chapter 9.risk and managerial options in capital budgeting
TRANSCRIPT
Capital BudgetingRisk Considerations
Section 1Let’s Recap Capital Budgeting
2
What is Capital Budgeting?
The process of identifying, analyzing, and selecting investment projects whose returns (cash flows) are expected to extend beyond one year;
The examples are;a. New products or expansion of existing products;b. Replacement of existing equipment or buildings;c. Research and development;d. Exploration;
3
The Capital Budgeting Process
Generate investment proposals consistent with the firm’s strategic objectives;
Evaluate projected cash flows;
Select projects based on a value-maximizing acceptance criterion;
Reevaluate implemented investment projects continually and perform post audits for completed projects;
4
Calculating Project Cash Flows
Initial cash outflow is the initial net cash investment;
Interim incremental net cash flows are those net cash flows occurring after the initial cash investment but not including the final period’s cash flow;
Terminal-year incremental net cash flows are the final period’s net cash flow;
5
Project Evaluation: Alternative Methods
Payback Period (PBP) Internal Rate of Return (IRR) Net Present Value (NPV) Profitability Index (PI)
6
Potential Problems Under Mutual Exclusivity Ranking of project proposals may create
contradictory results;a.scale of investment;b.cash flow pattern;c.project life;
7
Section 2An Illustration of Asset Replacement Decision
8
Asset Replacement Example
Kandy Corporation is considering a replacement investment. The machine currently in use was originally purchased two years ago for $65,000. Tax-allowable depreciation is $13,000 per year for five years. The current market value of this machine is $23,000. The new machine being considered would cost $140,000, and require $4,000 shipping cost and $2,000 installation costs. The economic life of the machine is estimated as three years. Tax-allowable depreciation is $70,000 per year for the first two years. If the new machine is acquired, the investments in accounts receivable is expected to increase by $9,000, the inventory by $13,000, and accounts payable by $15,000. The before-tax net operating cash flow is estimated as $120,000 per year for the next three years with the old machine and, $143,000 per year for the next three years with the new machine. The expected resale value of the old and new machines in three years’ time would be
$4,000 and $6,600, respectively. The corporate tax rate is 30%. 9
Asset Replacement Example
Requireda.Calculate the cash flows of proposed replacement project.b.Compute the NPV of the replacement project assuming a discount rate of 6% per annum.c.What is the proposed investment’s IRR?d.Use the computed IRR and NPV results and discuss the project accept / reject decision
10
Asset Replacement Solution
$+Purchase Price of New Asset 140 000+Shipping and Installation 6 000-Proceeds from the sale of old asset 23 000+Tax on sale of old asset*** -4800 +Change in NWC 7000Initial Investment 125 200*Tax Calculation(Sales Price-Book Value)TaxRate=(23000 -(65000-26000))*0.3=(23000-39000)*0.3=-4800
11
Asset Replacement Solution
Operating Cash Flows(New Machine) Year 1 Year 2 Year 3Cash inflow $143 000 $143 000 $143 000Depreciation $70 000 $70 000 0Taxable Basis $73 000 $73 000 $143 000Tax Charge $21 900 $21 900 $42 900Result $121 100 $121 100 $100 100
12
Asset Replacement Solution
Operating Cash Flows(Old Machine) Year 1 Year 2 Year 3Cash inflow $120 000 $120 000 $120 000Depreciation $13 000 $13 000 $13 000Taxable Basis $107 000 $107 000 $107 000Tax Charge $32 100 $32 100 $32 100Result $87 900 $87 900 $87 900
13
Asset Replacement Solution
Incremental Cash Flows(New Machine-Less Old Machine) Year 1 Year 2 Year 3 $ 33 200 $33 200 $12 200
Terminal Year Cash InflowLast Year’s Cash Inflow $12 200-Proceeds from old machine $ 4000+Proceeds from new machine $6600+Tax saving on sale of old machine $1200 -Tax on sale of new machine $180+Recovery of working capital $7000
Total $ 22 820 14
Asset Replacement Solution
Projected Cash Flows0 Year 1 Year 2 Year 3 -$125 200 $ 33 200 $ 33 200 $22 820
NPV=33200/(1+0.06)1+33200/(1+0.06)2+22820/(1+0.06)3-
125200=-$45 171 ✖IRR=-16% which is below 6% ✖
15
Section 3Evaluation of Project Risk
16
An Illustration of Total Risk
ANNUAL CASH FLOWS: YEAR 1PROPOSAL APROPOSAL A
State ProbabilityProbability Cash FlowCash Flow
Deep Recession .05 $ -3,000Mild Recession .25 1,000Normal .40 5,000Minor Boom .25 9,000Major Boom .05 13,000
17
An Illustration of Total Risk
ANNUAL CASH FLOWS: YEAR 1PROPOSAL BPROPOSAL B
State ProbabilityProbability Cash FlowCash Flow
Deep Recession .05 $ -1,000Mild Recession .25 2,000Normal .40 5,000Minor Boom .25 8,000Major Boom .05 11,000
18
CFCF11 PP11 (CFCF11)(P)(P11))
$ -3,000 .05 $ -150 1,000 .25 250 5,000 .40 2,000 9,000 .25 2,250 13,000 .05 650
=1.001.00 CFCF11=$5,000$5,000
Expected Value of Year 1 Cash Flows (Proposal A)
19
(CFCF11)(P)(P11)) (CF (CF11 - CF - CF11))22(P(P11) )
$ -150 ( -3,000 - 5,000)22 (.05) (.05) 250 ( 1,000 - 5,000)22 (.25) (.25) 2,000 ( 5,000 - 5,000)22 (.40) (.40) 2,250 ( 9,000 - 5,000)22 (.25) (.25) 650 (13,000 - 5,000)22 (.05) (.05)
$ 5,000$ 5,000
Variance of Year 1 Cash Flows (Proposal A)
20
Variance of Year 1 Cash Flows (Proposal A)
(CFCF11)(P)(P11)) (CF (CF11 - CF - CF11))22*(P*(P11) )
$ -150 3,200,000 250 4,000,000 2,000 0 2,250 4,000,000 650 3,200,000
$5,000$5,000 14,400,00014,400,000
21
Summary of Proposal A
The standard deviation standard deviation = SQRT (14,400,000) = $3,795$3,795
The expected cash flow expected cash flow = $5,000$5,000
Coefficient of Variation (CV) = $3,795 / $5,000 Coefficient of Variation (CV) = $3,795 / $5,000 = = 0.7590.759
CV is a measure of CV is a measure of relativerelative risk risk and is the ratio of and is the ratio of standard deviation to the mean of the distribution.standard deviation to the mean of the distribution.
22
Expected Value of Year 1 Cash Flows (Proposal B)
CFCF11 PP11 (CFCF11)(P)(P11))
$ -1,000 .05 $ -50 2,000 .25 500 5,000 .40 2,000 8,000 .25 2,000 11,000 .05 550
=1.001.00 CFCF11=$5,000$5,00023
(CFCF11)(P)(P11)) (CF(CF11 - CF - CF11))22(P(P11))
$ -50 ( -1,000 - 5,000)22 (.05) (.05) 500 ( 2,000 - 5,000)22 (.25) (.25) 2,000 ( 5,000 - 5,000)22 (.40) (.40) 2,000 ( 8,000 - 5,000)22 (.25) (.25) 550 (11,000 - 5,000)22 (.05) (.05)
$5,000$5,000
Variance of Year 1 Cash Flows (Proposal B)
24
Variance of Year 1 Cash Flows (Proposal B)
(CFCF11)(P)(P11)) (CF (CF11 - CF - CF11))22(P(P11))
$ -50 1,800,000 500 2,250,000 2,000 0 2,000 2,250,000 550 1,800,000
$5,000$5,000 8,100,000 8,100,000 25
Summary of Proposal B
The standard deviation of B < A ($2,846< $3,795), so B < A ($2,846< $3,795), so ““BB”” is is lessless risky than risky than ““AA””..
The coefficient of variation of B < A (0.569<0.759), so The coefficient of variation of B < A (0.569<0.759), so ““BB”” has has lessless relative risk than relative risk than ““AA””..
The standard deviation standard deviation = SQRT (8,100,000)= $2,846$2,846
The expected cash flow expected cash flow = $5,000$5,000Coefficient of Variation (CV) = $2,846 / $5,000 Coefficient of Variation (CV) = $2,846 / $5,000
= 0.569= 0.569
26
Probability Tree Approach
A graphic or tabular approach for organizing the possible cash-flow
streams generated by an investment. The presentation resembles the
branches of a tree. Each complete branch represents one possible cash-
flow sequence.27
Probability Tree Approach
Basket Wonders is examining a project that will have an initial initial
cost cost today of $900$900. Uncertainty surrounding the first year cash
flows creates three possible cash-flow scenarios in Year 1Year 1.
-$900-$900
28
Probability Tree Approach
Node 1: 20% chance of a $1,200$1,200 cash-flow.
Node 2: 60% chance of a $450$450 cash-flow.
Node 3: 20% chance of a -$600-$600 cash-flow.
-$900-$900
(.20) $1,200$1,200
(.20) -$600-$600
(.60) $450$450
Year 1Year 1
11
22
33
29
Probability Tree Approach
Each node in Year 2 Year 2
represents a branchbranch of our
probability tree.
The probabilities
are said to be conditional conditional
probabilitiesprobabilities.
-$900-$900
(.20.20) $1,200$1,200
(.20.20) -$600-$600
(.6060) $450$450
Year 1Year 1
22
33
(.60) $1,200$1,200
(.30) $ 900$ 900
(.10) $2,200$2,200
(.35) $ 900$ 900
(.40) $ 600$ 600
(.25) $ 300 $ 300
(.10) $ 500$ 500
(.50) -$ 100-$ 100
(.40) -$ 700-$ 700
Year 2Year 2 30
Joint Probabilities [P(1,2)].02 Branch 1.12 Branch 2.06 Branch 3
.21 Branch 4
.24 Branch 5
.15 Branch 6
.02 Branch 7
.10 Branch 8
.08 Branch 9
-$900-$900
(.20.20) $1,200$1,200
(.20.20) -$600-$600
(.6060) $450$450
Year 1Year 1
11
22
33
(.60) $1,200
(.30) $ 900$ 900
(.10) $2,200$2,200
(.35) $ 900$ 900
(.40) $ 600$ 600
(.25) $ 300 $ 300
(.10) $ 500$ 500
(.50) -$ 100-$ 100
(.40) -$ 700-$ 700
Year 2Year 2 31
Project NPV Based on Probability Tree Usage
The probability tree accounts for the distribution of
cash flows. Therefore,
discount all cash flows at only the risk-freerisk-free rate of
return.
The NPV for branch i NPV for branch i of the probability tree for two years
of cash flows is
NPV = (NPVNPVii)(PPii)
NPVNPVii = CFCF11
(1 + RRff )11 (1 + RRff )22
CFCF22
- ICOICO
+
i = 1
z
32
NPV for Each Cash-Flow Stream at 5% Risk-Free Rate
$ 2,238.32 $ 1,331.29 $ 1,059.18
$ 344.90 $ 72.79-$ 199.32
-$ 1,017.91-$ 1,562.13-$ 2,106.35
-$900-$900
(.20.20) $1,200$1,200
(.20.20) -$600-$600
(.6060) $450$450
Year 1Year 1
11
22
33
(.60) $1,200$1,200
(.30) $ 900$ 900
(.10) $2,200$2,200
(.35) $ 900$ 900
(.40) $ 600$ 600
(.25) $ 300 $ 300
(.10) $ 500$ 500
(.50) -$ 100-$ 100
(.40) -$ 700-$ 700
Year 2Year 2 33
Calculating the Expected Net Present Value (NPV) Branch NPV NPVii
Branch 1 $ 2,238.32Branch 2 $ 1,331.29Branch 3 $ 1,059.18Branch 4 $ 344.90Branch 5 $ 72.79Branch 6 -$ 199.32Branch 7 -$ 1,017.91Branch 8 -$ 1,562.13Branch 9 -$ 2,106.35
P(1,2) P(1,2) NPVNPVii * P(1,2) P(1,2) .02 $ 44.77 .12 $159.75 .06 $ 63.55 .21 $ 72.43 .24 $ 17.47 .15 -$ 29.90 .02 -$ 20.36 .10 -$156.21 .08 -$168.51
Expected Net Present Value Expected Net Present Value = -$ 17.01-$ 17.0134
Calculating the Variance of the Net Present Value NPVNPVii
$ 2,238.32 $ 1,331.29 $ 1,059.18 $ 344.90 $ 72.79-$ 199.32-$ 1,017.91-$ 1,562.13-$ 2,106.35
P(1,2) P(1,2) (NPV(NPVii - NPVNPV )2[P(1,2)P(1,2)] .02 $ 101,730.27 .12 $ 218,149.55 .06 $ 69,491.09 .21 $ 27,505.56 .24 $ 1,935.37 .15 $ 4,985.54 .02 $ 20,036.02 .10 $ 238,739.58 .08 $ 349,227.33
Variance Variance = $1,031,800.31$1,031,800.3135
Section 3 Managerial Options
36
Managerial (Real) Options
Management flexibility to make future decisions that affect a project’s
expected cash flows, life, or future acceptance.
Project Worth = NPV + Option(s) Value
37
Managerial (Real) OptionsExpand (or contract)Expand (or contract)
– Allows the firm to expand (contract) production if conditions become favorable (unfavorable).
AbandonAbandon– Allows the project to be terminated early.
PostponePostpone– Allows the firm to delay undertaking a project
(reduces uncertainty via new information).38
Previous Example with Project Abandonment
Assume that this project can be abandoned at the end of the first year
for $200$200.
What is the project worthproject worth?
-$900-$900
(.20.20) $1,200$1,200
(.20.20) -$600-$600
(.6060) $450$450
Year 1Year 1
11
22
33
(.60) $1,200$1,200
(.30) $ 900$ 900
(.10) $2,200$2,200
(.35) $ 900$ 900
(.40) $ 600$ 600
(.25) $ 300 $ 300
(.10) $ 500$ 500
(.50) -$ 100-$ 100
(.40) -$ 700-$ 700
Year 2Year 2 39
Project AbandonmentNode 3Node 3:
(500500/1.05)(.1)+ (-100-100/1.05)(.5)+ (-700-700/1.05)(.4)=
($476.19)(.1)+ -($ 95.24)(.5)+ -($666.67)(.4)=
-($266.67)-($266.67)
-$900-$900
(.20.20) $1,200$1,200
(.20.20) -$600-$600
(.6060) $450$450
Year 1Year 1
11
22
33
(.60) $1,200$1,200
(.30) $ 900$ 900
(.10) $2,200$2,200
(.35) $ 900$ 900
(.40) $ 600$ 600
(.25) $ 300 $ 300
(.10) $ 500$ 500
(.50) -$ 100-$ 100
(.40) -$ 700-$ 700
Year 2Year 2 40
Project Abandonment
--$900$900
(.20.20) $1,200$1,200
(.20.20) -$600-$600
(.6060) $450$450
Year 1Year 1
11
22
33
(.60) $1,200$1,200
(.30) $ 900$ 900
(.10) $2,200$2,200
(.35) $ 900$ 900
(.40) $ 600$ 600
(.25) $ 300 $ 300
(.10) $ 500$ 500
(.50) -$ 100-$ 100
(.40) -$ 700-$ 700
Year 2Year 2
The optimal decision at the
end of Year 1 Year 1 is to abandon the
project for $200$200.
$200$200 >
-($266.67)-($266.67)
What is the ““newnew”” project value?
41
Project Abandonment $ 2,238.32 $ 1,331.29 $ 1,059.18
$ 344.90 $ 72.79-$ 199.32
-$ 1,280.95
-$900-$900
(.20.20) $1,200$1,200
(.20.20) -$400*-$400*
(.6060) $450$450
Year 1Year 1
11
22
33
(.60) $1,200$1,200
(.30) $ 900$ 900
(.10) $2,200$2,200
(.35) $ 900$ 900
(.40) $ 600$ 600
(.25) $ 300 $ 300
(1.0) $ 0 $ 0
Year 2Year 2
*-$600 + $200 abandonment
42
Summary of the Addition of the Abandonment Option
* For “True” Project considering abandonment option
The standard deviation*standard deviation* SQRT (740,326) = $857.56$857.56 The expected NPV* expected NPV* = $ 71.88 $ 71.88
NPV* NPV* = Original NPV + Abandonment OptionAbandonment Option
Thus, $71.88 Thus, $71.88 = -$17.01 + OptionOption Abandonment Option Abandonment Option = $ 88.89$ 88.89
43
Thank You
44