competitive tarriff bidding
TRANSCRIPT
TOTA
L 341
94MW
INSTA
LLED C
APACITY
MORE THAN 3
DECADES OF O
&M EXPERIENCE
BETTER N
TPC P
LF vs
NATIO
NALOVER 25
000 S
KILLED M
ANPOWER
SOUND FINANCIA
L STR
ENGTH
INHOUSE R
&D (NETR
A)
FIRST M
AHARATNA OF I
NDIA
SASAN1.19
2.12
TILAIYA1.85
2.40 ?
Roadmap To carry outBest Competitive Tariff
Bidding
NTPC TandaAmit Nayak(TMD)Praveen Prajapati (BMD)Ravi Pal Singh (OPN)Shahnawaz Akhtar Khan
(TMD)
• Tariff determined through the process of competitive bidding.• Procurer can invite bids for purchase of power.• Contract for supply of power is awarded based on the lowest
tariff.• Supply of power by the generating company could be with or
without any fuel and specific location.
TARIFF BASED COMPETITIVE BIDDING
Case-II Bidding
Bidding Mechanism
Case-I Bidding
Not specified.Developer is responsible for all the clearances.
PPA for the portion or the total power generated.
Higher risk for developerLower risk for procurer
Provided by Procurer.Procurers (SPVs) responsible for all the clearances.
PPA for the portion or the total power generated.
Higher risk for procurerLower risk for developer
One part tariffMedium term
Two part tariffLong term
Optional
Capacity Charges Energy Charges
Non Escalable
(Firm price)
Escalable (Base price with index)
Base price (With Index) NQHR
Index notified by CERC
•Tariff in INR only-EXCEPT FERV on imported coal in Case-II
TARIFF STRUCTURE
• Lower Project Cost.
• Competitive Tariffs.
• Higher Benchmark of performance ;Heat rate, Auxiliary Power consumption, Availability etc.
• Induce market driven pricing mechanism.
BENEFITS OF THE COMPETITIVE BIDDING
ULTI
MAT
ELY
BENE
FIT
TO
CONS
UMER
RESEARCH AND FINDINGS
Mundra Tata (2.265)
K’patnam Reliance(2.336)
Tilaiya Reliance(1.77)
Sasan Reliance(1.196)
Girye
Tadri
Cheyyur
Sundargarh
Akaltara
UMPPs Allotted
UMPPs yet to be Allotted
EFFECT OF FUEL COST
≈65%
PROJECT Eqpt. Supplier
AGENCY
FUEL LINKA
GE
REMARK
Sasan-660X6(1.196)
Shanghai Electric
Reliance Indian Allocated capacity 707 MnT requirement 350 MnT
Tilaiya-660X6(1.77)
Shanghai Electric
Reliance Indian Coal mine allotted of total 1.23 Bn Tonne
Krishnapattanam-660X6(2.336)
Shanghai Electric
Reliance Imported Coal mines acquired by Reliance in Indonesia
Mundra-800X5(2.265)
DoosanToshiba
TATA Imported Coal blocks Acquired in Indonesia
EFFECT OF FUEL COST contd…
In spite of higher calorific value, generation with imported coal is costlier.
PARAMETER RATEEscalation Rate-Domestic Coal (Rs./kWh) 6.01%
Escalation Rate-Imported Coal Variable Cost (Rs./kWh)
Coal Sub-component 16.40%
Transportation Sub-component 16.23%
Inland handling Sub-component 5.11%
CERC RATES OF ESCALATION
Acquisition of coal mines will rid the developer from escalation component (6.01 %) of coal
BOILER-TURBINE-GENERATOR (BTG) EQUIPMENTS COST
•NTPC relies heavily on BHEL for supply of its BTG packages. Since BHEL is itself over burdened hence delay in delivery is inevitable.•Chinese BTG equipments are about 20% cheaper than BHEL.
EQUIPMENT SUPPLIER PROJECT COST PER MW EFFECT
Indian equipment(BHEL) 4.5-5.0 Crore 25-30% Reduction by using Chinese EquipmentChinese equipment 3.5-4.0 Crore
As per past record Chinese suppliers deliver the BTG
equipment well within scheduled time period,
thereby cutting down the delay costs
HIGHER CAPACITY WITH NEW TECHONOLOGY
LIMITATIONS
•Develop materials to withstand the tough operating conditions.•Developing technologies for castings, forgings and welding.•Component testing facility for corrosion/erosion with Indian coals.
ADVANTAGES
•Reduction in heat rate.•Higher efficiency.•Low APC.•Reduction in annual overhauling cost.•SOX/NOX reduction.
LOCATION EFFICIENCY CAPACITY MS/HRH MS PRESSURE HEAT RATE APCTANDA 32.00 110 535/535 138 2700 12.0
UNCHAHAR 35.70 210 535/535 152 2410 8.5
SINGRAULI 36.60 500 538/538 170 2390 6.0
SIPAT 39.56 660 (SC) 537/565 247 2174 5.0
LUNEN, GERMANY 45.60 800 (USC) 600/610 280 1885 4.2
YUHUAN, CHINA 46.00 1000 (USC) 600/600 262 1869 4.0
110 210 500 660 (SC) 800 (USC)
1000 (USC)
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
APC VS CAPACITY
APC VS CAPACITY
110 210 500 660 (SC)
800 (USC)
1000 (USC)
0
500
1000
1500
2000
2500
3000
HEAT RATE vs CAPACITY
HEAT RATE vs CAPACITY
HIGHER CAPACITY WITH NEW TECHONOLOGY
EFFECT OF FINANCIAL FACTORS
Normative ratio of debt/equity is 70/30, changing it to 80/20 or 75/25 marginalise the tariff cost
PROJECT TARIFF WINNER DEBT/EQUITY RATIO
Sasan UMPP 1.196 Reliance Power 75/25Krishnapattam UMPP 2.336 Reliance Power 75/25Mundra UMPP 2.265 Tata Power 75/25
Bara 3.02Jaiprakash Associates 75/25
Karchana 2.97Jaiprakash Associates 75/25
Bhaiyathan 0.81 India Bulls 75/25NORMATIVE 70/30
DEBT/EQUITY RATIO
EFFECT OF FINANCIAL FACTORS contd...
Normative financing period for power project loans is 10-12 years, increasing the period, pulls down the tariff rates.
PROJECT TARIFF WINNER YEARS OF FINANCING
Sasan UMPP 1.196 Reliance Power 18
Krishnapattam UMPP 2.336 Reliance Power 18
Mundra UMPP 2.265 Tata Power 18
Bara 3.02 Jaiprakash Associates 15
NORMATIVE 10-12
LONG TERM LOAN REPAYMENT
EFFECT OF FINANCIAL FACTORS contd...
INTEREST RATE
•Smart usage of Hedging to shield against foreign exchange risk
Cheaper loan from Domestic/Foreign lenders
EFFECT OF FINANCIAL FACTORS contd...
LOAN COMPONENT COST OF CAPITAL (%)
DOMESTIC LOANInterest rate 8
8Foreign exchange risk 0Compliance cost 0
FOREIGN LOANInterest rate 4
6Foreign exchange risk 1Compliance cost 1
FUNDS MANAGEMENT OBSERVATIONNTPC As per balance sheet 2009-2010(approx)Total Profits : 8000 CroreProfits From O&M : 5000 CroreInterest from surplus fund : 3000 CroreAs per DPE guidelines:• 30% surplus funds can be invested in public sector mutual fund.• In case of Short Term Deposits with Banks, at least 60% of total deposits should be placed with Public sector Banks• Similar trend shown by 2010-2011 balance sheet as well.
Reliance Power The IPO gets oversubscribed 69 times and total funds of Rs 11,600-crore which was floated in market.
EFFECT OF FINANCIAL FACTORS contd...
UTILIZATION OF BY-PRODUCTS
BY-PRODUCT UTILIZATION REMARKS
Fly Ash Cement/brickReliance Power is expected to earn Rs 450 Cr per annum by selling ash at the rate of Rs 300/- per tonne
Carbon Emissions Carbon Credits
Reliance Power is expected to earn Rs 1000 Cr per annum by Carbon Credit at current CER rate
Flue Gas Bio-DieselExtraction of Bio fuel can be to be sold in open market or can be used as secondary fuel in plant
ROADMAP
PARTICULARS VALUECapacity 4000 MWAvailability 85 %Generation (Ex-Bus) 28291 MUS Heat rate 2450 kCal/kWhSpecific coal consumption 0.7 KG/KWH APC 5.00 %
ASSUMPTIONS
Financial ParametersCapital Cost 5.00 Rs.Cr./MWReturn on Equity 16.00 %Rate of Interest on Loans 8.00 %Depreciation rate 5.28 %Interest rate on working capital 10.00 %Price & GCV of FuelsLanded Coal Price 700 Rs/MTCoal GCV 3500 kCal/kgOil Price 18000 Rs/KL Oil GCV 10000 kCal/litre
ASSUMPTIONS
FINANCIAL RESTRUCTURING
Increase the Debt/Equity ratio from conventional 70/30 to 80/20 or 75/25
Increasing the period Normative payback period of financing from 10-12 years.
Boost performance to obtain cheaper loans both from foreign as well as domestic investors
COMPONENT MODIFICATION paise/kWhDebt/Equity ratio 70/30 to 75/25 2.830Interest rate By decreasing 1% 5.300Payback period 10 years to 15 years 13.500
COMPONENT MODIFICATION paise/kWhDebt/Equity ratio 70/30 to 75/25 2.830Interest rate By decreasing 1% 5.300Payback period 10 years to 15 years 13.500Chinese BTG Equipment 1500 Cr cheaper than BHEL 2.662
EFFICIENCY CAPACITY HEAT RATE APC
PER UNIT COAL COST
EFFECT OF APC ON TARIFF
SAVINGS BY USING 800 MW USC IN PLACE OF 660 SC
DUE TO HEAT RATE
DUE TO APC
TOTAL SAVING
% MW kcal/kWHr % paisa
32.00 110 2700 12.0 51.429 19.8206
ALREADY RUNNING 35.70 210 2410 8.5 45.905 14.0396
36.60 500 2390 6.0 45.524 9.9103
39.56 660 (SC) 2174 5.0 41.410 8.25865.504 1.3214 6.826
45.60 800 (USC) 1885 4.2 35.905 6.9372
46.00 1000 (USC) 1869 4.0 35.600 6.6069 5.809 1.6517HIGHER CAPACITY WITH NEW TECHONOLOGYAssumptions: Calorific Value : 3500 kCal/kg.
COMPONENT MODIFICATION paise/kWhDebt/Equity ratio 70/30 to 75/25 2.830Interest rate By decreasing 1% 5.300Payback period 10 years to 15 years 13.500Higher capacity with new technology
Opting 800 MW units based on USC instead of 660 MW SC units 6.826
COMPONENT MODIFICATION paise/kWhDebt/Equity ratio 70/30 to 75/25 2.830Interest rate By decreasing 1% 5.300Payback period 10 years to 15 years 13.500Higher capacity with new technology
Opting 800 MW units based on USC instead of 660 MW SC units 6.826
Man/MW ratio 0.86 to 0.42 6.221
COMPONENT MODIFICATION paise/kWhDebt/Equity ratio 70/30 to 75/25 2.830Interest rate By decreasing 1% 5.300Payback period 10 years to 15 years 13.500Higher capacity with new technology
Opting 800 MW units based on USC instead of 660 MW SC units 6.826
Man/MW ratio 0.86 to 0.42 6.221Inland acquisition of coal mines Freedom from Escalation component of coal i.e. 6% 8.871
COMPONENT MODIFICATION paise/kWhDebt/Equity ratio 70/30 to 75/25 2.830Interest rate By decreasing 1% 5.300Payback period 10 years to 15 years 13.500Higher capacity with new technology
Opting 800 MW units based on USC instead of 660 MW SC units 6.826
Man/MW ratio 0.86 to 0.42 6.221Inland acquisition of coal mines Freedom from Escalation component of coal i.e. 6% 8.871
Working capital cost
Coal Stock 45 days to 15 days reserve 0.360
Oil Stock 60 days to 15 days reserve 0.023Spares 1% to 0.5 % of Capital Cost 0.353
COMPONENT MODIFICATION paise/kWhDebt/Equity ratio 70/30 to 75/25 2.830Interest rate By decreasing 1% 5.300Payback period 10 years to 15 years 13.500Higher capacity with new technology
Opting 800 MW units based on USC instead of 660 MW SC units 6.826
Man/MW ratio 0.86 to 0.42 6.221Inland acquisition of coal mines Freedom from Escalation component of coal i.e. 6% 8.871
Working capital cost
Coal Stock 45 days to 15 days reserve 0.360
Oil Stock 60 days to 15 days reserve 0.023Spares 1% to 0.5 % of Capital Cost 0.353
Oil consumption reduction 1 ml to 0.5 ml/kWh 1.620
COMPONENT MODIFICATION paise/kWhDebt/Equity ratio 70/30 to 75/25 2.830Interest rate By decreasing 1% 5.300Payback period 10 years to 15 years 13.500Higher capacity with new technology
Opting 800 MW units based on USC instead of 660 MW SC units 6.826
Man/MW ratio 0.86 to 0.42 6.221Inland acquisition of coal mines Freedom from Escalation component of coal i.e. 6% 8.871
Working capital cost
Coal Stock 45 days to 15 days reserve 0.360
Oil Stock 60 days to 15 days reserve 0.023Spares 1% to 0.5 % of Capital Cost 0.353
Oil consumption reduction 1 ml to 0.5 ml/kWh 1.620SUB TOTAL-1 45.904
NTPC quoted in Sasan 212.000After considering above mentioned factors 166.096
TREASURYNegotiate with DPE for more liberal financial investment regulations to:•Effectively utilize the dead surplus funds.•Short term earnings from project funds.
ALTERNATE REVENUE SOURCES
• Fly ash used in production of ash brick and cement.
• Setting up Cement factory near station to utilize fly ash and wagon siding.
• Certified Emission Reduction (CER)• CERs could be traded in the Market.
COMPONENT MODIFICATION paise/kWhDebt/Equity ratio 70/30 to 75/25 2.830Interest rate By decreasing 1% 5.300Payback period 10 years to 15 years 13.500Higher capacity with new technology
Opting 800 MW units based on USC instead of 660 MW SC units 6.826
Man/MW ratio 0.86 to 0.42 6.221Inland acquisition of coal mines Freedom from Escalation component of coal i.e. 6% 8.871
Working capital cost
Coal Stock 45 days to 15 days reserve 0.360
Oil Stock 60 days to 15 days reserve 0.023Spares 1% to 0.5 % of Capital Cost 0.353
Oil consumption reduction 1 ml to 0.5 ml/kWh 1.620SUB TOTAL-1 45.904
NTPC quoted in Sasan 212.000After considering above mentioned factors 166.096
ALTERNATE REVENUECarbon credits as mentioned by Reliance (Rs. 200 Cr. Per annum) from Sasan plant 6.720Selling of ash at the rate of Rs. 300 per tonne 5.840treasury functions 20 % against 8 % rate of return on 16000 Crore 6.600
COMPONENT MODIFICATION paise/kWhDebt/Equity ratio 70/30 to 75/25 2.830Interest rate By decreasing 1% 5.300Payback period 10 years to 15 years 13.500Higher capacity with new technology
Opting 800 MW units based on USC instead of 660 MW SC units 6.826
Man/MW ratio 0.86 to 0.42 6.221Inland acquisition of coal mines Freedom from Escalation component of coal i.e. 6% 8.871
Working capital cost
Coal Stock 45 days to 15 days reserve 0.360
Oil Stock 60 days to 15 days reserve 0.023Spares 1% to 0.5 % of Capital Cost 0.353
Oil consumption reduction 1 ml to 0.5 ml/kWh 1.620SUB TOTAL-1 45.904
NTPC quoted in Sasan 212.000After considering above mentioned factors 166.096
ALTERNATE REVENUECarbon credits as mentioned by Reliance (Rs. 200 Cr. Per annum) from Sasan plant 6.720Selling of ash at the rate of Rs. 300 per tonne 5.840Treasury functions 20 % against 8 % rate of return on 16000 Crore 6.600
SUB TOTAL-2 19.160After considering income from alternate sources 146.936
EXPLORATION OF ALLOTTED COAL BLOCKS
•Emphasis on acquiring offshore coal blocks for secure and cheaper fuel supply for long term.
•It helps to reduce tariff bids where coal blocks are not allocated it slashes the tariff at time of bidding.
• Allocated coal mines can be over explored and excess amount of coal may be used for feeding other nearest or starving stations.
MERCHANT POWER IN OPEN MARKET
Some states (eg. Chattisgarh) are floating bids for procuring only a proportion of total capacity of generated power. Sell of the PPA power at break even tariff and make up for it by selling the merchant power in open market.
Project Capacity(MW) Winner Bid Price
Bhaithan 1320 India Bulls 0.81
CRUSHER HOUSE AT COAL MINE• Effective utilization of Wagons.• Preventing transportation of Stones.• Prevention of Coal pilferage.• Lesser Land required for CHP.
The available power of the hydro system can be roughly estimated as:
Head X Flow X 9.81 = kWIn case of Sipat Stage-I CW flow = 2 X 35000 m3/hr
= 19.444 m3/sTaking Head = 2.0 mtrHence Available Power= 19.444 X 2.0 X 9.81
= 381.491 kW
= 0.400 MW (APPROX.)
CW HYDRO POWERSet up mini or micro hydro power plant from the huge amount of water required for cooling in the condenser.
AVOIDING DELAYS• Reduce overall project cost• Foregone Profits• Enhanced market reputation.
ERECTION SIMULATOR• To build a Dedicated Erection Expert
Team in NTPC.
PERMANENT SHED(CANOPY) IN CHP• Coal can be protected from rain.• Avoid Choking during rainy season.
MISCELLANEOUS• Vapor absorption refrigeration using flue gases.
• Economy of scale in procurement
TYPE LOCATION STATE ALLOTTED TO
Costal Mundra Gujrat Tata power
Krisnapatanam
A.P. Reliance power
Tadri Karnataka --
Girye Maharashtra --
Cheyyur Tamil nadu --
Pit head Sasan Madhya pradesh
Reliance power
Tilaiya Jharkhand Reliance power
Sundergarh Orissa --
Akaltara Chhattisgarh --
CONCLUSION
• Cut down any of the possible extravagance.
• Possible areas may be higher capacity units, fuel cost and inventory cost.
• Avert any delay costs and boost the company market reputation.
"It is not the strongest of the species that survives, nor the most intelligent; it is the one that is most adaptable to change."
-- Charles Robert Darwin (1809–82)
THANK YOU
Strategy LOWCOST
Cement factory for ash utilization
Strategic Pit-Head & Coastal Station Shed In Coal Yard
Acquire Coal Mines Erection simulator Exhaustive pooling of spares
Crusher house at coal mines
Faster Execution of Projects Coal Stock reduction
Reduce Man-MW Higher capacity units (SC & USC) Treasury functions
Debt/Equity ratio Cheaper loans Payback period
Low Cost Power Generation
QUERIES
Merchant power Carbon credits Economy of scale