cpm-500-c/d : integrating systems engineering with earned ... · integrating system engineering...
TRANSCRIPT
presented by:
Integrating System Engineering with Earned Value Management
Pat Barker MCR, [email protected] © MCR, LLC, 2008Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
What This is all about …• Purpose: This presentation explores the inter-relationship of system
engineering (SE) and earned value management (EVM). – Shows similarities between SE and EVM. – Hands-on requirements generation and work breakdown structure
(WBS) building exercises help students recognize the value of linking the two disciplines together.
• Objectives– Attendees with an EVM/Cost/Scheduling background will recognize the
value of building their next technical baseline, work breakdown structure and performance measurement baseline side by side with lead program engineers.
– Similarly, engineers attending this seminar will hopefully think twice before commencing system engineering planning, design activities, project planning and/or status meetings without “EVM expertise”present.
– All attendees will recognize the value of interdisciplinary work to support program management
© 2008 MCR, LLC 2
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Outline
• Context• Clarifying What the Customer Wants• The Role of Requirements• Planning Considerations• Performance Measurement• Your Turn• So What?• Summary• Acronyms
© 2008 MCR, LLC 3
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
What SE Does For Us …• SE enables:
– Planning and organization of the technical aspects of the project– Analysis of the problem posed by the stakeholders
• Defining the stakeholders’ problem by converting needs and expectations into validated and integrated technical requirements
• Developing detailed technical requirements to the extent necessary to enable feasible and economical design solutions
– Assessment and evaluation of alternatives which may satisfy these needs and expectations
– Selection of a balanced solution for each system element– A balanced solution for the system as a whole– An implementation of a balanced solution – Verification that the solution satisfies stakeholder requirements
Source: International Council on System Engineering (INCOSE)© 2008 MCR, LLC 4
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
What EVM Does for Us …
• Why Use Earned Value?– Requirement (on certain contracts)– Way to manage limited resources and
competing priorities– Essential for realistic planning– Critical for decisions that are rooted in reality– Objectively measures work progress– Enables trend analysis and change control
• What is Earned Value Management (EVM)?OMB Definition of EVM: “… a project management tool that effectively integrates the project scope of work with schedule and cost elements for optimum project planning and control.” (OMB Circular A-11, 2002)
ScheduleCost
Scope
© 2008 MCR, LLC 5
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
SE Examples• Analysis of Alternatives • System Definition• Requirements Analysis• Architectural Design• Requirements Loop• Functional Analysis• Functional Allocation• Design Loop Synthesis• Verification• System Analysis and Control• Trade Studies
What Might EVM and SE Together What Might EVM and SE Together Accomplish?Accomplish?
EVM Examples• WBS Development • OBS Development• RAM Development• Planning• Scheduling• Budgeting• Accounting• Analysis• Reporting• Management• Change Control
We Will Focus On These Two Areas For Today
© 2008 MCR, LLC 6
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Where Our Story Begins …..• A hard-to-find Department of Defense organization
decided it wanted a fresh bagel delivery system for its offices and it had $3.5 billion to spend on it.
• It was officially called the “ON-DEMAND FRESH BAGEL DELIVERY SYSTEM, or ODFBDS
• Others just called it the “Hyperbagel”
Using a concept most audience members are readily familiar with (most everyone has toasted a bagel and put cream cheese on it) enables proper focus on SE
and EVM concepts
© 2008 MCR, LLC 7
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Outline
• Context• Clarifying What the Customer Wants• The Role of Requirements• Planning Considerations• Performance Measurement• Your Turn• So What? • Summary• Acronyms
© 2008 MCR, LLC 8
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Customer Needs: Is This Clear Enough?
© 2008 MCR, LLC 9
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
A First Step in Translating Requirements
• Measures of Effectiveness (MOEs)– The Key “Operational” measures of success (customer
viewpoint) that meet the mission need
• Measures of Performance (MOPs)– The Key “Operational” measures of success (from the system
performance viewpoint) that enable the MOEs
• Technical Performance Measures (TPMs)– The “Acquisition” measures of success (from designer/developer
viewpoint) that enable the MOPs
© 2008 MCR, LLC
It can get more complicated than this and definitions might differ in other places, but we only
have 45 minutes today... So lets go with this!
10
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Exploring the Hyperbagel MOEs
• Hyperbagel MOEs
• So…– How do these relate to each other?– Is there a better way to describe these?– Is there more to this?
GREATTASTING
DELIVEREDFAST
PRESERVESPRODUCTIVITY
DOESN’TINTERFERE
ISAVAILABLE
AFFORDABLE
© 2008 MCR, LLC 11
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
From MOEs to MOPs
Delivered FAST
One Example: Provide bagel within x minutes/seconds of request
Is AVAILABLE
One Example: Provide bagels between 8am and 5pm every work dayPreserves PRODUCTIVITY
One Example: Delivers bagel directly to employee’s work space
Is GREAT TASTING
One Example: Not burned
Example Questions to Ask:•Where will the ODFBDS be used? Inside? Outside? Both?•How is the delivery of fast, great-tasting bagels envisioned to be accomplished?• What key parameters determine whether of not the bagel delivery is successful (how to measure “great tasting”?)•How long will the system need to last? Days? Months? Years?
GREATTASTING
DELIVEREDFAST
PRESERVESPRODUCTIVITY
DOESN’TINTERFERE
ISAVAILABLEAFFORDABLE
© 2008 MCR, LLC 12
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Result: What the Customer Really Wants
© 2008 MCR, LLC 13
MOE MOP
Doesn’t INTERFERE
Delivers bagels to a fully-occupied conference table without disrupting meeting or other employees
Requires no building and/or office modifications to accommodate
Is AFFORDABLEAcquisition Cost not to exceed $3500M (threshold) or $1000M (objective)
O&M cost minimized.
Delivered FAST Consistently (98% of the time) provide bagel within 10 minutes of stated need
Bagel consistently (98% of time) provided within 3 minutes of completing preparation
Is AVAILABLEEnabling technologies at TRL 8 within 8 months of contract award
System experiences little or no (<10%) degradation in inclement weather
Provide bagels between 8am and 5pm every work day
Preserves PRODUCTIVITY
Delivers bagel directly to employee’s work space on flat surface within 1 meter of employee
Entire process (request thru delivery) diverts less than 90 seconds of employee’s time
Is a GREAT TASTING Bagel
Fresh
Reasonably spread cream cheese
Not burned
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Outline
• Context• Clarifying What the Customer Wants• The Role of Requirements• Planning Considerations• Performance Measurement• Your Turn• So What?• Summary• Acronyms
© 2008 MCR, LLC 14
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
What is a Requirement?• According to INCOSE:
– The foundation of the project– The basis for design, build, test, manufacture and operations– State user needs in such a way as to guide development– Enables an understanding between the various interactions
within a system
© 2008 MCR, LLC 15
Each requirement is associated with specific costs that increase over its life if requirement changes
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
How Do We Get Requirements?
• Some examples (mostly from INCOSE):– External Environment
• Laws and Regulations• Legal liabilities• Social responsibilities• Standards
– Enterprise Environment• Policies• Procedures• Guidelines
– Project Environment• Contract (RFP, SOW)• Users/Operators• Design Reviews• Derivation
Requirement generation and
analysis involves more than “just”the engineers!
© 2008 MCR, LLC 16
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
What Makes a Good Requirement?
• Achievable• Verifiable – allowing for objective and (preferably)
quantitative verification• Have only one possible meaning• In aggregate, they must be complete (i.e., all the info
needed to understand the customer’s needs)• Expressed in terms of the need, not the solution
– Does not express “how” to do it
• Must be consistent with other requirements• Appropriate to the level so as not to be constraining
– System-level requirements in system-level documents
BAD Requirements do BAD THINGS to cost, schedule and scope!© 2008 MCR, LLC 17
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Why Requirements Matter to Cost & Schedule
Source: GAO Cost Estimating and Assessment Guide (March 2009)© 2008 MCR, LLC 18
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Outline
• Context• Clarifying What the Customer Wants• The Role of Requirements• Planning Considerations• Performance Measurement• Your Turn• So What?• Summary• Acronyms
© 2008 MCR, LLC 19
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Work Breakdown Structure
• Program management is not easy!
• It takes time to define the work and develop a realistic Program baseline and it requires the involvement of key people…
• First…gaining an understanding of the full scope of the Program– Define a Work Breakdown Structure
WBSWBS
© 2008 MCR, LLC 20
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
What is the Work Breakdown Structure?
• The Work Breakdown Structure (WBS)…– …is a systematic approach to
defining the work – …is product-oriented– …provides the framework for – …provides the necessary
framework for management control
– …is dynamic
•Level 1 – Product – entire product/service 1.2.3 where 1 is Level 1 •Level 2 – Major Element (Segment)/Subsystem 1.2.3 where 2 is Level 2•Level 3 – Subordinate Components to Level 2 1.2.3 where 3 is Level 3•Level 4 to Level X - Sub-products - defines further decomposition until a
manageable unit of work is identified.MCR
WBS Level 1
RADAR
Advanced Radar
TRAINING
RECEIVER SYSTEM ANTENNA
RECEIVER PHASE SHIFTER
POWER SUPPLY APPLICATION S/W
WBS Level 2
WBS Level 3
WBS Level 4
WBS Level 5
© 2008 MCR, LLC 21
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Our ODFBDS WBS
© 2008 MCR, LLC
DynamicOrderingSystem
ODFBDS
PM SE
DualSensorSuite
Bagel Prep & Delivery
Subsystem
SystemIntegratio
n
SystemTest
Sensor#1
Mount/Pedestal
Sensor#2
RadarMgt/QA/CM
RadarReqt’s
RadarDesign
RadarIntegration
RadarTest
RadarBuild
Antenna
REX
Signal/DataProcessor
Ancillary/Supt Equipment
ArrayFace
T/RModules
Power
Cooling
Mount/Pedestal
SuiteMgt/SE
Vehicle“Brains”
(software) Payload
O&M
Level 1Level 2
Level 3
Level 4
Level 5
Level 6 Level 7
Dynamic SupplySystem
IPTMgt/SE
SubsystemIntegration
& Test
SuiteIntegration
& Test
QA CM
22
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
The Control Account
CONTROLACCOUNT
CA Work Packages
WBS Level 2 Delivery Subsytem
Sensor Suite etc
Sensor #1 etc
Radar Build etc
Radar Antenna etc
WBS Level 3
WBS Level 4
WBS Level 5COMPANY
TEST
ENG
MFG
DESIGN
MECHANICALDESIGN
ElectricalDESIGN
DRAFTING/CHECKING
OrganizationBreakdownStructure
Work Breakdown Structure
ODFBDSWBS Level 1
WBS Level 6
THE CONTROL ACCOUNT
The lowest level of management control within a program that has a unique
•Cost•Schedule•Scope
“Owned” by a Control Account Manager (CAM)
Comprised of 2 or more distinct “work packages”
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Control Accounts• Control Accounts are where the action is. They…
– …represent the work assigned to one responsible organizational element on one program work breakdown structure element at the lowest level (intersection of WBS and OBS)
– …are a natural management point for planning and control– …are vital to performance measurement (EV Methodology)
• Rules of Thumb:– Integration of work, cost of the work, and schedule– Homogeneity* of work– What is logical to manage every day– Examine the nature of the work, breakout of labor, span of
control – Typically 6 - 18 months for discrete effort; level of effort can be
longer
*resemblance in structure© 2008 MCR, LLC 24
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
The Work Package
CONTROLACCOUNT
CA Work Packages
WBS Level 2 Delivery Subsytem
Sensor Suite etc
Sensor #1 etc
Radar Build etc
Radar Antenna etc
WBS Level 3
WBS Level 4
WBS Level 5COMPANY
TEST
ENG
MFG
DESIGN
MECHANICALDESIGN
ElectricalDESIGN
DRAFTING/CHECKING
OrganizationBreakdownStructure
Work Breakdown Structure
ODFBDSWBS Level 1
WBS Level 6
THE WORK PACKAGE
•Work packages are “natural”decompositions of the CA•Typically includes discrete (product-oriented) and non-discrete•Typically the focal point of performance measurement and resource tracking
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Work Packages• Work Packages (WP) contain a discrete segment of
work below the Control Account level that is defined by – a description or brief work statement– starting and ending dates– completion milestone– work-in-process measure– time-phased budget expressed in direct labor (hours and/or
dollars), material, other direct costs and subcontract dollars
• It is important that the duration of a Work Package be a relatively short span of time (normally, but not limited to, six months or less).
© 2008 MCR, LLC
CONTROL ACCOUNT PLAN
Work Pkg #1
Work Pkg #2
Work Pkg #3
$$
$ $
$
$
$
$$
26
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Outline
• Context• Clarifying What the Customer Wants• The Role of Requirements• Planning Considerations• Performance Measurement• Your Turn• So What?• Summary• Acronyms
© 2008 MCR, LLC 27
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
The Need for Objective Performance Data
• Project plans are not perfect nor is it realistic to expect perfect execution.– Consequently, there will always be deviations from the plan.
• Objective progress information removes the guesswork from status on progress and performance.– When information is not objective, project status may not be
accurate and reliable.
• The ability to know the precise status and understand the impact is dependent upon the quality of information available for those tasks.– EV Techniques by themselves are a partial solution– EV Techniques combined with technical performance
measurement (TPM) is a more complete (and realistic) solution
© 2008 MCR, LLC 28
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Control Account: Antenna Build
Antenna Work Package Example Without TPM Integration
T/R Module Build WP
Array Face WP
Power WP
Cooling WP
PrototypeComplete
25%
ProductionUnit
Complete50%
Here, completion of WP milestones are typically a binary “yes, it is complete” or “no, it is not complete”measurement.
EV is taken accordingly –25%, 50% then 100% at end.
But we cannot tell if performance goals have been met.
The Performance Measurement does not indicate whether the “built”unit will enable a successful antenna build
Measurement is not as useful to management as it could be
Start Task25%
© 2008 MCR, LLC 29
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Attributes of Technical PerformanceMeasurements Common to EVM
• Achieved to Date (sounds like EV)• Current Estimate (sounds like EAC/ETC)• Milestone• Planned (target) value (sounds like PV)• Planned performance profile (sounds like a PMB)• Tolerance band (sounds like reporting thresholds)• Threshold (yep, just what we thought)• Variance (sounds like variance!)
Similar in Language to EVM … Why NotIntegrate Directly With EVM Planning?
© 2008 MCR, LLC 30
PlannedProfile
AchievedTo Date
Tolerance Band
CurrentEstimate
Threshold
Milestones
PlannedValue
Variation10
5
15
Tech
nica
l Par
amet
er V
alue
(e.g
., Ve
hicl
e W
eigh
t, lb
)
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Requirements to WPs
© 2008 MCR, LLC 31
Let’s now adjust our CA planning to reflect these requirements
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Control Account: Antenna Build
Antenna Work Package Example with TPM Integration
T/R Module Build WP
Array Face WP
Power WP
Cooling WP
Prototype Build
Complete&
TRL6 Achieved
15%
Prototype Test
Complete&
TPM in tolerance
band15%
PilotBuild
Complete&
TRL7Achieved
15%
PilotTest
Complete&
TPM in tolerance
band15%
ProdUnitBuild
Complete&
TRL 8 Achieved
15%
ProdUnitTest
Complete&
TPM meets objective
15%
TRL 8 Enabling Technologies Requirement means that the CAM needs to characterize each WP in terms of TRL achievement. Thus no WP is “finished” until it meets the conditions of TRL8.For the T/R Module WP, the CAM needs to define what TRL is acceptable for Prototype, Pilot and Production Unit in order to assure Antenna of TRL8
Delivery within 1 meter/flat Surface Requirement affects several parts of the radar, but here it means the T/R modules need to achieve a certain power output (to enable a higher S/N ration for signal processing). Therefore the criteria for each test should now include power.
In both cases, CA planning becomes more realistic because it takes SE performance into consideration!
Array Face Integration
Requirements met10%
© 2008 MCR, LLC 32
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Outline
• Context• Clarifying What the Customer Wants• The Role of Requirements• Planning Considerations• Performance Measurement• Your Turn• So What?• Summary• Acronyms
© 2008 MCR, LLC 33
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Group Assignment• You are now the Toaster Design & Build CAM• Start with the following MOE:
– “Deliver a great tasting bagel”• Examine at least one of the MOPs that shape this MOE:
– Fresh– Reasonable amount of evenly spread cream cheese– Not burned
• Write 2 or 3 RELATED requirements that govern the design of yourtoaster
• Convert the effort required to realize these requirements into aWORK PACKAGE
• Determine at least one TPM that will help comprise an objective performance indicator for EVM
• Be prepared to discuss your planning
© 2008 MCR, LLC 34
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
ODFBDS
PM SEDynamicOrderingSystem
SystemIntegration
Bagel Prep & Delivery
Subsystem
DualSensorSuite
SystemTest
Propulsion Chassis Electrical
PrepMgt/QA/CM
PrepQA
PrepDesign &
Build
PrepIntegration
PrepTest
ToasterDesign & Build
Loader
Dispenser
Software
BagelPrep
VehicleMgt/SE
“Brains”(software)
Payload
O&M
Level 1
Level 2
Level 3
Level 4
Level 5Level 6
Dynamic SupplySystem
IPTMgt/SE
SubsystemIntegration &
Test
VehicleIntegration &
Test
QA CM
Our ODFBDS WBS
Vehicle
????YOU are now the Toaster Design/BuildCAM
© 2008 MCR, LLC 35
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Write your “toaster” performance requirements here that meet the at least one of the above MOPs:
MOP: “reasonable amount of evenly spread cream cheese”
MOP: “not burned”
MOP: “fresh”
Your Requirements
© 2008 MCR, LLC 36
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Your Technical PerformanceMeasurement
PlannedProfile
AchievedTo Date
Tolerance Band
CurrentEstimate
Threshold
Milestones
PlannedValue
Variation
10
5
15
Tech
nica
l Par
amet
er V
alue
(e.g
., Ve
hicl
e W
eigh
t, lb
)
© 2008 MCR, LLC 37
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Control Account: SuperToaster Design
Your Work Packages
WP #1
WP #2
WP #3
© 2008 MCR, LLC 38
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Outline
• Context• Clarifying What the Customer Wants• The Role of Requirements• Planning Considerations• Performance Measurement• Your Turn• So What?• Summary• Acronyms
© 2008 MCR, LLC 39
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
The CAM and System Engineer Have Common Challenges
• Objectives• Requirements• Dependencies• WP Breakout• PP Breakout• Resources• Budget• Time• Milestones• Deliverables• Products• Acceptance/Exit Criteria• Constraints• Assumptions• EV Performance
Measurement• Risks
• System Purpose• Technical Performance
Measurement• Performance Requirements• Functional Requirements• Interface Requirements• Architecture• WBS Breakout• Legacy of Similar Systems• Acquisition Strategy• Developmental Testing• Operational Testing• Production• Safety• Training• Resources• Disposal• Budget• Schedule• Milestones• Acceptance/Exit Criteria• Constraints• Assumptions• Risks
CA Scope SE Planning
© 2008 MCR, LLC 40
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Consider Performance-Based Earned Value® when Integrating SE with EVM
• Planning:– Link performance measurement baseline (PMB) to:
• Product requirements baseline, SE plan and SE process products– Identify product metrics for performance-based progress measurement
• Planned value profile of TPMs• Planned development maturity to date
– Generate Realistic Success criteria• Reviews• Work products
• Measurement– Objective measurement of interim progress– Progress of requirements through engineering life cycle– EVM linked with
• Indicated quality of end product and/or TPM achieved– EVM used to assess conformance to requirements
• Not just work accomplished
© 2008 MCR, LLC 41For Reference: The PBEV® Website: www.pb-ev.com
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Integration Holds Larger Benefits ….
TPM Development
MilestonesBudget
Technical Risk AnalysisOBS
DevelopmentCost Risk Analysis
Schedule Risk Analysis
Control Account Planning (cost/schedule)
Responsibility Assignment Matrix (RAM)
Programmatic Guidance / Constraints
System Requirements Analysis
System Definition
Analysis of Alternatives
WBS Development
Risk-Adjusted PMB
Parametric Cost & Schedule Estimates
MOE and MOP Development
System Engineering Planning
IMS Development
Integrating SE and EVM tends to have a broader effect of “pulling” disparate program planning & baseline development efforts together
RESULT: A Robust risk-adjusted baseline to set the stage for effective program execution
© 2008 MCR, LLC 42
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Outline
• Context• Clarifying What the Customer Wants• The Role of Requirements• Planning Considerations• Performance Measurement• Your Turn• So What?• Summary• Acronyms
© 2008 MCR, LLC 43
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Summary• This presentation explored the inter-relationship of system
engineering (SE) and earned value management (EVM). – Showed similarities between SE and EVM. – Hands-on requirements generation and work breakdown structure
(WBS) building exercises helped you recognize the value of linking the two disciplines together.
• Victory is Claimed If ….– All attendees recognize the value of interdisciplinary work to support
program management
© 2008 MCR, LLC 44
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Outline
• Context• Clarifying What the Customer Wants• The Role of Requirements• Planning Considerations• Performance Measurement• Your Turn• So What?• Summary• Acronyms
© 2008 MCR, LLC 45
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Acronyms
ACWP: Actual Cost of Work PerformedAPB: Acquisition Program Baseline BAC: Budget At CompletionBCWS: Budgeted Cost of Work Scheduled or “planned value”BCWP: Budgeted Cost of Work Performed or “earned value”CA: Control AccountCAIG: Cost Analysis Improvement GroupCFSR: Contract Funds Status ReportCPI: Cost Performance IndexCPR: Contract Performance ReportCRA: Cost Risk AssessmentCWBS: Contractor Work Breakdown Structure CV: Cost VarianceDID: Data Item DescriptionDoD: Department of DefenseDCMA: Defense Contract Management AgencyEAC: Estimate at CompletionETC: Estimate to CompletionEV: Earned ValueEVM: Earned Value ManagementEVMS: Earned Value Management System
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Acronyms (cont’d)GAO: Government Accountability OfficeGR&A: Ground Rules & AssumptionsICE: Independent Cost EstimateIEAC: Independent Estimate at CompletionIMS: Integrated Master ScheduleINCOSE: International Council on System EngineeringIPO: Integrated Program OfficeKPP: Key Performance ParameterLCAA™: Linked Crest Assessment & AnalysisLOE: Level of Effort (Earned Value Measurement Technique)LRE: Latest Revised EstimateM: Million(s)MCR: Management, Consulting, Research, LLCMOE: Measures of EffectivenessMOP: Measures of PerformanceMR: Management ReserveNDIA: National Defense Industrial AssociationOBS: Organizational Breakdown StructurePMO: Program Management OfficePM: Program Management
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com
Acronyms (cont’d)PMB: Performance Measurement BaselinePOE: Program Office EstimateRMP: Risk Management PlanSE: System EngineeringSEP: System Engineering PlanSOW: Statement of WorkSRA: Schedule Risk AssessmentTCPI: To-Complete Performance Index (a.k.a. “run-out
efficiency”)TPM: Technical Performance MeasureWBS: Work Breakdown Structure
Presented at the 2009 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com