commissioning procedure goedehoop

32
Commissioning Procedure Goedehoop Flotation Upgrade Commissioning Procedure Page 1 of 32 Enprotec Commissionin g Procedure Revisio n 01 Approved By: Date: 10/01/20 11

Upload: johann-lewis

Post on 02-Apr-2015

1.803 views

Category:

Documents


12 download

TRANSCRIPT

Page 1: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

Commissioning Procedure

Page 1 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 2: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

Contents1. Objectives......................................................................................................................................4

2. Scope.............................................................................................................................................4

3. Definitions.....................................................................................................................................4

4. Signature responsibilities per commissioning phase.....................................................................5

5. Punch list Description....................................................................................................................6

6. THE COMMISSIONING STUCTURE AND RESPONSIBILITIES............................................................7

6.1. Commissioning Manager.......................................................................................................7

6.2. General..................................................................................................................................8

7. Logistic Support.............................................................................................................................8

8. Commissioning Control..................................................................................................................8

8.1. C1 level – Commissioning “Punch Listing” – Contractor and/or Suppliers & Construction Team. Pre Commissioning Checks – Power Off..................................................................................9

8.2. C2 level – Commissioning “Dry”- Construction Team, Contractors and/or Supplier and Plant. Pre Commissioning Checks – Power On.................................................................................10

8.3. C3 level – Commissioning “Material” – Commissioning Team and Plant Cold Commissioning11

8.4. C4 level – Commissioning – Commissioning Team and Production Process Engineer. (Hot Commissioning)...............................................................................................................................12

8.5. C5 level – Commissioning “Production Build-up and Optimisation”- Production Process Engineer and Plant Operating Personnel (performance Test).........................................................12

8.6. General................................................................................................................................13

9. Request for Site Modifications – Construction Team..................................................................13

10. Final Handover.........................................................................................................................13

11. Commissioning team Identification and Induction..................................................................13

12. Attachments Commissioning Acceptance Certificates.............................................................14

C1 LEVEL – COMMISSIONING ACCEPTANCE CERTIFICATE...................................................................15

DETAILS OF WORK BEING HANDED OVER........................................................................................15

RESPONSIBLE PERSON.................................................................................................................15

C2 LEVEL – COMMISSIONING ACCEPTANCE CERTIFICATE...................................................................16

DETAILS OF WORK BEING HANDED OVER........................................................................................16Page 2 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 3: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

RESPONSIBLE PERSON.................................................................................................................16

C3 LEVEL – COMMISSIONING ACCEPTANCE CERTIFICATE...................................................................17

DETAILS OF WORK BEING HANDED OVER........................................................................................17

RESPONSIBLE PERSON.................................................................................................................17

C4 LEVEL – COMMISSIONING ACCEPTANCE CERTIFICATE...................................................................18

DETAILS OF WORK BEING HANDED OVER........................................................................................18

RESPONSIBLE PERSON.................................................................................................................18

C5 LEVEL – COMMISSIONING ACCEPTANCE CERTIFICATE...................................................................19

DETAILS OF WORK BEING HANDED OVER........................................................................................19

RESPONSIBLE PERSON.................................................................................................................19

Final Handover Certificate...................................................................................................................20

List of Exceptions.............................................................................................................................20

RESPONSIBLE PERSON.................................................................................................................20

Project Handover to Owner Certificate...............................................................................................21

List of Exceptions.............................................................................................................................21

RESPONSIBLE PERSON.................................................................................................................21

Request for site Modifications.............................................................................................................23

Full Description of Modification Requested.................................................................................23

Reasons and Justification for Modification......................................................................................23

Page 3 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 4: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

1. Objectives1.1. To define the commissioning strategy and control procedures required to allow for a

smooth transition from completion of construction by the Contractor – C1 to formal hand over and acceptance of equipment and systems by the Project Commissioning Team – C3 and to final hand over to the Plant after C5 commissioning.

1.2. To clarify and define the different phases of hand over, the different parties involved, their responsibilities and obligations at each stage

2. Scope

This procedure will cover the commissioning strategy that will be adopted for the commissioning of the Flotation B-Bank i.e. Multi Cell upgrades to Enprotec Dual Cell Technology. (Complete with it material handling sections)

3. DefinitionsThe Plant The Plant refers to Plant Management who is represented by the

Construction Manager, Metallurgical Manager and the Engineering Manager

Plant Operations The OMR refers to the Plant appointed operation team who will act on behalf of the plant from commissioning stages C3 through to C5 and ongoing plant operation

Operation and MaintenanceRepresentative (OMR)Acceptance Certificates C1 & C2

These certificate are signed by the Contractor and his Sub-contractor at stages C1 & C2 of the commissioning process signifying acceptance that the equipment is ready for C3 commissioningPre-commissioning Check

(Static testing) at component levelAcceptance Certificate C3 These certificates are signed by the Contractor and the OMR at stage C3

once the construction completion certificate/s is signed off. This means the plant is ready for operation by the Operations Team & Beneficial use is Identified. At this point there is a shift in Safety Responsibility as well as plant Operation and Maintenance from contractor to client GHC team. The contractor is still available for support and commissioning modification identified in the first 24 hrs of operation

Cold Commissioning(Dynamic testing) in Systems

Acceptance Certificate C4 This certificate is signed off by the OMR and the Contractor

Page 4 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 5: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

Hot Commissioning At stage C4 of the commissioning process signifying acceptance of plant operations

Acceptance Certificates C5 This certificate is signed by the OMR and the Contractor and the Client Projects Manager at stage C5 of the commissioning process signifying acceptance of the plant performance as per design requirements

Performance Testing Final Acceptance Certificate This takes place once all the plant equipment has met the expected

''Performance Specifications" to the satisfaction of the Plant. Exceptions will be noted on the Final Acceptance Certificate

4. Signature responsibilities per commissioning phase

C1Contractor, Vendor or supplier and Sub- Contractor Enprotec Construction Manager ( Main Area Contractor) Client Area Construction Manager

C2Contractor, Vendor or supplier and Sub- Contractor Enprotec Construction Manager ( Main Area Contractor) Client Area Construction Manager

C3C & I Vendor assistance during this phase Enprotec Commissioning Manager ( Main Area Contractor)Goedehoop Colliery Commissioning Manager

C4Enprotec Commissioning Manager ( Main Area Contractor)Goedehoop Colliery Commissioning Manager

C5Enprotec Commissioning Manager ( Main Area Contractor)Enprotec Projects Manager ( Main Area Contractor) Anlgo Senior Project Manager

FINAL HADOVER CERTIFICATEEnprotec Commissioning Manager ( Main Area Contractor)Enprotec Projects Manager ( Main Area Contractor) Anlgo Senior Project Manager

PROJECT HANDOVER TO OWNER CERTIFICATE

Anlgo Senior Project Manager Anlgo General Manager Anglo Board Representative

Page 5 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 6: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

5. Punch list DescriptionNote!Sequence for punching list sign off’s

Sub-Contractor punch list to be completed, then A request from the Enprotec Construction Manager/Supervisor to generate their punch list, Enprotec punch list to be generated and the punch list items to be worked off, A request for the client’s representative to generate their punch list, The client’s representative to generate punch items, which in turn the items are to be

worked off.

Punch List

At each stage of the commissioning phase a detailed and thorough inspection is performed by the relevant parties. This is aimed at identifying any deviations from design or short comings in the construction or performance of the plant or equipment prior to signing of the Final Acceptance Certificate

Punch list Type This refers to the degree of seriousness of the said deviation or punch list items ,the definition of such is noted below:

Type AThis deviation may affect health and/or safety of the plant personnel. The deviation must therefore be rectified before signing of the Acceptance Certificate and proceeding to the next commissioning phase

Type BDeviations can be rectified during the next stage of commissioning. However, an interim authorization may be given by the Responsible Engineer to allow the next stage of commissioning to proceed.

Type CThese are deviations that can be rectified while the plant is running, but must be rectified before the Final Handover Acceptance Certificate sign off

Type D

Commonly revered to as "Wish list items", which fall outside the Contractual Scope Of Work. These are detailed on a separate form Referred to as a Request for Site Modification. These forms are generated by the plant but are subject to approval and authorization by the Construction Manager & Engineering Manager.

Page 6 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 7: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

6. THE COMMISSIONING STUCTURE AND RESPONSIBILITIES

The Commissioning structure consists of the following key personnel:

6.1.Commissioning Manager

The commissioning Manager of each area Underground/Surface is responsible for managing both the dry and the ore commissioning of plant. His responsibilities shall include the following activities:

Commissioning strategy. Commissioning procedure. Initiation of audits and monitoring activities to ensure compliance to the

commissioning procedures and safety standards. Commissioning structure and functions. Identification and appointment of personnel on the commissioning structure. Identification of infrastructure requirements and ensuring availability ahead of

commissioning. Development of the commissioning program and monitoring of progress with the

assistance of the Project Planning Co-ordinator. Ensuring that the required operational parameters are identified and met before the

plant is handed over to the Plant. Manage and control the commissioning and hand over to the Plant. Ensure compliance with laid down procedures. Ensuring all documents, drawings and “as-build” drawings are available for Final

Handover to the Plant at the C5 Commissioning stage.

The commissioning package for each Commissioning Manager will typically contain the following:

P & ID highlighted to show equipment forming the particular module or piece of equipment to be commissioned.

An equipment summary extracted from the P & ID indicating all equipment by discipline.

Commissioning Hand over certificates C1 to C5. Commissioning schedule and plan for the respective area. Applicable check lists from the contractor submitted for approval. Equipment data sheets. Applicable commissioning, operating and maintenance procedures and manuals. Lubrication schedules and any vendor instructions.

Page 7 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 8: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

Operational parameters and system data for process equipment.

6.2. General

Other key members of the Commissioning Team shall be selected from mining personnel or representatives as required.

The relevant Discipline Engineers shall assist the Commissioning Managers in compiling procedures and check lists. These will be handed over to the Documentation controller for filling and issuing as required.

All Commissioning planning will be co-ordinated by the project planning co-ordinator.

7. Logistic Support

The project has included where necessary, maintenance and training requirements in the relevant contract document. These requirements have been identified in conjunction with Goedehoop and the Contractor/Supplier. In the event of additional commissioning requirements this shall be arranged directly by the Commissioning Manager in conjunction with the Contractor/Supplier taking cognizance of the time and cost involved for the supplier to present themselves on site.

The logistic support work typically involves liaising with Contractors to identify specifics such as; the maintenance frequency for specific equipment, recommended and strategic spares requirements, tools, personnel training, potential maintenance contracts and al related documentation.

On completion of commissioning a Flotation technician from Enprotec will be on site for six months thereafter. This will ensure adequate training to the relevant plant operators.

8. Commissioning Control

The responsibilities for the various stages of commissioning and handover shall be as follows:

C1 From the Contractor and/or supplier to the construction Engineer, technical punch list completed. Pre Commissioning Checks – Power Off

C2 From the Contractor and/or supplier to the Construction Engineer, no Process involvement, technical punch list completed and Contractor and/or Supplier. Pre Commissioning Check – Power on

Page 8 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 9: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

C3 From the construction Engineer and Plant Engineering staff to Process Operational staff and process punch list completed. No process MaterialCold CommissioningDynamic Testing – Systems as well Auto Start & Shut down of Plant

C4 Operational staff introducing limited process material and checking process functionality and safety. Hot Commissioning

C5 Operational staff introducing plant/equipment functionality for throughput, volumes and flow rates as specified in compliance with the test on completion contractually. Plant Performance Test

The Construction Electrical, Mechanical and C & I Engineers shall be responsible for their specific discipline throughout all the various stages of commissioning in conjunction with the Plant Process and Engineering staff on a modular basis.

8.1.C1 level – Commissioning “Punch Listing” – Contractor and/or Suppliers & Construction Team. Pre Commissioning Checks – Power Off

This means Punch Listings of discrete parts of equipment of systems By Contractors and/or suppliers before handing over to the Plant/Process Engineers.

The Commissioning manager will sign off this stage of commissioning when following have been achieved:

Punch Listings by Contractor and Project Construction Team. Rectification of punch list by Contractor. Cleaning of the area intended for handover. Completion of test sheet as for Megger, alignment and pressure test.(Power off) The equipment shall have all hardwired interlocks and protective systems checked

and tested by the Contractor or Supplier. Loss control and applicable security checks completed. The Contractor and/or Supplier shall complete the C1 Acceptance Form provided by

the Construction Engineer (copies also in contract document). This form shall be the Acceptance Certificate and shall reflect outstanding punch list items.

The Construction Engineer shall accept and sign off the certificate once he has satisfied himself that all the items on the punch list can be carried forward to run

Page 9 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 10: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

testing without endangering life of the safety of the works. He shall clear any uncertainties with the Construction Manager if in doubt.

C1 – Commissioning shall be considered complete when all the above including the entire Category A punch list items have been addressed and all the documentation has been handed over to the Documentation Controller.

C1 Document Package consists of; Acceptance Certificate. Contractors punch list. Construction Team punch list. Note pertaining to acceptable punch list items that may be carried to the

next stage of commissioning. After all safety checks have been completed. All certifications must be identified by Commissioning Manager.

The C1 Commissioning Acceptance Certificate must be signed of before proceeding to the next stage of commissioning.

8.2.C2 level – Commissioning “Dry”- Construction Team, Contractors and/or Supplier and Plant. Pre Commissioning Checks – Power On

Individual system/s check (interlocks) to take place.

This involves running the equipment or module dry to test or perform relevant checks on the equipment or system, all equipment such as motor etc. are run for short periods under the supervision of the Commissioning Manager, Contractor and/or Supplier in accordance with the running test and procedures provided by the Commissioning Manager, Contractor and/or Supplier.All witnessing certificates such as Megger test, loop checks, pressure test, rotational speed test etc.

The following shall be done during these tests:

The equipment or module PLC sequence interlocks shall be checked. The checking, calibration and rectification of all instrumentation such as level, flow,

pressure, density, and power meter shall be done. The leaks, splashing and any other adverse operating features shall be eliminated. Unacceptable structural vibrations shall be identified and eliminated. Warranty repairs shall be identified and the installation Contractor and/or Supplier

will provide a programme for rectification.

Page 10 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 11: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

The Plant/Process Engineer shall be present during these test to familiarise himself with equipment.

C2 Commissioning Acceptance certificate must be signed of before proceeding to the next stage of commissioning.

8.3.C3 level – Commissioning “Material” – Commissioning Team and Plant Cold Commissioning

All individual interlocks are completed and the control room to then take ownership of the completed interlocks system for sequential testing.

It is essential that all the construction activities, in the applicable area, are complete at this stage.

All equipment that forms a module or stream shall be run together to allow balancing and to check all the interlocks and process control.

Material shall only commence once a discreet piece of equipment or system is ready to run sequentially.

The purpose of wet commissioning is limited running of discreet piece of equipment or system with water to essentially check pump ,pipes, shuts, cells, pumps, etc, confirm instrument calibrations and confirm sequences and interlocks.The Commissioning Manager must ensure that all outstanding C1 and C2 punch list items are complete or progressing as planned before handing over.

At this stage, no “modification requests” shall be accepted until proven during the next phase of commissioning i.e. if a pump does not perform as expected during this phase, for example, it is essential to establish that the pump will not behave entirely differently under normal operating conditions.

It is essential that the Plant/Process Engineer and plant Operation Team be involved at this stage of commissioning in order to facilitate a seamless progression to the next stage of commissioning.

The C3 Commissioning Acceptance Certificate must be signed of before proceeding to the next stage of commissioning.

At this stage prior to the start of C4 commissioning; the plant or sections of the works must be handed over and accepted by the Plant Operations team from the commissioning team. All

Page 11 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 12: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

safety, plant operations and maintenance of the works is the responsibility of the plant operations.

8.4.C4 level – Commissioning – Commissioning Team and Production Process Engineer. (Hot Commissioning)

The Production Process Engineer shall take over full operational, safety and maintenance responsibility for the water/ore commissioning on the discreet piece of equipment or system.

The purpose of this stage of commissioning is to introduce material to the equipment or system, starting at low rates and building up progressively until rated capacities are achieved.

The Commissioning Ma anger and his team will be available to assist the Production Process Engineer during this phase. The two Managers, Engineers and their respective teams will work together until the discreet piece of equipment or system is running with material at the rated capacity.

Once the equipment or system is fully commissioned with material, the Senior Process Metallurgist/Plant Process Engineers shall commence with the optimisation of each relevant piece of equipment. The equipment and/or system shall be manned and run for at least eight hours during the optimisation process. This optimisation process is to optimise the process in line with the plant design parameters only.

The C4 Commissioning Acceptance Certificate must be signed off before proceeding to the next and final stage of the commissioning stage.

8.5.C5 level – Commissioning “Production Build-up and Optimisation”- Production Process Engineer and Plant Operating Personnel (performance Test)

Production build-up and optimisation follows material commissioning. A comprehensive list of all process equipment requiring optimisation shall be made available together with the expected performance criteria.

The Contractors and/or Suppliers where deemed necessary may be asked to be available during optimisation of their equipment to assist the team and ensure that process/performance guarantees are met. This would also provide an opportunity to reinforce training of operators and artisans.

Once the process/performance guarantees and the operational efficiencies are met by a specific piece of equipment, a C5 Commissioning Acceptance Certificate will be filled in and signed by the Construction Engineer who shall then arrange for the Plant representative to observe the process and accept on behalf of the plant

Page 12 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 13: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

Once all the C5 Certificates have been signed off, the equipment or system shall be run at full production as per the requirements of test on completion before official hand over to the Plant. The Construction Manager shall submit the Final Hand over Certificate to the relevant Plant representative.

8.6.General

Loss Control Systems such as fire detection/prevention, fire hydrants, portable fire extinguishers, fire escape routes and general loss control shall be commissioned by a nominated Loss Control representative and audited by the Plant Loss Control Manager. The relevant Construction Engineer shall provide all the required certification and back-up documentation.

The Electrical Engineer shall commission the Power Management System before acceptance. The commissioning engineers shall accept the system.

9. Request for Site Modifications – Construction Team

The Request for Site Modifications, Procedure PPP-RSM shall apply to all modifications. These are generated by the Construction Team and/or Plant personnel and reviewed and approved/rejected by the Construction Manager.The cost implication for such a modification determined prior to completing such a request.

10. Final Handover

After the final handover to the Plant, the following activities may remain to be completed and are the responsibility of the Project and Construction Engineers.

Updating of operating manuals, flow sheets and P & Ids to reflect any modifications, which have been made during commissioning.

The completion and forwarding to production of as-build drawings resulting from modifications during commissioning.

Compilation of a post completion audit and report.

11. Commissioning team Identification and Induction

All personnel to undergo commissioning induction understand the lockout procedure and adhere to the lockout procedure

Stickers on hard hats and different ID cards are to be utilized to identify the commissioning team.

Page 13 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 14: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

12. Attachments Commissioning Acceptance Certificates

C1 Level – Commissioning Acceptance Certificate............................................................ENP-C1

C2 Level – Commissioning Acceptance Certificate............................................................ENP-C2

C3 Level – Commissioning Acceptance Certificate............................................................ENP-C3

C4 Level – Commissioning Acceptance Certificate............................................................ENP-C4

C5 Level – Commissioning Acceptance Certificate............................................................ENP-C5

Final Hand-Over Certificate...............................................................................................ENP-FHC

Project Hand-Over to Owner Certificate...........................................................................ENP-POC

Commissioning Punch List.................................................................................................ENP-PL

Request for Site Modifications..........................................................................................ENP-RSM

APPROVED FOR ISSUE

Name: ___________________ Name: ________________

Signature: ___________________ Signature: ________________

Date: ___________________ Date: ________________

GHCPPP Commissioning Manager GHCPPP PROJECT MANAGER

Page 14 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 15: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

C1 LEVEL – COMMISSIONING ACCEPTANCE CERTIFICATEForm No. ENP C1 REF DATE: 13/01/2011 REV. NO.:00

CONTRACTOR/SUPPLIER CONTRACT NUMBER DESCRIPTION OF EQUIPMENT PUNCH LIST NUMBER

This is to certify that the Equipment/System as described below has been tested and punch list to the satisfaction of the Construction Engineer.Upon signing this certificate the Construction Engineer undertakes to carry out the next stage of the commissioning process namely C2 level “Dry” Commissioning.It is the responsibility of the Contractor/Supplier to address the attached Punch List as per the programme agreed with The Construction Manager.

DETAILS OF WORK BEING HANDED OVER

RESPONSIBLE PERSON(PER DISCIPLINE)

DISCIPLINE NAME SIGNATURE DATESUB- CONTRACTOR/SUPPLIER ENPROTEC CONSTRUCTION MNGR CLIENT AREA MANAGER

Page 15 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 16: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

C2 LEVEL – COMMISSIONING ACCEPTANCE CERTIFICATEForm No. ENP C2 REF DATE: 13/01/2011 REV. NO.:00

CONTRACTOR/SUPPLIER CONTRACT NUMBER DESCRIPTION OF EQUIPMENT PUNCH LIST NUMBER

This is to certify that the Equipment/System as describe below has been “Dry” Commissioned to the satisfaction of the Construction Engineer.

Upon signing this Certificate the Commissioning Engineer undertakes to carry out the next stage of the commissioning process, namely C3 level “Wet” Commissioning.

It is the responsibility of the Contractor/Supplier to address the attached Punch List as per the programme agreed with the Construction Manager

DETAILS OF WORK BEING HANDED OVER

RESPONSIBLE PERSON(PER DISCIPLINE)

DISCIPLINE NAME SIGNATURE DATESUB- CONTRACTOR/SUPPLIER ENPROTEC CONSTRUCTION MNGR CLIENT AREA MANAGER

Page 16 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 17: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

C3 LEVEL – COMMISSIONING ACCEPTANCE CERTIFICATEForm No. ENP C3 REF DATE: 13/01/2011 REV. NO.:00

CONTRACTOR/SUPPLIER CONTRACT NUMBER DESCRIPTION OF EQUIPMENT PUNCH LIST NUMBER

This is to certify that the Equipment/System as described below has been successfully “Wet” Commissioned tested and that all outstanding C1 and C2 Punch List items are completed or progressing as planned.

Upon signing this certificate the Commissioning Process Engineer undertakes to carry out the next stage of the commissioning process, namely C4 level “Material” Commissioning.

DETAILS OF WORK BEING HANDED OVER

RESPONSIBLE PERSON(PER DISCIPLINE)

DISCIPLINE NAME SIGNATURE DATEEnprotec Commissioning Mgr Client Commissioning Mgr

Page 17 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 18: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

C4 LEVEL – COMMISSIONING ACCEPTANCE CERTIFICATEForm No. ENP C4 REF DATE: 13/01/2011 REV. NO.:00

CONTRACTOR/SUPPLIER CONTRACT NUMBER DESCRIPTION OF EQUIPMENT PUNCH LIST NUMBER

This is to certify that the Equipment/System as described below has been successfully commissioned with MATERIAL and the rated capacities of the Equipment/System were achieved.

Upon signing this certificate the Maintenance and Commissioning Process Engineers undertake the responsibility to out the next stage of the commissioning process, namely C5 level, Production Build-up, Maintenance, Operation and Optimisation.

It is the responsibility of the Contractor/Supplier to address the attached Punch List items as per the programme agreed with the Commissioning Process Engineer & Construction Manager.

DETAILS OF WORK BEING HANDED OVER

RESPONSIBLE PERSON(PER DISCIPLINE)

DISCIPLINE NAME SIGNATURE DATEEnprotec Commissioning Mgr Client Commissioning Mgr

Page 18 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 19: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

C5 LEVEL – COMMISSIONING ACCEPTANCE CERTIFICATEForm No. ENP C5 REF DATE: 13/01/2011 REV. NO.:00

CONTRACTOR/SUPPLIER CONTRACT NUMBER DESCRIPTION OF EQUIPMENT PUNCH LIST NUMBER

This is to certify that the Equipment/System as described below has been successfully commissioned with Material at the rated production capacities of the said Equipment/System.

It is the responsibility of the Commissioning Process Engineer/Construction Manager to address the outstanding Punch List items as per attached programme prior to handover.

Upon signing this certificate the Maintenance and Commission Process Engineers undertakes the responsibility to carry out the next stage of the commissioning process, namely FINAL HANDOVER TO THE PLANT.

DETAILS OF WORK BEING HANDED OVER

RESPONSIBLE PERSON(PER DISCIPLINE)

DISCIPLINE NAME SIGNATURE DATEEnprotec Commissioning Mgr Enprotec Project Mgr Client Senior Project Mgr

Page 19 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 20: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

Final Handover CertificateForm No. ENP- FHC REF DATE: 13/01/2011 REV. NO.:00

CONTRACTOR/SUPPLIER CONTRACT NUMBER DESCRIPTION OF EQUIPMENT PUNCH LIST NUMBER

This is to certify that he Equipment/System as described below has been successfully commissioned and meets the expected performance specifications (attached)

List of Exceptions

RESPONSIBLE PERSON(PER DISCIPLINE)

DISCIPLINE NAME SIGNATURE DATEEnprotec Commissioning Mgr Enprotec Project Mgr Client Senior Project Mgr

Page 20 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 21: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

Project Handover to Owner CertificateForm No. ENP-POC REF DATE: 13/01/2011 REV. NO.:00

CONTRACTOR/SUPPLIER CONTRACT NUMBER DESCRIPTION OF EQUIPMENT PUNCH LIST NUMBER

This is to certify that he Plant/System as described below has been successfully commissioned and meets the expected performance specifications (attached)

List of Exceptions

RESPONSIBLE PERSON(PER DISCIPLINE)

DISCIPLINE NAME SIGNATURE DATEAnglo Snr Project Mgr Anglo General Mgr Anglo Board Representative

Page 21 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 22: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

Commissioning Punch List

Form No. ENP-PL REV Date: 13/01/2010 REV No.:00

Punch List No: Date: Sheet__________of__________

Location/Plant: Contract Number:

Equipment Number: Contractor/Supplier:

Description of Equipment:

Drawing Number: Commissioning Level: (C1 to C5)

Item No. Description of Defect

Defect Type Due Date Actual Date Responsibility

Legend

DEFECT: D= Design Required

S = Safety Required M = Modification Required

O =Outstanding Item

TYPE: A = Equipment/System is not handed over or approved for "Dry" commissioning

B = "Dry" commissioning is authorized

C = Equipment/System is handed over subject to the attached punch list programme

Discipline Name Signature Date Discipline Name Signature Date

Originator Originator

Clerk of Works Clerk of Works

Enprotec Commissioning Mgr

Enprotec Commissioning Mgr

Page 22 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 23: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

Request for site ModificationsForm No. ENP-RSM REV Date: 13/01/2011

REV NO:00

Modification No: Date: Location/Plant: Plant or Plant Section: Orginator: Signature:

Full Description of Modification Requested

Reasons and Justification for Modification CRITICALITY MINOR NON-CRITICAL MAJOR

ESTIM. Cost - R Up to R1000 +R1000 upto R5000+R5000 upto

R10000 +R10000 upto R50000

Disruptions to Production

Nil Minor Medium Major

Disciplines Name Signature Date Comments Commissioning Eng. Process Eng. Construction Eng. Project Eng. Project Manager Design Manager

Decision and Actions Taken____________________________________________________________________________________________________________________________________________________________________

Page 23 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011

Page 24: Commissioning Procedure Goedehoop

Commissioning Procedure

Goedehoop Flotation Upgrade

Page 24 of 24

Enprotec Commissioning Procedure

Revision 01 Approved By: Date:

10/01/2011