crane mobile specification

Upload: sancakemre

Post on 01-Mar-2016

117 views

Category:

Documents


7 download

DESCRIPTION

Crane mobile Specification

TRANSCRIPT

  • JOB SAFETY ANALYSIS

    SAFE WORK METHOD STATEMENT

    Rev 0 LIFTING SAFELY Page 1 of 13

    1. ACTIVITY OR TASK: 200T Mobile Crane Lift Location / Project:

    JSA preparation by: Ian Nathan HSEC Manager, Structural Cranes Job No:

    JSA No: STR031 JSA Rev: 0

    Competence/Qualifications required to complete work safely

    WorkCover NCC CO / DG / RB / RI / RA WorkCover General Construction Induction Card Structural Cranes Induction

    Codes of Practice & Legislation that are applicable:

    The AS 2550 series is referenced in the NSW Code

    of Practice Technical Guidance that supports the

    Occupational Health and Safety Regulation 2001

    (the Regulation), and which is called up under

    Section 43 of the Occupational Health and Safety

    Act 2000

    JSA reviewed by person responsible i.e. Team Leader / Supervisor

    Name Position/Competence/License: Date:

    2. HAZARD IDENTIFICATION Identify hazards that may be present by ticking items on the list below. 3. PRECAUTIONS: hardhat, safety glasses, safety boots compulsory

    CONFINED SPACE HAZARDOUS AREA HIGH RISK HIGH RISK ADDITIONAL PRECAUTIONS PERMITS Difficult Entry/Exit Hazardous Substances

    - attach MSDS to JSA

    Falling Objects Suspended loads Gloves: type - Riggers Hot Work Oxygen Deficiency Poor Lighting Poor Visibility Goggles Excavation

    Oxygen Excess Working at Heights Slippery Surfaces Inhale able Dusts/Fibres Full Face Shield Confined Space

    Engulfment Remote Area Multiple Electrical Feeds High Noise Levels High Visibility Vest Hazardous Work Clearance Poisonous Gas Present Motor Room Hazards Trip Hazards Use of Chemicals Harness C&A 6 Access to Area Temperature Extremes Toxic Substances Electrical Hazards Elevated Work Platform Fire Extinguishers High Voltage Access

    Biological Hazards Potential for Difficult Rescue

    Electrical High Fault Level work 400 amps or greater

    Difficulty to Communicate amongst workers

    Barricades Scaffolding

    Explosive Gas Present Ventilation Other?

    Manual Handling Moving Machinery Lighting

    HAZARDOUS SUBSTANCES in work area / to be used -attach MSDS Sharp Materials Tools & Equipment Erect Scaffolding to access SPECIAL ISSUES:

    1. Diesel Ladders used in the task Radiation Respirator or Dust mask 2. Castrol TQ DIII Working at Heights Traffic Movement Erect Warning signs

    3. Castrol EPX 85W-140 Working near Crane & Crane Runways

    Working near Operation Processing Lines

    Personal Locks or Tag system

    4. Castrol LSX 90 Group isolation

    5. Castrol Tection Rail Movement Live Rails Welding screen

    6. Castrol Cool Plus Pressurised Fluids Pneumatics Fall Arrest systems

    7. Valvoline Ultramax 68 Flammable Materials Present

    Lifting Gear - Shackles, Chains, Slings, etc

    Welding Face Shield

    4. ENVIRONMENTAL HAZARDS - tick those identified

    Air Pollution (dust, fumes) Spills to ground Other:

    Noise (plant & equipment) Soil Erosion Steel / copper

    Spills to drains/waterways Hazard to Flora /Fauna

    5. EQUIPMENT REQUIRED:

    Static Plant & Equipment

    Mobile Plant & Equipment 200T Demag AT Mobile Crane

    Safety / Emergency Equipment

    CONSEQUENCES

    1 Low: Short-term temporary inconvenience or symptoms, no medical treatment; environmental nuisance, limited temporary damage to immediate, low significance environment.

    3 Minor: Medical treatment injury, short-term reversible disablement; minor short-term effects on local environment, or small area of limited significance.

    10 Moderate: Serious injury with some permanent disablement; moderate

    widespread short-term impact on local environment of limited significance.

    30 Major: Single fatality, serious injury with severe permanent disablement; serious widespread, medium-term environmental harm to local environment, some ecosystem impairment.

    100 Critical: Multiple fatalities, major irreversible health effects to > 50 people; major widespread, long-term environmental harm to significant environment or ecosystem.

  • JOB SAFETY ANALYSIS

    SAFE WORK METHOD STATEMENT

    Rev 0 LIFTING SAFELY Page 2 of 13

    ACTIVITY or TASK: 200T Mobile Crane Lift JSA No: STR031 Rev: 0

    JSA / SWMS OVERVIEW

    Mandatory Job Prerequisites For the purposes of this JSA/SWMS, it is a base operating condition that all mandatory site prerequisites are in place e.g. Structural Cranes Induction, Customers Safety Requirements & Induction, Plant Inspections, Daily Plant Checklists, Prestart Meetings, Mandatory PPE, Site Rules, necessary work permits etc. and are considered minimum standards. Only additional control measures are considered in this JSA.

    Australian Standards relevant to Mobile Crane Lifting:

    AS1418.1 Cranes, Hoists and Winches Gen. Req. | AS1418.5 Cranes, Hoists and Winches Mobile Cranes | AS2550.1 Safe Use Part 1: Gen. Req. | AS2550.5 Safe Use Part 5: Mobile Cranes

    Site PPE Requirements

    JSA Document Index 1. General Crane Safety Overview

    2. Crane Set-up

    3. Crane Lift

    4. Pack up Crane and Return to Depot

    5. Lifting Gear List

  • JOB SAFETY ANALYSIS

    SAFE WORK METHOD STATEMENT

    Rev 0 LIFTING SAFELY Page 3 of 13

    PROCEDURE POTENTIAL SAFETY & ENVIRONMENTAL HAZARDS

    Initial Risk

    Rating

    CONTROL MEASURES Residual Risk

    Rating

    PERSON RESPONSIBLE

    1. General Crane Safety Overview

    General

    Dropped Loads (personnel / static object / equipment / machinery)

    H90 Minimise personnel in works area to essential staff only.

    Personnel only permitted within works area with permission of Structural Cranes Crane Supervisor/Operator.

    Personnel to make eye contact with plant operator before walking near working plant.

    Working area to be delineated with clear signage clearly stating that access is restricted to authorised personnel only.

    Traffic control where necessary

    M30 Operator / Dogman

    Crush injuries (personnel / static object) H300 Personnel and all body parts are to be kept clear of load and placement area

    Use Taglines

    Wear correct PPE (Riggers Gloves)

    Keep hands and fingers clear when slinging loads

    Observe the Load and the load placement area and keep well clear

    M30 Operator / Dogman

    Oil leaks / fluid spills (environmental) L9 Spill Kits are kept on all cranes. L3 Operator

  • JOB SAFETY ANALYSIS

    SAFE WORK METHOD STATEMENT

    Rev 0 LIFTING SAFELY Page 4 of 13

    POTENTIAL SAFETY & ENVIRONMENTAL HAZARDS

    Initial Risk

    Rating

    CONTROL MEASURES Residual Risk

    Rating

    PERSON RESPONSIBLE

    Uneven surface leading to personnel slips /sprains (personnel / static object)

    M30 All personnel in area must wear work boots with ankle support.

    Clear area of trip hazards where practical otherwise mind your step

    L10 Operator / Dogman

    Overhead powerlines - (personnel / static object)

    H300 Always keep the required safe distance between the crane and the powerlines using the distances specified in NSW WorkCover COP Safe work Near Powerlines

    If required to work close to power lines use a spotter or where possible have the power lines turned off

    M30 Operator / Dogman / Spotter

    Plant striking other plant, equipment, personnel, materials, etc - (personnel / static object)

    H100 Plant to be positioned in area clear of obstructions / roads

    Traffic Control When working within an active site traffic zone make sure adequate traffic management is in place

    M30 Site Manager

    Operator / Dogman

    Environmental Conditions (personnel / environmental)

    Sunlight (UV radiation)

    Heat (exhaustion, dehydration)

    Poor lighting (falls, mistakes etc)

    Wet (slippery)

    Mud (bogged)

    Windy (swinging loads)

    H100 Wear appropriate UV protection (PPE)

    Take adequate breaks in shade and air conditioned vehicles when extended periods of hot work is required, maintain intake of fluids (clean cool water)

    Insure lighting is sufficient before commencing work. If lighting is not sufficient obtain artificial lighting or put job off until lighting is suitable to continue.

    Assess wet and windy weather conditions and proceed cautiously or cease work accordingly.

    M30 Site Manager

    Operator / Dogman

  • JOB SAFETY ANALYSIS

    SAFE WORK METHOD STATEMENT

    Rev 0 LIFTING SAFELY Page 5 of 13

    PROCEDURE POTENTIAL SAFETY & ENVIRONMENTAL HAZARDS

    Initial Risk

    Rating

    CONTROL MEASURES Residual Risk

    Rating

    PERSON RESPONSIBLE

    2. Crane Set-up

    Step 1 Mobe Crane to final on site destination

    Faults with Crane

    Plant becoming bogged in sand & mud

    Pedestrians

    Onsite traffic / plant

    M30 Pre-start Checks

    Plant to stick to designated roadways and turning areas

    Personnel on hand to warn others of crane movement in the vicinity or via radio comms where available

    Alternate pathway defined by bollards and reflective tape

    L1 Operator / Dogman

    Step 2 Pre-job Meeting / Toolbox

    Inexperienced workers

    Inadequate consultation

    Inadequate understanding of equipment

    Site hazards and emergency procedures not known

    H100 Sufficiently skilled employees to complete tasks (competencies & licences)

    Adequate consultation with all relevant employees

    Adequate competent supervision throughout the project

    Proper planning for equipment required for the task

    Site + Work Area Inductions compulsory for All personnel

    M30 Site Manager

    Operator / Dogman

    Step 3 Locate cranes in lifting positions on site

    Pedestrians

    Traffic

    Other Plant

    Other Equipment

    Buildings

    Power Lines & underground utilities

    Lift radius

    H90 Spotter required when Franna enters or exits Rod Mill

    Check and Confirm Exclusion Zones

    Barricades, Witches Hats, Danger tape

    Warning signs

    M30 Operator / Dogman

  • JOB SAFETY ANALYSIS

    SAFE WORK METHOD STATEMENT

    Rev 0 LIFTING SAFELY Page 6 of 13

    PROCEDURE POTENTIAL SAFETY & ENVIRONMENTAL HAZARDS

    Initial Risk

    Rating

    CONTROL MEASURES Residual Risk

    Rating

    PERSON RESPONSIBLE

    Step 4 Inspect chains and/or slings, shackles, hooks and attachment points in preparation for use

    Tears in Slings

    Cracks in chains, shackles, rings and hooks

    Dropping of load due to faulty lifting gear or faulty attachment points

    H90 Check slings for rips and tears and remove from service if faults are found

    Check chains, shackles, hooks and rings for cracks, corrosion, wear, cracks, mechanism faults, etc and remove from service if faults are found

    Lifting gear / equipment inspected and tagged with appropriate monthly colour tag.

    Make certain personnel is

    L10

    Step 5 Locate crane in lifting position on site place timbers (pads) and set outriggers

    Crane overturning due to unstable ground conditions

    Personnel being crushed by outriggers

    H300 Outriggers must be positioned on flat surface, using timber or suitable material for pads to evenly distribute the load to the ground

    Crane to be located within the radius for the loads being lifted

    M30 Operator / Dogman

  • JOB SAFETY ANALYSIS

    SAFE WORK METHOD STATEMENT

    Rev 0 LIFTING SAFELY Page 7 of 13

    PROCEDURE POTENTIAL SAFETY & ENVIRONMENTAL HAZARDS

    Initial Risk

    Rating

    CONTROL MEASURES Residual Risk

    Rating

    PERSON RESPONSIBLE

    Step 6 - Position counterweight

    truck in an easily accessible spot for the crane to load its counterweights (Repeated Step) where required

    - Load Counterweights

    General - Plant striking other plant, equipment, personnel, materials, etc

    Dropping Counterweights

    Falls from height whilst positioning & loading counterweights

    H100 Plant to be positioned in area clear of obstructions / roads

    Traffic Control in place if required

    M30 Operator / Dogman

    Step 8 Dolly Trailer - preparation for the reinsertion of the boom into the dolly for transportation post lift

    Fall from Dolly Trailer

    Sprain / Strain from manually positioning support yoke on Dolly Trailer

    H90 Before releasing Jib from Dolly Trailer secure

    Yoke in position with 2 Ratchet Tie down

    Straps This can be done from the ground by

    throwing the straps through the yoke back on

    itself and attaching to the trailer. The Dolly will

    then remain in the correct position for pack-up

    L10

  • JOB SAFETY ANALYSIS

    SAFE WORK METHOD STATEMENT

    Rev 0 LIFTING SAFELY Page 8 of 13

    PROCEDURE POTENTIAL SAFETY & ENVIRONMENTAL HAZARDS

    Initial Risk

    Rating

    CONTROL MEASURES Residual Risk

    Rating

    PERSON RESPONSIBLE

    3. Crane Lift

    Step 1 Prepare load for Lifting (Repeated Step)

    Crush points when releasing ratchet straps (if unloading from truck)

    Pinch points

    Procedures not being adhered to

    M30 Ratchet strap to be secured in a location that can be released from ground level

    Make certain hands and fingers are clear of ratchet strap pinch points (Riggers Gloves)

    PPE Riggers Gloves, Steel Cap Boots, Safety Glasses, Hard Hat, LS-HV Shirt, Long Pants

    M10 Truck Company / Operator / Dogman

    Step 2 Attach chains or slings to load (Repeated Step)

    Falling from sling and injuring dogman

    Lifting gear failure

    Crush Injuries & Pinch Points

    H300 Qualified dogman using correct sling method to attach slings to transformers

    PPE Riggers Gloves

    Watch for crush & pinch points between chain and where it is inserted into the Tank components lift points

    Tagline used to guide into position

    Lifting gear / equipment inspected and tagged with appropriate monthly colour tag.

    Crane lifting gear register on board crane

    L30 Dogman

    Step 3 Prepare spreader bar for attachment and use with chains (if required)

    Coming away from the hook and dropping the load

    H300 Inspect all attachment points and check slings for faults ascertaining they are fit for each lift

    M30 Dogman

    Step 4 Crane lifting load Strains and fingers being damaged by lifting gear.

    H100 Wear riggers gloves when handling lifting equipment.

    Keep hands and body parts away from crush areas.

    M30 Dogman

    Load falling from lift H100 Rigging equipment to be inspected prior to lift and have current inspection tag

    All slings and lifting equipment to be free from damage

    Slings to be appropriately positioned to prevent slippage

    L10 Dogman

  • JOB SAFETY ANALYSIS

    SAFE WORK METHOD STATEMENT

    Rev 0 LIFTING SAFELY Page 9 of 13

    PROCEDURE POTENTIAL SAFETY & ENVIRONMENTAL HAZARDS

    Initial Risk

    Rating

    CONTROL MEASURES Residual Risk

    Rating

    PERSON RESPONSIBLE

    Lifted object striking other plant, equipment, personnel, materials, etc

    H300 Riggers and crane operator to plan lifts and path of item

    Riggers to carefully control lifted item with taglines

    No unnecessary personnel in lift area

    Correct radio procedure or hand signals to be used. Communications / directions by dogman only

    Do not conduct lifts in high winds

    M30 Dogman

    Machine strike energised overhead powerlines H300 Inspect area prior to unloading operation

    Stay clear from overhead powerlines maintain the correct clearance to conductors (3m/6m/ 8m) when slewing / boom

    Dogman to control/monitor clearance from overhead powerlines at all times

    M30 Operator

    Crane tipping over due to overload M30 Stay within radius of cranes working load limitations. Crane load assessment to be conducted

    L10 Operator

    Crane tipping over due to Instability of outriggers after lifting load

    M30 Outriggers pads to be stacked correctly

    Outriggers to be level and have not moved during lift

    L10 Operator

    Step 5 Placing Load in final position

    Crushed limbs, hands, feet from falling load

    Pinch Points and Crush Zones

    H100 Exclusion zone under load and path of lift

    PPE - Riggers Gloves

    Keep hands and fingers clear of placement areas

    L10 Operator / Dogman

  • JOB SAFETY ANALYSIS

    SAFE WORK METHOD STATEMENT

    Rev 0 LIFTING SAFELY Page 10 of 13

    PROCEDURE POTENTIAL SAFETY & ENVIRONMENTAL HAZARDS

    Initial Risk

    Rating

    CONTROL MEASURES Residual Risk

    Rating

    PERSON RESPONSIBLE

    4. Pack-up Crane & Return to Depot

    Step 1 Pack up Crane & Cleanup work area

    Trip hazards

    Manual Handling Injuries

    Crush & Pinch injuries

    Equipment damage

    H90 Use correct manual handling techniques

    Wear appropriate PPE

    Rubbish to be placed in bins

    Tools & Equipment to packed

    Lifting gear packed

    Timbers packed

    Pads loaded

    L10 Operator / Dogman

    Step 2 Load counter weights & equipment on to counterweight truck.

    Counterweights coming off the back of the truck

    Crush & Pinch injuries

    Falls

    H300 Make certain counterweight are stacked on rubber mats and correctly tied down for trip

    Guide counterweights onto the truck tray with taglines

    Where possible use EWP or Platform Ladder Access otherwise be cautious of footing

    M30 Operator / Dogman

    Step 3 Exit site and return to depot

    Overhead powerlines

    Collision with people/personnel and other vehicles/plant when exiting site

    Counterweights sliding off during travel

    Traffic Accidents

    H90 Crane boom to be down when travelling under power lines

    Maintain site speed limit when exiting work site.

    Communicate with other vehicles on site if necessary

    Observe road rules and take into consideration drivers and riders who dont understand the nature of cranes and trucks

    M30 Operator

  • JOB SAFETY ANALYSIS

    SAFE WORK METHOD STATEMENT

    Rev 0 LIFTING SAFELY Page 11 of 13

    200T LIFTING GEAR Item Working Load Limit (WLL) Qty Lifting Gear used on Job

    PERSON RESPONSIBLE

    16MM GRADE S BOW SHACKLE 3.2 TONNE 9 Dogman

    19MM GRADE S BOW SHACKLE 4.7 TONNE 3 Dogman

    22MM GRADE S BOW SHACKLE 6.5 TONNE 8 Dogman

    25MM GRADE S BOW SHACKLE 8.5 TONNE 8 Dogman

    29MM GRADE S BOW SHACKLE 9.5 TONNE 3 Dogman

    32MM GRADE S BOW SHACKLE 12 TONNE 7 Dogman

    35MM GRADE S BOW SHACKLE 13.5 TONNE 7 Dogman

    38MM GRADE S BOW SHACKLE 17 TONNE 8 Dogman

    44MM GRADE S BOW SHACKLE 25 TONNE 4 Dogman

    51MM GRADE S BOW SHACKLE 35 TONNE 3 Dogman

    38MM GRADE S DEE SHACKLE 17 TONNE 1 Dogman

    GRADE M DEE SHACKLE 13 TONNE 1 Dogman

    GRADE M DEE SHACKLE 5.5 TONNE 1 Dogman

    SAFETY BOW 85 TONNE 1 Dogman

    13MM X 2 LEG X 5 METRE CHAIN SLING 9.4 TONNE @ 60 DEGREES 1 Dogman

    13MM X 2 LEG X 6 METRE CHAIN SLING 9.4 TONNE @ 60 DEGREES 1 Dogman

    16MM X 2 LEG X 5 METRE CHAIN SLING 14.2 TONNE @ 60 DEGREES 1 Dogman

    16MM X 2 LEG X 5 METRE CHAIN SLING 13.8 TONNE @ 60 DEGREES 1 Dogman

    3 METRE ROUNDSLING 3 TONNE 1 Dogman

    3 METRE ROUNDSLING 3 TONNE 1 Dogman

    3 METRE ROUNDSLING 3 TONNE 1 Dogman

    3 METRE ROUNDSLING 3 TONNE 1 Dogman

    3 METRE ROUNDSLING 3 TONNE 1 Dogman

    3 METRE ROUNDSLING 3 TONNE 1 Dogman

    2 METRE ROUNDSLING 2 TONNE 1 Dogman

    2 METRE ROUNDSLING 2 TONNE 1 Dogman

    2 METRE ROUNDSLING 2 TONNE 1 Dogman

    2 METRE ROUNDSLING 2 TONNE 1 Dogman

    4 METRE ROUNDSLING 4 TONNE 1 Dogman

    4 METRE ROUNDSLING 6 TONNE 1 Dogman

    4 METRE ROUNDSLING 6 TONNE 1 Dogman

    4 METRE ROUNDSLING 6 TONNE 1 Dogman

    4 METRE ROUNDSLING 6 TONNE 1 Dogman

    4 METRE ROUNDSLING 10 TONNE 1 Dogman

    4 METRE ROUNDSLING 10 TONNE 1 Dogman

    8 METRE ROUNDSLING 10 TONNE 1 Dogman

    8 METRE ROUNDSLING 10 TONNE 1 Dogman

  • JOB SAFETY ANALYSIS

    SAFE WORK METHOD STATEMENT

    Rev 0 LIFTING SAFELY Page 12 of 13

    JSA CHANGE SHEET 200T Mobile Crane Lift JSA No: STR031 Rev: 0

    Procedure

    Amended or added Job steps

    Potential Safety & Environmental Hazards

    Identify the hazards associated with each step, examine each to find all possible risk factors

    Initial Risk Rating

    Control Measures

    Eliminate or minimize all hazards that could lead to an accident, injury, illness or environmental incident.

    Indicate who is responsible for the implementation of each control measure

    Residual Risk Rating

    Level of risk after corrective action

    Date of change and sign off by all workgroups

    Reviewed by: ... (print) .. (Superintendents Representative)

  • JOB SAFETY ANALYSIS

    SAFE WORK METHOD STATEMENT

    Rev0 Page 13 of 13

    CONSULTATION & SIGN-OFF RECORD

    I confirm by my signature below, that I have attended a briefing on the requirements of the attached Job Safety Analysis and agree to perform the work in the manner detailed on it. I confirm that copies of the relevant Permits, MSDS's and Isolation Plans etc. have been reviewed.

    JSA NAME: 200T Mobile Crane Lift JSA No: STR031 Rev: 0

    NAME and QUALIFICATION for task (Please print) SIGNATURE DATE

    THIS SAFE WORK BRIEFING / TRAINING WAS CARRIED OUT BY (Responsible person at that location) :

    Name: Signature: Date: