counting the chickens while they hatch and the double edged sword of tracking project claims and...

30
1 Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays Plenary Session 4 ABA Forum on the Construction Industry April 10-12, 2014 2014 Annual Meeting Allen Estes - Gordon & Rees, LLP John Livengood – Navigant Andrew Rhodes - The Rhodes Group

Upload: kin

Post on 25-Feb-2016

26 views

Category:

Documents


0 download

DESCRIPTION

Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays. Plenary Session 4 ABA Forum on the Construction Industry April 10-12, 2014 2014 Annual Meeting Allen Estes - Gordon & Rees, LLP John Livengood – Navigant - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

1

Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

Plenary Session 4ABA Forum on the Construction Industry

April 10-12, 20142014 Annual Meeting

Allen Estes - Gordon & Rees, LLPJohn Livengood – Navigant

Andrew Rhodes - The Rhodes Group

Page 2: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

2

INTRODUCTIONOwners and Contractors should focus on the

importance of having project procedures/mechanisms in place to

monitor and document the costs of change orders or claims to maximize the potential

for appropriate recovery or defense against unjustified claims.

Page 3: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

3

$

Time

$

Time

Planned Project Completion

Page 4: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

4

Why do We Run into the Same Issues?

Page 5: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

5

Substantiating

Disputing

StrategizingBuilding

Planning

Tracking

Why do We Run into the Same Issues?

Page 6: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

6

VS

Why do We Run into the Same Issues?

Institutional Knowledge Personal Knowledge

Page 7: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

7

Why do We Run into the Same Issues?

• Relationships• Optimism Bias• Did not Read the Contract• Cost-Reimbursable Mindset• Up-Stream/Down-Stream Coordination• Lack of Resources (too busy)• Lack of Expertise

Page 8: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

8

Why do We Run into the Same Issues?

Page 9: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

9

Project RecordsLikelihood

Insignificant Insignificant Minor Minor Moderate Moderate Major Major Catastrophic CatastrophicAlmost Moderate High High High High High High High High HighAlmost Low Moderate Moderate High High High High High High HighLikely Low Low Moderate High High High High High High HighLikely Low Low Moderate Moderate Moderate High High High High HighModerate Low Low Moderate Moderate Moderate Moderate High High High HighModerate Low Low Moderate Moderate Moderate Moderate Moderate High High HighUnlikely Low Low Low Moderate Moderate Moderate Moderate Moderate High HighUnlikely Low Low Low Low Moderate Moderate Moderate Moderate High HighRare Low Low Low Low Low Low Moderate Moderate Moderate HighRare Low Low Low Low Low Low Low Low Moderate High

Index Measured Risk Low Moderate High Included y/n Responsibility1 sdkjdj kjf dfj k kdkfj kjf kjkf kljd gdffg 1 6 4 y sadf sdf2 dsfsadf skfdj sdfkjhjxcuiv js oiud io sdf dfgdfgfg 2 1 6 n fgdfgg dfg3 df;lk fglk;lkg lkdl kds fl;kd dlk dlfk d fdgfgf 3 2 6 y dgf 4 dasfsdf asdf sdaf sd asdf 4 3 6 y sadf sdf5 sadf ds kijdklds fklj df sdaf 5 4 1 y dgf 6 sadf hhj jsdjkh dfjhjhjc jhdj hjk jhc jk sadf 6 5 2 n dgf 7 cdopko ckxkpdopk odsf asdgdfgdh 1 6 6 n fgdfgg dfg8 asdf sdj dklj ckljkjsd kjc sadfgdfgdf 2 5 1 y sadf sdf9 dfjioi xio sdijk ji idsio dk ijud asd 3 6 2 n dgf

10 sh iuui uiio dsij fki oijdsj odj io asf 4 3 1 y dgf 11 sadh I km, jklj lkdsklm kljk sadf 5 4 6 y sadf sdf12 asd klj kljkld kl kjsdkf jkkl fj kljdkjf lk dsaf 1 6 1 y dgf 13 dfjhn jk hh dfh jhk djhjd fjk j jh sjh sd fgdfhghds 2 1 6 n fgdfgg dfg14 sdjh h hjk dhjh jkh fd fdgdfh 3 2 1 n dgf 15 df j khj jkhdjh dkj lkj klkdjl d ds fhghggh 4 4 2 y sadf sdf

Description

Consequences

PROJECT RISK ASSESSMENT

Page 10: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

10

AGENDA• Introduction• Establishing legal entitlement• Establishing technical entitlement• Example 1: Differing Site Condition• Example 2: Schedule Delay• Wrap-up and Q&A

Page 11: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

11

LEGAL ENTITLEMENT• Define Legal Entitlement

– Basis in law for the claim• Based on contract requirements

– Each contract is different• Substantiated by documents that adhere to

contract requirements– Track events giving rise to claims– Ensure timely notice– Other required support

Page 12: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

12

TECHNICAL ENTITLEMENT• Define Technical Entitlement

– Based on Analysis completed either as outlined by the contract or utilizing industry accepted methodologies

• Scope of Work Change Technical Entitlement• Photos• Technical drawings and submissions• Soil Reports• Equipment cuts• Detailed Cost estimates

Page 13: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

13

TECHNICAL ENTITLEMENT

• Schedule Technical Entitlement– Based on Analysis – Method Identified in Contract or utilizing

industry accepted methodologies• Schedule Delay and Extension• Schedule Acceleration• Impacted Productivity

• Dependent upon completeness and accuracy of available records

Page 14: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

14

LEGAL ENTITLEMENTExample 1

• Example: Foundation subcontractor responsible for CIDH pile needed to support the foundation of a building.– Ideal Situation– Reality

Page 15: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

15

LEGAL ENTITLEMENTEXAMPLE 1

• Contracts typically identify specific process• Common Pitfalls –

– Failure to follow Notice requirements – Stopping work– Reasonable investigation & either stop-work or

notice to proceed– Substantiation– Evaluation of claim– Accord or dispute (DRB, litigation)

Page 16: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

16

EXAMPLE 1REALITY:• Relies on soil

reports in Docs• Starts before NTP• Maintains Diary• Continues Working• Provides Oral Notice • Written Notice Late

IDEAL:• Performs Site

Investigation• Waits for NTP• Maintains detailed DRs• Stops Work• Promptly Provides

Written Notice

Page 17: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

17

EXAMPLE 1REALITY:• Contractor Mixes costs• Contractor submits Total

Time claim• Contractor and Owner

cannot agree.• Contractor proceeds to

DRB or other dispute process

• DRB issues opinion and One side is disappointed.

• Project does not continue smoothly

IDEAL:• Contractor Segregates

Costs• Contractor Develops

TIA• Owner and Contractor

Meet• Equitable Adjustment is

negotiated• Contractor and Owner

move on to other aspects of the Work

Page 18: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

18

WHY DID IT GO WRONG?EXAMPLE 1

• Contractor failed to perform a sufficient investigation of the soil reports included in the documents.

• Contractor failed to sufficiently inform project personnel of the terms of the contract

• Contractor insisted on proceeding too quickly.

Page 19: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

19

WHY DID IT GO WRONG?EXAMPLE 1

• Contractor, tried to keep good relations by giving a “friendly” notice of DSC

• Contractor tried to save money on documenting extra costs

• Contractor had no capability to do a proper delay analysis.

Page 20: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

20

LESSONS LEARNEDEXAMPLE 1

• Project Staff must know the contract and what it means.

• Contractor and Owner are neither friends nor enemies – they are working together on a project – there is no place for friendship in lieu of contract requirements

• Contractor needs to plan better so it can spend money in compliance with the contract requirements, and not try to save it by providing less management.

Page 21: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

21

EXAMPLE 2

Schedule Delay

Page 22: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

22

TECHNICAL ENTITLEMENTExample 2

During the course of the project, there were significant weather delays, owner changes, productivity problems and the requirement to maintain the original completion date.

Page 23: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

23

TECHNICAL ENTITLEMENTExample 2

• As a result, the contractor prepared TIAs contemporaneously with some of the delays, and yet submitted an “wrap-up” delay claim that incorporated granted time extensions, weather delays, owner delays and alleged productivity impacts resulting from the many separate changes issued by the owner and the necessary acceleration

Page 24: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

24

TECHNICAL ENTITLEMENTSchedule Delay

• The ability to apply a methodology is contingent upon available source material

• Defining the Delay: – Excusable– Inexcusable– Compensable– Concurrent– Apportioned 

Page 25: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

25

TECHNICAL ENTITLEMENTSchedule Delay

• Types of Acceleration– Voluntary– Directed– Constructive– Acceleration to Recover from Concurrency

• Proving acceleration and the related records

Page 26: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

26

EXAMPLE 2REALITY:• Contractor eventually

delivered a baseline schedule that was rejected.

• The Contractor periodically submitted update schedule: always depicted owner delays – they were rejected

• The Contractor submitted some impacted as-planned submissions (masquerading as TIAs) after the work was completed: asserted all delay to be the responsibility of the Owner.

IDEAL:• Contractor submitted a

reasonable cost-loaded baseline schedule at the outset of the project: approved by the owner

• The contractor maintained a vigorous program for monthly update: submitted timely and approved.

• The contractor prepared TIAs contemporaneously for all changes identified on the project and negotiated them, predicated on the detailed schedule collection that was available

Page 27: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

27

EXAMPLE 2REALITY:• At the end of the project,

almost all delays issues remained unresolved, even for those that direct costs had been agreed to.

• The parties attempted mediation and then entered into a protracted trial where the schedule delay experts duked it out. The judge could not understand either delay expert and essentially tossed a coin.

IDEAL:• At the end of the project

there were some unresolved schedule delays that were prepared using an agreed upon methodology that showed some delays were the responsibility of the owner, some the Contractor, and some were concurrent.

• The parties settled their disputes amicable, with the Fairy Godmother acting as mediator.

Page 28: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

28

WHY DID IT GO WRONG?EXAMPLE 2

• Contractor failed to timely follow the contract requirements for submission of PROSPECTIVE costs and time

• Contractor was “too busy” doing the work to forward-price the owner’s changes

• The Contractor relied on the friendly relations between Owner and Contractor

• Contractor failed to recognize all potential changes• Contractor was “too busy” doing the work to

monitor and record activities

Page 29: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

29

LESSONS LEARNEDEXAMPLE 2

• The additional cost of documenting labor and costs is worth it

• Jeopardizing contractual obligations due to maintaining client relationships

• Forecast work to be performed at the most realistic durations, not optimistic

Page 30: Counting the Chickens While They Hatch and the Double Edged Sword of Tracking Project Claims and Delays

30

CONCLUSION• Establishing legal and technical

entitlement are integral to substantiating any claim

• Creation and maintenance of project documentation with a consciousness toward claims can greatly affect how useful they are in this capacity