copy of appendix c-comparative summary of state solar policies

Upload: aps05

Post on 05-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    1/40

    Appendix C - Comparative Summary ofThe information contained in this appendix is for general information purposes on

    Andhra Pradsesh

    Source

    Order Date

    Eligible Producer

    Land Allotment

    Operative Period

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    2/40

    Sale of Power

    and Tariff

    Wheeling

    (selling/

    transporting over

    transmission

    lines)

    Banking (Energy

    Banking)

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    3/40

    Power

    Evacuation and

    Grid Interfacing

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    4/40

    Incentives

    and

    General

    Source: adapted from IREDA, www.ireda.gov.in/solar/DATA/Policy/1%20Final%2

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    5/40

    tate Solar Policiesly, and has not been peer-reviewed. We make no representations or warranties of any kind, express or

    Bihar Chhattisgarh

    State renewable energy policy State renewable energy policy

    Notification No. 38 dated April 8, 2002

    Any industry, Institution, private agency,

    partnership firm, consortia, panchayat,cooperative or registered society

    Every unit, organisation or private agency

    setting up of renewable energy projects Parties may set-up units either themselves or as

    a joint venture

    Government land, if available on lease, otherwise

    private purchase

    Government land, if available, on lease

    Private land to be acquired by the government

    and made vailable to the party at acquisition cost

    5 Years with immediate effect

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    6/40

    The developer may sell generated power to the

    state grid/BSEB/third-party/HT consumers

    Parties may use the power themselves or sell it

    to a third-party after permission from GoC, CSEB.

    CSEB to purchase at rate of Rs.2.25 per unit

    For third-party, the rates to be settled mutually

    On BSEB transmission and distribution system as

    per agreed terms with developers

    On CSEB's transmission/

    distribution system

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    7/40

    Developer to bear cost for evacuation of power to

    the nearest State/BSEB gird/sub-station.

    Developer to bear cost for evacuation of power

    from plant to nearest grid sub-station

    Lines/equipments to be maintained by CSEB at

    Developers cost

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    8/40

    Incentives/concessions as applicable to new

    industrial units/backward areas

    Incentives/concessions

    as applicable to new Industrial units

    Reactive charges to be paid to CSEB for taking

    reactive power from them

    Electricity sold to third-party or for self use

    exempted from electricity duty for 5 years

    Com.sum.pdf

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    9/40

    implied, about the completeness, accuracy, reliability, suitability, legality or availability with respect to

    Gujarat Haryana

    State renewable energy policy

    Solar Power Policy 2009 G.R.No.SLR-11-2008-

    2176-B, dated 6th January, 2009 and

    modification vide .R.No.SLR-11-2010/170022/B

    dated 22nd June, 2010.

    GoH, Renewable Energy Dept. Dated 23-11-2005

    Any company or body corporate or association

    of body of individuals, whether incorporated ornot, or artificial juridical person,

    Minimum project capacity of a Solar Power

    Generators (SPG), in case of solar Photovoltaic

    (SPV) and Solar Thermal (ST) to be 5 MW each

    A maximum 500 MW SPG

    allowed for installation

    Companies, cooperatives, partnerships, local self

    governments, state nodal agency, Boards &corporations, power utilities, private developers,

    public

    private partnership companies, consortia,

    registered societies, NGOs, individuals etc.

    State government to acquire land if necessary at

    the cost of IPP

    Up to 31.3.2014. Date of notification till a new policy is notified

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    10/40

    Open Access for third-party sale

    Cross subsidy exempted in case of third-party

    sale and surplus energy over captive use to be

    considered as sale @85% of the tariff determined

    by the commission

    Energy to be sold to distribution licensees in the

    state at tariff( as detailed in Policy) for SPV & STfor 25 years

    To licensee/utilities at HERC tariff (for new

    projects after this Policy)

    Surplus power from captive power to utilities at

    negotiated price. (for old projects)

    Allowed on payment of transmission charges

    and losses applicable to normal open access

    consumer with in the state (at 66kV and above).

    For wheeling (below 66kV) transmission and

    wheeling losses @ 10% of the energy fed to the

    grid

    For wheeling to more than one location,

    generator to pay 5 paisa/unit on the energy fed to

    the grid

    On licensee/utilities grid for captive use or for

    third-party sale within the State as per approved

    HERC tariff

    Allowed for one year free of cost.

    If the banked energy is not utilized within

    twelve months, no charges shall be paid In lieu of

    such power

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    11/40

    Power by the SPG to be injected at 66 kV.

    Evacuation facility from the Solar

    substation/switch yard to GETCO substation to be

    approved & laid by GETCO

    Cost of power evacuation up to HVPN/UHBVN.

    DHBVN network to be borne by the developer.

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    12/40

    CDM benefit to developers in

    first year, 10% to beneficiaries in 2nd year to be

    increased by 10% every year upto 50% and then

    shared equally between developer and

    beneficiary

    SPGs installed and commissioned during this

    period to be eligible for the incentives, for aperiod of 25 years from the date of

    commissioning . Benefits of this policy will not be

    available to the projects set up under MNRE

    incentive scheme for SPG

    Any subsidy/incentive received

    by SPG developers from any source to be reduced

    from tariff rate except accelerated depreciation

    under I T Act

    Exemption from demand cut up to 50% of the

    installed capacity assigned for captive use

    Exempted from payment of electricity duty

    All new projects to be treated as Industry in

    terms of Industrial Policy 2005 and all the

    incentives available to new projects to be

    applicable as per this Policy.

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    13/40

    his document or the information, products, services, or related graphics contained in this document for

    Jammu & Kashmir Karnataka

    Solar Power Policy for J&K 2010 State renewable energy policy

    No. EN 354 NCE 2008 Bangalore. Dated

    19thJanuary, 2010.

    Any company or body corporate or association of

    body of individuals, whether incorporated or not,for the purpose of captive use and/or for selling

    of electricity as per MNRE & JKSERC norm

    KPTCL for allotment of projects above 100 MW

    Available sites to be advertised

    Government land on lease for 25 years at

    premium of Rs.1/Kanal

    Private land to be arranged by entity

    Government to acquire land and lease to entity

    lease for 25 years at premium of Re.1/Kanal plus

    compensation for land

    Government to facilitate acquisition of forest

    land

    Government land for Karnataka Renewable

    Energy Development Limited (KREDL)

    Private land from owners

    land owner farmers to be equity partners for

    equity not less than 5% of gross energy generated

    10% barren Government lands reserved for

    industrial use to KREDL for renewable energy

    development

    KREDL to sub-lease land to

    developer for 30 years

    From date of publication in state gazette untilsuperseded or modified

    5 years up to 2014

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    14/40

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    15/40

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    16/40

    Projects commissioned during operative period

    eligible for incentives for 25 years from COD or

    life of SPPs, whichever is earlier

    No entry tax on power generation/ transmission

    equipment and building material used for SPPs

    Exemption from court fee for registration of

    documents for lease of land No royalty in the shape of free power to be paid

    for solar projects

    Exemption from demand cut of 50% of installed

    capacity for captive use

    Electricity duty exempted for self

    consumption /Sale to third-party/sale to licensees

    Developer to pass the gross benefits of CDM to

    the distribution licensee with whom PPA is signed

    Mortgage deed in favour of financing

    institutions exempted from payment of stamp

    duty

    KREDL to facilitate availing CDM

    MNRE supported solar grid connected projects

    of 1MW and above have incentive up to Rs

    12/kWh for solar PV and Re.10/kWh for solar

    thermal in addition to tariff allowed by KERC

    Roof Top grid connected solar KWp projects of 5

    KWp to 100 KWp to be connected at 415 V, 3phase, 11 kV level of distribution licensees with

    maximum energy injection to be not more than

    70% of the consumption from distribution

    licensee sources

    After the plant completes 11 years, it has to sell

    power to Energy supply companies on tariff based

    on variable cost as per KERC norms

    Developer to commission the project with grid

    synchronization within a period of 3 years from

    the date of statutary clearance

    50% of the installed capacity assigned for

    captive use

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    17/40

    any purpose. Any reliance you place on such information is therefore strictly at your own risk. The inclu

    Kerala Madhya Pradesh

    State renewable energy policy Madhya Pradesh Solar Energy Policy 2010

    (Draft)

    G.O.(MS) No. 16/2002/, dated 03.04.200

    Companies, cooperatives, partnerships, local

    self governments, registered societies, NGOs,individuals

    Power producers for captive consumption

    All solar power developers

    Manufacturing units of equipment andancillaries related to solar power projects

    Government land @ Re.1/- /year (token

    premium) for 30 years or life of the Project,

    whichever is less

    Private land to be acquired by government &

    made available to Developer at acquisition cost

    Permission for government land to be given by

    Non-Convention Energy Department (GoMP)

    50% exemption on stamp

    duty on private land

    With effect from date of Issuance and to remainin force until further orders

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    18/40

    PPA for a minimum period of five years.

    Power purchase by KSEB at a ceiling rate of

    Rs.2.80 per unit with 2000-01 as base year and 5%

    escalation every year up to 5 years of operation.

    Higher tariff in special cases

    Terms & conditions for power purchase by

    distribution licensee or MP Power trading

    company as per MPERC

    Purchase rate of electricity generated by

    developers as per MPERC

    On KSEB grid for captive use or for banking, at a

    wheeling charge of 5 % of energy fed into the

    grid, including transmission loss

    Wheeling charges as per MPERC

    4% subsidy is available

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    19/40

    Developer to bear cost for evacuation facilities

    & interfacing including maintenance

    KSEB to initially bear the expenditure for

    erection of HT sub stations and transmission

    infrastructure

    ANERT to recover 50 percent of this expenditure

    from the power project promoters and give it toKSEB

    Cost for evacuation facilities to be borne by

    developer

    T&D lines and other equipment to be installed

    by the developer or

    By MPSEB/successor company at the cost of

    developer.

    Maintenance of T&D lines &equipments by MPSEB/successor company at the

    cost of developer

    All incidental/operational

    cost towards power evacuation shall be borne by

    the project developer during the entire life span

    of the project

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    20/40

    Industry status under the schemes

    administrated by Industries Department and

    incentives to be made available to them

    Large Industries having 2000 KVA and above as

    connected load, to produce at least 5 percent of

    their requirement through captive power plants

    KSEB to provide facilities of an irrevocable,divisible, revolving and confirmed stand by Letter

    of Credit (LC) by any Nationalised Bank

    The amount of LC to be equal to the Expected

    Payment for one month by Board

    All transactions involving wheeling, banking or

    sale of power to be settled on a monthly basis

    Solar equipment and other related equipment

    exempted from Entry Tax

    Electricity duty exempted subject to generation

    of atleast 70% of generation declared in DPR

    Developers to share CDM benefits on gross

    basis with distribution licensee as per GoI norms

    or on equal(50:50) basis from day one Distribution licensee shall pass on 10% of the

    CDM benefits from its share to the MPUVN

    Developer to commission the Solar PV Project in

    12 months and solar thermal in 28 months from

    signing of PPA

    Developers can Migrate from 2006 State policy

    to this policy i.e. MP Solar Policy 2010 (as detailed

    in the policy)

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    21/40

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    22/40

    Power department to purchase electricity at a

    minimum rate of Rs.2.25/- per unit to be increased every

    year for 10 operational years.

    Thereafter the rate of increase to be mutually settled

    between power department. and developer

    PPA for 20 years unless developer wants shorter period

    DISCOM to purchase electricity at SERC rate & on

    mutually accepted terms and conditions

    Department to transmit on

    its grid the power generated by producer and make it

    available to him for captive use or to a third party for

    sale within the State, at a uniform wheeling charge of 2%

    of the energy fed to the grid

    third-party to be a HT consumer of power

    STU to transmit on its grid the power for captive

    use of developer or to a third-party or sale within

    the state, at an applicable wheeling charge.

    Third-party to be HT consumer

    of the power unless relaxed by the DISCOM.

    Allowed up to 1 year

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    23/40

    Developer to bear cost for evacuation facilities &

    interfacing up to the nearest HT lines as well as

    for Mtc.

    Alternatively, these works and their maintenance could

    be undertaken by the Power department at charges to

    be decided by the Department

    Cost of augmentation of sub-station capacity at 33/11KV or higher & transmission lines to be borne by the

    Department.

    Developer to bear cost for

    evacuation facilities & interfacing up to the

    nearest HT lines as well as for

    maintenance

    Alternatively, these works and their

    maintenance could be undertaken by the DISCOM

    at charges to be decided by the DISCOM/SERC

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    24/40

    All transactions involving wheeling, banking or sale of

    power to be settled on monthly basis

    Exemption from electricity duty for 5 years from COD

    for captive use or third-party sale.

    Producers to be treated as industrial units and similar

    incentives available to them

    Concessions given to industrial units in backward areasto be provided

    Infrastructural facilities to be on the lines of industrial

    units if plant is set up in industrial area developed by

    state government

    GoI incentives

    Exemption of tax on solar devices and spare parts

    Sales Tax exempted

    MANIREDA to facilitate grant of loans by IREDA &

    MNRE & accord of clearances for execution

    If the applicant does not take effective steps (i.e at

    least 10% of the total

    project cost not incurred within six months) to

    implement the project, the

    agreement to be terminated and site

    allotted to another applicant

    Infrastructural facilities to be on the lines of

    industrial units if plant is set up in industrial area

    developed by State government

    Exemption from electricity duty for 5 years from

    COD for captive use or third-party sale.

    Sales Tax/VAT deferment/remission as

    applicable Meghalaya Non-Conventional and Rural Energy

    Development Agency

    (MNREDA), to facilitate clearances for the

    projects at the state and central levels and grant

    of loans by Indian Renewal Energy Development

    Authority (IREDA) and subsidies by MNRE.

    Developer to submit applications for projects

    and grid interfacing to MNREDA and DISCOM

    MNREDA/ State government to provide

    clearance within a period of 2 months from the

    date of submission of application

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    25/40

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    26/40

    Department to purchase

    electricity at a minimum rate of Rs.3.50/unit

    applicable for the year 2002-03 with escalation of

    5% every year for 10 operational years

    Thereafter the rate of increase to be mutually

    ettled between Department and the producer

    It shall not be compulsory for power producerto sell power to Department

    Developers with concurrence of the

    Department may sell the electricity to a third-

    party within and outside the State,

    at a rate to be mutually settled between them

    PPA for minimum period of 10 years unless

    developer wants for shorter period

    To bulk suppliers/ distribution licensee on basis of

    PPA with the approval of OERC

    Energy not utilized during the year for captive

    use to be treated as sold to GRIDCO/DISTCO

    Department to transmit on its grid the power

    generated and make it available to him for captive

    use or to a third-party nominated by eligible

    producer for sale within the State, at a uniform

    wheeling charge of 2% of the energy supplied to

    the grid

    third-party to be HT consumer unless condition

    relaxed by DISCOM

    Allowed, subject to payment of transmission/

    distribution and wheeling charges both for captive

    use and out side the State as approved by OERC

    Developer may supply energy to any area not

    served by the licensee .

    Allowed up to 1 year Allowed on annual basis.

    Banking charges 2.5% of energy dispatched

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    27/40

    Developer to bear cost for evacuation facilities

    & interfacing up to the nearest HT lines as well as

    for maintenance

    Alternatively, the above works and their

    maintenance could be undertaken by the

    Department at charges to be decided by the

    Department and the producer on mutualagreement

    Cost of augmentation of substation capacity at

    33/11 KV or higher & transmission lines to be

    borne by the Department

    Grid interfacing with the generating units to be

    constructed by the developer at their own cost

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    28/40

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    29/40

    commendation.

    Punjab Rajasthan

    State renewable energy policy State renewable energy policy

    Energy Dept. letter no. F.20 (4) Energy/2004

    dated 25.10.2004 and amended vide letters of

    even nos. dated 10.3.2005, 16.7.05, 18.8.05,

    24.2.06, 30-11-06 ,19-1-07, 27/29-3-2008,

    15.5.2008, and 10-11-2008.

    Government land at lease rent of Re.1/sq.

    meter/ annum for 33 years

    Agricultural land without conversion charges

    Government land to be allotted to power

    producer at concessional rates viz, 10% of DLC

    rates as detailed in policy

    Private land to be procured at cost.

    If any producer initiates activities on the

    allotted land without project approval, grid

    connectivity to be allowed only after payment of

    an amount @ Rs.5.00 lacs per MW as penalty

    amount to RREC

    Five years w.e.f. 8th December, 2006

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    30/40

    Rs.7.00 per unit (Base year 2006-07) with

    annual escalation @ 5% up to 2011-2012

    Thereafter PSEB/HT tariff , whichever is higher

    Producers may use power for captive

    consumption or for sale to consumers/licensees

    including DISCOMS.

    Energy to be offered to open access

    consumer/DISCOMS/ CPPs within the State

    After fulfilling RE Obligation developers may sell

    surplus energy out side the State. Price of power to be sold to

    consumers/licensees other than DISCOMS as per

    mutual agreement between seller and the

    purchaser. For DISCOMS the price of power to be

    as per RERC order 09-03-2007 & amendment 14-

    03-2007

    Cap on purchase of energy to be as specified by

    the (RERC)

    2% of energy fed to the grid Producers may use power for captive

    consumption or for sale to onsumers/licensees

    including DISCOMS.

    Energy to be offered to open access

    consumer/DISCOMS/ CPPs within the State

    After fulfilling RE Obligation developers may sell

    surplus energy out side the State.

    Price of power to be sold to

    consumers/licensees other than DISCOMS as per

    mutual agreement between seller and the

    purchaser. For DISCOMS the price of power to beas per RERC order 09-03-2007 & amendment 14-

    03-2007

    Cap on purchase of energy to be as specified by

    the (RERC)

    Allowed Allowed

    For third-party sale/captive use for which PPAs

    signed after March 31, 2007, the banking to be as

    specified by RERC

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    31/40

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    32/40

    VAT @ 4% on manufacturing & sale of NRSE

    devise/system and equipment/ machinery

    PEDA to assist in seeking carbon credit under

    CDM

    Octroi exempted

    Power projects established for which PPAs have

    been signed under the Policies - 1999, 2000 and

    2003 to be governed as per the terms &

    conditions under the concerned policies provided

    the power projects gets commissioned before

    31st March 2005

    Developer to deposit a refundable amount assecurity deposit of Rs.5.0 lac per MW, in the form

    of cash or bank guarantee with RREC, towards

    completion of the project in the prescribed time

    frame

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    33/40

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    34/40

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    35/40

    Developers to bear the entire cost of power

    evacuation and interfacing

    including maintenance to the earest HT lines

    Cost of augmentation of sub-station capacity at

    33/11 kV or higher and transmission lines to be

    borne by the Department

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    36/40

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    37/40

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    38/40

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    39/40

    T&D lines from generation site to be provided by

    UPCL/PTCUL

  • 7/31/2019 Copy of Appendix C-Comparative Summary of State Solar Policies

    40/40