columbia county community broadband network
TRANSCRIPT
DRAFT FINAL
Broadband Technology Opportunities Program
Award Number: NT10BIX5570037, Grant ID# 87
Columbia County Community Broadband
Network Environmental Assessment
October 14, 2010
Prepared by:
Columbia County Board of Commissioners
Broadband Utility Department
Evans, GA
Engineering Associates, Inc.
Alpharetta, GA
Terracon Consultants, Inc.
Duluth, GA
10‐14‐10 Page 1
Table of Contents Executive Summary 3
Chapter 1 ‐ Purpose and Need 5
1.1 Background and History 6
1.2 Geographic Setting and Need 9
1.3 Goals 10
Chapter 2 ‐ Proposed Actions 11
2.1 Project Description 12
2.1.1 Overview 12
2.1.2 Construction 19
2.2 Alternatives 20
2.2.1 “No Action” Alternative 20
2.3 Preferred Alternative 21
2.4 Alternatives Considered but Eliminated from Further Discussion 21
2.4.1 Leased circuit capacity from incumbent broadband providers 21
2.4.2 Other alternatives investigated but deemed not to be viable 24
Chapter 3 ‐ Existing Environment 26
3.1 Noise 26
3.2 Air Quality 26
3.3 Geology and Soils 26
3.4 Water Resources 28
3.5 Biological Resources / Critical Habitats 29
3.6 Historic and Cultural Resources 32
3.6.1 Historic Overview 32
3.6.2 Current Historic and Cultural Findings 33
3.7 Aesthetic and Visual Resources 52
3.8 Land Use 52
3.9 Infrastructure 52
3.10 Socioeconomic Resources 53
3.11 Human Health and Safety 54
Chapter 4 ‐ Environmental Consequences 55
4.1 Noise 55
4.2 Air Quality 55
4.3 Geology and Soils 55
4.4 Water Resources 56
4.5 Biological Resources / Critical Habitats 56
4.6 Historic and Cultural Resources 56
4.7 Aesthetic and Visual Resources 57
4.8 Land Use 57
4.9 Infrastructure 57
4.10 Socioeconomic Resources 58
4.11 Human Health and Safety 58
10‐14‐10 Page 2
Chapter 5 – Applicable Environmental Permits and Regulatory Requirements 60
Chapter 6 ‐ List of Preparers 62
Chapter 7 – References 63
10‐14‐10 Page 3
List of Appendices 69
Appendix 1 – Maps
Appendix 2 – Aerials
Appendix 3 – Georgia Technology Authority slide
Appendix 4 – Air Quality
Appendix 5 – Water Resources
Appendix 6 – Biological Resources / Critical Habitats
Appendix 7 – Historic and Cultural Resources
Appendix 8 – FAA forms
Appendix 9 – Letters of Support
Appendix 10 – List of Roads included in fiber optic project
Appendix 11 – FCC Environmental Assessment for Cobbham Road and Halali Farm Road and
Memorandum of Agreement for Cobbham Road and Halali Farm Road
10‐14‐10 Page 4
Executive Summary
Overview
This Environmental Assessment (EA) is being prepared for Columbia County, Georgia to fulfill the
requirements of BTOP Grant #87, “Columbia County Community Broadband Network (CCCBN)”. The
project was awarded by the National Telecommunications (NTIA) in March 2010, during Round 1 of the
American Recovery and Reinvestment Act (ARRA), Broadband Stimulus Funding.
The EA reviews the impacts of the preferred route, use of additional wireless technology, an alternate
route, use of disturbed and undisturbed property and a no action alternative to various aspects of the
environment. Areas considered include: Noise, Air Quality, Geology and Soils, Water Resources,
Biological Resources, Historic and Cultural Resources, Aesthetic and Visual Resources, Land Use,
Infrastructure, Socioeconomic Resources and Health and Human Safety.
The project will enhance broadband and wireless access in the community through the use of a 200‐mile
“middle mile” fiber optic network and 5 wireless towers. The network will also support 60 free wireless
access points in parks and other public spaces, with a focus on low income areas.
The network will establish an open access broadband platform that will be open to:
1. Health Care Providers, including the Medical College of Georgia and local clinics;
2. Educational Organizations including the school system, technical college and libraries;
3. Public Service and Community Organizations;
4. Local municipalities and utilities;
5. Broadband Service Providers and Wireless Service Providers;
6. Citizens in economically challenged neighborhoods through free community ―hot spots
The fiber network will provide interconnection points for numerous areas which have been identified as
both unserved and underserved. The project also includes 5 new communications towers to improve
public safety coverage and facilitate additional fixed and mobile wireless broadband services to citizens
throughout the county. The network will initially be equipped with LAN and WAN networking equipment
for use by anchor institutions. The network will also provide dark fiber for the exclusive use of the users
that need this capability.
The fiber optic cable construction will take place along various existing rights‐of‐way and utility
easements throughout the project area. The fiber will be installed using trenching, directional boring
and aerial techniques. Directional boring will be used in locations where surface disturbances must be
minimized; such as central business districts within communities and under sensitive environmental
locations such as wetland or stream crossings.
The project has received overwhelming support from all county and city agencies, whose facilities will be
connected as part of the project. In addition to the approximately 150 facilities connected to the
network, the Medical College of Georgia (MCG), the State’s flagship medical school, has plans to build a
10‐14‐10 Page 5
data center in Columbia County. MCG has made its support of the project known in terms of in‐kind
contributions and letters of support for the project.
From an environmental standpoint, it is important to note that all planned construction activities fall
within two specific parameters recognized as important for environmental assessment review:
1) All communications towers will be constructed on county‐owned land parcels which are
“previously disturbed” and “previously developed”. No pristine or undeveloped lands will be
affected by the tower construction.
2) All fiber optic cable construction will take place within previously disturbed rights‐of‐way of
existing roads (i.e. existing “road shoulders”).
The construction of the CCCBN will consist of well‐accepted construction activities commonly practiced
for telecommunications projects. Therefore the expected environmental impact of these activities will
be minimal, and the planned activities of the CCCBN represent the best alternative to meet the needs
and purposes of the project.
Purpose, Needs, and Alternatives Considered
The primary need of the project is to build a fiber optic and wireless infrastructure to the unserved and
underserved portions of Columbia County. The project’s objective is to establish a network that will
provide increased broadband and wireless access to the entire community, especially the areas of the
county in the most economic need. Increased broadband availability throughout the county will result
in improved economic and educational opportunities to the citizens throughout the county.
Prior to applying for the ARRA grant through NTIA, Columbia County investigated alternatives to building
a new network throughout the county. The first alternative investigated was to lease broadband
connections and unused fibers from any of the several incumbent service providers in the county. This
alternative was thoroughly investigated but ultimately proved not to meet the needs of the project. The
providers were only interested in providing leased connections to the county, and did not allow any of
their unused fibers to be leased. This proved to be the primary reason that this alternative was not
further pursued. Without dark fiber, many of the specific needs of the project could not be met. In
addition, the leased circuit costs presented were such that building and owning its own network proved
to be a much better financial alternative for the County.
Once all the analysis was concluded and it was determined that dark fiber would not be available from
the incumbents, it became clear that building its own network would be the best available alternative
for Columbia County. All of this effort had taken place prior to the creation of the ARRA and the BTOP
program within NTIA. When these programs were defined, the County continued its ongoing effort and
applied for funding in Round 1.
10‐14‐10 Page 6
In summary, all construction activities will be concentrated in previously developed and previously
disturbed areas such as rights‐of‐way of existing roads and county‐owned properties. Analysis of the
project, constructed using the methods described, showed no significant impact during construction or
operation for the preferred route and use of previously disturbed property to any of the resource areas.
In addition, the preferred route and use of pre disturbed property for towers is recommended to reduce
total length of construction and impact on the environment
10‐14‐10 Page 7
Chapter 1 Purpose and Need
1.1 Background and History
The Columbia County Community Broadband Network (CCBN) was conceived by the County’s
Information Technology (IT) department as a means to enhance and improve the lives of the citizens of
the County. The IT Department began earnest work on the project well before the details of the ARRA
Broadband Stimulus programs were finalized in July 2009. The BTOP program served as the final step in
formulating the project. The IT Department has gathered letters of support from the anchor
institutions, reached preliminary agreements with third party service providers, identified the cable
construction route, and designed the network electronics.
1.2 Geographic Setting and Need
Columbia County, Georgia is located in East Georgia northwest of the city of Augusta which is located in
Richmond County (see location maps and aerials in Appendices 1 and 2). According to the US Census
Bureau, Columbia County has a total population of 435,243. The northeastern portion of Columbia
County is relatively affluent, while the southern and western parts of the county are economically
challenged and sparsely populated. The northeastern section, which comprises approximately 40% of
the county, has reasonable commercial broadband access while the remaining 60% is economically
challenged and has very limited or no access. Due to the low subscriber densities in these areas, it is
difficult for a commercial entity to justify the investment necessary to provide reasonable broadband
access to these economically challenged communities. The State of Georgia’s Technology Authority
(http:/gta.georgia.gov) has classified Columbia County as an area in critical need of enhanced
broadband connectivity. The Georgia Technology Authority seeks to ensure that the state’s IT
infrastructure is stable, secure and well‐governed, and provides Georgians with the services they need
and expect. Their study of underserved and unserved areas of broadband coverage in the state rated
areas as critical, moderate, and low. Of 12 regions in the state Regional Commissions, five, including
Columbia County located in Region 7, were rated critical. Appendix 3 illustrates the GTA’s depiction of
a Regional View of Unserved and Underserved Areas in Georgia.
10‐14‐10 Page 8
Columbia County’s Location in Georgia
One of the primary needs of the project is to build a fiber optic infrastructure to the unserved and
underserved areas of the county. The project has identified multiple unserved areas and underserved
areas in the Appling/Harlem/Grovetown areas of the county. The fiber optic cable route establishes
interconnection points at all of these areas, from which last mile service providers can build their
networks to connect citizens in these areas. These areas are for the most part concentrated in the areas
south of Interstate 20, in the areas including and surrounding the cities of Harlem and Grovetown.
The objective of this project is to establish a network that will provide increased broadband
and wireless access to the entire community, especially the economically challenged areas. The network
will be used to improve the quality of life in these areas and enhance employment opportunities. The
County government is proposing to channel its existing IT expenditures to support the establishment
and maintenance of the new network.
The network will be open to commercial users, governmental users, broadband service providers (both
wireline and wireless) and anchor institutions. It will be operated for the sole benefit of the community,
but will be operated as an open network that can be used by commercial service providers to enhance
and expand service, especially in areas that are economically challenged. The County has extensive
project management experience with large complex projects and the operational experience necessary
to help ensure continued success. It has also engaged a professional engineering firm with extensive
10‐14‐10 Page 9
experience designing and developing communications networks in the area, and it has the commitment
of established construction firms and system integrators. Furthermore, commercial service providers,
educational organizations, health care providers, public safety organizations, libraries and other anchor
institutions have pledged their support and plan to use the network to improve the quality of life in the
area.
The following maps show unserved and underserved areas and a representation of the fiber route
throughout the county.
Columbia County Community Broadband Network (CCCBN)Modified Unserved and Under Served Coverage Areas
!(
!(!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(!(
!(
!(
!(!(!(
!(!(
!(
!(!(!(
!( !(!(!( !(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(!(
!( !(
!(!(
!( !(
!(
!(!(
!(
!(!(
!(
!(
!(!(
!(!(
!(!(
!(
!(
!(
!(
!(!(
!(!(!(
!(
!( !(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(!(!(
!(
!(
!(
!(!(!(
!(
!(
!(
!(
!(!(!(!(!(!(!(!(!(!(!(
!(!(!(
!(!(!(
!(!(!(!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
#7
#7
#7
#7
#7
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
&
&
&
CCCBN Total Proposed Length: 220 Miles& Network Interface Points
!? Points Of Interface
#7 Proposed Towers
!( Service Site FacilitiesExisting FiberMasterPlan BroadbandRoadwaysMain RoadsCity Boundaries
Unserved Census Block (15)Underserved Census Block (54)Fort GordonFort Gordon Recreational FacilityRailroad
Ê0 2 41 Miles
10‐14‐10 Page 11
Columbia County Map with Fiber Route
10‐14‐10 Page 12
1.3 Goals
The purpose of the project can be largely summarized by reviewing the initial set of Project Goals which
were formulated in the initial business plan for the project:
• Economic Growth and Quality Jobs
• Promotion of Private Sector Competition
• Enhancement of Digital Inclusion
• Wireless Backhaul
• E‐Government, Civic Participation and Public Safety –
• Education and Integrated Learning –
• Intelligent Transportation System (ITS)
• Communication Security, Capacity, Quality and Cost
• Interoperability and Disaster Recovery
• Telemedicine and Independent Living
• Supervisory Control and Data Acquisition (SCADA)
These goals are described in more detail below:
The CCCBN will spur private‐sector innovation and competition, thereby offering affordable bandwidth
and services to residents of Columbia County. The CCCBN will also integrate public safety, public health,
education, libraries, community centers, and other government users. The CCCBN will serve as a
backbone for networking County agencies and is essential to enhancing government services.
The project will provide broadband education, awareness, training, access, equipment, and support to a
variety of institutions including schools, libraries, medical and healthcare providers, institutes of higher
education, advocacy groups for low‐income and aged citizens, and others. The CCCBN has established
partnerships with groups and organizations from all of these categories and has included each of these
facilities as anchor tenants in the fiber optic cable route.
The project will improve access to and use of broadband services by public safety agencies, and will
stimulate the demand for broadband, economic growth, and job creation. Since this project has been
created, defined, and driven by the IT department of the Board of County Commissioners, buy‐in from
all public safety agencies has been virtually automatic and has been easily solidified from the origins of
the project. Public safety agencies are all included as anchor tenants on the cable route and letters of
support from all such agencies were included in the project application. Additionally, it is well‐known
that increased broadband access in an area is an established driver for economic growth and job
creation. Knology, an established broadband provider for a number of Tier‐2 cities in the Southeast
(including greater Augusta in Richmond County) has already committed to lease fibers from the CCCBN
project to provide broadband connectivity to previously underserved areas such as Grovetown, Harlem,
and the Greenbrier area of Evans in Columbia County.
The project has broad significance because it has potential positive impact on each and every citizen of
Columbia County. Even for citizens who live in areas which are well‐served, the project has broad
10‐14‐10 Page 13
significance because a county‐wide broadband infrastructure will result in increased job opportunities
and economic growth for the entire area.
10‐14‐10 Page 14
Chapter 2 ‐ Proposed Actions
2.1 Project Description
The project includes a fiber network with approximately 200 miles of fiber optic cable and five new 300‐
foot towers. A map is attached that shows the route for the fiber optic cable and the location the new
towers. The fiber and tower construction will consist of multiple phases over the next 24‐30 months.
2.1.1 Overview
Fiber Optic
The approximately 200 miles of fiber optic construction will take place exclusively along the rights‐of
way of existing roads (i.e. existing “road shoulders”). The construction along the right of way will be
performed by plowing, trenching or directional boring. Whenever possible, and in the vast majority of
cases, directional boring will be conducted on all stream crossings. The initial set‐up of the bore will be
outside the 25' stream buffer zone, and the opposite end of the bore will also be outside the 25' stream
buffer zone. These techniques are commonly used in telecommunications construction with minimal
impact on the environment. Silt fences will be used to help ensure that local streams and waterways are
not impacted. The network includes two points of presence (POPS) that will be used to interconnect the
inner and outer ring. These POPS will be collocated with towers and will be placed on existing county
land that includes existing buildings. These sites will be submitted to the FAA for Tower approval and
this submission will include the Phase I Environmental Site Assessment required for all towers by the
FAA.
The fiber optic cable will be used to interconnect approximately 150 “anchor tenant” sites. These
include schools, city and county facilities, public safety facilities, water utility facilities, and traffic signals.
None of the anchor tenant connections will require any new buildings to be constructed. The fiber optic
cable will be brought into these existing buildings via direct burial and/or new and existing conduits.
Directional drilling will be used to install these links. The fiber optic cable will be terminated inside the
existing buildings in areas suited for telecom equipment. In some cases interior conduit may need to be
installed within a building from the termination room into an equipment room located elsewhere in the
building.
The following photographs are some typical representations of the rights‐of‐way which will be used to
construct the project.
10‐14‐10 Page 15
Belair Road at Hereford Farm Rd.
Columbia Drive
William Few Parkway
10‐14‐10 Page 16
Horizon South Parkway
Clarks Hill Rd.
The following table summarizes the anchor institutions to be included in the project and connected to
the new broadband network.
Institution Location Address
Community
Center Eubank Blanchard Community 6868 Cobbham Road, Appling GA 30802
Community
Center Euchee Creek Community Center
5919 Euchee Creek Drive, Grovetown GA
30813
Community
Center Savannah Rapids Pavilion
3300 Evans to Locks Road, Martinez GA
30907
Community
Center
Grovetown Liberty Park Community
Ctr. 1040 Newmantown Rd Grovetown GA 30813
Education
Board of Education Admin Building ‐
Hereford Farm 4781 Hereford Farm Road, Evans GA 30809
Education Technology Department ‐ Appling 6430 Pollards Pond Road, Appling GA 30802
Education Bel Air Elementary School 325 N. Belair Rd, Evans GA 30809
10‐14‐10 Page 17
Institution Location Address
Education Blue Ridge Elementary School 550 Blue Ridge Drive, Evans GA 30809
Education Brookwood Elementary School 455 S. Old Belair Rd, Grovetown GA 30813
Education Cedar Ridge Elementary School 1000 Trudeau Trail, Grovetown GA 30813
Education Euchee Creek Elementary School 795 Louisville Road, Grovetown GA 30813
Education Evans Elementary School 628 Gibbs Road, Evans GA 30809
Education Greenbrier Elementary School 5116 Riverwood Parkway, Evans GA 30809
Education Grovetown Elementary School 300 Ford Avenue, Grovetown GA 30813
Education Lewiston Elementary School 5426 Hereford Farm Road, Evans, GA 30809
Education Martinez Elementary School 213 Flowing Wells Road, Martinez GA 30907
Education North Columbia Elementary School 2874 Ray Owens Road, Appling GA 30802
Education North Harlem Elementary School 525 Fairview Drive, Harlem GA 30814
Education River Ridge Elementary School 4109 Mullikin Road, Evans GA 30809
Education Riverside Elementary School 4431 Hardy McManus Road, Evans GA 30809
Education South Columbia Elementary School 325 McCormick Road, Martinez GA 30907
Education Stevens Creek Elementary School
3780 Evans‐to‐Lock Road, Martinez GA
30907
Education Westmont Elementary School 4558 Oakley Pirkle Road, Martinez GA 30907
Education Columbia Middle School 6000 Columbia Road, Grovetown GA 30813
Education Evans Middle School 4785 Hereford Farm Road, Evans GA 30809
Education Greenbrier Middle School 5120 Riverwood Parkway, Evans GA 30809
Education Grovetown Middle School
5463 Harlem‐Grovetown Road, Grovetown
GA 30813
Education Harlem Middle School 375 W. Forresst Street, Harlem GA 30814
Education Lakeside Middle School 527 Blue Ridge Drive, Evans GA 30809
Education Riverside Middle School 1095 Fury's Ferry Road, Evans GA 30809
Education Stallings Island Middle School
3830 Blackstone Camp Road, Martinez GA
30907
Education Evans High School 4550 Cox Road, Evans GA 30809
Education Greenbrier High School 5114 Riverwood Parkway, Evans GA 30809
Education Grovetown High School 2010 Warrior Way, Grovetown GA
Education Harlem High School
1070 Appling Harlem Highway, Harlem GA
30814
Education Lakeside High School 533 Blue Ridge Drive, Evans GA 30809
Education CCBOE Alternative School 112 Ford Avenue, Grovetown GA 30813
Education New Elementary School off Chamblin Rd Grovetown GA 30813
Education
Higher
Augusta Technical College Columbia
County Campus
3500 John Huffman Way, Grovetown GA
30813
Fire MCFR1 ‐ Headquarters(HDQ) 3910 Desoto Drive, Martinez GA 30907
Fire MCFR2 518 Gibbs Road, Evans GA 30809
Fire MCFR3 704 Fury's Ferry Road, Evans GA 30809
10‐14‐10 Page 18
Institution Location Address
Fire MCFR4 4590 Oakley Pirkle Road, Martinez GA 30907
Fire MCFR5 5074 Hardy McManus Road, Evans GA 30809
Fire MCFR6 2264 William Few Parkway, Evans GA 30809
Fire MCFR7 480 Sugarcreek Drive, Grovetown GA 30813
Fire MCFR8 1646 Clary Cut Road, Harlem GA 30814
Fire MCFR9
1090 Old Louisville Road, Grovetown GA
30813
Fire MCFR10 3141 Ray Owens Road, Appling GA 30802
Fire MCFR11 480 White Oak Road, Harlem GA 30814
Fire MCFR12 6383 Columbia Road, Appling GA 30802
Fire MCFR13 6285 Cobbham Road, Appling, GA 30802
Fire MCFR14 5776 Clarks Hill Road, Appling GA 30802
Fire MCFR15
5701 Burks Mountain Road, Appling GA
30802
Fire MCFR16 3653 Ray Owens Road, Appling, GA 30802
Government Evans Campus 630 Ronald Reagan Dr, Evans, GA 30809
Government Appling Campus
1954 Appling Harlem Road, Appling, GA
30802
Government Range Road Campus 201 Range Road, Appling GA 30802
Government
Columbia County Development
Authority
604 Government Center Way, Evans GA
30809
Government Animal Care and Control Chamblin Road, Grovetown, GA 30813
Grovetown City Hall
103 Old Wrightsboro Rd, Grovetown, GA
30813
Grovetown Grovetown Museum
103 Old Wrightsboro Rd, Grovetown GA
30813
Grovetown Public Safety(GFD1) 306 E Robinson Ave, Grovetown GA 30813
Grovetown Public Safety Annex 105 E Robinson Ave, Grovetown GA 30813
Grovetown Senior Center 103 E Robinson Ave, Grovetown GA 30813
Grovetown Maintenance 1034 Newmanton Rd, Grovetown GA 30813
Grovetown Recreation 1040 Newmanton Rd, Grovetown GA 30813
Grovetown Water Treatment 1400 Lakeview Rd, Grovetown GA 30813
Grovetown Public Safety (GFD2) 105 W Robinson Ave, Grovetown GA 30813
Harlem City Hall 320 N Lousiville St, Harlem GA 30814
Harlem Senior Center 405B W Church St, Harlem GA 30814
Harlem Community Connections 405A W Church St, Harlem GA 30814
Harlem Police Station 180 N Lousiville St, Harlem GA 30814
Harlem Public Works 145 New Street, Harlem GA 30814
Harlem Waste Water Treatment HWY 221, Harlem GA 30814
Harlem Fire Department(HFD1) 110 New Street , Harlem GA 30814
10‐14‐10 Page 19
Institution Location Address
Harlem Fire Department(HFD2) 120 S Hicks Street, Harlem GA 30814
Health MCG Health
Proposed Data Center (Horizon South)
Grovetown GA 30813
Health Columbia County Health Department Chamblin Road, Grovetown GA 30813
Libraries Harlem Library 375 North Louisville St, Harlem GA 30814
Libraries Euchee Creek Library 5907 Euchee Creek Dr, Grovetown GA 30813
Libraries Columbia County Library
7022 Evans Town Center Blvd, Evans GA
30809
Park Patriots Park 6445 Columbia Road, Grovetown GA 30813
Park Blanchard Park 4541 Dewey Dr, Martinez GA 30907
Park Blanchard Woods
4600 Blanchard Woods Drive, Evans GA
30809
Park Evans Towns Center 515 Faircloth Dr, Evans GA 30809
Park Lonnie Morris (Appling) Scotts Ferry Rd Appling GA 30802
Park Memorial Gardens 640 Ronald Reagan Dr, Evans, GA 30809
Park Reed Creek Park 3820 Park Lane, Martinez GA 30907
Park Riverside Park
4431 Hardy‐McManus Road, Evans GA
30809
Park Wildwood Park 3780 Dogwood Lane Appling GA 30802
Park Gooddale Park Grovetown
5200 Wrightsboro Road, Grovetown GA
30813
Public Safety Sheriff's Office 2273 County Camp Road, Appling GA
Public Safety Sheriff's Office Sub Station 650A Ronald Reagan Dr Evans GA 30809
Public Safety Emergency Management Agency 650B Ronald Reagan Dr, Evans GA 30809
Public Safety Georgia State Patrol Office 420 Chamblin RD, Grovetown GA 30813
Public Safety Georgia State Forestry 5887 Wrightsboro RD, Harlem GA 30814
Traffic Control S1 Baston Road/Old Petersburg
Traffic Control S2 Baston Road/Old Ferry/Cedar Lane
Traffic Control S3 Bobby Jones/Rose Lane
Traffic Control S4 Columbia Industrial Blvd/Evans to Locks
Traffic Control S5 Columbia Road/Belair Rd
Traffic Control S6 Columbia Road/Flowing Wells
Traffic Control S7
Columbia Road/Hereford Farm/Lewiston
Road
Traffic Control S8 Columbia Road/Merchant Village
Traffic Control S9 Davis Road/Oak Drive
Traffic Control S10 Evans to Locks/Blue Ridge Drive
Traffic Control S11
Flowing Wells Road/Old Trail Rd
West/Augusta Prep
Traffic Control S12 Futys Ferry Road/Baston Road/Vaughn Road
10‐14‐10 Page 20
Institution Location Address
Traffic Control S13 Furys Ferry Road/Evans to Locks
Traffic Control S14 Furys Ferry Road/Inverness Way/Park Lane
Traffic Control S15
Furys Ferry Road/North Belair/ Mullikin
Road
Traffic Control S16 Futys Ferry Road/The Pass
Traffic Control S17 Hereford Farm/Cox Road/Gibbs Road
Traffic Control S18
Jimmie Dyes Parkway/Belair Frontage
Road/Park West Drive
Traffic Control S19 Jimmie Dyes Parkway/EB I‐20 Ramps
Traffic Control S20 Lewiston Road/EB I‐20 Ramps
Traffic Control S21 Lewiston Raod/WB I‐20 Ramps
Traffic Control S22 Milledgeville Road/Louisville Street
Traffic Control S23 North Belair Road/Cox Road/Owens Road
Traffic Control S24 Old Evans Road/Blue Ridge
Traffic Control S25 Old Evans Road/Martinez Boulevard
Traffic Control S26 Old Evans Road/Old Petersburg Road
Traffic Control S27 Riverwatch Parkway/Pleasant Home Road
Traffic Control S28
Robinson Avenue/Harlem Grovetown
Road/Wrightsboro Rd
Traffic Control S29 South Belair Road/Oakley Pirkle Road
Traffic Control S30
South Belair Road/South Old Belair
Road/Wheeler Road
Traffic Control S31 South Belair Road/WB I‐20 Ramps
Traffic Control S32 Washington Road/Baston Road
Traffic Control S33
Washington Road/Bobby Jones
Expressway/Old Evans Rd
Traffic Control S34 Washington Road/Club Car Drive/AnnTaylor
Traffic Control S35
Washington Road/Columbia Road/Ruth
Street
Traffic Control S36 Washington Road/Davis Road
Water Utility Jim Blanchard Water Plant 832 Point Comfort Road, Martinez GA 30907
Water Utility Clarks Hill Water Plant 5776 Clarks Hill Road, Appling GA 30802
Water Utility Crawford Creek Waste Water Plant 1000 Shepherd Way, Grovetown GA 30813
Water Utility Reed Creek Waste Water Plant 578 Stevens Creek Rd, Martinez GA 30907
Water Utility Kiokee Creek Waste Water Plant 2281 County Camp Road, Appling GA 30802
Water Utility Little River Waste Plant 1130 Maple Ridge Court, Evans, GA 30809
Water Utility I‐20 Water Tank 4824 Old Belair Lane, Martinez GA 30907
Water Utility Winfield Water Tank 3317 Tom Bartles Road, Appling GA 30802
Water Utility Washington Road Water Tank 5801 Washington Road, Appling GA 30802
Water Utility Louisville Water Tank 5919 Euchee Creek, Grovetown GA 30813
10‐14‐10 Page 21
Institution Location Address
Water Utility Flowing Wells Water Tank 494 Flowing Wells Road, Martinez GA 30907
Water Utility Grovetown Water Tank
4939 Wrightsboro Road, Grovetown GA
30813
Water Utility Wrightsboro Rd Water Tank
4605 Wrightsboro Road, Grovetown GA
30813
Water Utility Belair Rd Water Tank 222 North Belair Road, Evans GA 30809
Water Utility Appling Water Tank 5984 Columbia Road, Appling GA 30802
Water Utility High View Water Tank 206 Pecan Drive, Martinez GA 30907
Water Utility
Administrative Buildings Chamblin
Road 205 Chamblin Road, Grovetown 30813
Towers:
As mentioned previously the 5 tower locations will reside on Columbia County owned property that has
been pre‐disturbed and pre‐developed. Therefore, it is expected that no significant clearing, excavating,
or other disturbance of the property will be required. There will need to be fencing constructed around
the perimeter of the tower footprint and (if applicable) any of its guy wire anchor points. The tower
construction will contain pre‐fabricated (typically concrete), above‐ground equipment buildings. These
buildings will be located at the base of the tower and will be situated within the property used for the
tower base. Approximate building dimensions are 10 feet x 15 feet (single story). The project will utilize
existing buildings and pre‐disturbed, pre‐developed areas. The only new buildings to be constructed
will be located adjacent to the (5) new radio towers within the same property parcels containing the
towers. These will most likely take the form of pre‐fabricated concrete structures commonly used for
telecommunications buildings, cell sites, etc. All tower locations are planned for previously disturbed,
previously developed land parcels currently owned by the County. All tower locations have been
submitted to the FAA for approval (see Appendix 8) and a Phase I Environmental Site Assessment will be
performed, as required by the FAA.
The 5 towers are described in the table below and shown in the following photographs and aerials.
ADDRESS LATITUDE LONGITUDE PARCEL #
480 White Road, Harlem, GA 33 deg 24’ 20” N 82 deg 17’ 20” W Parcel 043A020
6868 Cobbham Road, Appling
GA
33 deg 36’ 37” N 82 deg 19’ 32” W Parcel 025 047
590 Baker Place Road
Grovetown, GA
33 deg 29’ 17” N 82 deg 14’ 13” W Parcel 051 001B
962 Halali Farm Road 33 deg 34’15” N 82 deg 10’ 7” W Parcel 065 021
2292 County Camp Road
Appling, GA
33 deg 32’ 14” N 82 deg 18’ 32” W Parcel 028 057
The proposed 590 Baker Place Road site has commercial power immediately adjacent via utility pole line
located on the opposite side of the road. The provision of power to the site will require a simple
10‐14‐10 Page 22
extension from existing sources. The proposed 2292 County Camp Road site has commercial power
immediately adjacent via utility pole line located on the opposite side of the road. The provision of
power to the site will require a simple extension from existing sources. The proposed 6868 Cobbham
Road site already has commercial power located on the site. The proposed 480 White Road site has
commercial power on the opposite side of the road. Electrical power to the site will be provided via an
underground cable that will be located within the 12‐foot by 360 foot access road. An underground
trench will be excavated within the above mentioned access road to the communication site itself. An
underground cable buried in the trench will provide power to the site. The total linear distance of the
power run will be approximately 360 feet. The proposed 962 Halali Farm Road site has commercial on
the same side of the road. Electrical power to the site will be provided via an underground cable that
will be located within the 12‐foot by 480 foot access road. An underground trench will be excavated
within the above mentioned access road to the communication site itself. An underground cable buried
in the trench will provide power to the site. The total linear distance of the power run will be
approximately 480 feet.
All proposed sites include a standby generator to provide electric power in the event of a commercial
power failure. The standby generator will be powered by diesel, and will typically be comprised of a
108 horsepower internal combustion engine power unit driving a single‐phase 60 kilowatt generator.
The emissions level for the generator engine will be rated EPA Nonroad Tier 3. The generator will be
mounted inside a Level 2 Sound Enclosure, and will include a muffler on the power unit and appropriate
sound proofing within the walls of the enclosure to minimize noise. Diesel fuel will be provided from a
Dual Wall UL142 tank mounted inside the enclosure on concrete slabs. The diesel tank will be sized in a
manner to allow for a constant generator run time of up to 168 hours or one week, in the event of a
long‐term power failure.
2.1.2 Construction
The project will use a variety of techniques in installing the fiber optic cable and communications towers. The majority of the fiber optic construction will be underground, but in some congested areas or areas of a cost‐prohibitive nature, the cable will need to be installed aerially on either existing or new poles. In addition, in rare instances, it is possible that “aerial inserts” will need to be placed over stream
or waterway crossings if the preferred underground methods are for some reason impractical or cost‐
prohibitive.
For underground construction, the general requirement for minimum depth of placement is 36” below
grade. When new facilities cross under ditch lines, roads, and streams, the depth will usually be 48”.
Underground cable placement can be done via trenching, plowing, and boring. All construction will take
place within the right of way of existing roadways in pre‐disturbed areas.
Plowing: Construction along rural routes is usually done via plowing. Plowing employs the use of a
specialized piece of machinery called a track plow. The plow opens a slot into the ground at the
specified depth. The slot is no more than 6” wide. A reel of fiber cable is loaded onto the plow, and as
the plow moves forward the cable is fed into a chute which directs the cable into the bottom of the slot
opened by the plow. The cable is laid at the proper depth, and as the plow continues forward the
10‐14‐10 Page 23
excavated slot is compacted back to ground level. In a rural area with a minimal amount of
obstructions, plowing is the most time‐ and cost‐efficient method of placing underground fiber cable.
Trenching: Underground cable construction in more congested areas will typically make use of
trenching as opposed to plowing. If the area has many obstructions such as existing underground
utilities, driveway crossings, aerial transitions, etc. a trench is excavated and the cable is laid manually
into the bottom of the trench. The trenching method would require the use of a backhoe if rock or
especially hard ground is involved, or a trenching machine if the ground is less hard. Trench dimensions
will vary, but can be nominally summarized as 36” typical depth, with 24” maximum width if a backhoe
is used or 6” width if a trencher is used. No open trenches will be left overnight without cover. The
trench is back‐filled using the same soil material that was removed to create the trench, except in rocky
areas, where the backfill may be hauled in and the rock material removed.
Boring: Boring is used when underground fiber cable placement must be conducted in areas where no
linear excavations are feasible on the surface, or in areas where surface restoration is cost‐prohibitive.
In directional boring, a boring rig is used to tunnel under existing roads, utilities, driveways, waterways,
or other obstructions. Bore diameters are typically 4‐6 inches. Bore lengths are typically less than 100
feet, but can be as long as hundreds of feet when crossing large rivers or streams. A bore pit may need
to be dug at the beginning of the bore, which allows the excavation to start at the proper depth. The pit
can be as deep as 6‐8 feet, depending on the depth required for the bore. The boring head is directed
forward by the operator and is used to tunnel through the ground beneath the obstructions. As the
head moves forward, 10‐foot rod sections are added at the boring rig to increase the length of the
excavation. A slurry mixture is introduced through the rods and bore head to soften the soil for
compaction around the path of the boring head. Once the obstructions are cleared, the boring head
can be directed upward to the surface. Once the excavation has been completed and the head appears
above the surface, flexible PVC casing pipe from a spool is attached the bore head. The bore head is
then pulled back along the excavation, pulling the casing pipe back to the bore pit and thus creating a
pathway for cables and inner ducts to be pulled into at a later time.
Aerial – existing poles: Aerial fiber optic plant construction may be used as an alternative to
underground installation via plowing, trenching, or boring. Where existing pole lines are present, fiber
optic cable can be installed on existing poles. Installing cable on pole lines requires strict adherence to
electrical safety code requirements. Specifically, safety codes require that telecom cables can only be
installed in certain parts of the vertical space on the pole lines. The telecom space is closest to the
ground and is frequently crowded with cables owned by telephone companies, cable TV providers, and
in some cases, CLECs and municipal network providers. As a result, it is very common for existing pole
lines to be unusable for new telecom facilities because the telecom space is too crowded. In some cases
existing cables can be rearranged to gain additional space but the cost of this process (referred to as
“make‐ready” work) can be cost‐prohibitive. If the poles are owned by third parties (i.e. power
companies, telephone companies, or cable TV companies), then joint‐use agreements must be worked
out which allow new providers to lease space on un‐owned poles for a per‐year, per‐pole cost. Over the
long term, leasing space on third‐party poles can also prove to be cost prohibitive. As a new service
10‐14‐10 Page 24
provider, Columbia County owns no poles and would be dependent on leasing poles from third parties,
thus increasing the long‐term cost of the project. It is for these reasons that the majority of the fiber
optic construction planned in this project is planned to be underground whenever possible.
Aerial – new poles: In some cases aerial cable construction is done using new pole lines. This may occur
when there is no pole line present, when joint‐use costs are too expensive, or when the telecom space
on the existing pole line is too crowded. If aerial inserts are required for stream crossings, new poles are
usually needed on either side of the stream’s buffer zone to support the aerial crossing. The
construction of new utility poles has been ongoing since the beginnings of the telecom industry decades
ago. If any new poles are required, they will be engineered and constructed using best practices from
the industry. This includes adherence to all applicable RUS specifications and standards, including RUS
Bulletin 1753F‐152 / RUS Form 515c (“Specifications and Drawings for Construction of Aerial Plant”).
This specification addresses such requirements as pole materials, mounting depth relative to pole
height, backfill and tamping methods, support member requirements, grounding requirements, and
many more. Although the CCCBN is not financed using RUS funds, the RUS telecom practices represent
the best specifications and standards for telecom cable construction that the industry has.
Aerial Placement of Cable: The preferred method for cable placement for the CCCBN will be
underground via trenching, boring, or plowing. However in some areas these techniques may not be the
most cost‐effective method, thus requiring aerial cable placement. Aerial cable is typically placed on
pole lines by attaching the cable to a metallic, stranded support member known as messenger wire. The
cable is lashed tightly to the messenger wire using a thin, flexible, high‐strength attachment wire.
Ground clearance requirements for the cables and the supporting messenger must be taken into
account based on applicable electric safety codes. Aerial cable can be installed from a stationary reel or
a moving reel using temporary pulleys or "J‐hooks”. The pulleys can be installed at each pole, with a
truck winch being fed through the pulleys and attached to the end of the cable. The cable is then pulled
into place. The cable can also be installed by attaching one end to the first pole with the rest of the reel
moved to the next pole. In this case temporary pulleys are not needed, because the cable is attached to
each pole as it is unreeled.
Towers: The towers planned for this project are nominally 300 feet above ground level (AGL). They are
intended to be self‐supporting towers (i.e. without guy wires) so their footing dimensions will be
broader than those of a guyed tower. Exact foundation dimensions will be determined after the towers
are designed for the specific locations, but for planning purposes and Environmental Assessment
purposes, the concrete pad which will comprise the foundation for the tower can be assumed to be
approximately 40’ wide x 40’ long x 6’ in depth. Tower foundations will require excavations to depths to
be determined by a variety of factors. The structural design of the towers will specify the detailed
requirements of the excavations and backfills. Tower foundations will be secured using steel‐ reinforced
concrete below grade. All towers will be erected on county‐owned land parcels which have been
previously disturbed.
Tower construction will require the use of grading machinery to level the site and construct access
roads, excavation machinery to dig the tower foundations, concrete trucks to install the steel‐reinforced
10‐14‐10 Page 25
concrete for the tower foundations, and cranes to place the tower sections in place. The buildings to be
installed adjacent to the towers will be pre‐fabricated concrete structures designed for
telecommunications use. These structures will be transported to the site on flatbed trucks and lowered
into place using cranes.
2.2 Alternatives
2.2.1 ‐ “No Action Alternative”
In the “no action alternative” the CCCBN would not be built at all. If the CCCBN is not built, the county
will continue to suffer from lack of increased broadband opportunities. The following will be
consequences of not building the CCCBN:
Unserved and Underserved areas of the county will continue to suffer from lack of broadband
opportunities.
Anchor institutions will not have fiber connections.
County school children will not have high‐bandwidth 1 Gbps connections from the schools to the
Internet
Last mile providers will not be able to access potential customers in Grovetown and Harlem.
Economic development will suffer due to the lack of a robust fiber infrastructure.
The MCG Health data center will not be able to transmit medical imagery and patient records at
high speed throughout the area.
Control systems for county infrastructure (water/sewer, traffic systems, etc.) will not be able to
be controlled through advanced fiber optic technology.
Wi‐Fi in county parks would not be possible due to lack of fiber optic backhaul of the traffic
Public safety radio coverage will continue to be sporadic due to the lack of RF coverage resulting
from fewer towers.
2.3 – Preferred Alternative
In analyzing the alternates to the CCCBN construction, it is apparent that no alternative will meet the
needs of the project. Leased circuit capacity, as described in detail below, does not provide the dark
fiber required to connect all the anchor institutions. It would not allow third‐party service providers to
access the unserved and underserved areas of the county. It is not cost‐effective since it represents a
higher cost with no owned asset value. The “no action alternative” would consist of continuing the
current status of the county’s broadband infrastructure. This would result in none of the needs of the
project being met. Since neither of these alternatives represents viable solutions to the needs of the
project, it is concluded that building the fiber optic cable network and communications towers as
planned in the CCCBN grant will be the best method to meet the needs of the project.
2.4 ‐ Alternatives Considered but Eliminated from Further Discussion
A number of alternatives to the preferred alternative were considered early and then rejected as being
not worthy of further discussion. These alternatives consisted of variations in particular aspects of the
preferred alternative and are discussed below.
10‐14‐10 Page 26
2.4.1 Leased circuit capacity from incumbent broadband providers
As a possible alternative to building and operating its own network, Columbia County first investigated
the idea of leasing capacity on the network of one of the existing incumbent providers in the county.
This alternative would have resulted in a dramatically different environmental assessment, since no new
construction would need to take place. However, this alternative was investigated in detail and was
deemed inadequate to meet the needs and purpose of the project. After this alternative was
investigated and rejected, it was decided to move ahead with the planning and construction of the
CCCBN project. The discussion below explains how this alternative was deemed inadequate for the
needs of the project.
The effort to create the CCCBN has been ongoing since 2008, prior to the creation of the ARRA program.
The County recognized that dark fiber was needed for public safety radio system needs, SCADA needs
and medical imaging requirements. It also determined that high bandwidth requirements were needed
in the less affluent areas of the county and these high bandwidth requirements were not being satisfied
by the service providers in these areas. Approximately two years ago AT&T, Comcast and Charter were
approached by Columbia County to investigate the possibility of leasing or buying dark fiber from these
carriers. Charter declined to participate and thus no agreement was reached. Comcast showed some
interest but it had no spare fiber available for use. AT&T, following a widely observed policy repeated in
other states, was not willing to sell or provide dark fiber, but instead offered to provide leased circuit
capacity on their Metro E network. This offer included a connection to many county building locations
but did not include a county‐wide fiber build‐out.
As stated above, AT&T declined to provide dark fiber, but did propose a leased Metro E network. Using
the monthly lease cost and one‐time installation charges, the 5‐year lease cost totaled just over $20
million, which includes approximately $4 million in initial installation costs. In comparison, the total
proposed CCCBN project cost is just over $18 million. (It should be noted that the $18M CCCBN cost
also includes approximately $2 million for 5 wireless towers). Comparing these cost figures, it is
apparent that a county‐owned fiber network would be a better investment than a leased network. Not
only does the $20 million lease cost represent a higher initial investment, it also represents less value
since it is a leased network without owned assets. Furthermore, it does not represent the same
functionality as a dark fiber network, as is explained below.
First, the $20 million AT&T cost included a maximum bandwidth connection rate of 100 Mbps. In
contrast, the planned bandwidth speeds for the fiber‐based CCCBN are 100 Mbps minimum, with
maximum bandwidth connections of 1 Gbps. Secondly, a leased network represents only a collection of
building connections, with no additional infrastructure included. The fiber‐based CCCBN represents a
robust infrastructure which makes dark fiber available not only for the county’s use but also for the
potential use of network partners and service providers throughout the county. In summary, the Metro
E alternative was too expensive, did not cover the entire county, and did not fulfill all the needs of the
project.
10‐14‐10 Page 27
The following table summarizes the pros and cons of building the fiber network vs. using the leased
capacity from the AT&T Metro E network.
CCCBN Fiber Network AT&T Metro E Network
Investment $18 Million $20 Million
Asset Value $18 Million $0
Projected cost for Years 6‐10 operating cost only $16 Million (ongoing leasing
cost)
Dark Fibers Yes No
Maximum Bandwidth
Connection Speed
1 Gbps 100 Mbps
County‐wide presence Yes No
Future Capacity for Additional
Network Partners
Yes No
One of the most important partners in the CCCBN is the Medical College of Georgia Health System
(MCG). MCG is the state of Georgia’s flagship institution for medical education and public health, and it
is located in nearby Augusta. MCG Health is in the process of planning and building a new data center to
be located in Columbia County. One of the missions of MCG Health is the need to transmit high‐
resolution medical images and medical records to remote locations in the region surrounding Columbia
County. This is currently done via leased point‐to‐point microwave circuits and does not work well.
Fiber is the ideal media for this application.
In conclusion, the discussion above should make it apparent that dark fiber is a real necessity in the
CCCBN, and leased MetroE capacity does not provide the same benefits in a community middle mile
network. Once it became apparent that dark fiber could not be obtained from any of the existing
carriers it was made clear that a new fiber‐based county‐owned network would provide the most value
to the county and to its anchor institutions, business partners, and end users.
2.4.2 Other alternatives investigated but deemed not to be viable
One possible alternative to the planned fiber optic construction would be to place the fiber optic cable
on land that is not contained within right of way of existing roadways. This strategy would have resulted
in additional problems such as:
Need for property acquisition
Engineering and construction delays
Increased cost
Increased environmental impact
10‐14‐10 Page 28
The vast majority of telecommunications facility construction occurs within right of way of existing
roads. For this reason it is generally accepted that installing cable in existing right of way represents a
set of best practices that should be followed whenever possible.
Regarding the tower construction, the possible alternatives to building them on county‐owned
properties could have been 1) omitting them from the project and 2) installing them on private (non‐
county owned) property. The idea of omitting the towers was discussed in the “no action” alternative.
The idea of installing the towers on land not owned by the county can be rejected due to many of the
same reasons shown above:
Need for property acquisition
Need for property clearing and re‐use classification
Engineering and construction delays
More difficult site access
Increased project cost
Increased environmental impact
For the many reasons summarized, this alternative was decided to be not worthy of further discussion.
2.4.3 – Alternatives Using More Wireless Technology
Another possible alternative to installing all or part of the 200 miles of fiber optic cable would be to
incorporate more wireless technology into the CCCBN. If some or all of the needed services could be
delivered by wireless methods, then it may be possible to build less cable miles and thus reduce certain
environmental ramifications of the project. However, due to the reasons outlined below, wireless
technology does not support the same benefits that fiber optic cable does and is therefore not a good
alternative to the 200 mile fiber optic cable route.
It should be noted that the CCCBN already does incorporate wireless to a certain extent. The project
contains 5 towers which will be used for improved public safety coverage and will also be available for
broadband service providers to lease space and connect to customers throughout the county. However,
when it comes to the type of services that Columbia County is proposing in this middle mile network,
fiber optic technology offers much more bandwidth on a much more cost‐effective basis.
The previous discussion for section 2.4.1 (the evaluation of the leased circuit capacity alternative)
outlined many of the needs of the middle mile network, and explained the advantages of building fiber
through the county as opposed to leasing available circuit capacity. Specifically, higher bandwidths and
dark fiber are needed for many of the high‐bandwidth services and capabilities required in the CCCBN.
All of these same bandwidth advantages apply when compared to the bandwidth capability of a
potential wireless middle‐mile network. While the bandwidth of wireless services has grown
dramatically in recent years, the aggregate bandwidth capacity of a wireless middle mile network still
lags significantly behind that of a fiber‐based network. While it may be true that some point‐to‐point
10‐14‐10 Page 29
radio systems can achieve Gigabit Ethernet speeds (over relatively short distances), fiber is still
unmatched in its ability to transmit high capacity over long distances. As an example, optical Ethernet
transceivers can perform on the order of 10 Gbps over 50 miles and 40 Gbps over shorter distances.
Point‐to‐point wireless systems do not operate in this capacity.
In order to cover the same remote areas of the county (where the new bandwidth and services are
needed most) a significantly higher number of towers would be needed to establish a coverage area
comparable to the 200 mile fiber network. A conservative estimate would be an additional 20‐30
towers which would be needed to cover the same 200 route‐miles planned for the fiber. At an
approximate cost of $12 Million, the cost of the towers would be higher than the amount budgeted for
the fiber optic construction.
One final consideration is the dark fiber capability that a middle mile fiber network will support. In the
network as designed, there will be a robust amount of dark fibers available for network expansion and
for future capabilities to provide many services not yet defined. A wireless middle mile network would
not have such capacity for expansion and growth. The only way to expand the capacity would be to
install additional radio systems. This approach would be limited by spectrum availability restrictions as
well as physical space restrictions on the towers.
10‐14‐10 Page 30
Chapter 3 ‐ Existing Environment
3.1 Noise
Noise levels vary in Columbia County, depending on the type of land use for the area in question. The
county contains a Federal Interstate Highway (I‐20) which provides a fairly consistent level of ambient
noise in the immediate vicinity. However since the majority of the I‐20 route miles through the county
are rural in nature, the noise levels tend to fluctuate with traffic patterns and do not present sustained
periods of noise pollution. There are also a number of two‐lane and four‐lane state highways, whose
immediate vicinities contain ambient noise levels consistent with such roadways. The Evans / Martinez
areas exhibit some traffic congestion during rush hour periods, and therefore also contain ambient noise
levels consistent with suburban traffic patterns. There is some light industry in the county but none of
these industries contribute sustained, significant, levels of ambient noise.
The majority of the acreage of the county, once removed from the immediate vicinity of the traffic
corridors, contains rural forested lands with very low noise levels.
3.2 Air Quality
Columbia County does not fall within a non‐attainment zone, as defined by the National Ambient Air
Quality Standards (NAAQS) for all criteria pollutants. The county contains no Air Quality Management
Districts (AQMDs) or State Implementation Plans (SIPs). According to the Environmental Protection
Agency (EPA) (http://www.epa.gov/air/oaqps/greenbk/ancl3.html), the only non‐attainment zones in
Georgia are in the Atlanta metro area, and the Macon and Rome, Georgia areas.
Attached in Appendix 4 is a re‐print of a letter from the Georgia Department of Natural Resources
(dated 3‐12‐09) confirming that Columbia County does not fall in a non‐attainment zone. The letter may
be found on‐line at:
http://www.gaepd.org/air/airpermit/downloads/planningsupport/naa/ozone8_recomdesig_2009letter.
3.3 Geology and Soils
Columbia County lies near the confluence of the Atlantic Coastal Plain and the Appalachian Highland,
Piedmont Upland section. Since the construction will take place within right of way of existing
roadways, as well as county‐owned land parcels that have been previously disturbed, the project will
have no impact on prime or unique farmlands, as defined in the Farmland Protection Policy Act (FPPA).
A wide variety of soils are found within Columbia County, almost 40 in total. A detailed soil survey
report (found at http://soildatamart.nrcs.usda.gov/reportparams/counties.aspx ) is summarized below,
showing each type of soil present in the county along with corresponding acreage.
10‐14‐10 Page 31
Acreage and Proportionate Extent of the Soils by County Acres Pct AkA Altavista sandy loam, 0 to 2 percent slopes 735 0.1 AmB Appling sandy loam, 2 to 6 percent slopes 11,020 2.0 AmC Appling sandy loam, 6 to 10 percent slopes 7,860 1.4 Bh Bibb silt loam 2,035 0.4 CfB2 Cecil sandy clay loam, 2 to 6 percent slopes, eroded 12,655 2.3 CfC2 Cecil sandy clay loam, 6 to 10 percent slopes, eroded 14,510 2.6 CfE2 Cecil sandy clay loam, 10 to 25 percent slopes, eroded 10,450 1.9 CK Chewacla and Congaree soils 4,980 0.9 DgB Davidson loam, 2 to 6 percent slopes 1,560 0.3 DhC2 Davidson clay loam, 6 to 10 percent slopes, eroded 1,485 0.3 DhE2 Davidson clay loam, 10 to 25 percent slopes, eroded 1,020 0.2 EnD Enon sandy loam, 10 to 15 percent slopes 4,365 0.8 FdB Faceville sandy loam, 2 to 6 percent slopes 125 <0.1 GcB Georgeville fine sandy loam, 2 to 6 percent slopes 4,400 0.8 GdC2 Georgeville clay loam, 6 to 10 percent slopes, eroded 4,610 0.8 GdE2 Georgeville clay loam, 10 to 25 percent slopes, eroded 2,550 0.5 GeB Grover sandy loam, 2 to 6 percent slopes 1,565 0.3 GeC Grover sandy loam, 6 to 10 percent slopes 2,380 0.4 GeD Grover sandy loam, 10 to 15 percent slopes 1,345 0.2 HeB Helena loamy coarse sand, 2 to 6 percent slopes 3,625 0.7 HeC Helena loamy coarse sand, 6 to 10 percent slopes 5,550 1.0 MdB Madison sandy loam, 2 to 6 percent slopes 2,550 0.5 MdC Madison sandy loam, 6 to 10 percent slopes 2,905 0.5 MdE Madison sandy loam, 10 to 25 percent slopes 3,075 0.6 MgD Madison-Grover complex, 6 to 15 percent slopes 935 0.2 NhB Norfolk loamy sand, 2 to 6 percent slopes 2,505 0.5 NhC Norfolk loamy sand, 6 to 10 percent slopes 1,070 0.2 OcB Orangeburg sandy loam, 2 to 6 percent slopes 1,535 0.3 OcC Orangeburg sandy loam, 6 to 10 percent slopes 1,310 0.2 Pm Pits, quarries 250 <0.1 Ro Roanoke silt loam 5 <0.1 Rx Rock outcrop 275 <0.1 TfB Tifton loamy sand, 2 to 6 percent slopes 480 <0.1 TsC Tifton sandy loam, 6 to 10 percent slopes 470 <0.1 Tv Toccoa loam 5,140 0.9 TwC Troup sand, 2 to 10 percent slopes 4,780 0.9 TwE Troup sand, 10 to 25 percent slopes 805 0.1 VeB Vaucluse loamy coarse sand, 2 to 6 percent slopes 330 <0.1 VeD Vaucluse loamy coarse sand, 6 to 15 percent slopes 2,020 0.4 W Water 13,330 2.4 WaB Wagram loamy sand, 2 to 6 percent slopes 8,345 1.5 WaC Wagram loamy sand, 6 to 10 percent slopes 3,915 0.7 WaD Wagram loamy sand, 10 to 15 percent slopes 1,150 0.2 WeB Wedowee loamy sand, 2 to 6 percent slopes 5,850 1.1 WeC Wedowee loamy sand, 6 to 10 percent slopes 12,875 2.3 WeD Wedowee loamy sand, 10 to 15 percent slopes 10,060 1.8 WeE Wedowee loamy sand, 15 to 25 percent slopes 9,470 1.7 Wf Wehadkee silt loam 1,935 0.4 WhB Wickham fine sandy loam, 2 to 6 percent slopes 410 <0.1 Wo Worsham sandy loam 395 <0.1 Note: Percentages do not add to 100 because the survey was done on a three-county basis (Columbia, Warren, McDuffie) and only the Columbia results were printed in the report.
10‐14‐10 Page 32
3.4 Water Resources
Columbia County contains a variety of water resources. The northern border of the county lies along
Clarks Hill Lake, a man‐made reservoir through which the Savannah River flows. Clarks Hill Lake (also
known as J. Strom Thurmond Lake) covers 70,000 acres and was built circa 1950. The uses for the lake
include flood control, hydropower, and navigation, recreation, water quality, water supply, and
fish/wildlife management. The normal pool elevation is 330 feet above mean sea level and the
shoreline encompasses 1,200 miles.
The Savannah River forms part of the county’s northern border as well. Four watersheds are located in
Columbia County: the Savannah River watershed, the Little River watershed, the Middle Savannah River
watershed, and the Brier Creek watershed. The more significant streams and creeks that contribute
water flows to these watersheds include Euchee Creek, Kiokee Creek, Little Kiokee Creek, Crawford
Creek, and Greenbrier Creek. Columbia County contains no coastal areas.
Floodplain data has been researched from the FEMA website, and additionally Columbia County GIS has
provided maps with the fiber network and proposed tower locations layered onto current floodplain
data (see Appendix 5). All floodplain areas in Columbia County are 100‐year floodplain; no 500‐year
floodplains are indicated.
3.5 Biological Resources / Critical Habitats
As designated by the US Environmental Protection Agency
(http://www.epa.gov/wed/pages/ecoregions/na_eco.htm#Level%20I) Columbia County may be
classified in the following ecoregions:
Level I – Eastern Temperate Forest
Level II – Southeastern USA Plains
Level III – Piedmont
The fiber route will be constructed on pre‐disturbed roadways, and all 5 proposed tower sites are on
existing developed County property.
In accordance with Section 7(c) of the Endangered Species Act, as amended, 16 U.S.C. 1531 et seq.,
CCCBN contacted the United States Fish and Wildlife Service and the Georgia Department of Natural
Resources Wildlife Resources Division for the most updated species list and species accounts available. A
response from the US Fish and Wildlife Service in Athens, GA dated April 29, 2010 indicated that federally
listed species are not likely to occur on the project sites (Appendix 6). However, regarding the 5 towers,
the agency recommended practices to minimize potential impacts to migratory birds, specifically to
equip guy wires with bird diverters and light the tower only with white strobe lights with the maximum
off period between flashes (3 seconds is current maximum allowable).
The Georgia Department of Natural Resources Wildlife Resources office provided comprehensive data
for county‐wide special concern animals, plants and natural communities. This information is detailed in
the spreadsheet “Columbia Co_Rare Species.xlsx” and is included in Appendix 6.
Columbia County Community Broadband Network (CCCBN)Core Areas and Connectors
#0
#0
#0
#0
#0
Draba aprica
Astergeorgianus
Trilliumreliquum
Astergeorgianus
Dryopteriscelsa
Hymenocalliscoronaria
Paronychia virginica
Scutellariaocmulgee
Amphianthus pusillusAnemoneberlandieri
Arabis missouriensis
BARE ROCK/LICHENS,PD GRANITE OUTCROP
Trilliumreliquum
Isoetestegetiformans
Sedum pusillum
SHRUB/SCRUBVEG., PD
GRANITE OUTCROP
Astergeorgianus
Cyprinella nivea
Cyprinella nivea
Pediomelum sp. 2
Bouteloua curtipendula
Clematis ochroleuca
Elliottia racemosa
Marshalliaramosa
Scutellariaocmulgee
PD XERIC BROADLEAFDECID.-NEEDLELEAF
EVER. FOREST
Pediomelum sp. 2
Portulacaumbraticola
ssp. coronata
Amphianthuspusillus
Anemone berlandieri
Drabaaprica
Isoetes tegetiformans
Portulacaumbraticola
ssp. coronata
Sedum pusillum
Portulacaumbraticola
ssp. coronata
Portulacaumbraticola
ssp. coronata
Amorphageorgiana var.
georgianaAmorphageorgiana var.
georgiana
Cyprinella nivea
Cyprinella niveaHaliaeetus
leucocephalus
L i n c o l nL i n c o l nC o u n t yC o u n t y
G e o r g i aG e o r g i a
E d g e f i e l d C o u n t yE d g e f i e l d C o u n t yS o u t h C a r o l i n aS o u t h C a r o l i n a
C o l u m b i aC o l u m b i aC o u n t yC o u n t y
G e o r g i aG e o r g i a
M c D u f f i eM c D u f f i eC o u n t yC o u n t y
G e o r g i aG e o r g i a
W a r r e nW a r r e nC o u n t yC o u n t y
G e o r g i aG e o r g i a J e f f e r s o nJ e f f e r s o nC o u n t yC o u n t y
G e o r g i aG e o r g i a
R i c h m o n dR i c h m o n dC o u n t yC o u n t y
G e o r g i aG e o r g i a
M c C o r m i c kM c C o r m i c kC o u n t yC o u n t y
S o u t h C a r o l i n aS o u t h C a r o l i n a
0 2 41 Miles
CCCBN Total Length: 220 MilesCore Sections
Connector
Inner Loop
Outer Loop
Lateral
Edgefield County Connector
Lincoln County Connector
McCormick County Connector
McDuffie County Connector
Richmond County Connector
#0 Stimulus
Flood ZoneZone A - No base flood elevations determined
Zone AE- Base flood elevations determined
Floodway
Shaded X - Areas of the 0.2% annual chance flood
X Zone - Areas outside the 0.2% annual chance flood
Main Roads
Roadways
Railroad
City Boundaries
Fort Gordon Ê
10‐14‐10 Page 33
3.6 Historic and Cultural Resources
3.6.1 – Historic Overview
The history of Columbia County dates back to the year 2,750 B.C. when the area’s first residents settled
on Stalling’s Island, located in the eastern corner of the county. These early settlers were a group of
shell‐mound builders and the area they settled is listed on the National Register of Historic Places due to
its archaeological significance. The first European settlers to arrive in Columbia County during Colonial
times were a small group of Quakers who came from the Carolinas. They purchased land from the Uchee
Indians in 1751, but remained in the area for only a short time. During the 18th century, that area of the
county was within the territory known as St. Paul’s Parish. In 1790, Columbia County was officially
created from a part of Richmond County. It was named in honor of Christopher Columbus.
Most settlers arriving in the area during the late 1700s hailed from the Virginias and Carolinas. Cotton
reigned supreme as the chief crop in the area and afforded local settlers much prosperity. The Civil War
significantly impacted the area and contributed to the loss of many of Columbia County’s finest citizens,
much of its wealth, and the majority of its national political power. In the years that followed, the
county focused on expansion of the Augusta Canal and new rail lines to serve the southeast as it tried to
rebuild in the aftermath of the war.
During the 20th century, one of the most significant impacts on the county was the establishment in
1941 of the Camp Gordon military base (now Fort Gordon) in the southeastern portion of the county. As
a result of the military presence in the area, no longer was farming the primary occupation in the
county. Many residents retained their farms but pursued public jobs during World War II. Similarly,
many of the men and boys who went off to war returned home to seek occupations other than farming.
The construction of the Clark’s Hill Dam in 1946, and subsequent construction of the Atomic Energy
Commission’s Savannah River nuclear plant in nearby Aiken County, also fueled new job growth in the
area. Throughout the 1950s‐ 1960s Columbia County became an ever‐expanding bedroom community;
and with the new residents came national retail chains and modern shopping centers, particularly in the
Martinez area.
The Columbia County Historical Society, once active in promoting awareness of the county’s historic, is
now largely defunct. The City of Grovetown operates the Grovetown Museum which opened in 2000.
The Grovetown Museum presents exhibits and orchestrates displays on Grovetown’s history. The City of
Harlem operates the Laurel and Hardy Museum of Harlem Georgia because Oliver Hardy was born in
Harlem. The museum contains movies, exhibits, and memorabilia associated with Laurel and Hardy and
their comedic work. Responding to current growth pressures in the area, County residents have
expressed interest in an intensified approach to preservation, but current efforts remain on a case‐by‐
case basis.
The City of Harlem initiated a Historic Resources Survey in 2003. As a result of this survey the City has
created a locally designated historic district surrounding North Louisville Street downtown, including
both commercial and industrial properties. The City of Harlem also has a historic preservation ordinance
10‐14‐10 Page 34
that aims to preserve the community’s identity and historic character. The Historic Preservation
Ordinance established the Harlem Historic Preservation Commission, which oversees the design review
process for the historic district. In conjunction with its historic preservation efforts, the City of Harlem
has developed design guidelines for new development or renovation within the historic district.
3.6.2 Current Historic and Cultural Findings
In order to comply with Section 106 of the National Historic Preservation Act of 1966, the CCCBN
consulted with the Georgia Historic Preservation Division of the Department of Natural Resources
regarding the effect of the 200 mile fiber optic project on historic resources. In a letter dated May 27,
2010, the State Historic Preservation Office (SHPO) indicated that the fiber optic project would not
affect historic and/or archaeological resources on the route.
The project also includes 5 new communications towers to improve public safety coverage and facilitate
additional fixed and mobile wireless broadband services to citizens throughout the county. Property to
be used for the project is county‐owned containing some type of county‐owned facility. Pre‐fabricated
above‐ground equipment buildings will be constructed next to the tower. Approximate building
dimensions are 10 feet x 15 feet (single story). The concrete pad which will comprise the foundation for
the tower can be assumed to be approximately 40’ wide x 40’ long x 6’ in depth. Compounds will be
fenced. Land on which the towers will be located is pre‐disturbed and pre‐developed. The towers will
be 300 feet above ground level (AGL).
Towers to be constructed for the BTOP program will be located at the following address and coordinates in
Columbia County:
ADDRESS LATITUDE LONGITUDE PARCEL #
480 White Road, Harlem, GA 33 deg 24’ 20” N 82 deg 17’ 20” W Parcel 043A020
6868 Cobbham Road, Appling GA 33 deg 36’ 37” N 82 deg 19’ 32” W Parcel 025 047
590 Baker Place Road
Grovetown, GA
33 deg 29’ 17” N
82 deg 14’ 13” W
Parcel 051 001B
962 Halali Farm Road, Evans, GA 33 deg 34’15” N 82 deg 10’ 7” W Parcel 065 021
2292 County Camp Road, Appling,
GA
33 deg 32’ 14” N 82 deg 18’ 32” W Parcel 028 057
In compliance with Section 106 of the National Historic Preservation Act of 1966 (as amended), a records
review was conducted at the Georgia Historic Preservation Division (SHPO), the Georgia Natural,
Archaeological, and Historic Resources GIS (NAHRGIS), the National Register Information Systems web
site and the Georgia Archaeological Site Files to identify resources listed in the National Register of Historic
Places (NRHP), eligible properties, state‐surveyed historic resources, and archaeological sites within a 0.75‐
mile radius of the proposed project. Historic and archaeological findings are discussed below.
10‐14‐10 Page 35
480 White Road
Archaeology: An online review was of the National Register of Historic Places (NRHP) indicated that there
are no NRHP‐listed archaeological sites within the project APE. According to the Georgia Archaeological
Site File, there are no archaeological sites located within a one‐mile APE of the proposed tower.
Historic Structures: Resource 4923 is located on the north side of US 78 2,300 feet northeast of the
proposed tower. It is a c. 1900 one room commercial building which was recommended eligible for listing
on the NRHP in a 1991 survey. During the 2010 Section 106 survey, the resource was found to be
dilapidated and considered not eligible for the NRHP.
6868 Cobbham Road
Archaeology: An online review was of the National Register of Historic Places (NRHP) indicated that there
are no NRHP‐listed archaeological sites within the project APE. According to the Georgia Archaeological
Site File, there are no archaeological sites located within a one‐mile APE of the proposed tower.
Historic Structures: Resource 4886 is located on the north side of Cobbham Road, approximately 800 feet
northeast of the proposed tower site. This resource was identified as a circa 1920 Gabled wing cottage
with no academic style with a T‐plan shape. This resource was identified as possibly meeting the National
Register criteria in a 1991 survey. A 2010 survey determined that the resource appeared to have
maintained significance in materials; however, an ell may have been added to the older central hall house,
thus causing it to lose its significance in design.
590 Baker Place Road
Archaeology: According to the Georgia Archaeological Site File, there are two archaeological sites and one
report located within the 0.75‐mile APE of the proposed tower. The sites are 9CB169 and 170. The report
is 4333. No NRHP determination was made for the sites.
Historic Structures: Based on research at the Georgia Historic Preservation Division and NAHRGIS, as well
as the NRHP website, there are no NRHP‐listed resources and no state surveyed resources located within
the 0.75‐mile APE for visual effects. No historic or archaeological resources eligible for the National
Register of Historic Places were encountered during the file review and field work
962 Halali Farm Road
Archaeology: An online review was of the National Register of Historic Places (NRHP) indicated that there
are no NRHP‐listed archaeological sites within the project APE. A file review of the Georgia Archaeological
Site File indicated there are eight archaeological sites and six reports located within the one‐mile APE of
the proposed tower.
Historic Structures: Resource 4802 is located on Halali Farm Road approximately 2,000 feet south of the
proposed tower site. The house is a c. 1935 Georgia House with Colonial Revival elements and was
recommended eligible for listing on the NRHP in a 1991 survey.
10‐14‐10 Page 36
2292 County Camp Road
Archaeology: A file review was conducted by the staff of the Georgia Archaeological Site File to determine
if there are any archaeological sites located within a 1‐mile radius of the proposed project site. According
to the Georgia Archaeological Site File, there are two archaeological sites located within the 0.75‐mile APE
of the proposed tower. The sites are 9CB169 and 170. No NRHP determination was made for the sites.
Historic Structures: The NRHP‐listed Columbia County Courthouse (80536) is located approximately 4,700
feet northwest of the proposed tower just outside of the 0.75 mile APE. This Italianate structure was
constructed by John Trowbridge in 1856. It is a brick bearing two story structure with flat and arched
windows and decorative Italianate brackets and appears to be in excellent condition. State surveyed
resources included 4843, an eligible c. 1940 free standing rectangular commercial building located 1,000
feet south of the proposed tower; 4845, an eligible c.1925 double tower church with a Latin cross plan
located on the west side of US 221 approximately 2,500 feet northwest of the proposed tower; and the
following structures which make up the city of Appling: 4846, 4847, 4848, 4849, 4950, 4851, 4852, 4854,
4855, 4856 which are within approximately 4,000‐5,000 feet northwest of the proposed tower. Appling is
made up of front gable Bungalows, and American Small House, the NRHP listed courthouse, and free
standing commercial buildings. The majority of the resources were recommended eligible for listing on the
NRHP in a 1991 survey. A 2010 survey indicated that the resources would be contributing to a historic
district.
Fiber Optic Line
With regard to historic properties connected with the 200‐mile fiber optic line, Columbia County has
found four listings on the National Register of Historic Places. These four sites are as follows:
Columbia County Courthouse, Appling
Kiokee Baptist Church, Appling
Stallings Island (located within the Savannah River)
Woodville (private residence, Winfield area)
As an additional resource for researching historic properties and locations, the document “Columbia
County Growth Management Plan Update – Community Assessment” (dated 2005) was reviewed and
consulted. This report references an inventory of historic resources in the county. This report contained
a list of 28 sites that were deemed “possible” to be included on the National Register of Historic Places.
These sites included:
1. “The Cedars,” c. 1885
2. Macedonia Baptist Church, c. 1880
3. Evans School Dormitory, c. 1900, corner of Belair and Washington
roads
4. Evans School Arch and Columns, c. 1925, corner of Belair and
Washington roads
5. G.B. Lamkin House, c. 1925, west side of Belair Road, 2nd building
10‐14‐10 Page 37
south of Peachtree
6. “Cedar Hill.” c. 1820
7. Old Washington Road
8. Damascus Baptist Church, c. 1900, north side of Ridge Road, 1 mile
east of Washington Road
9. Dunns’ Chapel, c. 1890, northwest corner of GA 47 and Ridge Road
10. Winfield Area, c. 1840
11. Sharon Church, 1869, south side of GA 150 across from
intersection of Winfield Road
12. William Few house site, c. 1930
13. Shiloh Church, c. 1857, east side of GA 150, 1.5 mile southwest of
Winfield Road
14. Cedar Dale, c. 1858, east side of GA 150, 2 miles north of Cobbham
Crossroads.
15. Woodville, c. 1814
16. Old Kiokee Church, c. 1804, west side of GA 47, ¼ mile north of US
221
17. Appling Community (multiple sites, c. 1850‐1925)
18. Shucraft Road House, c. 1890
19. Columbia Road at Hereford Farm Road, c. 1870
20. Plantation House on Columbia Road, c. 1830
21. Columbia Road, c. 1790
22. Otts House, c. 1865, south side of Wrightsboro Road, ¾ mile west
of US 221
23. Wrightsboro Road, c. 1815
24. Magruder Home, c. 1810
25. Grovetown (multiple sites along Robinson Avenue)
26. The Dodge House, c. 1910
27. Campania
28. Harlem (multiple sites, c. 1850)
[Source: Columbia County Historic Resource Survey Report, Griffith Lamkin Polatty,
December 5, 1990; Georgia Department of Natural Resources, Historic Preservation
Division]
As part of the environmental assessment requirements for the Georgia Historic Preservation Division, an
Environmental Review Form was prepared and submitted (contained in Appendix 7). Part of the effort
required to complete this form was an investigation of all buildings in Columbia County that are 50 years
of age or older (a complete list of all 50‐year old buildings is included in Appendix 7). Working with the
county’s GIS and property records departments, a list of 50‐year old properties was developed and
cross‐referenced to the scope of the project. This effort yielded a list of 6 buildings that are over 50
years old and which will also be connected to the Broadband network. These buildings make up the
“Area of Potential Effect” (APE) and can be summarized as follows:
10‐14‐10 Page 38
Parcel Title Owner Year
Built
Effective
Year
Built
Description EW
Description
Property
Use
Property
Address
G06
073
Grovetown
Museum
City of
Grovetown
1935 1980 1.5 story Vinyl
Dwelling
Vinyl Siding Resid.
Finish –
Office,
General
Govt.
103 Old
Wrightsboro
Rd
H02
036
Harlem
Library
City of
Harlem
1930 1970 1 story Vinyl
Library
Vinyl Siding Resid.
Finish
375 N.
Louisville St
H03
073
Harlem
Middle
School
Columbia
County
Board of
Education
1935 1983 School
Auditorium
Face Brick
Veneer
Elem.
and Sec.
School
375 W
Forrest St.
H03
157
Harlem
Police Dept
City of
Harlem
1950 1971 Old City Hall /
Jail
Face Brick
Veneer
Office,
General
Govt.
and jail
180 N
Louisville St
026
017
North
Columbia
Elem.
School
Columbia
County
Board of
Education
1956 1990 North
Columbia
School
Face Brick
Veneer
Elem.
and Sec.
School –
Gym.
2874 Ray
Owens Rd
072
143
Evans
Elem.
School
Columbia
County
Board of
Education
1956 1985 Evans
Elementary
Com Brick
on Concrete
Block
Elem.
and Sec.
School –
Gym.
628 Gibbs
Rd
All of these buildings are functioning buildings which contain ongoing county business, and are
referenced in the Georgia Historic Preservation Division’s Environmental Review Form as the “Area of
Potential Effect” (APE). Photographs for all 6 of these buildings are included below:
10‐14‐10 Page 39
Grovetown Museum:
10‐14‐10 Page 40
Grovetown City Hall area:
10‐14‐10 Page 41
Harlem Library:
10‐14‐10 Page 42
Harlem Library:
10‐14‐10 Page 43
Harlem Middle School:
10‐14‐10 Page 44
Harlem Middle School Area:
10‐14‐10 Page 45
Harlem Police Department:
10‐14‐10 Page 46
Downtown Harlem area:
North Columbia Elementary:
10‐14‐10 Page 47
10‐14‐10 Page 48
North Columbia Elementary area:
10‐14‐10 Page 49
Evans Elementary:
10‐14‐10 Page 50
Evans Elementary area:
10‐14‐10 Page 51
Research into tribal cultural properties indicates there are no Indian reservations or tribal lands within
the Columbia County Community Broadband Network or within Columbia County in general. A map
indicating Federal Lands and Indian Reservations in the State of Georgia can be found at
www.nationalatlas.gov and is located in the appendices. Archaeologist David Saunders, Eastern
Regional Office, Bureau of Indian Affairs, has confirmed the finding that no reservations or tribal lands
are located within Columbia County.
Tribal information for the 5 towers was obtained from NTIA. The Shawnee Tribe has indicated interest
in the 5 towers and has requested further information. The Form 620 and SHPO responses were
forwarded to the tribe.
3.7 Aesthetic and Visual Resources
Columbia County borders on the Clarks Hill Lake, which is a man‐made lake controlled and administered
by the US Army Corps of Engineers. The project will not impact the shoreline or viewshed of the Clarks
Hill reservoir. The county contains one state park (Mistletoe State Park) and one county park (Wildwood
Park). Wildwood Park is leased by the county on land owned by the Corps of Engineers. The project
will include a new fiber optic cable route into Wildwood Park.
3.8 Land Use
Columbia County has mixed land use including varying degrees of the following: Commercial, Industrial,
Office/Professional, Governmental, Recreation, State and Federal Highways. Most of the acreage of the
county still consists of undeveloped land, which is designated to remain undeveloped in future land use
plans. The southern tip of the county contains part of Fort Gordon, a US Army post (which
predominantly lies in Augusta/Richmond County). The northern part of the county borders on Clarks Hill
reservoir (US Army Corps of Engineers).
The county contains two incorporated cities, Harlem and Grovetown. It also contains the census‐
designated places of Evans and Martinez, which border the metropolitan Augusta GA area. Although
not an incorporated city, the County Seat of Columbia County is Appling. However the Columbia County
government is based in Evans.
3.9 Infrastructure
Columbia County has a mixture of county‐owned and other infrastructure in place. The county is
bisected from east to west by Interstate 20. There are several state highways present throughout the
county. The county maintains a public water system primarily in the more populated areas of Evans and
Martinez. The cities of Grovetown and Harlem maintain their own water systems. The major
commercial utilities present in the county are Georgia Power (a division of the Southern Company),
AT&T (formerly BellSouth), Comcast, Charter, and Knology. Wireless carriers include AT&T, Verizon, T‐
Mobile, and Sprint. The objective of the CCCBN project is to enhance and improve the existing
telecommunications infrastructure provided by the existing carriers.
10‐14‐10 Page 52
3.10 Socioeconomic resources
The estimated population for Columbia County for 2008 is 108,276, according to US Census figures
(http://factfinder.census.gov). Racial population demographics are estimated as follows:
White 78.7%
Black or African American 14.5%
American Indian or Alaska Native 0.2%
Asian 3.3%
Native Hawaiian and other Pacific Islander 0.0%
Other Race 1.3%
Two or more races 2.0%
Hispanic or Latino (of any race) 3.2%
Other demographic information is as follows:
Male 48.4%
Female 51.6%
Median Age 35.9
Under 5 years 7.1%
18 years and over 72.7%
65 years and over 9.1%
Generally speaking the areas in the north and east areas of the county, including Evans and Martinez,
tend to be higher‐income areas. The lower income areas tend to be in the southern and western parts
of the county. These include some areas in and around the cities of Harlem and Grovetown. The
application which requested the ARRA Broadband stimulus funding identified several areas which are
considered “unserved” and “underserved” for the areas of Broadband availability. All of the unserved
areas were found to be in the Harlem and Grovetown areas, as were several of the underserved areas.
3.11 Human Health and Safety
Per the map obtained from the EPA’s website (http://iaspub.epa.gov/Cleanups/), Columbia County finds
there are no Brownfield or Superfund/RCRA clean‐up sites, as shown in the graphic below. There are
also no sites in Columbia County which are contained on the National Priorities List ‐‐
(http://www.epa.gov/superfund/sites/query/queryhtm/nplfin.htm#GA).
10‐14‐10 Page 53
Chapter 4 ‐ Environmental Consequences
4.1 Noise
The area of construction is both rural and suburban in nature, and thus ambient noise levels vary. It can
be assumed that the higher noise levels in the construction areas will coincide with the corridors of state
and county roadways already in existence. All of the fiber optic construction will be located within the
traffic corridors and within the right of way of existing paved roads. The cable will be constructed using
specialized construction equipment designed for the purpose of installing buried and underground
cables. Typical noise levels from this type of equipment range from 70‐90 dBA. These noise levels will
be temporary in nature and will not significantly add to the ambient noise levels found along the road
corridors at present.
In the case of tower construction, similar parameters will apply. The towers will also be constructed
using specialized construction equipment designed for that purpose. They will not be constructed on
right of ways, but will be constructed on county‐owned property parcels adjacent to and accessible via
state and county roadways. Noise levels attributed to tower construction will also be minor and
temporary in nature and will not significantly add to the ambient noise levels found in these properties
at present.
4.2 Air Quality
The construction will take place using specialized, mechanized equipment (backhoes, trenchers, plowing
rigs, directional bore machines, cranes, etc.) whose exhaust will be released into the surrounding air, but
the construction of the fiber optic cable and towers will not cause a detrimental effect on the existing air
quality of Columbia County. The construction will be concentrated within or near the existing road
corridors which already have the presence of automobiles and trucks; the additional exhausts from the
construction equipment will not have a significant additive effect or potential detrimental effects.
4.3 Geology and Soils
Since the construction will take place within right of way of existing roadways, as well as county‐owned
land parcels that have been previously disturbed, the project will have no impact on prime or unique
farmlands, as defined in the Farmland Protection Policy Act (FPPA).
A large degree of the construction of the fiber optic cable will be via underground placement.
Construction techniques include direct burial, trenching, plowing, directional boring, and micro‐
trenching. All construction will take place within the right of way of existing roadways in pre‐disturbed
areas. Soil disturbances using these methods will be minor and temporary in nature. Trench
dimensions will vary, but can be nominally summarized as 36” maximum depth, with 12” maximum
width. Open trenches will not be left for extended periods of time. Trenches and other ground
openings will be backfilled with the existing soil types initially removed.
10‐14‐10 Page 54
Tower foundations will require excavations to depths to be determined by a variety of factors. The
structural design of the towers will specify the detailed requirements of the excavations and backfills.
Tower foundations will be secured using reinforced concrete below grade. All towers will be erected on
county‐owned land parcels which have been previously disturbed.
4.4 Water Resources
The Columbia County Community Broadband Network will be constructed in previously‐disturbed
roadway rights‐of‐way. All wetlands crossed by the network are taken from National Wetland Inventory
location data. All proposed tower sites will be constructed on county‐owned high ground for maximum
signal propagation, well above any wetland areas.
Since the fiber optic construction will take place in the right of way of existing roadways, the fiber will
occasionally cross streams and creeks. In the overwhelming majority of such cases, these crossings will
take place using directional boring techniques. When directional boring is used, the bore pits will be set
outside the waterway boundaries and the depth of the bore will be such that the stream bed will be
crossed underneath at such a depth as to not impact the waterway.
In rare instances, it is possible that “aerial inserts” may occasionally be used for stream crossings. In an
aerial insert, new poles would be installed on both sides of the stream or creek buffer zone, and aerial
plant installed between the new poles, over the waterway. The insert poles would be set outside the
stream beds and waterway boundaries, thereby insuring that the waterways will not be adversely
impacted by these construction techniques.
Both techniques for crossing waterways are widely used for cable construction projects of this type and
are frequently permitted by federal, state, and local permitting bodies. The USACE has indicated a
willingness to coordinate easements required for installation of the fiber optics on Thurmond Project
lands. Coordination is planned between the USACE, Georgia EPD, and the CCCBN to expedite permitting
regarding wetlands, Corps Property and stormwater runoff.
The US Army Corps of Engineers (USACE), Savannah District, was contacted regarding the CCCBN project
and its effect on Corps Property. The USACE indicated that the broadband network would allow for
services to be porvided to the public that have not been readily available and would allow the Corps to
better coordinate public safety and law enforcement services. The Corps indicated a willingness to
coordinate easements required for installation of the fiber optics on Thurmond Project lands (see
Appendix 5). An email dated July 20, 2010 from Senior Project Manager Stanley J. Knight, indicated that
the project will more than likely require a Department of Army Permit. CCCBN personnel have
requested a meeting with USACE personnel to set up a pre‐construction pre‐application consultation
meeting to expedite the permitting process. In addition, CCCBN personnel have met with USACE
personnel at some of the locations where fiber and termination points will be placed on Corps Property.
In addition, the USACE Savannah District has announced that expedited permitting in the form of
Regional General Permits (RGP) will be approved for projects funded under the American Recovery and
10‐14‐10 Page 55
Reinvestment Act (ARRA) that meet all requirements of the Clean Water Act and the National
Environmental Policy Act. To use a regional permit, an applicant must receive approval from the Corps
verifying that the project meets the requirements of the RGPs and must obtain separate individual
Water Quality Certification from Georgia EPD. The CCCBN intends to obtain approval from both the
Corps and EPD.
A National Pollution Discharge Elimination System (NPDES) permit for Storm Water Discharges
associated with construction activities will be sought from the Environmental Protection Division of the
Georgia Department of Natural Resources (see Appendix 5). All construction contractors will be
required to abide by the State of Georgia’s Best Management Practices rules and regulations.
Contractors will be required to attend and receive a Georgia Soil and Water Conservation Fundamentals
Level 1A certification. Information on the certification can be found at
http://www.files.georgia.gov/SWCC/Files/Education%20and%20Certification%20Policies%20and%20Pro
cedures.pdf. Guidelines can be found at the Georgia Soil and Water Conservation Commission,
http://www.gaepd.org/Files_PDF/techguide/esc_manual/Chapter_6.pdf and
http://www.gaswcc.org/docs/ag_bmp_Manual.pdf.
4.5 Biological Resources / Critical Habitats
The fiber route will be constructed on pre‐disturbed roadways, and all proposed tower sites are on
existing pre‐developed County property. Section 3.5 included a map from the US Fish and Wildlife
Service showing that no critical habitats are located in Columbia County. The fiber project will have no
impact on species listed. The CCCBN has received concurrence in this regard from the USFWS; however
the USFWS has requested stipulations regarding migratory birds on the 5 towers in Columbia County.
The CCCBN has agreed to the stipulations and will implement them to minimize effects of the towers on
migratory birds. These USFWS practices will be put into place during and after tower construction. The
towers planned for this project will be 300‐foot self‐support towers, therefore bird diverters are not
applicable. In addition, specifications will require that the lights for the towers will be white in color and
operating for 3 second off periods between flashes, as requested by the US Fish and Wildlife office. A
copy of the correspondence received from the US Fish and Wildlife Office is included in Appendix 6.
4.6 Historic and Cultural Resources
According to a Program Comment for Streamlining Section 106 Review for Wireless Communication
Facilities Construction and Modification Subject to Review Under the FCC Nationwide Programmatic
Agreement and/or the Nationwide Programmatic Agreement for the Collocation of Wireless Antennas
issued by the Advisory Council on Historic Preservation (Federal Register /Vol. 74, No. 223 / Friday,
November 20, 2009): When an NTIA undertaking includes both communications facilities construction or
modification covered by the FCC Nationwide PA or Collocation PA and components in addition to such
communication facilities construction or modification, RUS, NTIA, or FEMA, as applicable, will comply
with Section 106 in accordance with the process set forth at 36 CFR 800.3 through 800.7, or 36 CFR
800.8(c), or another applicable alternate procedure under 36 CFR 800.14, but will not have to consider
the effects of the communication facilities construction or modification component of the undertaking
10‐14‐10 Page 56
on historic properties. NTIA has applied this Program Alternative as stipulated in 36 CFR 800.14 (e) in
lieu of reviewing proposed telecommunications towers which are undergoing Section 106 review under
the FCC Nationwide Programmatic Agreement.
Additionally, in order to comply with Section 106 of the National Historic Preservation Act of 1966, the
CCCBN consulted with the Georgia Historic Preservation Division of the Department of Natural
Resources regarding the effect of the 200 mile fiber optic project on historic resources. The State
Historic Preservation Office (SHPO), in a letter dated May 27, 2010, indicated that the fiber optic project
would not affect historic and/or archaeological resources on the route. All 5 towers have received SHPO
concurrence indicating no effect on archaeological resources. Three of the 5 towers have received
concurrence letters of no effect or no adverse effect from the SHPO; however, there are two towers in
which an adverse effect is anticipated: Halali Farm Road and Cobbham Road (Appendix 7).
6868 Cobbham Road
Resource 4886 is located on the north side of Cobbham Road, approximately 800 feet northeast of the
proposed tower site. In a letter dated July 19, 2010 the Georgia SHPO determined that the tower would
have an adverse effect on Resource 4886 (Appendix 7).
962 Halali Farm Road
Resource 4802 is located on Halali Farm Road approximately 2,000 feet south of the proposed tower site.
In a letter dated July 19, 2010 the Georgia SHPO concurred that the tower would have an adverse effect on
the resource (Appendix 7).
A summary of SHPO responses can be found in the table below:
TOWER SHPO DETERMINATION
480 White Road, Harlem, GA 30814 No Adverse Effect
6868 Cobbham Road, Appling GA 30802 Adverse Effect on Resource
590 Baker Place Road
Grovetown, GA
No Effect
962 Halali Farm Road Adverse Effect on Resource
2292 County Camp Road No Adverse Effect
In summary, there are two towers in which an adverse effect is anticipated, Halali Farm Road and
Cobbham Road, based on the SHPO correspondence (Appendix 7). The Georgia SHPO has indicated a
willingness to engage in mitigation regarding these towers. To that end, an Memorandum of Agreement
(MOA) was written and submitted to the Georgia SHPO. The Georgia SHPO’s mitigation project
involves research on resources that have become 50 years of age or older since the last survey was
conducted in the county. Tax assessors information will be field checked for dates of construction in a
corridor along Route 221/47 north of Harlem to the intersection with Ray Owens Road to the county
line/lake, a distance of approximately 14 miles, with an Area of Potential Effect (APE) of one mile on
either side of the highway. The MOA was accepted and signed by the Georgia SHPO, the FCC, and
10‐14‐10 Page 57
Columbia County. An FCC Environmental Assessment and the signed MOA for the adverse effect towers
is included in the appendix as an addendum.
Tribal information for the 5 towers was obtained from NTIA. The Shawnee Tribe indicated interest in
the 5 towers and requested further information. The Form 620 and SHPO responses were forwarded to
the THPO, who subsequently responded with no interest (see appendix).
Fiber Optic Line ‐‐ Of the buildings and structures referenced in Chapter 3, none are planned to be
connected to the new fiber optic network and will not be affected by network construction. The
Columbia County Courthouse is near the fiber route but will not be impacted by construction. It is in use
as an active government building, and currently has installed network connectivity devices. These will
be upgraded during project implementation to better serve county residents.
4.7 Aesthetic and Visual Resources
The project will not impact the shoreline or viewshed of the Clarks Hill reservoir. Mistletoe State Park
will not be impacted by the project, as the closest construction activity will be approximately 4 miles
away from the park. The project will include a new fiber optic cable route into Wildwood Park. The
Corps of Engineers has been consulted during the planning of the project; the Corps has given its
approval of the planned routes. The project will obtain all necessary permits from the Corps before
construction in Wildwood Park. The shoreline of the lake will not be impacted by construction.
Visual viewshed impacts on sensitive resources such as parks, waterways, trails, and scenic byways will
not occur. The fiber optic cable route will not traverse sensitive resources. The 5 Columbia County
towers associated with the project are not visible from sensitive resources and therefore have no
impact.
4.8 Land Use
The project will not result in any changes in the land use classification for any areas of the county. Since
all of the fiber optic cable will be installed in existing road rights‐of way, the land used for construction
will remained classified as “roads”. In the case of tower construction, the towers will be constructed on
county‐owned land parcels. The classification of these areas will remain “government/institutional”.
4.9 Infrastructure
The Columbia County Community Broadband Network project represents a marked improvement in the
county’s telecommunications infrastructure. The telecommunications infrastructure will be significantly
improved by the installation of fiber optic network into areas of the county which are unserved and
underserved. The new communications towers will result in improved wireless coverage for public
safety and mobile broadband providers.
The project will not have an adverse effect on any of the existing power, natural gas, waste disposal, or
water infrastructure present in the county. Experienced engineers will design the project in such a way
as to avoid conflict with and disruption of existing infrastructure. All required permits will be obtained
10‐14‐10 Page 58
during the engineering phase of the project. The engineers will provide inspectors for all construction
crews in order to insure that the new facilities are installed properly without disruption to existing
utilities.
4.10 Socioeconomic resources
One of the stated goals of the project is to improve the broadband services available to underserved and
unserved areas of the county’s population. These areas tend to coincide with the lower‐income areas of
the county, many of which contain minority populations. For this reason it is anticipated that the
project will have a very positive impact for these groups. No detrimental effects are anticipated from
the project, which is expected to spur economic growth opportunities throughout the county.
Completion of the proposed project will have a dramatically positive effect on the socioeconomic status
of Columbia County and its citizens. In the near term, it will result in increased jobs resulting from the
construction of the network. The construction will take place over an approximate two‐year interval.
The grant application estimated that a total of 195 jobs would be created as a result of the construction
of the network.
The long‐term socioeconomic impact of the project will be even more beneficial to the county. To a
great extent, it is for the long‐term benefit to the county that the project was envisioned and
implemented. Establishing a fiber optic broadband network throughout all areas of the county will
provide infrastructure that can be used to attract a high‐tech workforce. This is expected to result in
hundreds of additional jobs as new employers will be attracted to Columbia County. The grant
application had numerous letters of support, including a letter from the Columbia County Development
Authority, the organization charged with advancing commerce and industry within the county. The
letter states, “reliable broadband service and access is vital for business growth – growth that can lead
to greater employment opportunities for residents in the county and to an increased level of capital
investment in the county.” It also states, “the need for broadband will become critical to the county’s
economic survival”.
4.11 Human Health and Safety
The County contains no hazardous waste sites, Superfund sites, or brownfield sites. The project will not
create any such sites. By following existing rights‐of‐way and building towers on existing developed
County property, Columbia County research indicates no pollutant issues will appear with the project.
The project will require extensive use of heavy equipment to install the fiber optic cable along roadways
and to install towers on county‐owned properties. The cable construction will take place within the
existing rights‐of‐wayof existing roads. Construction is typically concentrated in the outermost 5 feet of
the right‐of‐way, away from the roadway traffic.
Safety will be a primary concern for all parties associated with the construction. This includes
construction engineers, construction crews, construction inspectors, and all personnel involved in the
construction process. In today’s business environment, engineering and construction companies place
10‐14‐10 Page 59
an extraordinary amount of emphasis on training workers in adequate safety programs. Proper safety
techniques will be used in all aspects of the construction. Contractors typically have their own Safety
Manual and hold regular “tailgate meetings” to insure that workers are adequately trained in safety.
These safety techniques insure that workers as well as the general public are protected from any
potentially dangerous consequences from the construction.
In addition to safety procedures, contractors must be properly licensed in order to perform certain
construction activities. For example, any contractors wishing to install underground facilities below a
depth of 5 feet must have a Utility Construction license which demonstrates that they are adequately
trained and insured for such activities.
There are no known health issues associated with a distribution system for fiber optic cable. It does not
give off any electromagnetic field and collocated fiber optic lines do not interfere with each other. Fiber
optic cable does not interfere with other utility transmission lines, such as telephone, cable, and electric
distribution. It is expected that all workers installing cable would adhere to construction safety
procedures and the appropriate traffic and roadside safety practices would be implemented.
The construction contractors will provide for a prompt rescue plan of employees in the event of a fall or
shall assure that employees are able to rescue themselves. The contractor employees must be prepared
to retrieve a fallen worker within minutes. The contractor must ensure employees being exposed to
elevations above 6 feet use and maintain 100% fall protection systems compatible with the tasks
assigned.
Tower workers responsible for rigging must be able to provide documented proof of rigging training
including an understanding of slings, blocks, reeving, strength calculations, winches, hydraulics, tagging,
riding the winch line and rigging hardware. In addition, safety standards and procedures mandated by
the Occupational Safety and Health Administration (OSHA) and the GADOT will be applied to this work.
For these reasons there are no expected detrimental effects anticipated regarding the Human Health
and Safety of the County.
10‐14‐10 Page 60
Chapter 5 ‐ Applicable Environmental Permits and Regulatory Requirements
Consultation has been sought from the following Federal, state, and local agencies:
US Army Corps of Engineers
US Fish and Wildlife Service
Tribal Historic Preservation Officer
Georgia State Historic Preservation Office
Georgia Environmental Protection Division
The following table indicates the applicable permitting and regulatory requirements, the regulatory
agency involved, the status of the project compliance, and further action.
Regulatory Agency Permitting/Regulatory
Requirements Description Status Further Action
US Army Corps of
Engineers Department of Army
Permit Permitting for
wetlands, Corps
Property
USACE notified Obtain RGP permit in
conjunction with State
EPD US Fish and Wildlife
Service Section 7 Consultation Consultation
regarding effect of
fiber optics and
towers on Threatened
and Endangered
Species and Critical
Habitats
Response received
from USFWS. No T&E
species will be
affected by the fiber
optic route. USFWS
recommends
selfsupport tower
type and specific
lighting to minimize
effects to migratory
birds.
The only remaining further action is to install medium intensity strobes on the towers at the time of construction, per the USFWS request to minimize effects to migratory birds.
Tribal Historic
Preservation Officer Tribal Consultation
required through Section
106 of NHPA
Consultation
regarding effect of
fiber optics and
towers on areas of
tribal significance.
Shawnee Tribe
requests Form 620
and SHPO response
on the 5 towers.
These documents will
be forwarded to the
Shawnee.
Concurrence letter
received. No further
action.
Georgia State Historic
Preservation Office Historic preservation
and archaeological
resources through
Section 106 of NHPA
Consultation
regarding effect of
fiber optics and
towers on areas of
historic and
archaeological
significance.
Georgia SHPO
indicates fiber optic
project will have no
effect on historic
resources. Regarding
5 towers, adverse
effect on two towers:
Halali Farm Road and
Cobbham Road.
Mitigation on Halali
Farm and Cobbham
Road. FCC
Environmental
Assessment and signed
MOA for the adverse
effect towers is included
in the appendix as an
addendum.
Georgia Environmental
Protection Division NPDES permit Consultation
regarding effect of
fiber optics and
towers on stormwater
runoff.
Georgia EPD notified
regarding Stormwater
NPDES permit for
Storm Water
Discharges
Obtain NPDES permit
10‐14‐10 Page 61
The preferred alternative will build fiber optic cable within the right‐of‐way of existing roadways, and to
build communications towers on previously developed county‐owned property parcels. These activities
present the best solution to meet the needs and problems of the project, and they are not anticipated
to adversely affect the environment.
10‐14‐10 Page 62
Chapter 6 ‐ List of Preparers
Lewis Foster
Broadband Utility Manager
Columbia County Board of Commissioners
PO Box 498
630 Ronald Reagan Drive, Building A
Evans, GA 30809
Mary Howard, GISP
GIS Manager
Columbia County Board of Commissioners
630 Ronald Reagan Drive, Building B
Evans, GA 30809
Mike Martin, P.E.
Engineering Associates, Inc.
1220 Old Alpharetta Rd, Suite 390
Alpharetta, GA 30022
S. Lorraine Norwood, MA
Terracon Consultants, Inc.
2855 Premiere Parkway, Suite C
Duluth, GA 30097
10‐14‐10 Page 63
Chapter 7 ‐ References
The following websites were consulted for this Environmental Assessment:
Noise Pollution Clearinghouse: www.nonoise.org
Currently Designated Nonattainment Areas for All Criteria Pollutants:
http://www.epa.gov/air/oaqps/greenbk/ancl3.html
National Resources Conservation Service: http://soildatamart.nrcs.usda.gov/Default.aspx
Tapestry of Time and Terrain: Physiographic Regions:
http://tapestry.usgs.gov/physiogr/physio.html
US Fish and Wildlife Service, Migratory Birds:
http://www.fws.gov/migratorybirds/mbpermits.html
Ecoregions of North America:
http://www.epa.gov/wed/pages/ecoregions/na_eco.htm#Level%20I
American Fact Finder, US Census Bureau:
http://factfinder.census.gov/servlet/ACSSAFFFacts?_event=&geo_id=05000US13073&_geoCont
ext=01000US|04000US13|05000US13073&_street=&_county=columbia&_cityTown=columbia&
_state=04000US13&_zip=&_lang=en&_sse=on&ActiveGeoDiv=&_useEV=&pctxt=fph&pgsl=050
&_submenuId=factsheet_1&ds_name=null&_ci_nbr=null&qr_name=null®=null%3Anull&_ke
yword=&_industry=
US EPA, National Priorities List:
http://www.epa.gov/superfund/sites/query/queryhtm/nplfin.htm#GA
Wildwood Park Draft Environmental Assessment, US Army Corps of Engineers:
http://www.sas.usace.army.mil/Wildwood%20Park%20%20DRAFT%20EA%20%20Mar10.pdf
The following reports and documents were consulted:
Columbia County Growth Management Plan Update – Community Assessment (June 2005).
Prepared for the County by EDAW. Found on‐line at:
http://www.columbiacountyga.gov/Index.aspx?page=2976
10‐14‐10 Page 64
Appendix 1
Maps
10‐14‐10 Page 65
Appendix 2
Aerials
10‐14‐10 Page 66
Appendix 3
Georgia Technology Authority slide
7-23-10 Page 67
Appendix 4
Air Quality
��������� ������
�
�Appendix�5��Water�Resources����� �
Columbia County Community Broadband Utility (CCCBU)Broadband Master Plan and Countywide Floodplain
#0
#0
#0
#0
#0
M c C o r m i c k C o u n t yM c C o r m i c k C o u n t yS o u t hS o u t h
C a r o l i n aC a r o l i n a
L i n c o l nL i n c o l nC o u n t yC o u n t y
G e o r g i aG e o r g i a
E d g e f i e l d C o u n t yE d g e f i e l d C o u n t yS o u t h C a r o l i n aS o u t h C a r o l i n a
C o l u m b i aC o l u m b i aC o u n t yC o u n t y
G e o r g i aG e o r g i a
M c D u f f i eM c D u f f i eC o u n t yC o u n t y
G e o r g i aG e o r g i a
W a r r e nW a r r e nC o u n t yC o u n t y
G e o r g i aG e o r g i a
R i c h m o n dR i c h m o n dC o u n t yC o u n t y
G e o r g i aG e o r g i a
J e f f e r s o nJ e f f e r s o nC o u n t yC o u n t y
G e o r g i aG e o r g i a
0 2 41 Miles
CCCBU Total Length: 220 Miles
#0 Stimulus
MasterPlan Broadband
Flood ZoneZone A - No base flood elevations determined
Zone AE- Base flood elevations determined
Floodway
Shaded X - Areas of the 0.2% annual chance flood
X Zone - Areas outside the 0.2% annual chance flood
Main Roads
Roadways
Railroad
City Boundaries
Fort Gordon
Ê