Page 1: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

Community Services Capital Project Sheets 

Ref 201‐337 

Page 2: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 201-Community Services Contribution to Post-Secondary Recreation Facility Expansion ID# 0 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Other THEME: Infrastructure Management WARD: City Wide As per CORP2019-066 Investing in Canada Infrastructure Program – Community, Culture and Recreation Funding Grant Application, the City of Waterloo has committed to providing a contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion & Indoor Track Project ICIP grant submission. Both of these facility rehab / expansion projects will provide increased community access to major recreation facilities supporting affiliate groups, adult groups, clubs, and major event / bid attraction. The final contribution is subject to the completion of the business plan model review and community use agreement for both projects.

SERVICE DELIVERY DIVISION: COMM-Commissioner IMPLEMENTATION DIVISION: COMM-Commissioner REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

PUB-GEN 4,857 4,857

TOTAL 4,857 4,857 INFLATED 5,000 5,000

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 202-Community Services In Camera ID# 0 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Other THEME: Infrastructure Management WARD: City Wide In Camera

SERVICE DELIVERY DIVISION: COMM-Commissioner IMPLEMENTATION DIVISION: COMM-Commissioner REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 2,914 2,914

TOTAL 2,914 2,914 INFLATED 3,000 3,000

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 250 250 ONE TIME TOTAL 250 250

Page 3: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 210-Museum Storage Facility ID# P01288 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Growth THEME: Facility Expansion WARD: City Wide Museums exist to preserve, document, and research the material evidence of our world, and make it accessible to the public through programs of interpretation, education, and exhibition. The artifacts in the museum's collection are a tangible representation of the community's heritage, and to retain their informational value they must be properly cared for and documented. Staff recommend a collection storage facility to adequately address current storage issues and plan for the anticipated growth of the collection. The City's museum collection was established when 8,000 objects were accepted from the former Seagram Museum. Since this time, the collection has grown and is now double in size. The oversized objects, including the refurbished 1919 Pierce Arrow truck, are stored in a rental space that is unsuitable to block risks from agents of deterioration and make it difficult to access them for exhibitions. Space at the Museum facility to safely store smaller objects and archival documents is reaching capacity. A more comprehensive approach needs to be taken to manage the museum's collection assets that are held in the public trust. By doing so, the Museum's operations will be improved greatly, especially in the area of exhibition development. Information gathered from the Museum Strategy (COMM2015-25), directed there be growth towards a more diversified collection, and recommended that a proper and dedicated storage facility be developed. The collection is growing annually which is limiting the opportunity to expand the collection's scope to better reflect the growing diversity of our residents. SERVICE DELIVERY DIVISION: COMM-Comm. Prog. & Outreach IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 749 749

TOTAL 749 749 INFLATED 817 817

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 5 5 ONE TIME TOTAL 5 5

PROJECT 211-Accessibility Facility Upgrades (AODA) ID# P01289 PSOFT # 170118 STRATEGIC PLAN LINK: Equity, Inclusion and a Sense of Belonging TYPE: Rehabilitation THEME: Facility Refurbishment WARD: City Wide The purpose and goal of the Accessibility of Ontarians with Disabilities Act (AODA) is to improve opportunities for persons with disabilities and to provide for their full involvement in the identification, prevention and removal of barriers to their full participation in the life of the province. The capital budget for accessibility upgrades allows for the removal of barriers in existing facilities and spaces at the time of retrofits. Projects vary from year to year and are identified annually through the facility accessibility audit, customer inquiries and requests and advice from the municipalities Accessibility Advisory Committee. Priority is given to initiatives identified in widely used public facilities and spaces. Projects can include but are not limited to washrooms, entrances, emergency exits, signage, communication equipment, ramps, automatic door openers. This work is ongoing and a municipal requirement so the capital project budget covers the span of the capital budget time frame. While Facilities Design and Management Services is the primary implementation division from time to time projects are identified and led through the Recreation Services division.

SERVICE DELIVERY DIVISION: COMM-Comm. Prog. & Outreach IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 37 70 86 35 36 27 28 59 27 405

TOTAL 37 70 86 35 36 27 28 59 27 405 INFLATED 39 74 94 39 41 30 32 70 32 452

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 4: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 212-Neighbourhood Strategy Implementation ID# P01578 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Other THEME: New Programs WARD: City Wide Capital funding is required for three projects as part of the Neighbourhood Strategy Implementation 1. Neighbourhood Event Equipment - providing neighbourhood groups with a supply of equipment needed to run community events 2. Neighbourhood Website - developing a new website where residents will be able to find tools and information needed to lead community-building in their neighbourhood 3. Neighbourhood Projects in Parks - development of new community gardens, outdoors rinks, and the like, in city parts to support resident-led, community building.

SERVICE DELIVERY DIVISION: COMM-Comm. Prog. & Outreach IMPLEMENTATION DIVISION: COMM-Comm. Prog. & Outreach REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 61 14 14 13 30 12 12 12 12 181

TOTAL 61 14 14 13 30 12 12 12 12 181 INFLATED 63 15 15 14 34 14 14 14 15 199

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 1 2 1 1 1 1 7 ONE TIME TOTAL 1 2 1 1 1 1 7

PROJECT 213-Truth and Reconciliation Implementation ID# 0 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Other THEME: New Programs WARD: City Wide The Truth and Reconciliation Commission has outlined a number of calls to action that are connected to the roles and responsibilities of municipal governments. In response, staff presented to Council in Fall 2019 a corporate action plan. This action plan aligns with the objective within the new Corporate Strategic Plan to respond to the Commission's Calls to Actions. Funding is required to implement the action plan. This funding would be used for placemaking activities that honour the pre- and post colonial history of Indigenous communities in this area and / or to celebrate Indigenous culture and contributions to our community. A highly collaborative approach involving local Indigenous leaders, organizations and residents would be used to implement these initiatives.

SERVICE DELIVERY DIVISION: COMM-Comm. Prog. & Outreach IMPLEMENTATION DIVISION: COMM-Comm. Prog. & Outreach REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 24 23 22 21 90

TOTAL 24 23 22 21 90 INFLATED 25 25 25 25 100

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 5: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 214-Dedicated Museum Website ID# P01610 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Other THEME: Technology Refresh / Upgrades WARD: City Wide The museum strategy implementations (COMM2015-25) identified 20 recommendations with a period for completion. Development of a dedicated website for the City of Waterloo Museum was identified as a project that would require additional funds. With the recent refresh of the city’s website, the capacity to effectively and efficiently communicate and promote the museum’s collection and programs has ended. As a result, the city’s website is unable to support the museum’s needs in terms of offering expanded digital content experience. Many museums have a dedicated stand-alone website to provide information that is more detailed. This initiative complies with IMTS and communications frameworks.

SERVICE DELIVERY DIVISION: COMM-Comm. Prog. & Outreach IMPLEMENTATION DIVISION: COMM-Comm. Prog. & Outreach REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 66 66

TOTAL 66 66 INFLATED 68 68

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 5 5 ONE TIME TOTAL 5 5

PROJECT 220-Forestry and Horticulture Storage Area Improvements ID# P01558 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Growth/Rehab Split THEME: Facility Expansion WARD: City Wide The funding will be used to improve the storage area serving Forestry and Horticulture needs. The project will include the supply and installation of new storage containers at the Waterloo Service Centre.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 45 45

TOTAL 45 45 INFLATED 46 46

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 6: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 221-RIM Park Ball Diamond Upgrades ID# P01291 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth/Rehab Split THEME: Facility Expansion WARD: Ward 4 - Northeast Funding will be used for the design and installation of MUSCO lighting systems and diamond reconfiguration to support the needs of user groups. The Outdoor Sports Field Strategy supports the investment / upgrade of City-owned facilities to expand inventory and bookable time prior to consideration of non-City owned facilities.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: IPPW-Engineering REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

PUB-GEN 400 1,918 2,318

TOTAL 400 1,918 2,318 INFLATED 424 2,092 2,516

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 30 30 ONE TIME TOTAL 30 30

PROJECT 222-West Side Recreation Facility Development ID# P01292 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Facility Expansion WARD: Ward 2 - Northwest The Recreation and Leisure Services Master Plan recommends that consideration be made to review options associated with the potential extension of facilities and services to the west side of the City. While the YMCA-Library and the Westmount sports fields have met current demand, no facilities, programming or services are currently planned for, nor has there been any exploration of any options that may provide potential opportunities to the residents of this area in the future. A review to be commissioned in 2022 will confirm the needs, associated costs and opportunities for providing community and recreation services to the residents on the west side of the City and beyond.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

PUB-GEN 59 59 DC 7,141 7,141 CRF (New) 216 518 734

TOTAL 7,200 216 518 7,934 INFLATED 8,271 258 631 9,160

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 304 304 ONE TIME TOTAL 304 304

Page 7: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 223-Park Amenity Upgrades ID# P01294 PSOFT # 150008 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth/Rehab Split THEME: Facility Refurbishment WARD: City Wide The funding is used to improve and / or establish new amenities and equipment in park spaces across the City.

Background information: Park amenities improve park usage and support greater community development within neighbourhoods. Demand for new and / or improved amenities is being experienced across the City within existing neighbourhoods that are experiencing intensification, newly built neighbourhoods, and existing parks in established neighbourhoods where amenities have not been established. Replacement of worn / deteriorated amenities and equipment also assists in eliminating potential safety hazards in parks. The list of priorities is updated on an ongoing basis as needs / issues arise.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 159 159 159 159 159 794 DC 159 159 159 159 159 794

TOTAL 318 318 318 318 318 1,589 INFLATED 337 344 358 372 387 1,798

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 5 5 5 5 5 25 ONE TIME TOTAL 5 5 5 5 5 25

PROJECT 224-Bechtel Park Bridge Removal ID# P01024 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Infrastructure Management WARD: Ward 5 - Southeast The 2018 Bridge Inspection Reports identified a number of bridges requiring significant work, including the Bechtel Park Bridge. The bridge leads to a natural area that has no public trails. Public trails are not planned to be built in this area and maintenance staff does not require the bridge to access the area. Considering this, and the significant repair work the bridge requires, the bridge will be removed.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: IPPW-Transportation REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 59 59

TOTAL 59 59 INFLATED 61 61

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 8: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 225-Camelot Place Noise Wall Replacement ID# P01029 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Infrastructure Management WARD: Ward 5 - Southeast The funding will be used to replace the noise wall in Camelot Park

Background Information: The noise wall in Camelot Park had emergency repairs carried out in 2011. The repairs are expected to extend the useful life for the wall for another 10 years before replacement of the wall is required. The funding will be used to replace the wall after its current useful life expires. Design and construction will take place in 2025.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 173 173

TOTAL 173 173 INFLATED 195 195

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 3 3 ONE TIME TOTAL 3 3

PROJECT 226-Park Infrastructure Replacement and Rehabilitation Needs ID# P01574 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Infrastructure Management WARD: City Wide Based on CORP2019-075 Long Term Financial Plan Update, the average annual funding gap for Tax Base assets is estimated to be approx. $17M. Council previously directed staff via CORP2018-011 to consider increased infrastructure funding opportunities as part of the 2020-2022 budget. For 2020, an 8% increase in infrastructure funding (allocated to CIRRF) is being recommended with 0.3% funded from a tax increase above inflation and 0.5% funded through a portion of Waterloo North Hydro Dividend revenue being allocated to CIRRF. For 2021 a .9% increase and 2022 a 1.5% increase in infrastructure funding (allocated to CIRRF) is being recommended funded from a tax increase above inflation. The increased infrastructure funding is being allocated to the major Asset Classes based on a weighted percentage need. The Park Infrastructure Replacement and Rehabilitation Needs project will be used to fund Parks Asset priorities that couldn’t be accommodated within the currently available funding including but not limited to Facility Refurbishment, Park Rehabilitation / Upgrade and Equipment Replacement. The increased infrastructure funding projects are classified as Non-Routine in nature and the subject matter experts will return at a later date with a prioritized list of candidate projects to be advanced via this funding.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 96 126 106 107 105 103 101 99 97 95 1,034

TOTAL 96 126 106 107 105 103 101 99 97 95 1,034 INFLATED 99 133 116 116 116 116 116 116 116 116 1,158

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 9: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 227-Pedestrian Bridge Replacements ID# P01023 PSOFT # 170003 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Infrastructure Management WARD: City Wide The City of Waterloo has a pedestrian bridge inventory of 34 bridges (2018 inventory numbers) that support crossing of water courses along the City's trail network. The identified capital funding will be used to carry out prioritized upgrades / improvements associated with the structure of the pedestrian bridge, its abutments and / or any required bank stabilization in the immediate vicinity of the bridge.

Background Information: The Ontario government legislates the mandatory inspection of bridges and culverts every two calendar years. The inspection must be led or supervised by a trained professional engineer. The Ontario Structure Inspection Manual (OSIM) is used to assess bridge and culvert components to determine the extent of the work that is required to be undertaken and recommend the timeframe within which to carry out the work. The consultant carries out the inspections and generates a report identifying a list of required upgrades / improvements. The list of priorities is updated every other year when the most current Bridge Inspection Report becomes available and on an ongoing basis as new needs/unexpected issues arise.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: IPPW-Transportation REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 66 66 66 66 66 66 66 133 66 663 SWM 66 66 66 66 66 66 66 66 66 66 663

TOTAL 133 133 133 66 133 133 133 133 199 133 1,325 INFLATED 136 140 145 72 146 149 152 155 238 162 1,495

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 228-West Side Recreation Facility-Land Acquistion ID# P01293 PSOFT # 170012 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Land Acquisition WARD: Ward 2 - Northwest Pursuant to the Recreation and Leisure Services Master Plan, facilities and / or extended services may be required to address a growing population on the west side of the City approximately years 2025-2030. This project provides funding to purchase land to support any Council endorsed strategies and recommendations of the west side facility needs analysis and feasibility study, budgeted and scheduled in 2022. Facility development funding is currently budgeted and scheduled for 2026.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

DC 2,378 2,378 PUB-GEN 2,906 2,906

TOTAL 5,284 5,284 INFLATED 5,439 5,439

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 10: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 229-Alexandra Park Expansion ID# P01026 PSOFT # 150009 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth/Rehab Split THEME: Park Expansion WARD: Ward 7 - Uptown The funding is for the design and construction of the new park space.

Background Information Alexandra Park is situated in the heart of an established neighbourhood that is experiencing significant growth as a result of an adjacent residential condominium development and other population increases associated with the intensification of the Uptown core. Land was purchased to expand the existing park area. The park expansion will provide additional recreational space and associated amenities to service the growth in the neighbourhood.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

PUB-GEN 729 729

TOTAL 729 729 INFLATED 750 750

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 37 37 ONE TIME TOTAL 37 37

PROJECT 230-Leash Free Dog Park ID# P01030 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Park Expansion WARD: City Wide The funding will be used for the development (planning, design, and construction) of a new leash-free dog park.

Background Information: The 2008 Recreation and Leisure Services Master Plan identifies leash-free dog parks as an emerging park use and recommends that the City undertake site development initiatives to accommodate the use where demand is evident. At this time the City has one leash-free dog park facility at Bechtel Park. The funding will be used to plan for (establish needs, identify potential locations and select preferred location), design and construct a new leash-free dog facility.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 8 24 32 DC 47 138 184

TOTAL 55 162 217 INFLATED 57 171 228

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 10 10 ONE TIME TOTAL 10 10

Page 11: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 231-Neighbourhood Action Sport Parks ID# P01189 PSOFT # 190008 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Park Expansion WARD: City Wide Neighbourhood Action Sport Parks are being implemented as per the Action Sport Strategy. There are four new park development locations - 1) a skate park at Albert McCormick Community Centre & Branch Library, 2) a bike park at RIM Park, 3) a skate park at RIM Park 4) a skate park at the Harper Branch Library & Stork Family YMCA. The AMCC skate park includes a splash pad (separately funded) and a significant parking realignment (funding within this project) to enable the new park development.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: IPPW-Engineering REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

PUB-GEN 119 69 99 99 386 DC 676 395 563 563 2,197

TOTAL 795 464 662 662 2,584 INFLATED 818 492 723 717 2,750

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 15 15 80 15 125 ONE TIME TOTAL 15 15 80 15 125

PROJECT 232-Park Strategy Implementation ID# P01193 PSOFT # 170005 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Other THEME: Park Expansion WARD: City Wide The funding will be used to implement priority projects identified by the Park Strategy.

Background Information: As an outcome of the proposed Parks Strategy, a list of priorities will be generated for the development / re-development, management and operation of public park resources across the City. The funding will be used for the design and implementation of priority items identified in the Park Strategy.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 40 40 40 40 40 40 40 40 40 40 400 DC 120 120 120 120 120 120 120 120 120 120 1,200 CIRRF (Rehab/Repl) 96 96 85 1,149 1,272 574 3,270

TOTAL 160 160 256 256 160 160 245 1,309 1,432 734 4,870 INFLATED 165 170 279 277 177 180 281 1,534 1,711 894 5,667

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 5 5 20 15 15 60 ONE TIME TOTAL 5 5 20 15 15 60

Page 12: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 233-Roger Street Parks Development ID# P01295 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Park Expansion WARD: Ward 7 - Uptown The funding will be used for the design and construction of the Roger Street Park and trail connections.

Background Information The established neighbourhood is experiencing significant growth as a result of an adjacent residential condominium development and other population increases associated with the intensification of the Uptown core. The park expansion will provide additional recreational space and associated amenities to service the growth in the neighbourhood and will act as a critical pedestrian link from the local community through Mount Hope Cemetery and on to King Street.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

PUB-GEN 366 366

TOTAL 366 366 INFLATED 388 388

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 16 16 ONE TIME TOTAL 16 16

PROJECT 234-Roselea Park Playground ID# P01545 PSOFT # 0 STRATEGIC PLAN LINK: Equity, Inclusion and a Sense of Belonging TYPE: Growth/Rehab Split THEME: Park Expansion WARD: Ward 5 - Southeast The funding will be used to design and build a playground in Roselea Park.

Background Information: Environment and Parks Services undertook a service level inventory for City owned and operated playgrounds. The neighbourhood delineated by Lincoln Road, University Ave. East, Conestoga Parkway, Bridgeport Road and Weber Street has been identified as lacking a playground facility that residents can reach within the standard 5-10 minutes of walking. Roselea park is located in the heart of the neighbourhood and has been identified as the best candidate to accommodate a playground. The funding will be used to design and build a playground in the park.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 85 85

TOTAL 85 85 INFLATED 87 87

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 13: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 235-Splash Pads Construction ID# P01297 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Park Expansion WARD: City Wide The funding will be used for the development (construction) of new splash pad facilities-sites to be determined.

Background Information: The 2008 Recreation and Leisure Services Master Plan recommends the development of three neighbourhood-based splash pads distributed across the City. Currently the city has one splash pad facility in the central core area of the City in Waterloo Park. The proposed new splash pad facilities will address growth related needs in the neighbourhoods outside of the City core.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 75 75 75 224 DC 425 425 425 1,276 PUB-GEN 106 103 100 308

TOTAL 606 603 600 1,808 INFLATED 623 639 654 1,916

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 25 65 25 115 ONE TIME TOTAL 25 65 25 115

PROJECT 236-Vista Hills Programmbale Soccer Field - Partnership with WRDSB ID# P01190 PSOFT # 190010 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Park Expansion WARD: Ward 2 - Northwest Design and construct a new programmable soccer field in the Vista Hills neighbourhood on new parkland.

0 Background Information: The 2012 Outdoor Sports Field Strategy (OSFS) identified a need for additional soccer fields on the west side of the City. The OSFS recommends exploring partnership opportunities with the school boards for the provision of programmable fields. City Staff have been working with the Waterloo Region District School Board (WRDSB) to identify such opportunities and are working toward joint use of two programmable soccer fields located at the new Vista Hills Public School and Vista Hills Park. The WRDSB will construct a second programmable soccer field on the School Board property and in turn the City will provide a similarly upgraded field in Vista Hills Park. The funds will cover the design and construction of the new field in Vista Hills Park.

0 SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: IPPW-Engineering REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 37 37 DC 334 334

TOTAL 371 371 INFLATED 452 452

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 15 15 ONE TIME TOTAL 15 15

Page 14: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 237-Waterloo Park New East-West Park Crossing ID# P01298 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Park Expansion WARD: Ward 7 - Uptown The funding will be used for the design and construction of the new east-west park crossing over Laurel Creek in Waterloo Park.

Background Information: Waterloo Park (WP) is a community park situated in the core of Uptown Waterloo. The Uptown District surrounding WP has undergone significant redevelopment and has been identified as a primary growth area in the City (WP is situated along several nodes and corridors planned for major growth). The Waterloo Park Master Plan (WPMP) 2009 outlines a plan to keep WP's programs and infrastructure current with the evolving context and needs of the community (extensive intensification, significant population increase in the Uptown core, dramatic increase in district and community use on LRT route). The funding will be used for the development (planning, design and construction) of a new pedestrian bridge over Laurel Creek and associated trail connections in accordance with the WPMP. The crossing will provide a vital trail connection between the new WP Festival Area and other amenities on the east side of Waterloo Park.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

PUB-GEN 360 360 DC 540 540

TOTAL 900 900 INFLATED 954 954

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 28 28 ONE TIME TOTAL 28 28

PROJECT 238-Waterloo Park - Public Open Space Improvements ID# P01299 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Park Expansion WARD: Ward 7 - Uptown The funding will be used for the design and construction of the new festival area in Waterloo Park.

Background Information: Waterloo Park (WP) is a community park situated in the core of Uptown Waterloo. The Uptown District surrounding WP has undergone significant redevelopment and has been identified as a primary growth area in the City (WP is situated along several nodes and corridors planned for major growth). The Waterloo Park Master Plan (WPMP) 2009 outlines a plan to keep WP's programs and infrastructure current with the evolving context and needs of the community (extensive intensification, significant population increase in the Uptown core, dramatic increase in district and community use (on LRT route).

The funding identified in this project sheet is for the design and construction of the new festival area, in accordance with the WPMP.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 1,053 648 1,701 DC 2,106 1,296 3,402 PUB-GEN 351 216 567

TOTAL 3,510 2,159 5,669 INFLATED 4,032 2,530 6,562

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 150 90 240 ONE TIME TOTAL 150 90 240

Page 15: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 239-Artificial Turf Replacement - RIM Park ID# P01301 PSOFT # 190011 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Park Rehabilitation / Upgrade WARD: Ward 4 - Northeast Turf replacement for the two artificial turf fields at RIM Park.

Background Information: The existing turf in both artificial turf facilities was installed in 2011. The lifespan of artificial turf is 8-10 years. With repairs scheduled for 2020 and 2022, the replacements will be due in the 2024 and 2026 periods. The funding will provide for the replacement of both fields.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 219 150 1,365 1,515 3,248

TOTAL 219 150 1,365 1,515 3,248 INFLATED 225 164 1,507 1,740 3,635

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 240-Bechtel Park Leash Free Dog Park Improvements ID# P01546 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Growth/Rehab Split THEME: Park Rehabilitation / Upgrade WARD: Ward 5 - Southeast The funding will be used to improve access and accessibility at the Bechtel Park Leash Free Dog Park.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 50 50

TOTAL 50 50 INFLATED 51 51

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 16: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 241-Bechtel Park Stadium Rehabilitation ID# P01303 PSOFT # 190012 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Park Rehabilitation / Upgrade WARD: Ward 5 - Southeast Asset replacement is required to meet the needs of the stadium users.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: IPPW-Engineering REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 437 437

TOTAL 437 437 INFLATED 450 450

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 3 3 ONE TIME TOTAL 3 3

PROJECT 242-Outdoor Sports Field Strategy Implementation ID# P01305 PSOFT # 160008 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth/Rehab Split THEME: Park Rehabilitation / Upgrade WARD: City Wide The funding would be used to implement capital sports field upgrades as identified in the 2012 Outdoor Sports Field Strategy.

Background Information: The Outdoor Sports Field Strategy (2012-2031) was approved by City Council in June 2012. The funding is for the implementation of strategic sports field improvements that aim to maintain and improve the long-term quality of the outdoor sports fields inventory and accommodate for the increased use of sports fields due to growth. Individual project sheets will be generated for major strategic initiatives that address significant field improvements or expansion / modification of field inventory.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: IPPW-Engineering REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 44 135 44 135 44 135 44 135 44 135 896 DC 44 135 44 135 44 135 44 135 44 135 896

TOTAL 89 270 89 270 89 270 89 270 89 270 1,793 INFLATED 91 286 97 292 98 304 102 316 106 329 2,021

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 10 5 15 5 15 5 15 20 90 ONE TIME TOTAL 10 5 15 5 15 5 15 20 90

Page 17: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 243-Park Operations Yard Relocation from Bauer Lot ID# P01547 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Park Rehabilitation / Upgrade WARD: Ward 7 - Uptown The funding will be used to relocate the Parks Operations yard from Bauer Lot in Waterloo Park to another suitable area to facilitate the Bauer Lot upgrade. The works will include the preparation of the new area to accommodate the yard.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

PUB-GEN 450 450

TOTAL 450 450 INFLATED 477 477

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 40 40 ONE TIME TOTAL 40 40

PROJECT 244-Parks Roadway and Multi-Use Pathway Upgrades-City Wide ID# P01306 PSOFT # 190013 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Park Rehabilitation / Upgrade WARD: City Wide Bi-annual funding is required for the rehabilitation of roadways and trails throughout City parks, as they degrade over time. Investment in these areas is necessary for the safety of vehicular and pedestrian traffic to provide access throughout City parks and dog park areas. The funding in 2024 will be used for the resurfacing of Bechtel Park roadway.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 86 86 160 86 87 505

TOTAL 86 86 160 86 87 505 INFLATED 89 94 177 99 104 562

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 18: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 245-Park Shade Structures and Washrooms ID# P01580 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth/Rehab Split THEME: Park Rehabilitation / Upgrade WARD: City Wide The funding will be used to design and build park shade structures and washrooms in parks.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

PUB-GEN 150 150 150 150 600

TOTAL 150 150 150 150 600 INFLATED 164 166 172 179 681

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 3 3 3 3 12 ONE TIME TOTAL 3 3 3 3 12

PROJECT 246-Park Signage Replacement Program - City Wide ID# P01036 PSOFT # 110086 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Park Rehabilitation / Upgrade WARD: City Wide The funding is used to carry out replacement of parkland signage in parks throughout the City, as well as to install new signage required as a result of new growth related amenities / facilities.

Background Information: An inventory of park signs is maintained and a program has been established to address the replacement of existing park signs that are aging or do not meet current standards. In addition, the work involves updating of new regulatory / identification signs, installing new signage associated with new facilities / amenities and addressing occasional vandalism issues.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 10 10 10 10 10 10 10 10 10 10 99 DC 1 1 1 1 1 1 1 1 1 1 11

TOTAL 11 11 11 11 11 11 11 11 11 11 110 INFLATED 11 12 12 12 12 12 13 13 13 13 123

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 19: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 247-Park Upgrades-City Wide ID# P01191 PSOFT # 130028 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Rehabilitation THEME: Park Rehabilitation / Upgrade WARD: City Wide The funding is used to carry out capital upgrades to existing aging park infrastructure.

Background Information: Park infrastructure includes items such as fences, light fixtures, roadways / trails / pathways, stairs, ramps, access gates, water supply lines, garbage receptacles, amenities, multi-use courts, etc. The funds will be used to carry out upgrades to these items, as well as to address erosion and drainage issues in parks. Replacement / improvement of aging infrastructure is essential in eliminating potential safety hazards in parks and the provided park infrastructure and supporting amenities improve park usage by residents and supports greater community development within neighbourhoods. The list of priorities is updated on an ongoing basis as needs / issues arise.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 145 145 205 120 145 265 265 145 1,435

TOTAL 145 145 205 120 145 265 265 145 1,435 INFLATED 149 154 224 132 163 310 317 177 1,626

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 248-Playground Upgrades / Expansion - City Wide ID# P01039 PSOFT # 110083 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Park Rehabilitation / Upgrade WARD: City Wide The funding will be used to carry out prioritized upgrades / improvements of the city's playground facilities and equipment as well as to expand playgrounds slated for improvements to accommodate for increased growth-related needs. Background Information: The City completes playground inspections in accordance with the requirements of the Canadian Standards Association. The standard is meant to ensure that playgrounds (equipment and surfacing) are designed, constructed, installed and maintained according to national safety standards. The inspection report outlines the condition of playgrounds and establishes a prioritized list of playground upgrades (retrofits or replacements) to be implemented. The list of priorities is updated annually based on the playground inspectors findings. At the time of the upgrades playgrounds located in areas experiencing growth are enlarged to accommodate for increased needs.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 108 108 117 117 126 126 135 135 144 144 1,260 DC 44 44 46 46 38 38 15 15 16 16 318

TOTAL 152 152 163 163 164 164 150 150 160 160 1,578 INFLATED 156 161 178 176 181 185 172 176 191 195 1,772

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 20: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 249-Sportsfield Upgrades - City Wide ID# P01192 PSOFT # 120064 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Rehabilitation THEME: Park Rehabilitation / Upgrade WARD: City Wide The funding is used to carry out improvements / renovations to sports fields, courts and replacement of sports fields equipment in City Parks and Schools, in part to accommodate for increased use of sports fields due to growth. Background Information: The ongoing improvements / renovation of sports fields ensures that our fields and equipment meet the recreational needs of our community and user groups. Quality sports fields offer increased level of service, encourage increased field usage and provide a safe playing environment. The list of priorities is updated on an ongoing basis as needs / issues arise. Examples include but are not limited to improvements / renovations to playing surface, artificial turf, courts, irrigation system, lighting, drainage infrastructure and replacement of worn and / or outdated sports field equipment such as bases, base inserts, pitching toes, home plates, soccer frames, soccer nets, etc. The funds will also be used for the repair and replacement of damaged or vandalized equipment in new parks.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 50 50 50 50 50 50 50 100 50 500 CRF (New) 25 25 25 25 25 25 25 25 25 25 250 DC 8 8 8 8 8 8 8 8 8 8 80

TOTAL 83 83 83 33 83 83 83 83 133 83 830 INFLATED 85 88 91 36 92 93 95 97 159 101 937

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 250-Waterloo Park - Bauer Parking Lot Upgrade ID# P01037 PSOFT # 150010 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Park Rehabilitation / Upgrade WARD: Ward 7 - Uptown The funding will be used to design and construct the Bauer Multi-Purpose Lot in Waterloo Park.

Background Information: The Waterloo Park Master Plan (2009) recognized the importance of the park frontage along the section of Father David Bauer Drive opposite the Waterloo Memorial Recreation Complex (WMRC). The park frontage along Father David Bauer Drive for the future Open Space Development was upgraded in 2014. The existing Bauer Lot forms part of the park frontage along Father David Bauer Drive. The lot is envisioned to be developed as a multi-purpose lot, to be able to facilitate both parking and occasional events / activities in the park. The lot is expected to be paved and lit.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

PUB-GEN 455 455

TOTAL 455 455 INFLATED 482 482

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 40 40 ONE TIME TOTAL 40 40

Page 21: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 251-Waterloo Park Lake Frontage Reconstruction ID# P01581 PSOFT # 190001 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Park Rehabilitation / Upgrade WARD: Ward 7 - Uptown Rehabilitation / Upgrades to the east side of Waterloo Park as required in response to the outcomes of the Silver Lake and Laurel Creek EA. Expected needs include decommissioning / demolition of Lions' Lagoon including the associated buildings, design/reinstatement of the shoreline area and design/construction of a new public gathering area along the reconfigured shoreline.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: IPPW-Engineering REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

PUB-GEN 2,272 2,272

TOTAL 2,272 2,272 INFLATED 2,339 2,339

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 50 50 ONE TIME TOTAL 50 50

PROJECT 252-Waterloo Park - Master Plan Implementation ID# P01038 PSOFT # 150011 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth/Rehab Split THEME: Park Rehabilitation / Upgrade WARD: Ward 7 - Uptown The funding will be used to implement the 2009 Waterloo Park Master Plan Project Initiatives. Background Information: Waterloo Park (WP) is a community park situated in the core of Uptown Waterloo. The Uptown District surrounding WP has undergone significant redevelopment and has been identified as a primary growth area in the City (WP is situated along several nodes and corridors planned for major growth). The Waterloo Park Master Plan (WPMP) 2009 outlines a plan to keep WP's programs and infrastructure current with the evolving context and needs of the community (extensive intensification, significant population increase in the Uptown Core, dramatic increase in district and community use along LRT route). A supporting implementation strategy was developed to allow Council and Staff to plan, fund and execute individual project initiatives over an extended period of time (20 Years) that collectively work toward the long term community vision identified for the park.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

DC 291 283 275 317 317 317 317 317 317 317 3,072 CRF (New) 194 189 183 214 214 214 214 214 214 214 2,066

TOTAL 486 472 458 532 532 532 532 532 532 532 5,138 INFLATED 500 500 500 575 587 599 611 623 635 648 5,778

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 10 10 10 10 10 10 10 10 10 90 ONE TIME TOTAL 10 10 10 10 10 10 10 10 10 90

Page 22: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 253-Westmount Sports Park Pedestrian Bridge ID# P01307 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Growth THEME: Sidewalks & Trails WARD: Ward 6 - Central-Columbia The funding will be used for the development (planning, design, and construction) of a new pedestrian bridge over Laurel Creek and the construction of associated trail connections.

Background Information: The Transportation Master Plan identifies a requirement for a trail connection over the Laurel Creek in close proximity to the Westmount Sports Park to connect the west-side trails with Laurel Trail. The bridge is a vital link in providing a trail connection between Uptown and numerous new and existing trails in the intensifying west side of the City.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: IPPW-Transportation REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 26 67 94 DC 238 607 845

TOTAL 264 674 939 INFLATED 298 790 1,088

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 42 42 ONE TIME TOTAL 42 42

PROJECT 254-Park Strategy Study ID# P01598 PSOFT # 160009 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Studies WARD: City Wide The funding will be used to update the Parks Strategy Study to define the priorities for the development, management and operation of public park resources across the City.

Background Information: The City of Waterloo has been going through significant growth, which combined with the accompanying social and environmental changes puts considerable pressure on the City's park related services. This highlights the need for a comprehensive overview of the City's park resources, the existing and future needs of the City's residents as well as the opportunities and constraints of meeting these needs. Comprehensive and informed planning is required in order to define the priorities for the development, management and operation of public park resources across the City. The Park Strategy will define priorities for the development / re-development, management and operation of public park resources.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 22 22 DC 67 67

TOTAL 89 89 INFLATED 109 109

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 23: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 255-Urban Forest Strategy ID# P01599 PSOFT # 0 STRATEGIC PLAN LINK: Sustainability and the Environment TYPE: Growth/Rehab Split THEME: Studies WARD: City Wide The funding will be used to develop an Urban Forest Strategy.

Background Information: The Draft Corporate Climate Change Adaptation Plan and the Parkland Strategy Research, Analysis & Visioning Report have identified the lack of an Urban Forest Strategy.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 63 63 DC 63 63

TOTAL 125 125 INFLATED 136 136

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 256-Waterloo Park Master Plan Update ID# P01600 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Growth THEME: Studies WARD: Ward 7 - Uptown The funding will be used to update the Waterloo Park Master Plan.

Background Information: The last Waterloo Park Master Plan Update was completed in 2009. The Uptown District surrounding WP has undergone significant redevelopment and has been identified as a primary growth area in the City (WP is situated along several nodes and corridors planned for major growth). The Waterloo Park Master Plan (WPMP) 2009 outlines a plan to keep WP's programs and infrastructure current with the evolving context and needs of the community (extensive intensification, significant population increase in the Uptown Core, dramatic increase in district and community use along LRT route). A supporting implementation strategy was developed to allow Council and Staff to plan, fund and execute individual project initiatives over an extended period of time (20 Years) that collectively work toward the long term community vision identified for the park.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 44 44 DC 131 131

TOTAL 175 175 INFLATED 189 189

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 24: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 257-West Side Recreation Facility Needs Analysis and Feasibility Study ID# P01346 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Studies WARD: Ward 2 - Northwest The Recreation and Leisure Services Master Plan recommends that considerations be made to review options associated with the potential extension of facilities and services to the west side of the City. While the YMCA-Library and the Westmount Sports Fields have or will meet current demand, no facilities, programming or services are currently planned for, nor has there been exploration of any options that may provide potential opportunities to residents of this area in the future. The review will outline the needs, associated costs and opportunities for providing community and recreation services to the growing community. In order to address population increases, 2008 master planning projected that new facilities and services may be required by approximately years 2025-2030 in order for the City to maintain existing service levels.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

PUB-GEN 41 41 DC 369 369

TOTAL 410 410 INFLATED 447 447

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 258-Emerald Ash Borer Management Plan Implemenation ID# P01308 PSOFT # 120060 STRATEGIC PLAN LINK: Sustainability and the Environment TYPE: Rehabilitation THEME: Tree Replacement WARD: City Wide The funding will be used for the removal and replanting of Ash trees along City streets and parks.

Background Information: The Emerald Ash Borer is a highly destructive invasive pest of ash trees. As the Ash Borer spreads throughout Waterloo it infests and kills all species of ash. The City will need to manage the removal and replanting of these trees. Currently, the City owns 5422 ash trees along the streets. Ash trees also comprise 15-30% of our woodlots.

SERVICE DELIVERY DIVISION: COMM-Environment & Parks IMPLEMENTATION DIVISION: COMM-Environment & Parks REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 300 400 400 100 300 300 100 500 500 300 3,200

TOTAL 300 400 400 100 300 300 100 500 500 300 3,200 INFLATED 309 424 436 108 331 338 115 586 598 366 3,610

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 25: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 260-Parkview Chapel-Niche Wall Additions ID# P01310 PSOFT # 160044 STRATEGIC PLAN LINK: Economic Growth & Development TYPE: Growth THEME: Facility Expansion WARD: Ward 5 - Southeast As the trend towards cremation continues to grow, this project expands existing niche inventory and creates new and unique memorialization options and revenue opportunities. This project aligns with recommendations of the Cemetery Services-Bechtel Park Master Plan. The benefit to the existing component of this project is 90% while the remainder will benefit anticipated growth. Additional niche installations help address growing needs related to increases in cemetery business and growth in population base within community.

SERVICE DELIVERY DIVISION: COMM-EPS-Cemeteries IMPLEMENTATION DIVISION: COMM-EPS-Cemeteries REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CEM 28 28 55 DC 3 3 6

TOTAL 31 31 61 INFLATED 33 34 68

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 1 1 2 ONE TIME TOTAL 1 1 2

PROJECT 261-Parkview Columbarium Features ID# P01311 PSOFT # 140008 STRATEGIC PLAN LINK: Economic Growth & Development TYPE: Growth THEME: Facility Expansion WARD: Ward 5 - Southeast This project includes the installation of Columbarium Niche units at Parkview Cemetery, including the Cremation Dedication Gardens. As the trend towards cremation continues to grow, this project expands existing niche inventory and creates new and unique memorialization options and revenue opportunities. This project aligns with the recommendations of the Cemetery Services-Bechtel Park Master Plan. The expected growth in population of 20% over the next 10 years, combined with anticipated demand from the existing population base, will necessitate a need for additional cemetery products and services. The anticipated new growth and existing demand rationalizes the expansion of cemetery inventories to meet these developing needs. The benefit to the existing component of this project is 90% while the remainder will benefit anticipated growth. Original installation was delayed pending a re-design of the project area to best align with current market opportunities.

SERVICE DELIVERY DIVISION: COMM-EPS-Cemeteries IMPLEMENTATION DIVISION: COMM-EPS-Cemeteries REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CEM 25 58 25 109 DC 3 6 3 11

TOTAL 28 64 28 120 INFLATED 30 74 34 138

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 1 1 1 3 ONE TIME TOTAL 1 1 1 3

Page 26: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 262-Parkview Cemetery Fence Replacement ID# P01313 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: Ward 5 - Southeast Fencing in Cemetery compound and some perimeter locations to be replaced as lifecycle is reached. Costs would include removal of existing and replacement of fencing and gates as required.

SERVICE DELIVERY DIVISION: COMM-EPS-Cemeteries IMPLEMENTATION DIVISION: COMM-EPS-Cemeteries REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CEM 77 77

TOTAL 77 77 INFLATED 88 88

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 263-Parkview Crematorium Retort Replacement ID# P01315 PSOFT # 180006 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: Ward 5 - Southeast Life cycle of current retorts has expired and machines are becoming costly to maintain and problematic to source components. Project covers the supply and installation of more efficient units.

SERVICE DELIVERY DIVISION: COMM-EPS-Cemeteries IMPLEMENTATION DIVISION: COMM-EPS-Cemeteries REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CEM 971 971

TOTAL 971 971 INFLATED 1,000 1,000

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 27: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 264-Parkview Crematorium Maintenance ID# P01314 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: Ward 5 - Southeast Project includes complete crematorium retort maintenance to the two units located at Parkview Crematorium. Rebuilds are typically required every four to five years and will depend on current retort replacement scheduled in 2020.

SERVICE DELIVERY DIVISION: COMM-EPS-Cemeteries IMPLEMENTATION DIVISION: COMM-EPS-Cemeteries REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CEM 43 43 86

TOTAL 43 43 86 INFLATED 47 49 96

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 265-Cemeteries Roadway Resurfacing ID# P01317 PSOFT # 180007 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Road Resurfacing WARD: Ward 5 - Southeast It is projected that Parkview and Mt.Hope Cemetery roadways will require resurfacing beginning in the year 2018. Project has been phased over 4 years.

SERVICE DELIVERY DIVISION: COMM-EPS-Cemeteries IMPLEMENTATION DIVISION: IPPW-Engineering REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CEM 60 60

TOTAL 60 60 INFLATED 64 64

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 28: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 270-Corporate Energy Management Implementation, Monitoring, and Reporting ID# P01360 PSOFT # 150017 STRATEGIC PLAN LINK: Sustainability and the Environment TYPE: Other THEME: Energy Management WARD: City Wide The Ontario Regulation 397/11 made under the Green Energy Act (GEA) 2009, mandates that the City of Waterloo report annually on energy consumption and greenhouse gas emissions for Corporate operations. The GEA also mandates that, the City of Waterloo prepare and implement a 5 year energy and greenhouse gas conservation and demand management plan for City-owned and operated facilities. The Corporate Energy and Greenhouse (GHG) Conservation and Demand Management Action Plan that meets this requirement was approved by City of Waterloo Council in 2013 and is in need of an update. Furthermore, the City of Waterloo is participating in two voluntary programs, the Federation of Canadian Municipalities’ Partners for Climate Protection (PCP) Program and Sustainable Waterloo Region's Regional Carbon Initiative (SWR RCI). In order to ensure continued success in the area of Corporate Energy Management, this funding request will ensure the ongoing implementation, monitoring, and reporting for the above programs are met. This funding may also be used for the following: 1. Measurement / verification of energy / water / greenhouse gas emission reductions as a result of system upgrades in City facilities. 2. Ongoing analysis of the gas and electricity procurement strategies. 3. The use of a utility software and sub-metering to track and further reduce energy / water consumption. 4. Develop and maintain infrastructure to meet current and projected needs. 5. The potential to evaluate new energy saving opportunities as they emerge.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 113 53 53 108 53 380

TOTAL 113 53 53 108 53 380 INFLATED 122 60 62 129 65 438

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 271-Green Building Policy Implementation ID# P01549 PSOFT # 0 STRATEGIC PLAN LINK: Sustainability and the Environment TYPE: Other THEME: Energy Management WARD: City Wide The City of Waterloo is committed to being a leader in demonstrating how the community can achieve GHG reduction, specifically, by striving for a community scope GHG emissions reduction target of 80% below 2010 levels by 2050. With this vision, the City intends to strive for a similar reduction target for City-owned buildings. To achieve this target, over the next 10 years City-owned buildings will be retrofitted / renovated with energy upgrades and green initiatives to reduce GHG. This funding will be used to initiate GHG reduction strategies in existing City facilities. Currently WMRC, AMCC and WCH are under investigation for potential GHG reduction strategies, however more buildings will be assessed for potential GHG reductions later this year. Note: The money spent through this project shall be quantifiable at the end through annual GHG and energy conservation reports. Co-op Student: this project would also require a coop student position, to help organize/coordinate the expected work. $80K is expected for this position.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 866 500 403 177 522 427 586 3,482 CIRRF (Rehab/Repl) 207 139 345

TOTAL 866 500 610 139 177 522 427 586 3,827 INFLATED 892 530 665 150 200 600 500 700 4,236

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 29: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 272-Fuel Tank Replacement-Service Centre ID# P01552 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Equipment Replacement WARD: City Wide Replacement of 3 underground fuel tanks at Waterloo Service Centre. The existing tanks are 30 years old. The project would require an initial assessment to determine extent of any required remediation. Project timelines are a projection only - staff is currently undertaking some investigations relating to the lifespan of the existing tanks. Total cost is an estimate only - degree of contaminants would impact total project costs based on remediation needs.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: IPPW-Engineering REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 100 496 596

TOTAL 100 496 596 INFLATED 110 559 669

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 273-Material Storage Implementation ID# P01362 PSOFT # 190016 STRATEGIC PLAN LINK: Supporting the Strategic Plan Guiding Principles TYPE: Growth THEME: Facility Expansion WARD: City Wide

As the natural building storage space in existing facilities has become insufficient due to growth, it is essential to centralize a location or two to accommodate the storage needs of various facilities. These storage facilities will be used for multi-purpose needs and will be built with minimal amenities (heating, lighting, and water).

At minimum, two locations will be considered for these new facilities: RIM Park and the Waterloo Service Centre. If feasible, a third location will be considered.

Assume a project start year of 2021, 2023, and 2029. Also, assume that each facility will be approximately 5,000 sq ft to 10,000 sq ft in size.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 25 27 27 79 DC 469 514 518 1,500

TOTAL 493 541 545 1,579 INFLATED 523 586 664 1,773

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 14 14 ONE TIME TOTAL 14 14

Page 30: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 274-Mini Operation Centre on the West Side ID# P01361 PSOFT # 0 STRATEGIC PLAN LINK: Economic Growth & Development TYPE: Growth THEME: Facility Expansion WARD: Ward 2 - Northwest

This Operation Centre would be constructed at a small scale, essentially to dispatch crews and vehicles to efficiently serve the west-side of the City. The facility is envisioned to have a mini salt shed, material storage bunkers, truck parking, a horticultural transfer station, an above ground fuel station, and a small office space.

The timing of this project would ideally align with possible construction of a new west-side Fire Station (dependent on Fire Master Plan requirements).

The cost of this project sheet is for construction only. Land use for this project is considered as part of future city owned development sites on the west-side of the City.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

DC 186 1,386 1,572 CRF (New) 10 180 190 PPC 2,035 2,035

TOTAL 196 3,601 3,797 INFLATED 214 4,056 4,269

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 56 56 ONE TIME TOTAL 56 56

PROJECT 275-Accessibility and Safety Upgrades at City Facilities ID# P01561 PSOFT # 190017 STRATEGIC PLAN LINK: Equity, Inclusion and a Sense of Belonging TYPE: Other THEME: Facility Refurbishment WARD: City Wide

In order to further its commitment to remove barriers for citizens with disabilities and to ensure compliance with the Accessibility for Ontarians with Disabilities Act, 2005 (AODA), the City of Waterloo initiated the Facility Accessibility Audit Project. The goal of this project was to systematically plan for the elimination of barriers for those with disabilities. Accessibility Audit Recommendations (Multiple Buildings): Systematically eliminate accessibility barriers at City-facilities. The work plan is based on the Accessibility study that was completed in 2008.

Health and Safety Upgrades at City Facilities (Multiple Buildings): Engineering assessments and implementation of corrective actions to reduce health and safety concerns with existing mezzanines, ladders, racks, roof tie-offs, and confined spaces at City-owned facilities.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 80 80 117 102 300 678 EMPDV 32 32 32 32 32 32 32 32 32 33 319

TOTAL 111 111 148 134 332 32 32 32 32 33 996 INFLATED 115 118 162 145 366 36 37 37 38 40 1,093

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 31: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 276-Albert McCormick Community Centre (AMCC) - Upgrades & Reconfiguration ID# P01562 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: Ward 4 - Northeast The primary function of the Albert McCormick Community Centre is the two indoor ice skating rinks. The Facility also consists change rooms, administrative offices, meeting rooms and storage for the various youth hockey and other seasonal athletic programs. The Library building adjoints the East Wing Building of the Albert McCormick Community Centre. The mainfunction of the facility is a city library. The purpose of the project is to build a multi purpose community facility to meet the present and future needs of the local community.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 150 1,500 835 2,485

TOTAL 150 1,500 835 2,485 INFLATED 162 1,656 940 2,758

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 277-Button Factory Elevator Installation and Accessible Washrooms ID# P01363 PSOFT # 0 STRATEGIC PLAN LINK: Equity, Inclusion and a Sense of Belonging TYPE: Rehabilitation THEME: Facility Refurbishment WARD: City Wide In order to further its commitment in the removal of barriers to citizens with disabilities and to ensure compliance with the Accessibility for Ontarians with Disabilities Act, 2005 (AODA), the City of Waterloo initiated the Facility Accessibility Audit Project. The goal upon completion of this project will be that the City of Waterloo be able to systematically plan for the elimination of barriers for those with disabilities. One area of great importance to both the City of Waterloo and the Waterloo Community Art Centre (WCAC) is to install a new elevator within the Button Factory, in order to ensure the building and its community services are fully accessible. In addition, n February 10, 2020, Council approved additional funding for this project to also provide for accessible washrooms at this facility.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 223 231 454 CRF (New) 277 277

TOTAL 500 231 731 INFLATED 515 250 765

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 1 1 1 1 1 1 1 4 ONE TIME TOTAL 1 1 1 1 1 1 1 4

Page 32: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 278-City Centre Upkeep Maintenance ID# P01562 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: Ward 7 - Uptown This funding is for capital projects over and above the current operating budget.

Projects would include: general mechanical and electrical upgrades/repairs, building envelope upgrades / repairs, accessibility improvements, removal and disposal of the exterior interlock bricks to create a courtyard in front of the building for ceremonies and special events, interior upgrades to increase aesthetic appeal for guests and potential new tenants, and upgrading the building to return it to a Class A commercial building.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 93 93 93 93 93 464

TOTAL 93 93 93 93 93 464 INFLATED 101 103 108 111 113 536

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 279-Corporate Space Planning ID# P01007 PSOFT # 140162 STRATEGIC PLAN LINK: Supporting the Strategic Plan Guiding Principles TYPE: Other THEME: Facility Refurbishment WARD: City Wide Corporate Space Planning funding is allocated for workspace renovations that benefit the City of Waterloo for, a) service delivery efficiencies, b) functional work spaces that meet current standards. The 3-year budget allocations will fund the priority space renovation updates to City Hall and RIM Park. Funding to be used as follows: 2020 allocate $2,071,000 to: a) Move Advanis to Sapphire space b) Renovate Advanis space for new tenant c) Renovate Hicks Morley space for new tenant d) Decommission IMTS space at City Hall for future use e) Move asset management from AMCC to City Hall f) Council Chambers and Erb meeting room upgrades 2021 allocate $1,161,000 to: a) Council Chambers and Erb meeting room upgrades b) WSC expansion for more staff space. 2022 allocate $695,000 to: a) WSC expansion. Remaining funds after 2022 will be allocated for WMRC upgrades and phase 2 City hall upgrades.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 729 663 1,392 EMPDV 86 88 90 85 82 78 76 73 71 71 801 CIRRF (Rehab/Repl) 1,197 344 548 50 2,139

TOTAL 2,012 1,096 638 85 132 78 76 73 71 71 4,332 INFLATED 2,071 1,161 695 92 146 88 88 86 85 87 4,599

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 33: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 280-Enterprise Wide Security Upgrades ID# P01364 PSOFT # 120023 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Other THEME: Facility Refurbishment WARD: City Wide

The City of Waterloo hired a Security Consultant to complete an assessment of all City-owned assets. Included in the assessment of City facilities was: hardware, software, programs / procedures, and vulnerabilities. Upon completion of the assessment, recommendations were provided to address any deficiencies. All recommendations were rated by risk level (high, medium, and low) and are to be implemented over a 10-year period. These upgrades will contribute to safe and secure facilities for staff and visitors. Funds for this project will be used for a variety of security related items, including: card access, software upgrades, staff training, loss prevention, and damage prevention across the entire Corporation. High-priority items have been addressed in previous capital work; therefore, this funding will be used to address the remaining items.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

EMPDV 86 88 90 85 82 78 76 73 75 75 809

TOTAL 86 88 90 85 82 78 76 73 75 75 809 INFLATED 89 94 98 92 90 88 88 86 89 91 905

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 281-Facility Condition Assessments and Re-Commissioning Services ID# P01563 PSOFT # 150072 STRATEGIC PLAN LINK: Supporting the Strategic Plan Guiding Principles TYPE: Rehabilitation THEME: Facility Refurbishment WARD: City Wide

Facility Condition Assessments of City-owned facilities is an important capital planning technique and is also required in order to fully understand and plan for end-of-life building system replacements.

Facility Condition Assessment Program: Condition Assessments of City-owned facilities including VFA updates, engineering studies, hazardous material audits, etc.

Re-Commissioning of Mechanical and Electrical Systems at City Facilities: Re-commissioning of Mechanical and Electrical systems at City-owned facilities to decrease energy use and greenhouse gas emissions.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 51 61 54 106 51 51 51 51 50 526 CIRRF (Rehab/Repl) 51 106 106 51 51 51 416

TOTAL 51 112 160 106 106 102 102 102 51 50 942 INFLATED 52 119 175 115 117 115 117 120 61 61 1,051

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 34: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 282-Facility Infrastructure Replacement and Rehabilitation Needs ID# P01564 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: City Wide Based on CORP2019-075 Long Term Financial Plan Update, the average annual funding gap for Tax Base assets is estimated to be approx. $17M. Council previously directed staff via CORP2018-011 to consider increased infrastructure funding opportunities as part of the 2020-2022 budget. For 2020, a .8% increase in infrastructure funding (allocated to CIRRF) is being recommended with 0.3% funded from a tax increase above inflation and 0.5% funded through a portion of Waterloo North Hydro Dividend revenue being directed to CIRRF. For 2021 a .9% increase and 2022 a 1.5% increase in infrastructure funding (allocated to CIRRF) is being recommended funded from a tax increase above inflation. The increased infrastructure funding is being allocated to the major Asset Classes based on a weighted percentage need. The Facility Infrastructure Replacement and Rehabilitation Needs project will be used to fund Facility Asset priorities that couldn’t be accommodated within the currently available funding including but not limited to Facility Refurbishment, Energy Management and Equipment Replacement. The increased infrastructure funding projects are classified as Non-Routine in nature and the subject matter experts will return at a later date with a prioritized list of candidate projects to be advanced via this funding.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 30 249 606 610 598 587 575 564 553 542 4,913

TOTAL 30 249 606 610 598 587 575 564 553 542 4,913 INFLATED 31 264 661 661 661 661 661 661 661 661 5,579

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 283-Heritage Buildings Maintenance Plan ID# P01564 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: City Wide The funding will allow to update site-specific conditions for each asset and will address any immediate threats to their structural stability

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 367 367

TOTAL 367 367 INFLATED 400 400

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 35: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 284-Large Scale Capital Repairs - Program - High Priority ID# P01565 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: City Wide The projects listed below are large scale (over $100k) capital expenditures. This includes rehabilitation/replacement work for existing assets that have reached the end of their serviceable life, as well as new assets that are required to maintain/improve existing service levels/operations at these facilities such as: 2021: The Waterloo Memorial Recreation Complex Pool Floor Rehabilitation. To be executed as part of the larger WMRC expansion and rehabilitation. 2020-2028: Mechanical and Electrical System Upgrades and Replacements (Multiple Buildings): Upgrade and replacement of existing Mechanical and Electrical equipment/systems (at multiple facilities) that is required to maintain existing service levels at these facilities. 2028: Waterloo Service Centre - Phase 2 Upgrades (Multiple Buildings): This project includes various upgrades work that was not completed during Phase 1 of this project due to budget constraints.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 635 820 389 389 389 389 389 389 389 4,178 CRF (New) 740 740

TOTAL 635 820 389 389 389 389 389 1,130 389 4,919 INFLATED 653 869 421 430 438 447 456 1,350 474 5,538

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 285-RIM Park Parking Lot Replacement ID# P01365 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: Ward 4 - Northeast 2022 & 2024: RIM Park Parking Lot Replacement - The existing asphalt paving and granular sub-base is deteriorated and in need of replacement. Includes engineering design work in 2022 and construction in 2022 and 2024.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

GTR 800 100 881 1,781

TOTAL 800 100 881 1,781 INFLATED 873 108 973 1,954

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 36: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 286-Roofing Replacement and Rehabilitation - Program ID# P01566 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: City Wide The existing roofing at several major City facilities is reaching the end (or is already beyond) its current lifespan. Given the age and condition of these roofs, major rehabilitation and replacement is required, in order to maintain the building envelope in a serviceable condition. Manulife Financial Sportsplex & Healthy Living Centre (RIM Park) - Flat Roof Replacement & Metal Roof Recoating. 2020-2024, 2027 & 2028 Waterloo City Centre - Roof replacement & metal flashing replacement, 2026 & 2027 Main Library - Roof replacement - 2027 Waterloo Service Centre - Multiple building roof replacements - 2020,2027 - 2029 Moses Springer - 2027, Fire Station 2 and Carnegie Library - 2028 Grey Silo Partially funded in 2019. Rest of funding scheduled in 2020

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 577 1,017 1,734 3,301 2,226 280 9,136 GTR 250 250 1,017 1,517

TOTAL 577 250 250 1,017 1,017 1,734 3,301 2,226 280 10,654 INFLATED 594 265 273 1,101 1,123 1,992 3,868 2,661 341 12,218

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 287-Small Scale Capital Repairs - High Priority ID# P01567 PSOFT # 190021 STRATEGIC PLAN LINK: Supporting the Strategic Plan Guiding Principles TYPE: Rehabilitation THEME: Facility Refurbishment WARD: City Wide General Infrastructure Renewal Replacement Program - Mehanical, Electrical, and Controls & Site, Architectural, and Structural: To address those high priority capital requirements/replacements identified in the Facility Condition Assessments (of mechanical, electrical, and controls nature and of site, archtectural, and structural nature), where the project details are not specifically identified in the capital budget/forecast. This funding is primarily geared towards multi-use buildings (facilities with ice rinks, sport surfaces, swimming pools, etc.) which account for around 50% of City-owned facilities. This work has a direct impact on the successful operations of these facilities and the programming that takes place within.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 199 195 157 487 628 421 196 308 630 3,221

TOTAL 199 195 157 487 628 421 196 308 630 3,221 INFLATED 205 207 171 527 693 474 225 361 753 3,616

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 37: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 288-Maximo - Deployment and System Maintenance ID# P01611 PSOFT # 110022 STRATEGIC PLAN LINK: Supporting the Strategic Plan Guiding Principles TYPE: Other THEME: Technology Refresh / Upgrades WARD: City Wide

The Maximo Work Management System Implementation Project is a multi-year initiative that intends to fully utilize the software across Facilities, Fleet, Fire, Community Services, and Integrated Planning & Public Works Operations. The project continues to improve work flows, preventative maintenance capabilities, work tracking and reporting for performance metrics, and field inspections. Information from Maximo is a critical feed to the Asset Management program and the coming years is improving and strengthening this process and the data quality. There continues to be expansion of functionality, with additional workflows being incorporated for all areas. Examples include Playground Inspections, Sanitary Sewer Backflow work orders, and others. Ongoing maintenance is required for system upgrades, consultant support for improvements, and license expansion to support program areas.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 91 91 91 91 364 WAT-CAP 53 61 61 61 61 61 61 61 61 61 605 SEW-CAP 53 61 61 61 61 61 61 61 61 61 605 SWM 53 61 61 61 61 61 61 61 61 61 605 CIRRF (Rehab/Repl) 266 91 91 91 539

TOTAL 159 184 450 275 275 275 275 275 275 275 2,718 INFLATED 163 195 491 298 304 310 316 322 329 335 3,062

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 289-Maximo - Implementation and Functionality Configuration ID# P01612 PSOFT # 110022 STRATEGIC PLAN LINK: Supporting the Strategic Plan Guiding Principles TYPE: Other THEME: Technology Refresh / Upgrades WARD: City Wide

The Maximo Work Management System Implementation Project is a multi-year initiative that intends to fully utilize the software across Facilities, Fleet, Fire, Community Services, and Integrated Planning & Public Works Operations. The project continues to improve work flows, preventative maintenance capabilities, work tracking and reporting for performance metrics, and field inspections. Information from Maximo is a critical feed to the Asset Management program, and the coming years is improving and strengthening this process and the data quality.

SERVICE DELIVERY DIVISION: COMM-Fac.Design & Mgmt IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 66 50 34 150 WAT-CAP 42 33 75 SEW-CAP 42 33 75 SWM 42 33 75

TOTAL 66 177 133 376 INFLATED 68 199 159 426

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 38: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 300-Defibrillator Replacement ID# P01318 PSOFT # 180008 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Equipment Replacement WARD: City Wide In addition to fire and rescue response, all personnel are trained as emergency medical responders and therefore contribute to tiered response with Waterloo Region Paramedic Services. Presently, there are defibrillators on all front line fire trucks and support vehicles that will require replacement. Defibrillators are used when responding to a patient who is vital-signs absent. Approximately 65% to 70% of Fire Services responses are medically related and early defibrillation is a definitive link to the chain of human survival. The defibrillators in service today are on a 7 year replacement schedule and will be jointly purchased with Waterloo Region Paramedic Services if applicable at the time of replacement.

SERVICE DELIVERY DIVISION: COMM-Fire IMPLEMENTATION DIVISION: COMM-Fire REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 60 60

TOTAL 60 60 INFLATED 69 69

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 301-Hazardous Materials Specialized Equipment ID# P01320 PSOFT # 140012 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Equipment Replacement WARD: City Wide This project sheet supports Fire Services ability to replace specialized rescue equipment such as chemical suits for training and emergency response. Additionally, gas detectors, portable shelters, and decontamination equipment will require replacement to ensure equipment is current to available technology and that it is in good working order.

SERVICE DELIVERY DIVISION: COMM-Fire IMPLEMENTATION DIVISION: COMM-Fire REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 36 40 76

TOTAL 36 40 76 INFLATED 39 48 87

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 39: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 302-Personal Protective Equipment ID# P01321 PSOFT # 110075 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Equipment Replacement WARD: City Wide This project links to the Occupational Health and Safety Act. This project consists of the replacement of personal protective turnout equipment (PPE) which has an approved lifespan of ten years as per the National Fire Protection Association Standards. Each fire fighter requires protective clothing that is certified for entry into fire, rescue and hazardous and non-hazardous conditions including extrication. Currently each firefighter is issued one set of gear. Gear that is damaged and requires third party cleaning and repair work is sent off site leaving firefighters without certified gear to wear. This project will allow each firefighter to have access to a primary set of PPE and share spare of gear to ensure a set of certified gear is available at all times (this is not a complete second set inventory, but rather an ongoing inventory of 7 year replacement (for primary PPE) , and a 3 year reserve of all PPE (shared PPE). This project will ensure the City is meeting its obligations under the OH&S Act that equipment be maintained in good condition as per the manufacturers requirements. The equipment is inspected yearly and will require replacement at the 10 year time frame. This project now includes funding for the replacement of all firefighter PPE that require the 10 year regulated replacement of structural firefighting helmets, and structural firefighting boots.

SERVICE DELIVERY DIVISION: COMM-Fire IMPLEMENTATION DIVISION: COMM-Fire REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 93 121 93 142 97 57 57 57 57 379 1,155

TOTAL 93 121 93 142 97 57 57 57 57 379 1,155 INFLATED 96 128 101 154 107 65 66 67 69 462 1,315

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 303-Self Contained Breathing Apparatus ID# P01333 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Equipment Replacement WARD: City Wide Self-contained Breathing Apparatus Cylinders (SCBA) are utilized by firefighters while performing firefighting and interior search and rescue operations as well as hazardous materials incidents. SCBA’s are available on each front-line fire apparatus and specialized response while firefighters are issued individual face pieces for health, safety and enhanced personal protection. All SCBA must comply with CSA and NFPA standards and are expected to be purchased jointly with area fire services.

SERVICE DELIVERY DIVISION: COMM-Fire IMPLEMENTATION DIVISION: COMM-Fire REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 601 601

TOTAL 601 601 INFLATED 636 636

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 40: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 304-Fire Rescue Expansion ID# P01335 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Facility Expansion WARD: Ward 1 - Southwest If the Master Fire Plan results in Councils approval of a new fire station and / or additional staffing, this key initiative will address Fire Rescue Services ability to meet Council's approved five minute response time requirement across the City. The current study, identified in City of Waterloo 2019 and 2020-2022 Business Plans, is advancing following the completion of a Fire Underwriter Survey review in 2019 coupled the need to maintain fire services ability to effectively respond to emergencies and changing risk in our community such as response to high-rise emergencies. This project will also include the construction of a mechanical service bay and hoist system due to an increase in frontline fire trucks, including the need to enhance preventative maintenance programs due to the impacts on all equipment secondary to increasing emergency response call volumes. The new fore station will be designed and constructed in accordance with the City of Waterloo's Green Building Policy (Corporate Policy A-33).

SERVICE DELIVERY DIVISION: COMM-Fire IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

DC 1,392 1,469 2,861 Debt 6,422 6,422

TOTAL 1,392 7,891 9,283 INFLATED 1,507 8,712 10,219

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 1,074 1,074 1,074 1,074 4,296 ONE TIME TOTAL 1,074 1,074 1,074 1,074 4,296

PROJECT 305-Personal Protective Equipment and Uniforms (New personnel) ID# P01336 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Facility Expansion WARD: Ward 1 - Southwest Personal protective equipment is dependent on increasing staff when fire station re-occupancy or a new fire station is built. The completion of a Fire Underwriter Survey review in 2019 coupled the need to maintain fire services ability to effectively respond to emergencies, and changing risk in our community. This project links to the Occupational Health and Safety Act. This project consists of the replacement of personal protective turnout equipment (PPE) which has an approved lifespan of ten years as per the National Fire Protection Association Standards. Each fire fighter requires protective clothing that is certified for entry into fire, rescue and hazardous and non-hazardous conditions including extrication. Currently each firefighter is issued one set of gear. Gear that is damaged and requires third party cleaning and repair work is sent off site leaving firefighters without certified gear to wear. This project will allow each firefighter to have access to a primary set of PPE and share spare of gear to ensure a set of certified gear is available at all times (this is not a complete second set of inventory, but rather an ongoing inventory of 7 year replacement (for primary PPE) , and a 3 year reserve of all PPE (shared PPE). This project will ensure the City is meeting its obligations under the OH&S Act that equipment be maintained in good condition as per the manufacturers requirements. The equipment is inspected yearly and will require replacement at the 10 year time frame.

SERVICE DELIVERY DIVISION: COMM-Fire IMPLEMENTATION DIVISION: COMM-Fire REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

DC 23 113 136

TOTAL 23 113 136 INFLATED 25 125 150

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 41: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 306-Storage Facility Space ID# P01559 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Facility Expansion WARD: City Wide Additional storage space is required as growing needs for vehicles, equipment and tools is maximizing existing space. Over the years additional equipment has been added to maintain safety in the community and allow firefighters to accomplish their duties. This additional equipment has slowly been taking up all available space and it is at the point where additional storage capacity is required. This storage space will be approximately 2000 sq. ft. located on site at Fire Station 1 which was built in 1966. This facility will need to be in close proximity to this location for access to the storage. Along with increasing storage space, some alterations will be made to the interior building space moving a self-contained breathing-apparatus refilling station and air compressor to reduce noise and risk of hearing loss for health and safety reasons.

SERVICE DELIVERY DIVISION: COMM-Fire IMPLEMENTATION DIVISION: COMM-Fac.Design & Mgmt REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

DC 318 318

TOTAL 318 318 INFLATED 327 327

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 307-Fire Prevention Officer Equipment and Vehicle ID# P01343 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Fleet Management WARD: City Wide The purpose of one additional Fire Prevention Officer is to assist the current team in managing risk and legislated requirements of the Fire Protection and Prevention Act such as the vulnerable occupancy program. This new position will immediately address known risks associated with open property files and outstanding orders toward a proactive approach to achieve goals and objectives outlined in the Provincially mandated Simplified Risk Assessment. This position will also contribute to the expansion of public education programming to reach aging, diverse and student populations in the City of Waterloo. Capital funds for this project would support the purchase of requisite resources such as a desk, computer, uniforms, investigative and personal protective equipment, radio and a vehicle.

SERVICE DELIVERY DIVISION: COMM-Fire IMPLEMENTATION DIVISION: COMM-Fire REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

DC 45 45

TOTAL 45 45 INFLATED 49 49

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 42: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 308-New Fire Pumper-Rescue Quint ID# P01337 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Fleet Management WARD: Ward 1 - Southwest If the Master Fire Plan results in Councils approval of a new fire station and / or additional staffing, a new pumper-rescue quint fire truck is required for emergency response. With the advancement of a new fire station and / or additional staffing a new pumper would become one of eight front line fire apparatus as part of the emergency response fleet for the City of Waterloo. A pumper-rescue-quint is an example of an efficient fire apparatus because it combines firefighting, medical, and specialized rescue tools and equipment in addition to a mounted aerial ladder. Pumper rescues have a permanently mounted fire pump capable of pumping at least 3,000 LPM; this type of truck has the capability to support first response to all core business functions such as fire incidents, emergency medical response, and motor vehicle collisions, in addition to elevated rescue and fire operations.

SERVICE DELIVERY DIVISION: COMM-Fire IMPLEMENTATION DIVISION: COMM-Fire REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

DC 1,155 1,155

TOTAL 1,155 1,155 INFLATED 1,250 1,250

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 24 24 ONE TIME TOTAL 24 24

PROJECT 309-New Fire Pumper-Rescue Quint Equipment ID# P01338 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Growth THEME: Fleet Management WARD: Ward 1 - Southwest If the Master Fire Plan results in Councils approval of a new fire station and / or additional staffing, a new pumper-rescue quint fire truck is required for emergency response; in addition, this first response vehicle will require specialized tools and equipment for emergency response. A pumper-rescue quint will serve to respond to fire and medical emergencies in the City of Waterloo and will require specialized equipment such as radios, a defibrillator, self-contained breathing apparatus, thermal imaging camera, gas detection, fire suppression and heavy rescue / extrication equipment.

SERVICE DELIVERY DIVISION: COMM-Fire IMPLEMENTATION DIVISION: COMM-Fire REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

DC 200 200

TOTAL 200 200 INFLATED 216 216

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 4 4 ONE TIME TOTAL 4 4

Page 43: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 310-Mobile Workstations ID# P01613 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Rehabilitation THEME: Technology Refresh / Upgrades WARD: City Wide Mobile workstations are installed on all frontline fire apparatus and primary emergency response vehicles. Mobile work stations provide firefighters with real time incident information contributing to civilian and firefighter safety. Other features of mobile workstations include an automatic vehicle locator (AVL) that ensures the closest unit is dispatched to the incident location in addition to directional routing provided via a global positioning system (GPS) feature. Mobile work stations contribute to more accurate time benchmarking as the fire officer has full control of incident segment benchmarking versus radio communication to spontaneously benchmark incident segments while managing other critical communication tasks.

SERVICE DELIVERY DIVISION: COMM-Fire IMPLEMENTATION DIVISION: COMM-Fire REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 66 66

TOTAL 66 66 INFLATED 75 75

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING 25 25 ONE TIME TOTAL 25 25

PROJECT 320-Rental Housing Vehicle Replacement ID# P01349 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Fleet Management WARD: City Wide Fire Prevention vehicles are to be replaced every 7 years in accordance with the vehicle replacement schedule. The subject vehicle proposed for replacement is utilized by the Fire inspector for inspections and public education related to the Rental Housing Licensing program and assists in meeting our legislated requirements under the Fire Protection and Prevention Act.

SERVICE DELIVERY DIVISION: COMM-Municipal Enforcement IMPLEMENTATION DIVISION: CORP-Fleet & Proc. REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

RHR 30 30

TOTAL 30 30 INFLATED 31 31

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 44: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 321-External Call Centre Support-Enforcement Services Pilot ID# P01359 PSOFT # 170013 STRATEGIC PLAN LINK: Supporting the Strategic Plan Guiding Principles TYPE: Other THEME: New Programs WARD: City Wide Municipal Enforcement Services, in coordination with Corporate Communications, wishes to pursue an agreement with the City of Kitchener, in order to improve our services and responses to the residents of Waterloo. The MES Division is challenged in that there is limited ability to respond to concerns and calls for service from the community, after normal business hours. A potential agreement with the City of Kitchener, to use their Corporate Contact Center, to respond to phone inquiries after normal business hours is seen as a potentially significant improvement in customer service. These capital funds would be used to scope the project and map out business processes in advance of implementing and “going live” with such an agreement.

SERVICE DELIVERY DIVISION: COMM-Municipal Enforcement IMPLEMENTATION DIVISION: COMM-Municipal Enforcement REPORTING CRITERIA: Non-Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 97 97

TOTAL 97 97 INFLATED 100 100

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 330-Master Plan Implementation ID# P01560 PSOFT # 110009 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Strategic THEME: Facility Expansion WARD: City Wide The Corporate Strategic Plan, the Recreation and Leisure Services Master Plan and various other plans include recommendations that necessitate actions requiring funding support. In the next several years, while potentially refocused following a Recreation and Leisure Services Master Plan refresh scheduled for 2020, funding will be required to systematically support initiatives, including but not limited to, in partnership with a City affiliated group, a potential modification to the beach volleyball courts at RIM Park in 2020 to 2022. Funding is also required to support the Recreation and Facility Services Master Plan refresh in 2020 as it is anticipated that the plan will be facilitated via contracted services. Future projects will be confirmed following the master plan refresh.

SERVICE DELIVERY DIVISION: COMM-Recreation Services IMPLEMENTATION DIVISION: COMM-Recreation Services REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 71 80 41 250 250 250 250 1,192

TOTAL 71 80 41 250 250 250 250 1,192 INFLATED 73 85 45 282 287 293 299 1,363

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 45: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 331-Facility and Programming Equipment ID# P01568 PSOFT # 140164 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: City Wide Complementing the Banquet and Meeting Room project, this program supports the purchase and replacement of specific equipment used to support day-to-day programming and operational requirements within Recreation Services facilities. Supported by the Facility Operations Strategy, approved by Council as part of the 2012 budget process, projects incorporated as part of this initiative were historically funded by the Facility Operations Reserve. The reserve was funded via annual contributions from the operating budget supported via levies integrated into event agreements, facility and food service fees which have now been redirected to CIRRF. As part of the strategy, certain user fees were adjusted an additional 0.5% in years 2012, 2013 and 2014 to better align contributions with future requirements. Planned purchases and / or replacements in 2020 to 2022 may include but not be limited to an ice edger purchase, hockey net replacements, plywood flooring replacement, water wheelchair replacement and necessary operational equipment for the delivery of recreation programs and opportunities.

SERVICE DELIVERY DIVISION: COMM-Recreation Services IMPLEMENTATION DIVISION: COMM-Recreation Services REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 49 51 52 54 55 57 58 60 61 115 613

TOTAL 49 51 52 54 55 57 58 60 61 115 613 INFLATED 50 54 57 58 61 64 67 70 73 140 696

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 332-Facility Banquet and Meeting Room Furnishings and Equipment ID# P01569 PSOFT # 110007 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: City Wide Project includes the replacement of aging program equipment, tables, chairs, electronic / technical equipment, lighting and associated amenities in banquet rooms, meeting rooms and other various spaces throughout Recreation Services facilities. The furnishings, equipment and amenities require ongoing replacement and in some cases, modification and enhancement, in order to continue to offer services to residents, affiliated groups and businesses in the region who choose to utilize City facilities for various meetings and events. Project also includes infrastructure refurbishment and enhancement where required (i.e. painting, flooring replacement ceiling tiles replacement, dividers, etc.).

SERVICE DELIVERY DIVISION: COMM-Recreation Services IMPLEMENTATION DIVISION: COMM-Recreation Services REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 43 49 51 80 81 83 84 164 164 798

TOTAL 43 49 51 80 81 83 84 164 164 798 INFLATED 44 52 56 88 91 95 99 196 200 920

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 46: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 333-Facility Bleacher and Player's Bench Replacement ID# P01353 PSOFT # 180012 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: City Wide Project includes the refurbishment and / or replacement of aging bleachers, players benches and associated accessories at the RIM Park Manulife Financial Sportsplex and Healthy Living Centre and at other indoor recreation facilities.

SERVICE DELIVERY DIVISION: COMM-Recreation Services IMPLEMENTATION DIVISION: COMM-Recreation Services REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 62 62

TOTAL 62 62 INFLATED 69 69

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 334-Facility Marquee Sign Purchases, Refurbishing and Replacement ID# P01354 PSOFT # 150016 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: City Wide Project includes the purchase, refurbishing and / or the replacement where required of marquee signs and / or hardware at various City facilities. Digital and other signage enhances the customer experience and assists staff, building tenants, City affiliated groups and others in better promoting events and other activities at City facilities.

SERVICE DELIVERY DIVISION: COMM-Recreation Services IMPLEMENTATION DIVISION: COMM-Recreation Services REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 31 31 31 31 31 153

TOTAL 31 31 31 31 31 153 INFLATED 31 32 33 34 36 167

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 47: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 335-Facility Scoreclock Refurbishing and/or Replacement ID# P01355 PSOFT # 0 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: City Wide Project includes the refurbishing and / or the replacement of aging scoreclocks at various City facilities including the Waterloo Memorial Recreation Complex and RIM Park.

SERVICE DELIVERY DIVISION: COMM-Recreation Services IMPLEMENTATION DIVISION: COMM-Recreation Services REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 360 128 487

TOTAL 360 128 487 INFLATED 370 146 517

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

PROJECT 336-Protective Covering for Athletic/Arena Surfaces ID# P01356 PSOFT # 150005 STRATEGIC PLAN LINK: Infrastructure Renewal TYPE: Rehabilitation THEME: Facility Refurbishment WARD: City Wide In order for City facilities to host and / or support various events, temporary flooring is often required to cover and protect existing surfaces. Replacement of the aged and deteriorating covering is required. With advances in products and materials, an efficiency related to a changed product may be achieved over the agreed current product and method of installation.

SERVICE DELIVERY DIVISION: COMM-Recreation Services IMPLEMENTATION DIVISION: COMM-Recreation Services REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CIRRF (Rehab/Repl) 102 102

TOTAL 102 102 INFLATED 111 111

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL

Page 48: Community Service Final Project Sheets · contribution to the Wilfrid Laurier University Stadium Project ICIP grant submission and the University of Waterloo Columbia Icefield Expansion

PROJECT 337-Master Plan and Recreational Trends Study ID# P01357 PSOFT # 0 STRATEGIC PLAN LINK: Healthy Community and Resilient Neighbourhoods TYPE: Other THEME: Studies WARD: City Wide The Recreation and Leisure Services Master Plan, approved in 2008, is scheduled for an update. Further, community recreation and leisure is an evolving area of municipal service that can be significantly affected by trends, including population growth, demographic changes, fluctuating market conditions, and as a result of other community strategies and initiatives such as the impact of LRT and downtown intensification, etc. To keep pace with this changing environment, it is recommended that the department conduct recreation needs and trend studies to identify and respond to any changing shifts in community need. The Trends Study research encompasses improved demographic data, community polling and consultation and provides significantly improved information about the City, the residents and what is evolving across the region and the country. The information gained is used to supplement and help inform the direction of the RLS Master Plan, various other master plans, facility plans and facility strategies. It is also recommended that the trends analysis and master plan be reviewed and updated approximately every five years.

SERVICE DELIVERY DIVISION: COMM-Recreation Services IMPLEMENTATION DIVISION: COMM-Comm. Prog. & Outreach REPORTING CRITERIA: Routine All figures in $'000s

FUNDING SOURCE 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

CRF (New) 59 61 120 DC 177 184 361

TOTAL 236 246 481 INFLATED 243 277 519

All figures in $'000s

OPERATING IMPACT 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 TOTAL

ONGOING ONE TIME TOTAL