construction management and administration
DESCRIPTION
CONSTRUCTION MANAGEMENT AND ADMINISTRATION . UNIT - III . Unit III: list of topics. Normal distribution curve and network problems Project cost Project Time Acceleration Cost time analysis in network planning Time compression of critical path Updating, Rescheduling - PowerPoint PPT PresentationTRANSCRIPT
CONSTRUCTION MANAGEMENT AND ADMINISTRATION
UNIT - III
Unit III: list of topics
1. Normal distribution curve and network problems
2. Project cost
3. Project Time Acceleration
4. Cost time analysis in network planning
5. Time compression of critical path
6. Updating, Rescheduling
7. Simple problems of civil engineering works
Normal distribution curve and network problems
• Estimating the Probability of Completion Dates
– Determine the expected durations of all activities– Compute critical path– Assess the expected project completion time (along critical path) and SD– Determine the abscissa of normal curve in SD units as x= (scheduled date – expected date)/SD– The probability of completing the project in x units of time = Area under
the normal curve from - ∞ to x
• Estimating the …..% sure of meeting a deadline
Normal Distribution of Project Time
= tp Timex
Z
Probability
X -3s -2s -1s 0 1s 2s 3sArea, % 0.135 2.28 15.87 50 84.13 97.73 99.865
Activity Immediate predecessor Opt.Time Most likely
TimePessimistic
Time
a - 10 22 22
b - 20 20 20
c - 4 10 16
d a 2 14 32
e b,c 8 8 20
f b,c 8 14 20
g b,c 4 4 4
h c 2 12 16
I g,h 6 16 38
j d,e 2 8 14
Expected Time
20
20
10
15
10
14
4
11
18
8
Std.Dev
20
2
52
2
0
2
5
2
Expected Time
20
20
10
15
10
14
4
11
18
8
3
g 4
0 b 20
c 10
a,20
2
1 d 15
6
4j 8
f 14
e10
5
i 18
20 35
h 11
20 21
10 24
43 43
2514
3520
Variance
4
0
4
25
4
4
0
5
28
4
Critical path: a-d-j
• What is the probability of completing Project in 40days?
• Expected project completion time =43days
• SD of activities in critical path = sqrt of (4+25+4) = 5.745
• X=(scheduled date-expected date)/SD
• X= (40-43)/5.745= -0.522
• The Probability for x=-0.500 is 0.3085
• Probability of completing project in 40days is 31% approx
Assume, PM promised to complete the project in 50 days. What are the chances of meeting that deadline? Calculate X, where X = (s-m) / s
s = 50; m= 43; s =5.745;
X = (50 – 43) / 5.745 = 1.22 •The probability value of X = 1.22, is 0.888
1.22
What deadline are you 95% sure of meeting X value associated with 0.95 is 1.645 S = Exp.D + 5.745 (1.645) = 43 + 9.45 = 52.45 days Thus, there is a 95 percent chance of finishing the project by 52.45 days.
Project costProject cost broadly divided into 1. Direct Cost and 2. Indirect cost
2. Direct CostIt consists of expenditures which are chargeable to and can be identified specially with the activities of the project e.g. material cost, labor cost..
3. Indirect costIt consists of expenditures which cannot be clearly allocated to individual activities of the project e.g. establishment charges, insurance charges, administration charges…..
Direct Cost
DIRECT COST
MANPOWER
SUB-CONTRACTOR DEPARTMENTAL
MATERIAL
BASIC MATERIAL CONSUMABLES
MACHINERY
OWN HIRED
Indirect Cost
INDIRECT COST
VARIABLE COST
STAFF EXPENSES
LABOUR EXPENSES
PF &OTHER ITEMS
WELFARE EXPENSES
OTHER RATES & TAXES
WATER & POWER
CONVEYANCE EXPENSES
OPE
HIRE & RENTAL CHARGES
POSTAGE & STATIONERY
FIXED COST INFRASTRUCTURE
Project costco
s t
time
Direct cost
Indirect cost
Total cost
Total cost = Direct cost+ Indirect cost
Project AccelerationWhat are the reasons for project time acceleration?
– The contractor may wish to achieve job completion by a certain date to avoid adverse weather, to beat the annual spring runoff, to free workers and equipment for other work
– Financial arrangements may be such that it is necessary to finish certain work within a prescribed fiscal period
– The prime contractor may wish to consummate the project ahead of time to receive an early completion bonus from the owner
– Project work schedules must be adjusted to accommodate adverse job circumstances (local political/social issues)
– Revisions are often essential to meet contract time requirements– On a job in progress, the owner may desire an earlier completion date
than originally called for by the contract and may request that the contractor quote a price for expediting the work
Cost time analysis in network planning• Normal time (Tn)
– It is time for performing an activity with the normally available resources• Normal Cost (Cn)
– It is the minimum direct cost when the activity is performed in normal time duration
• Crashing– Reducing project time by expending additional resources
• Crash time (Tc)– It is the minimum time in which an activity can be performed
• Crash cost (Cc)– It is the direct cost corresponding to the crash time
Activity crashingAc
tivi ty
cos
t
Activity time
Crashing activity
Crash time
Crash cost
Normal Activity
Normal time
Normal cost
Slope = crash cost per unit time
Rate of crashing or Cost slope: It is the ratio of difference between crash and normal cost to the difference between normal and crash time
=(Cc - Cn) /(Tn –Tc )
Cost Optimization• Optimized cost
– The curve for total cost has a point where the tangent is horizontal. At this point, the total cost is minimum and is called the “optimum cost”. The time duration corresponding to the optimum cost is called optimum time
cos t
time
Direct cost
Indirect cost
Total cost
Optimal Project time
Min Total cost
Cost optimization depends on…• Rate of crashing or Cost slope• Critical path• Indirect cost
Project Time-Reduction variety of terms used to the process of shortening project time
durations– ‘‘Least-cost expediting,’’– ‘‘project compression,’’ and – ‘‘time-cost trade-off’’
Which activity to be expedited to reduce total project time?
The time required to reach any future network event, terminal or otherwise, is determined by the longest time path/critical path from the current stage of project advancement to that event
When the date of project completion is to be advanced, it is the network critical path that must be shortened
When a longest path is shortened, the floats of other activity paths leading to the same event are reduced commensurately
continued shortening of the original critical path will lead, sooner or later, to the formation of new critical paths and new critical activities
When multiple critical paths are involved, all such paths must be shortened simultaneously if the desired time advancement of the event is to be achieved
What sequence to be followed in activity crashing?
Least Cost slope activities first….
Procedure for Cost Optimization1. Determine the total cost from network of normal durations2. Calculate the cost slope of all activities3. Starting with the network of normal durations, crash the critical activity
having the least cost slope4. Redraw the network considering the above crashing and determine the
project duration and total cost5. Successively crash critical activities and determine respective project time
durations and total costs6. Determine the total cost for the all/max. crash network7. Tabulate project time durations and corresponding total costs and draw
the total cost vs. time curve8. Identify least total cost which is the optimum cost. The time
corresponding to this cost is the optimum time
Determine the optimum time duration and optimum cost. Also plot a curve of total cost vs. time and indicate on it the optimum time and optimum cost
Activity Normal Time, Tn
Crash Time, Tc
Normal Cost, Cn
Crash Cost, Cc
1-2 4 3 400 600
2-3 5 2 300 750
2-4 7 5 360 540
3-4 4 2 500 1000
1 2
3
4
Indirect Cost = Rs.250/day
1 2
3
40 4
4
5
7
4
9
13 13
9
40
Total Cost = Normal cost + Crash cost + Indirect Cost=(400+300+360+500)+0+(250*13)=(1560)+(3250)=4810 P1(13, 4810)
Activity Normal Time, Tn
Crash Time, Tc
Normal Cost, Cn
Crash Cost, Cc
Cost Slope, Rs/Day
1-2 4 3 400 600
2-3 5 2 300 750
2-4 7 5 360 540
3-4 4 2 500 1000
Indirect Cost = Rs.250/day
250
90
150
200
Critical Path:1-2-3-4
Step1: determine project cost with normal time
1 2
3
4
0 4
4
5-1
7
4
8
12 12
8
40
Total Cost = Normal cost+ Crash cost + Indirect Cost=(1560)+(150*1)+250*12=4710 P2(12, 4710)
Activity Normal Time, Tn
Crash Time, Tc
Normal Cost, Cn
Crash Cost, Cc
Cost Slope, Rs/Day
1-2 4 3 400 600
2-3 5 2 300 750
2-4 7 5 360 540
3-4 4 2 500 1000
Indirect Cost = Rs.250/day
250
90
150
200
Step2: Crash least cost slope activity in Critical path by 1day
Critical Path:1-2-3-4
1 2
3
4
0 4
4
5-2
7
4
7
11 11
7
40
Total Cost = Normal cost+ Crash cost + Indirect Cost=(1560)+(150*2)+250*11=4610 P3(11, 4610)
Activity Normal Time, Tn
Crash Time, Tc
Normal Cost, Cn
Crash Cost, Cc
Cost Slope, Rs/Day
1-2 4 3 400 600
2-3 5 2 300 750
2-4 7 5 360 540
3-4 4 2 500 1000
Indirect Cost = Rs.250/day
250
90
150
200
Step3: Crash least cost slope activity in Critical path by 2days
Critical Path:1-2-3-4 &1-2-4
1 2
3
40 3
4-1
5-2
7
4
6
10 10
6
30
Total Cost = Normal cost+ Crash cost + Indirect Cost=(1560)+(200*1+150*2)+250*10=4560 P4(10, 4560)
Activity Normal Time, Tn
Crash Time, Tc
Normal Cost, Cn
Crash Cost, Cc
Cost Slope, Rs/Day
1-2 4 3 400 600
2-3 5 2 300 750
2-4 7 5 360 540
3-4 4 2 500 1000
Indirect Cost = Rs.250/day
250
90
150
200
Step4: Crash activity 1-2 by 1day
Critical Path:1-2-3-4 &1-2-4
1 2
3
4
0 3
4-1
5-3
7-1
4
5
9 9
5
30
Total Cost = Normal cost+ Crash cost + Indirect Cost=(1560)+(200*1+150*3+90*1)+250*9=4550 P5(9, 4550)
Activity Normal Time, Tn
Crash Time, Tc
Normal Cost, Cn
Crash Cost, Cc
Cost Slope, Rs/Day
1-2 4 3 400 600
2-3 5 2 300 750
2-4 7 5 360 540
3-4 4 2 500 1000
Indirect Cost = Rs.250/day
250
90
150
200
Step5: Crash activities 2-3&2-4 by 1day further
Critical Path:1-2-3-4 &1-2-4
1 2
3
40 3
3
2
5
4-1
5
8 8
5
30
Total Cost = Direct cost + Indirect Cost=(Normal cost+ Crash Cost) + Indirect Cost={(1560)+(200*1+150*3+90*2+250*1)}+250*8=4640 P6(8, 4640)
Activity Normal Time, Tn
Crash Time, Tc
Normal Cost, Cn
Crash Cost, Cc
Cost Slope, Rs/Day
1-2 4 3 400 600
2-3 5 2 300 750
2-4 7 5 360 540
3-4 4 2 500 1000
Indirect Cost = Rs.250/day
250
90
150
200
Critical Path:1-2-3-4&1-2-4
Step6: determine project cost with max. crash time
Total Cost TimeP1 4810 13
P2 4710 12
P3 4610 11
P4 4560 10
P5 4550 9
P6 4640 8
5 6 7 8 9 10 11 12 13 144000410042004300440045004600470048004900
Optimum cost is Rs.4550 and Optimum time is 9days
Step7:Tabulate the calculated total cost and time values
Step8:Plot the graph of Total cost and Time
Step9:Determine Optimum cost & Optimum Time
Determine the optimum time duration and optimum cost. Also plot a curve of total cost vs. time and indicate on it the optimum time and optimum cost
Activity Normal Time, week
Crash Time, week
Normal Cost, Rs.
Crash Cost, Rs.
1-2 3 2 12000 16000
1-3 6 3 18000 24000
2-4 2 1 20000 24000
3-4 4 2 16000 21000
4-5 5 4 30000 35000
1 4
2
5
Indirect Cost = Rs.3000/week
3
Activity Normal Time, week
Crash Time, week
Normal Cost, Rs.
Crash Cost, Rs.
1-2 3 2 12000 160001-3 6 3 18000 240002-4 2 1 20000 240003-4 4 2 16000 210004-5 5 4 30000 35000
1 4
2
5
Indirect Cost = Rs.3000/week
3
15 15
Total Cost = Normal cost+ Indirect Cost=(12000+18000+20000+16000+30000)+(3000*15)=96000 + 45000=141000 P1 (15, 141000)
Step1: determine project cost with normal durations
Critical Path:1-3-4-5
10 10
6 6
3 8
0 0 3
6
2
4
5
What next?...& Why?
5
Activity Normal Time, week
Crash Time, week
Normal Cost, Rs.
Crash Cost, Rs.
Cost Slope, Rs/week
1-2 3 2 12000 16000
1-3 6 3 18000 24000
2-4 2 1 20000 24000
3-4 4 2 16000 21000
4-5 5 4 30000 350002500
4000
2000
4000
1 4
2
5
Indirect Cost = Rs.3000/week
3
5000
12 12
Total Cost = Normal cost+ Crash cost+ Indirect Cost=(12000+18000+20000+16000+30000)+(3*2000)+(3000*12)=96000+6000+36000=138000 P2 (12, 138000)
Step2: determine project cost with least cost slope critical activity
Critical Path:1-3-4-5
7 7
3 3
3 5
0 0 3
6-3
2
4
5
What next?...& Why?
2
Activity Normal Time, week
Crash Time, week
Normal Cost, Rs.
Crash Cost, Rs.
Cost Slope, Rs/week
1-2 3 2 12000 16000
1-3 6 3 18000 24000
2-4 2 1 20000 24000
3-4 4 2 16000 21000
4-5 5 4 30000 350002500
4000
2000
4000
1 4
2
5
Indirect Cost = Rs.3000/week
3
5000
10 10
Total Cost = Normal cost+ Crash cost+ Indirect Cost=(12000+18000+20000+16000+30000)+(3*2000+2*2500)+(3000*10)=96000+11000+30000=137000 P3 (10, 137000)
Step3: determine project cost with critical activity 3-4 crashing 2weeks
Critical Path:1-3-4-5 &1-2-4-5
5 5
3 3
3 3
0 0 3
6-3
2
4-2
5
What next?...& Why?
Activity Normal Time, week
Crash Time, week
Normal Cost, Rs.
Crash Cost, Rs.
Cost Slope, Rs/week
1-2 3 2 12000 16000
1-3 6 3 18000 24000
2-4 2 1 20000 24000
3-4 4 2 16000 21000
4-5 5 4 30000 350002500
4000
2000
4000
1 4
2
5
Indirect Cost = Rs.3000/week
3
5000
9 9
Total Cost = Normal cost+ Crash cost+ Indirect Cost=(12000+18000+20000+16000+30000)+(3*2000+2*2500+1*5000)+(3000*9)=96000+16000+27000=139000 P4 (9, 139000)
5 5
3 3
3 3
0 0 3
6-3
2
4-2
5-4
Step4: determine project cost with critical activity 4-5 crashing 1week
Critical Path:1-3-4-5 &1-2-4-5
What next?...& Why?
Total Cost TimeP1 141000 15
P2 138000 12
P3 137000 10
P4 139000 09
6 7 8 9 10 11 12 13 14 15 16 17 18130000
132000
134000
136000
138000
140000
142000
144000
Optimum cost is Rs.137000 and Optimum time is 10weeks
Step5:Tabulate the calculated total cost and time values
Step6:Plot the graph of Total cost and Time
Step7:Determine Optimum cost & Optimum Time
Determine the optimum time duration and optimum cost.
Activity Normal Time, month
Crash Time, month
Normal Cost, Rs.
Crash Cost, Rs.
1-2(B) 2 1 30000 32000
1-3 (C) 8 6 40000 46000
1-4 (A) 10 5 50000 75000
2-5 (D) 5 3 10000 15000
3-5 (E) 7 6 25000 26000
4-6 (F) 15 10 70000 100000
5-6 (G) 6 4 15000 23000
Indirect Cost = Rs.10,000/month
3
D, 51 B, 2
C, 8
A,10
2 6
4F, 15
G, 65
E, 7
Activity Normal Time, month
Crash Time, month
Normal Cost, Rs.
Crash Cost, Rs. Cost Slope, Rs/month
1-2 2 1 30000 32000 20001-3 8 6 40000 46000 3000
1-4 10 5 50000 75000 50002-5 5 3 10000 15000 25003-5 7 6 25000 26000 1000
4-6 15 10 70000 100000 60005-6 6 4 15000 23000 4000
3
51 2
8
10
2 6
415
65
7
0 0
8 12
Indirect Cost = Rs.10,000/month10 10
2 14 15 19 25 25
Total Cost = Normal cost+ Crash cost+ Indirect Cost=(2,40,000)+0+(25*10000)=2,40,000+0+2,50,000=4,90,000 P1 (25, 490000)
12 4
4
What next?...& Why?
Activity Normal Time, month
Crash Time, month
Normal Cost, Rs.
Crash Cost, Rs. Cost Slope, Rs/month
1-2 2 1 30000 32000 20001-3 8 6 40000 46000 3000
1-4 10 5 50000 75000 50002-5 5 3 10000 15000 25003-5 7 6 25000 26000 1000
4-6 15 10 70000 100000 60005-6 6 4 15000 23000 4000
3
51 2
8
10-4
2 6
415
65
7
0 0
8 8
Indirect Cost = Rs.10,000/month6 6
2 10 15 15 21 21
Total Cost = Normal cost+ Crash cost+ Indirect Cost=(2,40,000)+(4*5,000)+(21*10,000)=2,40,000+20,000+2,10,000=4,70,000 P2 (21, 470000)
8
What next?...& Why?
Activity Normal Time, month
Crash Time, month
Normal Cost, Rs.
Crash Cost, Rs. Cost Slope, Rs/month
1-2 2 1 30000 32000 20001-3 8 6 40000 46000 3000
1-4 10 5 50000 75000 50002-5 5 3 10000 15000 25003-5 7 6 25000 26000 1000
4-6 15 10 70000 100000 60005-6 6 4 15000 23000 4000
3
51 2
8
10-5
2 6
415
65
7-1
0 0
8 8
Indirect Cost = Rs.10,000/month5 5
2 9 14 14 20 20
Total Cost = Normal cost+ Crash cost+ Indirect Cost=(240000)+(5*5000+1*1000)+(20*10000)=2,40,000+26,000+2,00,000=4,66,000 P3 (20, 466000)
7
What next?...& Why?
Activity Normal Time, month
Crash Time, month
Normal Cost, Rs.
Crash Cost, Rs. Cost Slope, Rs/month
1-2 2 1 30000 32000 20001-3 8 6 40000 46000 3000
1-4 10 5 50000 75000 50002-5 5 3 10000 15000 25003-5 7 6 25000 26000 1000
4-6 15 10 70000 100000 60005-6 6 4 15000 23000 4000
3
51 2
8-2
10-5
2 6
415-2
65
7-1
0 0
6 6
Indirect Cost = Rs.10,000/month5 5
2 7 12 12 18 18
Total Cost = Normal cost+ Crash cost+ Indirect Cost=(240000)+(5*5000+1*1000+2*3000+2*6000)+(18*10000)=2,40,000+44,000+1,80,000=4,64,000 P4 (18, 464000)
5
What next?...& Why?
Activity Normal Time, month
Crash Time, month
Normal Cost, Rs.
Crash Cost, Rs. Cost Slope, Rs/month
1-2 2 1 30000 32000 20001-3 8 6 40000 46000 3000
1-4 10 5 50000 75000 50002-5 5 3 10000 15000 25003-5 7 6 25000 26000 1000
4-6 15 10 70000 100000 60005-6 6 4 15000 23000 4000
3
51 B, 2
8-2
10-5
2 6
415-3
6-15
7-1
0 0
6 6
Indirect Cost = Rs.10,000/month5 5
2 7 12 12 17 17
Total Cost = Normal cost+ Crash cost+ Indirect Cost=(240000)+(5*5000+1*1000+2*3000+3*6000+1*4000)+(17*10000)=2,40,000+=464000 P5 (17, 464000)
5
What next?...& Why?
Activity Normal Time, month
Crash Time, month
Normal Cost, Rs.
Crash Cost, Rs. Cost Slope, Rs/month
1-2 2 1 30000 32000 20001-3 8 6 40000 46000 3000
1-4 10 5 50000 75000 50002-5 5 3 10000 15000 25003-5 7 6 25000 26000 1000
4-6 15 10 70000 100000 60005-6 6 4 15000 23000 4000
3
51 2
8-2
10-5
2 6
415-4
6-25
7-1
0 0
6 6
Indirect Cost = Rs.10,000/month5 5
2 7 12 12 16 16
Total Cost = Normal cost+ Crash cost+ Indirect Cost=(240000)+(5*5000+1*1000+2*3000+4*6000+2*4000)+(16*10000)=464000 P6 (16, 464000)
5
What next?...& Why?
Total Cost TimeP1 490000 25
P2 470000 21
P3 466000 20
P4 464000 18
P5 464000 17
P6 464000 16
15 17 19 21 23 25 27 29450000455000460000465000470000475000480000485000490000495000500000
Optimum cost is Rs.464000 and Optimum time is 16months
Tabulate the calculated total cost and time values
Plot the graph of Total cost and Time
Determine Optimum cost & Optimum Time
Project Time Monitoring• As construction proceeds, diversions from the established plan and schedule
inevitably occur, some of the reasons are– Inaccurate estimation of the duration of completed activities– Unforeseen climatic conditions– Non supply of materials on time– Changes in the scope of work– Inadequate resources– Labor strikes, Bandh etc.
• Unforeseen job circumstances result in changes in – Activity durations,– Activity delays, and– Changes in project logic
• As such deviations occur and accumulate, the true job status diverges further and further from that indicated by the programmed plan and schedule
Project Time Monitoring• Time monitoring of complex projects can broadly be divided into
the following three stages1. Measuring the progress of current activities2. Updating sub-project plans3. Updating the project master schedule/original network
Measuring the progress of current activities• The state of activities is measured by comparing their actual progress against
the programmed schedule• At any point of time, activities can be classified in to
– Completed activities– In-progress activities and – Still to start activities
• The completed activities and the non-starter activities can be easily identified• Measurement of the in-progress activities is considered from two angles, i.e.
time performance and physical performance (work done quantity performance) – Time performance in terms of time units– Physical performance in terms of % of work done quantity
• The progress reports gives management only a general idea of the time status of the job
• To know the overall time status of the project as of the date of the last progress report , it needs a complete updating calculation
What is Network update?
Why Network update?
The method used for displaying progress of activities on the planning charts, corresponding to a given time is called Network updating
•To continue to provide realistic management guidance, it becomes necessary to incorporate the changes and deviations into the working operational program
• The basic objective of an update is to reschedule the work yet to be done using the current project status as a starting point
• Updating reveals the current time posture of the job, indicates whether expediting actions are in order, and provides guidance concerning how best to keep the job on schedule
• An update is also very valuable in testing the effectiveness of proposed time-recovery measures.
• Updating involves making necessary network corrections and recalculating activity and float times
• It is concerned entirely with determining the effect of schedule deviations and plan changes on the portion of the project yet to be completed
• It would keep job management continuously up-to-date on the time status of the work and would assure prompt and informed remedial action when needed
Network Updating….…
Network Updating method
2
Completed activity Completed event
Partially Completed activity
4
D
4
D
2
Still to start activity
4
G
3
New activities as a result of changes in the scope of work, should be incorporated logically into the network, and their durations written
Compute the EFT of the network to determine the minimum time required for the completion of the remaining work
Set the LFT equal to project time objective in the network. Time analyze the updated network
Network Updating method
0A0 0
42
3C
2
B
34
1D
5
5
7H
3
G
38
6E
2
F
1
J
2
5 7
4 4
4 5 7 8
7 7
7 7
10 10
7 9
Original Time scaled Network
• Progress of work of a project at the end of 6th week
Network Updating method
S.No.
Activity Duration Work done value (in 1000$)
Code Description original Balance of work
Total %
1 0-1 D 5 2 100 602 1-6 E 2 2 10 Nil3 6-8 F 1 1 5 Nil4 5-8 G 3 3 15 Nil5 0-2 A 4 0 20 1006 2-4 B 3 2 30 337 0-3 C 2 0 20 1008 3-7 H 3 3 45 Nil9 7-8 J 2 2 15 Nil
Total 260 42.3%
Network Updating method
0A0 0
42
3C
2
B
34
1D
5
5
7H3
G3 8
6E
2
F
1
J2
2 7
0 0
0 0 3 3
2 2
2 2
5 5
4 9
End of 6th week, updated Time scaled Network
2
2
Rescheduling• Resource smoothing is accomplished through rescheduling• Equipment conflict can be removed by rescheduling one of the
activities involved by using its float or by adding a precedence restraint to the project network. – Adding a precedence restraint means using a dependency line to show
that one of the activities involved must follow the other rather than parallel it
• The conflict must be removed by rescheduling activities with the least possible increase in project duration and cost
‘‘Manpower leveling’’ is the process of smoothing out daily labor demands. Perfection in this regard can never be attained, but often the worst of the inequities can be removed through a process of selective rescheduling of noncritical activities
Assignment -31. Define terms
1. Project Normal time, Normal cost2. Crash Cost, Crash time3. Cost slope4. Optimized cost and duration
2. Differentiate direct cost and indirect cost3. Explain the procedure for determining optimum cost and
duration for a CPM network4. Explain network updating and rescheduling