concept note setting-up of vsat network up to gram ... · the vsat bandwidth provider should have...
TRANSCRIPT
Page 1 of 13
CONCEPT NOTE
SETTING-UP OF VSAT NETWORK UP TO GRAM
PANCHAYTS IN RAJASTHAN
Abstract:
The Government of Rajasthan (GoR) has envisaged to establish network connectivity
to Government Departments, and expand the network upto around 10,000 locations
spread across 9177 Gram Panchayats and 183 municipal areas in Rajasthan to cater
voice, video and data services.
It is proposed to extend connectivity to Gram panchayats and other offices of GoR, over
various mode of connectivity like VSAT, Leased line (Wireless/ Wired Line) i.e. multi-
mode solution.
For VSAT solution, set-up of CAPTIVE HUB is also proposed. The agency shall propose
technical solution for either in Extended-C band (XC) or KU-band. The specifications
for Portable VSAT - BUC (Extended C-band), SLA for CAPTIVE HUB and Annexures
of DOCUMENT are under preparation.
It is proposed to award the work along with a rate contract for expansion to a consortium
agency for providing connectivity over multi-mode, with minimum assured links of each
mode.
An integrated NOC is required to be set-up for monitoring of existing network/devices
and upcoming network. The complete solution should be operated, maintained and
managed by the agency for 5 years.
RISL is assigned for implementation of proposed network.
The prospective agencies are requested to go through the draft document and
provide inputs at email id given below.
-Kuldeep Yadav (ACP)
Email: [email protected]
Page 2 of 13
PROJECT PROFILE & BACKGROUND INFORMATION
Introduction
Government of Rajasthan has established a metropolitan area network (MAN) in 2005
covering around 48 various offices located in Jaipur city under SECLAN project.
Thereafter, in 2013, the network has been extended to 33 District Collectorates, 240
Block Head Quarters and 3500 (approx.) offices located in these District/Block
Headquarters under Rajasthan State Wide Area Network (RajSWAN) project.
State Government has envisaged to establish network connectivity to Government
Departments, and expand the network to 9200 locations covering mainly Gram
Panchayats and some other offices in Rajasthan to cater voice, video and data services
under various categories of G2G, G2B and G2C services.
RAJNET is envisaged as the platform to provide network connectivity through
multimode (i.e. Landline, RF, VSAT, OFC etc.) of connectivity throughout Rajasthan
state. It is also proposed to establish network operating center for monitoring of
multimode connectivity in the state. Under RAJNET, expansion of connectivity is
proposed through VSAT upto Gram Panchayats.
Detailed solution requirement for providing multi-mode connectivity is as below:
a) Connectivity to identified Gram Panchayats (GPs) and other offices located
under its jurisdiction.
b) It should provide VSAT connectivity in Ku band/Extended C-band for Data, Voice
and Video traffic.
a. The proposed VSAT network will be based on a star architecture and shall
be an IP based network for running various Network based applications
at remotes.
b. The Service Provider shall establish a dedicated, end-to-end, secured &
manageable VSAT network with backhaul connectivity over MPLS-VPN
from Service Provider’s HUB station to RSDC at Jaipur and requisite
bandwidth to designated locations.
c. Setup of HUB and Antenna within time period specified in DOCUMENT
for Captive model, and migration of already installed VSAT terminals in
the project, to the Captive HUB.
c) Setting-up of Operation & Maintenance of VSAT NETWORK and wide area
network on wire line/wireless for a period of 5 years.
Page 3 of 13
Satelite
RAJNET – Pictorial Representation of the Architecture
s
Remote VSAT
Remote VSAT
Remote VSAT
Remote VSAT
RISL HUB
RISL NOC
NMSHDMS
Sw
itc
h
SATCOM
WA
N R
ou
ter
Sw
itc
h
RajSWAN and SecLAN
WA
N R
ou
ter
Sw
itc
h
Other Networks
Integrated Network Monitoring System (NMS):
a) The agency is required to establish an integrated NMS, NOC and HDMS for
multi-mode type of connectivity under RAJNET.
b) It should configure exiting RSDC devices and network infrastructure of SECLAN,
RajSWAN, and GRAMSET etc.
c) The proposed connectivity through wired-line, wireless and VSAT should also be
monitored through proposed NMS.
Page 4 of 13
ELIGIBILITY
Consortium of IT companies/firms and Bandwidth providers shall be permitted.
Bills by the respective member of consortium shall be raised through Lead
agency. Payments to respective bandwidth service provider shall be made
directly.
The consortium partners should have experience of bandwidth services, O&M of
inter-city Wide Area Network of minimum 500 nodes and NOC operations.
The VSAT bandwidth provider must have at least 10,000 operational VSAT
terminals in India as on 31st March 2014.
The VSAT bandwidth provider should have at least one transponder satellite
bandwidth in offered frequency band (Ku band/Extended C-band) as on last date
of bid submission.
The VSAT hardware along with HUB should be supported by minimum two VSAT
bandwidth provider from different HUB locations.
The OEM of VSAT equipment must be a registered company in India for last five
years.
The OEM must have a service center in India.
SCOPE OF WORK FOR VSAT CONNECTIVITY
The agency shall be required to supply, install and integrate the solution as per the
scope of work detailed below. O&M of the proposed solution shall be provided for a
period of 5 years from GO-LIVE.
The successful deployment of project requires the agency to provide quality & timely
services to GoR. The agency is strongly advised to carefully read the complete
DOCUMENT, understand the RSDC/ SecLAN / RajSWAN network and carry-out the
site visits of proposed locations where multi-mode solution and IT infrastructure is to be
installed, implemented and commissioned.
For successful implementation of the project, the SP or lead agency in case of
consortium shall depute one Project Manager at DoIT&C, Jaipur as single point of
contact (SPOC) for DoIT&C. SP shall provide the contact numbers, e-mail id and other
relevant details of the SPOC to DoIT&C.
Page 5 of 13
1. Detailed Scope of work (SoW)
Deployment of core VSAT solution consists of various steps and activities like
preparation of the detailed project implementation plan, supply of required hardware
and software at project locations, implementation of VSAT solution, commissioning,
documentation, UAT reports with configuration details, basic training etc.
The Service Provider shall establish a dedicated, end-to-end, secured & manageable
VSAT network, initially with backhaul connectivity over MPLS-VPN from Service
Provider’s HUB station to RSDC at Jaipur. Antenna and HUB station should be supplied
and set up and all the VSATs should be migrated to this HUB station. The agency shall
propose technical solution either in Extended-C band (XC) or KU-band.
The service provider will also establish integrated wide area network on wire
line/wireless /leased line etc.
The scope of work also requires deployment of required manpower as defined in for
various activities like Project Management, O&M and support services etc.
1.1.1 Understanding of Project
To understand the overall scope of project, the agency shall be required to study the
following:
1) RajSWAN,SECLAN network and SATCOM,
2) Rajasthan State Data Centre (RSDC),
3) Any other plan, policy, document and report as deemed necessary for effective
implementation of required VSAT solution,
4) Providing turnkey solution for connectivity at the specified locations and integrate
with the RajSWAN/ SECLAN/ Data Centre and operation & maintenance and
management.
1.1.2 Infrastructure Deployment
During the implementation period, SP shall provide, on a weekly basis, the
implementation progress report to DoIT&C/RISL/ designated agency. The project
manager is required to attend regular review meetings with DoIT&C/RISL preferably on
fortnight basis.
1) Supply of the required items, equipment:
a) meeting technical specifications,
b) complete new set of hardware at all sites specified in minimum Bill of
Material as per the work order,
Page 6 of 13
c) any other peripherals & fixtures (e.g. screws, clamps, fasteners, ties
anchor, supports, wires, etc.), assemblies for fixing of cables, conductors
etc. necessary for the installation of the connectivity/ solution.
d) Software of genuine OEM license(s), as applicable, with all the requisites
updates and patches for entire contract period.
2) The agency should seek and submit statutory clearances such as SACFA, WPC
and any other permission/clearance required (if applicable) for DoIT&C/RISL/
GoR.
3) The SP is required to supply, install and integrate Antenna & Hub (as required
for captive setup) and VSAT Terminals.
4) The purchase order for supply of VSAT terminals shall be given in two phases
to the agency. The first purchase order shall be given for 7000 of the sites and
Hub equipment and around 1000 locations on wire line/wireless. The second
order shall be issued as per requirements within 9 months of the order.
5) Subsequently, the rates should be valid for another one year by way of rate
contract.
6) The equipment should have comprehensive onsite OEM warranty or agency
warranty and for a period, as specified in BOM, starting from go-live. The
comprehensive OEM onsite warranty includes the following:
a) Repair of faulty equipment.
b) Replacement of irreparable equipment or parts with equivalent or higher
compatible with the solution
c) Providing technical support
d) Software updates and Upgrades.
Any other activity to keep the solution/ set-up functional to its full capacity shall
be the responsibility of agency.
It is pertinent to mention that installation and commissioning of some
equipment may happen much earlier than the go-live. Therefore, agencies
are advised to take warranty from OEMs for the entire contract period,
including the period taken for installation and commissioning before go-
live.
7) Installation & configuration:
1. The installation and configuration:
a) of items supplied,
b) To be done appropriately and in a conscientious manner as per the OEM
guidelines,
c) Following statutory regulation/ codes at all times,
Page 7 of 13
d) Ensuring safety regulations and practices, and
e) Ensuring that no damage is caused to customer premises and property
and to restore the property, wherever required, at no cost to purchaser, if
any damage occurs.
2. Extending, fixing and installing the electrical points (switches, plugs, wire,
conduits etc.) from the existing electrical outlets to the supplied VSAT/ wire
line/wireless equipment, wherever required. It may be noted that no additional
payment will be made for this work and material, and so agencies are advised
to quote keeping this in mind.
3. Routing and Fixing of cables (like RF, Power, CAT-6 etc.) and making
necessary holes in the walls wherever required. The cable between VSAT
antenna and VSAT modem should be clipped/Clamped properly with the wall
without any loose cables hanging around. Excess cables if any should be
wound neatly near to the VSAT modem.
4. Plugging conduits and entrance holes wherever cabling is essential with
suitable sealing material.
5. Deployment of connectivity/ solution in consultation with the DoIT&C/RISL
and adhere to all the applicable GoI/GoR/TRAI or any other regulatory
agency, RSDC and RajSWAN policies (IP Addressing, Access Control,
Security, Backup/ Restore, Internet access, Routing and Switching, VSAT
Communication Standards and Policies etc.), as applicable throughout the
project period.
6. Initially, the service provider shall provide backhaul connectivity from the
service provider's hub to the SDC at Jaipur over MPLS-VPN for voice, video
and data, Anti-Virus, Network monitoring, etc., along with dual homing last
mile (Telecom Service Provider premises to RSDC, Jaipur).
7. The backhaul provided shall be on the infrastructure of the telecom service
provider having National Long Distance (NLD) license, to ensure end to end
quality of service (QOS) delivery and ownership.
8. The video bandwidth should be re-configurable for video multicast, video
conference and VoIP. Pool of satellite bandwidth supplied for video should
also be re-configurable for usage of data when Video / Voice / Multicast is not
used. Schedule of Voice / Video and Multicast would be provided to the
SPOC.
9. The satellite bandwidth should support guaranteed bandwidth, Bandwidth on
Demand, Slotted Aloha and Mix of these.
10. The agency should supply, install and commission Hub Baseband system
suitable to operate with 10,000 VSATs. Redundant UPS power backup to the
Hub should also be supplied by the agency.
11. After installation and commissioning of the Captive setup (Antenna, Hub etc.),
the agency shall migrate all the VSAT Links commissioned to the newly setup
HUB.
Page 8 of 13
8) Coordination by Agency
1. DoIT&C/RISL would initiate procurement of required licenses for operating
the Captive VSAT network and bandwidth from Antrix, ISRO. Upon receiving
work order, the service provider to coordinate / liaison between DoIT&C/RISL
and DoT/ respective authority for reception of clearances / licenses to operate
the captive VSAT network.
2. The Service Provider should also coordinate / liaison with Antrix, ISRO for
allocation of Bandwidth. RISL would make payment to DoT / WPC / SACFA
/ Antrix / any other regulatory authority.
3. The Service Provider during the implementation period and during O & M
should do the necessary coordination / liaising for compliance of the network
with appropriate authorities.
4. It should be noted by the agency that the payment of HUB, Antenna etc.
(to be installed at Jaipur) shall be made only after successful
installation of Captive hub and migration of all the operational VSATs
to Captive HUB. As such, the agency shall be required to make
aggressive efforts to install the equipment and seek all regulatory
clearances on behalf of DoIT&C/RISL.
9) Integration:
1) The service provider should ensure seamless integration with RSDC,
SECLAN and RajSWAN for data, voice and video services. Additional
hardware and software required for the same shall be detailed in the technical
bid.
2) The service provider shall ensure that all applications hosted at the Rajasthan
State Data Centre are accessible at all remote sites through VSAT network.
3) Configuration and fine-tuning of subsystems to achieve overall optimal
network performance and highest security.
4) Configuration of deployed VSAT terminals and all sub-systems to the Service
provider’s Network Management System (NMS), Helpdesk Management
System (HDMS) and Network Operation Center (NOC), till the captive setup
becomes operational.
5) Migration (re-orientation, re-configuration etc.) of Operational VSATs to
captive hub.
6) Laying and Routing of CAT-6 Cable for integration with RSDC/ SECLAN/
RajSWAN to the router being supplied under the project.
7) The overall satellite bandwidth of 36 Mbps and backhaul bandwidth of 24
Mbps on MPLS-VPN shall be procured in a phased manner.
8) The initial satellite bandwidth of 14 Mbps (10 Mbps for video and 4 Mbps for
Data) shall be hired and shall be increased/decreased in steps of 2 Mbps in
a phased manner by giving one month time. In case of delay in providing the
Page 9 of 13
additional bandwidth, the Liquidated Damages as defined in DOCUMENT
shall be applicable.
9) The agency should provide 20 video channels of 512 kbps each at the ratio
on 1:1 initially which may be increased or decreased as required.
10) Pool of satellite bandwidth supplied for voice and video should also be usable
for data.
11) The initial backhaul bandwidth of 8 Mbps shall be hired which shall be
increased/ decreased in a phased manner by giving one month time.
12) The additional satellite bandwidth and additional backhaul bandwidth shall be
procured on demand basis.
13) The complete network must be PCI complaint
14) The proposed solution must be end-to-end IPv4 and IPv6 (dual-stack)
complaint (ie without any IP translation from IPv6 to IPv4 and vice versa) from
day one.
15) Provide client interface of Agency’s Network Monitoring system at DoIT&C,
Jaipur through backhaul connectivity to monitor the entire network.
1.1.3 Migration
The agency on receipt of work order should start supply, installation & commissioning
of VSATs to the designated Gram Panchayats as provided along with the work order.
Initially, the VSATs should be commissioned to the shared network of Service Provider.
As and when the Captive Hub is ready with Bandwidth allocation and all Operating
licenses / clearances, the Service provider should migrate / re-orient the VSAT
commissioned from their hub to RISL network and all further VSAT commissioning at
Gram Panchayats should be to the Captive Network of RISL. The backbone bandwidth
re-configuration shall also be done accordingly.
1.1.4 User Acceptance Test (UAT)
The primary goal of Acceptance Testing is to ensure that the Project (including all the
project components as discussed in the scope of work) meets requirements, standards,
specifications and performance, by ensuring that the following are associated with clear,
quantifiable metrics for accountability:
Infrastructure Compliance
Performance
Integration
Project Documentation
1.1.4.1 Supply of following documents:
a) Detailed network solution design (architecture diagram, functionality etc.),
b) Details of inventory deployed including hardware and software location-wise along
with serial number, product ID, licenses, part code etc.
Page 10 of 13
c) Location-wise material delivery & installation report of all equipment/ software
supplied duly signed by purchasers authorized person.
d) Compliance certificate’s for specifications of hardware and software supplied.
e) Installation, configuration and integration settings of all the installed components of
VSAT solution with IP address details etc.
f) OEM Warranty documents,
g) Original S/w/ CDs/ DVDs and licenses, wherever applicable,
h) User Manuals, Administrator Manual and datasheets, wherever applicable,
i) UAT reports,
j) Service Operation Procedure (SOP),
1.1.4.2 Licensing:
a) All software licenses, documents and statutory clearances such as SACFA, WPC
and any other as applicable. The licenses should be valid over a period of five years
except otherwise specified in this DOCUMENT.
b) In case of licenses which requires annual renewal, an undertaking for timely
renewal by the agency should be submitted.
1.1.4.3 Others
a) The agency shall co-ordinate and carry any other required test as desired by
purchaser.
b) DoIT&C/RISL may associate authorized personnel for above test.
c) Rectifying the Hardware, Software and deployed solution issues/ bugs reported, if
any, during the testing. The selected agency shall make the required changes to
the application/solution deployed at no extra cost.
d) VSAT link(s)/equipment not passing the AT, if any, shall be rectified by the SP in a
timely manner with a request for re-test by DoIT&C/RISL/ designated agency. If any
VSAT link(s)/equipment fails the AT repeatedly, it may be cancelled by
DoIT&C/RISL, without any claim for payment to SP.
e) Agency is required to intimate the purchaser one week prior to the commencement
of UAT activities.
f) User Acceptance Test for the last phase of the ordered quantity may be conducted
on completion of installation and integration of 90% VSAT of ordered quantity in
case there is a possibility of delay in completion of 100% work on part of purchaser.
g) The QGR shall be payable to the Agency from the date of successful testing and
acceptance of the respective phase.
h) In case of UAT on 90% of installation and integration of VSAT as mentioned under
above clause, the commissioning for the balance 10% of endpoints shall be
conducted subsequently. The QGR for these endpoints shall be released from the
date of successful commissioning.
Page 11 of 13
i) The time taken for approval of UAT acceptance by DoIT&C/ RISL, shall not be
considered as delay on agency’s part.
1.1.5 Commissioning (Go-Live):
Final approval/ user acceptance of the deployed VSAT solution shall be given by
DoIT&C after successful implementation, testing and receipt of documents. It is the
responsibility of the agency to submit test reports and obtain the UAT approval from
the DoIT&C. On successful AT of the VSAT links of the particular phase, the links shall
be declared commissioned and GO-LIVE shall be given for that particular phase with
effective from date of submission of UAT report.
It is to be noted that the procurement agency may get the VSAT solution audited through
a Third Party, before Go-Live and periodically after Go-Live, in order to ensure the
success of the project. Such third-party agency for carrying out the acceptance testing
and certification of the entire solution will be nominated by the DoIT&C. All expenses
towards hiring of TPA shall be borne by purchaser. The SI shall be required to extend
co-ordination to such TPA for testing etc.
1.1.6 Training
Imparting the basic on-site training to designated officials so as to make them well
conversant with the functionalities, features and processes of VSAT and HUB
configuration, operation, and functionality and communication set-up at respective
project locations.
1.1.7 Operation & Maintenance (O&M)/ Facility Management Services (FMS)
The objective of O&M is to operate and manage the entire multi-mode network including
GPs locations, NOC/NMS center, HUB, Backhauls by the agency for a period of 5
years from GO-LIVE. This will include management, operations & maintenance
of all the facilities and all other elements that form the Network along with bandwidth
provisioning and bandwidth management.
The agency should provision sufficient manpower for operation & maintenance of the
Network.
It shall include the following:
Onsite Maintenance and Support Services
Network Management
Helpdesk Management
HUB Management
OEM Support Services
a) OEM Support Services:
Agency should have direct back-to-back service support agreement with the respective
OEM for the project duration of 5 years as per DOCUMENT. DoIT&C/RISL/Agency/
Page 12 of 13
GoR must be able to log a support ticket directly to OEM helpdesk to get telephonic/
remote support directly from OEM as required. Undertaking from OEM for above
support services should be submitted by the Agency along with the bid.
1.1.8 Project Handover
After successful completion of the Project/ contract (i.e. 5 years from commissioning),
it shall be handed-over to RISL/DoIT&C/GoR.
Evaluation & Tabulation of Financial Bids
In order to decide the L1 agency, NPV (Net Present Value) of the payable amount shall
be taken into account as given below:
Upfront payment = 30% of Price quoted for CAPEX = A
Price quoted for OPEX + Bandwidth for 5 years = B
Total quarters for which payment to be made = 20 for VSAT and 16 for CAPTIVE
HUB
Quarterly payable amount for VSAT = [{(Balance amount of A )+ B}/20] = C1
Quarterly payable amount for CAPTIVE HUB = [{(Balance amount of A )+ B}/16] =
C2
The PV factor would be 4.5% per quarter (18% per year).
NPV1 for VSAT = A+ [C/1.045] + [C/(1.045)2] + [C/(1.045)3] + [C/(1.045)4] +
[C/(1.045)5] + . . . . . . . . . . . . . [C/(1.045)20]
NPV2 for CAPTIVE HUB = A+ [C/1.045] + [C/(1.045)2] + [C/(1.045)3] + [C/(1.045)4]
+ [C/(1.045)5] + . . . . . . . . . . . . . [C/(1.045)16]
Net NPV = NPV1 + NPV2
NOTE: For wireline/wireless connectivity, a tentative quantity of different type
of connectivities shall be considered for evaluation.
Page 13 of 13
Payment Terms and Schedule for VSAT connectivity
a) Payment schedule – Payments to the agency, after successful completion of the
target milestones (including specified project deliverables), would be made as
under: -
Payment Terms and schedule
Sl.
No. Deliverable Applicable Payment (Code)
1.a. On Successful UAT of each
phase for VSAT terminals
30% of CAPEX (Ref. Fin. Bid) of each
phase after successful UAT,
AND
70% of the remaining CAPEX (Ref. Fin.
Bid) of the respective phase, shall be paid
in equal instalment per quarter, for 20
quarters, at the end of each quarter
1.b. On Successful UAT of CAPTIVE
HUB
30% of CAPEX (Ref. Fin. Bid) of each
phase after successful UAT,
AND
70% of the remaining CAPEX (Ref. Fin.
Bid) of the respective phase, shall be paid
in equal instalment per quarter, for 16
quarters, at the end of each quarter
2.a After GO-LIVE during O&M of
each phase upon submission of
quarterly deliverables:
MIS reports and
SLA reports
Applicable OPEX on actuals (Ref. Fin. Bid)
of the respective phase, payable on
quarterly basis.
2.b Bandwidth availability in each
quarter upon submission of
quarterly deliverables MIS
reports and SLA reports.
Applicable bandwidth charges on actuals
(Ref. Fin. Bid) payable on quarterly basis.