d i a z x y o u r m a n - el centro, california · d i a z x y o u r m a n ... associates (dya) ......
TRANSCRIPT
D I A Z • Y O U R M A N
& A S S O C I A T E S
1616 EAST 17th STREET SANTA ANA, CA 92705-8509 TEL. (714) 245-2920 FAX (714) 245-2950
ii K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
TABLE OF CONTENTS
1.0 INTRODUCTION................................................................................................................1
2.0 FIELD INVESTIGATION AND LABORATORY TESTING..................................................4
3.0 SITE CONDITIONS............................................................................................................5
4.0 CONCLUSIONS AND RECOMMENDATIONS..................................................................7 4.1 PAVEMENT THICKNESS DESIGN................................................................................7
4.1.1 New Pavements..........................................................................................................7 4.1.2 Existing Pavements ....................................................................................................8
4.2 EARTHWORK ................................................................................................................9 4.3 CONCRETE FLATWORK.............................................................................................10 4.4 SOIL CORROSION POTENTIAL..................................................................................11
5.0 PLAN REVIEW, CONSTRUCTION OBSERVATION, AND TESTING.............................13
6.0 LIMITATIONS...................................................................................................................14
7.0 BIBLIOGRAPHY ..............................................................................................................15
APPENDIX A - FIELD INVESTIGATION .................................................................................. A-1
APPENDIX B - LABORATORY TESTING ................................................................................ B-1
APPENDIX C - TRAFFIC INDEX CALCULATIONS ................................................................. C-1
LIST OF FIGURES Figure 1 - SITE VICINITY MAP.....................................................................................................1 Figure 2 - SITE PLAN ...................................................................................................................2 Figure 3 - PAVEMENT THICKNESS ............................................................................................8
LIST OF TABLES Table 1 - EXISTING PAVEMENT .................................................................................................5 Table 2 - SUBSURFACE SOIL CHARACTERISTICS ..................................................................6 Table 3 - IMPORT FILL CRITERIA.............................................................................................10 Table 4 - CORROSION POTENTIAL..........................................................................................12
1 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
1.0 INTRODUCTION
This report presents the results of the geotechnical investigation performed by Diaz•Yourman &
Associates (DYA) for the proposed El Dorado Colonia Street Improvement Project in El Centro,
California. DMC Design Group, Inc. (DMC) authorized this work on March 31, 2008.
The El Dorado Colonia Street Improvement Project consists of improvements on 8th Street
between El Dorado Avenue and the North Date Canal in El Centro, California, as shown on the
Vicinity Map, Figure 1. The approximate layout of the proposed project is shown on the Site
Plan, Figure 2. The proposed project will consist of widening the existing street; adding curbs,
gutters, sidewalks, and street lighting; and rehabilitating the existing pavement.
Figure 1 - SITE VICINITY MAP
SITE
3 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
The purpose of DYA's investigation was to provide geotechnical input for the design of the
proposed project. The scope of our services consisted of:
• Conducting a subsurface investigation.
• Performing laboratory tests on selected soil samples.
• Performing engineering analyses to develop conclusions and recommendations
regarding site preparation and grading, and pavement thickness for flexible pavements.
• Preparing this report.
4 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
2.0 FIELD INVESTIGATION AND LABORATORY TESTING
The subsurface investigation, conducted on May 22, 2008, consisted of sampling the subgrade
soils at three locations (Borings B-1 through B-3) as shown on the Site Plan, Figure 2. The
borings were drilled using hollow-stem auger techniques to a depth of approximately 11.5 feet.
Details of the field investigation, including sampling procedures and boring logs, are presented
in Appendix A. Borings were backfilled with soil cuttings and the surface was patched with cold
patch asphalt.
Soil samples were re-examined in the laboratory to substantiate field classifications. Selected
soil samples were tested for moisture content, dry density, Atterberg limits, compaction
characteristics, sand equivalent, grain size distribution, corrosion potential CpH, electrical
resistivity, soluble chlorides, soluble sulfates, and pavement-supporting capacity (R-Value). The
soil samples tested are identified on the boring logs. Laboratory test data are summarized on
the boring logs in Appendix A and presented on individual test reports in Appendix B.
5 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
3.0 SITE CONDITIONS
The project reach is located within an agricultural and residential zone. There was one lane in
each direction without center turn lanes. Concrete curbs and gutters were not present along the
project reach. The existing asphalt concrete (AC) pavement surface condition varied from fair to
poor. The AC surface exhibited signs of various AC distress including block, transverse,
longitudinal, and alligator cracking.
The existing pavement structural section consisted of approximately 5 to 6 inches of AC and 6
to 8 inches of base as shown in Table 1. The subgrade soils varied from silty sand to lean clay
and fat clay. The clayey subsurface soils were considered to have high expansion potential.
Expansive soils will undergo changes in volume with changes in moisture content (expand when
saturated and shrink when dried), which can result in lifting and settling of the subgrade.
Table 1 - EXISTING PAVEMENT PAVEMENT BASE BORING
ID Type Thickness (inches) Description1/Type Thickness
(inches) SUBGRADE
B-1 AC 5.5 Poorly Graded Gravel 6 7 inches Silty Sand above Fat Clay B-2 AC 6 Poorly Graded Gravel 7 11 inches of Silty Sand above Lean Clay B-3 AC 5 Poorly Graded Gravel 8 Silty Sand
Notes: 1. See Plate A-1 in Appendix A for soil classification. • AC = asphalt concrete. • AB = aggregate base. • 25mm = 1 inch.
The R-value was 5. The insitu and optimum moisture contents, insitu and maximum unit
weights, relative compaction1, and R-values of the subsurface materials are summarized in
Table 2. Groundwater was not encountered in the borings during the field investigation.
1 Relative compaction refers to the in-place dry density of soil expressed as a percentage of the maximum dry density of the same material, as determined by the American Society for Testing Materials (ASTM) D1557-91 test method. Optimum moisture content is the moisture content corresponding to the maximum dry density, as determined by the ASTM D1557-91 test method.
6 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
Table 2 - SUBSURFACE SOIL CHARACTERISTICS
BORING ID
DEPTH (feet)
SOIL TYPE
INSITU MOISTURE CONTENT
(%)
OPTIMUM MOISTURE CONTENT1
(%)
INSITU DRY UNIT WEIGHT
(pcf)
MAXIMUM DRY UNIT WEIGHT1
(pcf)
RELATIVE COMPACTION1
(%)
B-1 2 CH 25 15 100 115 87 B-1 10 CH 25 15 100 115 87 B-2 2 CL 14 15 100 115 87 B-2 6 SM 12 7 114 135 84 B-3 2 SM 5 7 118 135 87 B-3 10 ML 30 7 84 130 65
Note: 1. Based on ASTM D1557.
7 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
4.0 CONCLUSIONS AND RECOMMENDATIONS
For new pavements, the primary geotechnical consideration was the presence of fine-grained
silts and clays 10 to 15 percent over optimum moisture content as shown in Table 2 and the
high expansion potential of the fine-grained silts and clays. These fine-grained materials with
moisture contents greater than approximately 2 percent over optimum will likely require moisture
conditioning (drying) prior to compaction. At the same time, the expansion characteristics of the
soils require that soils should remain at or above optimum content, especially under concrete
flatwork. Therefore, precise moisture conditioning of the subgrade soils is the key to a
successful project.
The existing pavement in fair condition can be overlaid with 2-inch asphalt rubber hot mix
(ARHM). Loose and/or spalling pavement, potholes, localized failures, and the existing
pavement in poor condition should be repaired prior to any overlay.
4.1 PAVEMENT THICKNESS DESIGN
4.1.1 New Pavements
The following minimum pavement sections were based on an R-value of 5, the Caltrans design
method, and a traffic index (TI) of 8.5 provided by DMC. The recommend minimum pavement
thickness is presented on Figure 3.
8 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
Basement Soil - Layer 1
Base Course
Subgrade
Total Pavement Section
ARHM/AC Course
MINIMUM THICKNESS (mm)
COURSE Alternative 1 - ARHM/AC/AB
Alternative 2 - ARHM/AC/AB with
Geogrid6
Alternative 3 - AC/AB
Alternative 4 - AC/AB with Geogrid6
ARHM1 2 2 0 0 AC2 4 4 6 6 Base3 17 11 17 11 Basement Soil4,5 12 12 12 12 Notes:
1. Asphalt rubber hot mix (ARHM) should satisfy the requirements of Greenbook Sections 203 and 302. 2. Asphalt concrete (AC) should satisfy the requirements of Caltrans Standard Specifications Sections 39 and
40, respectively; or Greenbook Sections 203, 201, and 302, respectively. 3. Base course = AB or CMB, in accordance with Caltrans Standard Specifications Section 26 or Greenbook
Sections 200-2.2 and 200-2.4, respectively. The minimum relative compaction is 95 percent. 4. Compacted in-place natural basement soil or fill; at least 90 percent relative compaction. 5. Basement soil can be replaced. See Section 4.2. 6. Place geogrid at the bottom of the AB layer; Greenbook Table 213.2.2 (B), Biaxial S2 (Tensar BX1200, or
equivalent). Figure 3 - PAVEMENT THICKNESS
4.1.2 Existing Pavements
Recommendations for three pavement overlays are summarized below:
• Preferred Alternative - a 2-inch-thick ARHM overlay.
• Alternative A - a 2-inch-thick AC overlay with reinforcing material.
• Alternative B - a 2-inch-thick AC overlay with crack seal.
If conventional AC is used instead of ARHM, a reinforcing material should be placed on the
existing pavement to help resist reflective cracking. This reinforcing material can also be placed
at the junction between existing and new AC pavements. Note that Petromat is not considered
a reinforcing material. If reinforcing material is not used, cracks greater than ¼ inch should be
sealed prior to placing the pavement overlay (Caltrans, 2006a); see the crack seal
manufacturer’s recommendations for details. Loose and/or spalling pavement, potholes, and
localized failures should be repaired (Caltrans, 2006a) prior to the overlay.
9 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
The following should be considered when using reinforcing materials:
• If installed incorrectly, there can be slippage between the new pavement and the existing
pavement.
• Difficulty in recycling asphalt in the future due to reinforcing material collecting in the
recycling equipment and disposal, depending on the reinforcing material.
• Glassgrid tends to be more effective in reducing reflective cracking than other less stiff
reinforcing materials, but it is more expensive than other products.
4.2 EARTHWORK
Prior to the start of construction, all utilities should be located in the field and rerouted, removed,
abandoned, or protected. The areas should be graded to the planned subgrade elevation.
Reconstructing the road segments may require removing some or all of the existing pavement
and base materials. The excavated AC and base materials should be taken to a recycling plant.
Unpaved areas to be graded and paved areas should initially be stripped of all vegetation and
debris, and the material removed from the site.
Prior to placing fill, the exposed subgrade should be:
• Scarified to a depth of 8 inches.
• Moisture-conditioned to a minimum of 2 percent above-optimum moisture content.
• Compacted to at least 90 percent relative compaction.
Fill should be compacted by:
• Placing in loose layers less than 8 inches thick.
• Moisture-conditioning to a minimum of 2 percent above-optimum moisture content.
• Compacting to at least 90 percent relative compaction.
The basement soil (soils 1 foot below the pavement section [AC and base]) and aggregate base
(AB) should be compacted to at least 90 percent relative compaction. As insitu moisture
contents were generally between 10 and 15 percent over optimum moisture content, moisture
10 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
conditioning can consist of in-place drying involving scarifying, exposing the soil surface to sun
and wind, and/or mixing wet soils with dry soils.
Where the subgrade soils preclude compaction because combinations of high moisture content
and/or fine-grained silty and clayey soils exist, they should be overexcavated to a sufficient
depth such that a firm and unyielding surface is achieved at the planned bottom of the
excavation. Overexcavation limits, if required, are best and most accurately determined in the
field after the subgrade is exposed and proofrolled. Using geogrids and/or easily compacted
material such as crushed rock can reduce the depth of excavation. The geogrids should satisfy
the requirements of Standard Specifications for Public Works Construction (Greenbook)
Table 213.2.2 (B), Biaxial S1 (Tensar BX1100, or equivalent). The geogrid should be installed
as follows:
• Nail the geogrid with 6-inch-long “U” staples and/or other approved fasteners to the end
edges of the geogrid roll.
• Unroll the geogrid without dragging.
• Pull the geogrid taut to remove any slack.
• Overlap the geogrid by at least 1 foot.
• Push a new layer of AB on top of the geogrid without creating waves in the geogrid and
without the construction equipment contacting the geogrid.
• Compact the new layer of AB without pumping with light compaction equipment.
Import materials, if needed, for fill should meet the criteria in Table 3.
Table 3 - IMPORT FILL CRITERIA CRITERIA IMPORT FILL
Maximum particle size (inches) 2 Maximum liquid limit (%) 30 Maximum plasticity index (%) 10 Maximum percentage passing the #200 sieve (%) 30 R-value 50 Minimum sand equivalent 30
4.3 CONCRETE FLATWORK
Concrete flatwork (i.e., hardscape, sidewalks, curbs, and gutters) can be adversely influenced
when underlain by potentially expansive soils. The onsite soils were classified as highly
11 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
expansive. Expansive soils will undergo changes in volume with changes in moisture content
(expand when saturated and shrink when dried), which can result in lifting and cracking of
concrete flatwork. In order to reduce the effects of expansive soils, it is imperative that
expansive clays be maintained at or above optimum moisture content until the concrete is
placed. Once compacted, expansive soils must not be allowed to dry below optimum moisture
content. This can be accomplished by daily watering or soaking and/or the use of plastic
sheeting on the prepared subgrade until the concrete flatwork is poured.
To further limit the effects of expansive soils on concrete flatwork, additional methods to
consider in combination with subgrade presaturation include:
• A sublayer of granular material.
• Reinforcement.
• Moisture barriers and drains.
• Concrete mix design, materials, placement, curing, and finishing in conformance with the
Greenbook and the American Concrete Institute (1996, 1997).
• Frequent expansion joints.
• Frequent cold joints.
4.4 SOIL CORROSION POTENTIAL
One test performed during this investigation indicated 1,766 parts per million (ppm) soluble
sulfate concentrations in the near-surface soils. Based on these test results, we recommend
that Type V cement be used with a maximum water/cement materials ratio in accordance with
the CBC standard.
One soil sample was tested for pH, soluble chloride, and electrical resistivity to check for
corrosion potential. The test values are summarized in Table 4. Also presented in Table 4 are
Caltrans (1996) corrosion criteria. The corrosion potential test results are presented in
Appendix B. Based on Caltrans standards and other published correlations and the chemical
test results, the onsite soils are classified as severely corrosive to buried metal pipes. We
recommend that protective coatings on metal pipes be considered and that a corrosion
specialist be contacted for details of corrosion protection.
12 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
Table 4 - CORROSION POTENTIAL
CHARACTERISTIC RANGE OF VALUES CALTRANS CRITERIA FOR CORROSIVE MATERIALS
pH 8.3 <5.5 Soluble sulfate content (ppm) 1,766 >2,000 Soluble chloride content (ppm) 460 >500 Electrical resistivity (ohm-cm) 440 <1,000
13 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
5.0 PLAN REVIEW, CONSTRUCTION OBSERVATION, AND TESTING
DYA should be retained to review the finished grading earthwork and specifications for
conformance with the intent of our recommendations. The review will enable DYA to modify the
recommendations if final design conditions are different than presently understood.
During construction, DYA should provide field observation and testing to check that the site and
subgrade preparation, base material quality, and compaction conform to the intent of these
recommendations and the job specifications. This would allow DYA to develop supplemental
recommendations as appropriate for the actual soil conditions encountered and the specific
construction techniques used by the contractor.
As needed during construction, DYA should be retained to consult on geotechnical questions,
construction problems, and unanticipated site conditions.
14 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
6.0 LIMITATIONS
This report has been prepared for this project in accordance with generally accepted
geotechnical engineering practices common to the local area. No other warranty, expressed or
implied, is made.
The analyses and recommendations contained in this report are based on the field investigation,
and laboratory testing conducted in the area. The results of the field investigation indicate
subsurface conditions only at the specific locations and times, and only to the depths
penetrated. They do not necessarily reflect strata variations that may exist between such
locations. Although subsurface conditions have been explored as part of the investigation, we
have not conducted chemical laboratory testing on the samples obtained or evaluated the site
with respect to the presence or potential presence of contaminated soil or groundwater
conditions.
The validity of our recommendations is based in part on assumptions about the stratigraphy.
Observations during construction can help confirm such assumptions. If subsurface conditions
different from those described are noted during construction, recommendations in this report
must be reevaluated. DYA should be retained to observe earthwork construction in order to
help confirm that our assumptions and recommendations are valid or to modify them
accordingly. In accordance with CBC Appendix J, DYA cannot assume responsibility or liability
for the adequacy of recommendations if we do not observe construction.
This report is intended for use only for the project described. In the event that any changes in
the nature, design, or location of the facilities are planned, the conclusions and
recommendations contained in this report should not be considered valid unless the changes
are reviewed and conclusions of this report modified or verified in writing by DYA.
15 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
7.0 BIBLIOGRAPHY American Concrete Institute, 1996, ACI 302.1R-96, Guide for Concrete Floor and Slab
Construction. American Concrete Institute, 1997, ACI 360R-92, Design of Slabs on Grade. American Public Works Association, MicroPaver Distress Identification Manual. American Society of Testing Materials, 2007, Annual Book of Standards, Volumes 4.08 and
4.09, Soil and Rock. Building News, 2007, “Greenbook,” Standard Specifications for Public Works Construction. California Department of Transportation, 2006a, Highway Design Manual, Sixth Edition. California Department of Transportation, 2006b, Standard Specifications.
A-1 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
APPENDIX A - FIELD INVESTIGATION
The field investigation for the proposed project consisted of drilling three borings (B-1 through
B-3). The approximate boring locations are shown on Figure 2.
Borings were drilled by Landmark Consultants, Inc. on May 22, 2008, with a truck-mounted
CME-75 drill rig using hollow-stem auger drilling techniques. Their field engineer observed the
drilling operations and collected drive samples for visual examination and subsequent laboratory
testing. Drive samples were collected with a 2.4-inch-inside-diameter (3.0-inch-outside-
diameter) modified California split-barrel sample lined with brass tubes and a standard split-
spoon penetrometer with dimensions in accordance with ASTM 3550 and 1586, respectively.
Both samplers were driven with a 140-pound hammer falling 30 inches. An automatic trip
hammer was used. The blows required to drive the modified California sampler were converted
to "equivalent" standard penetration test (SPT) N-values by multiplying by 0.65 (N=0.65 x
modified California blows per foot). Field unconfined compression strengths were obtained
using a pocket penetrometer and/or torvane.
Soils encountered in the borings were classified in general accordance with the ASTM Soil
Classification System (ASTM D2487 and 2488), summarized on Plate A1. Boring logs
presented on Plates A2 through A4 were prepared from visual examination of the samples,
cuttings obtained during drilling operations, and results of laboratory tests.
Borings were backfilled with soil cuttings. The surface was patched with asphalt cold patch.
Groundwater was not encountered during the field investigation.
Boring locations were identified in the field by measuring from known locations using a
measuring wheel.
El Dorado Colonia Street Improvements
WELL-GRADED GRAVELS, GRAVEL - SAND MIXTURES,
LITTLE OR NO FINES
DESCRIPTIONS
CLAYEY SANDS, SAND - CLAY MIXTURES
SW
LIQUID LIMIT GREATER
THAN 50
SP
PT
OH
CH
MH
SC
INORGANIC CLAYS OF LOW TO MEDIUM PLASTICITY,
GRAVELLY CLAYS, SANDY CLAYS, SILTY CLAYS,
LEAN CLAYS
(APPRECIABLE AMOUNT OF
FINES)
MORE THAN 50% OF
COARSE FRACTION
PASSING ON NO. 4 SIEVE
GW
HIGHLY ORGANIC SOILS
SM
SILTY GRAVELS, GRAVEL - SAND - SILT MIXTURES
DS = Direct Shear
SPT "N" = Uncorrected equivalent blow count for last foot of driving (set to 100 for driving refusal)= 0.65 x modified California blows per foot
CLEAN GRAVELS
SA = Grain size; HD = Hydrometer
SPT "N" = Uncorrected equivalent blow count for last foot of driving (set to 100 for driving refusal)
(APPRECIABLE AMOUNT OF
FINES)
"Push" Sampler
SOIL CLASSIFICATION SYSTEM-ASTM D2487
Project No. 2008-014.00
LETTER
OL
CL
A1
GC
CN = Consolidation
TYPICAL
CP = Collapse Potential
HC = Hydraulic Conductivity Test
GRAVEL AND
GRAVELLY
SOILS
MD = Compaction Test
Standard Penetration Test (SPT) Sampler
MORE THAN 50% OF
COARSE FRACTION
RETAINED ON NO. 4 SIEVE
NP = Nonplastic
SG = Specific GravitySE = Sand EquivalentUC = Unconfined Comp.
UU = Undrained, Unconsol. Triaxial.CU = Consol. Undrained Triaxial.
CA = Chemical Analysis
EI = Expansion Index Test
SILTS AND
CLAYS
ORGANIC CLAYS OF MEDIUM TO HIGH PLASTICITY,
ORGANIC SILTS
(LITTLE OR NO FINES)
GP
ML
RV = R-Value
GRAVELS WITH FINES
(LITTLE OR NO FINES)
CD = Consol. Drained Triaxial.CU = Consol. Undrained Triaxial.
SAND AND
SANDY
SOILS
NOTE: DUAL SYMBOLS ARE USED TO INDICATE BORDERLINE SOIL CLASSIFICATIONS
GRAPH
Concrete/Rock Core
Bag Sample
WELL-GRADED SANDS, GRAVELLY SANDS, LITTLE OR
NO FINES
FINE-GRAINED
SOILS
Split Barrel "Drive" Sampler With Liner
POORLY GRADED SANDS, GRAVELLY SAND, LITTLE
OR NO FINES
SILTS AND
CLAYS
COARSE-GRAINED
SOILS
Groundwater Surface
CLEAN SANDS
GM
[PID] Reading in ppm above background
MORE THAN 50% OF
MATERIAL IS SMALLER
THAN NO. 200 SIEVE SIZE
LIQUID LIMIT LESS
THAN 50
MAJOR DIVISIONS
CLAYEY GRAVELS, GRAVEL - SAND - CLAY MIXTURES
PLATE
INORGANIC CLAYS OF HIGH PLASTICITY
INORGANIC SILTS, MICACEOUS OR DIATOMACEOUS
FINE SAND OR SILTY SOILS
POORLY GRADED GRAVELS, GRAVEL - SAND
MIXTURES, LITTLE OR NO FINES
PEAT, HUMUS, SWAMP SOILS WITH HIGH ORGANIC
CONTENTS
INORGANIC SILTS AND VERY FINE SANDS, ROCK
FLOUR, SILTY OR CLAYEY FINE SANDS OR CLAYEY
SILTS WITH SLIGHT PLASTICITY
SANDS WITH FINES SILTY SANDS, SAND - SILT MIXTURES
SYMBOLS
MORE THAN 50% OF
MATERIAL IS LARGER
THAN NO. 200 SIEVE SIZE
ORGANIC SILTS AND ORGANIC SILTY CLAYS OF LOW
PLASTICITY
9
BORING DIAMETER (inches):
JGS
DATE STARTED:
LOGGED BY: J. Avalos
7
15
19
CHECKED BY:
BORING LOCATION:
30 inches 140 lbs
LONGITUDE:
Project No. 2008-014.00
LATITUDE:
8-Inches
DATE COMPLETED:
BORING DEPTH (feet): 11.5
ID: 2.4 OD: 3
DRILLING METHOD: Hollow Stem AugerCME-75DRILLING EQUIPMENT:
SAPOORLY GRADED GRAVEL with SILT and SAND (GP-GM): 6inches Aggregate Base
Bottom of boring at 11.5 feet.Groundwater not encountered during drilling.Boring backfilled with cuttings.Surface patched with cold patch asphalt.
FAT CLAY (CH): reddish brown, moist, stiff, high plasticity
SANDY SILT (ML): brown, wet, soft to firm, fine-grained sandvery stiff
SILTY SAND (SM): 7 inches Aggregate Subbase
ASPHALT CONCRETE (AC): 5.5 inches
25
25RV
COMSE
FAT CLAY (CH): reddish brown, moist, very stiff, high plasticity
7
4764
2
1
3
100
100
5/22/08
3
Liqu
idLi
mit
(%)
Tem
plat
e: D
YLG
1-20
06;
Prj
ID: 2
008-
014.
GP
J
Pla
stic
ityIn
dex
(%)
Moi
stur
eC
onte
nt (%
)
Ele
vatio
n(fe
et)
Page 1 of 1
5/22/08
A2
Sam
pler
Blo
ws
per
6 In
ches
PLATE
El Dorado Colonia Street Improvements
Oth
er T
ests
[PID
]
SP
T N
Blo
ws
per F
oot
Fiel
d U
nc.
Com
p. S
tr. (t
sf)
Dep
th(fe
et)
See Figure 2
5/22/08
5
10
15
20
25
LOG OF BORING B-1
32° 48' 17.0" N
Sym
bol
DRIVE SAMPLER DIAMETER (inches)
Dry
Den
sity
(pcf
)
SPT HAMMER DROP: WT:
DESCRIPTION
ELEVATION AND DATUM (feet):
115° 35' 40.8" W
40
35
30
25
20
Per
cent
Pas
sing
#200
Sie
ve
30 inches 140 lbs
45 MSL
DRIVE HAMMER DROP: WT:
CHECKED BY:
8-InchesBORING DIAMETER (inches):
JGS
DATE STARTED:
LOGGED BY:
DRILLING EQUIPMENT:
J. Avalos
3
5
5
10
DATE COMPLETED:
30 inches 140 lbs
LONGITUDE:
Project No. 2008-014.00
5/22/08
BORING DEPTH (feet):
5/22/08
BORING LOCATION:
11.5
ID: 2.4 OD: 3
DRILLING METHOD: Hollow Stem AugerCME-75
CA
soft to firm
Bottom of boring at 11.5 feet.Groundwater not encountered during drilling.Boring backfilled with cuttings.Surface patched with cold patch asphalt.
SILTY SAND (SM): gray brown, wet, loose, fine-grained sand114
LEAN CLAY (CL): reddish brown, moist, stiff, high plasticitySILTY SAND (SM): 11 inches Aggregate Subbase
POORLY GRADED GRAVEL with SAND (GP): 7 inchesAggregate Base
ASPHALT CONCRETE (AC): 6 inches
12
14
LEAN CLAY (CL): reddish brown, moist, soft, high plasticity
0.75
13
31
1024100
0.5
1.5
48
Sam
pler
Pla
stic
ityIn
dex
(%)
Liqu
idLi
mit
(%)
Moi
stur
eC
onte
nt (%
)
Ele
vatio
n(fe
et)
LATITUDE:
PLATE
SPT HAMMER DROP: WT:
A3
SP
T N
Blo
ws
per F
oot
Oth
er T
ests
[PID
]
Blo
ws
per
6 In
ches
Dep
th(fe
et)
El Dorado Colonia Street Improvements
LOG OF BORING B-2
Fiel
d U
nc.
Com
p. S
tr. (t
sf)
32° 48' 25.2" N
See Figure 2
DRIVE SAMPLER DIAMETER (inches)Tem
plat
e: D
YLG
1-20
06;
Prj
ID: 2
008-
014.
GP
J
115° 33' 40.7" W
Sym
bol
45 MSL
30 inches 140 lbsDRIVE HAMMER DROP: WT:
ELEVATION AND DATUM (feet):
5/22/08
DESCRIPTION
Dry
Den
sity
(pcf
)
Per
cent
Pas
sing
#200
Sie
ve
5
10
15
20
25
40
35
30
25
20
Page 1 of 1
8-Inches
DRIVE HAMMER DROP: WT:
DRILLING METHOD: Hollow Stem AugerCME-75DRILLING EQUIPMENT:
11.5BORING DEPTH (feet):
BORING LOCATION:
BORING DIAMETER (inches):
JGS
DATE STARTED:
LOGGED BY:
ELEVATION AND DATUM (feet):
SPT HAMMER DROP: WT:
Project No. 2008-014.00
ID: 2.4 OD: 3
SE
6
LONGITUDE:
5/22/08
LATITUDE:
5/22/08DATE COMPLETED:
SILTY CLAY (CL-ML): brown, moist, stiff, medium plasticity
CHECKED BY:
SANDY SILT (ML): brown, wet, firm, medium plasticity,fine-grained sand
very loose
SILTY SAND (SM): gray brown, wet, loose, fine- tomedium-grained sand
POORLY GRADED GRAVEL with SAND (GP): 8 inchesAggregate Base
ASPHALT CONCRETE (AC): 5 inches
30
5
Bottom of boring at 11.5 feet.Groundwater not encountered during drilling.Boring backfilled with cuttings.Surface patched with cold patch asphalt.
1
4
9 118
84
21
1
J. Avalos
Oth
er T
ests
[PID
]
30 inches 140 lbs
Sam
pler
30 inches 140 lbs
Liqu
idLi
mit
(%)
Moi
stur
eC
onte
nt (%
)
Ele
vatio
n(fe
et)
PLATE
Dep
th(fe
et)
Blo
ws
per
6 In
ches
SP
T N
Blo
ws
per F
oot
Fiel
d U
nc.
Com
p. S
tr. (t
sf)
Pla
stic
ityIn
dex
(%)
El Dorado Colonia Street Improvements
Sym
bol
See Figure 2
Page 1 of 1
5
10
15
20
25
40
35
30
25
20
32° 48' 30.0" N
A4
Tem
plat
e: D
YLG
1-20
06;
Prj
ID: 2
008-
014.
GP
J
45 MSL
LOG OF BORING B-3
DRIVE SAMPLER DIAMETER (inches)
115° 33' 40.7" W
Dry
Den
sity
(pcf
)
5/22/08
Per
cent
Pas
sing
#200
Sie
ve
DESCRIPTION
B-1 K:\DATAFLS\PROJECTS\2008\2008-014\REPORT\REPORT 2008-014.DOC
APPENDIX B - LABORATORY TESTING
Diaz•Yourman & Associates (DYA) selected soil samples to be tested and tests to be performed
on the selected samples. Laboratory testing was performed by Landmark Consultants, Inc.
Laboratory data are summarized on the boring logs and presented on Plates B1 through B5. A
summary of the geotechnical laboratory testing is presented in Table B1. Corrosion potential
test results are summarized in Table B2.
Table B1 - LABORATORY TESTING SUMMARY
TEST NAME PROCEDURE PURPOSE LOCATION
Percent Passing the No. 200 Sieve ASTM D1140-92 Classification, index properties Boring Logs
Moisture Content, Dry Density ASTM D2216-92 Classification, index properties Boring Logs
Grain-Size Distribution ASTM D422-63 Classification, index properties Plate B1
Atterberg Limits ASTM D-4318-93 Expansion potential, classification, index properties Plate B2
Compaction ASTM D1557-91 Earthwork Plates B3 through B5
Resistance (R-) Value ASTM D2844-69CTM 301 Pavement thickness design Plate B6
pH CTM 532 Corrosion potential Table B2 and Plate B7
Resistivity CTM 532 Corrosion potential Table B2 and Plate B7
Soluble Sulfates CTM 417-B Corrosion potential Table B2 and Plate B7
Soluble Chlorides CTM 422 Corrosion potential Table B2 and Plate B7 Notes:
• ASTM = American Society for Testing and Materials • CTM = Caltrans Test Method
Table B2 - CORROSION POTENTIAL TEST RESULTS Boring No. B-2 Depth (feet) 2-4.5 pH 8.3 Water Soluble Sulfate Content (ppm) 1,766 Water Soluble Chloride Content (ppm) 460 Minimum Resistivity/Moisture Content (ohms-cm / %) 440
PLATEPARTICLE SIZE ANALYSIS
16
0.005
Project No. 2008-014.00
Coarse
50
0.0010.010.1110
U.S. Standard
100
90
80
60
40
30
20
10
0100
70
Source #200 Sieve% Passing
Symbol M. C. (%)LiquidDepth
(feet)
50
20050
Tem
plat
e: D
Y_S
IEV
E_W
IN
El Dorado Colonia Street Improvements
Limit (%)
216.00.5
B-3
B-2
B-1
SILTY SAND (SM)
SILTY SAND (SM)
POORLY GRADED GRAVEL WITH SILT AND SAND (GP-GM)
Plasticity
12
Natural
3
137
Classification Index (%)
GRAVEL
GRAIN SIZE IN MILLIMETERS
11
0.05
2
U.S. Standard Sieve Numbers
0.55
100308
Hydrometer
4
Sieve Size (in.)
6.0
3
Fine
PER
CEN
T FI
NER
BY
WEI
GH
T
SILT or CLAY
3
SAND
B1
Laboratory Testing by: LandMark
MediumCoarse
48
FineCOBBLES
100 120
U-LINE
CH or OH
PLASTICITY CHARTEl Dorado Colonia Street Improvements
Laboratory Testing by: LandMark
B2
PLA
STIC
ITY
IND
EX (%
)
ML
16 800
PLATE
40
40
20
70
50
30
20
10
060
60
#200 Sieve
10.0
2.0
2.0
ClassificationLiquid
M. C. (%)
10B-2
B-1
LEAN CLAY (CL)
LEAN CLAY (CL)
FAT CLAY (CH)
14
3117
47
Limit (%)Depth(feet) Limit (%)
25
SymbolPlastic
CL or OL
Project No. 2008-014.00
MH or OH
7
LIQUID LIMIT (%)
ML or OL
Tem
plat
e: D
Y_A
TTE
RB
ER
G_C
HA
RT_
WIN
A-LINE
CL-4
% Passing
14
17
48
24
64
Source
B-2
Index (%)PlasticityNatural
FAT CLAY (CH)
116
118
120
122
124
126
128
130
132
134
136
130.5
115
LiquidSymbolIndex (%)
% Passing
SILTY SAND (SM)
(pcf)
LEAN CLAY (CL)
Plasticity
2.0
2.0
1.5
110
Dry Density
114
960
108
106
104
102
98
112
100
Maximum
100 % Saturation Curves
64
DepthLimit (%)
Project No. 2008-014.00
PLATE
Specific Gravity = 2.7
Content (%)Source
7
8
16
24
47
El Dorado Colonia Street Improvements
MoistureOptimum
10
24
Specific Gravity = 2.6
(feet) #200 Sieve
28
135
20161284
B-1
Classification
COMPACTION TEST DATA
Laboratory Testing by: LandMark
MOISTURE CONTENT (%)
DR
Y D
ENSI
TY (p
cf)
Specific Gravity = 2.8
Tem
plat
e: D
Y_C
OM
PA
CT_
4_P
LOTS
_WIN
B-2
B-3
B3