Preparations for 925 Million Tonne Production from CIL in 2019-20

www.cmpdi.co.in

No drilling is required for the Blocks/Mines identified for 925 Mt production in 2019-20.

18 Project Reports (PRs) are to be prepared (production 57 Mt in 2019-20). Based on PR approval schedules of CIL, the PR submission schedule will

be as follows: 10 PRs will be submitted by March 2015.

7 PRs will be submitted in 2015-16.

1 PR will be submitted in 2016-17.

27 Updated Cost Estimates for PRs will be submitted well before their PR approval schedule.

6 Schemes for Patch OCPs (for ECL) will be submitted well before their approval schedule.

Preparations for 925 Mt Production in 2019-20

www.cmpdi.co.in

GRs Required for 925 Mt production in 2019-20

Sl No

Comp-any

Block Prodn in 2019-20 (Mt)

Remarks Alternative for Prodn

1 NCL Patpahari UG/OC

1.00 GR for non-forest part available. Drilling delayed due to forest clearance. 10-15 km rail link with Katni-Chopan main line needed. Power supply network needed. PR approval required by Nov-17. 2.5 Mt production

can be obtained from expansion of operating mines like Jayant Expn, Dudhichua Expn, etc.

2 NCL Marki-Barka (W)

UG

0.50 GR for non-forest part available. Drilling delayed due to forest clearance. 30 km rail link with Katni-Chopan main line needed. Power supply network needed. PR approval required by Nov-17.

3 NCL Marki-Barka (E) UG/OC

1.00 Drilling delayed due to forest clearance. 30 km rail link with Katni-Chopan main line needed. Power supply network needed. GR expected by Mar-17. PR approval required by Nov-17.

4 ECL Dhangajore UG

0.30 Drilling delayed due to forest clearance. Forest cover-75%. Number of villages to be rehabilitated. CBM overlap. GR expected by 18-19.

0.4 Mt production can be obtained from Hura C, Chuperbhita, etc.

5 ECL Madhu-kunda UG

0.10 Drilling delayed due to forest clearance. GR expected by 18-19.

www.cmpdi.co.in

Project Reports (PRs) to be Prepared for 925 MT Projection of CIL in 2019-20

Sl No

Comp-any

Project Report OC/ UG

Incremental Capacity

(Mty)

Contribution in 2019-20

(Mt)

Schedule of PR Submission

PR Approval Schedule

1 ECL Chaudhar-Gariapani-Kayada (119 blocks)

OC 3.00 0.50 Sep-15 Dec-15

2 ECL North Searsole Recast OC 2.00 0.80 Sep-15 Dec-15

3 ECL Nakrakonda Kumardih-B OC 0.70 0.70 Mar-15 Jun-15

4 ECL Madanpur Recast (119 blocks) UG 1.59 0.50 Sep-15 Dec-16

    Sub-total ECL   7.29 2.50  

Note: For CCL, the PR for Chatti-Bariatu-Kerendari is to be prepared before Jan 2016 only after these captive blocks are allotted to CCL.

www.cmpdi.co.in

PRs to be Prepared for 925 MT Projection of CIL in 2019-20

Sl No Comp-any

Project Report OC/ UG

Incremental Capacity

(Mty)

Contribution in 2019-20

(Mt)

Schedule of PR Submission

PR Approval Schedule

1 WCL Kumbharkhani UG to OC Recast OC 1.00 0.20 Mar-16 Mar-17    Sub-total WCL   1.00 0.20  

Note: 22 Updated Cost Estimates of PRs made earlier, are to be submitted. 7 in 2014-15, 14 in 2015-16, 1 in 2016-17.

1 SECL Chira Group OC (119 blocks) OC 15.00 1.50 Jul-16 Oct-162 SECL Syang Group OC (119 blocks) OC 20.00 3.00 Jan-16 Apr-163 SECL Gevra Expn OC (70 Mty) OC 35.00 24.00 Mar-15 Apr-154 SECL Mahamaya OC OC 1.14 1.25 Mar-15 Apr-155 SECL Chirimiri Expn OC 1.00 1.00 Mar-15 Apr-156 SECL Gayatri UG UG 0.66 0.66 Mar-15 Apr-157 SECL Batura Highwall OC 0.50 0.50 Mar-15 Jan-168 SECL Batura West Extn Highwall/OC OC 1.00 0.50 Mar-15 Sep-16    Sub-total SECL   74.30 32.41  

Note: 3 Updated Cost Estimates of PRs made earlier, are to be submitted by June 2015.

www.cmpdi.co.in

PRs to be Prepared for 925 MT Projection of CIL in 2019-20

Sl No

Comp-any

Project Report OC/ UG

Incremental Capacity

(Mty)

Contribution in 2019-20

(Mt)

Schedule of PR Submission

PR Approval Schedule

1 NCL Block B Expn Recast PR (6 Mty) OC 4.00 3.50 Nov-15 Jul-16

2 NCL Jayant Expn OC OC 10.00 6.00 Jan-15 Sep-15

3 NCL Dudhichua Expn OC OC 10.00 6.00 Dec-15 Mar-16

4 NCL Dongrital UG (119 blocks) UG 3.00 1.50 Mar-15 Nov-15

    Sub-total NCL   27.00 17.00  

Note: Projected production of 2.5 Mt in 2019-20 from Patpaharia, Marki-Barka E & Marki-Barka W (all 3 in 119 blocks list) is proposed to be obtained from expansion of operating mines e.g. Jayant Expn & Dudhichua Expn, etc.

1 MCL Bhubaneswari Expn (30 Mty) OC 10.00 5.00 Dec-15 Mar-16

    Sub-total MCL   10.00 5.00  

 TOTAL 18 PRs

(10 PRs in 14-15; 7 PRs in 15-16; 1 PR in 16-17)

 

119.59 57.11 

www.cmpdi.co.in

Sustaining the Production Level

Status of 119 Blocks assigned to CIL

No. of blocks

Tentative Reserves

(MT)

Tentative capacity

(Mty)

GR Available 37 9451.78 73.49

Exploration in progress 59 24396.29 102.70

Exploration to start 23 10297.09 29.25

Total 119 44145.16 205.44

Note: 1. GR preparation for all 23 Unexplored Blocks will be completed by 2026-27. 2. 7 of these 23 blocks are on dip side of operating mines. 1 block is under the NTPC power plant site in North Karanpura.

www.cmpdi.co.in

Geological Reports Available – 37 Blocks.

Project Reports Submitted – 7 Blocks

Project Reports to be submitted in 2015-16 – 19 Blocks

Project Reports to be Submitted in 2016-17 – 2 Blocks

Blocks allotted for CTL – 2 Blocks

Blocks to be Worked from Operating Mines – 3 Blocks

Blocks on Dip side of Other Mines/blocks – 4 Blocks

Exploration in Progress – 59 Blocks.

Exploration to commence – 23 Blocks.

Sustaining the Production Level

Status of 119 Blocks assigned to CIL

www.cmpdi.co.in

Comp-any

No. of Blocks

Type of Mine Reserves (in MT)

OC UG Mixed Proved Indicated Inferred Total

ECL 17 0 11 6 1212.73 6665.19 24.87 7902.79

BCCL 3 1 2 0 315.10 147.06 - 462.16

CCL 17 8 6 3 1020.04 3265.72 621.09 4906.85

WCL 18 3 15 0 208.37 1519.81 75.00 1803.18

SECL 40 8 15 17 1989.83 12978.51 150.00 15118.34

NCL 13 0 4 9 524.11 4790.83 - 5314.94

MCL 11 8 1 2 1965.02 5446.88 1225.00 8636.90

CIL 119 28 54 37 7235.20 34814.00 2095.96 44145.16

Note: Out of 119 blocks, 4 blocks (Brahmani, Chichropatsimal, East of Damagoria, and Takli-Jena-Bellora North) are deallocated captive blocks (Schedule-I), and 2 blocks (Brajnathpur and Radharamanpur) are allotted for CTL. So, the number of additional CIL blocks would be 113 instead of 119.

Sustaining the Production Level

Status of 119 Blocks assigned to CIL

www.cmpdi.co.in

Large Projects Likely in 119 Blocks

Sl No

Block Company Tentative Capacity (Mty)

1 Brahmani-Chichropatsimal ECL 18

2 Salaipahar ECL 6

3 Chirra Group (5 blocks) SECL 15

4 Syang Group (4 blocks) SECL 20

5 Mahan North SECL 5

6 Mahan South SECL 5

7 Prajapara MCL5

8 Prajapara Dip Side MCL

9 Tribira MCL 8

TOTAL 82

www.cmpdi.co.in

Operational Planning for large opencast mines

Surface Layout and Infrastructure support services

Introduction of higher size equipment (e.g. 42 cum rope shovel, 15 cum hydraulic shovels, 240 T dumpers, 381 mm drills, 860 HP dozers, 533 HP motor graders, etc)

Mobile In-pit crushing and conveying systems with dust suppression arrangements

Satellite Surveillance for R&R and Land Reclamation Monitoring OBR measurement for all mines of CIL (as per recent CVC guidelines) NDT. Laser Scanner for Survey. Environmental Monitoring for PM 2.5 micron. New Area for Space Technology Application:

Regional Air Quality Monitoring using space borne scanners Slope Stability monitoring using SAR Interferometry Rapid OB and Coal Stock Measurement using UAVs.

Support Services during Project Implementation

www.cmpdi.co.in

Planning and design of Coal Handling Plant including tender documents preparation, cost estimates, etc.

Blasting services - Controlled blasting, Fragmentation, Site-specific proper drilling/blasting design.

Design of roof support systems and strata control services. Management services for ISO Certification - ISO 9001(Quality Management System), ISO 14001

(Environment Management System), OHSAS (Occupational Health & Safety Assessment Series)18001, SA (Social Accountability) 8000, ISO 27001 (Information Security Management System), ISO 50001(Energy Management System).

Lab. services for – Coal characterisation, Washability, Air / water quality, Physico-mechanical properties of rocks, CBM, Shale Gas, etc.

Support Services during Project Implementation (Contd)

www.cmpdi.co.in

Production Enhancement from UG mines – Mass Production Technology

UNDERGROUND MINES IN OUTSOURCING MODE

Sl No Mine Comp-any

Capacity (Mty)

Technology Status

1 Moonidih XV Seam BCCL 2.500 PS Longwall Work Awarded2 Moonidih XVI Seam BCCL 0.700 PS Longwall Work Awarded3 Kapuria BCCL 2.000 PS Longwall Work Awarded4 Muraidih BCCL 2.000 PS Longwall Work Awarded5 Jhanjra ECL 0.950 Continuous Miner Work Awarded6 Sarpi ECL 0.460 Continuous Miner Work Awarded7 Jhanjra PSLW ECL 1.700 PS Longwall Work Awarded8 NCPH/Kapildhara SECL 0.430 Continuous Miner Work Awarded9 Sheetaldhara-Kurja SECL 0.420 Continuous Miner Work Awarded

10 Pinoura SECL 0.400 Continuous Miner Work Awarded11 Rani-Atari SECL 0.180 Continuous Miner Work Awarded12 Churcha RO SECL 1.000 Continuous Miner Work Awarded13 Haldibari SECL 0.420 Continuous Miner Work Awarded14 Vijay West SECL 0.420 Continuous Miner Work Awarded15 Tandsi WCL 0.510 Continuous Miner Work Awarded  Sub-total   14.090    

www.cmpdi.co.in

UNDERGROUND MINES IN OUTSOURCING MODE

Sl No Mine Comp-any

Capacity (Mty)

Technology Status

1 Block-II BCCL 0.450 Continuous Miner In Pipeline

2 Kottadih ECL 0.510 Continuous Miner In Pipeline

3 Khairaha SECL 0.465 Continuous Miner In Pipeline

4 Ketki SECL 0.300 Continuous Miner In Pipeline

5 Gayatri SECL 0.510 Continuous Miner In Pipeline

6 Tawa-II WCL 0.360 Continuous Miner In Pipeline

7 Borda WCL 2.000 PS Longwall In Pipeline

8 Murpar WCL 2.000 PS Longwall In Pipeline

  Sub-total   6.595    

  Grand-total   20.685    

Production Enhancement from UG mines – Mass Production Technology

www.cmpdi.co.in

OTHER MINES IDENTIFIED FOR CM TECHNOLOGY

Sl No Mine Comp-any

Capacity (Mty)

Technology Status

1 Kumardih B ECL 1.020 Continuous Miner PR approved

2 Churi CCL 0.500 Continuous Miner PR approved

3 Parej East CCL 0.510 Continuous Miner PR approved

4 Piparwar Mangardaha CCL 1.020 Continuous Miner PR approved

5 Amlo-Dhori CCL 0.300 Continuous Miner PR approved

6 Jamunia WCL 0.840 Continuous Miner PR approved

7 Gandhigram WCL 1.170 Continuous Miner PR approved

8 Dhau North WCL 0.360 Continuous Miner PR approved

9 Talcher West MCL 0.520 Continuous Miner PR approved

10 Natraj MCL 0.520 Continuous Miner PR approved

  Sub-total (PR approved)

  6.760    

Production Enhancement from UG mines – Mass Production Technology

www.cmpdi.co.in

OTHER MINES IDENTIFIED FOR CM TECHNOLOGY

Sl No Mine Comp-any

Capacity (Mty)

Technology Status

1 Tilaboni ECL 1.860 Continuous Miner Awaiting approval2 Jhanjra LHCM ECL 0.720 Continuous Miner Awaiting approval3 Shankarpur ECL 1.163 Continuous Miner Awaiting approval4 Pandaveswar-

DalurbandECL 1.170 Continuous Miner Awaiting approval

5 Rangamati-A ECL 0.855 Continuous Miner Awaiting approval

6 Rangamati-B (Tumni and Kanchanpur

Sector)

ECL 1.080 Continuous Miner Awaiting approval

7 Pathakpur SECL 0.720 Continuous Miner Awaiting approval Sub-total (PR awaiting approval) 7.568    

 Total (Other Identified Mines) 14.328     Grand-total (Outsourcing + Other

Identified Mines)35.013

   

Production Enhancement from UG mines – Mass Production Technology

www.cmpdi.co.in

Coal Resources & Reserves under CIL as per UNFC Classification

Total No. Of Blocks/Mines/

Projects

Total Resources

(BT)

Proved Resources

(BT)

Indicated / Inferred

Resources (Balance to be proved) (BT)

645 88.417 66.61 21.80

www.cmpdi.co.in

Resources in Stand Alone Blocks and Dip Side Blocks as per UNFC Classification

Type of Blocks Number Resources (BT)

Explored Stand alone Blocks 4 0.28

Total – Explored 0.28

Un-Explored Stand alone Blocks 2 0.50

Under Exploration Stand alone Blocks 5 0.98

Total - Unexplored Blocks 1.48

TOTAL – Stand alone Blocks 1.76

Resources on dip side blocks/lower seams 20.32

Grand Total 22.08

www.cmpdi.co.in

Stand-alone Blocks under CIL

Sl No

Block Coalfield Exploration Status

Tentative Reserves

(Mt)

OC/ UG

Tentative Capacity

(Mty)

Remarks

1 North Lohari Daltonganj Explored 3.62 UG 0.3 Small isolated block. Meager reserves.

2 Barul Bagdiha Ranigunj Unexplored 468.78 UG 1 Reserves deep seated below barren measure.

3 Madhupur Ib Valley In progress 70.73 OC 2 30% forest land. Dhutra Sardega Rly Corridor 52 km needed.

4 Baitarni East Talcher In progress 425.00 OC 5 Law & Order Problem. 60 % forest, Jarapada-Talcher Rail Corridor 87 km needed, 2 nalas to be diverted.

5 Tulsi Block A Bisrampur Explored 32.91 OC/UG

1 GR submitted in 2013. Block area 4.13 sq.km.

6 East of Manikpur (Bundeli-I, II, III)

Korba Explored 200.00 OC/UG

3 40% forest land, R&R of 1 village, 3-4 km rly link needed from proposed East West Rail Corridor.

7 Noonbirra Korba Explored 44.58 OC/UG

1 Indicated reserve. Detailed exploration not done due to low potential.

8 Keshwahi (Gerua Area)

Sohagpur Unexplored 30.00 UG 1 20% forest land, R&R of 7 villages, 20 km rly link needed from Burhar siding.

9 Amartipur Tatapani In progress 45.86 OC 1 Law and order problem. 95 % forest land, 49 km rly link needed from Bhatgaon siding.

10 Duba Tatapani In progress 87.81 OC 1 Law and order problem. 80% forest land. 43 km rly link needed from Bhatgaon siding

11 Mitgain Bhormi Tatapani In progress 350.00 OC 3 Law and order problem. 7 km rly link from Bhatgaon siding needed.

      1759.29 19.30  

THANK YOU

www.cmpdi.co.in

PRs prepared and not included in the 925 Mt production program

Sl No

Project Comp-any

OC/ UG Incremental Capacity (Mty)

PR Status

1 Pandaveswar-Dalurband ECL UG 2.27 Awaiting approval with ECL. OC (H) Patch Proposed.

2 Rangamati A ECL UG 0.86 Awaiting approval with ECL.

3 Rangamati B (Gourbazar Sector) ECL UG 0.51 Awaiting approval with ECL.

4 Rangamati B (Tumni Kanchanpur Sector)

ECL UG 1.08 Awaiting approval with ECL.

5 Shankarpur UG ECL UG 1.16 Awaiting approval with CIL.

  Sub-total ECL     5.88  

6 Block V BCCL OC 3.00 Awaiting approval with BCCL. OC (H) Patch Proposed.

7 Block VI BCCL OC 1.50 Awaiting approval with BCCL. OC (H) Patch Proposed.

8 Kalyaneshwari (119 blocks) BCCL OC 4.00 Awaiting approval with BCCL.

  Sub-total BCCL     8.50  

www.cmpdi.co.in

PRs prepared and not included in the 925 Mt production program

Sl No

Project Comp-any

OC/ UG Incremental Capacity (Mty)

PR Status

9 Ara OC CCL OC 2.50 Awaiting approval with CCL10 Argada OC CCL OC 1.70 Approved in Principle by CCL11 Asnagarha OC CCL OC 3.00 Awaiting approval with CCL12 Aswa NS CCL OC 1.00 Approved in Principle by CCL13 Chano Rikba CCL OC 2.00 Approved in Principle by CCL14 DRD OC CCL OC 4.00 Awaiting approval with CCL15 Gose OC CCL OC 2.00 Approved in Principle by CCL16 Hesalong CCL OC 1.50 Approved in Principle by CCL17 Jeevandhara OC CCL OC 1.00 Awaiting approval with CCL18 Kuju CCL OC 1.30 Approved in Principle by CCL19 Mahendra (Rajbar) (119 blocks) CCL OC 4.00 Approved in Principle by CCL20 Pundi Expn CCL OC 2.50 Approved in Principle by CCL21 Ramgarh-II West CCL OC 1.50 Awaiting approval with CCL22 Religara Expn CCL OC 0.60 Awaiting approval with CCL23 Sawang Pipradih OC CCL OC 2.00 Awaiting approval with CCL24 Sayal D CCL OC 1.00 Approved in Principle by CCL  Sub-total CCL     31.60  

www.cmpdi.co.in

PRs prepared and not included in the 925 Mt production program

Sl No Project Comp-any

OC/ UG

Incremental Capacity (Mty)

PR Status

25 Bakulmuni OC SECL OC 1.50 Submitted to SECL. Uneconomic.26 Amba UG SECL UG 0.24 Submitted to SECL. Uneconomic.27 Badauli PSLW UG SECL UG 0.78 Submitted to SECL.28 Bodri/Bodri North UG SECL UG 0.78 Submitted to SECL. Uneconomic.29 Pathakpur UG SECL UG 0.72 Submitted to SECL.  Sub-total SECL     4.02  

30 Chikalgaon / Chinchala WCL OC 3.00 Uneconomic31 Ghugus Expansion (Sector C) /Nokoda

UG to OCWCL OC 0.80 Uneconomic