Continuous Improvement Seminar – ETF Overview
Dr Mariesha Jaffray 1st December 2016
Contents
Case for Continuous Improvement
Oil & Gas UK Re-set
Successful Continuous Improvement
CI at Oil & Gas UK
ETF Project Update
Cooperation, Culture and Behaviours
Case for Continuous Improvement: Significant Industry Challenges
Industry is starting to turn a corner
Operating Cost Reductions
Reduction from Existing Fields
Contribution from New Fields
7.5
8.0
8.5
9.0
9.5
10.0
2014-15 2015-16
9.7
8.0
8.2 8.2
7.17.0
6.5
Tota
l Op
erat
ing
Co
sts
(£ B
illio
n)
7.5
Concerted industry action is required to sustain these improvements
20-25%
40-50%
10-15%
15-20%
Operational Change
Price Reduction
Deferred Demand
Eliminated Demand
TransformationalShort-term? Sustainable?
Not uniform across all our companies, differential impact
CI at Oil & Gas UK: Oil & Gas UK Re-set
CEO
Deirdre Michie
External Affairs and
Communications
Trisha O’Reilly
External Affairs
Communications
Editorial and Design
Upstream Policy
Michael Tholen
Operations Excellence
Fiscal Policy
Energy Policy
Market Intelligence
HSE
Mick Borwell
Health and Safety
Environment
BusinessExcellence
Stephen Marcos Jones
Supply Chain
Continuous Improvement
Workforce Engagement
and SkillsMembership
Relations
Events
Finance and Corporate Services
Graham Elgie
Finance
HR
Legal
Business Services
Business Excellence Objectives are to ensure Oil & Gas UK are“Delivering a first-class service to our membership; embedding a culture
of continuous improvement right across the supply chain and throughout the industry’s workforce; promoting this industry’s excellence
regionally, nationally and internationally through innovative means”
Successful CI Programmes Agreed need for change
- Clear, long term vision
- Awareness of driving & resisting forces
- Capacity and capability
Commitment
- Key leaders
- Stakeholder buy-in & engagement
Structured, planned approach
- Consistent, robust governance
- Communications plan
- Meaningful metrics
- Ongoing review
Objectives are to..
Continuous Improvement Seminar 1st December 2016
Oil & Gas UK
Continuous Improvement
Drive ETF Strategy
Implementation of Project Delivery
Governance
Oversee and support ETF Deliverables
Ensure BE activities are value-adding
ETF Industry Lead Liaison
Facilitation of CI Project cycle
To seek, evidence, promote and provide access to efficient practice across UK oil and gas industry, without compromise to safety, by industry for industry.
Interface with other industry initiatives to ensure alignment and avoid duplication
The Efficiency Task Force (ETF)
• Established in 2015 as a catalyst for rapid behavioural change (internally & externally);
• Led by Walter Thain, technical specialism provided by industry and dedicated Oil & Gas UK resource;
• Drives pan-industry efficiency improvements by encouraging cooperation, focusing on value adding initiatives to create a sustainable sector;
• Initial phase focus: • Business Process; • Standardisation;• Culture, Collaboration and Behaviours.
Continuous Improvement Seminar 1st December 2016
ETF Structure
Oil & Gas UK Board
Business Processes
Inventory Management
Compression Systems
Procurement
Logistics
Maintenance
Standardisation
Subsea Standardisation
Valves
ETF Steering Group
Co-operation, Culture and Behaviours
Rapid Efficiency ExchangeContinuous Improvement
Network
Continuous Improvement Seminar 1st December 2016
2
1
1 Improvement Projects2 Cooperation, culture & behaviours enablers
Business Processes: Inventory Management Project
• Total estimated value of UKCS inventory is $£2bn• Improved management of this has cost savings potential in region of $30-50m p.a.• Aims:
(1) Determine appetite for & provide proof of concept for shared cross-industry UKCS inventory
(2) Establish a function cross-industry mechanism for trading material, Determine feasibility of a industry pool of commonly held items
Continuous Improvement Seminar 1st December 2016
Ampelius Inventory Pilot
Companies Impact
Marathon & ConocoPhillips (trade) • Prevented SNS LOGGS System shutdown
Taqa & Centrica (pump transfer) • Mitigated the need for three month lead time and potential well shut in
Apache, EnQuest, Total, Fairfield (multiple low value tradings)
• Significant cost avoidance
Achieved:• Registration of 23 companies & 100,000 items• Significant trading examples:
• Demonstrated collaboration and trading via inventory management is possible• User group review revealed current platform is not fit for purpose or
economically viable
Next Steps:• Review of inventory management requirements• Consideration of alternative platforms• Maintenance of workgroup collaboration & facilitation of trading
Continuous Improvement Seminar 1st December 2016
Business Processes: Procurement Project
• Tender inefficiencies are well known, particularly duplication• Anecdotally, tender activity is 4 times higher for the same amount of work• Improvements in tender efficiency hold a saving potential of £25m per year
Aims to:• Determine the extent and nature of duplication in the tender process and best steps to
reduce/remove this• Develop good practice framework and proof of concept during expression of interest,
ITT, tendering and pre-qualification process
Continuous Improvement Seminar 1st December 2016
Procurement Progress
Recent Achievements:• Working Group established• Review of process waste & potential savings (£25m/4%) in sample projects
(tenders from four contractors)• Development of Tender Efficiency Framework & webpage• Launch of Tender Efficiency Frame work at Share Fair & policy dinner
Next Steps:• Ongoing webpage development, expansion of framework into guideline• Board Managing Directors & Supply Chain Representative/Business
Development Manager workshop 15/12/16:- Share work done to date- Explore potential barriers and enablers- Secure commitment to adopt, engage & feedback- Generate implementation plan
Continuous Improvement Seminar 1st December 2016
The Tender Efficiency Framework
Continuous Improvement Seminar 1st December 2016
Standardisation: Subsea Technology
• Application of standardisation practices to project delivery can realise substantial cost savings
Short-term aims • Development of simplified, standardised approach to subsea development design, manufacture and installation across UKCS and proof of concept via case study application
Long term aims • Development of optimisation guidelines for application across UKCS
Progress to Date • Industry workshops completed to generate good practice guideline standardisation themes of: codes, standards and specifications, alternative methodologies, process and hardware
• Retrospective case study application of theory• Real life application to Centrica Pegasus West Case study
Next Steps • Presentation of results of Chevron West Wick Case study• Handover of project to O&G UK to plan implementation phase• Scope other areas for potential application
Continuous Improvement Seminar 1st December 2016
Four previously executed projects revisited applying the standardisation themes Substantial savings potential
UKCS Theoretical Retrospective Case Studies
Case Study 2UKCS subsea pipeline tieback
Total Savings: £13m = 18%
Case Study 1FPSO riser system
Total Savings:£7.75m = 25%
Case Study 3Subsea manifold & bundle
Total Savings:£26m = 15%
Case Study 4UKCS subsea pipeline tieback
Total Savings:£14.5m = 28%
Continuous Improvement Seminar 1st December 2016
Applying the Theory
Research Findings
Centrica West Pegasus
Potential efficiencies that could be applied to subsea developments by adopting a fit for purpose and a more simplified approach to projects.
The objective of undertaking this prospect review was to establish what cost savings could be realised when applying the findings identified to date to an existing prospect considered ‘economically challenging’.
Industry Review Previous Initiatives
Industry Review – Cultures, Behaviours and Practices
Standardisation Themes
Real Life Case Study-Prospect Review
Continuous Improvement Seminar 1st December 2016
Range*
Project Management and Engineering 20.4% 24.7%
Procurement, Manufacture and Fabrication
14.8% 28.3%
Transportation and Installation 16.3% 33.6%
The above % indicates the savings achieved within these groupings.
Overall Percentage Savings 20.4% 24.7%
Efficiency Cost Savings
* Dependant on Field Option
Standardisation is feasible:
• Real life application can realise significant savings (20-24%);
• Approach is not just limited to subsea application;
• Further cost savings are possible through application to other areas.
Continuous Improvement Seminar 1st December 2016
Cooperation, Culture and Behaviours Enablers
Continuous Improvement Seminar 1st December 2016
Collaboration Index
Continuous Improvement Seminar 1st December 2016
Cooperation, Culture and Behaviours Enablers: CIN
• Established December 2015 with representation from 30+ companies
Provides an active body for CI experts from the UK in Oil and Gas to support delivery of the Oil and Gas Industry Behaviours Charter
Acts as a focal point of contact between the member companies of Oil & Gas UK on all relevant issues including participation in Rapid Efficiency Exchange, CI events;
2016 survey output –Development of Task Finish Groups:
1. CI Continuing Professional Development (tie in with ECITB CI Standardisation) – Darren Clyde, Aker
2. Cultural & Behavioural Change (tie in with IBC) – Stuart Insch, Expro
3. Shared Learning/Collaboration (REE) – Nick Readman, Total
4. Interface and learning with other industries – Philip Oliver, Shell
5. Supply Chain Value Stream Mapping - Gary Downs, Aker
Continuous Improvement Seminar 1st December 2016
CIN Members
24
Cooperation, Culture and Behaviours Enablers: REE
• To facilitate cross industry learning and sharing of case studies
• 50 industry efficiency improvement case studies
• Highlight challenges being faced to encourage potential solutions
• REE v2 being developed
• Inclusion of workforce engagement element
• Ideas submission portal
• Activity tracking/follow-up assessment
• Discussion forum
Continuous Improvement Seminar 1st December 2016
What we need from you…
Advocacy & support
Contribution – case studies & challenges
Involvement in delivery of key projects
Application of good practice guideline and feedback
Idea generation
Continuous Improvement Seminar 1st December 2016
[email protected]#oilandgasuk