columbia county community broadband network

111
DRAFT FINAL Broadband Technology Opportunities Program Award Number: NT10BIX5570037, Grant ID# 87 Columbia County Community Broadband Network Environmental Assessment October 14, 2010 Prepared by: Columbia County Board of Commissioners Broadband Utility Department Evans, GA Engineering Associates, Inc. Alpharetta, GA Terracon Consultants, Inc. Duluth, GA

Upload: others

Post on 17-Apr-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Columbia County Community Broadband Network

 DRAFT FINAL 

Broadband Technology Opportunities Program 

Award Number: NT10BIX5570037, Grant ID# 87 

 

Columbia County Community Broadband 

Network Environmental Assessment 

 

 

October 14, 2010 

 

 Prepared by: 

Columbia County Board of Commissioners 

Broadband Utility Department 

Evans, GA 

 

Engineering Associates, Inc. 

Alpharetta, GA 

 

Terracon Consultants, Inc. 

Duluth, GA 

    

Page 2: Columbia County Community Broadband Network

10‐14‐10  Page 1  

Table of Contents Executive Summary                  3 

Chapter 1 ‐ Purpose and Need                  5 

  1.1  Background and History               6 

  1.2  Geographic Setting and Need              9 

  1.3  Goals                    10 

Chapter 2 ‐ Proposed Actions                  11 

  2.1  Project Description                12 

    2.1.1  Overview                12 

    2.1.2  Construction                19 

  2.2  Alternatives                  20 

    2.2.1   “No Action” Alternative              20 

  2.3  Preferred Alternative                21 

  2.4  Alternatives Considered but Eliminated from Further Discussion      21 

    2.4.1   Leased circuit capacity from incumbent broadband providers    21 

2.4.2   Other alternatives investigated but deemed not to be viable    24   

Chapter 3 ‐ Existing Environment                26 

  3.1  Noise                    26 

  3.2  Air Quality                  26   

  3.3  Geology and Soils                26 

3.4  Water Resources                28 

  3.5  Biological Resources / Critical Habitats            29 

  3.6  Historic and Cultural Resources              32 

    3.6.1  Historic Overview              32 

    3.6.2  Current Historic and Cultural Findings          33 

3.7  Aesthetic and Visual Resources              52 

3.8  Land Use                  52 

3.9  Infrastructure                  52 

3.10  Socioeconomic Resources              53 

3.11  Human Health and Safety              54 

Chapter 4 ‐ Environmental Consequences              55 

  4.1  Noise                    55 

  4.2  Air Quality                  55 

  4.3  Geology and Soils                55 

4.4  Water Resources                56 

  4.5  Biological Resources / Critical Habitats            56 

  4.6  Historic and Cultural Resources              56 

4.7  Aesthetic and Visual Resources              57 

4.8  Land Use                  57 

4.9  Infrastructure                  57 

4.10  Socioeconomic Resources              58 

4.11  Human Health and Safety              58 

Page 3: Columbia County Community Broadband Network

10‐14‐10  Page 2  

Chapter 5 – Applicable Environmental Permits and Regulatory Requirements      60 

Chapter 6 ‐ List of Preparers                  62 

Chapter 7 – References                   63 

   

Page 4: Columbia County Community Broadband Network

10‐14‐10  Page 3  

 

List of Appendices                    69 

Appendix 1 – Maps 

Appendix 2 – Aerials 

Appendix 3 – Georgia Technology Authority slide 

Appendix 4 – Air Quality  

Appendix 5 – Water Resources 

Appendix 6 – Biological Resources / Critical Habitats  

Appendix 7 – Historic and Cultural Resources 

Appendix 8 – FAA forms 

Appendix 9 – Letters of Support 

Appendix 10 – List of Roads included in fiber optic project 

Appendix 11 – FCC Environmental Assessment for Cobbham Road and Halali Farm Road and 

Memorandum of Agreement for Cobbham Road and Halali Farm Road 

 

   

Page 5: Columbia County Community Broadband Network

10‐14‐10  Page 4  

Executive Summary 

 Overview 

This Environmental Assessment (EA) is being prepared for Columbia County, Georgia to fulfill the 

requirements of BTOP Grant #87, “Columbia County Community Broadband Network (CCCBN)”.  The 

project was awarded by the National Telecommunications (NTIA) in March 2010, during Round 1 of the 

American Recovery and Reinvestment Act (ARRA), Broadband Stimulus Funding.   

 

The EA reviews the impacts of the preferred route, use of additional wireless technology, an alternate 

route, use of disturbed and undisturbed property and a no action alternative to various aspects of the 

environment. Areas considered include: Noise, Air Quality, Geology and Soils, Water Resources, 

Biological Resources, Historic and Cultural Resources, Aesthetic and Visual Resources, Land Use, 

Infrastructure, Socioeconomic Resources and Health and Human Safety. 

 

The project will enhance broadband and wireless access in the community through the use of a 200‐mile 

“middle mile” fiber optic network and 5 wireless towers.   The network will also support 60 free wireless 

access points in parks and other public spaces, with a focus on low income areas.  

The network will establish an open access broadband platform that will be open to:  

 

1. Health Care Providers, including the Medical College of Georgia and local clinics;  

2. Educational Organizations including the school system, technical college and libraries;  

3. Public Service and Community Organizations;  

4. Local municipalities and utilities;  

5. Broadband Service Providers and Wireless Service Providers;  

6. Citizens in economically challenged neighborhoods through free community ―hot spots  

 

The fiber network will provide interconnection points for numerous areas which have been identified as 

both unserved and underserved.  The project also includes 5 new communications towers to improve 

public safety coverage and facilitate additional fixed and mobile wireless broadband services to citizens 

throughout the county. The network will initially be equipped with LAN and WAN networking equipment 

for use by anchor institutions.  The network will also provide dark fiber for the exclusive use of the users 

that need this capability.  

 

The fiber optic cable construction will take place along various existing rights‐of‐way and utility 

easements throughout the project area. The fiber will be installed using trenching, directional boring 

and aerial techniques.  Directional boring will be used in locations where surface disturbances must be 

minimized; such as central business districts within communities and under sensitive environmental 

locations such as wetland or stream crossings.  

 

The project has received overwhelming support from all county and city agencies, whose facilities will be 

connected as part of the project.  In addition to the approximately 150 facilities connected to the 

network, the Medical College of Georgia (MCG), the State’s flagship medical school, has plans to build a 

Page 6: Columbia County Community Broadband Network

10‐14‐10  Page 5  

data center in Columbia County. MCG has made its support of the project known in terms of in‐kind 

contributions and letters of support for the project.  

 

From an environmental standpoint, it is important to note that all planned construction activities fall 

within two specific parameters recognized as important for environmental assessment review: 

 

1) All communications towers will be constructed on county‐owned land parcels which are 

“previously disturbed” and “previously developed”.  No pristine or undeveloped lands will be 

affected by the tower construction.   

2) All fiber optic cable construction will take place within previously disturbed rights‐of‐way of 

existing roads (i.e. existing “road shoulders”).     

 

The construction of the CCCBN will consist of well‐accepted construction activities commonly practiced 

for telecommunications projects.  Therefore the expected environmental impact of these activities will 

be minimal, and the planned activities of the CCCBN represent the best alternative to meet the needs 

and purposes of the project.     

 

Purpose, Needs, and Alternatives Considered 

 

The primary need of the project is to build a fiber optic and wireless infrastructure to the unserved and 

underserved portions of Columbia County.  The project’s objective is to establish a network that will 

provide increased broadband and wireless access to the entire community, especially the areas of the 

county in the most economic need.  Increased broadband availability throughout the county will result 

in improved economic and educational opportunities to the citizens throughout the county.   

 

Prior to applying for the ARRA grant through NTIA, Columbia County investigated alternatives to building 

a new network throughout the county.  The first alternative investigated was to lease broadband 

connections and unused fibers from any of the several incumbent service providers in the county.  This 

alternative was thoroughly investigated but ultimately proved not to meet the needs of the project.  The 

providers were only interested in providing leased connections to the county, and did not allow any of 

their unused fibers to be leased.  This proved to be the primary reason that this alternative was not 

further pursued.  Without dark fiber, many of the specific needs of the project could not be met. In 

addition, the leased circuit costs presented were such that building and owning its own network proved 

to be a much better financial alternative for the County.   

 

Once all the analysis was concluded and it was determined that dark fiber would not be available from 

the incumbents, it became clear that building its own network would be the best available alternative 

for Columbia County.  All of this effort had taken place prior to the creation of the ARRA and the BTOP 

program within NTIA.  When these programs were defined, the County continued its ongoing effort and 

applied for funding in Round 1.   

 

Page 7: Columbia County Community Broadband Network

10‐14‐10  Page 6  

 In summary, all construction activities will be concentrated in previously developed and previously 

disturbed areas such as rights‐of‐way of existing roads and county‐owned properties.   Analysis of the 

project, constructed using the methods described, showed no significant impact during construction or 

operation for the preferred route and use of previously disturbed property to any of the resource areas.  

In addition, the preferred route and use of pre disturbed property for towers is recommended to reduce 

total length of construction and impact on the environment 

   

Page 8: Columbia County Community Broadband Network

10‐14‐10  Page 7  

Chapter 1 Purpose and Need 

 1.1 Background and History 

The Columbia County Community Broadband Network (CCBN) was conceived by the County’s 

Information Technology (IT) department as a means to enhance and improve the lives of the citizens of 

the County.  The IT Department began earnest work on the project well before the details of the ARRA 

Broadband Stimulus programs were finalized in July 2009.  The BTOP program served as the final step in 

formulating the project.  The IT Department has gathered letters of support from the anchor 

institutions, reached preliminary agreements with third party service providers, identified the cable 

construction route, and designed the network electronics.   

 

1.2 Geographic Setting and Need 

Columbia County, Georgia is located in East Georgia northwest of the city of Augusta which is located in 

Richmond County (see location maps and aerials in Appendices 1 and 2). According to the US Census 

Bureau, Columbia County has a total population of 435,243.  The northeastern portion of Columbia 

County is relatively affluent, while the southern and western parts of the county are economically 

challenged and sparsely populated. The northeastern section, which comprises approximately 40% of 

the county, has reasonable commercial broadband access while the remaining 60% is economically 

challenged and has very limited or no access. Due to the low subscriber densities in these areas, it is 

difficult for a commercial entity to justify the investment necessary to provide reasonable broadband 

access to these economically challenged communities.  The State of Georgia’s Technology Authority 

(http:/gta.georgia.gov) has classified Columbia County as an area in critical need of enhanced 

broadband connectivity.  The Georgia Technology Authority seeks to ensure that the state’s IT 

infrastructure is stable, secure and well‐governed, and provides Georgians with the services they need 

and expect.  Their study of underserved and unserved areas of broadband coverage in the state rated 

areas as critical, moderate, and low.  Of 12 regions in the state Regional Commissions, five, including  

Columbia County located in Region 7, were rated critical.  Appendix 3 illustrates the GTA’s depiction of 

a Regional View of Unserved and Underserved Areas in Georgia. 

 

Page 9: Columbia County Community Broadband Network

10‐14‐10  Page 8  

  

Columbia County’s Location in Georgia 

 

One of the primary needs of the project is to build a fiber optic infrastructure to the unserved and 

underserved areas of the county. The project has identified multiple unserved areas and underserved 

areas in the Appling/Harlem/Grovetown areas of the county. The fiber optic cable route establishes 

interconnection points at all of these areas, from which last mile service providers can build their 

networks to connect citizens in these areas. These areas are for the most part concentrated in the areas 

south of Interstate 20, in the areas including and surrounding the cities of Harlem and Grovetown.  

 

The objective of this project is to establish a network that will provide increased broadband  

and wireless access to the entire community, especially the economically challenged areas. The network 

will be used to improve the quality of life in these areas and enhance employment opportunities. The 

County government is proposing to channel its existing IT expenditures to support the establishment 

and maintenance of the new network.  

The network will be open to commercial users, governmental users, broadband service providers (both 

wireline and wireless) and anchor institutions. It will be operated for the sole benefit of the community, 

but will be operated as an open network that can be used by commercial service providers to enhance 

and expand service, especially in areas that are economically challenged. The County has extensive 

project management experience with large complex projects and the operational experience necessary 

to help ensure continued success. It has also engaged a professional engineering firm with extensive 

Page 10: Columbia County Community Broadband Network

10‐14‐10  Page 9  

experience designing and developing communications networks in the area, and it has the commitment 

of established construction firms and system integrators. Furthermore, commercial service providers, 

educational organizations, health care providers, public safety organizations, libraries and other anchor 

institutions have pledged their support and plan to use the network to improve the quality of life in the 

area. 

 

 The following maps show unserved and underserved areas and a representation of the fiber route 

throughout the county. 

   

Page 11: Columbia County Community Broadband Network

Columbia County Community Broadband Network (CCCBN)Modified Unserved and Under Served Coverage Areas

!(

!(!(

!(

!(

!(

!(

!(

!(

!(!(

!(

!(

!(!(!(

!(

!(

!(!(!(

!(!(

!(

!(!(!(

!( !(!(!( !(

!(

!(!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(!(!(

!( !(

!(!(

!( !(

!(

!(!(

!(

!(!(

!(

!(

!(!(

!(!(

!(!(

!(

!(

!(

!(

!(!(

!(!(!(

!(

!( !(

!(

!(

!(

!(

!(!(

!(!(

!(

!(

!(

!(!(

!(

!(

!(

!(

!(!(

!(!(

!(

!(

!(

!(!(

!(

!(

!(

!(!(

!(

!(

!(

!(!(

!(

!(

!(

!(

!(

!(!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(!(

!(

!(

!(

!(

!(

!(

!(!(

!(

!(

!(

!(

!(

!(

!(

!( !(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(!(

!(!(!(!(

!(

!(

!(

!(!(!(

!(

!(

!(

!(

!(!(!(!(!(!(!(!(!(!(!(

!(!(!(

!(!(!(

!(!(!(!(!(

!(!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

#7

#7

#7

#7

#7

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

&

&

&

CCCBN Total Proposed Length: 220 Miles& Network Interface Points

!? Points Of Interface

#7 Proposed Towers

!( Service Site FacilitiesExisting FiberMasterPlan BroadbandRoadwaysMain RoadsCity Boundaries

Unserved Census Block (15)Underserved Census Block (54)Fort GordonFort Gordon Recreational FacilityRailroad

Ê0 2 41 Miles

Page 12: Columbia County Community Broadband Network

10‐14‐10  Page 11  

 

 Columbia County Map with Fiber Route 

   

Page 13: Columbia County Community Broadband Network

10‐14‐10  Page 12  

1.3 Goals 

The purpose of the project can be largely summarized by reviewing the initial set of Project Goals which 

were formulated in the initial business plan for the project:   

• Economic Growth and Quality Jobs  

• Promotion of Private Sector Competition  

• Enhancement of Digital Inclusion  

• Wireless Backhaul  

• E‐Government, Civic Participation and Public Safety –  

• Education and Integrated Learning –  

• Intelligent Transportation System (ITS)  

• Communication Security, Capacity, Quality and Cost  

• Interoperability and Disaster Recovery  

• Telemedicine and Independent Living  

• Supervisory Control and Data Acquisition (SCADA)  

 

These goals are described in more detail below:   

 

The CCCBN will spur private‐sector innovation and competition, thereby offering affordable bandwidth 

and services to residents of Columbia County. The CCCBN will also integrate public safety, public health, 

education, libraries, community centers, and other government users. The CCCBN will serve as a 

backbone for networking County agencies and is essential to enhancing government services.  

 

The project will provide broadband education, awareness, training, access, equipment, and support to a 

variety of institutions including schools, libraries, medical and healthcare providers, institutes of higher 

education, advocacy groups for low‐income and aged citizens, and others. The CCCBN has established 

partnerships with groups and organizations from all of these categories and has included each of these 

facilities as anchor tenants in the fiber optic cable route.   

 

The project will improve access to and use of broadband services by public safety agencies, and will 

stimulate the demand for broadband, economic growth, and job creation. Since this project has been 

created, defined, and driven by the IT department of the Board of County Commissioners, buy‐in from 

all public safety agencies has been virtually automatic and has been easily solidified from the origins of 

the project. Public safety agencies are all included as anchor tenants on the cable route and letters of 

support from all such agencies were included in the project application.  Additionally, it is well‐known 

that increased broadband access in an area is an established driver for economic growth and job 

creation.  Knology, an established broadband provider for a number of Tier‐2 cities in the Southeast 

(including greater Augusta in Richmond County) has already committed to lease fibers from the CCCBN 

project to provide broadband connectivity to previously underserved areas such as Grovetown, Harlem, 

and the Greenbrier area of Evans in Columbia County.  

 

The project has broad significance because it has potential positive impact on each and every citizen of 

Columbia County. Even for citizens who live in areas which are well‐served, the project has broad 

Page 14: Columbia County Community Broadband Network

10‐14‐10  Page 13  

significance because a county‐wide broadband infrastructure will result in increased job opportunities 

and economic growth for the entire area. 

 

   

Page 15: Columbia County Community Broadband Network

10‐14‐10  Page 14  

Chapter 2 ‐ Proposed Actions 

 2.1  Project Description 

The project includes a fiber network with approximately 200 miles of fiber optic cable and five new 300‐

foot towers.  A map is attached that shows the route for the fiber optic cable and the location the new 

towers. The fiber and tower construction will consist of multiple phases over the next 24‐30 months. 

 

2.1.1 Overview 

 

Fiber Optic 

 The approximately 200 miles of fiber optic construction will take place exclusively along the rights‐of 

way of existing roads (i.e. existing “road shoulders”). The construction along the right of way will be 

performed by plowing, trenching or directional boring. Whenever possible, and in the vast majority of 

cases, directional boring will be conducted on all stream crossings.  The initial set‐up of the bore will be 

outside the 25' stream buffer zone, and the opposite end of the bore will also be outside the 25' stream 

buffer zone. These techniques are commonly used in telecommunications construction with minimal 

impact on the environment. Silt fences will be used to help ensure that local streams and waterways are 

not impacted. The network includes two points of presence (POPS) that will be used to interconnect the 

inner and outer ring. These POPS will be collocated with towers and will be placed on existing county 

land that includes existing buildings. These sites will be submitted to the FAA for Tower approval and 

this submission will include the Phase I Environmental Site Assessment required for all towers by the 

FAA. 

 

The fiber optic cable will be used to interconnect approximately 150 “anchor tenant” sites.  These 

include schools, city and county facilities, public safety facilities, water utility facilities, and traffic signals.  

None of the anchor tenant connections will require any new buildings to be constructed.  The fiber optic 

cable will be brought into these existing buildings via direct burial and/or new and existing conduits. 

Directional drilling will be used to install these links. The fiber optic cable will be terminated inside the 

existing buildings in areas suited for telecom equipment.  In some cases interior conduit may need to be 

installed within a building from the termination room into an equipment room located elsewhere in the 

building.  

 

The following photographs are some typical representations of the rights‐of‐way which will be used to 

construct the project.   

 

Page 16: Columbia County Community Broadband Network

10‐14‐10  Page 15  

 Belair Road at Hereford Farm Rd. 

 

   Columbia Drive 

 William Few Parkway 

Page 17: Columbia County Community Broadband Network

10‐14‐10  Page 16  

   Horizon South Parkway 

 

 Clarks Hill Rd. 

 

The following table summarizes the anchor institutions to be included in the project and connected to 

the new broadband network.   

 

Institution  Location   Address 

Community 

Center  Eubank Blanchard Community  6868 Cobbham Road, Appling GA 30802 

Community 

Center  Euchee Creek Community Center 

5919 Euchee Creek Drive, Grovetown GA 

30813 

Community 

Center  Savannah Rapids Pavilion 

3300 Evans to Locks Road, Martinez GA 

30907 

Community 

Center 

Grovetown Liberty Park Community 

Ctr.  1040 Newmantown Rd Grovetown GA 30813

Education 

Board of Education Admin Building ‐ 

Hereford Farm  4781 Hereford Farm Road, Evans GA 30809 

Education  Technology Department ‐ Appling  6430 Pollards Pond Road, Appling GA 30802 

Education  Bel Air Elementary School  325 N. Belair Rd, Evans GA 30809 

Page 18: Columbia County Community Broadband Network

10‐14‐10  Page 17  

Institution  Location   Address 

Education  Blue Ridge Elementary School  550 Blue Ridge Drive, Evans GA 30809 

Education  Brookwood Elementary School  455 S. Old Belair Rd, Grovetown GA 30813 

Education  Cedar Ridge Elementary School  1000 Trudeau Trail, Grovetown GA 30813 

Education  Euchee Creek Elementary School  795 Louisville Road, Grovetown GA 30813 

Education  Evans Elementary School  628 Gibbs Road, Evans GA 30809 

Education  Greenbrier Elementary School  5116 Riverwood Parkway, Evans GA 30809 

Education  Grovetown Elementary School  300 Ford Avenue, Grovetown GA 30813 

Education  Lewiston Elementary School  5426 Hereford Farm Road, Evans, GA 30809 

Education  Martinez Elementary School  213 Flowing Wells Road, Martinez GA 30907 

Education  North Columbia Elementary School  2874 Ray Owens Road, Appling GA 30802 

Education  North Harlem Elementary School  525 Fairview Drive, Harlem GA 30814 

Education  River Ridge Elementary School  4109 Mullikin Road, Evans GA 30809 

Education  Riverside Elementary School  4431 Hardy McManus Road, Evans GA 30809 

Education  South Columbia Elementary School  325 McCormick Road, Martinez GA 30907 

Education  Stevens Creek Elementary School 

3780 Evans‐to‐Lock Road, Martinez GA 

30907 

Education  Westmont Elementary School  4558 Oakley Pirkle Road, Martinez GA 30907 

Education  Columbia Middle School  6000 Columbia Road, Grovetown GA 30813 

Education  Evans Middle School  4785 Hereford Farm Road, Evans GA 30809 

Education  Greenbrier Middle School  5120 Riverwood Parkway, Evans GA 30809 

Education  Grovetown Middle School 

5463 Harlem‐Grovetown Road, Grovetown 

GA 30813 

Education  Harlem Middle School  375 W. Forresst Street, Harlem GA 30814 

Education  Lakeside Middle School  527 Blue Ridge Drive, Evans GA 30809 

Education  Riverside Middle School  1095 Fury's Ferry Road, Evans GA 30809 

Education  Stallings Island Middle School 

3830 Blackstone Camp Road, Martinez GA 

30907 

Education  Evans High School  4550 Cox Road, Evans GA 30809 

Education  Greenbrier High School  5114 Riverwood Parkway, Evans GA 30809 

Education  Grovetown High School  2010 Warrior Way, Grovetown GA 

Education  Harlem High School 

1070 Appling Harlem Highway, Harlem GA 

30814 

Education  Lakeside High School  533 Blue Ridge Drive, Evans GA 30809 

Education  CCBOE Alternative School  112 Ford Avenue, Grovetown GA 30813 

Education  New Elementary School  off Chamblin Rd Grovetown GA 30813 

Education 

Higher 

Augusta Technical College Columbia 

County Campus 

3500 John Huffman Way, Grovetown GA 

30813 

Fire  MCFR1 ‐ Headquarters(HDQ)  3910 Desoto Drive, Martinez GA 30907 

Fire  MCFR2  518 Gibbs Road, Evans GA 30809 

Fire  MCFR3  704 Fury's Ferry Road, Evans GA 30809 

Page 19: Columbia County Community Broadband Network

10‐14‐10  Page 18  

Institution  Location   Address 

Fire  MCFR4  4590 Oakley Pirkle Road, Martinez GA 30907 

Fire  MCFR5  5074 Hardy McManus Road, Evans GA 30809 

Fire  MCFR6  2264 William Few Parkway, Evans GA 30809 

Fire  MCFR7  480 Sugarcreek Drive, Grovetown GA 30813 

Fire  MCFR8  1646 Clary Cut Road, Harlem GA 30814 

Fire  MCFR9 

1090 Old Louisville Road, Grovetown GA 

30813 

Fire  MCFR10  3141 Ray Owens Road, Appling GA 30802 

Fire  MCFR11  480 White Oak Road, Harlem GA 30814 

Fire  MCFR12  6383 Columbia Road, Appling GA 30802 

Fire  MCFR13  6285 Cobbham Road, Appling, GA 30802 

Fire  MCFR14  5776 Clarks Hill Road, Appling GA 30802 

Fire  MCFR15 

5701 Burks Mountain Road, Appling GA 

30802 

Fire  MCFR16  3653 Ray Owens Road, Appling, GA 30802 

Government  Evans Campus  630 Ronald Reagan Dr, Evans, GA 30809 

Government  Appling Campus 

1954 Appling Harlem Road, Appling, GA 

30802 

Government  Range Road Campus  201 Range Road, Appling GA 30802 

Government 

Columbia County Development 

Authority 

604 Government Center Way, Evans GA 

30809 

Government  Animal Care and Control  Chamblin Road, Grovetown, GA 30813 

Grovetown  City Hall 

103 Old Wrightsboro Rd, Grovetown, GA 

30813 

Grovetown  Grovetown Museum 

103 Old Wrightsboro Rd, Grovetown GA 

30813 

Grovetown  Public Safety(GFD1)  306 E Robinson Ave, Grovetown GA 30813 

Grovetown  Public Safety Annex  105 E Robinson Ave, Grovetown GA 30813 

Grovetown  Senior Center  103 E Robinson Ave, Grovetown GA 30813 

Grovetown  Maintenance   1034 Newmanton Rd, Grovetown GA 30813 

Grovetown  Recreation   1040 Newmanton Rd, Grovetown GA 30813 

Grovetown  Water Treatment  1400 Lakeview Rd, Grovetown GA 30813 

Grovetown  Public Safety (GFD2)  105 W Robinson Ave, Grovetown GA 30813 

Harlem  City Hall  320 N Lousiville St, Harlem GA 30814 

Harlem  Senior Center  405B  W Church St, Harlem GA 30814 

Harlem  Community Connections  405A  W Church St, Harlem GA 30814 

Harlem  Police Station  180 N Lousiville St, Harlem GA 30814 

Harlem  Public Works  145 New Street, Harlem GA 30814 

Harlem  Waste Water Treatment  HWY 221, Harlem GA 30814 

Harlem  Fire Department(HFD1)  110 New Street , Harlem GA 30814 

Page 20: Columbia County Community Broadband Network

10‐14‐10  Page 19  

Institution  Location   Address 

Harlem  Fire Department(HFD2)  120 S Hicks Street, Harlem GA 30814 

Health  MCG Health 

Proposed Data Center (Horizon South) 

Grovetown GA 30813 

Health  Columbia County Health Department  Chamblin Road, Grovetown GA 30813 

Libraries  Harlem Library  375 North Louisville St, Harlem GA 30814 

Libraries  Euchee Creek Library  5907 Euchee Creek Dr, Grovetown GA 30813 

Libraries  Columbia County Library 

7022 Evans Town Center Blvd, Evans GA 

30809 

Park  Patriots Park  6445 Columbia Road, Grovetown GA 30813 

Park  Blanchard Park  4541 Dewey Dr, Martinez GA 30907 

Park  Blanchard Woods 

4600 Blanchard Woods Drive, Evans GA 

30809 

Park  Evans Towns Center  515 Faircloth Dr, Evans GA 30809 

Park  Lonnie Morris (Appling)  Scotts Ferry Rd  Appling GA 30802 

Park  Memorial Gardens  640 Ronald Reagan Dr, Evans, GA 30809 

Park  Reed Creek Park  3820 Park Lane, Martinez GA 30907 

Park  Riverside Park 

4431 Hardy‐McManus Road, Evans GA 

30809 

Park  Wildwood Park  3780 Dogwood Lane Appling GA 30802 

Park  Gooddale Park Grovetown 

5200 Wrightsboro Road, Grovetown GA 

30813 

Public Safety  Sheriff's Office  2273 County Camp Road, Appling GA 

Public Safety  Sheriff's Office Sub Station  650A Ronald Reagan Dr Evans GA 30809 

Public Safety  Emergency Management Agency  650B Ronald Reagan Dr, Evans GA 30809 

Public Safety  Georgia State Patrol Office  420 Chamblin RD, Grovetown GA 30813 

Public Safety  Georgia State Forestry  5887 Wrightsboro RD, Harlem GA 30814 

Traffic Control  S1  Baston Road/Old Petersburg 

Traffic Control  S2  Baston Road/Old Ferry/Cedar Lane 

Traffic Control  S3  Bobby Jones/Rose Lane 

Traffic Control  S4  Columbia Industrial Blvd/Evans to Locks 

Traffic Control  S5  Columbia Road/Belair Rd 

Traffic Control  S6  Columbia Road/Flowing Wells 

Traffic Control  S7 

Columbia Road/Hereford Farm/Lewiston 

Road 

Traffic Control  S8  Columbia Road/Merchant Village 

Traffic Control  S9  Davis Road/Oak Drive 

Traffic Control  S10  Evans to Locks/Blue Ridge Drive 

Traffic Control  S11 

Flowing Wells Road/Old Trail Rd 

West/Augusta Prep 

Traffic Control  S12  Futys Ferry Road/Baston Road/Vaughn Road 

Page 21: Columbia County Community Broadband Network

10‐14‐10  Page 20  

Institution  Location   Address 

Traffic Control  S13  Furys Ferry Road/Evans to Locks 

Traffic Control  S14  Furys Ferry Road/Inverness Way/Park Lane 

Traffic Control  S15 

Furys Ferry Road/North Belair/ Mullikin 

Road 

Traffic Control  S16  Futys Ferry Road/The Pass 

Traffic Control  S17  Hereford Farm/Cox Road/Gibbs Road 

Traffic Control  S18 

Jimmie Dyes Parkway/Belair Frontage 

Road/Park West Drive 

Traffic Control  S19  Jimmie Dyes Parkway/EB  I‐20 Ramps 

Traffic Control  S20  Lewiston Road/EB I‐20 Ramps 

Traffic Control  S21  Lewiston Raod/WB I‐20 Ramps 

Traffic Control  S22  Milledgeville Road/Louisville Street 

Traffic Control  S23  North Belair Road/Cox Road/Owens Road 

Traffic Control  S24  Old Evans Road/Blue Ridge 

Traffic Control  S25  Old Evans Road/Martinez Boulevard 

Traffic Control  S26  Old Evans Road/Old Petersburg Road 

Traffic Control  S27  Riverwatch Parkway/Pleasant Home Road 

Traffic Control  S28 

Robinson Avenue/Harlem Grovetown 

Road/Wrightsboro Rd 

Traffic Control  S29  South Belair Road/Oakley Pirkle Road 

Traffic Control  S30 

South Belair Road/South Old Belair 

Road/Wheeler Road 

Traffic Control  S31  South Belair Road/WB  I‐20 Ramps 

Traffic Control  S32  Washington Road/Baston Road 

Traffic Control  S33 

Washington Road/Bobby Jones 

Expressway/Old Evans Rd 

Traffic Control  S34  Washington Road/Club Car Drive/AnnTaylor 

Traffic Control  S35 

Washington Road/Columbia Road/Ruth 

Street 

Traffic Control  S36  Washington Road/Davis Road 

Water Utility  Jim Blanchard Water Plant  832 Point Comfort Road, Martinez GA 30907 

Water Utility  Clarks Hill Water Plant  5776 Clarks Hill Road, Appling GA 30802 

Water Utility  Crawford Creek Waste Water Plant  1000 Shepherd Way, Grovetown GA 30813 

Water Utility  Reed Creek Waste Water Plant  578 Stevens Creek Rd, Martinez GA 30907 

Water Utility  Kiokee Creek Waste Water Plant  2281 County Camp Road, Appling GA 30802 

Water Utility  Little River Waste Plant  1130 Maple Ridge Court, Evans, GA 30809 

Water Utility  I‐20 Water Tank  4824 Old Belair Lane, Martinez GA 30907 

Water Utility  Winfield Water Tank  3317 Tom Bartles Road, Appling GA 30802 

Water Utility  Washington Road Water Tank  5801 Washington Road, Appling GA 30802 

Water Utility  Louisville Water Tank  5919 Euchee Creek, Grovetown GA 30813 

Page 22: Columbia County Community Broadband Network

10‐14‐10  Page 21  

Institution  Location   Address 

Water Utility  Flowing Wells Water Tank  494 Flowing Wells Road, Martinez GA 30907 

Water Utility Grovetown Water Tank 

4939 Wrightsboro Road, Grovetown GA 

30813 

Water Utility Wrightsboro Rd Water Tank 

4605 Wrightsboro Road, Grovetown GA 

30813 

Water Utility  Belair Rd Water Tank  222 North Belair Road, Evans GA 30809 

Water Utility  Appling Water Tank  5984 Columbia Road, Appling GA 30802 

Water Utility  High View Water Tank  206 Pecan Drive, Martinez GA 30907 

Water Utility 

Administrative Buildings Chamblin 

Road  205 Chamblin Road, Grovetown 30813 

 

Towers:  

As mentioned previously the 5 tower locations will reside on Columbia County owned property that has 

been pre‐disturbed and pre‐developed. Therefore, it is expected that no significant clearing, excavating, 

or other disturbance of the property will be required.  There will need to be fencing constructed around 

the perimeter of the tower footprint and (if applicable) any of its guy wire anchor points.  The tower 

construction will contain pre‐fabricated (typically concrete), above‐ground equipment buildings.  These 

buildings will be located at the base of the tower and will be situated within the property used for the 

tower base.  Approximate building dimensions are 10 feet x 15 feet (single story).  The project will utilize 

existing buildings and pre‐disturbed, pre‐developed areas.   The only new buildings to be constructed 

will be located adjacent to the (5) new radio towers within the same property parcels containing the 

towers.   These will most likely take the form of pre‐fabricated concrete structures commonly used for 

telecommunications buildings, cell sites, etc.  All tower locations are planned for previously disturbed, 

previously developed land parcels currently owned by the County.  All tower locations have been 

submitted to the FAA for approval (see Appendix 8) and a Phase I Environmental Site Assessment will be 

performed, as required by the FAA. 

 

The 5 towers are described in the table below and shown in the following photographs and aerials. 

 

ADDRESS  LATITUDE  LONGITUDE  PARCEL # 

480 White Road, Harlem, GA   33 deg 24’ 20” N  82 deg 17’ 20” W  Parcel 043A020 

6868 Cobbham Road, Appling 

GA  

33 deg 36’ 37” N  82 deg 19’ 32” W  Parcel 025 047 

590 Baker Place Road 

Grovetown, GA 

33 deg 29’ 17” N  82 deg 14’ 13” W  Parcel 051 001B  

 

962 Halali Farm Road  33 deg 34’15” N  82 deg 10’ 7” W  Parcel  065 021 

2292 County Camp Road 

Appling, GA 

33 deg 32’ 14” N  82 deg 18’ 32” W  Parcel 028 057    

 

 

The proposed 590 Baker Place Road site has commercial power immediately adjacent via utility pole line 

located on the opposite side of the road.  The provision of power to the site will require a simple 

Page 23: Columbia County Community Broadband Network

10‐14‐10  Page 22  

extension from existing sources.   The proposed 2292 County Camp Road site has commercial power 

immediately adjacent via utility pole line located on the opposite side of the road. The provision of 

power to the site will require a simple extension from existing sources.   The proposed 6868 Cobbham 

Road site already has commercial power located on the site.  The proposed 480 White Road site has 

commercial power on the opposite side of the road.  Electrical power to the site will be provided via an 

underground cable that will be located within the 12‐foot by 360 foot access road.  An underground 

trench will be excavated within the above mentioned access road to the communication site itself. An 

underground cable buried in the trench will provide power to the site. The total linear distance of the 

power run will be approximately 360 feet.   The proposed 962 Halali Farm Road site has commercial on 

the same side of the road.  Electrical power to the site will be provided via an underground cable that 

will be located within the 12‐foot by 480 foot access road.  An underground trench will be excavated 

within the above mentioned access road to the communication site itself. An underground cable buried 

in the trench will provide power to the site. The total linear distance of the power run will be 

approximately 480 feet.  

All proposed sites include a standby generator to provide electric power in the event of a commercial 

power failure. The standby generator will be powered by diesel, and will typically be comprised of a  

108 horsepower internal combustion engine power unit driving a single‐phase 60 kilowatt generator. 

The emissions level for the generator engine will be rated EPA Nonroad Tier 3. The generator will be 

mounted inside a  Level 2 Sound Enclosure, and will include a muffler on the power unit and appropriate 

sound proofing within the walls of the enclosure to minimize noise.  Diesel fuel will be provided from a 

 Dual Wall UL142 tank mounted inside the enclosure on concrete slabs.  The diesel tank will be sized in a 

manner to allow for a constant generator run time of up to 168 hours or one week, in the event of a 

long‐term power failure. 

 

2.1.2  Construction 

The project will use a variety of techniques in installing the fiber optic cable and communications towers. The majority of the fiber optic construction will be underground, but in some congested areas or areas of a cost‐prohibitive nature, the cable will need to be installed aerially on either existing or new poles.  In addition, in rare instances, it is possible that “aerial inserts” will need to be placed over stream 

or waterway crossings if the preferred underground methods are for some reason impractical or cost‐

prohibitive.     

For underground construction, the general requirement for minimum depth of placement is 36” below 

grade.  When new facilities cross under ditch lines, roads, and streams, the depth will usually be 48”.  

Underground cable placement can be done via trenching, plowing, and boring.  All construction will take 

place within the right of way of existing roadways in pre‐disturbed areas.    

 

Plowing:  Construction along rural routes is usually done via plowing.  Plowing employs the use of a 

specialized piece of machinery called a track plow.  The plow opens a slot into the ground at the 

specified depth.  The slot is no more than 6” wide.  A reel of fiber cable is loaded onto the plow, and as 

the plow moves forward the cable is fed into a chute which directs the cable into the bottom of the slot 

opened by the plow.  The cable is laid at the proper depth, and as the plow continues forward the 

Page 24: Columbia County Community Broadband Network

10‐14‐10  Page 23  

excavated slot is compacted back to ground level.  In a rural area with a minimal amount of 

obstructions, plowing is the most time‐ and cost‐efficient method of placing underground fiber cable.   

 

Trenching:  Underground cable construction in more congested areas will typically make use of 

trenching as opposed to plowing.  If the area has many obstructions such as existing underground 

utilities, driveway crossings, aerial transitions, etc. a trench is excavated and the cable is laid manually 

into the bottom of the trench.  The trenching method would require the use of a backhoe if rock or 

especially hard ground is involved, or a trenching machine if the ground is less hard.  Trench dimensions 

will vary, but can be nominally summarized as 36” typical depth, with 24” maximum width if a backhoe 

is used or 6” width if a trencher is used.  No open trenches will be left overnight without cover.  The 

trench is back‐filled using the same soil material that was removed to create the trench, except in rocky 

areas, where the backfill may be hauled in and the rock material removed.   

 

Boring:  Boring is used when underground fiber cable placement must be conducted in areas where no 

linear excavations are feasible on the surface, or in areas where surface restoration is cost‐prohibitive.  

In directional boring, a boring rig is used to tunnel under existing roads, utilities, driveways, waterways, 

or other obstructions.  Bore diameters are typically 4‐6 inches.  Bore lengths are typically less than 100 

feet, but can be as long as hundreds of feet when crossing large rivers or streams.  A bore pit may need 

to be dug at the beginning of the bore, which allows the excavation to start at the proper depth.  The pit 

can be as deep as 6‐8 feet, depending on the depth required for the bore.  The boring head is directed 

forward by the operator and is used to tunnel through the ground beneath the obstructions.  As the 

head moves forward, 10‐foot rod sections are added at the boring rig to increase the length of the 

excavation.  A slurry mixture is introduced through the rods and bore head to soften the soil for 

compaction around the path of the boring head.   Once the obstructions are cleared, the boring head 

can be directed upward to the surface.  Once the excavation has been completed and the head appears 

above the surface, flexible PVC casing pipe from a spool is attached the bore head.  The bore head is 

then pulled back along the excavation, pulling the casing pipe back to the bore pit and thus creating a 

pathway for cables and inner ducts to be pulled into at a later time.     

 

Aerial – existing poles:  Aerial fiber optic plant construction may be used as an alternative to 

underground installation via plowing, trenching, or boring.  Where existing pole lines are present, fiber 

optic cable can be installed on existing poles.  Installing cable on pole lines requires strict adherence to 

electrical safety code requirements.  Specifically, safety codes require that telecom cables can only be 

installed in certain parts of the vertical space on the pole lines.  The telecom space is closest to the 

ground and is frequently crowded with cables owned by telephone companies, cable TV providers, and 

in some cases, CLECs and municipal network providers.  As a result, it is very common for existing pole 

lines to be unusable for new telecom facilities because the telecom space is too crowded.  In some cases 

existing cables can be rearranged to gain additional space but the cost of this process (referred to as 

“make‐ready” work) can be cost‐prohibitive.  If the poles are owned by third parties (i.e. power 

companies, telephone companies, or cable TV companies), then joint‐use agreements must be worked 

out which allow new providers to lease space on un‐owned poles for a per‐year, per‐pole cost.  Over the 

long term, leasing space on third‐party poles can also prove to be cost prohibitive.  As a new service 

Page 25: Columbia County Community Broadband Network

10‐14‐10  Page 24  

provider, Columbia County owns no poles and would be dependent on leasing poles from third parties, 

thus increasing the long‐term cost of the project.  It is for these reasons that the majority of the fiber 

optic construction planned in this project is planned to be underground whenever possible.   

Aerial – new poles:  In some cases aerial cable construction is done using new pole lines.  This may occur 

when there is no pole line present, when joint‐use costs are too expensive, or when the telecom space 

on the existing pole line is too crowded.  If aerial inserts are required for stream crossings, new poles are 

usually needed on either side of the stream’s buffer zone to support the aerial crossing.  The 

construction of new utility poles has been ongoing since the beginnings of the telecom industry decades 

ago.  If any new poles are required, they will be engineered and constructed using best practices from 

the industry.  This includes adherence to all applicable RUS specifications and standards, including RUS 

Bulletin 1753F‐152 / RUS Form 515c (“Specifications and Drawings for Construction of Aerial Plant”).  

This specification addresses such requirements as pole materials, mounting depth relative to pole 

height, backfill and tamping methods, support member requirements, grounding requirements, and 

many more.  Although the CCCBN is not financed using RUS funds, the RUS telecom practices represent 

the best specifications and standards for telecom cable construction that the industry has.        

Aerial Placement of Cable:  The preferred method for cable placement for the CCCBN will be 

underground via trenching, boring, or plowing.  However in some areas these techniques may not be the 

most cost‐effective method, thus requiring aerial cable placement.  Aerial cable is typically placed on 

pole lines by attaching the cable to a metallic, stranded support member known as messenger wire.  The 

cable is lashed tightly to the messenger wire using a thin, flexible, high‐strength attachment wire.  

Ground clearance requirements for the cables and the supporting messenger must be taken into 

account based on applicable electric safety codes.  Aerial cable can be installed from a stationary reel or 

a moving reel using temporary pulleys or "J‐hooks”.  The pulleys can be installed at each pole, with a 

truck winch being fed through the pulleys and attached to the end of the cable. The cable is then pulled 

into place.  The cable can also be installed by attaching one end to the first pole with the rest of the reel 

moved to the next pole.  In this case temporary pulleys are not needed, because the cable is attached to 

each pole as it is unreeled. 

Towers: The towers planned for this project are nominally 300 feet above ground level (AGL).  They are 

intended to be self‐supporting towers (i.e. without guy wires) so their footing dimensions will be 

broader than those of a guyed tower.  Exact foundation dimensions will be determined after the towers 

are designed for the specific locations, but for planning purposes and Environmental Assessment 

purposes, the concrete pad which will comprise the foundation for the tower can be assumed to be 

approximately 40’ wide x 40’ long x 6’ in depth.  Tower foundations will require excavations to depths to 

be determined by a variety of factors.  The structural design of the towers will specify the detailed 

requirements of the excavations and backfills.  Tower foundations will be secured using steel‐ reinforced 

concrete below grade.  All towers will be erected on county‐owned land parcels which have been 

previously disturbed.   

 

Tower construction will require the use of grading machinery to level the site and construct access 

roads, excavation machinery to dig the tower foundations, concrete trucks to install the steel‐reinforced 

Page 26: Columbia County Community Broadband Network

10‐14‐10  Page 25  

concrete for the tower foundations, and cranes to place the tower sections in place.  The buildings to be 

installed adjacent to the towers will be pre‐fabricated concrete structures designed for 

telecommunications use.  These structures will be transported to the site on flatbed trucks and lowered 

into place using cranes.     

 

2.2 Alternatives 

 

2.2.1 ‐ “No Action Alternative” 

In the “no action alternative” the CCCBN would not be built at all.  If the CCCBN is not built, the county 

will continue to suffer from lack of increased broadband opportunities. The following will be 

consequences of not building the CCCBN: 

Unserved and Underserved areas of the county will continue to suffer from lack of broadband 

opportunities. 

Anchor institutions will not have fiber connections. 

County school children will not have high‐bandwidth 1 Gbps connections from the schools to the 

Internet 

Last mile providers will not be able to access potential customers in Grovetown and Harlem. 

Economic development will suffer due to the lack of a robust fiber infrastructure. 

The MCG Health data center will not be able to transmit medical imagery and patient records at 

high speed throughout the area.  

Control systems for county infrastructure (water/sewer, traffic systems, etc.) will not be able to 

be controlled through advanced fiber optic technology. 

Wi‐Fi in county parks would not be possible due to lack of fiber optic backhaul of the traffic 

Public safety radio coverage will continue to be sporadic due to the lack of RF coverage resulting 

from fewer towers. 

 

2.3 – Preferred Alternative  

In analyzing the alternates to the CCCBN construction, it is apparent that no alternative will meet the 

needs of the project.  Leased circuit capacity, as described in detail below, does not provide the dark 

fiber required to connect all the anchor institutions.  It would not allow third‐party service providers to 

access the unserved and underserved areas of the county.  It is not cost‐effective since it represents a 

higher cost with no owned asset value.  The “no action alternative” would consist of continuing the 

current status of the county’s broadband infrastructure.  This would result in none of the needs of the 

project being met.  Since neither of these alternatives represents viable solutions to the needs of the 

project, it is concluded that building the fiber optic cable network and communications towers as 

planned in the CCCBN grant will be the best method to meet the needs of the project. 

     

2.4 ‐ Alternatives Considered but Eliminated from Further Discussion 

A number of alternatives to the preferred alternative were considered early and then rejected as being 

not worthy of further discussion.  These alternatives consisted of variations in particular aspects of the 

preferred alternative and are discussed below.   

 

Page 27: Columbia County Community Broadband Network

10‐14‐10  Page 26  

2.4.1 Leased circuit capacity from incumbent broadband providers 

As a possible alternative to building and operating its own network, Columbia County first investigated 

the idea of leasing capacity on the network of one of the existing incumbent providers in the county.  

This alternative would have resulted in a dramatically different environmental assessment, since no new 

construction would need to take place.  However, this alternative was investigated in detail and was 

deemed inadequate to meet the needs and purpose of the project.  After this alternative was 

investigated and rejected, it was decided to move ahead with the planning and construction of the 

CCCBN project.  The discussion below explains how this alternative was deemed inadequate for the 

needs of the project.   

 

The effort to create the CCCBN has been ongoing since 2008, prior to the creation of the ARRA program.  

The County recognized that dark fiber was needed for public safety radio system needs, SCADA needs 

and medical imaging requirements.   It also determined that high bandwidth requirements were needed 

in the less affluent areas of the county and these high bandwidth requirements were not being satisfied 

by the service providers in these areas. Approximately two years ago AT&T, Comcast and Charter were 

approached by Columbia County to investigate the possibility of leasing or buying dark fiber from these 

carriers.  Charter declined to participate and thus no agreement was reached.  Comcast showed some 

interest but it had no spare fiber available for use.  AT&T, following a widely observed policy repeated in 

other states, was not willing to sell or provide dark fiber, but instead offered to provide leased circuit 

capacity on their Metro E network.  This offer included a connection to many county building locations 

but did not include a county‐wide fiber build‐out.   

 

As stated above, AT&T declined to provide dark fiber, but did propose a leased Metro E network.  Using 

the monthly lease cost and one‐time installation charges, the 5‐year lease cost totaled just over $20 

million, which includes approximately $4 million in initial installation costs.  In comparison, the total 

proposed CCCBN project cost is just over $18 million.  (It should be noted that the $18M CCCBN cost 

also includes approximately $2 million for 5 wireless towers).  Comparing these cost figures, it is 

apparent that a county‐owned fiber network would be a better investment than a leased network.  Not 

only does the $20 million lease cost represent a higher initial investment, it also represents less value 

since it is a leased network without owned assets.  Furthermore, it does not represent the same 

functionality as a dark fiber network, as is explained below.  

 

 First, the $20 million AT&T cost included a maximum bandwidth connection rate of 100 Mbps.  In 

contrast, the planned bandwidth speeds for the fiber‐based CCCBN are 100 Mbps minimum, with 

maximum bandwidth connections of 1 Gbps.  Secondly, a leased network represents only a collection of 

building connections, with no additional infrastructure included.  The fiber‐based CCCBN represents a 

robust infrastructure which makes dark fiber available not only for the county’s use but also for the 

potential use of network partners and service providers throughout the county.  In summary, the Metro 

E alternative was too expensive, did not cover the entire county, and did not fulfill all the needs of the 

project. 

 

Page 28: Columbia County Community Broadband Network

10‐14‐10  Page 27  

The following table summarizes the pros and cons of building the fiber network vs. using the leased 

capacity from the AT&T Metro E network. 

 

  CCCBN Fiber Network  AT&T Metro E Network 

Investment  $18 Million  $20 Million 

Asset Value  $18 Million  $0 

Projected cost for Years 6‐10  operating cost only  $16 Million (ongoing leasing 

cost) 

Dark Fibers  Yes  No 

Maximum Bandwidth 

Connection Speed 

1 Gbps  100 Mbps 

County‐wide presence  Yes  No 

Future Capacity for Additional 

Network Partners 

Yes  No 

 

One of the most important partners in the CCCBN is the Medical College of Georgia Health System 

(MCG).  MCG is the state of Georgia’s flagship institution for medical education and public health, and it 

is located in nearby Augusta.  MCG Health is in the process of planning and building a new data center to 

be located in Columbia County.  One of the missions of MCG Health is the need to transmit high‐

resolution medical images and medical records to remote locations in the region surrounding Columbia 

County.  This is currently done via leased point‐to‐point microwave circuits and does not work well.  

Fiber is the ideal media for this application.   

 

In conclusion, the discussion above should make it apparent that dark fiber is a real necessity in the 

CCCBN, and leased MetroE capacity does not provide the same benefits in a community middle mile 

network.  Once it became apparent that dark fiber could not be obtained from any of the existing 

carriers it was made clear that a new fiber‐based county‐owned network would provide the most value 

to the county and to its anchor institutions, business partners, and end users.   

 

 

2.4.2 Other alternatives investigated but deemed not to be viable 

 One possible alternative to the planned fiber optic construction would be to place the fiber optic cable 

on land that is not contained within right of way of existing roadways.  This strategy would have resulted 

in additional problems such as: 

 

Need for property acquisition 

Engineering and construction delays 

Increased cost  

Increased environmental impact 

 

Page 29: Columbia County Community Broadband Network

10‐14‐10  Page 28  

The vast majority of telecommunications facility construction occurs within right of way of existing 

roads.  For this reason it is generally accepted that installing cable in existing right of way represents a 

set of best practices that should be followed whenever possible.   

  

Regarding the tower construction, the possible alternatives to building them on county‐owned 

properties could have been 1) omitting them from the project and 2) installing them on private (non‐

county owned) property.  The idea of omitting the towers was discussed in the “no action” alternative.  

The idea of installing the towers on land not owned by the county can be rejected due to many of the 

same reasons shown above: 

 

Need for property acquisition 

Need for property clearing and re‐use classification 

Engineering and construction delays 

More difficult site access 

Increased project cost 

Increased environmental impact 

 

For the many reasons summarized, this alternative was decided to be not worthy of further discussion.    

 

2.4.3 – Alternatives Using More Wireless Technology 

Another possible alternative to installing all or part of the 200 miles of fiber optic cable would be to 

incorporate more wireless technology into the CCCBN.  If some or all of the needed services could be 

delivered by wireless methods, then it may be possible to build less cable miles and thus reduce certain 

environmental ramifications of the project.  However, due to the reasons outlined below, wireless 

technology does not support the same benefits that fiber optic cable does and is therefore not a good 

alternative to the 200 mile fiber optic cable route. 

It should be noted that the CCCBN already does incorporate wireless to a certain extent.  The project 

contains 5 towers which will be used for improved public safety coverage and will also be available for 

broadband service providers to lease space and connect to customers throughout the county.  However, 

when it comes to the type of services that Columbia County is proposing in this middle mile network, 

fiber optic technology offers much more bandwidth on a much more cost‐effective basis.   

The previous discussion for section 2.4.1 (the evaluation of the leased circuit capacity alternative) 

outlined many of the needs of the middle mile network, and explained the advantages of building fiber 

through the county as opposed to leasing available circuit capacity.  Specifically, higher bandwidths and 

dark fiber are needed for many of the high‐bandwidth services and capabilities required in the CCCBN.  

All of these same bandwidth advantages apply when compared to the bandwidth capability of a 

potential wireless middle‐mile network.  While the bandwidth of wireless services has grown 

dramatically in recent years, the aggregate bandwidth capacity of a wireless middle mile network still 

lags significantly behind that of a fiber‐based network.   While it may be true that some point‐to‐point 

Page 30: Columbia County Community Broadband Network

10‐14‐10  Page 29  

radio systems can achieve Gigabit Ethernet speeds (over relatively short distances), fiber is still 

unmatched in its ability to transmit high capacity over long distances.  As an example, optical Ethernet 

transceivers can perform on the order of 10 Gbps over 50 miles and 40 Gbps over shorter distances.  

Point‐to‐point wireless systems do not operate in this capacity.   

In order to cover the same remote areas of the county (where the new bandwidth and services are 

needed most) a significantly higher number of towers would be needed to establish a coverage area 

comparable to the 200 mile fiber network.  A conservative estimate would be an additional 20‐30 

towers which would be needed to cover the same 200 route‐miles planned for the fiber.  At an 

approximate cost of $12 Million, the cost of the towers would be higher than the amount budgeted for 

the fiber optic construction.   

One final consideration is the dark fiber capability that a middle mile fiber network will support.  In the 

network as designed, there will be a robust amount of dark fibers available for network expansion and 

for future capabilities to provide many services not yet defined.  A wireless middle mile network would 

not have such capacity for expansion and growth.  The only way to expand the capacity would be to 

install additional radio systems.  This approach would be limited by spectrum availability restrictions as 

well as physical space restrictions on the towers.  

   

Page 31: Columbia County Community Broadband Network

10‐14‐10  Page 30  

Chapter 3 ‐ Existing Environment  

3.1 Noise   

Noise levels vary in Columbia County, depending on the type of land use for the area in question.  The 

county contains a Federal Interstate Highway (I‐20) which provides a fairly consistent level of ambient 

noise in the immediate vicinity.  However since the majority of the I‐20 route miles through the county 

are rural in nature, the noise levels tend to fluctuate with traffic patterns and do not present sustained 

periods of noise pollution.  There are also a number of two‐lane and four‐lane state highways, whose 

immediate vicinities contain ambient noise levels consistent with such roadways.  The Evans / Martinez 

areas exhibit some traffic congestion during rush hour periods, and therefore also contain ambient noise 

levels consistent with suburban traffic patterns.  There is some light industry in the county but none of 

these industries contribute sustained, significant, levels of ambient noise.    

 

The majority of the acreage of the county, once removed from the immediate vicinity of the traffic 

corridors, contains rural forested lands with very low noise levels.    

 

3.2 Air Quality   

Columbia County does not fall within a non‐attainment zone, as defined by the National Ambient Air 

Quality Standards (NAAQS) for all criteria pollutants.  The county contains no Air Quality Management 

Districts (AQMDs) or State Implementation Plans (SIPs).  According to the Environmental Protection 

Agency (EPA) (http://www.epa.gov/air/oaqps/greenbk/ancl3.html), the only non‐attainment zones in 

Georgia are in the Atlanta metro area, and the Macon and Rome, Georgia areas.     

 

Attached in Appendix 4 is a re‐print of a letter from the Georgia Department of Natural Resources 

(dated 3‐12‐09) confirming that Columbia County does not fall in a non‐attainment zone.  The letter may 

be found on‐line at: 

http://www.gaepd.org/air/airpermit/downloads/planningsupport/naa/ozone8_recomdesig_2009letter.

pdf  

 

 

3.3 Geology and Soils   

Columbia County lies near the confluence of the Atlantic Coastal Plain and the Appalachian Highland, 

Piedmont Upland section.   Since the construction will take place within right of way of existing 

roadways, as well as county‐owned land parcels that have been previously disturbed, the project will 

have no impact on prime or unique farmlands, as defined in the Farmland Protection Policy Act (FPPA).  

A wide variety of soils are found within Columbia County, almost 40 in total.  A detailed soil survey 

report (found at http://soildatamart.nrcs.usda.gov/reportparams/counties.aspx ) is summarized below, 

showing each type of soil present in the county along with corresponding acreage. 

   

Page 32: Columbia County Community Broadband Network

10‐14‐10  Page 31  

 

  

Acreage and Proportionate Extent of the Soils by County  Acres Pct AkA Altavista sandy loam, 0 to 2 percent slopes 735 0.1 AmB Appling sandy loam, 2 to 6 percent slopes 11,020 2.0 AmC Appling sandy loam, 6 to 10 percent slopes 7,860 1.4 Bh Bibb silt loam 2,035 0.4 CfB2 Cecil sandy clay loam, 2 to 6 percent slopes, eroded 12,655 2.3 CfC2 Cecil sandy clay loam, 6 to 10 percent slopes, eroded 14,510 2.6 CfE2 Cecil sandy clay loam, 10 to 25 percent slopes, eroded 10,450 1.9 CK Chewacla and Congaree soils 4,980 0.9 DgB Davidson loam, 2 to 6 percent slopes 1,560 0.3 DhC2 Davidson clay loam, 6 to 10 percent slopes, eroded 1,485 0.3 DhE2 Davidson clay loam, 10 to 25 percent slopes, eroded 1,020 0.2 EnD Enon sandy loam, 10 to 15 percent slopes 4,365 0.8 FdB Faceville sandy loam, 2 to 6 percent slopes 125 <0.1 GcB Georgeville fine sandy loam, 2 to 6 percent slopes 4,400 0.8 GdC2 Georgeville clay loam, 6 to 10 percent slopes, eroded 4,610 0.8 GdE2 Georgeville clay loam, 10 to 25 percent slopes, eroded 2,550 0.5 GeB Grover sandy loam, 2 to 6 percent slopes 1,565 0.3 GeC Grover sandy loam, 6 to 10 percent slopes 2,380 0.4 GeD Grover sandy loam, 10 to 15 percent slopes 1,345 0.2 HeB Helena loamy coarse sand, 2 to 6 percent slopes 3,625 0.7 HeC Helena loamy coarse sand, 6 to 10 percent slopes 5,550 1.0 MdB Madison sandy loam, 2 to 6 percent slopes 2,550 0.5 MdC Madison sandy loam, 6 to 10 percent slopes 2,905 0.5 MdE Madison sandy loam, 10 to 25 percent slopes 3,075 0.6 MgD Madison-Grover complex, 6 to 15 percent slopes 935 0.2 NhB Norfolk loamy sand, 2 to 6 percent slopes 2,505 0.5 NhC Norfolk loamy sand, 6 to 10 percent slopes 1,070 0.2 OcB Orangeburg sandy loam, 2 to 6 percent slopes 1,535 0.3 OcC Orangeburg sandy loam, 6 to 10 percent slopes 1,310 0.2 Pm Pits, quarries 250 <0.1 Ro Roanoke silt loam 5 <0.1 Rx Rock outcrop 275 <0.1 TfB Tifton loamy sand, 2 to 6 percent slopes 480 <0.1 TsC Tifton sandy loam, 6 to 10 percent slopes 470 <0.1 Tv Toccoa loam 5,140 0.9 TwC Troup sand, 2 to 10 percent slopes 4,780 0.9 TwE Troup sand, 10 to 25 percent slopes 805 0.1 VeB Vaucluse loamy coarse sand, 2 to 6 percent slopes 330 <0.1 VeD Vaucluse loamy coarse sand, 6 to 15 percent slopes 2,020 0.4 W Water 13,330 2.4 WaB Wagram loamy sand, 2 to 6 percent slopes 8,345 1.5 WaC Wagram loamy sand, 6 to 10 percent slopes 3,915 0.7 WaD Wagram loamy sand, 10 to 15 percent slopes 1,150 0.2 WeB Wedowee loamy sand, 2 to 6 percent slopes 5,850 1.1 WeC Wedowee loamy sand, 6 to 10 percent slopes 12,875 2.3 WeD Wedowee loamy sand, 10 to 15 percent slopes 10,060 1.8 WeE Wedowee loamy sand, 15 to 25 percent slopes 9,470 1.7 Wf Wehadkee silt loam 1,935 0.4 WhB Wickham fine sandy loam, 2 to 6 percent slopes 410 <0.1 Wo Worsham sandy loam 395 <0.1 Note: Percentages do not add to 100 because the survey was done on a three-county basis (Columbia, Warren, McDuffie) and only the Columbia results were printed in the report.

Page 33: Columbia County Community Broadband Network

10‐14‐10  Page 32  

3.4 Water Resources   

Columbia County contains a variety of water resources.  The northern border of the county lies along  

Clarks Hill Lake, a man‐made reservoir through which the Savannah River flows.  Clarks Hill Lake (also 

known as J. Strom Thurmond Lake) covers 70,000 acres and was built circa 1950.  The uses for the lake 

include flood control, hydropower, and navigation, recreation, water quality, water supply, and 

fish/wildlife management.  The normal pool elevation is 330 feet above mean sea level and the 

shoreline encompasses 1,200 miles. 

 

The Savannah River forms part of the county’s northern border as well.  Four watersheds are located in 

Columbia County: the Savannah River watershed, the Little River watershed, the Middle Savannah River 

watershed, and the Brier Creek watershed.  The more significant streams and creeks that contribute 

water flows to these watersheds include Euchee Creek, Kiokee Creek, Little Kiokee Creek, Crawford 

Creek, and Greenbrier Creek.  Columbia County contains no coastal areas.   

 

Floodplain data has been researched from the FEMA website, and additionally Columbia County GIS has 

provided maps with the fiber network and proposed tower locations layered onto current floodplain 

data (see Appendix 5).   All floodplain areas in Columbia County are 100‐year floodplain; no 500‐year 

floodplains are indicated.   

 

 

3.5 Biological Resources / Critical Habitats   

As designated by the US Environmental Protection Agency 

(http://www.epa.gov/wed/pages/ecoregions/na_eco.htm#Level%20I) Columbia County may be 

classified in the following ecoregions:   

Level I – Eastern Temperate Forest 

Level II – Southeastern USA Plains 

Level III – Piedmont 

The fiber route will be constructed on pre‐disturbed roadways, and all 5 proposed tower sites are on 

existing developed County property.   

 

In accordance with Section 7(c) of the Endangered Species Act, as amended, 16 U.S.C. 1531 et seq.,  

CCCBN contacted the United States Fish and Wildlife Service and the Georgia Department of Natural 

Resources Wildlife Resources Division for the most updated species list and species accounts available.  A 

response from the US Fish and Wildlife Service in Athens, GA dated April 29, 2010 indicated that federally 

listed species are not likely to occur on the project sites (Appendix 6).  However, regarding the 5 towers, 

the agency recommended practices to minimize potential impacts to migratory birds, specifically to 

equip guy wires with bird diverters and light the tower only with white strobe lights with the maximum 

off period between flashes (3 seconds is current maximum allowable).  

 

The Georgia Department of Natural Resources Wildlife Resources office provided comprehensive data 

for county‐wide special concern animals, plants and natural communities.  This information is detailed in 

the spreadsheet “Columbia Co_Rare Species.xlsx” and is included in Appendix 6.       

Page 34: Columbia County Community Broadband Network

Columbia County Community Broadband Network (CCCBN)Core Areas and Connectors

#0

#0

#0

#0

#0

Draba aprica

Astergeorgianus

Trilliumreliquum

Astergeorgianus

Dryopteriscelsa

Hymenocalliscoronaria

Paronychia virginica

Scutellariaocmulgee

Amphianthus pusillusAnemoneberlandieri

Arabis missouriensis

BARE ROCK/LICHENS,PD GRANITE OUTCROP

Trilliumreliquum

Isoetestegetiformans

Sedum pusillum

SHRUB/SCRUBVEG., PD

GRANITE OUTCROP

Astergeorgianus

Cyprinella nivea

Cyprinella nivea

Pediomelum sp. 2

Bouteloua curtipendula

Clematis ochroleuca

Elliottia racemosa

Marshalliaramosa

Scutellariaocmulgee

PD XERIC BROADLEAFDECID.-NEEDLELEAF

EVER. FOREST

Pediomelum sp. 2

Portulacaumbraticola

ssp. coronata

Amphianthuspusillus

Anemone berlandieri

Drabaaprica

Isoetes tegetiformans

Portulacaumbraticola

ssp. coronata

Sedum pusillum

Portulacaumbraticola

ssp. coronata

Portulacaumbraticola

ssp. coronata

Amorphageorgiana var.

georgianaAmorphageorgiana var.

georgiana

Cyprinella nivea

Cyprinella niveaHaliaeetus

leucocephalus

L i n c o l nL i n c o l nC o u n t yC o u n t y

G e o r g i aG e o r g i a

E d g e f i e l d C o u n t yE d g e f i e l d C o u n t yS o u t h C a r o l i n aS o u t h C a r o l i n a

C o l u m b i aC o l u m b i aC o u n t yC o u n t y

G e o r g i aG e o r g i a

M c D u f f i eM c D u f f i eC o u n t yC o u n t y

G e o r g i aG e o r g i a

W a r r e nW a r r e nC o u n t yC o u n t y

G e o r g i aG e o r g i a J e f f e r s o nJ e f f e r s o nC o u n t yC o u n t y

G e o r g i aG e o r g i a

R i c h m o n dR i c h m o n dC o u n t yC o u n t y

G e o r g i aG e o r g i a

M c C o r m i c kM c C o r m i c kC o u n t yC o u n t y

S o u t h C a r o l i n aS o u t h C a r o l i n a

0 2 41 Miles

CCCBN Total Length: 220 MilesCore Sections

Connector

Inner Loop

Outer Loop

Lateral

Edgefield County Connector

Lincoln County Connector

McCormick County Connector

McDuffie County Connector

Richmond County Connector

#0 Stimulus

Flood ZoneZone A - No base flood elevations determined

Zone AE- Base flood elevations determined

Floodway

Shaded X - Areas of the 0.2% annual chance flood

X Zone - Areas outside the 0.2% annual chance flood

Main Roads

Roadways

Railroad

City Boundaries

Fort Gordon Ê

Page 35: Columbia County Community Broadband Network

10‐14‐10  Page 33  

3.6 Historic and Cultural Resources 

 

3.6.1 – Historic Overview 

The history of Columbia County dates back to the year 2,750 B.C. when the area’s first residents settled 

on Stalling’s Island, located in the eastern corner of the county. These early settlers were a group of 

shell‐mound builders and the area they settled is listed on the National Register of Historic Places due to 

its archaeological significance. The first European settlers to arrive in Columbia County during Colonial 

times were a small group of Quakers who came from the Carolinas. They purchased land from the Uchee 

Indians in 1751, but remained in the area for only a short time. During the 18th century, that area of the 

county was within the territory known as St. Paul’s Parish. In 1790, Columbia County was officially 

created from a part of Richmond County. It was named in honor of Christopher Columbus. 

 

Most settlers arriving in the area during the late 1700s hailed from the Virginias and Carolinas. Cotton 

reigned supreme as the chief crop in the area and afforded local settlers much prosperity. The Civil War 

significantly impacted the area and contributed to the loss of many of Columbia County’s finest citizens, 

much of its wealth, and the majority of its national political power. In the years that followed, the 

county focused on expansion of the Augusta Canal and new rail lines to serve the southeast as it tried to 

rebuild in the aftermath of the war. 

 

During the 20th century, one of the most significant impacts on the county was the establishment in 

1941 of the Camp Gordon military base (now Fort Gordon) in the southeastern portion of the county. As 

a result of the military presence in the area, no longer was farming the primary occupation in the 

county. Many residents retained their farms but pursued public jobs during World War II. Similarly, 

many of the men and boys who went off to war returned home to seek occupations other than farming. 

The construction of the Clark’s Hill Dam in 1946, and subsequent construction of the Atomic Energy 

Commission’s Savannah River nuclear plant in nearby Aiken County, also fueled new job growth in the 

area. Throughout the 1950s‐ 1960s Columbia County became an ever‐expanding bedroom community; 

and with the new residents came national retail chains and modern shopping centers, particularly in the 

Martinez area. 

 

The Columbia County Historical Society, once active in promoting awareness of the county’s historic, is 

now largely defunct. The City of Grovetown operates the Grovetown Museum which opened in 2000. 

The Grovetown Museum presents exhibits and orchestrates displays on Grovetown’s history. The City of 

Harlem operates the Laurel and Hardy Museum of Harlem Georgia because Oliver Hardy was born in 

Harlem. The museum contains movies, exhibits, and memorabilia associated with Laurel and Hardy and 

their comedic work. Responding to current growth pressures in the area, County residents have 

expressed interest in an intensified approach to preservation, but current efforts remain on a case‐by‐

case basis. 

 

The City of Harlem initiated a Historic Resources Survey in 2003. As a result of this survey the City has 

created a locally designated historic district surrounding North Louisville Street downtown, including 

both commercial and industrial properties. The City of Harlem also has a historic preservation ordinance 

Page 36: Columbia County Community Broadband Network

10‐14‐10  Page 34  

that aims to preserve the community’s identity and historic character. The Historic Preservation 

Ordinance established the Harlem Historic Preservation Commission, which oversees the design review 

process for the historic district. In conjunction with its historic preservation efforts, the City of Harlem 

has developed design guidelines for new development or renovation within the historic district. 

  

3.6.2 Current Historic and Cultural Findings  

In order to comply with Section 106 of the National Historic Preservation Act of 1966, the CCCBN 

consulted with the Georgia Historic Preservation Division of the Department of Natural Resources 

regarding the effect of the 200 mile fiber optic project on historic resources.  In a letter dated May 27, 

2010, the State Historic Preservation Office (SHPO) indicated that the fiber optic project would not 

affect historic and/or archaeological resources on the route. 

 

The project also includes 5 new communications towers to improve public safety coverage and facilitate 

additional fixed and mobile wireless broadband services to citizens throughout the county.  Property to 

be used for the project is county‐owned containing some type of county‐owned facility.  Pre‐fabricated 

above‐ground equipment buildings will be constructed next to the tower.  Approximate building 

dimensions are 10 feet x 15 feet (single story).  The concrete pad which will comprise the foundation for 

the tower can be assumed to be approximately 40’ wide x 40’ long x 6’ in depth.  Compounds will be 

fenced.  Land on which the towers will be located is pre‐disturbed and pre‐developed.  The towers will 

be 300 feet above ground level (AGL).   

 

Towers to be constructed for the BTOP program will be located at the following address and coordinates in 

Columbia County:   

 

ADDRESS  LATITUDE  LONGITUDE  PARCEL # 

480 White Road, Harlem, GA   33 deg 24’ 20” N  82 deg 17’ 20” W  Parcel 043A020 

6868 Cobbham Road, Appling GA   33 deg 36’ 37” N  82 deg 19’ 32” W  Parcel 025 047 

590 Baker Place Road 

Grovetown, GA 

33 deg 29’ 17” N 

 

82 deg 14’ 13” W 

 

Parcel 051 001B  

 

962 Halali Farm Road, Evans, GA  33 deg 34’15” N  82 deg 10’ 7” W  Parcel  065 021 

2292 County Camp Road, Appling, 

GA 

33 deg 32’ 14” N  82 deg 18’ 32” W  Parcel 028 057    

 

 

In compliance with Section 106 of the National Historic Preservation Act of 1966 (as amended), a records 

review  was  conducted  at  the  Georgia  Historic  Preservation  Division  (SHPO),  the  Georgia  Natural, 

Archaeological, and Historic Resources GIS  (NAHRGIS),  the National Register  Information Systems web 

site and the Georgia Archaeological Site Files to identify resources listed in the National Register of Historic 

Places (NRHP), eligible properties, state‐surveyed historic resources, and archaeological sites within a 0.75‐

mile radius of the proposed project.  Historic and archaeological findings are discussed below. 

   

Page 37: Columbia County Community Broadband Network

10‐14‐10  Page 35  

 

480 White Road 

Archaeology: An online review was of the National Register of Historic Places (NRHP) indicated that there 

are no NRHP‐listed archaeological sites within  the project APE. According  to  the Georgia Archaeological 

Site File, there are no archaeological sites located within a one‐mile APE of the proposed tower.  

 

Historic  Structures:  Resource  4923  is  located  on  the  north  side  of US  78  2,300  feet  northeast  of  the 

proposed tower.  It is a c. 1900 one room commercial building which was recommended eligible for listing 

on  the  NRHP  in  a  1991  survey.  During  the  2010  Section  106  survey,  the  resource  was  found  to  be 

dilapidated and considered not eligible for the NRHP.   

 

6868 Cobbham Road 

Archaeology: An online review was of the National Register of Historic Places (NRHP) indicated that there 

are no NRHP‐listed archaeological sites within  the project APE. According  to  the Georgia Archaeological 

Site File, there are no archaeological sites located within a one‐mile APE of the proposed tower. 

  

Historic Structures: Resource 4886 is located on the north side of Cobbham Road, approximately 800 feet 

northeast of  the proposed  tower site. This  resource was  identified as a circa 1920 Gabled wing cottage 

with no academic style with a T‐plan shape. This resource was identified as possibly meeting the National 

Register  criteria  in  a  1991  survey.  A  2010  survey  determined  that  the  resource  appeared  to  have 

maintained significance in materials; however, an ell may have been added to the older central hall house, 

thus causing it to lose its significance in design.  

590 Baker Place Road 

Archaeology: According to the Georgia Archaeological Site File, there are two archaeological sites and one 

report located within the 0.75‐mile APE of the proposed tower.  The sites are 9CB169 and 170.  The report 

is 4333.  No NRHP determination was made for the sites.   

 

Historic Structures: Based on research at the Georgia Historic Preservation Division and NAHRGIS, as well 

as the NRHP website, there are no NRHP‐listed resources and no state surveyed resources located within 

the  0.75‐mile  APE  for  visual  effects.  No  historic  or  archaeological  resources  eligible  for  the  National 

Register of Historic Places were encountered during the file review and field work 

 

962 Halali Farm Road 

Archaeology: An online review was of the National Register of Historic Places (NRHP) indicated that there 

are no NRHP‐listed archaeological sites within the project APE. A file review of the Georgia Archaeological 

Site File  indicated there are eight archaeological sites and six reports  located within the one‐mile APE of 

the proposed tower.   

 

 Historic Structures: Resource 4802 is located on Halali Farm Road approximately 2,000 feet south of the 

proposed  tower  site.    The  house  is  a  c.  1935 Georgia House with  Colonial  Revival  elements  and was 

recommended eligible for listing on the NRHP in a 1991 survey.  

Page 38: Columbia County Community Broadband Network

10‐14‐10  Page 36  

2292 County Camp Road 

Archaeology: A file review was conducted by the staff of the Georgia Archaeological Site File to determine 

if there are any archaeological sites located within a 1‐mile radius of the proposed project site.  According 

to the Georgia Archaeological Site File, there are two archaeological sites located within the 0.75‐mile APE 

of the proposed tower.  The sites are 9CB169 and 170.  No NRHP determination was made for the sites.   

 

Historic Structures: The NRHP‐listed Columbia County Courthouse (80536) is located approximately 4,700 

feet  northwest of  the  proposed  tower  just outside  of  the  0.75 mile APE.  This  Italianate  structure was 

constructed by  John Trowbridge  in 1856.  It  is  a brick bearing  two  story  structure with  flat  and  arched 

windows  and  decorative  Italianate  brackets  and  appears  to  be  in  excellent  condition.  State  surveyed 

resources  included 4843, an eligible c. 1940 free standing rectangular commercial building  located 1,000 

feet south of  the proposed  tower; 4845, an eligible c.1925 double  tower church with a Latin cross plan 

located on the west side of US 221 approximately 2,500 feet northwest of the proposed tower; and the 

following structures which make up the city of Appling:  4846, 4847, 4848, 4849, 4950, 4851, 4852, 4854, 

4855, 4856 which are within approximately 4,000‐5,000 feet northwest of the proposed tower.  Appling is 

made  up  of  front  gable Bungalows,  and American  Small House,  the NRHP  listed  courthouse,  and  free 

standing commercial buildings. The majority of the resources were recommended eligible for listing on the 

NRHP  in a 1991 survey.   A 2010 survey  indicated  that  the resources would be contributing  to a historic 

district.   

 

Fiber Optic Line 

With regard to historic properties connected with the 200‐mile fiber optic line, Columbia County has 

found four listings on the National Register of Historic Places.  These four sites are as follows: 

 

Columbia County Courthouse, Appling 

Kiokee Baptist Church, Appling 

Stallings Island (located within the Savannah River) 

Woodville (private residence, Winfield area) 

 

As an additional resource for researching historic properties and locations, the document “Columbia 

County Growth Management Plan Update – Community Assessment” (dated 2005) was reviewed and 

consulted.  This report references an inventory of historic resources in the county.  This report contained 

a list of 28 sites that were deemed “possible” to be included on the National Register of Historic Places.  

These sites included:   

 

1. “The Cedars,” c. 1885 

2. Macedonia Baptist Church, c. 1880 

3. Evans School Dormitory, c. 1900, corner of Belair and Washington 

roads 

4. Evans School Arch and Columns, c. 1925, corner of Belair and 

Washington roads 

5. G.B. Lamkin House, c. 1925, west side of Belair Road, 2nd building 

Page 39: Columbia County Community Broadband Network

10‐14‐10  Page 37  

south of Peachtree 

6. “Cedar Hill.” c. 1820 

7. Old Washington Road 

8. Damascus Baptist Church, c. 1900, north side of Ridge Road, 1 mile 

east of Washington Road 

9. Dunns’ Chapel, c. 1890, northwest corner of GA 47 and Ridge Road 

10. Winfield Area, c. 1840 

11. Sharon Church, 1869, south side of GA 150 across from 

intersection of Winfield Road 

12. William Few house site, c. 1930 

13. Shiloh Church, c. 1857, east side of GA 150, 1.5 mile southwest of 

Winfield Road 

14. Cedar Dale, c. 1858, east side of GA 150, 2 miles north of Cobbham 

Crossroads. 

15. Woodville, c. 1814 

16. Old Kiokee Church, c. 1804, west side of GA 47, ¼ mile north of US 

221 

17. Appling Community (multiple sites, c. 1850‐1925) 

18. Shucraft Road House, c. 1890 

19. Columbia Road at Hereford Farm Road, c. 1870 

20. Plantation House on Columbia Road, c. 1830 

21. Columbia Road, c. 1790 

22. Otts House, c. 1865, south side of Wrightsboro Road, ¾ mile west 

of US 221 

23. Wrightsboro Road, c. 1815 

24. Magruder Home, c. 1810 

25. Grovetown (multiple sites along Robinson Avenue) 

26. The Dodge House, c. 1910 

27. Campania 

28. Harlem (multiple sites, c. 1850) 

 

[Source: Columbia County Historic Resource Survey Report, Griffith Lamkin Polatty, 

December 5, 1990; Georgia Department of Natural Resources, Historic Preservation 

Division] 

 

As part of the environmental assessment requirements for the Georgia Historic Preservation Division, an 

Environmental Review Form was prepared and submitted (contained in Appendix 7).  Part of the effort 

required to complete this form was an investigation of all buildings in Columbia County that are 50 years 

of age or older (a complete list of all 50‐year old buildings is included in Appendix 7).  Working with the 

county’s GIS and property records departments, a list of 50‐year old properties was developed and 

cross‐referenced to the scope of the project.  This effort yielded a list of 6 buildings that are over 50 

years old and which will also be connected to the Broadband network.  These buildings make up the 

“Area of Potential Effect” (APE) and can be summarized as follows: 

Page 40: Columbia County Community Broadband Network

10‐14‐10  Page 38  

 

Parcel  Title  Owner  Year 

Built 

Effective  

Year 

Built 

Description EW 

Description 

Property 

Use 

Property 

Address 

G06 

073 

Grovetown 

Museum 

City of 

Grovetown 

1935 1980 1.5 story Vinyl 

Dwelling 

Vinyl Siding Resid. 

Finish – 

Office, 

General 

Govt. 

103 Old 

Wrightsboro 

Rd 

H02 

036 

Harlem 

Library 

City of 

Harlem 

1930 1970 1 story Vinyl 

Library 

Vinyl Siding Resid. 

Finish 

375 N. 

Louisville St 

H03 

073 

Harlem 

Middle 

School 

Columbia 

County 

Board of 

Education 

1935 1983 School 

Auditorium 

Face Brick 

Veneer 

Elem.  

and Sec. 

School 

375 W 

Forrest St. 

H03 

157 

Harlem 

Police Dept 

City of 

Harlem 

1950 1971 Old City Hall / 

Jail 

Face Brick 

Veneer 

Office, 

General 

Govt. 

and jail 

180 N 

Louisville St 

026 

017 

North 

Columbia 

Elem. 

School 

Columbia 

County 

Board of 

Education 

1956 1990 North 

Columbia 

School 

Face Brick 

Veneer 

Elem.  

and Sec. 

School – 

Gym. 

2874 Ray 

Owens Rd 

072 

143 

Evans 

Elem. 

School 

Columbia 

County 

Board of 

Education 

1956 1985 Evans 

Elementary 

Com Brick 

on Concrete 

Block 

Elem.  

and Sec. 

School – 

Gym. 

628 Gibbs 

Rd 

 

All of these buildings are functioning buildings which contain ongoing county business, and are 

referenced in the Georgia Historic Preservation Division’s Environmental Review Form as the “Area of 

Potential Effect” (APE).  Photographs for all 6 of these buildings are included below:   

 

   

Page 41: Columbia County Community Broadband Network

10‐14‐10  Page 39  

Grovetown Museum: 

   

    

   

Page 42: Columbia County Community Broadband Network

10‐14‐10  Page 40  

Grovetown City Hall area: 

  

Page 43: Columbia County Community Broadband Network

10‐14‐10  Page 41  

Harlem Library: 

   

  

   

Page 44: Columbia County Community Broadband Network

10‐14‐10  Page 42  

Harlem Library: 

  

Page 45: Columbia County Community Broadband Network

10‐14‐10  Page 43  

Harlem Middle School: 

    

    

Page 46: Columbia County Community Broadband Network

10‐14‐10  Page 44  

Harlem Middle School Area: 

  

Page 47: Columbia County Community Broadband Network

10‐14‐10  Page 45  

Harlem Police Department: 

   

  

   

Page 48: Columbia County Community Broadband Network

10‐14‐10  Page 46  

Downtown Harlem area: 

 North Columbia Elementary: 

Page 49: Columbia County Community Broadband Network

10‐14‐10  Page 47  

   

    

Page 50: Columbia County Community Broadband Network

10‐14‐10  Page 48  

North Columbia Elementary area: 

  

Page 51: Columbia County Community Broadband Network

10‐14‐10  Page 49  

Evans Elementary: 

   

    

Page 52: Columbia County Community Broadband Network

10‐14‐10  Page 50  

Evans Elementary area: 

    

Page 53: Columbia County Community Broadband Network

10‐14‐10  Page 51  

Research into tribal cultural properties indicates there are no Indian reservations or tribal lands within 

the Columbia County Community Broadband Network or within Columbia County in general.  A map 

indicating Federal Lands and Indian Reservations in the State of Georgia can be found at 

www.nationalatlas.gov and is located in the appendices.  Archaeologist David Saunders, Eastern 

Regional Office, Bureau of Indian Affairs, has confirmed the finding that no reservations or tribal lands 

are located within Columbia County.   

 

Tribal information for the 5 towers was obtained from NTIA.  The Shawnee Tribe has indicated interest 

in the 5 towers and has requested further information.  The Form 620 and SHPO responses were 

forwarded to the tribe. 

 

3.7 Aesthetic and Visual Resources 

Columbia County borders on the Clarks Hill Lake, which is a man‐made lake controlled and administered 

by the US Army Corps of Engineers.  The project will not impact the shoreline or viewshed of the Clarks 

Hill reservoir.  The county contains one state park (Mistletoe State Park) and one county park (Wildwood 

Park).  Wildwood Park is leased by the county on land owned by the Corps of Engineers.    The project 

will include a new fiber optic cable route into Wildwood Park.    

 

 3.8 Land Use 

Columbia County has mixed land use including varying degrees of the following:  Commercial, Industrial, 

Office/Professional, Governmental, Recreation, State and Federal Highways.  Most of the acreage of the 

county still consists of undeveloped land, which is designated to remain undeveloped in future land use 

plans.  The southern tip of the county contains part of Fort Gordon, a US Army post (which 

predominantly lies in Augusta/Richmond County).  The northern part of the county borders on Clarks Hill 

reservoir (US Army Corps of Engineers).   

 

The county contains two incorporated cities, Harlem and Grovetown.  It also contains the census‐

designated places of Evans and Martinez, which border the metropolitan Augusta GA area.  Although 

not an incorporated city, the County Seat of Columbia County is Appling.  However the Columbia County 

government is based in Evans.   

 

3.9 Infrastructure 

Columbia County has a mixture of county‐owned and other infrastructure in place.  The county is 

bisected from east to west by Interstate 20.  There are several state highways present throughout the 

county.  The county maintains a public water system primarily in the more populated areas of Evans and 

Martinez.  The cities of Grovetown and Harlem maintain their own water systems.  The major 

commercial utilities present in the county are Georgia Power (a division of the Southern Company), 

AT&T (formerly BellSouth), Comcast, Charter, and Knology. Wireless carriers include AT&T, Verizon, T‐

Mobile, and Sprint.  The objective of the CCCBN project is to enhance and improve the existing 

telecommunications infrastructure provided by the existing carriers.  

   

Page 54: Columbia County Community Broadband Network

10‐14‐10  Page 52  

3.10 Socioeconomic resources 

The estimated population for Columbia County for 2008 is 108,276, according to US Census figures 

(http://factfinder.census.gov).  Racial population demographics are estimated as follows: 

 

White            78.7% 

Black or African American      14.5% 

American Indian or Alaska Native    0.2% 

Asian            3.3%   

Native Hawaiian and other Pacific Islander  0.0% 

Other Race          1.3% 

Two or more races        2.0% 

Hispanic or Latino (of any race)       3.2% 

Other demographic information is as follows: 

Male            48.4% 

Female            51.6% 

Median Age          35.9 

Under 5 years          7.1% 

18 years and over        72.7% 

65 years and over        9.1% 

 

Generally speaking the areas in the north and east areas of the county, including Evans and Martinez, 

tend to be higher‐income areas.  The lower income areas tend to be in the southern and western parts 

of the county.  These include some areas in and around the cities of Harlem and Grovetown.  The 

application which requested the ARRA Broadband stimulus funding identified several areas which are 

considered “unserved” and “underserved” for the areas of Broadband availability.  All of the unserved 

areas were found to be in the Harlem and Grovetown areas, as were several of the underserved areas.   

 

3.11 Human Health and Safety 

Per the map obtained from the EPA’s website (http://iaspub.epa.gov/Cleanups/), Columbia County finds 

there are no Brownfield or Superfund/RCRA clean‐up sites, as shown in the graphic below.  There are 

also no sites in Columbia County which are contained on the National Priorities List ‐‐

(http://www.epa.gov/superfund/sites/query/queryhtm/nplfin.htm#GA).   

  

 

 

 

Page 55: Columbia County Community Broadband Network

10‐14‐10  Page 53  

Chapter 4 ‐ Environmental Consequences  

 

4.1 Noise   

The area of construction is both rural and suburban in nature, and thus ambient noise levels vary.  It can 

be assumed that the higher noise levels in the construction areas will coincide with the corridors of state 

and county roadways already in existence.   All of the fiber optic construction will be located within the 

traffic corridors and within the right of way of existing paved roads.  The cable will be constructed using 

specialized construction equipment designed for the purpose of installing buried and underground 

cables.  Typical noise levels from this type of equipment range from 70‐90 dBA.   These noise levels will 

be temporary in nature and will not significantly add to the ambient noise levels found along the road 

corridors at present.   

 

In the case of tower construction, similar parameters will apply.  The towers will also be constructed 

using specialized construction equipment designed for that purpose.  They will not be constructed on 

right of ways, but will be constructed on county‐owned property parcels adjacent to and accessible via 

state and county roadways.  Noise levels attributed to tower construction will also be minor and 

temporary in nature and will not significantly add to the ambient noise levels found in these properties 

at present.   

 

4.2 Air Quality   

The construction will take place using specialized, mechanized equipment (backhoes, trenchers, plowing 

rigs, directional bore machines, cranes, etc.) whose exhaust will be released into the surrounding air, but 

the construction of the fiber optic cable and towers will not cause a detrimental effect on the existing air 

quality of Columbia County.  The construction will be concentrated within or near the existing road 

corridors which already have the presence of automobiles and trucks; the additional exhausts from the 

construction equipment will not have a significant additive effect or potential detrimental effects.    

 

4.3 Geology and Soils   

 Since the construction will take place within right of way of existing roadways, as well as county‐owned 

land parcels that have been previously disturbed, the project will have no impact on prime or unique 

farmlands, as defined in the Farmland Protection Policy Act (FPPA).   

 

A large degree of the construction of the fiber optic cable will be via underground placement.  

Construction techniques include direct burial, trenching, plowing, directional boring, and micro‐

trenching.  All construction will take place within the right of way of existing roadways in pre‐disturbed 

areas.  Soil disturbances using these methods will be minor and temporary in nature.  Trench 

dimensions will vary, but can be nominally summarized as 36” maximum depth, with 12” maximum 

width.  Open trenches will not be left for extended periods of time.  Trenches and other ground 

openings will be backfilled with the existing soil types initially removed.   

 

Page 56: Columbia County Community Broadband Network

10‐14‐10  Page 54  

Tower foundations will require excavations to depths to be determined by a variety of factors.  The 

structural design of the towers will specify the detailed requirements of the excavations and backfills.  

Tower foundations will be secured using reinforced concrete below grade.  All towers will be erected on 

county‐owned land parcels which have been previously disturbed.   

 

4.4 Water Resources   

The Columbia County Community Broadband Network will be constructed in previously‐disturbed 

roadway rights‐of‐way. All wetlands crossed by the network are taken from National Wetland Inventory 

location data. All proposed tower sites will be constructed on county‐owned high ground for maximum 

signal propagation, well above any wetland areas.  

 

Since the fiber optic construction will take place in the right of way of existing roadways, the fiber will 

occasionally cross streams and creeks. In the overwhelming majority of such cases, these crossings will 

take place using directional boring techniques.  When directional boring is used, the bore pits will be set 

outside the waterway boundaries and the depth of the bore will be such that the stream bed will be 

crossed underneath at such a depth as to not impact the waterway. 

 

In rare instances, it is possible that “aerial inserts” may occasionally be used for stream crossings.  In an 

aerial insert, new poles would be installed on both sides of the stream or creek buffer zone, and aerial 

plant installed between the new poles, over the waterway.  The insert poles would be set outside the 

stream beds and waterway boundaries, thereby insuring that the waterways will not be adversely 

impacted by these construction techniques.   

 

Both techniques for crossing waterways are widely used for cable construction projects of this type and 

are frequently permitted by federal, state, and local permitting bodies. The USACE has indicated a 

willingness to coordinate easements required for installation of the fiber optics on Thurmond Project 

lands. Coordination is planned between the USACE, Georgia EPD, and the CCCBN to expedite permitting 

regarding wetlands, Corps Property and stormwater runoff. 

 

The US Army Corps of Engineers (USACE), Savannah District, was contacted regarding the CCCBN project 

and its effect on Corps Property.  The USACE indicated that the broadband network would allow for 

services to be porvided to the public that have not been readily available and would allow the Corps to 

better coordinate public safety and law enforcement services.  The Corps indicated a willingness to 

coordinate easements required for installation of the fiber optics on Thurmond Project lands (see 

Appendix 5).  An email dated July 20, 2010 from Senior Project Manager Stanley J. Knight, indicated that 

the project will more than likely require a Department of Army Permit.  CCCBN personnel have 

requested a meeting with USACE personnel to set up a pre‐construction pre‐application consultation 

meeting to expedite the permitting process.  In addition, CCCBN personnel have met with USACE 

personnel at some of the locations where fiber and termination points will be placed on Corps Property. 

   

In addition, the USACE Savannah District has announced that expedited permitting in the form of 

Regional General Permits (RGP) will be approved for projects funded under the American Recovery and 

Page 57: Columbia County Community Broadband Network

10‐14‐10  Page 55  

Reinvestment Act (ARRA) that meet all requirements of the Clean Water Act and the National 

Environmental Policy Act.  To use a regional permit, an applicant must receive approval from the Corps 

verifying that the project meets the requirements of the RGPs and must obtain separate individual 

Water Quality Certification from Georgia EPD.  The CCCBN intends to obtain approval from both the 

Corps and EPD. 

 

A National Pollution Discharge Elimination System (NPDES) permit for Storm Water Discharges 

associated with construction activities will be sought from the Environmental Protection Division of the 

Georgia Department of Natural Resources (see Appendix 5).   All construction contractors will be 

required to abide by the State of Georgia’s Best Management Practices rules and regulations.  

Contractors will be required to attend and receive a Georgia Soil and Water Conservation Fundamentals 

Level 1A certification.  Information on the certification can be found at 

http://www.files.georgia.gov/SWCC/Files/Education%20and%20Certification%20Policies%20and%20Pro

cedures.pdf.  Guidelines can be found at the Georgia Soil and Water Conservation Commission, 

http://www.gaepd.org/Files_PDF/techguide/esc_manual/Chapter_6.pdf and 

http://www.gaswcc.org/docs/ag_bmp_Manual.pdf.   

 

 

4.5 Biological Resources / Critical Habitats   

The fiber route will be constructed on pre‐disturbed roadways, and all proposed tower sites are on 

existing pre‐developed County property. Section 3.5 included a map from the US Fish and Wildlife 

Service showing that no critical habitats are located in Columbia County. The fiber project will have no 

impact on species listed.   The CCCBN has received concurrence in this regard from the USFWS; however 

the USFWS has requested stipulations regarding migratory birds on the 5 towers in Columbia County. 

The CCCBN has agreed to the stipulations and will implement them to minimize effects of the towers on 

migratory birds.   These USFWS practices will be put into place during and after tower construction. The 

towers planned for this project will be 300‐foot self‐support towers, therefore bird diverters are not 

applicable.  In addition, specifications will require that the lights for the towers will be white in color and 

operating for 3 second off periods between flashes, as requested by the US Fish and Wildlife office.  A 

copy of the correspondence received from the US Fish and Wildlife Office is included in Appendix 6.   

 

4.6 Historic and Cultural Resources 

According to a Program Comment for Streamlining Section 106 Review for Wireless Communication 

Facilities Construction and Modification Subject to Review Under the FCC Nationwide Programmatic 

Agreement and/or the Nationwide Programmatic Agreement for the Collocation of Wireless Antennas 

issued by the Advisory Council on Historic Preservation (Federal Register /Vol. 74, No. 223 / Friday, 

November 20, 2009): When an NTIA undertaking includes both communications facilities construction or 

modification covered by the FCC Nationwide PA or Collocation PA and components in addition to such 

communication facilities construction or modification, RUS, NTIA, or FEMA, as applicable, will comply 

with Section 106 in accordance with the process set forth at 36 CFR 800.3 through 800.7, or 36 CFR 

800.8(c), or another applicable alternate procedure under 36 CFR 800.14, but will not have to consider 

the effects of the communication facilities construction or modification component of the undertaking 

Page 58: Columbia County Community Broadband Network

10‐14‐10  Page 56  

on historic properties.  NTIA has applied this Program Alternative as stipulated in 36 CFR 800.14 (e) in 

lieu of reviewing proposed telecommunications towers which are undergoing Section 106 review under 

the FCC Nationwide Programmatic Agreement.   

 

Additionally, in order to comply with Section 106 of the National Historic Preservation Act of 1966, the 

CCCBN consulted with the Georgia Historic Preservation Division of the Department of Natural 

Resources regarding the effect of the 200 mile fiber optic project on historic resources. The State 

Historic Preservation Office (SHPO), in a letter dated May 27, 2010, indicated that the fiber optic project 

would not affect historic and/or archaeological resources on the route. All 5 towers have received SHPO 

concurrence indicating no effect on archaeological resources.  Three of the 5 towers have received 

concurrence letters of no effect or no adverse effect from the SHPO; however, there are two towers in 

which an adverse effect is anticipated:  Halali Farm Road and Cobbham Road (Appendix 7).  

 

6868 Cobbham Road 

Resource 4886  is  located on  the north side of Cobbham Road, approximately 800  feet northeast of  the 

proposed tower site.   In a letter dated July 19, 2010 the Georgia SHPO determined that the tower would 

have an adverse effect on Resource 4886 (Appendix 7). 

 

962 Halali Farm Road 

Resource 4802 is located on Halali Farm Road approximately 2,000 feet south of the proposed tower site.    

In a letter dated July 19, 2010 the Georgia SHPO concurred that the tower would have an adverse effect on 

the resource (Appendix 7). 

 

A summary of SHPO responses can be found in the table below: 

 

TOWER  SHPO DETERMINATION 

480 White Road, Harlem, GA 30814  No Adverse Effect 

6868 Cobbham Road, Appling GA 30802  Adverse Effect on Resource 

590 Baker Place Road 

Grovetown, GA 

No Effect 

962 Halali Farm Road  Adverse Effect on Resource 

2292 County Camp Road  No Adverse Effect 

 

In summary, there are two towers in which an adverse effect is anticipated, Halali Farm Road and 

Cobbham Road, based on the SHPO correspondence (Appendix 7).  The Georgia SHPO has indicated a 

willingness to engage in mitigation regarding these towers.  To that end, an Memorandum of Agreement 

(MOA)  was written and submitted to the Georgia SHPO.   The Georgia SHPO’s mitigation project 

involves research on resources that have become 50 years of age or older since the last survey was 

conducted in the county.  Tax assessors information will be field checked for dates of construction in a 

corridor along Route 221/47 north of Harlem to the intersection with Ray Owens Road to the county 

line/lake, a distance of approximately 14 miles, with an Area of Potential Effect (APE) of one mile on 

either side of the highway.  The MOA was accepted and signed by the Georgia SHPO, the FCC, and 

Page 59: Columbia County Community Broadband Network

10‐14‐10  Page 57  

Columbia County.  An  FCC Environmental Assessment and the signed MOA for the adverse effect towers 

is included in the appendix as an addendum.   

Tribal information for the 5 towers was obtained from NTIA.  The Shawnee Tribe indicated interest in 

the 5 towers and requested further information.  The Form 620 and SHPO responses were forwarded to 

the THPO, who subsequently responded with no interest (see appendix). 

 

Fiber Optic Line ‐‐ Of the buildings and structures referenced in Chapter 3, none are planned to be 

connected to the new fiber optic network and will not be affected by network construction.  The 

Columbia County Courthouse is near the fiber route but will not be impacted by construction.  It is in use 

as an active government building, and currently has installed network connectivity devices.  These will 

be upgraded during project implementation to better serve county residents.   

 

4.7 Aesthetic and Visual Resources 

 The project will not impact the shoreline or viewshed of the Clarks Hill reservoir. Mistletoe State Park 

will not be impacted by the project, as the closest construction activity will be approximately 4 miles 

away from the park. The project will include a new fiber optic cable route into Wildwood Park. The 

Corps of Engineers has been consulted during the planning of the project; the Corps has given its 

approval of the planned routes. The project will obtain all necessary permits from the Corps before 

construction in Wildwood Park. The shoreline of the lake will not be impacted by construction. 

 

Visual viewshed impacts on sensitive resources such as parks, waterways, trails, and scenic byways will 

not occur. The fiber optic cable route will not traverse sensitive resources. The 5 Columbia County 

towers associated with the project are not visible from sensitive resources and therefore have no 

impact. 

 

4.8 Land Use 

The project will not result in any changes in the land use classification for any areas of the county.  Since 

all of the fiber optic cable will be installed in existing road rights‐of way, the land used for construction 

will remained classified as “roads”.  In the case of tower construction, the towers will be constructed on 

county‐owned land parcels.  The classification of these areas will remain “government/institutional”.   

 

4.9 Infrastructure 

The Columbia County Community Broadband Network project represents a marked improvement in the 

county’s telecommunications infrastructure.  The telecommunications infrastructure will be significantly 

improved by the installation of fiber optic network into areas of the county which are unserved and 

underserved.  The new communications towers will result in improved wireless coverage for public 

safety and mobile broadband providers.   

 

The project will not have an adverse effect on any of the existing power, natural gas, waste disposal, or  

water infrastructure present in the county.  Experienced engineers will design the project in such a way 

as to avoid conflict with and disruption of existing infrastructure.  All required permits will be obtained 

Page 60: Columbia County Community Broadband Network

10‐14‐10  Page 58  

during the engineering phase of the project.  The engineers will provide inspectors for all construction 

crews in order to insure that the new facilities are installed properly without disruption to existing 

utilities.   

 

4.10 Socioeconomic resources 

One of the stated goals of the project is to improve the broadband services available to underserved and 

unserved areas of the county’s population.  These areas tend to coincide with the lower‐income areas of 

the county, many of which contain minority populations.  For this reason it is anticipated that the 

project will have a very positive impact for these groups.  No detrimental effects are anticipated from 

the project, which is expected to spur economic growth opportunities throughout the county.   

 

Completion of the proposed project will have a dramatically positive effect on the socioeconomic status 

of Columbia County and its citizens.  In the near term, it will result in increased jobs resulting from the 

construction of the network.  The construction will take place over an approximate two‐year interval.  

The grant application estimated that a total of 195 jobs would be created as a result of the construction 

of the network.  

 

The long‐term socioeconomic impact of the project will be even more beneficial to the county.  To a 

great extent, it is for the long‐term benefit to the county that the project was envisioned and 

implemented.  Establishing a fiber optic broadband network throughout all areas of the county will 

provide infrastructure that can be used to attract a high‐tech workforce.  This is expected to result in 

hundreds of additional jobs as new employers will be attracted to Columbia County.  The grant 

application had numerous letters of support, including a letter from the Columbia County Development 

Authority, the organization charged with advancing commerce and industry within the county.  The 

letter states, “reliable broadband service and access is vital for business growth – growth that can lead 

to greater employment opportunities for residents in the county and to an increased level of capital 

investment in the county.”  It also states, “the need for broadband will become critical to the county’s 

economic survival”. 

 

4.11 Human Health and Safety 

The County contains no hazardous waste sites, Superfund sites, or brownfield sites.  The project will not 

create any such sites.  By following existing rights‐of‐way and building towers on existing developed 

County property, Columbia County research indicates no pollutant issues will appear with the project.  

 

The project will require extensive use of heavy equipment to install the fiber optic cable along roadways 

and to install towers on county‐owned properties.  The cable construction will take place within the 

existing rights‐of‐wayof existing roads.  Construction is typically concentrated in the outermost 5 feet of 

the right‐of‐way, away from the roadway traffic.   

 

Safety will be a primary concern for all parties associated with the construction.  This includes 

construction engineers, construction crews, construction inspectors, and all personnel involved in the 

construction process.  In today’s business environment, engineering and construction companies place 

Page 61: Columbia County Community Broadband Network

10‐14‐10  Page 59  

an extraordinary amount of emphasis on training workers in adequate safety programs.  Proper safety 

techniques will be used in all aspects of the construction.  Contractors typically have their own Safety 

Manual and hold regular “tailgate meetings” to insure that workers are adequately trained in safety.  

These safety techniques insure that workers as well as the general public are protected from any 

potentially dangerous consequences from the construction.   

 

In addition to safety procedures, contractors must be properly licensed in order to perform certain 

construction activities.  For example, any contractors wishing to install underground facilities below a 

depth of 5 feet must have a Utility Construction license which demonstrates that they are adequately 

trained and insured for such activities.    

 

There are no known health issues associated with a distribution system for fiber optic cable. It does not 

give off any electromagnetic field and collocated fiber optic lines do not interfere with each other. Fiber 

optic cable does not interfere with other utility transmission lines, such as telephone, cable, and electric 

distribution. It is expected that all workers installing cable would adhere to construction safety 

procedures and the appropriate traffic and roadside safety practices would be implemented.  

The construction contractors will provide for a prompt rescue plan of employees in the event of a fall or 

shall assure that employees are able to rescue themselves.  The contractor employees must be prepared 

to retrieve a fallen worker within minutes. The contractor must ensure employees being exposed to 

elevations above 6 feet use and maintain 100% fall protection systems compatible with the tasks 

assigned.   

Tower workers responsible for rigging must be able to provide documented proof of rigging training 

including an understanding of slings, blocks, reeving, strength calculations, winches, hydraulics, tagging, 

riding the winch line and rigging hardware.   In addition, safety standards and procedures mandated by 

the Occupational Safety and Health Administration (OSHA) and the GADOT will be applied to this work. 

For these reasons there are no expected detrimental effects anticipated regarding the Human Health 

and Safety of the County.   

 

   

Page 62: Columbia County Community Broadband Network

10‐14‐10  Page 60  

Chapter 5 ‐ Applicable Environmental Permits and Regulatory Requirements    

Consultation has been sought from the following Federal, state, and local agencies: 

US Army Corps of Engineers 

US Fish and Wildlife Service 

Tribal Historic Preservation Officer 

Georgia State Historic Preservation Office 

Georgia Environmental Protection Division 

The following table indicates the applicable permitting and regulatory requirements, the regulatory 

agency involved, the status of the project compliance, and further action. 

 Regulatory Agency  Permitting/Regulatory

Requirements Description Status Further Action

US Army Corps of 

Engineers Department of Army 

Permit Permitting for 

wetlands, Corps 

Property 

USACE notified Obtain RGP permit in 

conjunction with State 

EPD US Fish and Wildlife 

Service Section 7 Consultation Consultation 

regarding effect of 

fiber optics and 

towers on Threatened 

and Endangered 

Species and Critical 

Habitats 

Response received 

from USFWS. No T&E 

species will be 

affected by the fiber 

optic route. USFWS 

recommends 

selfsupport tower 

type and specific 

lighting to minimize 

effects to migratory 

birds. 

The only remaining further action is to install medium intensity strobes on the towers at the time of construction, per the USFWS request to minimize effects to migratory birds.   

Tribal Historic 

Preservation Officer Tribal Consultation 

required through Section 

106 of NHPA 

Consultation 

regarding effect of 

fiber optics and 

towers on areas of 

tribal significance. 

Shawnee Tribe 

requests Form 620 

and SHPO response 

on the 5 towers.  

These documents will 

be forwarded to the 

Shawnee. 

Concurrence letter 

received.  No further 

action. 

Georgia State Historic 

Preservation Office Historic preservation 

and archaeological 

resources through 

Section 106 of NHPA 

Consultation 

regarding effect of 

fiber optics and 

towers on areas of 

historic and 

archaeological 

significance. 

Georgia SHPO 

indicates fiber optic 

project will have no 

effect on historic 

resources. Regarding 

5 towers, adverse 

effect on two towers: 

Halali Farm Road and 

Cobbham Road. 

Mitigation on Halali 

Farm and Cobbham 

Road.  FCC 

Environmental 

Assessment and signed 

MOA for the adverse 

effect towers is included 

in the appendix as an 

addendum.  

Georgia Environmental 

Protection Division NPDES permit  Consultation 

regarding effect of 

fiber optics and 

towers on stormwater 

runoff. 

Georgia EPD notified 

regarding Stormwater 

NPDES permit for 

Storm Water 

Discharges 

Obtain NPDES permit

Page 63: Columbia County Community Broadband Network

10‐14‐10  Page 61  

 

The preferred alternative will build fiber optic cable within the right‐of‐way of existing roadways, and to 

build communications towers on previously developed county‐owned property parcels. These activities 

present the best solution to meet the needs and problems of the project, and they are not anticipated 

to adversely affect the environment. 

   

Page 64: Columbia County Community Broadband Network

10‐14‐10  Page 62  

 

 

Chapter 6 ‐ List of Preparers    

Lewis Foster 

Broadband Utility Manager 

Columbia County Board of Commissioners 

PO Box 498 

630 Ronald Reagan Drive, Building A  

Evans, GA 30809 

 

Mary Howard, GISP 

GIS Manager 

Columbia County Board of Commissioners 

630 Ronald Reagan Drive, Building B  

Evans, GA 30809 

 

Mike Martin, P.E.  

Engineering Associates, Inc.  

1220 Old Alpharetta Rd, Suite 390 

Alpharetta, GA 30022 

 

S. Lorraine Norwood, MA 

Terracon Consultants, Inc. 

2855 Premiere Parkway, Suite C 

Duluth, GA 30097 

   

Page 65: Columbia County Community Broadband Network

10‐14‐10  Page 63  

   

Chapter 7 ‐  References  

The following websites were consulted for this Environmental Assessment: 

 

Noise Pollution Clearinghouse:  www.nonoise.org  

Currently Designated Nonattainment Areas for All Criteria Pollutants:  

http://www.epa.gov/air/oaqps/greenbk/ancl3.html  

National Resources Conservation Service:  http://soildatamart.nrcs.usda.gov/Default.aspx  

Tapestry of Time and Terrain: Physiographic Regions: 

http://tapestry.usgs.gov/physiogr/physio.html  

US Fish and Wildlife Service, Migratory Birds: 

http://www.fws.gov/migratorybirds/mbpermits.html  

Ecoregions of North America: 

http://www.epa.gov/wed/pages/ecoregions/na_eco.htm#Level%20I  

American Fact Finder, US Census Bureau: 

http://factfinder.census.gov/servlet/ACSSAFFFacts?_event=&geo_id=05000US13073&_geoCont

ext=01000US|04000US13|05000US13073&_street=&_county=columbia&_cityTown=columbia&

_state=04000US13&_zip=&_lang=en&_sse=on&ActiveGeoDiv=&_useEV=&pctxt=fph&pgsl=050

&_submenuId=factsheet_1&ds_name=null&_ci_nbr=null&qr_name=null&reg=null%3Anull&_ke

yword=&_industry= 

US EPA, National Priorities List: 

http://www.epa.gov/superfund/sites/query/queryhtm/nplfin.htm#GA  

Wildwood Park Draft Environmental Assessment, US Army Corps of Engineers:  

http://www.sas.usace.army.mil/Wildwood%20Park%20%20DRAFT%20EA%20%20Mar10.pdf  

 

 

The following reports and documents were consulted: 

 

Columbia County Growth Management Plan Update – Community Assessment (June 2005).  

Prepared for the County by EDAW.  Found on‐line at:  

http://www.columbiacountyga.gov/Index.aspx?page=2976 

 

 

 

 

   

Page 66: Columbia County Community Broadband Network

10‐14‐10  Page 64  

Appendix 1  

Maps 

   

Page 67: Columbia County Community Broadband Network
Page 68: Columbia County Community Broadband Network
Page 69: Columbia County Community Broadband Network
Page 70: Columbia County Community Broadband Network

10‐14‐10  Page 65  

Appendix 2  

Aerials 

 

 

 

   

Page 71: Columbia County Community Broadband Network
Page 72: Columbia County Community Broadband Network
Page 73: Columbia County Community Broadband Network
Page 74: Columbia County Community Broadband Network
Page 75: Columbia County Community Broadband Network
Page 76: Columbia County Community Broadband Network
Page 77: Columbia County Community Broadband Network
Page 78: Columbia County Community Broadband Network
Page 79: Columbia County Community Broadband Network
Page 80: Columbia County Community Broadband Network

10‐14‐10  Page 66  

Appendix 3  

Georgia Technology Authority slide 

   

Page 81: Columbia County Community Broadband Network
Page 82: Columbia County Community Broadband Network

7-23-10 Page 67

Appendix 4

Air Quality

Page 83: Columbia County Community Broadband Network
Page 84: Columbia County Community Broadband Network
Page 85: Columbia County Community Broadband Network

��������� ������

�Appendix�5��Water�Resources����� �

Page 86: Columbia County Community Broadband Network
Page 87: Columbia County Community Broadband Network

Columbia County Community Broadband Utility (CCCBU)Broadband Master Plan and Countywide Floodplain

#0

#0

#0

#0

#0

M c C o r m i c k C o u n t yM c C o r m i c k C o u n t yS o u t hS o u t h

C a r o l i n aC a r o l i n a

L i n c o l nL i n c o l nC o u n t yC o u n t y

G e o r g i aG e o r g i a

E d g e f i e l d C o u n t yE d g e f i e l d C o u n t yS o u t h C a r o l i n aS o u t h C a r o l i n a

C o l u m b i aC o l u m b i aC o u n t yC o u n t y

G e o r g i aG e o r g i a

M c D u f f i eM c D u f f i eC o u n t yC o u n t y

G e o r g i aG e o r g i a

W a r r e nW a r r e nC o u n t yC o u n t y

G e o r g i aG e o r g i a

R i c h m o n dR i c h m o n dC o u n t yC o u n t y

G e o r g i aG e o r g i a

J e f f e r s o nJ e f f e r s o nC o u n t yC o u n t y

G e o r g i aG e o r g i a

0 2 41 Miles

CCCBU Total Length: 220 Miles

#0 Stimulus

MasterPlan Broadband

Flood ZoneZone A - No base flood elevations determined

Zone AE- Base flood elevations determined

Floodway

Shaded X - Areas of the 0.2% annual chance flood

X Zone - Areas outside the 0.2% annual chance flood

Main Roads

Roadways

Railroad

City Boundaries

Fort Gordon

Ê

Page 88: Columbia County Community Broadband Network
Page 89: Columbia County Community Broadband Network
Page 90: Columbia County Community Broadband Network
Page 91: Columbia County Community Broadband Network
Page 92: Columbia County Community Broadband Network
Page 93: Columbia County Community Broadband Network
Page 94: Columbia County Community Broadband Network
Page 95: Columbia County Community Broadband Network
Page 96: Columbia County Community Broadband Network
Page 97: Columbia County Community Broadband Network
Page 98: Columbia County Community Broadband Network
Page 99: Columbia County Community Broadband Network
Page 100: Columbia County Community Broadband Network
Page 101: Columbia County Community Broadband Network
Page 102: Columbia County Community Broadband Network
Page 103: Columbia County Community Broadband Network
Page 104: Columbia County Community Broadband Network
Page 105: Columbia County Community Broadband Network
Page 106: Columbia County Community Broadband Network
Page 107: Columbia County Community Broadband Network
Page 108: Columbia County Community Broadband Network
Page 109: Columbia County Community Broadband Network
Page 110: Columbia County Community Broadband Network
Page 111: Columbia County Community Broadband Network