Financial Reporting Procedure Lead Partner Seminar 14th November 2012 City Hotel, Londonderry/Derry, Northern Ireland, UK Gustaf Forsberg

Upload: fala

Post on 24-Feb-2016

42 views

Category:

Documents


0 download

DESCRIPTION

Financial Reporting Procedure Lead Partner Seminar 14th November 2012 City Hotel, Londonderry/Derry, Northern Ireland, UK Gustaf Forsberg. Claiming procedure, financial report. Document retention. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Claiming procedure, financial report

Financial Reporting ProcedureLead Partner Seminar14th November 2012

City Hotel, Londonderry/Derry, Northern Ireland, UK

Gustaf Forsberg

Page 2: Claiming procedure, financial report

Claiming procedure, financial report

Page 3: Claiming procedure, financial report

Document retention

NOTE: In case of an audit, all project partners must preserve copies of ALL supporting documents until three years have passed after Programme closure. We recommend that supporting documentation is preserved at least until year 2021. Lead Partner and Partners must also consider national legislation regarding preservation of accounting material.

Page 4: Claiming procedure, financial report

General information 1 (3)

Two types of budgets in an application

1. Project specific cost budget2. Common cost budget

When claiming and distributing common cost throughout the project partnership:

Certification of Common cost has to be done by the holder of the common cost First Level Controller (FLC).

A specific template for Common Cost certification has to be filled in by the FLC The holder of the common cost will include the total common cost in the SoE for the

reporting period when the cost was originally occurred. Distribution of common cost is made by an invoice between the different partners, the

invoice should be supported by documentation that common cost have been certified by the holders First Level Controller.

Page 5: Claiming procedure, financial report

General information 2 (3)

When claiming and distributing common cost throughout the project partnership:

The partners will include their share of the common costs in the SoE for the reporting period when the common cost were paid and put into their accounts.

The holder will report the common cost payments from other partners in the SoE, most likely in a specific budget line, for the reporting period when the payments were received and registered in the accounts. The payment will reduce the common cost to a net cost for common activities in the Lead Partner SoE, and not be reported as a revenue.

Page 6: Claiming procedure, financial report

General information 3 (3)

Holder FLC Partners

CoE, project costs incl. common costs

SoE, project costs incl. common costs

”Certificate of common costs”

Distribution of common costs

Invoice, share of common costs

Attached

Comparative check -invoice amount vs

certified share

Payments deducted from total common

costs

Shares of

common costs Payments

Page 7: Claiming procedure, financial report

CERTIFICATE OF COMMON COSTS

When distributing common costs a Certificate of common costs shall be attached to all invoices. The certificate is issued by the national controller of the holder of the common costs. The certificate certifies that the common costs are eligible according to applicable rules and regulations, and that the shares together sum up to the total common cost amount. Project Title: Reporting period: Project partner holding common costs: Partner country: I / We hereby certify that the reported common costs for the period stated above have been checked, according to Art. 16 of Regulation (EC) No 1080/2006, for accuracy and compliance with the Grant Letter including its enclosures and the Northern Periphery Programme Common Eligibility Rules, as well as all applicable National legislation and Community rules and regulations. I / We also certify that the control has been conducted independently from project implementation. Certified common costs for the period stated above (EUR): With this certificate I / We also certify that the distribution shares together sum up to the total common cost amount. The certified common cost shares are listed below: Project partner: Share of common costs: Sum of shares: …………………………….. …………………………….. Signature of National Controller Name in clear …………………………. Place and date

Page 8: Claiming procedure, financial report
Page 9: Claiming procedure, financial report

The use of National Controllers is a new feature within the European Co-operation.• National Controllers have one main task, to ensure that a

reliable and functional national control system is in place in its nation.

• National Controllers are responsible for OLAF reporting, in case of any irregularities

• National Controllers designate First Level Controllers (FLC’s) to perform the check.

• Only costs certified by the FLC’s can be eligible for ERDF or ERDF equivalent funding

• Different systems in different countries• Current list of National Controllers and First Level

Controllers are available on our website and annexed to our Programme Manual

Explanation of National Controllers 1 (3)

Page 10: Claiming procedure, financial report

Example; National Controller Finland “Decentralised system”: Finnish Ministry of the InteriorDepartment for Development of Regions and Public AdministrationRegional Development UnitP.O.Box 26, FI-00023 Government  (From 1.1.2008: Ministry of Employment and Economy, details to be specified)

Explanation of National Controllers 2 (3)

Finnish system

• Note that the Ministry of Employment will not carry out the control. It will only be the responsible authority.

kirsti
Is this the correct address? What is the town/city?
Page 11: Claiming procedure, financial report

Example; National Controller Sweden “Centralised system”: County Administrative Board of VästerbottenIndustry and Commerce Department901 86 Umeå Tel: +46 90 10 70 00Fax:+46 90 10 71 [email protected] Mr Håkan TörnströmHead of Unit+46 90 10 71 [email protected]

Explanation of National Controllers 3 (3)

Swedish system

• Note that listed person is the person responsible for the unit of Industry and Commerce at CAV.

• A desk officer / FLC responsible for the task of certififying expenditure will be appointed

• Currently no fee will be charged for Swedish partners to get their expenditure certified.

Page 12: Claiming procedure, financial report

National Controllers will most likely require the following documents in order to complete a first level of control:

• Statement of Expenditure (signed by authorized person) • Ledger for the current reporting period (every partner

should keep separate project accounts)• Time sheets (for part time employees)• Copies of all invoices and receipts• Employment contracts (for full time employees)• Model to show the office costs distributed proportional +

supporting documentation (when applicable)• Transaction list• Partner activity report• Other relevant documentation

Supporting Documents to National Controllers

Note: It is up to each programme partner country to establish what documentation they will require.

This is only an indicative list of required documentation for the first level control provided by the NPP 2007-2013

Page 13: Claiming procedure, financial report

Statement of Expenditure by MS Partners to National Controller 1 (5)                   

      Statement of Expenditure                               From: dd.mm.yyyy To: dd.mm.yyyy      

     

Note: The dates should be stated by [day.month.year], e.g. "30.09.2008"            

                   Project Title:        Reference number:        Partner claim no.:                                     Contact information                                   

Partner organisation (original language):            

Partner organisation (english translation):                               

Address:   Person responsible:    Postal code:   E-mail:    

Location:   Phone:    Country:   Mobile:    

Legal status:                                 

Phone:   Contact person:    Fax:   E-mail:    

E-mail:   Phone:    Website:   Mobile:    

                                      VAT-status   VAT recoverable   VAT non recoverable      

Page 14: Claiming procedure, financial report

Statement of Expenditure by MS Partners to National Controller 2 (5)Supporting documents Note: The documents listed below is an indicative list of supporting documentation recommended by the Managing Authority.It is up to each nation to decide on what documentation they will require.

LedgerTime sheets (part time employees)Copies of invoices and receiptsEmployment contracts (full time employees)Model to show the proportional distribution of office costs (if applicable)Currency convertion sheetStatement of Expenditure, 10% area partner + underlying documentation, see indicative list above (if applicable)Other relevant documents (such as contracts, vat-documents etc.)

Other funding and information measures Yes No

Has any other EU funding been received?Has the project received any eligible co-financing that was not stated in the budget?Has the project fulfilled its information duties in accordance with Commission Regulation (EC) No 1828/2006? Has the project undergone any substantial modification affecting the nature of implementation?

Expenditure Yes No

All expenditure has been incurred during the project periodAll expenditure included has been paid during current reporting period All expenditure concerns the projectAll expenditure concerns activities that were stated in enclosure 1 to the decision

Signature

I hereby certify that all information in this Statement of Expenditure is complete and correct and that project net costs for this reporting period amounts to: 0,00 euro

Place and date Authorized signature for partner organisation

Name in clear

Page 15: Claiming procedure, financial report

Statement of Expenditure by Partners to National Controller 3 (5)

Project Title: 0        

Project partner: 0        

Partner country: 0          

Reference no: 0          

    

           

MS Partner from 20% area:              

NMS Partner from 20% area:              

NMS Partner from 10% area:   Note: If 10% partner, please fill in information of responsible Lead Partner below

Lead Partner responsible:   Country:   Partner no:  

Other partner:                

Page 16: Claiming procedure, financial report

Statement of Expenditure by Partners to National Controller 4 (5)

Cost and co-financing statement for Northern Periphery projects

This statement refers to the period from: dd.mm.yyyy to: dd.mm.yyyyPartner claim no.: 0

PROJECT COSTS INCURRED (all amounts in euro)

Types of Expenditure Approved budgetCert ified cost,

earlier reporting periods

Claimed cost,current period

Project cost,accumulated

1. Staff costs incl. social contributions20.000,00 20.000,00

2. Travel and accomodation200.000,00 200.000,00

3. External experts200.000,00 200.000,00

4. Office costs (direct ly allocated)200.000,00 200.000,00

5. Office costs (distributed proportionally)20.000,00 20.000,00

6. Promot ion / publications, Seminars / conferences, Meetings

200.000,00 200.000,007. Equipment and supplies

20.000,00 20.000,008. Other (including 1st level control)

20.000,00 20.000,009. In kind costs

20.000,00 20.000,0010. Share of common costs

200.000,00 200.000,00Total expenditure

0,00 0,00 1.100.000,00 1.100.000,00Deducted: Received common cost payments

0,00Deducted: Project revenue

0,00Deducted: In kind costs

0,00 0,00 20.000,00 20.000,00Project net cost

0,00 0,00 1.080.000,00 1.080.000,00 #DIV/0!

Page 17: Claiming procedure, financial report

Statement of Expenditure by Partners to National Controller 5 (5)

PUBLIC MATCH FUNDING RECEIVED (all amounts in euro)                   

Public match funding, In kind (source, type)Budgeted match

fundingCertified funding,earlier reporting

periods

Claimed received funding,

current period

Actual funding,accumulated

 

      0,00  

      0,00  Totally received In kind contribution

0,00 0,00 0,00 0,00             

Public match funding, cash (source)Budgeted match

funding Certified funding,earlier reporting

periods

Claimed received funding,

current period

Actual funding,accumulated

 

      0,00  

      0,00  

      0,00  

      0,00  

      0,00  

      0,00  

      0,00  

      0,00  

      0,00  

      0,00  Totally received public cash contribution

0,00 0,00 0,00 0,00             Total public financial contribution 0,00 0,00 0,00 0,00 #DIV/0!

Page 18: Claiming procedure, financial report

Supporting document to Statement of expenditure

Currency conversion sheet

All project partners have to state their expenditure in Euro, only programme partner countries using Euro are Finland and Ireland. All other partners except for Finnish and Irish partners have to convert their currency into Euros. This is made by applying the Currency conversion sheet, and its principles:

Currency conversion sheet (for non Euro partners) The currency used in the Northern Periphery Programme 2007-2013 is Euro (EUR). Consequently all non Euro partners must convert their expenses from national currency into Euro. All costs should be converted using the monthly Commission rate for the last month in the current reporting period. The Commission exchange rates is found on the official website:

http://ec.europa.eu/budget/inforeuro/index.cfm?fuseaction=countries&Language=en

Page 19: Claiming procedure, financial report

Currency Conversion Sheet 1 (2)Project Title:Project partner:Partner country:Reference no:

Currency convertion sheet (for non Euro partners)The currency used in the Northern Periphery Programme 2007-2013 is Euro (EUR). Consequently all non Euro partners must convert their expenses from national currency into Euro. All costs should be converted using the monthly Commission rate forthe last month in the current reporting period. The Commission exchange rates are found on the official website: http://ec.europa.eu/budget/inforeuro/index.cfm?fuseaction=countries&Language=en

Last month of current reporting period: month rate

This statement refers to the period from dd.mm.yyyy to dd.mm.yyyyPartner claim no.: 0

PROJECT COSTS INCURRED

Types of Expenditure Claimed cost,current period

National currency

Exchange rateClaimed cost,current period

Euro1. Staff costs incl. social contributions

0,00 0,00000 #DIV/0!2. Travel and accomodation

0,00 0,00000 #DIV/0!3. External experts

0,00 0,00000 #DIV/0!4. Office costs (directly allocated)

0,00 0,00000 #DIV/0!5. Office costs (distributed proportionally)

0,00 0,00000 #DIV/0!6. Promotion / publications, Seminars / conferences, Meetings

0,00 0,00000 #DIV/0!7. Equipment and supplies

0,00 0,00000 #DIV/0!8. Other (including 1st level control)

0,00 0,00000 #DIV/0!9. In kind costs

0,00 0,00000 #DIV/0!10. Share of common costs

0,00 0,00000 #DIV/0!Total expenditure

0,00 #DIV/0!Deducted: Received common cost payments

0,00 0,00000 #DIV/0!Deducted: Project revenue

0,00 0,00000 #DIV/0!Deducted: In kind costs

0,00 0,00000 #DIV/0!Total project net cost

0,00 #DIV/0!

Corresponding exchange rate:

000

0

Page 20: Claiming procedure, financial report

Currency Conversion Sheet 2 (2)Project Title:Project partner:Partner country:Reference no:

PUBLIC MATCH FUNDING RECEIVED

Public match funding, In kind (source, type)Claimed received

funding,current period

National currency

Exchange rate

Claimed received funding, current

period

Euro

0,00 0,00000 #DIV/0!

0,00 0,00000 #DIV/0!Totally received In kind contribution

0,00 #DIV/0!

Public match funding, cash (source)Claimed received

funding,current period

National currency

Exchange rate

Claimed received funding, current

period

Euro

0,00 0,00000 #DIV/0!

0,00 0,00000 #DIV/0!

0,00 0,00000 #DIV/0!

0,00 0,00000 #DIV/0!

0,00 0,00000 #DIV/0!

0,00 0,00000 #DIV/0!

0,00 0,00000 #DIV/0!

0,00 0,00000 #DIV/0!

0,00 0,00000 #DIV/0!

0,00 0,00000 #DIV/0!Totally received public cash contribution

0,00 #DIV/0!

0

000

Page 21: Claiming procedure, financial report

Supporting documents from National Controllers

National/First Level Controllers will send two main document to the project partner:

• Certificate of Expenditure• Checklist of First Level Control

Page 22: Claiming procedure, financial report

Certificate of Expenditure 1 (4)

Certificate of Expenditure

This certificate refers to the period from dd.mm.yyyy to dd.mm.yyyy Note: The dates should be stated by [day.month.year ], e.g. "30.09.2008"Partner claim no.:

I / We hereby certify that the financial statement for the period stated above has been checked,according to Art. 16 of Regulation (EC) No 1080/2006, for accuracy and compliance with theGrant Letter including its enclosures and the Northern Periphery Programme Common EligibilityRules, as well as all applicable National legislation and Community rules and regulations

I / We also certify that the control has been conducted independently from project implementation

Project partner:Project Title:

Partner from flexibility rule area:

Reference no:Partner country:

Choose

Page 23: Claiming procedure, financial report

Certificate of Expenditure 2 (4)

Types of Expenditure Approved budgetCertified cost,

earlier reporting periods

Claimed cost,current period

Certified cost,current period

Certified cost,accumulated

1. Staff costs incl. social contributions0,00

2. Travel and accomodation0,00

3. External experts0,00

4. Office costs (directly allocated)0,00

5. Office costs (distributed proportionally)0,00

6. Promotion / publications, Seminars / conferences, Meetings

0,007. Equipment and supplies

0,008. Other (including 1st level control)

0,009. In kind costs

0,0010. Share of common costs

0,00Total expenditure (NPP area)

0,00 0,00 0,00 0,00 0,00Deducted: Received common cost payments

0,00Deducted: Project revenue

0,00Deducted: In kind costs

0,00 0,00 0,00 0,00 0,00Total project net cost (NPP area)

0,00 0,00 0,00 0,00 0,00 #DIV/0!

Page 24: Claiming procedure, financial report

Certificate of Expenditure 3 (4)Project Title:Project partner:Partner country:Reference no:Partner claim no.: 0

PUBLIC MATCH FUNDING RECEIVED (all amounts in euro)

Public match funding, In kind (source, type)Budgeted match

fundingCertified funding,earlier reporting

periods

Stated financial contribution,

current period

Certified financial contribution,

current period

Certified funding,accumulated

0,00

0,00Totally received In kind contribution

0,00 0,00 0,00 0,00 0,00

Public match funding, cash (source)Budgeted match

funding Certified funding,earlier reporting

periods

Stated financial contribution,

current period

Certified financial contribution,

current period

Certified funding,accumulated

0,00

0,00

0,00

0,00

0,00

0,00

0,00

0,00

0,00

0,00Totally received public cash contribution

0,00 0,00 0,00 0,00 0,00

Total public financial contribution 0,00 0,00 0,00 0,00 0,00

0

000

Page 25: Claiming procedure, financial report

Certificate of Expenditure 4 (4)DEDUCTIONSList of cost deductions made for the current reporting periodNote: The total deduction amount should equal the difference between "Claimed cost current period" and "Certified cost current period", see above.

Budget Line Verification no. Deducted amount

Deductions, total 0,00

Supporting documentsThe following documents should be sent back to the project partner

Certificate of ExpenditureFirst level control checklistCertificate of Expenditure, 10% area partner (if applicable)First level control checklist, 10% area partner (if applicable)

Signature

Place and date Authorized signature Stamp

Name in clear

Type of Cost Supplier Comments

Page 26: Claiming procedure, financial report

Common errors

Copies of Certificate of Expenditure and First Level Control checklists Missing Blue-ink signatures, First Level Control and Lead Partner

• Certificate of Expenditure missing pages Whole or part of document

Missing First Level Control checklist Whole or part of document

Old template for the Certificate of Expenditure Template from previous programme period Not the latest version, i.e. missing budget lines 10 and/or 11

Statement of Expenditure instead of Certificate of Expenditure

Page 27: Claiming procedure, financial report

All partners have to sumbit the following documents to the Lead Partner:

• Certificate of Expenditure (blue ink version)

• Additional documents which may be part of the Partnership Agreement:

• Partner Activity Report (as part of the aggregated activity report)

• FLC checklist• Transaction list of all expenditures• Other documents agreed within

the project partnership

Documents from Partner to Lead Partner

Page 28: Claiming procedure, financial report

Lead Partner Principle

Role Lead Partner:

Be the policeman of the project, ensure that all certified costs can be connected to eligible/approved project activities (Letter distributed)

Northern Periphery Programme recommends that all partner Certificates of Expenditures (CoEs) to the LP are supported by a partner activity report, clearly outlining the individual partner activities, and a transaction list to demonstrate which costs are related to what activities.

AND

It is vital that the Lead Partner can extract the individual partner activities from the overall Work Package activity plan, potentially outline individual partner activities in the partnership agreement.

Page 29: Claiming procedure, financial report

Lead Partner Principle

Role Lead Partner:

Note

The NPP does not require the first level controller of the Lead Partner to check the complete claim. This is instead done by the Managing Authority something we believe saves time in the payment process.

However, according to EC guidelines this is within the scope of the Lead Partner’s

FLC.

Page 30: Claiming procedure, financial report

Lead Partner Principle

Role Lead Partner:

Acting as link between the project partners and the programme Submitting the project progress report Overall responsibility for project coordination Formal beneficiary of ERDF and ERDF equivalent funding Lead Partner has the responsibility to distribute the funding received from the

NPP 2007-2013 among the project partnership in accordance with the spending by the partners.

The complete Lead Partner responsibilities are stipulated in Regulation: (EC) 1080/2006, Art 20

Page 31: Claiming procedure, financial report

In order to make a complete progress report the Lead Partner has to submitt the following documents to the Secretariat:

• Activity Report• Project claim• Summary of Certificates of Expenditure• Certificate of Expenditure (blue ink version) from all partners• FLC checklists from all partners

Note that the Activity Report and COE have to be submitted both in blue ink version, by post, as well as an electronic version by e-mail.

Documents from Lead Partner to the Secretariat

Page 32: Claiming procedure, financial report

Project Claim is the formal decleration of spending by the Lead Partner in order to receive ERDF or ERDF equivalent co-financing, 2 page document:

Project Claim 1 (4)

1 (2)

Note: The dates should be stated by [day.month.year ], e.g. "30.09.2008"Reporting period: From: dd.mm.yyyy To: dd.mm.yyyyProject claim No.:Project Title:Reference number:Priority:

Contact information

Lead partner organisation (original language):Lead Partner organisation (english translation):

Address:Postal code:

Location:Country:

Phone:Fax:

E-mail:Website:

Bank information

Name of bank:Address:

IBAN number:BIC code:

Contact person:

Mobile:Phone:E-mail:

Phone:Mobile:

page 1Project claim

Person responsible:

Priority 1: Priority 2:

E-mail:

Page 33: Claiming procedure, financial report

Project Claim 2 (4)Supporting documents                

                   

Project Claim (page 1 and 2)                  

Summary of CoE                  

Certificates of Expenditure (for all claiming project partners)                  

First level control checklists (for all claiming project partners)                  

Activity Report                  

                   

                   Other funding and information measures         Yes No                   

Has any other EU funding been received?                  

Has the project received any eligible co-financing that was not stated in the budget?                  

Has the project fulfilled its information duties in accordance with Commission Regulation (EC) No 1828/2006?                  

                   

                   Expenditure               Yes No                   

All expenditure has been incurred during the project period                  

All expenditure included has been paid during current reporting period                  

All expenditure concerns the project                  

All expenditure concerns activities that were stated in enclosure 1 to the decision                  

Has the project undergone any substantial modification affecting the nature of implementation?                  

                   

                   Signature                  

                   

I hereby certify that all information in this Project claim is complete and correct. By signing this Project claim I also apply for        payment in accordance with the Northern Periphery Programme 2007-2013 decision for project funding.  

                   

Place and date      

Authorized signature for the Lead Partner organisation          

                   

                   

                   

                   

        Name in clear        

                   

Page 34: Claiming procedure, financial report

Summary of CoE is the ”calculator” to ensure that the project claim has been compiled correctly:

1. Fill in the reported period for the project, and the claim number

Summary of Certificates of Expenditures 3 (4)

From: dd.mm.yyyy To: dd.mm.yyyy

Claim No. 0Project PartnersThe Summary of CoE template is a summary of all Certificates of Expenditure (CoE).PLEASE NOTE: All yellow fields together with the scroll lists must be filled in!

Lead partner Partner 2 Partner 3 Partner 4 Partner 5 Partner 6 Partner 7 Partner 8 Partner 9 Partner 10 Partner 11 Partner 12 Partner 13 Partner 14 Partner 15 Partner 16 Partner 17 Partner 18 Partner 19 Partner 20

Type of ExpenditureApproved budget

Fill in LP name Fill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameTotal

expenditure

Country Country Country Country Country Country Country Country Country Country Country Country Country Country Country Country Country Country Country Country 1. Staff costs 0,002. Travel and accomodation 0,003. External experts 0,004. Office costs (directly allocated) 0,005. Office costs (distributed proportionally) 0,006. Promotion / publications, Seminars /conferences, Meetings 0,007. Equipment and supplies 0,008. Other (including 1st level control) 0,009. In kind costs 0,0010. Share of common costs 0,00 0,00Total expenditure 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00Deducted: Received common cost payments 0,00 0,00Deducted: Project revenue 0,00Deducted: In kind costs 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00Total net cost 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00

Lead partner Partner 2 Partner 3 Partner 4 Partner 5 Partner 6 Partner 7 Partner 8 Partner 9 Partner 10 Partner 11 Partner 12 Partner 13 Partner 14 Partner 15 Partner 16 Partner 17 Partner 18 Partner 19 Partner 20

Public financial contributionBudgeted public

matchfunding

Fill in LP name Fill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameFill in partner

nameTotal

contribution,current period

FALSE FALSE FALSE FALSE FALSE FALSE FALSE FALSE FALSE FALSE FALSE FALSE FALSE FALSE FALSE FALSE FALSE FALSE FALSE FALSE

Public match funding, in kind 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00Public match funding, cash 0,00Total public financial contribution 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00

C e r t i f i e d f i n a n c i a l c o n t r i b u t i o n, c u r r e n t r e p o r t i n g p e r i o d

Summary of CoESummary of certified costs and financial contributions

C e r t i f i e d e x p e n d i t u r e, c u r r e n t r e p or t i n g p e r i o d

Choose Choose Choose Choose Choose Choose Choose Choose Choose Choose Choose Choose Choose Choose Choose Choose Choose Choose Choose Choose

Page 35: Claiming procedure, financial report

Project Claim 4 (4)NOTE: Self generated table after completing the Summary of Certificates of Expenditures

Reporting period: From: dd.mm.yyyy To: dd.mm.yyyyProject Claim No.: 0Project Title:Reference number:Priority: Priority 1: Priority 2:

Project Expenditure and Financial contributionsExpenditure and financial contributions sorted by source of financeThis table is self generated from the "Summary of CoE" sheet.

Type of Expenditure Approved budget

MS+NMS

Member States Member State

20% area

Non Member State

10% area

FaroeIslands

Greenland Iceland Norway Norway

20% area

Total expenditure

1. Staff costs 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,002. Travel and accomodation 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,003. External experts 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,004. Office costs (directly allocated) 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,005. Office costs (distributed proportionally) 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,006. Promotion / publications, Seminars /conferences, Meetings 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,007. Equipment and supplies 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,008. Other (including 1st level control) 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,009. In kind costs 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,0010. Share of common costs 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00Total project expenditure 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00Deducted: Received common cost payments 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00Deducted: Project revenue 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00Deducted: In kind costs 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00Total project net cost 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00

Financial contribution

Budgeted matchfunding

MS+NMS

Member States Member State

20% area

Non Member State

10% area

FaroeIslands

Greenland Iceland Norway Norway

20% area

Total financial contribution,

current period

Public match funding, in kind 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00Public match funding, cash 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00Total public financial contribution 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00

Project claimpage 2

C e r t i f i e d e x p e n d i t u r e, c u r r e n t r e p or t i n g p e r i o d

C e r t i f i e d f i n a n c i a l c o n t r i b u t i o n, c u r r e n t r e p o r t i n g p e r i o d

00

Page 36: Claiming procedure, financial report

Desk check errors Wrong expense period on Payment claim

In relation to decision In relation to Certificate of Expenditures

Wrong bank information, IBAN / BIC In relation to application/decision In relation to latest supplied information

Claim signed by person not authorized to sign for the organisation In relation to enclosure 2 of decision In relation to latest supplied information

Faulty Summary of CoE:s page Partner listed on wrong funding source compared to the decision, mostly of the

20% flexibility area Expenditure amounts entered in Summary of CoE:s not corresponding with

Partner CoE. Faulty 2nd page of project claim due to mistakes in Summary of CoE:s page Match funding amounts entered in Summary of CoE:s not corresponding with

Partner CoE:s Costs certified in budget lines that has nothing budgeted for.

Page 37: Claiming procedure, financial report

Desk check errors

Invalid Certificate of Expenditure First Level Controller not approved by National Controller Wrong expense period, expenses approved beyond the claim period Deductions missing from page 3 of CoE Wrong expenditure and match fundin

Amounts in current CoE versus previous CoE, doesn’t correspond.

Insufficient First Level Control Check list All answers not ticked Answers on questions 8-12 “Not checked” or “Not applicable”, without specifying

reason why.

Page 38: Claiming procedure, financial report

Changes in project implementation All changes in project implementation have to be communicated to the Secretariat and need preapproval before becoming eligible (this includes changes in project end date, budget changes and changes in the activity plan). The degree of the change (major or minor) will be determined by the Secretariat:

Rule of thumb:

1. Please describe the change in the budget, activity plan, partnership, project co-ordinator staff, project time period, indicators or other changes to the Secretariat in an e-mail.

2. Justify the need for change3. Describe the impact on project implementation.

Maximum number requests two per year.

Project changes

Page 39: Claiming procedure, financial report

Changes in project implementation Minor changes are:

• A change with no major impact on project implementation and less than 40 000 Euro increase in one project budgetline

• A change of a minor impact is approved in regular correspondence between the Lead Partner and the Secretariat, i.e request and answer by e-mail.

• All changes are to be listed in the project activity report and should confirm the picture that the changes are of a minor degree when being described in its full context.

Major changes are:

• A change with a major impact on the projects implementation or more than 40 000 Euro increase in one project budgetline

• A change with a major impact normally requires a formal request in a specific template and the Secretariat will provide information on how to make that request.

• Different bodies can be responsible for approving the change (Managing Authority and Programme Monitoring Committee)

Major changes on the overall project can normally only be allowed once during the project lifetime .

Project changes

Page 40: Claiming procedure, financial report

Budget changes template

Page 41: Claiming procedure, financial report
Page 42: Claiming procedure, financial report

What happens after your project submission