city of alexandria, va - riverrenew update to the ...alexandria renew enterprises, with support from...
TRANSCRIPT
RiverRenew Update to the
Waterfront Commission
May 21, 2019
RiverRenew is a program owned and implemented by
Alexandria Renew Enterprises, with support from the
City of Alexandria.
1800 Limerick Street | Alexandria, VA 22314
2
• RiverRenew Program Snapshot
• Outfall 001 Diversion Facility as presented in Development
Special Use Permit #2018-0020
• Outfall 001 Construction Sequence Example
• Outfall 001 Conceptual Restoration Plans
• Potential Haul Routes and Rates during Construction
Presentation Outline
RiverRenew Program Snapshot
4
RiverRenew Program Snapshot May 2019
Major Components:
► Proposed Work in Alexandria
• Tunnel System to capture flows from Outfalls 001-004
► Proposed Work at AlexRenew
• Tunnel Dewatering Pumping Station and Superstructure
• Increase of peak primary pumping capacity
• Lab relocation and administrative building demolition
• Wet Weather Treatment Facility
• Site security and gate access
Estimated Capital Cost at Construction Midpoint:
• $370M - $555M (conceptual level of design)
Schedule:
• Tunnel System: Dec 2020 – July 2025
• Work at AlexRenew: July 2019 – March 2021
More information:
• riverrenew.com
Outfall 002
Outfall 004(current location)
AlexRenew
Old Town
Alexandria
Outfall 003
Outfall 001
LEGEND
Shaft & Diversion Chamber
Existing Outfall
Pumping Station Shaft
Diversion Chamber
12’ Diameter Waterfront Tunnel
6’ Diameter Hooffs Run Tunnel
Historic District
N
Technically Preferred Alternative for the Tunnel System. Note that the selection of the
final alignment will be accomplished through the Environmental Assessment process.
5
Diversion Chambers & Drop Shafts
(at existing outfall locations)Hooffs Run Tunnel (open-cut) Waterfront TunnelPumping Station
Major Tunnel System Components to be Constructed
6
ACTIVITY2018 2019 2020 2021
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Environmental Assessment (EA)
Draft Development
NPS Review
Public Comment and Listening Sessions
NPS Issues Decision Document
Tunnel System DSUP
Planning Commission Meeting
City Council Hearing, Issue DSUP
Tunnel Pumping Station DSUP
Planning Commission Meeting
City Council Hearing, Issue DSUP
Procurement (Fixed Price Design-Build)
Request for Qualifications (RFQ)
Request for Proposal (RFP) Development
Meetings with Design-Build Team
Notice to Proceed (NTP)
Construction
RiverRenew Tunnel System Permit and Procurement Schedule
Issue RFQ (Jun 2019)
NPS Issues EA (June 2019)
NPS Issues Decision Document (Jul 2019)
Submit Draft EA (Mar 2019)
Issue RFP (Feb 2020)
Proposals Due (Aug 2020)
June 2019
7/9/19
6/25/19
Shortlist (Oct 2019)
NTP (Dec 2020)
DSUP Development and Coordination with City Regulatory Team
Environmental Assessment
DSUP
Procurement
Current Quarter
Milestone
Construction
Legend:
DSUP: Development Special Use Permit
DSUP Development and Coordination with City Regulatory Team
9/14/19
9/3/19
Subject to NPS Schedule
Outfall 001 Diversion Facility as Presented in DSUP #2018-0020
8
Outfall 001 Existing Conditions
36” Potomac InterceptorOutfall 001 and Regulator
Flow to AlexRenew
Oronoco Bay
Founders Park
Oronoco Bay Park
Potomac River
84” × 72” Combined Sewer
N
Potomac River
9
Outfall 001 Diversion Facility Alternatives in DSUP #2018-0020
Robinson Terminal North Oronoco Bay Park East
Technically Preferred Alternative. Note that the selection of the final alternative will
be accomplished through the Environmental Assessment process.
Drop Shaft
Outfall 001Extension
Diversion Chamber
Waterfront Tunnel
N U
nio
n S
t
Pendleton St
Oronoco Bay
N
N U
nio
n S
t
Drop Shaft
Outfall 001
Extension
Waterfront Tunnel
Pendleton St
Po
tom
ac R
ive
r
Oronoco Bay
Diversion Chamber
Oronoco Bay Park
Construction Staging Area
Re
sid
en
tia
l B
uild
ing N
Po
tom
ac R
ive
r
Construction Staging Area
Existing Outfall
001
Existing Outfall
001
Outfall 001 Construction Sequence Example
11
Phase 1: Site Mobilization3 months
12
Phase 2: Cofferdam Installation8 months
Sheet pile installation
Finished sheet pile wall
Work within sheet pile wall
Braced sheet pile wall
Sheet pile hammer
13
Phase 3: Shaft Construction10 months
Shaft excavation support installation
Shaft excavation
14
Phase 4: Near Surface Structures9 months
Reinforcing installation
Excavation support and flume Concrete formwork and pours
Equipment installation (where necessary)
15
Phase 5: Tunnel Boring Machine Removal & Shaft Fit-out4 months
Shaft internal concrete (lower shaft)
TBM removal Shaft internal concrete (upper shaft)
Shaft cover and backfill
16
Phase 6: Site Restoration2 months
Outfall 001 Conceptual Restoration Plans
18
Illustrative Renderings of Outfall 001 Diversion Facility RestorationRobinson Terminal North Alternative
Rendering, looking west at Robinson Terminal North
Illustrative Landscaping PlanRendering, looking east at Robinson Terminal North
Technically Preferred Alternative. Note that the selection of the final alternative will be
accomplished through the Environmental Assessment process.
19
Illustrative Landscaping Plan
Rendering, looking south from Oronoco Bay
Illustrative Renderings of Outfall 001 Diversion Facility RestorationOronoco Bay Park East Alternative
Technically Preferred Alternative. Note that the selection
of the final alternative will be accomplished through the
Environmental Assessment process.
Potential Haul Routes andRates during Construction
21
Existing Traffic Volumes near Construction Sites
Existing = 1,400 vehicles/day
Existing = 1,300 vehicles/day
N
Existing = 19,000 vehicles/day
Outfall 002 Site
Outfall 001 Site
Outfalls 003/4 Site
Counts collected in January 2019. Reported values are totals between the hours of 7AM-6PM
WRRF Site
Existing = 17,000 vehicles/day*
*Annual Average Daily Traffic for Eisenhower Avenue from 2017 VDOT Special Locality Report 100 (Alexandria)
22
Proposed Haul Routes for All Construction Sites
Line Site1 Truck
Every
001 9 mins
002 11 mins
003/4 16 mins
WRRF 5 mins
Shared 5 mins
PEAK RATE
Outfall 002 Site
Outfall 001 Site
Outfalls 003/4 Site
WRRF Site
N
Assumes 7AM-6PM Work Hours
23
Estimated Outfall 001 Trucks per Day during Construction
0
10
20
30
40
50
60
70
80
90
Esti
ma
ted
Tru
ck
s p
er
Da
y
Total
Soil
Materials
Dirty Soil
RiverRenew Average = 39 trucks/day
(3% of existing traffic volume)
RiverRenew Peak = 78 trucks/day
(6% of existing traffic volume)
24
Estimated Outfall 003/4 and WRRF Trucks per Day during Construction
0
20
40
60
80
100
120
140
160
180
Esti
ma
ted
Tru
ck
s p
er
Da
y
Total
Soil
Materials
Dirty Soil
RiverRenew Average =
35 trucks/day (0.2% of
existing traffic volume)
RiverRenew Peak = 166
trucks/day (1% of existing traffic
volume)
25
Potential Construction Practices for Soil Containment
Tarping Street SweepingWheel Wash Hauling Inspector
26
Comparison of Outfall 001 Diversion Facility Soil Volumes to Other Approved Alexandria Waterfront Projects
Outfall 001 Diversion Facility
20,000 CY excavated soil
Robinson Terminal North
68,000 CY excavated soil + 17,000 CY
imported soils = 85,000 CY
Robinson Landing
55,000 CY excavated soil + 15,000
imported soil = 70,000 CY
CY = Cubic Yards
27
Questions?