community drop-in...community drop-in scs works update 6th november 2019. 13/11/2019 1 construction...

20
13/11/2019 1 Community drop-in SCS works update 6 th November 2019

Upload: others

Post on 19-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 1

Community drop-inSCS works update

6th November 2019

Page 2: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 1

▪ Construction

▪ Planning and

consents ongoing

▪ Ground

investigations and

surveys

▪ Detailed design

starts

▪ Minor, track-level

works

▪ Test piling

• Worksite set up

• Vehicle holding area

set up

▪ Tree removal

▪ Hoarding

▪ Site offices (5-storey

cabin near Langdale /

Granby Terrace

▪ Piling

▪ Ground anchors

▪ Park Village East

lay-by

▪ Open vehicle

holding area

What’s been happening? What next?

Dec 2019to

Jan 2020

Apr 2020ongoing

Jan 2020to

Apr 2020

Dec2019

Oct 2019to

Nov 2019

▪ Ground

investigations and

surveys

▪ Prepare for main

works

Nov 2019 to

Dec 2019

▪ Ground

investigations and

surveys

▪ Mobilise to site

(share CSJV

worksite in former

DB Cargo shed)

▪ Deliveries to site

Jan 2020 onBuilding surveys prior to

heavy works. We’ll contact eligible

properties in early 2020. You don’t need to do

anything yet.

Page 3: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 3

Current project status

Milestone Status Date*

Start of detailed design and construction expected Jan 2020

Upcoming milestones

• Utility surveys start (traffic management required) in progress Oct 2019

• Section 61 noise consent application for main works decision due Nov 2019

• Schedule 17 lorry routes application (Camden-wide) decision due Nov 2019

• Building surveys start (structural and pre-condition) expected Dec 2019

*Dates are subject to change.

Page 4: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 4

Some of our key activities in early 2020

Granby Terrace

site officeSite hoarding

Early site

deliveries

Ground

anchors

Page 5: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 5

Granby Terrace

site officeSite hoarding

Early site

deliveries

Ground

anchors

Page 6: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 6

Set-up works within the site include:

• utility connections

• preparing the ground

• installing the site office and wrap

• preparatory works for an internal

haul road, if possible (design

currently being worked on)

Granby Terrace / Regent’s Park Estate site office

Location of

site offices

Page 7: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 7

Granby Terrace / Regent’s Park Estate site office

Buildings being

demolished

Granby Terrace compound (5 storey)

Augustus House

Langdale House

Page 8: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 8

Site office appearance

Our 5 storey office block can be “wrapped” after installation to improve its appearance for our

neighbours.

What do you think about wrapping the building? Some examples below.

Page 9: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 9

Granby Terrace

site officeSite hoarding

Early site

deliveries

Ground

anchors

Page 10: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 10

Changes to current hoarding around Regents Park estate

SCS has a bigger works area than CSJV. That means:

• we need to expand the size and number of worksites

• we will move and add some hoarding

HS2 has kept Hampstead Gardens and a path through to

Harrington Street open for as long as possible.

Unfortunately, once SCS works start, this area will be

closed to the public with no access.

The bus stops on Hampstead Road in this area will be

moved away from the works for safety.

SCS hoarding (to be added/moved)

CSJV hoarding (existing)

Page 11: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 11

Hoarding – current designs around Regents Park Estate

We plan to decorate the hoarding in this area in a similar way to what you see now.

What do you think?

Page 12: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 12

Hoarding changes on Park Village East

Current Early Works hoarding is 2.4m high.

This will be increased to 3.6m for Main Works

From: January 2020*

Proposed hoarding for Main Works.

Hoarding will stand at a height of 3.6m.

From: January 2020*

*Dates are subject to change.

Page 13: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 13

Hoarding – current designs around Park Village East

We plan to keep the hoarding design the same along Park Village East.We are planting trees behind the hoarding so they will soon be seen above.

What do you think?

Trees being grown behind the hoarding to be visible above it.

Extr

a 1

.2m

Page 14: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 14

Adelaide Road site hoarding

Proposed 3.6m high hoarding (planned for early 2020)

When we install the hoarding, we will need to remove trees.

All tree removal will go through the HS2 Tree Panel.

Page 15: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 15

Granby Terrace

site officeSite hoarding

Early site

deliveries

Ground

anchors

Page 16: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

Click to add text

Road closedSCS lorry route ( <24/day)CSJV approved lorry routeA501 Euston RoadContinuation of proposed route to Adelaide Road worksiteSite access – entry/exit

SCS routes for early activities

Stanhope Street

Robert Street

Albany Street

Hampstead RoadDeliveries so far:

• Herras fencing

• Containers

• timber

Page 17: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 17

Granby Terrace

site officeSite hoarding

Ground

anchors

Early site

deliveries

Page 18: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 18

• Park Village East retaining wall is no longer being demolished for HS2

• We will strengthen the wall and undertake groundwater management before we start

tunnelling and excavating in this area

• This is to protect the wall during heavy construction and to ensure long term stability of the

wall

• Works

1. Ground anchors drilled into the wall from the track-side between Granby Terrace and

Parkway (de-stressed at end of all HS2 construction works and once the there is no

longer movement from the works)

2. Build a ‘berm’ made of earth and concrete at track-level to add support to the wall

3. Boreholes drilled in at street level to manage groundwater levels

• We have started monitoring the wall and will continue this until after the works are finished

Park Village East retaining wall

Page 19: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 19

• Ground anchors are drilled into

the wall about every metre

• Anchors are tensioned to keep the

wall stable during construction

• The anchors will stay in the

ground once construction is

finished but the tension will be

released in most cases (so they

can be cut or destroyed if needed)

• A berm will be added to the front

of the wall afterwards – an earth

and concrete structure to add

extra strength to the wall

Park Village East retaining wall works

Page 20: Community drop-in...Community drop-in SCS works update 6th November 2019. 13/11/2019 1 Construction ... Adelaide Road site hoarding Proposed 3.6m high hoarding (planned for early 2020)

13/11/2019 20

Thank you

Please note the contents are likely to change. We’ll keep you up to date. Also subscribe to the HS2inCamden website for updates.