cyclic load testing of pre-stressed rock anchors for slope...

11
J. Mt. Sci. (2016) 13(1): 126-136 e-mail: [email protected] http://jms.imde.ac.cn DOI: 10.1007/s11629-015-3605-8 126 Abstract: The objective of this research was to assess the characteristics of seismic induced damage and the deformation patterns of pre-stressed cement-grouted cables that are used for rock slope stabilization projects subjected to quasi-static cyclic loading. The experimental configuration includes the installation of 15 pre-stressed cables in a slope model made of concrete blocks (theoretically rigid rock mass) on top of a pre-existing sliding surface. The study showed that: (i) The pre-stressed cables exhibited great seismic performance. Rapid displacement of the model blocks was observed after the complete loss of the initial pre-stress load under continued applied cyclic loads and exceedance of the state of equilibrium, which implies the higher the initial pre-stress load, the better the seismic performance of the rock anchor; (ii) The failure of the pre-stressed cables was due to fracture at the connection of the tendons and cable heads under cyclic loading. The sequence of failure had a distinct pattern. Failure was first observed at the upper row of cables, which experienced the most severe damage, including the ejection of cable heads. No evidence of de-bonding was observed during the cyclic loading; (iii) The stress distribution of the bond length for pre-stressed cables was highly non-uniform. High stress concentrations were observed at both the fixed end and the free end of the bond length both before and immediately after the state of equilibrium is exceeded. The results obtained can be used to evaluate the overall performance of pre-stressed rock anchors subject to seismic loading and their potential as rockfall prevention and stabilization measures. Keywords: Rock anchor; Prestressed cables; Cyclic loading; Slope stabilization; Seismic analysis Introduction Seismic activity has caused significant damage to existing geological disaster prevention and remedial measures, which in turn has compromised the stability of slopes and the reliability of hazard prevention structures worldwide. As the most widely used rock slope reinforcement measure, rock anchors have been used for decades in slope stabilization programs as temporary or permanent structural member to minimize the potential relaxation and loosening of the rock mass (Hoek and Bray 1981). In practice, Cyclic load testing of pre-stressed rock anchors for slope stabilization ZHENG Da 1 http://orcid.org/0000-0003-1640-7190; e-mail: [email protected] LIU Fang-zhou 2 http://orcid.org/0000-0001-5600-4017; e-mail: [email protected] JU Neng-pan 1 http://orcid.org/0000-0002-3159-1689; e-mail: [email protected] FROST J. David 2 http://orcid.org/0000-0001-9625-1258; e-mail: [email protected] HUANG Run-qiu 1 http://orcid.org/0000-0003-2560-4962; e-mail: [email protected] 1 State Key Laboratory of Geohazard Prevention and Geoenvironment Protection, Chengdu University of Technology, Chengdu 610059, China 2 School of Civil and Environmental Engineering, Georgia Institute of Technology, Atlanta 30318, GA, U.S.A. Citation: Zheng D, Liu FZ, Ju NP, et al. (2016) Cyclic load testing of pre-stressed rock anchors for slope stabilization, Journal of Mountain Science 13. DOI: 10.1007/s11629-015-3605-8 © Science Press and Institute of Mountain Hazards and Environment, CAS and Springer-Verlag Berlin Heidelberg 2016 Received: 25 June 2015 Accepted: 29 October 2015

Upload: others

Post on 14-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Cyclic load testing of pre-stressed rock anchors for slope …hgycg.cdut.edu.cn/data/upload/1563410315587.pdf · 2019-07-18 · engineering application of which dates back to the

J. Mt. Sci. (2016) 13(1): 126-136 e-mail: [email protected] http://jms.imde.ac.cn DOI: 10.1007/s11629-015-3605-8

126

Abstract: The objective of this research was to assess the characteristics of seismic induced damage and the deformation patterns of pre-stressed cement-grouted cables that are used for rock slope stabilization projects subjected to quasi-static cyclic loading. The experimental configuration includes the installation of 15 pre-stressed cables in a slope model made of concrete blocks (theoretically rigid rock mass) on top of a pre-existing sliding surface. The study showed that: (i) The pre-stressed cables exhibited great seismic performance. Rapid displacement of the model blocks was observed after the complete loss of the initial pre-stress load under continued applied cyclic loads and exceedance of the state of equilibrium, which implies the higher the initial pre-stress load, the better the seismic performance of the rock anchor; (ii) The failure of the pre-stressed cables was due to fracture at the connection of the tendons and cable heads under cyclic loading. The sequence of failure had a distinct pattern. Failure was first observed at the upper row of cables, which experienced the most severe damage, including the ejection of cable heads. No evidence of de-bonding was observed during the cyclic loading; (iii) The stress distribution of the bond length for pre-stressed cables was highly non-uniform.

High stress concentrations were observed at both the fixed end and the free end of the bond length both before and immediately after the state of equilibrium is exceeded. The results obtained can be used to evaluate the overall performance of pre-stressed rock anchors subject to seismic loading and their potential as rockfall prevention and stabilization measures. Keywords: Rock anchor; Prestressed cables; Cyclic loading; Slope stabilization; Seismic analysis

Introduction

Seismic activity has caused significant damage to existing geological disaster prevention and remedial measures, which in turn has compromised the stability of slopes and the reliability of hazard prevention structures worldwide. As the most widely used rock slope reinforcement measure, rock anchors have been used for decades in slope stabilization programs as temporary or permanent structural member to minimize the potential relaxation and loosening of the rock mass (Hoek and Bray 1981). In practice,

Cyclic load testing of pre-stressed rock anchors for slope

stabilization

ZHENG Da1 http://orcid.org/0000-0003-1640-7190; e-mail: [email protected]

LIU Fang-zhou2 http://orcid.org/0000-0001-5600-4017; e-mail: [email protected]

JU Neng-pan1 http://orcid.org/0000-0002-3159-1689; e-mail: [email protected]

FROST J. David 2 http://orcid.org/0000-0001-9625-1258; e-mail: [email protected]

HUANG Run-qiu1 http://orcid.org/0000-0003-2560-4962; e-mail: [email protected]

1 State Key Laboratory of Geohazard Prevention and Geoenvironment Protection, Chengdu University of Technology, Chengdu 610059, China

2 School of Civil and Environmental Engineering, Georgia Institute of Technology, Atlanta 30318, GA, U.S.A.

Citation: Zheng D, Liu FZ, Ju NP, et al. (2016) Cyclic load testing of pre-stressed rock anchors for slope stabilization, Journal of Mountain Science 13. DOI: 10.1007/s11629-015-3605-8

© Science Press and Institute of Mountain Hazards and Environment, CAS and Springer-Verlag Berlin Heidelberg 2016

Received: 25 June 2015 Accepted: 29 October 2015

Page 2: Cyclic load testing of pre-stressed rock anchors for slope …hgycg.cdut.edu.cn/data/upload/1563410315587.pdf · 2019-07-18 · engineering application of which dates back to the

J. Mt. Sci. (2016) 13(1): 126-136

127

rock anchors can be either tensioned or untensioned. An untensioned rock anchor is generally grouted over its full length and installed prior to excavation, and thus its capacity is mobilized upon the displacement of the reinforced rock mass. A tensioned rock anchor is installed across the potential sliding surface with the fixed end grouted and located in the intact rock mass behind the sliding surface, and thus stabilizes the rock mass by altering the normal and shear stress along the discontinuity (Wyllie and Norrish 1996). The tensioned rock anchor consists of a bonded length and an unbonded length of an anchor tendon and can be made of different materials. A tensioned rock anchor with strand tendons is referred to as the pre-stressed cable, the engineering application of which dates back to the early work for the improvement of the seismic stability of concrete dams.

Although pre-stressed cables have been used for decades to improve the seismic stability of rock slopes, the analysis and design of the cables is still largely based on the working and ultimate capacities obtained under static loading condition due to the lack of understanding on the behavior of prestressed cables under cyclic loading. Furthermore, the evaluation of the performance of pre-stressed cables after seismic events provides inadequate feedback regarding their stress-strain characteristics during the seismic loading, as the condition of the damaged cables are usually documented based on external indicators and replaced without assessment on the internal damage. Limited information on the behavior of pre-stressed cables under cyclic loading is available. Some general trends emerged from reviewing the early tests on repeated loading of plate anchors embedded in soils, and yielded the following conclusions: (i) The failure of anchors may occurred at load levels below the ultimate static pullout capacity; (ii) Repeated loading caused additional cumulative movement of the anchor; and (iii) The magnitude of the repeated loading is a governing factor in the service life of the anchor (Hanna 1982; Xanthakos 1991). Previous evaluations on the seismic damage of anchored bulkheads installed at ports indicated that the failures were primarily due to overloading of the anchors (Kitajima and Uwabe 1979). A vertical anchorage system in sand subject to cyclic loading

under tidal conditions was modelled in centrifuge test (Merrifield and Carey 1997). Field study on the repeated uplift loading of cement-grouted pre-stressed cables in rock indicated that the difference between the magnitude of the initial pre-stress load and the repeated load governed the service life of the cable (Benmokrane et al. 1995). Shake table tests have been widely used as a direct approach for assessing the seismic performance of slopes and retaining structures, but the analysis of the impact has often been concerned with the overall performance of the slope and/or the structure with limited or no specific study on the pre-stressed cables (Morin et al. 2002; Wartman et al. 2003; Ling et al. 2005; Lin and Wang 2006; Cheng 2008; Xu et al. 2010).

Pre-stressed cables are the most widely used technique for rock slope stabilization and rockfall prevention programs in China due to the rapid development of hydropower stations (Huang and Xu 2008; Huang 2009; Zheng et al. 2012). Prior to the Wenchuan Earthquake in 2008, the study primarily focused on the dynamic response of the pre-stressed cables under blasting (Lu 2000; Su and Zhang 2003; Yang et al. 2006). The severe damage caused by the widely distributed seismic-induced geohazards during the Wenchuan Earthquake emphasized the needs for exploiting the application of pre-stressed cables for seismic measures. However, the absence of large-scale laboratory experimental studies to investigate the seismic response of pre-stressed cable and their interaction with rock masses under cyclic loading resulted in their extrapolation to the seismic application often being based on numerical simulation and engineering judgment only.

Cyclic load testing has been used for decades to simulate the impact of seismic loading on structures. The tests usually employ a horizontal load with gradually increasing magnitude or displacement in successive cycles (Driver et al. 1998). The experimental study presented herein describes cyclic load testing on pre-stressed cables that were installed to reinforce a large-scale concrete block mass with in-plane discontinuities. The test offers the opportunity for detailed assessment on the stress distribution along the tendon and the interface as well as the failure process of the cable, which provides additional information to study the suitability of pre-stressed

Page 3: Cyclic load testing of pre-stressed rock anchors for slope …hgycg.cdut.edu.cn/data/upload/1563410315587.pdf · 2019-07-18 · engineering application of which dates back to the

J. Mt. Sci. (2

128

cables for s

1 Exper

The exKey LaborGeoenvironthe seismictypically inin Southwexperimentvariations and the fanchors upunder cyclisimulate aQingchuan(i.e. prototyand an oveangle of 60

Figure 1 Sdimensionascaled mod

2016) 13(1): 12

seismic appli

iment Des

xperiments wratory of Gnment Protecc response ofnstalled for rwest China.

t which arein the dynamfailure procpon the relaic loading. T

an existing pn in Sichuan

ype) has a wrall height of

0°. The proto

Schematic draal view (side w

del prior to the

26-136

ications.

sign and Se

were performGeohazard Pction (SKLGf pre-stressedockfall preveThe main

e of direct imic responsecesses of thaxation of thThe model wproject near Province. T

width of apprf 38 m with aotype compr

awings of thewalls of the moe test.

etup

med in the SPrevention P) to investigd cables thatention progrfeatures of interest are e characterishe pre-streshe sliding bwas designedr the countyThe actual slroximately 5an average slrises of layer

e scaled modeodel box are om

State and gate t are rams the the stics ssed

body d to y of lope

52 m lope rs of

sanin instEarrepcracTheongin groseisinteIntegroEar

con2.5 heigexcthe

el and pre-strmitted for clar

ndstone, whicthe area. Ntalled in therthquake with

ported after thcks that deve installationgoing. The sethat area,

ound motion smic parameensity level ensity (MMI

ound accelerrthquake Adm

A scaled nstructed in a m × 2 m) ght of the m

cluding the w overall lengt

ressed cables: rity); c, photo

ch is the typiNumerous pre prototype phout field mohe earthquak

veloped nearn of additionaeismic designas recomm zoning in C

eters associat VIII on tI) Scale withration (PGAministration

test modea rigid laboraas shown in

model is 2 m,walls of the m

th is 2 m. Th

a, elevation o of the laborat

ical geologicaprestressed c

prior to themonitoring. Fa

ke together wr the crest o

nal pre-stressn criteria fo

mended by tChina, are baated with an the Modifieh a correspo

A) of a 0. 2010).

el was desratory model n Figure 1. , and the ov

model box, is he dimension

and side-viewtory reaction w

al condition cables were Wenchuan ailures were with tension of the slope. sed cables is r structures the seismic ased on the earthquake ed Mercalli onding peak 25 (China

signed and box (3 m × The overall

verall width, 2.5 m while

ns of the test

w; b, three-wall and the

Page 4: Cyclic load testing of pre-stressed rock anchors for slope …hgycg.cdut.edu.cn/data/upload/1563410315587.pdf · 2019-07-18 · engineering application of which dates back to the

J. Mt. Sci. (2016) 13(1): 126-136

129

model are representative of the slope at 5% scale of the prototype. The model consists of four components including a group of 15 pre-stressed anchors, and a concrete base and top separated by a thin galvanized iron sheet. As depicted in Figure 1, the concrete base is fixed within the model box, whereas the concrete top (sliding body) with a vertical slope face designed for simplicity was cast inside a wood model box (Figure 1b) and placed above the concrete base. The concrete used to simulate the rock mass was proportioned as 1 (Portland Cement): 7 (medium sand with particle size ranges between 0.35 and 0.5 mm) with the addition of 300 kg water for 1 m3 cement/sand mixture.

The heights of the front and the back of the sliding body are 2.0 m and 0.35 m, respectively. The length and width are 2.0 m. The prestressed cables have bond lengths of 500 mm and unbonded lengths ranging from 700 mm to 1100 mm. The concrete top and base were designed to simulate the theoretical condition of rigid rock mass. A geological discontinuity was designed as the potential sliding surface in order to assess the performance of the prestressed cables in a single joint rock mass. The sliding surface strikes parallel to the slope face and dips to the front at an angle of 60°, which is simulated by the interbedded iron sheet. The bearing plates were placed on the sliding body and connected to a hydraulic actuator by a set of metal rings that permits the actuator to apply both tensile and compressive forces to the model.

The principles of geometric, kinematic and dynamic similarity are critical to the design and testing of physical models. The development of the law of similitude as used in geotechnical engineering progressed as the use of shaking tables gained wide popularity globally. The similitude theory adopted in this experimental study follows the same dimensional analysis that has been applied in many other studies using scaled models, in which the ratio of the material densities between the model and the prototype are designed to be unity in one-g scale tests (Iai 1989; Gibson 1997; Meymand

1998; Lin and Wang 2006). Using dimensional analysis reduces the engineering parameters to their fundamental units and the scaling relations between the prototype and model can be expressed in the form of a geometric scaling factor λ, and the ratios of the dimensionless parameters are set to be unity to meet the similarity requirements. The scaling factor λ applied in the test is 20. The scaling relations for the primary parameters are determined and shown in Table 1, and the resulting relationship of similarity between the prototype and model is presented in Table 2.

The assumption for the tests was that the sliding body reaches a state of equilibrium at a 0.25 , which represents the corresponding PGA for the aforementioned level of earthquake acceleration. The seismic loading is modeled as a cyclic horizontal force exerted on the sliding body based on the pseudo-static analysis defined as (Jibson 2011):

c ∙ W ∙ cosα ksinα ∙ tanϕW ∙ sinα kW ∙ cosα

(1)

where is the pseudo-static factor of safety, W is the weight of the sliding body, and α, ϕ and c are the slope angle, angle of friction, and cohesion of the failure surface, respectively. Area of the failure surface is represented by A, and k is the seismic coefficient defined as

k a / (2)

where a is the horizontal ground acceleration and is the gravitational acceleration. The uncertainty

in the magnitude of the earthquake and the associated a commonly result in the selection of the seismic coefficient that plays a decisive role in

Table 1 The law of similitude (ratio of prototype to model) in terms of the geometric scaling factor λ (after Meymand 1998). Derivations are presented in Appendix 1.

Density 1 Acceleration 1 Strain 1 Angle of friction 1 Poisson ratio 1 Length λ Mass λ3 Force λ3 Stress λ Time λ1/2 Stiffness λ2 Modulus λ Frequency λ-1/2 Cohesion λ Share wave velocity λ1/2 Table 2 The relationship of similarity between the prototype and model

Parameter Scale Prototype Model Slope Geometry L λ 52m(W) × 38m(H) 4m × 2.5m × 2m

Density ρ 1 1.80 – 2.42 g/cm3 1.978 g/cm3 Cohesion c λ 3 – 6 MPa 0.22 MPa Friction Angle ϕ 1 38° – 49° 45°

Cable Tensile Strength σ λ 7440 MPa 322.45 MPa

Page 5: Cyclic load testing of pre-stressed rock anchors for slope …hgycg.cdut.edu.cn/data/upload/1563410315587.pdf · 2019-07-18 · engineering application of which dates back to the

J. Mt. Sci. (2

130

the accuraccoefficient (Seed 1979California Kramer anThe value study wasaverage PGseismic resunique to The angle obe 30° usinvalues of (1).

The mgalvanized (length/widbetween thand the parametersthe iron she

The tythe tensioprojects. Tprojects in a strand thhelical formtypically 1strength is195 10 Gthe steel wAccordinglywas neededa requiredbased on t

Figure 2 Tafter groutpanel of thnot connec

2016) 13(1): 12

cy of the an has been dis9; Hynes-GDivision of

nd Smith 199of applied

s calculated GA in the stusponse of thany specificof the failureng an iterati until 1

measured thi iron sheet isdth) is 1.15, he inclined bconcrete bas of the failureet, were ϕ

ype and specned rock aThe tendon southwest C

hat comprisem. The diam15.24 mm s 1860 MPa

GPa, and thewire is typicy, a cable w

d to simulated ultimate te

the dimensi

The constructting (front vie

he wood box (hcted to the con

26-136

nalysis, and tscussed in va

Griffin and f Mines and97; Wyllie a in the expe based on

udy area. Thehe pre-stressc magnitudee surface waive approach1 was determ

ickness for ts 1 mm, andto cover thebottom of tase. The shre surface, as26.8° and c

cification ofanchor variens used fo

China are coms a group of

meter of a sinwith the u

a. The elaste maximum cally greater

with a diamee a 4-wire strensile strengional analysi

tion of the moew); b, wood bhighlighted in ncrete based or

the value of arious literatu

Franklin 19d Geology 19and Mah 20eriments in the estimae analysis fored cables is

e of earthquas determineh using diffemined using

the interbed the aspect r

e area of conhe sliding bhear resistas representedc 4.9 kPa. f the tendones for diffeor stabilizammonly madf 4 wires spungle steel wirultimate tenic modulus, tensile forcr than 260 eter of 2.98 and system w

gth of 372 Mis. Tensile t

odel: a, iron shbox for castin yellow) was rer to the model

f the ures 984; 997; 04). this

ated r the not

uake. ed to erent Eq.

dded ratio ntact body ance d by

n for rent

ation de of un in re is nsile ,E

ce of kN. mm with MPa tests

werinclidencopselein streten

theholconmmby holdiamon folltheenvwhiconanylengafteappcuranddev

steetheadjuwhewas

heet as the fang the sliding emoved after tl box.

a

re conducteluding lead,ntify the mo

pper strand ected to reprthe prototypength of σsile force of F

The constru cast of cones (20 mm

ncrete base am. The cables

injecting thees through meter). The the surface owed by the base. The u

veloped by aich formed a

ncrete was cay developmength and the er casting plication of ring time used the slidingvelopment of

Each cableel shim (100 sliding bousting the loere the magns recorded b

ilure surface cbody with prethe casting of

ed for diffe copper, aluost appropri (4 mm d

resent the actpe, which h

322.45F 2026uction of thencrete base

m diameter) at an angle os were groutee cement uni

hollow alum iron sheet w of the conc wood box (Funbonded lea 20 mm diaa liner insideasted in the wnt of bond st concrete. Ththe slidingpre-stress

ed for the cong body, weref strength ande head was l0 mm diameody. The caoad sensor cnitude of the by the senso

covers the sure-installed cab the sliding bo

erent cable uminum, aniate materiadiameter) s

ctual strand shas the ultim

MPa and 6 N. e model was s in layers. T were drilleof 18° to a deed over the b

niformly intominum tube

was subsequecrete base (

Figure 2b) poength of the ameter alume the sliding wood box andtrength betwhe liners weg body priloads the c

ncrete, for boe 15 days to d durability.locked by a

eter) at the fables were connected to initial pre-s

or and contr

rface of the coble liners; No

ody and the wo

materials, nd steel, to al. A 2-wire system was system used mate tensile

maximum

started with The anchor ed into the epth of 500 bond length the anchor es ( 12 mm ently placed (Figure 2a), ositioned on cables was

minum tube, body as the d prevented

ween the free ere removed ior to the cables. The oth the base ensure the 5 mm thin front face of

loaded by o the head, tress load P rolled to be

oncrete base te the front

ood box was

b

Page 6: Cyclic load testing of pre-stressed rock anchors for slope …hgycg.cdut.edu.cn/data/upload/1563410315587.pdf · 2019-07-18 · engineering application of which dates back to the

J. Mt. Sci. (2016) 13(1): 126-136

131

200 kN. Four observational cables were monitored throughout the test to provide quantitative evidence to explore the analytical models of the structure. Load sensors were connected to the cable heads with 62 strain gauges installed on the surface of the observational cables (5 were damaged in the grouting process). The strain gauges were installed at 5 cm intervals over the bond length and 10 cm, 15 cm and 20 cm intervals over the unbonded length.

The horizontal loads applied to the model slope by the hydraulic actuator were resisted by a laboratory reaction wall. The horizontal loads were exerted on the sliding body through the bearing plates. The conventional application of quasi-static cyclic loading can be controlled by either load or displacement, of which the load-controlled cyclic loading is often used prior to the development of joints and/or cracks in the rock mass and is followed by displacement-controlled loading. Following the same line of reasoning, displacement-controlled loading was considered sufficient for this test program due to the presence of a fully developed sliding surface. An alternating load- and displacement-controlled cyclic loading was applied, as the application of load-controlled loading permitted direct assessment on the prestressed cables in light of the equivalent earthquake intensity levels. The subsequent displacement-controlled loading pull the sliding body back to its original location to ensure the recorded displacement remained positive throughout the experiment.

2 Application of Loads and Model Behavior

The load-controlled cyclic loading was designed to perform each cycle with an increment of 5 kN, which simulates a step increase of PGA starting from 0.05 in an idealized earthquake. No apparent deformation of the model and pre-stressed cables was observed as the first cycle started with the application of 5 kN horizontal load (a 0.05 ). A displacement of 0.1 mm for the sliding body was measured in the load-controlled loading excursion, and the sliding body was subsequently pulled back to the origin in the displacement-controlled loading excursion.

In cycle 5 (a 0.25 ), the equilibrium was exceeded. The displacement was measured as 1.19 mm with light cracking noise from the cable heads as the result of stress concentrations.

In cycle 6 (a 0.30 ), a consistent stress concentration was postulated at the cable heads, as strong cracking noises were detected from the cable heads in both the load-controlled and displacement-controlled loading process. A displacement of 2.24 mm was achieved with a rapid increase in the axial force measured in the pre-stressed cables. A number of strain gauges were damaged by the end of this cycle.

In cycle 7 (a 0.35 ), a displacement of 3.08 mm was reached. Surface peeling was first observed on the front face of the sliding body with intensive cracking noises coming from the cable heads. Significant changes in the axial forces were reported throughout this cycle. More than 20% of the strain gauges were damaged. Small partings and cracks (max. length < 10 mm) were formed during this cycle, but did not propagate during subsequent cycles.

As loading continued, the increase in the displacement of the sliding body and the axial load in the pre-stressed cables became more pronounced during each of the remaining cycles. During cycle 10 (a 0.50 ), a displacement of 16.55 mm was recorded with more than 50% of the strain gauges damaged. Failure of the pre-stressed cables was observed during the load-controlled loading excursion of cycle 13 (a 0.65 ). The measured displacement of the sliding body exceeded 143 mm. All of the failures involved damage of the cable heads, including four of the cable heads which were ejected from the model. Five of the cable heads were detached from the model and the connections of the rest of the cable heads were loosened. Small partings and cracks (max. length < 20 mm) could be seen on the surface of the sliding body, although no propagations were observed during the loading cycles, which suggest the development of cracks have a negligible effect on the behavior of the model.

3 Results and Failure Mode

The fracture at the connection between the

Page 7: Cyclic load testing of pre-stressed rock anchors for slope …hgycg.cdut.edu.cn/data/upload/1563410315587.pdf · 2019-07-18 · engineering application of which dates back to the

J. Mt. Sci. (2

132

cable headloading excobservationfailure was3b, followeA4, B3 anresulted intravelled a subsequentC4, but thedue to theCable head(travel dist~0.5 m). loosening which causfront face o

The sethe upper tgroup. Theconnectiondamage ongenerally mNo de-bonstressed cab

The dias a key inIt was meathe actuatocategorizeddisplacemeapparent dwas observon the preas static eq

Figure 3monitoring

a

2016) 13(1): 12

ds and the tecursion of cynal cables ars first observed by the dend B4. The n the eject horizontal tt failure of Ae travel dist

e additional d ejections tance ~1.6 mFailure occat the connsed both of of the model.equence of fato the lowere severity of

ns followed n the upper

much greaternding was ob

bles. isplacement

ndicator in thasured director. The damd into fouent (Figure displacement ved and no sie-stressed cabquilibrium w

3 Pre- and pog cells and sen

26-136

endons occuycle 13. The re shown in

ved in A1 as setachment of

subsequenttion of cabtravel distanA5 caused a tance was on weight of twere also om) and C3

curred at B5nections of t

the heads to.

ailure was apr rows of pref damage of the samer rows of car than that ofbserved for

of a sliding he analysis otly in the premage of the ur phases 4). During (max. displaigns of damable. Starting

was exceeded

ost-test imagensors; b, failur

urred during locations of Figure 3a. shown in Figf cable head rupture of

ble head whce of 1.7 m. similar resulnly 0.4 m lithe load senobserved for

(travel dista5 and C5 whe cable heo hang over

parent, i.e. fe-stressed caf the cable he pattern. able group f the lower roany of the p

body can seof slope stabiesent study f models canbased on

g Phase I, acement < 1 age were evidg from Phased, the additio

es of the prere of prestress

the f the The

gure ds of f C4 hich The lt as ikely nsor. r A3 ance with

eads, r the

from ables head The was

ows. pre-

erve ility. from n be

the no mm) dent e II, onal

shecabAlthequdispthapottheconincrlast

lengunbconexctestof uniconfreealonhighwhesimfullHigandstretheendendlessgrofixe

estressed cablsed cables duri

b

ear resistancble was mobhough the sl

uilibrium anplacement re

at the apptentially impr distinct sl

ntrolled loadrease of dispts until the fa

Strain concgth with nobonded lengntrolled andcursions (Figt, the stress a fully gro

iform under ncentrates at e end (Farmng the pre-shly non-unereas the st

milarity comply grouted rogh strain cond free ends essed cables stress conce

d (on averaged) of the bons pronounce

outed rock aed end).

les. a, the obing cycle 13.

b

ce introducebilized to relope was unsnalysis, theemained closplication ofroved the staliding surfa

ding excursioplacement cailure of all thcentration iso significant gth of the cad displacemgure 5). Base distributionuted rock a static loadi the fixed en

mer 1975). Tstressed cabliform undetrain concenpared to thatock anchor incentration of the bond. However, entrations ate about 30% d length in aed comparenchor (< 20

bservational c

ed by the esist the dristable basede rate of se to linear. Tf pre-stressability of a slace. During on of cycle can be identhe pre-stresss evident in strain chanable during

ment-controlled on the stan along the banchor is hing, whereas

nd with low sThe strain le was also fer cyclic lontration exht of the bondin a static lowas found a

ded section the different the fixed a of the stressa pre-stressee to that o0% of the st

cables with a

prestressed iving force.

d on a limit-change of

This implies sed cables lope despite the load-13, a rapid

tified which sed cables. the bonded

nges in the both load-ed loading atic loading bond length highly non-s the stress stress at the distribution found to be

oad testing, hibited high d length of a oading test. at the fixed of the pre-

nce between and the free at the fixed

ed cable was of the fully tress at the

a variety of

Page 8: Cyclic load testing of pre-stressed rock anchors for slope …hgycg.cdut.edu.cn/data/upload/1563410315587.pdf · 2019-07-18 · engineering application of which dates back to the

The stwas affectecycle 5. Tlength failecycle 6 withstrain gaugstrain cudistributionimmediatelequilibriumnear the heinconsistenfracture atcable headaway frombeen suffic

Figure 4 controlled l

Figure 5 Sload-contro

train distribued by the daThe strain ded to demonh null data inges. It is rea

urves herein of a pre-ly after

m. No strainead of the prnt with the t the conne

ds. The closem the cable cient distance

Displacemenloading excurs

Strain distribuolled loading e

ution in theamage of stradistribution nstrate the snput from theasonable to pin represen-stressed caexceeding n concentratrestressed caobserved fa

ection betweest strain gahead, whiche to capture

nt of sliding sion of each cy

utions along prexcursion of ea

e bonded lenain gauges ain the bon

same trend ae majority ofpropose thatnt the stable before

the state tion was fo

ables, which ailure mode, een tendon auge was 25h may not hany pronoun

body at endycle.

restressed cabach cycle prior

ngth after nded after f the t the train and

of ound was i.e. and

5 cm have nced

themax#1 wcapThithesuswhiunbin tloadgrecabturn

d of the load

ble #1 during tr to cycle 11.

changTh

for bofound displaexcurscontroimpliegreatecablesunidir

Thdirect initial the observof P imkN) as(Fstress 12.1%,respecof thestage. for a(Benmwas a well asloadinin FigoccurrThe observwhichno lon

The maxim observatioximum tensiwas less than

pacity of the sis implies tha upper row ceptible to ich may bebonded lengtturn the greading. Additioater cumulat

bles than the n accelerates

d-

the

J. Mt

es in the strahe strain of

oth bond and to be cement-contsion comparolled loadines that theer deformati than

rectional loadhe changes i reflections pre-stress l

pre-stressedvational cablmmediately as shown in F

30 kN), t load from c, 17.3%, 23.ctively, whiche initial pre- Similar to n in-situ r

mokrane et a function of ts the amplitu

ng for pre-strgure 6. A red after cycchange excvational cabl indicated th

nger effectivemum axial lo

nal cables ile force capan 50% of thestrand systemat the pre-str of the cabl

damage due partly attth of the cablater elongatioonally, the cytive deforma unidirections the damage

t. Sci. (2016) 1

ain at the cabf the pre-strd unbonded

greater dtrolled re to duringng excursie cyclic loaion in the p

the cords. in the axial loon the chan

loads P . Thed loads les were lesafter cycle 5 Figure 6. Duthe changes cable #1 to .9%, and 27h indicate a g-stress load the findingsrepeated loal. 1995), ththe number ude of the aptressed cable

rapid pre-ycle 8 (Fceeded 100les by the endhat pre-stres

e in the systemoads prior to

were less acities. The loe maximum tm as shown ressed cablesle group ma

during the tributed to les in the uppon induced u

cyclic loadingation in the pnal loading de of the cable

3(1): 126-136

133

ble heads. ressed cable length was

during the loading

g the load-on, which ads caused pre-stressed rresponding

oads are the nges of the changes of

for the s than 10% (F 25 ring cycle 6 of the pre-#4 reached

7.25% of P , gradual loss up to this s presented oading test he loss of P of cycles as pplied cyclic es as shown -stress loss

40 kN). 0% for all

d of cycle 9, ss load was m. o failure for

than their oad in cable tensile force in Figure 6. s located on ay be more earthquake, the longer

per row and under cyclic g may cause pre-stressed does, and in es.

Page 9: Cyclic load testing of pre-stressed rock anchors for slope …hgycg.cdut.edu.cn/data/upload/1563410315587.pdf · 2019-07-18 · engineering application of which dates back to the

J. Mt. Sci. (2

134

4 Discu

Numerconducted interactionsuch as earthquakein the loaincreasing lead to th(Driver et aadopted insimulate tinfluence desired accin the labknowledge intensity orsequence dloading hcomplexityThe loadintest in lighrate of the cwhich permdata acquiunforeseenirreversible

The usimulation

Figure 6 Cthe second cycle.

Axi

al lo

ad

2016) 13(1): 12

ssion

rous quasi-s in geotechni

n between sopiles and

e-type loadinading sequen load cycle ahe test resal. 1998). Alt

n the experimthe typical on the stru

curacy, they boratory env is requiredr the capacit

does not relyhistory, whiy for the cang excursionht of the syscyclic loadinmits sufficieisition as w

n problems e damage to tuse of a s of complex

Change of axi loading excur

26-136

static cyclic ical engineeroil and struc

anchors ung. Howevernce betweenand actual esults being though the loments in this

seismic loucture mem offer two mvironment.

d either for ty of the systy on the inpuich reduces

andidate strun can be altestem respon

ng can be defient time to well as respduring the the test specscaled mode systems un

Loa

ial load negatrsion (i.e. disp

tests have bring to studyctural membunder idealr, the differen the graduearthquake m

unconservaoading seques study may ading and

mbers with major advanta

First, no pthe earthqu

em. The loadut of earthqus the loaducture memered during

nse. Second, ined by the u ensure reliponding to

test to previmen. el permits der a contro

ading

ive number oplacement-con

been y the bers, lized ence ually may ative ence

y not the the

ages prior uake ding uake ding

mber. the the

user, able any

vent

the olled

for

simsurwasmatnatimpthedesstreper

laboandtheAn preinstcorloadcabfor rocdesreqlocathemathe

on loading axintrolled loadi

modificationThe concre

mulate intact face. Even ths not explicitterial for th

turally not portant to co prototype r

sign of slopessed cables,rformance of

The constroratory tests

d the model c displaceme exact dup

eferred for cotalled presrelations bed and the ult

bles were esta exploring thk anchors in

sign of the onquired for boation of the experimennuscript fail pre-stressed

is represents ng) for each

environmthe phencannot bthe protoThe resmodels predictionperformacables, wcalibratioanalytic study on rock anstressed cslope stacan finterpretafailure tydifferent which ma

n on the currete of the slo rock masseshough the datly consideredhe rock mas

homogenoonsider the prock mass, spe stabilizat, as it may c the pre-stresuction of the

s consumed acannot be rent occurringlication of

onducting anstressed catween the atimate staticablished. Addhe seismic ren a laboratongoing experoth the insta

strain gaugental resultsled to captud cable head

ment, especnomena beibe achieved otype (Meymsults from

provide qns of th

ance of which can bon benchm

models fr the seismic

nchors. For cables impleabilization, facilitate ation on thype and pat earthquakeay be used asrent measureope model ws separated bamage of thed in the expess in the p

ous. Therefpossibility ofsuch as cracktion project compromise ssed cables. e scaled moa great amou

e-used after ag at the slidi

the model n uplift staticables. Theramplitude oc load of the ditional workesponse of u

ory environmriments, impallation methes. As previos described

ure the displds due to the

ially when ing studied ‘at-will’ in

mand 1998). the scale

quantitative he seismic

prestressed be used as marks for rom future response of the pre-emented for the results qualitative

he potential ttern under e intensity, s a guideline e. was made to

by a sliding e rock mass eriment, the prototype is fore, it is f damage of king, in the with pre- the seismic dels for the unt of time, a test due to ing surface. would be c test on the refore, no f the cyclic prestressed k is ongoing untensioned

ment. In the rovement is

hod and the ously noted, d in this lacement of e absence of

Page 10: Cyclic load testing of pre-stressed rock anchors for slope …hgycg.cdut.edu.cn/data/upload/1563410315587.pdf · 2019-07-18 · engineering application of which dates back to the

J. Mt. Sci. (2016) 13(1): 126-136

135

strain gauges near the connections between the tendons and cable heads.

One of the limitations of pseudo-static analysis, is the assumption of considering the earthquake load as a permanent unidirectional force and results in the analysis being conservative (Jibson 2011). Although the possibility of failure cannot be judged from limit-equilibrium analysis, the potential effectiveness of pre-stressed cables in slope stabilization was clearly demonstrated by the results of the experiment.

5 Summary and Conclusions

A quasi-static cyclic loading test was performed on 15 pre-stressed cables installed on a scaled rock slope model with a distinct planar sliding surface. The scaled model was constructed using the dimensional analysis to closely simulate an actual slope from an ongoing stabilization project in China. The strand system of the cables was prestressed with P 200 N. The loading excursion of the cyclic loading was controlled by both load and displacement with a step increase of 5 kN to simulate an idealized earthquake load. The state of equilibrium was set at F 25 kN based on the result of a pseudo-static analysis. Prior to the failure of the test model, high stress concentration were observed at the fixed end of the bonded section of the prestressed cables.

The pre-stressed cables in the test model exhibited realistic and very good performance. The change of P and the displacement behavior of the model indicated that rapid displacement of rock slope occurred after the complete loss of the initial pre-stress load. This phenomenon implies that the application of pre-stress loads can improve the service life of a rock anchor subject to cyclic load, even after exceeding the state of equilibrium and the amplitude of the cyclic load can be much greater than the initial pre-stress load. The higher the initial pre-stress load, the greater the seismic performance of the rock anchors. Therefore, the pre-stressed cables can serve as an effective measure for stabilizing rock slopes under seismic loading.

The failure mode of the pre-stressed cables

revealed that the connection between the tendons and the cable heads may be more vulnerable under cyclic loading. The sequence of failure occurred from the upper to the lower rows of the cable group. The damage of cables was also found to be more severe on the upper row. No debonding was generated in the experiment, but since the mechanism of bonding interaction of the pre-stressed cable – grouting material – rock mass remains unclear, the bonding effect in the bond length of the rock anchor cannot be neglected under cyclic loading.

The stress distribution along the bond length of pre-stressed cables was found to be highly non-uniform under cyclic loading. High stress concentrations were observed at both the fixed end and the free end (averaging 30% of the stress at the fixed end) of the bonded length before and immediately after exceeding the state of equilibrium. The stress distribution along the pre-stressed cable was not fully captured in the late stage of the experiment due to failure of the strain gauges. No significant stress concentrations along the unbonded length of the cable were recorded with the available strain gauges located 25 cm away from the cable head, but the failure of the cable heads implies that high stress concentrations may be occurring at the connection between the tendons and cable heads.

Acknowledgements

This study is financially supported by the National Basic Research Program of China (973 Program) (Grant No. 2013CB733202), the National Natural Science Foundation of China (Grant No.41102191), the State Key Laboratory of Geohazard Prevention and Geoenvironment Protection (Chengdu University of Technology) (Grant No. SKLGP2011Z019), and the National Natural Science Foundation of China (Grant No. 11670589).

Electronic Supplementary Material: Supplementary material (Appendix 1) is available in the online version of this article at http://dx.doi.org./10.1007/s11629-015-3605-8

Page 11: Cyclic load testing of pre-stressed rock anchors for slope …hgycg.cdut.edu.cn/data/upload/1563410315587.pdf · 2019-07-18 · engineering application of which dates back to the

J. Mt. Sci. (2016) 13(1): 126-136

136

References

Benmokrane B, Chekired M, Xu H, Ballivy G (1995) Behavior of grouted anchors subjected to repeated loadings in field. Journal of Geotechnical Engineering 121:413-420. DOI: 10.1061/(ASCE)0733-9410(1995)121:5(413)

California Division of Mines and Geology (1997) Guidelines for evaluating and mitigating seismic hazards in California. California Division of Mines and Geology Special Publication.

Cheng CT (2008) Shaking table tests of a self-centering designed bridge substructure. Engineering Structures 30: 3426-3433.

China Earthquake Administration (2010) Seismic Ground Motion Parameter Zonation Map of China (GB18306-2001).

Driver BRG, Kulak GL, Kennedy DJL, Elwi AE (1998). Cyclic test of four-story steel plate shear wall. Journal of Structural Engineering 124: 112-120.

Farmer IW (1975) Stress distribution along a resin grouted rock anchor. International Journal of Rock Mechanics and Mining Sciences & Geomechanics Abstracts 12:347-351. DOI: 10.1016/0148-9062(75)90168-0

Gibson AD (1997) Physical scale modeling of geotechnical structures at one-G. Ph.D. Thesis. California Institute of Technology.

Hanna TH (1982) Foundations in tension-ground anchors. Trans. Tech. Publications/McGraw Hill Book Co., Clausthal-Zellerfeld, West Germany.

Hoek E, Bray JW (1981) Rock slope engineering. Institutet of Mining and Metallurgy, London, UK.

Huang RQ (2009) Some catastrophic landslides since the twentieth century in the southwest of China. Landslides 6:69-81. DOI: 10.1007/s10346-009-0142-y

Huang RQ, Xu Q (2008) Catastrophic landslides in China. Beijing: Science Press. pp 243, 424.

Hynes-Griffin ME, Franklin AG (1984) Rationalizing the Seismic Coefficient Method. (No. WES/MP/GL-84-13). Army Engineer Waterways Experiment Station Vicksburg MS Geotechnical Lab.

Iai S (1989) Similitude for shaking table tests on soil-structure-fluid model in 1g gravitational field. Soils and Foundations 29:105-118.

Jibson RW (2011) Methods for assessing the stability of slopes during earthquakes—A retrospective. Engineering Geoleology 122:43-50. DOI: 10.1016/j.enggeo.2010.09.017

Kitajima S, Uwabe T (1979) Analysis of seismic damage in anchored sheet-piling bulkheads. Report of the Japanese Port and Harbor Research Institute 18:67-130.

Kramer SL, Smith MW (1997) Modified newmark model for seismic displacements of compliant slopes. Journal of Geotechnical and Geoenvironmental Engineering 123: 635-644.

Lin ML, Wang KL (2006) Seismic slope behavior in a large-scale shaking table model test. Engineering Geology 86:118-133.

Ling HI, Mohri Y, Leshchinsky D, et al. (2005) Large-scale shaking table tests on modular-block reinforced soil retaining walls. Journal of Geotechnical and Geoenvironmental Engineering, American Society of Civil Engineers 131:465-476.

Lu X (2000) Influence of Rock High Slope Explosive Excavation on Anchored Installations. Blasting 17:147-151. (In Chinese)

Merrifield CM, Carey JM (1997) Response of Vertical Anchorages to Cyclic Loading, Modelled in the Centrifuge. Gr. Anchorages Anchored Struct. Proceedings of the International Conference Organized by the Institution of Civil Engineers and Held in London, UK, 20-21 March 1997. American Society of Civil Engineers. p 450.

Meymand PJ (1998) Shaking table scale model tests of nonlinear soil-pile-superstructure interaction in soft clay. Ph.D. Thesis. University of California, Berkeley.

Morin PB, Léger P, Tinawi R (2002) Seismic behavior of post-tensioned gravity dams: shake table experiments and numerical simulations. Journal of Structural Engineering 128:140-152.

Seed H (1979) Considerations in the earthquake-resistant design of earth and rockfill dams. Geotechnique 29: 215-263.

Su H, Zhang J (2003) Analysis on Blasting Vibration Effect on Prestressed Cable of High Slope in Zipingpu Project. Chinese Journal of Rock Mechanics and Engineering 22:6-8. (In Chinese)

Wartman J, Bray JD, Seed RB (2003) Inclined plane studies of the Newmark sliding block procedure. Journal of Geotechnical and Geoenvironmental Engineering 129: 673-684.

Wyllie DC, Mah C (2004) Rock slope engineering. CRC Press, Boca Raton, Florida.

Wyllie DC, Norrish NI (1996) Landslides: Investigation and Mitigation. Transportation Research Board Special Report 247.

Xanthakos PP (1991) Ground anchors and anchored structures. John Wiley & Sons, Hoboken, New Jersey, USA.

Xu Q, Liu H, Zou W, et al. (2010) Large scale shaking table test study of acceleration dynamic responses characteristics of slopes. Chinese Journal of Rock Mechanics and Engineering 29:2420-2428. (In Chinese)

Yang S, Liang B, Gu J, et al. (2006) Research on Characteristics of Prestress Change of Anchorage Cable in Anti-Explosion Model Test of Anchored Cavern. Chinese Journal of Rock Mechanics and Engineering 25:3749-3756. (In Chinese)

Zheng W, Zhuang X, Cai Y (2012) On the seismic stability analysis of reinforced rock slope and optimization of prestressed cables. Frontiers of Structural and Civil Engineering 6:132-146.