Page 1: Cycle Time Mathematics

Cycle Time Mathematics

Presented at KLRAT 2013 [email protected]

Page 2: Cycle Time Mathematics

Commercial in confidence2

Conclusions

• Forecasting using cycle time is proving useful• Cycle time follows a Weibull/Lognormal shape

– We can estimate the actual distribution with just a minimum and a maximum guess (initially)

• Controlling the shape of the distribution (narrowing) improves predictability

• Proposing a way of identifying what risks and delays will have the greatest impact…

Page 3: Cycle Time Mathematics

Prediction Intervals

Page 4: Cycle Time Mathematics

Actual Maximum

Actual Minimum

1

3

2

Q. What is the chance of the 4th sample being between the range seen after the first three samples? (no duplicates, uniform distribution, picked at random)

4

Page 5: Cycle Time Mathematics

Actual Maximum

Actual Minimum

1

3

2

4

Highest sample

Lowest sample

Q. What is the chance of the 4th sample being between the range seen after the first three samples? (no duplicates, uniform distribution, picked at random)

?

?

?

?

Page 6: Cycle Time Mathematics

Actual Maximum

Actual Minimum

1

3

2

4

25% chance higher than highest seen

25% lower than highest and higher than second highest

25% higher than lowest and lower than second lowest

25% lower than lowest seen

Highest sample

Lowest sample

Q. What is the chance of the 4th sample being between the range seen after the first three samples? (no duplicates, uniform distribution, picked at random)

A. 50%

% = (1 - (1 / n – 1)) * 100

Page 7: Cycle Time Mathematics

Actual Maximum

Actual Minimum

1

3

2

12

5% chance higher than highest seen

5% lower than lowest seen

Highest sample

Lowest sample

Q. What is the chance of the 12th sample being between the range seen after the first three samples? (no duplicates, uniform distribution, picked at random)

?

?

A. 90%

% = (1 - (1 / n – 1)) * 100

4

5

6

7

8

9

10

11

Page 8: Cycle Time Mathematics

# Prior Samples Prediction Next Sample Within Prior Sample Range

3 50%4 67%5 75%6 80%7 83%8 86%9 88%

10 89%11 90%12 91%13 92%15 93%17 94%20 95%

Halved the risk with 3 samples

Page 9: Cycle Time Mathematics

Monte Carlo

Page 10: Cycle Time Mathematics

Commercial in confidence10

If a measurement changes over time or is different each time you measure it, it is a

DISTRIBUTION

Can’t apply normal mathematical operators….

Page 11: Cycle Time Mathematics

Commercial in confidence11

Cycle Time Forecasting

1. Easy to Capture Metric

3. Follows Known Distribution Pattern

2. Forecasting using Historical Data

(even a little)

4. Forecast at Project or Feature

or Story Level

Page 12: Cycle Time Mathematics

Sum Random Numbers

25112943342631452227

31436545

87

34735448

1912242721

39

202329

187410295Sum:

…..

Historical Story Lead Time Trend

Days To Complete

Basic Cycle Time Forecast Monte Carlo Process

1. Gather historical story lead-times2. Build a set of random numbers based on pattern3. Sum a random number for each remaining story to build a single outcome4. Repeat many times to find the likelihood (odds) to build a pattern of likelihood outcomes

𝑇𝑜𝑡𝑎𝑙𝐷𝑎𝑦𝑠❑=𝑆𝑢𝑚 (𝑆𝑡𝑜𝑟𝑦𝑛×𝑅𝑎𝑛𝑑𝑜𝑚𝑛)

𝐸𝑓𝑓𝑜𝑟𝑡

Page 13: Cycle Time Mathematics

How I Quantify Lead Time Reduction

Lead Time # Stories / Year Throughput Benefit

Current 6 0%

10% Decrease 7 17% More

20% Decrease 8 33% More

When no ROI is easily discerned (maintenance teams?)

Even a small decrease in Cycle Time has a increased impact on throughput over a year..

Page 14: Cycle Time Mathematics

Cycle Time

Forecast Date Forecast Cost

Cash flow to EOY14(cost saving + revenue)

Benefit

Current 15-Jul-2014 $1,000,000 $0 + $60,000 = $60,000 0%10% Decrease 27-May-2014 $912,500 $87,500 + $90,000 =

$177,500296% Better

20% Decrease 04-Apr-2014 $820,000 $120,000 + $145,000 =

$265,000442% Better

Month Revenue

April $30,000

May $25,000

June $20,000

July $20,000

Aug-Dec $10,000

Revenue Estimates for product:

How I Quantify Cycle Time Reduction

Even a small decrease in Cycle Time can have huge a benefit on

cash flow over time.

This example shows the cost of missing a seasonal uptick in summer sales (revenue estimates shown to the left). Cost per work day is calculated at $2,500 day.

Page 15: Cycle Time Mathematics

Shape and Impact of Cycle-Time & Scope

Page 16: Cycle Time Mathematics

Commercial in confidence16

Probability Density Function

Histogram Gamma (3P) Lognormal Rayleigh Weibull

x1301201101009080706050403020100-10

f(x)

0.32

0.28

0.24

0.2

0.16

0.12

0.08

0.04

0

Note: Histogram from actual data

Page 17: Cycle Time Mathematics

Commercial in confidence17

Probability Density Function

Histogram Weibull

x1301201101009080706050403020100-10

f(x)

0.32

0.28

0.24

0.2

0.16

0.12

0.08

0.04

0

Page 18: Cycle Time Mathematics

Commercial in confidence18

Likelihood…

Page 19: Cycle Time Mathematics

Total Story Lead Time

30 days

Story / Feature Inception5 Days

Waiting in Backlog25 days

System Regression Testing & Staging 5 Days

Waiting for Release Window5 Days

“Active Development”30 days

Pre Work

30 days

Post Work

10 days

Page 20: Cycle Time Mathematics

Commercial in confidence20

Binary PermutationsRisk1

Risk2

Risk3

Risk 4

Risk 5

Risk 6

Risk 7

Risk 8

Risk 9

Risk 10

No No No No No No No No No No

No No No No No No No No No Yes

No No No No No No No No Yes No

No No No No No No No No Yes Yes

No No No No No No No Yes No No

… … … … … …

Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes

Page 21: Cycle Time Mathematics

Why Weibull

• Now for some Math – I know, I’m excited too!

• Simple Model• All units of work between 1 and 3 days• A unit of work can be a task, story, feature, project• Base Scope of 50 units of work – Always Normal• 5 Delays / Risks, each with

– 25% Likelihood of occurring– 10 units of work (same as 20% scope increase each)

Page 22: Cycle Time Mathematics

Normal, or it will be after a few

thousand more simulations

Page 23: Cycle Time Mathematics

Base + 1 Delay

Page 24: Cycle Time Mathematics

Base + 2 Delays

Page 25: Cycle Time Mathematics

Base + 3 Delays

Page 26: Cycle Time Mathematics

Base + 4 Delays

Page 27: Cycle Time Mathematics

Base + 5 Delays

Page 28: Cycle Time Mathematics

Commercial in confidence28

Probability Density Function

Histogram Weibull

x1201101009080706050403020100

f(x)

0.28

0.24

0.2

0.16

0.12

0.08

0.04

0

Scale – How Wide in Range. Related to the

Upper Bound. *Rough* Guess: (High – Low) / 4

Shape – How Fat the distribution. 1.5 is a good starting point.

Location – The Lower Bound

KEY POINT: WITH JUST MIN AND MAX THE CURVE CAN BE INFERRED

Page 29: Cycle Time Mathematics
Page 30: Cycle Time Mathematics

Changing Cycle Time Shape

Page 31: Cycle Time Mathematics

Commercial in confidence31

Probability Density Function

Weibull (1.2; 25)

x8880726456484032241680

f(x)

0.028

0.024

0.02

0.016

0.012

0.008

0.004

0

Probability Density Function

Weibull (1.5; 30)

x8880726456484032241680

f(x)

0.026

0.024

0.022

0.02

0.018

0.016

0.014

0.012

0.01

0.008

0.006

0.004

0.002

0

Teams following this curve WILL be able to predict more

predictability because forecast range will be tighter

When forecasting, the wider the curve, the MORE higher

value numbers will occur

Page 32: Cycle Time Mathematics

Commercial in confidence32

Binary PermutationsRisk1

Risk2

Risk3

Risk 4

Risk 5

Risk 6

Risk 7

Risk 8

Risk 9

Risk 10

No No No No No No No No No No

No No No No No No No No No Yes

No No No No No No No No Yes No

No No No No No No No No Yes Yes

No No No No No No No Yes No No

… … … … … …

Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes

EVERY RISK OR DELAY YOU CAN REMOVE REDUCE COMBINATIONS BY 2n

Page 33: Cycle Time Mathematics

Commercial in confidence33

Order of Priority for Improvement

• Prioritized list of blockers and delay states• Balanced to include most frequent & biggest delay• Order Risks and Delays by weighted impact

Impact = Frequency Risk or Delay “Type” x Duration

• This will remove the most combinations of delay and shrink the area of our distribution giving biggest benefit of predictability

Page 34: Cycle Time Mathematics

Mining Cycle Time Data

Page 35: Cycle Time Mathematics

Commercial in confidence35

Mining / Testing Cycle Time Data

Capture Data

Scatter Plot

Histogram

Fit Shape

Page 36: Cycle Time Mathematics

Commercial in confidence36

Cycle Time Capture Practices

• Clearly understand from where and to where• Capture begin and end date; compute the

number of days in-between• Does cycle time include defect fixing?• Are there multiple types of work in the same

cycle time data– Stories– Defects– Classes of Service

Page 37: Cycle Time Mathematics

Commercial in confidence37

Things that go wrong…

• Zero values• Repetitive (erroneous) values• Batching of updates• Include/exclude weekends• Project team A staff raided impacting their

cycle time (Team A up, team B’s down)• Work complexity changes• Team skill changes

Page 38: Cycle Time Mathematics

Commercial in confidence38

Probability Density Function

Histogram Weibull

x120100806040200

f(x)

0.36

0.32

0.28

0.24

0.2

0.16

0.12

0.08

0.04

0

Probability Density Function

Histogram Weibull

x160140120100806040200

f(x)

0.22

0.2

0.18

0.16

0.14

0.12

0.1

0.08

0.06

0.04

0.02

0

Many low values. Often zero or values below what makes sense. Check the most frequent low values.

Multiple modes. In this case two overlapping Weibulls. Often due to multiple classes of service, or most often - defects versus stories.

Page 39: Cycle Time Mathematics

Commercial in confidence39

Probability Density Function

Histogram Weibull

x1201101009080706050403020100

f(x)

0.28

0.24

0.2

0.16

0.12

0.08

0.04

0

Scale – How Wide in Range. Related to the

Upper Bound

Shape – How Fat the distribution.

Location – The Lower Bound

Page 40: Cycle Time Mathematics

Estimating Distributions using

Historical Data

Page 41: Cycle Time Mathematics

Commercial in confidence41

What Distribution To Use...

• No Data at All, or Less than < 11 Samples (why 11?)– Uniform Range with Boundaries Guessed (safest)– Weibull Range with Boundaries Guessed (likely)

• 11 to 50 Samples– Uniform Range with Boundaries at 5th and 95th CI– Weibull Range with Boundaries at 5th and 95th CI– Bootstapping (Random Sampling with Replacement)

• More than 100 Samples– Use historical data at random without replacement– Curve Fitting

Page 42: Cycle Time Mathematics

Commercial in confidence42

Sampling at Random Strategies

• If you pick what samples to use, you bias the prediction…

• Strategies for proper random sampling –– Use something you know is random (dice, darts)– Pick two groups using your chosen technique and

compute your prediction separately and compare– Don’t pre-filter to remove “outliers”– Don’t sort the data, in fact randomize more if

possible

Page 43: Cycle Time Mathematics

Commercial in confidence43

Concurrent WIP Sample : Find the smallest and the biggest or take at least 11 samples to be 90% sure of range

Estimating Concurrent Effort from Cumulative Flow Chart

Page 44: Cycle Time Mathematics

20% 40%

60% 80%

Page 45: Cycle Time Mathematics

Commercial in confidence45

Scope Creep Over TimeLook at the rate new scope is added over time