columbia solar plant interconnect 69 kv switching station ... · columbia solar (q148) facilities...

58
Columbia Solar (Q148) Facilities Study July 13, 2018 Columbia Solar Plant Interconnect 69 kV Switching Station Facilities Study Report Final Version - 7/13/18 Energy Resource Interconnection Service and Network Resource Interconnection Service (Q148) Prepared by:

Upload: others

Post on 05-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

  • Columbia Solar (Q148) Facilities Study July 13, 2018

    Columbia Solar Plant Interconnect

    69 kV Switching Station

    Facilities Study Report

    Final Version - 7/13/18

    Energy Resource Interconnection Service and Network Resource Interconnection Service (Q148)

    Prepared by:

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 2 of 25

    Table of Contents 1.0 Executive Summary ........................................................................................................................... 3

    2.0 Baseline Assumptions ....................................................................................................................... 4

    3.0 Required Network Upgrades ............................................................................................................ 6

    3.1 Transmission Lines ........................................................................................................................ 6

    3.1.1 Work Scope ........................................................................................................................... 6

    3.1.2 Clarifications and Assumptions ............................................................................................. 7

    3.1.3 Transmission Line Cost Estimate ........................................................................................... 7

    3.2 Substation Physical ....................................................................................................................... 8

    3.2.1 Work Scope ........................................................................................................................... 8

    3.2.2 Major Substation Equipment ................................................................................................ 8

    3.2.3 Clarifications and Assumptions ............................................................................................. 9

    3.2.4 Cost Estimate ...................................................................................................................... 10

    3.3 Protection and Control................................................................................................................ 10

    3.3.1 Work Scope ......................................................................................................................... 10

    3.3.2 Major P&C Equipment ........................................................................................................ 12

    3.3.3 Remote End Substations ..................................................................................................... 12

    3.3.4 Clarifications and Assumptions ........................................................................................... 13

    3.3.5 Protection and Control Cost Estimate ................................................................................ 14

    3.4 Telecommunications ................................................................................................................... 14

    3.4.1 Work Scope ......................................................................................................................... 14

    3.4.2 Clarifications and Assumptions ........................................................................................... 15

    3.4.3 Telecommunications Cost Estimate .................................................................................... 15

    4.0 Connection Requirements .............................................................................................................. 16

    4.1 General ........................................................................................................................................ 16

    4.2 Point of Interconnection ............................................................................................................. 16

    4.4 Equipment Ratings and Protection Coordination ....................................................................... 16

    4.5 Insulation Requirements ............................................................................................................. 17

    4.6 Communications ......................................................................................................................... 17

    4.7 Metering ..................................................................................................................................... 17

    4.8 Grounding ................................................................................................................................... 17

    5.0 Cost Estimate Summary .................................................................................................................. 18

    6.0 Milestone Schedule ......................................................................................................................... 19

    7.0 Appendices ...................................................................................................................................... 20

    8.0 Facilities Study Approval ................................................................................................................. 25

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 3 of 25

    1.0 Executive Summary

    The Q148 Solar Plant is a planned Solar PV station, capable of 74.9 MW net output. The facility will be located in Columbia County, Florida (See Appendix A). The point of interconnection will be a new four (4) terminal, four (4) breaker 69kV Columbia Switching Station, initially configured as a ring bus. The switching station will be used to loop in and out Duke Energy Florida’s (DEF) Fort White to High Springs (FH) 69kV line including the Fort White Clay Electric Cooperative Tap creating: Fort White to Columbia, Fort White Clay Electric Cooperative to Columbia and High Springs to Columbia 69kV lines. The fourth terminal will be for connection to the proposed Solar PV station.

    The customer has requested this generation facility be studied for Network Resource Interconnection Service (NRIS) and Energy Resource Interconnection Service (ERIS) with a requested Commercial Operating Date (COD) of December 31, 2019.

    Duke Energy Florida (DEF) the “Transmission Company” previously completed a System Impact Study (SIS) and issued the report on March 15, 2018, that summarizes the thermal, voltage, short circuit and transient stability impacts associated with the proposed interconnection.

    The primary objective of this Facilities Study (FS) is to quantify necessary Transmission Owner network upgrade(s), other direct assigned upgrade(s), and associated upgrade lead times. Therefore, this FS quantifies the cost, work scope, and tentative schedules associated with the design and installation of the required network modifications. This study evaluates and estimates the date that service could be granted based on specific criteria outlined within this report.

    The SIS identified potential network upgrades to DEF’s transmission network to accommodate the full capacity of the proposed Solar PV station under NRIS. This included a third Powerline to Holder 230kV line that was found to be required due to an N-1 contingency. This line would connect to a proposed Powerline Substation that was identified previously in another queue study with an in-service date of 2021 which would need to be in-service prior to completion of a NRIS interconnection.

    The facilities and costs discussed herein are for DEF upgrades only, and do not include any known or potential affected system upgrades. In the SIS, a Third Party Short Circuit Impact was identified. The short circuit analysis revealed one impact greater than 3% to a third-party (SECI/CEC delivery point) substation. All third-party impacts will be evaluated further in a future FRCC-TTS Reliability Assessment that is performed on Generator Interconnection Service Requests (GISR) and Transmission Service Requests (TSR) that potentially affect the FRCC region.

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 4 of 25

    The short circuit analysis performed in the SIS revealed impacts greater than 3% at several DEF substations. These substations were reviewed, and no equipment was identified as being over-dutied.

    The FS includes cost estimates to permit, engineer, procure equipment and materials, construct and place facility upgrades or additions in service to accomplish the requested service.

    The facilities needed to accomplish the interconnection have been reviewed and proposed schedules for completion were based on the DEF and the Customer executed Agreement/Contract on March 16, 2018. Schedules were developed utilizing typical project durations experienced by DEF for project engineering, procurement, permitting, construction, and outage requirements. Schedules durations do not include seasonal capacity considerations as well as system configuration constraints such as concurrent line outages.

    Subsequent to the requirements and preparation listed in this document a design review shall take place prior to any facilities construction to maintain compliance with the North American Electric Reliability Corporation (NERC) Reliability Standard FAC-002-1, or its successor. Also, in compliance with the NERC Reliability Standard FAC-002-1, or its successor, a testing and inspection activity will take place prior to the in-service date.

    2.0 Baseline Assumptions

    The estimated costs and schedule are based on the assumptions identified in this Facilities Study.

    The Transmission Company’s (DEF’s) Facilities are based on application of industry standard equipment. All new and rebuilt facilities will be designed and built according to the DEF’s current practice. These facilities will become a part of the DEF network transmission system therefore in addition to having sufficient capacity to accept the proposed Solar PV station generation these facilities must also have the capacity to carry the power flows to upstream loads. As such the total energy handling capability of the proposed interconnection facilities could potentially accommodate energy flows greater than the requested 74.9 MW. However, in the event the Customer decides to designate additional capacity, a new request will be required to evaluate the impacts. Any constraints that may result will be identified as part of the new study request.

    Any required outages necessary to support construction of the Interconnect Facilities must be coordinated with the DEF Energy Control Center (“ECC”). If an outage of sufficient duration cannot be obtained to support any of the required construction activities, alternative solutions such as new facilities or temporary facilities may have to be constructed to maintain integrity of the grid. No provisions have been made for temporary work in the estimates provided herein.

    The proposed protection schemes to be installed by DEF at the Associated Facilities are intended to protect DEF’s Transmission Network.

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 5 of 25

    Estimates prepared for this FS are considered to be good faith estimates represented in present day dollars as of the date of the study. The estimates do not include upgrade costs for third party facilities. The cost estimates provided use currently available pricing in Duke’s estimating system. The estimated budget has been computed with an expected accuracy of +/-20 %. Costs may fluctuate due to inflation or changes in market price. The estimates are further premised on being able to perform work during normal business hours with minimum overtime or weekend work. The estimates assume no changes in scope or design from that provided in previous studies.

    Cost estimates are inclusive of engineering, material (equipment, structures, conductors, OPGW, etc.), survey, geotechnical, access, clearing, siting, environmental, construction and removal.

    Cost estimates for the NRIS required third Powerline to Holder 230kV line are from a previous facilities study (Q137 Shady Hills) and will need to be revised if the customer proceeds with NRIS.

    DEF will be provided with sufficient easements across the solar facility for the new switching station, 69kV loop and the Fort White – Fort White Clay Electric Cooperative 69kV Tap (see Appendix A) at the location identified in the Q148 Facilities Study Agreement dated March 26, 2018. The Customer will provide the environmental permits (FDEP, USACOE, EPA, County, etc.), storm water permits, endangered species permits, Historical Resources studies, zoning and driveway permits. DEF shall be responsible for complying with the permit conditions, the SWPPP (by DEF) and any other Best Management Practices required by these permits. DEF will be responsible for any construction related permits for the switch yard, transmission lines and storage yard.

    A draft Large Generator Interconnection Agreement (LGIA) will be provided to the Interconnection Customer consistent with the final results of this report. The Interconnection Customer will have 30 days to execute the LGIA consistent with the Joint Open Access Transmission Tariff.

    The scope of work, durations, clarifications, assumptions and cost estimates apply to the core work associated for both NRIS and ERIS. Additional scope required for NRIS is identified throughout the document as required.

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 6 of 25

    3.0 Required Network Upgrades

    3.1 Transmission Lines

    The transmission line scope changes of the facilities that are required to support this transmission service are addressed by the following sections.

    3.1.1 Work Scope

    Columbia 69kV Switching Station

    The result of the SIS requires the following upgrades in support of the Columbia Solar interconnection request:

    Loop-in 69kV lines from Fort White, Fort White Clay Electric Cooperative Tap and High Springs substations. Cut-in occurs approximately mid-span of Fort White to High Springs Line. Existing lines are on single circuit poles.

    ▪ Install two (2) steel dead ends in the existing Fort White – High Springs 69 kV line atexisting structure FH-102 and construct a loop in and out of the Northeast andSouthwest Bays of the new Columbia Interconnect Sub. A total of six (6) dead end poleswill be needed to construct the loop.

    ▪ Install one (1) steel dead end in the existing Fort White – Fort White Clay ElectricCooperative 69 kV Tap at existing structure FH-99-4 and construct 0.2 miles of new lineinto the Northwest Bay of the new Columbia Interconnect Sub. A total of four (4) steelpoles will be needed to construct the tap.

    ▪ Anticipating 20’ direct embedded foundations utilizing concrete backfill▪ Existing 4/0 HDB Copper and 795 ACSR will be dead-ended on new structures and new

    1272 ACSS TW will be installed into the new substation terminals▪ The existing switch at FH-99 will be removed and approximately 0.1 miles of the Fort

    White – Fort White Clay Electric Cooperative 69 kV Tap from FH-99 to FH-99-4 will beremoved

    This will create Fort White to Columbia, Fort White Clay Electric Cooperative to Columbia and High Springs to Columbia 69 kV lines. (See Appendix A)

    NRIS

    In addition to the scope required for ERIS, NRIS also requires the addition of a third Powerline to Holder 230kV line due to an N-1 contingency. In addition, the Lecanto to Pine Ridge 115kV line is overloaded which would also be resolved by a third Powerline to Holder 230kV line. This line was identified previously in another queue study (Q137 Shady Hills). As identified in the previous study, the current DEF practice is to utilize 3000A capacity lines with 2627 KCM ACSS/TW/HS Santee conductor.

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 7 of 25

    3.1.2 Clarifications and Assumptions

    ▪ It is assumed that the outages/clearances required for construction are compatible withload flow conditions at the time of construction. These projects may require difficult toobtain outages which could delay or increase the cost of this project, if they are notreceived in a timely manner.

    ▪ It is assumed that the Customer will build the generator lead lines from the proposed

    Solar PV station to the Columbia 69kV Switching Station - Point of Interconnection (see

    Appendix C)

    ▪ NRIS only (from Q137 Shady Hills)o The new Powerline to Holder line will be built in the existing Crystal River Plant

    to Central Florida right-of-wayo The new Powerline substation is assumed to be in-service, prior to the

    construction of the upgrades associated with Q148 and is therefore not included

    in the scope of work

    3.1.3 Transmission Line Cost Estimate

    ERIS

    Q148 69kV Fort White to Columbia, High Springs to Columbia, Fort White C.E.C. to Columbia, Solar Station to

    Columbia

    Estimated Cost ($)

    Engineering $91,000

    Equipment and Material $303,000

    Labor $551,000

    Other (includes Indirect Allocations) $204,000 Total $1,149,000

    NRIS

    NRIS Required Upgrades Estimated Cost ($)

    Q148 69kV Fort White to Columbia, High Springs to Columbia, Fort White C.E.C. to Columbia, Solar Station to Columbia

    $1,149,000

    230kV Line from Powerline Sub to Holder Substation (from Q137 Shady Hills)

    $32,054,000

    Total $33,203,000

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 8 of 25

    3.2 Substation Physical

    3.2.1 Work Scope

    The physical scope of work identified in this study is listed below. For all the equipment identified:

    Columbia 69kV Switching Station

    ▪ A four (4) position 69kV ring bus with associated breakers, switches and bus (See AppendixB)

    ▪ Four (4) 69kV line positions with associated dead-end towers, motor operated line switches,surge arresters, and potential transformers (PT)

    ▪ The switching station will be used to loop in and out DEF’s Fort White to High Springs (FH)69kV line including the Fort White Clay Electric Cooperative Tap creating: Fort White toColumbia, Fort White Clay Electric Cooperative to Columbia and High Springs to Columbia69kV lines

    o Three (3) of the line positions will be used to loop in/out the Fort White to HighSprings 69kV line including the Fort White Clay Electric Cooperative Tap

    o The fourth line position will be for the interconnection of the proposed Solar PVstation

    ▪ Install 69kV current transformers (CT) & PTs on the proposed Solar PV station 69kV line formetering

    ▪ New HDS-Small Control Equipment Enclosure (CEE) building (approx. 28’-8” x 44’-0”)▪ Four station service voltage transformers (SSVT), 69kV / 240-120V, 100kVA and associated

    69kV switches, fused disconnects, auto transfer switch (flip flop), and AC panels

    NRIS

    In addition to the new 69kV Columbia Switching Station, NRIS also requires the addition of a new line position at DEF’s Powerline Substation for a third Holder 230kV line and a new line position at DEF’s Holder Substation for a third Powerline 230kV line.

    3.2.2 Major Substation Equipment

    Columbia 69kV Switching Station

    New yard equipment to be installed for 69kV Columbia Switching Station:

    ▪ Four (4) Motor Operated Switches 2000A▪ Four (4) 69kV / 240-120V, 100kVA Station service voltage transformers▪ Four (4) 69kV 3000A 40kA Circuit Breakers▪ Ten (10) 69kV 2000A disconnect switches with manual operators▪ Twelve (12) single-phase PT’s for 69kV lines▪ Three (3) single-phase metering class PT’s for 69kV revenue metering

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 9 of 25

    ▪ Three (3) single-phase metering class CT’s for 69kV revenue metering▪ Twelve (12) 69kV station class surge arresters

    NRIS In addition to the new 69kV Columbia Switching Station, NRIS also requires the scope of work from the Q137 Shady Hills FS at Powerline Substation and Holder Substation including the following equipment:

    ▪ Powerline Substationo Five (5) 230kV, 3000A, disconnect switches including four (4) breaker switches

    and one (1) motor operated line switcho Two (2) 230kV, 3000A, breakerso One (1) 230kV, dead-end towero Three (3) 230kV PT’so Three (3) 230kV surge arresterso 4” IWCB bus & double 1750 AAC jumpers

    ▪ Holder Substationo Three (3) 230kV, 3000A, disconnect switches including two (2) breaker switches

    and one (1) motor operated line switcho Two (2) 230kV, 3000A, breakerso One (1) 230kV, dead-end towero Three (3) 230kV PT’so Three (3) 230kV surge arresterso Complete 230kV ring buso 4” IWCB bus & double 1750 AAC jumpers

    3.2.3 Clarifications and Assumptions

    ▪ This report does not consider possible environmental (wetlands, soil contamination,etc.) mitigation. Testing and environmental assessments are required to identify andquantify environmental costs. These items are outside the scope of this study.

    ▪ The ability to utilize standard and typical foundations is assumed▪ This report assumes the ability to acquire a suitable site adjacent to the existing DEF

    Fort White to High Springs 69kV right-of-way for the proposed 69kV Columbia SwitchingStation

    ▪ It is assumed that the Customer will provide a suitable area of sufficient size at no costadjacent to the proposed 69kV Columbia Switching Station that can be utilized as amaterial storage yard

    ▪ It is assumed that the Customer will provide a suitable driveway and access road fromthe existing road (Fry Road) to the proposed 69kV Columbia Switching Station site

    ▪ Costs associated with upgrades to remote end ground grids (if required) are notincluded

    ▪ DEF will have full access and rights to the property to perform due diligence uponexecution of Interconnection Agreement.

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 10 of 25

    3.2.4 Cost Estimate

    ERIS

    Q148 Columbia Switching Station Estimated Cost ($)

    Engineering $475,000

    Equipment and Material $1,515,000

    Labor $2,964,000

    Other (includes Indirect Allocations) $1,025,000 Total $5,979,000

    NRIS

    NRIS Required Upgrades Estimated Cost ($)

    Q148 Columbia Switching Station $5,979,000

    Holder Substation (from Q137 Shady Hills FC)

    $2,347,000

    Powerline Substation (from Q137 Shady Hills FC)

    $1,662,000

    Total $9,988,000

    3.3 Protection and Control

    3.3.1 Work Scope

    This project includes a complete Protection and Control package for the new 69kV Columbia Switching Station interconnections to existing DEF’s Fort White (111), Fort White Clay Electric Cooperation Tap (6851) and High Springs (67) substations using a ring bus configuration with four (4) breakers and four (4) line positions including one (1) position for connection to the proposed Solar PV station (by others).

    Protection system addition or upgrades shall be implemented with full redundancy. New breakers will utilize a breaker control relay and a breaker failure relay, with current supervision, from a bushing current transformer on the breaker. Should a breaker fail to trip within the allowable time setting, the associated breaker failure trip relay and associated lockout relay will trip and lock out adjacent breakers and remote breakers via breaker failure transfer trip.

    The transmission line protective relay schemes continuously monitor conditions of the transmission lines and are designed to detect and isolate the faults with appropriate speed and minimum disturbance to the system. The transmission lines will be protected by redundant Line Protection 1 and Line Protection 2 current differential relays designed to clear a fault on the line. The schemes will use relay-to-relay communications utilizing fiber optic cable.

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 11 of 25

    Columbia 69kV Switching Station

    Items listed in the following table are the collective number of devices required for the 69kV Columbia Switching Station.

    Total Qty

    Device Function

    4 SEL-311L Line Protection 1

    4 SEL-411L Line Protection 2

    1 SEL-735 Power Quality Meter

    4 86-LOR/ER Breaker Failure Transfer Trip Lockout (Elec Reset)

    4 SEL-351S MOS Control

    4 SEL-351S Breaker Control

    4 SEL-451 Breaker Failure

    4 86-LOR Breaker Failure Lockout

    NRIS

    In addition to the new 69kV Columbia Switching Station, NRIS also requires the following protection & control scope of work at Powerline Substation and Holder Substation based on the Q137 Shady Hills FS for the Powerline to Holder 230kV line:

    Total Qty

    Device Function

    1 SEL-311L Line Protection 1

    1 SEL-411L Line Protection 2

    1 86-LOR/ER Breaker Failure Transfer Trip Lockout (Elec Reset)

    1 SEL-351S MOS Control

    2 SEL-351S Breaker Control

    2 SEL-451 Breaker Failure

    2 86-LOR Breaker Failure Lockout

    *Items listed in the previous table are collectively referred to as “P&C linepackage” in subsequent scope items

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 12 of 25

    3.3.2 Major P&C Equipment

    69kV Columbia Switching Station

    ▪ New Control Equipment Enclosure HDS/Small size 28’-8”x 44’-0” outer dimension▪ One (1) Battery Bank #1 (approx. size 200AH) and associated battery charger (approx.

    size 25AH)▪ Relay panels

    o 69kV High Springs Line LP1, BKR 8081 CTRL & MOS 8085 CTRLo 69kV High Springs Line LP2, BKR 8081 BFo 69kV Solar PV Station Meteringo 69kV Solar PV Station LP1, BKR 8088 CTRL & MOS 8089 CTRLo 69kV Solar PV Station LP2, BKR 8088 BF, Power Quality Metero 69kV Fort White Line LP1, BKR 8084 CTRL & MOS 8074 CTRLo 69kV Fort White Line LP2, BKR 8084 BFo 69kV Fort White Clay Electric Cooperative Tap Line LP2, BKR 8072 BFo 69kV Fort White Clay Electric Cooperative Tap Line LP1, BKR 8072 CTRL & MOS

    8070 CTRLo Securityo P&C TSCADAo P&C Non-CONTROL CLOCKo IT/Telecom #2o IT/Telecom #1

    3.3.3 Remote End Substations

    There are three existing remote end substations associated with the interconnection including

    Fort White (111), Fort White Clay Electric Cooperation Tap (6851) and High Springs (67)

    substations.

    Fort White Substation

    The existing protection schemes at Fort White for the High Springs 69kV line will be upgraded

    by the end of 2018 to include Line Current Differential protection under a separate, in-process

    project. Upon commissioning of the 69kV Columbia Switching Station, the relay settings for the

    Fort White to High Springs 69kV line will be modified to accommodate what will become the

    Fort White to Columbia Switching Station 69kV line.

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 13 of 25

    High Springs Substation

    The existing protection schemes at High Sprints for the Fort White 69kV line will be upgraded

    by the end of 2018 to include Line Current Differential protection. Upon commissioning of the

    69kV Columbia Switching Station, the relay settings for the High Springs to Fort White 69kV line

    will be modified to accommodate what will become the High Springs to Columbia Switching

    Station 69kV line.

    Clay Electric Co-op Substation

    Upon commissioning of the 69kV Columbia Switching Station, the incoming line name change

    to Clay Electric Co-op will need to be communicated and updated on their system.

    NRIS

    ▪ In addition to the new 69kV Columbia Switching Station and associated remote ends,NRIS also requires the following protection & control scope of work at PowerlineSubstation and Holder Substation based on the Q137 Shady Hills FS for the Powerline toHolder 230kV line:

    o One (1) P&C line package at the Holder Substation location▪ 230kV Powerline Line LP1, BKR CTRL & MOS CTRL▪ 230kV Powerline Line LP2, BF

    o One (1) P&C line package at the Powerline Substation location▪ 230kV Holder LP1, BKR CTRL & MOS CTRL▪ 230kV Holder LP2, BF

    3.3.4 Clarifications and Assumptions

    ▪ The standard 69kV line protection includes primary & backup SEL-311L and SEL-411Lrelaying, breaker failure tripping is provided using SEL-451

    ▪ The project generating units will meet all applicable NERC Standards▪ NRIS only

    o The standard 230kV line protection includes primary & backup SEL-311L and SEL-

    411L relaying, breaker failure tripping is provided using SEL-451

    o The new Powerline substation is assumed to be in-service, prior to the

    construction of the upgrades associated with Q148 and is therefore not included

    in the scope of work

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 14 of 25

    3.3.5 Protection and Control Cost Estimate

    ERIS

    Q148 69kV Columbia Switching Station and Associated Remote Ends Protection and Control Cost

    Estimated Cost ($)

    Engineering $509,000

    Equipment and Material $529,000

    Labor $1,095,000

    Other (includes Indirect Allocations) $478,000 Total $2,611,000

    NRIS

    NRIS Required Upgrades Estimated Cost ($)

    Q148 69kV Columbia Switching Station and Associated Remote Ends

    $2,611,000

    Holder Substation (from Q137 Shady Hills FC)

    $250,000

    Powerline Substation (from Q137 Shady Hills FC)

    $250,000

    Total $3,111,000

    3.4 Telecommunications

    3.4.1 Work Scope

    This project requires fiber to be installed to the proposed Columbia Switching Station for tele-protection and SCADA. ADSS will be installed from a splice point on the existing DEF FO 230kV line (Fort White to Ginnie Springs) to the Columbia Switching Station. Approximately 28,900 feet will be underground build and then connected to the new Columbia Switching Station. The Columbia Switching Station to Fort White 69kV line will include Direct Fiber and J-MUX forms of communication. The 69kV Columbia Switching Station to High Springs 69kV line will utilize J-MUX communication.

    Procure and install as required the necessary equipment to support J-MUX and Direct Fiber at the Columbia Switching Station, this includes:

    ▪ One (1) GE JungleMUX device▪ One (1) Fiber Patch Panel▪ One (1) 2010 Connected Grid Router▪ Three (3) 2520 Connected Grid Switches▪ One (1) Positron Power

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 15 of 25

    NRIS

    In addition to the new 69kV Columbia Switching Station, NRIS also requires the following telecommunications scope of work at Powerline Substation and Holder Substation based on the Q137 Shady Hills FS for the Powerline to Holder 230kV line:

    ▪ Installation of fiber from the dead-end tower into the control house at Holder andPowerline

    ▪ Perform OPGW to ADSS transition splicing at the terminals at both substations▪ Perform OPGW line splicing at 5 locations along the line

    3.4.2 Clarifications and Assumptions

    ▪ There is DC available to power the Telecom equipment▪ For the OPGW builds, splices will be performed where necessary along the routes

    3.4.3 Telecommunications Cost Estimate

    ERIS

    Q148 69kV Columbia Switching Station Estimated Cost ($)

    Engineering $62,000

    Equipment and Material $286,000

    Labor $180,000

    Other (includes Indirect Allocations) $72,000 Total $600,000

    NRIS

    NRIS Required Upgrades Estimated Cost ($)

    Q148 Columbia Solar Station Switch Yard $600,000

    230 kV Line from Powerline Sub to Holder Substation

    $192,000

    Total $792,000

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 16 of 25

    4.0 Connection Requirements

    4.1 General

    This Facilities Study document is intended to provide a basic scope definition of facilities on which the Transmission Company has based its facilities study and cost estimates. It shall serve as the basis for the facilities that the Transmission Company proposes to design, build, and operate in connection with interconnection of Customer generation in the Columbia County, FL area. DEF requires the installation of a Customer owned circuit breaker to be located at the high side of the Generator Step-Up Transformer (GSU).

    4.2 Point of Interconnection

    The point of interconnection (POI) will be the “face of steel” on the dead-end tower inside the proposed DEF 69kV Columbia Switching Station. The Customer will install and own the jumpers from the strain bus connection dead-end insulators to the 69kV disconnect switch in the 69kV Columbia Switching Station (See Appendix C). The Customer shall install a Phasor Measurement Unit (PMU) at the Point of Interconnection (POI), according to DEF’s Facility Connection Requirements.

    The Customer will own, maintain and install all facilities from this point back to the proposed Solar PV Station including the strain bus.

    4.3 Short-Circuit Withstand Capability

    DEF assumes no responsibility for appropriately sizing the short circuit withstands capability of any equipment installed on the Customer’s Side of the POI. DEF will provide upon request the maximum available short circuit current based on its current models. The Customer will need to exercise extreme care in appropriately sizing its equipment while providing for reasonable margin for future increases in available short circuit current. The Transmission Company bears no responsibility in the sizing decision.

    4.4 Equipment Ratings and Protection Coordination

    Prior to finalizing the specification for the equipment necessary to interconnect to the power grid, the Customer shall consult with DEF to establish the required ratings necessary to reliably interconnect and provide the expected Voltage and VAR support as defined in the Interconnection and Operating Agreement. Specific parameters shall include but are not limited to available transformer taps and short circuit withstands capabilities.

    Customer shall also coordinate their relay protection schemes to be in compliance with the DEF requirements.

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 17 of 25

    4.5 Insulation Requirements

    DEF’s standard requirements for equipment installed on the 69kV systems shall meet the following minimum Basic Insulation Level (BIL).

    69kV BIL Basic Insulation Level (BIL) *350kV

    * 550kV BIL required for Station Post Insulators and Airbreaks

    4.6 Communications

    The Customer will provide 48 fiber optic- cable (OPGW or ADSS) including a splice interface cabinet from the proposed Solar PV Plant to the POI as described in Section 4.2

    4.7 Metering

    Metering shall comply with Duke Energy Florida’s “Transmission Interconnection/Generation/Revenue Metering”, Rev. 11/7/2017. See Appendix D.

    4.8 Grounding

    Grounding of the Customer’s interconnect facilities shall comply with the requirements Duke’s STDP-STD-TRM-00098 rev. 000 “Standard Ground Grid System.” See Appendix E.

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 18 of 25

    5.0 Cost Estimate Summary

    ERIS

    The ERIS option requires the installation of a 69kV Columbia Switching Station with a 4-terminal configuration including the associated transmission line work. Located in Columbia County, Florida, the station will be built at the interconnection point adjacent to the existing DEF Fort White and High Springs (FH) 69kV line. The ERIS estimated cost breakdown of the 69kV Columbia Switching Station is located below in the following table and is based on LGIA execution as identified in Section 2.0 Baseline Assumptions.

    Q148 Columbia Switching Station

    Engineering Material Labor Other (includes Indirect Allocations)

    Total ERIS Estimate

    Transmission Line $91,000 $303,000 $551,000 $204,000 $1,149,000

    Switching Station Physical

    $475,000 $1,515,000 $2,964,000 $1,025,000 $5,979,000

    Protection and Control $509,000 $529,000 $1,095,000 $478,000 $2,611,000

    Telecommunications $62,000 $286,000 $180,000 $72,000 $600,000

    TOTAL $ 1,137,000 $2,633,000 $4,790,000 $1,779,000 $10,339,000

    NRIS

    The NRIS option includes the scope identified above under ERIS in addition to the necessary build of the third Powerline to Holder 230kV line, which currently is assigned to the Shady Hills (Q137) project. Per the Q137 Shady Hills LGIA, the project is expected to be completed by November 30, 2021. Substantial acceleration of this schedule is unlikely. If the In-Service Date (ISD) for this Q148 Facilities Study is after the Q137 Shady Hills ISD, no additional network upgrades beyond the scope identified for ERIS are required for Q148 to proceed with NRIS. The table below shows the NRIS estimated cost of the required facilities and builds necessary if completed prior to Q137 Shady Hills. If the planned Q148 ISD is after the Q137 ISD, the estimated cost for NRIS will be the same as the estimated cost for ERIS.

    Project Total NRIS Estimate ($)

    69kV Columbia Switching Station (from this facilities study) $10,339,000

    Powerline to Holder 230kV Line and Substations (potentially required for NRIS, costs from Q137 Shady Hills)

    $36,755,000

    TOTAL ESTIMATE $47,094,000

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 19 of 25

    6.0 Milestone Schedule

    ERIS

    The table below identifies completion timeframes for major activities for this project with an

    expected ISD of 24 months from LGIA execution as identified in Section 2.0 Baseline

    Assumptions.

    Activity Date

    Interconnection Agreement Executed LGIA

    Initiate Request for Proposal LGIA + 2 weeks

    Contract Award LGIA + 24 weeks

    Permitting LGIA + 55 weeks

    Line Engineering LGIA + 44 weeks

    Civil Engineering LGIA + 60 weeks

    Substation Physical Engineering LGIA + 60 weeks

    Protection and Control Engineering LGIA + 64 weeks

    Line Construction LGIA + 92 weeks

    Civil/Control Equipment Enclosure Construction LGIA + 103 weeks

    Substation Physical Construction LGIA + 100 weeks

    Protection and Control Construction LGIA + 102 weeks

    Ready for Backfeed LGIA + 96 weeks

    In-Service LGIA + 104 weeks

    Schedule durations may be impacted by outage availability and time of the year the work is

    planned.

    NRIS

    Schedule for NRIS is dependent on the planned ISD for the 3rd Powerline to Holder 230kV

    circuit, related to the Q137 Shady Hills project as identified in Section 5.0 Cost Estimate

    Summary.

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 20 of 25

    7.0 Appendices

    Appendix A Location Map

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 21 of 25

    Appendix B Switching Station Proposed Three-Line

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 22 of 25

    Appendix C Point of Interconnection

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 23 of 25

    Appendix D Metering Standard

    (Attached)

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 24 of 25

    Appendix E Grounding Standard

    (Attached)

  • Facilities Study Report

    Columbia Solar (Q148) Facilities Study July 13, 2018 Page 25 of 25

    8.0 Facilities Study Approval This Facilities Study for the Columbia Solar Plant Interconnection reports on the Energy Resource Interconnection Service (ERIS) and Network Resource Interconnection Service (NRIS) required for a new Solar PV Plant to be located in Columbia County, FL.

    Approval Signatures:

    Ray De Souza Ed Scott Director, Transmission Engineering Director, Transmission Planning

  • Tra

    nsm

    issi

    on

    Inte

    rco

    nnec

    tion

    /Gen

    era

    tion

    /Rev

    en

    ue M

    ete

    ring

    Cre

    ate

    d b

    y:

    Jose

    ph

    L.

    Sta

    rnes

    , M

    ete

    r E

    ng

    inee

    rin

    g a

    nd

    Su

    ppo

    rt

    Ap

    pro

    ved

    by:

    Au

    gu

    st 1

    6, 2

    01

    7

    Rev

    ise

    d:

    Nov

    em

    ber

    7, 2

    017

    Du

    ke E

    ner

    gy

    Flo

    rida

  • En

    gr.

    Doc

    : T

    ran

    smis

    sio

    n In

    terc

    onn

    ectio

    n-G

    ene

    ratio

    n M

    ete

    ring

    Da

    te:

    Aug

    ust

    16

    , 20

    17

    Pag

    e 2

    of

    6

    1.

    SC

    OP

    E

    1.1

    Th

    is

    docu

    men

    t re

    fers

    to th

    e D

    uke

    En

    erg

    y F

    lorid

    a r

    equ

    irem

    en

    ts f

    or t

    ran

    smis

    sio

    n le

    vel I

    nte

    rco

    nne

    ctio

    n/G

    ene

    ratio

    n/R

    eve

    nue

    M

    ete

    ring

    be

    twee

    n D

    uke

    Ene

    rgy

    Flo

    rida

    an

    d an

    y in

    terc

    on

    nect

    ion

    an

    d/o

    r re

    venu

    e b

    ase

    d cu

    stom

    er/

    util

    ity b

    ein

    g se

    rved

    at

    tran

    smis

    sion

    vo

    ltage

    leve

    ls 6

    9kV

    an

    d ab

    ove

    .

    1.2

    S

    ectio

    ns

    2 t

    hro

    ugh

    7 a

    dd

    ress

    the

    ge

    ne

    ral i

    nte

    rco

    nne

    ctio

    n re

    qu

    irem

    ents

    . 2

    . L

    OC

    AT

    ION

    2.1

    W

    hen

    a D

    uke

    Ene

    rgy

    Flo

    rida

    line

    ter

    min

    al h

    as

    been

    det

    erm

    ine

    d to

    be

    wh

    ere

    inte

    rcon

    nec

    t m

    ete

    rin

    g is

    to b

    e in

    sta

    lled

    , th

    ere

    will

    b

    e a

    me

    ter

    pa

    cka

    ge w

    ith p

    rim

    ary

    an

    d b

    ack

    up m

    ete

    rs.

    Typ

    ical

    ly t

    he

    me

    ter

    pa

    cka

    ge s

    hall

    be in

    sta

    lled

    in a

    su

    bst

    atio

    n c

    ontr

    ol

    hou

    se p

    an

    el.

    3

    . C

    UR

    RE

    NT

    IN

    PU

    T T

    O M

    ET

    ER

    ING

    3.1

    P

    rimar

    y M

    ete

    ring

    CT

    s

    3.1

    .1

    Pri

    ma

    ry M

    ete

    ring

    CT

    s sh

    all

    be

    hig

    h a

    ccu

    racy

    ext

    end

    ed

    ra

    nge

    (H

    AE

    R)

    curr

    en

    t t

    ran

    sfo

    rme

    rs w

    ith a

    ra

    tio w

    hic

    h w

    ill in

    clu

    de

    the

    con

    tinu

    ous

    ratin

    g of

    the

    conn

    ect

    ed d

    evi

    ces

    at t

    he

    hig

    hest

    em

    erg

    enc

    y ra

    ting

    of

    the

    ass

    ocia

    ted

    ele

    men

    t.

    3.1

    .2M

    inim

    um

    acc

    ura

    cy c

    lass

    : 0

    .15

    @ B

    urd

    en 1

    .8

    3.1

    .3

    Acc

    ura

    cy R

    ang

    e: *

    *1%

    - 2

    00%

    of

    rate

    d ra

    tio (

    20

    400

    0 a

    mpe

    res

    usi

    ng a

    20

    00:5

    rat

    io w

    ith a

    ra

    ting

    fact

    or =

    2.0

    as

    an

    e

    xam

    ple

    ) .

    CT

    s w

    ith 5

    % -

    200

    % o

    f ra

    ted

    rat

    io is

    als

    o a

    cce

    pta

    ble

    .

    3.2

    N

    o bu

    rde

    n o

    ther

    tha

    n th

    e m

    ete

    r sh

    all

    be c

    onn

    ect

    ed

    in th

    e m

    ete

    ring

    CT

    cir

    cuits

    .

    3

    .3C

    T r

    atio

    3.3

    .1

    CT

    rat

    io s

    ha

    ll b

    e e

    ither

    100

    0:5

    or 2

    00

    0:5

    de

    pen

    din

    g on

    the

    lim

    itin

    g e

    lem

    ent

    fact

    or.

    Th

    e r

    atio

    sha

    ll be

    as

    sma

    ll as

    po

    ssib

    le

    to p

    rovi

    de t

    he r

    equi

    red

    acc

    ura

    cy a

    t lo

    w lo

    ads

    .

    3.3

    .2

    CT

    rat

    io s

    ho

    uld

    als

    o be

    larg

    e e

    nou

    gh th

    at t

    he

    se

    con

    dary

    cu

    rre

    nt

    is le

    ss t

    han

    the

    co

    ntin

    uo

    us

    ratin

    g of

    the

    conn

    ect

    ed

    d

    evic

    es

    at

    the

    hig

    he

    st e

    me

    rgen

    cy r

    atin

    g o

    f th

    e a

    sso

    cia

    ted

    ele

    me

    nt.

    3.3

    .3T

    he

    the

    rma

    l ra

    ting

    fact

    or

    sha

    ll b

    e 2

    .0 a

    t 3

    0 d

    egr

    ee

    s C

    . T

    he t

    herm

    al r

    atin

    g s

    ha

    ll be

    se

    lect

    ed

    such

    tha

    t th

    e se

    lect

    ed

    CT

    3.3

    .4

    En

    gine

    erin

    g sh

    all

    req

    uire

    the

    man

    ufa

    ctu

    rers

    to p

    rovi

    de te

    st d

    ata

    for

    met

    erin

    g C

    Ts,

    and

    sh

    all f

    orw

    ard

    th

    is d

    ata

    to

    Me

    terin

    g

    Ser

    vice

    s.

  • En

    gr.

    Doc

    : T

    ran

    smis

    sio

    n In

    terc

    onn

    ectio

    n-G

    ene

    ratio

    n M

    ete

    ring

    Da

    te:

    Aug

    ust

    16

    , 20

    17

    Pag

    e 3

    of

    6

    4.

    VO

    LT

    AG

    E I

    NP

    UT

    TO

    ME

    TE

    RIN

    G

    4.1

    A

    PT

    or

    CC

    VT

    with

    thr

    ee (

    3) s

    eco

    nda

    ry w

    ind

    ings

    is r

    equ

    ired

    fo

    r th

    e p

    rima

    ry a

    nd

    ba

    ckup

    inte

    rcon

    nec

    tion

    me

    teri

    ng.

    Th

    e

    e

    r a

    t WX

    Y &

    Z b

    urd

    en.

    4.2

    T

    he

    prim

    ary

    an

    d b

    acku

    p m

    ete

    rs s

    ha

    ll b

    e c

    on

    nect

    ed

    to th

    e 1

    20 v

    olt

    win

    din

    gs.

    4.3

    E

    ngin

    ee

    ring

    sha

    ll re

    quire

    the

    man

    ufa

    ctu

    rers

    to p

    rovi

    de t

    est

    da

    ta fo

    r m

    ete

    ring

    PT

    s o

    r C

    CV

    Ts,

    and

    sh

    all

    forw

    ard

    th

    is d

    ata

    to

    M

    ete

    r O

    pera

    tion

    s.

    4.4

    P

    rimar

    y M

    ete

    ring

    4.4

    .1

    4.4

    .2

    No

    bu

    rde

    n o

    ther

    th

    an th

    e m

    ete

    r sh

    all

    be c

    onne

    cte

    d in

    this

    me

    teri

    ng s

    eco

    ndar

    y P

    T c

    ircu

    it.

    5.

    ME

    TE

    R

    5.1

    T

    he

    Flo

    rida

    Me

    ter

    Dep

    artm

    ent

    sha

    ll p

    rovi

    de a

    nd

    ma

    inta

    in th

    e p

    rim

    ary

    an

    d b

    acku

    p m

    ete

    rs.

    5.2

    A

    fou

    r-q

    ua

    dra

    nt, b

    i-d

    irect

    ion

    al,

    thre

    e e

    lem

    en

    t rev

    en

    ue

    cla

    ss m

    ete

    r sh

    all b

    e us

    ed f

    or

    the

    pri

    ma

    ry a

    nd

    ba

    cku

    p m

    ete

    r. T

    he

    me

    ter

    sha

    ll be

    ca

    pa

    ble

    of p

    rod

    ucin

    g th

    e fo

    llow

    ing

    out

    pu

    ts:

    a.

    Kw

    h (

    De

    live

    red

    /Re

    ceiv

    ed)

    b.

    Kva

    rh (

    De

    live

    red/

    Re

    ceiv

    ed)

    c.

    Inst

    anta

    neo

    us th

    ree

    ph

    ase

    wat

    ts

    d.

    Inst

    anta

    neou

    s th

    ree

    ph

    ase

    va

    rs

    e.

    Inst

    anta

    neou

    s si

    ngl

    e p

    hase

    vo

    ltsf.

    In

    stan

    tane

    ous

    sin

    gle

    pha

    se a

    mp

    s

    5.3

    T

    he

    me

    ter

    sha

    ll be

    pro

    vid

    ed

    with

    Eth

    erne

    t an

    d R

    S-2

    32/4

    85

    com

    mu

    nic

    atio

    n p

    ort

    s a

    nd s

    hall

    sup

    port

    DN

    P-3

    .0 p

    roto

    col.

    5.4

    T

    he

    me

    ter

    sha

    ll ha

    ve th

    e c

    apa

    bili

    ty o

    f co

    nne

    ctin

    g to

    the

    sta

    tion

    serv

    ice

    au

    xilia

    ry 1

    20 v

    olt

    AC

    pow

    er

    sou

    rce

    .

    6.

    ME

    TE

    R O

    UT

    PU

    T

    6.1

    Prim

    ary

    an

    d B

    acku

    p M

    ete

    ring

    6.1

    .1

    Th

    e P

    rimar

    y a

    nd

    Bac

    kup

    met

    ers

    ou

    tput

    s sh

    all b

    e co

    nn

    ect

    ed to

    the

    Sub

    stat

    ion

    RT

    U v

    ia th

    e E

    the

    rne

    t co

    mm

    un

    ica

    tion

    po

    rt.

  • En

    gr.

    Doc

    : T

    ran

    smis

    sio

    n In

    terc

    onn

    ectio

    n-G

    ene

    ratio

    n M

    ete

    ring

    Da

    te:

    Aug

    ust

    16

    , 20

    17

    Pag

    e 4

    of

    6

    7.

    ME

    TE

    R IN

    ST

    AL

    LA

    TIO

    N P

    AC

    KA

    GE

    7.1

    C

    ontr

    ol H

    ou

    se P

    ane

    l (S

    ee F

    igur

    e 1

    )

    7.1

    .1

    Kem

    co P

    late

    (R

    U J

    EM

    -1)

    7.1

    .2

    2 J

    EM

    ST

    AR

    II

    swit

    chbo

    ard

    met

    ers

    wit

    h ca

    se

    Pri

    mar

    y/B

    acku

    p (S

    uppl

    ied

    by M

    eter

    Dep

    artm

    ent)

    7.1

    .3

    2

    FT

    -1 F

    lexi

    10

    pol

    e t

    est

    switc

    h (c

    urre

    nt/

    volta

    ge)

    (S

    ub

    stat

    ion

    sup

    plie

    d)

    7.1

    .4

    1 F

    T-1

    Fle

    xi 1

    0 po

    le T

    est s

    wit

    ch (

    volt

    age

    only

    ) (S

    ubst

    atio

    n su

    ppli

    ed)

    7.1

    .5

    1 3

    pos

    ition

    sel

    ecto

    r sw

    itch

    (Sub

    stat

    ion

    supp

    lied

    )

    7.1

    .6

    If th

    e m

    eter

    is lo

    cate

    d on

    the

    dist

    ribu

    tion

    side

    (25

    KV

    and

    bel

    ow)

    of th

    e po

    wer

    tran

    sfor

    mer

    , the

    CT

    s an

    d PT

    s w

    ill b

    e su

    ppl

    ied

    by

    the

    Met

    er D

    epar

    tmen

    t.

    7.2

    Sub

    sta

    tion

    yar

    d M

    ete

    r C

    ab

    ine

    t(S

    ee

    Fig

    ure

    2)

    7.2

    .1

    1

    40

    x40x

    15 A

    lum

    inu

    m M

    ete

    r C

    ab

    ine

    t 7

    .2.1

    .1

    All

    Me

    ters

    an

    d c

    om

    pone

    nts

    in

    sid

    e th

    e m

    ete

    r ca

    bin

    et i

    s su

    pplie

    d b

    y th

    e M

    ete

    r D

    epa

    rtm

    en

    t (in

    clu

    din

    g t

    he

    40x

    40x

    15 c

    abin

    et)

    7.2

    .2.1

    If

    the

    me

    ter

    is lo

    cate

    d o

    n th

    e d

    istr

    ibut

    ion

    sid

    e (2

    5 K

    V a

    nd b

    elo

    w)

    of

    the

    po

    we

    r tr

    ans

    form

    er,

    the

    CT

    s an

    d P

    Ts

    will

    be

    su

    pp

    lied

    by

    the

    Met

    er D

    epa

    rtm

    ent

    .

    7.3

  • En

    gr.

    Doc

    : T

    ran

    smis

    sio

    n In

    terc

    onn

    ectio

    n-G

    ene

    ratio

    n M

    ete

    ring

    Da

    te:

    Aug

    ust

    16

    , 20

    17

    Pag

    e 5

    of

    6

    Fig

    ure

    1

  • En

    gr.

    Doc

    : T

    ran

    smis

    sio

    n In

    terc

    onn

    ectio

    n-G

    ene

    ratio

    n M

    ete

    ring

    Da

    te:

    Aug

    ust

    16

    , 20

    17

    Pag

    e 6

    of

    6

    Fig

    ure

    2