conditions of contract - 19.11.2011

Upload: sujani-maarasinghe

Post on 14-Apr-2018

233 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Conditions of Contract - 19.11.2011

    1/28

  • 7/27/2019 Conditions of Contract - 19.11.2011

    2/28

    Types of Standard Conditions of

    Contract FIDIC (Fdration Internationale Des Ingnieurs-

    Conseils)

    JCT (Joint Contracts Tribunal) NEC (New Engineering Contracts)

    ICE (Institution of Civil Engineers )

    ACA (Association of Consultant Architects)

    Local

    SBD (Standard Bidding Document)

  • 7/27/2019 Conditions of Contract - 19.11.2011

    3/28

    New tendency in contracts worldwide

  • 7/27/2019 Conditions of Contract - 19.11.2011

    4/28

    FIDIC stands for the Fdration Internationale des Ingnieurs-

    Conseils and is the French acronym for the international

    federation of national associations of independent consulting

    engineers. FIDIC was founded in Belgium in 1913. Theobjectives of forming the federation were (and I believe are

    today):

    to promote

    the professional interests of the memberassociations and to disseminate information of interest

    to members of its component national associations.

    Introduction To The FIDIC Contracts (1999 Edition)

    FIDIC

  • 7/27/2019 Conditions of Contract - 19.11.2011

    5/28

    (Engineer hired, paid by and has

    contract with Employer

    Introduction To The FIDIC Contracts (1999 Edition)

    EngineerEmployer

    Contractor

    Engineers Dual Role:

    (1) Employers agent in some cases

    (2) Duty to act impartially between

    Employer and Contractor in other

    cases

  • 7/27/2019 Conditions of Contract - 19.11.2011

    6/28

    What is FIDIC?

    The function of Conditions of Contract is of greatest

    importance providing the rights, obligation andresponsibility for the parties concerned in theContract execution.

    During the past half century, the InternationalFederation of Consulting Engineers (FIDIC) hasdevoted itself to the compilation of managementdocuments for all kinds of projects, among which theFIDIC Conditions of Contract are of the highest

    influence and are the most popular application.

  • 7/27/2019 Conditions of Contract - 19.11.2011

    7/28

  • 7/27/2019 Conditions of Contract - 19.11.2011

    8/28

    The first edition of FIDIC Conditions of Contract

    for Works of Civil Engineering Construction (useRed Book in the following) was compiled in 1957,and later its second, third, and fourth edition wereissued in 1963, 1977, and 1987 respectively.

    Mostly compiled in the reference of the relateddocuments of the Institution of Civil Engineers

    With the investigation of the governments,

    employers, contractors and consulting engineersall over the world about their application of theRed Book, the FIDIC Contract Committeeorganized a group of experts to compile the newContract Condition models to be applied in the21stcentury.

  • 7/27/2019 Conditions of Contract - 19.11.2011

    9/28

    The new models include :FIDIC Conditions of Contract for Construction, the (New Red Book)

    FIDIC Conditions of Contract for Plant and Design/Build, the

    (New Yellow Book)

    FIDIC Conditions of Contract for EPC Turnkey Projects, the

    (Silver Book)

    FIDIC Short Form of Contract, the (Green Book)

  • 7/27/2019 Conditions of Contract - 19.11.2011

    10/28

    The FIDIC Red Book

    In 1957 FIDIC published the first edition of itsConditions of Contract for Works of CivilEngineering Construction, which came to be

    known as the Red Book.

  • 7/27/2019 Conditions of Contract - 19.11.2011

    11/28

    The Current (1999) Red Book

    Basic Features

    1. Suitable for all civil works projects where mainresponsibility for design lies with Employer (or his

    Engineer).2. Some design may, of course, be carried out by Contractor.

    3. Administration of Contract and supervision by Engineer.

    4. Approval of work, payment and claims certified by Engineer.

    5. Work done is measured, payment according to Bill ofQuantities.

    6. Option for payment on lump sum basis.

    7. Balanced / fair risk-sharing.

  • 7/27/2019 Conditions of Contract - 19.11.2011

    12/28

    The FIDIC

    In 1963, FIDIC published the first edition of its

    Conditions of Contract for Electrical and

    Mechanical Works suitable for use in contracts

    between an employer (owner) and contractor forthe supply and erection of plant and machinery.

    As its covers were yellow, it came to be known

    as the Yellow Book.

  • 7/27/2019 Conditions of Contract - 19.11.2011

    13/28

    The Current (1999) Yellow Book

    Basic Features

    1. Suitable for all types of projects where main responsibility for design lies with

    Contractor.

    2. Recommended for the provision of electrical and/or mechanical plant, and for thedesign and execution of building or engineering works.

    3. Some design may be carried out by Employer or his Engineer.

    4. Employer provides Employers Requirements to which Contractor designs.

    5. Administration of Contract and supervision by Engineer.

    6. Approval of work, payment and claims certified by Engineer.

    7. Lump sum Contract Price with payment usually based on schedule of payments.

    8. More extensive testing procedures than for New Red Book, including Tests after

    Completion.

    9. Balanced / fair risk-sharing.

  • 7/27/2019 Conditions of Contract - 19.11.2011

    14/28

    Reasons for a New (1999) Contract for EPC Turnkey

    Projects

    (the Silver Book)

    1. Increased use of two-party approach, without Engineer.

    2. Increased sophistication, improved education and experience in developing

    countries hence reduced need for an intermediary like an Engineer.

    3. Increase in privately-financed projects, like BOT, where customary for design andconstruction to be governed by an EPC Contract.

    4. As a result of increase in privately-financed projects, increased emphasis on risk

    allocation.

    5. In privately-financed projects, desire of lenders to place majority of risk on

    Contractor.

    6. Lump sum Contract Price with payment usually based on schedule of

    payments.

    7. Extensive testing procedures, including Tests after Completion

    8. Contractor takes majority of risks, Employer pays more to cover such risks.

    9. Final price and time of completion are intended to be more certain.

  • 7/27/2019 Conditions of Contract - 19.11.2011

    15/28

    New development of FIDIC conditions of contractDesign-Build Operate Contract

    It was published on

    September 2007,

    Gold Book

  • 7/27/2019 Conditions of Contract - 19.11.2011

    16/28

    Format of a DBO arrangement can be based ongreen field scenario (D-B-O), or

    brown field scenario (O-D-B). Either is quite common, however the contractual requirements

    and procedures are quite different.

    FIDIC - DBO green field scenario, with a Guide on the changesnecessary to cover a brown field arrangement, in which FIDICYellow Book for the DB is the basement.

  • 7/27/2019 Conditions of Contract - 19.11.2011

    17/28

    General Structure and Organization of

    the Red, Yellow and Silver Books

    1. General Conditions, comprising clauses that are believed

    will apply generally to most contracts (previously

    called Part I),

    2. Guidance for the Preparation of Particular Conditions,

    which will supplement or modify the General

    Conditions (they also include as annexes seven forms of

    security or guarantee) (previously called Part II), and

    3. Form of Letter of Tender, Contract Agreement and

    Dispute Adjudication Agreement (the Red and

    Yellow Books also contain an Appendix to Tender

    form to be attached to the Letter of Tender).

  • 7/27/2019 Conditions of Contract - 19.11.2011

    18/28

    18

    Issue of

    the Tender

    Documents

    Submission

    of the

    Tender

    Issue of the Letter

    of Acceptance

    8.1 Com-

    mencement

    Date

    Tender Period

    8.2 Time For Completion1

    28d 28d

    4.2 Issue of the

    Performance

    Security

    BaseDate

    9.1 Tests on2Completion . . .

    Delay attributable to

    the Contractor

    10.1 Issue of

    Taking-OverCertificate

    Defects Notification Period3

    11.9 Issue of

    PerformanceCertificate

  • 7/27/2019 Conditions of Contract - 19.11.2011

    19/28

    Characteristics of FIDIC Conditions of

    Contract Unification of Terms and Clause

    Not influenced by the former ICE framework, which was included

    in all 20 clauses. So if the clauses content could be unified, it would be under the

    same titles and expressions.

    In these three books, more than 80% of the content wasconsistent, and 85% of the definitions and expressions were the

    same.

  • 7/27/2019 Conditions of Contract - 19.11.2011

    20/28

    Wider Application

    Conditions could be applied under not only the Customary Law , but also Civil Law.

    An attorney present to review the clauses. More flexibility and adaptability.

    E.g.In the old edition, the conditional performance guarantee was necessary, which the WorldBank had different opinions of. While in the new edition, the guarantee forms were set byParticular Conditions which can be applied giving the employers better flexibility.

    Applicability under Various Project Delivery and Contracting System

    1. The New Red Book can be used in any kind of Engineering Construction Contract.

    2. The New Yellow Book applies to the lump sum contract project where the Contractor takesparticipation in the design work.

    3. The Silver Book applies to the turnkey projects of infrastructures or large-scale factories,where the Contractor takes on more work and risk while the Employers participation is small(private financing or government financing), but it is strictly defined upon the investment andconstruction period.

    4. The Green Book can be used in all kinds of small-scale projects.

    5. Altogether, these four Contract Conditions can be applied to nearly every kind of project,expect for that of managing contracting or simply consulting or designing

  • 7/27/2019 Conditions of Contract - 19.11.2011

    21/28

    High-quality Provisions and Logical Clause

    Sequencing

    Compared with the original Red Book, the New Red Book has

    163 clauses, nearly 40% being freshly compiled.

    An additional 40% were modified and given supplements. Only 20% were kept intact.

    The old edition adopted ICEs disorderly style bit in the clause

    sequence, while in the new edition, the related sub-clauses are put

    into one clause when possible, and convenient to the users.

    More Specific Provisions concerning the Rights

    and Obligations of the Contract Parties

  • 7/27/2019 Conditions of Contract - 19.11.2011

    22/28

    Changes in the Preparing Style

    General Conditions in the former edition were fairly concise;some recommendable clauses were given Particular Conditions.

    While in the new edition, there is a way around the regulationsbeing that the General Conditions are relatively comprehensiveand detailed. An example would be advanced payment andadjustment formula.

    The new edition writers believe that it is more convenient for theusers to delete the clauses they do not need than to write them inthe Particular Conditions by themselves.

    Concise Language

    The language and sentence structures in the new edition arerather easy to understand, and a great help to the people whose

    native language is not English.

  • 7/27/2019 Conditions of Contract - 19.11.2011

    23/28

    Application Prospect of FIDIC Conditions of

    Contract

    The traditional project management mode, which isuniversal in the world, has been applied in most of the

    engineering project management cases in the world.

    The new edition has many advanced ideas andregulations such as standardizing of the Contract

    words and expressions, clearer and stricter claimprocedure, and emphasis on the protection ofintellectual property rights

  • 7/27/2019 Conditions of Contract - 19.11.2011

    24/28

    Since the problems of the Employers financial vacancy or

    Contractor financing are originating worldwide, therelative clauses and regulations are added into FIDICConditions of Contract.

    To Carry out the General Contracting Mode ofDesign/Build and EPC Turnkey Enthusiastically

    FIDIC makes out the New Yellow Book andSilver

    Book independently in addition to meet thedevelopment tendency of international projectmanagement mode.

  • 7/27/2019 Conditions of Contract - 19.11.2011

    25/28

    To Make Clear the Position of the Construction

    Supervising Engineer, Raise Their WorkingResponsibility, and Open up New Regions of Work

    In the New Red Book, it needs the Engineer to be timelier, and

    more explicit in solving the problems than before. It pays more respect to the position and the authority of the Engineer,

    such as, without the consent of the Contractor, the Employer shallnot be entitled to exchange the Engineer or impose further restrictionon the Engineers authority which has been specified in the contract.

    To Prepare the MODEL of Short Form Contract

    FIDIC Green Book

  • 7/27/2019 Conditions of Contract - 19.11.2011

    26/28

    To Improve the Mediation Methods for Dispute

    DAB to mediate the dispute.

    The most outstanding merit of DAB is that it iscomposed of three experts who are chosen, approved

    and paid for by both parties. These experts go to site to solve the dispute occurring

    between the two parties after commencingconstruction work.

    While in the FIDIC Red Book, the Engineer is

    required to mediate the problem which he can nothandle.

    It is hard to be impartial because the Engineer is theEmployers employee, so very often the contradictionwill still be unsolved after a long time.

  • 7/27/2019 Conditions of Contract - 19.11.2011

    27/28

    FIDIC Latest!!!

    FOR BUILDING ANDENGINEERING WORKSDESIGNED BY THEEMPLOYER

    MDB Harmonised Edition,June 2010 Version

    Amended Version publishedJune 2010

    Amended Version publishedMarch 2006

    FOR USE UNDER LICENCEON PROJECTS FUNDED BYPARTICIPATINGMULTILATERALDEVELOPMENT BANKS(MDB)

  • 7/27/2019 Conditions of Contract - 19.11.2011

    28/28