copy of appendix c-comparative summary of state solar policies
TRANSCRIPT
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
1/40
Appendix C - Comparative Summary ofThe information contained in this appendix is for general information purposes on
Andhra Pradsesh
Source
Order Date
Eligible Producer
Land Allotment
Operative Period
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
2/40
Sale of Power
and Tariff
Wheeling
(selling/
transporting over
transmission
lines)
Banking (Energy
Banking)
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
3/40
Power
Evacuation and
Grid Interfacing
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
4/40
Incentives
and
General
Source: adapted from IREDA, www.ireda.gov.in/solar/DATA/Policy/1%20Final%2
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
5/40
tate Solar Policiesly, and has not been peer-reviewed. We make no representations or warranties of any kind, express or
Bihar Chhattisgarh
State renewable energy policy State renewable energy policy
Notification No. 38 dated April 8, 2002
Any industry, Institution, private agency,
partnership firm, consortia, panchayat,cooperative or registered society
Every unit, organisation or private agency
setting up of renewable energy projects Parties may set-up units either themselves or as
a joint venture
Government land, if available on lease, otherwise
private purchase
Government land, if available, on lease
Private land to be acquired by the government
and made vailable to the party at acquisition cost
5 Years with immediate effect
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
6/40
The developer may sell generated power to the
state grid/BSEB/third-party/HT consumers
Parties may use the power themselves or sell it
to a third-party after permission from GoC, CSEB.
CSEB to purchase at rate of Rs.2.25 per unit
For third-party, the rates to be settled mutually
On BSEB transmission and distribution system as
per agreed terms with developers
On CSEB's transmission/
distribution system
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
7/40
Developer to bear cost for evacuation of power to
the nearest State/BSEB gird/sub-station.
Developer to bear cost for evacuation of power
from plant to nearest grid sub-station
Lines/equipments to be maintained by CSEB at
Developers cost
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
8/40
Incentives/concessions as applicable to new
industrial units/backward areas
Incentives/concessions
as applicable to new Industrial units
Reactive charges to be paid to CSEB for taking
reactive power from them
Electricity sold to third-party or for self use
exempted from electricity duty for 5 years
Com.sum.pdf
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
9/40
implied, about the completeness, accuracy, reliability, suitability, legality or availability with respect to
Gujarat Haryana
State renewable energy policy
Solar Power Policy 2009 G.R.No.SLR-11-2008-
2176-B, dated 6th January, 2009 and
modification vide .R.No.SLR-11-2010/170022/B
dated 22nd June, 2010.
GoH, Renewable Energy Dept. Dated 23-11-2005
Any company or body corporate or association
of body of individuals, whether incorporated ornot, or artificial juridical person,
Minimum project capacity of a Solar Power
Generators (SPG), in case of solar Photovoltaic
(SPV) and Solar Thermal (ST) to be 5 MW each
A maximum 500 MW SPG
allowed for installation
Companies, cooperatives, partnerships, local self
governments, state nodal agency, Boards &corporations, power utilities, private developers,
public
private partnership companies, consortia,
registered societies, NGOs, individuals etc.
State government to acquire land if necessary at
the cost of IPP
Up to 31.3.2014. Date of notification till a new policy is notified
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
10/40
Open Access for third-party sale
Cross subsidy exempted in case of third-party
sale and surplus energy over captive use to be
considered as sale @85% of the tariff determined
by the commission
Energy to be sold to distribution licensees in the
state at tariff( as detailed in Policy) for SPV & STfor 25 years
To licensee/utilities at HERC tariff (for new
projects after this Policy)
Surplus power from captive power to utilities at
negotiated price. (for old projects)
Allowed on payment of transmission charges
and losses applicable to normal open access
consumer with in the state (at 66kV and above).
For wheeling (below 66kV) transmission and
wheeling losses @ 10% of the energy fed to the
grid
For wheeling to more than one location,
generator to pay 5 paisa/unit on the energy fed to
the grid
On licensee/utilities grid for captive use or for
third-party sale within the State as per approved
HERC tariff
Allowed for one year free of cost.
If the banked energy is not utilized within
twelve months, no charges shall be paid In lieu of
such power
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
11/40
Power by the SPG to be injected at 66 kV.
Evacuation facility from the Solar
substation/switch yard to GETCO substation to be
approved & laid by GETCO
Cost of power evacuation up to HVPN/UHBVN.
DHBVN network to be borne by the developer.
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
12/40
CDM benefit to developers in
first year, 10% to beneficiaries in 2nd year to be
increased by 10% every year upto 50% and then
shared equally between developer and
beneficiary
SPGs installed and commissioned during this
period to be eligible for the incentives, for aperiod of 25 years from the date of
commissioning . Benefits of this policy will not be
available to the projects set up under MNRE
incentive scheme for SPG
Any subsidy/incentive received
by SPG developers from any source to be reduced
from tariff rate except accelerated depreciation
under I T Act
Exemption from demand cut up to 50% of the
installed capacity assigned for captive use
Exempted from payment of electricity duty
All new projects to be treated as Industry in
terms of Industrial Policy 2005 and all the
incentives available to new projects to be
applicable as per this Policy.
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
13/40
his document or the information, products, services, or related graphics contained in this document for
Jammu & Kashmir Karnataka
Solar Power Policy for J&K 2010 State renewable energy policy
No. EN 354 NCE 2008 Bangalore. Dated
19thJanuary, 2010.
Any company or body corporate or association of
body of individuals, whether incorporated or not,for the purpose of captive use and/or for selling
of electricity as per MNRE & JKSERC norm
KPTCL for allotment of projects above 100 MW
Available sites to be advertised
Government land on lease for 25 years at
premium of Rs.1/Kanal
Private land to be arranged by entity
Government to acquire land and lease to entity
lease for 25 years at premium of Re.1/Kanal plus
compensation for land
Government to facilitate acquisition of forest
land
Government land for Karnataka Renewable
Energy Development Limited (KREDL)
Private land from owners
land owner farmers to be equity partners for
equity not less than 5% of gross energy generated
10% barren Government lands reserved for
industrial use to KREDL for renewable energy
development
KREDL to sub-lease land to
developer for 30 years
From date of publication in state gazette untilsuperseded or modified
5 years up to 2014
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
14/40
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
15/40
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
16/40
Projects commissioned during operative period
eligible for incentives for 25 years from COD or
life of SPPs, whichever is earlier
No entry tax on power generation/ transmission
equipment and building material used for SPPs
Exemption from court fee for registration of
documents for lease of land No royalty in the shape of free power to be paid
for solar projects
Exemption from demand cut of 50% of installed
capacity for captive use
Electricity duty exempted for self
consumption /Sale to third-party/sale to licensees
Developer to pass the gross benefits of CDM to
the distribution licensee with whom PPA is signed
Mortgage deed in favour of financing
institutions exempted from payment of stamp
duty
KREDL to facilitate availing CDM
MNRE supported solar grid connected projects
of 1MW and above have incentive up to Rs
12/kWh for solar PV and Re.10/kWh for solar
thermal in addition to tariff allowed by KERC
Roof Top grid connected solar KWp projects of 5
KWp to 100 KWp to be connected at 415 V, 3phase, 11 kV level of distribution licensees with
maximum energy injection to be not more than
70% of the consumption from distribution
licensee sources
After the plant completes 11 years, it has to sell
power to Energy supply companies on tariff based
on variable cost as per KERC norms
Developer to commission the project with grid
synchronization within a period of 3 years from
the date of statutary clearance
50% of the installed capacity assigned for
captive use
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
17/40
any purpose. Any reliance you place on such information is therefore strictly at your own risk. The inclu
Kerala Madhya Pradesh
State renewable energy policy Madhya Pradesh Solar Energy Policy 2010
(Draft)
G.O.(MS) No. 16/2002/, dated 03.04.200
Companies, cooperatives, partnerships, local
self governments, registered societies, NGOs,individuals
Power producers for captive consumption
All solar power developers
Manufacturing units of equipment andancillaries related to solar power projects
Government land @ Re.1/- /year (token
premium) for 30 years or life of the Project,
whichever is less
Private land to be acquired by government &
made available to Developer at acquisition cost
Permission for government land to be given by
Non-Convention Energy Department (GoMP)
50% exemption on stamp
duty on private land
With effect from date of Issuance and to remainin force until further orders
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
18/40
PPA for a minimum period of five years.
Power purchase by KSEB at a ceiling rate of
Rs.2.80 per unit with 2000-01 as base year and 5%
escalation every year up to 5 years of operation.
Higher tariff in special cases
Terms & conditions for power purchase by
distribution licensee or MP Power trading
company as per MPERC
Purchase rate of electricity generated by
developers as per MPERC
On KSEB grid for captive use or for banking, at a
wheeling charge of 5 % of energy fed into the
grid, including transmission loss
Wheeling charges as per MPERC
4% subsidy is available
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
19/40
Developer to bear cost for evacuation facilities
& interfacing including maintenance
KSEB to initially bear the expenditure for
erection of HT sub stations and transmission
infrastructure
ANERT to recover 50 percent of this expenditure
from the power project promoters and give it toKSEB
Cost for evacuation facilities to be borne by
developer
T&D lines and other equipment to be installed
by the developer or
By MPSEB/successor company at the cost of
developer.
Maintenance of T&D lines &equipments by MPSEB/successor company at the
cost of developer
All incidental/operational
cost towards power evacuation shall be borne by
the project developer during the entire life span
of the project
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
20/40
Industry status under the schemes
administrated by Industries Department and
incentives to be made available to them
Large Industries having 2000 KVA and above as
connected load, to produce at least 5 percent of
their requirement through captive power plants
KSEB to provide facilities of an irrevocable,divisible, revolving and confirmed stand by Letter
of Credit (LC) by any Nationalised Bank
The amount of LC to be equal to the Expected
Payment for one month by Board
All transactions involving wheeling, banking or
sale of power to be settled on a monthly basis
Solar equipment and other related equipment
exempted from Entry Tax
Electricity duty exempted subject to generation
of atleast 70% of generation declared in DPR
Developers to share CDM benefits on gross
basis with distribution licensee as per GoI norms
or on equal(50:50) basis from day one Distribution licensee shall pass on 10% of the
CDM benefits from its share to the MPUVN
Developer to commission the Solar PV Project in
12 months and solar thermal in 28 months from
signing of PPA
Developers can Migrate from 2006 State policy
to this policy i.e. MP Solar Policy 2010 (as detailed
in the policy)
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
21/40
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
22/40
Power department to purchase electricity at a
minimum rate of Rs.2.25/- per unit to be increased every
year for 10 operational years.
Thereafter the rate of increase to be mutually settled
between power department. and developer
PPA for 20 years unless developer wants shorter period
DISCOM to purchase electricity at SERC rate & on
mutually accepted terms and conditions
Department to transmit on
its grid the power generated by producer and make it
available to him for captive use or to a third party for
sale within the State, at a uniform wheeling charge of 2%
of the energy fed to the grid
third-party to be a HT consumer of power
STU to transmit on its grid the power for captive
use of developer or to a third-party or sale within
the state, at an applicable wheeling charge.
Third-party to be HT consumer
of the power unless relaxed by the DISCOM.
Allowed up to 1 year
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
23/40
Developer to bear cost for evacuation facilities &
interfacing up to the nearest HT lines as well as
for Mtc.
Alternatively, these works and their maintenance could
be undertaken by the Power department at charges to
be decided by the Department
Cost of augmentation of sub-station capacity at 33/11KV or higher & transmission lines to be borne by the
Department.
Developer to bear cost for
evacuation facilities & interfacing up to the
nearest HT lines as well as for
maintenance
Alternatively, these works and their
maintenance could be undertaken by the DISCOM
at charges to be decided by the DISCOM/SERC
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
24/40
All transactions involving wheeling, banking or sale of
power to be settled on monthly basis
Exemption from electricity duty for 5 years from COD
for captive use or third-party sale.
Producers to be treated as industrial units and similar
incentives available to them
Concessions given to industrial units in backward areasto be provided
Infrastructural facilities to be on the lines of industrial
units if plant is set up in industrial area developed by
state government
GoI incentives
Exemption of tax on solar devices and spare parts
Sales Tax exempted
MANIREDA to facilitate grant of loans by IREDA &
MNRE & accord of clearances for execution
If the applicant does not take effective steps (i.e at
least 10% of the total
project cost not incurred within six months) to
implement the project, the
agreement to be terminated and site
allotted to another applicant
Infrastructural facilities to be on the lines of
industrial units if plant is set up in industrial area
developed by State government
Exemption from electricity duty for 5 years from
COD for captive use or third-party sale.
Sales Tax/VAT deferment/remission as
applicable Meghalaya Non-Conventional and Rural Energy
Development Agency
(MNREDA), to facilitate clearances for the
projects at the state and central levels and grant
of loans by Indian Renewal Energy Development
Authority (IREDA) and subsidies by MNRE.
Developer to submit applications for projects
and grid interfacing to MNREDA and DISCOM
MNREDA/ State government to provide
clearance within a period of 2 months from the
date of submission of application
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
25/40
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
26/40
Department to purchase
electricity at a minimum rate of Rs.3.50/unit
applicable for the year 2002-03 with escalation of
5% every year for 10 operational years
Thereafter the rate of increase to be mutually
ettled between Department and the producer
It shall not be compulsory for power producerto sell power to Department
Developers with concurrence of the
Department may sell the electricity to a third-
party within and outside the State,
at a rate to be mutually settled between them
PPA for minimum period of 10 years unless
developer wants for shorter period
To bulk suppliers/ distribution licensee on basis of
PPA with the approval of OERC
Energy not utilized during the year for captive
use to be treated as sold to GRIDCO/DISTCO
Department to transmit on its grid the power
generated and make it available to him for captive
use or to a third-party nominated by eligible
producer for sale within the State, at a uniform
wheeling charge of 2% of the energy supplied to
the grid
third-party to be HT consumer unless condition
relaxed by DISCOM
Allowed, subject to payment of transmission/
distribution and wheeling charges both for captive
use and out side the State as approved by OERC
Developer may supply energy to any area not
served by the licensee .
Allowed up to 1 year Allowed on annual basis.
Banking charges 2.5% of energy dispatched
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
27/40
Developer to bear cost for evacuation facilities
& interfacing up to the nearest HT lines as well as
for maintenance
Alternatively, the above works and their
maintenance could be undertaken by the
Department at charges to be decided by the
Department and the producer on mutualagreement
Cost of augmentation of substation capacity at
33/11 KV or higher & transmission lines to be
borne by the Department
Grid interfacing with the generating units to be
constructed by the developer at their own cost
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
28/40
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
29/40
commendation.
Punjab Rajasthan
State renewable energy policy State renewable energy policy
Energy Dept. letter no. F.20 (4) Energy/2004
dated 25.10.2004 and amended vide letters of
even nos. dated 10.3.2005, 16.7.05, 18.8.05,
24.2.06, 30-11-06 ,19-1-07, 27/29-3-2008,
15.5.2008, and 10-11-2008.
Government land at lease rent of Re.1/sq.
meter/ annum for 33 years
Agricultural land without conversion charges
Government land to be allotted to power
producer at concessional rates viz, 10% of DLC
rates as detailed in policy
Private land to be procured at cost.
If any producer initiates activities on the
allotted land without project approval, grid
connectivity to be allowed only after payment of
an amount @ Rs.5.00 lacs per MW as penalty
amount to RREC
Five years w.e.f. 8th December, 2006
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
30/40
Rs.7.00 per unit (Base year 2006-07) with
annual escalation @ 5% up to 2011-2012
Thereafter PSEB/HT tariff , whichever is higher
Producers may use power for captive
consumption or for sale to consumers/licensees
including DISCOMS.
Energy to be offered to open access
consumer/DISCOMS/ CPPs within the State
After fulfilling RE Obligation developers may sell
surplus energy out side the State. Price of power to be sold to
consumers/licensees other than DISCOMS as per
mutual agreement between seller and the
purchaser. For DISCOMS the price of power to be
as per RERC order 09-03-2007 & amendment 14-
03-2007
Cap on purchase of energy to be as specified by
the (RERC)
2% of energy fed to the grid Producers may use power for captive
consumption or for sale to onsumers/licensees
including DISCOMS.
Energy to be offered to open access
consumer/DISCOMS/ CPPs within the State
After fulfilling RE Obligation developers may sell
surplus energy out side the State.
Price of power to be sold to
consumers/licensees other than DISCOMS as per
mutual agreement between seller and the
purchaser. For DISCOMS the price of power to beas per RERC order 09-03-2007 & amendment 14-
03-2007
Cap on purchase of energy to be as specified by
the (RERC)
Allowed Allowed
For third-party sale/captive use for which PPAs
signed after March 31, 2007, the banking to be as
specified by RERC
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
31/40
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
32/40
VAT @ 4% on manufacturing & sale of NRSE
devise/system and equipment/ machinery
PEDA to assist in seeking carbon credit under
CDM
Octroi exempted
Power projects established for which PPAs have
been signed under the Policies - 1999, 2000 and
2003 to be governed as per the terms &
conditions under the concerned policies provided
the power projects gets commissioned before
31st March 2005
Developer to deposit a refundable amount assecurity deposit of Rs.5.0 lac per MW, in the form
of cash or bank guarantee with RREC, towards
completion of the project in the prescribed time
frame
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
33/40
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
34/40
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
35/40
Developers to bear the entire cost of power
evacuation and interfacing
including maintenance to the earest HT lines
Cost of augmentation of sub-station capacity at
33/11 kV or higher and transmission lines to be
borne by the Department
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
36/40
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
37/40
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
38/40
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
39/40
T&D lines from generation site to be provided by
UPCL/PTCUL
-
7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies
40/40