Configuration ManagementNon Government Std: EIA Standard-649
Configuration ManagementNon Government Std: EIA Standard-649
“A management process for establishing and maintaining consistency of a product’s performance, functional and physical attributes with its requirements, design and operational information throughout its life.”
• Identify and document the functional and physical characteristics of configuration items.
• Control changes to configuration items and their related documentation.
• Record (or Status Accounting in DoD terms) and report information needed to manage configuration items effectively, including the status of proposed changes and implementation status of approved changes.
• Audit configuration items to verify conformance to specifications, drawings, interface control documents, and other contract requirements.
- Adopted by DoD, 22 Nov 96
Configuration ItemsConfiguration Items
• CONFIGURATION ITEM (CI) - An aggregation of hardware or software that satisfies an end use function and is designated by the Government for separate configuration management.
• CIs will be directly traceable to WBS.
• Any item required for logistics support and designated for separate procurement is also a CI.
• Computer hardware & software will be treated equally as CIs.
• High risk or safety concern?
• Readily identifiable physically ?
• Newly developed?
• Use new technologies?
• Interface with item developed under another contract?
• Interface with other CI’s whose configuration is controlled by someone else?
• Requirement to know exact configuration during life?
Why Designate it as a Configuration Item?Why Designate it as a Configuration Item?
Impact of CI DesignationImpact of CI Designation
• Separate specifications.
• Put under configuration control.
Documentation
Formal approval of changes
Status accounting
Configuration Audits
• Individual design reviews.
• Separate qualification tests.
• Separate operating and user manuals.
Configuration BaselinesConfiguration Baselines
• Used to ensure an orderly transition from one major commitment point to the next.
• Three distinct evolutionary increasing levels of detail:
• Functional configuration documentation.
• Allocated configuration documentation.
• Product configuration documentation
• A baseline plus approved changes from that baseline constitutes the current approved configuration documentation.
ECP
Baseline
ECP+ + Approved
Configuration=
APPROVED APPROVED
IOCBA
Single Step orEvolution to Full
Capability
Concept &Technology
DevelopmentSystem Development
& Demonstration
Production &Deployment
Pre-SystemsAcquisition
Systems Acquisition(Engineering and Manufacturing
Development, Demonstration, LRIP &Production)
Operations &
Support
C
Technology Opportunities &User Needs
Post-SystemsAcquisition
Process entry at MilestonesA, B, or C (or within phases)
Program outyear fundingwhen it makes sense, but nolater than Milestone B(unless entering at C)
Relationship to Requirements Process
MNS ORD
All validated byRequirements Authority
or PSA
FRPDecisionReview
BLOCK II
BLOCK III
FOC
IOT&E
DESIG
N
FAB
, IN
TEG
RAT
E &
TEST
SFR
PDR
CDR
TRR
SVRSRR
Specification Evolution Across the Life Cycle
Specifications - - - - - - - - - - - - -----------------------------------------------------------------------------------------
System Spec
- - - - - - - - - - - - - -------------------------------------------------------------------------Item Performance Spec
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ------------------------------------------------Item Detail, Process, Material Specs
SFR
PDR
PCA
FCACDR
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ------------------------------------------------
- - - - - - - - - - - - - -------------------------------------------------------------------------
Functional (system)
Allocated (design to)
Product (build to)
Configuration Baselines - - - - - - - - - -----------------------------------------------------------------------------------------
Configuration Management PlanningConfiguration Management Planning
• The decision as to
• Which baselines the government should eventually control
• The data needed
• When that control should be established
are strategic management decisions that involve
• Acquisition strategies - sources, competition, etc.
• Logistics support plans - repair levels, data needs, open systems, etc.
• Technology insertion - stable vs rapidly moving technologies, etc.
Configuration Management StrategyConfiguration Management Strategy
• Government should control the Functional Baseline (documents system level requirements)
• DoD PMO’s increasingly choose to leave Allocated Baselines under contractor control until late in development. (Documents the CI level design requirements.) • Promotes contractor design flexibility
• Relieves PMO from administrative burdens of managing design ECPs
• Requires effective implementation of IPPD
• When and if to control baselines is dependent on support philosophy and acquisition management strategy.
Configuration IdentificationConfiguration Identification
• The selection of the documents to comprise the technical baseline for the system and configuration items involved.
• Selection of the numbers and other identifiers affixed to the items and documents.
• Basis for configuration audits, configuration control, and configuration status accounting.
s/n xxxxxx
s/n yyyyyy
ECPDWG
Spec’n
Dwg no xxx
Configuration ControlConfiguration Control
• Purpose of configuration control:
• Provide management visibility.
• Prevent unnecessary or marginal changes.
• Establish change priorities.
• Assure prompt action:
• Control the change.
• Document the change.
• Control the release system.
• A configuration control board is established to review
proposed changes and advise the program manager.
CONTRACTING
OFFICER
Configuration Control BoardConfiguration Control Board
OTHER
IMPLEMENTING
ACTIVITIES
ENGINEERING CHANGE
PROPOSAL (ECP)
Alteration in approved
CM Doc’s CI (possibly
with a spec change)
CONFIGURATION
CONTROL BOARD
DIRECTIVE
CCB SECRETARIAT (CONFIG MGR)
CHAIRMAN (PM)
USING COMMAND
TNG COMMAND
LOG COMMAND
ENGINEERING
PROCUREMENT
PROGRAM CONTROL
TEST
CONFIG MGT
SAFETY
FLT SURGEON
MAINTENANCE
CONTRACTOR
Begins & Ends
Configuration Status AccountingConfiguration Status Accounting
• Provides a track of configuration identification changes.
• Documents the configuration of items.
• Helps ensure on time shipments of change kits.
• Helps provide proper training.
• Helps ensure installation of correct items.
Configuration AuditsConfiguration Audits
• Verify and document that the configuration item and its configuration documentation:
• Agree.
• Are complete and accurate.
• Satisfy program requirements.
• Two types:
• Functional Configuration Audit
• Physical Configuration Audit
Functional Configuration AuditFunctional Configuration Audit
“ASBUILT”RECORDS
TEST
PROCEDURES
CONFIGURATIONIDENTIFICATION
CONFIG
ITEM
SPEC
QUALIFICATIONTEST REPORTS
COMPAREDWITH
RELEASEDENGINEERING
CONFIGURATION
QUALIFICATIONTESTING
INITIAL UNIT OF PRODUCTIONHARDWARE
AUTHORIZEDCHANGES
Physical Configuration AuditPhysical Configuration Audit
ACCEPTANCE TESTDATA
INTEGRATEDRECORDSSYSTEMFORMS
INPUT FOR CONFIGURATION
STATUS ACCOUNTING
REPORT
ACCEPTANCETEST
PROCEDURESRELEASE
ENGINEERINGDATA
PHYSICALLY(size, type, dimensions)
COMPARED WITH
ITEM DETAILSPECIFI-CATION
CONFIGURATIONIDENTIFICATION
INDEX
INITIALUNIT OF
PRODUCTIONHARDWARE
AUTHORIZEDCHANGES
COMPLIANCE REPORTED
VERIFY
SummarySummary
• Configuration management is essential to control the system design throughout the life cycle. The issue is not whether or not to have a configuration management program, but, rather, how it shall be managed.
• Configuration management impacts across the technical and business spectrum and requires an integrated (IPPD) approach to ensure that decisions made are well founded and that surprises do not occur.