cmc boiler controls

Upload: devidutta-panda

Post on 03-Jun-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 CMC Boiler Controls

    1/41

  • 8/12/2019 CMC Boiler Controls

    2/41

    Without automatic controllers, all regulationtasks will have to be done manually. Forexample: To keep constant the temperatureof water discharged from an industrial gas-fired heater, an operator has to watch atemperature gauge and adjust a gas controlvalve accordingly (Figure 1). If the watertemperature becomes too high, the operator

    has to close the gas control valve a bit - justenough to bring the temperature back tothe desired value.If the water becomes too cold, he has toopen the valve

    To relieve our operator from the tedious task of

    manual control, we automate the controls - i.e. we

    install a PID controller (Figure 2). The controllerhas a Set Point (SP) that the operator can adjust to

    the desired temperature. We also have to automate

    the control valve by installing an actuator (and

    perhaps a positioner) so that the Controller's

    Output (CO) can change the valve's position. And

    finally, we'll provide the controller with an

    indication of the temperature or Process Variable

    (PV) by installing a temperature transmitter. The

    PV and CO are mostly transmitted via 4 - 20mAsignals . So, when everything is up and running,

    our PID controller compares the process variable

    to its set point and then calculates the difference

    between the two signals, also called the Error (E).

    Then, based on the error, a few adjustable settings

    and its internal structure (described next), the

    controller calculates an output that positions the

    control valve.

  • 8/12/2019 CMC Boiler Controls

    3/41

  • 8/12/2019 CMC Boiler Controls

    4/41

    PROCESS

    CONTROLLED QUANTITIES

    (I/L WTR FLOW & O/L WTR FLOW)

    MANIPULATED QUANTITIES

    (I/L VLV & O/L VLV OPENING

    SENSED VALUESPV

    FEEDBACK CONTROL

    SET VALUE

    MANIPULATEDVALUES

    MV

    Tank level

  • 8/12/2019 CMC Boiler Controls

    5/41

    P

    I

    D

    ERROR

    INPUT

    If P Controller is used , it will have fast response

    but with steady State error.

    If only I controller is used, its response is slow

    compared to P , but no steady state error.

    If D derivative controllers are used it gives an extremely fast

    response as they give vast output for even moderate variations in

    input, as their Gain is dependent on rate of change of input.Because of this they have the characteristic of ANTICIPATION.

    These controllers anticipate What is going to happen and apply corrective

    action. The greatest disadvantage is any slightest hunting in the processvalue will create severe disturbances in the process.

  • 8/12/2019 CMC Boiler Controls

    6/41

    The use of proportional control alone has a large drawback i.e. Offset. Offset is a

    sustained error that cannot be eliminated by proportional control alone.For example, let'sconsider controlling the water level in the tank as shown in Figure above with a proportional-

    only controller. As long as the flow out of the tank remains constant, the level (which isour process variable in this case) will remain at its set point.But, if the operator shouldincrease the flow out of the tank, the tank level will begin to decrease due to the imbalance

    between inflow and outflow. While the tank level decreases the error increases and

    proportional controller increases the controller output proportional to this error . Consequently,

    the valve controlling the flow into the tank opens wider and more water flows into the tank. Asthe level continues to decrease, the valve continues to open until it gets to a point wherethe inflow matches the outflow. At this point the tank level remains constant, and sodoes the error. Then, because the error remains constant P-controller will keep itsoutput constant and the control valve will hold its position. The system now remains atbalance with the tank level remaining below its set point. This residual error is calledOffset.

    P - CONTROLLER

  • 8/12/2019 CMC Boiler Controls

    7/41

    PI

    P+I controller helps to have a finite output even though the

    input (ERROR) is ZERO. as the integration of zero is some

    constant value. Presence of P element helps in faster

    response, and presence of I element makes the steadystate error to make zero.

    PI - CONTROLLER

  • 8/12/2019 CMC Boiler Controls

    8/41

    PID

    MV=100/PB (E(t) + 1/TE(t) dt + Td / t E(t) )

    MV=100/PB(PV +t / T (E) + Td /(PV))MV=100/PB(E+t / T (E) + Td /(PV))

    Note that the PID controller output is oscillating , this is due to theD controllers sensitive response to NOISE.

    PID - CONTROLLER

  • 8/12/2019 CMC Boiler Controls

    9/41

    LT

    Water I / l

    Water o / l

    MAIN steam.

    EXAMPLE FOR FEED FORWARD CONTROL CONCEPT

  • 8/12/2019 CMC Boiler Controls

    10/41

    PROCESS

    SENSED VALUESPV

    FEEDBACK CONTROLHARDWARE.

    SET VALUE

    MANIPULATEDVALUES

    MV

    Disturbances

    Controlled quantities

    Sensed valuesof

    Disturbances

    FEED FORWARD & FEEDBACK CONTROL CONCEPT

    Feedback control works to eliminate errors, but feed forward feedback controloperates to prevent errors from occurring in the first place.

  • 8/12/2019 CMC Boiler Controls

    11/41

  • 8/12/2019 CMC Boiler Controls

    12/41

    P+I_

    +PV

    SV X

    COMPENSATED I/P VALUE

    CS+

    INPUT COMPENSATION METHOD

    _+

    PV

    SV

    P+I

    X

    COMPENSATED I/P VALUE

    CS

    OUTPUT COMPENSATION METHOD

    P+I

    ERROR DERIVING BLOCK

    CONTROL ALGORITHAM

    COMPENSATION BLOCK

    P I D

  • 8/12/2019 CMC Boiler Controls

    13/41

    POWER PLANT INSTRUMENTATION

    ~

    DRUM LEVEL MONITORING

    FURNACE DRAFT

    BOILER MASTER(FUEL CONTROL)

    STEAM TEMP. MONITORING&CONTROL

    AIR FLOW CONTROL

    TURBINE LOAD CONTROLTURBO SUPERVISORY SYSTEM

  • 8/12/2019 CMC Boiler Controls

    14/41

    DRUM LEVEL MEASUREMENT

    INTRODUCTION:Level measurement is very important aspect in thermal power plant.

    We are having level measurements in the following areas

    1. HOT WELL LEVEL2. DEARATOR LEVEL3. DRUM LEVEL4. LPH,&HPH LEVELS

    Generally for measurement and control we use level transmitters . There areSeveral principles for level measurement.

    1. Differential principle. : Drum level , Dearator level, HPH&LPH level

    2. Displacer tube principle.: Hotwell level

    3. Capacitive principle. : MOT oil tank level

    4. Ultrasonic principle : ----

    5. Air bubble principle. : proposed in BCW sump level.

    Out of all, the Boiler Drum level measurement is crucial one. it uses

    the differential method.

  • 8/12/2019 CMC Boiler Controls

    15/41

    HYDRAUSTEP DRUM LEVEL MONITORING

  • 8/12/2019 CMC Boiler Controls

    16/41

    PRINCIPLE OF OPERATION

  • 8/12/2019 CMC Boiler Controls

    17/41

  • 8/12/2019 CMC Boiler Controls

    18/41

    T

    X

    AIR

    BUBBLER SYSTEM FOR LEVEL ME SUREMENT IN OPEN SUMPS

    V CONST.

    CURRENT

    SOURCE

    Bubbler type method is a cost effective way to measure level in open tanks only.In this method, a positive air/gas flow is passed through the liquid & back pressure

    is sensed which is proportional to liquid head. Excess pressure is vented in the

    form of bubbles .The bubble air through the tube must be maintained at a constant

    Flow rate, A bubbler system typically consists of pressure regulator, needle valve,

    pressure gauge, airflow meter, air line extending to the bottom of the wet well.

    Transmitter

    H= X.* Specific gravity.

    6 bar1.2 barAir flow

    50 l/h

  • 8/12/2019 CMC Boiler Controls

    19/41

  • 8/12/2019 CMC Boiler Controls

    20/41

    H L

  • 8/12/2019 CMC Boiler Controls

    21/41

    Now, assuming the transmitter has a reversed output, LRaw, calibrated with cold water, so that when the level

    increases so does the analog signal, then it is possible toexpress the level, L, in % as a function of the densities ofthe water (both hot and cold) and of the steam:

    L=100(100L raw) / K

    K=(ws) / c

  • 8/12/2019 CMC Boiler Controls

    22/41

    DRUM LEVEL CONTROL

  • 8/12/2019 CMC Boiler Controls

    23/41

  • 8/12/2019 CMC Boiler Controls

    24/41

    DRUM LVL

    (L) (R)

    /2

    DRUM PR

    XCOMPENSATED

    DRUM LVL

    DRUM LVL SET

    WITH VEL LIMITER

    P+I

    1ELEMENTDRUM LVL

    CNTRLER

    P+I

    FEED FLOW

    (BFPS DISCH)

    TOT SH

    SPR FLOW

    RH SPR

    FLOW

    P+I

    3ELEMENTDRUM LVL

    CNTRLER

    FEED FL TO DRUM

    TOT STM FLOW

    SEL SW

    SEL SW

    FEED FL CNTRLR

    LOW LOAD

    CVMAIN LOAD

    CV

    ST BY LOAD

    CV

    1 ELEMENT/ 3 ELEMENT

    DRUM LEVEL Y FEED CVS

  • 8/12/2019 CMC Boiler Controls

    25/41

    P+I

    3ELEMENTDRUM LVLCNTRLER

    TOT STM FLOW

    COMPENSATED DRUM LVL

    DRUM LVL SET

    P+I

    SEL SW

    SEL SW

    FEED FL CNTRLR

    MAIN LOAD

    CV

    ST BY LOAD

    CV

    1 ELEMENT/ 3 ELEMENT

    FEED FL TO DRUM

    P+I

    DRUM LVL

    CNTRL

    BFP SCOOP

    DP ACROSS FCV

    (1) (2)

    /2

    P+I

    DP ACROSS FCV

    SV

    SEL SW

    BFP A,B,C SCOOPS

    I

    II

    IF POS II selected

    Force to manual

    DRUM LVL BY BFP SCOOP

  • 8/12/2019 CMC Boiler Controls

    26/41

    COORDINATED MASTER CONTROL

    Objective:To have a quick and stable load control thatmatches variable power demand.

    CMC

    TURBINE MASTER BOILER MASTER

  • 8/12/2019 CMC Boiler Controls

    27/41

    TURBINE MASTER

    TURBINE MASTER

    Power generation is controlled byturbine governor by varyingsteam flow to turbine.

    CMND. FROM CMC

    PR.DEVIATIONFROM

    BLR. MASTER

  • 8/12/2019 CMC Boiler Controls

    28/41

    BOILER MASTER

    BOILER MASTER

    Air flowcontroller

    Fire demandcontroller

    THE BOILER HAS MANY SYSTEM VARIABLES AND AlSO HAS A GREAT DELAY INDYNAMIC RESPONSE. CMC SYSTEM ENABLES THE OPERATORS TO CONTOL THESTEAM FLOW RATE TO THE TURBINE. THIS IS DONE BY REGULATING THEBOILER INPUT IN ADVANCE TO MEET THE LOAD DEMAND..

    FD-ABLADEPITCH.

    FD-BBLADEPITCH.

    PA-Damper.

    Bypass PADamper.

    CMND. FROM CMC

    O/P FROMMW CNTRL(as feed forward comp.)

    AFL CNTL

  • 8/12/2019 CMC Boiler Controls

    29/41

    Unit Operations Mode

    There are four unit control operation modes,where in the boiler and turbine controllersboth operate simultaneously or any one ofthem in Auto.

    They are as follows . . .

    1. coordinated control mode.

    2. Turbine follow mode. 3. Boiler follow mode.

    4. Runback mode.

  • 8/12/2019 CMC Boiler Controls

    30/41

    Unit Master Control

    This also called as coord inated mastercont ro l (CMC).

    In this mode, both boiler master control

    and turbine master control automaticallycoordinate the boiler and turbine to match

    the load setting signal given by the

    operator or load dispatch system.

  • 8/12/2019 CMC Boiler Controls

    31/41

    The fundamental of unit master controller is to control the steampressure at the inlet of governing valves of steam turbine. This controllerhas to give Load Setto Turbine Masterafter taking into consideration ofPressure Deviation, and similarly Pressure Set to the Boiler Master inadvance. Boiler master considers the following 2 points . . .

    1. Normally if there is an imbalance between the boiler and turbine loads,the Steam pressure changes steadily (but not abruptly) because theboiler has a thermal capacity. It may be visualized as the time taken forthe steam pressure to change by a specified amount for a specifiedchange in load demand. For a large Boiler a change in demand equal to

    full-load would cause the pressure to fall by 10 % in about 12 sec.

    2. There is a lag of some 200 sec between a change in steam demand andthe response of the steam pressure action of a Master pressure control.

    D

    1 2TM 0003

    LOAD SET FROMFREQ.

  • 8/12/2019 CMC Boiler Controls

    32/41

    TP0501

    PR. SET TO HPBP

    TP0503

    PR. SET TO EHG

    BM0509AIR FLOW CNTRL

    BM0508FUEL FLOWCNTRL

    F(x)

    SS1861

    Selector switch

    A/M STNDS1889

    DS1888

    RATE LIMITER

    MW VEL LMTVL1894

    F(x)

    FRQ. INFL OFF

    TM0001

    DS1890 SS1861A

    LOWSELECT

    TM0002

    DS1891 SS1862

    LOWSELECT

    TSE UPPER MARGIN

    UPPER MARGINSET FROM CRT

    LOWER MARGINSET FROM CRT

    TSE LOWER MARGIN

    PI1992SUB

    PI

    PC1597

    MWGENERATED

    GW0001

    PC1595-M

    WCNTRL

    PI1993SUB

    SS19941=MW, 2=STM FLW

    PI1994SUB

    PI

    PC1596-BL

    R.MSTR

    STEAMFLOW

    MF0003

    SS1867

    SS1865

    MP001

    MP002

    SS1596

    SP.TOBM

    SV1596

    LoadVsPr

    PI1997

    BIASAS1596

    PV1596

    TP0507

    PI1996

    LOAD SET TO EHG

    TP0505

    PR. ACT TO EHG

    TP0502

    PR. ACT TO HPBP

    LOAD SET FROMLDC

    SCHEME TO ENSURE FUEL FOLLOWS AIR DURING LOAD INCREASE

  • 8/12/2019 CMC Boiler Controls

    33/41

    CL1620

    TOT PA FLOW

    >