CAREER TECHNICAL EDUCATION FACILITIES PROGRAMCOST ESTIMATE GUIDELINE
Page 1
SCHOOL DISTRICT 5-DIGIT DISTRICT CODE:SCHOOL NAME COUNTY:ARCHITECT FIRM DATE OF ESTIMATE:PREPARED BY
SIGNATURE:
APPLICATION NUMBER: Estimate Reference
Plan Location Item Quantity Unit CostComments
Construction Specification InstituteDivision 1 General Requirements
a General Conditions
General Conditions $0
Mobilization, On & Off $0
Non-Distributable Labor $0
Permits, Licenses & Fees $0
$0
Equipment Rental $0
Other General Conditions $0
$0
$0
Sub Total $0
Division 2 Site Work a Site work
Site Demolition: $0
General Building Demolition: $0
Excavation, Fill & Grading: $0
Piling $0
Caissons & Drilling $0
Shoring & Bulkheading $0
Site Utilities $0
Storm Drainage & Sanitary Sewer $0
Water, Steam & Gas Distribution $0
Valves & Specialties $0
Mechanical Utilities, Accessories $0
Miscellaneous Site Equipment $0
Electrical Distribution, Underground $0
General Site Work, Paving & Walks $0
Miscellaneous Site Improvements $0
Irrigation, Sprinkler Head Systems $0
Landscaping $0
$0
Sub Total $0
Category
Unit
Architect's Estimate
Saylor Publications, Inc. Current Construction Costs
District may itemize General Conditions or Apply a percentage to the estimated subtotal of construction costs.
Temporary Utilities, Structures & Fences
![Page 2: CTE_CE_GL](https://reader035.vdocuments.mx/reader035/viewer/2022080901/563db881550346aa9a944e1f/html5/thumbnails/2.jpg)
CAREER TECHNICAL EDUCATION FACILITIES PROGRAMCOST ESTIMATE GUIDELINE
Page 2
APPLICATION NUMBER: Estimate Reference
Plan Location Item Quantity Unit CostComments
Category
Unit
Architect's Estimate
Saylor Publications, Inc. Current Construction Costs
Division 3 Concretea
Precast Concrete $0
Specialty Concrete $0
Excavation & Backfill $0
Concrete Forms $0
Foundation forms $0
Footing Forms $0
Forms, Slab on Grade $0
Reinforcing steel $0
Concrete placement $0
Slab Finishes $0
Vertical surface Finishes $0
Insulating Decks $0
Fiber Deck $0
$0
Sub Total $0
Division 4 Masonry
a
Brick Masonry $0
Concrete Unit Masonry $0
$0
Sub Total $0
Division 5 Metalsa
Structural Steel $0
Decking & Siding $0
Misc Iron $0
$0
Sub Total $0
Division 6 Carpentrya
Rough Carpentry $0
Vertical Framing, Walls $0
Horizontal Framing $0
Misc. Framing & Materials $0
Sheathing $0
Carpentry Specialties $0
Finish Carpentry $0
Beams, trusses $0
Stairs, Wood $0
Rough Hardware $0
$0
Sub Total $0
![Page 3: CTE_CE_GL](https://reader035.vdocuments.mx/reader035/viewer/2022080901/563db881550346aa9a944e1f/html5/thumbnails/3.jpg)
CAREER TECHNICAL EDUCATION FACILITIES PROGRAMCOST ESTIMATE GUIDELINE
Page 3
APPLICATION NUMBER: Estimate Reference
Plan Location Item Quantity Unit CostComments
Category
Unit
Architect's Estimate
Saylor Publications, Inc. Current Construction Costs
Division 7 Thermal & Moisture Protectiona
Waterproofing $0
Thermal & Sound Insulation $0
Roofing $0
Composite Building Panels $0
Sheet metal & Fabricated Skylights $0
Architectural Sheet Metal $0
Caulking & Sealants $0
$0
Sub Total $0
Division 8 Doors, Windows & Glassa
Hollow Metal Doors & Frames $0
Wood Doors & Frames $0
Wood Garage Doors $0
Wood Door Specialties $0
Special Doors $0
Vinyl, Windows & Doors $0
Aluminum, Windows & Doors $0
Wood Windows & Doors $0
Finish & Hardware $0
Glass & Glassing $0
Curtain Walls $0
$0
Sub Total $0
Division 9 Finishesa
Studs $0
Furring $0
Lathing $0
Plaster & Lath $0
Gypsum Wall board, Studding & Furring $0
Gypsum Wall board, Secularities $0
Ceramic Tile $0
Terrazzo $0
Acoustic Treatment $0
Wood Flooring $0
Resilient Flooring $0
Painting & Wall covering $0
Plastic & Factory Finish Wall Surfaces $0
Sub Total $0
![Page 4: CTE_CE_GL](https://reader035.vdocuments.mx/reader035/viewer/2022080901/563db881550346aa9a944e1f/html5/thumbnails/4.jpg)
CAREER TECHNICAL EDUCATION FACILITIES PROGRAMCOST ESTIMATE GUIDELINE
Page 4
APPLICATION NUMBER: Estimate Reference
Plan Location Item Quantity Unit CostComments
Category
Unit
Architect's Estimate
Saylor Publications, Inc. Current Construction Costs
Division 10 Specialtiesa
Chalk & Tack Boards $0
Toilet Partitions & Compartments $0
Partitions Toilet Accessories $0
Misc. Building Specialties $0
$0
Sub Total $0
Division 11 CTE Program Equipment to be supplied on separate sheet.
a
Sub Total $0
Division 12 Furnishings Indicate F&E included in a construction contract
(i.e., built-in equipment)
Blinds & Shades $0
Cabinets & Laminated Plastic Tops $0
$0
Carpets $0
Draperies & Curtains $0
Other $0 Must Provide a Description of "Other"
Sub Total $0
Division 13 Special Construction
Special Construction $0
Prefabricated Structures $0
$0
Sub Total $0
Division 14 Conveying Systems
Conveying Systems $0
$0
Sub Total $0
Division 15 Mechancial
Equipment $0
Fixtures $0
Piping $0
Valves & Specialties $0
Insulation, Piping $0
Miscellaneous Plumbing Specialties $0
Medical & Laboratory Equipment & Pipe $0
Fees, Permits & Sterilization $0
Industrial Piping Insulation $0
HVAC $0
Equipment, Furnaces $0
Laminated Plastic & Simulated Marble Tops
![Page 5: CTE_CE_GL](https://reader035.vdocuments.mx/reader035/viewer/2022080901/563db881550346aa9a944e1f/html5/thumbnails/5.jpg)
CAREER TECHNICAL EDUCATION FACILITIES PROGRAMCOST ESTIMATE GUIDELINE
Page 5
APPLICATION NUMBER: Estimate Reference
Plan Location Item Quantity Unit CostComments
Category
Unit
Architect's Estimate
Saylor Publications, Inc. Current Construction Costs
Equipment, Hot Water & Steam Boilers $0
Equipment, Cooling $0
$0
Auxiliary heating & Cooling Equipment $0
Air Handling Equipment, Primary $0
Distribution, Terminal Equipment $0
Miscellaneous Equipment $0
Controls $0
Duct Work, Grills & Registers $0
Piping & Insulation $0
Fittings $0
Valves & Specialties $0
Insulation, Piping $0
Fire Protection Systems $0
$0
$0
Sub Total $0
Division 16 Electrical
Total Electrical Work , Buildings $0
$0
$0
Distribution Panels to 600v $0
Transformers $0
Raceway & Wire, Combined $0
Under floor Distribution Systems $0
Lighting Fixtures, In-Place $0
$0
Signal & Communications Systems $0
Branch Circuit Outlets & Devices $0
Fees, Permits, Testing $0
Equipment, Unit Substations $0
Equipment, Switchgear & Transformers $0
Equipment, High Voltage Transformers $0
Service Sections $0
$0
Motor Control Centers $0
$0
Transformers, Dry, Low Voltage $0
$0
$0
Plug-In Circuit Breakers, Type So $0
Special Gear $0
PVC, RSC, IMC & AL Raceway $0
Equipment, Heating & Cooling Combinations
Electrical Cost, In-Place, Prelim EstimatesMain Switchboards, 600v, Service & Distribution
Branch Circuit Runs, Sp Purpose Conduit & Wire
Combination Service & Distribution, Switchboards
Panelboards, 600v Max, Bolt-On Breakers
Panelboards For Bolt-On Breakers, 1240/240v, 1ph, 3wLoad Circuits, Main Lug & Circuit Breaker Types, 240v Max
![Page 6: CTE_CE_GL](https://reader035.vdocuments.mx/reader035/viewer/2022080901/563db881550346aa9a944e1f/html5/thumbnails/6.jpg)
CAREER TECHNICAL EDUCATION FACILITIES PROGRAMCOST ESTIMATE GUIDELINE
Page 6
APPLICATION NUMBER: Estimate Reference
Plan Location Item Quantity Unit CostComments
Category
Unit
Architect's Estimate
Saylor Publications, Inc. Current Construction Costs
$0
ENT Raceway, Terminations & Elbows $0
PVC,RSC,IMC, & AL Condit Term, Elbows & Fittings
![Page 7: CTE_CE_GL](https://reader035.vdocuments.mx/reader035/viewer/2022080901/563db881550346aa9a944e1f/html5/thumbnails/7.jpg)
CAREER TECHNICAL EDUCATION FACILITIES PROGRAMCOST ESTIMATE GUIDELINE
Page 7
APPLICATION NUMBER: Estimate Reference
Plan Location Item Quantity Unit CostComments
Category
Unit
Architect's Estimate
Saylor Publications, Inc. Current Construction Costs
ENT MI Cable & Terminations $0
Special Raceway Assembly Systems $0
Conductor Only $0
Busways $0
Lighting Fixtures $0
Electric & Signal Devices $0
$0
Special Hospital Systems $0
Soft Wire Systems, 3 Wire $0
$0
$0
$0
$0
Sub Total $0
Estimate Sub-total $0
9% $0
9% $0
Design Fees 8% $0
Inspection 1% $0
Escalation 4% $0
DSA fees 0.7% $0
Contingency 10.0% $0
Estimate Sub-Total $0
Equipment Total (Division 11) $0
Cost Estimate Total $0 * All percentages are compounded and apply to all Divisions, excluding Division 11- Equipment.* Percentages are based on the industry standards in the Saylor Publications Guide and represent the maximum amount typically allowed.
Communication, Intercom, Public Address
Energy & Building Management Systems
General Conditions (includes Soft Costs)
The percentage is allowed in lieu of all Division 1 line items from above. If Division 1 is completed, then this section will automatically populate with "N/A".
General Requirements, Overhead & Profit, Bonds