chhattisgarh state electricity regulatory commission 1 of 24 petition no. 78 of 2013(d) in the...
TRANSCRIPT
Page 1 of 24
Petition No. 78 of 2013(D)
In the Matter of
Petition under Regulation 13.6 of the State Electricity Grid
Code, 2011
M/s Godawari Power & Ispat Ltd.,
Siltara, Raipur …. Petitioner
Versus
1. Chhattisgarh State Power Transmission
Co. Ltd., Daganiya, Raipur (C.G.)
2. Chhattisgarh State Power Distribution
Co. Ltd., Daganiya, Raipur (C.G.)
3. M/s Jagdamba Power & Alloys Ltd.,
Raipur (C.G.) …. Respondents
Present: Narayan Singh, Chairman
Vinod Shrivastava, Member
ORDER
(Passed on 11.09.2014)
1. The petitioner herein, M/s Godawari Power & Ispat Ltd. is an
Integrated Steel Plant situated in Siltara Industrial Area,
Raipur comprising of manufacturing facilities for Sponge Iron
(DRI), MS Billets, Ferro Alloys and MS Wires. The petitioner
has also set up power generation facility of 73 MW.
2. The petitioner is a 'captive generating plant' within the
meaning of section 2(8) of the Electricity Act, 2003 with zero
Chhattisgarh State Electricity Regulatory Commission Shanti Nagar, Irrigation Colony, Raipur - 492 001 (C.G.)
Ph. 0771-4048788, Fax: 2445857 Website: www.cserc.gov.in, E-mail: [email protected]
Page 2 of 24
contract demand and is presently connected through the 132
KV DCSS dedicated feeder (constructed by the petitioner)
with the 220/132 KV Siltara sub-station of the respondent.
3. The Respondent, Chhattisgarh State Power Transmission Co.
Ltd. (hereinafter referred to as 'CSPTCL'), is a deemed
licensee (STU) within the meaning of section 14 of the
Electricity Act, 2003.
4. The instant petition is filed by the petitioner under Regulation
13.6 of the Chhattisgarh State Electricity Grid Code, 2011
("Grid Code"), seeking relaxation from the Commission from
complying with the provisions of Regulation 4.2.1 and
Regulation 4.2.2 of the Grid Code.
5. As per petitioner, he is intending to avail the entire quantum
of 25 MW electricity generated by one of its group companies
i.e. M/s Jagdamba Power & Alloys Ltd. ("JPAL"), located near
to the petitioner for captive use. It is submitted that the
petitioner is holding ownership of 26.06% equity in JPAL, and
is thus a captive consumer of JPAL, subject to fulfillment of
51% consumption norm in terms of Rule 3 of the Electricity
Rules, 2005.
6. As per the petitioner, in order to avail the 25 MW power from
JPAL, the petitioner has written to the respondent STU,
requesting that JPAL be disconnected from the grid sub-
station and the power generated by JPAL be transmitted to
Page 3 of 24
the petitioner through the vacant second circuit of existing
132 KV dedicated line constructed by the petitioner. However,
the respondent has orally informed the petitioner that the
transmission of power of JPAL through the vacant second
circuit of existing 132 KV dedicated line to the petitioner is not
possible as the respondent has already planned to utilize the
vacant second circuit for its own purpose and for which
necessary steps have already been initiated.
7. Further, considering the above and also that the petitioner
and JPAL are located in different directions of same industrial
area and the option of laying a dedicated line between the
two plants is practically not possible, hence, the petitioner has
no other option but to seek approval for tapping of line of
JPAL with petitioner's existing 132 KV line. As per Regulation
4.2.1, Note 2, the licensee may, under special circumstances,
consider any deviation from the prescribed quantum for
injection of power to the state grid with reference to voltage
of injection, subject to technical feasibility and specific
approval by the Commission, and further subject to fulfillment
of minimum technical requirement of meter as specified in
Regulation 8.6 of the Grid Code. In the instant case, though it
may appear at first that the petitioner's installed capacity is
higher than the prescribed permissible limits on 132 KV i.e.
upto 75 MVA for single circuit, transmission of power on the
proposed tapped line will never exceed the permissible limit
Page 4 of 24
due to limitation of its transformer capacity. As such, the
Commission may consider relaxation of the above norm in
view of the special circumstances of the instant case and non
availability of vacant second circuit.
8. The petitioner further submitted that as per provisions of
Regulation 4.2.4 of the Grid Code, the Commission is
competent to consider the connectivity as proposed by the
petitioner for availing the 25 MW electricity of JPAL for captive
use, as a special case on account of the fact that laying down
of dedicated line between the two plants is impractical and
also because the vacant second circuit of the 132 KV
dedicated line is not available.
9. As per petitioner, the erstwhile CSEB has sanctioned for
construction of 1 No. of 132 KV bay at 220/132 KV sub-
station Siltara, for 132 KV DCSS line, so that the petitioner
could avail dedicated connectivity with the grid. After
depositing an amount of Rs. 1,01,52,575/- with CSEB for
execution of the above work.
10. Now, the petitioner has planned to expand its Steel Melting
Shop requiring an additional power of approximately 25 MW.
The petitioner's group company i.e. JPAL which is an
independent power plant is also having dedicated connectivity
on 132 KV with 220/132 KV S/s Siltara with installed capacity
Page 5 of 24
of 25 MW and injecting power with the grid for third party
sale.
11. In order to fulfill the requirement of consumption of 51%
power from JPAL so that the petitioner may qualify as a
'captive user', the petitioner vide letter dated 14.11.2013
requested for permission from the respondent to synchronize
the captive generators of the petitioner with that of JPAL
through the vacant second circuit of the existing 132 KV
dedicated line constructed by the petitioner. The petitioner
proposed that JPAL be disconnected from the substation / grid
and the power generated by JPAL be transmitted to the
petitioner through the vacant second circuit of existing 132
KV dedicated line constructed by the petitioner. It is also
submitted that the said proposal is within the tenets of the
Grid Code as well as the petitioner's legal right to use the
power of its group company i.e. JPAL, for captive use, as per
Rule 3 of the Electricity Rules, 2005. However, no favorable
consideration of the aforesaid proposal has been received by
the petitioner from the respondent till date.
12. In view of the above, following peculiar circumstances arise in
the instant case which require consideration of the
Commission:
(a) The petitioner can lawfully use the power of its group
company i.e. JPAL for captive use;
Page 6 of 24
(b) Ordinarily the petitioner could have and would have
used the power of JPAL by transmitting the same
through the vacant second circuit of existing 132 KV
dedicated line constructed by the petitioner and paid for
by the petitioner;
(c) However, the transmission licensee apparently requires
the same for its own purpose; and
(d) The petitioner and JPAL are located in different
directions of same industrial area and the option of
laying a dedicated line between the two plants is
practically impossible.
13. That having no other alternative available and having
analyzed all available options, the petitioner submits the
instant petition seeking relaxation from the Commission in the
provisions of the Grid Code in relation to line loading limits
and mode of connectivity.
14. Petitioner in its rejoinder dated 19.02.2014 has also
submitted that the above position has been further clarified
by the Hon'ble Tribunal in Appeal No. 16 of 2013 vide
judgment dated 13.01.2014. The relevant portion is as
under:-
"17. As pointed out by the learned Counsel for the Appellant
in view of the above judgment, it is now settled position that
a common evacuation system / transmission line can be built
Page 7 of 24
for more than one generating station without obtaining a
transmission license.
Xxxxxxxxxxx
25. That apart, the dedicated transmission lines as defined
under the Act contemplate the same to connect two
generating stations.
26. The definition of the term 'dedicated transmission lines'
under the Electricity Act, 2003 is extracted below:
2(16) "Dedicated Transmission Lines" means any
electric supply line for point to point transmission which
are required for the purpose of connecting electric lines
or electric plants of a captive generating plant referred
to in Section 9 or generating station referred to in
Section 10 to any transmission lines or sub stations or
generating stations or the load centre, as the case may
be."
27. The reading of the above definition would make it clear
that merely because a transmission line connects two
generating stations, it does not lose the character of a
dedicated transmission line.
XXXXXXXXXXX
58. The next question is as follows: If two generating
stations can make use of a common evacuation system,
consisting of dedicated transmission lines, whether the
metering system and the energy computation formula
proposed by the Appellant and endorsed by Power Grid could
be utilized for accounting among the two systems?
XXXXXXXXXX"
Page 8 of 24
15. In reply to the petition, the Respondent CSPTCL submitted
that at present M/s Godawri Power & Ispat Limited (herein
Petitioner) & M/s Jagdamba Power & Alloys Limited (JPAL) are
having connectivity with 220 KV substation Siltara through
132 KV independent & dedicated 132 KV DCSS lines.
16. The 132 KV DCSS dedicated line meant for Petitioner from
220 KV Substation Siltara to Petitioner premises was
constructed by erstwhile CSEB under deposit scheme and this
circuit was charged on 04.09.2007.
17. Similarly, the 132KV DCSS dedicated line from 220 KV
Substation Siltara to JPAL premises was constructed by
erstwhile CSEB under deposit scheme and this circuit was
charged on 10.03.2007.
18. The aforesaid connectivity arrangements of Petitioner and M/s
JPAL from 220 KV substation Siltara on 132 KV through
independent dedicated 132 KV feeder was made for
complying to the provisions of the Electricity Act, 2003.
19. As per CSEGC, the generators are to be connected through
dedicated feeder with the grid substation and metering
arrangements are provided that is in line with the CEA
Metering Code.
20. Dedicated line so constructed under deposit scheme shall be
the property of the licensee and can be utilized by him after
Page 9 of 24
expiry of two years from the date of connection under the
provisions of prevailing Supply Code-2005 regulation 5.3.
21. The respondent has highlighted clause 4.2.1 & 4.2.2 of State
Grid Code-2011, which are as follows:-
Clause 4.2.1: Generating Stations: The voltages at which a
generating station may be connected with the grid of transmission
or distribution license (as applicable) can be 400, 220, 132 or 33
KV. The connection point/interface point shall be the point at the
sub-station of the licensee system where power is injected. The
metering point shall be at the connection point/interface point.
Following are the prescribed quantum for injection of power to the
state grid with reference to voltage of injection:-
S.N. Voltage of injection
Maximum Quantum of power that can be injected into grid
1 33 KV Up to 15 MVA
2 132 KV Up to 75 MVA for single circuit and 150 MVA for double circuit
3 220 KV Up to 200 MVA for single circuit and 400
MVA for double circuit
Note :-
1. For arriving at the quantum of power to be injected in MVA,
power factor as indicated in the nameplate or the design
details of the generator will be taken into account.
2. Under special circumstances, any deviation from the above
limits may be considered by the license subject to technical
feasibility and specific approval by the Commission. Subject
to fulfillment of minimum technical requirement of meter as
specified at clause no. 8.6 of this code.
3. Provision for redundancy in dedicated transmission line shall
be the responsibility of generator concerned.
Page 10 of 24
Clause 4.2.2 : All the generating stations including captive
generating plants (CGP) having Injection and/or drawal
requirements of more than 15 MVA shall have connectivity with the
grid under either of the following modes, at their own cost, subject
to technical feasibility:-
1. At nearest EHV sub-station through dedicated EHV
transmission line.
2. At pooled/switching/load catering/step up EHV sub-station
with dedicated EHV transmission line.
3. No tap connectivity at EHV line shall be allowed.
22. Further clause 4.2.4 of State Grid Code-2011 says "All the
existing generators including CGPs connected with the grid
under any modes other than prescribed at clause 4.2.2 and
4.2.3 shall have to ensure connectivity with the grid as per
prescribed options given in Clause 4.2.2/4.2.3 failing which
their connectivity shall be liable for disconnection from the
grid. However, Commission may allow such connection for
Certain Period on request of the Intra-state user as a special
case on compelling reasons."
23. On going through the clause 4.2.2 of State Grid Code, it is
evident that connectivity of intra state user whether IPP/CPP
with the grid of the transmission licensee will be at EHV
substations through dedicated EHV lines or at pooled /
switching / load catering/ step up EHV sub-station and no tap
connectivity at EHV line shall be allowed.
24. Second circuit of 132 KV dedicated line meant for petitioner
connectivity is being used by the respondent for system
Page 11 of 24
improvement work as approved by the Commission under
capital investment plan and hence cannot be spared to
petitioner for providing connectivity with JPAL.
25. In present scenario, as far as connectivity to Petitioner is
concerned, they are having grid connectivity with respondent
grid on 132 KV through 132 KV dedicated transmission line &
also for M/s JPAL, they are having independent grid
connectivity from respondent grid, and the petitioner can opt
open access for transfer of power for its own use as per the
provisions of the CSERC (Connectivity & intra State Open
Access) Regulations-2011.
26. The manner in which Petitioner has sought captive user status
of M/s JPAL under clause 3 of Electricity Rule 2005 by tapping
M/s JPAL generator on 132 KV dedicated line meant for
Petitioner is not permissible under any Act / Regulations.
Tapped connectivity of a generator (herein M/s JPAL) in to a
dedicated line meant for another captive consumer (herein
Petitioner) to fulfillment the criteria of captive user is against
the provision of EA-2003, Electricity Rule 2005 and the
prevailing CSEGC which is in consistent with the IEGC as per
the section 86(1) (h) of the EA-2003.
27. Definition of captive user as defined in electricity Rule 2005 is
"shall mean the end user of the electricity generated in
Page 12 of 24
Captive Generating Plant and he term captive use" shall be
construed accordingly.
28. Petitioner is a CPP having own captive generation & captive
load cannot be termed as captive consumer of another
generator (herein M/s JPAL) under the ambit of clause 3 of
Electricity Rule 2005.
29. In the past Hon'ble commission through Suo-Motu motion
under petition No. 21/2009 (M) had regularized dedicated
connectivity with respondent grid substations of several
IPP/CPPs having tapped connectivity with grid after serving
notices to the generators, Transmission & Distribution
licensee.
30. Further relaxation as desired by the Petitioner in Grid Code-
2011 clause 4.2.2 can be permitted for certain period as a
special case. However, future planning to maintain
connectivity as per the provision of clause 4.2.2 by Petitioner
is missing in the instant petition. There is no provision for
permanent relaxation in Grid Code 2011 clause 4.2.2. In view
of it, the call of the petitioner is misleading and undefined.
31. Regarding granting relaxation in provisions of clause 4.2.1 i.e.
maximum power which can be injected by IPP/CPP in to the
grid on 132 KV that is 75 MVA per circuit, Petitioner in its
petition has highlighted action plan to limit their injection of
power in to the grid from their total capacity of generators i.e.
Page 13 of 24
110 MW or 137 MVA and otherwise drawal from grid to meet
out their load (about 102 MW) which is a subject matter of
State Supply Code under the desired connectivity
arrangement under various contingencies like outage of load
& failure of generators respectively. Respondent states that
according to the technical standards of the CEA and the
provision in the Grid code a single Circuit 132 KV line is
sufficient only for 75 MVA, and the petitioner's proposal will
breach the aforesaid provision and endanger grid security.
32. Connectivity arrangement as desired by petitioner may lead
ambiguity while deciding the captive status of generators by
this Commission.
33. The petitioner themselves have admitted that they have
supply agreement with distribution licensee CSPDCL upto
01.10.2008. However, they do not intend to avail any
contract demand from CSPDCL even in future and this line is
primarily used for the purpose of evacuation of power. This
version of petitioner is incorrect and misleading. Recently
before filing the instant petition they have requested CSPDCL
for enhancement of CD from zero (0) to 4000 KVA.
34. Petitioner's submission about Hon'ble APTEL judgments dated
02.01.2013 and 13.01.2014 on appeal No. 81/2011 and No.
16/2013 respectively to justify their proposed connectivity
arrangement in the instant petition is not appropriate without
Page 14 of 24
considering the connectivity conditions of generators in the
above said appeals. In both the appeals various issues
involved were discussed in related with utilization of common
transmission corridor in order to have connectivity with CTU
of two generators. Whereas, In this case tapping of one
generator with the dedicated line of other CPP is proposed,
which is not in order.
35. Therefore, proposed connectivity arrangement in the instant
petition between two generators is not acceptable as it is not
permitted under any regulations or grid code. Further
relaxation as desired by the petitioner in Grid Code 2011
clause 4.2.2 can be permitted for certain period as a special
case, but future planning to maintain connectivity as per the
provisions of clause 4.2.2 by petitioner is missing. There is no
provision of permanent relaxation of clause 4.2.2 of the Grid
Code 2011.
36. In the desire connectivity arrangement under the ambit of
Rule 3 of Electricity Rule 2005, metering for the purpose of
power drawal from CSPDCL, meters will be installed at
respective bus of generator / CPP i.e. M/s GPIL & M/s JPAL.
When power is drawn by petitioner from M/s JPAL it will be
recorded in the import register of CSPDCL's meter installed at
M/s GPIL end. Similarly in case of power drawn by M/s JPAL
from M/s GPIL, it will be recorded in the import register of
Page 15 of 24
CSPDCL's meter installed at M/s JPAL. This may lead to
various complication in energy accounting.
37. Respondent No. 2 Chhattisgarh State Power Distribution Co.
Ltd. (CSPDCL) in thier submission dated 08.07.2014 have
pointed out that as per Clause 4.2.2 all the generating
stations including captive generating plants (CPP) having
injection and / or drawal requirements of more than 15 MVA
shall have connectivity with the grid under either of the
following modes, at their own cost subject to technical
feasibility:
(a) At nearest EHV substation through dedicated EHV
transmission line.
(b) At pooled / switching / load catering / step up at EHV
substation with dedicated EHV transmission line.
(c) No tap connectivity at EHV line shall be allowed.
38. It is very clear that tap connectivity of EHV line has been
prohibited. In the past also the Commission itself had initiated
proceeding under section 142 of the Electricity Act, 2003
against CSPDCL and 20 generators by registering a suo motu
[petition No. 21/2009(M)] for ensuring independent
connectivity by various generators which was not availed by
generators even after 2 years of enactment of State Grid
Code 2007. Thus any relaxation on this count is not
acceptable to anybody including CSPDCL.
Page 16 of 24
39. Thus the option left to the petitioner to avail power of JPAL as
a captive consumer is either through laying a dedicated
transmission line from JPAL to GPIL or through Open Access.
Accordingly, the petitioner may opt either of the feasible
options available for which CSPDCL has no objection.
40. From various submissions made by the petitioner and
respondent, and also arguments made during the hearing of
the petition. The case in brief as emerges is as follows:-
41. M/s Godawari Power Ispat Ltd. has established an integrated
steel plant in the Siltara Industrial Estate, Raipur where he
has also set up power generating plant having capacity 73
MW. The petitioner has availed connectivity with State
Transmission Licensee (CSPTCL) by laying dedicated 132 KV
DCSS line from 220 KV S/s Siltara. The petitioner is availing
the said connectivity with zero (0) contract demand with the
Distribution Licensee of the area.
42. The sister concern of the petitioner M/s Jagdamba Power &
Alloys Ltd. (JPAL) is a generating plant having capacity 25 MW
and is installed in the same industrial area i.e. Siltara, Raipur.
This generating plant is situated in the opposite direction with
that the petitioner. M/s JPAL for injection of power in the
State Grid has also availed dedicated connectivity on 132 KV
through DCSS line with 220 KV S/s Siltara, Raipur.
Page 17 of 24
43. As per the prevailing Supply Code, for availing the said
connectivity by the petitioner and its sister concern M/s JPAL,
the cost of line along with the cost of bay at substation has
been borne by them.
Keeping in view, the proposed expansion in
manufacturing units of the petitioner, he has proposed to
utilize power of M/s JPAL as CPP through vacant second circuit
of 132 KV line laid for his industry from 220 KV S/s Siltara by
disconnecting connection of M/s JPAL from the grid. As the
petitioner is having more than 26% equity share in M/s JPAL
therefore this power plant is a captive power plant, under
Rule 3 of the Electricity Rules, 2005 subject to fulfillment of
more than 51% consumption by the petitioner in a year. This
situation has arisen because M/s JPAL is situated in the
opposite direction of the industrial area where the petitioner
industry is situated and it is very difficult for the petitioner to
lay a dedicated line connecting M/s JPAL.
44. On receipt of request by the respondent CSPTCL, they
intimated the petitioner that 2nd circuit of the line for
providing connectivity to his industry is being utilized for
some other purpose under system improvement scheme and
therefore the respondent is unable to spare the 2nd circuit for
providing connectivity with M/s JPAL. Keeping in view that
respondent is unable to spare 2nd circuit of his line he has
Page 18 of 24
proposed to have direct tapped connectivity of M/s JPAL with
the line connecting his industry with the substation.
45. The petitioner is well aware that tapped connectivity with such
dedicated line is not permitted under various provisions of the
State Grid Code.
46. Let us first see the provisions made in clause 4.2.1, 4.2.2 and
4.2.4 of the Electricity Grid Code, 2011:
"Clause 4.2.1: Generating Stations: The voltages at which a
generating station may be connected with the grid of transmission
or distribution license (as applicable) can be 400, 220, 132 or 33
KV. The connection point/interface point shall be the point at the
sub-station of the licensee system where power is injected. The
metering point shall be at the connection point/interface point.
Following are the prescribed quantum for injection of power to the
state grid with reference to voltage of injection:-
S.N. Voltage of injection
Maximum Quantum of power that can be injected into grid
1 33 KV Up to 15 MVA
2 132 KV Up to 75 MVA for single circuit and 150 MVA for double circuit
3 220 KV Up to 200 MVA for single circuit and 400
MVA for double circuit
Note :-
1. For arriving at the quantum of power to be injected in MVA,
power factor as indicated in the nameplate or the design
details of the generator will be taken into account.
2. Under special circumstances, any deviation from the above
limits may be considered by the license subject to technical
feasibility and specific approval by the Commission. Subject
Page 19 of 24
to fulfillment of minimum technical requirement of meter as
specified at clause no. 8.6 of this code.
3. Provision for redundancy in dedicated transmission line shall
be the responsibility of generator concerned.
Clause 4.2.2 : All the generating stations including captive
generating plants (CGP) having Injection and/or drawal
requirements of more than 15 MVA shall have connectivity with the
grid under either of the following modes, at their own cost, subject
to technical feasibility:-
4. At nearest EHV sub-station through dedicated EHV
transmission line.
5. At pooled/switching/load catering/step up EHV sub-station
with dedicated EHV transmission line.
6. No tap connectivity at EHV line shall be allowed.
Clause 4.2.4: All the existing generators including CGPs
connected with the grid under any modes other than prescribed at
Clause 4.2.2 and 4.2.3 shall have to ensure connectivity with the
grid as per prescribed options given in Clause 4.2.2 / 4.2.3 failing
which their connectivity shall be liable for disconnection from the
grid. However, Commission may allow such connection for certain
period on request of the Intra-state user as a special case on
compelling reasons.
Connectivity through pooling substation will be allowed only if
found technically feasible. The cost of common infrastructure like,
transmission line, switchgear / step up transformer or any other
equipment / infrastructure including the facility for real time data
transfer/communication etc. as the case may be, shall be borne by
the constituent generators/CGP(s) in proportion to their respective
power injection to the grid.
An existing generating plant, presently not covered under clause
4.2.2 and 4.2.3, shall be subject to load-shedding plan of CSPDCL
as and when enforced, till their connectivity is as per clause 4.2.2
or 4.2.3 as the case may be."
Page 20 of 24
47. As per the information furnished in the petition by the
petitioner, it is evident that, finally his total connected load
will reach to 110 MW (85 MW + 25 MW) or 137 MVA, which
will be more than permissible limit of 75 MVA for single circuit
132 KV line, as per the State Grid Code. The petitioner
through its submission made has tried to explain the
modalities which he will be adopting to restrict maximum
transfer of power to the tune of 75 MW only. In his
submission, apart from the difficulties shown in providing
connectivity with M/s JPAL with his industry has expressed his
financial constrain in transfer of power through open access.
Therefore, he has requested the Commission to condone
various provisions of the State Grid Code and permit him to
avail connectivity of M/s JPAL with his industry through
tapped connectivity by isolating the connectivity of M/s JPAL
with the State Grid.
48. On the submission made by the petitioner, respondent
CSPTCL has strongly opposed for permitting tapped
connectivity of M/s JPAL with the dedicated line connecting
the grid with the petitioner industry on the ground that
tapped connectivity of a generator (M/s JPAL) with the
dedicated line meant for another captive user, herein is
petitioner to fulfill the criteria of captive user is against the
provisions of the Electricity Act, 2003, Electricity Rules, 2005
Page 21 of 24
and the prevailing CSEGC which is in consistent with the IEGS
as per the Section 86(1)(h) of the Electricity Act, 2003.
49. Here the petitioner is having its captive power plant. Captive
generation and the captive load cannot be termed as captive
consumption of another generator, as per Clause 3 of the
Electricity Rules, 2005.
In the order passed by this Commission under Suo Motu
P. No. 21/2009(M) has regularized dedicated connectivity with
the grid S/s for several IPP/ CPP which were earlier connected
under tapped connectivity through constant persuasion with
the Generator / Transmission & Distribution Licensees. As per
the State Grid Code, 2011 Clause 4.2.4, The Commission is
permitted to allow transfer of power under tapped
connectivity for certain period as a special case but in the
instant case, the petitioner has not declared his future
planning to remove such tapped connectivity. As per the
Supply Code, transfer of maximum 75 MW is permitted on
132 KV single circuit line but going through the details
furnished by the petitioner, total load that will be connected if
tapped connectivity is permitted will be 110 MW i.e. 137 MVA
which will be violation of the provisions of the Supply Code
and technical standards as laid down by the Central Electricity
Authority and may in danger the grid security.
Page 22 of 24
The connectivity arrangement as requested by the
petitioner may also lead to ambiguity while deciding the
captive status of the generator. In the submission made by
the respondent CSPTCL, it is already clarified that the 2nd
circuit of 132 KV DCSS line is being utilized by them under
system improvement scheme as approved by this
Commission.
50. Petitioner in his various submissions and arguments made
during the hearing highlighted that the DCSS line was
constructed as a dedicated line for his industry for which he
has paid the entire amount, therefore he has got the legal
rights to use the same as on date also.
Here definition of dedicated feeder as defined in clause
4.50 of the prevailing Supply code, is as follows:-
"4.50 Consumers desirous of getting power supply from
dedicated feeder may request for such facility to the licensee. The
dedicated feeder may be extended from the substation to the
consumer’s point of supply. In such cases the consumer shall be
liable to pay the cost of bay and all protection switchgears and its
accessories provided at the substation for this feeder in addition to
the cost of laying of the feeder. On receipt of such request, the
licensee will check the feasibility based on merit of providing a
dedicated feeder to the consumer’s premises. Such dedicated
feeder shall be the property of the licensee and shall be maintained
by the licensee. Such feeder shall not be used to extend supply to
any other consumer within the initial period of two years from the
date of its commissioning without written consent of the consumer
who has paid the cost of line and bay."
Page 23 of 24
From the above, it is amply clear that use of such
dedicated line for other purpose is prohibited till expiry of
initial two years agreement period. Without written consent of
the petitioner, however, in the present case, the two year
period has already over, the transmission licensee can use
such line for other purpose also.
51. The petitioner in his submission has intimated that they are
availing connectivity with the State Grid with zero contract
demand, whereas, as per the documents filed by the
respondent, it shows that recently petitioner has requested
the State Distribution licensee for enhancement of his
contract demand from zero to 4000 KVA, which is under
process. The petitioner plea of Hon'ble ATE on appeal No.
81/2011 & 16/2013 on proposed connectivity arrangement so
far it relates with the instant petition, it is also not correct
because the same stand submitted without considering the
connectivity condition of generator under the said appeals.
Thus it is amply clear that proposed connectivity
arrangements between two generators are not acceptable and
permitted. However, the relaxation as said by the petitioner in
clause 4.2.2 can be permitted for certain period as a special
case but in absence of their planning for independent
connectivity, such permission cannot be granted.
52. For determination of captive status of the petitioner under the
proposed connectivity, metering for the purpose of power to
Page 24 of 24
be drawn from CSPDCL, metering will be done at respective
bus of generator / CPP. In case power is drawn by the
petitioner from M/s JPAL it will be recorded in the import
register of CSPDCL's meter. Similarly, in case, any power is
drawn by M/s JPAL from M/s GPIL, it will be recorded in
import register of CSPDCL's meter installed at M/s JPAL end,
which will lead to complication in energy accounting.
53. Therefore going through the various discussions made in
foregoing para, we are of the considered opinion that
petitioner cannot be permitted for availing tapped connectivity
as proposed by him in his petition. However, he is at the
liberty to avail the power from M/s JPAL through open access
under the prevailing Rules and Regulations or by laying
dedicated line from his industry to M/s JPAL.
We dispose of the petition accordingly.
Sd/-
(Vinod Shrivastava)
MEMBER
Sd/-
(Narayan Singh)
CHAIRMAN