contract system - andhra pradeshaphrdi/aees... · contract system (including engineering, ... in...
TRANSCRIPT
CONTRACT SYSTEM(including Engineering, Procurement &
Construction system)
Ghanta Surender
Former Director(ITC)
WALAMTARI
HYDERABAD
EVOLUTION OF CONTRACT SYSTEM➢ CONTRACT SYSTEM
• A promise enforceable by law
• Offer acceptance (legally binding)
• To be legally binding as a contract, a promise must be
exchanged for adequate consideration. i.e., benefit a party
receives.
➢ AGREEMENT
• “Every promise and every set of promises forming the
consideration for each other is an agreement ” section 2 (e)
of the Indian Contract Act 1872 ( as amended by Act 1 of
1997).
➢ AGREEMENT AND CONTRACT
• An agreement which is enforceable by law is considered to be
a contract – section 2 (h) of the Indian Contract Act.
GOVERNMENT CONTRACTS
➢ Government is, by far, the largest contractor in anycountry, so too in India. Supply products (purchases ) andservices (consultancy, labour etc.,)
➢ Contracts entered into between private persons and thegovernment are governed by article 299 of constitution ofIndia.
➢ Article 299 stipulates “all contracts made in exercise of theexecutive power of the union or the state shall be expressedto be made by the president or by the governor of the state asthe case may be and all such contracts and all assurances ofproperty made in the exercise of that power shall be executedon behalf of the president or the governor by such personand in such manners as he may direct or authorise”
➢ Neither the president nor the governor shall be personallyliable_______”
CONTRACT SYSTEM IN AP
➢ AP Financial code mentions only 4 forms of
execution of work, vide chapter VIII, Article
163
1) Department execution
2) K2 Contract – Piece Work
3) Lump Sum Contract
4) Schedule Contract
➢ Only the first 3 forms are in vogue in
Government Departments
1.DEPARTMENTAL EXECUTION OF WORKS :
The Public works are executed departmentally, by
engaging work charged staff.
2.K2 CONTRACTS :
• When several developmental works were taken-up,
it became difficult to manage several works with the
available meager work charged staff.
• The system of ‘K2 Contracts’, or piece work
agreements have come into force.
• This is basically a labour and material supply
agreement and the contractor has to execute the
work, strictly as directed by the Engineer-in-Charge
and with no responsibility fixed on him.
3) L.S. Contracts :
As the number of experienced contractors started
raising, with the passage of time, the ‘Lump Sum’
contracts have come into force. In this form of
contracts, the contractor has to execute the work as
per Designs & Specifications issued by the
Department by duly employing technical persons. The
contractor is also responsible for QUALITY
EXECUTION of work.
Estimates, Administrative Approval and
Technical Sanction (Article 185 of “F” code, para
99, 101, 102, 154, 390 of A.P.P.W. “D” Code,
G.O.Ms.No.94 dt.1.7.2003)
➢ State Government works are executed following
the specifications, rules and regulations laid down
in:
▪ AP Standard Specifications (APSS)
▪ ISI, IRC, MOST, CPWD etc specifications
▪ AP Departmental code
▪ AP Accounts code
▪ G.O’s issued from time to time
➢ In Irrigation department, for every project, estimates are
prepared on 3 different occasions.
➢First, at the time of preparation of feasibility report; a very
rough estimate is prepared, based on experience in
construction of similar projects.
➢When once Government accords approval to take up detailed
investigation, a detailed project report (DPR) is prepared
based on preliminary designs.
➢ In the DPR the main canal estimates are prepared on levels
taken at 200 m interval. For the distributor net work and
CM/CD works estimates are drawn from cost curves. There
are bound to be variations when actual construction takes
place.
➢Government first accords Administrative Approval, based
on DPR estimates.
➢When actual execution is taken up, further detailed
investigation is carried out at closer intervals of 25 m,
actual quantities are worked out and then detailed
estimates are prepared adopting Rates as per:
➢The common SSR (Standard Scheduled of Rates) of
all Engineering Depts approved by Board of Chief
Engineers every year (which comes into force with
effect from Ist June of every year).
➢The Estimated Amount thus arrived will be the ECV
(Estimated Contract Value) of the tender put to bid.
➢The technical sanction is accorded by the competent
authority and after technical sanction, tenders are invited.
➢ It is observed in practice that detailed estimates prepared
so carefully are also revised based on actual at the time of
construction.
➢Revised Estimates (Article 197, Para 214, Para 215 ).
➢A revised technical estimate must be submitted when the
expenditure is likely to exceed the amount of sanctioned
estimate plus such excess as can be passed by the
appropriate authority for any case what ever other than
tender premium or when material developments or
deviations necessitate revised administrative approval.
11
Flaws in the existing practices
➢ Abnormal variations in the sanctioned estimates and revised
estimates.
➢ Delays due to non-finalization of alignment, non-approval of
drawings, delays due to approval from competent authority for
change in soil classification, Change in leads and lifts and delays in
land acquisition and R & R.
➢ Prolonged litigation by Arbitration.
➢ Thus there are both time and cost overruns in conventional
tender system.
12
EXAMPLE:
➢ Telugu Ganga Project started in 1983 with an
estimated cost of Rs. 640 crores and programmed to
be completed in 6 years, expenditure till 2003 was
Rs 1800 crores with stage of completion @ 60%.
Balance works are taken up and nearing completion
under Jalayagnam Programme. The total revised
cost of project is about Rs. 4000 crores with actual
completion period of more than 25 years.
13
Prolonged Litigation by ARBITRATION:
➢ Arbitration clause as per act, was introduced in L.S.contracts, with a noble intention to render quickjustice.
➢ The most common factors in the arbitration claims are-Change in quarries and increase in leads,-Reclassification of soil strata,-Delays in processing of Land Acquisition and R & R,-Delays in processing of Project Clearances from
different departments and acquisition of forest areasetc,.
14
Prolonged Litigation by ARBITRATION:
➢ All these lapses are often attributed to theDepartment and the Department in most of thecases put up a meek defense and leads toexorbitant claims used to be admitted.
➢ Government, therefore, brought a change in thesystem in 1986, putting a ceiling of Rs. 50,000/ forresolution of disputes through Arbitration. Forclaims above Rs. 50,000 agency has to seek disputeresolution only through civil suit. This has resultedin bringing down the amounts due to arbitrationclaims drastically.
15
➢ CAG in his report ending 31st March, 2004 has reviewed 24
Irrigation projects (10 Major and 14 Medium), taken up in
Andhra Pradesh, out of which 17 were more than 20 years
old,
➢ observed that out of 24 projects, 13 projects only were
giving partial benefits
➢ in respect of 11 projects no benefits accrued.
➢ It was also observed as “Delay in completion of the
projects resulted in huge cost overrun (583%) and non-
achievement of intended benefits (vide para 1.8.1 of CAG
Report for the year ended 31st March , 2004. )
Observations of CAG
Concept of
EPC Contracts & Salient Features
17
NEED FOR EARLY COMPLETION OF IRRIGATION PROJECTS
➢Certain areas of Andhra Pradesh have been under thesevere influence of Drought for many years.Agriculture in those areas were fully dependent onmonsoon.
➢The livelihood of farmers in those regions wereaffected. Many debt strapped farmers took theextreme step of taking their own lives.
➢On one hand more than 2000 TMC of water is wastedin to sea every year and on the other hand in about 800taluks out of a total of 1128 taluks in A.P., peoplesuffer for want of water, both for irrigation anddrinking needs.
18
➢ Thus, urgent need was felt by government for earlycompletion of Irrigation projects to utilise the dependablewaters.
➢ To stabilize the agricultural sector, I & CAD Department in 2004has introduced the “Jala Yagnam” program.
➢ In these efforts, the State Government has not only sanctionedprojects but is also giving adequate financial resources tocomplete the projects. From 2004 onwards till date, 86irrigation projects (including major and medium irrigation,modernization and flood banks) are taken up with estimatedcost of Rs.1,85,610 Crores for creating an additional irrigationpotential of 109 lakh acres.
19
CHOICE OF PROCUREMENT
➢To carryout the programme in a time bound manner, the
Government looked around the world for the existing
practices of procurement for Irrigation Projects to obtain
the best practices.
➢Breaking up the works into convenient packages and
entrusting them to major construction companies on
EPC Turn Key System.
➢The EPC system is in vogue in developed countries and
in some of the public sector undertakings in India and
successfully adopted in Narmada Valley project, NTPC,
NHPC, NHAI etc.
FIDIC : (French acronym for the International Federation of Consulting
Engineers)
International Federation of Engineering Consultants, Europe – released a
standard tender document.
in 1987 – Red Book (Designs by employer, work by contractor)
in 1995 – Orange Book / Yellow Book (Designs & work by contractor)
in 1999 – Silver Book – EPC Turnkey System (Definite date & definite
amount) As per this document
The Employer
(i) has to obtain all project clearances, land acquisition and R & R.
(ii) make fund arrangements and make payments in time.
The Contractor
(i) has to Investigate & Design (Engineering)
(ii) has to Procure men and materials and
(iii) construct the project
FIDIC : (French acronym for the International Federation of
Consulting Engineers)
International Federation of Engineering Consultants,
Europe – released a standard tender document.
in 1987 – Red Book (Designs by employer, work by
contractor)
in 1995 – Orange Book / Yellow Book (Designs & work by
contractor)
in 1999 – Silver Book – EPC Turnkey System (Definite
date & definite amount) As per this document
THE SILVER BOOK(EPCT Contract)
• More certain final price and time required
– Balance of risk being changed
– Privately financed BOT type
• Contractor asked to cover extra risks
• Employer will have to pay more
• Completely new book – unbalanced risk
• Full open acceptance of risk picture
• Starting point for BOT type projects
22
(contd….) EPCT Contract
The EPCT Contract is suitable for:
➢particularly E&M and process plant projects
➢all types of Employers
➢civil law jurisdictions
➢where government employer or private developer wants a fixed price turnkey basis and two-party approach
23
Special Features of theSilver Book
• Responsibility for design lies with Contractor
• Employer’s Requirements usually a ‘performance specification’ (functional basis)
• Contractor carries out all engineering, procurement, construction, ready for operation at the ‘turn of a key’
• No Engineer - instead the Employer
• Lump Sum Contract Price (but adjustments in limited specified cases)
24
(contd…) Special Features
• These Conditions are not suitable in the following circumstances:
➢ if time or information is insufficient before Contract signature
➢ if considerable work underground or difficult to inspect
➢ if Employer intends to supervise closely or control or review
➢ if an intermediary certifies interim payments
➢ where part of the works is designed by the Employer
25
Mr. Grove, the Eminent Engineer, who was the chairman
of the Engineers team, which executed the Hong Kong Air
Port (1990-1997) pleaded for all risks to be borne by
employer.
The winning tenderer, under EPC system, will either be
the gambler or low guesser.
Mr. Christopher Wade, Chairman, FIDIC commented in
2001 that Silver Book is now a reality.
The Silver Book, has become internationally popular and
is now available on U.N. website.
27
28
E.P.C – TURN KEY SYSTEM
E.P.C (Engineering Procurement Construction) /
Turn Key System is the methodology being
adopted for expeditious completion of the
projects to achieve the targeted goals by
simultaneous Investigation, Exploration, Design,
Estimating, Procurement and Construction and
Completion of Projects in a time-bound manner.
29
ENGINEERING
➢The Agency (Contractor) shall carry out all the related
surveys ie., Project site, Head Works, Canals and Distributory
system etc.
➢The Agency shall also conduct the exploration of sub soil for
preparation of detailed designs and drawings of various
structures.
➢The Agency shall prepare Hydraulic Particulars of canals
and designs for all Structures (Head Works and CM & CD
Works) and submit to the Department for approval. The
Construction will be taken up after approval by the
Department.
30
➢The Agency shall also prepare the Land Plan schedules
required for acquisition of land for construction of the
project components including localization of area to be
irrigated and submit to the Department for further
processing and making available the lands for construction.
31
PROCUREMENT
➢The agency shall work out the requirement of machinery,
material, men etc for construction and procure them as per
requirement for completion of various components of the
project as per the time frame stipulated.
➢The agency shall also evolve the construction programme to
complete the whole work in a stipulated period (PERT and
CPM charts) and the Department shall approve the same.
32
CONSTRUCTION
➢As per the approved Hydraulic Particulars, designs
and drawings for various components of the project, the
construction shall be taken up and completed by the
agency as per the milestones agreed.
➢The agency shall establish a quality control lab and
conduct various tests to specify the quality requirements
and standards specified for each item of work as per the
BIS codes.
33
➢The agency shall also maintain all the required
records of the materials, test results, mark out,
placement, consolidation, and any other registers
that are required for satisfying the Department as
well as the third party quality assurance teams or
any other agency.
➢The agency shall prepare the record of
measurements of the work done and produce to
the Department for checking and arranging
payment.
34
➢The Department shall arrange land to the agency and
continuously monitor and keep a watch on the quality of
work, rate of progress, approval of designs and take
necessary actions as per agreement, payments etc., to
ultimately get the whole work completed on turnkey basis
by the agency within the stipulated period.
➢The agency shall also do the operation and maintenance
for a period of 2 years after completion of the project.
During the operation and maintenance period of the system
they should ensure water supply to the whole of the ayacut
contemplated under the project.
➢The contractor will be discharged of his responsibility only
after successful performance of all the above conditions.
35
ADVANTAGES OF EPC SYSTEM
➢The procurement is for completion of the job in totality, but not
for completion of quantities assigned, as per the existing age old
practice.
➢The contract covers investigation, soil/foundation exploration,
preparation of designs & drawings, procurement of materials and
execution of the work to complete the job in all aspects.
➢Minimization of Project cost due to competitive designs and
latest construction techniques.
Advantages. . .
36
➢Contract value is only one fixed amount. No additional payments
either by way of increased quantities, variation of classification of
soils, increased foundation depths, deviations due to leads, change
of quarries etc. will be given.
➢ This system is followed in Narmada valley project and other
Central Government undertakings and has been completed
successfully.
➢ Pre-qualification (RFQ & RFP)▪ In case of specialized nature of works, tenders for pre-
qualification will be called for inviting the firms havingrequired experience in that specialized category ofworks.
▪ They will be short listed against some qualificationcriteria.
▪ Whenever the tenders are called for that specializedcategory of work, only these short listed firms will beeligible to tender.
➢ Tender (bid) documentsTender documents are to be approved by the authority whoaccords technical sanction.
37
➢ Tender (Bid) documents comprise off
▪ NIT (Notice Inviting Tenders)
▪ Instruction to bidders
▪ Conditions of contract (General/special)
▪ Technical Specifications
▪ Basic Parameters / Project Profiles
▪ Mile Stones (Annexure – I)
▪ Payment Schedule (Annexure – II)
38
➢ To supply copies of estimates, agreements etc. to QC
& 3rd party agency, if not already supplied by
EE/SE.
➢ To study thoroughly the specifications, drawings,
estimates, agreements etc., pertaining to all works
under his jurisdiction.
➢ To ensure that the following registers are opened
and maintained by the EPC agency.
Roles And Responsibilities Of The
Assistant Executive Engineers
39
1 Site order book2 Mark out register3 Placement registers for different items of
work i.e., earthwork, masonry, concrete, revetment, reinforcement and other test reports.
4 Bench mark registers5 Compaction registers in case of
embankments6 Materials register7 Register of test report of compressive
strength of concrete specimens8 Cement day book.
Note:- shall check and produce the above records to
the QC, 3rd party agency & inspecting officers.
Roles And Responsibilities Of The
Assistant Executive Engineers
40
➢To verify whether any phased execution is being
planned by the EPC Agency. If not give inputs
freely in writing to Engineer-in-charge.
➢Whether 5% Mobilization advance taken for men
and materials is being properly utilized.
➢ Whether 5% Machinery advance taken is being
properly invested for purchasing new or old
machinery and availability of them at the site of
work.
➢Whether insurance coverage is taken on labour,
materials, machinery and its crew for the the
agreement period including observation period.
41
➢Whether land to be acquired is properly
assessed .
➢Whether the authorized technical agents are
being deployed by the EPC agency.
➢Whether all the investigations required for the
project is being carried as per agreement
conditions.
➢Shall see that the mark out of the area to be
tackled is properly taken and recorded in the
register by the EPC Agency. The same shall also
be got duly checked by the Dy. E.E Construction.
42
➢ Shall see that the following OK cards are kept ready at
the site of work by the EPC agency before starting the
work and that they are used at different stages of work.
1. OK card for cast-in-situ cocrete lining .
2. OK card for Earthwork Embankment.
3. OK card for grouting .
4. OK card for structural concrete work.
➢ Pre-levels(33%) and final levels(100%) should be
checked in respect of earthwork and also get them
checked by DEE Construction.
➢ As soon as the cutoff trenches are excavated, the fact
should be intimated to the QC Staff & 3rd party agency
and got them passed area wise, before filling the COT.
43
➢ To ensure that the Foundation levels in respect of
structures are recorded by the EPC Agency and get
them checked by the DEE (Const.) immediately
including verification of soils met with and the same
should be intimated to the AEE and DEE of QC and
3rd party to check the levels and soils and get the
areas passed before laying concrete.
➢ The returns of LF Books pages used, MB pages used,
progress reports, log extracts of all machinery etc., and
maintained should be verified & submitted to the 3rd
party Agency through EE concerned before 20th of
current month and 5th of succeeding month. The
measurement book and L.F. book are to be issued by
the concerned Executive Engineer duly certified and
numbered.
44
➢ The construction materials required and got collected
at site should be checked and intimated to QC staff
and 3rd party Agency well in advance, so as to enable
them to conduct necessary field tests required for
passing of the materials.
➢ The samples of materials proposed to be used on the
work to the extent required as per norms are to be
collected and sent to the lab for testing their suitability
and results obtained before starting the work.
➢ Similarly ensure that the samples are also got tested
by the EPC Agency at their established laboratory and
also some of the samples tested by the EPC Agency at
independent laboratories such as APERL or any GOVT
Eng Colleges/Institutes.
45
➢ Copies of the above test results shall be made available
to the counterparts and 3rd party Agency for study and
verification.
➢ Shall ensure that all the machinery/equipment being
used by the Contractor are got periodically calibrated.
➢ The values of OMC and MDD may be obtained for the
soils from the lab in advance .
➢ All the materials proposed to be used and the areas for
placing the embankment, earth/concrete may be got
passed by the QC Staff and 3rd party Agency before
starting of the work.
➢ To examine the foundations, so as to assess that they
are to designed specifications and to record the same in
the registers.
46
➢ If the above soils are varying from the
proposed, the revised drawings may have to
be obtained from the competent authority.
➢ The earth/structural work should be carried out
strictly in accordance with the specifications
laid down in the APSS and relevant IS Codes,
as well as agreements. In case of any
discrepancy the same should be brought to the
notice of the Executive Engineer construction.
➢ Before starting the concrete work, he should
ascertain that the materials and equipment
available for the work is adequate.
47
➢ Shall supervise and ensure that, correct
quantities of input materials as per the mix
design communicated by the central lab are fed
into the mixers/batching plants and shall ensure
adequate mixing time.
➢ Shuttering for concrete/RCC works to be
checked, not only for dimensions, but also for
gaps between shutters, dents in shutters, before
allowing the concrete for getting correct shape
and smooth faces.
➢ The steel used for reinforcement is to be got
tested for its tensile strength, diameter, unit
weight etc and to satisfy before use. Proper
cover to be ensured for reinforcement.48
➢ Shall ensure proper curing of samples collected, till the
stipulated time is over and to make arrangements to
send the samples to the laboratory.
➢ The concrete samples may be obtained during the laying
of concrete and the same may be sent to the lab for their
strength at 7 days and 28 days respectively. The results
to be recorded in the registers. Latest equipment to be
used to test these at site of work.
➢ Shall ensure cutting of concrete and scrapping so as to
prepare the surface for the next lift of work.
➢ Shall ensure proper curing/watering and shall allow the
removal of the centering only after prescribed time limit
as per specifications.
49
➢ Shall ensure conducting the field tests on the day of
working
➢ Testing of materials being used on the work like cement,
steel, sand, aggregates etc.
➢ Conducting of Non-destructive tests.
➢ Further work is to be done only after attending to the
remarks of the QC Staff and after obtaining their
signature, in token of their acceptance.
➢ Whether payments made to the contracting agencies
are as per actual execution and drawings and according
to the agreement conditions.
50
➢ Whether advances paid are being recovered regularly
including interest accrued from the work bills as per
agreement.
➢ Whether the work is being executed as per milestones
agreed according to the agreement.
1. If not, reasons for not achieving the
milestones.
2. Is it due to contracting agency fault or
department delay.
3. If it is due to agency fault, whether liquidated
clause is imposed and recovered as per
agreement.
4. If it is due to departmental delay, whether
revised milestone programme is approved by
the competent authority.
51
➢ Whether recoveries like Siegnorage fee, IT, VAT
and other statutory taxes are being recovered from
the work bills.
➢ Whether defects pointed out by various
supervising agencies being rectified or redone.
➢ Whether labour amenities are provided to the
working labour and their families.
➢ Verification of final measurements for the
completed works and comparing with approved
drawings.
52
53
➢Now a days, several Govt., memos and technical
circulars amending the existing norms are being
issued very frequently and hence keep always
updated.
➢ Insist upon regular meetings at division and
circle office level for frank and free airing of views.
➢Shall ensure that the 3rd party Agency shall
possess all the testing facilities as per Agreement
relevant to the works in progress and that they
verify 10% of the tests being done by the EPC
Agency besides conducting independent tests to
assure the quality of work.
➢ Shall obtain the daily reports being furnished by
the 3rd party Agency. Adverse remarks if any shall
be got attended by EPC Agency and cleared by
them and shall then only recommend for
payment to the EPC Agency by sending his bills
to the 3rd party Agency for certification through
the Engineer – in – charge.
➢ All the above can only be implemented if day to
day record is being maintained which leads to the
conventional system of execution.
54
INSTITUTIONAL ARRANGEMENTS:
1. IBM : Through a High Level Technical Committee.
(Eng in Chief, CE/CDO and Concerned ProjectChief Engineer)
2. State Level Standing Committee: ENC, CE/CDO,.
Commissioner of Tenders, Chief Engineer (Projects),
representative of Finance (DOA). (Evaluation of Tenders,
Price Escalation, Addition / Deletion of work, Extension
of time, Sub-Contracts etc.,)
3. ENCs Committee: To examine agreements, deviations
in basic project parameters and other issues, as
directed by the Government.
INSTITUTIONAL ARRANGEMENTS:
4(a). High Power Committee: Chief Secretary, Spl.
Chief Secretary (Finance), Secretary, Irrigation. For
scrutinizing tenders and recommending category – I
packages, each valued above Rs. 150 Crs.
(b). Committee of Secretaries: Prl. Secretary
(Finance), Secretary (W&P) Finance and Secretary,
Irrigation. For scrutinizing Medium Size Packages
(below Rs 150 crores).
57
Internal Bench Mark
➢ ECV (Estimated Contract Value as per detailedestimate) in conventional LS contract method isreplaced by Internal Bench Mark in EPC mode ofcontracting.
➢ IBM is prepared by field Engineers with provisionsmade based on the cost of already approved similaritems of work, data from the available DPRs, arrivingat prorate cost by detailed survey of some portion ofayacut / command and scrutinized and approved bythe concerned Chief Engineer.
58
Internal Bench Mark (Contd….)
➢ To verify the sufficiency of the IBM value i.e. from eliminating any unnecessary provisions / inflation as well as to include any missing essential provisions, IBM Committee consisting of the following Technical Experts was constituted by the Government
1) Engineer in Chief (of the respective region)2) Chief Engineer, CDO.3) Chief Engineer (of the concerned project)
The IBM Committee examines the provisions andfinalises the IBM value.
59
Designs
➢The EPC Agency is not vested with approval of any
Designs.
➢Approval of all designs is vested only with the
Department i.e. Chief Engineer, CDO, concerned Chief
Engineer / Superintending Engineer as per delegation
ensuring compliance of the standards stipulated as per
the CWC guidelines, Bureau of Indian Standards
(Formerly IS Codes).
➢Detailed design guidelines were also issued from time
to time .
60
➢Further guidelines for approval and finalization of
designs of structures were issued streamlining the
whole process vide Government Memo No.
3277/Reforms/2008 Dt: 2-4-2008.
➢Foundations of all Earth Dams and major structures,
deep cut reaches tunnels etc, get inspected by the
Geological Survey of India and designs are finalized
as per their suggestions irrespective of proposals of the
EPC Agency.
61
Construction➢ EPC Agency is not allowed to take up any item of work on his
own.
➢ Construction work by the EPC Agency either Earth work orconcrete work etc., is permitted only after due checking of themark out / passing the area by the field Engineers of theDepartment duly ensuring necessary soil explorations,material testing, design mix for concrete etc.
➢ Necessary checks are exercised by the respective level of FieldEngineers.
➢ The measurements recorded are check measured (as per thepercentages stipulated) by the Field Engineers up to level ofSuperintending Engineer and certified by the TPQC Agencybefore recommending for payment.
62
Quality Control
➢ The quality control of all works executed by the EPC Agencies ischecked by the Field Engineers and quality control wing of theDepartment / V& E.
➢ No materials i.e. soils, sand, metal, cement, steel is allowed tobe used in the works without fully satisfying the characteristicsof the material by the Field Engineers of the Department.
➢ Other tests on the dams, concrete structures, gates, pumps,Motors, Pressure mains etc., are also carried out regularly bythe field engineers and quality control wing of the department.
63
Quality Control
➢Apart from the above, 3rd Party Quality Control
Agencies are also engaged to carry out necessary tests
to assure the quality of works executed out by the
EPC Agencies.
➢ 3rd Party Quality Control independently carry out
quality assurance measures by engaging experts like
experienced engineers and Professors from reputed
universities / Engineering Colleges by establishing
their own mobile testing laboratories, central
laboratory and all other equipment required.
64
Quality Control
➢Detailed guide lines for quality control were issued
vide Engineer-in-Chief, Irrigation Circular Memo No.
DCE-I/OT MP/AEE/29384/2005-3 Dt: 15.6.2006.
➢Without the certificate issued by the 3rd party quality
control after fully satisfying quality standards of the
works, no bill is admitted for payment.
➢Chief engineers for Quality Control also supervise
quality aspects.
65
Price Adjustment
➢Normal full price adjustment clause was notallowed for EPC contracts .
➢As a Safe Guard, Price adjustment of Cement,Steel, Fuels and electro mechanical componentsonly were allowed for EPC contract leaving asideother materials and labour which constitutesmajor amount in EPC Agreements.
66
Mobilization Advance
➢As per earlier procedure works exceeding more than Rs. 1.00crore of estimated contract value are permitted to availmobilization advance in two installments equivalent to 10%of the contract amount (5% for labour mobilization and 5%for machinery and equipment).
➢As a safe guard, mobilization advance of 5% towards Labourmobilization is paid in two installments i.e. 1% afterconcluding agreement and 4% at the time of commencementof work after completion of investigation, design and survey(clause 49.1 of the Agreement) as per instructions ofGovernment vide Memo No. 26135/Reforms/06 Dt:16.9.2006.
67
Maintenance Period
➢As Safe Guard towards performance of the system aftercompletion under EPC contract, Maintenance responsibilityis vested with the EPC Agencies for a period of 2 to 15 yearsas per system need.
➢After completion of the Project, the agency shall take careof maintenance for a period of 2 years in respect of gravitycanal systems and 5 to 15 years in respect of Lift IrrigationSchemes.
➢The agency shall be responsible for the maintenance of allcomponents of the project including associated works inaccordance with prudent utility practice (Clause – I ofSection – V of the Agreement).
68
Retention amount
➢ The Department retains from each payment due to thecontractor at the rate of 7.5% of bill amount as FSD untilcompletion of the whole of the works.
➢ The retention amount so accumulated will be released to atune of 5% against Bank Guarantee in Spells of Rs. 25.00 /50.00 lakhs. (Clause 47.1 of the Agreement) keeping a balanceof 2.5% (clause 47.2 of the Agreement)
➢ 5% (2.5% from EMD and 2.5% from FSD) of the value of workwill be retained till defect liability period of 2 years.
69
Liquidated Damages
➢As Safe Guard against delays in exemption of contract,
LD are stipulated in the Agreements.
➢ If the contractor fails to complete whole of the works or
any part thereof or section of the works within the
stipulated periods of individual mile stones (including
any bona fide extensions allowed by the competent
authority without levying liquidated damages), the
Superintending Engineer may without prejudice to any
other method of recovery:
70
Liquidated Damages
➢will deduct one twentieth of one percent (0.05%) of
respective mile stone financial programme value per
calendar day or part of the day for the period of
delays subject to a maximum of 10% of the contract
value as damages due from the contractor from any
amounts in his hands due or which may become due to
the contractor (Clause – 48.2 of the Agreement).
71
Insurance
➢The contractor shall obtain and maintain in force
including period of maintenance, contractor all risk
insurance for the project providing full coverage on
replacement value basis. Covered peril shall include
fire, flood and allied perils.
➢ Insurance for workers against injury and death as per
workman compensation act shall also be obtained by
the contractor (Clause – 8 of Section – V of the
Agreement)
72
Payment Schedules for Civil, Hydro-mechanical and Electro-mechanical
works
➢ Payment for Earth Work Excavation and lining of
gravity canals:
A) The unit length of eligibility for arranging payment for
earth work excavation of canals (excluding CM & CD
works) shall be taken as 100 M. for main canal
(discharge more than 10000 Cusecs), 250 M. for
main canal (discharge between 1000 cusecs and
10000 cusecs), 1.0 Km. for branch canal and
distributaries/majors (discharge between 10 cusecs
and 1000 cusecs).
73
Payment Schedules for Civil, Hydro-mechanical and Electro-mechanical
worksB) In case of deep cuts, the payment schedule shall
further subdivided into components berm wise with a
bay length of 25 M. and the berm wise payments shall
be followed duly restricting the berm wise payment to a
maximum length of 1 KM. in a reach (Govt. Memo
No.3277/Major.Irri/ 2006-5, Dt.24-2-2007).
C) The unit length for eligibility for arranging payment for
lining of canals shall be taken as 100 M.
74
➢ Payment for construction of CM
& CD works:A) In respect of CM & CD works, the intermediate payments
shall be in three stages, i.e., at (a) Completion of
foundations including earthwork, (b) Completion of Sub-
structure and (c) Completion of Super structure including
miscellaneous items. The mode of payment shall be 30%
after completion of foundations, 30% after completion of
Sub-structure and balance 40% after completion of
individual structure.
B) However, 30% of payment against 40% in the 3rd stage
shall be released after completion of deck slab of the
structure (CM & CD works), other than Aqueducts and
super passages and remaining 10% shall be released after
completion of structure in full shape. (Govt. Memo. No.
31960/ Reforms/2007-1, dt. 27.5.2008)
75
➢ Payment for construction of CM &
CD works:A) In case of big structures where ever the length
of structure is more than 40 M. and above on
main canal, the Chief Engineer may revise the
payment schedule subject to ensuring that the
over all payment is limited to the agreement
value. (Govt. Memo. No. 37245/
Reforms/2007-1, dt.11.2.2008)
76
➢ Payment for Hydro-Mechanical works:A) 85 % of the quoted price of Hydro-Mechanical works
component for supply of goods including fabrication (for
price including all taxes and duties) shall be paid on
receipt at the Project Site based on certificate prepared
by Engineer-in-Charge and Supplier’s Representative,
on the basis of various items received in accordance
with the Contract Agreement.
B) 10 % of quoted price of Hydro-Mechanical Works
component shall be paid on erection, testing and
commissioning of equipment, on pro rate contract value
of work completed as per the agreed construction
schedule and on certification by the Engineer-in-Charge
and Supplier’s Representative.
C) Balance 5 % of the quoted price of Hydro-Mechanical
Works component shall be paid at the time of final bill.
77
Contingent works
➢Where work can not be proceeded independentlywithout interfering with the work let out but havenecessarily to be executed along with the originalcontract shall be considered as contingent on theoriginal work.
➢ Contingent works may be with in the defined scopeor out side.
78
Non Contingent Works
➢Wherever additional items not contingent on themain work and outside the scope of originalagreement which has to be executed along with theoriginal work are non contingent works.
79