cryostat assembly, integration and commissioning procedures

90
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008

Upload: forrest-church

Post on 01-Jan-2016

48 views

Category:

Documents


0 download

DESCRIPTION

Cryostat assembly, integration and commissioning procedures. M.Olcese Version: 07 May 2008. Definitions. Flanges/plates (from innermost): MC plate: mixing chamber plate HEX plate: heat exchanger plate STILL plate 4K flange: Inner Vacuum Chamber (IVC) plate 40K plate - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Cryostat assembly, integration and commissioning procedures

1

Cryostat assembly, integration and commissioning procedures

M.Olcese

Version: 07 May 2008

Page 2: Cryostat assembly, integration and commissioning procedures

2

Definitions

• Flanges/plates (from innermost):– MC plate: mixing chamber plate– HEX plate: heat exchanger plate– STILL plate– 4K flange: Inner Vacuum Chamber (IVC) plate– 40K plate– 300K flange: Outer Vacuum Chamber (OVC) plate

• Vessels/screens:– MC screen (upper and lower part)– HEX screen– 4K vessel: IVC vessel– 40K screen– 300K vessel: OVC vessel

Page 3: Cryostat assembly, integration and commissioning procedures

3

Schematic: cryostat

Main external shielding

300K, 4K vessels and 40K screen

300K, 4K flangesand 40K plate

Lateral STILL lead shield

Internal screens (STILL-HEX-MC)

Lateral STILL lead shield support cradle

Detector

Detector support plate

Internal top lead shield

STILL plate

STILL top lead ring

HEX and MC plates

Page 4: Cryostat assembly, integration and commissioning procedures

4

Main platform (lower)

1° floor

Main platform (upper)

2° floor

Light platform

Corridorside

ParkingSide of main shielding

Concrete walls

Main rail system

Aux. rail system

Schematic: building and platform

Page 5: Cryostat assembly, integration and commissioning procedures

5

Scenarios

1. Initial installation:1.1 Installation of 300k-40k-4k plates

1.2 Dry fit of vessels and screens

1.3 Installation of STILL-HEX-MC plates

2. Cryostat commissioning

3. Detector installation

4. Access for maintenance

Page 6: Cryostat assembly, integration and commissioning procedures

6

General issues

• All the individual items (with few exceptions) can be brought on the main platform for the installation:– from the hut ground floor with the platform in

the side position– Directly from the external corridor using an

auxiliary rail system

Page 7: Cryostat assembly, integration and commissioning procedures

7

1 Initial installation1.1 installation of top plates/flanges

• The plates are delivered clean and inside plastic bags• The plates are piled up on the main platform (a platform

add-on may be required to reach the 1° floor level)• The main platform is raised• Eye bolts + radial extensions (if needed) will be fixed to

the plates.• The plates are lifted by means of the hoist cable system

and connected to the tie rods/suspensions• It may be convenient to install, along with the plates,

some of the internal components like: sections of the source tube, wire feed-throughs, IVC pumping tube, …

Page 8: Cryostat assembly, integration and commissioning procedures

8

Main platform

Platform extension

Option 1

Stack of plates in reverse order (4K-40K-300K)

Initial installation 1.1: setting of plates on platform at ground level

Page 9: Cryostat assembly, integration and commissioning procedures

9

Option 2

Plates set on auxiliary platform from the corridor side

Initial installation 1.1: setting of plates on platform at ground level

Page 10: Cryostat assembly, integration and commissioning procedures

10

Initial installation 1.1: platform with plates ready for lifting

Page 11: Cryostat assembly, integration and commissioning procedures

11

Initial installation 1.1: platform reach the 1° floor level

Page 12: Cryostat assembly, integration and commissioning procedures

12

Initial installation 1.1: 300K-4K flanges and 4K plate are installed in sequence

Page 13: Cryostat assembly, integration and commissioning procedures

13

Initial installation 1.1: completed

Page 14: Cryostat assembly, integration and commissioning procedures

14

1 Initial installation1.2 dry-fit of 300K-4K vessels and 40K screen

• Purpose: – check the handling procedure and sign-off of the

cable hoist system– Check vacuum tightness and deformations of OVC

and IVC

Issues/comments:• The internal screens (still, HEX, MC) must be installed in clean

conditions, so they will not be installed in this phase through the floor opening. They will be installed and removed from the clean room at the end of the dry fit

• All the screens/vessels are delivered in upright position on a basement

Page 15: Cryostat assembly, integration and commissioning procedures

15

Initial installation 1.2: 4K (40K, 300K) vessel set on platform

Option1 Option2

Page 16: Cryostat assembly, integration and commissioning procedures

16

Initial installation 1.2: 4K (40K, 300K) vessel ready for lifting

Lifting ears and eye bolts are installed and hoist cables connected

Lifting cables

Page 17: Cryostat assembly, integration and commissioning procedures

17

Initial installation 1.2: 4K (40K, 300K) vessel lifted and fixed to the 4K flange

Page 18: Cryostat assembly, integration and commissioning procedures

18

Initial installation 1.2: testing

• Leak tightness• Vacuum• Deformations

Page 19: Cryostat assembly, integration and commissioning procedures

19

1 Initial installation1.3 Installation of STILL-HEX-MC plates

Page 20: Cryostat assembly, integration and commissioning procedures

20

Initial installation 1.3: installation of temporary support structure

The main platform is moved aside

Page 21: Cryostat assembly, integration and commissioning procedures

21

Initial installation 1.3: 300K-40K-4K vessels lowered down

Page 22: Cryostat assembly, integration and commissioning procedures

22

Initial installation 1.3: the floor is closed and sealed off

From this moment on the area around the cryostat will have to be kept clean at all time

Page 23: Cryostat assembly, integration and commissioning procedures

23

Initial installation 1.3: installation of the STILL plate

Page 24: Cryostat assembly, integration and commissioning procedures

24

Initial installation 1.3: installation of the STILL plate

Page 25: Cryostat assembly, integration and commissioning procedures

25

Initial installation 1.3: installation of the HEX and MC plates

Page 26: Cryostat assembly, integration and commissioning procedures

26

Initial installation 1.3: installation of the HEX and MC plates

Page 27: Cryostat assembly, integration and commissioning procedures

27

2. Cryostat commissioning

• 2.1 integration of all the internal components (DU, pulse tubes, wire inserts, source guiding tubes, suspensions)

– Preliminary cooling tests and functional tests of all components• 2.2 installation of STILL lateral lead shield• 2.3 installation of the internal top lead shield and dummy detector (DD)

– alignment and calibration of the detector suspension system • 2.4 Final tests

• COMMENTS:– The 2.1 phase will last for quite some time and will require several openings and

closings of the cryostat: it is recommended to use a temporary support structure on the main platform to store the screens/vessels. This would allow the assembly of the main external shielding in parallel and off-line

– In phase 2.1 not all the screens/vessels may be needed for the tests: those internal are stored on the first floor and could be installed when needed independently from the external ones

Page 28: Cryostat assembly, integration and commissioning procedures

28

2. Cryostat commissioning

2.1 integration of all the internal components (DU, pulse tubes, wire inserts, source guiding

tubes, suspensions)

Page 29: Cryostat assembly, integration and commissioning procedures

29

Cryostat commissioning 2.1: installation of internal components

In parallel: assembly of main

shielding

Page 30: Cryostat assembly, integration and commissioning procedures

30

Cryostat commissioning 2.1: installation of internal screens (1)

Page 31: Cryostat assembly, integration and commissioning procedures

31

Cryostat commissioning 2.1: installation of internal screens (2)

Page 32: Cryostat assembly, integration and commissioning procedures

32

Cryostat commissioning 2.1: installation of internal screens (3)

Screens lifted by the cable hoist system or by hydraulic

jacks

Page 33: Cryostat assembly, integration and commissioning procedures

33

Cryostat commissioning 2.1: installation of external vessels (1)

Page 34: Cryostat assembly, integration and commissioning procedures

34

Cryostat commissioning 2.1: installation of external vessels (2)

main shielding

completed

Page 35: Cryostat assembly, integration and commissioning procedures

35

Cryostat commissioning 2.1: cold tests

Page 36: Cryostat assembly, integration and commissioning procedures

36

Cryostat commissioning 2.1: cold tests

During testing:• The temporary support is removed

Page 37: Cryostat assembly, integration and commissioning procedures

37

Cryostat commissioning 2.1: cold tests

During testing:• The platform with the main

shielding is brought on-axis

Page 38: Cryostat assembly, integration and commissioning procedures

38

2. Cryostat commissioning

2.2 installation of STILL lateral lead shield

Page 39: Cryostat assembly, integration and commissioning procedures

39

Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (1)

The floor is opened

Page 40: Cryostat assembly, integration and commissioning procedures

40

Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (2)

The 4K-40K-300K vessels are lowered into the main shield

Page 41: Cryostat assembly, integration and commissioning procedures

41

Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (3)

• Floor closed• External vessels sealed off

Page 42: Cryostat assembly, integration and commissioning procedures

42

Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (4)

Removal of internal screens

Page 43: Cryostat assembly, integration and commissioning procedures

43

Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (5)

Removal of internal screens

Page 44: Cryostat assembly, integration and commissioning procedures

44

Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (6)

Main shielding moved aside

Page 45: Cryostat assembly, integration and commissioning procedures

45

Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (7)

Temporary support added on main platform

Page 46: Cryostat assembly, integration and commissioning procedures

46

Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (8)

Platform raised and sealed

Page 47: Cryostat assembly, integration and commissioning procedures

47

Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (9)

• Floor opened• Temporary support raised

to reach floor level

Page 48: Cryostat assembly, integration and commissioning procedures

48

Cryostat commissioning 2.2: installation of STILL lateral lead shield (1)

Still lead cradle set on support

Page 49: Cryostat assembly, integration and commissioning procedures

49

Platform lowered

Cryostat commissioning 2.2: installation of STILL lateral lead shield (2)

Page 50: Cryostat assembly, integration and commissioning procedures

50

Cryostat commissioning 2.2: installation of STILL lateral lead shield (3)

Bottom lead layer and first ring added

Page 51: Cryostat assembly, integration and commissioning procedures

51

Cryostat commissioning 2.2: installation of STILL lateral lead shield (4)

Platform lowered

Page 52: Cryostat assembly, integration and commissioning procedures

52

Cryostat commissioning 2.2: installation of STILL lateral lead shield (5)

Installation of 2° lead ring

Page 53: Cryostat assembly, integration and commissioning procedures

53

Cryostat commissioning 2.2: installation of STILL lateral lead shield (6)

Platform lowered

Page 54: Cryostat assembly, integration and commissioning procedures

54

Cryostat commissioning 2.2: installation of STILL lateral lead shield (7)

Lead rings installation completed

Page 55: Cryostat assembly, integration and commissioning procedures

55

Cryostat commissioning 2.2: installation of STILL lateral lead shield (8)

• Top Cu ring added• Lead assembly lifted• Tie rods connected• Load transfer to STILL plate• Check correct placement

Page 56: Cryostat assembly, integration and commissioning procedures

56

Cryostat commissioning 2.2: preparation for installation of internal top lead shield (1)

• Platform lowered• Floor closed• Temporary support removed

Page 57: Cryostat assembly, integration and commissioning procedures

57

• Main shielding moved on axis• Flexible seal is connected• Floor opened

Cryostat commissioning 2.2: preparation for installation of internal top lead shield (2)

Page 58: Cryostat assembly, integration and commissioning procedures

58

• The main shielding is raised• The still lateral lead shield

assembly is transferred on the main shielding

Cryostat commissioning 2.2: preparation for installation of internal top lead shield (3)

Page 59: Cryostat assembly, integration and commissioning procedures

59

• The platform is lowered• The floor is closed

Cryostat commissioning 2.2: preparation for installation of internal top lead shield (4)

Page 60: Cryostat assembly, integration and commissioning procedures

60

• The internal screen (STILL; HEX; MC) are installed by using the hoist system

Cryostat commissioning 2.2: preparation for installation of internal top lead shield (5)

Page 61: Cryostat assembly, integration and commissioning procedures

61

• The internal screens (STILL; HEX; MC) are installed by using the hoist system

Cryostat commissioning 2.2: preparation for installation of internal top lead shield (6)

Page 62: Cryostat assembly, integration and commissioning procedures

62

• The floor is opened• The internal screens (STILL;

HEX; MC) are lowered into the main shielding by using the hoist system

Cryostat commissioning 2.2: preparation for installation of internal top lead shield (7)

This is the final configuration

of the cryostat vessels/screens in “fully open”

conditions

Page 63: Cryostat assembly, integration and commissioning procedures

63

2. Cryostat commissioning

2.3 installation of the STILL internal top lead shield and dummy detector (DD)

Page 64: Cryostat assembly, integration and commissioning procedures

64

• The floor is closed• The floor plug must be

designed to withstand the load of the internal top lead shield

Cryostat commissioning 2.3: installation of internal top lead shield (1)

Page 65: Cryostat assembly, integration and commissioning procedures

65

A support structure allowing access to the anchoring points at the bottom of the support plate is added

Cryostat commissioning 2.3: installation of internal top lead shield (2)

Page 66: Cryostat assembly, integration and commissioning procedures

66

The base support plate is set on the platform

Cryostat commissioning 2.3: installation of internal top lead shield (3)

Page 67: Cryostat assembly, integration and commissioning procedures

67

The Lead layers and copper sheets are added in sequence

Cryostat commissioning 2.3: installation of internal top lead shield (4)

Page 68: Cryostat assembly, integration and commissioning procedures

68

• The platform is raised to bring the internal top lead shield assy at the nominal position

• The suspensions are connected• The load is transferred from the

platform to the suspensions

Cryostat commissioning 2.3: installation of internal top lead shield (5)

Page 69: Cryostat assembly, integration and commissioning procedures

69

• The platform is lowered• The position of the internal top

lead assy is surveyed and adjusted as required

Cryostat commissioning 2.3: installation of internal top lead shield (6)

An alternative option may consist in using the detector installation cart, thus avoiding moving up and down the main platform

Page 70: Cryostat assembly, integration and commissioning procedures

70

• The dummy detector is set on the platform

• the same cart+rail system used later on to install the detector may be used

Cryostat commissioning 2.3: installation of the dummy detector (1)

Installationcart

Rail system

Page 71: Cryostat assembly, integration and commissioning procedures

71

• The dummy detector (DD) is lifted up to the nominal position

• Load is transferred to the suspensions

• The position of the DD is checked and the suspensions are adjusted if needed

Cryostat commissioning 2.3: installation of the dummy detector (1)

Page 72: Cryostat assembly, integration and commissioning procedures

72

• The top part of the MC screen is installed by hands

• The innermost sections of the source guiding tubes are added

Cryostat commissioning 2.3: installation of the top part of MC screen

Page 73: Cryostat assembly, integration and commissioning procedures

73

Cryostat commissioning 2.3: installation of the STILL top lead ring

Page 74: Cryostat assembly, integration and commissioning procedures

74

• The floor is opened• The platform is raised up to

approach the MC flange• The MC screen is fastened

Cryostat commissioning 2.3: closing of the cryostat (1)

Page 75: Cryostat assembly, integration and commissioning procedures

75

The platform is raised up again to allow the fastening of the HEX and STILL screens and of the STILL lateral lead shield

Cryostat commissioning 2.3: closing of the cryostat (2)

Page 76: Cryostat assembly, integration and commissioning procedures

76

The 4K-40K-300K vessels are lifted with the cable hoist system

Cryostat commissioning 2.3: closing of the cryostat (3)

Page 77: Cryostat assembly, integration and commissioning procedures

77

2. Cryostat commissioning 2.4 Final tests

The cryostat is cooled down and the final commissioning tests are carried out

including the full test of the calibration system

Page 78: Cryostat assembly, integration and commissioning procedures

78

3. Detector installation

3.1 Preparation for the installation (removal of dummy detector)

3.2 detector installation

Page 79: Cryostat assembly, integration and commissioning procedures

79

The 300K-40K-4K vessels are lowered with the cable hoist system

Preparation for detector installation 3.1: opening of the cryostat (1)

Page 80: Cryostat assembly, integration and commissioning procedures

80

The STILL-HEX-MC screens and lead shield are lowered by lowering the platform

Preparation for detector installation 3.1: opening of the cryostat (2)

Page 81: Cryostat assembly, integration and commissioning procedures

81

• The platform is fully lowered• The floor is closed

Preparation for detector installation 3.1: opening of the cryostat (3)

Page 82: Cryostat assembly, integration and commissioning procedures

82

The detector installation cart+rail system is installed on the floor

Preparation for detector installation 3.1 : removal of the dummy detector (1)

Page 83: Cryostat assembly, integration and commissioning procedures

83

The dummy detector is lowered

Preparation for detector installation 3.1 : removal of the dummy detector (2)

Page 84: Cryostat assembly, integration and commissioning procedures

84

• The dummy detector is removed

• The clean room around the cryostat is now switched to “radon-free”

Preparation for detector installation 3.1 : removal of the dummy detector (2)

Page 85: Cryostat assembly, integration and commissioning procedures

85

The detector is moved in

Detector installation 3.2 (1)

Radon-free

Page 86: Cryostat assembly, integration and commissioning procedures

86

• The detector is raised to the nominal position

• The load is transferred to the suspensions

Radon-free

Detector installation 3.2 (2)

Page 87: Cryostat assembly, integration and commissioning procedures

87

• The suspensions are adjusted if needed

• The tapes are connected to PP1• The source guiding tubes are

adjusted to match

Radon-free

Detector installation 3.2 (3)

Page 88: Cryostat assembly, integration and commissioning procedures

88

• The floor is opened• The platform is raised• The MC-HEX-STILL screen and the

STILL lead shield are fastened to the corresponding plates

• The detector is flushed with N2

Radon-free

Detector installation 3.2 (4)

Page 89: Cryostat assembly, integration and commissioning procedures

89

• The 4K-40K-300K vessels are raised by the cable hoist system

• The main shield is raised up to the top position

The experiment is ready to run

Detector installation 3.2 (5)

Page 90: Cryostat assembly, integration and commissioning procedures

90

4. maintenance

Subset of the procedures followed for the detector installation