columbia solar plant interconnect 69 kv switching station ... · columbia solar (q148) facilities...
TRANSCRIPT
-
Columbia Solar (Q148) Facilities Study July 13, 2018
Columbia Solar Plant Interconnect
69 kV Switching Station
Facilities Study Report
Final Version - 7/13/18
Energy Resource Interconnection Service and Network Resource Interconnection Service (Q148)
Prepared by:
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 2 of 25
Table of Contents 1.0 Executive Summary ........................................................................................................................... 3
2.0 Baseline Assumptions ....................................................................................................................... 4
3.0 Required Network Upgrades ............................................................................................................ 6
3.1 Transmission Lines ........................................................................................................................ 6
3.1.1 Work Scope ........................................................................................................................... 6
3.1.2 Clarifications and Assumptions ............................................................................................. 7
3.1.3 Transmission Line Cost Estimate ........................................................................................... 7
3.2 Substation Physical ....................................................................................................................... 8
3.2.1 Work Scope ........................................................................................................................... 8
3.2.2 Major Substation Equipment ................................................................................................ 8
3.2.3 Clarifications and Assumptions ............................................................................................. 9
3.2.4 Cost Estimate ...................................................................................................................... 10
3.3 Protection and Control................................................................................................................ 10
3.3.1 Work Scope ......................................................................................................................... 10
3.3.2 Major P&C Equipment ........................................................................................................ 12
3.3.3 Remote End Substations ..................................................................................................... 12
3.3.4 Clarifications and Assumptions ........................................................................................... 13
3.3.5 Protection and Control Cost Estimate ................................................................................ 14
3.4 Telecommunications ................................................................................................................... 14
3.4.1 Work Scope ......................................................................................................................... 14
3.4.2 Clarifications and Assumptions ........................................................................................... 15
3.4.3 Telecommunications Cost Estimate .................................................................................... 15
4.0 Connection Requirements .............................................................................................................. 16
4.1 General ........................................................................................................................................ 16
4.2 Point of Interconnection ............................................................................................................. 16
4.4 Equipment Ratings and Protection Coordination ....................................................................... 16
4.5 Insulation Requirements ............................................................................................................. 17
4.6 Communications ......................................................................................................................... 17
4.7 Metering ..................................................................................................................................... 17
4.8 Grounding ................................................................................................................................... 17
5.0 Cost Estimate Summary .................................................................................................................. 18
6.0 Milestone Schedule ......................................................................................................................... 19
7.0 Appendices ...................................................................................................................................... 20
8.0 Facilities Study Approval ................................................................................................................. 25
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 3 of 25
1.0 Executive Summary
The Q148 Solar Plant is a planned Solar PV station, capable of 74.9 MW net output. The facility will be located in Columbia County, Florida (See Appendix A). The point of interconnection will be a new four (4) terminal, four (4) breaker 69kV Columbia Switching Station, initially configured as a ring bus. The switching station will be used to loop in and out Duke Energy Florida’s (DEF) Fort White to High Springs (FH) 69kV line including the Fort White Clay Electric Cooperative Tap creating: Fort White to Columbia, Fort White Clay Electric Cooperative to Columbia and High Springs to Columbia 69kV lines. The fourth terminal will be for connection to the proposed Solar PV station.
The customer has requested this generation facility be studied for Network Resource Interconnection Service (NRIS) and Energy Resource Interconnection Service (ERIS) with a requested Commercial Operating Date (COD) of December 31, 2019.
Duke Energy Florida (DEF) the “Transmission Company” previously completed a System Impact Study (SIS) and issued the report on March 15, 2018, that summarizes the thermal, voltage, short circuit and transient stability impacts associated with the proposed interconnection.
The primary objective of this Facilities Study (FS) is to quantify necessary Transmission Owner network upgrade(s), other direct assigned upgrade(s), and associated upgrade lead times. Therefore, this FS quantifies the cost, work scope, and tentative schedules associated with the design and installation of the required network modifications. This study evaluates and estimates the date that service could be granted based on specific criteria outlined within this report.
The SIS identified potential network upgrades to DEF’s transmission network to accommodate the full capacity of the proposed Solar PV station under NRIS. This included a third Powerline to Holder 230kV line that was found to be required due to an N-1 contingency. This line would connect to a proposed Powerline Substation that was identified previously in another queue study with an in-service date of 2021 which would need to be in-service prior to completion of a NRIS interconnection.
The facilities and costs discussed herein are for DEF upgrades only, and do not include any known or potential affected system upgrades. In the SIS, a Third Party Short Circuit Impact was identified. The short circuit analysis revealed one impact greater than 3% to a third-party (SECI/CEC delivery point) substation. All third-party impacts will be evaluated further in a future FRCC-TTS Reliability Assessment that is performed on Generator Interconnection Service Requests (GISR) and Transmission Service Requests (TSR) that potentially affect the FRCC region.
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 4 of 25
The short circuit analysis performed in the SIS revealed impacts greater than 3% at several DEF substations. These substations were reviewed, and no equipment was identified as being over-dutied.
The FS includes cost estimates to permit, engineer, procure equipment and materials, construct and place facility upgrades or additions in service to accomplish the requested service.
The facilities needed to accomplish the interconnection have been reviewed and proposed schedules for completion were based on the DEF and the Customer executed Agreement/Contract on March 16, 2018. Schedules were developed utilizing typical project durations experienced by DEF for project engineering, procurement, permitting, construction, and outage requirements. Schedules durations do not include seasonal capacity considerations as well as system configuration constraints such as concurrent line outages.
Subsequent to the requirements and preparation listed in this document a design review shall take place prior to any facilities construction to maintain compliance with the North American Electric Reliability Corporation (NERC) Reliability Standard FAC-002-1, or its successor. Also, in compliance with the NERC Reliability Standard FAC-002-1, or its successor, a testing and inspection activity will take place prior to the in-service date.
2.0 Baseline Assumptions
The estimated costs and schedule are based on the assumptions identified in this Facilities Study.
The Transmission Company’s (DEF’s) Facilities are based on application of industry standard equipment. All new and rebuilt facilities will be designed and built according to the DEF’s current practice. These facilities will become a part of the DEF network transmission system therefore in addition to having sufficient capacity to accept the proposed Solar PV station generation these facilities must also have the capacity to carry the power flows to upstream loads. As such the total energy handling capability of the proposed interconnection facilities could potentially accommodate energy flows greater than the requested 74.9 MW. However, in the event the Customer decides to designate additional capacity, a new request will be required to evaluate the impacts. Any constraints that may result will be identified as part of the new study request.
Any required outages necessary to support construction of the Interconnect Facilities must be coordinated with the DEF Energy Control Center (“ECC”). If an outage of sufficient duration cannot be obtained to support any of the required construction activities, alternative solutions such as new facilities or temporary facilities may have to be constructed to maintain integrity of the grid. No provisions have been made for temporary work in the estimates provided herein.
The proposed protection schemes to be installed by DEF at the Associated Facilities are intended to protect DEF’s Transmission Network.
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 5 of 25
Estimates prepared for this FS are considered to be good faith estimates represented in present day dollars as of the date of the study. The estimates do not include upgrade costs for third party facilities. The cost estimates provided use currently available pricing in Duke’s estimating system. The estimated budget has been computed with an expected accuracy of +/-20 %. Costs may fluctuate due to inflation or changes in market price. The estimates are further premised on being able to perform work during normal business hours with minimum overtime or weekend work. The estimates assume no changes in scope or design from that provided in previous studies.
Cost estimates are inclusive of engineering, material (equipment, structures, conductors, OPGW, etc.), survey, geotechnical, access, clearing, siting, environmental, construction and removal.
Cost estimates for the NRIS required third Powerline to Holder 230kV line are from a previous facilities study (Q137 Shady Hills) and will need to be revised if the customer proceeds with NRIS.
DEF will be provided with sufficient easements across the solar facility for the new switching station, 69kV loop and the Fort White – Fort White Clay Electric Cooperative 69kV Tap (see Appendix A) at the location identified in the Q148 Facilities Study Agreement dated March 26, 2018. The Customer will provide the environmental permits (FDEP, USACOE, EPA, County, etc.), storm water permits, endangered species permits, Historical Resources studies, zoning and driveway permits. DEF shall be responsible for complying with the permit conditions, the SWPPP (by DEF) and any other Best Management Practices required by these permits. DEF will be responsible for any construction related permits for the switch yard, transmission lines and storage yard.
A draft Large Generator Interconnection Agreement (LGIA) will be provided to the Interconnection Customer consistent with the final results of this report. The Interconnection Customer will have 30 days to execute the LGIA consistent with the Joint Open Access Transmission Tariff.
The scope of work, durations, clarifications, assumptions and cost estimates apply to the core work associated for both NRIS and ERIS. Additional scope required for NRIS is identified throughout the document as required.
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 6 of 25
3.0 Required Network Upgrades
3.1 Transmission Lines
The transmission line scope changes of the facilities that are required to support this transmission service are addressed by the following sections.
3.1.1 Work Scope
Columbia 69kV Switching Station
The result of the SIS requires the following upgrades in support of the Columbia Solar interconnection request:
Loop-in 69kV lines from Fort White, Fort White Clay Electric Cooperative Tap and High Springs substations. Cut-in occurs approximately mid-span of Fort White to High Springs Line. Existing lines are on single circuit poles.
▪ Install two (2) steel dead ends in the existing Fort White – High Springs 69 kV line atexisting structure FH-102 and construct a loop in and out of the Northeast andSouthwest Bays of the new Columbia Interconnect Sub. A total of six (6) dead end poleswill be needed to construct the loop.
▪ Install one (1) steel dead end in the existing Fort White – Fort White Clay ElectricCooperative 69 kV Tap at existing structure FH-99-4 and construct 0.2 miles of new lineinto the Northwest Bay of the new Columbia Interconnect Sub. A total of four (4) steelpoles will be needed to construct the tap.
▪ Anticipating 20’ direct embedded foundations utilizing concrete backfill▪ Existing 4/0 HDB Copper and 795 ACSR will be dead-ended on new structures and new
1272 ACSS TW will be installed into the new substation terminals▪ The existing switch at FH-99 will be removed and approximately 0.1 miles of the Fort
White – Fort White Clay Electric Cooperative 69 kV Tap from FH-99 to FH-99-4 will beremoved
This will create Fort White to Columbia, Fort White Clay Electric Cooperative to Columbia and High Springs to Columbia 69 kV lines. (See Appendix A)
NRIS
In addition to the scope required for ERIS, NRIS also requires the addition of a third Powerline to Holder 230kV line due to an N-1 contingency. In addition, the Lecanto to Pine Ridge 115kV line is overloaded which would also be resolved by a third Powerline to Holder 230kV line. This line was identified previously in another queue study (Q137 Shady Hills). As identified in the previous study, the current DEF practice is to utilize 3000A capacity lines with 2627 KCM ACSS/TW/HS Santee conductor.
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 7 of 25
3.1.2 Clarifications and Assumptions
▪ It is assumed that the outages/clearances required for construction are compatible withload flow conditions at the time of construction. These projects may require difficult toobtain outages which could delay or increase the cost of this project, if they are notreceived in a timely manner.
▪ It is assumed that the Customer will build the generator lead lines from the proposed
Solar PV station to the Columbia 69kV Switching Station - Point of Interconnection (see
Appendix C)
▪ NRIS only (from Q137 Shady Hills)o The new Powerline to Holder line will be built in the existing Crystal River Plant
to Central Florida right-of-wayo The new Powerline substation is assumed to be in-service, prior to the
construction of the upgrades associated with Q148 and is therefore not included
in the scope of work
3.1.3 Transmission Line Cost Estimate
ERIS
Q148 69kV Fort White to Columbia, High Springs to Columbia, Fort White C.E.C. to Columbia, Solar Station to
Columbia
Estimated Cost ($)
Engineering $91,000
Equipment and Material $303,000
Labor $551,000
Other (includes Indirect Allocations) $204,000 Total $1,149,000
NRIS
NRIS Required Upgrades Estimated Cost ($)
Q148 69kV Fort White to Columbia, High Springs to Columbia, Fort White C.E.C. to Columbia, Solar Station to Columbia
$1,149,000
230kV Line from Powerline Sub to Holder Substation (from Q137 Shady Hills)
$32,054,000
Total $33,203,000
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 8 of 25
3.2 Substation Physical
3.2.1 Work Scope
The physical scope of work identified in this study is listed below. For all the equipment identified:
Columbia 69kV Switching Station
▪ A four (4) position 69kV ring bus with associated breakers, switches and bus (See AppendixB)
▪ Four (4) 69kV line positions with associated dead-end towers, motor operated line switches,surge arresters, and potential transformers (PT)
▪ The switching station will be used to loop in and out DEF’s Fort White to High Springs (FH)69kV line including the Fort White Clay Electric Cooperative Tap creating: Fort White toColumbia, Fort White Clay Electric Cooperative to Columbia and High Springs to Columbia69kV lines
o Three (3) of the line positions will be used to loop in/out the Fort White to HighSprings 69kV line including the Fort White Clay Electric Cooperative Tap
o The fourth line position will be for the interconnection of the proposed Solar PVstation
▪ Install 69kV current transformers (CT) & PTs on the proposed Solar PV station 69kV line formetering
▪ New HDS-Small Control Equipment Enclosure (CEE) building (approx. 28’-8” x 44’-0”)▪ Four station service voltage transformers (SSVT), 69kV / 240-120V, 100kVA and associated
69kV switches, fused disconnects, auto transfer switch (flip flop), and AC panels
NRIS
In addition to the new 69kV Columbia Switching Station, NRIS also requires the addition of a new line position at DEF’s Powerline Substation for a third Holder 230kV line and a new line position at DEF’s Holder Substation for a third Powerline 230kV line.
3.2.2 Major Substation Equipment
Columbia 69kV Switching Station
New yard equipment to be installed for 69kV Columbia Switching Station:
▪ Four (4) Motor Operated Switches 2000A▪ Four (4) 69kV / 240-120V, 100kVA Station service voltage transformers▪ Four (4) 69kV 3000A 40kA Circuit Breakers▪ Ten (10) 69kV 2000A disconnect switches with manual operators▪ Twelve (12) single-phase PT’s for 69kV lines▪ Three (3) single-phase metering class PT’s for 69kV revenue metering
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 9 of 25
▪ Three (3) single-phase metering class CT’s for 69kV revenue metering▪ Twelve (12) 69kV station class surge arresters
NRIS In addition to the new 69kV Columbia Switching Station, NRIS also requires the scope of work from the Q137 Shady Hills FS at Powerline Substation and Holder Substation including the following equipment:
▪ Powerline Substationo Five (5) 230kV, 3000A, disconnect switches including four (4) breaker switches
and one (1) motor operated line switcho Two (2) 230kV, 3000A, breakerso One (1) 230kV, dead-end towero Three (3) 230kV PT’so Three (3) 230kV surge arresterso 4” IWCB bus & double 1750 AAC jumpers
▪ Holder Substationo Three (3) 230kV, 3000A, disconnect switches including two (2) breaker switches
and one (1) motor operated line switcho Two (2) 230kV, 3000A, breakerso One (1) 230kV, dead-end towero Three (3) 230kV PT’so Three (3) 230kV surge arresterso Complete 230kV ring buso 4” IWCB bus & double 1750 AAC jumpers
3.2.3 Clarifications and Assumptions
▪ This report does not consider possible environmental (wetlands, soil contamination,etc.) mitigation. Testing and environmental assessments are required to identify andquantify environmental costs. These items are outside the scope of this study.
▪ The ability to utilize standard and typical foundations is assumed▪ This report assumes the ability to acquire a suitable site adjacent to the existing DEF
Fort White to High Springs 69kV right-of-way for the proposed 69kV Columbia SwitchingStation
▪ It is assumed that the Customer will provide a suitable area of sufficient size at no costadjacent to the proposed 69kV Columbia Switching Station that can be utilized as amaterial storage yard
▪ It is assumed that the Customer will provide a suitable driveway and access road fromthe existing road (Fry Road) to the proposed 69kV Columbia Switching Station site
▪ Costs associated with upgrades to remote end ground grids (if required) are notincluded
▪ DEF will have full access and rights to the property to perform due diligence uponexecution of Interconnection Agreement.
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 10 of 25
3.2.4 Cost Estimate
ERIS
Q148 Columbia Switching Station Estimated Cost ($)
Engineering $475,000
Equipment and Material $1,515,000
Labor $2,964,000
Other (includes Indirect Allocations) $1,025,000 Total $5,979,000
NRIS
NRIS Required Upgrades Estimated Cost ($)
Q148 Columbia Switching Station $5,979,000
Holder Substation (from Q137 Shady Hills FC)
$2,347,000
Powerline Substation (from Q137 Shady Hills FC)
$1,662,000
Total $9,988,000
3.3 Protection and Control
3.3.1 Work Scope
This project includes a complete Protection and Control package for the new 69kV Columbia Switching Station interconnections to existing DEF’s Fort White (111), Fort White Clay Electric Cooperation Tap (6851) and High Springs (67) substations using a ring bus configuration with four (4) breakers and four (4) line positions including one (1) position for connection to the proposed Solar PV station (by others).
Protection system addition or upgrades shall be implemented with full redundancy. New breakers will utilize a breaker control relay and a breaker failure relay, with current supervision, from a bushing current transformer on the breaker. Should a breaker fail to trip within the allowable time setting, the associated breaker failure trip relay and associated lockout relay will trip and lock out adjacent breakers and remote breakers via breaker failure transfer trip.
The transmission line protective relay schemes continuously monitor conditions of the transmission lines and are designed to detect and isolate the faults with appropriate speed and minimum disturbance to the system. The transmission lines will be protected by redundant Line Protection 1 and Line Protection 2 current differential relays designed to clear a fault on the line. The schemes will use relay-to-relay communications utilizing fiber optic cable.
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 11 of 25
Columbia 69kV Switching Station
Items listed in the following table are the collective number of devices required for the 69kV Columbia Switching Station.
Total Qty
Device Function
4 SEL-311L Line Protection 1
4 SEL-411L Line Protection 2
1 SEL-735 Power Quality Meter
4 86-LOR/ER Breaker Failure Transfer Trip Lockout (Elec Reset)
4 SEL-351S MOS Control
4 SEL-351S Breaker Control
4 SEL-451 Breaker Failure
4 86-LOR Breaker Failure Lockout
NRIS
In addition to the new 69kV Columbia Switching Station, NRIS also requires the following protection & control scope of work at Powerline Substation and Holder Substation based on the Q137 Shady Hills FS for the Powerline to Holder 230kV line:
Total Qty
Device Function
1 SEL-311L Line Protection 1
1 SEL-411L Line Protection 2
1 86-LOR/ER Breaker Failure Transfer Trip Lockout (Elec Reset)
1 SEL-351S MOS Control
2 SEL-351S Breaker Control
2 SEL-451 Breaker Failure
2 86-LOR Breaker Failure Lockout
*Items listed in the previous table are collectively referred to as “P&C linepackage” in subsequent scope items
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 12 of 25
3.3.2 Major P&C Equipment
69kV Columbia Switching Station
▪ New Control Equipment Enclosure HDS/Small size 28’-8”x 44’-0” outer dimension▪ One (1) Battery Bank #1 (approx. size 200AH) and associated battery charger (approx.
size 25AH)▪ Relay panels
o 69kV High Springs Line LP1, BKR 8081 CTRL & MOS 8085 CTRLo 69kV High Springs Line LP2, BKR 8081 BFo 69kV Solar PV Station Meteringo 69kV Solar PV Station LP1, BKR 8088 CTRL & MOS 8089 CTRLo 69kV Solar PV Station LP2, BKR 8088 BF, Power Quality Metero 69kV Fort White Line LP1, BKR 8084 CTRL & MOS 8074 CTRLo 69kV Fort White Line LP2, BKR 8084 BFo 69kV Fort White Clay Electric Cooperative Tap Line LP2, BKR 8072 BFo 69kV Fort White Clay Electric Cooperative Tap Line LP1, BKR 8072 CTRL & MOS
8070 CTRLo Securityo P&C TSCADAo P&C Non-CONTROL CLOCKo IT/Telecom #2o IT/Telecom #1
3.3.3 Remote End Substations
There are three existing remote end substations associated with the interconnection including
Fort White (111), Fort White Clay Electric Cooperation Tap (6851) and High Springs (67)
substations.
Fort White Substation
The existing protection schemes at Fort White for the High Springs 69kV line will be upgraded
by the end of 2018 to include Line Current Differential protection under a separate, in-process
project. Upon commissioning of the 69kV Columbia Switching Station, the relay settings for the
Fort White to High Springs 69kV line will be modified to accommodate what will become the
Fort White to Columbia Switching Station 69kV line.
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 13 of 25
High Springs Substation
The existing protection schemes at High Sprints for the Fort White 69kV line will be upgraded
by the end of 2018 to include Line Current Differential protection. Upon commissioning of the
69kV Columbia Switching Station, the relay settings for the High Springs to Fort White 69kV line
will be modified to accommodate what will become the High Springs to Columbia Switching
Station 69kV line.
Clay Electric Co-op Substation
Upon commissioning of the 69kV Columbia Switching Station, the incoming line name change
to Clay Electric Co-op will need to be communicated and updated on their system.
NRIS
▪ In addition to the new 69kV Columbia Switching Station and associated remote ends,NRIS also requires the following protection & control scope of work at PowerlineSubstation and Holder Substation based on the Q137 Shady Hills FS for the Powerline toHolder 230kV line:
o One (1) P&C line package at the Holder Substation location▪ 230kV Powerline Line LP1, BKR CTRL & MOS CTRL▪ 230kV Powerline Line LP2, BF
o One (1) P&C line package at the Powerline Substation location▪ 230kV Holder LP1, BKR CTRL & MOS CTRL▪ 230kV Holder LP2, BF
3.3.4 Clarifications and Assumptions
▪ The standard 69kV line protection includes primary & backup SEL-311L and SEL-411Lrelaying, breaker failure tripping is provided using SEL-451
▪ The project generating units will meet all applicable NERC Standards▪ NRIS only
o The standard 230kV line protection includes primary & backup SEL-311L and SEL-
411L relaying, breaker failure tripping is provided using SEL-451
o The new Powerline substation is assumed to be in-service, prior to the
construction of the upgrades associated with Q148 and is therefore not included
in the scope of work
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 14 of 25
3.3.5 Protection and Control Cost Estimate
ERIS
Q148 69kV Columbia Switching Station and Associated Remote Ends Protection and Control Cost
Estimated Cost ($)
Engineering $509,000
Equipment and Material $529,000
Labor $1,095,000
Other (includes Indirect Allocations) $478,000 Total $2,611,000
NRIS
NRIS Required Upgrades Estimated Cost ($)
Q148 69kV Columbia Switching Station and Associated Remote Ends
$2,611,000
Holder Substation (from Q137 Shady Hills FC)
$250,000
Powerline Substation (from Q137 Shady Hills FC)
$250,000
Total $3,111,000
3.4 Telecommunications
3.4.1 Work Scope
This project requires fiber to be installed to the proposed Columbia Switching Station for tele-protection and SCADA. ADSS will be installed from a splice point on the existing DEF FO 230kV line (Fort White to Ginnie Springs) to the Columbia Switching Station. Approximately 28,900 feet will be underground build and then connected to the new Columbia Switching Station. The Columbia Switching Station to Fort White 69kV line will include Direct Fiber and J-MUX forms of communication. The 69kV Columbia Switching Station to High Springs 69kV line will utilize J-MUX communication.
Procure and install as required the necessary equipment to support J-MUX and Direct Fiber at the Columbia Switching Station, this includes:
▪ One (1) GE JungleMUX device▪ One (1) Fiber Patch Panel▪ One (1) 2010 Connected Grid Router▪ Three (3) 2520 Connected Grid Switches▪ One (1) Positron Power
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 15 of 25
NRIS
In addition to the new 69kV Columbia Switching Station, NRIS also requires the following telecommunications scope of work at Powerline Substation and Holder Substation based on the Q137 Shady Hills FS for the Powerline to Holder 230kV line:
▪ Installation of fiber from the dead-end tower into the control house at Holder andPowerline
▪ Perform OPGW to ADSS transition splicing at the terminals at both substations▪ Perform OPGW line splicing at 5 locations along the line
3.4.2 Clarifications and Assumptions
▪ There is DC available to power the Telecom equipment▪ For the OPGW builds, splices will be performed where necessary along the routes
3.4.3 Telecommunications Cost Estimate
ERIS
Q148 69kV Columbia Switching Station Estimated Cost ($)
Engineering $62,000
Equipment and Material $286,000
Labor $180,000
Other (includes Indirect Allocations) $72,000 Total $600,000
NRIS
NRIS Required Upgrades Estimated Cost ($)
Q148 Columbia Solar Station Switch Yard $600,000
230 kV Line from Powerline Sub to Holder Substation
$192,000
Total $792,000
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 16 of 25
4.0 Connection Requirements
4.1 General
This Facilities Study document is intended to provide a basic scope definition of facilities on which the Transmission Company has based its facilities study and cost estimates. It shall serve as the basis for the facilities that the Transmission Company proposes to design, build, and operate in connection with interconnection of Customer generation in the Columbia County, FL area. DEF requires the installation of a Customer owned circuit breaker to be located at the high side of the Generator Step-Up Transformer (GSU).
4.2 Point of Interconnection
The point of interconnection (POI) will be the “face of steel” on the dead-end tower inside the proposed DEF 69kV Columbia Switching Station. The Customer will install and own the jumpers from the strain bus connection dead-end insulators to the 69kV disconnect switch in the 69kV Columbia Switching Station (See Appendix C). The Customer shall install a Phasor Measurement Unit (PMU) at the Point of Interconnection (POI), according to DEF’s Facility Connection Requirements.
The Customer will own, maintain and install all facilities from this point back to the proposed Solar PV Station including the strain bus.
4.3 Short-Circuit Withstand Capability
DEF assumes no responsibility for appropriately sizing the short circuit withstands capability of any equipment installed on the Customer’s Side of the POI. DEF will provide upon request the maximum available short circuit current based on its current models. The Customer will need to exercise extreme care in appropriately sizing its equipment while providing for reasonable margin for future increases in available short circuit current. The Transmission Company bears no responsibility in the sizing decision.
4.4 Equipment Ratings and Protection Coordination
Prior to finalizing the specification for the equipment necessary to interconnect to the power grid, the Customer shall consult with DEF to establish the required ratings necessary to reliably interconnect and provide the expected Voltage and VAR support as defined in the Interconnection and Operating Agreement. Specific parameters shall include but are not limited to available transformer taps and short circuit withstands capabilities.
Customer shall also coordinate their relay protection schemes to be in compliance with the DEF requirements.
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 17 of 25
4.5 Insulation Requirements
DEF’s standard requirements for equipment installed on the 69kV systems shall meet the following minimum Basic Insulation Level (BIL).
69kV BIL Basic Insulation Level (BIL) *350kV
* 550kV BIL required for Station Post Insulators and Airbreaks
4.6 Communications
The Customer will provide 48 fiber optic- cable (OPGW or ADSS) including a splice interface cabinet from the proposed Solar PV Plant to the POI as described in Section 4.2
4.7 Metering
Metering shall comply with Duke Energy Florida’s “Transmission Interconnection/Generation/Revenue Metering”, Rev. 11/7/2017. See Appendix D.
4.8 Grounding
Grounding of the Customer’s interconnect facilities shall comply with the requirements Duke’s STDP-STD-TRM-00098 rev. 000 “Standard Ground Grid System.” See Appendix E.
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 18 of 25
5.0 Cost Estimate Summary
ERIS
The ERIS option requires the installation of a 69kV Columbia Switching Station with a 4-terminal configuration including the associated transmission line work. Located in Columbia County, Florida, the station will be built at the interconnection point adjacent to the existing DEF Fort White and High Springs (FH) 69kV line. The ERIS estimated cost breakdown of the 69kV Columbia Switching Station is located below in the following table and is based on LGIA execution as identified in Section 2.0 Baseline Assumptions.
Q148 Columbia Switching Station
Engineering Material Labor Other (includes Indirect Allocations)
Total ERIS Estimate
Transmission Line $91,000 $303,000 $551,000 $204,000 $1,149,000
Switching Station Physical
$475,000 $1,515,000 $2,964,000 $1,025,000 $5,979,000
Protection and Control $509,000 $529,000 $1,095,000 $478,000 $2,611,000
Telecommunications $62,000 $286,000 $180,000 $72,000 $600,000
TOTAL $ 1,137,000 $2,633,000 $4,790,000 $1,779,000 $10,339,000
NRIS
The NRIS option includes the scope identified above under ERIS in addition to the necessary build of the third Powerline to Holder 230kV line, which currently is assigned to the Shady Hills (Q137) project. Per the Q137 Shady Hills LGIA, the project is expected to be completed by November 30, 2021. Substantial acceleration of this schedule is unlikely. If the In-Service Date (ISD) for this Q148 Facilities Study is after the Q137 Shady Hills ISD, no additional network upgrades beyond the scope identified for ERIS are required for Q148 to proceed with NRIS. The table below shows the NRIS estimated cost of the required facilities and builds necessary if completed prior to Q137 Shady Hills. If the planned Q148 ISD is after the Q137 ISD, the estimated cost for NRIS will be the same as the estimated cost for ERIS.
Project Total NRIS Estimate ($)
69kV Columbia Switching Station (from this facilities study) $10,339,000
Powerline to Holder 230kV Line and Substations (potentially required for NRIS, costs from Q137 Shady Hills)
$36,755,000
TOTAL ESTIMATE $47,094,000
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 19 of 25
6.0 Milestone Schedule
ERIS
The table below identifies completion timeframes for major activities for this project with an
expected ISD of 24 months from LGIA execution as identified in Section 2.0 Baseline
Assumptions.
Activity Date
Interconnection Agreement Executed LGIA
Initiate Request for Proposal LGIA + 2 weeks
Contract Award LGIA + 24 weeks
Permitting LGIA + 55 weeks
Line Engineering LGIA + 44 weeks
Civil Engineering LGIA + 60 weeks
Substation Physical Engineering LGIA + 60 weeks
Protection and Control Engineering LGIA + 64 weeks
Line Construction LGIA + 92 weeks
Civil/Control Equipment Enclosure Construction LGIA + 103 weeks
Substation Physical Construction LGIA + 100 weeks
Protection and Control Construction LGIA + 102 weeks
Ready for Backfeed LGIA + 96 weeks
In-Service LGIA + 104 weeks
Schedule durations may be impacted by outage availability and time of the year the work is
planned.
NRIS
Schedule for NRIS is dependent on the planned ISD for the 3rd Powerline to Holder 230kV
circuit, related to the Q137 Shady Hills project as identified in Section 5.0 Cost Estimate
Summary.
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 20 of 25
7.0 Appendices
Appendix A Location Map
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 21 of 25
Appendix B Switching Station Proposed Three-Line
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 22 of 25
Appendix C Point of Interconnection
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 23 of 25
Appendix D Metering Standard
(Attached)
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 24 of 25
Appendix E Grounding Standard
(Attached)
-
Facilities Study Report
Columbia Solar (Q148) Facilities Study July 13, 2018 Page 25 of 25
8.0 Facilities Study Approval This Facilities Study for the Columbia Solar Plant Interconnection reports on the Energy Resource Interconnection Service (ERIS) and Network Resource Interconnection Service (NRIS) required for a new Solar PV Plant to be located in Columbia County, FL.
Approval Signatures:
Ray De Souza Ed Scott Director, Transmission Engineering Director, Transmission Planning
-
Tra
nsm
issi
on
Inte
rco
nnec
tion
/Gen
era
tion
/Rev
en
ue M
ete
ring
Cre
ate
d b
y:
Jose
ph
L.
Sta
rnes
, M
ete
r E
ng
inee
rin
g a
nd
Su
ppo
rt
Ap
pro
ved
by:
Au
gu
st 1
6, 2
01
7
Rev
ise
d:
Nov
em
ber
7, 2
017
Du
ke E
ner
gy
Flo
rida
-
En
gr.
Doc
: T
ran
smis
sio
n In
terc
onn
ectio
n-G
ene
ratio
n M
ete
ring
Da
te:
Aug
ust
16
, 20
17
Pag
e 2
of
6
1.
SC
OP
E
1.1
Th
is
docu
men
t re
fers
to th
e D
uke
En
erg
y F
lorid
a r
equ
irem
en
ts f
or t
ran
smis
sio
n le
vel I
nte
rco
nne
ctio
n/G
ene
ratio
n/R
eve
nue
M
ete
ring
be
twee
n D
uke
Ene
rgy
Flo
rida
an
d an
y in
terc
on
nect
ion
an
d/o
r re
venu
e b
ase
d cu
stom
er/
util
ity b
ein
g se
rved
at
tran
smis
sion
vo
ltage
leve
ls 6
9kV
an
d ab
ove
.
1.2
S
ectio
ns
2 t
hro
ugh
7 a
dd
ress
the
ge
ne
ral i
nte
rco
nne
ctio
n re
qu
irem
ents
. 2
. L
OC
AT
ION
2.1
W
hen
a D
uke
Ene
rgy
Flo
rida
line
ter
min
al h
as
been
det
erm
ine
d to
be
wh
ere
inte
rcon
nec
t m
ete
rin
g is
to b
e in
sta
lled
, th
ere
will
b
e a
me
ter
pa
cka
ge w
ith p
rim
ary
an
d b
ack
up m
ete
rs.
Typ
ical
ly t
he
me
ter
pa
cka
ge s
hall
be in
sta
lled
in a
su
bst
atio
n c
ontr
ol
hou
se p
an
el.
3
. C
UR
RE
NT
IN
PU
T T
O M
ET
ER
ING
3.1
P
rimar
y M
ete
ring
CT
s
3.1
.1
Pri
ma
ry M
ete
ring
CT
s sh
all
be
hig
h a
ccu
racy
ext
end
ed
ra
nge
(H
AE
R)
curr
en
t t
ran
sfo
rme
rs w
ith a
ra
tio w
hic
h w
ill in
clu
de
the
con
tinu
ous
ratin
g of
the
conn
ect
ed d
evi
ces
at t
he
hig
hest
em
erg
enc
y ra
ting
of
the
ass
ocia
ted
ele
men
t.
3.1
.2M
inim
um
acc
ura
cy c
lass
: 0
.15
@ B
urd
en 1
.8
3.1
.3
Acc
ura
cy R
ang
e: *
*1%
- 2
00%
of
rate
d ra
tio (
20
400
0 a
mpe
res
usi
ng a
20
00:5
rat
io w
ith a
ra
ting
fact
or =
2.0
as
an
e
xam
ple
) .
CT
s w
ith 5
% -
200
% o
f ra
ted
rat
io is
als
o a
cce
pta
ble
.
3.2
N
o bu
rde
n o
ther
tha
n th
e m
ete
r sh
all
be c
onn
ect
ed
in th
e m
ete
ring
CT
cir
cuits
.
3
.3C
T r
atio
3.3
.1
CT
rat
io s
ha
ll b
e e
ither
100
0:5
or 2
00
0:5
de
pen
din
g on
the
lim
itin
g e
lem
ent
fact
or.
Th
e r
atio
sha
ll be
as
sma
ll as
po
ssib
le
to p
rovi
de t
he r
equi
red
acc
ura
cy a
t lo
w lo
ads
.
3.3
.2
CT
rat
io s
ho
uld
als
o be
larg
e e
nou
gh th
at t
he
se
con
dary
cu
rre
nt
is le
ss t
han
the
co
ntin
uo
us
ratin
g of
the
conn
ect
ed
d
evic
es
at
the
hig
he
st e
me
rgen
cy r
atin
g o
f th
e a
sso
cia
ted
ele
me
nt.
3.3
.3T
he
the
rma
l ra
ting
fact
or
sha
ll b
e 2
.0 a
t 3
0 d
egr
ee
s C
. T
he t
herm
al r
atin
g s
ha
ll be
se
lect
ed
such
tha
t th
e se
lect
ed
CT
3.3
.4
En
gine
erin
g sh
all
req
uire
the
man
ufa
ctu
rers
to p
rovi
de te
st d
ata
for
met
erin
g C
Ts,
and
sh
all f
orw
ard
th
is d
ata
to
Me
terin
g
Ser
vice
s.
-
En
gr.
Doc
: T
ran
smis
sio
n In
terc
onn
ectio
n-G
ene
ratio
n M
ete
ring
Da
te:
Aug
ust
16
, 20
17
Pag
e 3
of
6
4.
VO
LT
AG
E I
NP
UT
TO
ME
TE
RIN
G
4.1
A
PT
or
CC
VT
with
thr
ee (
3) s
eco
nda
ry w
ind
ings
is r
equ
ired
fo
r th
e p
rima
ry a
nd
ba
ckup
inte
rcon
nec
tion
me
teri
ng.
Th
e
e
r a
t WX
Y &
Z b
urd
en.
4.2
T
he
prim
ary
an
d b
acku
p m
ete
rs s
ha
ll b
e c
on
nect
ed
to th
e 1
20 v
olt
win
din
gs.
4.3
E
ngin
ee
ring
sha
ll re
quire
the
man
ufa
ctu
rers
to p
rovi
de t
est
da
ta fo
r m
ete
ring
PT
s o
r C
CV
Ts,
and
sh
all
forw
ard
th
is d
ata
to
M
ete
r O
pera
tion
s.
4.4
P
rimar
y M
ete
ring
4.4
.1
4.4
.2
No
bu
rde
n o
ther
th
an th
e m
ete
r sh
all
be c
onne
cte
d in
this
me
teri
ng s
eco
ndar
y P
T c
ircu
it.
5.
ME
TE
R
5.1
T
he
Flo
rida
Me
ter
Dep
artm
ent
sha
ll p
rovi
de a
nd
ma
inta
in th
e p
rim
ary
an
d b
acku
p m
ete
rs.
5.2
A
fou
r-q
ua
dra
nt, b
i-d
irect
ion
al,
thre
e e
lem
en
t rev
en
ue
cla
ss m
ete
r sh
all b
e us
ed f
or
the
pri
ma
ry a
nd
ba
cku
p m
ete
r. T
he
me
ter
sha
ll be
ca
pa
ble
of p
rod
ucin
g th
e fo
llow
ing
out
pu
ts:
a.
Kw
h (
De
live
red
/Re
ceiv
ed)
b.
Kva
rh (
De
live
red/
Re
ceiv
ed)
c.
Inst
anta
neo
us th
ree
ph
ase
wat
ts
d.
Inst
anta
neou
s th
ree
ph
ase
va
rs
e.
Inst
anta
neou
s si
ngl
e p
hase
vo
ltsf.
In
stan
tane
ous
sin
gle
pha
se a
mp
s
5.3
T
he
me
ter
sha
ll be
pro
vid
ed
with
Eth
erne
t an
d R
S-2
32/4
85
com
mu
nic
atio
n p
ort
s a
nd s
hall
sup
port
DN
P-3
.0 p
roto
col.
5.4
T
he
me
ter
sha
ll ha
ve th
e c
apa
bili
ty o
f co
nne
ctin
g to
the
sta
tion
serv
ice
au
xilia
ry 1
20 v
olt
AC
pow
er
sou
rce
.
6.
ME
TE
R O
UT
PU
T
6.1
Prim
ary
an
d B
acku
p M
ete
ring
6.1
.1
Th
e P
rimar
y a
nd
Bac
kup
met
ers
ou
tput
s sh
all b
e co
nn
ect
ed to
the
Sub
stat
ion
RT
U v
ia th
e E
the
rne
t co
mm
un
ica
tion
po
rt.
-
En
gr.
Doc
: T
ran
smis
sio
n In
terc
onn
ectio
n-G
ene
ratio
n M
ete
ring
Da
te:
Aug
ust
16
, 20
17
Pag
e 4
of
6
7.
ME
TE
R IN
ST
AL
LA
TIO
N P
AC
KA
GE
7.1
C
ontr
ol H
ou
se P
ane
l (S
ee F
igur
e 1
)
7.1
.1
Kem
co P
late
(R
U J
EM
-1)
7.1
.2
2 J
EM
ST
AR
II
swit
chbo
ard
met
ers
wit
h ca
se
Pri
mar
y/B
acku
p (S
uppl
ied
by M
eter
Dep
artm
ent)
7.1
.3
2
FT
-1 F
lexi
10
pol
e t
est
switc
h (c
urre
nt/
volta
ge)
(S
ub
stat
ion
sup
plie
d)
7.1
.4
1 F
T-1
Fle
xi 1
0 po
le T
est s
wit
ch (
volt
age
only
) (S
ubst
atio
n su
ppli
ed)
7.1
.5
1 3
pos
ition
sel
ecto
r sw
itch
(Sub
stat
ion
supp
lied
)
7.1
.6
If th
e m
eter
is lo
cate
d on
the
dist
ribu
tion
side
(25
KV
and
bel
ow)
of th
e po
wer
tran
sfor
mer
, the
CT
s an
d PT
s w
ill b
e su
ppl
ied
by
the
Met
er D
epar
tmen
t.
7.2
Sub
sta
tion
yar
d M
ete
r C
ab
ine
t(S
ee
Fig
ure
2)
7.2
.1
1
40
x40x
15 A
lum
inu
m M
ete
r C
ab
ine
t 7
.2.1
.1
All
Me
ters
an
d c
om
pone
nts
in
sid
e th
e m
ete
r ca
bin
et i
s su
pplie
d b
y th
e M
ete
r D
epa
rtm
en
t (in
clu
din
g t
he
40x
40x
15 c
abin
et)
7.2
.2.1
If
the
me
ter
is lo
cate
d o
n th
e d
istr
ibut
ion
sid
e (2
5 K
V a
nd b
elo
w)
of
the
po
we
r tr
ans
form
er,
the
CT
s an
d P
Ts
will
be
su
pp
lied
by
the
Met
er D
epa
rtm
ent
.
7.3
-
En
gr.
Doc
: T
ran
smis
sio
n In
terc
onn
ectio
n-G
ene
ratio
n M
ete
ring
Da
te:
Aug
ust
16
, 20
17
Pag
e 5
of
6
Fig
ure
1
-
En
gr.
Doc
: T
ran
smis
sio
n In
terc
onn
ectio
n-G
ene
ratio
n M
ete
ring
Da
te:
Aug
ust
16
, 20
17
Pag
e 6
of
6
Fig
ure
2