dam assignment

Upload: niranjan1483

Post on 07-Apr-2018

233 views

Category:

Documents


2 download

TRANSCRIPT

  • 8/6/2019 DAM Assignment

    1/4

    Roll No Name

    112 Movin Crasto

    a. What is the sample mean and sample variance of the set?Ans:

    b. What is the inventory policy that American Aerospace should implement for part 10003487?Ans: As per the case , we are of the opinion that American Aerospace should implement theRe-

    order Point , Order-Quantity Policy ( R,Q) Model , because of the following assumptions :-

    1) Part 10003487 inventory appears to be a stable/critical product and is under continuousreview.

    Month

    Number Of MX332

    ordered

    June 25

    July 31

    August 18September 22

    October 40

    November 19

    December 38

    January 21

    February 25

    March 36

    April 34

    May 28

    June 27Mean 28

    Variance 53.16666667

    Std. Dev 7.291547618

  • 8/6/2019 DAM Assignment

    2/4

    2) No lead time for Part 10003487 by itself , however the lead time of one and a half months andthe corresponding delay is due to that of the other steel parts. This lead time is considered in

    our workings below.

    3) The demand ofPart 10003487 is equal to the demand of MX332 jet engines , since it isexclusively used for this type of jet engines. Therefore the assumption is that the part is

    normally distributed with a mean and Variance of 28 & 53.1667 as per answer a.

    4) Fixed set up cost K = 5,800 and holding cost h= 750 and shortage cost p = 3,250

    Average Demand Yearly = Mean * 12 months

    D = 28 * 12 = 336

    There for Average Demand for Lead time of One & Half Months = Mean * 1.5 months

    D = 28 * 1.5 = 42

    & Standard Deviation = 7.29154761807579 * 1.5 = 10.9373214271137

    Average Demand per Unit Time D 336

    Set Up Cost K 5800

    Unit Holding Cost h 750

    unit Shortage Cost p 3250

    Service Level L 0.85

    From the above : Order Quantity (Q ) = Sqrt of ( 2*D*K) / h) * Sqrt of ( ( p+h)/p) = 79.97538

    Re-order Point ( R ) = a + L (b-a) = 53.3358

    To Summarise American Aero space should implement the (R,Q) model withrounded off values

    ofQ = 80 & R=53

    c. What are the average annual holding costs and set up costs as associated with this inventorypolicy.

    Average inventory Cost before Order Arrives = R -Average Demand for Lead time = 53-42 = 11

    Average inventory Cost After Order has Arrived = Average inventory Cost before Order Arrives + Q

    = 11+80 = 91

  • 8/6/2019 DAM Assignment

    3/4

    Therefore Average Inventory Level = (11+91)/2 = 51

    Hence Average Yearly Holding Cost = 51 * Unit Holding Cost = 51 * 750 = 38,250

    Average number of set ups per year = Average Demand Yearly / Q = 336 / 80= 4.2

    Hence Average Yearly Set Up Cost = 4.2 * Set Up Cost = 4.2 * 5800 = 24,360

    d. How do the average annual holding costs and set up costs change if the desired probability thata shortage will not occur between the time an order is placed and the time the order is

    delivered is increased to 0.95

    New L = 0.95 and hence the revised table below and revised values ofQ & R

    Average Demand per Unit Time D 336

    Set Up Cost K 5800

    Unit Holding Cost h 750

    unit Shortage Cost p 3250

    Service Level L 0.95

    Using similar formulas as used in solution to question c : Q = 80 & R = 60 ( Rounded Off )

    Average inventory Cost before Order Arrives = 60-42 =18

    Average inventory Cost After Order has Arrived = 18+80 =98

    Therefore Average Inventory Level = (18+98)/2 = 58

    Hence Average Yearly Holding Cost = 58 * Unit Holding Cost = 58 * 750 = 43,500

    Average number of set ups per year = 336 / 80 = 4.2

    Hence Average Yearly Set Up Cost = 4.2 * Set Up Cost = 4.2 * 5800 = 24,360

  • 8/6/2019 DAM Assignment

    4/4

    No Change in Average Yearly Set Up Cost while there is an increase in Average Yearly Holding Cost

    e. Do you think Scarletts independent analysis of each stationary part could generate inaccurateinventory policies ? Why or Why Not

    Scarletts independent analysis of stationary part 10003487 is justified since only a single jet engine that

    needs this part and this part is the one causing the lead time in the process .

    However in most cases stationary parts would be used for multiple jets and the lead time due to this

    stationary part affects the demand for other parts as well . Hence the interdependency cannot be

    analyzed correctly performing an independent analysis of each stationary part. Hence it can be said that

    Scarletts approach of independent part analysis may be inaccurate for other stationary parts.

    f . Scarlett knows that the aerospace industry is very cyclical the industry experiences several years of

    high sales , several years of mediocre sales and several years of low sales . How would you recommend

    incorporating this fact into the analysis.

    Ans: Forcasting method could be used.