Cogeneration at UC July 18, 2013
2
Welcome
3
Transformation of thePower Plant
POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007
4
Power Plant Site transformedCampus Recreation Center
POWER PLANT SITE OF REC CENTER CAMPUS RECREATION CENTER
Investing for the future
• $84,000,000 Construction of Central Utility Plant 2004• $6,000,000 Solar Turbine Maintenance contract 2004 - 2011• $6,000,000 Construction of Thermal Storage System 2011 • $7,000,000 Construction of New Substation
• Total Investment of Over $100,000,000
5
Central Utility Plant
Childrens Hospital Medical Center Shriners Hospital for Children
Veterans HospitalUniversity Hospital Hoxworth Blood Bank
Holmes Hospital
Hospitals Served by UC Utilities
8
University of Cincinnati Consolidated Utilities
• UC and 6 Hospitals• 100 buildings• 12 million square feet
• Two Utility Production Plants
• Piping/Tunnel System• 100% distribution
9
• Electric production 47MW• Steam Production
• 610,000 pounds-per-hour capacity-coal, gas, oil, interruptible gas
• Chilled Water Production • 34,000 tons capacity• natural gas and electric chillers
• Thermal Energy Storage• 2.8 million gallons of chilled water East Campus• 4.0 million gallons of chilled water West Campus
Consolidated Utilities Operations Capacity
10
• Steam Pipes - 35,509 Linear Feet• Chilled Water Pipes - 32,889 Linear Feet• Tunnels - 13,947 Linear Feet
Utilities Distribution System
Central Utility Plant
• 2 Solar Titan Combustion Turbines• 12.47 kV• 13,400 kVA
State of the Art Electric Production Equipment
• 2 ERI HRSGs• 600 PSIG• 40,000 #/hr • 120,000 #/hr with burners
Heat Recovery From Cogen Increases Efficiency
•Overall efficiency is double the efficiency of a large utility plant
• Use for campus heat in winter• Use for more electricity in summer• 20 MW steam turbine generator• 12.47 kV
Additional Electric Production Equipment
Cogen Benefits
• Increased Reliability• “Free” Steam• $2,590,000 per year
of savings• Lower Emissions•No transmission and distribution losses
Certified Emission Monitoring System
Cogen Benefits
17
Electric Monitoring
• Duke Energy Ohio regulated
• DERS non regulated supply
• Both depend on PJM 5 CP
• 5 CP is determined by regional transmission operator
• 5 CP stands for top 5 highest coincident peaks in PJM total territory
Peak Load Is Main Priority
Weather in DC,
Philadelphia, New
Jersey, or Chicago
Could affect total
Peak load
PJM Service Territory
PJM Historical Coincident Peak Hours
Year Date_Time Year Date_Time2006 8/2/2006 17:00 2009 8/10/09 17:002006 8/1/2006 17:00 2009 8/18/09 16:002006 7/17/2006 17:00 2009 8/17/09 17:002006 7/31/2006 17:00 2009 8/11/09 17:002006 8/3/2006 16:00 2009 8/20/09 17:002007 8/8/2007 17:00 2010 7/7/2010 17:002007 8/7/2007 17:00 2010 7/6/2010 17:002007 7/9/2007 17:00 2010 7/23/2010 17:002007 8/2/2007 17:00 2010 8/10/2010 17:002007 6/27/2007 16:00 2010 8/11/2010 17:002008 6/9/2008 17:00 2011 7/22/2011 15:002008 7/17/2008 17:00 2011 7/21/2011 17:002008 7/18/2008 17:00 2011 7/20/2011 17:002008 7/21/2008 17:00 2011 7/19/2011 17:002008 6/10/2008 17:00 2011 6/8/2011 17:00
• Look at the trend• Peak is almost always
hour ending 17:00• Only 4 of 25 hours were
not hour ending 5PM and they were close
20
DATE HOUR PEAK TIME
Meter - 105014030
(kw)
Meter - 106156664
(kw)
Meter - 106995461
(kw)
Meter - 108026022
(kw)
Meter - 108026025
(kw) Total (kw)PeakAverag
(kw)70512 15:00-16:00 1530 0 0 0 0 57.6 57.6 28.870612 16:00-17:00 1615 0 0 0 0 0 0 071612 16:00-17:00 1615 0 0 0 0 0 0 071712 16:00-17:00 1615 0 0 0 0 57.6 57.6 14.471812 14:00-15:00 1445 0 0 0 0 57.6 57.6 14.4
Average 11.52
Last Year’s 5 Peak days
These results are excellent and avoided millions of dollars of additional demand charges on our electric bill
•Electric Bill would be additional $380,000 per month higher
CTG Performance
Simple Fuel Operation
• We use 600 cfm more gas to produce additional 5,000 kW
• This is equal to 36 MCF per hour
• $4 per MCF = $144/5,000kWh = $0.0288/kWh
• $5 per MCF = $180/5,000kWh = $0.036/kWh
• $6 per MCF = $180/5,000kWh = $0.0432/kWh
• $7 per MCF = $180/5,000kWh = $0.0504/kWh
• $10 per MCF = $180/5,000kWh = $0.072/kWh
O& M Costs
• 4 Additional Operators
• Full Service Contract with Solar
• $1,500,000 per year fixed cost
• $0.01/kWh
Debt Costs
• Tax Exempt Bonds
• Low Interest rates
• $40,000,0000
• $3,600,000/ yr
• $0.02/kWh
• Could be less if you needed more capacity
Gas is still low but climbing
EFFICIENCY RESULTS
Energy use per student down 30% over last 9 years
City water usage down 43% over last 9 years
GF Adjusted Utility Budget Compared to PUCO Historical Commercial &
Industrial Rates for Cincinnati
Award Winning Operations
Energy Conservation• Saves money • Reduces carbon footprint• Over $2,500,000 of rebates• Promotes sustainability• Duke Power Partner Award
Awards and Honors• 2012 International Thinking Buildings Award • 2011 EPA Combined Heat and Power Award• 2010 EPA Combined Heat and Power Award• 2009 EPA Combined Heat and Power Award• 2005 Energy Project of the Year, Association of Energy Engineers (AEE)• 2005 System of the Year, International District Energy Association (IDEA)• 2005 CHP Certificate of Recognition, U.S. EPA • 2005 Governor’s Award for Excellence in Energy, State of Ohio • 2003 Ohio Governor’s Award for Excellence, highest award in the Ohio Award for Excellence competition • 2001 Corporate Energy Management of the Year, Association of Energy Engineers (AEE) • 2001 Award for Excellence in Facilities Management, Association of Higher Education Officers (APPA) • 2000 Governor’s Award for Excellence in Energy Efficiency, State of Ohio • 2000 Facilities Management Excellence Award, Association for Facilities Engineers • 1999 Facility Management Achievement Award, International Facilities Management Association (IFMA) • 1997 Greenlights Partner, U.S. Environmental Protection Agency (EPA)
33
Additional Benefits
• Improved Reliability
• Voltage Sags reduced
• Reduced carbon footprint
• Less transmission and distribution losses
• Good Publicity
Additional Concerns
• Increased Fuel Volatility
• Increased Operational Complexity
• Additional regulatory issues
• PJM Interconnect may be needed
• Increased Staff may be needed
• Additional environmental permitting, monitoring, and reporting
Summary
• Great technology, but it is not for everyone
• Need a medium - large summer steam load and year round need for power
• Adds complexity to operations
• Capital and regulatory intensive
• Works great with low gas prices
Other Sources of Information
• http://www.midwestcleanenergy.org/
• DOE’s Federal Energy Management Program (FEMP) has issued a Notice of Intent (NOI) to provide grants for capital projects to Federal Agencies through a Funding Opportunity Announcement (FOA) entitled, "Assisting Federal Facilities with Energy Conservation Technologies (AFFECT)." CHP projects will be eligible for direct funding.