confidential. for internal use only. smud smart...

168
Powering forward. Together. Dwight MacCurdy SMUD Smart Charging Pilot Program EPRI Infrastructure Working Council March 28, 2012

Upload: others

Post on 26-Feb-2020

12 views

Category:

Documents


0 download

TRANSCRIPT

  • CONFIDENTIAL. FOR INTERNAL USE ONLY.

    Powering forward. Together.

    Dwight MacCurdy

    SMUD Smart Charging

    Pilot Program

    EPRI Infrastructure Working Council

    March 28, 2012

  • DOE Smart Grid Investment Grant

    (SGIG) Acknowledgement

    • Acknowledgement: “This material is based upon work supported by the Department of Energy under Award Number OE000214.”

    • Disclaimer: “This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.”

    2

  • • 595,000 accounts

    527,000 residential accounts

    Peak demand of 3,299 MW in 2006

    Service area population 1.4 million

    ~ 100,000 participants in SMUD’S Air Conditioning Load Management Program

    ~ 70,000 transformers

    SACRAMENTO MUNICIPAL UTILITY DISTRICT

    3

  • SMART CHARGING PILOT PROGRAM:

    RESEARCH DESIGN

    • Up to 180 Participants in 3 or 4 treatment groups

    • For 2012 -- 2 or 3 new experimental rate offerings

    • Whole house EV TOU rate for Level 1 charging (not Level 2)

    • Submetered EV TOU rate (not whole house) with demand charge penalty above 2 kW for charging during peak hours on event days (12 days) for Level 1 or Level 2 charging

    • BUT, how can participants easily adjust to event-day dynamic pricing? What type of manual or automated control is needed in the car, or the EVSE, to make this effortless?

    • Possibly one other submetered rate offering for L1 and L2

    4

  • $0

    $10,000,000

    $20,000,000

    $30,000,000

    $40,000,000

    $50,000,000

    $60,000,000

    2011 -

    (500 E

    V's

    )

    2012 -

    (1,0

    00 E

    V's

    )

    2013 -

    (2,0

    00 E

    V's

    )

    2014 -

    (5,0

    00 E

    V's

    )

    2015 -

    (10,0

    00 E

    V's

    )

    2016 -

    (15,0

    00 E

    V's

    )

    2017 -

    (21,0

    00 E

    V's

    )

    2018 -

    (30,0

    00 E

    V's

    )

    2019 -

    (40,0

    00 E

    V's

    )

    2020 -

    (51,0

    00 E

    V's

    )

    2021 -

    (70,0

    00 E

    V's

    )

    2022 -

    (90,0

    00 E

    V's

    )

    2023 -

    (115,0

    00 E

    V's

    )

    2024 -

    (140,0

    00 E

    V's

    )

    2025 -

    (164,0

    00 E

    V's

    )

    2026 -

    (194,4

    000 E

    V's

    )

    2027 -

    (224,8

    00 E

    V's

    )

    2028 -

    (255,2

    00 E

    V's

    )

    2029 -

    (285,6

    00 E

    V's

    )

    2030 -

    (316,0

    00 E

    V's

    )

    An

    nu

    al

    Syste

    m U

    pg

    rad

    e C

    osts

    Year (Cumulative # EV's Installed)

    Annual System Upgrade Costs for Residential Charging 100% Coincidence Except for Sequential Smart Charging

    12 A.M. (6.6 KW)

    2 A.M. (6.6 KW)

    8 P.M. (3.3 KW)

    12 A.M. (3.3 KW)8 P.M. (2.0 KW)2 A.M. (3.3 KW)

    12 A.M. (2.0 KW)

    2 A.M. (2.0 KW)MANAGED CHARGING

    8 P.M. (6.6 KW)

  • SMART CHARGING PILOT PROGRAM:

    RESEARCH DESIGN

    • For 2013 -- Submetered EV TOU rate with “managed” charging during the summer. Communicating EVSE provided at no or low cost for up to 60 participants.

    • Shed signal from DRMS to EVSE

    • Billing systems will be fully interoperable.

    • Pricing info via gateway to EVSE in 2014

    • SMUD DRMS will trigger load shed events for up to 12 days/summer that drops Level 2 EVSE load to 1. 4 kW during peak (Level 1 equivalent, 6A @ 240V)

    • Summer peak from 2 pm to 2 am on critical days (12 event days, e.g. > 100 F)

    • Summer peak from 2 pm to midnight on non-critical days (non-event days)

    6

  • SMART CHARGING PILOT PROGRAM:

    RESEARCH DESIGN

    CBA

    7

  • • Radio

    8

  • • Radio

    9

  • Communication Paths for EVSE with “Managed

    Charging”: Dispatched by DRMS

    • Radio

    Zigbee

    SEP1.1

    Radio

    in EVSE

    Talks to EV

    Submeter

    To Receive

    Load Shed

    Commands

    SEP1.1

    over

    Broadband:

    Wifi Radio

    In EVSE for

    Shed Signal

    through

    HAN

    Gateway 1/

    Zigbee

    2.0

    Radio in

    EVSE

    with PLC

    Bridge

    To

    Vehicle

    10

    SMART CHARGING PILOT

    AutoDR

    through

    DRAS

    Server To

    EVSE

    DRAS

    Client

    with PLC

    to PEV

    FUTURE

    Preferred

    1/ Must Be SMUD Broadband Head End Software

    “Direct To

    Grid” SSN

    Protocol

    NIC Module

    in EVSE for

    Load Shed

    Commands

    with HCM

  • Where Is the Win-Win for the Customer

    and the Utility ?

    • Leverage existing utility AMI infrastructure investment

    • Encourage off peak charging – lowest cost of service

    for all

    • Convey pricing signals – transformer replacement

    cost

    • Allow for Customer choice – customer satisfaction

    11

  • Where Is the Win-Win for the Customer

    and the Utility ?

    • To minimize cost/complexity, the EVSE communications path is

    tied to DRMS communications path – zigbee / SEP2.0 / PLC,

    open standards, but with backups in mind

    • Zigbee communications to EVSE represents the most ubiquitous

    & flexible solution with AMI

    • In the long run how do we simplify metering and maintain revenue

    grade metrology? 3 meters? Primary meter, EV submeter, PV

    submeter? Or, single integrated meter with multiple metrology

    boards/circuits?

    • SMUD direction -- PLC from EVSE to EV

    12

  • THANK YOU!

    Dwight MacCurdy

    [email protected]

  • IWC – Atlanta, GA

    March 28th, 2012

  • PEV NPD Project : Duke Energy PROPRIETARY – Use pursuant to Company instructions. 2

    FACTS ABOUT DUKE ENERGY

    150+ years of service4 million customers5 states: NC, SC, IN, KY, OHFortune 500$50 billion in assetsStock dividends for 80+ yearsTraded on NYSE as DUKDow Jones Sustainability Index

  • PEV NPD Project : Duke Energy PROPRIETARY – Use pursuant to Company instructions. 3

    Utility testing through vehicle telematics

    • In a lab test with Onstar, we were able to:• Determine the customer

    preferences loaded in the vehicle

    • Determine the current state of charge of the vehicle

    • Determine which program the customer was enrolled in

    • Reduce the charge of the vehicle to 1.2 kw, to match the output of the solar panels in the lab

  • PEV NPD Project : Duke Energy PROPRIETARY – Use pursuant to Company instructions. 4

    Utility testing through an “intelligent” EVSE

    • Use cases:• Start/Stop Commands• Curtailment Commands• Override Capabilities• Conflict Scenarios – Vehicle vs. EVSE

    • Results:• Overall testing went well. Basic functionality worked as expected

    • Preliminary Recommendations:• Provide customer override functionality• During a load shed event the EVSE should show an indication of the

    event. • Ensure that DR functionality works independent of whether the vehicle

    is tethered at the time the event is called

    NOTE: the intelligent EVSE was tested against many more use cases than the testing done with Onstar. These preliminary recommendations should not be interpreted that the vehicle telematics solution is more robust than the intelligent charging station solution.

  • PEV NPD Project : Duke Energy PROPRIETARY – Use pursuant to Company instructions. 5

    What is the right solution for a Utility and the Customer?

    Challenges

    Many car companies to considerOEM desire to answer simple question, “How much does it cost to charge”?Long term implications of telematics contracts expiring Proprietary / non standard interfaces communications

    Challenges

    Many EVSE companies to considerExternal sub metering is expensiveHigh cost of equipment, installation and communicationsProprietary / non standard interfaces communications

    Car “Smarts” EVSE “Smarts”

    Fusion

  • PEV NPD Project : Duke Energy PROPRIETARY – Use pursuant to Company instructions. 6

    “Focus and simplicity. Simple can be harder than complex”- Steve Jobs

    • In the near term, utilities should look for low cost, flexible solutions• Utilities have been managing the load of air conditioners for years with simple,

    low cost commodity load control devices• As we move to two way communications and AMI, do we need a solution similar

    to what the USB port was to the PC years ago?

    • When possible, avoid a separate meter for PEV rates• Whole house TOU rates that incent PEV owners to charge on off peak hours• Challenge your rates department and PUCs to consider non-traditional metering

    approaches

    • Vehicle and EVSE OEMs should continue to innovate to further evolve the customer experience for PEV drivers• Onstar opening up their API’s to cultivate innovation in mobile applications and

    customer experience

  • PEV NPD Project : Duke Energy PROPRIETARY – Use pursuant to Company instructions. 7

    It seems like it was just yesterday…wasn’t it????

    • Johnny Carson retires and Jay Leno became host of NBC Tonight Show

    • The largest shopping mall in the US was constructed..."Mall of America"

    • Sinéad O'Connor rips a photo of Pope John Paul II on Saturday Night Live, causing huge controversy.

    • The Bodyguard, starring Kevin Costner and Whitney Houston, debuts in cinemas;

    • Governor Bill Clinton became the 42nd President of the United States.

    That was 20 years ago!!!We have time!!!!

  • PEV NPD Project : Duke Energy PROPRIETARY – Use pursuant to Company instructions. 8

    Stay focused and stay engaged…we are making a difference!

  • PEV PLC Communications(IEC/ISO, SAE Standardization)

    Slav BerezinGeneral Motors

  • PEV Communications topology

    PEVHAN/EMS

    Grid/Operators

    EVSE(AC/DC)

    Owner

    PEV will be communicating with all!

    Else

    2March 28, 2012 Slav Berezin

  • PLC standard• PLC is standardized as the primary PEV Communications protocol

    – Utilities specified PLC as the most reliable solution (August 2008)• Association with EUMD/ESI is needed to offer EV services/tariffs

    – OEMs have agreed to PLC as the international standard (May 2011)• PLC is absolutely required to facilitate communications with DC Off-board charger

    – HomePlug GP has been selected by ISO/IEC (January 2012) and SAE (March 2012) as a PLC technology of choice.

    • IEC/ISO and SAE are harmonizing on a single international PLC solution for PEV Communications– Premise is the same stack support PEV to EVSE/Utility communications and DC

    Off-board Charging• Minimizes development and integration costs• Provides better economies of scale and ensures interoperability

    – Provides simple uniformity to the utility industry for integration of PEV with their architectures

    3March 28, 2012 Slav Berezin

  • Layer

    ISO/IEC to SAE documents mapping

    1 Physical

    2 Data Link

    3 Network

    4 Transport

    5 Session

    6 Presentation

    7 Application

    ISO/IEC 15118 Vehicle to grid communication interface

    Part 1: General information and use-case definition

    ISO/IEC 15118 Vehicle to grid communication interface

    Part 2: Technical protocol description and Open

    Systems Interconnections (OSI) layer requirements

    ISO/IEC 15118 Vehicle to grid communication interface

    Part 3: Wired physical and data link layer requirements

    SAE J2836/1, J2836/2Use cases for Communications..

    SAE J2847/1, J2847/2Communications Between Plug-in Vehicles and the Utility Grid, Off-Board DC Charger (Messages)

    SAE J2931/4Broadband PLC Communication

    for Plug-in Electric Vehicles

    J2931/1Digital Communications for

    Plug-in Electric Vehicles(Protocol)

    TBD* (*J2931/1 or J2847/1 and /2)

  • PEV PLC-based System Setup

    PEV-EVSE communications link

    PLCCellular/PLC/Wi-FiWi-MAX/ZigBee/…

    5March 28, 2012 Slav Berezin

  • Next steps• Power Utilities need to achieve consensus on the PEV PLC link

    defined by SAE J2931/1, /4 and ISO/IEC 15118-2, -3 in designing their communications architectures– Harmonization of ISO/IEC utility communications with SEP2 needs to be

    addressed

    • EVSE Mfgrs will need to complete the communications link by providing the network bridge between the PEV and the Utility Communications Networks

    • OEMs and Utilities need to collaborate on requirements and timing for pilot, implementation, and roll out of the PEV PLC standard protocol– Utilities and EVSE Mfgrs engagement in the development and implementation

    process is critical

    6March 28, 2012 Slav Berezin

  • • Click to edit Master text styles

    • Second level

    EVSE CommunicationSecond level

    • Third level

    F th l l

    Communication Solutions for

    • Fourth level

    • Fifth level Dave PackardUtilities

    PresidentMarch 28, 2012

    1

  • Direct to Grid

    ClipperCreek Silver Spring Network Solution

    Utilit

    • Click to edit Master text styles

    • Second levelNeighboring meter

    Neighboring

    Utility Backhaul

    Direct integration from Utility DR Program w / verification

    Revenue Grade Metering

    Utility

    Second level

    • Third level

    F th l l

    Neighboringmeter Robust Solution

    Takes advantage of Utility SG

    • Fourth level

    • Fifth levelCustomermeter EVSE

    22

  • HAN Connection (ZigBee / Wi-Fi)

    Direct integration from Utility DR Program w / verification

    Utilit

    • Click to edit Master text styles

    • Second level

    Utility Backhaul

    In-Home Display

    Revenue grade metering (?)

    “Universal” solution

    Takes advantage of Utility SG

    Utility

    Second level

    • Third level

    F th l l

    y

    • Fourth level

    • Fifth levelCustomer

    meterEVSE

    HAN repeater

    33

  • Parallel Proprietary NetworkProprietary

    Cloud Application

    Proprietary Cloud

    Application

    Proprietary Cloud

    Application

    Proprietary Cloud

    Application

    Proprietary Cloud

    ApplicationUtility

    BackhaulProprietary Cloud Application UtilityUtilityUtility

    • Click to edit Master text styles

    • Second level

    In-Home Display

    Second level

    • Third level

    F th l lEVSE Customer

    Meter

    Neighboring Meter

    Metering

    • Fourth level

    • Fifth level HAN Repeater“Universal” solution

    Possible integration of utility DR w / verification

    Home Possible tie to public infrastructureUtility not in control

    44

  • Cellular ConnectionUtility

    Backhaul

    Utility

    Cell Service Provider

    • Click to edit Master text styles

    • Second levelIn-Home Display

    Second level

    • Third level

    F th l lEVSENeighboring

    Meter

    • Fourth level

    • Fifth level

    CustomerMeter

    EVSE

    CustomerAppliance

    Metering“Universal” solutionUtility controlled cloud

    HAN Repeater

    Home

    Possible tie to public infrastructureDR w / verification

    55

  • Pager Network

    Utility

    • Click to edit Master text styles

    • Second level

    ?

    Second level

    • Third level

    F th l lEVSE

    SimpleInexpensive“Universal” solution

    • Fourth level

    • Fifth level

    CustomerAppliance DR w / o verification

    No metering

    HomeHome

    66

  • Options

    Communication Options

    900 mHz Proprietary

    Metering Options

    Revenue Grade

    Control Options

    Scheduling

    • Click to edit Master text styles

    • Second level

    900 mHz Proprietary

    Cellular

    Wi-Fi

    Revenue Grade

    (?)

    Removable

    Scheduling

    Rate schedule

    User interfaceSecond level

    • Third level

    F th l l

    ZigBee (?)

    Ethernet

    Other

    Contained within EVSE

    Utility Access

    User home portal

    • Fourth level

    • Fifth level

    Other y

    Submeter

    77

  • Discussion

    Develop a solution that has the most options possible, EVSE core unchanged from utility to utility

    • Click to edit Master text styles

    • Second level

    Communications In

    Communications Out

    M t iSecond level

    • Third level

    F th l l

    Metering

    DR

    Time of use control• Fourth level

    • Fifth levelTime of use verification

    Other

    88

  • • Click to edit Master text styles

    • Second levelSecond level

    • Third level

    F th l lThank You

    • Fourth level

    • Fifth level

    9

  • Wireless Charging of Electric Vehicles Using

    Strongly‐Coupled Resonance

    Morris KeslerWiTricity Corporation

    National Electric Transportation Infrastructure Working Council

  • Outline

    • Motivations• Introduction to WiTricity’s Technology

    – Resonance– Coupling and Quality Factor

    • Application to EV/PHEV Charging– System description– Performance– Issues

    WiTricity Corporation 2IWC 2012

  • In the Middle of the Night…

    WiTricity Corporation  3IWC 2012

  • WiTricity Corporation  4IWC 2012

    From the Wall Plug to the DeviceApproaches to Wireless Energy Transfer

    Omni-directional

    Directed

    Radiative techniques Induction

    http://images.google.com/imgres?imgurl=http://opticsclub.engineering.ucdavis.edu/home_files/laser.jpg&imgrefurl=http://opticsclub.engineering.ucdavis.edu/&usg=__rExLLrlhpQfUIBZPSsxUkOrk-ss=&h=355&w=400&sz=25&hl=en&start=14&um=1&tbnid=uUYb6NlfsEzKvM:&tbnh=110&tbnw=124&prev=/images?q=laser&hl=en&rls=com.microsoft:*:IE-SearchBox&rlz=1I7DKUS&sa=N&um=1

  • Add Resonance to the Picture

    WiTricity Corporation  5IWC 2012

    • Resonator:– Stores Energy– Energy oscillates between two modes (spatial, temporal, form, etc.)

    – Examples: Pendulum, Quartz crystal, LC Circuit

    • Coupled Resonators:– Coupling mediates energy exchange between resonators

    – Efficient and selective energy transfer can be achieved

    – Examples: Coupled pendulums, coupled waveguides (filters, switches)

  • Coupled Resonators

    WiTricity Corporation 6IWC 2012

    • Described using coupled‐mode theory– Parameters: Coupling rate (κ), loss rate (Γ), resonant frequency

    • Conditions for efficient energy transfer– “Similar” resonant frequencies– Coupling rate greater than loss rate

    • Figure of Merit for system– U = κ/sqrt(Γ1Γ2) = k*sqrt(Q1Q2)– Optimum efficiency only a function of U

  • Efficiency of Energy Transfer

    WiTricity Corporation  7IWC 2012

    ( )2

    221 1

    U

    Uη =

    + +

    Optimum efficiency only a function of the figure-of-merit U

    1 21 2

    U k Q Qκ= =Γ Γ

    where

    Resonators with High Quality factor enable efficient energy transfer over distance.

    50% at U=3

    90% at U=20

    Coupling and Q are important factors

  • Using Magnetic Resonance

    WiTricity Corporation  8IWC 2012

    • Magnetic resonator– Simple example is a loop and capacitor

    B

    E

    Coupled Magnetic Resonators

  • WiTricity Corporation 9IWC 2012

    A Multitude of Applications

    Consumer Electronics

    Medical Devices

    LightingRobotics

    Electric Vehicles

    New applications are limited only by one’s imagination

    Solar Power

  • WiTricity Corporation  10IWC 2012

    Residential Use Case

  • Requirements for Wireless Charging of EV

    • Power levels up to 3.3 kW (initially)

    • High‐efficiency (90% end‐to‐end)• Tolerant to parking variations• Tolerant to variations in vehicle 

    ground clearance (vehicle loading, tire pressure, etc.)

    • Safely operate with people in and around vehicle

    • Satisfy EMC/EMI requirements

    • Safe, unattended operation

    WiTricity Corporation 11IWC 2012

    Resonators designed for high Q and coupling, efficient power electronics

    Efficiently operate over a range of magnetic coupling

    EM fields below ICNIRP limits where accessible

    Low radiated EM fields, Choice of frequency

    Detection of foreign objects, Built-in temperature sensing

  • WiTricity Corporation  12IWC 2012

    System Components for Wireless EV Charging

    RF AMP(DC‐RF)

    AC/DC(PFC)

    SourceResonator

    DeviceResonator

    AC/DC(Rect.)

    Battery

    MainsPower

    Source Electronics

    DeviceElectronics

    BMS

    Source Efficiency> 95%

    Wireless Efficiency90 – 98.5%

    Rectifier Efficiency> 99%

    Control

    AC Mains to Battery Efficiency of greater than 90% possible

  • Tolerance to Offsets

    WiTricity Corporation  13IWC 2012

    SourceResonator

    DeviceResonator

    Direction of Travel

    Parking Tolerance

    Δx

    Δy

    Δz

    Source Resonator

    Device Resonator

    Air-Gap Variations

    Δx up to +/- 20 cmΔy up to +/- 10 cmΔz up to +/- 2.5 cm

    Typical ranges:

    Systems must operate at high efficiency over this range of offset.

  • Magnetic Field Strengths

    WiTricity Corporation 14IWC 2012

    • Zone 1: Energy Transfer Region– Largest B field– No prolonged human exposure

    • Zone 2: Under Vehicle Region– B rapidly decreasing– No prolonged human exposure

    • Zone 3: Exterior Region– B < ICNIRP MPE– Unlimited human exposure

    • Zone 4: Vehicle Interior– B < ICNIRP MPE– Unlimited human exposure

  • Foreign Object Debris

    • Magnetic field in energy transfer region (between coils) is large– Maximum field depends on coil design and size– Can cause heating of some metallic objects

    • Examples of likely debris

    WiTricity Corporation 15IWC 2012

  • Detection of Foreign Object Debris

    WiTricity Corporation 16IWC 2012

    • Two Basic Approaches• Passive techniques:

    – Reduce likelihood of FOD interacting hazardously with high magnetic fields.

    – Large coils to reduce peak B field– Shaped structures

    • Active techniques:– Detect and react to the presence of FOD.– Reduce power or interupt charging– Scales to higher power 

    • WiTricity prototype FOD detection system demonstrated– http://www.youtube.com/watch?v=my5fvOh15kg

    http://www.youtube.com/watch?v=my5fvOh15kg

  • WiTricity Corporation 17IWC 2012

    Standard Capture Resonator

    Standard Source Resonator

    Rectifier

    Integrated Power Supply(Level 2)

    Standard Resonator Configuration(10-15cm or 15-20cm offset)

    (1)

    WiTricity Prototype System

  • WiTricity 3.3 kW PrototypeOn‐Vehicle Installation , June 2010

    IMS Workshop 2011 WiTricity Corporation  18

  • Electric Smart Car Demonstration

    IMS Workshop 2011 WiTricity Corporation  19

    Source Coil on Floor

    Device Coil mounted on Car

  • Wireless Charging for EV/PHEV is Coming

    IMS Workshop 2011 WiTricity Corporation  20

    • High efficiency ( > 90%)• High power rates (3.3 kW and greater)• Power transfer over several tens of cm• “Robust” to:  misalignment, weather, vehicle materials, building materials

    • Safe operation in residential, commercial, and municipal configurations

    Availability of wireless charging will increase adoption rates for EV/PHEV

  • BMW CHARGING STRATEGY.EPRI IWC, ATLANTA 2012.

    Cliff Fietzek, Manager connected e-mobility, March 26th, 2012

  • Page 2

    BMW CHARGING STRATEGY.MIGRATION INTO A GLOBAL SOLUTION.

  • Page 3

    AC1

    Phase

    Charging TimeCharging Power3,3kW 300kW

    AC1 Phase plus (USA)

    6,4kW

    AC3 Phasen (Europa/China)

    DC-HighDC-Low

    AC1 Phase plus (USA / Japan)

    19kW~6h ~4 min~3h ~1h

    43kW~30min

    100kW~15min

    35kW~35min

    J1772Combo 1

    J1772Combo 1

    BMW CHARGING STRATEGY – COMBINED CHARGING.CHARGING POWER AND CHARGING TIMES.

    EU

    USA

    WW

  • Page 4

    BMW-CHARGING STRATEGY – COMBINED CHARGING.SCENARIOS.

    AC1

    Phase

    Charging TimeCharging Power

    mls / hour

    3,3kW

    DC-High

    ~6h100kW~15min

    30kW~40min

    At Home

    Low Charging PowerAbout 6h

    Cafe/ Supermarket

    Medium Charging Power About 1h

    „Fuel Station“

    Higher Charging Power Less than 30 minabout 60 mls per15min

    AC1

    Phase

    DC-Low

    ~16mls ~133mls ~400mls

  • Page 5

    BMW CHARGING STRATEGY.REDUCTION OF COMPLEXITY.

    Do you want this?

    AC DC There will be different charging modes with different Connectors

    Solution: Combined Charging System( Combo-Charging )

    Only one receptacle in the car for AC and DC.Same PLC link for AC communication and DC control.

    For the Customer: supports all chargersEasy to handle

    For the OEM: Easy to integrate Cost effective

    Only one DC charging standard will ensure customer i f i !

    BMW Solution!

  • IMPLEMENTATION OF COMBO DC CHARGING

    2010

    Years

    -First running BMW Combo System with type 2connectorand PLC (HP GP)communication for DC charge control

    2011

    2012

    2013

    - First Combo connectors available

    - SAE Combo Standards finished

    - German local DIN Standard finished

    - Certified Combo Charger expected

    - Sample Combo Charger available

    - Combo system standardization

    - EV’s with Combo System in the market

    Page 6

  • SAE TASK FORCE TIMING: COMBINATION CONNECTOR AND COMMUNICATIONS.

    Page 7

    SAE schedule yields draft standards by mid-April; usable by Task Force members

    Yield final published standards by mid-July

    2012Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    SAE J1772UL Combo TestingTask Force TopicHybrid Committee BallotAffirmation Ballot / SAE FormattingMVC BallotPublication

    SAE PLC Test Complete (EPRI, ANL, others)SAE Task Force Topic & Survey ‐ DC Charging

    J2847/2 (DC Charging)J2931/2, 3, 4 (PLC Protocol)Tabulate topic & survey results, review with task force

    SAE Hybrid Committee Ballot ‐ DC Charging J2847/2 J2931SAE Formatting J2847/2 J2931

    Publish J2931 doc(s) Techical Information Reports (TIR)MVC Ballot ‐ DC Charging  (J2847/2 only) J2847/2

    Publish J2847/2 Recommended Practice (RP)

  • Seite 8

    COMBO PARTNERSOEMs

    Equipment Suppliers

    Connector Suppliers Communications

    http://images.search.yahoo.com/images/view;_ylt=A0PDoS7khDpPt2QAZwqJzbkF;_ylu=X3oDMTBlMTQ4cGxyBHNlYwNzcgRzbGsDaW1n?back=http://images.search.yahoo.com/search/images?p=audi&n=30&ei=utf-8&tab=organic&ri=1&w=1024&h=768&imgurl=www.thefundu.com/wp-content/uploads/2010/08/audi-logo.jpg&rurl=http://www.thefundu.com/2010/08/explore-the-world-of-audi-a-series/&size=48+KB&name=Explore+The+World+Of+Audi+A+series+|+Cars+Guide+for+Automobile+...&p=audi&oid=b1ec0241be1da5ab0b95a3d3945d0e7f&fr2=&fr=&tt=Explore+The+World+Of+Audi+A+series+|+Cars+Guide+for+Automobile+...&b=0&ni=96&no=1&tab=organic&ts=&sigr=123niomvb&sigb=12iftiumn&sigi=11pba3m0b&.crumb=VrXOhGCsuDXhttp://images.search.yahoo.com/images/view;_ylt=A0PDoS57hTpP3U0ATc.JzbkF;_ylu=X3oDMTBlMTQ4cGxyBHNlYwNzcgRzbGsDaW1n?back=http://images.search.yahoo.com/search/images?p=porsche&n=30&ei=utf-8&tab=organic&ri=73&w=1678&h=1937&imgurl=www.directsalesanddesign.com/images/porsche-logo11.jpg&rurl=http://www.directsalesanddesign.com/index.php?cPath=24&size=435.5+KB&name=PORSCHE+-+Direct+Sales+&+Design&p=porsche&oid=e55a008ebf827498ad6514502762569c&fr2=&fr=&tt=PORSCHE+-+Direct+Sales+&+Design&b=61&ni=96&no=73&tab=organic&ts=&sigr=11m3viqsq&sigb=12me031cb&sigi=11m8o2ad3&.crumb=VrXOhGCsuDXhttp://www.google.com/imgres?imgurl=http://www.fcpablog.com/storage/siemens_logo.jpg?__SQUARESPACE_CACHEVERSION=1323805778295&imgrefurl=http://www.fcpablog.com/blog/tag/siemens&usg=__iqEznn9oZSwNMqby9YChs96ce3I=&h=371&w=1024&sz=26&hl=en&start=3&zoom=1&tbnid=T4HTx6ilJfIQEM:&tbnh=54&tbnw=150&ei=Xpw6T9ufJ4mDtgeo8633Cg&prev=/search?q=Siemens&um=1&hl=en&safe=active&sa=N&rls=com.microsoft:*&tbm=isch&um=1&itbs=1http://www.google.com/imgres?imgurl=http://www.worldindustrialtech.com/files/2010/04/gk-logo.jpg&imgrefurl=http://www.worldindustrialtech.com/official-buyers-guide/gustav-klein/&usg=__G_jgbc2mhk4OJZUOvSrco70zVng=&h=119&w=368&sz=12&hl=en&start=3&zoom=1&tbnid=Yn-zQ18uU0ncWM:&tbnh=39&tbnw=122&ei=nZw6T7z_CJDqtgffybTpCg&prev=/search?q=Gustav+Klein+logo&um=1&hl=en&safe=active&sa=N&rls=com.microsoft:*&tbm=isch&um=1&itbs=1http://www.google.com/imgres?imgurl=http://www.noae.com/uploads/tx_a2csponsoren/EDAG_logo.gif&imgrefurl=http://www.noae.com/en/members.html&usg=__C37mztNPLu1Yc8q91pMUxISpVJQ=&h=60&w=169&sz=1&hl=en&start=13&zoom=1&tbnid=ukDjbmyUPZMJKM:&tbnh=35&tbnw=99&ei=s5w6T4vuDoGgtwfeiOj1Cg&prev=/search?q=EDAG+logo&um=1&hl=en&safe=active&sa=N&rls=com.microsoft:*&tbm=isch&um=1&itbs=1http://www.google.com/imgres?imgurl=http://www.greersappliance.com/images/logos/bosch.jpg&imgrefurl=http://www.greersappliance.com/brands.html&usg=__b2BV2naO12oCL4QZodekzH3phvw=&h=90&w=180&sz=5&hl=en&start=21&zoom=1&tbnid=g4Be02NIQp79hM:&tbnh=51&tbnw=101&ei=0Jw6T4q1J8-btwe5p9HfCg&prev=/search?q=Bosch+logo&um=1&hl=en&safe=active&sa=N&rls=com.microsoft:*&tbm=isch&um=1&itbs=1http://www.google.com/imgres?imgurl=http://solarbyrobko.com/yahoo_site_admin/assets/images/fronius_logo.244165249_std.jpg&imgrefurl=http://www.solarbyrobko.com/&usg=__mno5ip8La5S1FKCx5_p3LlsN5HQ=&h=80&w=190&sz=8&hl=en&start=5&zoom=1&tbnid=-y6LbIKE72McpM:&tbnh=43&tbnw=103&ei=-5w6T6yRIc6CtgfV3-nlCg&prev=/search?q=Fronius+logo&um=1&hl=en&safe=active&sa=N&rls=com.microsoft:*&tbm=isch&um=1&itbs=1http://www.google.com/imgres?imgurl=http://www.aero-news.net/images/content/general/2011/aerovironment-logo-1011A.jpg&imgrefurl=http://www.aero-news.net/index.cfm?do=main.textpost&id=dd10ba11-ac6e-44c1-8f66-d500f6f63695&usg=__KWh3_e8o-s-Wp-XcJehiQeNZYmA=&h=323&w=400&sz=8&hl=en&start=3&zoom=1&tbnid=o-8zj31DlDt4GM:&tbnh=100&tbnw=124&ei=VZ06T-eMDIOutwfOqszZCg&prev=/search?q=AeroVironment+logo&um=1&hl=en&safe=active&sa=N&rls=com.microsoft:*&tbm=isch&um=1&itbs=1http://www.google.com/imgres?imgurl=http://www.schneider-electric.at/images/pictures/press-releases/2009_logo-schneider-electric.jpg&imgrefurl=http://www.schneider-electric.at/sites/austria/de/unternehmen/news/pressefotos-allgemein.page&usg=__sirkwaQ07hpdg81uGXqu92Ov4C8=&h=872&w=2953&sz=453&hl=en&start=4&zoom=1&tbnid=ObQopzkHcFFZRM:&tbnh=44&tbnw=150&ei=i506T8maBsm4twfh4-TtCg&prev=/search?q=Schneider+electric+logo&um=1&hl=en&safe=active&sa=N&rls=com.microsoft:*&tbm=isch&um=1&itbs=1

  • Cliff Fietzek, Manager connected e-mobility, March 26th, 2012

    THANK YOU FOR YOUR ATTENTION.

  • Arindam MaitraIWC Meeting

    March 28, 2012

    EPRI’s Utility Direct DC Fast Charger –Development, Testing, Demonstration

  • 2© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Utility Direct “Medium Voltage” Fast Charger

    • Conventional DC Fast Charger needs a new three-phase service

    – Three-phase transformer– Three primary conductors and

    associated medium voltage fuses– Three high-current service conductors– 208/480 Vac DC fast charger– Overall efficiency (w xfmr) ~88-91%– Installation costs

    • Utility Direct Fast Charger

    – Combines service transformer and DC fast charger into one unit

    – Needs only one primary conductor, no isolation transformer and no secondary conductors

    – Overall efficiency >95%– Installation costs

  • 3© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Configuration of Utility Direct Fast Charger

    M-level AFEAC-DC &Isolated DC-DC

    DC-DC

    Charger400-V

    DC

    2.4 or8 kV AC +

    • HV components are enclosed within thepad-mounted enclosure

    • AC input can be interrupted with high-voltage vacuum switch

    • DC voltage can be interrupted with a DCcircuit breaker

    • Charger output is Chademo compatible

  • 4© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Pad-Mount Case for Medium-Voltage AFE Converter and Isolated DC-DC Stage (Box-A)

    Photograph of the case and internal circuits

  • 5© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Utility Direct Fast Charger with CHAdeMOInterface

    DSP

    board

    Medium

    Voltage

    DC-DC

    Charger

    Vehicle

    Side

    Battery

    Management

    System

    Interface

    PC Display

    Control

    Console

    1,7

    2

    4

    GNDd1

    d2

    RDY

    8

    9

    10

    CAN+CAN–

    5

    6

    PWR+

    PWR–

    IrefVref

    CMD

    2.4kV

    rms

  • 6© 2012 Electric Power Research Institute, Inc. All rights reserved.

    2.4KV 50kW Medium Voltage IUT Based DC Charger –Efficiency Comparisons

  • 7© 2012 Electric Power Research Institute, Inc. All rights reserved.

    EPRI Web/Mobile Application

    CAN Listener

    EPRI Server

    Charger

    Android Tablet

    • Provides user interface to the charger

    • Sends DC charging data to the EPRI Server

    Bluetooth

    Instrumentation

    2.4 kV AC

    500 VDC

    CAN Bus

    AC Charging Data

    DC Charging

    Data

  • 8© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Demo in Knoxville @March 6-7, 2012

    • Medium Voltage IUT DC Fast Charger

    – Fully functional 1-phase 2.4KV 45KVA IUT DC Fast charger (FC) system with the CHAdeMOcommunication protocols (CAN)

    • Why is it valuable?– Utility owned asset for fast charging– Provide customers with a variety of

    products and services that go “beyond the meter”

    – Reduced energy losses versus conventional chargers

    – Reduced weight versus fast chargers using conventional transformers

  • 9© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Installation Options

    • Conventional FC installation

    – Option 1: Underground installation (pad-mount)

    – Option 2: Overhead installation (pole-mount)

    • Medium Voltage FC installation (pad-mount)

    The objective is to compare cost of installing a 480 Vac fast charger vs an EPRI MV fast charger

  • 10© 2012 Electric Power Research Institute, Inc. All rights reserved.

    480 Vac Fast Charger vs MV Fast Charger Installations

    480 Vac Fast Charger Installation – Option 1 480 Vac Fast Charger Installation – Option 2

    Medium Voltage Fast Charger Installation

  • 11© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Key Installation Components

    480 Vac FC (Option 1) 480 Vac FC (Option 2) EPRI MVDC FC3 long primaries (135 ft) 3 short primaries (5 ft) 1 long primary (135ft)1 three-phase 75 kVA pad-mount xfmr (13.8 kV/480 Vac)

    3 single-phase 25 kVA pole-mount xfmrs(7.32kv/277 Vac)

    -

    Excavation, foundation, concrete pad, MV terminations

    - -

    4 underground service conductors (10ft) + 2underground DC service conductors (10 ft)

    4 overhead service conductors (110 ft) + 2underground DC service conductors (10 ft)

    2 underground DC service conductors (10 ft)

    Trenching, conduits Some trenching, conduits Trenching, conduits

    480 Vac service panel+ Secondary side metering

    480 Vac service panel+ Secondary side metering

    Primary side metering

  • 12© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Installation Cost

    480 Vac FC (Option 1)

    480 Vac FC (Option 2)

    EPRI MVDC FC

    Primaries $3937 $261 $1399

    Transformer(s) $14776 $3638

    Service conductor $752 $2284 $378

    Service Panel $350 $350

    Metering $365 $365 $1500

    Foundation Cost for FC Main Box $3272 $3272 $3272

    Total Cost $23452 $10170 $6549

    * Approximate costs – these do not include unit price of the fast charger

  • 13© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Where this Technology Makes Sense

    • Utilities who want to provide fast charging capability directly from their distribution system. This could be especially useful in dense cities where you place fast chargers that aren't hosted by a business

    • Businesses could install Intelligent Universal Transformer (IUT) technology, as their building transformer and conveniently add fast charging service (and also integrate their onsite solar, energy storage, and building energy management system). This would help in managing the high peak loads of the DC charger and the impact both on the utility and to a business' own cost of service, specifically by reducing demand charges

    • DC fast charging technology has the potential to significantly increase the range and versatility of battery electric vehicles, enhancing their commercial appeal

  • 14© 2012 Electric Power Research Institute, Inc. All rights reserved.

    TVA iMieV CHARGING (Charging Event #1)March 6th, 2012

  • 15© 2012 Electric Power Research Institute, Inc. All rights reserved.

  • 16© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Charging Power as a Function of Time – iMieV

    Time (minute)

    Cha

    rgin

    g P

    ower

    (kW

    )

  • 17© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Battery Capacitor and State-of-Charge – iMieV

    Time (minute)

    Bat

    tery

    Cap

    acity

    (kW

    h)

    Sta

    te o

    f Cha

    rge SOC

  • 18© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Voltage and Current During Charging – iMieV

    Time (minute)

    Bat

    tery

    Vol

    tage

    (V)

    Cha

    rgin

    g cu

    rrent

    (A)

  • 19© 2012 Electric Power Research Institute, Inc. All rights reserved.

    EPRI LEAF CHARGING – Charging Event #2 March 6th, 2012

  • 20© 2012 Electric Power Research Institute, Inc. All rights reserved.

  • 21© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Charging Power as a Function of Time – Leaf

    Time (minute)

    Cha

    rgin

    g P

    ower

    (kW

    )

  • 22© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Battery Capacitor and State-of-Charge – Leaf

    Time (minute)

    Bat

    tery

    Cap

    acity

    (kW

    h)

    Sta

    te o

    f Cha

    rge

  • 23© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Voltage and Current During Charing – Leaf

    Time (minute)

    Bat

    tery

    Vol

    tage

    (V)

    Cha

    rgin

    g cu

    rrent

    (A)

  • 24© 2012 Electric Power Research Institute, Inc. All rights reserved.

    EPRI LEAF CHARGING – Charging Event #3 March 6th, 2012

  • 25© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Charging Power as a Function of Time – Leaf

    Time (minute)

    Cha

    rgin

    g P

    ower

    (kW

    )

  • 26© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Battery Capacitor and State-of-Charge – Leaf

    Time (minute)

    Bat

    tery

    Cap

    acity

    (kW

    h)

    Sta

    te o

    f Cha

    rge SOC

    kWh

  • 27© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Voltage and Current During Charing – LeafB

    atte

    ry V

    olta

    ge (V

    )C

    harg

    ing

    curre

    nt (A

    )

    Time (minute)

  • 28© 2012 Electric Power Research Institute, Inc. All rights reserved.

    EPRI LEAF CHARGING – Charging Event #4

    March 7th, 2012

  • 29© 2012 Electric Power Research Institute, Inc. All rights reserved.

  • 30© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Charging Power as a Function of Time – EPRI Leaf

    Time (minute)

    Cha

    rgin

    g P

    ower

    (kW

    )

  • 31© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Battery Capacitor and State-of-Charge – EPRI Leaf

    Time (minute)

    Bat

    tery

    Cap

    acity

    (kW

    h)

    Sta

    te o

    f Cha

    rge SOC

    kWh

  • 32© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Voltage and Current During Charging – EPRI Leaf

    Bat

    tery

    Vol

    tage

    (V)

    Cha

    rgin

    g cu

    rrent

    (A)

    Time (minute)

  • 33© 2012 Electric Power Research Institute, Inc. All rights reserved.

    LEAF CHARGING – Charging Event #5 March 7th, 2012

  • 34© 2012 Electric Power Research Institute, Inc. All rights reserved.

  • 35© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Charging Power as a Function of Time – TVA Leaf

    Time (minute)

    Bat

    tery

    Cap

    acity

    (kW

    h)

    Sta

    te o

    f Cha

    rge

    SOC

    kWh

  • 36© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Charging Power as a Function of Time – TVA Leaf

    Time (minute)

    Cha

    rgin

    g P

    ower

    (kW

    )

  • 37© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Voltage and Current During Charging - TVAB

    atte

    ry V

    olta

    ge (V

    )C

    harg

    ing

    curre

    nt (A

    )

    Time (minute)

  • 38© 2012 Electric Power Research Institute, Inc. All rights reserved.

    Together…Shaping the Future of Electricity

  • Infrastructure Overview

    Joseph ThompsonPrincipal Engineer Zero Emission Technology PlanningNissan Technical Center North America

  • DC Fast Charge

    Level 1 & 2

    Nissan LEAF Charge Ports

  • Type Power SupplyCharger

    Power

    Charging

    Level

    Charger

    Location

    Charging

    Time

    (24kwh

    Battery)

    Normal

    120VAC

    Single

    Phase

    12A 1.4kW Level 1

    On-board

    18h

    240VAC

    Single

    Phase

    15A 3.3kW

    Level 2

    8h

    30A 6.6kW 4h

    Fast480VDC

    3-phase50kW Level 3

    Off-

    board30min

    Nissan Confidential

    Charging Levels

  • Charging time and mileage

    USA

    Charging LevelMileage and Charging time

    2hr 4hr 6hr 8hr

    Level 2

    (240 volts, 16amps)+25mile +50mile +75mile +100mile

    Level 1

    (120 volts, 12amps)+10mile +20mile +30mile +40mile

    • DC Quick charging: 80% in about 30 min

  • HOME CHARGING

    WORKPLACE CHARGING

    PUBLIC

    Majority of Charging

    • Owners with single family homes will charge overnight at off-peak rates

    • Business fleets charge overnight at their “home” location

    Supports EV Ownership

    • Provides charging for those without dedicated home charging

    • Extends daily travel range

    Allows for Mass Adoption

    • Relieves “range anxiety”

    • Level 2 and Fast charging capability

    Charging Pyramid

  • • A level 1 cordset is included with each vehicle (located in the trunk)

    • 1.4kw, 12.5 amps

    Level 1 trickle charge

  • • Goal– Simple, one-stop shop for the

    consumer have charging equipment installed at home

    • AeroVironment selected as Nissan’s preferred vendor for residential charging equipment– Includes all US markets

    • AeroVironment provides– The charging dock

    – Manages permitting + installations

    – Trains contractor network

    Level 2 Residential

  • SAFETY DESIGN•Automatic short circuit shut off

    •Automatic ground fault shut-off

    •Protection against live power in event of cable breakaway

    •UL listed

    •Outdoor rated to withstand weather conditions

    •Surge protection

    •15’ or 25’ cord, no-cost option

    DEPENDABILITY•Technology based on more than 20 years of EV charging

    •Americans with Disabilities Act (ADA) compliant

    •Standard 3-year warranty

    SERVICE•Nationwide network of certified electrician installers

    •Rapid response time for warranty service and support

    AeroVironment Equipment

  • • Allocating 5,700 Nissan LEAF vehicles to project participants in 5 states

    • Integrating the Nissan LEAF retail sales process with Ecotality to ensure a seamless customer experience

    • Providing data from the LEAF telematics system to support the Ecotality / Dept. of Energy infrastructure usage study

    • Installing a DC Fast Charge Port on each project vehicle

    • Providing Nissan LEAF handraiser and reservation data to assist with the infrastructure planning phase of the project

    Nissan’s Role in The EV Project

  • Strong competition in the market

    • AeroVironment

    • ECOtality

    • Coulomb

    • Clipper Creek

    • SemaConnect

    • Go Smart

    • Leviton

    • Shore Power

    • Better Place

    • General Electric

    • Schneider Electric

    • EV Charge America

    • Juice Bar

    • Eaton

    Level 2 Public Charging

  • Program Total Amount MarketsLevel 2

    PublicDC Fast

    EV Project (Ecotality) [DOE] $230.0M AZ, CA, OR, TN, TX, WA 5,600 340

    ChargePoint America (Coulomb) [DOE]

    $37.0MCA, DC, FL, TX, MI, NY, WA

    2,600 0

    Bay Area AQMD$5M CA 0 30

    California AB 118 [CEC] $3.6M CA 635 0

    Hawaii (State Grant) $3.0M HI 450 0

    City of Chicago $1.9M IL 207 73

    Total + $280 M 26 States 12K+ 600+

    Sample of Large Infrastructure Projects

  • 12

    More than 13,000 EV Charge Stations on the way by the end of 2012…

    Public (Planned) Infrastructure

  • 13

    • Charging/Climate Control

    • Charge Status

    • Plug-in reminder

    • Access by internet and web-enabled phone

    Remote vehicle access

    Telematics and Station Mapping

    Automatic charging spot

    updates

    NEW charging spots

    LEAF is equipped with Telematics control unit that transmits and receives data that will allow for unprecedented conveniences.

    Data Center

  • 208-

    240V

    Supply

    Panel &

    Circuit Breaker

    Utility Meter

    Ground

    • Level 2 EVSE – 40amp dedicated circuit

    • Run conduit and wiring to EVSE box location (Garage,

    Carport, etc)

    • Mount and hardwire the EVSE box

    Conduit & Wire

    Wall-

    mounted

    EVSE

    Breaker / Panel

    Upgrades

    Installation &

    Materials CostEVSE

    Typical Installation

    Costs:

    Residential Installation

    Electrical Box

    Permit

    $50 - $700 $200 - $700 $800 $1k - $2.5k$50-$200

    TOTAL

  • 208-

    240V

    Supply

    Panel &

    Circuit Breaker

    Utility Meter

    Ground

    • Level 2 EVSE – 40amp dedicated circuit

    • Installation costs can vary greatly depending on:

    • Existing electrical service capacity and

    location

    • Distance from electrical panel to EVSE

    • Trenching required in some installations

    Conduit & Wire

    Pedestal

    mounted

    EVSE

    Breaker / Panel

    UpgradesInstallation &

    Materials Cost

    Commercial Grade EVSE

    Typical Installation

    Costs:

    Commercial Installation

    Electrical Box

    Permit

    $50 - $700 $2000 - $7000 $1k-$3k $3k - $11k$100-$300

    TOTAL

  • DC Fast Charging

  • UL Certifications Directory

    http://database.ul.com/cgi-

    bin/XYV/cgifind.new/LISEXT/1FRAME/srchres.html?collection=/data3/verity_collectio

    ns/lisext&vdkhome=/data3/verity_sw_rev24/common&SORT_BY=textlines:asc,ccnsh

    orttitle:asc&query=FFTGCCN+and+not+GUIDEINFO

  • Planned DC Quick Charge Stations

    ProjectPlanned DC QC

    Region Funding Notes

    Blink Network

    EV Project 340

    CA – San Diego, Bay Area

    WA - Seattle

    OR - Portland

    AZ- Phoenix/Tucson

    TN – Nash/Knox/Chatta

    $230M (DOE – ARRA funded)

    Installations begin summer

    2011

    eVgo Network

    NRG Energy100

    Houston, TX

    Dallas, TXPrivately funded 50 in each city

    350 Green 110 Various US Cities State grantsAlso developing private-sector

    partners

    State of Maryland

    3 Baltimore, MD State

    Various Projects

    5

    Portland –PGE

    North Carolina - Duke Uni

    South Carolina – Plug in Carolina

    Private/StateCurrently operating

  • Installed DC QC StationsCHAdeMO, publically accessibleAs of December 1, 2011

    Number of Stations: 27

  • eVgo Freedom Station

  • DFW: 1 operational; 3 under construction; 13 in permitting

    https://www.evgonetwork.com/eVgo_Charging_Stations/

  • HOU: 8 operational; 4 under construction; 3 in permitting

    https://www.evgonetwork.com/eVgo_Charging_Stations/

  • • Some hosts do not have 480V 3P electrical service

    • For hosts who do have 480V 3P service, they usually do not have 50KW+ extra panel capacity to support the DC charger.

    • The hosts increasingly have underground service that is difficult or impossible to expand.

    • This pushes the installation street-side to access the utility service directly with a new service drop

    • Street-side installations have permitting challenges on equipment heights and setbacks

    • This results in the installation being mid-parking lot with lots of boring and retail disruption

    • Parking space code requirements often add an addition dedicated parking space

    • In some parts of the country, these new service drops can take 6 months

    • If we are lucky, the utility feeder is over-head and may only require a pole set

    • If we are not lucky, the utility feeder is underground requiring an expense pad mount transformer

    • The monthly demand charges run $300-700/mo plus another $50-200/mo meter charge

    Challenges to Installation

  • Governor Brown Announces $120 Million Settlement to Fund Electric Car Charging Stations Across California

    • NRG will be developing the following in CA:

    • 200 Public DC Fast Charging stations

    • Wiring for “10,000 plug-in units at 1,000 locations across the state”

    • Installations of DC Fast Charging will be in the following locations: San Francisco Bay Area; San Joaquin Valley, the Los Angeles Basin, and San Diego County

    • The NRG press release state this will occur over “the next 4 years.”

  • Governor Brown Announces $120 Million Settlement to Fund Electric Car Charging Stations Across California

    • The Executive Order issued today by the Governor sets the following targets:

    • By 2015, all major cities in California will have adequate infrastructure and be “zero-emission vehicle ready”;

    • By 2020, the state will have established adequate infrastructure to support 1 million zero-emission vehicles in California;

    • By 2025, there will be 1.5 million zero-emission vehicles on the road in California; and

  • Governor Brown Announces $120 Million Settlement to Fund Electric Car Charging Stations Across California

    By 2050, virtually all personal transportation in the State will be based on zero-emission vehicles, and greenhouse gas emissions from the transportation sector will be reduced by 80 percent below 1990 levels.

    • AB 32, the 2006 Global Warming Solutions Act, calls for a 30 percent reduction of greenhouse gas emissions by 2020. The goal of 80 percent below 1990 levels by 2050 was set by an executive order signed by former Governor Arnold Schwarzenegger.

    • Last year, Governor Brown signed SB X1-2, which directed the California Air Resources Board to adopt regulations setting a 33 percent renewable energy target.

  • 440-

    480V

    Supply

    (3

    phase)Panel and

    Circuit

    Breaker

    Utility Meter

    Ground

    • DC Quick Charge

    • Installation costs can vary greatly depending on:

    • May require separate electrical service

    • May require transfomer upgrades or additional

    work

    Conduit & Wire

    DC Quick

    Charge

    Unit

    Breaker / Panel

    UpgradesInstallation &

    Materials Cost

    Commercial Grade EVSE

    Typical Installation

    Costs:

    DC Quick Charge Installation

    Electrical Box

    Permit

    $2,000 $10,000 - $30,000 $15k-$50k $28k - $83k$1,000

    TOTAL

  • NEC CP-12 Update for EPRI-IWC

    March 2012 Gery Kissel

    NEC CP-12 EV Task Group Lead

  • Report On Proposal (ROP) Meeting

    ROP meeting held January 18-21

    Article 625 had 30 proposals ◦ Including the restructure proposal from the EV Task Group

    CP-12 vote summary: ◦ 15 – Reject

    ◦ 14 – Accept In Principle

    Accepting the Proposal in principle but with Code Panel changes in the proposed wording

    ◦ 1 - Accept

  • Report On Proposal (ROP) Meeting

    SAE Proposal 12-59 Rejected ◦ Proposed length extension of AC cord from 1 foot to 6 foot before Personal Protection System (PPS)

    Remove mass of control box from AC receptacle / plug system

  • Upcoming NEC Activity

    Technical Correlating Committee (TCC) Meeting ◦ They make sure that changes proposed by one

    committee correlates with other committee’s text and proposals.

    ◦ TCC meeting April 23-27

    ROP Publication ◦ June 15, 2012

    Comments on ROP close October 27 Report on Comments (ROC) meeting

    November 28 – December 8 2014 code published September 2013

  • PEV/EVSE Communication SAE Task Force Status

    IWC Meeting

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status1

  • Outline

    • Background

    • PLC Status

    • Additional Document Status

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status2

  • BackgroundMajor Documents and Functions

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status3

    1. J2836™ - Use Cases (establishes requirements)

    ISO/IEC 15118-1

    2. J2847 – Messages, diagrams, etc. (derived from

    the use case requirements)

    ISO/IEC 15118-2

    3. J2931 – Communication Requirements

    ISO/IEC 15118-3

    4. J2953 – Interoperability

    ISO/IEC 15118-4

  • 3/28/2012Rich Scholer - SAE Communication Task

    Force Status4

    Summation of SAE Communication StandardsJ2836™ – General info (use cases)

    Dash 1 – Utility programs *

    Dash 2 – Off-board charger communications*

    Dash 3 – Reverse Energy Flow

    Dash 4 – Diagnostics

    Dash 5 – Customer to PEV and HAN/NAN

    Dash 6 – Wireless charging/discharging

    J2953– Interoperability

    Dash 1 – General Requirements

    Dash 2 – Testing and Cert

    Dash 3 –

    • * Published

    J2847– Detailed info (messages)

    Dash 1 – Utility programs *

    Dash 2 – Off-board charger communications *

    Dash 3 – Reverse Energy Flow

    Dash 4 – Diagnostics

    Dash 5 – Customer to PEV and HAN/NAN

    Dash 6 – Wireless charging/discharging

    J2931– Protocol (Requirements)

    Dash 1 – General Requirements*

    Dash 2 – InBand Signaling (control Pilot)

    Dash 3 – NB OFDM PLC over pilot or mains

    Dash 4 – BB OFDM PLC over pilot or mains

    Dash 5 – Telematics

    Dash 6 – DSRC/RFID (wireless charging)

    Dash 7 - Security

  • 3/28/2012Rich Scholer - SAE Communication Task

    Force Status5

    J2931/7 Security

    J2953/1 Interoperability, J2953/2 Test Procedures

    Document Interaction

    Utility Programs

    DC Charging

    Reverse Power

    Flow

    Diagnostics

    Customer to

    PEV and

    HAN/NAN

    Wireless Power

    Flow

    Use Cases Requirements Protocol

    BB OFDM (PLC)

    Telematics

    DSRC

    (& RFID)

    Basis

    J2836/1™ J2847/1

    J2931/1J2836/2™ J2847/2

    J2836/3™ J2847/3

    J2836/4™ J2847/4

    J2931/4

    J2836/5™ J2847/5 J2931/5

    J2836/6™ J2847/6 J2931/6

  • PLC Development steps

    1. Establish Requirements (publish J2931/1)2. PLC System Diagram (make a picture)3. Generate Test Plan and Lab Setup (EPRI & ANL)4. Review Test Report results (SAE Meeting)5. Establish Timeline

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status6

  • 3/28/2012Rich Scholer - SAE Communication Task

    Force Status7

    System Architecture (Utility Messages)

    EVSE

    Com modulePEV

    Com modulePLC

    ESI

    PLC

    EUMD

    CANZigBee

    SEP 1.x to SEP 2.0 Migration Unit

    (if needed) ESI Dependent

    SEP 2.0 SEP 1.x or 2.0

    J1772™

    Control

    Pilot

    SEP 1.x to

    SEP 2.0

    ZigBee

    PLC ZigBee

    • Fundamental case

    – Highest expected usage

  • 3/28/2012Rich Scholer - SAE Communication Task

    Force Status8

    Actual Lab Set-up (ANL)

  • PLC Test Status• March 21-22, 2012 Task Force Meeting

    – During this meeting, each of the requirements identified in J2931/1 were voted on for a Pass, Fail or Unknown/Untested position from both attendees and WebEx participants.

    – We agreed to move forward with HP GP as the single PLC technology for DC Charging and Utility messages between the PEV and EVSE.

    – A decision was also taken to discontinue any testing of other technologies (G3, FSK).

    – We are continuing to coordinate effort with the ISO/IEC Project Team 4 testing

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status9

  • PLC Test Status (cont)Two requirements need additional testing.

    • RelComm4 is the effect of consumer network on PEV network, and this showed conflicting results between EPRI and ANL. – We identified differences as updated firmware of PL16 modules, and

    corset type.

    – The action item was taken for ANL to retest with the EPRI boards, use the coupling cap variation along with a common cordset.

    • DCComm.6, the shared network requirement, is the combined effect of both Utility and DC charging messages with the effects of the consumer network. – This solution requires Qualcomm to provide new firmware fixes so that

    this requirement can be successfully met. It was decided that the testing will be carried out within two-three weeks at ANL and EPRI.

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status10

  • Timeline

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status11

    Jan Feb Mar Apr May Jun Jul Aug

    SAE PLC Test (EPRI, ANL, PNNL)

    SAE Task Force Topic - DC Charging

    J2847/2 (DC Charging)

    J2931/1 (Stack info)

    J2931/4 (PLC Protocol)

    SAE Hybrid Committee Ballot - DC Charging

    J2847/2 (DC Charging) J2847/2

    J2931/1, 4 J2931

    SAE Formatting

    J2847/2 (DC Charging) J2847/2

    J2931/1, 4 J2931

    Publish J2931 doc(s) Techical Information Reports (TIR)

    MVC Ballot - DC Charging (J2847/2 only) J2847/2

    Publish J2847/2 Recommended Practice (RP)

    2012

  • Additional Document Status

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status12

  • Document StatusUtility & DC Charging

    • Reopened J2847/1 – Utility messages

    – Dan Mepham is adding SEP2 info

    • Reopened J2847/2 – DC Charging

    – Doug Oliver is adding messages to harmonize with IEC

    – Moving sequence diagrams into J1772™

    • Reopened J2931/1 – Protocol Requirements

    – Slav Berezin is adding Communication Stack sections

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status13

  • Document Status (cont)• J2836/3™ – PEV as Distributed Energy Resource

    (DER) (formerly known as Reverse Power Flow)

    – Hank McGlynn – developing use cases for PEV communicating as a DER device

    – Grid connected operation as a DER (V2G)• PEV connects through EVSE to a live grid (which can be

    islanded) – current source

    • On-board or eternal inverter (J2847/2 to be updated to allow for reverse DC flow into external inverter)

    • Inverter must fully comply with IEEE 1547 - exceptions to be deferred until next version (e.g. IEEE 1547.4 microgrids and IEEE 1547.8)

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status14

  • J2836/3™ (cont)

    – Off-grid operation of PEV as a power (voltage) source (V2L, V2H, and V2V)

    • On-board inverter sets and regulates voltage and frequency for loads

    • Loads plug into a vehicle power panel with NEMA outlets (not via EVSE)

    • For V2H the connection to the home must be through a UL1008 transfer switch

    • High level communication not required for PEV as sole source of off-grid power (defer load sharing with other power sources until next version)

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status15

  • Document Status (cont)• J2847/3 will follow J2836/3™ effort and use the

    J2847/1 SEP2-based approach• SEP2 provides basic DER functionality

    • SEP2 will need to be updated for IEEE 1547.8 advanced DER modes

    • J2836/4™ - Diagnostics - J2847/4 to follow– Mike Muller is preparing for EVSE standard functions

    and diagnostics.

    • J2836/5™ - Telematics – J2847/5 to follow– Venkatesh Donthy is collecting HAN/NAN use cases for

    customer to HAN interactions

    – Consumer and Utility Network expanded cases and synchronizations

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status16

  • Wireless Charging – Use Cases

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status17

    • J2836/6™ - Wireless Charging - Mark Klerer – Coordinating the completion of use cases with the

    requirements from J2954 (EVSE and alignment)

    – Created second draft with input from J2954 members• Covers Use Cases

    – Wireless EV Charger (WEVC) Discovery

    – Vehicle Alignment

    – Charging Control: Initiation, Power Transfer, Termination

    – Monitoring and Diagnostics

    • Emergency Shutdown

    – Where possible reuse concepts and procedures from conductive charging applications

  • 3/28/2012Rich Scholer - SAE Communication Task

    Force Status18

    Wireless Charging Use Case Diagram

  • 3/28/2012Rich Scholer - SAE Communication Task

    Force Status19

    J2847/6 & J2931/6

    • J2847/6 Messages for Wireless Charging– Draft to be created to meet requirements from Use

    Cases in J2836/6: First Draft expected begining May

    • J2931/6 Communications Protocol– DSRC to be used as protocol between Base Unit and

    Vehicle Unit (EVSE) to be worked in cooperation with J2735 (First Draft end of April)

    – RFID to be used to assist in vehicle alignment. Configuration to be defined by J2954. (Expected by end of May)

  • Interoperability and Security

    • J2953/1– Cliff Fietzek restarted monthly meetings

    • J2931/7– Hina Chaudhry is coordinating input from SGIP

    CSWG and others• Incorporating NIST 7628 guidelines to map out different

    domains and defining corresponding threats and risks

    • Future focus will be on different security policies and controls recommendation to mitigate the threats thus identified

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status20

  • The End

    Questions?

    3/28/2012Rich Scholer - SAE Communication Task

    Force Status21

  • SAE J1772™ Update

    for EPRI-IWC

    March 2012

    Gery Kissel

    SAE J1772™ Task Force Lead

  • Contents

    SAE J1772™ Revision 4 Status

    SAE J1772™ Revision 5 Plan

    DC Coupler UL2251 Testing

    DC Coupler Design Status

    SAE J1772™ DC Development

    Team

  • SAE J1772™ Revision 4 Status

    Revision 4 published 2/21 includes:

    ◦ Normative

    Editorial corrections

    Technical corrections

    EVSE compatibility test (new Appendix)

    ◦ Informative

    Charging configurations and ratings definitions

    Illustration of Combo coupler

    Reference to PLC communications for DC charge

    control

  • SAE J1772™ Revision 5 Plan

    Revision 5 will re-integrate DC charging

    ◦ Coupler dimensional information

    ◦ EVSE DC output interface definitions

    ◦ System sequence diagrams and data messages

    ◦ Additional requirements for DC charging

    Revision 5 will be formatted into 3 main sections:

    ◦ General requirements for AC and DC charging

    ◦ Specific requirements for AC charging

    ◦ Specific requirements for DC charging

  • SAE J1772™ Revision 5 Plan

    PLC related information will located in the

    appropriate 2836/X, 2847/X and 2931/x

    documents

    As in Revision 4, additional clarifications and

    corrections will be made as time warrants

  • SAE J1772™ Revision 5 Plan SAE Charging Configurations and Ratings Terminology

    AC level 1(SAE J1772™)

    PEV includes on-board charger120V, 1.4 kW @ 12 amp120V, 1.9 kW @ 16 ampEst. charge time:PHEV: 7hrs (SOC* - 0% to full)BEV: 17hrs (SOC – 20% to full)

    *DC Level 1

    EVSE includes an off-board charger200-500 V DC, up to 40 kW (80 A)Est. charge time (20 kW off-board charger):

    PHEV: 22 min. (SOC* -0% to 80%)BEV: 1.2 hrs. (SOC – 20% to 100%)

    AC level 2(SAE J1772™)

    PEV includes on-board charger (see below for different types)240 V, up to 19.2 kW (80 A)Est. charge time for 3.3 kW on-board charger

    PEV: 3 hrs (SOC* - 0% to full)BEV: 7 hrs (SOC – 20% to full)

    Est. charge time for 7 kW on-board chargerPEV: 1.5 hrs (SOC* - 0% to full)BEV: 3.5 hrs (SOC – 20% to full)

    Est. charge time for 20 kW on-board chargerPEV: 22 min. (SOC* - 0% to full)BEV: 1.2 hrs (SOC – 20% to full)

    *DC Level 2

    EVSE includes an off-board charger200-500 V DC, up to 100 kW (200 A)Est. charge time (45 kW off-board charger):

    PHEV: 10 min. (SOC* -0% to 80%)BEV: 20 min. (SOC – 20% to 80%)

    *In developmentVoltages are nominal configuration voltages, not coupler ratingsRated Power is at nominal configuration operating voltage and coupler rated currentIdeal charge times assume 90% efficient chargers, 150W to 12V loads and no balancing of Traction Battery Pack

    Notes: 1) BEV (25 kWh usable pack size) charging always starts at 20% SOC, faster than a 1C rate (total capacity charged in one hour) will also stop at 80% SOC instead of 100%2) PHEV can start from 0% SOC since the hybrid mode is available. ver. 082911

  • SAE J1772™ Revision 5 Plan

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    SAE J1772

    UL Combo Testing

    Task Force Topic

    Hybrid Committee Ballot

    Affirmation Ballot / SAE Formatting

    MVC Ballot

    Publication

    SAE PLC Test Complete (EPRI, ANL, others)

    SAE Task Force Topic & Survey - DC Charging

    J2847/2 (DC Charging)

    J2931/2, 3, 4 (PLC Protocol)

    Tabulate topic & survey results, review with task force

    SAE Hybrid Committee Ballot - DC Charging J2847/2 J2931

    SAE Formatting J2847/2 J2931

    Publish J2931 doc(s) Techical Information Reports (TIR)

    MVC Ballot - DC Charging (J2847/2 only) J2847/2

    Publish J2847/2 Recommended Practice (RP)

    DIN 70121 DC Charging Communications

    Submitted

    Expected Approval / Publication

    2012

    Topic Posted

    3/20

  • DC Coupler UL2251 Testing

    DC coupler will be tested to UL 2251 - Plugs,

    Receptacles and Couplers for Electric Vehicles

    ◦ Testing to begin soon and be completed prior to J1772 Hybrid Committee ballot closure

    Testing will be limited to only those tests

    applicable to the interface specified in J1772

    ◦ For example, tests related to material properties will not be ran as these are manufacture specific

    and not specified in J1772

  • DC Coupler Design Status

    SAE is coordinating efforts to tool DC

    charge couplers

    REMA and Korea Electric Terminal (KET)

    are the suppliers involved in the effort

    ◦ REMA

    Began shipping couplers week of 2/6

    ◦ KET

    Have shipped parts since 12/11

    Have temporally stopped shipping to correct

    durability issue of the Proximity terminal in plug

    Expect shipping to resume mid April

  • DC Coupler Design Status

    Design revision needed to meet UL finger proof test

    Design complies to IEC finger proof test

    UL finger proof compliant parts available early/mid March (REMA)

  • DC Coupler Design Status

    Contacts for parts:

    Tim Rose, REMA – [email protected]

    Seungwoo Lee, KET - [email protected]

    mailto:[email protected]

  • SAE J1772™ DC Development

    Team

    OEMsEquipment Suppliers

    Connector Suppliers Communications

    D2_PEV_D2-2B_MacCurdy.pdfD2_PEV_D2-2C_Bishop.pdfD2_PEV_D2-2D_Berezin.pdfD2_PEV_D2-2E_Packard.pdfD2_PEV_D2-3_Kesler.pdfD2_PEV_D2-4_Fitzek.pdfD2_PEV_D2-5_Maitra.pdfD2_PEV_D2-6_Thompson.pdfD2_PEV_D2-7_Kissel_on_NEC.pdfD2_PEV_D2-9_Scholer.pdfD2_PEV_D2-10_Kissel_on_SAE.pdf