communication & works department government of...
TRANSCRIPT
LAHORE RING ROAD PROJECT
COMMUNICATION & WORKS DEPARTMENT COMMUNICATION & WORKS DEPARTMENT COMMUNICATION & WORKS DEPARTMENT COMMUNICATION & WORKS DEPARTMENT
GOVERNMENT OF THE PUNJABGOVERNMENT OF THE PUNJABGOVERNMENT OF THE PUNJABGOVERNMENT OF THE PUNJAB
PROJECT MANAGEMENT UNIT
LAHORE RING ROAD
1
February 22, 2011
NATIONAL ENGINEERING SERVICES PAKISTAN (PVT) LIMITE D
SOUTHERN LOOP
LAHORE
AFGHANISTAN
CHINA
P U N J A B
JAMMU & KASHMIR
(DISPUTED TERRITORY)
GILGIT
BALTISTAN
PAKISTAN
BHAKKARFAISALABAD
SARGODHA
MIANWALI
CHAKWAL
ATTOCK CITY
JHANG
GUJRAT
JHELUM
RAWALPINDI
LAHORE
IRAN
ARABIAN SEA
INDIA
BALUCHISTAN
SIND
MULTAN
D G KHAN
KASUR
BAHAWALPUR
RAHIMYAR KHAN
PAKPATTAN
P U N J A B
• Punjab, Land of 5 rivers, most populous province of Pakistan.
• Lahore , its capital situated at bank of River Ravi.
GROWTH OF LAHORE
Estimated Population (2010) = 10.0 Million
Municipal Area = 2,300 Sq. Km.
TRANSPORTATIONTRANSPORTATION CENTRAL BUSINESS DISTRICT (2 TO 3Km RADIUS)
80% POPULATION (within 7Km RADIUS)
Predominantly radial with few inter- radials
Total registered vehicles = 2.3 Million(1.16 millions in Last 10 years)
Vehicle travel hours = 1.87 Million / day
Vehicle travel distance = 40 Million Kms / day
33,4
70
Vehicle travel distance = 40 Million Kms / day
Lahore Documentary Lahore Documentary
LAHORE DOCUMENTARY
NORTHERN LOOP LENGTH = 40 Km
LAHORE RING ROAD (APPROVED ALIGNMENT)
SOUTHERN LOOP (PROPOSED)
LENGTH = 50 Km
SL Study
Salient Feature
NORTHERN LOOP (CONSTRUCTED)LENGTH = 30 Km
SOUTHERN LOOP
142,801
NORTHERN LOOP (UNDER-CONSTRUCTION)
LENGTH = 10 Km
CONSTRUCTION AND TRAFFIC STATUS
SOUTHERN LOOP (PROPOSED)
LENGTH = 50 Km
45,880
Present Traffic
Post Project Traffic
SYSTEM OCCUPANCY AFTER COMPLETION: 636,000 Vehicles/day
TYPICAL CROSS SECTION - NORTHERN LOOP
ROW = 58 ~ 90 m
SERVICE ROAD / UTILITY
CORRIDOR6 LANE CARRIAGEWAY
SERVICE ROAD / UTILITY
CORRIDOR
ROW = 120 m
TYPICAL CROSS SECTION - SOUTHERN LOOP
Service Road
6 Lane Carriageway
30m Reserved
for METRO
Service Road
MOCK Presentation MOCK Presentation
MOCK Presentation
TO DATE PROGRESS
� Approved alignment handed over to representatives of Board of Revenue
� Construction of Northern Loop is completed from Niazi Interc hange toLahore Airport costing Rs. 45.32 Billion (Length = 30 Km).
� Remaining 10 Km costing Rs. 27.93 Billion is under-construc tion andscheduled to be completed by June 2011.
Northern Loop
Southern Loop
� Approved alignment handed over to representatives of Board of Revenueand land acquisition process started.
� NESPAK has completed Topographical survey of the entire Loo p.
� Detailed Planning of 30 Km length (SL-1, 2 & 3) completed and R .O.W plansissued to Board of Revenue.
� At-site demarcation of 22 Km length completed.
� Detailed design & preparation of PC-1 yet to be taken in hand.
� E.I.A Study completed.
NORTHERN
LOOP
SOUTHERN LOOP (Length = 58 km)Including Road on River Front from Babu Sabu to Nia zi Interchange
Length = 10 km
LOOP
Length = 48 km
SOUTHERN
LOOP
SectionsLand
AcquisitionConstruction
CostTotal Cost
Southern Loop (SL-1), L= 8.5 Km8.5 Km 5.62 6.00
Southern Loop (SL-2), L=13.0 Km3.0 Km 4.51 8.00
Southern Loop (SL-3), L= 8.0 Km8.0 Km 3.35 5.60
Southern Loop (SL-4), L=18.2 Km18.2 Km 3.68 10.10
PROJECT COST - SOUTHERN LOOP (Billion Rs.)
Southern Loop (SL-4), L=18.2 Km18.2 Km 3.68 10.10
Cost of Southern Loop (only) 17.16 29.7 46.86
Realignment of Northern Loop(from Babu Sabu to Niazi Chowk, L=10.0 Km10.0 Km)
1.54 14.10
Cost of Southern Loop + Realignment of Northern Loop (River Front)
18.70 43.80 62.50
* Above Costs are based upon January 2011 rates
PROJECT FUNDING OPTIONS
1. Collection of toll
a) Toll from Southern Loop only.b) Toll from entire Ring Road.
2. Revenue generation by development of Economic Zo nes along Southern Loop (Value Addition)
i. Ribbon Development Onlyii. Ribbon + Cluster Development
3. GoPb to acquire land from its own resources. Cons truction from loan.
4. Entire Funding by arranging Loan from a Chinese ban k (loan to be returned by revenue generation through 1 & 2 above)
PROPOSED TOLL RATES
• NO TOLL FOR TWO (2) & THREE (3) WHEELERS (MOTOR CYCLE / RICKSHAW EXEMPTED)
• TOLL RATES FOR CAR / JEEP
Rs. 10/- per Entry (Light Toll Rate)
Rs. 15/- per Entry (Medium Toll Rate)
Rs. 20/- per Entry (Heavy Toll Rate)
• FLAT TOLL TO BE COLLECTED AT EACH INTERCHANGE ENTRY POINT
• TOLL RATES FOR OTHER VEHICLES
Hiace/wagon 1.25 x Car Toll
Minibus 2.00 x Car Toll
Loader pickup 2.50 x Car Toll
Bus 3.50 x Car Toll
Truck/trailer 4.00 x Car Toll
Rs. 20/- per Entry (Heavy Toll Rate)
INTERCHANGENUMBER OF ENTERING VEHICLES (ADT)
North-Bound South-Bound Total
Northern LoopNiazi 38,474 61,516
Lakhu Dair 57,341 17,502G.T. Road 15,999 34,068
Harbanspura 27,348 26,652Barki Road 23,191 33,088
Package-11 near Bhatta Chowk 22,603 16,815Bedian Road 24,982 18,922Package 17 32,005 38,066
EXPECTED TOLL TRAFFIC (Daily)
Package 17 32,005 38,066
Total 241,943 246,629 488,572Realignment along River Front
Babu Sabu 48,728 -Saggian 6,776 -
New Interchange near Niazi 40,750 -
Total 96,254 - 96,254Southern Loop
Ferozepur Road 22,161 43,272Halloki 8,502 17,172
Raiwind Road 21,421 22,559Multan Road 1,483 8,031
Total 53,567 91,034 144,601
TOLL REVENUE STREAM (Million Rs.)
YearsSouthern Loop Northern Loop
@ Rs. 10/- @ Rs. 15/- @ Rs. 20/- @ Rs. 10/- @ Rs. 15/- @ Rs. 20/-
2011 0 0 0 0 0 0
2012 0 0 0 2,100 3,150 4,201
2013 0 0 0 2,389 3,584 4,778
2014 662 993 1,324 2,718 4,077 5,436
2015 750 1,124 1,499 3,077 4,615 6,153
Revenue has been calculated for 15 years stream
2015 750 1,124 1,499 3,077 4,615 6,153
2016 849 1,273 1,697 3,483 5,225 6,966
2017 961 1,441 1,922 3,944 5,915 7,887
2018 1,088 1,632 2,176 4,465 6,697 8,929
2023 1,994 2,992 3,989 8,186 12,279 16,372
2028 3,600 5,400 7,201 14,777 22,166 29,555
TOTAL 26,687 40,031 53,374 114,028 171,042 228,056
Northern Loop Revenue = 4.25 times Southern Loop Re venue
DEVELOPMENT OF ECONOMIC ZONES
1. Ribbon Development
Increase Ring Road ROW from 120 m to 244 m (800 fee t) to create a linear Economic Zone along Southern Loop w herever undeveloped land is available.
Estimated Area = 7,953 Kanals
2. Cluster Development
Road Way = 120 m
CITY SIDE
TYPICAL CROSS SECTION - SOUTHERN LOOP (WITH RIBBON DEVELOPMENT)
Service Road
30m Reserved
for METRO
124 m Reserved for Ribbon Development
ROW = 244 m (800 ft)
2. Cluster Development
Four (4) number consolidated clusters of land are i dentified at various locations along Southern Loop which can be developed into Industrial area, Grain market, Freight Station , Truck/Bus Stand and Residential Colony.
Estimated Area = 22,790 Kanals
6 Lane Carriageway
for METRO
Service Road
PROPOSED SITES FOR ECONOMIC ZONES
Ribbon Development
Industrial Area at Kahna
Freight Station / Grain Market at
Halloki
Residential Area at Taru Gill
Truck/Bus Stand at Miraka
LAHORE MASTER PLAN FEATURES
Commercial
Bus/Wagon Terminal
Industrial
Institutional
Health
Proposed Educational
Parks
PROPOSED ALONG RING ROAD
RIBBON Development
CLUSTER DEVELOPMENT
Industrial
Residential
Truck/Bus Terminal
Ribbon Development7,953 Kanals
Cluster Development22,790 Kanals
Ribbon Development
Cluster Development
TotalResidential Area
(1 location)
Industrial Areas
(3 locations)
COST
Total land to be acquired (Kanals) 7,953 5,850 16,940 3 0,743
Land Acquisition Cost (Million Rs.) 6,124 4,388 9,539 20,051
Development Cost (Million Rs.) 3,181 1,755 6,776 11,712
COST OF ECONOMIC ZONES & ESTIMATED REVENUE
Development Cost (Million Rs.) 3,181 1,755 6,776 11,712
Cost of Land + Development (Million Rs.) 9,305 6,143 16,315 31,763
Average Land Acquisition Cost = Rs. 0.65 Million pe r Kanal
REVENUE
Sellable Developed Land (Kanals) 5,567 3,510 11,858 20, 935
Estimated Revenue from Developed Land (Million Rs.)
27,836 14,040 29,645 71,521
Average Selling Cost = Rs. 3.5 Million per Kanal
PROJECT FUNDING SCENARIOS
Scenario-1: Road Construction & land acquisition for Southern Loop, (No Economic Zones).
a) Toll from Southern Loop only (62.50 Billion)b) Toll from entire Ring Road (65 .55 Billion)
Scenario-2: Road Construction & land acquisition for Southern Loop including Economic Zones.
a) Toll from Southern Loop only (94.28 Billion)b) Toll from entire Ring Road (97.31 Billion)
Scenario-3: Construction of Southern Loop excludingRealignment of Northern Loop along River Front, fro mBabu Sabu to Niazi Interchange. (No Economic Zones)
a) Toll from Southern Loop only (46.86 Billion)b) Toll from entire Ring Road (49 .91 Billion)
All the above scenarios shall also be analyzed for GoPb funding in the form of Cost of Land.
PARAMETERS FOR THE LOAN
� The Chinese road construction firm will facilitate loan for Government of the Punjabthrough a Chinese bank (Expected Interest Rate = 3.14% on for eign currency).
� The road construction firm will in return be awarded constru ction of Southern Loop (SL)and development works of Economic Zones (Commercial, Indus trial and ResidentialAreas).
� The road construction firm will hand over the project to Gove rnment of the Punjab aftercompleting construction and development works.
� Government of the Punjab shall collect toll (either on South ern Loop or from entire RingRoad).
� Developed land in Economic Zones shall be sold out by Governm ent of the Punjab withinfive years after completion of the development.
� Loan shall be returned by Government of the Punjab in 15 equal installments. Thereforeanalysis of the project has been made for a period of 18 years i ncluding constructionperiod of three (3) years.
� Fluctuation in Pak Rupee vs. foreign currency exchange rate covered by assumingre-lending of the soft loan by Government of Pakistan to Gove rnment of the Punjab at aninterest rate of 13.17%.
� Detailed design of Southern Loop and Economic Zones will be r esponsibility ofGovernment of the Punjab.
� Price escalation at 10% has been included in Revenue and Cost Streams.
Cost ofLand Acquisition18.70 Billion Rs.
Cost of Road Construction
43.80 Billion Rs.
Ring Road
Total Input
87.93 Billion Rs.
PROJECT FINANCIAL ANALYSISScenario 1a: Toll on Southern Loop only, no Economi c Zones
Miscellaneous Costs (Inflation, IDC, Insurance and Loan Arrangement Charges)
25.43 Billion Rs.
Loan = 1.02 Billion US $
Loan = 0.74 Billion US $
GoPb Funding
Miscellaneous Costs (Inflation, IDC, Insurance and Loan Arrangement Charges)
20.08 Billion Rs.Total Input
82.58 Billion Rs.
Out
putToll Rs./car FIRR Annual Loan Repayment
10 -ve 13.73 Billion Rs. for 15 years
(Foreign currency loan @ 3.14% re-lent by GOP at 13 .17%)
15 -ve20 -ve
Toll from SL only 26.69 Billion Rs. (Toll Rs. 10/car)40.03 Billion Rs. (Toll Rs. 15/car)53.38 Billion Rs. (Toll Rs. 20/car)
9.97 Billion Rs.
LOAN = 87,930 TOLL REVENUE FROM SL = 40,031
PROJECT CASH FLOW STATEMENTScenario 1a: Toll on Southern Loop only, no Economi c Zones
Year 2011 2012 2013 2014 2015 2016 2017 2018 2023 2028 Total
CASH INFLOW
Toll Revenues (Northern Loop) 0 0 0 0 0 0 0 0 0 0 0
Toll Revenues (Southern Loop) 0 0 0 993 1,124 1,273 1,441 1,632 2,992 5,400 40,031
Sale of Economic Zone plots 0 0 0 0 0 0 0 0 0 0 0
Commercial Loan 40,369 28,159 19,401 0 0 0 0 0 0 0 87,929
Total INFLOW 40,369 28,159 19,401 993 1,124 1,273 1,441 1,632 2,992 5,400 127,960
Million Rs.
LOAN = 87,930 TOLL REVENUE FROM SL = 40,031
CASH OUTFLOW
O & M Costs 0 0 0 463 510 560 616 678 1,092 1,758 14,710
Ring Road Authority Costs 150 165 182 200 220 242 266 292 471 758 6,840
Capital Expenditure 40,369 28,159 19,401 0 0 0 0 0 0 0 87,929
Repayment of Interest 0 0 0 11,580 11,298 10,978 10,616 10,206 7,192 1,597 117,961
Repayment of Commercial Loan
0 0 0 2,146 2,428 2,748 3,110 3,520 6,534 12,129 87,929
Total OUTFLOW 40,519 28,324 19,582 14,389 14,455 14,528 14,608 14,696 15,289 16,242 315,369
NET CASH FLOW -150 -165 -181 -13,396 -13,331 -13,255 -13,167 -13,064 -12,297 -10,842 -187,409
CONSTRUCTION LOAN REPAYMENT = 205,890
Cost ofLand Acquisition18.70 Billion Rs.
Cost of Road Construction
46.85 Billion Rs.
Ring Road
Total Input
92.09
Billion
Rs.
Miscellaneous Costs (Inflation, IDC, Insurance and Loan Arrangement Charges)
26.54 Billion Rs.
Loan = 1.07 Billion US $
PROJECT FINANCIAL ANALYSISScenario 1b: Toll on Entire Ring Road, no Economic Zones
Loan = 0.79 Billion US $
GoPb Funding
Miscellaneous Costs (Inflation, IDC, Insurance and Loan Arrangement Charges)
21.19 Billion Rs.Total Input
86.74 Billion
Rs.Southern Loop 19%
Out
put
Toll from entire Ring Road 140.71 Billion Rs. (Toll Rs. 10/car)211.07 Billion Rs. (Toll Rs. 15/car)281.43 Billion Rs. (Toll Rs. 20/car)
Toll Rs./car FIRR Annual Loan Repayment10 2.84 % 14.38 Billion Rs. for 15 years
(Foreign currency loan @ 3.14% re-lent by GOP at 13 .17%)
15 8.49 %20 12.74 %
10.62 Billion Rs.
Northern Loop 81%
PROJECT CASH FLOW STATEMENTScenario 1b: Toll on entire Ring Road, no Economic Zones
Year 2011 2012 2013 2014 2015 2016 2017 2018 2023 2028 Total
CASH INFLOW
Toll Revenues (Northern Loop)
0 3,150 3,584 4,077 4,615 5,225 5,915 6,697 12,279 22,166 171,042
Toll Revenues (Southern Loop)
0 0 0 993 1,124 1,273 1,441 1,632 2,992 5,400 40,031
Sale of Economic Zone plots
0 0 0 0 0 0 0 0 0 0 0.00
Commercial Loan 43,928 28,628 19,534 0 0 0 0 0 0 0 92,090
Total INFLOW 43,928 31,778 23,118 5,070 5,740 6,498 7,357 8,329 15,271 27,567 303,163
Rs. Million
LOAN = 92,090 TOLL REVENUE FROM NL & SL = 211,073
CASH OUTFLOW
O & M Costs 0 25 28 931 1,025 1,127 1,239 1,364 2,196 3,537 29,641
Ring Road Authority Costs 150 165 182 200 220 242 266 292 471 758 6,840
Capital Expenditure 43,928 28,628 19,534 0 0 0 0 0 0 0 92,090
Repayment of Interest 0 0 0 12,128 11,832 11,497 11,118 10,689 7,533 1,673 123,543
Repayment of Commercial Loan
0 0 0 2,247 2,543 2,878 3,257 3,686 6,843 12,703 92,090
Total OUTFLOW 44,078 28,818 19,743 15,506 15,620 15,744 15,881 16,031 17,042 18,670 344,204
NET CASH FLOW -150 2,960 3,375 -10,436 -9,880 -9,246 -8,524 -7,702 -1,771 8,897 -41,041 CONSTRUCTION LOAN REPAYMENT = 215,633
Cost of Total Land Acquisition38.75 Billion Rs.
Cost of Development of Economic Zone11.71 Billion Rs.
Ring Road
Total Input
132.29
Billion
Rs.
Economic Zones
Miscellaneous Costs (Inflation, IDC, Insurance and Loan Arrangement Charges)
38.03 Billion Rs.
Loan = 1.53 Billion US $
Loan = 0.96 Billion US $
GoPb Funding
Miscellaneous Costs (Inflation, IDC, Insurance and Loan Arrangement Charges)
26.95 Billion Rs.Total
Input
121.21 Billion
Rs.
PROJECT FINANCIAL ANALYSISScenario 2a: Toll on Southern Loop only, with Econo mic Zones
Cost of Road Construction
43.80 Billion Rs.
Economic Zones 74%
Southern Loop 26%
Ring Road
Out
put
Economic Zones
Toll from SL only 26.69 Billion Rs. (Toll Rs. 10/car)40.03 Billion Rs. (Toll Rs. 15/car)53.38 Billion Rs. (Toll Rs. 20/car)
Sale of Economic Zones in 5 years(from years 4 to 8)111.93 Billion Rs.
Total Return FIRR Annual Loan Repayment138.61 1.89 % 20.65 Billion Rs. for 15 years
(Foreign currency loan @ 3.14% re-lent by GOP at 13 .17%)
151.93 3.96 %165.30 5.57 %
12.87 Billion Rs.
PROJECT CASH FLOW STATEMENTScenario 2a: Toll on Southern Loop only, with Econo mic Zones
Year 2011 2012 2013 2014 2015 2016 2017 2018 2023 2028 Total
CASH INFLOW
Toll Revenues (Northern Loop) 0 0 0 0 0 0 0 0 0 0 0
Toll Revenues (Southern Loop) 0 0 0 993 1,124 1,273 1,441 1,632 2,992 5,400 40,031
Sale of Economic Zone plots 0 0 0 28,558 26,178 17,278 19,006 20,906 0 0 111,926
Commercial Loan 64,155 38,927 29,211 0 0 0 0 0 0 0 132,292
Total INFLOW 64,155 38,927 28,211 29,552 27,303 18,551 20,447 22,538 2,992 5,400 284,249
Rs. Million
TOLL REVENUE FROM SL = 40,031REVENUE FROM SALE OF PLOTS = 111,926
LOAN = 132,292
CASH OUTFLOW
O & M Costs 0 0 0 463 510 560 616 678 1,092 1.758 14,710
Ring Road Authority Costs 150 165 182 200 220 242 266 292 471 758 6,840
Capital Expenditure 64,155 38,927 29,211 0 0 0 0 0 0 0 132,292
Repayment of Interest 0 0 0 17,423 16,998 16,517 15,972 15,356 10,821 2,403 177,476
Repayment of Commercial Loan
0 0 0 3,228 3,653 4,135 4,679 5,295 9,830 18,248 132,292
Total OUTFLOW 64,305 39,092 29,393 21,314 21,381 21,454 21,533 21,621 22,214 23,167 463,610
NET CASH FLOW -150 -165 -182 8,238 5,922 -2,903 -1,086 917 -19,222 -17,767 -179,361CONSTRUCTION LOAN REPAYMENT = 309,768
Cost of Total Land Acquisition38.75 Billion Rs.
Cost of Road Construction
46.85 Billion Rs.
Cost of Development of Economic Zone11.71 Billion Rs.
Total Input
136.45
Billion
Rs.
Miscellaneous Costs (Inflation, IDC, Insurance and Loan Arrangement Charges)
39.14 Billion Rs.
Loan = 1.58 Billion US $
Loan = 1.01 Billion US $
GoPb Funding
Miscellaneous Costs (Inflation, IDC, Insurance and Loan Arrangement Charges)
28.06 Billion Rs.Total Input
125.37 Billion
Rs.
PROJECT FINANCIAL ANALYSISScenario 2b: Toll on entire Ring Road, with Economi c Zones
Northern Loop 53%
Economic Zones 35%
Ring Road
Out
put
Economic Zones
Sale of Economic Zones in 5 years
(from years 4 to 8)
111.93 Billion Rs.
Total Return FIRR Annual Loan Repayment
252.64 10.90 % 21.30 Billion Rs. for 15 years
(Foreign currency loan @ 3.14% re-lent by GOP at 13 .17%)
322.99 14.80 %393.35 17.91 %
Toll from entire Ring Road 140.71 Billion Rs. (Toll Rs. 10/car)211.07 Billion Rs. (Toll Rs. 15/car)281.43 Billion Rs. (Toll Rs. 20/car)
13.52 Billion Rs.
Loop 53%
PROJECT CASH FLOW STATEMENTScenario 2b: Toll on entire Ring Road, with Economi c Zone
Year 2011 2012 2013 2014 2015 2016 2017 2018 2023 2028 Total
CASH INFLOW
Toll Revenues (Northern Loop) 0 3,150 3,584 4,077 4,615 5,225 5,915 6,697 12,279 22,166 171,042
Toll Revenues (Southern Loop) 0 0 0 993 1,124 1,273 1,441 1,632 2,992 5,400 40,030
Sale of Economic Zone plots 0 0 0 28,558 26,178 17,278 19,006 20,906 0 0 111,926
Commercial Loan 67,713 39,396 29,344 0 0 0 0 0 0 0 136,453
Total INFLOW 67,713 42,546 32,928 33,628 31,917 23,776 26,362 29,235 15,271 27,566 459,451
Rs. Million
TOLL REVENUE FROM SL & NL = 211,072 REVENUE FROM SALE OF PLOTS = 111,926
LOAN = 136,453
Total INFLOW
CASH OUTFLOW
O & M Costs 0 25 28 931 1,025 1,127 1,239 1,364 2,196 3,537 29,639
Ring Road Authority Costs 150 165 182 200 220 242 266 292 471 758 6,839
Capital Expenditure 67,713 39,396 29,344 0 0 0 0 0 0 0 136,453
Repayment of Interest 0 0 0 17,971 17,532 17,036 16474 15,839 11,161 2,479 183,057
Repayment of Commercial Loan
0 0 0 3,330 3,768 4,265 4,826 5,462 10,139 18,822 136,453
Total OUTFLOW 67,863 39,586 29,553 22,432 22,545 22,669 22,806 22,956 23,967 25,595 492,441
NET CASH FLOW -150 2,960 3,375 11,197 9,374 1,107 3,556 6,287 -8,697 1,971 -32,990
CONSTRUCTION LOAN REPAYMENT = 319,510
Cost ofLand Acquisition17.16 Billion Rs.
Cost of Road Construction
29.70 Billion Rs.
Ring Road
Total Input
65.73 Billion Rs.
PROJECT FINANCIAL ANALYSISScenario 3a: Toll on Southern Loop only,
No Economic Zones, No Realignment of Northern Loop along River FrontMiscellaneous Costs
(Inflation, IDC, Insurance and Loan Arrangement Charges)
18.87 Billion Rs.
Loan = 0.76 Billion US $
Loan = 0.50 Billion US $
GoPb Funding
Miscellaneous Costs (Inflation, IDC, Insurance and Loan Arrangement Charges)
13.96 Billion Rs.Total Input
60.82 Billion Rs.
Out
putToll Rs./car FIRR Annual Loan Repayment
10 -ve 10.26 Billion Rs. for 15 years
(Foreign currency loan @ 3.14% re-lent by GOP at 13 .17%)
15 -ve20 -ve
Toll from SL only 26.69 Billion Rs. (Toll Rs. 10/car)40.03 Billion Rs. (Toll Rs. 15/car)53.38 Billion Rs. (Toll Rs. 20/car)
6.81 Billion Rs.
PROJECT CASH FLOW STATEMENTScenario 3a: Toll on Southern Loop only, No Economi c Zones,
No Realignment of Northern Loop along River FrontYear 2011 2012 2013 2014 2015 2016 2017 2018 2023 2028 Total
CASH INFLOW
Toll Revenues (Northern Loop) 0 0 0 0 0 0 0 0 0 0 0
Toll Revenues (Southern Loop) 0 0 0 993 1,124 1,273 1,441 1,632 2,992 5,400 40,031
Sale of Economic Zone plots 0 0 0 0 0 0 0 0 0 0 0
Commercial Loan 32,688 19,794 13,247 0 0 0 0 0 0 0 65,730
Total INFLOW 32,688 19,794 13,247 993 1,124 1,273 1,441 1,632 2,992 5,400 105,761
Million Rs.
LOAN = 65,730 TOLL REVENUE FROM SL = 40,031
CASH OUTFLOW
O & M Costs 0 0 0 322 355 389 428 472 759 1,223 10,230
Ring Road Authority Costs 150 165 182 200 220 242 266 292 471 758 6,840
Capital Expenditure 32,688 19,794 13,247 0 0 0 0 0 0 0 65,730
Repayment of Interest 0 0 0 8,657 8,445 8,206 7,936 7,630 5,377 1,194 88,179
Repayment of Commercial Loan
0 0 0 1,604 1,815 2,054 2,325 2,631 4,884 9,067 65,730
Total OUTFLOW 32,838 19,959 13,429 10,783 10,835 10,891 10,955 11,025 11,491 12,242 236,709
NET CASH FLOW -150 -165 -182 -9,789 -9,711 -9,618 -9,514 -9,393 -8,499 -6,842 -130,949
CONSTRUCTION LOAN REPAYMENT = 153,909
Cost ofLand Acquisition17.16 Billion Rs.
Cost of Road Construction
32.75 Billion Rs.
Ring Road
Total Input
69.89
Billion
Rs.
Miscellaneous Costs (Inflation, IDC, Insurance and Loan Arrangement Charges)
19.98 Billion Rs.
Loan = 0.79 Billion US $
PROJECT FINANCIAL ANALYSISScenario 3b: Toll on Entire Ring Road,
No Economic Zones, No Realignment of Northern Loop along River Front
Loan = 0.55 Billion US $
GoPb Funding
Miscellaneous Costs (Inflation, IDC, Insurance and Loan Arrangement Charges)
15.07 Billion Rs.Total Input
64.98 Billion
Rs.Southern Loop 22%
Ring Road
Out
put
Toll from entire Ring Road 122.22 Billion Rs. (Toll Rs. 10/car)183.33 Billion Rs. (Toll Rs. 15/car)231.11 Billion Rs. (Toll Rs. 20/car)
Toll Rs./car FIRR Annual Loan Repayment10 4.71 % 10.91 Billion Rs. for 15 years
(Foreign currency loan @ 3.14% re-lent by GOP at 13 .17%)
15 10.38 %20 13.91 %
7.46 Billion Rs.
Northern Loop 78%
PROJECT CASH FLOW STATEMENTScenario 3b: Toll on entire Ring Road, No Economic Zones,
No Realignment of Northern Loop along River Front
Year 2011 2012 2013 2014 2015 2016 2017 2018 2023 2028 Total
CASH INFLOW
Toll Revenues (Northern Loop)
0 2,639 3,003 3,416 3,867 4,378 4,956 5,611 10,288 18,571 143,303
Toll Revenues (Southern Loop)
0 0 0 993 1,124 1,273 1,441 1,632 2,992 5,400 40,031
Sale of Economic Zone plots
0 0 0 0 0 0 0 0 0 0 0.00
Commercial Loan 36,247 20,263 13,381 0 0 0 0 0 0 0 69,891
Total INFLOW 36,247 22,902 16,384 4,409 4,991 5,651 6,397 7,243 13,280 23,971 253,225
Rs. Million
LOAN = 69,891 TOLL REVENUE FROM NL & SL = 183,334Total INFLOW 36,247 22,902 16,384 4,409 4,991 5,651 6,397 7,243 13,280 23,971 253,225
CASH OUTFLOW
O & M Costs 0 25 28 649 714 786 864 951 1,531 2,466 20,681
Ring Road Authority Costs 150 165 182 200 220 242 266 292 471 758 6,840
Capital Expenditure 36,247 20,263 13,381 0 0 0 0 0 0 0 69,891
Repayment of Interest 0 0 0 9,205 8,980 8,726 8,438 8,113 5,717 1,270 93,762
Repayment of Commercial Loan
0 0 0 1,706 1,930 2,184 2,472 2,798 5,193 9,640 69,891
Total OUTFLOW 36,397 20,453 13,590 11,759 11,844 11,937 12,040 12,153 12,912 14,134 261,065
NET CASH FLOW -150 2,449 2,794 -7,350 -6,853 -6,287 -5,643 -4,910 368 9,837 -7,840
CONSTRUCTION LOAN REPAYMENT = 163,653
Scenario Funding Scenarios
Project Cost
(Billion Rs.)
Loan Amount
[Billion Rs. (Billion $)]
GoPb Funding
(Billion Rs.)
Revenue(Billion
Rs.)
FIRR(%)
Installment (Billion Rs.)
1aToll from Southern Loop only
62.5087.93 (1.02 $) -
40.03 - ve13.73
63.88 (0.74 $) 18.70 9.97
1bToll from entire Ring Road
65.5592.09 (1.07 $) -
211.07 8.4914.38
68.04 (0.79 $) 18.70 10.62
SUMMARY OF FINANCIAL ANALYSIS (Toll = Rs. 15/Car)
68.04 (0.79 $) 18.70 10.62
2aEconomic Zone with Toll from Southern Loop only
94.26132.29 (1.53 $) -
151.93 3.9620.65
82.46 (0.96 $) 38.75 12.87
2bEconomic Zone with Toll from entire Ring Road
97.31136.45 (1.58 $) -
322.99 14.8021.30
86.62 (1.01 $) 38.75 13.52
3aToll from Southern Loop Only (No River Front)
46.8665.73 (0.76 $) -
40.03 - ve10.26
43.66 (0.50 $) 17.16 6.81
3bToll from entire Ring Road (No River Front)
49.9169.89 (0.79 $) -
183.33 10.3810.91
47.82 (0.55 $) 17.16 7.46
Both Parties agree that the following formalities m ust be met in the manner and according to the schedule set out herein below:
Sr. No.
ActivityMonths Subsequent to Signing of Agreement
1 2 3 4 5 6 7 8 9 10 11 12 13
a.The Government of Punjab shall finalize and approve project design with provision of feasibility studies, geological report, topographical report and notify the same to prospective contractor.
b.
The Government of Punjab shall obtain and secure all necessary and or relevant authorizations, sanctions and approvals including but not limited to PC-1, Public Private Partnerships Agreement, Approval from ECNEC.
The Government of Punjab shall finalize and approve Technical
FRAMEWORK AGREEMENT FOR LOAN ACQUISITION
STUDIES
DESIGN
c.The Government of Punjab shall finalize and approve Technical Specifications relevant to the Project and notify the same to prospective contractor.
d.
Prospective contractor shall initiate negotiations with China Development Bank for provision of Project financing and supply provisional Terms and Conditions for such facility against Sovereign Guarantee.
e.Parties shall prepare reports and document for submission to the financing institution.
f.Parties shall negotiate firm Contract Price and Terms and Conditions of the Commercial Contract after assurance of financial assistance from the Bank / Institution.
g.The Government of Punjab shall conduct detailed negotiations and finalize Project Financing Agreement with active assistance of prospective contractor.
� Alleviate congestion on radial arterials� Improve operation of critical intersections in the city� Reduce overall travel time along city network
In 2005, C&W Department awarded the task to NESPAKfor alignment study with the objectives to:
BACKGROUND
� Traffic Counts at 107 locations and 65,000 O-D interviews� Travel Time Surveys & Road Inventory of major arterials� Development of Computerized Traffic Model
NESPAK completed the task through:
BACK
SALIENT FEATURES
NORTHERN LOOP SOUTHERN LOOP
Lengths: 40 Km72 Km120 Km
50 Km120 Km120 Km
Design Speed 100 Km / h 100 Km / h
No. of Lanes3+3 (with provision of Service
Roads)
3 + 3 (with provision of Service Roads & space for provision of
6 Lane Carriageway2 Lane Service RoadDrains
No. of LanesRoads)
Roads & space for provision of 4th lane & Metro)
R.O.W 58~90 m 160 m
Interchanges Present 9 6
Future 1 5
Underpasses
Vehicular 10 17
Pedestrian 6
+ 26 Pedestrian Bridges15
+ Pedestrian Bridges
CostLand Acquisition Rs. 22 Billion (US$ 250 M) Rs. 20.4 Billion (US$ 230 M)
Construction Rs. 25 Billion (US$ 290 M) Rs. 31.0 Billion (US$ 350 M)BACK
Pkg#
Package Name Length (Km)Physical
Progress (%)
1 Interchange at Niazi Chowk 1.2 100
2 Road from Niazi Chowk to Saggian 2.7 100
3 Road from Niazi Chowk to Mahmood Booti 8.7 100
4 Interchange at Saggian Chowk 1 100
5 Road from Saggian to Gulshan-e- Ravi 1.5 100
6 Road from Barki Road Int. to Ghazi Road Int. 3 100
7 Abdullah Gul Interchange 1.6 86
8 Road from Canal to Airport Access Road 1.8 100
PROGRESS OF NORTHERN LOOP
8 Road from Canal to Airport Access Road 1.8 100
9 Interchange at Harbanspura Canal Crossing 2 100
10 Quaid-e-Azam Interchange 2 100
11 Interchange at Ghazi Road 1.6 42
12 Road from Lakhudair to G.T Road 2.7 95
13 Road from Mahmood Booti to Lakhudair 1.9 97
14 Road from Ghazi Road Int. to Bedian Road Int. 2.5 2 7
15 Interchange at Bedian Road 1.4 55
16 Road from Bedian Road Int. to Khaira Disty. 2.5 75
17 Interchange at Khaira Distributary 1.9 65
(30 Kms Constructed) Total 40 Overall 85% BA
CK
FULL CLOVERLEAF INTERCHANGE AT FEROZEPUR ROAD CROSSING
Gaju MattahRehmat Pura
BISMA RICEMILL
Back
PARTIAL CLOVERLEAF INTERCHANGE AT RAILWAY CROSSING NEAR HALLOKI VILLAGE
RAILWAY LINE
HALLOKI
Back
FULL CLOVERLEAF INTERCHANGE AT RAIWIND ROAD CROSSING
Back
FULL CLOVERLEAF INTERCHANGE AT MULTAN ROAD / CANAL CROSSING
BERGER PAINTS
RAIWIND ROAD
Back
SLSL--11 SLSL--22 SLSL--33 SLSL--44 TOTAL(50.0 Km)(8.5 Km)(8.5 Km) (13.0 Km)(13.0 Km) (8.0 Km)(8.0 Km) (20.5 Km)(20.5 Km)
Billion Rs.
COST OF RECOMMENDED PACKAGES
Construction Cost
6.0 8.0 5.6 11.4 31.0
Land Cost 3.9 6.1 3.7 6.7 20.4
Total 9.9 14.1 9.3 18.1 51.4
Back
RECOMMENDED PACKAGES
````
Pac
kage
SL
-1
(L =
8.5
Km
)
Pac
kage
SL
-4
(L =
20.
5 K
m)
LRR Southern Loop (L = 50 Kms)
````
Pac
kage
SL
(L =
8.5
Km
)
Package SL-2 (L = 13.0 Km)
Package SL-3 (L = 8.0 Km)
Pac
kage
SL
(L =
20.
5 K
m)
Back
OPTIONOPTION--11 OPTIONOPTION--22 OPTIONOPTION--33(49.5 Km)(49.5 Km)
OPTIONOPTION--44(58.0 Km)(58.0 Km)(50.0 Km)(50.0 Km) (41.5 Km)(41.5 Km)
Construction Cost (Billion Rs.) 31.0 24.6 37.8 43.8
COST OF OPTIONS
Cost (Billion Rs.)
Land Cost (Billion Rs.)
20.4 16.5 18.0 21.9
Total (Billion Rs.) 51.4 41.1 55.8 65.7
Back
NORTHERN
LOOP
CONSTRUCTION OPTION - 1 (Length = 50 km)Southern Loop from P – 17 to Babu Sabu Interchange
SOUTHERN
LOOP
OPTION – 1
Length = 50 km
Back
NORTHERN
LOOP
CONSTRUCTION OPTION - 2 (Length = 41.5 km)From Ferozepur Road to Babu Sabu Interchange (Packag e SL-1 excluded)
LOOP
OPTION – 2
Length = 41.5 km
SOUTHERN
LOOPBack
NORTHERN
LOOP
CONSTRUCTION OPTION - 3 (Length = 49.5 km)Option-2 + Road on River Front from Babu Sabu to Niazi Interchange
LOOP
OPTION – 3
Length = 49.5 km
SOUTHERN
LOOPBack
NORTHERN
LOOP
CONSTRUCTION OPTION - 4 (Length = 58 km)Option-3 + Road on River Front from Babu Sabu to Niazi Interchange
LOOP
SOUTHERN
LOOP
Length = 58 km
Back
LOCATION ACQUISITION COSTDEVELOPMENT
CHARGES
SALE PRICE OF DEVELOPED
LAND
RIBBON DEVELOPMENT
1. Kahna 1,050,000 400,000 5,000,000
2. Halloki 850,000 400,000 5,000,000
3. Miraka 600,000 400,000 5,000,000
LAND, DEVELOPMENT AND SELLING UNIT COSTS (Rs. / Kanal)
3. Miraka 600,000 400,000 5,000,000
CLUSTER DEVELOPMENT
a) Industrial1. Kahna 750,000 400,000 2,500,000
2. Halloki 600,000 400,000 2,500,000
3. Miraka 400,000 400,000 2,500,000
b) Residential
1. Taru Gill 750,000 300,000 4,000,000
Scenario Land Acquisition
Construction Cost
SubTotal
Toll System Total Cost
Scenario 1Southern Loop excluding economic zones
18.70 43.80 62.50 3.05 65.55
Development of Economic Zones 20.05 11.71 31.76 - 31.76
Scenario 2
Project Cost in Various Scenarios (Billion Rs.)
Scenario 2Southern Loop including Economic Zones
38.75 55.51 94.26 3.05 97.31
Realignment of Northern Loop 1.54 14.10 15.64 - 15.64
Scenario 3Southern Loop excluding economic zones and Realignment of Northern Loop
17.16 29.70 46.86 3.05 49.91
* Above Costs are based on January 2011 rates
End of Link SlidesEnd of Link Slides