crib point pakenham pipeline project · web viewadopting engineering noise controls at the source...

61
Construction Environment Management Plan Crib Point Pakenham Pipeline Project Day 1 amendments. Day 2 changes shown with highlight & explanation in last column Other party recommendations in green & explanation in [APPENDIX J TO PIPELINE CONSTRUCTION ENVIRONMENT MANAGEMENT PLAN] INDEX Topic Page Table 9-F: Performance standards (all activities) Site access and property management Air, Noise & Vibration Management Biodiversity Cultural heritage Historic heritage Biosecurity Surface water and Groundwater Fuels & chemicals Waste 23 Sustainability and greenhouse gas Table 9-G: Performance standards (Clear and Grade, Right of Way Maintenance) Clear and Grade, Right of Way Maintenance Table 9-H: Performance standards (Trench management) Trench management Table 9-I: Performance standards (Watercourse Crossings) Watercourse Crossings Table 9-J: Performance standards (HDD and Horizontal Boring) Horizontal Directional Drilling & Thrust Boring Table 9-K: Performance standards (Hot works) Hot works 1

Upload: others

Post on 18-Dec-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

[APPENDIX J TO PIPELINE CONSTRUCTION ENVIRONMENT MANAGEMENT PLAN]

INDEX

Topic Page

Table 9-F: Performance standards (all activities)Site access and property managementAir, Noise & Vibration ManagementBiodiversityCultural heritageHistoric heritageBiosecuritySurface water and GroundwaterFuels & chemicalsWaste 23Sustainability and greenhouse gas

Table 9-G: Performance standards (Clear and Grade, Right of Way Maintenance)

Clear and Grade, Right of Way Maintenance

Table 9-H: Performance standards (Trench management)

Trench management

Table 9-I: Performance standards (Watercourse Crossings)

Watercourse Crossings

Table 9-J: Performance standards (HDD and Horizontal Boring)

Horizontal Directional Drilling & Thrust Boring

Table 9-K: Performance standards (Hot works)Hot works

Table 9-L: Performance standards (hydrostatic testing)Cleaning, hydrostatic testing

Table 9-M: Performance standards (reinstatement)

1

Page 2: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Reinstatement

Table 9-N: Performance standards (Pakenham Delivery Facility)

Pakenham Delivery Facility

2

Page 3: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

J Performance objectives and standardsThe following performance standards address the environmental impacts and risks and legal requirements for the Project. The standards cover design, management and mitigation measures. Monitoring and contingency plans are also detailed. The performance objectives and standards outlined in Table 9-F are general across the Project and are applicable to all activities undertaken on the site. Performance standards applicable to specific activities are further outlined below. Table 9-F: Performance standards (all activities)

Performance Standards – all activities

Objective To plan and manage environmental impacts associated with the proposed construction activities.

Target Conformance with the relevant limits and controls specified in this performance standard.

Application

The duration of the proposed works across all areas.

Ref Environmental Controls Project Phase Explanation of Changes

Site access and property management

A1 All project activity and construction works are to be confined to the identified route and confirmed alignment. No activity will occur outside this area unless approved under existing conditions.

Construction

A2 Prior to any works commencing on a property, agreements with the landowners and occupiers regarding the use of existing roads or tracks, the selection of new access routes and any property-specific measures to implement during construction and operations, such as:a. Access across the ROW during constructionb. Stock management, access and exclusionc. Management of overland flowd. Biosecuritye. Relocation / duplication of facilities and

Pre-construction

Adopted from H Burge evidence

3

Page 4: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

infrastructuref. Planting and screening vegetation.

A3 Crossing water infrastructureMethods and timing of construction for crossings of water transfer infrastructure will be agreed with the landholders, occupiers and/or operators of the system prior to any works commencing on the property.

Pre-construction

A4 Management of third party services Prior agreements will be made with the affected third parties where the interruption of identified third party services cannot be reasonably avoided.

Pre-construction

A5 Landowners and occupiers will be informed of the construction commencement, and details of the proposed construction programme, in accordance with the Consultation Plan

Pre-constructionConstruction

A6 Any requirements noted in landowner agreements with APA will be met. Pre-

constructionConstructionPost-construction

A7 A Site plan is to form part of the site induction and be available to site supervisors at all times during construction. The Site plan will clearly delineate the site, access points and sensitive areas (e.g. native vegetation) in or adjacent to the site.

Pre-constructionConstruction

A8 A Traffic Management Plan (TMP), approved by the relevant local government authorities and VicRoads, will be in place prior to the commencement of construction. The TMP will include the following:- Stakeholder and communications arrangements- Public transport and school bus disruption management- Pedestrian & cyclist connectivity- Level crossing audit requirements for the level

Pre-construction

C Dunstan evidenceC Dunstan Reply evidence

4

Page 5: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

crossing adjacent to Frankston-Flinders Road - Road safety audit requirements, including review of performance of key intersections and safe intersection sight distance (SISD) and any necessary mitigation measures - Car parking management- Pavement strength survey and condition assessment requirements- The design, construction and management measures for access point intersections to provide safe vehicle movements

For the purpose of the TMP, key intersections will include, as a minimum:- Tyabb-Tooradin Road/Bungower Road- Western Port Highway/Bungower Road- Western Port Highway/Tyabb-Tooradin Road- Frankston-Flinders Road/Western Port Highway/Denham Road- Frankston-Flinders Road/Marine Parade- Woolleys Road/Stony Point Road.

In response to Document 413 (H Marshall)

TP01 Hillary Marsh (Ratio):

Amend MM-TP01:A Car Park Management Plan to be prepared as part of the construction phase, to minimise the impact of parking in the vicinity of the various construction segments.

Not accepted as necessary but adopted in the above

TP04

TP05

TP07

Hillary Marsh (Ratio):

Amend MM-TP04:A Road Safety Audit to be undertaken at the following intersections:

1. Tyabb-Tooradin Road / Bungower Road2. Western Port Highway / Bungower Road3. Western Port Highway / Tyabb-Tooradin Road4. Frankston Flinders Road / Western Port Highway / Denham Road (Peak

Hour analysis by Aecom)5. Frankston Flinders Road / Marine Parade (Peak Hour analysis by Aecom)6. Woolleys Road / Stony Point Road.

Amend MM-TP05:Preferred route (once identified) to be included in the Pavement Strength Survey.

Amend MM-TP07:A Road Safety Audit be undertaken at the two blackspot locations on Coolart Road to determine if additional mitigation is required to reduce any potential increase in risk at these locations.Preferred route for the Liquid Nitrogen Truck to be included in the Pavement Strength Survey, with appropriate mitigation identified as relevant.

Not accepted based on evidence of C Dunstan

TP05/07 relate solely to nitrogen trucks

5

Page 6: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

A9 Restricted vehicle movementsAfter arrival at the Project site, all construction vehicles and plant will remain within the construction footprint or on public roads and designated access tracks, unless undertaking survey or property management activities with prior agreement of the land owner.

Construction

A10 Vehicles and plant will be checked daily to ensure that combustible materials such as grass and debris do not build up in areas where ignition may occur.

Construction

A11 Vehicle and pedestrian access Where vehicle and pedestrian access are altered during construction, vehicle and pedestrian access will be replaced, in accordance with relevant road design standards and in consultation with landholders and any other relevant third parties.

Post- construction

A12 Suitably qualified contractors

Contractor(s) that are suitably qualified and experienced in trenchless installation techniques and piling installation will be used.

Construction

Moved to D10 as relates to HDD

A12 Landscape screeningWhere a reasonable request for landscape screening (planting)   is received from affected landowners or adjoining neighbours associated with above ground pipeline infrastructure, the request will be subject to review by APA, considering but not limited to:

(i) proximity of proposed planting to buried pipeline, above ground facilities and any other existing infrastructure;

(ii) pipeline inspection and line- of-sight requirements;

(iii) site access and visibility; (iv) fire safety; and (v) regulatory considerations.

Where the request is from an adjoining neighbour, implementation would also be subject to agreement

Construction

Additional Standard to respond to Hayden H Burge and MM-LV02

6

Page 7: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

from the relevant landowner and any occupier. Where a requested planting is approved by APA, it would be addressed as part of APA CEMP Performance Standard A2: agreements made with the landowners and occupiers regarding any property-specific measures to implement during construction and operations.

A13 Materials and finishes

Selection of materials and finishes will appropriately respond to the environment and be complementary to the setting.

Pre-Construction

To reflect MM-LV03

A14 Reflective surfaces

Reflective surfaces on infrastructure will be minimised to reduce reflection of artificial light where practicable.

Construction

M Cook evidence and to reflect MM-LV05

Air, Noise & Vibration Management

E1 Speed limit within the site boundary including access tracks restricted to a maximum of 40kph.

Construction

E2 Activities will be managed onsite to ensure dust is not a hazard. Observational monitoring of dust will be undertaken along the construction right of way (ROW) where adjacent to sensitive receptors, including monitoring of fine particulates.Management/control measures proportionate to the level of risk must be put in place to minimise risk of generation. Control measures used may include:• Water carts used on unsealed work areas; • crushed rock placed on existing permanent unsealed

access tracks where agreed with relevant stakeholders • Water spray units used on soil stockpiles and during the

loaded and unloaded of dust generating materials .i.e. soil/sand/fill and aggregates; and

• Vehicle loads covered when carrying dust (or litter) generating material.

Dust suppression activities are to be undertaken as directed by the APA Construction Manager, who will take

Construction

G Ross evidence

7

Page 8: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

the following factors into consideration:• Weather patterns; hot, dry, windy forecasts; • Ground cover .i.e. exposed surfaces;• Type and moisture content of soil present; and• Type of activities being conducted, such as vehicle

movement, vegetation clearing and excavation.

E3 If all available methods of dust stabilisation fail to suppress dust and dust emissions are evident beyond the Site boundary, the APA Construction Manager will temporarily modify or suspend dust generating activities until conditions subside.

Construction

E4 Vehicles, plant and machinery will be maintained in good working order to minimise air emissions that may cause nuisance and so that noise and vibration do not exceed the manufacturer’s specifications.

Construction

E5 Construction may occur up to 24 hours a day, 7 days a week. Normal working hours will be between 7 am and 6 pm weekdays and 7 am to 1 pm Saturday. Where, for practical reasons, out-of-hours work is unavoidable, it must only occur with prior approval by the APA Construction Supervisor and affected residents must be notified at least 24 hours before the out of hours work commences.

Construction

E6 Managing noise from construction activitiesConstruction noise and vibration will be managed with reference to Section 2 (Construction and Demolition Site Noise) of EPA Publication 1254 Noise Control Guidelines and Section 5 (Noise and vibration) of EPA Publication 480 Environmental Guidelines for Major Construction Sites. This includes the development of a construction noise and vibration management plan (CNVMP) plan to manage noise and vibration during construction in consultation with the EPA , and approved by the relevant authority . The plan will include: • critical works through townships or other sensitive

regions affected by the pipeline works including Hastings;

• site specific noise controls to be implemented at the HDD locations listed in Performance D9; and

• an appropriate stakeholder communication strategy that incorporates the complaint management procedures and includes prior communication advice and notices to affected residents, with assessment

Construction

Expanded to respond to T Marks evidenceAdded to better reflect O Boushel evidence

Response to Document 459

8

Page 9: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

conducted prior to any night works taking place , and timely communication of noise monitoring results, on request, to affected residents .

The plan CNVMP w ill also include the following general good practice techniques: Using the lowest-noise work practices and equipment

that meet the requirements of the job. Locating and positioning site buildings, access roads

and plant to minimise noise disturbance at the locality. Installing broadband reversing alarms on construction

vehicles and machinery in preference to 'beeper' reversing alarms. The site will also be planned to minimise the need for reversing of vehicles.

Turning off plant and vehicles when not being used. Taking care not to drop spoil and construction

materials that cause peak noise events.The CNVMP must be informed by modelling and/or monitoring undertaken by a suitably qualified noise and vibration consultant prior to the construction activities occurring.Where the construction noise and/or vibration levels are predicted or measured to be exceeded at sensitive receptor locations, noise management measures detailed in the CNVMP and consistent with the requirements of NSW CNVG shall be implemented prior to works occurringreduction measures proportionate to the level of risk of impacting on a sensitive receptor will be included in the planning and design of the Project activities. These may include, but are not limited to, the following: Adopting engineering noise controls at the source (e.g.

silencer, mufflers, enclosures) by the best practical means using current technology – Expected reduction of 10 dB to 15 dB.

Installation of onsite barriers such as hoardings or temporary enclosures to provide a noise barrier between any particularly noisy construction works and the residences - Expected reduction of 5 dB to 10 dB.

Limiting normal works between 6am and 7am to the arrival of staff on site, toolbox meetings and pre-work checks. The use of loud equipment, generation of unnecessary noise and the movement of vehicles on the construction footprint will be minimised outside normal working hours.

Respite periods by restricting the hours that the very

(Jim Antonopoulos changes)

9

Page 10: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

noisy activities can occur.

E7 Offsite noise management measuresOffsite management measures will be considered where measured or predicted construction noise exceeds the following noise management levels for an extended period of time at sensitive receptors.Levels in the following table are not noise limits but represents a threshold that triggers an action to minimise the noise impact at the receptor after all reasonable and feasible measures have been implemented to manage construction noise impacts onsite.Works notifications for unavoidable night works will include details of the specified tasks that cannot be done during normal working hours

Time periodNoise management

levels Management measuresLAeq (15 min)

EPA Normal working hoursMon-Fri: 6am - 6pm

External construction noise level:

Works notification

Sat: 6am - 6pm LAeq(15min) > 75dB(A)

EPA Evening/weekend hours and public holidaysMon-Fri: 6pm - 10pm

External construction noise level:

Adopt management measures based on NSW CNVG. Measures include but not limited to:Works notificationIndividual briefingsSpecific notificationRespite offer

LAeq(15min) > LA90, Evening + 10 dB

Sat: 6pm - 10pm  Sun/Public Holiday: 6pm - 10pm

 

EPA Night hoursMon-Sun: 10pm - 6am

External construction noise level:

Works notification Individual briefingsSpecific notificationRespite offerAudible night period construction works not acceptable unless unavoidable works status approved.offer

LAeq(15min) > LA90, night + 05 dB

EPA Unavoidable works at nightMon-Sun: 10pm - 6am

External construction noise level:

Adopt management measures with reference to NSW CNVG.Targeted engagement

LAeq(15min) > LA90 + 550 dB

Pre-constructionConstruction

Updated in response to EPA question to T Marks

In response to Document 459 (J Antonopoulos)

10

Jim Antonopoulos, 19/11/20,
We either need to define what an extended period is or delete this
Jim Antonopoulos, 19/11/20,
Normal trigger for any management action should also be audibility. Recommend a threshold trigger of B/g+0dB (which triggers works notifications / communications). Further management measures triggered at B/g+different margins as per NSW CNVG. Only having 55 dBA as the single trigger point of any engagement/management is concerning if that is what is intended here. The 55 dBA level is when relocation is normally adopted. It is easier to adopt the NSW guidance fully which addresses this, otherwise we can customise a version with all the management measures at different noise levels. Is that preferred?
Jim Antonopoulos, 19/11/20,
inaudibility is the EPA target requirement. B/g +5dB is not likely to meet inaudibility. B/g+0dB or more (ie B/g-5dB) would be a more appropriate screening level for inaudibility. There cant be any audible construction works at night unless it qualifies as unavoidable.
Page 11: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

with impacted landholders to discuss individual mitigation options.Options include:-Provision of ear plugs or noise cancelling

Noise will be predicted or measured above 55 dB(A) for two or more nights to justify the application of management measures.

Residents with special requirements will be consulted with on a case to case basis.

E8 Out of hours work will be scheduled in consideration of other projects occurring in the area to reduce cumulative noise impactsThe EPA and the proponents of the projects listed below will be consulted during detailed design and the construction planning phase for the purpose of managing cumulative noise impacts associated with the following projects:

• Pakenham East rail depot construction and operation (Department of Transport)

• Healesville-Koo Wee Rup Road upgrade construction (Major Road Projects Victoria and the principal contractor)

• Crib Point Jetty upgrade construction works (Port of Hastings Development Authority)

• Crib Point Jetty operation (United Petroleum).

Pre-constructionConstruction

In response to EPA SubmissionUpdated to remove matters only relevant to GIJW

E9 Vibration safe working distances. Where driven piling, vibratory compaction or other activity causing high levels of vibration are planned, safe working distances will be derived using the values in the following standards: British Standard BS 6472-1:2008 Guide to evaluation of

human exposure to vibration in buildings. Vibration sources other than blasting – Table 1 Vibration dose value ranges which might result in various probabilities of adverse comment within residential buildings

German Standard DIN4150-3:2016-12: Table 1 – Guideline values for vibration velocity for evaluating the effects of short-term vibration on structures

German Standard DIN4150-3:2016-12: Table 3 – Guideline values for vibration velocity for evaluating the

Pre-constructionConstruction

11

Jim Antonopoulos, 19/11/20,
Is the project relocation policy defined somewhere?
Page 12: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

effects of short-term vibration on buried pipework An asset owner’s utility standards.Where occupancies, structures and assets are within the derived safe working distance, additional management measures will investigated and implemented. These may include, but are not limited to: Selecting equipment that would emit lower levels of

vibration Consultation with above and below ground utility asset

owners to establish construction vibration limits to maintain asset integrity

Vibration monitoring of sensitive buildings Conditions survey off sensitive buildings and assets

within safe working distances.

E10

Noise and vibration monitoringNoise and/or vibration monitoring spot checks will be undertaken during construction at: The nearest noise sensitive residential property or

properties impacted by out-of-hours works to confirm compliance with project noise targets.

The nearest building or assets that are within 50 metres of driven piling, vibratory compaction or other activity causing high levels of vibration.

Where an asset owner’s utility standards are at risk of being exceeded.

In the event of a complaint regarding noise in relation to an ongoing activity.

A response plan will be developed to manage potential impacts if nominated targets are exceeded, including: Any actions taken to rectify the exceedance. Actions to minimise risk of reoccurrence. Name of person(s) responsible for undertaking the

required actions. The type and duration of any further monitoring to be

undertaken.

Construction

Biodiversity

12

Page 13: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

B1 All vegetation clearing works will be confined to the RoW. The boundary of the RoW will be clearly demarcated with survey pegs. If there is any loss of native vegetation outside of the RoW, it will be replaced.

Construction

B2 Clearing of native vegetation will be offset in accordance with the Guidelines for the removal, destruction or lopping of native vegetation (DELWP 2017) prior to the clearing commencing.

Pre-constructionConstruction

B3 No native vegetation to be retained will be cleared. Environmental features to be retained within or directly adjacent to, the construction footprint, will be clearly demarcated and identified on site (Attachment G – Environmental Line List).

Pre-constructionConstruction

B4 Reduce right of wayThe width of the right of way is reduced at environmentally sensitive locations as identified in Attachment G – Environmental Line List

Pre-construction

B5 Branches of trees on the edge of the RoW, but overhanging into construction / activity areas, will be trimmed as necessary by a qualified arborist.

Construction

B6 Woody vegetation, trees and hollows to be removed are to be inspected for fauna by a suitably qualified wildlife handler immediately prior to removal. This will include:

A walk-through/visual inspection of the habitat to be removed immediately prior to clearance to flush out fauna and capture and relocate.

Advise on clearing techniques that minimise fauna impact.

Keep records of important fauna interactions, listing the species concerned, the nature of the interaction and GPS coordinates.

Construction

B7 Work areas, particularly excavations and open trench, are to be visually inspected for fauna at the start of each work day and any trapped fauna removed.

Construction

13

Page 14: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

B8 Native fauna are to be relocated by a qualified and authorised fauna handler only. Records of all relocations will be retained.

Construction

B9 Welded pipe strings are to be end capped to prevent fauna entry

Construction

B10 Swamp Skink

Where areas of Swamp Skink habitat are identified in the Environmental Line List (Attachment G), the following measures will be taken to reduce impacts:

Clear and grade activities will occur preferentially in warmer months (late Spring to early Autumn) when skinks are more active and better able to avoid activities.

A fauna handler will complete an inspection of the habitat area immediately prior to any vegetation removal (including ground cover).

If clear and grade occurs during cooler months, when skinks may be in burrows (April to September or as determined by a fauna ecologist), a fauna handler will be present during topsoil stripping to monitor the area and inspect stripped material.

A fauna handler will complete an inspection of topsoil and vegetation stockpiles prior to respreading.

Erosion and sediment controls and temporary fencing will be inspected for sheltering skinks prior to removal.

Any individuals captured during the inspections described above will be relocated to the nearest adjacent habitat away from the construction area.

Construction

14

Page 15: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

B11 Southern Brown BandicootFollowing clearing, fencing suitable to exclude the Southern Brown Bandicoot will be installed at the edges of the construction footprint where it is adjacent to any of the of Southern Brown Bandicoot habitat areas identified in the Environmental Line List (attachment G) to reduce the likelihood of animals entering the construction footprint. Monitoring of fencing will be undertaken and repairs completed as required.

In the event that Southern Brown Bandicoot are discovered within the construction footprint, all mobile construction equipment in the surrounding area will cease work, excluding use of light vehicles to move staff to and from the area. Mobile construction equipment will not recommence work until a wildlife handler has removed the individual or it has been confirmed that individual has left the workspace. Captured individuals will be removed and relocated to nearest adjacent habitat away from the construction area.

If night time activities are required within or adjacent to any of the identified locations of Southern Brown Bandicoot habitat, a wildlife handler will be available to the construction site.

At least one t T emporary Southern Brown Bandicoot shelter site s (shelter pile or bandicoot hide) will be established for every 100 metres of potential habitat along the alignment to provide interim cover / refuge whilst vegetation is re-established.

See also reinstatement standards (R14).

Construction

Updated in response to B Lane Reply to J Urlus evidence and questions from the IAC

Response to Document 441 (J Urlus)

15

Page 16: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

B12 Merran's Sun-orchid, Pallid Sun-orchid and Gaping Sun-orchidKnown Merran's Sun-orchids, Pallid Sun-orchids and Gaping Sun-orchids will be avoided, with the locations (Environmental Line LIst- attachment G) clearly demarcated within the ROW and activities that may cause impact excluded to ensure no indirect or accidental impacts.Project Environmental Advisor to supervise the placement of the return line, which will be micro-sited to avoid threatened orchids.

Project Environmental Advisor to supervise dismantling of return line and complete inspection of habitat following completion of drilling .

If further individuals are identified within areas of planned impact, a relocation protocol will be developed in consultation with DELWP.

Pre-constructionConstruction

Added text in response to G Lorimer Evidence. See also TN27 for full response to G Lorimer suggested changes to CEMP

16

Page 17: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

B13 Growling Grass Frog The following mitigation measures will be implemented to manage impacts to the Growling Grass Frog:a. Two nocturnal pre-clearance surveys of the

construction footprint for the Growling Grass Frog (as per Commonwealth of Australia 2009c) will be undertaken at each of the following locations within four days prior to clear and grade activities commencing, but only if clear and grade activities at these locations are to occur during the breeding season (spring and summer):

a. Farm Dam adjacent to KP21.5: KP21.4 to KP21.6

b. Western Outfall Drain: KP 30.8. to KP 31.8c. Cardinia Creek: between KP 39.9 and the

western cadastral boundary of Crown Allotment 24A Parish of Koo Wee Rup

d. Cardinia Creek: section of the access track linking to Ballarto Road, where it lies directly adjacent to Lot 1 Title Plan 828572X

e. Lower Gum Scrub Creek, Deep Creek and Toomuc Creek: KP 40.8 to KP 40.9

f. Lower Gum Scrub Creek, Deep Creek and Toomuc Creek: between the eastern cadastral boundary of Crown Allotment 97F Parish of Nar-nar-goon and KP 41.5

b. Any Growling Grass Frog that can be located within the proposed construction footprint during these surveys will be relocated to suitable locations, as determined by the ecologist conducting the survey, within the adjacent waterways.

c. If night time activities are required during the breeding season (spring and summer) within the survey areas described in (a) ), a wildlife handler will be available to the construction site.

d. Hygiene protocols as set out in Murray et al. (2011) will be followed when conducting the surveys described in (a).

Construction

17

Page 18: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

B14 Lighting impacts to faunaLight generated during construction will be managed in general accordance with the guidance measures described in National Light Pollution Guidelines for Wildlife Including Marine Turtles, Seabirds and Migratory Shorebirds.

Construction

Cultural heritage

CH1 Cultural heritage will be managed in accordance with the Cultural Heritage Management Plans (CHMPs 15383 and 15384)

Pre-constructionConstructionPost-construction

CH2 Where required by the project’s Cultural Heritage Management Plan (CHMP #15574), areas of cultural heritage significance will be avoided (e.g. reduced ROW, realignment or trenchless construction). Refer to CHMPs 15383 and 15384 for details.

Pre-constructionConstructionPost-construction

CH3 Construction areas will be demarcated with survey pegs, fencing or other markers to ensure works are limited to the approved CHMP Activity Areas.

Pre-construction

CH4 Areas of cultural heritage significance to be avoided will be shown on site plans.

Pre-construction

CH5 Areas of cultural heritage significance to be avoided will be fenced and signed in accordance with the requirements of the CHMP.

Pre-construction

CH6 Cultural heritage artefacts will be salvaged prior to ground disturbance in accordance with any CHMP requirements.

Pre-construction

18

Page 19: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

CH7 Should cultural heritage artefacts be found during the project, the Cultural Heritage accidental finds protocol in the relevant CHMP will be followed

Construction

Note: recommendation of Ms Nicolson that coordination is required between the different groups being picked up in Amended the Pipeline Consultation Plan, Appendix B - Stakeholder engagement matrix, to include an updated “Desired Outcome” as follows:

“Coordinated consultation for the cultural heritage management plans for the Pipeline Works and for Cultural Heritage Management Plan 16300

Historic heritage

HH1 Condition surveys and monitoring (former BP refinery administration building H1016)A condition survey of the Victorian Heritage Register site (Former BP refinery administration building H1016, as identified in the Environmental Line List (attachment G)), will be undertaken prior to commencing and following completion of construction. Any damage deemed to have resulted from the Project will be rectified.  

Pre-constructionConstructionPost-construction

HH2 Horizontal directional drillingSubject to further detailed geotechnical investigations confirming suitability, trenchless construction techniques will be used to minimise direct impacts on historic heritage values at the Denham Road farmhouse (VHI site H7921-0119), as identified in the Environmental Line List (Attachment G).

Construction

HH3 Unexpected finds procedureShould an unknown historic heritage site, value or object be discovered during construction, the Contingency Plan for unexpected historic heritage finds will be followed (refer to Section 6.1).

Construction

Biosecurity

S1 All vehicles and plant, including third parties, will be clean prior to arrival to the site consistent with A Guide for Machinery Hygiene for Civil Construction (Civil Contractor’s Federation, 2011). Weed and seed inspections are to be completed for all vehicles and plant on arrival, with a record of the inspection to remain with the vehicle.

Pre-constructionConstruction

19

Page 20: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

S2 The project will comply with Australian Quarantine and Inspection Service (AQIS) regulatory requirements for any vehicles, equipment or materials sourced from overseas.

Pre-construction

S3 A baseline weed survey of the ROW will be completed prior to construction to identify locations of existing weed infestations

Pre-construction

S4 Construction activities will occur in accordance with relevant elements of existing property specific biosecurity plans which landholders operate under.

Construction

20

Page 21: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

S5 Soil sampling for Cinnamon Fungus Phytophthora cinnamomi is to be undertaken, prior to construction at locations as follows:

every 200m through areas of native vegetation at the following locations (excluding areas to be subject to HDD):

o KP 0 to 2 Crib Point to Woolleys Rd

o KP 3 to 5 Warringine Park. o KP 7.3 to 8.3 in the Stony

Point rail corridoro KP 13.7 to 14.4 in BlueScope o KP 18.5 to 18.7 north of

Bungower Rd at points where the RoW intersects

corridors/ discrete patches of native vegetation (as identified in the Environmental Line List (Attachment G)).

If an area of Cinnamon Fungus Phytophthora cinnamomi dieback is identified within the ROW, biosecurity clean-down locations will be established at the exits to the area. The design of any clean-down locations will consider the containment and appropriate disposal of removed soil and runoff. Clean-down will be required for vehicles, machinery and personnel clothing exiting the area. This will involve the following steps: scrape off soil (clumps, lumps and thick caked

on soil), manure and organic material from vehicles, machinery and personnel clothing with a shovel and/or hard bristled brush.

Spray/rinse with Phytoclean vehicles and machinery areas and footwear or other items areas that have contacted soil.

These locations and requirements will be communicated to all personnel.

Construction

Updated to reflect B Lane Reply evidence and M Cole evidence

21

Page 22: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

M Cole evidence:

A survey every 200m along the proposed pipeline would be necessary to determine the active contamination sites. Plant and equipment could not move between these sites without washdown. Plant and equipment could not move across farm boundaries between infected and non-infected farms without washdown. Washdown between properties is essential.

Bunded washdown pads are concreted with containment drains and facilities to sanitise the collected water and soil. Adequate testing of the soil and water before it is released from the site for safe disposal. Risk is reduced for grassland but is high for vegetation, so testing is adjusted accordingly.

If considering the models for information on presence or absence of the pathogen, then they need to be used pragmatically. If the pipeline is following an existing easement then risk is lower. If in vegetation then risk is high. The pipeline should be tested along its length for the presence of Pc. Pc is in the agricultural land so cleaning from property to property is essential. If in a crown land easement then risk is lower.

Accepted in part as above. Concrete wash down bays not accepted

S6 Vehicles and plant are to be free of soil clumps and sods prior to exit from site.

Construction

Surface water and Groundwater

G1 Facilities designThe Pakenham Delivery Facility will be designed to maintain existing overland flow paths and not result in increased flood risk upstream of the site.

Pre-construction

G2 Water Sensitive Urban Design (WSUD) treatmentsWSUD treatments will be incorporated into the site design for the Pakenham Delivery Facility to capture surface runoff and reduce pollutants in accordance with the Best Practice Environmental Management Guidelines (CSIRO 1999).

Pre-construction

22

Page 23: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

G3 Sourcing of groundwater for construction supply (if required) will be in accordance with Section 50 Licence to take and use water of the Water Act 1989.

Construction

G4 An up to date bore search will be undertaken prior to construction to identify any new bores that have the potential to be affected by the works.If a groundwater bore is impacted by construction activities, the location, condition and functionality of the bore will be visually confirmed and make-good arrangements will be agreed in consultation with affected landholders, if required.

Construction Post-construction

J Medd evidence, supported by C Smitt

Fuels & chemicals

F1 Dangerous goods, as defined by the Australian Dangerous Goods Code, and flammable and combustible liquids will be stored and handled in accordance with all relevant Australian Standards including but not limited to the requirements of: Australian Standards AS1940, AS1210, AS4343,

AS3846, AS2941, AS/NZS60079; EPA Publication 347: Bunding Guidelines; EPA Victoria Publication 1698 – Liquid Storage

and Handling Guidelines Victorian Worksafe Codes of Practice; Manufacturer’s instructions; and Relevant safety data sheets.

Pre-constructionConstruction Post-Construction

F2 The following measures will be implemented to ensure that fuel and chemical storage is safe and spilt liquids do not cause environmental harm: The type and volume of liquid material (fuel, oil,

lubricant) stored on-site for construction activities is to be limited to only that which is required.

Liquid material will not be stored within 50 m of waterways.

All liquid material will be stored within containment facilities (e.g. bunded areas, leak proof trays) at a designated area(s) within the site.

Pre-constructionConstruction Post-Construction

23

Page 24: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

F3 Safety data sheets will be available for reference for all fuels and chemicals at the storage location.

Pre-constructionConstruction Post-Construction

F4 Spill kits will be available at all locations where machinery/plant are operating, refuelling points and fuel and chemical storage locations.

Refuelling of vehicles and machinery (excluding hand held machines) on the ROW will:

a) be undertaken with appropriate measures to contain spills;

b) utilise auto shut off valves; and

c) not occur within 50m of a watercourse.

Pre-constructionConstruction Post-Construction

Expanded to cover matters from SW08

F5 Where flammable or combustible chemicals are required to be stored on-site, fire-fighting equipment proportionate to the risk of the materials stored will be available for the duration of the material storage.

Pre-constructionConstruction Post-Construction

F6 Fire extinguishers (complying with relevant Australian Standards) are to be provided and validated in all construction vehicles

Construction

F7 Only qualified and trained personnel with knowledge of appropriate personnel protective equipment, chemical handling, spill response and recovery procedures will handle chemicals within the site.

Pre-constructionConstruction Post-Construction

F8 Diesel generators will be bunded. Construction

24

Page 25: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

F9 Vehicles/plant/machinery/equipment will be maintained in good condition to minimise the potential for leaks/spills to occur

Pre-constructionConstruction Post-Construction

F10 Daily vehicle and equipment inspections will be undertaken to check for oil, lubricant or fuel leaks and general wear and tear of hoses.

Pre-constructionConstruction Post-Construction

F11 Monitoring of chemical and fuel storage facilitiesVisual monitoring of chemicals and fuel storage facilities will be undertaken as part of routine operational practices, with inspections completed weekly.

Pre-constructionConstruction Post-Construction

F12 Should a spill/release occur the Contingency Plan for Chemical/Fuel Spill Response will be followed (refer to Section 6.1).

Pre-constructionConstruction Post-Construction

Waste

W1 Waste will be managed in accordance with Environment Protection (Industrial Waste Resource) Regulations 2009, including establishment of appropriate and secured waste storage locations on-site, as required.

Construction

25

Page 26: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

W2 Waste management will comply with the EPA waste hierarchy - waste avoidance, waste re-use, waste recycling, and waste disposal.

Construction

W3 Identification of suitable waste disposal locations will occur prior to construction commencing in consultation with licenced waste contractors.

Construction

W4 The work site will be kept free of litter and waste.Waste containers will be located at each worksite to enable collection of waste, with regular removal from worksites to designated storage areas. Waste containers will be available for different types of waste generated.Refuse containers will be lidded to mitigate fauna access

Construction

W5 Liquids, such as sump oil, diesel and kerosene that cannot be reused are to be placed in labelled regulated waste drums. A licensed contractor will collect it for recycling or licensed disposal.

Construction

W6 Disposal of any waste contaminated soil will be undertaken in accordance with EPA Publications IWRG 821: Waste Transport Certificates and IWRG 822: Waste Codes and will require the use of EPA-registered trucks for transport of the soil to appropriately licensed landfills. Contaminated soil will be remediated or disposed of at an EPA approved facility in accordance with EPA waste disposal guidelines.

Construction

W7 Portable toilet facilities will be available for work construction crews at designated locations. Toilets will be self-bunded portables. Clearing of portable toilet facilities, including waste collection and disposal, must be by a licensed waste contractor.

Construction

W8 Where excess soils, including HDD screened cuttings, are required to be disposed off-site, these will be sampled and categorised in accordance with EPA Victoria Publications IWRG702 – Soil Sampling and IWRG621 – Soil Hazard Categorisation and Management.

Construction

26

Page 27: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref Environmental Controls Project Phase Explanation of Changes

W9 Drilling muds will be disposed in accordance with Environment Protection (Industrial Waste Resource) Regulations 2009 and EPA Victoria Industrial Waste – Classification for Drilling Mud, Victoria Government Gazette G37.

Records of HDD mud disposal will be maintained and kept for 2 years as per the EPA Victoria Industrial Waste – Classification for Drilling Mud.

Construction

W10 Appropriate receptacles provided and used for cigarette butt disposal.

Construction

Sustainability and greenhouse gas

SG1 Source local materials and labour

Locally sourced materials, including those provided by suppliers, will be considered and implemented where they are of comparable quality and utility. Contractors will provide reasonable opportunity for subcontractors and labour from regions local to the Site (including, without limitation, the shires of Casey, Cardinia and Mornington Peninsula) to be engaged on the Works.

Pre-constructionConstruction

O Boushel evidence

SG2 Low embodied energy materials

Low embodied energy materials (e.g. substituting concrete mixes) will be considered and used where they are of comparable quality and utility.

Pre-constructionConstruction

SG3 Managing the quality of materials

The quality of key materials (i.e. pipe and pipe fittings) will be inspected before supplying to site or ROW for installation to avoid additional transport and handling of materials.

Pre-constructionConstruction

27

Page 28: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Table 9-G: Performance standards (Clear and Grade, Right of Way Maintenance)

Performance Standards – clear and grade, Right Of Way Maintenance

Objective To plan and manage environmental impacts associated with the proposed clear and grade, and right of way maintenance activities.

Target Retain soils and maintain soil condition. No sedimentation of water outside of the designated work areas.

Application

During clear and grade activities and through construction to reinstatement.

Ref. Environmental Controls Project Phase

Explanation

Clear and Grade, Right of Way Maintenance

C1 Vegetation will be cleared prior to stripping of topsoil. Construction

C2 Topsoil will not be stripped when saturated. Construction

C3 Topsoil will be stripped across the construction footprint to maximum depths determined during pre-construction surveys.

Construction

C4 Stripped topsoil will be stockpiled separately from woody material and subsoil stockpiles.

Construction

C5 Topsoil stockpile heights will not exceed two metres. Construction

C6 Gaps in the linear topsoil stockpiles will be left at appropriate intervals for the movement of vehicles and fauna through the site.

Construction

C7 Soil stockpiles will be managed to reduce impacts to surface water runoff: the creation of a continuous row of stockpiled

materials that cause water to pond on the upstream side will be avoided.

where drainage lines intersect the RoW, flow diversion measures will be placed upstream of soil stockpiles.

surface water runoff from external catchments will be directed through regular gaps in soil stockpiles where ESC are installed to allow runoff to pass over

Construction

28

Page 29: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref. Environmental Controls Project Phase

Explanation

the RoW at a controlled location without causing erosion.

C8 Topsoil stockpiles, other than linear stockpiles on the ROW, will be clearly signposted.

Construction

C9 ESC will be established immediately after clear and grade activities.

Construction

C10 Erosion and sediment controls (ESC) for the site will be implemented in accordance with EPA Publication 275: Construction Techniques for Sediment Pollution Control.

Construction

C11 Construction will be restricted during heavy wet weather and during wetter months/periods in low lying areas and will be stopped if working conditions are causing excessive compaction and surface rutting.

Construction

A McCowan evidence

C12 The weather reports and warning services will be monitored in order to efficiently plan construction works and review the capacity of erosion and sediment controls.

Construction

C13 Diversion measures and ESC devices will be checked prior to forecast rain events to ensure these are maintained in good condition.

Construction

29

Page 30: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Table 9-H: Performance standards (Trench management)Performance Standards – trench management

Objective To plan and manage environmental impacts associated with the proposed trenching activities and other excavations.

Target Maintain soil condition. No contamination of soils or groundwater.

Application

During trenching, padding and backfill activities.

Ref. Environmental Controls Project Phase Explanation of Changes

Trench management

T1 Identification of third party servicesAll third party services within the easement, including on farm infrastructure, will be identified and marked on the ground in advance of trenching activities.

Construction

T2 Stockpiles of trench spoil will be separate from topsoil.

Construction

T3 Excavated pits and trench to have fauna egress points and fauna shelters not more than 250m apart

Construction

T4 The duration that trench sections and bell holes are open will be minimised to reduce the potential for poor quality runoff impacting groundwater.

Construction

T5 Dewatering If trenching is to occur within a Southern

Toadlet habitat area because HDD is not feasible, no earthworks will be carried out during the Southern Toadlet breeding season (generally March to November).

Non-contaminated groundwater and surface runoff that enters the open trenches and bell holes will be managed in accordance with SEPP (Waters).

Water will be tested for pH and salinity prior to discharge to land. pH will be between 4 and 9, and salinity will not exceed 6,000 µS/cm.

Water that cannot be treated to meet the

Construction Response to

Document 441 (J Urlus)

30

Page 31: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref. Environmental Controls Project Phase Explanation of Changes

relevant discharge criteria will be disposed to an EPA Victoria licensed facility.

Dewatering of excavated trenches/bellholes will be managed to minimise sedimentation, including the use of sediment control devices to remove suspended solids and dissipate flow as described in EPA publication 480 (Section 4.4 Dewatering work sites) and EPA publication 275 (Section 16 Water treatment). Sediment control devices may include, but are not limited to:

i. settlement pondsii. floating pump intakesiii. filtered intakes/outlets

Discharge will be to low gradient, stable, grassed areas and through ESC systems to prevent scour or erosion.

Discharge to land will not occur within 50 metres of watercourses.

Water will not be discharged directly to waterways or into stormwater drains without prior approval from relevant authorities.

Visual monitoring will be undertaken during discharge to land.

Where groundwater is entering excavations, dewatering activities will be limited to two days or less in trenched sections and HDD tie-in bell holes, and 10 days or less at thrust bore sections and thrust bore bell holes.

T6 Trench breakers will be installed adjacent to watercourses, wetlands and steep slopes as shown in the standard drawing (CPT.2373-DWG-L-0106).

Construction

T7 Compaction of backfill using excavated material will be carried out to reduce the potential for preferential lateral flow along the trench

Construction

T8 Topsoil will not be used as a padding or backfill material.

Construction

T9 Any material imported for use as backfill will comply with the EPA Victoria Publication IWRG621 – Soil Hazard Categorisation and Management for ‘Fill Material’, and must be accompanied by relevant documentation confirming its compliance to the ‘Fill Material’ criteria.

Construction

31

Page 32: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref. Environmental Controls Project Phase Explanation of Changes

T10 Soil will be visually assessed for possible soil contamination such as discolouration, odours, buried waste and abnormal soil structure.Where potentially contaminated soils (including asbestos containing material) are uncovered during construction, the following measures will be undertaken: Cessation of ground disturbance at the

location and within the immediate vicinity. Assessment of site contamination and

determination of appropriate management actions in consultation with suitably qualified personnel.

If contamination is confirmed, the EPA will be notified as soon as reasonably possible.

Construction

T11 Contaminated SoilsContaminated soil will be managed in accordance with the SEPP (Prevention and Management of Contaminated Land). All Project personnel will be made aware of

the presence of contaminated soils at the locations identified in the Environmental Line List (Attachment G) and any new sites as they are identified.

An intrusive investigation will be undertaken in the area between KP7.3 and KP7.9 (including PFAS) once vegetation has been cleared, to confirm the presence or absence of contaminated soils, due to historical and existing land uses. Should contamination of soil and/or groundwater be encountered, appropriate management actions will be determined in consultation with suitably qualified personnel.

Construction works during wet weather (i.e. winter and spring e.g. June – September) will be avoided unless conditions are such that contaminated soils and surface water issues can be managed. 

Contaminated soils will be left in situ to the extent possible.

Where it is necessary to excavate contaminated soils, they will be stockpiled separately, with containment and treatment measures appropriate to the type of contamination present.

Handling and transport of contaminated spoil for off-site treatment/disposal will be in

Construction

Updated to respond to J Medd recommendation in Reply to C Smitt evidence

32

Page 33: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref. Environmental Controls Project Phase Explanation of Changes

accordance with Environment Protection (Industrial Waste Resource) Regulations 2009 and waste management standards set out in this EMP.

T12 Contaminated groundwater/trench water Contaminated groundwater/trench water will

be managed in accordance with:– SEPP (Waters)– PFAS National Environmental

Management Plan. All Project personnel will be made aware of

the presence of contaminated groundwater containing PFAS east of the former Tyabb landfill (Environmental Line List - Attachment G).

Where there are open excavations adjacent to the former Tyabb landfill site, the excavation will be monitored for landfill gas as part of morning pre-start checks and prior to any hot works commencing.

Disturbance of saturated soil and groundwater within the PFAS affected area will be minimised. The management plan will include measures to prevent migration of PFAS into the surrounding soil or surface water.

An intrusive groundwater investigation will be undertaken in the area between KP7.3 and KP7.9 prior to commencing pipeline construction, to confirm presence or absence of contaminated groundwater within the area, due to historical and existing land uses.

Water from areas that have been identified as contaminated will not be discharged to the environment (land, waterways, sewer).

Contaminated water will either be treated onsite, depending on contaminant encountered (this may require approval from the EPA Victoria) or disposed offsite to an EPA Victoria licensed facility. Alternatively, a construction approach may be adopted where contaminated groundwater is left in-situ (i.e. not abstracted or disturbed).

Where the potential for soil or groundwater contamination has been identified, any imported backfill materials must have similar or lower hydraulic conductivity to the surrounding soils.

Construction

In response to M Davidson evidence

In response to J Medd evidence

33

Page 34: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref. Environmental Controls Project Phase Explanation of Changes

T13 All soils are to be managed in accordance with the Acid Sulfate Soils Management Protocol (Attachment K).Note: V Wong recommendations to Mitigation Measures do not appear to take into account Attachment K.

Construction

Attachment K has been updated to capture J Medd evidence

T14 A dewatering plan must be developed and provided to DELWP Pipelines Group in circumstances where:

i) more than two days (48 hours) of dewatering is required at a trenched section or HDD tie-in bell-hole, or

ii) more than 10 days (240 hours) of dewatering is required at a thrust bore location, or

iii) exceedance of these durations is anticipated to occur in the course of the works, in which case the dewatering works should cease and groundwater levels allowed to rebound until such time as an approved dewatering plan is prepared.

The dewatering plan should include distance drawdown estimates to assess potential impacts to groundwater users, installation and monitoring of shallow monitoring wells, and/or groundwater ingress mitigation measures.

Construction

J Medd evidence, supported by C Smitt

T15 C Smitt: recommends:

Prior to project approval a groundwater monitoring event should be undertaken in early spring. Confirm if findings agree with current assumptions, if not, revisit impact assessment.

Before construction starts :

a An ecological st to survey is to be undertaken between KP55.1 and KP 55.5 to determine the presence (or otherwise) of any GDEs and qualitative degree of groundwater dependence ; and

A dewatering plan is to be prepared in

In response to Document 400 (C Smitt) Not accepted on basis that unnecessary, and TN 39 (Document 305) confirms impact and provides dataNot accepted on basis that GDEs have

34

Page 35: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref. Environmental Controls Project Phase Explanation of Changes

consultation with a terrestrial ecologist to ensure any identified GDE is not stressed by construction and full recovery of the perched water table is achieved . along the alignment with the outcome to inform an updated risk and impact assessment .

The dewatering plan is to be approved by the DELWP Pipelines Group.

been considered in Technical Report B

T16 Any fill imported for backfilling will be inspected before use to ensure it is free of pests and weeds.

MPSC – This is of particular concern in sensitive environmental areas such as Warring ine Park.

35

Page 36: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Table 9-I: Performance standards (Watercourse Crossings)Performance Standards – Watercourse crossings

Objective To plan and manage environmental impacts associated with the proposed watercourse crossings.

Target No destabilisation of the watercourse or sedimentation of water outside of the designated work areas.

Application

During the installation of pipe across watercourses.

Ref. Environmental Controls Project Phase

Watercourse Crossings

WC1 Work on a designated watercourse (as identified Attachment G – Environmental Line List), must have a CMA permit for Works on Waterways. All works must be completed in accordance with CMA permit requirements. Work requiring a permit includes, but is not limited to, installation of temporary culverts, vegetation removal and trenchless construction where entry/exit is within 30 m to the watercourse.

Construction

WC2 The proposed design and the work method statements, including HDD profiles where applicable, are to be submitted to Melbourne Water and approved prior to the commencement of works at watercourses managed by Melbourne Water.

Construction

WC3 Watercourse trenchless crossingWhere identified in the environmental line list (Attachment G), trenchless construction methods will be used to avoid open cut construction across flowing watercourses.

Construction

WC4 Watercourse trenchingWhere trenching is undertaken over a watercourse the following mitigation measures will be undertaken: Trenched crossings of ephemeral watercourses will

preferentially be constructed during no or low flow conditions.

Weather forecasts will be monitored to minimize the likelihood of having open trenches at the waterway when high rainfall events are expected.

Where watercourses are trenched, all obstructions to flow will be removed after the pipe has been laid and backfilled.

The pipeline will be assembled and prepared so that it can be immediately installed once the trenching over

Construction

36

Page 37: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref. Environmental Controls Project Phase

the watercourse has been undertaken. The exposed trench within the watercourse and riparian

zones will be reinstated immediately following the installation of the pipeline.

Waterway reinstatement will be designed to avoid future erosion over the pipeline alignment. This may include the use of riprap made of stones to stabilise the waterway.

Temporary ESC will be provided as needed to prevent erosion and scour until the vegetation has established.

Visual monitoring will be undertaken downstream of the trench during flow events if the trench has not been reinstated.

Temporary diversions will be provided if there is permanent or tidal flow in the waterway in accordance with International Erosion Control Association (IECA) Best Practice Erosion and Sediment Control Appendix P: Land-based Pipeline Construction (2008). Flow diversion measures may include pumps to ensure that water can be moved from one side of trench to the other, screened inlets (or other appropriate equipment) to minimise the entrapment of aquatic fauna and outlet structures that are designed to avoid scouring of the channel.

WC5 No above-ground grit blasting will occur within 10m to top of bank of a watercourse

Construction

WC6 Soil and other materials will not be stockpiled near waterways. Material will be located away from the top of banks so that there is no restriction to the flow conveyance area.

Construction

37

Page 38: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Table 9-J: Performance standards (HDD and Horizontal Boring)Performance Standards – Horizontal Directional Drilling & Thrust Boring

Objective To plan and manage environmental impacts associated with the proposed HDD and thrust boring activities.

Target No loss of material or contamination of land or water outside of the designated work areas.

Application

During the installation of HDD and thrust bored crossings.

Ref. Environmental Controls Project Phase Explanation

Horizontal Directional Drilling & Thrust Boring

D1 For HDDs, the drill profile design, the work method statement and the proposed volumetric drilling fluid tracking program, including proposed intervention levels, is to be submitted to DELWP and approved prior to the commencement of HDD activities.

Pre-construction

D2 An Inspection and Test Plan will be developed to ensure quality control during the HDD activities.

Pre-construction

D3 Earth bunds and drainage channels will be placed around the upper edges of drill sites and work areas, to divert natural run-off around and away from the site so that it doesn’t mix with drilling compound runoff.

Construction (HDD Activities)

D4 Sump pits will be constructed at the bottom of the drill site. The sump pit will be positioned (during site planning) so as all runoff from the drilling compound will flow into it. The sump pit is to be of such dimensions to provide a buffer for the drilling fluid returns. An earth bund will be placed around the sump pit to contain any spillage.

Construction (HDD Activities)

38

Page 39: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

D5 The sump pit will be pumped out into the mud system at the end of drilling each day.

Construction (HDD Activities)

D6 A volumetric drilling fluid tracking program will be implemented to monitor fluid use during drilling operations with defined levels for fluid loss, stop works and further investigation.

Construction (HDD Activities)

D7 Drilling must use will preferentially use non-toxic (e.g. bentonite) and/or biodegradable drilling muds, where geotechnical conditions allow.The composition of HDD drilling muds and an assessment of their environmental risk will be included in the HDD Management Plan required under D1.

Construction (HDD Activities)

Updated to better reflect J Medd evidenceC Smitt says J Medd recommendations should be adopted

D8 Appropriate spill response and clean-up equipment (e.g. sandbags, vac-truck) will be on-site during HDD activities. Except between KP 1.13 and KP 1.8, iIf a spill/release occurs the Contingency Plan for  Chemical Spill response in Appendix F (refer to Section 6.1) will be implemented. (Refer also to Section 6.1). A frac-out/release of drilling mud release between KP1.13 and KP 1.8 (HDD Location 3), is to be treated as a major spill and the Sun Orchid Emergency Protection and Salvage Plan in Appendix # will be implemented immediately.

Construction (HDD Activities)

In response to Document 427 (G Lorimer)This requires further work in the form of a Sun Orchid Emergency Protection and Salvage Plan to be prepared to address particular containment, clean-up and salvage works in the event a frac-out occurs within Merran’s Sun Orchid habitat.

39

Page 40: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

D9 HDD noise control

A minimum of 10 dB noise reduction will be installed adjacent to the following HDD sites: HDD Location 3: Warringine Park (northern

work site) HDD Location 4: Along the railway corridor,

southern end of Hastings HDD Location 5: Along the railway corridor,

northern end of Hastings HDD Location 6: Beneath Kings Creek along

the railway corridor.Stationary equipment such as generators and pumps will be stored within shipping containers or suitable acoustic enclosures at all HDD locations. The impacts and the design of site-specific mitigation will be determined prior to construction works via acoustic modelling and confirmed during construction via onsite monitoring.

Construction (HDD Activities)

D10 Suitably qualified contractors

Contractor(s) that are suitably qualified and experienced in trenchless installation techniques and piling installation will be used.

Construction (HDD Activities)

Moved from A12 as relates only to HDD

New D11

Inspections

The HDD alignment and return lines will be inspected regularly on foot for mud release, at a frequency not less than 2-hourly

Construction (HDD Activities)

In response to G Lorimer evidence. See also TN27

Table 9-K: Performance standards (Hot works)Performance Standards – Hot works

Objective To plan and manage environmental impacts associated with hot works during construction of the new pipeline.

Target No hot works impacts to land or property. No non-conformance with these performance standards.

Application

The duration of pipeline construction.

40

Page 41: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref. Environmental Controls Project Phase

Hot works

F1 Hot-works will only be undertaken on non-vegetated/cleared areas with a minimum of 5m to combustible materials. A fire response unit will be in place next to the works for the duration of any hot works with a capacity of not less than 1000L with a dedicated spotter.

Construction

F2 During the CFA declared Fire Danger Period, hot works must comply with CFA restrictions: a fire-resistant shield or guard is in place to stop sparks,

hot metal or slag an area at least 1.5 metres from the operation is clear of

flammable material or wetted down sufficiently to prevent the spread of fire

a hose connected to a reticulated water supply or water spray knapsack containing at least 9 litres of water

all cut-offs and hot materials from the operation are placed in fire-proof containers

a person is in attendance at all times while the fire is alight (hot work in progress) and has the capacity and means to extinguish the fire

the fire is completely extinguished before the person leaves.

Where the requirements of EMP management standard F1 are more stringent, they will take precedence.

Construction

F3 On Total Fire Ban Days, any hot works must have a CFA Section 40 permit in place and must comply with the conditions of the permit.

Construction

41

Page 42: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Table 9-L: Performance standards (hydrostatic testing)Performance Standards – Cleaning, hydrostatic testing

Objective To plan and manage environmental impacts associated with the cleaning and hydrotesting of the new pipeline.

Target No adverse impacts to land or water from cleaning, hydostatic testing. No non-conformance with this performance standard or complaint from landowners or occupiers.

Application The duration of the cleaning, hydrotesting activities.

Ref. Environmental Controls Project Phase

Cleaning, hydrostatic testing

H1 Prior to hydrostatic testing, the pipeline will be pre-cleaned to remove weld debris, dust and surface scale. Produced waste water will be captured in a temporary pit or bunded area and removed by an EPA licenced waste contractor.

Post -construction

H2 All hydrotesting operations will conform to AS2885.5: Gas and liquid petroleum - Field pressure testing.

Post -construction

H3 Where the hydrotest schedule allows, water will be reused to conserve water and minimise the number of discharge locations.

Post -construction

H4 If oxygen scavengers and biocides are used during hydrostatic testing, they will be neutralised before disposal, in accordance with manufacturer guidelines, to ensure that the water is free from any remaining active biocide and oxygen scavengers before discharge to land.

Post -construction

H5 Water will be sampled and analysed by a NATA accredited laboratory to ensure that no biocides (sodium hydroxide, tetrakis(hydroxymethyl) phosphonium sulfate) and oxygen scavengers (ammonium bisulfite) are detected, and to establish an adequate method of disposal or reuse, after the hydrostatic testing water is no longer needed.

Post -construction

H6 Hydrostatic test water discharge will only be undertaken where water designated for release into the environment is of a quality that is within relevant statutory water quality guidelines. Relevant landholder(s) will be consulted prior to any discharge of hydrostatic test water to land.

Post -construction

H7 Dams and hydrostatic test water may remain for landholders’ beneficial use with landholder and regulatory approval if water quality requirements are met.

Post -construction

42

Page 43: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref. Environmental Controls Project Phase

H8 Where hydrostatic test water is not consistent with relevant statutory water quality guidelines, hydrostatic test water will be removed by an EPA licenced waste contractor.

Post -construction

H9 Any discharge of hydrotest water will not result in soil erosion or sedimentation of land or water. Sediment control devices to remove suspended solids such as geotextile fabric filters will be used. No direct discharge will occur to watercourses or drains.

Post -construction

H10 Pumps and compressors used for hydrotesting and pigging activities will be muffled to reduce noise in accordance with the EPA Environmental Guidelines for Major Construction Sites, Publication 480 and Noise Control Guidelines, Publication 1254.

Post -construction

43

Page 44: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Table 9-M: Performance standards (reinstatement)Performance Standards – Reinstatement

Objective To allow for the return of the land to its previous land use and capacity.

Target Landowner/occupier satisfaction with completion of works and timely rectification of any defects.

Application The duration of the proposed reinstatement works and the identified defects liability period.

Ref. Environmental Controls Project Phase

Reinstatement

R1 Project activities will be progressed sequentially, with clean-up, restoration and rehabilitation as soon as installation activities are complete unless weather conditions prevent this.

Construction

R2 Stockpiled topsoil and sub soils will be reinstated to depths consistent with the original soil horizons.

Construction

R3 Topsoil will not be respread for rehabilitation when saturated.

Construction

R4 Soil inversion will be avoided during respreading of topsoil Construction

R5 The site will be reinstated to pre-existing contours with natural drainage lines restored and protected if required as determined by post construction assessments.

Construction

R6 Any topsoil imported for reinstatement or easement maintenance will be of an appropriate quality and as agreed with the landholder.

ConstructionPost- Construction

R7 Soil surfaces that have been compacted due to construction activities, such as those subject to traffic and/or storage areas within the site, will be ripped to allow the topsoil to bind with the subsoil and increase water filtration.

Construction

R8 Where required as determined by post construction assessments and in consultation with the landholder, Soil amelioration and fertiliser will be applied will be undertaken as part of the reinstatement activities.

Post -construction

44

Page 45: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref. Environmental Controls Project Phase

R9 Seeding for revegetation and soil stabilisationWhere seeding is adopted to facilitate prompt revegetation and soil stabilisation, the following principles will be considered: Seed mixtures to be formulated with consideration of

the vegetation composition of the areas adjacent to the construction footprint and in consultation with the relevant landholder. Only certified seed to be used.

Sterile seed stock (cover crop) may be used to provide short term surface stability.

Seed to be evenly dispersed over the disturbed area. Seeding to take place as soon after reinstatement of the

soil profile as the weather allows.

Post -construction

R10 If weather conditions prevent the prompt reseeding of the disturbed areas within the site (refer to R6), controls will be put in place, monitored and maintained to manage erosion and sedimentation until such time reseeding can occur and soils are stabilised.

Post -construction

R11 Reinstatement of infrastructureAll access tracks, fences and gates will be reinstated post construction in consultation with landholders and any relevant third parties.

Post -construction

R12 Habitat features removed during construction such as large hollow logs and large rocks will be returned to the ROW during rehabilitation if consistent with rehabilitation objectives at a particular location. Landholder requirements will be considered prior to returning habitat features to the ROW

Post -construction

R13 Rehabilitation by assisted natural regeneration will be undertaken on the ROW, except within four metres of the pipeline, in areas where there is an increased risk of habitat fragmentation (as identified in the Environmental Line List (Attachment G) but with the following changes:).

Planting of trees or over-shading shrubs growing over 2 metres in height will be avoided in and adjacent to areas of Swamp Skink habitat.

Revegetation in Swamp Skink habitat will focus on establishing continuous or near continuous ground layer plants, particularly grasses, sedges and rushes.

Post -construction

Response to Document 441 (J Urlus)

45

Page 46: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Ref. Environmental Controls Project Phase

R14 The following measures will be implemented to reinstate area of Southern Brown Bandicoot habitat and contribute to predator control in and surrounding the alignment as identified in the Environmental Line Lis (Attachment G): Dense cover of suitable native shrubs or vegetation of

similar structure will be reinstated, other than directly above the pipeline and a narrow track to allow ground access for surveillance patrols. Easement agreements with landholders will require that this vegetation be reinstated and protected.

Rapid re-establishment of dense ground cover will be achieved at any of the sites of known or assumed presence for the Southern Brown Bandicoot impacted by the construction footprint, but not subject to HDD, by planting of semi-mature native shrubs, or fast-growing tubestock, at an appropriate density during rehabilitation. The aim is to re-establish dense understory vegetation in the 0.2–1m height range.

Woody branches and hollows removed from the ROW during construction are to be used to create Southern Brown Bandicoot shelter piles under the supervision of a suitably qualified wildlife handler.

A material contribution, to existing programs or agency land managers, for the long-term management of introduced predators in and surrounding the study area, commensurate with the spatial scale of the project and covering at least 10 years.s.

Post -construction

Response to Document 441 (J Urlus)

R15 In consultation with landowners and occupiers, targeted control of weeds will be undertaken by a qualified pest plant control contractor to ensure that the site does not have an increased density and distribution of noxious and agricultural weeds relative to adjacent areas

Post -construction

R16 Following completion of reinstatement, written agreement will be sought from landowners (and occupiers, managers or government agencies as applicable) of the satisfaction of the reinstatement works.

Post -construction

R17 Following the completion of reinstatement activities, the site will be monitored for a period of 12 months to ensure the land is stable, consistent with adjacent areas and vegetated with site appropriate vegetation. Any defects from construction will be rectified during this time and following this period any residual environmental issues will be addressed through the APA’s Operating Environmental Management Plan.

Post -construction

R18 Following the landowners written agreement of acceptance of the reinstatement works (R16) or the expiry of the 12 month defect liability period (R17), APA will seek the return of the rehabilitation bond for the works from DELWP.

Post -construction

46

Mornington Peninsula Shire Council , 27/11/20,
In respose to Documnt 441 (Jake Urlus changes), MPSC requests the Proponet re-draft this control to include include clear time frames for rapid re-establishment of habitat and for monitoring.
Page 47: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

47

Page 48: Crib Point Pakenham Pipeline Project · Web viewAdopting engineering noise controls at the source (e.g. silencer, mufflers, enclosures) by the best practical means using current technology

Construction Environment Management PlanCrib Point Pakenham Pipeline ProjectDay 1 amendments. Day 2 changes shown with highlight & explanation in last columnOther party recommendations in green & explanation in last column

Table 9-N : Performance standards (Pakenham Delivery Facility) Performance Standards – Pakenham Delivery Facility

Objective To plan and manage risk associated with the Pakenham Delivery Facility

Target To ensure the location specific individual risk (LSIR) contour for ‘1 in a million per year' (1.00E-06) does not affect any area subject to an applied residential zone under Cardinia Planning Scheme clause 37.07 - Urban Growth Zone, schedule 5 - Pakenham East Precinct Structure Plan

Application

Pakenham Delivery Facility

Ref.

Controls Project Phase

Explanation

Pakenham Delivery Facility

P1

Risks associated with the Pakenham Delivery Facility should be mitigated such that the location specific individual risk (LSIR) contour for ‘1 in a million per year' (1.00E-06) does not affect any area subject to an applied residential zone under Cardinia Planning Scheme clause 37.07 - Urban Growth Zone, Schedule 5 - Pakenham East Precinct Structure Plan to the satisfaction of Energy Safe Victoria

Construction

In response to recommendations in K Filippin evidence

48