cognis - soil remediation investigation - … ii traatabhtty study cfrgnis * 'lomwny 'or...
TRANSCRIPT
C*GNISA Company for Biological and Environmental Technology
MlmMota PoRuHon Control AgancyArrowhaad Refinery
2^ UPDATE REPORTCOQNIS Twraftter Uad Extraction
Phaaa II TraatabHtty Study
CfrGNIS— ;L-i 0 2* 'lomwny 'or Sffiiogoi anfl Environmental
Minnesota Pollution Control AgencyArrowhead Refinery
2nd UPDATE REPORTCOGNIS TerraMet™ Lead Extraction
Phase II Treatability Study
COGNIS, Inc. • 2330 Circadian Way • Santa Rosa, CA 95407(707)575-7155 • Fax:(707)575-7833
C*GMS
SOIL REMEDIATION INVESTIGATION
PHASE II TREATABILITY STUDY
ARROWHEAD REFINERY
HERMANTOWN, MINNESOTA
REPORT
Prepared For:
Minnesota Pollution Control Agency520 Lafayette Road
St. Paul, MN 55155
August 31, 1993
William E. Fristad, Ph.D.Project Manager
C*GMS
TABLE OF CONTENTS
STATEMENT OF THE PROBLEM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
CONCLUSIONS TO DATE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
SCOPE OF WORK . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
PHASE I TREATABILITY STUDY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5Physical Characterization of Soil Sample . . . . . . . . . . . . . . . . . . . . 5
Magnetic Properties . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5Soil Classification Potential . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5Lead Source . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Leaching Feasibility Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7Pre-Leaching Lead and TPH Concentration in Soil . . . . . . . . . . . . . 7COGNIS Metal Leaching Process . . . . . . . . . . . . . . . . . . . . . . . . . 8
PHASE II TREATABILITY STUDY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16Physical Pretreatment of Soil . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Soil Sieving . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16Attrition Scrubbing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Larger Scale Continuous Leaching of Soil . . . . . . . . . . . . . . . . . . . 16Leaching . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16Post-Treatment Lead Concentration in Soil . . . . . . . . . . . . . . . . . . . 24
Material Balance On Lead And TPH . . . . . . . . . . . . . . . . . . . . . . . . 25Experimental Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
EIMCO Bioreactor Slurry with Subsurface S o i l . . . . . . . . . . . . . . . . 27Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27Setup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
Proposed Remediation Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31Scheme . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31Cleanup Level Attainable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34Estimated Treatment Price . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
APPENDIX A Quality Assurance/Quality Control Data
APPENDIX B COGNIS Standard Operating Procedures Referenced
CfrGMS;CGNIS M«UI &draciKxi TraauoiiRy Studies. 2nO Wias* n upoau ftoport Arrown«ad
STATEMENT OF THE PROBLEM
COGNIS, Inc. (COGNIS) is to perform a Phase II Treatability Study on soil contaminatedwith lead from the Arrowhead Refinery site in Hermantown, MM. COGNIS is to determinewhether the proprietary COGNIS metals extraction process is amenable to removing orsignificantly lowering the lead concentration in the soil. The target level for residual leadwas established at the outset of the study to be < 500 ppm. Lead (Pb) is the onlyhazardous heavy metal known to be at the site, although considerable hydrocarbon (TPH)contamination is present and possibly polycyclic aromatic hydrocarbons (PAHs).
The company operated an oil recycling facility from 1945 -1977. Used oil was treatedwith sulfuric acid and filtered to give an acidic filter cake, sludge and oil. Contaminationat the site is known to be in the sludge, filter cake, and surrounding soil which was morelightly contaminated with oil and lead. Lead is a common contaminant of used oil frominternal combustion engines which ran on leaded gasoline.
COGNIS was requested to perform the Phase II Treatability Study for the MinnesotaPollution Control Agency based on a contract with a final signature on February 5,1993.The contract, initiated January 25, 1993, was signed by Dr. Kenneth MacKay, Presidentof COGNIS, Inc. on January 29, 1993. The Arrowhead Refinery site is on the MinnesotaSuperfund Permanent List of Priorities dated December 1991.
CfrGMS:O<3NIS M«tM Extracoon Trvaitttty StudlM. 2na Ptu** ll update Ftopon. ArrownMd
CONCLUSIONS TO DATE
Pretreatment and leaching of the subsurface soil reduced the lead concentration by overtwo thirds to < 200 ppm residual Pb (bench-scale unit, Phase I test) and < 300 ppm(continuous unit, Phase II test). On full-scale remediation, residual lead concentrationsafter complete treatment of < 500 ppm (cleanup standard) would be very achievable.The treated soil passes TCLP for lead (<5 ppm Pb). This is based on return of all treatedsoil to the site.
One additional set of duplicate runs with optimized soil washing conditions is yet to berun. These conditions should give even better lead leaching results. The lower residuallead levels expected should also give lower TCLP values on this optimally treated soil.
The surface soil sample was much higher in lead. Improved soil washing conditionshave led to acceptable lead removal. Currently, ca. 90% of the lead is readily leached,leaving < 1,000 ppm residual lead. Since this surface sample does not represent a largepercentage of the site soil (estimated to be < 5-10% this type of soil), this level ofremediation is considered acceptable.
The proposed processing scheme to date involves grizzly screening of gross oversize,attrition scrubbing of the soil with an oil emulsifying solution to somewhat reduce the TPHcontamination, particle size separation into a clean gravel fraction and contaminated sandand fines fractions, and leaching of the pretreated sand and fines. Particle sizeclassification alone, i.e. "soil washing" with the emulsifying solution, may generate a clean(<500 ppm) sand fraction from the majority, if not all of the sand at the site. If the sandis sufficiently clean, only the fines may need to be leached to remove lead. The treatedoversize, sand and fines are to be redeposited on-srte after treatment. The lead leachedsoil will still contain a substantial amount of the original oil. The recovered oil afterdeemulsification will have to be handled as a separate disposal issue. It should beconsidered for incineration as off-spec oil.
CfcGMSCOGNIS MMM Exlractton TreataCMMy StudWs. 2nd PTUM II UfXM* Report Airwn«aa Raflrwy
SCOPE OF WORK
The scope of the work described in the proposal and included in the contract signed byCOGNIS and the Minnesota Pollution Control Agency is as follows:
Phase II Treatabllity study: Lead RemovalFurther evaluation of the best option (s) identified in Phase IEvaluate feasibility of soil classification prior to lead removalEstablishment of parameters for process recyclabilrtyProcess optimization; physical handling, chemistry, and separationsProcess scale-up; physical treatment, leaching, and lead recoveryVerification of the remediation level to be expectedTCLP testing of the treated soilProvide basic distribution of the soil fractions; oversize, sand, finesSummary report containing all experimental data, estimated treatment cost
($/ton, ±20% confidence level) and time frame for remediation
Phase II Treatabllity Study: Organic Blodegradatlon• Perform "batch" bioslurry degradation of TPH• Document degree of biodegradation to be expected• Study effect of additives to the bioslurry reactor
The final set of Phase II lead leaching under optimized conditions are not yet available.These results will be reported in the Final Report.
CfrGMSCOGNIS MM« Extraction TmattUHy Studto*. 2nd ftMM ll UpdM* Report
PHASE I TREATABILITY STUDY
The original Phase I treatability study was performed on a 5 gallon sample (COGNISidentification IS #67). For the Phase II study additional material was supplied (COGNISidentification TS #204). In order to fully understand the behavior of this latter sample inthe Phase II study, a portion of the Phase I study was repeated on the TS #204 sample.The Phase I data on TS #204 is summarized in this section. The Phase I data on the TS#67 sample has been previously reported.
Physical Characterization of Soil Sample
The second sample (TS #204) was received in three five gallon pails. Two of thesesample buckets were taken from a 2 • 3 foot depth ("subsurface") on the site and the thirdwas taken to a 1 foot depth ("surface"). The surface sample was found to be more highlycontaminated with both organics and lead. The moisture content of the surface soil asreceived was 8% and the subsurface soil was 15%.
Magnetic Properties________________________________
Magnetic separations were not conducted on this soil. No significant amount of ferrousmetal was found in the sample, and the history of the site would not predict unusualamounts of magnetic material.
Soil Classification Potential____________________________
The presence of approximately 30% oversize (>2.00 mm) material in the soil would makethis an ideal candidate for soil washing (particle size classification), i.e. particle sizeseparation and further treatment of onty the fines fraction. Tables I and II summarize thesoil classification data for the surface and subsurface samples. The goal of soil washingwould be to separate the oversize as a clean fraction, free of lead. The sand fraction, aswill be seen later, may be considered dean after washing, or may require leaching inorder to further lower the lead level and to more comfortably pass TCLP for lead. Thefines will definitely require leaching as they hold most of the lead.
COGNIS M«UJ Extraction TrwiaCMlMy StuaM. 2nd RUM ll UpcUt* fltport A/rowTMM ftoflrwyC*GMS
Table I.Soil Classification, Surface Sample
SoilFraction(mesh)
> 4
4-140
<140
Total
SoilWeight
(g)3,264
3,450
2,480
9,194
SoilWeightFraction
(%)35
38
27
100
Table II.Soil Classification, Subsurface Sample
SoilFraction(mesh)
> 44-140
<140Total
SoilWeight
(9)2,695
4,208
2,730
9,633
SoilWeightFraction
{%)28
44
28
100
Lead Source
The most likely sources of lead contamination at this site are various lead salts/oxidesfrom combustion of leaded gasoline found in the used oil and lead sulfate from thesulfunc acid precipitation step in the used oil refining. Over time the lead sulfate mayhave been converted into other lead salts. Metallic lead is not expected to be present atthe site.
CfrGMS:OGNIS Mtnai Exiracuon TrMUDURy Studtas, 2nd RUM 11 uptuw Report. Arrwrwaa Rsflrwry
Leaching Feasibility Analysis
Pre-Leachlng Lead and TPH Concentration in Soil
Soil Washed Surface SampleThe soil washed surface fractions {sand and fines) were recombined and triplicatesamples subjected to EPA acid digestion and lead analysis. The values obtained were9,310 ppm, 10,60X3 ppm and 9,340 ppm, Average = 9,750 ppm total lead. The surfacesample had a much higher lead concentration than the TS #67 sample and thesubsurface sample. Duplicate TPH analysis on soil washed samples contained 3.47% and4.20% by gravimetric analysis and 4.15% and 4.83% by the infrared method.
Soil Washed Subsurface SampleThe soil washed subsurface sand and fines were analyzed separately. The sand fractiongave triplicate lead analyses of 236 ppm, 210 ppm, and 221 ppm, Avg = 222 ppm lead.The fines fraction gave triplicate measurements of 1670 ppm, 1670 ppm, and 1610 ppm,Avg = 1650 ppm total lead. Therefore, the subsurface soil used in the experimentsdescribed in this Report would be calculated to have total lead concentrations as below:
Cone. fpprrri Percentage (%) Contribution (ppm)Fines 1650 40 660Sand 222 60 133
Lead Concentration in sieved subsurface soil 793 ppm (ca. 800 ppm)
Duplicate TPH measurements by the infrared method found 7.8% and 8.0% TPH in thesoil washed fines and 0.90% and 0.96% TPH in the sand fraction.
Subsurface, BloremedlatedLead analyses were not taken before bioremediation of the sample. However, afterblending 1:1 with uncontaminated soil (Goldridge sandy loam) in. order to generateenough sample to load the bioreactor, the soil contained 426 ppm lead (by XRF). Thus,the original soil would have contained 852 ppm lead. TPH analysis prior tobioremediation, but after blending, gave 3.37% TPH (gravimetric analysis), or 6.74% in theoriginal soil. TPH measurement after bioremediation found 0.73% and 0.90% in duplicatesamples. Bioremediation in this sample had degraded almost 90% of the TPH.
CfcGMSCOGNIS M*tai Extraction TrMaDMVy Stuctttt. 2nd PhM* II UpdM ffeport Anowrwaa HMkwry
COGNIS Metal Leaching Process_________________________
Because a new sample was obtained (TS #204) additional Phase I leaching studies wereconducted in addition to the Phase II study. The Phase I results reported here are all onthe TS #204 sample. Phase I leaching results on TS #67 were reported previously.
The COGNIS Phase I bench-scale metal leaching process was conducted on small,duplicate or triplicate samples of the soil in order to determine leaching feasibility. Thisscale allowed the leaching and acid digestion data to be gathered on the exact same soilsample so that no sampling errors were introduced. In this way the amount of Pbleached from the soil plus the residual Pb remaining in the soil can be added together togive the amount of Pb initially in the soil sample and the percentage of teachable Pbcalculated with confidence.
A series of conditions were checked because teachability is a function of the soil type, Pbconcentration, form of Pb contamination, strength of the binding mechanisms, and otherunknown parameters at the outset of the investigation. The effectiveness of any leachantand optimum conditions of its use must be determined empirically.
The results in the following five Tables (III - VII) summarize the leaching results for the soilwashed surface sand plus fines (recombined) sample under five different conditions.Condition #2 employed a longer leaching time than #1 and #3 employed a higherleachant: soil ratio than #1. In these three cases the results are similar, only 40 - 50%of the total lead is leached. The reason for the difficulty in leaching is that the TPH levelin the soil washed surface sample was still high (4 - 5%), and leaching of suchhydrophobic soil was shown to be difficult in the Phase I Report. Lead is being slowly butsteadily leached, and with continued contacts, the lead level would be lowered. However,the TPH level must be further lowered by more efficient soil washing before lead leachingwill be successful.
Condition #4 employed a caustic wash step in the soil washing process in an attempt toincrease the efficiency of the TPH removal. Table VI shows that this wash step followedby standard leaching removes approximately 65% of the lead. Condition #5 differed from#4 in the inclusion of a wash additive to the caustic wash step. Table VII shows that upto 90% removal of lead was accomplished with this pretreatment followed by standardleaching.
The removal of ca. 90% of the lead leaving ca. 1,000 ppm residual lead was deemedacceptable since this surface sample represents a very small percentage of the total soilat the site. The lead contamination in the surface sample also starts at more than 10times (ca. 10,000 ppm vs ca. 800 ppm) the level found in the subsurface, or more normal,soil at the site.
In full-scale operation, this caustic wash could be incorporated into the soil washingintroducing no extra steps to the process.
8
COGNlS M«ai Extraction TmalatMWy SUxUw. 2nd F*UM ll Upon Rtgort. ArrowHMd FWInwyC*GMS
Table 111.Leaching1 of Soil Washed Surface Sand + Fines
Conditions
11
Cumulative % Pb LeachedLeaching Contact #
1
18
19
2
25
26
3
30
31
4
34
35
5
38
38
Initial2
[Pb](ppm)
10,600
10,100
Final3
[Pb](ppm)
6,640
6,280
1 Data Is from five consecutive contacts of soil samples with leachant.2Based upon the total Pb detected in leachant plus Pb retained in soil asdetermined by nitric acid digestion.3Based upon EPA acid digestion of treated soil.
Table IV.Leaching1 of Soil Washed Surface Sand + Fines
Conditions
2
2
2
Cumulative % Pb LeachedLeaching Contact #
1
18
21
20
2
27
30
30
3
33
36
35
4
37
41
40
5
41
46
45
Initial2
[Pb}(ppm)
12,300
10,900
10,800
Final3
[Pb](ppm)
7,230
5,840
5,910
'Data is from five consecutive contacts of soil samples with leachant.'Based upon the total Pb detected In leachant plus Pb retained in son asdetermined by nitric acid digestion.'Based upon EPA acid digestion of treated sol
C*GMSCOGNiS MMI Extraction Trttfautty Stud**, 2nd RUM n upom Mpon wwn«aa
Table V.Leaching1 of Soil Washed Surface Sand + Fines
Conditions
33
Cumulative % Pb LeachedLeaching Contact #
1
25
25
2
33
31
3
38
36
4
43
40
5
47
43
Initial2
[Pb}(ppm)
9,480
10,700
Final3
[Pb]
(ppm)
5,020
6,150
'Data is from five consecutive contacts of soil samples with teachant.2Based upon the total Pb detected in leacnant plus Pb retained in soil asdetermined by nitric acid digestion.3Based upon EPA acid digestion of treated soil.
Table VI.Leaching1 of Soil Washed Surface Sand + Fines
Conditions
4
4
4
Cumulative % Pb LeachedLeaching Contact #
126
2827
2
39
48
41
3
47
56
48
4
51
61
53
5
55
65
57
6
59
68
60
7
62
71
64
initial2
[Pb](ppm)
12,470
11,320
11,700
Final3
[Pb](ppm)
4,750
3,290
4,250
'Data to from seven consecutive contacts of soil samples with leacnant.*Baaed upon the total Pb detected In leacnant plus Pb retained In soil asdetermined by nitric acid digestion.'Based upon EPA add digestion of treated soil.
10
COGNIS hMM Extraction TrMUUHTy StucttM. 2nd RUM il updtf* Rvport *ro*fi«adC*GMS
Table VII.Leaching1 of Soil Washed Surface Sand + Fines
Conditions
5
5
5
Cumulative % Lead LeachedLeaching Contact #
1
45
49
46
2
72
77
72
3
78
85
82
4
81
88
86
5
83
90
89
6
84
92
92
7
85
92
93
Initial*
[PbJ(ppm)
11,040
11,430
14,510
Rnal3
[Pb](ppm)
1,640
861
968
'Datais from seven consecutive contacts of soil samples with leachant2Based upon the total Pb detected in leachant plus Pb retained In soil asdetermined by nitric acid digestion.'Based upon EPA acid digestion of treated soil.
11
C*GMSCOGNIS tMM extraction TrMUUHv StuoiM, 2nd RUM tl UpdM* ftoport MroMttMd Rrtlnwy
The soil washed subsurface sand and fines fractions were separately leached with theresults summarized in the following four tables (Table VII! - XI).
For the subsurface sample the efficiency of oil removal in the standard soil washing stage(classification) was sufficient to remove oil and allow satisfactory lead leaching. As shownin Table VIII, the sand fraction starts below the 500 ppm total lead limit; however leachingremoved an additional 60% of the lead. Approximately 60% of the lead present is alsoleached from the fines fraction, and the lead concentration in the fines fraction afterleaching is in the 650 - 700 ppm range. This is sufficient to give a satisfactory (< 500 ppmtotal lead) concentration in the composite soil when the sand and fines are remixed intheir normal ratio and returned to the site.
As demonstrated with the surface soil, even better results are obtained when a causticwash step with an additive is incorporated before leaching (condition #5, Table IX).Condition #6, Table X involved a shorter more realistic caustic washing time as well asa lower liquid to solid ratio. These conditions better mimic those that would be used inthe full-scale operation. As seen in Table X under these conditions the residual leadlevels are still very good. Conditions #7 and #8 mimic #6 but use different washadditives. Condition #9 was run at 50 °C to see if the addition of heat to the systemwould help free the oil from the fine soil particles. Clearly, the washing/leachingconditions #8 are the optimum conditions for room temperature treatment of the fines.Leaching at elevated temperature is even more effective.
In sum/nan/, the subsurface sand and tines are adequately leached under conditions #8(residual lead in sand is < 100 ppm, Ones is <450ppm) which could be readity seated-up to a full-scale remediation system. While leaching at 50 °C Is clearly superior toleaching at 22 °C (room temperature), the cost of the additional heat input may not bejustified on the full-scale remediation.
12
COGNIS MMM Extraction Traaaewy Stud***, 2nd Phw* ll UpdM* ftaport AmwvHMd R*fln«ryC*GMS
Table VIII.Leaching1 of Soil Washed Subsurface Fractions
Soft/Conditions
Sand/#1Sand/#1
Fines/#1Fines/#1Fines/* 1
Cumulative % Pb LeachedLeeching Contact #
142
38
37
35
35
2
51
48
50
48
49
3
55
53
57
55
56
4
58
55
60
59
59
5
59
57
62
61
61
Initial2
[Pb]
(ppm)
211
201
1,720
1,760
1,750
Final3
[Pb](ppm)
86
86
656
686
674
'Data Is from five consecutive contacts of soil samples with leachant.2Based upon the total Pb detected In leachant plus Pb retained In soil as determined bynitric acid digestion.3Based upon EPA acid digestion of treated soil.
Table IX.Leaching1 of Soil Washed Subsurface Fractions
SoU/Condftioos
Sand/#5
Sand/#5Rnes/#5Rnes/*5
Cumulative % Lead LeachedLeaching Contact #
149
57
55
54
2
59
67
70
69
3
62
71
73
72
4
64
73
75
74
5
65
74
76
75
6
67
76
77
76
7
68
78
77
76
Initial2
[Pb}(ppm)
250
199
1592
1633
FinaP[Pb]
(ppm)
80
43.5
359
388
'Datato from seven consecutive contacts of soil samples with leachant2Based upon the total Pb detected In leachant plus Pb retained In soil as determined bynitric add digestion.38ased upon EPA acid digestion of treated soil.
13
COGNlS Extraction TPMUCMWV StudM* 2nd RUM tl UptUM Report. AnowMM RrtnwyC*GMS
Table X.Leaching1 of Soil Washed Subsurface Fractions
Soil/Conditions
Sand/#6Sand/#6
Fines/#6Fines/#6
Cumulative % Lead LeachedLeaching Contact #
1
44
40
48
45
2
53
48
61
59
3
57
52
66
64
4
60
55
66
66
5
62
57
67
68
6
64
58
69
69
7
65
60
70
70
Initial2
[Pb](ppm)
221
255
1700
1666
RnaP
[Pb]
(ppm)
77
103
517
501
1 Data is from seven consecutive contacts of soil samples with leachant.28ased upon the total Pb detected in leachant plus Pb retained In soil as determined bynitric acid digestion.'Based upon EPA acid digestion of treated soil.
Table XI.Leaching1 of Soil Washed Subsurface Fines
Condition#7
#7
#8
#8
*9
#9
Cumulative % Pb LeachedLeeching Contact #
1
4545
51
51
52
52
2
56
57
66
66
69
69
3
61
61
70
71
76
75
4
67
67
75
75
79
78
5
68
69
76
76
81
81
6
69
69
76
77
83
82
7
—
—
—
—
83
83
Initial2
[Pb}(ppm)
1750
1706
1779
1749
1811
1780
Final*
[Pb](ppm}
551
531
424
409
311
311
'Data is from six or seven consecutive contacts of soil samples wtth leachant.2Based upon the total Pb detected in leachant plus Pb retained in soil as determined bynitric acid digestion.3Based upon EPA acid digestion of treated soil.
14
CfrGMSCOGNIS Extraction StudM* 2nd Rww u UpdMi ftoport. Rafln*ry
In addition to oil removal by soil washing techniques, bioremediation of the TPH andPAHs at the site was also investigated. The bioremediation results are reported in a latersection. A sample of bioremediated soil was subjected to leaching to verify that removalof substantial hydrocarbon loading would allow lead leaching to be effective. In Table XIIbelow are summarized the leaching results with subsurface soil (recombined sand plusfines). The percentage of lead removal was high (70%), and the final lead concentrationwas also low. This subsurface soil had been blended 1:1 with clean soil, so the resultsreally mean that the subsurface soil was leached from an initial 870 ppm lead to 260 ppmlead, i.e. multiply the lead concentrations in Table XII by two.
Table XII.Leaching1 of Bioremediated Subsurface Sand + Fines
Soil/Conditions
Sand+Fines/#10Sand+Fines/#10
Cumulative % Pb LeachedLeaching Contact #
150
49
2
64
62
3
68
66
4
71
68
5
72
69
Initial2
[Pb](ppm)434435
Final3
[Pb]
(Ppm)122134
'Data Is from five consecutive contacts of soil samples with leachant.'Based upon the total Pb detected In leachant plus Pb retained in soil as determined bynitric acid digestion.'Based upon ERA acid digestion of treated sod.
The final post-treatment lead levels after bioremediation and lead leaching were similar tothose after soil washing and lead leaching as shown below, assuming cleanup levels of90 ppm for sand (Table X, Cond. #6) and 420 ppm for fines (Table XI, Cond. #8).
Bioremediation/LeachSoil Wash/Leach 90 ppm (60%) + 420 ppm (40%)
= 260 ppm= 222 ppm
15
;OGNiS Metal Extraction Tr»«att«y stucttOT, 2nd UpcUM taped A/TOWTMMC*»GMS
PHASE II TREATABILITY STUDY
Physical Pretreatment of Soil
Soil Sieving
The soil sieving data on IS #204 was presented earlier. The relative amounts ofoversize, sand and fines has varied with each sample. A summary of the sieving data ispresented below in Table XIII. For calculations in the Cleanup Level Attainable sectionof this Report, the average ratio of oversize : sand : fines being used for the site is 30%: 45% : 25%.
Table XIII.Compilation of Sieving Data
SampleTS #204, Surface
TS #204, Subsurface
TS#67
Oversize352825
Sand3844
64
Rnes27
28
11
Attrition Scrubbing
In order to remove oil from the surface of the soil particles, the soil was vigorouslyagitated with the washing solution. The amount of agitation used can be achieved atfield-scale with a conventional trommel washer. A trommel is currently part of the soilwashing plant. If higher scrubbing intensity is found to be required to adequately removeoil from the surface soil, this would likely be accomplished by a commercial attritionscrubber. Further scrubbing of the surface soil could be investigated in a pilot study.
Larger Scale Continuous Leaching of Soil
Leaching_____________________________________
Larger scale teachings were conducted in order to verify the leaching results on a largerscale as well as identify physical handling problems. The Phase II leaching unit is a smallscale model of full-scale process equipment. It employs an agitated leaching vessel fromwhich a soil slurry is pumped into a darifier. The ctarifier separates the slurry into aclarified feed at the overflow and a thickened slurry at the underflow. The underflow slurryis continuously returned to the leaching vessel. The overflow is pumped into the metal
16
COGNIS M«w Extraction TrMUOMy Studta*. 2nd RUM ll llpdtt* ftoport. AmmffMKi FMrwcy C*GMS
recovery unit where the lead is removed from the leachant and the lead recovered assolid flakes/powder of metallic lead. The barren leachant after lead removal is returnedto the leaching vessel. After leaching is complete, the soil-leachant slurry is dewateredand neutralized. Thus, the entire leaching, clarification and metal recovery processoperates continuously on the batch of soil in the leaching vessel.
The Phase II leaching tests are run for a specified period of time with aliquots taken of thelead-loaded leachate before metal recovery and lead-depleted leachate after metalrecovery to ensure proper functioning of the metal recovery unit and to monitor the leadremoved from the soil. At the end of the leaching cycle, the soil-leachate slurry isneutralized, the soil dewatered and dried. The treated soil is sampled in replicate andanalyzed by EPA acid digestion to determine with reasonable confidence the residual leadconcentration in the remediated soil. A schematic drawing of the process is shown belowin Figure 1.
Continuous Leaching Scheme
regenerated leachant
sediment-leachantslurry
overflowclarified
feedunderflow slurry
RecoveredMetals
Figure 1.
In the first Phase II experiment (Table XIV), the soil washed surface sample was leached.The lead concentration was lowered by 50% to approximately 5,000 ppm. This was aslight improvement over the Phase I results under the same soil washing conditions.Phase I leaching removed on average 45% to ca. 6,000 ppm residual lead. Importantly,it demonstrated that the Phase I results were certainly reproducible at the Phase II level.The overall lead removal in this soil washed surface sample was not adequate, but thiscan be addressed further in the next few weeks.
The influent and effluent samples from metal recovery also indicate that the efficiency oflead recovery is high (a 95%). Therefore, the difficulty in reducing the lead concentrationis a leaching problem and not a result of inefficient metal recovery. This verifies that thestandard metal recovery process should remove lead satisfactorily from this particularleachate, i.e. no site-specific complications with lead recovery were observed.
17
CfrGMSCOGNlS MMM Extraction TrMttttwy StudM*. 2nd PTw* ll Updtf* Report. Anwn««a
Table XIV.Phase II Leaching of Soil Washed (Cond. #1) Surface Whole Soil*
Matrix
Soil (Avg)
Replicate 1Replicate 2
Replicate 3
LeachateSample 1Sample 2Sample 3Sample 4Sample 5Sample 6Sample 7
Lead Concentration ( g/mL orj/g/g)Pre-Leaching
9,750
10,600
9,310
9,340
Influent
6.4—
49.5
37.8
40.2
111°
90.8
Leached5,090
5,580
4,940
4,740
Effluent«
4.6
2.7
2.0
1.8
4.8
10.5
"Soil was neutralized after leaching with calcium carbonate. Recovered soil after drying (98% recovery).^The improvement in leaching at this point was due to improved mixing. Better mixing through the courseof the entire experiment should have given significantly better teaching results.
18
C*GMSCOGNIS M«tat Extraction Tr*ouoiwv StuOM*. 2na II UpOM Rtport. R*fln*rv
The next four runs were conducted on duplicate soil washed subsurface fines (Table XV& XVI) and soil washed subsurface sand (Table XVII & XVIII). The soil washingconditions were identical to the Phase I experiment, Table VIII, Cond. #1 (non-optimized).The results show that the fines can be leached down to 830 ppm residual lead (50%removal), while the sand can be leached down to 100 ppm lead (55% removal). Theseresults meet the cleanup criteria of < 500 ppm residual lead when the lead concentrationin the average soil (oversize, sand and fines) is calculated based on the leadconcentration in each fraction (see Cleanup Level Attainable section of this Report).
Thus, the subsurface soil can be washed and leached to betow the established cleanupcriteria of < 500 ppm residual lead.
In the fines run the metal recovery unit still removed >90% of the dissolved lead from theleachant on one pass through the unit. TOs is considered acceptable. The metalremoval efficiency on the sand run was somewhat less; however, the initial concentrationof lead to be removed is very low. The lead removal efficiency under these conditions isalso considered acceptable.
Table XV.Phase II Leaching of Soli Washed (Cond. #1) Subsurface Fines'
Matrix
Soil (Avg.)
Replicate 1
Replicate 2Replicate 3
LeachateSample 1
Sample2SampledSample 4Sample 5Sample 6
Lead Concentration fyg/mL or jug/g)Pre-Leaching
1,6501,610
. 1,6701,670
Influent51.5
30.2
46.3
26.4
14.8
11.5
Leached
830805
814
872
Effluent4.7
3.5
< 0.5
2.4
1.6
0.9
'Soil was neutralized after leaching with calcium carbonate. Recovered soil after drying (98% recovery).
19
C*GMSCOGNiS MMM Extrecdon TrMttcwy StudM. 2nd RWM II Updrt* Report. Airowfwad Artkwy
Table XVI.Phase II Leaching of Soil Washed (Cond. #1) Subsurface Rnes1 Duplicate
Matrix
Soil (Avg.)
Replicate 1Replicate 2Replicate 3
LeachateSample 1
Sample 2Sample 3Sample 4Sample 5
Lead Concentration (jug/mL orjug/g)Pre-Leaching
1,650
1,610
1,670
1,670
Influent50.138.5
18.9
10.9
7.7
Leached838
831
843
841
Effluent13.5
3.21.1
< 0.5
< 0.5
"Soil was neutralized after teaching wtth calcium carbonate. Recovered sol after drying (96.8% recovery).Table XVII.
Phase II Leaching of Soil Washed (Cond. #1) Subsurface Sand*
Matrix
Soil (Avg.)
Replicate 1Replicate 2Replicate 3
LeachateSample 1Sample 2Sample 3Sample 4Sample 5
Lead Concentration (ug/mL or pg/g)Pre-Leaching
222
236
210
221
Influent8.6
—
4.8
4.8
2.6
Leached100
81.4
89.5
129
Effluent—
1.4
2.7
1.5
0.7
'Soil was neutralized after leaching with calcium carbonate. Recovered son after drying (98.3% recovery).
20
CfrGMSCOGNIS M«w Extraction TrvMCMy ShjOM*. 2nd RUM ll Updtf* Report.
Table XVlll.Phase II Leaching of Soil Washed (Cond. #1) Subsurface Sand* Duplicate
Matrix
Soil (Avg.)
Replicate 1Replicate 2Replicate 3
LeachateSample 1Sample 2Sample 3Sample 4Sample 5
Sample 6
Lead Concentration (ug/mL or ug/g)Pre-Leaching
222
236
210
221
Influent8.1
—
4.8
1.5
1.3
1.5
Leached94
10187
-
Effluent1.41.2
< 0.7
< 0.7
< 0.7
«
"Soil was neutralized after leaching with calcium carbonate. Recovered soil after drying (99.4% recovery).
77)e Phase II results in Tables XV - XVH/ meet the cleanup criteria; hcwever, the soilwashing conditions (Conditions $1) used correspond to those shown in Phase Iexperiments and are dearly not optimal. Therefore, Phase II experiments will be repealedunder more favorable soil washing conditions, Conditions *& These results will bereported shortly.
21
C*GMSCOGNIS MMat Extraction TrMUMRy StudM. 2nd Run* H Updtf* Report, fWlrwy
Table XIX.Phase II Leaching of Soli Washed (Cond. #8) Subsurface Fines*
Matrix
Soil (Avg.)
Replicate 1Replicate 2Replicate 3
LeachateSample 1Sample 2Sample 3Sample 4Sample 5Sample 6
Lead Concentration fcg/mL or g/g)Pre-Leaching
Influent
Leached
Effluent
"Soil was neutralized after leaching with calcium carbonate. Recovered soil after drying (_% recovery).
22
C*GMSCOGNiS MMM Extmcuon TrMUtMMy StudlM, 2nd il UpdW Report *nwn»aa Rcflrwry
Table XX.Phase II Leaching of Soil Washed (Cond. #8) Subsurface Fines'
Matrix
Soil (Avg.)
Replicate 1Replicate 2Replicate 3
Leachate
Sample 1Sample 2Sample 3Sample 4
Sample 5Sample 6
Lead Concentration fcg/mL or pg/g)Pre-Leaching
Influent
Leached
Effluent
'Soil was neutralized after leaching with calcium carbonate. Recovered soil after drying (_% recovery).
23
CfrGMSCOGNIS M«UJ Extraction TrMtaoNRy StudMt. 2nd Rial* II UpcMM flvport
Post-Treatment Lead Concentration In Soil
Samples of the treated subsurface sand (from Table XI) and fines (from Table X) weresubmitted for TCLP testing (D & M Laboratories, Petaluma, CA). The results are shownin Table XXI.
Table XXI.TCLP Results (Lead) on Phase II Leached Soil Fractions
SoilSand
Fines
TCLPLimit5.0
5.0
DetectionLimit (mg/L)
0.15
0.15
Results(mg/L)
3.0
5.4
These TCLP results are disconcertingly high, although when the sand and fines arerecombined, the combined soil would pass TCLP (< 5 ppm). Because of these highTCLP results, Phase II teachings under the optimized soil washing conditions will still beconducted.
The above TCLP results are very surprising since they are not consistent with earlierTCLP tests which showed that untreated soil (TS #67) had a TCLP value of 1.84 ppmPb, and after Phase I leaching under three different conditions (reported in Phase IReport) TCLP values of non-detectable, 0.61, and 0.53 ppm Pb had been obtained. Thelarge discrepancy in TCLP results could be due to sample variability; however, thedifference is very large. COGNIS feels the only satisfactory resolution of the TCLPbehavior to expect from treated soil is to repeat the soil washing-lead leaching under theoptimum conditions as planned.
24
CfrGMSCOGNIS M«Uj Extractor TrMUtMWy StudM. 2nd (***• H UptUM Report. AmnwDMU R*fln*ry
Material Balance On Lead And TPH
In order to document the fate of the lead and TPH in the soil after soil washing, a carefulmass balance experiment was conducted. The goal was to account for all the lead andTPH which was initially present in the soil as ending up in either the washed soil, orremoved to one of the soil washing solutions.
Experimental Procedure_______________________________
Oven dried subsurface soil (200 g) from the site (TS # 204) was attrition washed with 145mL of soil washing solution (Cond. #1). Separate 2 gram samples (in duplicate) of thisstarting soil were submitted for Pb and TPH analysis. After attrition scrubbing the soil wasclassified into sand and sitt/clay fractions using a wet LaMotte classification method. Thesoil fractions were then oven dried and weighed before submitting for final analysis of Pband TPH. Both the attrition solution and classification water were submitted for Pb andTPH as well.
Results________________________________________
The mass balance was very good, 99.5% of the starting soil was recovered as either sandor fines. The mass balance on lead was within expected error. Actually, 2.7% more leadwas found in the soil fractions after soil washing than before. The TPH recovered aftersoil washing showed an unaccounted for loss of 12.6% based on the average initial TPHlevel. However, this is within the expected variation of TPH at the site.
Thus, the mass balance experiment showed that less than 2% of the total lead and lessthan 1% of the total petroleum hydrocarbons dissolved or were dispersed in the washingsolution.
25
CfrGMS:OGNIS M*«u Extraction T maturity SludMt. 2nd Phot ll UpdlM fitport, Amnvrwaa Refinery
Table XXII.Material Balance of Subsurface Soil
PROCESS
ScreenAttrition
Classify
SAMPLE
Starting SoilWash WaterClassification
WaterFines
Sand
LEAD
Cone.fr<g/g)666
14.2
ND
1,264
525
Mass(9)200
145
459
41
158
Pbfeg)
133,200
2,059
0
51,824
82,950
TPH
Cone.fcg/g)35,300
7
24
53,400
25,100
Mass(g)200
145
459
41
158
TPHW
7.06 X106
1,015
11,016
2.19 x 106
3.97 x106
TOTAL RECOVERED
LOSS/GAIN (+/-)
% LOSS/GAIN (+/•)
136,833
+ 3,633
+ 2.7%
6.17 x 106
-0.89 X106
-12.6%
26
CfcGMS:OGNiS M#at Extraction TrMUDHRy SludMs. 2nd RUM it updM Report. AJTOWPMO R«nn*ry
EIMCO Bioreactor Slurry with Subsurface Soil
Background_____________________________________
In anticipation of carrying out experiments in continuous operation of the EIMCO SoilSlurry Bioreactor units with a much larger quantity of soil, this "batch" slurry bioreactorexperiment was intended to demonstrate (1) that TPH could be degraded by theindigenous population in the EIMCO reactor; (2) that when the rate of biodegradation ofTPH by the indigenous population had slowed, addition of more microorganisms fromsewage sludge or commercial cultures could help to degrade the remaining TPH, and (3)assuming unlimited time to operate, what was the maximum possible level ofbiodegradation of the TPH? Because the single reactor was operated in a "batch*process that is typically less efficient than a continuous process using two or three linkedEIMCO bioreactors, the time required for biodegradation in a continuous process usingboth indigenous and commercial microorganisms would most likely be less than in thisexperiment. Several problems with sampling the slurry and measuring the slurry volumealso made the accuracy of some of the analysis at the midpoint of the experimentquestionable.
Setup________________________________________
EIMCO recommends that a soil be characterized by screening and determining itsparticular "hydraulic load"; that is the percentage of solids in a slurry that can prevent thecoarser soil fractions from rapidly settling out of the slurry. Rapid settling can quickly"crash" a bioreactor slurry by jamming the airlifts. Our initial survey indicated that at least35% solids would be needed to support the coarse fractions in screened subsurface soil.
The contents of a single five gallon bucket of subsurface soil (T.S. #204) were wetscreened through a 10 mesh screen for loading in the EIMCO reactor. Due to the largeamount of pebbles and cobbles in this sample, less than half the soil could be used in thebioreactor. To load the reactor at a high enough solids (>35%) level it was necessaryto add additional screened "Goldridge Sandy Loam" soil at about a 1:1 final ratio. ThisGoldridge soil typically contains less than 0.5% organics and more fines than thesubsurface soil sample. Although not previously exposed to petroleum hydrocarbons,one must assume that the Goldridge soil could have contributed to the microbialpopulation that grew up on the petroleum contaminants in the slurry. In spite of thedilution by Goldridge soil the final slurry mixture still contained greater than 33,000 mg/Kg(soil dry weight) of TPH (Table XXIII).
The reactor was run at ambient temperatures with an airflow of approximately 20 CubicFeet per Hour (CFH) to the diffusers. "Die diffuser airflow varied somewhat with changesin the airflow to the airiifters. Ca(OH)2 was added periodically to compensate for the acidpH drive and to keep the slurry within a pH range of 6.6 • 7.4. NH4NO3 and K,PO4 were
27
CfrGMSOGNIS M«<ai Extraction TrwiattWy Stuawt. 2nd PhaM II Updtt* Atpofl, Anowrwad Renn*ry
added at the beginning and after two weeks of operations.
Samples were drawn from the three ports at the bottom middle and top of the slurrybioreactor. The three 100 mL samples were combined, then ether extracted andtransferred to freon (COGNIS SOP020, Appendix B). Total Petroleum Hydrocarbons(TPH) were determined gravimetrically by EPA Method 413.1 (COGNIS SOP019, AppendixB). Total Recoverable Petroleum Hydrocarbons (TRPH) were determined from the non-polar fraction by EPA Method 418.1 (COGNIS SOP018, Appendix B). To determine thedry weight of the slurry, 100 mL samples from each of the three ports were separatelydried in an 80 °C oven until no further weight reduction was seen. Microbial enumeration,pH and nutrient determinations were carried out on samples drawn from the middlesampling port.
Results________________________________________
As can be seen in the second column of Table XXIII, the indigenous microbial populationgrew more than ten fold in the first three days of operation, in a continuous slurryoperation, this elevated population level needed to biodegrade the hydrocarbons wouldbe present from the start. In this batch mode the average TPH level had been reducedby more than 35% within seven days of operation (Table XXIII, third column). When theday 14 and day 21 analyses clearly showed that the initial rate of bioremediation haddrastically slowed down, the reactor was dosed at 21 days and 28 days with activatedsewage sludge, and then dosed at 36 days with a commercial microbial culture (MicroPro G, Microbe Masters, Inc.) to see if the more recalcitrant TPHs could be furtherbiodegraded.
Some problems were encountered by the third week with estimating the total volume ofthe slurry due to foaming. It became clear that the 28 and 36 day TPH analysis mostlikely were obtained from a more concentrated slurry (therefore contained more solids)than what was calculated. Most likely the numbers at 28 and 36 days are on the highside. In the last two samples obtained at 42 and 57 days the solids were determined bydrying and weighing the samples, and therefore these values are much more accurate.
In the absence of measurement of the CO2 evolution or O2 consumption, the viablemicrobial population enumeration and the magnitude of the daily change in slurry pH (the"pH drive") were the best indicators of significant biological activity. The pH drive hasespecially been proven to be a useful means of predicting the biodegradation inunbuffered soil slurry shake flasks typically used by COGNIS for Phase I investigations.Please note how the addition of the commercial culture Micro Pro G (Microbe Masters,Inc.) at 36 days seemed to greatly increase the pH drive in the slurry, while the slurry hada much smaller pH drive after the additions of activated sewage sludge. Possibly theMicro Pro G significantly affected the TPH levels and made large amounts of fatty acidsor other organic acid material from the available TPH. Based on the analytical results, thepH drive, and results from soil slurry shake flask experiments (not shown) it appeared thatthe Micro Pro G culture was able to continue to biodegrade TPH when the indigenousculture had faltered. TTie effect of adding Micro Pro G to the initial slurry or after the
28
CfrGMSCOGNIS M«Ul ExlracUon TrMtaDMRy Studies. 2nd Rwse II UpdaM Report. A/rowneaa Refinery
indigenous population had achieved peak growth cannot be predicted from this singlebioreactor experiment.
The EIMCO BL60 slurry bioreactor ran well for the entire two months of operation, withoutmuch evidence of settling of the coarser fractions to the bottom. Although the mechanicalfoam breaker did prevent serious buildup of backpressure from foaming of the slurry,enough pressure occasionally built up to force a small amount of the slurry up the rakedrive shaft into the gearbox. By the end of this extended (2 month) run there was some(1 Kg?) dried mud in the gearbox, but not enough to interfere with operations.
29
CfrGMS;OGNIS MMAI Exlractton TrMUCxHtv StudlM. 2nd Pnas* II UptUM RtQOrt. AfTOwrwaa R*fln«fY
Table XXIN.EIMCO BIOREACTOR DATA
Subsurface* Clean Soil (Goldrtdge)TIME(days)
01245
6
7
8
9
12
14
16
19
21
23
26
28
30
36
42
43
50
54
5557
61
cfu/mL'
0.170.65
1.07
2.23
2.44
2.84
2.81
4.48
6.4
5.65
NO
10.611.1
11.621.4
7
9.556.2
5.8
ND
NO
10.6
NO
9.25ND
ND
AcidpHdrive/day
0(.47)
(.11)
(.19)(.24)
(.02)
(.3)(.37)
(-2)
(-3)(.16)
(.23)
(.23)
(.21)
(.18)
(.17)
(.16)
(.11)
(-3)(.84)
(.78)
(.90)
(.17)
ND
(.18)
+ .01
TPH(ppm)
33,700
22,200
20,200
18,300
21,300®
20,300*10,800
7,800
Notes
Started 3/23/93
Add additional NH.NO3and KP04as nutrients
Foaming started day 18Added 1 L activated sludgeAdded 200 ml Poiyseed supernatant
Added 1 L activated Sludge
Added 1 L MP-G supernatant9,500 ppm IR
6,900 ppm IR
* = 1 X 10*@ = Estimated due to evaporation in reactor (volume decreased, slurry concentration increased, but wasnot measured)Note: GoJdridge soil was added to increase the percentage of fines In the slurry. This facilitated theoperation of the airltfts in keeping the slurry in suspension.
30
CfrGMSCOGNIS Mtui Exiracflon TrMauuiy SluatM. 2nd RUM il uodM Rtport AmnvriMd Rcflrwry
Proposed Remediation Process
Scheme______________________________________
The initial goal of reducing the total residual lead concentration to < 500 ppm has beenachieved. The treated soil appears visibly less contaminated with TPH and has very littlemotor oil odor. Additional work is being done to achieve still lower residual lead levelsand also to further lower the TCLP.
Proposed Remediation Option A combined soil washing-lead leaching process willreduce the total lead concentration to < 500 ppm in the whole soil returned to the site(oversize, sand and fines). The treated soil will also pass TCLP. This appears justifiablebased on the Phase II data to date. TPH removal was not specifically requested in thelead removal process; however, in order to effectively leach lead from the soil, a portionof the TPH may be removed in order to make the soil particle surfaces less hydrophobicand allow wetting by the aqueous leachant.
The proposed remediation process scheme is illustrated in Figure 2 as a block diagram.The percentages shown by each soil fraction represent roughly the weight percent ofeach fraction present at the end of the treatment process which must either be disposedof or returned to the site.
The site would first require that all vegetation be removed, primarily small trees andgrasses. The soil would then be excavated. It is assumed that a portion of the site wouldbe excavated before start of soil treatment and that excavation would continue throughoutthe remediation, providing soil on an as needed basis. The excavated soil is dryscreened to remove gross oversize debris, a reject gross oversize of +4" or +6" issuggested. If dry screening proves impossible, and this is quite possible because of themarshy nature of the site, screening could be performed wet. The reject oversize can bewater sprayed/rinsed to remove adhering fines. The gross oversize fraction is to bedeposited back on-srte. This material has not been tested for lead concentration or TCLPbehavior, but should fall under the debris classification.
The -4" (-6") material passes through a wet trommel containing a caustic solution toemulsify a portion of the oil. The trommel also cleans gravel of fines by rock-on-rockattrition and ejects rinsed oversize (+'/4N) and generates an aqueous slurry of -Vi" soil(sand, silt and clay) and emulsified oil in water. The + Vi" fraction exits the system at thispoint. It is free of fines, and will consist of gravel and wood.
The soil slurry (-%") then undergoes a separation of the sand from the soil fines. Theseparation is done in an upflow classifier which separates panicles based on settling ratesagainst an upflowing column of water. The fines are swept up and out of the classifier
31
CfrGMS:OGNIS Mew Extraction rreaiawiitv StuCW. 2nd Rias« it UpOM fttpon. A/rovm«a R»fln«fY
and are settled in a standard clarifier. The thickened fines are pumped to the finesleaching circuit. The sand settles down and out of the classifier and is subjected to aslight caustic rinse If it is not leached. The sand fraction may be clean enough for returnon-site after dewatering in a sand screw. If necessary, the sands are leached in acounter-current leaching circuit similarly to the fines.
The oil/water separation must be finalized at the pilot plant scale because on the smallscale operations to date the volume of solution is quite small. However, the current planwould be that the oil and water emulsion is broken and separated in a standard oil-waterseparator. The recovered washing solution is reused in the process. The recovered oilfraction is removed for disposal.
The fines are leached in a counter-current system and finally discharged as a thickenedsludge onto a conveyer for neutralization and remixing with sand and oversize. The metalloaded leachant after leaching contact passes through the metal recovery unit for removalof the dissolved lead. The metal recovery unit regenerates the leachant and the leachantis recycled into the process. The recovered lead is in the form of solid, metallic leadflakes/powder and will be sold as a lead product to a secondary lead smelter.
The cleaned oversize, sand, and fines fractions are neutralized in a pug mill after leaching.The neutralized soil is to be returned to the site. The recovered oil will require disposal.
A more detailed process flow for the BESCORP pretreatment steps and COGNISTerraMet* leaching can be supplied if a decision is made to remediate the site or to verifythe current scheme in a demonstration run.
32
lS M*>lal Fxlracllon Irpalahlllty SUifltes. ?ml Phase II Ufxlale Report. Arrowhead Hefkiery
'3 COGNIS-BESCORP Remediation ProcessPercent of Soil Fractions Through Process
Physical Separation Stage — Emulsif ier
r rrntamioaft.cjL _. _ _^j Screen L —— -^JTrommell ————— >- Particle ———— DSoil
Gross("IVPISI7P
-»4"
20%
Chemical Leaching St
Soil Finesfrom Separation Stnq^
Sandfrom Separation Stnq^
f if nerpqt;^! y)^ ' ' '
Oversize+ 1/4
10%
uiassny
Fines
^ De
age
HLeach I jDewaterma 25%Circuit j " Clarifier
H Leach ICircuit I
["lead"I Recovery
^ nirnHor I
~L
K Dewaterma I -_.. ISand Screw [ 45% |
Lmtestone
J
ewater| ——— »- Sandto Leaching urcun
(if necessary)
Clarifier ^ Finesemulsif ier to Leaching Circuit
/Recovered Oil—— ( for Disposal
/Dewatered \^.f N^iitra)i7Pd Soil J
\ ^^QO/ /x^ ^S^J /Q _s*
/^~~ ~~—-XLead Concentrate
^( lorecycler
Figure 2
33
C*GMSCOGNlS M«taf ExiraclKxi TrMiaDHfly StuOMa. 2na Pnaa* n Updai* fltport. Arrowneao flefliwy
Cleanup Level Attainable_____________________________
Phase II results on the subsurface sample show that residual lead in fully treated wholesoil can be < 500 ppm as stated in the original goal. This value should be reproduciblein the field. The data to date has actually been able to achieve a cleanup level of < 300ppm under the conditions tested, which include all the normal processing steps.
The cleanup levels attainable are calculated below based on the observed cleanup inPhase II experiments on sand (100 ppm) and fines (830 ppm) fractions (Tables XVII andXV) and Phase I data (Tables VIII and XI, Cond. #8). The calculation assumes a sitegradation of 30% oversize, 45% sand and 25% fines. The site gradation is a conservativeestimate based on the gradations listed in Table XIII. The lead content of the oversizefraction has not been measured and would be difficult to measure accurately in any case.A worst case assumption has been made that the oversize will still contain the sameamount of lead as the sand fraction. In all likelihood, the oversize lead concentration ismuch lower because of the much lower surface area of the oversize relative to the sand.
Calculation of Final Lead Concentration in Treated Whole Soil
SubsurfacePhase II Oversize Sand Fines TotalData (0.30)(100) + (0.45)(100) + (0.25)(830) = 283 ppm
SubsurfacePhase I Oversize Sand Fines TotalData (0.30)(86) + (0.45)(86) + (0.25)(417) = 169 ppm
Even lower cleanup levels should be attainable when the final results are in from thecurrently scheduled Phase II experiments using the optimized soil washing solution.
34
CfrGMS;OGNiS Meial Extracilon Tr«aia£Mlffy SUxMs. 2nd Www a upcUM fltoon. A/rownesa Refiner/
Estimated Treatment Price____________________________
The estimated treatment cost for the site is $170/ton ± 20%. This price includes loadingof previously excavated soil into the treatment train, complete treatment process, processanalytical, and sale of the recovered lead as a product of the process. The priceassumes the following:
Quantity: 40,00X3 cu. yds. of soil to be treated.Soil gradation: roughly 30% oversize, 45% sand, 25% fines.The two samples obtained are representative of the site, and that the subsurface
sample is most representative.Level "D" Protective Requirements with occasional times in "C".24 hr/day operation at 20 - 50 tons/hr.Mobilization/Demobilization Charges: $200,000
The price estimate does not include initial excavation, regulatory agency requiredanalytical and QA, or health and safety requirements (plan preparation and on-siteimplementation), although these could be performed by COGNIS/BESCORP as well. Ifthese were to be performed by COGNIS/BESCORP, the additional price estimates wouldbe as follows:
Health & Safety Plan Prep.: $50,000Excavation and Backfill: $12/yard
This treatment estimate can best be refined after completion of a demonstration scale runwhich will allow more accurate chemical consumption costs and cycle time. Otherquestions which control cost are permitting requirements, hours of operation and otherpossible restrictions which may be imposed by the MPCA, the RPs, or other localauthorities.
35
CfrGMSCOGNiS M«tai Extraction TreaatMtty StudMs. 2nd PhaM u UPON* n«pon. A^owrwaa R*An«ry
APPENDIX A
Quality Assurance/Quality Control Data
36
CfcGMS:OGNiS M«t» Exiractton rrMtattllty SluatM. 2nd RMM n updtt* Report. Arrowrwad
Table III. QA/QCDATA
T.S. # : 204
SampleNumber
051
052
053
054
055
056
061
062
063
064
065
066
pH
1.04
0.84
0.81
0.81
0.78
Soil
0.99
0.84
0.81
0.80
0.78
Metals: PbLeach
Contact
1
2
3
4
5
Residue
1
2
3
4
5
Soil Residue
AA(ug/g)
404
156
94.2
98.8
66.6
6640
388
136
97.6
85.9
59
6280
Leach Sample Wt.: 2 gramsLeachate
(g)9.27
10.32
10.32
10.28
10.08
9.86
10.34
10.32
10.25
10.29
Leach(ug)
3745
1610
972
1016
671
3826
1406
1007
880
607
Total(ug)
3745
5355
6327
7343
8014
3826
5232
3239
7120
7727
Total(ug/g)
1873
2678
3164
3671
4007
1913
2616
3120
3560
3863
Total(%)
18
25
30
34
38
19
26
31
35
38
QUAUTY CONTROL
Leachates:
SRM
Spike Recovery
101
108%(107, 109)
Spike Duplicate Recovery 105%(104, 106)
(Acceptable Range 96.36 -104.04)
(Acceptable Range 80 -120%)
RPD * 1.62%
(Acceptable Range 80 • 120%)
RPD = 1.78%
Soils:
Blank
Soil Blank
Soil Spike
Soil Spike Dup.
< 26
< 26
234
229
(Detectable Level - 20)
(Detectable Level * 20)
Recovery - 93.6%
Recovery = 91.6%
RPD = 2.10
37
COGNIS Meta) Extraction TrvdaUMy StudtM. 2nd Chat* ll UpdJM R»poaC*»GMS
Tabto IV. QA/QC DATA
T.S. * ; 204
SampleNumber
041
042
043
044
045
046
051
052
053
054
055
056
061
062
063
064
065
066
PH
1.22
1.02
0.96
0.94
0.94
Soil
1.22
1.00
0.95
0.94
0.94
Soil
1.17
0.99
0.96
0.94
0.93
Metafr Fb
LeachContact
1
2
3
4
5
Residue
1
2
3
4
5
Reefdue
1
2
3
4
5
SollReeidue
AA(ug/g)455
209
127
104
99.3
7230
462
185
123
103
112
5840
440
186
111
103
105
5910
Leach Sampto Wt: 2 grams
Leachat*(g)
9.92
10.41
10.36
10.5
10.52
9.92
10.47
10.32
10.43
10.45
9.92
10.92
10.41
10.4
10.44
Leach(ug)
4514
2176
1316
1092
1045
4583
1938
1269
1074
1170
4365
2031
1156
1071
1096
Total(ug)
4514
6689
8005
9097
10142
4583
6521
7790
8864
10035
4365
6396
7551
8623
9719
Total(ug/g)2257
3345
4003
4549
5071
2292
3260
3895
4432
5017
2182
3196
3776
4311
4859
Total(%)
18
27
33
37
41
21
30
36
41
46
20
30
35
40
45
QUALTTY CONTROL
Leachaltt:
045
061
Duplicate
Duplicate
SRM
102
442
101.3
Soil*:
SRM
Blank
Soil Blank
Soil Spike
Soil Spike Oup.
103.5
<20
<20
528
521
RPD - 2.38%
RPD - 0.45%
(Acceptable Range 96.36 -104.04)
(Acceptable Range 96.36 - 104.04)
(Detectable Level - 20}
(Detectable Level - 20)
Recovery - 105.2%
Recovery » 104.2%
RPD - 0.95%
38
CfcGMSCOGNIS M«w Extraction TrwtaDONy Studta*. 2nO ffias* II UfXUM R*oort. AmmrtMd FWInwy
Tibia V. QA/QC DATA
T.S. # : 204
SampleNumber
051
052
053
054
055
056
021
022
23
024
025
026
PH
0.94
0.91
0.91
0.90
0.90
Soil
Metals: Pb
LeachContact
1
2
3
4
5
Residue
1
2
3
4
5
Soil Residue
AA(ug/g)
119
39.3
23
22.6
20.1
5020
127
40.3
23.7
20.6
16.9
6150
Leach Sample Wt: 2 grams
Leachate(g)
39.5
40.3
40
40.5
39.9
42.7
31.7
40
40.4
40
Leach(ug)
4701
1584
920
915
802
5423
1278
948
832
676
Total(ug)4701
6284
7204
8120
8922
5423
6700
7648
8481
9157
Total(ug/g)2350
3142
3602
4060
4461
2711
3350
3824
4240
4578
Total(%)
25
33
38
43
47
25
31
36
40
43
QUALITY CONTROL
Leachates:
Spike Recovery 107% (Acceptable Range 80 -120%)
RPD = 3.15%
Soils:
SRM
Blank
Soil Blank
Soil Spike
Soil Spike Dup.
103.5
< 20
< 20
526
521
(Acceptable Range 96.36 - 104.04)
(Detectable Level - 20)
(Detectable Level - 20)
Recovery = 105.2%
Recovery - 104.2%
RPD = 0.95%
39
Ejdraaioo Stuowr 2nd RUM H UpaaU flwort. Arnxwrwao C*GMS
TabteVf. QA/QCDATA
T.S. # : 204
SampleNumber
012
013
014
015
016
017
018
019
022
023
024
025
026
027
028
029
032
033
034
035
036
037
036
039
pH
1.3
1,05
1.01
0.98
0.96
0.97
0.97
Soil
.
-
-
.
-
.
-
Soil
.
.
-
-
-
-
.
Matate Pb
Acid LaachContact
i
2
3
4
5
6
7
Ratidua
1
2
3
4
5
6
7
Rasidua
1
2
3
4
5
6
7
SoURMUlM
AA(ug/g)
558
322
177
112
89
79.6
81.1
4750
613
394
170
109
77.8
64.6
66.9
3290
547
323
160
106
89.8
7^875.2
4280
Laach Sampt* V*.: 2 grama
Laachata0)
10.61
10.50
10.34
10.48
10.56
10.60
10.31
10.38
10.48
10.27
10.60
10.32
10.42
10.39
10.52
10.50
10.33
10.47
10.41
10.42
10.37
Laach(ug)
5920
3381
1830
1174
940
844
836
6363
4129
1746
1155
803
673
716
5754
3992
1653
1131
935
759
780
Total<ug)
6430
9811
11640
12815
13755
14599
15435
6838
10967
12713
13666
14671
15344
16060
6254
9646
11299
12430
13365
14124
14904
Total(ug/g)
3215
4906
5820
6408
6878
7300
7718
3489
5484
6457
6394
7336
7672
8030
3127
4823
5650
6215
6683
7062
7452
Total(*)
26
39
47
51
55
59
62
28
46
56
61
65
68
71
27
41
48
53
57
60
64
OUAUTY CONTROL
Laacnataa3pika nacovary
Soils: SRM
Blank
Soil Blank
Soil Spika
Soil Splka Oup.
101%
101.0
< 20
< 20
454
464
(Aooaptabla Ranga 80 -120%)
RPO - 0.44%
(Aocaptabta Ranga 96.36 • 104.04)
(Datactabla Uva< - 20)
(Datactabia Lava! - 20)
Racovary • 90.8%
Raoovary » 92.8%
RPO • 2.07
40
C*GMS
COGNIS M»ut Extract**! Tra«MU«y Studta. 2nd RWM ll Update Mport.
TabtoW. QA/OC DATA
T,S. #: 204
SamplaNumb«r
012
013
014
015
016
017
018
019
022
023
024
025
026
027
028
029
pH
1.45
1.10
1.01
1.00
0.98
0.98
0.98
Soil
.
-
-
-
-
-
-
Mrtato: Pb
Acid LaachContact
1
2
3
4
5
6
7
Rasidut
1
2
3
4
5
6
7
Soil RMidut
AA(ug/o)
792
577
142
61.9
38.9
25.3
19.0
1640
824
640
175
72.9
40.9
284
20.7
861
Uach Sarapl* WL: Zgrama
LaachAt*(g)
10.46
10.31
10.49
'10.52
10.29
10.42
10.67
10.67
10.09
10.39
10.47
10.37
10.16
10.52
Laach(ug)
8284
5948
1489
651
380
263
203
8792
6458
1818
763
424
286
218
Total(ug)
9864
15812
17301
17952
18332
13596
18798
11177
17635
19463
20216
20640
20928
21146
Total(ug/g)
4932
7906
8661
8976
9166
9298
9399
5586
8818
9727
10108
10320
10464
10573
Total(%)
45
72
78
81
83
84
85
49
77
85
88
90
92
92
41
C*GMS
COGNIS M«w Extraction TrMtatoMy SludiM, 2nd Phat* u update Report. Anuwrwad
TabteVII. QA/QCDATA
T.S. #: 204
Sampl*Mum bar
032
033
034
035
036
037
038
039
pH
.
-
•
-
.
-
-
MMate Pb
Acid LaachContact
1
2
3
4
5
6
7
Soil Raaidu*
AAWO)
899
737
267
128
82.2
59.9
49.3
968
Laach Sampl* Wt: 2 grama
Laachat*(9)
10.65
10.24
10.51
10.40
10.38
10.30
10.49
Laach(ug)
9574
7546
2806
1331
853
617
517
Total(ug)
13414
20960
23766
25097
25950
26567
27064
Total(ug/g)6707
10480
11883
12549
12975
13284
13542
Total(%)
46
72
82
86
89
92
93
QUAUTY CONTROL
Laachataa:
025
038
Duplicate
Duplicate
SRM
Spikt Racovtry
Soils: SRM
Soils: Blank
Soil Blank
Soil Spik*
Soil Spike Dup.
72.349.6
102.0
104.0%
101.0
< 20
<20
484
464
RPD - 0.82%
RPO - 0.61%
(Aeoaptabla Rang* 96.36 - 104.04)
(Aeoaptabla Rang* 80 -120%)
(Aooaptabi* Rang* 96.36 • 104.04)
(Datactabla Laval - 20)
(Oataetabla Lav»i . 20)
Raoovary « 90.8%
Raeovery - 92.8%
RPO • 2.07%
42
CfrGMSCOGNiS Extraction Tr*aiao«iy SludiM. 2nd mas* II Upd«« fitpoct R*fln«ry
Tabto VIII. QA/QC DATA
T.S. # : 204
SampleNumber
011
012
013
014
015
016
021
022
023
024
025
026
031
032
033
034
035
036
PH
1.14
0.99
0.97
0.94
0.94
SoU
1.13
0.99
0.96
0.93
0.93
Soil
1.13
1.00
0.97
0.94
0.94
Metals: Pb
LeachContact
1
2
3
4
5
Residue
1
2
3
4
5
Residue
1
2
3
4
5
Soil Residue
AA(ufl/0)
133
43.9
21.2
10.3
6.8
656
130
45.8
24.1
11.2
7.7
686
129
48.4
23.7
11.6
7.2
674
Leach Sample Wt.: 2 grams
Leachate(g)
9.47
10.56
10.51
10.50
10.54
9.42
10.44
10.45
10.40
10.41
9.35
10.2
10.39
10.39
10.41
Leach(ug)
1260
464
223
108
72
1225
478
252
116
80
1206
494
246
121
75
Total(ug)
1260
1723
1946
2054
2126
1225
1703
1955
2071
2151
1206
1700
1946
2067
2142
Total(ug/g)
630
862
973
1027
1063
612
851
977
1036
1076
603
850
973
1033
1071
Total(%)
37
50
57
60
62
35
48
55
59
61
35
49
56
59
61
43
CfcGMSCOGMIS MM* Exlmcdon ShjdtM, 2nd RUM II UpdM ftoport.
TabteVIII. QA/QCDATA
T.S. # : 204
SampleNumber
a HHal051
052
053
054
055
056
061
062
063
064
065
066
PH
^^m1.00
0.95
0.94
0.92
0.92
SOU
-
-
-
-
-
Metals: PbLeach
Contact•ala M
12
3
4
5
Residue
1
2
3
4
5
Soil Residue
AA(ug/Q)
a^aVM18
3.6
1.7
0.9
< 0.7
85.5
15.9
4.2
1.8
1.0
0.7
66
Leach Sample Wt: 2 gramsLeachate
(g)a^a^Hal
9.9
10.4
10.46
10.24
10.55
9.7
9.1
10.53
10.34
10.44
Leach(ug)
••••178
37
18
9
7
154
38
19
10
7
Total(ug)
mmmm178
216
233
243
250
154
192
211
222
229
Total(ug/g)aMHaV
89
108
117
121
125
77
96
106
111
115
Total(%)
•alBH42
51
55
58
59
38
48
53
55
57
QUALITY CONTROL
Leachates:
Spike Recovery 101%
Spike Duplicate Recovery 98.5%
(Acceptable Range 80 - 120%)
RPD - 1.48%
(Acceptable Range 80 - 120%)
RPD - 2.62%
Soils:
SRM
Blank
Soil Blank
Soil Spike
Soil Spike Dup.
103.5
< 20
<20
526
521
(Acceptable flange 96.36 - 104.04)
(Detectable Level - 20)
(Detectable Level - 20)
Recovery = 105.2%
Recovery = 104.2%
RPD = 0.95%
44
CfrGMS
COGNIS MMal Extraction TrMUOWty 9udto>. 2nd RUM H Updrt* Rtport,
TabtolX. QA/QCDATA
T.S. # : 204
SampleNumber
012
013
014
015
016
017
018
019
022
023
024
025
026
027
028
029
032
033
034
035
036
037
038
039
PH
1.7
1.13
1.04
1.02
1.00
0.98
1.01
SOD1.65
1.12
1.04
1.01
0.98
0.99
0.97
SOU
1.15
1.01
0.99
0.99
0.96
0.97
0.96
Metals: PbAcid Leach
Contact
1
2
3
4
5
6
7
Residue
1
2
3
4
5
6
7
Residue
1
2
3
4
5
6
7
SoN Residue
AA(ug/g)
167
46.1
10.6
5.1
3.0
2.5
1.8
359
170
45.9
10.8
5.7
3.2
2.4
1.9
388
21.4
4.5
2
0.8
<0.7
<0.7
<0.7
80
Leach Sample Wl: 2 grams
Leachate ,(g)
10.23
10.27
10.26
10.32
10.26
10.33
10.32
10.08
10.45
10.26
10.35
10.28
10.17
10.37
10.30
10.33
10.29
10.33
10.14
10.28
10.50
Leach(ug)
1708
473
109
53
31
26
18.6
1713
479
111
60
33
24
20
220.4
46.5
20.6
8.3
7.1
7.2
7.4
Total(ug)
1757
2231
2339
2391
2422
2449
2467
1762
2242
2352
2413
2446
2470
2490
242.9
289.4
310
318.3
325.4
332.6
340
Total(ug/g)
879
1115
1170
1196
1211
1224
1234
881
1121
1177
1207
1223
1235
1245
121.5
144.7
155
159.2
162.7
166.3
170
Total(%)
55
70
73
75
76
77
77
54
69
72
74
75
76
76
49
59
62
64
65
67
68
45
COGNIS Mew Extraction Tn*ici«y StudkM. 2nd RMM II Updtf* Report. Arrowrwwi Mflnwy
CfrGMS
Tab* IX QA/QCDATA
T.S. # : 204
SampleNumber
042
043
044
045
046
047
048
049
pH
1.16
1.00
0.98
0.96
0.98
0.96
0.96
Metals: PbAcid Leach
Contact
1
2
3
4
5
6
7
Sou Residue
AA(ug/g)19.9
3.8
1.5
0.7
0.7
<0.7
<0.7
43.5
Leach Sample Wt: 2 grams
Leachate(9)
10.15
10.44
10.17
10.49
10.36
10.20
10.36
Leach(ug)
202
39.7
15.3
7.32
7.3
7.1
7.3
Total(ug)
226.2
265.9
281.2
288.5
295.8
302.9
310.2
Total(ug/g)
113.1
133
140.6
144.3
147.9
151.5
155.1
Total(%)57
67
71
73
74
76
78
QUALITY CONTROL
Leachates:
Spike Recovery 111%
Duplicate Spike Recovery 110%
(Acceptable Range 80 - 120%)
RPD = 0%
(Acceptable Range 80 - 120%)
RPD - 4.46%
Soils:
SRM
Blank
Soil Blank
Soil Spike
Soil Spike Dup.
98.6
< 20
< 20
475
487
(Acceptable Range 96.36 - 104.04)
(Detectable Level = 20)
(Detectable Level - 20)
Recovery = 95%
Recovery = 97.4%
RPD - 2.49%
46
COGNIS MM Erfracikxi TrMUUtty StudlM. 2nd Phtt* II UpdlM Rtport. ArrownMd FMtrwry
C*GMS
TabtoX. QA/QCDATA
T.S. * : 204
SampleNumber
032
033
034
035
036
037
038
039
042
043
044
045
046
047
046
049
012
013
014
015
016
017
016
019
PH
-
-
-
-
-
-
-
Soil
-
-
-
-
-
-
-
SON
-------
Metals: Pb
Acid LeachContact
1
2
3
4
5
6
7
Residue
1
2
3
4
5
6
7
Residue
1
2
3
4
5
6
7
Sol Residue
AA(ug/g)
149
43.8
15.7
8.9
5.2
3.9
3.4
517
140
42.6
15.3
8.4
5.0
3.8
3.3
501
18.7
3.9
1.8
1.2
1.0
0.7
0.6
76.9
teach Sampto Wt.: 2 grams
Leachate(g)
9.85
10.42
10.34
10.26
10.39
10.36
10.40
9.80
10.43
10.42
10.37
10.41
10.39
10.37
10.36
10.35
10.2
10.32
10.31
10.44
10.48
Leach(ug)
1468
456
162
91.3
54.03
40.4
35.36
1372
444.3
159.4
87.1
52.1
39.5
34.2
193.8
40.4
18.36
12.4
10.3
7.3
6.3
Total(ug)
1618
2074
2236
2328
2382
2422
2458
1514
1958
2117.4
2204.5
2256.6
2296.1
2330.3
193.7
234.1
252.5
264.8
275.2
282.5
288.8
Total(ug/g)
809
1037
1118
1164
1191
1211
1229
757
979
1058.7
1102.3
1128.3
1148
1165
96.8
117.1
126.3
132.4
137.6
141.2
144.4
Total(%)
46
59
64
67
68
69
70
45
59
64
66
68
69
70
44
53
57
60
62
64
65
47
CfcGMSCOGNIS Extraction TrMUDWy SludtM, 2nd RWM ii UpdM Report, ArrowhMd FWtn*ry
Tabto X. QA/QC DATA
T.S. * : 204
SampleNumber
022
023
024
025
026
027
022
029
PH
-
-
-
-
-
-
-
Metals: Pb
Acid LeachContact
1
2
3
4
5
6
7
SoU Residue
AA(ug/g)19.9
3.9
1.9
1.3
1.0
0.8
0.7
103
Leach Sample Wt.: 2 grams
Leachate(9)
10.32
10.26
10.33
10.24
10.33
10.38
10.46
Leach Total(ug) (ug)
205.4 245.4
40.0 265.0
19.6 278.3
13.3 288.7
10.3 297
8.3 304.3
7.3
Total Total(ug/g) (%)102.7 40
122.7 48
132.5 52
139.2 55
144.3 57
148.5 58
152.1 60
QUALITY CONTROL
Leachatas:
012
022
034
043
Duplicate
Duplicate
Duplicate
Duplicate
SRM
Spike Recovery
18.3
19.9
15.6
42.1
102.6
82.8%
RPD = 1.89%
RPD = 0.00%
RPD - 0.64%
RPD - 1.18%
(Acceptable Range 96.36 -104.04)(Acceptable Range 80 -120%)
Soils:
SRM
Blank
Soil Blank
Soil Spike
Soil Spike Dup.
< 26
< 26
476
496
(Acceptable Range 96.36 - 104.04)
(Detectable Level - 20)
(Detectable Level - 20)
Recovery - 95.2%
Recovery * 99.2%
RPD = 4.22
48
CfrGMSCOGNIS MMM Exiracuon Studtot. 2nd RUM II UpdcU fltport, AmwttMd
Table XI. QA/QCDATA
T.S. # : 204
SampleNumber
PH
Metals: Pb
Acid LeachContact
AA(ug/g)
Leach Sample Wt.: 2 grams
Leachate(g)
Leach(ug)
Total(ug)
Total(ug/g)
Total(%)
Condition #7
031 (7)
032 (7)
033 (7)
034 (7)
035 (7)
036 (7)
037 (7)
038 (7)
041 (7)
042 (7)
043 (7)
044(7)
045 (7)
046(7)
047 (7)
048 (7) }
-
-
-
-
-
-
-
Soil
.
-
-
-
-
-
-
1
2
3
4
5
6
7
Residue
1
2
3
4
5
6
7
Soil Residue
29.8
125
26.6
15.7
20.1
5.6
3.3
551
30.0
123
36.7
14.7
19.4
5.3
3.10
531
8.94
10.39
10.25
10.33
10.16
10.36
10.33
9.04
10.29
10.32
10.29
10.14
10.37
10.30
266.4
1298.8
375.2
162.2
204.2
58.0
34.1
271.2
1265.7
378.7
151.3
196.7
55
31.9
266.4
1565.2
19403
2102.5
2306.7
2364.7
2399
271.2
1536.9
1915.6
2066.9
2263.6
2318.6
2350.5
133.2
782.6
970.2
1051.3
1153.4
1182.4
1199.4
135.6
768.4
957.8
1033.4
1131.8
1159.3
1175.2
8
45
56
61
67
68
69
8
45
57
61
67
69
69
Condition #8
012 (8)
013(8)
014 (8)
015(8)
016 (8)
017 (8)
018 (8)
-
-
-
-
-
-
1
2
3
4
5
6
Sou Residue
177
54.5
15.9
15.7
3.9
2.0
424
10.05
10.25
10.27
10.18
10.27
10.38
1778.9
527.9
163.3
159.8
40.1
20.8
1798.2
2326.1
2489.4
2649.2
2689.2
2710
899.1
1163.0
1244.7
1324.6
1344.6
1355
51
66
70
75
76
76
49
COGNIS MMM Extracdon TPMttOHty Stuotot, 2nd RUM II Updtf* Report. ArrowrwM
C*GMS
TabtoXI. QA/QCDATA
T.S. # : 204
SampleNumber
022 (8)
023 (8)
024 (8)
025 (8)
026 (8)
027 (8)
028 (8)
011 (9)
012 (9)
013 (9)
014 (9)
015 (9)
016 (9)
017(9)
018 (9)
021 (9)
022 (9)
023 (9)
024 (9)
025 (9)
026 (9)
027 (9)
028 (9)
PH
-
-
-
-
-
-
Soil
-
-
-
-
-
-
-
Metals: Pb
Acid LeachContact
1
2
3
4
5
6
Residue
1
2
3
4
5
6
7
Residual Soil
.
-
-
-
-
-
-
1
2
3
4
5
6
7
Restdual Soil
AA(ug/g)
177
51.2
15.7
15.7
3.9
2.0
409
255
61.2
21.4
10.9
8.1
5.3
4.2
311
241
56.6
18.2
10.6
8.3
5.7
3.9
311
Leach Sample Wt.: 2 grams
Leachate(g)
9.94
10.24
10.41
10.21
10.20
10.31
7.24
10.35
10.34
10.34
10.27
10.67
11.08
7.56
10.82
10.8
10.64
10.89
10.98
10.66
Leachtug)
1759.4
524.3
163.4
160.3
39.8
20.6
1846
633
221
113
83
57
47
1822
612
197
113
90
63
42
Total<ug)
1772.4
2296.7
2460.1
2620.4
2660.2
2680.8
1846
2480
2701
2814
2897
2953
3000
1822
2434
2631
2744
2834
2897
2938
Total(ug/g)
886.2
1148.3
1230
1310.2
1330.1
1340.4
923
1240
1350
1407
1448
1477
1500
911
1217
1315
1372
1417
1448
1469
Total(%)
51
66
71
75
76
77
52
69
76
79
81
83
83
52
69
75
78
81
82
83
50
CfrGMS
COGNIS Extraction TrMUOWty StudM. 2nd RUM II UpdM Report. A/rawftMd
T.S. * : 204
SampleNumber
Leachates:
034(7)
042 (7)
023 (8)
014(9)
022 (9)
SRM (8)
TabtoXl. QA/QCDATA
Metals: PbpH Acid Leach
ContactAA
(ug/g)
Leach Sample Wtr 2 grams
Leachate Leach Total Total Total(9) (ug) (ug) (ug/g) (%)
QUALITY CONTROL
Duplicate
Duplicate
Duplicate
Duplicate
Duplicate
Spike Recovery (8)
Spike Recovery (9)
15.3
123
50.6
10.9
58.2
103
88.9%
90.9%
RPD - 0.33%
RPD = 0.16%
RPD = 1.18%
RPD = 0.46%
RPD = 2.76%
(Acceptable Range 96.36 -104.04)
(Acceptable Range 80 -120%)
(Acceptable Range 80 - 120%)
Soils:
SRM (7) (8)
Blank (7) (8)
Blank (9)
Soil Blank (7) (8)
Soil Blank (9)
Soil Spike (7) (8)
Soil Spike Oup. (7) (8)
101.2
< 20
< 26
< 20
< 26
514
519
Soil Spike (9)
Soil Spike Dup (9)
478
468
(Acceptable Range 96.36 - 104.04)
(Detectable Level = 20)
(Detectable Level = 20)
(Detectable Level = 20)
(Detectable Level = 20)Recovery = 102.8%
Recovery - 103.8%
RPD - 1.9%
Recovery = 95.6%
Recovery = 93.6%
RPD - 2.03%
51
CfrGMS
COGNIS M*W ExlracOor TrMMHMy StuOtM. 2nd RUM II UptMM ftoport. Rtfkwy
T.S. # : 204
SampleNumber
071
072
073
074
075
076
081
082
083
084
085
086
PH
1.14
0.98
0.97
0.94
0.94
Soil
-
-
-
-
-
Tabl« XII. QA/QC DATA
Metals: Pb
LeachContact
1
2
3
4
5
Residue
1
2
3
4
5
Soil Residue
AA(ug/g)46.6
11.5
4
1.7
1.1
122
45.6
11
3.6
1.6
1.0
134
Leach Sample Wt.: 2 grams
Leachate(g)
9.31
10.37
10.28
10.52
10.39
9.26
10.45
10.25
10.65
10.17
Leach(ug)
434
119
41
18
11
422
115
37
17
10
Total(ug)
434
553
594
612
624
422
537
574
591
601
Total(ug/g)
217
277
297
306
312
211
269
287
296
301
Total(%)
50
64
68
71
72
49
62
66
68
69
QUAUTY CONTROL
Leachates:
Spike Recovery 101% (Acceptable Range 80 -120%)
RPD = 1.48%
Soils:
SRM
Blank
Soil Blank
Soil Spike
Soil Spike Dup.
103.5
< 20
< 20
526
521
(Acceptable Range 96.36 - 104.04)
(Detectable Level - 20)
(Detectable Level - 20)
Recovery = 105.2%
Recovery = 104.2%
RPD - 0.95%
52
C*GMS
COGNIS M«W Extmcflon TrNtabMy Studtac. 2nd PhM* H Updttt Rtport AmnwrtMd Mttwy
TabteXIV. QA/QCDATA
QUALITY CONTROL
Leachates:SRM
Spike Recovery
101
108%(108, 109)
Spike Duplicate Recovery 105%(104, 106)
(Acceptable Range 96.36 -104.04)
(Acceptable Range 80 -120%)
RPO = 1.62%
(Acceptable Range 80 -120%)
RPD = 1.78%
Soils:
Blank
Soil Blank
Soil Spike
Soil Spike Dup.
< 26
< 26
234
229
(Detectable Level - 20)
(Detectable Level - 20)
Recovery = 93.6%
Recovery = 91.6%
RPD = 2.10%
53
CfcGMSCOGNIS hMM extraction TrMttDWy Sludln. 2nd PhBM II UpdM Report. ArrownMd fltflrwry
Tabto XV. QA/QC DATA
QUAUTY CONTROL
Leachatet:
Duplicate [3 Influent]
Duplicate [6 Influent]
Spike Recovery
46.6
11.5
97.6%
RPD = 0.64%
RPD - 0.00%
(Acceptable Range 80 -120%)
Soils:
Blank
Soil Blank
Soil Spike
Soil Spike Dup.
< 26
< 26
473
475
(Detectable Level =
(Detectable Level =
20)
20)
Recovery = 92.4%
Recovery = 92.8%
RPD * 3.09%
54
C*GMSCOGNIS M«d Extraction TrMtaUMy SIUOM. 2nd RWM 11 upon ftoport. A/rowtwea
TabteXVl. QA/QCDATA
QUAUTY CONTROL
Leacnater
Duplicate [3 Influent]
SRM
Spike Recovery
19.1 RPD = 1.31%
101.7 (Acceptable Range
93.9% (Acceptable Range
96.36 • 104.04)
80-120%)
Soils:
SRM
Blank
Soil Blank
Soil Spike
Soil Spike Dup.
101.0 (Acceptable Range
< 20 (Detectable Level -
< 20 (Detectable Level =
96.36 - 104.04)
20)
20)
454 Recovery = 90.8%
464 Recovery = 92.8%
RPD = 2.07%
55
Ct>GMS
COGNIS MMal Extraction TrwiabWy StudlM, 2nd Ria»t II Update Report Arrowrwad Heflnwy
Table XVII. QA/QC DATA
QUAUTY CONTROL
Leachatet:
Duplicate [influent 1 ]
Spike Recovery
8.6
90.9%
RPD = 0.0%
(Acceptable Range 80 -120%)
Soil*:
Blank
Soil Blank
Soil Spike
Soil Spike Dup.
< 26
< 26
473
475
(Detectable Level = 20)
(Detectable Level - 20)
Recovery = 92.4%
Recovery - 92.8%
RPD = 3.09%
56
CfcGMS
COGNiS M«UI Extraction TruiaotMty stud**, 2nd RUM n Updau ftoport AmwrtMd Rvfinwy
Tabta XVIII. QA/QC DATA
QUAUTY CONTROL
Leachater
Duplicate (6 Influent]
SRM
Spike Recovery
Spike Duplicate Recovery
1.5
97.3
101%
102%
RPD = 13.13%
(Acceptable Range 96.36 -104.04)
(Acceptable Range 80 -120%)
(Acceptable Range 80 -120%)
Soils:
SRM
Blank
Soil Blank
Soil Spike
Soil Spike Dup.
101.0
< 20
< 20
454
464
(Acceptable Range 96.36 - 104.04)
(Detectable Level - 20)
(Detectable Level * 20)
Recovery - 90.8%
Recovery = 92.8%
RPD - 2.07%
57
C*GMSCOGNIS hWal Extraction TrMUOHty SudlM, 2nd Rmt II UpdM Ftopon ArrawrtMd
APPENDIX B
COGNIS Standard Operating Procedures Referenced
58
C*GNIS
COGNIS, INC.ANALYTICAL TECHNOLOGY
Page 1 of 4SOP01 8.001
STANDARD OPERATING PROCEDURES
EFFECTIVE: 12-04-92
SUPERSEDES: NONE
TITLE: TOTAL PETROLEUM HYDROCARBONS BY FTIR
APPROVAL: fa^ /?2<*/4^ DATE;
APPROVAL: L T). **7£j£z/. tfd rtL^ DATE: V - /———— ' ™
1.0 PURPOSE AND SCOPE
1.1 This Standard Operating Procedure (SOP) describes a method for themeasurement of extractabte matter from soil and shake flasks, it is applicable tothe determination of hydrocarbons, vegetable oils, animal fats, waxes, soaps,greases and related matter. The method is also applicable to the measurementof most light petroleum fuels, although some loss of any gasoline present duringthe extraction manipulations can be expected.
1.2 The scope of this method includes organic components having a concentration inthe soil of >100 mg/Kg (estimated).
2.0 SUMMARY OF METHOD
2.1 The sample is extracted using the procedure for Shake Flasks SOP020, orUltrasonic Extraction SOP016. TTie extract is diluted and subjected to silica geltreatment before infrared analysis. The petroleum hydrocarbons are determinedby comparison of the infrared absorbance of the sample extract with standards.
3.0 SAFETY HIGHLIGHTS
3.1 ETHYL ETHER (ether) is an extremely flammable liquid, highly volatile, harmful ifswallowed or inhaled, use with adequate ventilation.
3.2 FREON 113 is harmful if inhaled, has anesthetic properties, may cause irritation.
C*GMS
SOP NUMBER SOP018.001 Page 2 of 4
4.0 APPARATUS
4.1 Infrared spectrophotometer, Digitab FTS-60 or equivalent.
4.2 10 mm quartz cell.
4.3 Volumetric flasks, 100, 50, and 25 ml.
4.4 Pipets, 1, 2, 5, 10 ml.
4.5 Sample filter, Prep-Disc BIO-RAD 343-0001 or equivalent.
5.0 REAGENTS
5.1 Freon 113 (l.i^-trichloro-i^-trifluoroethane), pesticide quality or equivalent.
5.2 Sodium sulfate, anhydrous crystals.
5.3 Silica gel, 70-230 mesh, Aldrich catalog # 28,862-4.
5.4 Calibration mixtures:a. Reference oil: Pipet 15.0 ml n-hexadecane, 15.0 ml isooctane, and 10.0 ml
chtorobenzene into a 50 ml glass stoppered bottle.
b. Stock standard: Pipet 1.0 ml reference oil into a tared 200 ml volumetricflask and immediately stopper. Weigh and dilute to volume with freon-113/
c. Working standards: Pipet 1, 2, 4, 5, and 10 ml volumes of stock standardinto 100 ml volumetric flasks to make working standards for the calibrationcurve.
6.0 PROCEDURE
6.1 Pipet 1.0 ml of the extract solution from either the Ultrasonic extraction procedure(COGNIS AT SOP016) or the Shake Flask extraction proceaure (COGNIS ATSOP020) into a 25 ml volumetric flask. Dilute to the mark with freon 113.
6.2 Discard 3-4 ml solution from the volumetric flask. Add 3 g silica gel, stopper andshake for a few seconds every minute for 5 minutes. It is not necessary to addsilica gel to the working standards.
C*GNIS
SOP NUMBER SOP018.001 Page 3 of 4
6.3 Calibrate the instrument using the 10 mm cell and the working standards.Determine the absordance at the peak near 2930 cm"1 for each solution. Preparea calibration plot of absorbance vs. mg petroleum hydrocarbon 100 ml solution.This 5 point calibration must be done on a monthly basis.
6.4 After the silica gel has settled in the sample extract, fill a clean cell with solutionand determine the absorbance of the extract. If the absorbance exceeds 0.8prepare an appropriate dilution. The possibility of the absorptive capacity of thesilica gel has been exceeded can be tested at this point by adding another 3 gsilica gel to the extract and repeating the treatment and determination.
6.5 Calculations:
a. Calculate the petroleum hydrocarbons in the sample using the formula:
mg/kg Petroleum Hydrocarbon - R X D X 1000S
where:
R = mg of petroleum hydrocarbons as determined from thecalibration plot.D = extract dilution factor, if used.S = weight of sample in grams.
6.6 Precision and Accuracy:a. Precision data is not available at this time. Duplicates and triplicates have
been used as part of the pnase 1 measurements, Accuracy measurementsusing spiked soil samples are underway.
7.0 METHOD QC
7.1 For each analytical batch (1-7 samples):
a. Blank. To check method for contamination.
b. Duplicate. To check precision (relative percent difference).
c. Spike. To check accuracy (percent recovery)
d. Laboratory control sample. A secondary standard to check for methodcontrol.
C*GMS
SOP NUMBER SOP018.001 pagt 4 0( 4
3.0 REFERENCES
8.1 Petroleum Hydrocarbon, Total Recoverable. Method 418.1 Storet No. 45501.
8.2 Procedure for glassware cleaning is found in "Chemical Technicians ReadyReference Handbook" (COGNISt Inc. library reference number HTC QD 61.S58).
8.3 Procedure for operation of an analytical balance is found in COGNIS, Inc.Analytical Technology standard operating procedure COGAT-4A and in operatingmanuals of individual balances.
CfrGMS
COGNIS, INC.ANALYTICAL TECHNOLOGY
Page 1 of 3SOP01 9.001
STANDARD OPERATING PROCEDURES
EFFECTIVE: 12-04-92
SUPERSEDES: NONE
TITLE: TOTAL EXTBACTABLES. GRAVIMETRIC METHOD
APPROVAL: -»~ _______ DATE: A -*~f 2~
APPROVAL: >- *ZZ ^A aJ" DATE: /2 - ? '^
1.0 PURPOSE AND SCOPE
1.1 This Standard Operating Procedure (SOP) describes a method that includes themeasurement of extractadle matter from soil samples. It is applicable to thedetermination of hydrocarbons, vegetable oils, animal fats, waxes, soaps, greases,and related matter. The method is applicable to measurement of most lightpetroleum fuels, although some loss of any gasoline present during the extractionmanipulation can be expected.
1.2 Applicable to organic components having a concentration in the soil of >100mg/kg (ppm).
2.0 SUMMARY OF METHOD
2.1 The sample is extracted using the procedure for Shake Flasks (SOP020) orUltrasonic Extraction (SOP016). An aliquot of the extract is weighed and theamount of total extractables is calculated.
3.0 SAFETY HIGHLIGHTS
3.1 Ethyl Ether (ether) is an extremely flammable liquid, highly volatile, harmful ifswallowed or inhaled, use with adequate ventilation.
3.2 Freon 113 is harmful if inhaled, has anesthetic properties, and may cause irritation.
C*GMS
SOP NUMBER SOP019.001 Page 2 of 3
4.0 APPARATUS
4.1 Balance, capable of accurately weighing to the nearest 0.1 mg.
4.2 Pipet, 15 ml.
4.3 6 dram glass vials.
5.0 PROCEDURE
5.1 Pipet 15 mi of the extract solution from either the ultrasonic extraction procedure(SOP016) or the Shake Flask extraction procedure (SOP020) into a tared 6 dramglass vial.
5.2 Pipet 15 ml of the extraction solvent into another tared 6 dram vial.
5.3 Remove the solvent on a steam bath under a stream of clean, dry nitrogen.
5.4 Cool down vials to room temperature in a desiccator.
5.5 Determine weight of residue to the nearest 0.1 mg.
6.0 CALCULATIONS
6.1 Calculate the total extractabtes using the following formula:
mg/kg total extractables = (R - m x 3.3333 x 1000W
where:R » weight of residue in mg.8 - weight of blank in mg.3.3333 » 15 of 50 ml used in determination.1000 = g/kg.W = weight of sample in g
C*GNIS
SOP NUMBER SOP019.001 Page 3 of 3
7.0 METHOD QC
7.1 For each analytical batch (1-7 samples):
a. One blank. To check method for contamination.
b. One duplicate. To check precision (relative percent difference).
c. One spike. To check accuracy (percent recovery).
d. One laboratory control samcle. A secondary standard to check for methodcontrol (control chart).
8.0 REFERENCES
8.1 Oil and Grease, Total Recoverable. Method 413.1 Storet No. 00556.
8.2 Procedures for glassware cleaning and use of pipet are described in "ChemicalTechnicians' Ready Reference Handbook" (COGNIS, Inc. library reference numberHTCQD61.S58).
8.3 Procedure for operation of an analytical balance is found in COGNIS, Inc.Analytical Technology standard operating procedure COGAT-4A and in operatingmanuals of individual balances.
CfrGMS
COGNIS. INC.ANALYTICAL TECHNOLOGY
Page 1 of 4SOP020.001
STANDARD OPERATING PROCEDURES
EFFECTIVE: 12-04-92
SUPERSEDES: NONE
TITLE: SHAKE FM*SK EXTRACTION PROCEDURE
APPROVAL ik6^'/fy£w*~*_______ DATE: / 2. "^ ~^
APPROVAL: /. 2). fZZl. OA aJ^^ DATE: /j? - /-— "
1.0 PURPOSE AND SCOPE
1.1 This Standard Operating Procedure (SOP) describes a method for extractingnonvolatile and semi-volatile organic compounds from shake flasks generallycontaining approximately 30% water and 20 % soil with a total volume ofapproximately 100 ml.
1.2 This method is applicable to organic components having a concentration in the soilof >100 mg/Kg.
2.0 SUMMARY OF METHOD
2.1 The entire contents of the shake flask is extracted with ethyl ether at least threetimes. The extract is separated from the sample by decanting after centrifugation.The extract is ready for cleanup and/or analysis following concentration. Forinfrared analysis following extraction, a solvent exchange must be performed.
3.0 SAFETY HIGHLIGHTS
3.1 ETHYL ETHER (ether) is an extremely flammable liquid, highly volatile, harmful ifswallowed or inhaled, and should be used with adequate ventilation.
C*GMS
SOP NUMBER SOP020.001 Page 2 ol 4
4.0 APPARATUS
4.1 250 ml Naigene centrifuge bottles.
4.2 Sorvall Instruments RC5C centrifuge or equivalent.
4.3 Disposable Serological pipets.
4.4 Portable pipet aid filler and dispenser.
4.5 Heated water bath with concentric rings.
4.6 Beakers - 400 ml.
4.7 Boiling chips • silicon carbide.
4.8 Volumetric flasks, 50 ml.
4.9 Millipore pressure filter with 0.5 micron filter membranes.
5.0 REAGENTS
5.1 Sodium sulfate, anhydrous crystals.
5.2 Ethyl Ether, Pesticide quality or equivalent.
5.3 Hydrochloric acid, reagent grade, diluted 1:3 in water.
5.4 Goldridge reference soil.
5.5 Matrix spiking standard mixture (1:1 by weight mixture of Mazola corn oil and n-Hexadecane.
6.0 PROCEDURE
6.1 Sample handling At time of submission all samples are placed in a refrigeratoroperating at approximately 4 °C. and stored until analysis.
C*GMS
SOP NUMBER SOP020.001 Pagt 3 of 4
6.2 Extraction procedure
a. Transfer contents of shake flask into a 250 ml centrifuge bottle. Rinse theshake flask first wrth three 5 ml portions of water followed by three 5 mlportions of ether. Add 3 ml hydrochloric acid solution.
b. To prepare matrix spike; weigh accurately approximately 20 g Gofdridgereference soil into a centrifuge bottle, add 150 mg spiking standard mixture.Record weights to nearest 0.1 mg. Add 80 ml water and approximately 40ml ether and close the bottle.
c. Shake vigorously for two minutes. Release pressure slowly. Recap bottleand centrifuge at 10,000 RPM for 5 minutes to break the emulsion.
d. Decant extract into a 400 ml beaker. Serological pipets and a pipet aidfiller/dispenser may be used.
e. Repeat the extraction two or more times wrth additional portions of solvent.Decant the solvent after each extraction. If the sample is expected tocontain more than 10% total recoverables, two additional extractions arenecessary. After the final extraction, rinse the pipet into the beaker with afew ml extraction solvent.
f. Add one or two boiling chips and concentrate on the water bath under agentle stream of clean, dry nitrogen to a volume of about 30 ml.
g. Pressure filter into a 50 ml volumetric flask through a Millipore filter equippedwith a 0.5 micron pore membrane. Five grams of anhydrous sodium sulfateis added to the filter assembly to remove any water that has been collected.5 psi is generally used, more pressure may be used if necessary (up to 45psi).
h. Rinse the filter flask and the Millipore filter three times with 3 to 4 ml etherDilute to mark wrth and stopper.
C*GMS
SOP NUMBER SOP020.001 Pag. 4 of 4
7.0 REFERENCES
7.1 Method 3550B. Test Methods for Evaluating Solid Wastes Physical/ChemicaiMethods SW856
7.2 Procedures for glassware cleaning and use of votumetric glassware are describedin "Chemical Technicians' Ready Reference Handbook" (COGNIS, Inc. libraryreference number HTC QD 61.S58).
7.3 Procedure for operation of an analytical balance is found in COGNIS, Inc.Analytical Technology standard operating procedure COGAT-4A and in operatingmanuals of individual balances.
Minnesota Pollution Control Agency Technical Support Memo,
From : Rodolphe Cramail, Engineer AJI** (n ~P-cAndrew Streitz, Hydrogeologist Arz<;
To : Ted Smith, EPA Project ManagerTom Kelley, MPCA Project Leader
Re : Arrowhead Site: Soil Washing Benchscale ResultsDate : 9/2/93
Introduction: highlights on soil washingSection 121b of CERCLA recommends/prefers remedial actions in which treatment"permanently and significantly reduces the volume, toxicity or mobility of hazardoussubstances, pollutants and contaminants" as a principal element. Further, "The offsitetransport and disposal of hazardous substances or contaminated materials without suchtreatment should be the least favored alternative remedial action where practicable treatmenttechnologies are available." Soil washing satisfies these requirements through the reductionof the volume of contaminated soils and the resulting placement of cleaned soils back on thesite.
Soil washing is a liquid-based {often water) process that mechanically separates the differentparticle size classes of a soil, transferring and concentrating the contamination from thewhole soil into the fine fractions which can then be recovered. Therefore it generatescontaminated fines and clean sandy and oversize fractions. This can lead to a considerablereduction in the volume of contaminated material depending on the original fraction of thefines in the total soil because the efficiency of the soil washing process is driven mainly bythe particle size distribution of the soil to be processed as well as by the mobility of thecompounds to be treated.
Status of Soil Washing as Remedial Alternative:Soil washing is an innovative technology which was chosen for remediation (as of August1991) for 16 Super-fund sites and that has been demonstrated under the EPA SITE program(US EPA. "The Superfund Innovative Technology Evaluation (SITE) program : TechnologyProfiles, Fourth Edition."). Though not widely used in the US, at least five remediationcompanies use it regularly in the Netherlands.
Suitability of the Arrowhead site contaminated soils to soil washing treatment:According to EPA guidance (US-EPA, Engineering Bulletin: "Soil washing treatment."EPA/540/2-90/017, September 90) aa it applies to the particle size distribution datagenerated at the Arrowhead site, the soils are amenable to soil washing. The percentage offines observed at the Arrowhead site range from 9 to 28% (table 1), resulting potentially ina volume reduction of 72 to 90%.
Table 1: Currently available particle size distribution dataSource :
Fines %Upper Mesh
EcovaBiostudy:26/7/8/9
<200
BARR/ABBBiostudv:
18<140
CognisPhase 1a:
9<270
CognisPhase 1b:
12Lamotte cl.
CognisPhase 227/28<140
The Arrowhead soils are essentially fill, and therefore primarily sands and gravels with debrisand gross oversize particles also present. For this type of soil, washing is considered agood choice for lead contamination treatment. Vendor and data base information (US-EPAV.I.S.I.T.T. Data Base) is supportive:• Observed particle size distribution of the site soils fits the basic requirements of soil
washing.• TPH, PAH and Lead contamination in soils can be effectively remediated by soil washing
in the range of concentration observed at Arrowhead and down to levels below sitecleanup levels.
As soil washing efficiency is mainly driven by the fines content, it is reasonable to assumethat this process will be rather insensitive to contaminate concentration variation.
Existing data on soil washing efficiency at the Arrowhead site :Within the framework of the lead removal treatability study phase 2, COGNIS performed asoil washing step on a batch scale sample {5 - 6 kg) of Arrowhead soils. The contaminantconcentrations appear to be representative of the fill soils for the entire process area with aTPH content of 4-6%, and a lead content of 1000-2000 ppm. COGNIS was able to achievea 75% volume reduction through emulsifier enhanced soil washing, corresponding to anobserved average particle size distribution of oversize/sand/fines of 30/45/25% respectively.The soil washing step of the benchscale was performed by the Alaskan company BESCORP,whose soil washing process was demonstrated under the EPA SITE program at the AlaskanBattery Enterprises Site in the summer of 1992.
Table 2: Soil Wash results COGNIS phase IISoil Fraction
Total Pb (ppm)TCLP Pb (mg/l)
TPH (%)
Oversizenot analyzednot analyzednot analyzed
Sand222
pass « 1 }0.93
Fines1650
fail (>5)7.9
Oversized was not analyzed because: 1) it is assumed the wash is both more efficient forthis sized particle and because contaminants correlate with available surface area, and 2) ofthe difficulty in sampling and submitting this matrix to analysis.
An oil phase was recovered, but the volume (on the order of 0.01 liter) was too small tosubmit to analysis. COGNIS considers the oil recovered from the large scale remediation ofthe soils to be classed as an off-specification oil. Depending on the final concentration ofPb, a BIF unit can either be paid to burn or given the oil as an alternate fuel.
Wash water was recycled during the process, reaching a TPH concentration at the end ofthe Benchscale of less than 24 ppm.
Full Scale ImplementationBESCORP/COGNIS is currently carrying on a full scale remedial action on Pb contaminatedsoils utilizing this technology at TCAAP (Twin Cities Army Ammunition Plant), an NPLSuperfund Site in Minneapolis.
Relationship with other treatment trains:The selection of soil washing does not preclude the use of any other treatment such as solidphase bioremediation or Pb removal {acid extraction and precipitation of Lead), where soilwashing would be a pretreatment for further remediation. It can also function as the soletreatment prior to landfilling.