conceptual design of thermal hydrolysis … 2010/mohammad abu-orf_nbp...step action time description...
TRANSCRIPT
4/12/2010
1
Conceptual Design of Thermal Hydrolysis Processes for Enhanced SolidsProcesses for Enhanced Solids Reduction from Anaerobic Digestion
Mohammad Abu-Orf, PhD
AECOM Water
North America Biosolids Practice Leader
Outline
1. Overview of Thermal Hydrolysis Pretreatment Processes
1-TH Overview
2. Cambi Process– Process components– Reactor design– Reactor sequencing/operation
3. BioThelys Process
2-Cambi
3-BioThelys– Process components– Reactor design– Reactor sequencing/operation
4. Future of Thermal Hydrolysis April 12, 2010 Page 2
4-Future of TH
4/12/2010
2
1. Overview of Thermal Hydrolysis Pretreatment ProcessesPretreatment Processes
Page 3
Thermal Hydrolysis Process (THP)Process• Treat dewatered sludge prior to
anaerobic digestion, under the following conditions:
Hi h f
Result• Decrease viscosity
– Allows sludge mixing at higher concentrationD di ti l
1-TH Overview
– High temperature of 150°C to 170°C
– Under pressure of 6 to 9 bars– Reaction time 20 to 30 min
• Dewatered sludge from 14 to17%
• Input to digestion 10 to 12%
– Decrease digestion volume
• Sterilized sludge (Class A)
• Improvement anaerobic digestion– Increase VS reduction– Improve biogas production– Reduce mass for further
processingInput to digestion 10 to 12% processing
Before TH After TH
4/12/2010
3
Thermal Hydrolysis for Anaerobic Digestion
7 Desired Parameters
for
1. Class A biosolids: sustainability and reuse cost2. Less digestion volume: water content of the feed3. High digestibility: more gas4. Good dewaterability: less hauling and cost 5 Minimize FC reactivation/regrowth potential and odors:
1-TH Overview
for Digestion
5. Minimize FC reactivation/regrowth potential and odors: sustainability for land application
6. High digester loading rate7. Good mixing efficiency
Thermal Hydrolysis Achieves All Above• Pasteurized solids, Class A• Digester is fed at 11-12% total solids (half), energy
Aberdeen
Digester is fed at 11 12% total solids (half), energy efficiency
• Volatile solids destruction is high 55- 65%• Dewatered cake is in low to mid 30%• Proven to not have problem with FC
reactivation/regrowth, better odor quality• 50% more solids loading compared to conventional • Power required to mix digester is less
Considerations for Thermal Hydrolysis
• Only achieve Class A if all sludges are treated by THP
• 10-12% into digestion if both primary and WAS are g p ytreated
• % solids to the digester is determined partly by % N
• THP WAS only plant goes into digester by a smaller percentage
THP d t t d h t t b i l• THP needs to capture and re-use heat to be economical
• Hydrolyzed sludge stinks, need tight sealing with potential for gas escape
April 12, 2010 Page 6
4/12/2010
4
Two Main Thermal Hydrolysis Processes
They are different processes in terms of operations and design
1-TH Overview
BioTHELYS CAMBIReactors in parallel Reactors in series
Flash steam
Reactor 2
Flash steam
Fresh steam Reactor 1
Fresh steam
Pulper Flash tankReactors
Thermal Hydrolysis References1-TH Overview
Cambi BioThelysFirst installation in 1996 First installation in 2006First installation in 1996 First installation in 200620 plants in operation 4 plants in operation5 plants ordered and under construction
All
All plants as of 2010 are outside North America
Plants are in France only
Treating ~ 417,600 dry tonnes/yr Treating ~ 6,200 dry tonnes/yr (1.5% of Cambi)
April 12, 2010 Page 8
of Cambi)Smallest plant is ~ 3.3 dtpd Smallest plant is 3 dtpdLargest plant is ~ 250 dtpd Largest is 5 dtpd
4/12/2010
5
2. Cambi Process
1-TH Overview
2-Cambi
Process
Typical Cambi™ Integration with WWTP2-Cambi
Typical Cambi
Typical WWTP
scope forthis area
4/12/2010
6
Cambi and Reactor Operation (90 minute cycle time)
Dewatered solids (14.7%)
Recycled Steam
2-Cambi
Fresh Steam
~11% to digestion
FLASHTANK
PULPER REACTOR
Dilution Water
HE
Step Action Time Description1 Fill 15 min Fill Reactor with 7.6 m3 of sludge (12 m3 reactor)
2 Steam injection 15 min Inject steam in the Reactor
3 React 30 min Hold Reactor at 165C and 90 psig
4 Steam out 15 min Release steam to Pulper
5 Empty 15 min Transfer sludge to Flash Tank by pressure release.
Reactor Sizing for Cambi
• Standard size Pulper and Flash tanks
• Standard size reactor is 12 m3 and expected to operate 70% (7.6 m3)
2-Cambi
• Assuming a 14.7% and 90 minute cycle time– Capacity of each reactor is 17.9 dry metric ton/day, use 95% up time
• For effective asset use, one train with one reactor can process sludge from a 15-20 MGD plant
• Use maximum month or maximum-15d to determine number of reactors, and number of Cambi trains
• At average day more Cambi capacity allowing some level of• At average day, more Cambi capacity, allowing some level of redundancy depending on plant size
• Can increase Cambi throughput through reducing reaction time and increase solids input concentration
• Uses 1 lb of fresh steam per dry ton of solids processed
4/12/2010
7
Cambi Reactors Sequencing (example 3 reactors)• Reactors are doing different
things at same point in timeChertsey, UK
2-Cambi
• Only valves opening and closing to direct sludge and steam
• Works best if runs continuously, no cooling down
z
down15 min 15 min 30 min 15 min 15 min
Reactor 1 Fill Steam In React Steam out EmptyReactor 2 Empty Fill Steam In React Steam outReactor 3 Steam out Empty Fill Steam In React
3. BioThelys ProcessIs it really a “copy cat” of Cambi?
1-TH Overview
2-Cambi
3-BioThelys
4/12/2010
8
G h ld
Cogeneration
Dewatering
Sludge Water kW
HeatLive steamBiogas
Fl h tF di G h ld
Cogeneration
Dewatering
Sludge Water kW
HeatLive steamBiogas
Fl h tF di
BioThelys in Saumur, France
15 %
3-BioThelys
Anaerobic digester
Gas holder
Buffertank
Heatexchanger
THELYS reactors
Boiler
Service water
Flash steam
Hydrolysed sludge
Feedingtank
Anaerobic digester
Gas holder
Buffertank
Heatexchanger
THELYS reactors
Boiler
Service water
Flash steam
Hydrolysed sludge
Feedingtank
Mesophilic anaerobic digestion
110°C
45°C
38°C 15 days
Dewatering
Dewaterd sludge
Return liquor
BioTHELYS®D Process
Digested sludge
Dewatering
Dewaterd sludge
Return liquor
BioTHELYS®D Process
Digested sludge
Storagecells
15 days
27-29%
8 monthsAgricultural valorisation
BioThelys Rector Operation (150 min cycle time)25 min 20 min 25 min 30 min 20 min 25 min 5 min
3-BioThelys
Raw sludge
0Live steam
1Raw sludge
2Flash steam
3Live steam
4Flash steam
65Raw sludge
7Live steam
BA BA
15°C
160°C
BA
160°C
BA
160°C
110°C
15°C
75°C
A
110°C
B
Hydrolysed sludge
75°C
160°C
BA
15°C
75°C
160°C
110°C
BA
160°C
Hydrolyse sludge
BA
75°C
160°C
110°C
4/12/2010
9
Reactor Specifications• Standard design uses 2 reactors, each reactor to be filled at 50%
• All reactors are same size and same function, no Pulper or Flash Tanks
• Kruger custom design the reactors to meet the process needs and
3-BioThelys
Kruger custom design the reactors to meet the process needs and application – Previous sizes include 3.1, 3.9, 4.6, 4.9 m3 thus expected to be more economical than Cambi
for smaller size plants
• Consider plant processing 4.5 dtpd, with two (2) 3.1 cubic meter reactors as a practical minimum size plant
• The operations of thermal hydrolysis and regulation around boiler operators may increase the practical minimum size due to staffingoperators may increase the practical minimum size due to staffing requirements
• Veolia can design/construct trains of 3 reactors (scale and economy)
• The total cycle time is 165 min for 3 reactors (compared to 150 min with 2 reactors). The flash steam goes from reactor 1 to 2 and 2 to 3 and 3 to 1
Page 17
BioThelys Reactor Sizing• Assuming a 15% solids feed and 150 minute cycle time, and 50%
active volume
• One cubic meter able to process 0.72 metric dtpd
3-BioThelys
• The flexible size of Biothelys allows more efficient sizing
Reactor size (m3)
Metric dtpd processed per
reactor
Plant sizedtpd
(2 reactors)3.1 2.25 4.54.9 3.5 7.012.5 9.0 18.0
• The flexible size of Biothelys allows more efficient sizing
• However, standardized Cambi reactor size increases quality control
• If one reactor is out, process is out
• No Flash tank to equalize the flow to digestion
4/12/2010
10
Issues to consider when adapting Thermal Hydrolysis • Maintenance of the process components can be a challenge
• Operators skill – require operators used to pressure and steam
• Regulations regarding frequency of pressure vessel inspection include in the
3-BioThelys
• Regulations regarding frequency of pressure vessel inspection – include in the design
• Ammonia in recycled stream can be a concern
• Two dewatering steps
• Require proper screening of sludge
• Delivery method in Europe mainly DB and DBO in one package with digestion and co-gen, guarantees usually in terms of electricity production per solids processed
• Processing FOG through digestion requires separate system of pasteurization after treatment to incorporate with digestion for Class A production
• Issues with rDON and recalcitrant COD
• If flash tank is inside needs to manage building environment (process gets hot)
April 12, 2010 Page 19
The Future of Thermal Hydrolysis
1-TH Overview
2-Cambi
Hydrolysis
3-BioThelys
4-Future of THTH
4/12/2010
11
Cambi Progress Increased plant size is a sign of credibility Took off since 2006, start of BioThelys
Cambi Plants Biosolids treated by Cambi
4-Future
Cambi Plants Biosolids treated by Cambi
10
15
20
25New Plants OnlineCumulative Plants
200,000
250,000
300,000
350,000
400,000
450,000New Capacity Online, DTPYCumulative Capacity, DTPY
April 12, 2010 Page 21
0
5
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
0
50,000
100,000
150,000
1996
1998
2000
2002
2004
2006
2008
2010
North America Update
Blue Plains• 4 Cambi trains, six reactors per train
Trinity River Authority• CDM/AECOM team
recommended thermal
4-Future
• 4 digesters
• New pre-dewatering facility: centrifuge
• New post-dewatering facility: (BFP)
• ~10-14 MW facility
recommended thermal hydrolysis as the best option to process residuals at CRWS – phased approach
Hamilton• AECOM/CH2MHILL team
d d th l
April 12, 2010 Page 22
recommended thermal hydrolysis of WAS to increase gas generation and energy revenues from cogeneration, and to avoid expanding digesters
4/12/2010
12
New Advancement from Veolia
• Veolia Water Systems is rolling a new thermal hydrolysis design (Exelys) during 2010 RBC in Savannah
4-Future
Savannah
• Claims:– Increase energy efficiency – Plug flow, continuous one reactor design– Compact, with lower footprint
April 12, 2010 Page 23
Thank you!
Mohammad Abu-Orf, PhDAECOM Water
North America Biosolids Practice [email protected]