cnca ccan slump of concrete · 2018-09-18 · 1. if two consecutive slump tests demonstrate falling...

2
TECHNICAL SPECIFICATIONS A23.2-5C The slump of concrete is a measure of consistency and it provides an indicaon of workability. The slump shall be consistent with the placement and consolidaon methods, equipment, and site condions and shall be idenfied by the Contractor and concrete supplier prior to construcon. The higher the slump, the higher the workability and ulmately the easier the placement. A small variaon in slump caused by improper procedure or equipment, may cause the rejecon of an enre load of concrete and observing good pracce is the key to ensure that the concrete properes are properly evaluated. Apparatus 1. A test specimen mould with a cone shape which includes foot pieces and handles made of metal not thinner than 1.5 mm with the following dimension: base 200 mm in diameter, the top 100 mm in diameter, and a height 300 mm. 2. A round straight steel tamping rod shall be 16 mm ± 1 mm in diameter and between 450 mm and 600 mm in length, having at least one end rounded to a hemispherical p. 3. If a rigid, flat, and non-absorbent surface is not available, base plates made of plywood, plasc or steel may be used. 4. A measuring tape or measure at least 300 mm in length and having 1 mm graduaons. Procedure for tesng 1. Time constraint – Complete the test for slump within 10 minutes aſter obtaining the sample, including transporng and remixing. The enre slump test, from filling to the removal of the mould, must be completed without interrupon within 2 minutes. 2. Sampling – Obtain a representave grab sample from between the 10% and 90% points of discharge as per CSA A23.2-1C. 3. Preparaon – Aſter moistening the slump cone, place it on a moist, smooth, non- absorbent, level and stable surface which is large enough to accommodate the two foot pieces. 4. First Layer – Standing on the foot pieces throughout the test, fill the cone one third by volume (~70 mm depth) and rod 25 mes, uniformly distribung the strokes across the layer. 5. Second Layer – Fill the cone to two-thirds of its volume (~160 mm depth) and rod 25 mes, penetrang the first layer approx- imately 25mm. 6. Third Layer – Fill the cone to overflowing and rod 25 mes as above with the rod just penetrang the second layer approximately 25 mm. Add addional concrete to keep an excess in the mould at all mes. Slump of Concrete

Upload: others

Post on 24-Apr-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CNCA CCAN Slump of Concrete · 2018-09-18 · 1. If two consecutive slump tests demonstrate falling away or shearing of the concrete when the cone is lifted, the concrete may lack

T E C H N I C A L S P E C I F I C A T I O N S

A23.2-5C

The slump of concrete is a measure of consistency and it provides an indication of workability. The slump shall be consistent with the placement and consolidation methods, equipment, and site conditions and shall be identified by the Contractor and concrete supplier prior to construction. The higher the slump, the higher the workability and ultimately the easier the placement. A small variation in slump caused by improper procedure or equipment, may cause the rejection of an entire load of concrete and observing good practice is the key to ensure that the concrete properties are properly evaluated.

Apparatus1. A test specimen mould with a cone shape

which includes foot pieces and handles made of metal not thinner than 1.5 mm with the following dimension: base 200 mm in diameter, the top 100 mm in diameter, and a height 300 mm.

2. A round straight steel tamping rod shall be 16 mm ± 1 mm in diameter and between 450 mm and 600 mm in length, having at least one end rounded to a hemispherical tip.

3. If a rigid, flat, and non-absorbent surface is not available, base plates made of plywood, plastic or steel may be used.

4. A measuring tape or measure at least 300 mm in length and having 1 mm graduations.

Procedure for testing1. Time constraint – Complete the test for

slump within 10 minutes after obtaining the sample, including transporting and remixing. The entire slump test, from filling to the removal of the mould, must be completed without interruption within 2 minutes.

2. Sampling – Obtain a representative grab sample from between the 10% and 90% points of discharge as per CSA A23.2-1C.

3. Preparation – After moistening the slump cone, place it on a moist, smooth, non-absorbent, level and stable surface which is large enough to accommodate the two foot pieces.

4. First Layer – Standing on the foot pieces throughout the test, fill the cone one third by volume (~70 mm depth) and rod 25 times, uniformly distributing the strokes across the layer.

5. Second Layer – Fill the cone to two-thirds of its volume (~160 mm depth) and rod 25 times, penetrating the first layer approx-imately 25mm.

6. Third Layer – Fill the cone to overflowing and rod 25 times as above with the rod just penetrating the second layer approximately 25 mm. Add additional concrete to keep an excess in the mould at all times.

Slump of Concrete

Page 2: CNCA CCAN Slump of Concrete · 2018-09-18 · 1. If two consecutive slump tests demonstrate falling away or shearing of the concrete when the cone is lifted, the concrete may lack

This publication is intendedfor general informationpurposes only. The ReadyMixed Concrete Associationof Ontario disclaims any andall responsibility and liabilityfor the accuracy and theapplication of theinformation contained in thispublication to the full extentpermitted by law.

No part of this publicationmay be reproduced in anyform, including photocopyingor other electronicmeans, without permissionin writing from ReadyMixed ConcreteAssociation of Ontario.

Technical information prepared by:Ready Mixed ConcreteAssociation of Ontario102B – 1 Prologis BoulevardMississauga, ON L5W 0G2

T: 905.564.2726F: 905.564.5680

[email protected]

©2018 RMCAOAll rights reserved. 07/18

7. Strike-off – Strike off the excess concrete with the rod using a screeding rolling motion. Remove all spilled concrete from around the base of the mould.

8. Cone Removal – Carefully step off the foot pieces while maintaining downward pressure on the handles and lift the cone vertically with a slow even motion, taking approximately 5 seconds to remove the cone. Lateral or torsional movement must be avoided.

9. Measurement – Place the rod across the top of the inverted slump cone and measure the height difference from the bottom of the rod to average top of the slumped concrete to the nearest 5 mm.

Notes:1. If two consecutive slump tests demonstrate

falling away or shearing of the concrete when the cone is lifted, the concrete may lack the necessary plasticity and cohesiveness for the slump test to be applicable.

2. Duplicate slump test results on two portions of the same sample should not vary by more than 10 mm.

3. Concrete from slump tests can be reused after proper mixing.

References:1. OPSS.MUNI 1350 (Nov. ‘17) - Material Specification for Concrete – Materials and Production2. CSA A23.2-14-5C – Slump of Concrete, Test Methods and Standard Practices for Concrete, Canadian Standards

Association (CSA Group)