudent level of procurement that should be
authorized at this time, it is useful to consider alternative assumptions. For
example, an alternative analysis might determine that we should authorize
procurement consistent with the recommendation of the ISO and other parties
regarding load-shedding and an SPS (thus not subtracting 588 MW), but at the
same time assume that the Mesa Loop-In project would be viable (thus
subtracting 734 MW). Or, that we should authorize procurement of 588 MW to
fully avoid the N-1-1 contingency, but agree with NRDC that more aggressive
153 SDG&E witness Anderson requested flexibility in the utility’s request, “We don't know the numbers this precisely. We ought to have some range to be flexible given the size of bids and the size of power plants.” (RT 1845.)
R.12-03-014 ALJ/DMG/avs
- 72 -
energy efficiency assumptions worth up to 733 MW154 are appropriate. As
another possibility, we could have determined that some or all of the ‘second
contingency’ demand response adjustments worth 800 MW should be accounted
for.
In determining an alternative maximum prudent procurement amount,
determinations should not incorporate more than one potential source to meet or
reduce LCR needs into the analysis. In other words, we should consider, for
example, whether either not to procure capacity to fully avoid the N-1-1
contingency or whether to assume another resource (or combination of partial
achievements of resources) should be counted – but not both. Otherwise, there is
too great a likelihood of under-procurement because of the risk that various
uncertain or speculative resources will not materialize.
Table 2 shows the upper bound of a reasonable procurement range under
different assumptions. Per Chart 1 above, the maximum procurement level is
2,390 MW before the 588 MW adjustment related to load-shedding policy. With
various alternative assumptions, the maximum procurement level varies from
1,800 MW (our determination) down to 1,393 MW. Therefore, this sensitivity
analysis allows us to confidently conclude that, under either the facts we find
today or other reasonable sets of facts, the upper bound of procurement that
should be authorized today should in no case be higher than 1,800 MW, and that
levels between 1,393 and 1,800 MW could potentially be considered excessive.
However, we again note that there is no operational data to determine LCR
154 NRDC calculates 885 MW of energy efficiency capacity that is not included in the ISO models. However, we subtract for 152 MW of this total in our analysis. The difference is 733 MW.
R.12-03-014 ALJ/DMG/avs
- 73 -
effectiveness for uncommitted energy efficiency, energy storage, ‘second
contingency’ demand response or total ‘second contingency’ solar PV.
Therefore, a reasonable maximum procurement level should be somewhere
between 1,393 and 1,800 MW.
As a check on this methodology, the total of possible resources or
assumptions identified by parties included in Table 2 that were not studied by
the ISO equals about 4,600 MW. The range of reasonable maximum procurement
levels takes into account between 588 and 997 MW of this 4,600 MW, or between
13% and 22% of 4,600 MW. This is very close to our judgment that, in some
combination, approximately 10% to 20% of resources will be available, at a
minimum. For the purpose of calculating a maximum procurement level, it is
reasonable to assume that at least 13% - 22% of the resources or assumptions in
Table 2 will ultimately be available to meet or reduce LCR needs in the SONGS
service area by 2022.
Table 2 Maximum Procurement Range
Assumed adjustment to 2390 MW
Need Impact On Need
Derived Upper-bound of
Procurement Needed
Temporary Load-shedding -588 MW 1802 MW
Mesa-Loop in Transmission Project -734 MW 1656 MW
Uncommitted EE -733 MW 1657 MW
Energy Storage -745 MW 1645 MW
Second contingency Solar PV -800 MW 1590 MW
Second contingency DR -997 MW 1393 MW
R.12-03-014 ALJ/DMG/avs
- 74 -
A minimum procurement level must also be defined. Several
environmental and ratepayer parties (e.g., NRDC,155 CEJA,156 Sierra Club,157
EDF,158 CLECA159)160 recommend no procurement at this time, based on their
analysis that there are likely to be sufficient resources available (and reductions
in demand) to obviate any LCR need in the SONGS study area through 2022.161
We disagree. Our concern in D.13-02-015 included the reliability risks of
under-procurement. The analysis in the above sections shows that it is not
reasonable to assume that most or all of these resources (or the SCE and potential
SDG&E Living Pilots) counted by these parties will be fully procured and in
place by 2022, and will meet or reduce LCR needs. For example, even in the
unlikely event that all of parties’ proposed highest amounts of 800 MW of
‘second contingency’ demand response resources or 733 MW of remaining
‘naturally-occurring’ energy efficiency were to exist, the actual LCR impacts are
certain to be less than these MW amounts.
155 NRDC Opening Brief, at 1.
156 CEJA Opening Brief, at vii.
157 Sierra Club Opening Brief, at 2.
158 EDF Opening Brief, at 3.
159 CLECA Opening Brief, at 2.
160 EnerNOC recommends no incremental procurement for SCE at this time, but does not oppose SDG&E’s recommendation. EnerNOC Opening Brief, at 13, 14.
161 Other parties, such as CEERT, recommend no procurement authorization at this time for procedural reasons. For example, CEERT argues “The Commission should find that…the current record in Track 4 does not justify any “interim” Track 4 authorization for SCE or SDG&E by January or Q1 2014, especially without consideration of those near-term changes in key assumptions, and, instead, Track 4 should be the subject of a “holistic” final decision that can be issued on a timely basis as early as June or July 2014.” (CEERT Opening Brief, at v.)
R.12-03-014 ALJ/DMG/avs
- 75 -
We have determined that it is reasonable to assume that some combination
of these and other (e.g., energy efficiency, energy storage) resources will be
available and will mitigate LCR needs, however it is not reasonable to assume
this will be true for all (or even most) of these resources. Therefore, while it is
mathematically possible to construct an analysis using a series of optimistic
assumptions about resource availability that could lead to a finding of zero need
(or negative need, which would indicate a surplus through 2022) at this time,162
we find that a conclusion of zero need is not reasonable. A finding of zero need
would not be prudent because it would most likely lead to under-procurement.
At the same time, between all the various resources and assumptions
considered in this decision, there are potentially far more than 1,800 MW of
additional resources that may be procured and meet or reduce LCR needs by
2022 in the SONGS service area (for example, we have identified 4,600 MW in
Table 2). It is not prudent to assume that all of these resources will actually be
effective and available at the right places and at the right time. In addition, in
most cases we do not have sufficient information in the record to determine the
LCR impact of such resources, because no party included these resources in their
studies.163
A prudent analysis of the minimum procurement levels at this time should
take into consideration a higher level of reasonably likely resources than
162 For example, Sierra Club calculates a surplus of at least 488 MW. Sierra Club Opening Brief, at 16.
163 As discussed herein, SDG&E and SCE calculated the LCR impacts of certain transmission projects. However, these projects are not yet approved by the ISO and (even if approved and ultimately constructed), completion dates are uncertain.
R.12-03-014 ALJ/DMG/avs
- 76 -
included in maximum procurement levels. As a proxy for calculating a
minimum LCR need level we can calculate the LCR impact if any two of the most
likely potential scenarios (load-shedding, Mesa Loop-In, additional energy
efficiency impacts, ‘second contingency’ demand response, solar PV, energy
storage) should occur.164 This methodology is roughly parallel with the ISO’s
N-1-1 analysis for LCR needs, which considers the loss of the two largest
contingencies, and might be considered an “N+1+1” analysis (although a less
rigorous endeavor). It is worth noting that another way of looking at this
analysis is that some combination of scenarios could substitute for some LCR
reduction from other scenarios. It is not useful or necessary to evaluate all
possible scenarios to consider a minimum analysis. Analyzing 100% availability
of any two scenarios is a reasonable proxy for the largest amount of available
LCR reductions.
Table 3 illustrates a similar methodology as used to consider the
reasonable maximum procurement range, starting with a base of 2,390 MW and
subtracting for various potential resources not included in the ISO modeling.
Table 3 shows that, in each case of 100% availability of any two scenarios not
included in the ISO’s modeling, the lower bound ranges from 593 to 1,067 MW.
Therefore, this analysis allows us to confidently conclude that, under either the
facts we find today or a reasonable sensitivity analysis, the lower bound of
procurement that should be authorized today should in no case be lower than
593 MW. To be certain that the amounts authorized today will not result in
164 Assuming for the sake of discussion that, when not studied, a MW decrease in demand equals a MW decrease in LCR needs. In reality, demand reductions are likely to result in less than a one-to-one decrease in LCR needs. This suggests that the minimum procurement level should be higher than calculated in this analysis.
R.12-03-014 ALJ/DMG/avs
- 77 -
under-procurement, the minimum authorized procurement level should be no
less than 593 MW. Authorization of this level of resources at this time would be
the most conservative action we could reasonably take in terms of procurement
cost and environmental sensitivity – but would be the most risky in terms of
reliability.165
However, we once again note that there is no data to determine LCR
effectiveness for uncommitted energy efficiency, energy storage, ‘second
contingency’ demand response or total ‘second contingency’ solar PV.
Therefore, a reasonable minimum procurement level should be somewhere
between 593 and 1,067 MW.
Another way of looking at this methodology is that the total of all possible
resources or assumptions identified by parties (and which are included in Table
2) that were not studied by the ISO equals about 4,600 MW. The range of
reasonable minimum procurement levels takes into account between 1,322 and
1,797 MW of this 4,600 MW, or between 29% and 39% of 4,600 MW. This is
approximately double the minimum level of resources we judge to be available,
in some combination. For the purpose of calculating a minimum procurement
level, it is reasonable to assume that at least 29% and 39% of these resources or
assumptions will ultimately be available to meet or reduce LCR needs in the
SONGS service area by 2022.
165 There are significant costs involved in any degradation of reliability. The section in this decision on SPS and load-shedding provides a partial discussion of such costs.
R.12-03-014 ALJ/DMG/avs
- 78 -
Table 3 Minimum Procurement Range
Assumed adjustment to 2390 MW Need Impact on Needed
Procurement
Procurement
Still Needed
Load-shedding (588) + Mesa Loop-in (734) -1322 1068
Load-shedding (588) + Uncommitted EE (733) -1321 1069
Load-shedding (588) + Energy Storage (745) -1333 1057
Load-shedding (588) + Second Contingency Solar PV (800) -1388 1002
Load-shedding (588) + Second Contingency DR (997) -1585 805
Mesa-Loop In (734) + Uncommitted EE (733) -1467 923
Mesa-Loop In (734) + Energy Storage (745) -1479 911
Mesa-Loop In (734) + Second Contingency Solar PV (800) -1534 856
Mesa-Loop In (734) + Second Contingency DR (997) -1731 659
Uncommitted EE (733) + Energy Storage (745) -1478 912
Uncommitted EE (733) + Second Contingency Solar PV (800) -1533 857
Uncommitted EE (733) + Second Contingency DR (997) -1730 660
Energy Storage (745) + Second Contingency Solar PV (800) -1545 845
Energy Storage (745) + Second Contingency DR (997) -1742 648
Second Contingency Solar PV (800) + Second Contingency DR
(997) -1797 593
We next consider the recommendations of the parties about what amounts
should be authorized to fill identified needs, other than PG&E (which
recommends above the upper level of prudency) and those parties
recommending zero procurement at this time (below the lower level of
prudency).
As a starting point, the ISO’s August 5, 2013 study yielded a resource need
of 612 MW for SDG&E (after consideration of D.13-03-029 authorization of
300 MW) and up to 1,922 MW for SCE, depending on the portion of the LCR
study identified need being allocated to the LA Basin and after deducting Track 1
authorization. However, this is not the ISO’s recommended procurement level.
SCE and SDG&E each submitted testimony on August 26, 2013 based on
power flow studies that reflected transmission upgrades, including reactive
power resources, not studied by the ISO. SCE and SDG&E began their studies in
R.12-03-014 ALJ/DMG/avs
- 79 -
advance of the revised Scoping Memo; accordingly, the utilities’ assumptions are
not identical to those used in the revised Scoping Memo.166 However, SCE and
SDG&E analyzed several scenarios, as shown in Exhibit 1 (the Joint Comparison
Exhibit).
Considering all of its scenarios as well as the ISO’s forecasts, SCE
recommends procurement of 500 MW in the LA Basin. SCE witness Nelson
testified that “no new generation is needed to meet NERC Reliability Standards”
at this time.167 We have already determined that it is reasonable to defer
procurement of at least 588 MW of additional resources (433 MW in SCE
territory) that otherwise would be required to meet N-1-1 requirements and
avoid load shedding. Thus, SCE’s calculation that no additional procurement is
needed at this time in its territory appears consistent with this determination.
However, SCE’s study assumed that the Mesa Loop-In transmission project
would be approved and completed by 2022, thereby reducing LCR needs by
734 – 1,200 MW (depending upon if load shedding is allowed through an
extended SPS in the SDG&E territory). We do not make this assumption about
the Mesa Loop-In project. Therefore, SCE’s recommendation to authorize
500 MW in the LA Basin is consistent with a policy decision to not authorize
resources to meet all N-1-1 criteria at this time.
166 Exhibit SDG&E 1 (Anderson), at 2.
167 Exhibit SCE-1 (Nelson), at 6.
R.12-03-014 ALJ/DMG/avs
- 80 -
SDG&E’s technical studies calculate a need for at least 1,028 MW of new
local resources between now and 2022 in the San Diego area.168 SDG&E’s
minimum base case analysis assumed 408 MW of load reduction/resource
additions from incremental preferred resources above current levels (prior to
running the transmission models), which effectively reduces minimum local
need in the SDG&E sub-area to 620 MW (1,028 MW minus 408 MW).169 Thus,
SDG&E has identified in this Track 4 a minimum need for new local resources in
the San Diego sub-area of between 620 MW and 1470 MW by 2022.170 Of the
620 MW minimum need, SDG&E’s procurement strategy holds 70-120 MW open
to be filled with demand response and/or energy storage resources (consistent
with ISO for operational characteristics that address local reliability needs). For
the remaining need, SDG&E requests authority to procure 500-550 MW of long
lead-time supply-side resources, including conventional generation and/or
renewable resources.171
Redondo Beach performed its own technical studies, using power flow
analysis. Redondo Beach claims that its studies used the same inputs and
assumptions as the ISO. Redondo Beach recommends procurement of 1,140 MW
168 This analysis assumes Commission approval of SDG&E’s A.13-06-015, which seeks authority to enter into a power purchase and tolling agreement with Pio Pico Energy Center for 300 MW of conventional generation.
169 Exhibit SDG&E-1 (Anderson), at 9. The analysis assumes a “dependable” peak reduction of 338 MW of Energy Efficiency, 30 MW of rooftop solar and 20 MW of Combined Heat and Power resources. (Id., at 7, Table 1.) It also assumes 20 MW of dependable peak reduction associated with local renewable generation. (Id. at 11, Table 2.)
170 Exhibit SDG&E-3 (Jontry), at 2.
171 SDG&E Opening Brief, at 4.
R.12-03-014 ALJ/DMG/avs
- 81 -
in the LA Basin and 753 MW in the SDG&E area. For the LA Basin, Redondo
Beach recommends all procurement be from preferred resources based on its
studies.172 SCE responds that, while Redondo Beach claims that their proposal is
the only solution that addresses both the Western LA Basin sub-area as well as
the greater SONGS area, the record shows that Redondo Beach only studied the
Western LA Basin and did not perform a study to analyze the impacts on the
greater SONGS study area.173 We do not agree with SCE that Redondo Beach’s
study is incomplete in this regard. However, significant parts of Redondo
Beach’s studies rely on interpretations of N-1-1 contingencies that are at odds
with the ISO’s studies; we have already determined that we will defer to the ISO
on this point. While we consider Redondo Beach’s recommendations along with
those of other parties, we will rely on the ISO study (as modified herein) as the
better analytical tool.
The ISO now recommends approval of the recommendations of SCE and
SDG&E:
“Given the importance of maintaining reliability in this heavily populated, urban area of California, and the complex array of actions necessary to meet the residual needs identified by the [ISO], it is urgent for the Commission to authorize an all-source procurement for SCE and SDG&E for the amounts requested. This is much different, of course, than authorizing a comprehensive amount of procurement meant to address all the residual needs, which we advised against in Mr. Sparks’ initial testimony.”174
172 Redondo Beach Opening Brief, at 1-4.
173 SCE Reply Brief, at 47.
174 Exhibit ISO-7, at 6.
R.12-03-014 ALJ/DMG/avs
- 82 -
In Opening Briefs, the ISO, TURN, CalWEA, Alton, CESA, WPTF, and
Wellhead all support SCE’s request for procurement authorization for an
additional 500 MW in this Track 4.175 In a change from its position in testimony
(as reflected in Exhibit 1), ORA now recommends176 that the Commission
authorize procurement of between 1,315 and 1,450 MW, with 700 MW in SCE
service territory and between 615 and 750 MW in SDG&E service territory.177
TURN recommends that SCE and SDG&E each be authorized to procure up to
500 MW, plus or minus ten percent within their respective service territories to
accommodate the potential “lumpiness” of transmission or generation
investments (thus TURN’s recommendation is for procurement authorization for
450 – 550 MW for each utility, or 900 – 1,100 MW in total). IEP recommends that
the Commission should authorize an interim procurement of at least 706 MW for
SCE and 820 MW for SDG&E.178 CalWEA recommends procurement of 500 MW
for SCE and 300 - 350 MW for SDG&E.179 AES Southland recommends that the
Commission authorize SCE to procure an additional 1,440 MW of generation,
175 ISO Opening Brief, at 33-34, TURN Opening Brief, at 1-2, CalWEA Opening Brief, at 1-2, Alton Opening Brief, at 3, WPTF Opening Brief, at 2, Wellhead Opening Brief, at 1-2.
176 In its Opening Brief at 11, ORA also recommends that the Commission consider the ISO’s 2013/2014 Transmission Planning Process in determining need for the SONGS study area.
177 ORA Opening Brief, at 13-14.
178 Exhibit IEP-1 (Monson), at 30.
179 CalWEA Opening Brief, at 5.
R.12-03-014 ALJ/DMG/avs
- 83 -
based upon SCE’s own need calculation, absent load shed, less the Track 1
procurement already authorized.180
Each of these parties’ recommendations stem from modestly different
methodologies, although each have in common certain subtractions from a total
LCR need for procurement already authorized and calculations of expected
resources. While varying in some aspects, each of these parties’
recommendations fall within the prudent range of procurement we have
identified for the SONGS service area: a number significantly greater than zero
and less than 1,800 MW. The lowest recommendation of these parties is 800 MW
for the SONGS service area, the highest is over 1,400 MW.
Similar to the Track 1 decision in this docket, we will authorize a
procurement range. Authorizing a procurement range takes into account
a) uncertainties about supply and demand conditions; b) the ability to process
new information during the procurement process; c) the need to provide the
utilities with flexibility to procure resources which may only be available in large
increments; d) increases in requirements to procure preferred resources (as
discussed below); and e) the need to provide utilities and the Commission with
the ability to protect ratepayers by not forcing certain less economic procurement
decisions.
180 AES Southland Opening Brief, at 5.
R.12-03-014 ALJ/DMG/avs
- 84 -
We have determined that the outer edges of a reasonable procurement
range to be 593 MW to 1,800 MW, but that minimum procurement could be up to
1,067 MW and maximum procurement could be as low as 1,383 MW. The overall
procurement level we authorize for the SONGS service area at this time is
1,000 - 1,500 MW. This range is consistent with the recommendations of many
parties and is near the center of the overall zone of reasonableness. This range
provides greater ratepayer protection against over procurement and
simultaneously reduces the likelihood of any reliability impacts from under
procurement.181 These authorized amounts are not the full amounts needed to
meet the LCR needs; a significant amount of future procurement in the SONGS
service territory will come from the various resources analyzed herein. Further,
there may be a need to authorize further procurement in future LTPP
proceedings in the event of changes in supply and demand forecasts, to meet ISO
reliability criteria, or if circumstances change significantly.
We accept the ISO’s analysis that between 67% and 80% of procurement
needed to address LCR needs in the SONGS service area by 2022 must be in the
LA Basin, which is in SCE territory. The remainder would be in the SDG&E
service territory. It is not possible at this time to discern how resources between
the 1,000 – 1,500 MW amounts authorized today, and the approximately 4,500 –
4,600 MW level of total procurement need identified by the ISO, ultimately will
be distributed between SCE and SDG&E territories. We already have
determined that 1,800 MW will be procured from Track 1 by SCE, and 300 MW
from D.13-03-029 for SDG&E; thus, over 85% of these authorized resources are
181 Environmental considerations of procurement levels are addressed in Section 5 of this decision, where we determine the mix of resources to be procured.
R.12-03-014 ALJ/DMG/avs
- 85 -
already slated for SCE territory. Other opportunities are less clear. For example,
it is possible the Mesa Loop-In project goes forward, but the SDG&E proposed
transmission projects do not. In that case, at least several hundred MW more
resources would be in SCE territory, necessitating a greater procurement
requirement for SDG&E to retain a proper allocation. Because of several
unknowns, authorized amounts today may need to be adjusted in the future to
balance procurement between utility territories.
We authorize SCE to procure between 500 and 700 MW. We authorize
SDG&E to procure between 500 and 800 MW. The greater maximum amount for
SDG&E reflects several factors. First, SDG&E’s recommendations include
assumptions for transmission lines which we do not accept as reasonably likely
(unlike the Mesa Loop-In for SCE). Second, even with its transmission
assumptions, SDG&E’s studies show a need for at least 1,028 MW in its territory
by 2022. After assuming the Pio Pico plant, SDG&E shows a need for at least
728 W in its territory. Third, as discussed below, we will require SDG&E to
procure more preferred resources than the 120 MW it contends are achievable
(on top of 408 MW of preferred resources SDG&E expects to procure through
other proceedings). In light of all of these factors, it is appropriate and prudent
to allow SDG&E to procure up to 800 MW at this time to avoid under-
procurement.
Given that the bulk of both total authorized and potential resources are
expected to be in SCE territory, authorizing the same procurement range for both
utilities should be consistent with the ISO’s range that 67 - 80% total procurement
needs to be in the SCE territory. In both cases, the high end of the range is above
what the utilities requested, but within the range of prudent procurement
R.12-03-014 ALJ/DMG/avs
- 86 -
established in this order. For both utilities, these authorized amounts are subject
to conditions established herein.
We note that there are also additional safeguards to ensure that under
procurement does not occur, beyond the various expectations for resource
procurement discussed herein, and future LTPP proceedings. For example, ORA
recommends that, notwithstanding California’s commitment to meeting OTC
compliance deadliness, the Commission should consider that limited extensions
to OTC compliance deadlines of the most electrically effective OTC plant(s) may
be available if needed to bridge a short-term gap between when resources are
needed, and when they are available.182
In D.13-02-015, Finding of Fact 10 stated: “It is reasonable to assume that
the OTC plants in the SCE territory required to comply with SWRCB regulations
will comply through retirement or repowering consistent with the SWRCB
schedule, for the purpose of LCR forecasting in this proceeding. However, no
finding on this point is intended to apply to SONGS.”183 We do not revisit this
Finding. At the same time, we agree with ORA’s observation that it may be
possible to extend OTC deadlines if it is necessary to ensure reliability. Any such
action will occur through the appropriate process.
182 ORA Opening Brief, at 27.
183 The reference to SONGS in this Finding of Fact was intended to reference SONGS as an OTC plant. In other words, there was no Finding of Fact about whether SONGS would remain in service, retire, or repower in any given timeframe.
R.12-03-014 ALJ/DMG/avs
- 87 -
5. Filling the Identified Need
5.1. Requirement for Procurement of Preferred Resources
At the time of the Track 1 decision in this proceeding, the permanent
closure of SONGS was not anticipated or factored into the modeling considered
in that track. As a nuclear power facility, SONGS has been subject to various
safety and environmental concerns over the years, but SONGS did not emit any
greenhouse gases during its time in service. To replace a zero emission facility
like SONGS with other resources, several parties argue it is necessary to mandate
only low-to-no emitting resources as a source of replacement capacity. NRDC,
Sierra Club, CEJA, and EDF all urge that any procurement authorized by the
Commission should include preferred resources only.184
Other parties point out that the complexities of maintaining reliability on
the local grid require a sophisticated set of characteristics, which cannot always
be met with preferred resources. A number of parties therefore recommend
requiring procurement of preferred resources to the greatest extent possible, but
providing the utilities with the opportunity and obligation to procure a mix of
resources that balances fealty to the Loading Order with meeting grid
requirements. For example, CEERT recommends that, consistent with the
Loading Order and procurement proportions established in D.13-02-015, no more
than 2/3 of the authorized maximum procurement levels should be met by
conventional gas-fired resources; the remainder should be preferred resources.185
Another group of parties – including SCE and SDG&E - recommend allowing the
184 NRDC Opening Brief, at 18-19; Sierra Club Opening Brief, at 1-3; CEJA Opening Brief, at vii; and EDF Opening Brief, at 7-8.
185 CEERT Opening Brief, at 47-48.
R.12-03-014 ALJ/DMG/avs
- 88 -
utilities to use all-source RFOs to procure authorized resources on a
least-cost/best-fit basis, thereby providing the utilities with the ability to choose
the resource mix (subject to subsequent Commission approval).
The ISO endorses the idea that substantial portions of the local capacity
needs created by the SONGS outage can be filled with preferred resources, with
two caveats:
First, the Commission and parties must be diligent in moving ahead to
develop the necessary programs that can participate with other supply-side
resources (such as demand response) and that will provide load-shaping
demand-side benefits (such as energy efficiency and small PV) with the
necessary locational data that the ISO can use in its local area capacity studies to
offset the need for conventional infrastructure.
Secondly…the Commission must be diligent and expeditious in tracking the development of preferred resources in order to verify that they are actually materializing in the locations and amounts predicted in the studies and resource procurement efforts that established such forecasts.186
NRG points out that local generation must provide a suite of reliability
benefits, such as: a) allowing for the regular maintenance of other generation or
transmission within the local area; b) continuously following variations in
demand or variable renewable generation; c) providing contingency reserve to
respond to sudden changes in demand or the loss of a generating or transmission
resource; d) maintaining transmission voltages within acceptable levels by
producing or absorbing reactive power as needed; e) providing or standing by
ready to provide real power output to maintain network flows within safe limits.
186 ISO Reply Brief, at 24.
R.12-03-014 ALJ/DMG/avs
- 89 -
Thus, NRG contends that relying on preferred resources to meet local area
requirements and still provide the same level of reliability requires a complex
analyses; most LCR needs are currently met by gas-fired resources.187
SDG&E also argues against mandating the use of all or nearly all preferred
resources in this decision:
While SDG&E strongly supports inclusion of preferred resources in its portfolio to serve bundled load…it does not perceive that a capacity procurement approach heavily skewed toward reliance on preferred resources is reasonable at this time, while there is still great uncertainty as to the ability of preferred resources to meet local capacity need. In short, placing all of SDG&E’s eggs in the single basket of preferred resources is an imprudent planning approach which exposes ratepayers to unreasonable risk.188
Some parties contend that SCE and SDG&E should procure only preferred
resources and energy storage because these resources can be developed
significantly quicker than traditional gas-fired generation. SCE rebuts that it
takes about seven years to develop gas-fired generation facilities in the LA Basin
and it is now approximately seven years until new LCR resources are needed in
2020. SCE contends that
“if the Commission authorizes preferred resource procurement only at this time, it is likely precluding gas-fired generation development to meet LCR need in 2020. If this occurs, then gas-fired generation will not even be an option to meet LCR need in 2020 (if it is needed) because it will not be able to be developed quickly enough. Choosing preferred resource procurement only, without any expedited approval of contingent site development and/or options PPAs, would
187 NRG Opening Brief, at 7 -8.
188 SDG&E Reply Brief, at 10.
R.12-03-014 ALJ/DMG/avs
- 90 -
likely reduce grid reliability in 2020. This is because the options to replace all OTC generating facilities, including SONGS, would be very limited.”189
In D.13-02-015, Finding of Fact 30 stated: “It is necessary that a significant
amount of this procurement level be met through conventional gas-fired
resources in order to ensure LCR needs will be met.” There is nothing in the
record of Track 4 of this proceeding that would require a change to this Finding.
While we strongly intend to continue pursuing preferred resources to the
greatest extent possible, we must always ensure that grid operations are not
potentially compromised by excessive reliance on intermittent resources and
resources with uncertain ability to meet LCR needs.
In the Commission’s RA proceeding (R.11-10-023), we are currently
exploring the ability of various preferred resources and energy storage to meet
LCR needs.190 The ISO is engaged in this effort as well. As this highly technical
process develops, we will have a better idea of how such resources can be
integrated with gas-fired resources to ensure reliability. In addition, we will
learn more about the extent to which non-gas-fired resources can be used instead
of gas-fired resources to meet LCR needs. Until this effort is better developed,
we will take a prudent approach to reliability, while still promoting preferred
resources to the greatest extent feasible. The prudent approach we take entails a
189 SCE Reply Brief, at 8.
190 In the August 2, 2013 Phase 3 Scoping Memo for R.11-10-023 (RA proceeding), the scope of the proceeding includes: “In workshops and comments, stakeholders will develop counting rules, eligibility criteria, and must-offer obligation for use-limited resources, preferred resources, combined cycle gas turbines, and energy storage resources for Commission consideration.”
R.12-03-014 ALJ/DMG/avs
- 91 -
gradual increase in the level of preferred resources and energy storage into the
resource mix, to historically high levels.
In the Track 1 decision, Ordering Paragraph 1 included the following
requirements for SCE for its authorization to procure 1,400 to 1,800 MW:
a. At least 1,000 MW, but no more than 1,200 MW, of this capacity must
be from conventional gas-fired resources, including combined heat and
power resources;
b. At least 50 MW of capacity must be procured from energy storage
resources;
c. At least 150 MW of capacity must be procured from preferred resources
consistent with the Loading Order of the Energy Action Plan;
d. Subject to the overall cap of 1,800 MW, up to 600 MW of capacity,
beyond the amounts specified required to be procured pursuant to
subparagraphs (a), (b) and (c) above, may be procured through
preferred resources consistent with the Loading Order of the Energy
Action Plan (in addition to resources already required to be procured or
obtain by the Commission through decisions in other relevant
proceedings) and/or energy storage resources.
R.12-03-014 ALJ/DMG/avs
- 92 -
We will build upon the Track 1 approach in this decision. As discussed
below, we authorize SCE to procure resources for both Track 1 and Track 4
pursuant to its Track 1 procurement plan as approved by Energy Division. This
generally entails procurement of additional resources through SCE’s
already-issued RFO as well as bilateral contracts.191 Combining Track 1 and
Track 4, SCE is now authorized to procure up to 2,500 MW in the LA Basin. SCE
proposes to add its additional requirement from Track 4 without any
specification of resource type. However, this approach is not consistent with our
stated goals here and in Track 1 to adhere to the Loading Order.
Under the terms of the Track 1 decision, if SCE procured the minimum
1,400 MW of total resources, between 200 and 400 MW (or 14% to 29%) would be
from preferred resources or energy storage. If SCE procured the maximum
1,800 MW of total resources per that decision, between 600 and 800 MW (33% to
44%) would be from preferred resources or energy storage.
In this decision, we authorize SCE to procure between 1900 MW (the
1,400 minimum from Track 1 plus the 500 minimum from Track 4) and 2,500 MW
(the 1,800 maximum from Track 1 plus the 700 maximum from Track 4). Under
SCE’s approach, SCE could procure as much as 1,700 MW from gas-fired
generation: 1,200 MW per Ordering Paragraph 1a in D.13-02-015 plus 500 MW
from this decision. If SCE procured the overall minimum amount, between
200 and 900 MW of the 1,900 MW minimum procurement authorization (11%to
47%) would be from preferred resources or energy storage. If SCE procured the
191 In addition, Ordering Paragraph 9 of D.13-02-015 states: “Southern California Edison Company is authorized to procure bilateral cost-of-service contracts to meet authorize local capacity requirements as specified in this Order, including bilateral contracts consistent with the provisions of Public Utilities Code § 454.6.”
R.12-03-014 ALJ/DMG/avs
- 93 -
overall maximum amount, between 600 and 1,500 MW of the 2,500 MW
minimum procurement authorization (24%to 67%) would be from preferred
resources or energy storage.
SCE’s proposal would expand the range of potential procurement of
preferred resources and energy storage. On the other hand, SCE could procure
up to 89% of authorized resources from gas-fired generation. It is not clear what
would actually occur; under its proposal, SCE would control the procurement
process consistent with its Track 1 procurement plan. Assuming SCE pursues a
least-cost/best-fit approach to the increased discretionary portion of
procurement authority192 (the additional 500 – 700 MW), it is likely that SCE
would procure mostly gas-fired resources if such resources are less costly than
preferred resources. From a ratepayer perspective, this may be beneficial;
however, the Loading Order calls for prioritization of cost-effective preferred
resources, in some cases even if they are more expensive than other resources.
We will modify SCE’s proposal to ensure that SCE procures a higher
percentage of authorized resources from preferred resources and energy storage.
For SCE (and SDG&E as delineated below), we will not require any specific
incremental procurement from gas-fired resources. This means that all
incremental procurement as a result of this decision may be from preferred
resources. At the same time, we will not modify the requirements from
D.13-02-015 that some procurement must be from gas-fired resources in order to
ensure reliability. Further, to provide a level of flexibility to utilities and to
192 SCE Reply Brief, at 9 (“SCE will use least-cost/best-fit criterion to ‘obtain a cost-effective mix of resources to meet SCE’s LCR needs in a manner consistent with the Preferred Loading Order.’”). Also see Exhibit SCE-2, at 22.
R.12-03-014 ALJ/DMG/avs
- 94 -
ensure procurement consistent with ISO reliability standards, we will expand the
range for both gas-fired resources and preferred resources (as well as energy
storage).
SCE is authorized to procure resources as follows, as shown in Chart 2:
a. At least 1,000 MW, but no more than 1,500 MW, of local capacity must
be from conventional gas-fired resources, including combined heat and
power resources;
b. At least 50 MW of local capacity must be procured from energy storage
resources (as defined in D.13-10-040);
c. At least 550 MW of local capacity must be procured from preferred
resources consistent with the Loading Order of the Energy Action Plan
(beyond the requirement of subsection b of this Ordering Paragraph).
Bulk energy storage and large pumped hydro facilities shall not be
excluded.
d. At least 300 MW, but no more than 500 MW, of local capacity, beyond
the minimum amounts specified in subparagraphs (a), (b) and (c), must
be procured and can be from any resource able to meet local capacity
requirements.
e. Subject to the overall cap of 2,500 MW, any additional local capacity,
beyond the amounts specified in subparagraphs (a), (b), (c) and (d),
may only be procured through preferred resources (including bulk
energy storage and large pumped hydro facilities) consistent with the
Loading Order of the Energy Action Plan. Such preferred resources
shall be in addition to preferred resources already required by the
Commission to be procured or obtained through decisions in other
relevant proceedings, and/or energy storage resources.
R.12-03-014 ALJ/DMG/avs
- 95 -
Chart 2 SCE Authorized Procurement
Track 1 + Track 4
This method ensures that at least 400 MW of the additional procurement
authorized by this decision will be obtained through preferred resources or
energy storage. In total, SCE is now authorized to procure between 400 and
1,500 MW from preferred resources or energy storage, up from 200 to 800 MW in
the Track 1 decision. If SCE procures the minimum 1,900 MW of total resources,
between 21% and 47% will be from preferred resources or energy storage. If SCE
procures the maximum 2,500 MW of total resources, between 40% and 60% will
be from preferred resources or energy storage.
SDG&E seeks to issue an all-source RFO or to contract bilaterally. SDG&E
contends that moving forward on an expedited basis with a bilateral contract to
address a portion of LCR need would support the policy goals of the State
related to timely retirement of OTC facilities and would promote system
R.12-03-014 ALJ/DMG/avs
- 96 -
reliability – the sooner new local resources are added to the portfolio, the lower
the reliability risk.193 SDG&E expects that 50 to 120 MW will be procured from
preferred resources and energy storage.
There are no requirements from D.13-03-027 for specific resource
procurement amounts to meet SDG&E’s LCR needs; however, SDG&E now has
been approved to fill the authorized 300 MW from the gas-fired Pio Pico project.
We will take a similar approach for SDG&E as for SCE. We approve SDG&E’s
proposal to issue an all-source RFO or enter into bilateral contracts for the
additional 500 – 800 MW authorized herein. SDG&E proposes that it procure
preferred resources through specific proceedings dedicated to these resources.
We agree that SDG&E should continue to follow the Commission’s requirements
in other dockets; SDG&E already anticipates 407 MW will be procured in this
manner. However, as with SCE, it is our intent that SDG&E should also pursue
significant percentages of procurement to replace SONGS through preferred
resources, energy storage and consistency with the Loading Order. Therefore,
SDG&E shall ensure than no less than 200 MW of procurement authorized by
this decision is from preferred resources or energy storage. This amount is
higher than the 120 MW of preferred resources SDG&E recommends in this
proceeding. We believe the record shows that SDG&E’s recommendations are
conservative. To the extent that SDG&E seeks to procure incremental preferred
resources and energy storage (beyond those already expected to be procured
elsewhere) through other procedural vehicles authorized by the Commission, it
193 SDG&E September 30, 2013 Comments, at 5-6.
R.12-03-014 ALJ/DMG/avs
- 97 -
must delineated this process in its procurement plan (discussed below). To
summarize, as shown in Chart 3:
a. At least 25 MW of capacity must be procured from energy storage
resources;
b. At least 175 MW of capacity must be procured from preferred resources
consistent with the Loading Order of the Energy Action Plan;
c. Subject to the overall cap of 800 MW, up to 600 MW of capacity, beyond
the amounts specified required to be procured pursuant to
subparagraphs (b) and (c) above, may be procured through any set of
resources appropriate to meet LCR needs in the SDG&E territory,
consistent to extent feasible with the Loading Order of the Energy
Action Plan (in addition to resources already required to be procured or
obtained by the Commission through decisions in other relevant
proceedings).
R.12-03-014 ALJ/DMG/avs
- 98 -
Chart 3 SDG&E Procurement Authorization
Thus SDG&E may procure from 25%to 100% of additional resources
authorized by this decision from preferred resources or energy storage. We
provide this wider range of possibilities for SDG&E, as compared to SCE,
because SDG&E is already approved to procure about 300 MW from gas-fired
generation (Pio Pico). Now that the Pio Pico application is approved, SDG&E’s
total procurement for LCR purposes will be from 800 to 1,100 MW; thus SDG&E
will be authorized to procure from 22%to 79% of additional resources from
preferred resources or energy storage, a range reasonably similar to the 21% to
60% range for SCE discussed above.
R.12-03-014 ALJ/DMG/avs
- 99 -
5.2. Energy Storage
CalWEA contends that requiring SCE and SDG&E to fulfill their storage
targets in the process of meeting Southern California’s local reliability needs will
lower the total cost of meeting both goals, given that the utilities are required to
fulfill the storage targets within the 2020-2024 timeframe regardless of viability
or cost-effectiveness.194 SDG&E recommends that all energy storage be procured
via the process contemplated in D.13-10-040 and LCR need reduced only to the
extent energy storage is shown to meet local need.195
D.13-10-040 in section 4.5.3 states:
“The procurement targets and the schedule for solicitations proposed here are not presently tied to need determinations within the LTPP proceeding. Instead, in the near term, we view the Storage Framework adopted herein as moving in parallel with the ongoing LTPP evaluations of need – system and local, and with the new consideration of the outage at SONGS. In the longer term, we expect that any procurement of energy storage will be increasingly tied to need determinations within the LTPP proceeding.”
We do not modify the energy storage procurement targets established in
D.13-10-040. It is too early to know if such targets are too high, too low or just
right. More information will become available after the first utility solicitations;
per D.13-10-040, Ordering Paragraph 3, applications containing a proposal for
procuring energy storage resources are due by March 1, 2014, with the
solicitation to occur no later than December 1, 2014. Nor will we modify the
50 MW energy storage requirement for SCE in D.13-02-015. That requirement
194 CalWEA Opening Brief, at 7.
195 SDG&E Opening Brief, at 22.
R.12-03-014 ALJ/DMG/avs
- 100 -
will remain a part of the 1,900 – 2,500 MW combined authorization for Track 1
and 4 of this proceeding. Per D.13-10-040, this will partially meet the energy
storage target for SCE. For SDG&E, we will establish a smaller 25 MW energy
storage procurement requirement, which will partially meet the lower D.13-10-
040 target for SDG&E. Similar to SCE, this new energy storage requirement for
SDG&E shall be separate from the preferred resources requirements.
For both SCE and SDG&E, the set energy storage procurement
requirements in this decision are minimum, not maximum, levels. Both utilities
may also procure energy storage as part of their preferred resources
requirements or all-source authorizations, subject to any other conditions in this
decision.
5.3. Large Scale Pumped Storage (Bulk Storage) Procurement
D.13-10-040 at 30,34 excluded large-scale (50 MWs or more) pumped
storage projects from the energy storage targets, reasoning that “the sheer size of
pumped storage projects would dwarf other smaller, emerging technologies; and
as such, would inhibit the fulfillment of market transformation goals.”
The
decision at 35 further found that applicable statute indicated a legislative intent
“to encourage a broad range of energy storage technologies” and, “to achieve
this,” placed “a limit on the size of pumped hydro storage systems eligible to
participate in the particular mechanisms outlined in this decision.” D.13-10-040
at 33 identified this LTPP Track 4 proceeding as the venue for providing a
procurement mechanism for large-scale pumped or bulk storage, especially since
that technology would have particular application in terms of addressing “local
reliability impacts of a potential long-term outage at the SONGS.” D.13-10-040
also states: “We strongly encourage the utilities to explore opportunities to
partner with developers to install large-scale pumped storage projects where
R.12-03-014 ALJ/DMG/avs
- 101 -
they make sense within the other general procurement efforts underway in the
context of the LTPP proceeding or elsewhere.”
According to ISO witness Sparks, if “it has the right characteristics,” there
is no basis to exclude “bulk storage” from being procured by SCE or SDG&E to
meet a local capacity requirement in the absence of SONGS.196 In addition, ISO
witness Millar testified that “pump storage can be a very effective mitigation in
meeting local needs, whether it’s characterized as a preferred resource or not.”197
SCE witness Nelson testified that pumped storage “technology is fairly well
understood” and “that there are some significant advances in controls and
variable speed pumps that could add additional value to the grid.”198 While
witness Nelson was uncertain about the “effectiveness” of “any large pumped
hydro storage” in meeting the “West LA Basin LCR,” he did believe it could be
“bid in” for Track 1 and would contribute to the “balanced approach” of using
“all resources” to avoid “the possibility of failure and being overly reliant on
anyone.”199
CEERT contends that large-scale (50 MW or more) pumped storage must
be part of any procurement or RFO authorized by this Commission in this
decision. 200 CEERT witness Caldwell testified: “[T]here are multiple pumped
storage facilities under consideration in Northern San Diego County that could
easily provide for LCR need found in Track 4, plus provide other significant grid
196 RT 1544.
197 RT 1655.
198 RT 1917.
199 RT 1916-1917.
200 CEERT Opening Brief, at 51.
R.12-03-014 ALJ/DMG/avs
- 102 -
benefits.”201 ORA agrees that the Commission should ensure that SDG&E and
SCE extend bid eligibility to include large scale pumped storage projects. 202
Eagle Crest recommends that nothing in this decision should preclude or restrict
opportunities for the utilities to procure bulk energy storage, especially large
pumped hydro facilities.203
As discussed herein, we require SCE and SDG&E to procure MW ranges of
certain types of resources. Each utility should solicit all resources as required by
this decision, and may propose for approval any set of resources which can meet
the LCR need in its portion of the SONGS service area consistent with the
authorized resource ranges herein. Within the categories that include preferred
resources, bulk energy storage and large pumped hydro facilities should not be
excluded. We have also set aside specific procurement amounts for energy
storage. Within the energy storage category, we will limit procurement to the
types of energy storage anticipated by D.13-10-040.
5.4. Contingency (Options) Contracts
In its testimony, SCE discussed a conceptual plan to potentially backstop
SCE’s procurement approach with contingent GFG contracts. The contingent
GFG contracts (also known as options contracts) would require the seller to begin
the process of developing a power plant, including the necessary
pre-development work to site, permit, and construct a specified GFG resource.204
SCE asserts this pre-development work will reduce development time, if
201 Exhibit CEERT-1 (Caldwell), at II-3.
202 ORA Reply Brief, at 4.
203 Eagle Crest Opening Brief, at 6.
204 Exhibit SCE-1, at 58; RT 1960.
R.12-03-014 ALJ/DMG/avs
- 103 -
triggered, by two years. However, the entities would not begin actual
construction of the power plant without SCE authorization. The contingent
contract would contain a buyer’s right to terminate the contract, and “SCE would
only proceed with completing commercial operation of the contingent contract
for GFG if a demonstrated need existed, and after receiving Commission
approval to do so.”205
SCE identifies several reasons for which a need to backstop SCE’s
procurement may arise: “(1) failure to successfully develop GFG procured in
SCE’s Track 1 LCR procurement process; (2) inability to develop sufficient
Preferred Resources to meet SCE’s Track 1 LCR procurement authorization;
(3) planned local area grid enhancements are not completed; and (4) planning
assumptions on the availability and effectiveness of resources do not
materialize.”206 If a need did arise, SCE contends the contingent contracts would
reduce the lead-time for developing GFG, thus improving grid reliability in the
LA Basin and ensuring preservation of the OTC regulatory compliance dates.
SCE is not requesting approval of this plan in Track 4. Instead, SCE intends
to submit any proposed contingent GFG contracts to the Commission for
approval, if SCE determines they are cost effective and beneficial, in the third
quarter of 2014.207
IEP argues that the concept of contingent development contracts could be
a practical and cost-effective way to insure against future reliability problems
while buying time to see how uncertainties about demand and supply are
205 Exhibit SCE-1, at 59; RT 1960.
206 Exhibit SCE-1, at 58.
207 RT 1962, 1966, 1982, 1983.
R.12-03-014 ALJ/DMG/avs
- 104 -
resolved.208 Vote Solar recognizes there may be some value in SCE’s request for
permission to enter into gas-fired generation contingency contracts as backup for
resources authorized in Tracks 1 and 4. Vote Solar contends SCE’s proposal to
sign PPAs with gas-fired generation developers that contain opt-out clauses
appear to be more reasonable and simpler to implement than the utilities’
contingent site preparation proposals, provided the option payment is not
exorbitant.209
ORA witness Rogers testified that SCE’s options contract proposal is an
“approach would expose ratepayers to costly termination payments in the event
the contracts prove unnecessary.”210 CEERT similarly contends that SCE’s
proposal is problematic.211 Alton Energy argues for rejection of SCE’s proposal
as an inappropriate use of ratepayer funds, and argues it would distract SCE
from their other initiatives such as the Living Pilot and Mesa Loop-In.212
WPTF does not oppose the SCE proposal, subject to certain caveats. WPTF
opposes the concept of using bilateral negotiations for securing the option
contracts proposed by SCE, arguing that bilateral negotiations do not ensure that
the least cost option will be identified and selected. Further, WPTF argues that
such contracts allows utility to pick “winners and losers” on criteria other than
least cost.213 WPTF advocates that the Commission should make it clear that in
208 IEP Opening Brief, at 34.
209 Vote Solar Comments, at 13.
210 Exhibit ORA-5 (Rogers), at 3, 11.
211 CEERT Opening Brief, at 41.
212 Alton Energy Opening Brief, at 3.
213 WPTF Opening Brief, at 4.
R.12-03-014 ALJ/DMG/avs
- 105 -
option contracts contingency proposals, SCE should allow existing generators,
including OTC unit owners, to offer their sites for redevelopment.214
We need not make a determination on the merits of SCE’s contingency
contract proposal here, as SCE is not seeking any specific approval. We do see
potential value in such an approach, because there are many unknowns
regarding future supply and demand in the LA Basin; contingency contracts may
(if appropriately priced, effectively managed and well-located) reduce/mitigate
disruptions and uncertainties in the future.
On the other hand, there are many uncertainties about what SCE may
propose, and how such contracts work. There are significant questions that must
be answered before we could approve such contracts. Such questions include:
Would these contingency contracts be in addition to site preparation by SCE in the vicinity of Johanna and Santiago substations, thus potentially leading to costly redundancy?
What metrics should be used to evaluate the cost-effectiveness of these contracts?
Should separate RFOs be held to procure contingency contracts? If not, how can it be shown that proposed contracts represent the lowest reasonable rate?
If SCE waited until the next RFO, might a contingency contract bidder improve its offer?
How would SCE measure and enforce performance under contingency contracts?
Would contingency contracts unfairly influence the next RFO? For example, if a contract is terminated after site preparation and permitting have already been completed, it may be more likely that this site will be selected in the next RFO.
214 WPTF Opening Brief, at 7.
R.12-03-014 ALJ/DMG/avs
- 106 -
In its testimony, SCE states "Second, the availability of Preferred Resources typically cannot be assured until much closer to the time of resource need. There is no assurance these Preferred Resources will ultimately be available to meet needs related to OTC closures because it is unlikely that customers will commit in 2014 that they will implement EE or DR in 2021." 215 If the preferred resources ultimately come online as expected, how will SCE avoid paying for both preferred resources and the contingency GFG contract, in light of SCE’s assumed EE and DR procurement timeline? If SCE does not know if the preferred resources will perform until much closer to the time of delivery, on what grounds would SCE ever terminate a GFG option contract?
Would contingency contracts, in practical terms, make it much more likely that there would be additional, unnecessary GFG procurement?
What potential costs (direct, indirect or stranded) will ratepayers be exposed to if these contracts are pursued?
SCE may propose contingency contracts in its upcoming procurement
application, expected in late 2014 or in a separate application. SDG&E may also
propose similar contracts in its procurement application stemming from this
decision or in a separate application. In either case, the utility must provide clear
and full answers to the questions above before we will consider approving such
contracts.
215 Exhibit SCE-1, at 63.
R.12-03-014 ALJ/DMG/avs
- 107 -
6. Conditions for Procurement
6.1. Procurement Process
SCE recommends combining new LCR all source procurement from
Track 4 with its all-source procurement RFO authorized in D.13-02-015. SCE
argues this combination will both improve the competitiveness of all source
bidding, allow for a more optimal selection of resources, and reduce
administrative costs to ratepayers of issuing two separate all source solicitations.
SCE recommends that this solicitation not be limited to any particular
resource type or project size. As Exhibit SCE-1 states: “[c]reating carve outs for
certain technologies or project sizes shrinks the market for all other potential
resources, potentially precluding the opportunity to contract with more cost-
effective, better fit resources.”216 SCE contends the use of an all source solicitation
for incremental Track 4 procurement authorization with no buckets for certain
technologies or project sizes will allow SCE to seek a cost-effective portfolio of
resources to meet SCE’s LCR need consistent with the Loading Order. SCE plans
to use the least-cost/best-fit criteria to choose the most cost-effective portfolio to
meet SCE’s LCR needs, consistent with the Loading Order.217
For procurement authorized in this proceeding, SDG&E requests that the
Commission direct it to issue an all-source RFO or to contract bilaterally. SDG&E
contends that moving forward on an expedited basis with a bilateral contract to
address a portion of LCR need would support the policy goals of the State
related to timely retirement of OTC facilities and would promote system
216 Exhibit SCE-2, at 23.
217 SCE Opening Brief, at 12.
R.12-03-014 ALJ/DMG/avs
- 108 -
reliability – the sooner new local resources are added to the portfolio, the lower
the reliability risk.218
SDG&E argues that the public interest is best served by procurement of
preferred resources through the relevant dedicated Commission proceedings.
SDG&E contends there are important issues that require stakeholders input that
are best addressed in the dedicated proceeding, such as establishing rules for
counting of such resources to meet overall procurement targets, separate from
LCR need, and developing mechanisms for recovery of costs from all benefitting
customers.219 SDG&E’s procurement strategy holds 70-120 MW open to be filled
with demand response and/or energy storage resources in the Commission
proceedings dedicated to each such resource, provided that these resources
satisfy requirements established by the ISO for operational characteristics that
address local reliability needs.220
IEP and others recommend that procurement of local capacity resources
should occur primarily through an all-source solicitation, where all resources
that can meet the specified requirements can compete on a fair basis. IEP argues
that the focus of procurement of capacity needed for local reliability should be
the resource's viability and ability to provide the products and services needed to
maintain reliability.221
ORA recommends directing each utility to submit a procurement plan
explaining how it plans to accomplish the procurement of preferred resources,
218 SDG&E September 4, 2013 Comments, at 5-6.
219 SDG&E Opening Brief, at 34.
220 SDG&E Opening Brief, at 8.
221 IEP Reply Brief, at 22.
R.12-03-014 ALJ/DMG/avs
- 109 -
including proposed milestones and evaluation dates, and detailed proposals to
back stop the procurement. The plans should explain how the totality of the
contracts or programs are cost effective and consistent with the loading order,
including a demonstration that each utility has assessed the availability,
economics and viability of the preferred resources in meeting LCR need. The
plans should demonstrate technological neutrality, so that no resource was
prevented from the solicitation process, although SCE and SDG&E may include
proposals to solicit preferred resources through different avenues.222
CEERT recommends adopting a stakeholder process to permit public
input on the development of RFOs for both supply-side (i.e., bulk storage) and
preferred resources that permits input from parties on its terms and conditions
before approved for the IOUs.223
Parties including Sierra Club, ORA and CLECA and Vote Solar share a
concern that if the Commission adopts SCE’s procurement proposals, only
gas-fired resources will win, regardless of SCE’s intent to pursue preferred
resources solutions.224 These parties recommend that the Commission, if it
authorizes any additional Track 4 LCR procurement, require the utilities to first
seek to satisfy that additional need with preferred resources. EDF contends that
“[i]n comparison to combustion resources, the siting of [energy efficiency,
demand response,] and small and large scale renewable generation is
significantly less likely to face time delays and substantial obstacles to
222 ORA Opening Brief, at 31.
223 CEERT Opening Brief, at 54.
224 Sierra Club Opening Brief, at 26-27; Exhibit ORA-2, at 1; CLECA Opening Brief, at 10-11; Vote Solar Reply Brief, at 3.
R.12-03-014 ALJ/DMG/avs
- 110 -
implementation.”225 EnerNOC indicates such delays would include “attaining
GHG emissions reductions required by Assembly Bill (AB) 32.”226
We have already determined both in D.13-02-015 and in this decision that
authorized procurement should be a combination of gas-fired generation and
preferred resources, with ranges of procurement for different resource types.
Any all-source RFO (and all other procurement methods) must be consistent
with the resource ranges authorized in this decision. As discussed herein,
compared to D.13-02-015 for SCE, we do not increase the minimum levels of
procurement of gas-fired generation and do increase the minimum levels of
procurement of preferred resources.
D.13-02-015 at 3 - 4 noted that that decision was a first step in a longer
procurement process related to the retirement of OTC plants and other factors:
“We consider today’s decision a measured first step in a longer process. If as
much or more of the preferred resources we expect do materialize, there will be
no need for further LCR procurement based on current assumptions. If
circumstances change, there may be a need for further LCR procurement in the
next long-term procurement proceeding.”
There is a need for expeditious action to procure further resources in
response to the retirement of SONGS. It will be approximately 18 months form
the date for the Track 1 decision to the time SCE files an application for approval
of Track 1-authorized procurement. We cannot wait another 18 months or more
beyond the date of this decision for consideration of Track 4-authorized
procurement. To ORA’s point, SCE has already shown how it will procure
225 EDF Opening Brief, at 7.
226 EnerNOC Opening Brief, at 8-9.
R.12-03-014 ALJ/DMG/avs
- 111 -
preferred (and other) resources in a detailed plan, which has already been
reviewed and approved by the Energy Division. As SCE has already completed
its Track 1 RFO solicitation process, the most efficient and timely method toward
approval of new resources in SCE’s territory is to use the results of the Track 1
RFO for resources authorized in this decision as well as D.13-02-015. SCE may
also propose for approval bilateral contracts for Track 4, consistent with the
authority granted in Track 1.
Ordering Paragraph 1 of the track 1 decision, D.13-02-015, states in part:
“Southern California Edison Company shall procure between 1,400 and
1,800 MW of electrical capacity in the West Los Angeles sub-area of the
Los Angeles basin local reliability area to meet long-term local capacity
requirements by 2021.” This track 4 decision concerns the SONGS service
territory, which for SCE consists of the entire LA Basin. At the same time, we
build upon the track 1 decision and recognize that the resource need identified in
that decision continues to exist. Thus, SCE should prioritize procurement in the
West Los Angeles sub-area of the LA basin. To the extent that SCE wishes to
procure resources in the LA Basin, but not in the West LA sub-area, to meet the
incremental authorizations in this decision (i.e., for resources beyond those
authorized in D.13-02-015), SCE shall amend its approved procurement plan
from Track 1 within 90 days of this decision, subject to Energy Division approval.
SCE shall file an application including procurement authorized in Tracks 1
and 4 in 2014, consistent with its Energy Division-authorized procurement plan
from Track 1 (and any approved amendment). This application shall include all
procurement contracts stemming from Tracks 1 and 4 for which SCE seeks
approval at this time, whether from its RFO or bilateral contracts. The exception
is any procurement covered by Ordering Paragraph 8 of D.13-02-015, which
R.12-03-014 ALJ/DMG/avs
- 112 -
states: “Southern California Edison Company may provide the conventional
gas-fired resources portion of the procurement plan for review ahead of its full
procurement plan. If Energy Division approves this portion of the plan Southern
California Edison Company may go forward with that procurement.” SCE may
include any proposed contingency contracts in its application.
For SDG&E, we also will require an all-source RFO as part of its Track 4
solicitation process, in addition to allowing bilateral contracts. The RFO shall
meet the same requirements as for SCE in Ordering Paragraph 4 of D.13-02-015.
We will require SDG&E to show that it has a specific plan to procure at least the
minimum level of resources authorized by this decision, consistent with this
decision’s requirements for specific resource categories. We agree with parties’
comments that all resources that can meet the specified requirements should be
able to compete on a fair basis. An RFO is an effective method to accomplish this
goal.227 While SDG&E witness Anderson contends that the potential for double-
counting and cannibalization of existing programs arises when procurement of
preferred resources occurs along two parallel paths,228 we find it better to
compare resources procured for the same purpose (meeting LCR needs) in the
same process (an RFO). SDG&E maintains the responsibility to ensure that its
LTPP procurement process is consistent with other Commission requirements.
Therefore, SDG&E’s RFO shall provide for at least the 200 MW minimum
preferred resources/energy storage components.
227 We are aware that SCE’s Track 1 RFO received a robust response from potential suppliers of various types of resources.
228 RT 1812 – 1813.
R.12-03-014 ALJ/DMG/avs
- 113 -
To this end, and consistent with the process ordered for SCE in Track 1,
SDG&E shall first submit a procurement plan to be reviewed and approved by
Energy Division. The SDG&E procurement plan shall meet the procurement
plan requirements as required for SCE in D.13-02-015, and be consistent with this
decision. The SDG&E procurement plan shall be provided to Energy Division
for review no later than 90 days after the effective date of this decision.
Consistent with an approved procurement plan, SDG&E shall file an application
for all procurement contracts stemming from Track 4 for which SDG&E seeks
approval at that time, whether from an all-source RFO or bilateral contracts. As
with SCE, SDG&E may propose in its procurement plan a separate, earlier
application for gas-fired generation due to long lead times. SDG&E should
include any proposed contingency contracts in its application.
Procurement authorized by this decision should begin as soon as possible.
Procurement needs may become critical as early as 2018, and certainly by 2020.
To the extent authorized, SCE and SDG&E must expeditiously pursue
procurement of any gas-fired generation expected to take several years to
develop. Other procurement activities may not need as much lead-time to
develop. However, the utilities should not wait until very close to when the
need is critical to acquire such resources; to the extent that additional preferred
resources or energy storage is cost-effective and well suited to meet LCR needs in
the subject geographical areas, SCE and SDG&E should work to procure these
resources in advance.
6.2. Solicitation Requirements
Ordering Paragraph 4 of D.13-02-015 required SCE to include the
following elements in a Track 1 RFO:
R.12-03-014 ALJ/DMG/avs
- 114 -
Any Requests for Offers (RFO) issued by Southern California Edison
Company pursuant to this Order shall include the following elements, in
addition to any RFO requirements not delineated herein but specified by
previous Commission procurement decisions (including Decision 07-12-052) and
the authorization and requirements of this decision:
a. The resource must meet the identified reliability constraint identified by the California Independent System Operator (ISO);
b. The resource must be demonstrably incremental to the assumptions used in the California ISO studies, to ensure that a given resource is not double counted;
c. The consideration of costs and benefits must be adjusted by their relative effectiveness factor at meeting the California ISO identified constraint;
d. A requirement that resources offer the performance characteristics needed to be eligible to count as local Resource Adequacy capacity;
e. No provisions specifically or implicitly excluding any resource from the bidding process due to resource type (except as authorized in this Order);
f. No provision limiting bids to any specific contract length;
g. Provisions designed to be consistent with the Loading Order approved by the Commission in the Energy Action Plan and to pursue all cost-effective preferred resources in meeting local capacity needs;
h. Provisions designed to minimize costs to ratepayers by procuring the most cost-effective resources consistent with a least cost/best fit analysis;
i. A reasonable method designed to procure local capacity requirement amounts at or within the levels authorized or required in this decision, not counting amounts procured through cost-of-service contracts;
R.12-03-014 ALJ/DMG/avs
- 115 -
j. An assessment of projected greenhouse gas emissions as part of the cost/benefit analysis;
k. A method to consider flexibility of resources without a requirement that only flexibility of resources be considered; and
l. Use of the most up-to-date effectiveness ratings.
As SCE is authorized to use the results of its Track 1 RFO to procure
resources for Track 4 as well, the requirements of Ordering Paragraph 4 of
D.13-02-015 continue to hold. To the extent that SCE institutes future RFOs for
these purposes, these requirements will apply. SCE should include any proposed
contingency contracts in its application. In addition, we will apply the same
requirements to SDG&E for any RFO it issues for Track 4 procurement.
7. 2013/2014 TPP Update
Some parties urge the Commission to revise any interim procurement
authorization for incremental need in the SONGS study area once the 2013/2014
TPP results are available. For example, ORA contends that revising the need
(upwards or downwards) based on more accurate information, would allow LCR
procurement based on the facts that are more likely to reflect that need that will
exist in 2022.229 A number of other parties echo this sentiment.230
As discussed herein, it is necessary to authorize procurement at this time
to replace capacity lost by the untimely retirement of SONGS. The authorization
approved today does not assume any specific transmission upgrades or new
229 ORA Opening Brief, at 8.
230 See, for example, CEERT Opening Brief, at 20: “it is CEERT’s position that inclusion of the ‘additional evidence’ of the TPP results will create a better record than at present to determine both LCR needs without SONGS and the best means (in particular, preferred resources) to reduce or meet that need without jeopardizing timeliness.”
R.12-03-014 ALJ/DMG/avs
- 116 -
projects which might be determined in the 2013/2014 TPP. At the same time, we
do not authorize procurement of all resources identified by the ISO as needed to
meet LCR needs in the SONGS service area by 2022. As discussed at length
herein, we determine that some combination of already-authorized procurement,
additional expected preferred resources, and new transmission projects will
significantly reduce the need identified by the ISO.
If, at one extreme, no new transmission resources are identified in the
2013/2014 TPP which would reduce LCR needs in the SONGS service area by
2022, the procurement authorized today may need to be supplemented. We
anticipate this would occur through some combination of: a) procurement at or
near the maximum levels authorized in this decision; b) procurement of
additional preferred resources (beyond the assumptions used by ISO in Track 4
models) as anticipated in this decision; c) additional procurement authorized in
future LTPP proceedings; and d) potential delay in retirements of OTC plants. In
other words, because we assume no new transmission projects in our analysis, a
similar outcome from the 2013/2104 TPP does not require any change or update
to this decision.
If some level of new transmission resources is identified in the 2013/2014
TPP which would reduce LCR needs in the SONGS service area by 2022 (for
example, the Mesa Loop-In project), the total amount of overall procurement
needed in the SONGS service area would be reduced. However, we have
already considered the possibility of the Mesa Loop-In going forward in
analyzing procurement authorizations. Nevertheless, it is possible that the
2103/2014 TPP results would mean that fewer of the resources identified in this
subsection ultimately would be needed. However, this does not mean there
would be a need to change or update this decision. Instead, some combination of
R.12-03-014 ALJ/DMG/avs
- 117 -
the following would occur: a) procurement at or near the minimum levels
authorized in this decision; b) less procurement or no procurement authorized in
future LTPP proceedings; and c) less of a need to delay retirements of OTC
plants.
The range of procurement authorized for both utilities in this decision is
intended to provide flexibility to meet a variety of circumstances. The 2013/2104
TPP is unlikely to result in major changes to the analysis in this decision.
Therefore, we will close Track 4 of this proceeding with this decision.
8. Cost Allocation Mechanism
The Cost Allocation Mechanism, or CAM, is designed to ensure that the
costs of new resources procured to ensure local or system reliability are shared
equally among all utility distribution customers, regardless of their generation
provider. CAM is based on the principle that reliability is a collective good and
that the customers of Electrical Service Providers (ESPs) and Community Choice
Aggregators (CCAs) will also benefit from investments in system reliability
made by regulated utilities. The current CAM achieves this goal by subtracting
the energy value of new generation out from long-term contracts for new
generation and sharing the residual capacity costs equally among all bundled
and un-bundled customers within the utility service-area.
SCE231 and SDGE232 both argue that all Track 4 procurement should receive
CAM treatment. SCE argues that the issue of CAM treatment was already
litigated in Ordering Paragraph 21 of D.13-02-015 and therefore should not be
re-litigated. SCE argues that Track 4 is intended to maintain local reliability and
231 Exhibit SCE-1, at 59-60.
232 Exhibit SDG&E-1 (Anderson), at 12.
R.12-03-014 ALJ/DMG/avs
- 118 -
therefore, according to Pub. Util. Code § 365.1(2)(B) all procurement coming out
of Track 4 is CAM-eligible.
AReM/DACC233 disputes both of these arguments. First, AReM/DACC
suggests that since SONGS replacement was not discussed in Track I any
determination of CAM applicability to Track I procurement should not
automatically apply for Track 4 procurement as well.234 AReM/DACC argues
that as a general principle, CAMs should be applied with circumspection and the
utilities need to justify CAM treatment on a case-by-case basis. For Track 4
procurement, they argue that procurement is to meet the bundled load of
SDG&E and SCE customers, as opposed to general local or system reliability
needs. Therefore, only utility bundled customers should pay SONGS
replacement costs.
In reply briefs, PG&E, SCE, SDG&E and TURN argue that Track 4
procurement is for local reliability and not to meet bundled load, and therefore
should be subjected to CAM. These parties argue that any resources the
Commission asks the utilities to make to meet local reliability criteria in the
SONGS service area will benefit both bundled and unbundled customers.
TURN235 argues that local reliability needs – including those driven by
expected resource retirements – are not solely the responsibility of bundled
customers, even when they may be driven in part by the retirement of a resource
that served bundled customer needs, such as SONGS. Further, all of the utilities’
customers will benefit equally from the resources that may be procured pursuant
233 Exhibit AReM/DACC-1, at 2-17.
234 See also Exhibit WPTF-1, at 13.
235 TURN Reply Brief, at 2-3.
R.12-03-014 ALJ/DMG/avs
- 119 -
to Track 4 authorization, so all customers should share equally in paying for such
resources. Finally, SCE and SDG&E have already met, are continuing to meet
and will continue meeting – to the extent the Commission requires and allows –
their bundled customers’ additional capacity and energy needs arising from the
retirement of SONGS. TURN also argue that the utilities are meeting bundled
customers’ needs at bundled customers’ expense, and have no other obligation to
make long-term investments in resources to meet local reliability needs other
than as directed by the Commission in a docket such as this Long-Term
Procurement Plan.
Section 365.1(c)(2)(A)-(B) holds that in instances when the Commission
determines that new generation is needed to meet local or system area reliability
needs for the benefit of all customers in the IOU’s service area, the net capacity
costs for the new capacity shall be allocated in a fair and equitable manner to all
benefiting customers, including DA, CCA and bundled load. Simply put, each
customer must pay their fair share for the benefits that flow to them from new
generation for reliability purposes for the full life of the asset.
D.13-02-015, Conclusion of Law 21 states:
“The cost allocation mechanism established in D.06-07-029 and refined in D.07-09-04, D.08-09-012 and D.11-05-005 remains reasonable for application in this proceeding without modification, and is fair and equitable as required by Section 365.1(c)(2)(A)-(B).”
Ordering Paragraph 15 of D.13-02-015 states:
“Southern California Edison Company shall allocate costs incurred as a result of procurement authorized in this decision and approved by the Commission consistent with the cost allocation mechanism approved in Decisions (D.) 06-07-029, D.07-09-044, D.08-09-012 and D.11-05-005.”
R.12-03-014 ALJ/DMG/avs
- 120 -
The basic question related to CAM in this decision is whether procurement
authorized in this decision should be treated any differently from procurement
authorized in D.13-02-015. There is no significant difference between
procurement authorized in this decision and procurement authorized in
D.13-02-015. In both cases, procurement is pursuant to local reliability
determinations starting with ISO studies for this purpose, as modified by our
analysis. We find that the procurement authorized in this decision is for the
purpose of ensuring local reliability in the SONGS service area, for the benefit of
all utility distribution customers in that area. We conclude that such
procurement meets the criteria of Section 365.1(c)(2)(A)-(B). Therefore, SCE and
SDG&E shall allocate costs incurred as a result of procurement authorized in this
decision, and approved by the Commission. In most cases we expect this
allocation to be consistent with D.13-02-015 and the CAM adopted in
D.06-07-029, D.07-09-044, D.08-09-012 and D.11-05-005, but there may be
resources where an existing alternative method of allocating resources costs may
be preferred; for example, cost may be recoverable through the Energy Program
Investment Charge. As SCE states in its Reply Comments on the Proposed
Decision at 3, it will “propose an RA allocation method in its application for
approval of the results of its LCR RFO when those results are fully understood."
We will require that, in applications for contract approval, the IOU shall
recommend a method of cost allocation appropriate for the resource being
procured.
SCE has proposed that some of its procurement for Track 4 could involve
contingency or option contracts for GFG, giving SCE the right to terminate the
contracts should sufficient renewables or transmission solutions obviate the
R.12-03-014 ALJ/DMG/avs
- 121 -
need.236 SCE argues that while such contracts are not covered by current CAM
rules, the CAM framework could be expanded to cover such option contracts.
AReM/DACC237 argues that these contracts cannot be subjected to CAM
because there is no way to calculate net capacity costs by accounting for revenues
from generation or related products. Since this calculation is required by statute
(Section 365.1(c)(2)(C)), SCE should not be allowed to use CAM for these option
contracts.
TURN238 argues that it is not possible to make a determination regarding
CAM or some similar cost-sharing mechanism for contingent generation
contracts until the utilities have filed for approval of such programs. Therefore,
there is no need to address the CAM issue for SCE’s proposed contingent
gas-fired generation contracts at this time.
Contingency or options contracts raise issues concerning cost allocation
that have not been contemplated by the Commission to date. SCE does not have
a specific proposal for contingency or options contracts before us at this time.
SCE and/or SDG&E may propose such contracts in their future procurement
applications stemming from this decision. We do not make any determination
about whether contingency or options contracts will be eligible for CAM. If and
when SSCE and/or SDG&E propose such contracts, they should propose
whether certain costs should be allocated through CAM, and, if so determined,
propose a methodology for allocation.
236 Exhibit SCE-1, at 58.
237 Exhibit AReM/DACC-1, at 5.
238 TURN Opening Brief, at 20-21.
R.12-03-014 ALJ/DMG/avs
- 122 -
9. Comments on Proposed Decision
The proposed decision of the ALJ in this matter was mailed to the parties
in accordance with Section 311 of the Public Utilities Code and comments were
allowed under Rule 14.3 of the Commission’s Rules of Practice and Procedure.
Comments were filed on March 3, 2014, and reply comments were filed on
March 10, 2014.
The following changes were made by the Administrative Law Judge based
on comments:
1. Increase SDG&E maximum procurement authorization from 700 MW to 800 MW (based on comments from SDG&E, IEP and NRG);
2. Allow SCE to submit an amended procurement plan, if SCE wishes to procure in the LA Basin, but outside of the West LA sub-area as required in D.13-02-015 (based on comments from CEERT);
3. Modify Attachment B to require SDG&E to explain it its procurement plan how it will ensure that energy efficiency and demand response resources procured to meet its LCR needs are incremental to resources that would otherwise develop or be procured in other programs (based on comments from ORA);
4. Add an additional question regarding potential contingency contracts (based on comments from ORA);
5.
Modifications to discussion of City of Redondo Beach testimony (based on comments from City of Redondo Beach);
6. Editing of Ordering Paragraph 1(e) to clarify requirements for energy storage procurement (based on comments from SCE);
R.12-03-014 ALJ/DMG/avs
- 123 -
7. Modify Ordering Paragraph 3 to allow bilateral contracts which are not cost-of-service contracts (based on comments of SDG&E);
8. Editing of Finding of Fact 45 regarding ISO modeling of demand response resources (based on comments from EnerNOC);
9. Clarification that the CAM may not be the only Commission-authorized cost allocation method which may be appropriate for certain resources (based on comments of SCE).
Other minor edits and clarifications to the Proposed Decision were made
throughout the decision.
10. Assignment of Proceeding
The assigned Commissioner is Michel Peter Florio and the assigned ALJ is
David M. Gamson. ALJ Gamson is the Presiding Officer. This proceeding is
categorized as ratesetting.
Findings of Fact
1. The Track 1 decision in this docket, D.13-02-015, authorized SCE to
procure between 1,400 and 1,800 MW of electrical capacity in the West
Los Angeles sub-area of the LA Basin local reliability area to meet long-term local
capacity requirements by 2021.
2. The San Onofre Nuclear Generation Station, Units 2 and 3 (SONGS)
permanently closed in June 2013.
3. The SONGS study area consists of all of the territory of SDG&E, and the
LA Basin portion of SCE’s territory.
4. Until 2011, SONGS had supplied 2,246 MW of greenhouse gas -free base
load power to the LA Basin and San Diego and played an important role in
system stability in the San Diego Local Area.
R.12-03-014 ALJ/DMG/avs
- 124 -
5. Both SCE and SDG&E have sufficient supplies to meet projected demands
in the SONGS service area through at least 2018, even with the unexpected early
retirement of SONGS.
6. Starting in 2015, around 4,900 MW of OTC plants in the local
transmission-constrained areas of the LA Basin local area may retire over the
next several years, as well as other OTC plants in the San Diego local areas,
because of State Water Resources Control Board regulations.
7. The ISO modeled retirement of OTC plants in the SONGS study area,
along with the retirement of SONGS, to produce an analysis of need for the area.
8. The ISO based its long-term LCR study on a 1-in-10 year annual peak load
and a Category C Contingency.
9. On May 21, 2013, Attachment A of the revised Scoping Memo for this
proceeding set forth a series of assumptions for the ISO to use in modeling long-
term capacity needs in the absence of SONGS.
10. The revised Scoping Ruling established a 1-in-10 year versus 1-in-2 year
peak weather forecast for transmission and local area planning.
11. The ISO performed its SONGS Study area LCR study consistent with the
assumptions in the revised Scoping Memo.
12. The ISO calculates that between 2,399 MW and 2,534 MW (depending on
the allocation between SCE and SDG&E) will be needed in the SONGS study
area by 2022.
13. Other parties performed power flow models. While these studies were
useful for analytical purposes, they did not conform to the revised Scoping
Memo.
14. SCE and SDG&E study results show projected residual long-term local
capacity needs ranging from 2,302 – 2,534 MW based on slightly different
R.12-03-014 ALJ/DMG/avs
- 125 -
assumptions and methodologies from those used by the ISO per the revised
Scoping Memo.
15. It is very likely or near certain that 1,800 MW authorized by the
D.13-02-015 will be procured by SCE.
16. It is certain that 300 MW authorized D.13-03-029 will be procured by
SDG&E, due to the approval given in D.14-02-016.
17. The June 28, 2013 Motion of ORA, CEJA and Sierra Club was not ruled
upon before the proceeding was submitted.
18. The revised Scoping Memo did not include any specific amount of reactive
power as an assumption for the ISO to model.
19. The record in the proceeding shows that there are sufficient resources to
provide VAR support in the SONGS study area without further action at this
time.
20. Because there is not sufficient information available from the record to
determine if additional reactive power resources not modeled by the ISO could
be available to reduce LCR needs, any analysis of whether or how much
additional reactive power support would change LCR needs in the SONGS
service area is speculative.
21. Consistent with Western Electricity Coordinating Council and North
American Reliability Corporation guidelines, the ISO has approved Special
Protection Systems (SPS), also known as a Special Protection Schemes, on several
occasions in California.
22. An SPS allows the use of load shedding as an interim measure when there
are insufficient resources to meet more stringent guidelines.
23. The ISO has the authority within WECC/NERC guidelines to implement
or continue a SPS in the SDG&E territory.
R.12-03-014 ALJ/DMG/avs
- 126 -
24. The most important contingencies identified by the ISO in the SDG&E
territory have a likelihood of an N-1-1 failure between every 21 and 928 years.
25. In the unlikely event that an N-1-1 failure would occur in the planning
period of this proceeding during summer hours, it will not lead to load shedding
except for less than 2.5% of the time.
26. There would need to be a minimum of 588 MW fewer resources if there is
a temporary SPS in place, as compared to the resources needed to support the
N-1-1 contingency identified by the ISO in the SDG&E territory.
27. The cost to ratepayers of additional resources to mitigate the N-1-1
contingency identified by the ISO in the SDG&E territory would be at least
$595 million; there is evidence that such investment may not be cost-effective.
28. The cost to affected customers of a load shedding event under an SPS
approach is estimated at under $250 million per event, and must be weighted by
the low probability of the occurrence of load shedding.
29. It is likely that the procurement of preferred resources and/or
transmission solutions will develop sufficiently over time to mitigate the need for
further resources, so that the SPS in the SDG&E territory can be lifted and
reliability at an N-1-1 contingency level can be maintained.
30. Exogenous modifications (including assumptions regarding load-
shedding) do not affect the ISO modeling directly, but inform our judgment
regarding appropriate procurement levels.
31. Changing a Category C contingency to a Category D contingency would
directly change the ISO model output.
32. Issues regarding whether an ISO-determined Category C contingency
should instead be functionally a Category D contingency under WECC reliability
standards are more within the expertise of the ISO than the Commission.
R.12-03-014 ALJ/DMG/avs
- 127 -
33. There is no credible basis upon which to find that the ISO’s analysis, that
the limiting contingency for the SONGS study area is the N-1-1 Category C3
SWPL/Sunrise overlapping outage assumed and modeled by the ISO, is flawed.
34. SCE and SDG&E propose potential transmission solutions to part of the
LCR need in the SONGS study area.
35. The Mesa Loop-In project involves rebuilding and upgrading the existing
Mesa 230 kV substation in the LA Basin to 500 KV and looping the Vincent –
Mira Loma 500 kV line and two 230 kV lines into the substation.
36. The Mesa Loop-In project would reduce the amount of gas-fired
generation that would need to be sited in the LA Basin by approximately
1,200 MW, or 734 MW if there is no load shedding or additional gas-fired
generation in the SDG&E territory.
37. The Mesa Loop-In project was submitted to the ISO as part of its 2013-2014
Transmission Planning Process.
38. There is no record to determine if the Mesa Loop-In will be approved by
the ISO in its TPP, or to determine whether, even if approved, it would be in
service before 2022.
39. The Mesa Loop-In proposal is a promising and reasonably likely
alternative to other new resources in the LA Basin, if it is approved by the ISO
and if it would be in service before 2022.
40. SDG&E’s proposed 500 kV Direct Current transmission project from
Imperial Valley to SONGS would reduce the San Diego generation requirement
by 850 MW and would reduce the generation requirement for the LA Basin by
551 MW.
41. SDG&E’s proposed 500 kV regional transmission project from
Devers Substation to a new 230 kV substation in north San Diego County would
R.12-03-014 ALJ/DMG/avs
- 128 -
reduce the LCR need for San Diego by 550 MW and reduce the LCR need for the
LA Basin by 400 MW.
42. SDG&E submitted two 500 kV transmission options with different routing
options from Imperial Valley to North County to the ISO’s 2013-2014
Transmission Planning Process.
43. There is substantial uncertainty as to how quickly SDG&E’s proposed
transmission projects could be licensed and built.
44. There is a reasonable possibility that at least one of the transmission
solutions examined by SCE and SDG&E will be operational by 2022. The least
complex of these projects is the Mesa-Loop-In project, which is therefore the
most likely to meet this timeframe.
45. Consistent with the revised Scoping Memo, the ISO determined that
demand response resources which cannot respond in 30 minutes should be
considered ‘second contingency’ resources.
46. Consistent with the revised Scoping Memo, 997 MW of ‘second
contingency’ demand response in the ISO modeling was not available to avoid
the second contingency, but would be available to respond to the second
contingency.
47. It is reasonable to expect that, in the future, some amount of what is now
considered ‘second contingency’ demand response resources can be available to
mitigate the first contingency, and therefore meet LCR needs.
48. D.13-10-040 sets energy storage targets of 580 MW for SCE and 165 MW for
SDG&E, to be procured gradually through biennial solicitations from 2014
through 2020 and to be online no later than December 31, 2024.
49. The energy storage targets adopted in D.13-10-040 cannot be assumed to
count toward meeting the LCR need on a megawatt-for-megawatt basis.
R.12-03-014 ALJ/DMG/avs
- 129 -
Potential amounts of demand response, energy efficiency or solar PV resources
also cannot be assumed to count toward meeting the LCR need on a megawatt-
for-megawatt basis.
50. It is likely that some of the energy storage targets will available and
effective to meet LCR needs in the SONGS service area before 2022.
51. The incipient nature of energy storage resources, uncertainty about
location and effectiveness, and unknowns concerning timing provide insufficient
information at this time to assess how and to what extent energy storage
resources can reduce LCR needs in the future.
52. The revised Scoping Memo erroneously used the low-level uncommitted
energy efficiency estimate instead of the mid-level uncommitted energy
efficiency level, because the latter is consistent with the fact that SDG&E’s
territory is co-existent with its part of the SONGS service territory.
53. LCR study data from SDG&E shows the LCR difference is 152 MW for the
more appropriate mid-level energy efficiency estimate.
54. Consistent with the revised Scoping Memo, the ISO correctly designates
incremental customer-side solar PV as a ‘second contingency’ resource because it
is difficult to predict the location where customer-side PV will get built.
55. It is likely that Commission programs and the marketplace will increase
the amount of solar PV in the future. However, there is no specific data or
analysis in the record to determine where solar PV will locate, or the impacts of
solar PV on LCR needs.
56. SCE’s Living Pilot is a promising concept.
57. The Living Pilot is not being proposed by SCE at this time, therefore it is
not possible now to make any determination about its viability or ability to meet
LCR needs in the LA Basin.
R.12-03-014 ALJ/DMG/avs
- 130 -
58. D.13-02-015, Finding of Fact 7, continues to be valid: “Both
under-procurement and over-procurement entail significant risks.
Under-procurement entails risks of reliability problems and the impacts of
mitigating such problems in a short timeframe. Over-procurement entails risks
of excessive costs and unnecessary environmental degradation. It is not possible
to quantify whether the risks of over- or under-procurement are greater.”
59. D.13-02-015, Finding of Fact 32 continues to be valid: “A maximum LCR
procurement level will protect ratepayers from excessive costs resulting from
potential over-procurement.”
60. PG&E does not adequately take into account the likelihood of various
supply or demand considerations which are either very likely or reasonably
likely to occur, and which will lower the overall LCR need from the levels
modeled by the ISO.
61. Redondo Beach’s study does not use many of the same analytical methods
as the ISO.
62. The highest reasonable LCR need level must take into account those
resources which are very likely to be procured in the time frame between now
and 2022.
63. Taking very likely or certain modifications into account, the highest
prudent level of procurement authorization for the SONGS study area would be
1,802 MW (rounded to 1,800 MW).
64. At least some resources beyond those counted to determine the 1,800 MW
maximum procurement level are reasonably likely to be procured in the SONGS
study area by 2022.
65. The total of all reasonably possible resources or assumptions identified by
parties that were not studied by the ISO equals approximately 4,600 MW.
R.12-03-014 ALJ/DMG/avs
- 131 -
66. It is reasonable to assume that at least between 10% and 20% of the
approximately 4600 MW of resources not studied by the ISO will be available.
67. Using a methodology of subtracting out any one of several possible
resources or assumptions not included in the ISO modeling produces a range of
maximum procurement levels which takes into account between 588 and
997 MW, or between 13% and 22% of the 4,600 MW in total not studied by the
ISO.
68. A maximum prudent procurement analysis which incorporate one of the
likely resources or assumptions to meet or reduce LCR needs shows the upper
bound of a reasonable procurement range under different assumptions ranges
from 1,800 MW down to 1,393 MW.
69. While it is reasonable to assume that some resources not accounted for in
the calculation of maximum need will be available and will mitigate LCR needs,
it is not reasonable to assume this will be true for most of these resources.
70. While it is mathematically possible to construct an analysis using a series
of optimistic assumptions about resource availability that could lead to a finding
of zero or negative need, we find that a conclusion of zero need is not reasonable.
71. A proxy for calculating a minimum LCR need level is to calculate the LCR
impact if any two likely potential scenarios (load-shedding, Mesa Loop-In,
additional energy efficiency impacts, ‘second contingency’ demand response,
energy storage, ‘second contingency’ solar PV) should occur.
72. Using a methodology of subtracting out any two of several possible
resources or assumptions not included in the ISO modeling produces a range of
minimum procurement levels which takes into account between 1,322 and
1,797 MW, or between 29% and 39% of 4,600 MW.
R.12-03-014 ALJ/DMG/avs
- 132 -
73. In each case of 100% availability of any two likely scenarios not included in
the ISO’s modeling, a minimum procurement level ranges from 593 to 1,067 MW
(not taking into account uncertainties of effectiveness of various resources in
meeting or reducing LCR needs).
74. Parties’ recommendations (other than those recommending zero
procurement or over-procurement) have in common certain subtractions from a
total LCR need for procurement already authorized and calculations of expected
resources. These parties’ recommendations range from approximately 800 MW
to 1,500 MW for the SONGS service area.
75. An overall authorized procurement level for the SONGS service area at
this time of 1,000 -1,500 MW is consistent with the recommendations of many
parties and is near the center of the overall zone of reasonableness.
76. Authorized procurement levels of 1,000 to 1,500 MW will not provide the
full amount needed to meet the LCR needs in the SONGS service territory
through 2022; a significant amount of future resources to meet LCR needs in the
SONGS service territory will come from procurement authorized in other
Commission proceedings, the marketplace and other regulatory forums.
77. Between 67% and 80% of procurement needed to address LCR needs in the
SONGS service area by 2022 must be in the LA Basin, which is in SCE territory.
The remainder would be in the SDG&E service territory.
78. It is not possible at this time to discern how resources ultimately will be
distributed between SCE and SDG&E territories.
79. Between D.13-02-015 and D.13-03-029/D.14-02-016, over 85% of authorized
resources are already slated for SCE territory.
R.12-03-014 ALJ/DMG/avs
- 133 -
80. Authorizing a similar procurement range for SCE and SDG&E, with a 100
MW higher maximum for SDG&E, should be consistent with the requirement
that 67 -80% total procurement needs to be in the SCE territory.
81. Authorizing SCE to procure between 500 and 700 MW in its portion of the
SONGS service area is within the range of prudent procurement. Authorizing
SDG&E to procure between 500 and 800 MW in its portion of the SONGS service
area is within the range of prudent procurement.
82. D.13-02-015, Finding of Fact 30 continues to be valid: “It is necessary that a
significant amount of this procurement level be met through conventional
gas-fired resources in order to ensure LCR needs will be met.”
83. Pursuing procurement of preferred resources consistent with the Loading
Order must be balanced by ensuring that grid operations are not potentially
compromised by excessive reliance on intermittent resources and resources with
uncertain ability to meet LCR needs.
84. It is not necessary to require any specific incremental procurement for SCE
from gas-fired resources, beyond that specified in D.13-02-015. However,
expanding the range of potential gas-fired procurement from 1,000 – 1,200 MW
(per D.13-02-015) to 1,000 – 1,500 MW provides greater flexibility to SCE to meet
reliability needs.
85. SCE’s procurement proposal would expand the range of potential
procurement of preferred resources and energy storage, but would allow SCE to
procure up to 89% of authorized Track 1 and Track 4 resources from gas-fired
generation.
86. Requiring SCE to procure at least 400 MW additional procurement from
preferred resources or energy storage, beyond the amount required by
R.12-03-014 ALJ/DMG/avs
- 134 -
D.13-02-015, increases the percentage of procurement from these resources to
21% to 60%, which is above the 14% to 44% range authorized in D.13-02-015.
87. Requiring SDG&E to procure from at least 200 MW of additional resources
authorized by this decision from preferred resources and/or energy storage
would result in 22%to 78% of additional resources from preferred resources
and/or energy storage, after consideration of procurement authorized by
D.13-03-029 and approved by the Commission in D.14-02-016.
88. Because the process for utility solicitations of energy storage per
D.13-10-040 has not yet started, it is too early to know if such targets are too high,
too low or just right.
89. It will be approximately 18 months form the date for the Track 1 decision
to the time SCE files an application for approval of Track 1-authorized
procurement. It would likely be another 18 months or more beyond the date of
this decision for consideration of Track 4-authorized procurement, unless SCE is
allowed to combine Track 4 procurement with its Track 1 procurement process.
90. SDG&E can potentially procure the required amount of preferred and
other resources needed to meet the LCR need in its portion of the SONGS service
area through an all-source RFO and bilateral contracts.
91. Procurement needs may become critical as early as 2018, and certainly by
2020.
92. The procurement authorized in this decision is for the purpose of ensuring
local reliability in the SONGS service area, for the benefit of all utility
distribution customers in that area.
93. The resource need identified in D.13-02-015 continues to exist in the West
Los Angeles sub-area of the LA Basin. Resources in other portions of the LA
Basin may also meet incremental LCR needs identified in this decision.
R.12-03-014 ALJ/DMG/avs
- 135 -
Conclusions of Law
1. While a primary responsibility of the Commission is to ensure safety and
reliability in the electrical system under § 380(c), § 330(g), § 330(h), § 362(a), and
§ 334, that responsibility must be balanced with other statutory and policy
considerations. Specifically, the Commission has a statutory duty to ensure that
customers receive reasonable services at just and reasonable rates per § 451 and
§ 454, and to protect the environment under Pub. Util. Code sections including
§ 399.11 (Renewables Portfolio Standard) and § 454.5(b)(9)(C) (Loading Order).
2. The ISO has statutory responsibility for the efficient use and reliable
operation of the transmission grid under § 345 and shall “ensure the reliability of
electric service and the health and safety of the public” under § 345.5(b).
3. The Loading Order, first set forth in the Commission’s 2003 Energy Action
Plan, and presented in the Energy Action Plan II adopted by this Commission
and the CEC in October 2005, established that the state, in meeting its energy
needs, would invest first in energy efficiency and demand-side resources,
followed by renewable resources, and only then in clean conventional electricity
supply.
4. It is reasonable for the Commission to use LCR forecasts modeled by the
ISO using assumptions pursuant to the revised Scoping Memo as the starting
point for analyzing long-term LCR requirements in the SONGS study area.
5. The ISO study adjustment of forecasted LCR need for 1,800 MW from
D.13-02-015 for the SONGS study area is reasonable and should be included in
determining how much local capacity to procure for the SONGS study area.
6. The ISO study adjustment of forecasted LCR need for 300 MW from
D.13-03-029 for the SONGS study area is reasonable and should be included in
determining how much local capacity to procure for the SONGS study area.
R.12-03-014 ALJ/DMG/avs
- 136 -
7. The June 28, 2013 Motion of ORA, CEJA and Sierra Club should be denied
as moot.
8. The ISO study of LCR needs for the SONGS service area should not be
adjusted to account for speculative amounts of additional reactive power
support.
9. Load shedding through an SPS instituted or continued by the ISO should
only be used judiciously as mitigation for contingencies.
10. It is not reasonable to authorize procurement of additional resources at
this time to mitigate load-shedding for the N-1-1 contingency identified by the
ISO in the SDG&E territory.
11. It is prudent to wait to see what resources develop in the SONGS service
area to determine if an SPS or other load-shedding protocol can serve as a bridge
until such resources are in place.
12. It is reasonable to subtract 588 MW from the ISO’s forecasted LCR need to
account for resources that will not be procured at this time to fully avoid the
possibility of load-shedding in San Diego as a result of the identified N-1-1
contingency.
13. In decisions including D.13-06-024, D.13-02-015, and D.13-03-029, the
Commission has deferred to the ISO regarding power flow modeling.
14. It is reasonable to use the ISO power flow models as the basis for this
decision, with certain exogenous modifications.
15. There is not enough information available at this time to make a specific
finding that SCE or SDG&E’s proposed transmission projects will be able to
reduce the LCR need in the SONGS service territory by 2022.
R.12-03-014 ALJ/DMG/avs
- 137 -
16. Due to significant uncertainties, the ISO’s forecast should not be adjusted
at this time to assume LCR benefits from the SCE Mesa Loop-In project or
SDG&E’s proposed transmission projects.
17. Potential transmission solutions provide more confidence that it is not
necessary at this time to authorize the utilities to procure all of the resources
indicated to be necessary in the ISO’s study.
18. The ISO’s forecast should not be adjusted to assume ‘second contingency’
demand response resources will be available to meet LCR needs.
19. The likelihood that some demand response resources, currently
considered ’second contingency’ resources, will be available to meet LCR needs
in the future provides more confidence that it is not necessary at this time to
authorize the utilities to procure all of the resources indicated to be necessary in
the ISO’s study.
20. While the LCR effect of potential energy storage resources cannot be
quantified at this time, the targets and requirements of D.13-10-040 lead to a
conclusion that energy storage resources will reduce LCR needs in the SONGS
service area to some extent in the future.
21. The potential of energy storage to meet LCR needs provides more
confidence that it is not necessary at this time to authorize the utilities to procure
all of the resources indicated to be necessary in the ISO’s study.
22. The revised Scoping Memo should have used the mid-level uncommitted
energy efficiency estimate for SDG&E instead of the low-level estimate.
23. It is reasonable to adjust the ISO study results by 152 MW consistent with
the mid-level uncommitted energy efficiency level for SDG&E.
24. It is too speculative to make any changes to the ISO study results to
account for solar PV.
R.12-03-014 ALJ/DMG/avs
- 138 -
25. PG&E’s recommended procurement levels carry a significant risk of
over-procurement.
26. Any procurement level above 1800 MW entails too high of a possibility of
over procurement.
27. It would be prudent to authorize procurement of less than 1,800 MW
because other resources are reasonably likely to be procured, even though in
some cases their LCR impacts cannot be precisely measured. To do otherwise
would most likely lead to over-procurement.
28. For the purpose of calculating a maximum procurement level, it is
reasonable to assume that at least 13% - 22% of resources or assumptions not
studied by the ISO will ultimately be available to meet or reduce LCR needs in
the SONGS service area by 2022.
29. To account for uncertainties about effectiveness of LCR reductions for
certain resources, a reasonable maximum procurement level should be
somewhere between 1,383 and 1,800 MW.
30. A finding of zero LCR need for the SONGS service area for 2022 would
not be prudent because it would most likely lead to under-procurement.
31. Analyzing 100% availability of any two sets of resources or assumptions
not included in the ISO models is a reasonable proxy for the largest amount of
available LCR reductions from the ISO analysis.
32. For the purpose of calculating a minimum procurement level, it is
reasonable to assume that at least 29% to 39% of resources or assumptions not
studied by the ISO will ultimately be available to meet or reduce LCR needs in
the SONGS service area by 2022.
33. To be certain that authorized procurement levels will not result in
under-procurement, the minimum authorized procurement level should in no
R.12-03-014 ALJ/DMG/avs
- 139 -
case be no less than 593 MW, but could be reasonably set anywhere between 593
and 1,067 MW.
34. Authorizing a procurement range takes into account a) uncertainties
about supply and demand conditions; b) the ability to process new information
during the procurement process; c) the need to provide the utilities with
flexibility to procure resources which may only be available in large increments;
d) increases in requirements to procure preferred resources (as discussed below);
and e) the need to provide utilities and the Commission with the ability to
protect ratepayers by not forcing certain less economic procurement decisions.
35. An overall authorized procurement level for the SONGS service area at
this time of 1,000 -1,500 MW provides reasonable ratepayer protection against
over procurement and simultaneously provides reasonable protection from
reliability impacts from under procurement.
36. It is reasonable to authorize SCE to procure between 500 and 700 MW in
its portions of the SONGS service area. It is reasonable to authorize SDG&E to
procure between 500 and 800 MW in its portions of the SONGS service area.
37. It is prudent to promote preferred resources to the greatest extent feasible,
subject to ensuring a continued high level of reliability.
38. A prudent approach to reliability entails a gradual increase in the level of
preferred resources and energy storage into the resource mix.
39. Consistent with D.13-02-015, it is reasonable to provide a level of
flexibility to SCE and to ensure procurement consistent with ISO reliability
standards by expanding the range of procurement specified in D.13-02-015 for
gas-fired resources, preferred resources and energy storage.
40. A similar range of procurement flexibility should be provided to SDG&E
as to SCE.
R.12-03-014 ALJ/DMG/avs
- 140 -
41. SCE’s proposal to add its additional Track 4 procurement requirement to
its Track 1 authorization from D.13-02-015, without any specification of resource
type, is not consistent with Commission policies to adhere to the Loading Order.
42. Requiring SCE to procure between 400 and 1,500 MW (or 21% to 60%)
from preferred resources or energy storage in total between D.13-02-015 and this
decision is more consistent with the Loading Order than SCE’s proposal.
43. SDG&E should be authorized some flexibility to procure gas-fired,
preferred and energy storage resources to meet reliability needs.
44. Requiring SDG&E to procure at least 200 MW from preferred resources or
energy storage is consistent with the authority granted to SCE herein and
consistent with the Loading Order.
45. There is insufficient information to modify the energy storage
procurement targets established in D.13-10-040.
46. It is reasonable to allow SCE to use the same procurement process for
both Track 1 and Track 4-authorized procurement, consistent with SCE’s
approved Track 1 procurement plan.
47. SDG&E should be required to show that it has a specific plan to procure
the resources authorized by this decision, consistent with the procurement
categories and other requirements of this decision.
48. Procurement authorized by this decision should begin as soon as possible.
49. SCE should prioritize procurement in the West Los Angeles sub-area of
the LA Basin.
50. The procurement authorized in this decision meets the criteria of
Section 365.1(c)(2)(A)-(B) for the purposes of cost allocation.
51. The cost allocation mechanism established in D.06-07-029 and refined in
D.07-09-004, D.08-09-012 and D.11-05-005 (and as applied in D.13-02-015)
R.12-03-014 ALJ/DMG/avs
- 141 -
remains reasonable for application in this proceeding without modification, and
is fair and equitable as required by Section 365.1(c)(2)(A)-(B). Other Commission-
authorized cost allocation methods may instead be appropriate for certain
resources.
52. The November 14, 2013 e-mail Ruling of ALJ Gamson denying a
November 4, 2013 Motion for Official Notice of Protect Our Communities should
be affirmed because the requested materials do not meet the criteria for Official
Notice or Judicial Notice.
53. The SCE Motion to Strike the Opening Brief of the City of Redondo Beach
should be denied because the brief addresses record issues related to local
reliability.
54. The SCE and SDG&E Joint Motions to Strike the Opening Brief and Reply
Brief of Protect Our Communities should be granted because the brief is
substantially based on non-record evidence.
55. The SCE, SDG&E and PG&E Motions to Strike the Opening Brief of Marin
Energy Authority should be granted because the brief is substantially concerned
with matters outside of the scope of the this track of the proceeding.
56. The Southern California Edison Company Motion to Partially Strike the
Opening Brief of Nevada Hydro Company is granted because the portions of the
brief to be stricken are outside of the scope of this track of the proceeding.
O R D E R
IT IS ORDERED that:
1. In combination with procurement authorizations totaling 1,400 to
1,800 Megawatts (MW) in Ordering Paragraph 1 of Decision 13-02-015, Southern
California Edison Company is authorized to procure between 1,900 and
R.12-03-014 ALJ/DMG/avs
- 142 -
2,500 MW of electrical capacity in the Los Angeles Basin local reliability area to
meet long-term local capacity requirements by the end of 2021. Procurement
must abide by the following guidelines and table:
a. At least 1,000 MW, but no more than 1,500 MW, of local capacity must be from conventional gas-fired resources, including combined heat and power resources;
b. At least 50 MW of local capacity must be procured from energy storage resources (as defined in Decision 13-10-040);
c. At least 550 MW of local capacity must be procured from preferred resources consistent with the Loading Order of the Energy Action Plan (beyond the requirement of subsection b of this Ordering Paragraph). Bulk energy storage and large pumped hydro facilities shall not be excluded.
d. At least 300 MW, but no more than 500 MW, of local capacity, beyond the minimum amounts specified in subparagraphs (a), (b) and (c), must be procured and can be from any resource able to meet local capacity requirements.
e. Subject to the overall cap of 2500 MW, any additional local capacity, beyond the amounts specified in subparagraphs (a), (b), (c) and (d), may only be procured through preferred resources (including bulk energy storage and large pumped hydro facilities) consistent with the Loading Order of the Energy Action Plan and/or energy storage resources. Such preferred resources shall be in addition to preferred resources already required by the Commission to be procured or obtained through decisions in other relevant proceedings,.
R.12-03-014 ALJ/DMG/avs
- 143 -
Resource Type
Track 1 LCR
Resources
(D.13-02-015)
Additional Track 4
Authorization
Total
Authorization
Preferred Resources
Minimum
Requirement
150 MW 400 MW 550 MW
Energy Storage
Minimum
Requirement
50 MW 50 MW
Gas-fired Generation
(including CHP)
Minimum
Requirement
1,000 MW 1,000 MW
Optional Additional:
Only From Preferred
Resources /Energy
Storage
Up to 400MW Up to 400 MW
Additional from Any
Resource
200 MW 100 to 300 MW 300 to 500 MW
Total Procurement
Authorization
1,400 to 1800
MW 500 to 700 MW 1,900 to 2,500 MW
2. San Diego Gas & Electric Company is authorized to procure between
500 Megawatts (MW) and 800 MW of electrical capacity in its territory to meet
long-term local capacity requirements by the end of 2021. Procurement must
abide by the following guidelines:
a. At least 25 MW of local capacity must be procured from energy storage resources (as defined in Decision 13-10-040);
b. At least 175 MW of local capacity must be procured from preferred resources consistent with the Loading Order of the Energy Action Plan (beyond the requirement of subparagraph (a) of this Ordering Paragraph). Bulk energy
R.12-03-014 ALJ/DMG/avs
- 144 -
storage and large pumped hydro facilities shall not be excluded from this category.
3. Southern California Edison Company and San Diego Gas & Electric
Company are authorized to procure bilateral contracts to meet authorized local
capacity requirements as specified in this Order, including bilateral contracts
consistent with the provisions of Public Utilities Code Section 454.6.
4. Southern California Edison Company and San Diego Gas & Electric
Company shall work with the California Independent System Operator to
determine a priority-ordered listing of the most electrically beneficial locations
for preferred resources deployment.
5. Southern California Edison Company shall prioritize any procurement
authorized by this decision in the West Los Angeles sub-area of the Los Angeles
Basin local reliability area to the extent possible, and shall document efforts to
comply with this Ordering Paragraph in its Application(s) required by Ordering
Paragraph 8.
6. San Diego Gas & Electric Company (SDG&E) shall issue an all-source
Request for Offers (RFO) for some or all capacity authorized by this decision in
Ordering Paragraph 2. The RFO shall include the elements specified by Ordering
Paragraph 4 of Decision (D.) 13-02-015, in addition to any RFO requirements not
delineated herein but specified by previous Commission procurement decisions
(including D. 07-12-052) and the authorization and requirements of this decision.
7. No later than 90 days after the effective date of this decision, San Diego
Gas & Electric Company (SDG&E) shall submit a procurement plan to be
reviewed and approved in writing by the Director of the Energy Division.
SDG&E may propose in its procurement plan a separate, earlier application for
gas-fired generation. The procurement plan shall include a proposed Request for
R.12-03-014 ALJ/DMG/avs
- 145 -
Offers as required by Ordering Paragraph 6. SDG&E shall not commence any
procurement activities until the Director of the Energy Division approves its
procurement plan, which shall be reviewed consistent with this decision. The
SDG&E procurement plan shall be subject to the same procurement plan
requirements of Ordering Paragraphs 6, 7 and 8 in Decision 13-02-015 as were
required of Southern California Edison Company. In addition, SDG&E shall
provide to Energy Division all of the information listed in Attachment B to this
decision. If SCE issues one or more additional Requests for Offers to procure
capacity pursuant to this decision, it shall also provide to Energy Division all of
the information listed in Attachment B to this decision.
8. Southern California Edison Company (SCE) and San Diego Gas & Electric
Company (SDG&E) shall each file one Application for approval of any and all
contracts entered into as a result of the procurement process authorized by this
decision. The requirements of Ordering Paragraph 11 of Decision 13-02-015 shall
apply to both utilities. Neither SCE nor SDG&E shall receive recovery in rates for
the costs related to any such contract before Commission review and approval of
these Applications. In addition to currently applicable rules, the Applications
shall specify how the totality of the contracts meet the following criteria:
a. Cost-effectiveness;
b. Consistency with the Loading Order, including a demonstration that it has identified each preferred resource and assessed the availability, economics, viability and effectiveness of that supply in meeting the LCR need;
c. Compliance with Ordering Paragraphs 1 or 2 (as applicable);
d. For applicable bilateral contracts, compliance with Public Utilities Code Section 454.6; and
R.12-03-014 ALJ/DMG/avs
- 146 -
e. A demonstration of technological neutrality, so that no resource was arbitrarily or unfairly prevented from bidding in SCE’s or SDG&E’s solicitation process. To the extent that the availability, viability and effectiveness of resources higher in the Loading Order are comparable to fossil-fueled resources, SCE and SDG&E shall show that it has contracted with these preferred resources first.
9. In its Application to implement this decision pursuant to Ordering
Paragraph 8, Southern California Edison Company shall present contracts for at
least 50 Megawatts (MW) of energy storage resources (pursuant to Ordering
Paragraph 1) to the Commission for approval, or have the burden to show that it
should procure less than 50 MW because the bids it received were unreasonable.
The same requirements shall apply for San Diego Gas & Electric Company,
except the requirement for energy storage resources shall be 25 MW.
10. Southern California Edison Company and San Diego Gas & Electric
Company shall treat the retrofitting of a power plant cooling system, which is
undertaken to comply with State Water Resources Control Board Statewide
Policy on the Use of Coastal and Estuarine Waters for Power Plant Cooling and
has a compliance deadline before December 31, 2022, as a new resource in
considering resources to meet the procurement authorized in Ordering
Paragraph 1 and 2.
11. Southern California Edison Company (SCE) and San Diego Gas & Electric
Company (SDG&E) shall provide documentation in their respective Applications
required by Ordering Paragraph 8 of efforts to consult with the California
Independent System Operator to develop performance characteristics for local
reliability, and how SCE and SDG&E meet any such performance characteristics.
12. Southern California Edison Company (SCE) may modify its procurement
plan approved by Energy Division per Decision 13-02-015 solely so that
R.12-03-014 ALJ/DMG/avs
- 147 -
resources in portions of the Los Angeles Basin beyond the West Los Angeles sub-
area may also be procured to meet incremental local capacity needs identified in
this decision. Any such modification shall be submitted by SCE to Energy
Division within 90 days of the effective date of this decision and shall be subject
to the written approval of the Director of the Energy Division.
13. In applications for contract approval, Southern California Edison
Company and San Diego Gas & Electric Company shall recommend a method of
cost allocation appropriate for the resources being procured as authorized in this
decision, either consistent with the cost allocation mechanism approved in
Decision (D.) 06-07-029, D.07-09-044, D.08-09-012, D.11-05-005 and D.13-02-015 or
through another Commission-authorized method.
14. The November 4, 2013 Motion of the Protect Our Communities
Foundation for Official Notice of Exhibits, identified as Exhibits POC-3, POC-4
and POC-5, is denied.
15. The Southern California Edison Company Motion to Strike the Opening
Brief of the City of Redondo Beach is denied.
16. The Southern California Edison Company and San Diego Gas and Electric
Company Joint Motions to Strike the Opening Brief and Reply Brief of Protect
Our Communities are granted.
17. The Southern California Edison Company, San Diego Gas & Electric
Company and Pacific Gas and Electric Company Motions to Strike the Opening
Brief of Marin Energy Authority are granted.
18. The Southern California Edison Company Motion to Partially Strike the
Opening Brief of Nevada Hydro Company is granted.
R.12-03-014 ALJ/DMG/avs
- 148 -
19. Rulemaking 12-03-014 is closed.
This order is effective today.
Dated March 13, 2014, at San Francisco, California.
MICHAEL R. PEEVEY President
MICHEL PETER FLORIO CATHERINE J.K. SANDOVAL CARLA J. PETERMAN MICHAEL PICKER
Commissioners
R.12-03-014 ALJ/DMG/avs
- 1 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
1. a)
CAISO 80% 1,922 MW 612 From the results of CAISO’s LCR study assuming 80% of the needed identified in the SONGS area is allocated to the LA Basin and after deducting Track 1 authorization
From the results of CAISO’s LCR study assuming 80% of the needed identified in the SONGS area is allocated to the LA Basin and after deducting Track 1 authorization
1. b) CAISO 2/3rds 1,222 MW 1,177 MW From the results of CAISO’s LCR study assuming 2/3rds of the identified need in the SONGS Area is assumed to be in the LA Basin, and after deducting Track 1 authorization
From the results of CAISO’s LCR study assuming 2/3rds of the identified need in the SONGS Area is assumed to be in the LA Basin, and after deducting Track 1 authorization
2. SCE 500 NA Incremental to preferred resources and transmission Needed to meet the higher reliability standards used by CAISO particularly relating to voltage support and to mitigate uncertainty in assumptions including load growth
NA
R.12-03-014 ALJ/DMG/avs
- 2 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
3. SDG&E NA 1,320 – 1,470 MW without transmission improvement, could be reduce to 370 – 820 MW with major new transmission (Jontry at 10-11)239
NA From results of SDG&E power flow study cases which included 408 MW of load reduction or new supply by 2022 from preferred resources that currently do not exist.
239 Assumes approval of 300 MW Pio Pico Application currently before the Commission in A.13-03-019.
R.12-03-014 ALJ/DMG/avs
- 3 -
4. AES Southland240 (AES)
1000 MW (at 11)
MW Number Not Provided
Recommends that SCE be authorized to procure an additional 1,000 MW of generation in addition to what was approved at the conclusion of the Track 1 process. (at 11) AES strongly urges its recommendation for the following reasons: (1) procuring generation from outside the LA Basin area to replace SONGs may not be the most reliable nor cost-effective solution, (2) transmission solutions to reduce the need for procurement of generation from the most effective LA Basin generation locations may not result in the most robust or reliable system configuration. (3) Importing large amounts of generation, particularly when system demand undergoes sudden changes, will expose the system to voltage collapse conditions. (4) In addition, permitting and construction timelines for repowering existing OTC sites are likely to be considerably shorter than the timeline for developing greenfield transmission such as the Mesa Loop-In project and/or new generation. (at 10.)
NA
R.12-03-014 ALJ/DMG/avs
- 4 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
5. AREM/DACC MW Number Not Provided
MW Number Not Provided
Takes no position on need to replace energy and capacity from loss of SONGS. (at 2)
Takes no position on need to replace energy and capacity from loss of SONGS (at 2)
6. Center for Energy Efficiencies and Renewable Technologies (CEERT)
0 MW (at II-2)
0 MW (at II-2)
Recommends that the Commission make a final, not interim, Track 4 need determination based on consideration of the CAISO’s 2013-2014 TPP, projected success of the 33% RPS program, and results of SCE’s Track 1 preferred resource procurement and “living pilot” in order to avoid a piecemeal or premature overreliance on fossil procurement. (at II-2 – II-6). CEERT recommends a schedule to achieve that end that will permit a timely Proposed Decision in Track 4 by June 2014 and achieve the “early 2015” goal for any needed procurement by acceleration of the process after the issuance of that decision. (p. II-6, citing CEERT 9-10 Comments on Track 4 Schedule, at 5-6; see also, CEERT 10-14 Reply Comments on ALJ Questions, at 1-7).
240 Witness Hala N. Ballouz’s Testimony
R.12-03-014 ALJ/DMG/avs
- 5 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
7. California Environmental Justice Alliance (CEJA )
0 MW (at 2)
0 MW (at 2)
CAISO’s modeling assumptions were too conservative:
Updated 2013 CEC demand forecast for LA Basin and San Diego for 2022 is 1,320-3,200 MW lower than the 2012 CEC forecast CAISO used.
Transmission fixes, especially for reactive support, were found to reduce need by at least 1,500 MW and CAISO transmission planning results should be considered.
Preferred resources include 50 MW storage, 997 MW of DR, and 496 MW of DG.
New CPUC storage proceeding targets should be considered in Track 4. (at 2) All resources authorized in Track 1should be assumed to be available in considering local capacity requirements for SONGS. California Energy Demand 2014-2024 Revised Forecast, and in particular the CEC’s draft Estimates Of Additional Achievable Energy Savings should be considered. Contingency planning should not favor new GFG over renewable resources or short-term solutions.
R.12-03-014 ALJ/DMG/avs
- 6 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
8. California Energy Storage Alliance (CESA)
MW Number Not Provided
MW Number Not Provided
CESA asserts that Energy storage is an important technology class for meeting LCR needs in general, including those in SCE's service territory. If the Commission finds need, it should allocate procurement authority to SCE that includes the procurement of Energy Storage. (at 2) CESA asserts that energy storage is an extremely diverse and modular resource class that addresses many of SCE's stated needs, including facilitating transmission upgrade deferral, and does so effectively (especially given SCE's definition of effectiveness for Preferred Resources). Storage resources are controllable and dispatchable (sometimes providing services almost instantaneously) and can provide services "across all or most of the times when needed," needed. Energy storage also has multiple resource subsets with diverse durations. (at 2)
R.12-03-014 ALJ/DMG/avs
- 7 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
9. City of Redondo Beach
1,140 MW (1,140 = 2,940 MW SCE total need -1800 MW, authorized for SCE in Track 1)
757 MW (757= 1,100 MW SDG&E total need – 343 MW authorized for SDG&E currently authorized)
Iterative power flow studies show that 940 MW of conventional gas-fired generation added at the Huntington Beach generating station PLUS 2,000 MW of preferred resources added throughout the Western LA Basin can meet the Western LA Basin sub-area LCR.
CAISO’s 2012-2013 transmission plan for the no-SONGS case (City of Redondo Beach’s original testimony241) and the CAISO’s Track 4 base case (comments submitted by the City of Redondo Beach).
10. Clean Coalition (CCC)
0 MW (at 8)
0 MW (at 8)
No new conventional generation and transmission investments until full value of renewable resources assessed through public procurement and planning process. (at 8)
241. The (About 900 MW) mentioned in the City’s original testimony for the generation assumed in the San Diego area by year 2022 for the no-SONGS study in the CAISO’s 2012-2013 transmission plan is a typographical error. The correct number is 1,100 MW.
R.12-03-014 ALJ/DMG/avs
- 8 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
11. Environmental Defense Fund (EDF)
EDF presented data indicating that no additional combustion resources are needed with the use of preferred resources, such as EE and demand response.
EDF presented data indicating that no additional combustion resources are needed with the use of preferred resources, such as EE and demand response
EDF commended SCE’s “Preferred Resources Scenario” approach, innovative pilot, and clear identification of the uncertain need for additional capacity. Recommends that the Commission refrain from rendering a decision until a comprehensive a set of analyses becomes available. (at 2-3)
EDF points to the ability of demand response, including time-variant rates, as well as energy efficiency, distributed generation and other clean resources, to address the range of capacity needs currently identified by different parties.
R.12-03-014 ALJ/DMG/avs
- 9 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
12. EnerNOC Testimony
MW Number Not Provided
MW Number Not Provided
It is reasonable to authorize additional capacity procurement for SCE, for as much as 500 MW, because SCE has adequate capacity, according to its studies, between the Track I authorization and the planned Mesa Loop-In transmission project unless the likelihood of realizing the transmission project is low. (at II-2-3; II-7-9). Before authorizing SCE to procure additional resources beyond its Track I authorization, the Commission must resolve the calculation difference between SCE’s and CAISO’s analysis. (at II-2, II-7-6-8) The Commission should not authorize additional capacity procurement until the CAISO has completed its 2013-14 Transmission Planning Process. (at II-3, II-9-11) Further, the Commission should reject the CAISO’s and utilities’ objections to updating assumptions and any efforts to impose inappropriate conditions on demand response reducing or meeting local need. Any Track 4 need determination must be consider all updated assumptions (i.e., CAISO’s TPP results, Track 1 solicitations/pilots results, and further development of DR programs) through at least the first quarter of next year before any Track 4 procurement is authorized.
SDG&E’s calculation of its incremental resource need appears to be reasonable. (at III-31, II-12.) SDG&E’s analysis of need is consistent with CAISO’s, which shows an incremental need between 620 and 147 MW, after adjusting for Track 1 authorized procurement. (at II-12.) SDG&E’s proposal is only partially consistent with the loading order. (at II-11-12). As in the case of SCE, the Commission should also use updated assumptions in identifying
R.12-03-014 ALJ/DMG/avs
- 10 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
13. Independent Energy Producers (IEP)
2,506 MW (including the Track 1 solicitation of 1,400-1,800 MW). If full 1,800 MW from Track 1 is procured, then Track 4 authorization should be 706 MW (2,506 – 1,800) (at 30)
820 MW However, if Commission does not approve the Pio Pico application, then resource need would increase to 1,118 MW (820 + 298). (p. 30)
Factors in SCE’s and SDG&E’s service area drive uncertainty in forecasting, which can result in under-estimating need and threatening grid, include (1) net load forecasts in local resources are subject to significant uncertainty because of energy reduction and uncertainty as to demand; (2) slow economic recovery could accelerate increasing demand; (3) some preferred resources may not prove viable skewing load forecasts; (4) new and upgraded transmission may be delayed. (at 12-14) While over-capacity might result in slightly higher costs, under-capacity would come with a very high social cost. (at 15) Track 4 authorization should be based on total resource need in Track 4 studies. (PHC Comments, at 2.)
14. National Resources Defense Council (NRDC)
SCE’s local capacity need for LA Basin should be reduced by 543 MW under either CAISO or SCE models. (at 13)
SDG&E’s local capacity need should be reduced by 211 MW as compared to SDG&E’s model results or 342 MW as compared to CAISO’s modeling results. (at 13)
Reductions justified because energy efficiency assumptions were substantially underestimated. (at 13) Further reductions may be justified from inclusion of CAISO’s 2012/2013 transmission plan results and the CEC’s 2013 managed demand forecast results. (Testimony, at 9; Comments, at 2)
R.12-03-014 ALJ/DMG/avs
- 11 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
15. NRG Testimony
MW Number Not Provided
MW Number Not Provided
Loss of SONGS creates substantial need for new resources in LA and San Diego areas. (at 5.) The loss of 2,246 MW of real power support and 1,100 MVAR of reactive power support degrades the reliability of the local bulk power system. (at 6.)
R.12-03-014 ALJ/DMG/avs
- 12 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
16. Office of Ratepayer Advocates (ORA) 242
MW Number Not Provided
MW Number Not Provided
CPUC should deny SCE’s and SDG&Es request for authorization. (at 8-9.) Recommends conservative procurement authorization that while ensuring reliability would minimize costs to ratepayers. (at 13) Recommends need determination and procurement authorization should be based on supplemental joint power flow studies that show the effect of all SCE and SDG&E identified LCR need reduction solutions on the entire SONGS study area. Studies submitted by SCE and SDG&E are insufficient. (at 14-15) The current record lacks adequate information to determine need and optimize procurement allocation for the SONGS study area, so ORA recommends that the Commission find 0 MW of need at the present time. (10/17 email) Although ORA believes that the current record is inadequate to determine need in the SONGS study area, if the Commission nevertheless finds need, it should allocate procurement authority to SCE and SDG&E in manner that minimizes overall procurement, ratepayer costs and greenhouse gas emissions while maintaining reliability in the SONGS study area. (For example, the CAISO determined that overall procurement would be less if 33.3% were located in SDG&E’s service territory and 66.7% in SCE’s service territory.) (10/17 email)
242 Witness Radu Ciupagea.
R.12-03-014 ALJ/DMG/avs
- 13 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
17. PG&E243 3,302 MW (Table 2-1, at 2-4 of reply testimony)
1,770 MW (Table 2-1, at 2-4 of reply testimony)
Figure II-1 of SCE Track 4 opening testimony, at 8. For SCE, PG&E uses the LA Basin Generation scenario and recommended additional 500 MW of procurement authorization as the identified need.
Table 3 of SDG&E Track 4 opening testimony of John M. Jontry, at 12
243 The numbers cited for Track 4 need by utility represent PG&E’s recommendation for a need determination. The need determination should identify the full incremental need (in MW) to meet southern California’s local reliability needs given the Track 4 power flow study assumptions made by SCE and SDG&E. These numbers are not incremental to procurement authorized in Track 1 of the 2012 LTPP. To the extent that resources are procured through authorization granted in Track 1 of the 2012 LTPP or other recent procurement authorizations, this need can be met by those estimated amounts to the extent deemed effective at meeting the identified need. Likewise, to the extent that transmission solutions are approved, verified to reduce local reliability needs without building new generation, and on track to be completed in the necessary timeframe, the need can also be met by those estimated amounts to the extent deemed effective at meeting the identified need.
R.12-03-014 ALJ/DMG/avs
- 14 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
18. Protect Our Communities (POC)
NA 0 MW NA No additional authorization should be made at this time. Current CAISO N1-1 criterion is an unreasonable reliability measure to base Local Capacity Requirement need for SDG&E. In addition, the retirement of the Encina OTC should not be assumed when determining LCR need. Further, the San Diego local area must include the 1080 MW in generation assets connected to SDG&E’s Imperial Valley substation.
R.12-03-014 ALJ/DMG/avs
- 15 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
19 Sierra Club 0 MW (at 1)
0 MW (at 1)
Considering load shedding, the latest CEC demand forecast, and the Mesa Loop-In Transmission Upgrade eliminates the need that CAISO identified in its Track 4 studies. Also, the assumptions do not include enough energy efficiency, demand response, energy storage, or distributed generation; accounting for these resources would eliminate need. Finally, CAISO’s N-1-1 reliability standard is overly conservative and resulted in an overinflated estimate of need.
Assuming use of the standard G-1, N-1 SDG&E limiting contingency (which would add 1,080 MW of existing combined cycle generation to LCR capacity), the latest CEC demand forecast, and load shedding eliminates the need that CAISO identified in its Track 4 studies. Also, the assumptions do not include enough energy efficiency, demand response, energy storage, or distributed generation; accounting for these resources would eliminate need. Finally, CAISO’s reliability standard (N-1-1 contingency) is overly conservative, and resulted in an overinflated estimate of need.
R.12-03-014 ALJ/DMG/avs
- 16 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
20. The Utility Reform Network (TURN)
500 MW (at 9)
500 MW (at 9)
TURN believes there is no “grand plan” to answer the Southern California Reliability needs but that the Commission will need to incrementally consider from a series of competing measures to gradually meet such needs. (at 4-5.)
R.12-03-014 ALJ/DMG/avs
- 17 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
21. Vote Solar Before authorizing any additional resource procurement in Track 4, SCE should first fulfill entire Track 1 Preferred Resources (PR) procurement authorization and develop the Mesa Loop-In.
Before authorizing any additional resource procurement in Track 4, SDG&E should first fulfill entire Track 1 PR procurement.
If additional resources are still needed, Vote Solar recommends using only PR and storage, phased-in over time as needed with annual solicitations; leverage Distributed Energy Resources (DER), storage & PV-DG to meet LCR in-basin and ensure reliability; use Living Pilot to test interoperability; include smart grid in Living Pilot; and ensure pilot-to-deployment process is developed. Too maximize PV-DG, orient PV to west to address afternoon ramp and use intelligent inverters to provide voltage support on distribution grid; include both in Living Pilot. No need for land set aside for future generation development or options contracts for gas (though preferable to SDG&E Energy Park proposal)
If additional resources are still needed, Vote Solar recommends using only PR and storage, phased-in overtime as needed with annual solicitations; leverage Distributed Energy Resources (DER), storage & PV-DG to meet LCR in-basin and ensure reliability; and develop a parallel pilot to SCE’s Living Pilot or participate in SCE’s Living Pilot. No need for Energy Park proposal.
R.12-03-014 ALJ/DMG/avs
- 18 -
No.
Party Track 4 Need by Utility
(Need is incremental to any authorization already
provided for in the Track 1 decision)
Basis for Track 4 Need By Utility
SCE SDG&E SCE SDGE
22. Wellhead Electric
MW Number Not Provided
MW Number Not Provided
In comparison to conventional gas-fired generation, the fast acting attribute of energy storage is valuable to the grid with fewer efficiency losses; is also more accurate at tracking fast changing regulation signals. Any procurement authorization should include all resources with attributes able to meet local area needs and ensure that certain classes of resources are not excluded from participation and, as a result, from consideration by the utility customer.(at 7. tyvm. Kerner)
23. Women’s Energy Matters (WEM)
NA NA NA NA
24. Western Power Trading Forum (WPTF)
500 MW (at 4) Recommends all-source RFO as opposed to mandating which specific resources should be used.
NA SONGS is now permanently retired and the Commission and the affected utilities need to move forward expeditiously to meet the affected need. (at 4)
NA
(END OF ATTACHMENT A)
R.12-03-014 ALJ/DMG/avs
- 1 -
ATTACHMENT B
SDG&E Procurement Plan Requirements
In the proposed procurement plans to be reviewed by Energy Division, SDG&E shall include all of the following:
1. Overall description of procurement process: Major procurement steps,
such as soliciting bids, bid evaluation, selection of bids/signing contracts,
filing application for Commission approval, expected decision, on-line
date. Also include details on contingent contract process including triggers
that would necessitate the execution of contingent contracts, option cost,
contract terms, and a detailed break up of costs. Describe which elements
of the solicitation will be made public.
2. Timeline: The procurement plan should contain a detailed timeline that
includes an estimate for when resources with specific megawatt quantities
are expected to come online up to the year of authorization. The timeline
should also include:
a. Major procurement steps, such as soliciting bids, bid evaluation,
selection of bids/signing contracts, filing application for
Commission approval, expected decision, and on-line date
b. A sub-timeline for any contingent contracts
c. Major decision points for backup procurement when resources do
not materialize
3. Locational details: Indicate the substations and the locational effectiveness
of the sites where the utility plans to procure resources.
4. Description and quantification of how authorized demand-side
resources are incremental: Detail plans to distinguish resources procured
for the purpose of meeting LCR capacity/ energy from resources procured
within existing IOU-DSM programs like energy efficiency and demand
response.
a. For energy efficiency: Establish baseline planning assumptions that
reflect LTPP planning assumptions. Detail how the utility will direct
R.12-03-014 ALJ/DMG/avs
- 2 -
bidders to propose resources whose procurement would exceed the
baseline, such as resources with strong economic potential that face
a market barrier, resources that are cost-competitive with other
resources because of transmission constraints, or vendor
identification of “to energy efficiency program baseline” and “above
energy efficiency program baseline” savings. State the methodology
and assumptions by which the utility will conduct an assessment to
quantify the energy efficiency program baseline and the capacity
and energy saving values of the incremental resources, including
such data sources as impact evaluation studies, engineering
estimates, before-and-after operational data using advanced
metering infrastructure, or approved measure-based M&V.
Document how the assessment uses methods and assumptions
consistent with current Commission adopted policy concerning the
estimation of savings for energy efficiency projects and measures.
b. For demand response: Similar to energy efficiency, demand response
load impact from the selected bids should be incremental to the CEC
load forecast and the supply assumptions used for this decision. In
addition, establish RFO criteria that are consistent with all approved
Commission decisions in the demand response rulemaking (R.13-09-
011), Commission resolutions addressing demand response, Electric
Rule 24, and any approved California ISO determinations of
operational characteristics required of demand response to meet local
reliability needs. The RFO criteria should provide flexibilities for
meeting future adopted demand response policy if the Commission
decisions in the demand response rulemaking (R.13-09-011) are
pending. Detail how the utility will direct bidder to propose resources
capable of meeting these criteria. State the methodology by which the
utility will quantify and verify the operation of demand response
resources to meet local reliability needs.
5. LCR and flexible attributes: Describe the LCR and flexible attributes of
the various technology-specific resources considered for procurement.
Apply RA counting rules and the ISO “Non Transmission Alternatives”
R.12-03-014 ALJ/DMG/avs
- 3 -
study in most cases. In cases where there are no defined attributes for a
resource, propose attributes with a detailed rationale.
6. Procurement Process: Include detailed description of the procurement
process resources, specifying the structure of any RFO, bilateral contract,
existing procurement programs or alternative procurement process and
related timelines. Include information on structure of offers, selection,
short listing, and cost competitiveness threshold.
7. Include evaluation details. Include a detailed description for evaluating
resources which contains the following information:
a. A process to evaluate different resources in a non-discriminatory
fashion
b. A method to quantify costs and benefits related to capacity, energy,
flexibility, GHG, ancillary services etc. for all resources
c. Standardized assumptions for costs and benefits across resource
type
d. A method to capture non-energy and other quantitative benefits
8. Include CAM details: Indicate which resources should be subject to CAM
treatment. Indicate which procured resources will count towards IOU
program goals.
9. Project details: Include details on how its plans to evaluate the viability of
preferred resource projects. Also include the following project details for
each technology type:
a. Desired start dates for delivery
b. Acceptable contract durations
c. Minimum size in terms of capacity
d. Interconnection requirements
10. Other Details: Include information on the following.
R.12-03-014 ALJ/DMG/avs
- 4 -
a. Bidder outreach before and after the solicitation including details
like bidder conferences, advertisements, and webinars
b. Participation of disadvantaged business enterprises
c. Independent Evaluator (IE) details and IE role
11. Other statutes affecting procurement: Cite relevant state laws and
Commission decisions influencing this procurement. List potential
challenges.
12. Documents: Include non-binding pro form as and draft solicitation
documents.
(END OF ATTACHMENT B)