compliance report of environmental clearances · the analysis reports for fuel gas emission are...
TRANSCRIPT
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCES
[Compliance Report: April’16 to September’16]
Submitted By:
M/s. BEEPEE COATINGS PVT. LTD.
Plot No. 443, GIDC Estate, Vithal Udyognagar
Ta & Dist: Anand, Gujarat – 388121.
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE
Project : Our is an existing large scale unite in the name of M/s. Bee Pee Coatings Pvt. Ltd. Located
at plot no. 443, GIDC Estate, Vithal Udyognagar, Tal& Dist: Anand, Gujarat involved in the
manufacturing of Alkyd Resin, Primer, Synthetic Enamel, Emulsion & Epoxy paint, Zinc Silicate,
Thinners and Water Based Polymer Emulsion.
Reference: SEIAA letter no. SEIAA /GUJ/EC/5(f)/38/2009 dated 09/04/2009
Products : Details of various products
Sr.
No
Products Capacity , per
Month
1. Alkyd Resin 550 MT
2. Primer 600 MT
3. Synthetic Enamel 1000 MT
4. Emulsion Paints 2000MT
5. Epoxy paint 100 KL
6. Zinc Silicate 80 KL
7. Thinners 200 KL
8. Water Based Polymer Emulsion 2000 MT
Period: April 2016 to September 2016
Sr.
No.
Points Compliance Status
A. SPECIFIC CONDITIONS:
A-1: Water
1. No ground water shall be used for the
project. Water supply for the project shall be
sourced from GIDC.
No ground water shall be used for the project as
water supply for the project is sourced from
GIDC.
2 The industrial effluent of 36500 liters/day to
be generated shall be treated in the modified
effluent treatment plant and the treated
effluent shall be utilized for gardening &
plantation within the factory premises.
There shall be no waste water discharge
outside the factory premises.
We have provided effluent treatment plant
comprising of primary and secondary treatment
to treat and handle the existing effluent load.
The existing ETP is upgraded and modified to
treat and handle the total effluent load @
60KLPD. The treated wastewater is utilized on
land for irrigation purpose or reused for cooling
make–up. Hence, no waste water is being
discharged outside the factory premises.
3. Domestic waste water shall be discharged
into septic tank /soak pit system.
Domestic waste water shall be discharged into
soak pit /septic tank system.
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
6. There shall be no process emission from the
manufacturing process.
There is no process gas emission from the
manufacturing activity of water best emulsion
plant or any other industrial activity
7. Gaseous emission at work place shall be
controlled and kept below the limits
prescribed by the factories Act and Rules.
There records shall be maintained.
The work area monitoring is carried out monthly
through NABL approved laboratory to achieve the
norms prescribed as per factories act and rules.
Work area monitoring reports for the compliance
period are enclosed here as Annexure B.
8. The gaseous emissions and particulate matter
from various process units shall confirm to the
standards prescribed by GPCB. At no time, the
emission levels shall go beyond the stipulated
standards in the event of failure of pollution
control system adopted by the unit, the
respective unit shall not be restarted until the
control measure are rectified t to achieve the
prescribed standards.
We are using natural gas as a fuel in the boiler
and therefore, no need provided any air pollution
control system. There is no process gas emission
from the manufacturing activity.
We are maintaining the stack emission within the
GPCB limits. Regular monitoring of the same is
being carried out NABL approved laboratory.
The analysis reports for fuel gas emission are
enclosed here as Annexure C which shows that
the concentration of flue gas emission from stack
confirms to the GPCB standards.
A-3 : Solid Waste
9. The ETP sludge and process waste shall be
dried in sludge drying bed. It shall be packed
and stored in hazardous waste storage area
facility with pucca bottom with adequate
leachate collection facility.
The process waste and ETP sludge are dried in
sludge drying beds and after proper drying it is
packed into HDPE Bags and stored in the
hazardous waste storage shed.
The leachate collected from sludge drying beds is
sent back to the equalization tank for further
treatment.
We have provided isolated storage area @152 Sq.
meters having impervious flooring for the storage
of hazardous waste.
We have also provided proper arrangement for
the separation of contaminated and
decontaminated drums/container/barrels and
placed a specific identification sign board
(contaminated barrels and decontaminated
barrels) in our storage area.
10. Hazardous waste like ETP sludge, process We have obtained membership for the disposal
4. Unit shall provided metering facilitate the
inlet and outlet of the ETP and maintain
records for the same
We have provided the flow meter at the final
outlet of the Effluent Treatment Plant and also
maintaining log book for daily treated effluent
utilization quantity.
5. Adequate capacity of final treated water
guard pond shall be provided for storage
treated waste water during the monsoon
period.
We have provided treated effluent storage tank
having storage capacity @272.5KL, which is
adequate for storage of treated wastewater
during monsoon period.
A-2 : Air
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
waste & cotton waste shall be sent for
disposal at the TSDF of (Nandesari
Environment Control Limited)
NECL, Nandesari and the discarded
containers/ liners shall be sold only to the
registered recyclers after decontamination.
of filter paper & cotton waste by incineration and
ETP sludge & process waste at M/s. Nandesari
Environment Control Limited (NECL), Nandesari.
Empty drums are sold to the scrap vendors.
We have installed and commissioned barrels
Decontamination system within our premises
having impervious flooring and the wash water is
collected in a collection sump and then is
pumped to the equalization tank of Effluent
treatment plant for further treatment.
11. Used oil/ waste oil shall be sold only to the
registered recyclers as per the Authorization
of the GPCB.
Used oil is reused as a lubricant within premises
and remaining quantity is sold to MoEF approved
recyclers if required.
12. The unit must strictly comply with the rules
and regulation with regard to handling and
disposal of Hazardous waste in accordance
with the hazardous Waste (Management and
Handling) rules 2003.Authorization from the
GPCB must be obtained for collection /
treatment /storage /disposal of hazardous
waste.
We have already obtained Authorization under
Hazardous Waste rules, 2008 in our CC & A of
28/05/2013 for our all applicable categories of
hazardous waste i.e. ETP sludge (2.85 MTPM),
process waste (6.25MTPM), Cotton waste Used
oil (0.33 KLPM) & Discarded Containers,
Drums/Bags (1295& 12417 Nos./ Month). We are
also maintaining log book and register for the
generation and disposal of all categories of
hazardous waste. We have provided isolated
storage area @ 152 sq. m. having impervious
flooring for the storage of hazardous waste and
have provided proper arrangement for the
separation of contaminated and de
contaminated drums/container/barrels and
placed a specific identification sign board
(contaminated and de contaminated Barrels) in
our storage area.
We have obtained membership for the disposal
of filter paper & Cotton waste by incineration and
ETP sludge 7 Process waste at M/s. Nandesari
Environment Control Limited (NECL), Nandesari.
We regularly maintain the proper record for the
hazardous waste generation & disposal in Form3
and submit the Annual return in Form4 to GPCB.
13. The project management shall strictly comply
with the provisions made in Manufacture
Storage and Impact of Hazardous chemicals
Rules 1989 as amended in 2000 for handling of
hazardous chemicals. Necessary approval from
the Govt. Authorities shall be obtained before
commissioning of the project if applicable.
Complying
14. All Transportation of hazardous chemicals We are complying with the Motor Vehicle Act &
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
shall be as per the Motor Vehicle Act & Rules. Rules for transportation of Hazardous Chemicals.
15. Hazardous materials storage shall be at an
isolated designated location, bund/ dyke walls
shall be provided for storage tank for
hazardous Chemicals.
We have already provided an isolated area for
keeping the storage tank for Styrene. Dyke wall
has been made around the storage tanks.
16. AII transportation routes within the factory
premise shall have paved roads to minimize
splashes and spillages.
We have already provided necessary precaution
to control the spillages of the raw material which
are necessary to avoid contamination of land.
We have provided road within our premises, and
also provided impervious and RCC floor area at all
the storage area so there is no contamination of
land occurred. We are also doing regular cleaning
of the floor area and all the spillages collected
area and all the spillages collected are either
recycled back to the process or treated properly
as ETP waste.
A-4 : Safety
17. Necessary flameproof fitting shall be provided
in the manufacturing plant.
We have provided flameproof electric connection
in entire industrial plant. Proper earthling has
been provided in all the electrical equipment
wherever chemical handling is done.
18. Proper ventilation shall be provided in the
work place.
We have installed Air ventilation over the roof of
the water Based Emulsion plant.
19. Storage and use of toxic chemicals be
minimized to the “extent possible and all
necessary precaution shall be taken to
mitigate the risk generated out of it.
We have provided all the measures to minimize
the risk.
We are regularly carrying out safety audit for
industrial plant. We have also prepared risk
Assessment report and Disaster management
plan.
20. Acids shall be stored in MSRL tanks for safety
purpose. Storage of hazardous chemicals shall
be multiple small capacity tanks/ containers
instead of one single large capacity tank to
reduce the risk.
We have stored acid in the small
containers/barrels having maximum capacity of
220 liter.
21. AII venting equipment shall have vapor
recovery system. All the pumps and other
equipments where there is a likelihood of
leakage shall be provided with Leakage
Detection and repair (LDAR) system.
Provisions for immediate isolation of such
equipment in case of a leakage shall also be
made. The detector sensitivity shall be in ppm
levels.
There is no requirement for providing leak
Detection and Repair (LDAR) system.
There is no any gaseous emission from
manufacturing of new product, however we will
provide the gas detection system if required.
22. All the storage tanks shall be fitted with
appropriate controls to avoid any leakages.
Close handling system for chemicals shall be
We are talking all the possible measures to avoid
fugitive emissions and leakages.
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
provided. Double mechanical seals shall be
provided for pump/agitators for rectors for
reduction of fugitive emissions and leakages.
Solvent traps shall be installed wherever
necessary.
All the raw materials and chemicals are being
handled in a closed system. All the reactors are
closed and its manhole is also tightly close.
All the raw materials are stored in isolated
storage area and containers are tightly closed.
A precautionary measure is also being taken
while handling various organic/hazardous
chemicals.
We have also developed green belt within the
factory premises to control the fugitive emission
from spreading in to surrounding environment.
Dedicated pipelines are installed for transfer of
chemicals from respective storage tanks to
reactors in the production blocks.
The all pumps require for the handling and
transfer of the chemicals are fitted with
mechanical seal and provided with standby
arrangement.
Maintenance of the pipeline and valves & fittings
are carried out regularly to avoid any leakages.
We carry out regular monitoring of fugitive
emission in the work zone environment through
NABL approved laboratory to comply with the
norms specified as per the factory act & rules.
The copy of report is enclosed as Annexure B.
23. During material transfer, spillages shall be
avoided and garland drain be constructed to
avoid mixing of accidental spillages with
domestic waste and storm water drain
We have already provided necessary precautions
to control the spillages of the raw material which
are necessary to avoid contamination of land and
water.
We have provided the impervious and RCC, floor
area at all the storage area, process plant and
finished go-down so that there will be no
contamination of land occurred. We are also
doing regular cleaning of the floor area and all
the spillages are collected and either recycled
back to the processes or treated properly as ETP
waste.
We have provided garland drains on the
chemicals having possibility of creating any type
of hazardous situation. Dike wall are provided
with the garland drain to each storage tank to
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
avoid spillages and contamination.
We have also provided separate drainage line for
storm water and sewage.
24. Personal Protective Equipment shall be
provided to workers and its usage shall be
ensured and supervised
We provided proper PPE like hand gloves, safety
shoes, face mask, ear plug, etc. to the workers as
per requirements and it is supervised regularly to
ensured that they use it properly.
25. First Aid Box and required Antidotes for the
chemicals used in the unit shall be made
readily available in adequate quantity at all
the time.
The first Aid facilities and antidotes of hazardous
chemicals provided and several locations within
premises.
26. Training shall be given to all workers on safety
and health aspects of handling chemicals.
Training is given by our trainer to the workers for
pollution prevention and safety purpose at
regular time of interval.
27. Occupational health surveillance of the
workers shall be carried out on a regular basis
and records shall be maintained as per the
Factories Act and Rules. Pre-employment and
periodical medical examination for all workers
shall be undertaken as statutory requirement.
Occupational Health Surveillance program is
conducted regularly for all employees including
those which are engaged in handling of
hazardous substances.
The medical checkup of the employees is carried
out regularly and their records are maintained
properly.
We have appointed Dr. K.D. Balchandani,
M.B.B.S, who is attending our factory on
alternate day for the medical examination and
treatment of the employees.
The pre-employment medical checkup is being
done before employment and their records are
maintained.
28. The project management shall prepare a
detailed Disaster management plan (DMP)
forth project as per the guideline from
Directorate of Industrial Safety and Health.
We have prepared Disaster management plan
include all the scenario of natural catastrophe like
earth quake, cyclone, tsunami, flood, etc.
A-5: Noise
29. The overall noise level in and around the plant
area shall be kept well within the prescribed
standards by providing noise control measures
including acoustic insulation, hood, silencer,
enclosures vibration dampers etc. on all
sources of noise generation. The ambient
noise levels shall confirm to the standards
prescribed under the Environment
(Protection) Act and Rules. Workplace noise
We have installed low noise D.G. sets with latest
technology.
An adequate noise control measures are
provided to control the noise level and the ear
muffs/ear plugs are provided to the workers
working in the high noise area.
All the equipments/ machineries are installed as
per national/ international regulatory norms with
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
levels for workers shall be as per the Factories
Act Rules.
respect to noise generation for individual units.
The maintenance of machinery is carried out
regularly.
Proper oiling and lubrication is done to the
machineries at regular time of interval.
We are maintaining noise level as per Noise
Pollution (Regulation and Control) Rules, 2000
published by MoEF and EPA Rules, 1986.
A-6: Cleaner Production and Waste minimization
30. The company shall undertake following waste
minimization measures:
Metering and control of quantities of active
ingredients to minimize waste.
Reuse of by-product from the process as raw
materials or raw materials substitutes in other
process.
Use of automated and closed filling to
minimize spillages.
Use of close feed system into batch rectors.
Venting equipment through vapor system.
Use of high pressure houses for equipment
clearing to reduce wastewater generation
We are applying different type of cleaner
production technologies for waste minimization.
The liquid chemicals are transferred through
closed pipeline system.
We are maintaining good housekeeping within
premises.
We are reusing the treated wastewater for
cooling and gardening purpose to reduce fresh
water consumption.
We are doing mopping instead of washing
wherever possible.
A-7 Green Belt and Other plantation
31. The unit shall develop green belt premises as
per the CPCB guideline However if sufficient
land is not available within the premises. Unit
shall tie up with local agencies like gram
panchayat, schools, social forestry office etc.
for necessary plantation at available open land
in nearby area and submit an action plan for
plantation for the next three years to GPCB.
We have developed 19,700 m2 (43.42%)
greenbelt area within premises.
Growing some flowering plant and medicinal
plants by our gardener under the guidance of
Green brigade Committee. We will tie up with
GIDC association for additional green belt
development in GIDC area, open plot, road side,
etc.
B. GENRAL CODITIONS
32. In the event of failure of any pollution control In case of failure of pollution control equipment.
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
system adopted by the unit, unit shall be
safely closed down and shall not be restarted
until the desired efficiency of the control
equipment has been achieved.
The complete unit is being shut down and
resumed only after the said equipment is
rectified. We assure you that the same practice
will be followed in future also.
33. The management shall ensure that the unit
complies with all the environment protection
measures and risk mitigation measures/
safeguards proposed in the EIA report.
We are complying with Environmental
protection Measures and risk mitigation
measures/ safeguard proposed in the EIA report.
34. The unit shall undertake eco-development
measures including community welfare
program most useful in the project area for
the overall improvement of the environment.
The eco-development plan shall be submitted
to GPCB within three months of the receipt of
the EC.
Will be complied.
35. The applicant shall develop rain water
harvesting structures to harvest the runoff
water for recharge of ground water. Also
harvesting of surface as well as rain water
from the rooftops of the building proposed in
the project shall be undertaken and the same
water shall be used for the various activates of
the projects conserve fresh water.
We have developed rain water harvesting
structures. The photographs are attached as
Annexure F.
36. At no time, the emission shall exceed the
prescribed limits. In the event of failure of any
pollution control system adopted by the unit
shall be immediately put out of operation and
shall not be restarted until the desired
efficiency has been achieved.
In case of failure of pollution control equipment,
the complete unit is being shutdown and
resumed only after the said equipment is
rectified. We assure you that the same practice
will be followed in future also.
37. The applicant shall also comply with any
additional condition that may be imposed by
the SEAC or the SEIAA or any other competent
authority for the purpose of the environment
protection and the management.
Will be complied.
38. No further expansion or modifications in the
plant shall be carried out without prior
approval of the MoEF/SEIAA, as the case may
be. In case of deviations or alterations in the
project proposal from those submitted to
MoEF/SEIAA/SEAC for clearances fresh
reference shall be made to the SEIAA/SEAC to
assess the adequacy of condition imposd and
to add additional environmental protection
measures required if any.
We are operating our plant as per MoEF
clearance. In case of deviation/ alternation we
will obtain prior clearance from MoEF/SEIAA.
39. The project authorities shall earmark
adequate funds to implement the conditions
stipulated by SEIAA as well as GPCB along with
We have allotted adequate fund to meet with
the recurring cost of Environment Protection
Measures and Environmental Management
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
the implementation schedule for all the
conditions stipulated herein. The funds so
provided shall not be diverted for any other
purpose.
system.
40. The applicant shall inform the public that the
project has been accorded environmental
clearance by the SEIAA and that the copies of
the clearance letter are available with the
GPCB and may also be seen at the Website of
SEIAA/SEAC/GPCB. This shall be advertised
within seven days from the date of clearance
letter, in at least two local newspapers that
are widely circulated in the region, one of
which shall be in the Gujarati language and the
other in English. A copy each of the same shall
be forwarded to the concerned regional office
of the ministry.
We had already published advertisement in
newspaper informing the public that our project
has been accorded environmental clearance by
the SEAC.
41. It shall be mandatory for the project
management to submit half-yearly compliance
report in respect of the stipulated prior
environmental clearance terms and conditions
in hard and soft copies to the regulatory
authority concerned, on 1st June and 1st
December of each calendar year.
We regularly submit our six monthly compliance
report of EC to concerned authorities.
42. The project authorities shall also adhere to the
stipulation made by the Gujarat pollution
Control board.
We have obtained Consent to Operate
(CTO/CC&A) from GPCB vide order No. AWH-
54396, dated 28/05/2013, which is valid up to
10/02/2018. We are adhering to the stipulations
made by GPCB and complying with all the
conditions prescribes on the consent to operate
(CTO/CC&A). we are enclosing copy of CCA
granted by GPCB & Compliance of as Annexure
D.
43. The project authorities shall inform the GPCB,
Regional office of MoEF and SEIAA about the
date of financial closure and final approval of
the project by the concerned authorities and
the date of start of the project
Complied
44. The SEIAA may revoke or suspend the
clearance, if implementation of any of the
above conditions is not found satisfactory.
Noted and Agreed
45. The company in a time bound manner shall
implement these conditions.
The SEIAA reserves the right to stipulate
additional condition, if the same is found
necessary. The above condition will be
enforced, interlay under the provisions of the
We have obtained Consent to operate (CCA) vide
order No. 53496, dated 28/05/2013 which is
valid up to 10/02/2018.
We are complying all conditions specified by
GPCB under consent order and all the
application provisions of the water (Prevention
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
Water (Prevention & Control of pollution) Act-
1974, Air (Prevention & Control of pollution)
Act 1981, the Environment (Protection) Act
1986. Hazardous Waste (Management and
Handling) Rules 2003 and the Public Liability
Insurance Act, 1991 along with their
amendments and rules.
& Control of Pollution) Act 1974, Air (Prevention
& Control of Pollution) Act 1981, the
Environment ( Protection) Act, 1986, Hazardous
Waste (Management, handling and
Transboundary Movement) rules, 2008.
We have also obtained PLI policy
(1517322712000012) from Reliance General
Insurance Company Limited for the total liability
of Rs.15 Crores as per requirement under the
public liability Insurance Act, 1991.
The copy of PLI Policy is enclosed as Annexure E.
46. The environmental Clearance is valid for five
years from the date of issue.
Noted
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
ANNEXURES
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
Annexure A: Details of Production and Resource Utilization
� Production: Month and
Year
Primer,
MT
Synthetic
Enamel,
MT
Emulsion
Paints,
MT
Alkyd
Resins,
Mt
Water
Based
Polymer
Emulsions,
MT
Epoxy
Paint,
KL
Zinc
Silicate,
KL
Thinner,
KL
April’16 600 1000 1915 513.5 1998 98 65 198
May’16 600 1000 1481 549 1992 95 45 198
June’16 570 1000 1501 418.1 1940 98 26 198
July’16 550 1000 1486 433.6 1958 95 35 198
August’16 600 1000 1775 550 2000 98 35 198
September’16 600 1000 2000 523 2000 98 55 200
Quantity as per
CCA
Granted/month
600
1000
2000
550
2000
100
80
200
� Water Consumption and Wastewater Generation:
Month and Year Water Consumption, KL Wastewater Generation, KL
April’16 4275 488
May’16 4240 520
June’16 3005 692
July’16 3307 624
August’16 3970 798
September’16 4007 838
Quantity as per CCA
Granted/day
145.58 36.5
� Hazardous Waste Generation:
Month and
Year
ETP
Sludge,
MT
Process
waste,
MT
Filter
Paper,
kg
Cotton
Waste,
kg
Discarded
Containers/bags,
Nos.
Used
Oil, lit
April’16 2.7 1.0 0.05 0.01 1150 0
May’16 2.7 1.0 0 0.01 1175 0
June’16 2.7 1.0 0 0.01 1240 0
July’16 2.7 1.0 0 0.01 1110 0
August’16 2.7 1.0 0 0.01 1350 0
September’16 2.7 1.0 0. 0.01 1310 0
Total 16.2 6.0 0.05 0.06 7335 0
Quantity as per
CCA
Granted/month
2.85
6.25
1.2
0.20
13712
0.33
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
� Hazardous Waste Disposal:
Month and
Year
ETP
Sludge,
MT
Process
waste,
MT
Filter
Paper,
kg
Cotton
Waste,
kg
Discarded
Containers/bags,
Nos.
Used
Oil, lit
April’16 9.810 0 0 0 1100 0
May’16 3.455 0 0 0 1120 0
June’16 0 0 0 0 1100 0
July’16 0 0 0 0 1130 0
August’16 0 0 0 0 1100 0
September’16 0 0 0 0 1100 0
Total 13.265 0 0 0 6650 0
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
ANNEXURES B: Work Place Area Monitoring Reports
(As per Submitted Physical Copy)
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
ANNEXURES C: Flue Gas Emission Monitoring Reports
(As per Submitted Physical Copy)
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
Annexure D: Copy of CCA & Its Compliance
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
CC&A Compliance:
Sr.
No.
Consent condition Compliance
status
1. Consent order AWH-54396, date of issue 28/05/2013 Noted
2. The consent shall be valid up to 10/02/2018 for use of outlet for the
discharge of trade effluent and emission due to operation of industrial
plant for manufacture of the following product.
Sr.
No.
Product Quantity
MT/Month
1 Primer 600
2 Synthetic Enamel 1000
3 Emulsion Pains 2000
4 Alkyd Resin (Intermediate product) 550
5 Water Based polymer emulsion 2000
Industrial Paint
6 Epoxy paint 100KL/M
7 Zinc Silicate 80KL/M
8 Thinner 200KL/M
Complying
(3) Condition under the Water Act
3.1 The quantity of industrial effluent shall not exceed 36.5KL/Day. Complying
3.2 The quantity of the domestic waste water (sewage) shall not exceed
11.3 KL/Day.
Complying
3.3 Trade Effluent
3.3.1 The industrial effluent shall confirm the following parameter
Sr.
No.
Parameter GPCB Norms
1 pH 6.5-8.5
2 Temperature 40˚C
3 Suspended Solids 100 mg/l
4 Oil & Grease 10 mg/l
5 Phenolic compounds 1.2 mg/l
6 Cyanides 0.2 mg/l
7 Fluorides 1.5 mg/l
8 Sulphide 2 mg/l
9 Total chromium 1 mg/l
10 Hexavalant chromium 0.1 mg/l
11 Copper 3 mg/l
12 Lead 0.1 mg/l
Complying
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
13 Mercury 0.01 mg/l
14 Nickel 3 mg/l
15 Zinc 2 mg/l
16 Cadmium 2 mg/l
17 BOD (5 days at 20˚c) 30 mg/l
18 COD 100 mg/l
19 Chlorides 600 mg/l
20 Sulphates 1000 mg/l
21 Total Dissolved Solids 2100 mg/l
22 Free Ammonia 5 mg/l
23 % Sodium 60 mg/l
24 Bio-Assay Test 90% survival of fish
after 96 hrs in 100%
effluent
25 Total Heavy Metals 7.0 mg/l
3.3.2 The treated effluent conforming to the standers shall be utilized for
gardening/ plantation within the industries premises only.
Complying
3.3.3 Domestic effluent shall be disposed off through septic tank/ soak pit
system or it shall be treated along with industrial effluent or it shall
treated separately to conform to the following standards and shall
discharged on land for plantation or gardening within the factory
premises.
BOD( 5 days at 20 ˚C ) Less than 20 mg/l
Suspended solids Less than 30 mg/l
Residual chlorine Minimum 0.5 ppm
Complying
4 Condition under the Air Act
4.1 The following shall be used as fuel in Thermic Fluid Heater/ G.D.G set
respectively
Sr.
No.
Fuel Quantity
1 CNG 516 m³/hrs
2 HSD 240 LITS/hrs
3 LDO 195 LITS/hrs
Complying
4.2 The applicant shall install & operate comprehensive adequate air
pollution in order to achieve prescribe norms control system to as to
achieve standards
Complied
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
4.2.1 The fuel gas emission through stack attached to boiler/ furnace shall
conform to the following standards:
Stack
No.
Stacked
Attached
Stack
Height
parameter Permissible
Limit
1 Thermic
Fluid heater-
3,5,6
30 m
Common
Stack
Particular
Matter
SO₂
NOₓ
150mg/NM³
100 ppm
50 ppm
2 Thermic
Fluid heater-4
30m Particular
Matter
SO₂
NOₓ
150mg/NM³
100 ppm
50 ppm
3 Boiler- 1,2 &
3 (2.0 TPH-
each)
30m Particular
Matter
SO₂
NOₓ
150mg/NM³
100 ppm
50 ppm
4 D.G. sets-2
No’s
(250KVA)
Each
14m each Particular
Matter
SO₂
NOₓ
150mg/NM³
100 ppm
50 ppm
5 D.G. set
(125KVA)
30m Particular
Matter
SO₂
NOₓ
150mg/NM³
100 ppm
50 ppm
Complying
4.2.2 There shall be no process emission from the manufacturing process as
well as any other ancillary process.
Complying
4.2.3 The concentration of the following parameters in the ambient air within
the premises of the industry shall not exceed the limits specified
hereunder.
Parameter Permissible limit
Annual 24 Hrs Avg
Particulate matter
10(PM 10)
60 µg/m³ 100 µg/m³
Particulate matter
2.5(PM 2.5)
40 µg/m³ 60 µg/m³
Oxides of sulphur 40 µg/m³ 80 µg/m³
Oxide of Nitrogen 50 µg/m³ 80 µg/m³
Complying
4.2.4 The applicant shall operate industrial plant / air pollution control
equipment very efficiently and continuously so that the gaseous
emission always conforms to the standards specified in condition
no.4.4.1, 4.2.2 & 4.4.3 above.
Complying
4.2.5 The consent to operate the industrial plant shall lapse if at any time the
parameters of the gaseous emission are not within the tolerance limits
Noted
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
specified in the condition no.4.2.1 and 4.2.3 above
4.3 The applicant shall provide portholes, ladder, platform, etc. at
chimney(s) for monitoring the air emission and the same shall be open
for inspection to/and for use of board’s staff. The chimney(s) vents
attached to various sources of emission shall be designed by numbers
such as s-1, s-2, etc. and these shall be painted/ displayed to facilitate
identification.
Complying
4.4 The industry shall take adequate measures for control of noise levels
from its own sources within the premises so as to maintain ambient air
quality standards in respect of noise to less than 75db (a) during day
time and 70 db (a) during night time. Daytime is reckoned between 6
a.m. and. 10 p.m. and nighttime is reckoned between 10 p.m. and 6 a.m.
Complying
5 GENRAL CONDITIONS:
5.1 Any changes in personnel, equipment or working condition as
mentioned in the consents from/ order should immediately be
intimated to this board.
Noted
5.1.2 Applicant shall also comply with the general condition as mentioned in
the consents from/ order should immediately be intimated to this
Board.
Compiled
6 Authorized for the Management & Handling of hazardous Waste Form-2
(See rule 3(c) & 5 (5) )
Number of Authorization: AWH-54396 Date of issue: 28/05/2013
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
6.1 M/s. Bee pee Coating Pvt. Ltd. Is hereby granted an authorization to
operate facility for following hazardous wastes on the premises situated
at plot No. 443(Part), GIDC Estate, P.B. No. 50, Vithal Udhyognagar.
Dist-Anand-388121
Sr.
No.
Waste Quantity Category Facility
1 ETP Waste 2.85 MT/M 34.3 Collection,
Storage,
Transportation,
Disposal at
TSDF
2 Used oil 0.333 KL/M 5.1 Collection,
Storage,
Transportation,
Disposal by
selling to
Registered
3 Discarded
Containers/bag
1295
Nos./Month
12417
Nos./Month
33.3 Collection,
Storage,
Transportation,
Disposal by
selling to
Registered
Reprocesses.
4 Filler paper
Waste
0.7 MT/M 23.1 Collection,
Storage,
Decontamination
At CHWI
5 Cotton waste 0.2 MT/M 23.1 Collection,
Storage,
Decontamination
At CHWI
6 Process waste 6.25 MT/M 21.1 Collection,
Storage,
Decontamination
At CHWI
Complying
6.2 The authorization is granted to a facility for collection, storage, within
the factory premises transportation and disposal to TSDF at NECL-
Nandesari for landfill and incineration.
Noted
6.3 The authorization is subject to the conditions stated below and such
other conditions as may be specified in the rules from time to time
under the Environment(Protection) Act-1986
Noted
6.4 The authorization shall be in force for a period up to 10/02/2018 Noted
6.5 Terms and Condition of Authorization
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
6.5.1 The applicant shall comply with the provision of the EPA-1986 and rules
made there under.
Complying
6.5.2 The authorization shall be produced for inspection at the request of an
officer authorized by GPCB.
Noted
6.5.3 The authorization shall not rent, Lend, sell, and transfer of otherwise
transport the hazardous waste without obtaining prior permission of the
GPCB.
Noted
6.5.4 Any unauthorized changes in personnel, equipment or working
condition as mentioned in the authorization order by the person
authorized shall constitute a breach of the authorization.
Noted
6.5.5 It is the duty of the person to take prior permission of the GPCB to close
down the facility.
Noted
6.5.6 An applicant for the renewal of an authorization shall be made as laid
down in rule 5(7) (ii)
Noted
6.5.7 Industry shall have to display the relevant information with regard to
hazardous waste as indicated in the court’s order in W.P. No.657 of 1995
dated 14th
October 2003.
Complying
6.5.8 Industry shall submit annual report within 15 day and sub squint by 31st
January every year.
Complying
6.5.9 Industry shall have to manage waste oil, discarded containers etc.,
process waste as per Amended Rules-2003 and apply Authorization/
submit details for all applicable waste per amended Rules 2003 with 15
days.
Noted
And
Agreed
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
Annexure E: Copy of PLI Policy
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Phone: (02692) 236140, 236207, 236334, Fax (02692) 236190
Annexure F: Photographs of Rain Water Harvesting Scheme
Compliance of Environmental C
09/04/2009) Period: from April’16 to September’ 16
Regd. Office: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand. Gujarat 388121
Compliance of Environmental Clearance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
Period: from April’16 to September’ 16
: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand.
learance (REF. NO: SEIAA/GUJ/EC/5(f)/38/2009, Dated:
: Plot No. 443 (Part), GIDC Estate, Post Box No. 50, Vithal Udyognagar, Dist. Anand.