coe business case

70
MARMARA UNIVERSITY INSTITUTE FOR GRADUATE STUDIES IN PURE AND APPLIED SCIENCES CENTER of EXCELLENCE in INFORMATION TECHNOLOGY G. ERSEN CELEBI FINAL WORK Department of Engineering Management ISTANBUL, 2012 ADVISOR Prof. Dr. Neset Kadirgan

Upload: ersen-celebi

Post on 16-Apr-2017

3.992 views

Category:

Technology


0 download

TRANSCRIPT

Page 1: CoE Business Case

MARMARA UNIVERSITYINSTITUTE FOR GRADUATE

STUDIES IN PURE AND APPLIED SCIENCES

CENTER of EXCELLENCE in INFORMATION TECHNOLOGY

G. ERSEN CELEBI

FINAL WORKDepartment of Engineering Management

ISTANBUL, 2012

ADVISORProf. Dr. Neset Kadirgan

Page 2: CoE Business Case

G. Ersen CELEBI, a Master of Science/Engineering Management student of Marmara

University Institute for Graduate Studies in Pure and Applied Sciences, defended his

final work entitled “Business Case for a CoE\”, on 12 27, 2012 and has been found to

be satisfactory by the jury members.

Jury Members

Prof.Dr. Neset Kadirgan (Advisor)

Marmara University ...............(SIGN)..................

İSTANBUL, 2012

MARMARA UNIVERSITYINSTITUTE FOR GRADUATE

STUDIES IN PURE AND APPLIED SCIENCES

Page 3: CoE Business Case

APPROVAL Marmara University Institute for Graduate Studies in Pure and Applied Sciences

Executive Committee approves that G. Ersen CELEBI is granted the degree of Master

of Science/Engineering Management in Department of Engineering Management

Program on 12 27, 2012. (Resolution no:).

Director of the Institute

Prof. Dr.

Page 4: CoE Business Case

TABLE OF CONTENTS

ABSTRACT.................................................................................................................................................iiiABBREVIATIONS.....................................................................................................................................viiLIST OF FIGURES......................................................................................................................................ixLIST OF TABLES........................................................................................................................................xi1. INTRODUCTION..............................................................................................................................13

1.1. CoE Definition in the lecture............................................................................................................131.2. Key characteristics of a (CoE):.........................................................................................................151.3. Responsibilities:................................................................................................................................151.4. (CoE) Framework:............................................................................................................................161.5. Key Performance Areas for (CoE)....................................................................................................171.6. (CoE) Benefits..................................................................................................................................20

2. MOST COMMON CoE IMPLEMENTATIONS IN CURRENT IT INDUSTRY:..........................242.1. BPM CoE:........................................................................................................................................242.2. Business Intelligence........................................................................................................................282.3. PMO..................................................................................................................................................302.4. Test CoE...........................................................................................................................................322.5. Performance CoE..............................................................................................................................352.6. Integreation Competence Center (ICC)............................................................................................372.7. Banking CoE.....................................................................................................................................372.8. Finance CoE (FCoE).........................................................................................................................382.9. SOA..................................................................................................................................................412.10. ERP CoE.........................................................................................................................................422.11. Cloud Computing............................................................................................................................43

3. The Business Case:............................................................................................................................453.1. “Decision through the opportunities and business needs”................................................................453.2. WHY CoE is Needed........................................................................................................................49

4. COCLUSION.....................................................................................................................................50

Page 5: CoE Business Case

ABSTRACT

The Centers of Excellence (CoE), also known as Competency Center trend very recently has gained traction within the IT department of large organizations. Although the (CoE) concept itself is not quite new; however top companies in the sector are combining (CoE) together with some other recent concepts such as BI1 , BPM2, Cloud Computing, SOA3, mobile applications and services,..,etc accordingly to their marketing strategies.

Definitions are vary in the lecture for CoE and the expected benefits, which you can find some mixture of them as a part of this study as well but I found a lack of information in the area of defining the conditions and drivers for an organization to build a (CoE).

This study, aimed to shed a bit light for the questions raised above. Despite there are a lot of sectors and the domains which may implement (CoE); this study primarily will be focusing on IT area and IT organizations and their needs.

December, 2012 G.Ersen, CELEBI

Page 6: CoE Business Case

ABBREVIATIONS

(CoE) : Center of ExcellenceCC : Competence Center1-BI : Business Intelligence2-BPM : Business Process Management3-SOA : Service Oriented Architecture4-BPR : Business Process Re-Engineering5-TOC :Total Cost of Ownership 6-TOC :Theory of Constraints7-BICC : Business Intelligence Competency Center8-TCoE : Test Center of Excellence9- SDLC : Software Development Life Cycle10-PM :Project Management11-PMO :Project Management Office

Page 7: CoE Business Case

LIST OF FIGURES

.....................................................................................................................................PageFigure 1.1 ROI for (CoE)...............................................................................................................................2Figure 1.2: Sample Coe Framework..............................................................................................................4Figure 1.3: Sample CC Framework:..............................................................................................................5Figure 1.4 Race pit stop.................................................................................................................................8Figure 1.5 Forrester BPM Report................................................................................................................11Figure 2.1 Gartner Report :Top 10 Business priorities in 2012...................................................................12Figure 2.2 Flavors of BPM (CoE)...............................................................................................................14Figure 2.3 BICC and BI Operating Model..................................................................................................16Figure 2.3: Improving BI capabilities via BICC..........................................................................................17Figure 2.4: BI Maturity Levels....................................................................................................................17Figure 2.6: Key Interactions of CoE............................................................................................................18Figure 2.7 PPM CoE Corporate Relationships............................................................................................19Figure 2.8 CoE: Coordinating function responsible for managing the organisation’s portfolio.................20Figure 2.9: TCoE Elements.........................................................................................................................21Figure 2.10 TCoE extended capabilities......................................................................................................22Figure 2.11 TCoE model.............................................................................................................................23Figure 2.12 PCoE Model.............................................................................................................................24Figure 2.13 ICC Models and comparison:...................................................................................................25Figure 2.14 FCoe Model..............................................................................................................................29Figure 2.15 SOA CoE Model......................................................................................................................30Figure 2.16 Cloud Computing Models........................................................................................................31Figure 2.17 Business Cloud Technical capacity View................................................................................32

Page 8: CoE Business Case

LIST OF TABLES

PageTable 2.1: FCoE functions and Activities....................................................................................................40Table 3.2 Business Units and Domains.......................................................................................................45Table 3.3 Expenditure Formula...................................................................................................................46

Page 9: CoE Business Case

1. INTRODUCTION

1.1.CoE Definition in the lecture

A center of excellence refers to a team, a shared facility or an entity that provides leadership, evangelization, best practices, research, support and/or training for a focus area.

The focus area in this case might be a technology (e.g. Java), a business concept (e.g. BPM), a skill (e.g. negotiation) or a broad area of study (e.g. health). A center of excellence may also be aimed at revitalizing stalled initiatives. [Wikipedia]

A team of people that promote collaboration and using best practices around a specific focus area to drive business results. [27]

In today’s world, the Centre of Excellence (CoE) applies to any organization who wants to create and use excellent state of art and showcase its technological, service and business oriented capabilities to the entire world in a competitive environment. CoE is the combined effect of emerging business model and technologies. [53]

A Competency Centre or Centre of Excellence can be a highly effective way to implement and sustain specialist capabilities where a consistent, expert and cost effective service is required across organisational boundaries and where a comprehensive view is required to ensure synergies are identified and exploited. [1]

Business competency centers are strategically placed business intelligence and IT teams that work single mindedly to promote expertise, compliance and regulation throughout an organization [3].

A center of excellence is a premier organization providing an exceptional product or service in an assigned sphere of expertise and within a specific field of technology, business, or gov-ernment, consistent with the unique requirements and capabilities of the COE organization. [37]

Also known as a Center of Excellence (COE) or a Center of knowledge, a Competency Center endeavors to encourage and provide business intelligence (BI) skills, standards and best practices, which are not limited to a single project; its benefits permeate throughout a division or organization.

A (CoE) is essential for maximizing the effectiveness and quality of your business and for greater success and increased value, at less cost and in less time. The end

Page 10: CoE Business Case

result is of course an efficiently run business with improved technology management, tremendous value to IT, and successful end user adoption.

A (CoE) initiates all over development- of people, technology and the entire process. The idea is first to ensure success and later to sustain that success. Centre of Excellence (CoE) refers to creation of assets for an organization and reaping maximum business benefits from the usage of such assets. The objective of creating CoE for any organization is always customer centric and is meant for providing unique solutions to their customers. [53]

A center of excellence an organizational unit that embodies a set of capabilities that has been explicitly recognized by the firm as an important source of value creation, with the intention that these capabilities be leveraged by and/or disseminated to other parts of the firm.

Centers of excellence represent a focus for a superior set of capabilities within the firm, including tangible resources such as equipment, licenses, and patents, and intangible resources such as knowledge and experience capabilities that are able to create value for more than one line of business.

Figure 1.1 ROI for (CoE)

[4]

1.2.Key characteristics of a (CoE):

Page 11: CoE Business Case

Focus on a particular domain of expertise Takes an enterprise wide view, enables reuse by identifying commonality Provides a shared service across the enterprise Has an End-to-End lifecycle responsibility, e.g. from requirements definition

and architecture through to operational support Provides thought leadership, awareness of the market and how best practice can

be applied to the organisation Communicates its activities and disseminates knowledge Has authority for its domain of responsibility Delivers clearly defined capabilities, boundaries, roles and responsibilities Provides strong process, methods and governance Dedicated small core team of highly skilled resource

1.3.Responsibilities:

Support: For their area of focus, CoE’s should offer support  to the business lines. This may be through services needed, or providing subject matter experts.

Guidance: Standards, methodologies, tools and knowledge repositories are typical approaches to filling this need.

Shared Learning: Training and certifications, skill assessments, team building and formalized roles are all ways to encourage shared learning.

Measurements: CoEs should be able to demonstrate they are delivering the valued results that justified their creation through the use of output metrics.

Governance: Allocating limited resources (money, people, etc.) across all their possible use is an important function of CoEs. They should ensure organizations invest in the most valuable projects and create economies of scale for their service offering. In addition, coordination across other corporate interests is needed to enable the CoE to deliver value.

1.4. (CoE) Framework:

Page 12: CoE Business Case

A COE is an organization recognized as a world leader in accomplishing its mission. In this framework, that accomplishment is characterized via the following dimensions:

Figure 1.2: Sample Coe Framework

The framework and the approach to developing the appropriate criteria were derived from elements of both the balanced scorecard (BSC) [Kaplan 1998] and the Baldrige Criteria for Performance Excellence [Baldrige 2008].

Figure 1.3: Sample CC Framework:

Page 13: CoE Business Case

[1]

1.5.Key Performance Areas for (CoE)

1.5.1. Internal business process:

Has the operational work system, capacity, and capability to accomplish its assigned mission in an outstanding manner where

o its operational work system is aligned with organizational needs as determined by the organization and is repeatable, integrated, and applied consistently

o it has the capacity (environment) to accomplish mission or tasks (e.g., equipment, facili-ties, work, and support processes exist and are in use)

o it has the capability (leadership, both management and technical), knowledge and skills, and an education system for all employees exists and is in use

Consistently equals or exceeds established effectiveness and efficiency requirements in its measured operational performance in accomplishing the assigned mission.

Collects and uses measures to make management decisions in managing the internal business

Page 14: CoE Business Case

1.5.2. Customer Focus:

Provides measured, customer-focused performance5 addressing customer satisfaction

Elicits customer needs or requirements proactively and collaboratively

Responds in a timely manner to customer requests

Delivers customer-defined, high-quality products and services

Anticipates customer issues and problems compatible with the COE mission

1.5.3. Leadership:

Has proactive leadership to create and promote an environment for empowerment, innovation, organizational agility, and organizational and employee learning

Has senior leaders intrinsically involved with setting organization performance goals and expectations, setting and deploying organizational values, establishing short- and longer term direction focused on creating and balancing value for customers, their customers, and other stakeholders

Has senior leaders who communicate values, vision, directions, key decisions, and expectations through the leadership system to all employees

Has senior leaders regularly reviewing organizational performance for improvement purposes and needed actions

Has senior leaders focus on sustaining and growing the organization in terms of both the depth and breadth of its expertise

Has senior leaders who focus on finding and sharing new insights that relate to both the problem space and solution space relevant to the COE

Has senior leaders that embody the value of “learning is never over” through their visible, continual learning in both traditional and new areas of enquiry

Has senior leaders who can facilitate appropriate interactions with leading academic and practitioner organizations with the fields relevant to the COE organization

Page 15: CoE Business Case

1.5.4. Innovation and Learning:

Has the demonstrated and proven ability to incrementally innovate and improve

Has the demonstrated and proven ability to anticipate the direction of promising solutions to address the COE’s problems

Has the demonstrated and proven ability to introduce and gain traction for revolutionary as well as incremental innovations

Has the demonstrated and proven ability to develop the transition mechanisms needed to turn innovations into accepted technology improvements

Has the demonstrated and proven ability to create and leverage the value network needed to support introduction and deployment of innovations that are relevant to the COE’s customers and their customers

Has an environment that fosters both incremental and innovative learning

Develops, institutionalizes and applies leading-edge technology in the accomplishment of its COE mission

1.5.5. Financial:

Has a financial management system that supports advocating effectively for both incremental and revolutionary innovations, as appropriate for its domain

Has an established financial management system that accommodates the organization’s needs to accomplish and improve its mission performance

Has and implements a financial management system that is sufficiently flexible to accommo-date customer needs and changes in customer requirements

Has a financial management system that allows appropriate differentiation of non-recurring and recurring costs related to proposed innovations

1.6. (CoE) Benefits

Page 16: CoE Business Case

Figure 1.4 Race pit stop

The key question for many CIOs today is not whether the CoE approach would benefit the organization, but rather how best to make the transition to the CoE model from existing state.

Those who have followed disciplined approach towards setting –up and implementing CoE successfully have realized many business benefits. CoE offers the means to coordinate the effort by creating a common set of resources, models and tools to meet the broad set of business needs—while taking advantage of existing organization expertise, standards and infrastructure.

IT organizations of all types and dimensions are embracing the CoE model as a practical way of consistent and continuous ally improvement of their business operations. Industry analysts also support the move to the CoE model.

A CoE is an organization, focused on optimizing application or service characteristics such as quality, performance, or availability. It provides management an automation platform for processes, consulting, and support services, leadership as well as advocacy to optimize these attributes.

In IT world, CoE acts as a central point of contact to facilitate collaboration between the lines of business, enterprise architects, database administrators and application developers. It helps in speed adoption, improve knowledge sharing, lower the TOC5 And broaden the reach and context of enterprise application deployment, migrations, consolidations and upgrades.

CoE Brings together a dedicated team of appropriate domain expertise and enables the organizations to identify core patterns of integration, share best practices, leverage skills and standard tools across the enterprise.

A CoE provides a central source of standardized products & services with expertise, and best practices. It can also provide the entire organization with visibility into quality and

Page 17: CoE Business Case

performance parameters of the delivered application and support functions, helping them to keep everyone informed and keeping the applications and services aligned with business objectives.

The strategy and roadmap for CoE are required to launch and sustain the business needs. Without a COE, you will lack the necessary ecosystem and opportunity to optimize resources, funding, competencies, and governance structure, hence the ideology of the CoE should be in synchronization with the philosophy of the organization business imperative. [53]

Providing cost-efficient support:o Time and cost savings achieved through rationalisation and re-use of e.g.

patterns, business processes and services etc.

o Environments and supporting technologies (i.e. source control, web hosting systems, test environments), are shared and their use maximized leading to reduced costs and implementation time-lines.

Delivering resourceful performance.o Greater predictability achieved through consistent estimation, process

and management controls

o Faster learning curve and lower blended rate achieved through standard methods and approaches. Training is co-ordinated and shared across the CoE to ensure maximum take-up. Trainers become CoE specialists and can provide more specific knowledge of theuse and application of the technology and methods.

Eliminating IT holdups.o Operational efficiency and excellence achieved through the use of best

practice tools and approaches across the enterprise

Managing the technical infrastructureo Common data models are developed which makes future integration and

reuse of rule bases possible.

Maintain and enhance business processes, methodologies, andpractices.

o Reduced rework through consistent and coherent use of processes and methods and the implementation of appropriate quality standards and checks

o Ability to market internally in order to be able to increase use of the technology and grow rule development practice.

Page 18: CoE Business Case

Promote a single business standard across the enterprise.o Consistent and appropriate sourcing decisions and service provider

management ensuring optimal cost / risk evaluation and predictable delivery.

Promote familiarity with business knowledge across theenterprise.

o A flexible approach to project engagement and service delivery suitable for customers with varying levels of internal capability

Encourage development of advanced skill sets.o A staff career structure can be developed to promote staff and improve

retention.

Provide a single point of contact for business relationships.

Decreased time to market.o The rapid response capability of the CoE helps reduce total time for

development and servicing, resulting in faster time to market and on-time response to business needs — all at a lower total cost.

Culture of qualityo The transition from islands of expertise to standardized quality

processes and toolsets helps focus the organization on quality issues and speeds the evolution to a culture of quality.

High-performing companies make business process improvement a core competency. These leading firms share a common characteristic: they continually find clever ways to improve the process of process improvement.

As companies develop successful BPR4 projects, they’re giving greater thought as to how to capture, promote and disseminate the best process improvement ideas that are created throughout their organization

As a result, high-performing companies are implementing business process competency centers or business process centers of excellence (CoE). These committees set priorities, create a strategy map, standardize procedures and collect best practices for business process initiatives.

“A center of excellence provides visibility in the company about the idea of business process improvement, and helps the idea catch on in organizations that might otherwise be resistant to change.”

Page 19: CoE Business Case

According to some research almost half of the enterprises thatreported clear and measurable benefits from their BPM efforts had a BPMCenter of Excellence (COE) in place; only 10 percent of the group reporting mixed results had a BPM COE in place.

It is important to note that a COE does not compete with other industry-accepted practices such as Lean, TOC6, and Six Sigma, which target some of above activities. Rather it complements and leverages any existing expertise and process initiatives in an organization. [63]

Forrester study of BPM shows that having a center of excellence significantly enhances the ability of an organization to meet or exceed the goals that center supports.

Figure 1.5 Forrester BPM Report.

Source: Forrester October 2007 US and UK Enterprise Architecture and Business Process Management Online Survey

Page 20: CoE Business Case

2. MOST COMMON CoE IMPLEMENTATIONS IN

CURRENT IT INDUSTRY:

Since (CoE) concept can be applied to different line of businesses, in this chapter you can find some examples and a brief overview about them.

2.1.BPM CoE:

Figure 2.1 Gartner Report :Top 10 Business priorities in 2012

Particularly in light of today’s volatile economy, organizations are looking to trim the fat off their operations. In a receding market, process agility is an objective that organizations strive for. In order to leverage business opportunities with a short window of execution, an organization must be able to adapt its processes quickly and efficiently.“[BPM and Beyond: The Human Factor of Process Management, October 2008]

The most common types of actions IT executives have been recently taking to increase IT's business orientation and cut costs through the adoption of standard management processes, shared services, and coordinated IT governance.

To turn initiatives into sustainable programs that continuously improve and transform processes, business process professionals must establish centers of excellence (COEs) as quickly as the organization can support them.

Page 21: CoE Business Case

Advanced COEs in areas like ERP and BPM drive process innovation from the customer perspective, support business transformation led by senior executives, while also optimizing investments in process resources across the enterprise. When implemented as a shared service, or distributed across functional units and cross-functional processes, COEs connect business stakeholders with skilled process pros, service suppliers, and IT vendors through five essential capabilities:

1) clearly articulated portfolios of business process services; 2) formalized relationships with business stakeholders and suppliers; 3) effective working structures for delivering the portfolio; 4) efficient service management processes; 5) integrated quality assurance.

“Best practices and case studies show that while business process technologies, methods, and tools may differ from initiative to initiative, mature COEs employ similar organizational and management practices for greatest impact.” [57]

Regarding to experts, a center of excellence is ideal where there are multiple players contributing to each project. A BPM center of excellence often consists of IT and business people and serves as a formal hub to coordinate goals, priorities and governance for process implementations.  If centers of excellence are tied to BPM success, why aren’t more people implementing them?  One reason might be credibility. For organizations new to BPM, it’s a business culture change. Justifying the value of BPM isn’t always easy, especially without proof.

“That’s why it’s often easier to implement BPM successfully on a couple of projects first and then set up a center of excellence as phase two.” [66]

BPM COE (Center of Excellence) is essential to an enterprise BPM strategy.However, positioning of the COE within the organization is a key success factor. There are various flavors of BPM CoE that serve different purposes and most organizations would go through some of these before reaching the right positioning and right level of maturity. Thereare various flavors of BPM COE – sometimes in combination, sometimes in progression:

Page 22: CoE Business Case

Figure 2.2 Flavors of BPM (CoE)

2.1.1. Competency & Resource Management: Focuses on competency development and resource management, and formulating the knowledge frameworks, standards, methodologies and best practices. The primary focus being brainpower and not necessarily as a hub for all the hardware and software requirements too.

Page 23: CoE Business Case

2.1.2. Solutions Center Model: For organizations that have a little better laid out plan on the iniatives on BPM implementations, this model would provide a more efficient delivery and governance around initiatives. This, however, still resides more on Technology side due to the nature of the projects.

2.1.3. Factory Model : This offers a better chargeback and resource usage mechanism between the business needs and Technology capability. This also works better for a more well-defined BPM strategy where the definition of the projects are more tuned to the business process objectives and enterprise strategy. This moves governance closer to business and a better handshake is possible.

2.1.4. Business Process Centric Factory: This is driven by the process centricity, the KPIs and the process improvement objectives. The Process owners more involved throughout the initiatives and really help focus on business outcomes.

High-performing companies make business process improvement a core competency. These leading firms share a common characteristic: they continually find clever ways to improve the process of process improvement.

Ideally, though, a CoE doesn’t simply perform the role of process cop, but collects the best ideas throughout the enterprise, so the skills and experience of all employees can be leveraged.

“If you’re doing it right, a CoE is keeping a knowledge library and being proactive about presenting ideas for constant process improvement,” [26]

One study found that nearly half of companies that experienced a clear, measureable improvement from BPM have implemented a CoE. Of the companies that failed with BPM, a mere 4 percent have a CoE.

Various studies suggest that organizations with a Process Centerof Excellence can see benefits such as:

Increased usage of business process management practices Increased business user satisfaction Better understanding of the value of BPM Increased productivity Increased decision-making speed Decreased staff costs Decreased software maintenance costs Increased operational consistency Higher knowledge retention and faster transfer

Page 24: CoE Business Case

That is achieved by providing functions in and support for: BPM methodology Process engineering BPM tool usage Training and skill transfer Knowledge management Repository of reusable artifacts

In addition, a formal BPM strategy through a COE can help withreducing the overall cost of automating business processes.

2.2. Business Intelligence

BICC7 can be defined as a team of dedicated Business and IT specialists accountable for defining, owning and managing the execution of the company’s BI1 strategy and agenda. While many leaders, stakeholders, contributors, managers, analysts, developers and user communities participate in BI1efforts in one way or another, a BICC7 serves as the catalyst and glue that creates, promotes ,and holds together the overall BI1operating model.

Figure 2.3 BICC and BI Operating Model

[50]The BI1 program is not simply the sum of the various projects and independent efforts, but instead reflects a comprehensive network of people, processes, and technology working as one integrated operating model supporting and enabling those projects and efforts.

Figure 2.3: Improving BI capabilities via BICC

Page 25: CoE Business Case

[50]Figure 2.4: BI Maturity Levels

[50]

A company whose strategy takes a holistic approach to their BI1 program will have a better opportunity and capability to minimize risks and maximize value. A mature BICC7 set of capabilities (people, process, technologies) enables quick reaction to changing business needs, including:

Better enterprise-wide decisions Fewer information disagreements Less effort to develop and maintain information over time Lower long-term technology costs with better scalability

Figure 2.5: BI architecture

Page 26: CoE Business Case

[42]

2.3. PMO

A CoE can accommodate the possible mix of roles and activities related to assurance, improving programme, PM10 capability and capacity, as well as monitoring and controlling the departmental portfolio.

The role of CoE is to support the senior management of the organization in achieving successful delivery of the portfolio. The activities of CoE will involve interactions upwards to the management board, inwards to individual programmes and projects, and outwards to external bodies, other CoEs and delivery partners.

Figure 2.6: Key Interactions of CoE

Page 27: CoE Business Case

[6]

Figure 2.7 PPM CoE Corporate Relationships

[6]

Page 28: CoE Business Case

Figure 2.8 CoE: Coordinating function responsible for managing the organisation’s portfolio.

2.4.Test CoE

When the 2011-2012 World Quality Report survey participants were asked whether they have already implemented a Testing Center of Excellence, only four percent indicated that their companies have a fully operational TCoE8, and an additional six percent said that they have started the effort of establishing a TCoE8 within the past two years.

Figure 2.9: TCoE Elements

Page 29: CoE Business Case

[17]

[17]

Figure 2.10 TCoE extended capabilities

Page 30: CoE Business Case

[39]

2.4.1. Benefits of TCoE

The benefits of TCoE can be cathegorized as quality, time and cost; and can be achieved in timely manner.

2.4.1.1. Quality: Ad hoc test methods used by organizations are capable of identifying 70% of the defects in average. The TCoE model uses formal steps for test planning, execution and verification and skilled resources to raise removal rate significantly 95% for functional testing and 98% for regression testing.

2.4.1.2. Cost: Cost savings achieved from the reduction of overall defect density in the SDLC79. In Most large enterprises, the IT budget is approximately 4%-8% of the sales budget. Any savings on this is a direct add-on to the bottom line.

2.4.1.3. Time: TCoE Model helps reduce time to market by effective usage of automated testing tools and contunially improved operations. Newer services can be offered to customer in shorter period of time and with higher quality.

Page 31: CoE Business Case

Figure 2.11 TCoE model

[39]

2.5.Performance CoE

2.5.1. The business value of the Performance CoE model :

2.5.1.1. Lower costs, higher revenues: The efficiency of the Performance CoE model helps cut the cost of test lab infrastructure and operations while improving application performance, resulting in more satisfied end users and competitive advantages that drive revenue.

2.5.1.2. Higher profits: The Performance CoE model delivers better application software, more satisfied end users, faster deployment of high-performance software-driven services, and, ultimately, increased competitiveness and profitability.

2.5.1.3. Improved business productivity: Higher application performance typically yields higher end-user productivity. For example, the productivity of a clerk entering orders into an ERP system depends on the response efficiency of the system.

2.5.1.4. Decreased time to market: The rapid response capability of the Performance CoE helps reduce total project time, resulting in faster time-to-market of high performance applications and on-time response to business needs—all at a lower total cost.

Page 32: CoE Business Case

2.5.1.5. Greater flexibility: Organizations can implement a Performance CoE on a small scale, leveraging existing resources, and expand its capabilities as the value is proven.

2.5.1.6. Tighter alignment: By defining and measuring Key Performance Indicators (KPIs), the Performance CoE helps keep the application performance aligned tightly with business needs.

2.5.1.7. Career advancement: The Performance CoE model creates a compelling new career opportunity for IT professionals, leading to better HR, and helping the organization recruit and retain top talent.

2.5.2. Specific support services provided by a Performance CoE include:

Performance benchmarking Performance testing Capacity planning Infrastructure optimization Problem diagnostics

Examples of typical KPIs include: Number of customers Number of requests for service Total number of projects Number of references Revenues Gross margins

Figure 2.12 PCoE Model

[8]

Page 33: CoE Business Case

2.6.Integreation Competence Center (ICC)

2.6.1. Value system for the ICC (Integration Competence Center)

A value system is set of principles and hypotheses that enterprise strategically adopts in order to govern materialization of the enterprise system. Key points are:

Integration Technologies will change Multiple Integration Technologies will co-exist Objective of ICC is to deliver value and not “deploy technology” There is lot more to Enterprise Integration Management than just

Technology Integration Systems should be managed like an enterprise portfolio

Figure 2.13 ICC Models and comparison:

[7]Enterprises have option of adopting a strategy that takes best of both models.

2.7.Banking CoE

Many banks and financial institutes are currently undergoing changes regarding their IT Infrastructure and Business Applications landscape. Their challenges are among others to increase efficiency, reduce costs and add value to their clients by creating innovative products and services.

Banking Competence Center (BCC) addresses those challenges in a unique way with specialists embedded in the national and international enterprise networks.

Page 34: CoE Business Case

The specific knowledge about Banking Systems coupled with a large experience in the financial services industry makes (BCC) a strong and reliable partner to help clients manage, migrate or host their IT Infrastructure and Business Applications.

2.8.Finance CoE (FCoE)

2.8.1. The changing FPM landscape and a growing need for Finance Centers of ExcellenceTo understand why an FCOE makes sense for companies with a full-function FPM solution in place, or for any company looking to add to the FPM solution they have, it’s important to look at how the financial performance management landscape is changing. In the past, FPM was the purview of the CFO and finance organization — with very little executive or organizational involvement. Finance gathered up as many spreadsheets as possible and accessed static, historical data and created enterprise plans, budgets and forecasts — sometimes collaboratively with business.  They typically looked at actuals and decided on a percentage increase for earnings, revenue and products, or a percentage decrease for expenses. This has never been the ideal way to go about FPM.  We learned that expense reduction was not at the top of most CFOs’ agendas [“IBM 2010 Global CFO Study”].  Instead, CFOs ranked “providing inputs into enterprise strategy” as their most important priority. CFOs indicated that their role as strategic advisors is broader and more important than ever. More than 70 percent play a critical role in enterprise risk mitigation, business model innovation and selection of the key metrics linking performance to strategy execution. The pressure to help the business make all manner of decisions better, faster and with more certainty is intense.  As we have learned in the last few years, the global economy is unpredictable, prone to substantial and sudden highs and lows. To keep a competitive edge, companies must be prepared to make decisions in compressed time frames compared to the last half of the 20th century, responding quickly to changing business and marketplace demands.  As a result, a comprehensive FPM initiative— one that assures that a company’s success will not be a flash in the pan, but long-term — can now connect operations and finance for continuous enterprise planning.

2.8.2. What is an FCOE and what does it do?As organizations realize that FPM is more than a tool, they have begun investing resources to help manage performance more effectively and gain competitive advantage.  To approach FPM as a strategic asset, many organizations are combining IT staff and FPM users into coordinated teams.  These emerging organizational structures bring together people — with interrelated disciplines, domains of knowledge, and experience—with well defined processes, standards and technology. The goal is to achieve greater business efficiency on a foundation of trusted information, and deliver more effective decision-making across the enterprise.  These teams

Page 35: CoE Business Case

form the foundation of an FCOE because, to paraphrase the multiple definitions available, a center of excellence is a group of people who collaborate to promote best practices in a specific focus area and drive successful business outcomes.

2.8.3. What benefits come with a Finance Center of Excellence?

To ensure that you can support your organization’s long-term performance agenda, you need a managed, repeatable approach. An FCOE can help your organization define the knowledge, standards and resources that can wring more value out of your FPM solutions and technology. An FCOE is essential to the strategic deployment of FPM technology because it:

Maximizes the efficiency, use and quality of FPM everywhere in your business

Drives end-user adoption by streamlining integration with routine planning and analysis workflow

Encourages alignment between IT, finance and business areas Increases your enterprise’s understanding of performance

in finance terms (the “Financial IQ”) Reduces organizational overhead associated with

maintaining budget, plan and forecast consistency and use Increases the success of FPM solution and technology deployments

by helping them deliver more value, at less cost and in less time Helps you base your strategies on business priorities for maximum

ROI and added value Improves business agility and technology management, which in

turn drives business efficiency. The finance center of excellence consists of a team of four people

who support the enterprise planning, budgeting and forecasting functions in a variety of ways:

Bottom-up budgeting and forecasting templates — standard and customized

Support for identifying business drivers and key metrics, particularly with a new business or line of service

Development of the majority of the planning applications Review of models built for solutions that planning application, even

at the metadata level to ensure consistency Planning and forecasting education: Twice annually, an update on the planning system — what it does,

how to work through a monthly forecast and/or budget Assistance with standard and ad hoc reporting across the year for

business and for management

Page 36: CoE Business Case

Table 2.1: FCoE functions and Activities

[23]

Figure 2.14 FCoE Model

Page 37: CoE Business Case

[23]

2.9.SOA

SOA is a way to design software for distributed computing environments that involves the use of independent services, or activities that provide a certain business function, to support the needs of a business. Not only are these services used to exchange information and support business processes, but they can also be reused by other applications.

Given that SOA implementations can have a huge impact on IT and the organization as a whole, experts advise setting up some sort of governance and best practices effort to help ensure a successful migration. For many, part of that effort will include creating a COE to gather information about SOA implementations and to leverage best practices within the organization.

The center of excellence can act as the governance body for an SOA implementation, overseeing what goes into a new architecture that the organization is creating and ensuring that the architecture will meet the current and future needs of the organization,

"It's a shift from being project oriented to building out an architecture with long-term assets that are going to be used in future projects," he says. "That requires a central group." [22]

Figure 2.15 SOA CoE Model

Page 38: CoE Business Case

2.10.ERP CoE

ERP is a long term commitment. Without a center of excellence approach, employees take undocumented knowledge with them when they leave. Dependence on consultants leads to cost overruns.

An ERP COE will de facto have to establish goals, measure performance, and demonstrate the value to the organization.

To be successful, the goals of the ERP COE must be aligned with the goals of the business. Therefore, IT must understand what they are. This is different from the sundry, ad hoc, and ad infinitum requests of LOB managers. IT management must seek to understand not only the company's short- and long-term goals, but also its strategies, culture, politics, policies, and values.

An ERP COE can be mutually beneficial to both IT and its brethren LOBs. If the ERP COE can help to solve problems, be prepared when issues arise, and contribute to the growth and/or betterment of the organization, it will become a valuable tool and IT may come to be held in higher esteem.

Page 39: CoE Business Case

2.11.Cloud Computing

Enterprises require a host of custom applications to manage day-to-day business processes. Historically, this means supporting three IT layers: (1) the Applications themselves; (2) the Platform needed to develop them; and (3) the underlying infrastructure; each with its own support and maintenance costs. More and more organizations these days are looking to shift this IT paradigm by building business applications quickly, using off-the-shelf capabilities without worrying about application upgrades or infrastructure scaling. The advent of ‘Cloud Computing’ has provided businesses with such a lightweight alternative.

Almost all well known global IT and Consultancy firms have already built their (CoE) in different areas on the world which specified in Cloud Computing technologies.

Figure 2.16 Cloud Computing Models

[69]

Figure 2.17 Business Cloud Technical capacity View

Page 40: CoE Business Case

[74]

It is possible to extend the list of the implementation areas above (e.g. Software Development, Enterprise Architecture) though, however it is not needed in this context; please see the recommended readings section for further details.

Page 41: CoE Business Case

3. The Business Case:

3.1.“Decision through the opportunities and business needs”

This is the core part of this study to clarify, why an organization decides to build an (CoE) while there are vary of concepts to improve the efficiency, productivity and quality also reduce the cost such as Lean, Six Sigma,…,etc.

For instance most of the symptoms identified by BPM and BPR as mentioned earlier would lead an organization to consider whether a (CoE) is needed or not.

It is very common that corporate organizations continuously review and restructure their processes in order to optimize the ultimate benefits. Although such initiatives add value in holistic approach and could be considered as a success from process engineering perspective; however by the time either by nature of the business itself or based on the changing market needs these processes may cause some disadvantages for specific business domains and it may not be efficient to redesign all the processes for the sake of one business domain or unit. Actually this the reason why (CoE)s by definition response to needs of a specific Business Domain/Unit.

To be more specific I will be referring to tables below to explain how some business domains could feel the impact more than the other ones.

Table 3.1 Processes

Process Time CostProject Man. X C1Software Development

Y C2

Change Man. Z C3Security Man.

Q C4

Hosting (Inf. Man)

W C5

Support T C6Test Man. S C7Performance Man.

R C8

Table 3.2 Business Units and Domains

Business Unit #Domain # Hosting Services

Expected #Projects 2011

Expected #Projects 2012

A 20 400 50 250B 30 500 120 40C 40 1000 100 60D 30 600 90 70

Page 42: CoE Business Case

Sum 120 2500 410 420

For instance IT department that providing hosting, consultancy software development, project management, security, change management, performance, test and support services of a corporate, which have different business units and domains. As you can see the figures above in the Table 3.1 and Table 3.2 IT department could achieve a huge financial success by making major cuts for C5 and W in 2010-2011 due to high number of the hosted services for all the business units even with minor reduction for the rest of the processes.

When Business unit A completes the financial analyses for 2012 may find out that it won’t be financially effective to work with internal IT department for the new projects. The reason is not very complicated and self explanatory once the programme budget formalized as in the following table for 2011 and 2012.

Table 3.3 Expenditure Formula

Expenses of Business Unit A Year[400 * {(W *C4)+ (Q*C5) + (T*C6)} ]+ [50 * {(X*C1) +(Y*C2) +(Z*C3)+(S*C7)+(R*C8)}]

2011

[400 * {(W *C4)+ (Q*C5) +(T*C6)} ]+ [250 * {(X*C1) +(Y*C2) +(Z*C3)+(S*C7)+(R*C8)}]

2012

As described in the Table 3.3 and Table 3.2 the total number of the projects has not been increased significantly for 2012 but there has been a significant increase in terms of number of the project for business unit A.

Because the previous improvements on the IT processes haven’t been as successful as the Infrastructure Man., Security Man. and Support for the other processes (it may not be targeted at all) now IT department might be losing certain amount of business. Probably business can sign a contract with an external company to deploy all the projects for 2012.(Business may still want to keep hosting the services internally)

This is the reason why (CoE) also called as Competency Center. Now might be the right time to consider build an internal (CoE); in order to response to the business needs with a skilled group of people and deploy all the projects in a way that business unit A would find effective, meantime IT organization gain some benefits on top of keeping the all IT business functions and resources utilized as well. Main decision point here should be; whether the (CoE) meets with the corporate strategy or not.

One of the reasons for business to choice internal (CoE) instead of a 3rd party is basically ultimate benefits, which would be reached possibly by the extension of the similar needs to other Business Units and Domains.

This approach can also be considered as creating a SME in the organization since most of the time for such a case competitors are (focused on a specific business domain) small or medium size enterprises. The advantage of SMEs is capability of acting and

Page 43: CoE Business Case

delivering fast solutions for the customers without loosing too much effort and time due to internal processes. Another advantage of an SME is holding necessary skills for the business.Very similar to case above enterprises also can build (CoE)s for the external customers in order to deploy a specific product suit and/or technology such as BI, CRM, ERP, Cloud Computing,…,etc.

Before explaining any other benefits of (CoE) for the Business Unit A in the same scenario above, we can focus on another case, out of business environment to emphasize the benefits in a simple form.

One of the most common project management case for all human beings is planning a holiday. You can see the parallelism between following scenario and the one above.

Consider that you are planning a 2-3 weeks long holiday in a trans-Atlantic or trans- Pacific country(s) that you haven’t been before. What are the challenges that you need to consider while you are planning your trip?

1. If you need a visa for the country(s) a. How to applyb. How long does it take to receive the visac. How much does it costs

2. Flight tickets:a. How much does it cost?

i. Which airlines are flyingii. Different dates different prices

iii. Any special discount that you can have.b. Direct and transit flightsc. Comfort

3. Accommodation a. Hotel, pension,…,etcb. Standards & Pricec. Compliance to destinations in scope

4. Places to visita. You may lost in the number of the places that you can visitb. How to find the most common advises

5. What to do6. What to eat

a. Different tastes and (un)expected resultsb. Quality of the foodsc. Prices

7. Health and insurancea. What to do in case of emergencyb. What kind of insurance and preventative actions you may need.c. What are the common issues and solutions.

8. Entertainmenta. What to do?b. When.

Page 44: CoE Business Case

9. Securitya. List of the not to do(s).b. Warnings.

10. If you are planning the trip for a group of people you need to optimize all the possible combinations to fit for everyone’s taste.

Of course we can extend the list with much more details but it is not needed at the moment. If you go trough financial approach to find cheapest flights and accommodations you can reduce the costs but you may not cover all the fun or you may spent more time on the way, you may first find out (due to visa obligations) when you can fly earliest,..,etc. Missing any important detail can cause a fail that your holiday turns out a disaster.

To plan such a trip successfully may take too much time and also too much risk. What about a travel agency which offers an end-to end service including visa application, flight tickets, hotel bookings, guided tours and one price for all?

First of all you can get a better overview on the whole trip and you can try to plan very similar trip yourself (or via another agency as well) and compare the price, quality and time to decide.

This is exactly what expected from a (CoE) as well. A (CoE) should be guiding to customer as a single point of contact, providing end-2-end overview on the requested service and within competitive price, quality, time range. With different words centralization is one of the benefits of (CoE) for the corporate.

Usually when you compare the prices, the one offered by agency should be much better than you can get yourself. The reason behind it is the same with the example we had as IT department; “Business Case”. The agency should have been identified the destination for expected number of clients and booked flight tickets, hotel rooms accordingly months ago with much lower prices than you can get. Again referring to previous chapters probably one of the most important factors which implies your decision to choose your agency for the trip would be their experience on this destination (in case of equal budgets offered more than one agency) which is actually in parallel with the maturity level for the (CoE).

Page 45: CoE Business Case

3.2.WHY CoE is Needed

Creating a CoE is a proven, yet flexible approach to obtain the strategic benefits of business in all its forms, while maintaining control on costs, quality and operation. CoE can bring tremendous benefits to an organization, by creating the necessary state of art to provide service and product excellence to their valued customers and users. CoE is used to provide the best technical solutions to the challenging, complex, and evolving business needs of customers.

There are various reasons for organizations to create CoE and the most common are as follows:

To keep pace with technologies and their impact on how business is conducted, Organizations create dedicated Centers of Excellence (CoE) in various technologies.

Creating a CoE addresses the need of organizations to maximize the usage of hardware, software and highly skilled personnel to provide solutions to the customers, partners or end users.

A CoE enables to centralize technology as well as create a repository of solutions, and reusable components, sharing best practices and knowledge base. Reuse of technology in some cases can be leveraged across different segments of business.

It provides timely information, measures, KPI’s to the users and senior management throughout the organization enabling them to take appropriate and timely decisions in competitive advantage.

If CoE is created for providing services and products then enterprises can rapidly realize the benefits of a CoE by leveraging service and product expertise with the help of consistent methodology and industry knowledge.

CoE for some organizations is meant for Implementing the most optimal technologies, architectures, and frameworks to provide best-of-breed solutions and services to the customers and Clients.

Some organizations use CoE to enable implementation of all needed regulatory requirements.

A CoE enables collaboration across business units to ensure consistency and integration of value stream, business data and governance models.

CoE can provide a governance framework that enables open participationfrom every business unit, business partner, IT and other keystakeholders.

It provides a clear mapping between business models and IT modelingparadigms that can be used to clearly communicate businessrequirements to IT.

Page 46: CoE Business Case

Create a focal point where business strategy can be translatedinto operational reality.

4. COCLUSION

Current industrial environment is pushing all the organizations to review their processes for improvement either in order to gain competitive advantage or just to survive.

As explained CoE is one of the most powerfull tool or concept that helps to any organization to achieve some specific benefits and improvements.

One of the most valued component for all the organizations in today’s world, is time. One of the purpose of this study is also helping the readers to find out if the CoE is not the right choice for them to avoid wasting their time with try and fail approach.

Basically what you may have achieved by reading this study is: “if the CoE is the right concept for your organization to adopt”

I believe that you could find what benefits to expect and what is the purpose of building a CoE.

In short the decision is depending on the expectations and the circumstances of the organization and the business.

Decision makers should consider all the parameters, benefits and needs before taking the final decision. It is not quite possible to establish a framework or desicion support system based on a couple of standard questions or parameters to answer this question . In contrary minor details can be quite significant for any organisation when they are evaluating the necessity of a CoE.

Page 47: CoE Business Case

5. REFERENCES

Ref

No

Reference Author Type URL

1

COMPETENCY CENTRES & CENTRES OFEXCELLENCE Glue Reply Article

2Setting up your owncompetency center A1 technology Article

3

CENTERS OF EXCELLENCE IN MULTINATIONALCORPORATIONS

Strategic Management JournalStrat. Mgmt. J., 23: 997–1018 (2002) Article

4

Using Action Research for Gaining CompetitiveAdvantage out of the Internet’s Impact on ExistingBusiness Models

Christoph Auer, Manuela Follack Article

5The Centre Of Excellence Pocketbook Article

6 Integration Competency centersRakesh Kumar Mishra Article

7

Building and managing a PerformanceCenter of Excellence HP

White Paper

8 Process center of ExcellencePejman Makhfi & David Patton, Article

9Building a BusinessIntelligence Competency Center Cognos

White Paper

10How a Center of ExcellenceCan Boost Automation Benefits BMC software

White Paper

11

The Business Intelligence Competency Center: Enabling Continuous Improvement in Performance Management Oracle

White Paper

12Accelerating efficiency with best practices EMC^2 Article

13 Swarming UAS II

MAJ Matthew Dabkowski, MS,USMA, Mr. James CookDonnelly & Moore Corporation, LTC Robert Kewley, PhD Article

14 Customer Competence Center SAPWhite Paper

15 A Framework for a BPM Center of Excellence

Leandro Jesus, Andre Macieira,

Article

Page 48: CoE Business Case

Daniel Karrer, Michael Rosemann

16The Power of Centralization and Standardization Capgemini, HP

White Paper

17Control Costs and Improve Customer Satisfaction CSC Article

http://www.csc.com/workplace_services/offerings/87346/87598-csc_embrace_contact_center_solutions

188 characteristics of successful SOA implementations

Mike Kavis, ITWorld Article

http://www.itworld.com/soa/55696/8-characteristics-successful-soa-implementations

19Wyeth's prescription for BPM success

David F. Carr, ITWorld Article

http://www.itworld.com/business-process-management/53148/wyeths-prescription-bpm-success

20Process makes PRACTICE better

Michael Hammer, ITWorld Article

http://www.itworld.com/CIO030100_reply_content

21 Build SOA Center Of Excellenc Bob Violino Article

http://www.ciozone.com/index.php/SOA/Build-SOA-Center-Of-Excellence-Say-Experts.html

22

Building a Finance Center of Excellence: Sharing knowledge and best practices in financial performance management IBM Article

http://ibm-business-analytics.com/2012/06/04/building-a-finance-center-of-excellence-sharing-knowledge-and-best-practices-in-financial-performance-management/

23 BPM Center of Excellence bpminstitute.org Article

http://www.bpminstitute.org/resources/articles/BPM-center-excellence

24 The Business Architecture Center of Excellence

Article http://www.bpminstitute.org/resources/

Page 49: CoE Business Case

articles/business-architecture-center-excellence

25Building a Business Process Center of Excellence

Joe Mullich, The Wall Street Journal Article

http://online.wsj.com/ad/article/enterprisetech-building

26 why-create-centers-of-excellenceagileelements.wordpress Article

http://agileelements.wordpress.com/2008/10/27/why-create-centers-of-excellence/

27

Information Technology Strategic PlanFY 2010 – 2015 fbi Article

http://www.fbi.gov/about-us/itb/it-strategic-plan-2010-2015

28 Sharing Agile Best Practices Michael Kutch Article

http://prezi.com/h-rqlkmooqcn/sharing-agile-best-practices/

29Recession-proof your Company with SOA Bradley D. Brown Article

30 IBM Banking Competence Center IBM Article

31

ERP System Implementation andBusiness Process Change: Case Study of aPharmaceutical Company

Vesna Bosilj-Vuksic and Mario Spremic Thesis

32Master thesis in Software Engineering and Management

ANDREY YEMELYANOV Thesis

33

The ContinuousInnovation Advantageof Software-As-A-Service Jason Corsello Article

34

Simplified approach to effort estimation in software maintenance

Thesis, Petr Marounek 2012 Thesis

35

An Analysis of the Benefits and Savings of the Center of Excellencewithin the Fleet Readiness Centers

Thesis, Philip Deboe,John GoolsbyDecember 2007 Thesis

36

Generalized Criteria and EvaluationMethod for Center of Dr. William Craig Article

37 SOA CoE Oracle Article38 Test CoE Infosys Article

39Steps For Implementing a SAP Center of Excellence Bob White Article

http://it.toolbox.com/blogs/sap-support/steps-for-implementing-a-sap-center-of-excellence-10988

40 Forrester report Q2 2012 Forrester Report

Page 50: CoE Business Case

41

Establishing a Business Intelligence Competency Center (BICC)

Hitachi Consulting Article

42

Getting a Business Intelligence Competency Center Off the Ground itbusinessedge Article

http://www.itbusinessedge.com/cm/community/features/interviews/blog/getting-a-business-intelligence-competency-center-off-the-ground/?cs=41019

43

Gartner's Business Intelligence and PerformanceManagement Framework

Bill Hostmann, Nigel Rayner, Ted Friedman Article

44

Business Intelligence Maturity Models: AnOverview

Gerrit Lahrmann1, Frederik Marx1, Robert Winter1, Felix Wortmann1 Article

45

OVERVIEW OF BUSINESS INTELLIGENCE MATURITY MODELS

Irena Hribar Rajteriè Article

46SOA and BPM Are Better Together Gartner Article

47

Implementing a Successful Business Intelligence Competency Center Markus Sprenger Article

http://www.b-eye-network.com/view/7297

48 Best Practices TDWI Article

49

BI Competency CentersPeople + Information = Intelligence Timo Elliott Article

50The Cornerstones of Business Intelligence Excellence

T. Friedman, B. Hostmann Article

51Why BI CoE: Struggling to justify ROI? Murali Moturi Article

http://www.saama.com/blog/bid/79371/Why-BI-CoE-Struggling-to-justify-ROI

52Create Centre of Excellence (CoE) for Better Business

Sunil V Tadwalkar Article

53 Building a CoE HPWhite Paper

54 CENTERS OF EXCELLENCENicolas Vendramin

Case study

http://www.tesionline.com/intl/preview.jsp?pag=1&idt=10757

5556 How bpm coes increase business

technology maturity your organization

forrester Alexander Peters, Ph.D.

Article http://blogs.forrester.com/alexander_peters_phd/10-05-02-

Page 51: CoE Business Case

how_bpm_coes_increase_business_technology_maturity_your_organization_0

57Which flavor of coe is right for your enterprise bpm strategy?

ashishbhagwat.com Article

http://ashishbhagwat.com/2010/02/25/which-flavor-of-coe-is-right-for-your-enterprise-bpm-strategy/

58The Service Portfolio of a BPM Center of Excellence

Michael Roseman Article

59 BPM COE Sandy Kemsley Article

60Creating a BPM Centerof Excellence (COE)

Lisa Dyer, Andrew Forget, Fahad Osmani e-book

61

Process Governance Best Practices: Building a BPM Center of Excellence Clay Richardson Article

62

A Step -by-Step Guideto Estab lis hinga BPM Center ofExcellence

Progress Savvion ® ™

White Paper

63

BPM Voices: The case for a Center of Excellence approach to BPM adoption IBM Article

http://www.ibm.com/developerworks/websphere/bpmjournal/1109_col_fasbinder/1109_fasbinder.html

64 Definition Wikipedia

http://en.wikipedia.org/wiki/Business_process_management

65Is a center of excellence necessary for BPM success? Karen Guglielmo Article

http://itknowledgeexchange.techtarget.com/total-cio/is-a-center-of-excellence-necessary-for-bpm-success/

66

A Computer Scientist’sIntroductory Guide toBusiness Process Management (BPM) Ryan K. l. Ko Article

67 BPM Standards & GuidelinesRaymond Braakhekke Article

68 Business Process ManagementKrystl Campos, Paige Leavitt Report

69 Cloud Computing InfosysWhite Paper

Page 52: CoE Business Case

.

Page 53: CoE Business Case

6. About the Author

Adı Soyadı : Goksal Ersen Celebi

Doğum Yeri ve Tarihi : Istanbul, Turkey. 1977

Yabancı Dili : English, Czech

E-Posta : [email protected]

Öğrenim Durumu (Yüksek Lisans öğrencileri son satırı silmelidir.)

Derece Bölüm/Program Üniversite/Lise Mezuniyet Yılı

Lise Fenerbahce Lisesi 1994

Üniversite Computer Science

Engineering

Istanbul University 1998

İş Deneyimi (Eklenecek bir bilgi yoksa silinmelidir.)

Yıl Firma/Kurum Görevi

2006- DHL ITS Production Services

2003-2006 Bizitek Technical project Manager

7. RECOMMENDED READINGS