control aspects common to all mc process groups & control schedule 1 mec-2
TRANSCRIPT
Control AspectsCommon to All MC Process Groups
&Control Schedule
1
MEC-2
Integration 1. M&C Proj Work2. Perform Integrated Change Control
Scope 3. Validate Scope4. Control Scope
Time 5. Control Schedule
Cost 6. Control Costs
Quality 7. Control Quality
HR
Comm 8. Control Communication
Risk 9. Control Risks
Procurement 10. Control Procurements
Stakeholder 11. Control Stakeholder Engagements
MEC in PMI Perspective
2
Overall Project Controls
Project Deliverables
Agenda
3
1. WPD, WPI & WPR
2. General Scheme of any M&C Process Group
3. Control Schedule
Monitoring, Evaluation & Control Data Flow
4
Work Performance Data: Raw observations & measurements identified during activities being performed to carry out the project work
eg % work completed, Q & Tech Performance Measure, Actual Costs, Actual Durations etc
Manifestation of MONITORING Produced by the overall Direct & Manage Process Group Goes to the Respective Monitoring & Control Process
Group
Monitoring, Evaluation & Control Data Flow
5
Work Performance Information: Performance data collected from various controlling processes, analyzed in context and integrated based on relationships across areas
eg Variances, Status of Deliverables, Implementation Status of Change Requests, Forecasts etc
Manifestation of EVALUATION Produced by the respective Monitoring & Control
Process Group Goes to the Over All Project Control (Monitor & Control
Project Work)
Monitoring, Evaluation & Control Data Flow
6
Work Performance Reports: Physical or electronic representation of work performance information compiled in project documents, by the Overall Project Control (Monitor & Control Project Work), intended to generate decisions, actions, or awareness
eg Status Reports, Memos, Information Notes, Electronic Dashboards, Briefs, Recommendations etc
Manifestation of CONTROL Produced by the Overall Project Control Go to the Integrated Change Control, Project
Management Plan & Project Communications
Project Data, Information & Report Flow
7
D&M Proj Work
Respective M&C PG
Overall Proj Cont
(M&C Proj Work)
Integrated Change Control
• WPD
• WPR
• WPI
Project Manage-
ment Plan
Project Comm-
unication
General ITTO Scheme of any M&C Process Group
8
M&C Process
Group in any KA
• PMP (KA PMP)•WPD (D&M Proj Wk)• OPA
•WPI• Change Request• PMP Updates• PD Updates• OPA Updates
What is Schedule Baseline?
9
Approved Version of the Schedule Model, comprising:‒ Start & Finish Dates‒ Sequencing & Logical Relationship (Dependencies)‒ Milestones
Presented in the form of:‒ Gantt or Bar Chart‒ Milestone Chart‒ Network Diagram
….Cont’d
Control Schedule Inputs & Outputs
10
Control Schedule
1. PSMP (PMP)2. WPD (D&M PW)3. OPA
1. WPI2. Change Request3. PSMP Updates4. PD Updates5. OPA Updates
4. Proj Schedule5. Proj Calendars6. Schedule Data
6. Schedule Forecasts
Control Schedule Inputs
11
Input Details
PSMP Schedule Baseline
WPD • Activities Completed with Start & Finish Dates• Activities in Progress with Start Date & % Complete
OPA • Schedule control policies, procedures, guidelines• Control Tools• Monitoring & Reporting Methods
Proj Schedule
Proj Calendars One or more Calendars
Schedule Data • Milestones• Activities• Activities Attributes• Assumptions & Constraints
Control Schedule Outputs
12
Output Details
WPI SV & SPI for WBS components (WPs & Control Accounts)
Change Request Based on Schedule Variance Analysis, Recommendations for:• Changes to Baselines (Schedule, Cost, Scope etc)• Corrective, Preventive Actions & Defect Repairs
PMP Updates • Schedule control policies, procedures, guidelines• Control Tools• Monitoring & Reporting Methods
PD Updates • Schedule Baseline ?• PSMP for any changes in Proj Schedule Management• Cost Baseline ?
OPA Updates • Schedule Data• Project Schedule updated with actual situation• Risk Register updated the schedule delay risks
Schedule Forecast Indirectly from Estimate At Completion (EAC)
Control Schedule Tools & Techniques
13
Tool Category Tools
Performance Reviews • Trend Analysis• CPM• CCM• EVM
Project Management Software e.g. MS Project, @ Risk
Resource Optimization Techniques
• Resource Levelling• Resource Smoothing
Modelling Techniques • What-If Scenario• Simulation (Monte Carlo)
Leads & Lags
Schedule Compression • Crashing• Fast Tracking
• Reduce Scope• Lower Quality
Scheduling Tool Gantt Chart (Manual or Software)
Trend Analysis
14
Variance Trend Performance Index Trend
Regression Analysis
• Performance improving or deteriorating? • Forecast
Critical Path Method
15
• Variance on Critical Path have a direct impact on the Project• Variance on Near Critical Paths can identify Schedule Risk; more the Near Critical Paths,
more the Risks of Delays• Status of Floats; more the remaining float more the flexibility, security
Critical Path Method
16
Difference between Buffer remaining and Buffer needed to protect the delivery/completion date of a Deliverable can help determine CORRECTIVE ACTION
8
1
4
2
Earned Value Management (EVM)
17
• Tool to determine both Cost & Schedule Variances• Schedule Variance determined in terms of Costs• Key Terms (Some common with Cost Variance, others specific to
Schedule Variance: - Planned Value (PV)- Earned Value (EV)- Actual Cost (AC)- Schedule Variance (SV)- Schedule Performance Index (SPI)
EVM – Simplified Example
18
Procurement Project• 200 heavy duty concrete security blocks• Price: Rs 2,000K/Rs 10K per block• Delivery Time: 20 days/10 blocks per day• Contract Type: Cost Reimbursable
Situation at the end of Day 1080 blocks delivered; Contractor invoiced Rs 900K for these 80 blocksConsiderations• 80 blocks should have cost: 80 x Rs 10K = Rs 800K. This is EV• At the end of Day 10, 100 blocks should have been delivered, which
would have cost: 1,000 x Rs 10K = Rs 1,000K. This is PV• These 80 blocks actually cost Rs 900K. This is AC
EVM – Simplified Example
19
EV = 800K
PV = 1,000K
SV=2 Days
BAC = 2,000K
SV = 1,000K-800K = 200K = 2 Days
SV has nothing to do with AC
Schedule Slippage
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 200
20
40
60
80
100
120
140
160
180
200
220
Time in Days
Rupe
es in
Tho
usan
ds
24
AC = 900K
Term Formula What it means
Planned Value (PV) As of today, the estimated value of the WORK PLANNED to be done
Earned Value (EV) As of today, the estimated value of the WORK ACTUALLY ACCOMPLISHED?
Budget at Completion (BAC)
BUDGET for the TOTAL PROJECT
Schedule Variance (SV) = EV-PV Difference between ACCOMPLISHED WORK & PLANNED WORK (+ ahead, - behind schedule)
Schedule Performance Index (SPI)
= EV/PV Comparison of ACCOMPLISHED WORK with PLANNED WORK (ACCOMPLISHED WORK as fraction or % of PLANNED WORK) (>1 ahead, <1 behind schedule)
EVM for Schedule Variance - Terminology
20
Earned Value Management
21
RISK
PV
AV
EV
• Tool to determine both Cost & Schedule Variances• Schedule Variance determine in terms of Costs
Resource Levelling
22
• Adjustment of Start & Finish Dates to produce a Resource Limited Schedule• Lengthens the Schedule & increases Cost to deal with a limited
amount of Resources, Resource Availability and other Resource Constraints• Also caters to situation where lengthening of Schedule is preferred
to hiring Resources• Can cause change in the Critical Path or generate Near Critical
Paths
Resource Levelling
23
Resource Smoothing
24
• A technique that adjusts the activities of a Schedule Model such that the requirements for Resources on the Project do not exceed certain Predefined Source Limits
• Usually applied considering the Float of their activities so that completion dates are not changed, thereby maintaining the integrity of the Critical Path• Critical Path is not changed
Crashing
25
• Adding or adjusting resources in activities on the Critical Path in order to compress the schedule while maintaining the original Project Scope• Trades Time for Money
• Downside: Increased Costs, and possibly Risk
R1, R2 R1, R2,R3, R4
Fast Tracking
26
• Doing Critical Path activities in-Parallel which were originally planned in Series
• Downside: Often results in Rework (Cost), usually increases Risk and requires more attention to Communication
What-If Scenario
27
• Process of evaluating scenarios in order to predict their Effect (+ve or –ve) on Project Objectives• Schedule Network Analysis performed using Schedule to compute
difference scenarios such as delays in major component delivery, extension of specific engineering durations, force majeure etc•Out of analysis used to assess the Feasibility of the Project
Schedule under adverse conditions, preparing Contingency & Response Plans to overcome or mitigate he impact of the unexpected situations
28
What-If Scenario
Project Duration
Simulation
29
• Calculating Multiple Project Durations with different sets of activity Assumptions, usually using Probability Distributions constructed from the 3-Point Estimates to account for uncertainty eg Monte Carlo simulation
What Monitoring & Control Project Work Entails?
30….Cont’d