comparative study on precast and cast in-situ concrete ... · recommended to adopt precast concrete...
TRANSCRIPT
1
Comparative study on precast and cast in-situ concrete structures in
Rwanda.
GATETE Seleman
Corresponding author: GATETE Seleman,
Email:[email protected]
Abstract
The main objective of the present work is to
determine the comparative study between
precast concrete and cast in situ concrete on
some properties of concrete and determine
precast and merits of precast structure where
my part is to identify various factors which
gives signification importance to precast
fabrication with respect to cast in situ by
showing the importance of precast in today
is world in especially with reference to the
results show that the strength of cast in situ
concrete is 21.83 N/mm2 compared to
precast which has 24.53 N/mm2 means there
is a little bit different in strength and is
better to use precast one because the
construction will be quick and curing was
done on factory that led to high compressive
strength. The obtained results will help the
constructors to choose the appropriate
concrete for any structure.
Keywords: Precast concrete, cast in situ
concrete, compressive Strength
1. Introduction
Concrete is a mixture of cement and water
binds together fine and coarse particles of
inert materials known as aggregates, it is
readily seen that by varying the proportions
of the ingredients innumerable combinations
are possible. These combinations result in
concrete of different qualities. When the
cement has hydrated, the plastic mass
changes to a material resembling stone. This
period of hardening is called curing, which
three things are required: time, favorable
temperatures and the continued presence of
water. The durability of concrete is of vital
importance regarding the life cycle cost of
the structure, which includes not only the
initial cost of the material and labour but
also the cost of maintenance and repair. The
durability of concrete is therefore defined as
2
its ability to resist weathering action,
chemical attack, abrasion, and other forms
of deterioration. Concrete has much higher
level of fire resistance than other building
materials. It is not combustible and would
not produce smoke or fuel the fire. Concrete
product can be either precast or in situ
concrete. This study seeks to analyze the
elemental cost comparison of precast and
cast-in-place in Rwandan construction
industry.
2. Literature Review
According to Frederick Raina (2001),
precast refers to the process of construction
in which a concrete element is cast
somewhere other than where it is to be used.
The other place may be somewhere else on
the building site or away from the site,
probably in a casting yard or factory. The
precast element may be pre-stressed, may be
of ordinary reinforced concrete, or may even
be without reinforcement. The single precast
elements may be component of a general
precast concrete system, or may serve as
singular purpose in a construction system of
mixed materials or types of elements. In this
project, I am going to research on advantage
and disadvantage of precast and cast in-situ
concrete elements and the problems
encountered in designing precast element.
The use of precast concrete has various
advantages which include the reduction of
the site labours, less wastage, less volume of
building materials, and increased
environmental and construction site
cleanliness. The use of precast products also
provides safety at construction site and
reduces time of completion in construction.
Most concrete buildings are cast in situ; the
wet mix is deposited and formed at the place
where the finished concrete is desired,
generally referred to as site cast concrete,
since the location is usually at a building
site. Precast concrete is defined as the
process of casting of concrete elements
offsite and move them to the actual building
site. Concrete for site cast construction is
typically brought to the site by concrete,
transporting mixer trucks with the large
rotating barrels. The mix is prepared at a
central batching plant, where controls of the
materials may be carefully monitored.
However, the transporting to the site, proper
mixing in truck, discharging from the truck
and depositing in the forms, and handling
for placement, finishing, and curing are all
subject to the level of responsibility and
craft exercised by the people involved. Site
conditions in terms of accessibility and
3
weather can be highly critical to the work,
requiring extreme measure in some
situations to control all the stages in the
production process. The precast process
takes place in a controlled environment,
unaffected by weather. Rigorous inspection
before installation removes cause of delay
on site. Some HCC techniques can reduce or
eliminate follow –on trades, e.g. installing
ceilings and finishes. This enables even
faster program times but requires greater co-
ordination and care in detailing and
protection on site (Emmit Stephen, Gorse
Christopher , 2005). The quantity of
concrete in a precast framework is less than
4 percent of the gross volume of the
building, and of this is in the floors. The
precast concrete elements are columns,
beams, floor slabs, staircases and diagonal
bracing (Raina, 2001).
Marco Breccolotti , Santino Gentile , Mauro
Tommasini , Annibale Luigi Materazzi ,
[2016 ] Beam-column joints in continuous
RC frames: Comparison between cast-in-situ
and precast solutions. Nevertheless, cast-in-
situ solutions intrinsically allow building
moment resisting frames, a behaviour that is
usually hard to achieve using precast
elements. In this paper a technical solution
able to offer both high strength and ductility,
simplicity of construction of the
prefabricated elements and ease of assembly
on site is presented. The solution realizes the
continuity between beam and column by
means of loop splices and cast-in-place
concrete with steel fibers to improve the
ductility of the concrete struts in the wet
joint. It is based on prefabricated beams and
columns with protruding bars that are
connected in situ by means of a concrete wet
joint with steel fibres to moderately increase
the ductility properties of the compressed
struts in the joint. The results of these tests
showed that the two solutions exhibited very
similar structural behaviours, with the
proposed solution achieving a slightly
greater strength and stiffness than those of
the cast-in-situ solution without relevant
modifications to the joint ductility. In detail,
the arrangement of the reinforcing steel has
been updated in order to avoid the yielding
of the steel inside the column and to move
the plastic zone inside the beam.
3. Research methodology
The study was conducted in laboratory tests
in order to assess the compressive strength
of precast concrete. The focused tests were
sieve analysis test, water absorption test;
aggregate and sand and both slump cone test
and compression test on concrete cubes
testing in compression machine. In this
4
project we preferred to use concrete cubes.
In order to make those cubes’ different
materials had been used. In additional
different tests on these materials had been
done before in civil engineering laboratory,
for getting data to be used in concrete mix
design and of course for making sure that
they will give correct results.
Selection of materials
The materials selected to be used for the
project are:
Cement
The cement that had been used for making
concrete cubes is CIMERWA 42.5 KN
Aggregates: Fine and course
Aggregates used Fine aggregate (sand)) used
in making concrete cylinders were taken
from Kayumbu quarry and coarse
aggregates (gravel) from Ruhango quarry.
Water
Water used in preparing concrete used for
making concrete cylinders is water supplied
by WASAC. It was free from impurities so
that it did not affect the final results Tests on
sand.
Test for sand
Before deciding that sand from Kayumbu
quarry is good quality sand so that it can be
used as concrete ingredient to be used in
making concrete cubes, the following tests
had been early performed:
Sieve analysis
Water absorption
Sieve analysis test
This test was conducted in order to
determine the particle size distribution of
fine aggregate (sand), to know the grade of
each in two types of sand and to determine
the amount of silt and clay composed.
Test procedure
Preparation of sample
Weighting the sample of 1500g was
taken as a sample to be tested or
sieved
Set a series of sieves with the largest
opening on top to the smallest
downward into a pan to receive the
fineness one that passed through out
of those set of sieves
Separate the material into a series of
particle sizes using the sieves
required by the material
Using a mechanical shaker
Establish a shaking time of 10
minutes as a sample shaking time
Brush particles clearly from each
sieve into the next lower sieve with a
bristle brush ensure that no material
is lost
Place an empty pan on the electronic
balance and tare or zero out its
weight
5
Determine the individual weights to
the sand retained on each sieve and
record these weight
Re-tare the pan for the next sizes
sieve or tare a new pan if required to
keep the material separate for sure
Repeat this process until the weight
of the material on each sieve and the
retaining pan(typically the material
passing the No 200 sieve has
recorded)
Make the original sieve analysis a ‘’
total retained” analysis by weighting
the material cumulatively.
Fineness modulus was obtained by
adding cumulative percentage of
aggregates retained on each sieve
and dividing the sum by 100.
Water absorption test
This test was conducted in order to know
how the amounts of water were absorbed by
sand. Sample weight was 500g.
Test Procedure
Preparation of sample
Record the sample weight by balance
Put the sample in water within 24
hours
Removing sample from water
Record the amount of water
absorbed in weight (M1)
Drying the sample in the dry oven in
24 hours
Record the dried sample weight
(M2)
Finally, the water absorption was given by
this formula: ((W1-W2)/W2)100 where;
w1: wet weight
w2: dry weight
Test for aggregates
In order to decide the suitability of
aggregate for concrete the following test has
been carried out:
Aggregate compressive value test
Aggregate compressive value is a value of
compressive forces at which a building
construction stone can crushes less than 400
KN.
ACV we have conducted with Indian
Standard IS 2386 (Part IV) which reports
that aggregate crushing value shall not
exceed 45% of aggregates used for concrete.
Test Procedure
Preparing the sample
Making the weight of the sample that
have passed in a sieve 14mm and
retained in sieve 10 as BS
recommends
Compressive test with 400KN on the
sample through the compressive
machine
Making the weight of the sample
retained in 2.36 sieve after passing
the crushed sample in the sieve of
6
2.36 Diameter retained sample as
British Standard requires
Calculating an ACV value as the
formula of BS Requires as IW-
R2.36S*100/IW
The formula say that IW=Initial Weight
R2.36S =Items retained in 2.36 mm Sieve
Tools and materials that were required to
make acv test are:
• Sieves of 14 and 12 mm
• Sieve of 2.36
• Mould
• Plunge
• Pan
• Gravels that have passed sieve 14mm
and retained in sieve 12mm
Test for concrete
The test for concrete is carried out to decide
the strength of the concrete against the loads
applied on it.
Compressive strength
This was a laboratory test conducted in
order to determine the compressive strength
(load bearing capacity) of quarry sand and
rainfall deposited sand, to evaluate the
performance and durability of quarry and
rainfall deposited sand and to check the
uniformity of quarry and rainfall deposited
sand quality.
Apparatus:
• Compression testing machine
• Tape measure
• Electronic Jointing table
• Electric or pneumatic hammer
• Vibrating table
Test procedure
Filling of cube moulds must be done
in three layers each approximately of
50 mm thickness. The concrete must
be placed using a scoop and the
scoop should be moved around the
top edges of the cube mould so that
symmetrical distribution of concrete
is done in each layer as the concrete
slides down from the inclined scoop
into the moulds.
Each layer must be compacted fully
either by using a tamping rod or by
using vibration techniques. If
concrete is compacted by hand
tamping, in 150 mm mould, then 35
strokes are given per layer uniformly
covering the entire surface especially
the corners. If 100mm mould is used
then each concrete layer must be
hand tamped giving 25 strokes.
To avoid entrapment of air in corners
and the sides it is recommended to
tamp the sides of the moulds either
by using the tamping rod or by using
a wooden mallet. Concrete in cube
moulds can also be compacted using
vibrations techniques. Electric or
pneumatic hammer or vibrating table
should be generally used. Never try
to compact cubes using a needle or
poker vibrator.
If the electric or pneumatic hammer
vibrator is used then it is
7
recommended that cube moulds,
which have firm bolting arrangement
between the sides and the base
plates, be used. Use of clamps
instead of bolts may not give
adequate fixity. It is necessary that
filling and compacting operations
should be done in an identical
manner in three layers as in the case
of hand tamping.
It is necessary to hold the electronic
or pneumatic hammer down onto a
piece of timber placed over the top
of the mould. When the electric
hammer is used, it is also preferable
to keep the mould on a levelled hard
wooden piece rather than on any
hard surface.
Finally, trowel the surface level with
the top of the mould. Identification
mark, number and/or date can be
lightly scratched on the wet towelled
concrete surface using a matchstick
or a scraper.
Curing the specimen in 14days and
28days for getting to be hardened
After curing the specimen, placing it
with flat faces horizontal in
compression test machine
Apply load axially till failure occurs
and note maximum load at failure
The load at failure is a maximum load at
which the specimen fails to produce any
further increase in the indicator reading on
testing machine.
Maximum load at failure dived by average
area of bed face gives compressive strength
Bed face area=150mm*150mm= 22500mm2
4. Results
Results for sand tests
Sieve analysis test results of dry sand
The dry sieve analysis was conducted to
bank sand we take 500g, liver sand from
NYABARONGO River (Kayumbu) and
crushed stone sand.
Sieve
size
accordi
ng to
British
Standar
d
Mass of
fine
aggregat
es
retained
(g)
Percentag
e of fine
aggregates
retained
(%)
Cumulat
ive
percenta
ge of
fine
aggregat
es
retained
(%)
Cumul
ative
percen
tage of
fine
aggreg
ates
passing
(%)
10.0mm 0 0 0 100
4.75mm 10 2 2 98
2.36mm 60 12 14 86
1.18mm 120 24 38 62
600μm 80 16 54 46
300μm 120 24 7
8
22
150μm 80 16 94 6
75μm 20 4 98 2
Pan 10 2 100 0
TOTAL 500 100
Conclusion: The our sand is of good quality
because there is no many clay
8
By the sieve, analysis diagrams above, the
visible difference varies depends on the
sieves arrangement (from the bigger to the
smaller sizes) on x- axis and percentages of
passing on y-axis. Therefore, our sand is
finer as shown. By ISI 383 grading graph
compared with the percentage of passing
sample below
SNo Sieve Size(mm) %Passing Grading zone III
1 10 100 100
2 4.75 98 95-100
3 2.36 86 85-90
4 1.18 62 60-65
5 0.6 46 45-60
6 0.3 22 20-25
7 0.15 6 0-5
8 0.075 2 3-5
Water absorption test result
The weight of moist(wet) sand sample
(M1 =2500g)
The weight of dry sand sample
(M2=2461.5g)
Water absorption test results of our sand(w)
W = 100=
= 1.56 %
Our sand absorbs water at the rate of 1.56%,
Therefore, by ASTM values of water
absorption test should not exceed 2.3% for
concrete purpose. Therefore, the above used
type of sand is good for high quality project
of concrete.
4.2 Test for aggregate
Aggregate compressive value test (ACV)
An aggregate compressive value is a value
of compressive forces at which a building
construction stone can crushes under
400KN.
We have used two samples
The first sample was contained of 3541.5g
of aggregates that have passed in sieve of
14mm and retained in sieve of 12mm.
With this sample, we made the test as the
procedures say and we got the Aggregate
compressive value as 14 KN/mm2
In our test we have conducted with
IW=3541.5g
9
R2.36mm=3030.5g
After making an ACV we got =
During the project we have also used
another acv test of 3891g of stones sample
the results as the formula says IW-
R2.36S*100/IW we got
From this we have choose to use the sample
14% due to the Indian standard that says the
lower value of ACV the higher strength of
the aggregates.
5. Discussion
Slump test result
The height of the cone = 30cm
Block-test height = 21.7cm
Slump = 7.5cm which falls in the range of
medium workability
Concrete workability
Degree of workability Slump (cm)
Extremely low 0
Very low 0-2.5
Low 2-2.5
Medium 5-10
High 10-12.5
Very high 15
According to The degree of workability, the
workability concrete of our concrete is
medium this is good to be used for
manufacturing of concrete.
Compression test
The result of compression test which
differentiates compressive strength of
precast and cast in situ concrete
TARGET GRADE: M25
10
Compressive Strength of cast in situ concrete at 14 days and 28 days
CAST IN SITU CONCRETE
No of
specimen
Water
cement ratio
Ratio Area of each
specimen(mm2)
Load of each
specimen(N)
Compressive
strength after
14 days
curing(N/mm2)
Load of each
specimen(N)
Compressive
strength after
28 days
curing
1 0.5 1:1:2 22500 407475 18.11 496125 22.05
2 0.5 1:1:2 22500 398025 17.69 478575 21.27
3 0.5 1:1:2 22500 407925 18.13 498825 22.17
Average 17.97 21.83
Compressive Strength of Precast concrete after 7 days and 28 days
PRECAST CONCRETE
No of
specimen
Water cement
ratio
Ratio Area of each
specimen(mm2)
Load of each
specimen(N)
Compressive
strength after 7
days
curing(N/mm2)
Load of each
specimen(N)
Compressive
strength after
28 days curing
1 0.5 1:1:2 22500 470250 20.9 537750 23.9
2 0.5 1:1:2 22500 473175 21.03 558000 24.80
3 0.5 1:1:2 22500 554625 22 560475 24.91
Average 21.31 24.53
The curing was conducted on the following
way in this test:
For precast
•We used 6 cubes of 15*15cm each were
cured in the bucket full of water for 28 days
For cast in situ
•We used 6 cubes also of 15*15cm each
were cured every day repeatedly in period of
14 days and 28 days, the results of the
compressive strength for every test are
shown in the table above.
11
Conclusion
The main goals of the work have been
achieved.
As conclusion the result of test shows that
the strength of cast in situ concrete is 21.83
N/mm2 compared to precast which has 24.53
N/mm2 means there is a little bit different in
strength and is better to use precast one
because the construction will be quick and
curing was done on factory that led to high
compressive strength.
The study also revealed that the Rwandan
construction industry based on cast in situ
concrete more that on precast concrete
structures.
After the completion of different laboratory
test, analyzing and reading, consulting and
browsing on several source of information
including books, publications, adverts and
website as stated in references there are
number of conclusion which we are able to
make:
1. With using a precast concrete
structures, the strength of concrete
increases and also last longer
compared to cast in place concrete
2. With using a precast concrete
structures, the construction is very
quick
3. With using a precast concrete, the
future expansion is easy
4. With using precast concrete, the
curing is preserved
5. With using precast concrete, the
destruction is easy
6. With precast concrete we get
alternative economic use of
materials.
Limitation and recommendation
While conducting this study I met some of
the challenges. I was unable to purchase the
abundant materials of concrete for making
many samples of concrete because of lack of
enough funding. Again it was not an easy
task for me to get soil and concrete
laboratory where to perform different tests
as time of project was rushing. After seeing
the challenges met during this project, I
recommend IST Burkinafaso to support the
final year’s student projects; if possible they
should have MoUs with Institutions having
soil laboratory such as in Rwanda.
Based on the research works, it is highly
recommended to adopt precast concrete in
building construction.
I also recommend the institution to increase
the period reserved for academic
dissertation.
Acknowledgement
12
It is my pleasure to thank Prof. Naon
Betabole for accepting me to work under his
guidance. I thank him cordially for the help
extended to me during the entire time of
doing the assessment. I remain ever grateful
to him. I also thank all professors, lecturers
of IST Burkinafaso who gave me technical
and professional supported while conducting
the assessment. I finally thank my family
members who funded this research; I
acknowledge their services with thanks.
List of abbreviations
TVET: Technical and
Vocational Education and
Training
WDA: Workforce
Development
M: Grade of concrete
GOR: Government of
Rwanda
R2.36: Materials retained in
sieve 2.36 mm
ASTM: American Society
for Testing Material
FCK: Characteristic strength
IW: Initial Weight
References
A, S. (2009). How To Use Solving Formula.
Deek, O. (1985). Precast concrete structure
fabrication revised edition 2.
Emmit Stephen, Gorse Christopher . (2005).
Precast structural Analysis.
F.A.MNSE, E. A. (2015). Comparison of
compressive strength of concrete. Ilaro:
HRMARS.
J., A. (february 2012). Precast Concrete
Product.
Neville. (1987). Type of slump test.
Pumnia, D. B. (1967). Building
construction.
Raina, F. (2001). Concrete technology.
London.
Wiley, J. (1991). Engineering Material. Sons
Inc.